ConnectGreaterWashington - Transit Project/Strategy Summary Gallery Place/Metro Center and Farragut North/Farragut West Pedestrian Tunnels District of Columbia Proposed Strategy: Build an underground pedestrian tunnel between Gallery Place and Metro Center Stations. Build an underground pedestrian tunnel between Farragut North and Farragut West Stations. These connections would provide additional opportunities to transfer between Metrorail Lines and relieve crowding at Gallery Place and Metro Center Stations. Goals Addressed: Provide a high-quality transit system that accommodates and encourages future ridership growth. Regional Activity Centers Connected: Enables more efficient access to activity centers connected by the Metrorail system. (Continues on Back) Page 1 Red Line Orange Line Blue Line Yellow Line Green Line Silver Line Transfer Station Station Pedestrian Tunnel LEGEND Arlington Cemetery Dupont Circle Woodley Park Van Ness-UDC Tenleytown-AU Friendship Heights Bethesda Mt Vernon Sq Shaw-Howard U U Street Columbia Heights Fort Totten Brookland-CUA Rhode Island Ave Judiciary Sq Federal Triangle Smithsonian Archives L’Enfant Plaza McPherson Sq U t NoMa-Gallaudet U Union Station Foggy Bottom- GWU Court House Federal Center SW Eastern Market Capitol South Potomac Ave Georgia Ave- Petworth N Arlington Cemetery Arlington Cemetery Dupont Ci Dupont Ci r cle cle W oodley Park oodley Park Cleveland Park Cleveland Park V an Ness-UDC an Ness-UDC V V T enleytown-AU enleytown-AU T T Friendship Heights Friendship Heights Bethesda Bethesda Mt Mt V e V V r non Sq non Sq Shaw-Howa Shaw-Howa r d U d U d U d U U Street U Street Street Street Street et et Columbia Columbia a a a Heights Heights s s s Fort Fort T otten otten T T B r ookland-CUA ookland-CUA Rhode Island Rhode Island A ve ve A A Judiciary Sq Judiciary Sq c c Federal Federal Federa Federa Federa T T riangle riangle rian rian T T T T Smithsonian Smithsonian Smithsonia Smithsonia Smithsonia mith mith A A r r chives chives ves ves L ’Enfant Plaza ’Enfant Plaza ’En ’En ’En Plaza Plaza ’Enfant Plaza ’Enfant Plaza McPherson McPherson M M McPh McPh McPh q q Sq Sq q q q Rosslyn Rosslyn U U NoMa-Gallaudet U NoMa-Gallaudet U Union Station Union Station Foggy Bottom- Foggy Bottom- oggy Bottom- oggy Bottom- oggy Bottom- Foggy Bottom- Foggy Bottom- GWU GWU GWU GWU GWU Court House Court House Medical Center Medical Center Federal Center SW Federal Center SW SW SW SW Fed Fed Easte Easte Eas Eas r n Market n Market n Market n Market n Market Capitol South Capitol South outh outh outh Cap Cap Potomac Potomac mac mac mac Pot Pot A ve ve ve ve ve A A Georgia Georgia A ve- ve- A A Petworth Petworth h h h Farragut North Gallery Place Metro Center Farragut West

Gallery Place/Metro Center and Farragut North/Farragut ... · Gallery Place/Metro Center and Farragut North/Farragut West ... Gallery Place/Metro Center and Farragut North/Farragut

Embed Size (px)

Citation preview

ConnectGreaterWashington - Transit Project/Strategy Summary

Gallery Place/Metro Center and Farragut North/Farragut West Pedestrian TunnelsDistrict of Columbia

Proposed Strategy:Build an underground pedestrian tunnel between Gallery Place and Metro Center Stations. Build an underground pedestrian tunnel between Farragut North and Farragut West Stations. These connections would provide additional opportunities to transfer between Metrorail Lines and relieve crowding at Gallery Place and Metro Center Stations.

Goals Addressed: Provide a high-quality transit system that accommodates and encourages future ridership growth.

Regional Activity Centers Connected:• Enables more effi cient access to activity

centers connected by the Metrorail system.

(Continues on Back)Page 1

Red Line

Orange Line

Blue Line

Yellow Line

Green Line

Silver Line

Transfer Station

Station

Pedestrian Tunnel

LEGEND

Pentagon City

Arlington Cemetery

Dupont Circle

Woodley Park

Cleveland Park

Van

Ness-

UDC

Tenle

ytown-

AU

Friendship Heights

Bethesda

Grosvenor-Strathmore

Mt V

erno

n Sq

Shaw-H

oward U

U Street

ColumbiaHeights

Fort Totten

Brook

land-C

UA

Rhode

Islan

d Ave

Judiciary Sq

Feder

al Tr

iangle

Smith

sonia

n Archiv

es

L’Enf

ant P

laza

McPhersonSq

Rosslyn

Virgini

a Sq-G

MU

Ballst

on-M

U

Wat

erfro

nt

Navy P

ark-

Ballpar

k

Anaco

stia

Congre

ss H

eight

s

Southe

rn A

ve

Naylo

r Rd

Suitlan

d

Branc

h Ave

NoMa-

Gallau

det U

Union

Sta

tion

Foggy Botto

m-

GWU

Court H

ouse

Medical Center

Federal Center SW

Eastern Market

Capitol South

Potomac Ave

Georgia Ave-

Petworth

N

Arlington CemeteryArlington Cemetery

Dupont CiDupont Cirrclecle

WWoodley Parkoodley Park

Cleveland ParkCleveland Park

VVan

Ness-

UDC

an N

ess-

UDC

VVan

Ness-

UDC

VVTTe

nleyt

own-AU

enley

town-

AU

TTenle

ytown-

AU

TTFriendship HeightsFriendship Heights

BethesdaBethesda

Mt

Mt VV

eeVVeVVrrn

on Sq

non

SqSha

w-Howa

Shaw-H

owarrd Ud Ud Ud U

U StreetU StreetU StreetU StreetU StreetU StreetU Street

ColumbiaColumbiaColumbiaColumbiaColumbiaHeightsHeightsHeightsHeightsHeights

Fort Fort TTottenottenTTottenTT

BBrrook

land-C

UA

ookla

nd-C

UA

Rhode

Islan

d

Rhode

Islan

d AAveveAAveAA

Judiciary Sq

Judiciary Sq

Judiciary Sq

Judiciary Sq

Feder

al

Feder

al

Feder

al

Feder

al

Feder

al TTTTr

iangle

riang

le

riang

le

riang

le

riang

le

riang

le

TTrian

gle

TTTTrian

gle

TT

Smith

sonia

n

Smith

sonia

n

Smith

sonia

n

Smith

sonia

n

Smith

sonia

n

Smith

sonia

n

Smith

sonia

n AAAAArrrrrchiv

es

chive

s

chive

s

chive

s

LL’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

’Enf

ant P

laza

McPhersonMcPhersonMcPhersonMcPhersonMcPhersonMcPhersonMcPhersonSqSqSqSqSqSqSq

RosslynRosslyn

Ballst

on-M

U

Ballst

on-M

U

NoMa-

Gallau

det U

NoMa-

Gallau

det U

Union

Sta

tion

Union

Sta

tion

Foggy Botto

m-

Foggy Botto

m-

Foggy Botto

m-

Foggy Botto

m-

Foggy Botto

m-

Foggy Botto

m-

Foggy Botto

m-

GWU

GWU

GWU

GWU

GWU

Court H

ouse

Court H

ouse

Medical CenterMedical Center

Federal Center SW

Federal Center SW

Federal Center SW

Federal Center SW

Federal Center SW

Federal Center SW

Federal Center SW

EasteEasteEasteEasterrn M

arket

n Market

n Market

n Market

n Market

Capitol South

Capitol South

Capitol South

Capitol South

Capitol South

Capitol South

Capitol South

Potomac

Potomac

Potomac

Potomac

Potomac

Potomac

Potomac AAAveveveveve

AAAveAAA

Georgia

Georgia AAve-ve-

AAve-AAPetworth

Petworth

Petworth

Petworth

Petworth

Farragut North

Galler

y Plac

e

Met

ro C

ente

rFar

ragut

Wes

t

ConnectGreaterWashington - Transit Project/Strategy Summary

Key Findings:This strategy was modeled with 2030 regional travel and development forecasts.1

• Farragut pedestrian tunnel is used by 32,000 daily passengers.

• Gallery Place/Metro Center pedestrian tunnel is used by 8,200 passengers during the morning and evening peak hours.

Helps relieve Metrorail passenger loads near the two transfer points but does not address the most crowded line segments.

• Farragut pedestrian tunnel reduces the number of transfers at Metro Center by 23%.

• Pedestrian tunnels do not fully relieve crowding at Gallery Place or Metro Center stations.

• Adding the tunnel between Farragut North and West increases crowding. Internal station improvements are needed as well to improve movement within the stations.

Gallery Place/Metro Center and Farragut North/Farragut West Pedestrian TunnelsDistrict of Columbia

1. Farragut tunnel usage modeled with MWCOG Round 8.2 Cooperative Land Use Forecast, and Gallery Place/Metro Center tunnel usage modeled with Round 7.2A Forecast. Page 2

NewMetrorail Lines

for the Region’s Core

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Blue Line in Virginia 11 miles from Franconia-Springfi eld to Potomac Mills in Prince William County. This extension would expand the reach of Metrorail along the congested I-95 Corridor.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Springfi eld

• Fort Belvoir North Area• North Woodbridge

• Potomac Town Center

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

34,000 daily riders (or 3,100 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

Only 13,000 riders are new public transit riders. The remainder are already public transit riders on either commuter bus or VRE.

2040 station areas are projected to have 7 households per acre and 11 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity at Franconia-Springfi eld and Huntington Metro stations.

More suburban riders increase crowding along the Blue and Yellow Lines closer to DC and at core transfer stations.

Blue Line Extension – Franconia-Springfi eld to Potomac MillsFairfax County/Prince William County, Virginia

395

495

95

Fairfax County

City ofAlexandria

Prince WilliamCounty

FRANCONIA-SPRINGFIELD

NEWINGTON

LORTON

OCCOQUAN

POTOMAC MILLS

Springfield

Fort BelvoirNorth Area

NorthWoodbridge

PotomacTown Center

P o t om

a c Ri v

e r

1

210

600

0 31.5Miles

Proposed Blue Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'SCOUNTY

PRINCEWILLIAMCOUNTY

PROJECTLOCATION

MONTGOMERYCOUNTY

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Blue Line 7 miles in Maryland from Largo Town Center to Blue Star Memorial Highway near Bowie. This extension would expand the reach of Metrorail along the Central Avenue Corridor (MD 214).

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Largo Town Center

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

10,000 daily riders (or 1,400 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

Only 1,000 riders are new public transit riders. The remainder are already public transit riders on either commuter or local bus.

2040 station areas are projected to have 3 households per acre and 3 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity at Largo Town Center and Morgan Boulevard stations.

More suburban riders increase crowding at core transfer stations.

Blue Line Extension – Largo Town Center to BowiePrince George’s County, Maryland

Prince George's County

495

LARGO TOWN CENTER

Largo Town Center/ Morgan Blvd

95HARRY S. T

RUMAN AVE

KETTERING DRIVE

ENTERPRISE ROAD

CHURCH ROAD

BLUE STAR

MEMORIAL

HIGHWAY

Joint BaseAndrews

50

301

202

564

725

410

295

410

0 21Miles

Proposed Blue Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

DCPRINCE

GEORGE'SCOUNTY

MONTGOMERY COUNTY

PROJECTLOCATION

MONTGOMERYCOUNTY

FAIRFAXCOUNTY

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Green Line 18 miles in Maryland from Greenbelt to BWI Airport. This extension would expand the reach of Metrorail along the U.S. 1 and Baltimore-Washington Parkway Corridors.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Greenbelt Metro • Konterra

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

16,000 daily riders (or 900 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

Only 6,000 riders are new public transit riders. The remainder are already public transit riders on either MARC or commuter or local bus.

2040 station areas are projected to have 6 households per acre and 14 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity at Greenbelt and other stations closer to DC.

More suburban riders increase crowding at core transfer stations.

Green Line Extension – Greenbelt to BWI AirportPrince George’s County/Anne Arundel County, Maryland

Anne Arundel County

Howard County

New Carrollton

295

Crain Highway

Prince George'sCounty

MontgomeryCounty

495

95BWI AIRPORT

ARUNDEL MILLS

SAVAGE

LAUREL

KONTERRA

CALVERT

GREENBELT

Konterra

GreenbeltMetro

Fort Meade

0 42Miles

Proposed Green Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

ANNE ARUNDELCOUNTY

HOWARDCOUNTY

PROJECTLOCATION

IncreasedService for

Commuter Rail andCommuter Bus

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Build a Metrorail Green Line spur running 6 miles from Congress Heights in DC to National Harbor in Maryland. This spur would expand the reach of Metrorail along South Capitol Street to Oxon Hill. However, there would be no additional service on the Green Line to L’Enfant Plaza. This spur would be served by some trains that normally serve Branch Avenue.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Poplar Point

• St. Elizabeths • Oxon Hill

• National Harbor

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

23,000 daily riders (or 4,000 per mile) on the new extension. This is above the minimum recommended for Metrorail extensions.

4,000 riders are new public transit riders. Replaces many bus-to-Metrorail transfers along the Green Line in Southeast DC with direct Metrorail Access.

2040 station areas are projected to have 8 households per acre and 14 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Green Line Spur – Congress Heights to National HarborDistrict of Columbia/Prince George’s County, Maryland

495295 95

Branch Avenue

National Harbor

ALABAMA ANDMLK SE

MLK SE AND SOUTH CAPITOL

SOUTH CAPITOL AND SOUTHERN

OXON HILL ROAD

NATIONAL HARBOR

ANACOSTIA

Po

t om

ac

Ri v

er

Prince George'sCounty

VIRG

INIA

Oxon Hill

MARYLAND

DISTRICT OF COLUMBIA

FairfaxCounty

Cityof

Alexandria

St Elizabeths

Poplar Point

0 21Miles

Proposed Green Line SpurProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'SCOUNTY

MONTGOMERYCOUNTY

PROJECTLOCATION

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

(Continues on Back)Page 1

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

Frees up Park & Ride capacity at Anacostia station.

• More suburban riders increase crowding along the Green Line south of L’Enfant Plaza and at core transfer stations.

• Reduction in service to Branch Avenue increases crowding on that portion of the line.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

Green Line Spur – Congress Heights to National HarborDistrict of Columbia/Prince George’s County, Maryland

Page 2

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Green Line 18 miles in Maryland from Branch Avenue to Charles County. This extension would expand the reach of Metrorail along the MD 5 Corridor (Branch Avenue).

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Branch Avenue • Waldorf

Note: Extension bypasses the commercial spine of Waldorf and White Plains along U.S. 301.

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

30,000 daily riders (or 1,700 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

18,000 riders are new public transit riders. The remainder are already public transit riders on either commuter, local, or express bus.

2040 station areas are projected to have 2 households per acre and 5 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity at Branch Avenue, Suitland, and Southern Avenue stations.

More suburban riders increase crowding along the Green Line closer to DC and at core transfer stations.

Green Line Extension – Branch Avenue to White PlainsPrince George’s County/Charles County, Maryland

Charles County

MARY

LAND

VIRG

INIA

495

Prince George's County

295

95

Branch Avenue BRANCH AVENUE

JOINT BASEANDREWS

CLINTON

SOUTHERNMARYLAND

HOSPITAL CENTER

BRANDYWINE

WALDORF

WHITE PLAINS

La Plata

Waldorf

5

5

301

351

0 42Miles

Proposed Green Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

PROJECTLOCATION

CHARLESCOUNTY

IncreasedService for

Commuter Rail andCommuter Bus

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Orange Line 8 miles in Maryland from New Carrollton to Crain Highway, near Bowie. This extension would expand the reach of Metrorail along the U.S. 50 Corridor.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• New Carrollton • Bowie

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

24,000 daily riders (or 3,000 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

Only 8,000 riders are new public transit riders. The remainder are already public transit riders on either bus or MARC.

2040 station areas are projected to have 2 households per acre and 2 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Provides additional Park & Ride spaces; however, existing Orange Line stations will have spare capacity.

More suburban riders increase crowding at core transfer stations.

Orange Line Extension – New Carrollton to Bowie Town CenterPrince George’s County, Maryland

Prince George's County

495

NEW CARROLLTON

New Carrollton

95

Bowie

95

495

WOODMOORE

BOWIE TOWN CENTER

CRAIN HIGHWAY

295

Anne Arundel County

50

301

3

0 21Miles

Proposed Orange Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

PROJECTLOCATION

ANNE ARUNDELCOUNTY

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

66

Fairfax County

FAIR OAKS/FAIRFAX CORNER

VIENNA

Centreville

Fairfax Center

ViennaSTRINGFELLOW ROAD

CENTREVILLE 495City ofFairfax

0 42Miles

Proposed Strategy:Extend the Metrorail Orange Line 19 miles in Virginia from Vienna to Centreville and Gainesville. This extension would extend the reach of Metrorail along the congested I-66 Corridor. A shorter 10-mile extension ending at Centreville was also considered.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Vienna

• Fairfax Center• Centreville

• Gainesville

Key Findings:Both strategies were modeled with 2040 regional travel and development forecasts.1

• 28,000 daily riders (or 1,500 per mile) on the new extension to Gainesville.

• 17,000 daily riders (or 1,700 per mile) on the shorter extension to Centreville.

• Both segments are below the minimum recommended for Metrorail extensions.

Only about half of the riders are new public transit riders. The remainder are already public transit riders on either bus or VRE.

2040 station areas are projected to have 6 households per acre and 14 jobs per acre on the Gainesville extension, which are below the recommended minimums for Metrorail extensions.

Orange Line Extension – Vienna to Centreville/GainesvilleFairfax County/Prince William County, Virginia

66

Washington DullesInternational Airport

267

Fairfax County

Prince William County

VIRGINIA

Lorton

OccoquanPotomac Mills

Loudoun County

Prince WilliamCounty

FAIR OAKS/FAIRFAX CORNER

VIENNA

Gainesville

Centreville

Fairfax Center

ViennaSTRINGFELLOW ROAD

CENTREVILLE

SUDLEY ROAD

GAINESVILLE

495

Cityof

Mannasas

City ofFairfax

Springfield

NorthWoodbridge

PotomacTown Center

0 42Miles

Proposed Orange Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

LOUDOUNCOUNTY

PRINCEWILLIAMCOUNTY

PROJECTLOCATION

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Extension to Gainesville

Extension to Centreville

(Continues on Back)Page 1

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

• 2040 station areas are projected to have 8 households per acre on the Centreville extension, which is below the recommended minimum for Metrorail extensions.

• However, the 2040 station areas are projected to have 21 jobs per acre along this extension, which is above the minimum.

Frees up Park & Ride capacity at existing Orange Line stations in Fairfax County.

More suburban riders increase crowding along the already crowded Orange and Silver Lines closer to DC and at core transfer stations.

Orange Line Extension – Vienna to Centreville/GainesvilleFairfax County/Prince William County, Virginia

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

IncreasedService for

Commuter Rail andCommuter Bus

Page 2

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Red Line 4 miles in Maryland from Shady Grove to Metropolitan Grove. This extension would expand the reach of Metrorail along the I-270 and MD 355 Corridors to Gaithersburg.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• King Farm/Rockville

Research Center

• Gaithersburg-Central

• Gaithersburg-Metropolitan Grove

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

16,000 daily riders (or 9,000 per mile) on the new extension. This is above the minimum recommended for Metrorail extensions.

Only 7,000 riders are new public transit riders. The remainder are already public transit riders on either bus, Corridor Cities Transitway, or MARC.

2040 station areas are projected to have 5 households per acre and 17 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity between Shady Grove and Grosvenor-Strathmore stations.

More suburban riders increase crowding at core transfer stations.

Red Line Extension – Shady Grove to Metropolitan GroveMontgomery County, Maryland

270

200

SHADY GROVE

MUDDY BRANCH ROAD

METROPOLITAN GROVE

Gaithersburg - Metropolitan Grove

Gaithersburg- Central

King Farm/Rockville Research Center

Montgomery County

370

Montgomery CountyMontgomery County Airpark Airpark

0 21Miles

Proposed Red Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

MONTGOMERY COUNTY

PROJECTLOCATION

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Silver Line 8 miles in Virginia from Route 772 to the Route 7 Bypass near Leesburg. This extension would expand the reach of Metrorail along the Dulles Greenway Corridor.

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Route 772

Transit Area• Leesburg

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

6,000 daily riders (or 750 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

Only 3,000 riders are new public transit riders. The remainder are already public transit riders on either commuter bus or MARC.

2040 station areas are projected to have 2 households per acre and 4 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity between Route 772 and Tysons Corner.

More suburban riders increase crowding along the Silver Line closer to DC and at core transfer stations.

Silver Line Extension – VA 772/Dulles Greenway to LeesburgLoudoun County, Virginia

Loudoun County

Route 772Transit Area

VA 7 BYPASS

Leesburg

CROSSTRAIL BLVD

BELMONT RIDGE

ROUTE 772

267

15

Washington DullesWashington Dulles International Airport International Airport

0 21Miles

Proposed Silver Line ExtensionProposed Metrorail StationPlanned Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

MONTGOMERY COUNTY

LOUDOUNCOUNTY

PROJECTLOCATION

IncreasedService for

Commuter Rail andCommuter Bus

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Extend the Metrorail Yellow Line 12 miles in Virginia from Huntington to Lorton. This extension would expand the reach of Metrorail to serve the U.S. Route 1 Corridor (Richmond Highway).

Goals Addressed: Facilitate transit-oriented, mixed-use communities that capture employment and household growth, providing choices in where to live, work, and play.

Maximize availability of and convenient access to integrated transit choices.

Regional Activity Centers Connected:• Huntington/Penn Daw

• Beacon Groveton• Hybla Valley/

Gum Springs

• Fort Belvoir

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

29,000 daily riders (or 2,400 per mile) on the new extension. This is below the minimum recommended for Metrorail extensions.

7,000 riders are new public transit riders. The remainder are already public transit riders on either commuter bus, local bus, or VRE.

2040 station areas are projected to have 6 households per acre and 7 jobs per acre, which are below the recommended minimums for Metrorail extensions.

Frees up Park & Ride capacity at Huntington, Franconia-Springfi eld, and Van Dorn Street stations.

More suburban riders increase crowding along the Yellow Line closer to DC and at core transfer stations.

Yellow Line Extension – Huntington to LortonFairfax County, Virginia

395

495

City of Alexandria

MAR

YLAN

D

VIRG

INIA

FairfaxCounty

Po

tom

ac

Riv

er

95

HUNTINGTON

PENN DAW

BEACON HILL ROAD

GUM SPRINGS

POLE ROAD

WOODLAWN

FORT BELVOIRTELEGRAPHROAD

LORTON

Huntington / Penn Daw

Beacon Groveton

Hybla Valley / Gum Springs

Ft. Belvoir

1

0 21Miles

Proposed Yellow Line ExtensionProposed Metrorail StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

FAIRFAXCOUNTY

DC

PRINCEGEORGE'SCOUNTY

PROJECTLOCATION

MONTGOMERYCOUNTY

A Network of

Regionally SignificantHigh-Capacity Surface

Transit Corridors

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.1 Aspirations Scenario Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Build a new Metrorail Station on the existing Blue Line between King Street and Van Dorn Street Stations. This strategy is intended to attract new ridership to Metrorail and provide greater access to the system for City of Alexandria residents and businesses.

Goals Addressed: Maximize availability of and convenient access to integrated transit choices.

Provide a fi nancially viable and sustainable transit service that is effi cient and effective for the region.

Regional Activity Centers Connected:• None

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

Fewer than 1,000 daily riders would use the new station.

Only 400 riders are new Metrorail riders. The remaining are existing users of adjacent stations.

The 2040 station area is projected to have 3 households per acre and 4 jobs per acre, which are below the recommended minimums for Metrorail infi ll stations.

Station access and development potential is limited by physical barriers, including Cameron Run, I-495, and adjacent freight rail lines.

Eisenhower Valley Infi ll StationCity of Alexandria, Virginia

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.3 Cooperative Land Use Forecast.

$

395

295

City ofAlexandria

EISENHOWERVALLEY

Fairfax County

MARYLAND

DISTRICT OF COLUMBIA

49595

Po

t om

ac

Ri v

er

VAN DORNSTREET

KING ST-OLD TOWN

0 21Miles

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

Proposed Infill StationExisting Metrorail Station

Regional Activity Center

PROJECTLOCATION

Improved Access to Leverage Transit Investments

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

ConnectGreaterWashington - Transit Project/Strategy Summary

Kansas Avenue Infi ll StationDistrict of Columbia

Proposed Strategy:Build a new Metrorail Station on the existing Red Line between Fort Totten and Takoma Stations, serving northeast DC in the vicinity of Kansas Avenue NE and North Capitol Street. This strategy is intended to attract new ridership to Metrorail and provide greater access to the system for area residents and businesses.

Goals Addressed: Maximize availability of and convenient access to integrated transit choices.

Provide a fi nancially viable and sustainable transit service that is effi cient and effective for the region.

Regional Activity Centers Connected:

• None

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

3,700 daily riders would use the new station.

Only 1,250 riders are new Metrorail riders. The remaining are existing users of adjacent stations.

The 2040 station area is projected to have 6 households per acre and 8 jobs per acre, which are below the recommended minimums for Metrorail infi ll stations.

Station access is facilitated by grid street network.

$ 495

Prince George's County

District ofColumbia

KANSAS AVE

Montgomery County

TAKOMA

FORTTOTTEN

0 21Miles

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

MONTGOMERYCOUNTY

PROJECTLOCATION

Proposed Infill StationExisting Metrorail Station

Regional Activity Center

DISTRICT OF COLUMBIA

MARYLAND

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.3 Cooperative Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

Improved Access to Leverage Transit Investments

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Build a new Metrorail Station on the existing Red Line between Rockville and Shady Grove Stations, serving Montgomery County in the vicinity of the Montgomery College Campus. This strategy is intended to attract new ridership to Metrorail and provide greater access to the system for area residents, businesses, and students.

Goals Addressed: Maximize availability of and convenient access to integrated transit choices.

Provide a fi nancially viable and sustainable transit service that is effi cient and effective for the region.

Regional Activity Centers Connected:• Montgomery College

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

2,000 daily riders would use the new station.

Only 550 riders are new Metrorail riders. The remaining are existing users of adjacent stations.

The 2040 station area is projected to have 2 households per acre and 8 jobs per acre, which are below the recommended minimums for Metrorail infi ll stations.

Station access is partially limited by long block lengths and low connectivity among land uses.

Montgomery College Infi ll StationMontgomery County, Maryland

$

270

MONTGOMERYCOLLEGE

Montgomery County

SHADY GROVE

ROCKVILLE

MontgomeryCollege

200

370

0 21Miles

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

PROJECTLOCATION

Proposed Infill StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.3 Cooperative Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

Improved Access to Leverage Transit Investments

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Build a new Metrorail Station on the existing Blue/Orange/Silver Line just east of the Stadium-Armory Station, becoming the fi nal transfer point before the lines diverge east of the Anacostia River. This strategy is intended to attract new ridership to Metrorail and provide greater access to the system for DC residents and businesses in the vicinity of the intersection of Oklahoma Avenue NE and Benning Road NE.

Goals Addressed: Maximize availability of and convenient access to integrated transit choices.

Provide a fi nancially viable and sustainable transit service that is effi cient and effective for the region.

Regional Activity Centers Connected:• Stadium-Armory • H Street

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

3,000 daily riders would use the new station.

Only 1,250 riders are new Metrorail riders. The remaining are existing users of adjacent stations.

• The 2040 station area is projected to have 7 households per acre and 6 jobs per acre, which are below the recommended minimums for Metrorail infi ll stations.

• Station area development potential is severely limited by National Park Service ownership of RFK Stadium property.

Station access is partially limited by the location near the Anacostia River.

Design of an infi ll station would need further study to address grade change between underground and elevated track segments at this location.

Oklahoma Avenue Infi ll StationDistrict of Columbia

$

295

Prince George's County

District ofColumbia

OKLAHOMAAVE

MARYLAND

DISTRICT OF COLUMBIA

Po

t om

ac

Ri v

er

STADIUMARMORY

MINNESOTA AVE

BENNINGROAD

Stadium Armory

H St

0 21Miles

FAIRFAXCOUNTY

DC

PRINCEGEORGE'S

COUNTY

MONTGOMERY COUNTY

Proposed Infill StationExisting Metrorail Station

Regional Activity Center

Other Regional Activity Center

PROJECTLOCATION

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.3 Cooperative Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

(Continues on Back)Page 1

ConnectGreaterWashington - Transit Project/Strategy Summary

Improved Access to Leverage Transit Investments

Page 2

Oklahoma Avenue Infi ll StationDistrict of Columbia

ConnectGreaterWashington - Transit Project/Strategy Summary

Proposed Strategy:Build a new Metrorail Station on the Green Line between the existing Anacostia and Congress Heights Stations. This strategy is intended to attract new ridership to Metrorail and provide greater access to the system for DC residents, businesses, and government employees in the vicinity of the St. Elizabeths campuses in southeast DC.

Goals Addressed: Maximize availability of and convenient access to integrated transit choices.

Provide a fi nancially viable and sustainable transit service that is effi cient and effective for the region.

Regional Activity Centers Connected:• St. Elizabeths

Key Findings:This strategy was modeled with 2040 regional travel and development forecasts.1

9,300 daily riders would use the new station.

5,000 riders are new Metrorail riders. The remaining are existing users of adjacent stations.

• The 2040 station area is projected to have 9 households per acre, which is below the recommended minimum for Metrorail infi ll stations.

• However, the 2040 station area is projected to have 20 jobs per acre, which is above the minimum.

Forecast ridership depends on convenient pedestrian access to/from government campuses.

Design and construction of an infi lll station would be diffi cult as the existing line is in a tunnel at this location.

St. Elizabeths Campus Infi ll StationDistrict of Columbia

295

Prince George's County

ST. ELIZABETHSCAMPUS

MARYLAND

DISTRICT OF COLUMBIA

495 95Po

t om

ac

Ri v

er

ANACOSTIA

CONGRESSHEIGHTS

St. Elizabeths

0 21Miles

FAIRFAXCOUNTY

DC

PRINCEGEORGE'SCOUNTY

MONTGOMERYCOUNTY

Proposed Infill StationExisting Metrorail StationRegional Activity CenterConnected by Proposed Strategy

Other Regional Activity Center

PROJECTLOCATION

Prince George'sCounty

$

1. Ridership modeled with MWCOG Round 7.2A Cooperative Land Use Forecast. Forecast 2040 density from MWCOG Round 8.3 Cooperative Land Use Forecast.

Colors indicate strategy performance: Good, Mixed, Poor, Not Applicable

(Continues on Back)Page 1

ConnectGreaterWashington - Transit Project/Strategy Summary

Improved Access to Leverage Transit Investments

St. Elizabeths Campus Infi ll StationDistrict of Columbia

Page 2