Upload
jothipriyad
View
218
Download
0
Embed Size (px)
Citation preview
8/10/2019 Future Indian Grid With 765kV and Above
1/45
Future Indian grid with 765kV and
above
A.K.Tripathy
Advisor Silicon Institute ofTechnology NWET 2013
8/10/2019 Future Indian Grid With 765kV and Above
2/45
Towards a strong grid
Large grid does not mean a strong grid.
Grid is as weak as the weakest interconnection is.
Distant nodes have larger phase angle difference
Islanding is difficult with high level inter connection
Possibility of un-damped oscillation is higher
Consequences of grid failure in a large grid can be moredamaging.
This has to be weighed against higher reliability, better
trading opportunity, optimal utilization of network.Is there a limit to the size of a grid from aboveconsiderations
8/10/2019 Future Indian Grid With 765kV and Above
3/45
Question
Overlaying a higher voltage networkstabilizes the grid.
Major issues are reactive power management,and contingency management,
Intangible benefits are
research and development, new generation ofproducts, lesser right of way
8/10/2019 Future Indian Grid With 765kV and Above
4/45
Peak demand inIndia is expected
to increase
to more than500,000 MW by
2027 for which
installed
generation
capacity of
about 700,000
MW is required..
8/10/2019 Future Indian Grid With 765kV and Above
5/45
Pushing Technological Frontiers in Transmission
400 kV
1977 1990 2000 2011 2012/13
765kVAC
800 kV HVDC 1200kV UHVAC
500 kV HVDC
8/10/2019 Future Indian Grid With 765kV and Above
6/45
Changing philosophy in expanding the
Indian grid
Regional self sufficiency
Asynchronous inter regional connection by HVDCB2B links
Synchronous north, north east , eastern andwestern regions
And southern region joined asynchronously.
One Nation , one grid A 765kV backbone and introduction of UHV AC
and DC
8/10/2019 Future Indian Grid With 765kV and Above
7/45
A large grid propagates disturbancewider and farther
1. Different mix of generators respond differently.
The faster ones take the onus and slower ones donot participate
2. Protection settings are fixed and not adaptive,and therefore ,no survival effort
3. Larger fault currents stress equipments andfaster protection reduces fault ride through
capability
8/10/2019 Future Indian Grid With 765kV and Above
8/45
Indian Power Network is one
of the biggest
Transmission Grid Comprises:
765kV/400kV Lines - 95,500 ckt. km
220/132kV Lines - 114,600 ckt. km
HVDC bipoles - 4 nos.
HVDC back-to-back - 7 nos.
FSC 18 nos.; TCSC 9 nos.
NER, ER, NR & WR operating as single grid of 95,000MW
Inter-regional capacity : 27,600 MW
8/10/2019 Future Indian Grid With 765kV and Above
9/45
NORTH EAST-AGRA 3000
MW
ADANI 2500 MW
CHAMPA HVDC ARECA
8/10/2019 Future Indian Grid With 765kV and Above
10/45
JEYPORE
SASARAM
SIPAT
DHULE
SOLAPUR
PUNE
KARNOOL
HYDERABAD
ITARSI
BINA
WARDHA
RAICHUR
INDORE
VIJAYAWADA
SEONI
SATNASASAN
KOTA
JAIPUR
AGRA
MOGA
MUNDKA
GWALIOR
KISHENPUR
TEHRI
LUCKNOW
FATEHPUR
BAREILLY
MEERUT
1200KV UHVAC LINES
765KV EHVAC LINES
800kV HVDC BIPOLE
LEGEND
IB VALLEY
NKSTPP
RANCHI
GAYA
BALIAPURNEA
SILIGURI POOLING
POINT
NER
AURANGABAD
RAIPUR
Perspective Hybrid Grid by 2022 & beyond
765kV/1200kV AC and
800kV, 6000MW HVDC
Hybrid Grid
8/10/2019 Future Indian Grid With 765kV and Above
11/45
LINE VOLTAGE 765 KV
HIGHEST SYSTEM VOLTAGE 800 KV
RATED CURRENT 2000 A
SYSTEM NEUTRAL EFFECTIVELY EARTHED
SHORT CKT CURRENT 40 KA for 1sec BIL 1950 KVp for transformer and
reactors and 2100 KVp for
S/S AND 2400Kvp for line
SIWL 1550 KVp
POWER FREQ 830 KV rms RIV at 508 KV rms
8/10/2019 Future Indian Grid With 765kV and Above
12/45
Progress in 765 kV
First 765 kV line Sipat-Seoni approved in 2000 andcommissioned in 2008
Western pooling stations and LILO of D/C line
completed. Under various stages:-
Anpara-Unao, Seoni-Bina, Seoni-Wardha, Bara-Fatehpur, Bara-Mainpuri, Gaya-Balia, Gaya-Baranasi,
Sasaram-Fatehpur, Barh-Gorakhpur, Auria-Gwalior,Agra-Gwalior, Gwalior-Jaipur, Raichur-Sholapur,Narendra-Kolhapur, Gwalior-Bina, Sasaram-NorthKarampura, North Karampura-Sipat
8/10/2019 Future Indian Grid With 765kV and Above
13/45
Prominent Ferranti Effect
Higher Corona losses
Prolonged secondary arc extinction time Higher slow front O/V on ground faults
High breaker TRV peak
Severe VFTO due to geometry and Topology
ISSUES AT UHV LEVEL
8/10/2019 Future Indian Grid With 765kV and Above
14/45
National Grid by 2012
CHANDRAPUR
U.SILERU
NAGJHARI
SR
KOLHAPUR
PONDA
1000
MW
BELGAUM
MW1000
GAZUWAKA
RAIPUR
VINDHYACHAL
WR POOLING
GORAKHPUR
WR
GWALIOR
UJJAIN
NAGDAZERDA
MALANPUR
AGRA
KANKROLI
RAPP
KOTA
AURAIYA
FATEHPUR
NR
BIRPARA
ER
MALDA
SILIGURI
NAGARPURI
BALIMELA
SIPAT
KORBA
ROURKELARANCHI
TALCHER
DEHRI
SAHU
BALIA
MUZAFFARPUR
PATNA
BARH
B'SHARIFF
NABI
NER
BONGAIGAONSALAKATI
NARENDRA
1000MW
500MW
BUDHIPADAR
SASARAM
GAYA
Inter-regional capacity : 30,700
MW
8/10/2019 Future Indian Grid With 765kV and Above
15/45
+500kV HVDC experience from Rihand Delhi &ChandrapurPadge
+600kV HVDC experience from Foz-du-Iguasu
to Sao Paulo Specifications of + 800kV Systems are under
preparation by POWERGRID, CHINA, SOUTH
AFRICA, BRAZIL, EPRI and other consultants.
+800kV HVDC Systems
8/10/2019 Future Indian Grid With 765kV and Above
16/45
1200 kV introduced
1200kV test line commissioned at Bina and
handed over to Nation
Deol near Wardha will be the first 1200 kV
commercial line
DeolAurangabad line will be second
400/1200kV substations are planned at Deol
and Aurangabad
8/10/2019 Future Indian Grid With 765kV and Above
17/45
UHV Transmission: India and
China
Development of a 1200 KV UHV AC system, thehighest AC system in the world, is an Indian dream to
tackle the ever growing power demand which isexpected to be over 400 GW by 2020. Although manycountries in the world like USSR, Japan, America &Italy have made great progress in the research of
1200KV ultra high voltage AC transmission systemonly China has recently established the commercial1100 kV system successfully.
8/10/2019 Future Indian Grid With 765kV and Above
18/45
NORMAL
ANDCOMPACT
TOWERSAT 800 kV
8/10/2019 Future Indian Grid With 765kV and Above
19/45
Corona cage is used to
study the corona
characteristics and
environmental aspects of
the UHV overhead
transmission line, such as
:
radio interference
audible noise and
corona loss.
The corona cage consists ofa single test conductor or
conductor bundle placed
concentrically inside a
metallic cylinder with a
much larger radius.
8/10/2019 Future Indian Grid With 765kV and Above
20/45
A 400 km long line
generates 2400 MVRShunt MVAR to behandled will be 2400MVAR
Dynamic compensation
Instead of fixed andswitched shuntreactors, matching
dynamically controlledshunt reactor will berequired
Dynamic compensation
system
8/10/2019 Future Indian Grid With 765kV and Above
21/45
Air Insulation Studies For 1200 kV UHVAC
Transmission Line:
The study is to optimize conductor tower
air insulation clearances for adoption in1200 kV AC transmission lines. Eight
Bersimis conductor bundle was used for the
study.
The critical wave shape was used for
determining the optimum clearance required
for withstand voltage of 1800 kVp
corresponding to 1200 kV transmission lines.
8/10/2019 Future Indian Grid With 765kV and Above
22/45
Crompton Grieve
and BHEL supply the 1200 kV
CVT
India's First 1200 KV Power Product
8/10/2019 Future Indian Grid With 765kV and Above
23/45
1200KV single V suspension
string for 8 bundle ACSR MOOSE
(OCTAGONAL)
1200kv double tension insulator
string suitable for 8 x ACSR
bundle
T-connector and BPIconnector
8/10/2019 Future Indian Grid With 765kV and Above
24/45
1200kv single suspension insulator for 8 x ACSR
8/10/2019 Future Indian Grid With 765kV and Above
25/45
CVT and CT
Transformer
CVT,CT and Surge arrester
8/10/2019 Future Indian Grid With 765kV and Above
26/45
The rated voltage of surgearrester is 850 kV and LightningImpulse Protective Level (LIPL)and Switching ImpulseProtective Level (SIPL) as 1700kV (at 20 kA) and 1500 kV (at 2
kA) respectively. Few moreexamples of such equipmentsuccessfully developed areTransformer,Circuit
breakers,Isolators,insulators bothprocelain and
polymers,Transmission LineTowers,Line Hardware andconductors etc.
.
8/10/2019 Future Indian Grid With 765kV and Above
27/45
800kV HVDC CONVERTER TRF.
BUSHING (20.6 m)
8/10/2019 Future Indian Grid With 765kV and Above
28/45
800kV Ultra HVDC
Impressions from Transformer Transport
8/10/2019 Future Indian Grid With 765kV and Above
29/45
View of 1200kV Trf. Vijai electricals
make
8/10/2019 Future Indian Grid With 765kV and Above
30/45
CGL MAKE Trf.
8/10/2019 Future Indian Grid With 765kV and Above
31/45
BHEL make Transformer
8/10/2019 Future Indian Grid With 765kV and Above
32/45
Bina 1200 kV Subtations
8/10/2019 Future Indian Grid With 765kV and Above
33/45
Another view
8/10/2019 Future Indian Grid With 765kV and Above
34/45
1200kV double ckt. towers
8/10/2019 Future Indian Grid With 765kV and Above
35/45
1200 kV single ckt. Transmission line
8/10/2019 Future Indian Grid With 765kV and Above
36/45
Evening shadows on the substation
8/10/2019 Future Indian Grid With 765kV and Above
37/45
Cooler bank transformers
8/10/2019 Future Indian Grid With 765kV and Above
38/45
View of switchyard
8/10/2019 Future Indian Grid With 765kV and Above
39/45
765kV CTs
8/10/2019 Future Indian Grid With 765kV and Above
40/45
765kV Transformer Yard
8/10/2019 Future Indian Grid With 765kV and Above
41/45
765kV Circuit Breakers
8/10/2019 Future Indian Grid With 765kV and Above
42/45
765kV Tower
8/10/2019 Future Indian Grid With 765kV and Above
43/45
765kV Transformer Yard
8/10/2019 Future Indian Grid With 765kV and Above
44/45
Need for a National Reliability Council
IN USA MODEL
The best managed grids in the world can fail.
Important thing is to analyse failure and learn.
Claiming high PLF and Transmission availability is not all.The acid test is reliability of the supply chain.
We need a neutral National level reliability council.
Public at large have a right to information.
8/10/2019 Future Indian Grid With 765kV and Above
45/45
Conclusion
Research provides knowledge.
Knowledge provides courage
Courage allows risk.
No Risk, there is No gain.
Research therefore is always justified