7
Advanced Energy Systems, Inc. FY 09 AES Phase I Crab Cavity SBIRs Michael Cole, Doug Holmes

FY 09 AES Phase I Crab Cavity SBIRs

  • Upload
    farrah

  • View
    25

  • Download
    0

Embed Size (px)

DESCRIPTION

FY 09 AES Phase I Crab Cavity SBIRs. Michael Cole, Doug Holmes. SBIR Program Format. Phased Program Phases Awarded Independently Phase One Starting July 09 (in neg. now) 8-9 Months Limited Program 500 Hours (13 Man Weeks) Feasibility Study Costing Study for Phase Two - PowerPoint PPT Presentation

Citation preview

Page 1: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

FY 09 AES Phase I Crab Cavity SBIRs

Michael Cole, Doug Holmes

Page 2: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

SBIR Program Format

• Phased Program• Phases Awarded Independently• Phase One Starting July 09 (in neg. now)

– 8-9 Months– Limited Program– 500 Hours (13 Man Weeks)– Feasibility Study– Costing Study for Phase Two– Awards mid to late April

• Phase Two– Based on successful Phase One, Late Summer 2010 Award.– Phase Two is proposed via Phase One report.– Two year program $750K max Level Funded– Year two technically optional for DOE– Detailed Design, Hardware, and Test phase

Page 3: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

Submitted SBIRs

• The Crab Cavity: AES (Cole), BNL, LBL, and SLAC

• Couplers for the Crab Cavity including LOM, SOM, HOM, and FP: AES (Cole), BNL, LBL, and SLAC

• A Cryostat for use with the Crab Cavity: AES (Holmes) and FNAL

• Crab Cavity Tuning Devices: AES (Holmes) and FNAL

• Of these we only won the first, the Crab Cavity SBIR.

Page 4: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

Impact

• Only have funding for engineering and analysis of Cavity.

• Effort on potentially complex coupler structures will have to come from elsewhere.

• Same for Cryostat and Tuner development.

Page 5: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

Prototype Crab Cavity

• Collaborators are AES, BNL, LBL, and SLAC• Phase 1

– Preliminary Design of Cavity (3 man months supported by SBIR)• Coordinate transfer of Physics Design• Develop initial mechanical solid model• Perform Initial Thermal and Structural Analysis• Preliminary Mechanical Design and Fabrication Feasibility Study

• Phase 2– Complete mechanical design with supporting thermal/structural

analysis.– Generate complete fabrication drawing package for the Crab Cavity.– Fabricate Prototype Crab Cavity– Perform BCP and HPR on Prototype Crab Cavity at AES if our

facilities can accommodate it. We anticipate that we will be able accommodate an 800 MHz elliptical crab cavity.

– Support Crab Cavity VTF testing at BNL

Page 6: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

Crab Cavity Couplers

• Focus of the coupler SBIR was to have been the coupler structures.

• The boundary between the cavity and couplers is quite blurry for some of the configurations.

• It is reasonable to expect that provisions can be made to retrofit couplers at a later date.

Page 7: FY 09 AES Phase I Crab Cavity SBIRs

Advanced Energy Systems, Inc.

Cryostat

• Effort required to look at retrofitting cavity to some existing cryostat will have to come from elsewhere.

• This program can support some of this but it will be at the expense of the cavity work.

• Best results will be from external support of cryostat engineering.

• We will provide models and drawings of the cavity.