Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
FUTURE GROWTH/WELLHEADPRESSURE MANAGEMENT
110 kV GIS CORE & MAIN SUBSTATIONS
DISCOVERED IN 1979, TENGIZ IS ONE OF THE WORLD’S DEEPEST PRODUCING SUPER GIANT OILFIELDS AND ONE OF THE LARGEST DISCOVERIES IN RECENT HISTORY.
01
FGP/WPMP PROJECTLOCATED IN A REMOTE AREA OF WEST-ERN KAZAKHSTAN, THE UNDERGROUND TENGIZ RESERVOIR MEASURES 20 KILOMETRES BY 21 KILOMETRES. THE ENTIRE TENGIZ OILFIELD AREA IS ESTI-MATED TO CONTAIN 750 MILLION TO 1.1 BILLION METRIC TONNES (6 TO 9 BIL-LION BARRELS) OF RECOVERABLE OIL.
KAZAKHSTAN
Caspian Sea Uzbekistan Kyrgyzstan
Russia
02 03
SKEMA FOR THE TENGIZ FGP/WPMP PROJECTCORE & MAIN SUBSTATIONS
IN CONSORTIUM WITH GE GRID SOLUTIONS, SKEMA WAS
AWARDED THE CONTRACT FOR THE DESIGN, ENGINEER-
ING, DEVELOPMENT, FABRICATION, ELECTRICAL EQUIP-
MENT, MULTIDISCIPLINARY INSTALLATION ACTIVITIES,
INSPECTION, TESTING PROGRAM, DOCUMENTATION AND
PRESERVATION FOR SHIPMENT OF THE 110 kV CORE AND
MAIN SUBSTATIONS FOR THE TCO FGP/WPMP PROJECT.
The substations were divided into transportable packaged sub-
modules complete with access platforms, stairs, electrical equip-
ment and building services.
“On behalf of our team, I would like to express our deep gratitude to the Skema team involved in Main substation design, development,
fabrication, and testing program. We appreciate your strong capabilities and commitment establishing effective cooperation and communication
with us and all the specialists from supporting companies. Your professionalism allowed us to achieve our targeted shipment date with
a high-quality work product. This large and complex scope has been completed with a total of 637 days of Incident and Injury Free work.
This is a great accomplishment and very important achievement for the TCO Future Growth Project and for all of us.
TCO appreciates SKEMA for their partnership in this work.”
Senior Project Manager,FGP/WPMP Project
0504
SKEMA’S SCOPE OF WORK
Skema was awarded the contract for the sizing, design, materials, fabrication, inspection, non-destructive examination, shop-
testing, documentation and preparation for shipment of the 110 kV GIS Core and Main substations. The Core substation was
divided into 32 transportable packaged sub-modules for sea and road transportation and the Main substation into 2 mod-
ules for sea and road transportation. Performance was according to IEC/GOST standards and PUE ROK.
EPC CONTRACTOR: KPJV / A JV BETWEEN FLUOR, WORLEY PARSONS, JSC KING AND LLP KGNT
END USER: TENGIZCHEVROIL / A CONSORTIUM OF CHEVRON, EXXONMOBIL, KAZMUNAIGAS, LUKARKO
CORE SUBSTATION SHIPPED IN 32 MODULES
LENGTH 81.1 M
WIDTH 14.48 M
HEIGHT 8.6 M
HEIGHT 7.9 M
WEIGHT 1,097 T
WEIGHT 750 T
WIDTH 14.6 M
LENGTH 56 M
MAIN SUBSTATION SHIPPED IN 2 MODULES
0706
08 09
ENGINEERING
THE DESIGN AND ENGINEERING
OF THE CORE AND MAIN MODU-
LAR SUBSTATIONS WERE DEVEL-
OPED THROUGH STUDIES, CALCU-
LATIONS, DRAWINGS, VERIFICATIONS
AND VALIDATIONS, AND A SE-
RIES OF SPECIFIC DETAILED PRO-
CEDURES TO ENSURE THE COR-
RECT SEQUENCE OF ASSEMBLY
AND TESTING OPERATIONS ON SITE.
The structure of the substations, man-
ufactured in steel and installed above
concrete foundations, was designed
to meet all the requirements defined
in the Client’s specifications.
A complete three-dimensional com-
puter model of the structure was de-
veloped, using a dedicated calcula-
tion software, in order to perform the
analysis for all conditions applicable
to the substation, as detailed below:
> Structural in-service analysis
> Structural lifting analysis
> Structural transportation analysis
The analyses, which included the
structural verifications of all weld-
ed and bolted joints, were carried
out considering the gravity loads of
the structure and equipment, com-
bined with the dynamic loads and
environmental loads (such as wind,
seismic, snow, thermal and blast) ap-
plicable to each specific condition.
A set of detailed structural and ar-
chitectural drawings, representing
the actual structural and architec-
tural design and providing all nec-
essary input for construction, were
developed according to the re-
sults of the structural analyses.
Dedicated calculations, drawings,
technical documentation and installa-
tion details were also developed to de-
sign each system, including the main
equipment, to comply with all pro-
ject and environmental requirements.
Drawings and documentation (in-
cluding Procedures, Passports,
Manufacturing Record Books, Dis-
patch Dossiers) were provided most-
ly in dual language (Russian and
English), while the Installation Op-
erating and Maintenance Manu-
als were provided in three languag-
es (Kazakh, Russian and English).
3D MODEL – Skema developed a 3D
model of each substation, that allows
a 360° view of the whole substation
complete with structural and archi-
tectural parts, electrical and instru-
mentation, HVAC and F&G systems.
The 3D model of the substation and
its equipment enables Skema to en-
sure a thorough and consistent mon-
itoring of the most critical areas, a
functional dimensional verification of
the correct position of the internal el-
ements in the various areas, and the
removal of any clashes between the
elements of the disciplines. It also en-
ables Skema to interface with its Cli-
ent efficiently, giving a unique access
key to the project for the success of
both the engineering and construc-
tion phases.
10 11
CORE SUBSTATION 32 MODULES
12 13
CORE SUBSTATION 32 MODULES
14 15
MAIN SUBSTATION 2 MODULES
16 17
MAIN SUBSTATION 2 MODULES
18 19
THE CORE SUBSTATION CONSISTS OF
32 MODULES, WHICH WERE PREFAB-
RICATED, ASSEMBLED, SAND-BLAST-
ED, PAINTED AND BOLTED TO FORM A
UNIQUE STRUCTURE. AFTER COMPLE-
TION OF THE STRUCTURAL AND AR-
CHITECTURAL ASSEMBLY, THE INTER-
NAL EQUIPMENT WAS INSTALLED AND
THE SUBSTATION WAS TESTED. THE
MODULES WERE THEN DISASSEM-
BLED AND SHIPPED TO KAZAKHSTAN.
The Core substation is built over
2 levels, each divided into rooms. More
in detail, the ground floor includes:
110 kV GIS AREA (18 modules)
Steel structure made by assembled
units which contain the gas insulated
switchgear (GIS). A 1.5 t bridge crane
is installed at elevation level of the
GIS area for switchgear maintenance
purposes.
ELECTRICAL ROOM (6 modules)
2 transformers feeding the LV switch-
gear, UPS, battery box, and the distribu-
tion boards are installed in the electri-
cal room on the ground floor, which
includes also an office and a restroom.
BATTERY ROOM (1 module) – Bat-
teries are located on specific racks in
this room, which is equipped with an
eye wash facility and a trolley to move
the batteries.
The mezzanine floor hosts:
HVAC ROOM (5 modules) – The HVAC
LV switchgear and PLC panel, the main
air conditioning equipment and the duct
system for the whole substation are lo-
cated in the HVAC room, which includes
also 2 chemical filters and 2 fans.
INSTRUMENT EQUIPMENT ROOM
(2 modules) – This room has been
designed to host the control panels.
Access ladders, entrance, emergency
and maintenance service doors com-
plete the substation, and 5 removable
panels ensure easy installation and
maintenance of the bigger and heavier
equipment. A system of cable trays at
different heights serve the electro/
instrumental paths, starting from the
lower part beneath the floor beams, all
through the intermediate section, up to
the upper part of the substation, ensur-
ing the connection among the main
equipment such as GIS, transformers,
switchgear, lighting, small power and
sensors from the various rooms.
THE EQUIPMENT
Skema provided the following main
equipment for the 110 kV Core sub-
station:
> LV Switchgear and MCCs com-
plete with auto-transfer scheme,
momentary synchronizing be-
tween incomers, switchgear and
transformer protection, control
and metering equipment
> Distribution Boards, Bus Ducts,
Distribution Transformers and PLC
panel
> Electrical/Instruments and F&G
systems, internal and external
lighting
> HVAC system
> Hydrosanitary system
> Bridge crane
THE CORE SUBSTATION
2120
22 23
THE MAIN SUBSTATION, WHICH IS
THE LARGEST SUBSTATION OF THE
OVERALL FUTURE GROWTH PRO-
JECT, CONSISTS OF 2 MODULES
WHICH WERE PREFABRICATED,
ASSEMBLED, SAND-BLASTED,
PAINTED AND BOLTED TO FORM A
UNIQUE STRUCTURE. THE MODULES
WERE THEN DISASSEMBLED AND
SHIPPED TO KAZAKHSTAN BY BARGE.
The Main substation is built over 2
levels, each divided into rooms. More
in detail, the Utility Module includes
the Battery Room and the Electrical
Room on the ground floor, and the
HVAC Room and Instrument Equip-
ment Room on the mezzanine floor.
The GIS module corresponds to the
GIS area which includes the 110 kV
GIS switchgear with the control panels
and a 1.5 t bridge crane for GIS main-
tenance. Access ladders entrance,
emergency and maintenance service
doors complete the substation, and 3
removable panels ensure easy instal-
lation and maintenance of the bigger
and heavier equipment. The substa-
tion is complete with air conditioning,
electro/instrumental and Fire and Gas
systems. A system of cable trays at
different heights serve the electro/
instrumental paths, starting from the
lower part beneath the floor beams, all
through the intermediate section, up
to the upper part of the substation, en-
suring the connection among the main
equipment such as GIS, transform-
ers, switchgear, lighting, small power
and sensors from the various rooms.
110 kV GIS AREA (Gis module) – This
module contains the gas insulated
switchgear (GIS). A 1.5 t bridge crane is
installed at elevation level of the GIS area
for switchgear maintenance purposes.
ELECTRICAL ROOM (Utility module)
3 transformers feeding the LV
switchgear, UPS, and the distribution
boards are installed in the electrical
room, which also includes an office
and a restroom.
BATTERY ROOM (Utility module)
Batteries are located on specific racks
in this room, which is equipped with
an eye wash facility and a trolley
to move the batteries.
The mezzanine floor hosts:
HVAC ROOM (Utility module) – The
HVAC LV switchgear and PLC panel,
the main air conditioning equipment
and the duct system for the whole
substation are located in the HVAC
room, which includes also 2 chemical
filters and 2 fans.
INSTRUMENT EQUIPMENT ROOM
(Utility module) – This room has been
designed to host control panels.
THE EQUIPMENT
Skema provided the following main
equipment for the 110 kV Main sub-
station:
> LV Switchgear and MCCs com-
plete with auto-transfer scheme,
momentary synchronizing be-
tween incomers, switchgear and
transformer protection, control
and metering equipment
> Distribution Boards, Bus Ducts,
Distribution Transformers and
PLC panel
> Electrical/Instruments and F&G
systems, internal and external
lighting
> HVAC system
> Bridge crane
THE MAIN SUBSTATION
2524
2726
SKEMA HAS DEVELOPED THROUGH
AN EXTENSIVE PROJECT EXPERIENCE,
A WIDE KNOWLEDGE AND EXPERTISE
WITH REGARDS TO OPERATIONS RE-
LATED TO PRESERVATION, DISASSEM-
BLY, LIFTING, HANDLING AND LOAD
OUT OF MODULAR SUBSTATIONS.
PRESERVATION AND DISASSEMBLY
For the Core and Main substations,
Skema supplied the following services:
> Preservation, protection and stor-
age at the fabrication yard
> Disassembly in modules
> Packaging, preservation and pro-
tection for sea and land transport
> Winterization for shipment and
storage
> Load out
Preservation procedures were pro-
vided to give guidance till the mod-
ules shipment to Kazakhstan and from
shipment to Kazakhstan up to the op-
eration of the substation.
LOAD OUT - The substations were pre-
pared for load out by removing all the
external items (e.g. rain hoods, ex-
ternal lighting, F&G and HVAC items)
which were properly packed and fixed
inside the modules or shipped as loose
items inside standard containers.
All the internal equipment was stead-
ily fixed to the designed supports,
and all the cabinets doors locked.
The openings on the external clad-
dings, like MCTs or HVAC sleeves,
were closed from outside, and sealed
all over to avoid penetration of dust
and water. Once the preparation was
completed, the substations modules
were moved, by means of Self Pro-
pelled Modular Transporters (SPMTs),
and positioned along yard quay ready
to be handed over to the Client for sea
transportation.
INSTALLATION MANUAL - Skema pro-
vided detailed Installation Manuals
containing Safety tips and operating
instructions for the unloading, handling
and reassembly of the modules onsite.
Dedicated installation manuals were
also provided for all dismantled items
to allow a proper reinstallation at site
of all plants and equipment belonging
to the substations.
DISASSEMBLY, LOAD OUT AND TRANSPORTATION
28 29
THANK YOU FOR WORKING WITH SKEMA!“During my career I chose to be passionate and have pride for
work, and this has become part of Skema’s company values
as well. The desire for continuous improvement and the metic-
ulous attention to detail in an effort to deliver superior quality
and to exceed our Clients’ expectations has become the mis-
sion of the company. I would like to thank our Clients for their
trust and valued collaboration and all the workers and all the
subcontractors involved, that with blood, sweat and tears, made
possible the completion of the Core and Main substations in
compliance with the specifications and the safety requirements
of this challenging project.”
Mario Cerveglieri - President
30 31
www.skemaq.it