Gas Turbine Start Up

Embed Size (px)

Citation preview

  • 8/12/2019 Gas Turbine Start Up

    1/131

    GAS TURBINE

    Petronas Gas

    Berhad

    GPP 5&6 18 December 2005

  • 8/12/2019 Gas Turbine Start Up

    2/131

    History of Gas Turbine

    1. Gas turbine cycle is also known as BraytonCycleGeoge Brayton 1870.

    2. The first gas turbine was constructed by BrownBoveri having a capacity of 4MW beeninstalled at Neuchatel, Switzerland atefficiency of 17%.

  • 8/12/2019 Gas Turbine Start Up

    3/131

    GAS-TURBINE THEORY

    A simple gas turbine is comprised of three main sect ion s

    a compressor, a combustor, and a turbine. The gas-

    turbine operates on the principle of the Brayton cycle,

    where compressed air is mixed with fuel, andburnedunder constant pressure conditions. The resulting hot

    gas is allowed to expand through a turbine to perform

    work. approximately two / thirds of this work is spent

    compressing the air, the rest is available for other workie.( mechanical drive, electrical generation)

  • 8/12/2019 Gas Turbine Start Up

    4/131

    Brayton Cycle

  • 8/12/2019 Gas Turbine Start Up

    5/131

    Types of Gas Turbines

    There are two basic typesof gas turbines

    Aero derivativeunits are aircraft jet engines

    modified to drive electrical generators

    Industrial gasturbinesunits robust

    construction, are suitable for base load

    operation

  • 8/12/2019 Gas Turbine Start Up

    6/131

    Aero derivative (from jet engine)

  • 8/12/2019 Gas Turbine Start Up

    7/131

    Industrial Gas Turbines

  • 8/12/2019 Gas Turbine Start Up

    8/131

    Gas Turbine with Regeneration

    One variation of this basic cycle is the addition of a

    regenerator. A gas-turbine with a regenerator

    (heat exchanger) recaptures some of the energyin theexhaust gas,pre-heating the air entering

    the combustor. This cycle is typically used on

    low pressure ratio turbines.

  • 8/12/2019 Gas Turbine Start Up

    9/131

    Gas Turbine with Regeneration

    http://nyethermodynamics.com/primer/turbine2.gif
  • 8/12/2019 Gas Turbine Start Up

    10/131

    HORSE POWER

    A unit of power equals to 33,000 ft-lb/minor

    550 ft-lb/secor 2,545 Btu/hr.

    1hp = 746 watts

  • 8/12/2019 Gas Turbine Start Up

    11/131

    COMPRESSORSURGE

    Pulsating of compressor discharge pressure

    due to chokage as a result of too much of air to

    be handled

  • 8/12/2019 Gas Turbine Start Up

    12/131

    Blow Off Valve

    Prevention against compressor surgeduring start up

    / shut down and acceleration (The valve reduce back

    pressure by venting air to atm through BOV line to

    exhaust duct) and compressor began surging whenfront stages of compressor would be highly loaded

    (mid Span)

  • 8/12/2019 Gas Turbine Start Up

    13/131

    Type of Gas Turbine

    There are two type of gas turbine

    Single Shaft

    Split Shaft

  • 8/12/2019 Gas Turbine Start Up

    14/131

    Single Shaft Gas Turbine

    Inlet Air

    Combustion Chamber

    Exhaust

    WorkTurbine

    Compressor

    Fuel

  • 8/12/2019 Gas Turbine Start Up

    15/131

    Single Shaft Gas Turbine

    The single shaft gas turbine was develop

    primarily for the electric power industry

    and uses a compressor and a powerturbine integrated on a common shaft. As

    the unit is used continuously at single

    rotational speed.

  • 8/12/2019 Gas Turbine Start Up

    16/131

    Split Shaft Gas Turbine

    Inlet Air

    Combustion Chamber

    Exhaust

    Work

    Power Turbine

    Compressor

    Fuel

    High Power Turbine

  • 8/12/2019 Gas Turbine Start Up

    17/131

    Split Shaft Gas Turbine

    The split shaft gas turbine was develop

    primarily for mechanical drive application

    like pump and compressor, where theoutput power and speed might be

    expected to be variable.

  • 8/12/2019 Gas Turbine Start Up

    18/131

    Main component

    1. Gas Generator (GG) which consist of

    Compressor / air compressor

    Combustion chamber

    High Power Turbine (HPT)

    3. Power Turbine (PT)

    Casing for compressor and turbine

    Accessory (L.O, Sealing & etc)

  • 8/12/2019 Gas Turbine Start Up

    19/131

    Main component

  • 8/12/2019 Gas Turbine Start Up

    20/131

    Gas Generator

    The gas generator consists of an axial flow

    compressor, combustion chambers and two-

    stage turbine. When in operation, air enters the gas generator

    inlet, passes through the inlet duct and enters

    the compressor, where the air is compressed to

    an approximate ratio of 18/1

  • 8/12/2019 Gas Turbine Start Up

    21/131

    The angles of the inlet guide vanesand first six

    stages of compressor vanesare varied as a

    function of gas generator speed and compressorinlet temperature.

    Changing the vane positions gives efficientoperation of the compressor over a broad speedrange, while maintaining an effective stallmargin. The vane positions are controlled by aspeed sensor and servo valve.

  • 8/12/2019 Gas Turbine Start Up

    22/131

    Air leaving the compressor, enters the

    combustionsection. Here the temperature

    of some air is raised as a result of fullcombustion, which takes place inside the

    combustion liner. The remaining air

    entering the combustor section cools thecombustion section,

  • 8/12/2019 Gas Turbine Start Up

    23/131

    Leaving the combustor, hot gas passes

    through the two-stage high pressure

    turbine, where energy is extracted fromthe gas to turn the axial compressor.

    Turbine blade and vane cooling air mixes

    with the mainstream gas it passes throughthe turbine.

  • 8/12/2019 Gas Turbine Start Up

    24/131

    Leaving the gas generator, the hot gas

    drives the free wheeling GT-61 power

    turbine. The power turbine provides themechanical power output for the driven

    equipment.

  • 8/12/2019 Gas Turbine Start Up

    25/131

    Compressor

    The compressor is driven by the

    turbine via a connecting shaft and has

    the job of drawing external air into

    the engine,pressurizing it, and

    passing italong to the combustionchamber.

  • 8/12/2019 Gas Turbine Start Up

    26/131

    Compressor

    stator

    rotor

    shaft

    Air flow

  • 8/12/2019 Gas Turbine Start Up

    27/131

    Compressor

    Axial compressor type ismostly used due toitshigh output and

    efficiency. (Usuallyvariable blade couldproduce 16bar)

    Compressor design beenimprove by

    Improving blade profile

    Improving blade sealing

    Improving blade material towithstand high

    temperature.

  • 8/12/2019 Gas Turbine Start Up

    28/131

    1. Centrifugal compressor This compressor uses a spinning impeller to draw in

    intake air and accelerates it outward by means ofcentrifugal force into a diffuser.

    It is used in small gas turbinesand is best suited

    for low pressure ratioswhere the overall engine

    diameter is not important.

  • 8/12/2019 Gas Turbine Start Up

    29/131

    2. Axial flow compressor

    Consists of rotating blades andstationary vanes. Air is

    compressed as it flows axiallyalong the shaft. This allowsgreater efficiencyand higher pressure ratiosby multi-

    stage construction. A stage of compression consists of one

    row of rotating blades followed by a row of stationary

    vanes. This is the most common type of compressor used inmarine gas turbine engines.

  • 8/12/2019 Gas Turbine Start Up

    30/131

  • 8/12/2019 Gas Turbine Start Up

    31/131

  • 8/12/2019 Gas Turbine Start Up

    32/131

    Variable stator

  • 8/12/2019 Gas Turbine Start Up

    33/131

    Air flow

    Air for gas generator combustion flows

    through air inlet filter, silencer and

    plenum before entering the gasgenerator

  • 8/12/2019 Gas Turbine Start Up

    34/131

  • 8/12/2019 Gas Turbine Start Up

    35/131

    Fuel sprayedfrom the fuel injector nozzles,

    mixes with high-pressure airentering the

    combustion chamber through its perforationsfrom the compressor.

    This mixture of compressed air and fuel then

    burns at temperatures approaching 2000

    o

    C, inorder to maximize the heat energy obtained

  • 8/12/2019 Gas Turbine Start Up

    36/131

    The combustion processis first initiatedby

    igniter plugs, which are then isolated after

    ignition has been accomplished.The combustion of the fuel and air mixture is

    continuous and remains so until the fuel

    supply is removed.

  • 8/12/2019 Gas Turbine Start Up

    37/131

    Zone in which fuel is evaporated

    and mixed with air

    Zone in which fuel is ignited

    And burnt Heat is generated

    Cooling air

  • 8/12/2019 Gas Turbine Start Up

    38/131

    combustor

    Combustion chamber configuration

    1.Single Silo

    compressor is mixed with fuel and ignited in thischamber

    3.Twin silo (each consist of multiple burners)

    4.Can annular (ez maintenance & betterbalance)

    5.Annular ring (popular for >200MW)

  • 8/12/2019 Gas Turbine Start Up

    39/131

    Silo combustor

    Silo combustion chamber in

    its simplest form

    consist of single burner or

    multiple burner.Compressed air from the

    The hot gas is then lead to

    the turbine section

  • 8/12/2019 Gas Turbine Start Up

    40/131

    Silo combustor

    Disadvantageinfluence the size of the

    turbine house.

    Advantagefurnace inspection can be

    done easilybecause of it big

    size.

  • 8/12/2019 Gas Turbine Start Up

    41/131

    Silo combustor

  • 8/12/2019 Gas Turbine Start Up

    42/131

    Can Annular combustor

    1. Individual burner cansare mounted around the

    periphery of the engine. Each can is an

    individual combustorand liner receiving its own

    fuel supply.

    Advantage: Easy replacement

    Disadvantages - Inefficient, structurally weaker

  • 8/12/2019 Gas Turbine Start Up

    43/131

  • 8/12/2019 Gas Turbine Start Up

    44/131

    Annular combustor

    One large combustor within the engine case.

    Multiple fuel nozzles form a solid "ring of fire".

    This type is used on the LM2500

    Advantage

    Most efficient, strongest, frame member of engine

    Disadvantage

    A repair or replacement requires complete enginedisassembly.

  • 8/12/2019 Gas Turbine Start Up

    45/131

  • 8/12/2019 Gas Turbine Start Up

    46/131

    Annular combustor

  • 8/12/2019 Gas Turbine Start Up

    47/131

    High Power Turbine & Power

  • 8/12/2019 Gas Turbine Start Up

    48/131

    High Power Turbine & Power

    Turbine

    Function

    To convert high pressureand temperature

    combustion gasesinto mechanical energyanddrive the compressor and generator.

    turbine blades

    convertsthe kinetic energyinto mechanical

    energy

  • 8/12/2019 Gas Turbine Start Up

    49/131

  • 8/12/2019 Gas Turbine Start Up

    50/131

    HPT cooling

  • 8/12/2019 Gas Turbine Start Up

    51/131

    Cooling HPT

  • 8/12/2019 Gas Turbine Start Up

    52/131

  • 8/12/2019 Gas Turbine Start Up

    53/131

    GG lube oil

    Synthetic oilis used for the gas generator.

    The console is mounted outside of the

    turbine enclosure.

  • 8/12/2019 Gas Turbine Start Up

    54/131

    Hydraulic oilafter filtration is routed to the

    fuel metering valveactuator. Hydraulic oil

    exiting the fuel metering valve actuator isreturned to the reservoir.

  • 8/12/2019 Gas Turbine Start Up

    55/131

    Lube oilafter filtration is routed to theaccessory gearboxand bearing sumps.The lube oil is removed from theaccessory gearbox and bearing sumps byscavenge pumpP5-0502. The oil passesthrough filter S5-0506 which has a

    pressure 505-PTD-1171 set to alarm at 30psig(207 kPa G) increasing on gauge505-PDG-1171.

  • 8/12/2019 Gas Turbine Start Up

    56/131

    Magnetic chip detectorsare installed inthe drain linesfrom the accessory gearboxand each gas generator bearing sumpahead of the scavenging pumps. Anadditional magnetic chip detector isinstalled in the common drain header.

    Metal carried by the drain oil willaccumulate on the detectors and signal analarm.

  • 8/12/2019 Gas Turbine Start Up

    57/131

    Scavenge oilafter filtration flows to Cooler

    E5-0502. A temperature valve 505-TCV-

    1173regulates oil flow through or aroundthe cooler to maintain oil temperature at

    60C.

  • 8/12/2019 Gas Turbine Start Up

    58/131

  • 8/12/2019 Gas Turbine Start Up

    59/131

  • 8/12/2019 Gas Turbine Start Up

    60/131

  • 8/12/2019 Gas Turbine Start Up

    61/131

    Air oil separator

  • 8/12/2019 Gas Turbine Start Up

    62/131

    GG lube oil sump

  • 8/12/2019 Gas Turbine Start Up

    63/131

    GG lube oil

    FMV

    Hydraulic oil filter

    Hydraulic

    Oil pump

    Lube oil

    pumpLube oil

    Filter

    Acc Gearbox

    Lube Oil Sump

    Scavenge oil pump

    Scavenge oil Filter

    Scavengeoilcoole

    r

    Gas Generator

    7bar

    36bar

  • 8/12/2019 Gas Turbine Start Up

    64/131

    Power Turbine and Compressor Lube Oil

    Mineral oilis used for the power turbineandcompressor lubrication. The console ismounted outside of the turbine enclosure.

    Two pumpsare used for normal operation.

    One pumpis driven by an electric motorandis used for start-upand standby. Theremaining pumpis drivenfrom the powerturbine accessory gearboxand supplies all of

    the lube oil to the power turbineandcompressoronce the unit is in operation.

  • 8/12/2019 Gas Turbine Start Up

    65/131

    Oil from the pumps flows to a separately

    mounted fin fan cooler, E5-0506.

    Temperature control valve 505-TCV-1108regulates oil flow through or around the

    cooler to maintain oil temperature at 49C.

  • 8/12/2019 Gas Turbine Start Up

    66/131

    Lube oilfrom the power turbine and compressor

    bearings is returned to the reservoir.

    A third oil pump, P5-0510 (Post Pump) isincluded in the lube oil console to provide

    cooling oilto the power turbine after shutdown.

    Unit control panel logicwill start pump P5-0510

    after main unit shutdown has commenced.

  • 8/12/2019 Gas Turbine Start Up

    67/131

    Lube Oil System (PT)

    compressorGas Turbine

    Filter

    Aux LO Pump

    Main PumpLO Reservoir

    Cooler

    Check valve

    Emergency pump

    Safety precautions

  • 8/12/2019 Gas Turbine Start Up

    68/131

    y p

    The following safety precautions must be

    observed when adding lubricant (top up):

    1.Avoid touching moving partsof the machine

    2. Keep loose clothingwell away from moving

    parts3.Avoid spilling lubricantonto hot surface

    4. Clear up spillage immediately

    5. Do not remove safety protectionfrom the machine

    A good quality of lube oil

  • 8/12/2019 Gas Turbine Start Up

    69/131

    A good quality of lube oil

    Continuous checkof physical oil

    characteristicsduring operation will predict

    warrant of machinery life spent,

    maintenance costand time saving.

    The oil shall be oxidation, foam inhibited

    and have good demulsibility for rapid

    separation of water.

  • 8/12/2019 Gas Turbine Start Up

    70/131

    Lube oil filter S5-0510A/B

    hydraulic filters S5-0508A/B

    scavenge oil filter S5-0506 PDI alarm at 30 psig

    Operating precautions

  • 8/12/2019 Gas Turbine Start Up

    71/131

    p g p

    1. Avoid mixing different grades of oil

    2. Avoid mixing different gradesof grease

    3. Avoid mixing with water or other liquids

    4. Avoid contaminationwith dust or dirt

    5. Check that oil cansare free of all foreign

    materials before filling

    6. Avoid overfilling equipment

    R ti Ch k

  • 8/12/2019 Gas Turbine Start Up

    72/131

    Routine Checks1. During the shift, routine checks must be carried out

    on a regular basis.2. The operator must carry out routine checks

    immediately upon taking over the shiftto ascertainthe operating conditions of the unit and/orequipment.

    3. Just prior to the end of the shift, the operator mustagain check the unit and/or equipment to ensurethathis handoverto the next operator is accurateandgives a true reflectionof the situation at that time.

    4. Operating troublesthat may have been experienced

    on the unit and/or equipment should berecorded inthe log bookand verbally

  • 8/12/2019 Gas Turbine Start Up

    73/131

    The following check shall be carried out.

    1. Check oil level.

    2. Check oil temperature

    3. Check oil pressure

    4. Check and drain water.(Investigate

    reason for water in the bearing.).

    5. Take samplesfor laboratory analysiswhen requested

  • 8/12/2019 Gas Turbine Start Up

    74/131

    Fuel and Start Gas

    With control panel switchesin proper positionfora unit start, the logic circuits cause the followingevents to occur.

  • 8/12/2019 Gas Turbine Start Up

    75/131

    Once purge cycle is complete, upstream

    fuel gas valve(505-XCV-1181) is

    energised to open. Vent valve(505-XCV-1183) is energised closedand the igniters

    are switched on. Starting gasflow control

    valve (505-PCV-1192) is ramped fully

    opento bring starterup to high speedto

    crankthe gas generator for startup.

  • 8/12/2019 Gas Turbine Start Up

    76/131

    Fuel gas block valve (505-XCV-1184) is

    energised open. Fuel is ignitedin the

    combustion chambers of the gas generator and

    speed ramps up to idle.

    Once at idle the ignitersare switched off.

    Starting gas flow control valve (505-PCV-1192)

    is de-energised closed. Starting gas upstreamshutoff valve (505-XCV-1191) is de-energised

    closedand the starter is shutdown.

  • 8/12/2019 Gas Turbine Start Up

    77/131

    PT

    1182

    gas

    manifold

    XV

    1183

    XV

    1181

    XV

    1184

    VENT

    TO SAFE

    LOCATION

    HP FUEL GAS

    FMV

    LM2500

    GAS GENERATOR

    ACC

    GEARBOX

    XV

    1191

    PV

    11

    92

    STARTER GAS

    STARTER

    EXHAUST

    POWER TURBINE

  • 8/12/2019 Gas Turbine Start Up

    78/131

    Enclosure ventilation system

    The enclosure surrounding the gas generatorand power turbine is provided with a ventilationsystem.

    Air is pulled from the inlet air filter through asilencer by an electric driven fan

    Three fansare used for the ventilation system.

    Two fansare to be used during normaloperationand the third fanis for emergencyuse.

  • 8/12/2019 Gas Turbine Start Up

    79/131

  • 8/12/2019 Gas Turbine Start Up

    80/131

    The differential pressure within the enclosure is

    monitored by a differential pressure switch 505-

    PDS-1207

    alarm and start the emergency ventilation fan

    at 2.54 mm H2O decreasing

    shutdown after 60 second delay if the

    differential pressure does not increase abovethe alarm setting

  • 8/12/2019 Gas Turbine Start Up

    81/131

    Fire and Gas Suppression Systems

    Gas detectors505-AE-1211, 1212 and1213 are located in the intake plenum.

    Gas detectors505-AE-1214, 1215 and1216 are located in the turbine enclosure

    The gas sensors monitor gas levels withinthe plenum and enclosure. An alarmis

    sounded if gas levels reach 20%.Shutdownoccurs if gas levels reach 60%.

  • 8/12/2019 Gas Turbine Start Up

    82/131

    All access doorsto the air filter enclosure, intake

    plenumand turbine enclosure are fitted with limit

    switches which will sound an alarmif any door is

    left open.

    Fire detectorsare placed in the turbine

    enclosure. The fire detectors are of the optical

    type, and response to ultravioletand infraredradiationwhich is emitted by flame. The

    detectors have a 120 field of view.

  • 8/12/2019 Gas Turbine Start Up

    83/131

    When the detector senses UV or IR radiation, it signalsthe control panel module. The module issues signals totrigger release of CO2, and closesthe fire damper doorsto isolatethe fire in the enclosure. Two dump nozzles

    559 and 560 are provided. The 559 nozzlesdump theCO2 into the enclosure at a fast rate. The 560 nozzledumps the CO2 at a slow rate. The CO2 bottles arestored in a cabinet which is adjacent to the unit. TwoCO2 tanksare provided for the main system (fast dump)and one CO2 tankis provided for the extended system(slow dump).A duplicate set of reserve tanks are alsoincluded in the system.

  • 8/12/2019 Gas Turbine Start Up

    84/131

    WARNING

    PERSONNEL SHOULD NOT BE EXPOSED TO

    HIGH CONCENTRATIONS OF FOR

    PROLONGED PERIODS TO CO2

    DISCHARGE.

    CO2MAY CAUSE SUFFOCATION AND

    REDUCED VISIBILITY DURING AND AFTER ADISCHARGE PERIOD.

  • 8/12/2019 Gas Turbine Start Up

    85/131

    Gas DetectorFire Detector (Optical)

    FastDis

    charge

    SlowD

    ischarge

    Alarm 20%S/Down 60%

    Response to ultraviolet and

    infrared

    Gas Turbine Enclosure

    CO

    2

    CO

    2

    Temperature

    Alarm 71deg CS/down 80deg C

  • 8/12/2019 Gas Turbine Start Up

    86/131

    Periodic Maintenance

    Every 4000Running hours

    detergent wash with boroscope

    25,000Running hours

    Replacement of the Hot Section

    Note; Depend on vender recommendation

  • 8/12/2019 Gas Turbine Start Up

    87/131

    Water wash system

    A.Purpose: Used to remove dirt and salt buildup on the

    compressor blades.

    B.Components: Consists of a 40 gallon tank and permanentlyinstalled piping to direct water wash solution into the inlet of the

    compressor.

    C.Procedure: Compressor must be washed to maintainefficiency and prevent compressor stalls.

  • 8/12/2019 Gas Turbine Start Up

    88/131

    EXHAUST SYSTEM

    Function:- Convey hot exhaust gases to eitheratmosphere or waste heat boiler

    - exhaust casing-provides exhaust gases flow path

    - exhaust ducting and silencer

    - routes the exhaust gases to chimney or waste

    heat boiler with a reduction in noise

  • 8/12/2019 Gas Turbine Start Up

    89/131

    UNIT START-UP

    Types of start-up

    1. Start-up after maintenance.

    2. Start-up after temporary shut-down. 3. Start-up after emergency shut-down.

  • 8/12/2019 Gas Turbine Start Up

    90/131

    Start-up after Maintenance

    Summary

    Following a planned shutdown for

    maintenance and inspection, the equipment

    are handed back to operations department for

    start up.

    1. Pressure testsmust be made to ensure that all

    disturbed flanges, valves and pipe work are leakfree

  • 8/12/2019 Gas Turbine Start Up

    91/131

    2. The whole system must be thoroughly

    purged of air by using nitrogen

    3.AII accessoriesand equipmentrelated to the

    operation of the main equipment must be

    checked out correctly.

    4. Check that all the platforms and immediate

    external areasare clean and unwantedmaterial removed.

  • 8/12/2019 Gas Turbine Start Up

    92/131

  • 8/12/2019 Gas Turbine Start Up

    93/131

    CAUTION

    WATER WASH VALVE IS OPENED ONLY

    WHEN USING A WATER WASH CART.

    OPEN EXHAUST CASING DRAIN VALVE

    AFTER WATER WASH CART HAS BEEN

    USED TO CLEAN THE UNIT OR TO REMOVE

    LIQUIDWHICH HAS ACCUMULATED DURINGUNIT OPERATION.

  • 8/12/2019 Gas Turbine Start Up

    94/131

    Gas Generator Lube Oil System

    The pressureand temperature checkscan

    only be made afterthe gas generatoris inoperation.

  • 8/12/2019 Gas Turbine Start Up

    95/131

    Normal Start Sequence

    A Normal Start Sequence can only be

    initiated locally from the Local Control

    Panel (LCP). When themodeselect switch on the LCP

    is in Local, a Normal Start is initiated by

    depressing the Start push button (PB-

    1314) on the face of the LCP.

    "Permissive To Start "

  • 8/12/2019 Gas Turbine Start Up

    96/131

    Permissive To Start.

    Gas Generator Oil Reservoir Level is OK

    Power Turbine / Compressor Oil Reservoir Level is OK

    Fuel Metering Valve is at Minimum Position (ZS-1186)

    Fuel Shutoff Valves are closed

    Start Gas Shutoff Vent Valves are closed (ZSC-1191)

    AC Power "OK"

    Vibration Monitor is "OK"

    Turbine Enclosure Doors are closed

    Unit Process Valves are in Shutdown (Prestart) Position

  • 8/12/2019 Gas Turbine Start Up

    97/131

    Gas Generator Coastdown Timer Time out

    Gas Generator Speed (N1) Ramp is at Minimum

    Power Turbine Speed (N2) Ramp is at Minimum

    LCP Run Local Mode is Selected (SS-1402)

    All Fire and Gas System Alarms are Cleared

    All Trip to Idle/Recycle Alarms are Cleared

    Unit Shutdown is Cleared Buffer Gas Supply is greater than the Low Alarm

    Fuel Control Summary Shutdown is Cleared

  • 8/12/2019 Gas Turbine Start Up

    98/131

    NOTE

    If the Permissive To Start pilot light is not

    illuminated on the face of the LCP, select the

    Start Permissive Screenon the Operator

    Interface CRT the status for each of the above

    conditions will be displayed.

    The corrective actionfor each point should betaken in order to achieve a Unit Start

    Permissive.

  • 8/12/2019 Gas Turbine Start Up

    99/131

  • 8/12/2019 Gas Turbine Start Up

    100/131

    Auxiliary Sequences

    Stand-by Lube Oil Pump Test

    Power Turbine/Compressor Lube Oil Pressure

    Lube Oil Pump Sequence Enclosure fan Sequence

    Seal Gas System

    After the Auxiliary Sequence has been

    completed, the Purge and Pressurising

    Sequence for the Compressor will be initiate

  • 8/12/2019 Gas Turbine Start Up

    101/131

    Pressurising Sequence

    The Suction Bypass Valve (505-XV-0102) is

    opened.

    When the Differential Pressure across the

    Suction Valve (505-XV-0101) is reduced to less

    than 1.0 Bar the Suction Valve (505-XV-0101)

    will open

    After the Suction Valve is fully open, the SuctionBypass Valve (505-XV-0102) closes and the

    Discharge Valve (505-XV-0103) will open

  • 8/12/2019 Gas Turbine Start Up

    102/131

    Gas Turbine Start Sequence

    The Gas Starter Control and ShutoffSolenoids 505-XY-1192 and 505-XY-1191are energised

    The Primary Fuel Gas Shutoff Solenoid(505-XY-1181) is energised to open

    The Starter Speed Control Output will be

    ramped up until the Gas Generator Speed(N1) has achieved 1250 RPM

  • 8/12/2019 Gas Turbine Start Up

    103/131

    If the Gas Generator fails to reach 1200 RPM withinthirty (30) seconds, a Fail To Crank Shutdown will beinitiated; thus the Unit Start/Run Sequence will beaborted.

    GG Speed (N1) will be controlled between 1250 and1350 RPM to purge the Plenum, GG, PT/Exhaust Ductand the GG Purge Timer (TM-08)will begin to time out.

    When the GG Purge Timer has timed out, the Starter

    Speed Control Card High Speed command will beenabled and the Starter Speed Control Output will rampup to maximum.

  • 8/12/2019 Gas Turbine Start Up

    104/131

    The Gas Generator will begin to accelerate. and. The

    Ignitors (A or B) are alternated on successive starts of

    the Gas Generator.

    The Fuel Gas Vent solenoid (XY-1183) will be energised

    to close.

    The Ignitor Relay (A or B) (IGN-1261 or 1262) is

    energised The Fuel Gas Secondary Shutoff Valve Solenoid (505-

    XY-1184) is energised to open 505-XV-1184

  • 8/12/2019 Gas Turbine Start Up

    105/131

    Light Off (T5.4 greater than 204C) must

    be verified within 10 seconds after the

    Secondary Shutoff is opened or a "Fail toLight Off Shutdown " is initiated. This will

    then initiate a High Speed Purge of the

    Gas Generator at greater than 2000 RPM

    to rid it of any residual fuel.

  • 8/12/2019 Gas Turbine Start Up

    106/131

    Once Light Off has been verified, the Gas

    Generator will continue to accelerate until the

    GG Speed (N1 ) has achieved 4500 RPM. When

    the GG Speed (N1 ) is greater than 4500 RPM,the Starter Control Signal is disabled and both

    the Gas Starter Supply and Shutoff Solenoids

    are de-energised. Simultaneously, the Ignition is

    also disabled. The Gas Generator continues

    accelerating to Idle.

  • 8/12/2019 Gas Turbine Start Up

    107/131

    Once the Gas Generator has reached Idle

    Speed (5000 RPM), the Unit Warmup Timerwill

    begin to time out. When the warmup Timer has

    time out, the Unit is ready to load.

    When the Unit Load Sequence is initiated, the

    GG will accelerate until the Power Turbine

    minimum speed (3250 RPM) is achieved. TheUnit will now be operated in Power Turbine

    Speed Control Mode.

    Normal operation & routineh k

  • 8/12/2019 Gas Turbine Start Up

    108/131

    checks

    During the shift, routine checksmust be carried out on a

    regular basis.

    The operator must carry out routine checks immediately

    upon taking over the shift to ascertain the operatingconditions of the unit and/or equipment.

    Just prior to the end of the shift, the operator must again

    check the unit and/or equipment to ensure that his

    handover to the next operator is accurate and gives atrue reflection of the situation at that time.

  • 8/12/2019 Gas Turbine Start Up

    109/131

    Operating troubles that may have been

    experienced on the unit and/or equipment

    should be recorded in the log book andverbally communicated to the incoming

    operator.

  • 8/12/2019 Gas Turbine Start Up

    110/131

    Operating aspects to be monitored in order tokeep the performance of the unit under controland to identify proper corrective actions are:

    Compressor and Turbine vibrations Compressor and Turbine axial displacement

    Temperature and pressure of the lube oil systems.

    Differential pressure across the Lube Oil Filters.

    Differential pressure across the Hydraulic Oil Filters.

    Status of the Lube Oil Stand-by Pumps. Differential pressure across Seal Gas Filters.

    Differential pressure across Nitrogen Buffer Gas Filters.

    Differential pressure across Instrumental air Filters.

    Gas Generator speed.

    Power Turbine/Compressor speed.

    ypes o s ut own

  • 8/12/2019 Gas Turbine Start Up

    111/131

    1. Shut down for maintenance

    2. Temporary shut-down.3. Emergency shut-down.

    Scheduled shut-down

  • 8/12/2019 Gas Turbine Start Up

    112/131

    Scheduled shut-downs occur at infrequentintervals and are carefully planned. This

    enables preventive maintenance workto be

    carried out e.g. internal inspection of an

    equipment. All maintenance work which cannot be

    handled whilst the Equipment is in operation

    is carried out at this time. A Previously

    prepared shut-down procedure and work listmust be strictly adhered to. This will ensure a

    safe, controlled shut-down and a minimum

    loss of time in completing maintenance work.

    perat ng precaut ons

  • 8/12/2019 Gas Turbine Start Up

    113/131

    Close co-ordination between the Panel

    Operator and Field Operator is essential forgood control.

    Safe operating proceduresand safety

    regulations must be followed at all times. Coordinate with other Units and warn the

    other departments, especially the Fire

    Department.

    emporary s ut own

  • 8/12/2019 Gas Turbine Start Up

    114/131

    A temporary shut-down is unscheduledand

    may only last for a few hours. The shut-downfollows the same procedure as for ascheduled shut-down except that thepressure should be maintained ready for

    immediate start up. A temporary shut-down is usually due to

    operational requirements, or, a unit upsetofshort duration. Every effort must be made to

    return to normal operations as soon aspossible.

    Emergency shut-down

  • 8/12/2019 Gas Turbine Start Up

    115/131

    An emergency shut-down can be caused byequipment failuresrelated to the plantoperation or utility failures, e.g. loss ofinstrument air.

    In the event of an emergency shut-downbeing necessary the unit must be taken out ofservice as quickly and safely as possible.

    The prevailing conditions at the time must betaken into consideration when shutting downthe unit.

  • 8/12/2019 Gas Turbine Start Up

    116/131

    WARNING

    Safety of personnel and the prevention of

    damage to equipment are the primaryconsiderations. All operations personnel

    must be thoroughly conversant with the

    procedures to be taken for an emergency

    shut-down.

  • 8/12/2019 Gas Turbine Start Up

    117/131

    The exact procedure to follow must be

    decided in the light of individual

    circumstances at the time. Frequentchecking of equipment can normally give

    adequate warning of impending trouble

    and allow a normal shut-down to be

    effected.

  • 8/12/2019 Gas Turbine Start Up

    118/131

    A thorough knowledge of all the

    equipment related to unit operation is

    essential.

    The main causesof unit emergencies are:

    power failure, instrument air failure, fuel

    gas failure.

  • 8/12/2019 Gas Turbine Start Up

    119/131

  • 8/12/2019 Gas Turbine Start Up

    120/131

    The following conditions will initiate a VentedShutdown: CO2 Release Shutdown

    Common Fire Shutdown Inlet Plenum Gas Shutdown

    Turbine Enclosure Gas Shutdown

    Compressor Vibrations Shutdown

    Compressor Thrust Shutdown Gas Seal Vent Leakage Primary High Shutdown or

    Signal Fail

  • 8/12/2019 Gas Turbine Start Up

    121/131

    PT/Compressor Lube Oil Supply Pressure

    Low Shutdown or Signal Fail

    Compressor Rupture Disc Failure Shutdown

    Process ShutdownVented

    Unit ESD

    2 of 3 CPUs Failure Shutdown

    Engine troubleshooting

  • 8/12/2019 Gas Turbine Start Up

    122/131

    Engine troubleshooting

    Troubleshooting is a systematic analysis

    of symptoms that indicate equipment

    malfunction. These symptoms usually

    appear as deviations from normal values

    of observed equipment parameters.

  • 8/12/2019 Gas Turbine Start Up

    123/131

    Before concluding that an engine fault

    does exist, the troubleshooter must assure

    that his knowledge of suspected trouble

    area is adequate, that the instruments

    used are calibrated and working properly,

    and that they have been accurately read

    and interpreted.

    NOTE

  • 8/12/2019 Gas Turbine Start Up

    124/131

    NOTE

    If troubleshooting procedures do not

    isolate and eliminate the fault, secure

    assistance from vendor service

    representative through your customer

    service manager.

    GG Fails to reach maximummotoring speed

  • 8/12/2019 Gas Turbine Start Up

    125/131

    motoring speed

    If engine is hot, allow it to cool for 30minutesand then attempt motoring.

    Check starter supply pressure. If pressure is

    below minimum limit, check pressure source. Check instrumentation. Replace indicator if

    defective.

    Replace starter.if the rotation is still low,perform

    borescope inspection of compressor and HPT.Check scavenge oil screens for sump problems.

  • 8/12/2019 Gas Turbine Start Up

    126/131

    CAUTION

  • 8/12/2019 Gas Turbine Start Up

    127/131

    CAUTION

    ALWAYS PURGE FUEL FROM GAS

    GENERATOR BY MOTORING THE GAS

    GENERATOR AFTER ANY FALSE

    START

    WARNING

  • 8/12/2019 Gas Turbine Start Up

    128/131

    WARNING

    NO FUEL AIR MIXTURE MAY BE

    PRESENT DURING THIS TEST.HIGH

    VOLTAGE EXISTS AT THE IGNITERS,

    THEY MUST NOT BE TOUCHED WHILE

    ENERGIZED.

    High Vibration in Gas Generator

  • 8/12/2019 Gas Turbine Start Up

    129/131

    High Vibration in Gas Generator

    Check that vibration instrument and its wiring

    are operating properly

    Check that vibration pickup is securely mounted.

    Inspect oil scavenge and magnetic plugs in lube

    scavenge pump.

    Water wash compressor if inspection reveals

    dirty blades and vanes.

    High Vibration in Power Turbine

  • 8/12/2019 Gas Turbine Start Up

    130/131

    High Vibration in Power Turbine

    Check that vibration instrument and its

    wiring are operating properly

    Check that vibration pickup is securelymounted.

    Inspect oil scavenge and magnetic plugs

    in lube scavenge pump.

    Low Lube Oil Pressure

  • 8/12/2019 Gas Turbine Start Up

    131/131

    Low Lube Oil Pressure

    Oil pressure is a function of gas generator

    speed and supply temperature.

    If oil supply pressure is low,check supplyoil filters for cleanliness and supply line for

    leaks. If low pressure persists, replace

    lube/scavenge pump.