Future Ancillary Services: Description of Pricing Proposals
ERCOT Staff
September 15, 2014
1
• There is general consensus that the proposed AS procurement constraints are appropriate– The constraints allow substitutability between different AS where
applicable, and hence mitigate liquidity concerns
• At the August 25th FAST/TAC workshop concerns were raised about the proposed formula for FFR (FFR1 & FFR2) MCPC that came out of the discussions of the various FAST work sessions and workshops
• The following slides describe the FAST proposal and the Alternate Proposal 1 and Alternate Proposal 2
Introduction
2
• Keeps the current policy of pricing equivalent AS MW awards the same for equivalent AS types. i.e.– FRRS-Up, FRRS-Down, FFR1, FFR2, CR2, SR2 awards priced the same
as the corresponding equivalent RegUp, RegDown, PFRS, CR1, SR1 AS respectively
– In the case of FFR, the ratio (R) determines the equivalence of R MW of PFR to 1 MW of FFR
– If the RegUp, RegDown, PFR, CR1, SR1 MCPCs reflect opportunity costs, then the corresponding equivalent FRRS-Up, FRRS-Down, FFR1, FFR2, CR2, SR2 MCPCs will also reflect the same opportunity costs
FAST Proposal
3
AS MCPC
FRRS-Up RegUp MCPC
FRRS-Down RegDown MCPC
FFR1 Min(Ratio * PFR MCPC, VOLL)
FFR2 Min(Ratio * PFR MCPC, VOLL)
CR2 CR1 MCPC
SR2 SR1 MCPC
• In case there is a need to replace FRRS-Up, FRRS-Down, FFR1, FFR2, CR2 or SR2 responsibility with an equivalent RegUp, RegDown, PFR, CR1 or SR1, the FAST proposal will, in general, make the cost of replacement of these AS consistent with the cost of replacing a given AS type with exactly the same AS type (i.e. PFR for PFR, etc.)
FAST Proposal
4
• This proposal attempts to keep the current policy of pricing equivalent AS MW awards the same for equivalent AS types
• The only difference from the FAST proposal is with the determination of MCPC for FFR1 and FFR2– Starting with the FAST formula for MCPC for FRRS-Up, FRRS-
Down, FFR1, FFR2, CR2, SR2, subtract the shadow price of the constraint that limits how much of that AS can be procured. This shadow price includes any opportunity costs if present
– The resulting computed price for each of the FRRS-Up, FRRS-Down, FFR1, FFR2, CR2 and SR2 is compared to each of the respective equivalent MCPCs for RegUp, RegDown, PFR, CR1, and SR1.
– If this computed price is less than the MCPC for RegUp, RegDown, PFR, CR1, and SR1 , then the MCPC for FRRS-Up, FRRS-Down, FFR1, FFR2, CR2, and SR2 is set to the equivalent MCPC of RegUp, RegDown, PFR, CR1, and SR1 respectively
– The end result is that the MCPC for FRRS-Up, FRRS-Down, CR2, SR2 are the same as the MCPC from the FAST proposal
Alternate Proposal 1
5
Alternate Proposal 1
6
AS MCPC
FRRS-Up RegUp MCPC
FRRS-Down RegDown MCPC
FFR1 Max( PFR MCPC, Ratio * PFR MCPC – Shadow Price of FFRmax constraint1 – Shadow price of FFR1max constraint1)
FFR2 Max( PFR MCPC, Ratio * PFR MCPC – Shadow Price of FFRmax constraint1 )
CR2 CR1 MCPC
SR2 SR1 MCPC
1 Opportunity costs, if present, will be included in the shadow prices
• In case there is a need to replace FFR1 or FFR2 responsibility with an equivalent PFR, then this proposal leads (when the ratio is greater than 1) to a replacement cost that may be inconsistent with the cost of replacing PFR MW with another PFR MW• Occurs when Shadow price of FFRmax constraint and/or
FFR1max constraints is binding and the Ratio (R) is greater than 1
Alternate Proposal 1
7
• This proposal changes the current policy of pricing equivalent AS MW awards the same for equivalent AS types– Starting with the FAST formula for MCPC for FRRS-Up, FRRS-
Down, FFR1, FFR2, CR2, SR2, subtract the shadow price of the constraint that limits how much of that AS can be procured. This shadow price includes any opportunity costs if present
– This resulting computed price is the MCPC for each of the FRRS-Up, FRRS-Down, FFR1, FFR2, CR2, and SR2
– The end result is that even though substitutability is maintained, the resulting MCPCs for FRRS-Up, FRRS-Down, FFR1, FFR2 CR2, SR2 are as if they were cleared on their own offer stack
Alternate Proposal 2
8
Alternative Proposal 2
9
AS MCPC
FRRS-Up RegUp MCPC – Shadow price of FRRS-Upmax constraint*
FRRS-Down RegDown MCPC – Shadow price of FRRS-Downmax constraint*
FFR1 Ratio * PFR MCPC – Shadow Price of FFRmax constraint* – Shadow price of FFR1max constraint*
FFR2 Ratio * PFR MCPC – Shadow Price of FFRmax constraint*
CR2 CR1 MCPC – Shadow price of CR1min constraint*
SR2 SR1 MCPC – Shadow price of SR1min constraint*
*Opportunity costs, if present, are included in the shadow price
• In case there is a need to replace FRRS-Up, FRRS-Down, FFR1, FFR2, CR2, SR2 responsibility with an equivalent RegUp, RegDown, PFR, CR1, SR1, then this proposal leads to a replacement cost that may be inconsistent with the cost of replacing a given AS type with exactly the same AS type (i.e. PFR for PFR, etc.)• Occurs when the shadow price of the constraint that is
subtracted is binding
Alternate Proposal 2
10