49
ES10026 Examensarbete 30 hp December 2010 Power quality in low voltage grids with integrated microproduction mårten einarsson

Full Text 01

Embed Size (px)

DESCRIPTION

power uality

Citation preview

ES10026

Examensarbete 30 hpDecember 2010

Power quality in low voltage grids with integrated microproduction

mårten einarsson

Teknisk- naturvetenskaplig fakultet UTH-enheten Besöksadress: Ångströmlaboratoriet Lägerhyddsvägen 1 Hus 4, Plan 0 Postadress: Box 536 751 21 Uppsala Telefon: 018 – 471 30 03 Telefax: 018 – 471 30 00 Hemsida: http://www.teknat.uu.se/student

Abstract

Power quality in low voltage grids with integratedmircroproduction

mårten einarsson

This report seeks to evaluate and predict possible power quality issues regardingFortums engagement in the project of Stockholm Royal Seaport. Stockholm RoyalSeaport is a city district planned by Stockholm Municipality to be constructed basedon sustainable urban city principles. Fortum has, together with additional partners,engaged in the challenge to create a sustainable energy system. This is thought to be achieved through several measures. Energy saving actions arein-corporated at several levels and there is a plan to create a “smart grid” for theelectricity supply. A smart grid has no strict definition but in this case a key feature is“demand-response” which effectively means a way to optimize the consumption tohave a more balanced consumption over the 24 hours of a day. One of the key components in the smart grid is the “active house” which is plannedto have several specific features separating it from an ordinary house. It is planned tohave its own contribution to electricity production using solar cells and an energystorage using batteries. Another feature is thought to be both automation andeconomic incentives measures to achieve peak load reduction. This thesis has taken the perspective of the end customer in the active house and hastried to evaluate the power quality to be experienced. An investigation regarding thedif-ferent components has been carried out to get an overview from the mentionedperspective and identify possible problems or issues that may require attention in therealization of Stockholm Royal Seaport. It has been found that no major problems are to be expected but some smaller issueshas arisen that might be worthwhile giving some attention.

Sponsor: Fortum Distribution ABISSN: 1650-8300, ES10026Examinator: Kjell PernestålÄmnesgranskare: Mats LeijonHandledare: Jan-Olof Olsson, Johan Lundin

4

5

Sammanfattning

Den här rapporten syftar till att evaluera och förutspå eventuella elkvalitetsproblem för

Fortums engagemang i projektet Norra Djurgårdsstaden. Norra Djurgårdsstaden är en

stadsdel i Stockholm planerad av Stockholms stad i hållbarhetens tecken. Fortum har, till-

sammans med ytterligare aktörer, engagerat sig i att skapa ett hållbart energisystem.

Detta är tänkt att uppnås genom flera åtgärder. Energibesparingsåtgärder utförs på flera

plan och man tänker sig implementera ett koncept man kallar ”smarta nät” för elförsörj-

ningen. Ett smart nät kan definieras på flera olika sätt men här handlar det mycket om att

styra elkonsumtion för att uppnå en jämnare elförbrukning över dygnet.

En av baskomponenterna i det tänkta smarta nätet är det ”aktiva huset” som planeras ha

ett antal speciella egenskaper jämfört med ett ordinärt hus. Man tänker sig egen elproduk-

tion i form av solceller samt energilagring med hjälp av batterier. Man tänker sig också

olika former av mjuka och hårda styrmedel för att kontrollera elkonsumtion.

Examensarbetet har utgått från slutkund i det aktiva huset och har sökt utvärdera vad

denne kommer att uppleva i form av elkvalitet. Man har tittat på de olika komponenterna

för att bilda en helhetsuppfattning ur det givna perspektivet och identifiera eventuella pro-

blem eller frågeställningar som kräver uppmärksamhet inför genomförandet av projektet

Norra Djurgårdsstaden.

Examensarbetet har börjat med att definiera begreppet elkvalitet som utgångspunkt. Det

är väldigt vagt formulerat i svensk lagstiftning utan grundar sig på branschpraxis som utgår

ifrån ett antal europeiska standarders. Vidare förs en diskussion om vem och vad som på-

verkar elkvaliteten i nätet.

Därefter görs en grov ekonomisk uppskattning kring problem orsakade av elkvaltetsfe-

nomen. Olika rapporter från forskningsorganet Elforsk har gåtts igenom och citeras på

uppgifter kring samhällsmässiga, företagsmässiga och privata utgifter i relaterade till dålig

elkvalitet.

Det görs sedan en mer teknisk utvärdering av problemet. Här börjar man i den tilltänkta

applikationen, solceller, för att ta reda på vilka elektriska egenskaper denna har. Dessa

egenskaper har sedan tagits som mall för att utvärdera möjliga elkvaltetsproblem uppkom-

na i Norra Djurgårdsstaden.

Man har funnit att det inte väntas uppkomma några större problem men har identifierat

några punkter som kan komma att kräva lite noggrannare övervägning.

Nyckelord: elkvalitet, lågspänningsnät, solceller, mikroproduktion, smarta elnät, Norra

Djurgårdsstaden

6

7

Innehållsförteckning

1 Background 10 1.1 Stockholm Royal Seaport ............................................................................................ 10 1.2 Actors and research goals ........................................................................................... 10 1.3 Distributed generation .................................................................................................. 11 1.4 This thesis relation to the over all goal ......................................................................... 11

2 Theory 12 2.1 The power grid of today ............................................................................................... 12 2.2 Future grid ................................................................................................................... 12 2.3 Motivation to a Power Quality study ............................................................................. 13

2.3.1 Voltage drop ..................................................................................................... 13 2.3.2 Less traditional loads ........................................................................................ 15 2.3.3 Phase asymmetry ............................................................................................. 15

3 Power Quality 16 3.1 General and definition .................................................................................................. 16 3.2 A brief description of the phenomena [V] ..................................................................... 17

3.2.1 Outage.............................................................................................................. 17 3.2.2 Frequency variations ........................................................................................ 17 3.2.3 Phase angle ..................................................................................................... 17 3.2.4 Transients ......................................................................................................... 17 3.2.5 Harmonics ........................................................................................................ 17 3.2.6 Voltage variations ............................................................................................. 17 3.2.7 Flicker ............................................................................................................... 18 3.2.8 Asymmetry ....................................................................................................... 18

3.3 Regulations and Guidelines ......................................................................................... 18 3.4 Official documents ....................................................................................................... 18 3.5 Crude guidelines .......................................................................................................... 19 3.6 Actual threshold values ................................................................................................ 19 3.7 Comments to EN 50160 .............................................................................................. 21

4 Dangers and implications of bad power quality 22 4.1 Fortums distributing role .............................................................................................. 22 4.2 Protection .................................................................................................................... 22 4.3 Common customer damage claims ............................................................................. 23 4.4 A theoretical example .................................................................................................. 24 4.5 Costs related to power quality on a national scale ....................................................... 24 4.6 Discussion about power quality costs .......................................................................... 25 4.7 Good power quality is sought ...................................................................................... 26

5 Solar cells 28 5.1 History ......................................................................................................................... 28 5.2 Functionality ................................................................................................................ 28 5.3 Electrical characteristics .............................................................................................. 29 5.4 Output of power ........................................................................................................... 32

8

6 Other components in Stockholm Royal Seaport 33 6.1 General ....................................................................................................................... 33 6.2 PV generation and batteries ....................................................................................... 33 6.3 Electric cars ................................................................................................................ 34

7 Detailed descriptions of PQ phenomena and its effects 36 7.1 Outage ........................................................................................................................ 36

7.1.1 Outages in Stockholm Royal Seaport .............................................................. 37 7.2 Frequency variations................................................................................................... 37

7.2.1 Frequency deviations in Stockholm Royal Seaport ......................................... 38 7.3 Phase angle ................................................................................................................ 38

7.3.1 Phase angle in Stockholm Royal Seaport ....................................................... 38 7.4 Transient over voltages............................................................................................... 38

7.4.1 Transients in Stockholm Royal Seaport ........................................................... 39 7.5 Harmonics ................................................................................................................... 39

7.5.1 Harmonics in Stockholm Royal Seaport .......................................................... 40 7.6 Voltage variations ....................................................................................................... 40

7.6.1 Swells .............................................................................................................. 41 7.6.2 Dips ................................................................................................................. 41 7.6.3 Current transients ............................................................................................ 41 7.6.4 Voltage variations in Stockholm Royal Seaport ............................................... 42

7.7 Flicker ......................................................................................................................... 42 7.7.1 Flicker in Stockholm Royal Seaport ................................................................. 43

7.8 Asymmetry .................................................................................................................. 43 7.8.1 Asymmetry in Stockholm Royal Seaport ......................................................... 44

7.9 Summary .................................................................................................................... 44

8 Conclusions 46

Acknowledgements 49

9

10

1 Background

1.1 Stockholm Royal Seaport

Stockholm municipality has taken an initiative to carry out a large scale replanning

of a city district through an organization called Stockholm Innovation. This district

is located around Hjorthagen and Värtahamnen and the project goes under the

name Stockholm Royal Seaport.

The main focus of this new city district revolves around sustainable urban solu-

tions. The project is part of Clinton Climate Initiative which is a cooperation be-

tween 40 cities across the world to reduce greenhouse gases emissions. The CCI

acts as a forum for the participants to exchange experiences in order to promote

advances within the field1.

1.2 Actors and research goals

Together with ABB, Fortum has joined the project from its position as leading

provider of electricity and heat. The idea is to create a full scale test site for a con-

cept called “smart grid” that is looked upon as very promising in the struggle to

fight climate change. There is no strict definition of what a smart grid is but gener-

ally all mentioned properties of a smart grid refer to different ways to optimize

electricity generation, transmission and consumption in a smart way. A key feature

of the smart grid planned for Stockholm Royal Seaport is the utilization of demand

– response technology. This effectively means that one wants to smoothen out the

power consumption over a 24 hour horizon, e.g. decrease consumption peaks and

move consumption to times when consumption is lower. This is also thought to be

achieved through energy storage[II].

1 www.clintonfoundation.org, march 2010

11

1.3 Distributed generation

Another aspect of Fortums involvement in the Stockholm Royal Seaport project is

the addition of micro production of electricity. For the specific case of Stockholm

Royal Seaport, this means electricity production from solar cells. This project is

supposed to be a forerunner of things to come. There are strong indications that

the electrical environment is about to change from its traditional layout to a much

more diversified system with new components to take into account. Small scale

production units, connected in locations where the grid was not originally de-

signed to connect them, is such a thing. This is generally a widely accepted way to

reach goals of renewable energy input set up by both Swedish authorities and

European guidelines.

1.4 This thesis relation to the over all goal

The goal of this thesis project has been to look at what can be expected to be the

implications of such a change in the providing electrical system from the end cus-

tomers point of view. The focus will be on power quality, what problems can be

expected, how harmful these problems are expected to be and how to address

them.

12

2 Theory

2.1 The power grid of today

The distribution network of tradition is built up around big powerful production

units. These units generate onto a core grid that transports the power in high volt-

age to the different consumers. Some industrial consumers that are heavy power

consumers are connected to the grid on the high voltage side and a regular domes-

tic consumer is typically connected at the low voltage side.

Fig 1. Schematic view of traditional power gridFel! Hittar inte

referenskälla.

2.2 Future grid

The trend within the electricity sector is pointing towards a more diversified grid

concept. It is expected that the future grids will be more diversified in both genera-

tion and consumption[II]. This is a feature of the subtle expression “smart grids”.

13

Substation

User

240V

230V

Substation

User

230V

220V

Fig 3. Voltage upped at the

substation to meet demand

This thesis takes aim at providing a small piece of the puzzle in exploring how

distributed generation can affect the power quality in the low voltage grid. The

thesis is generally focused a bit more on solar power generation but as we will see

later on, the conclusions draws can be applied to other power sources.

Fig2. Schematic view of a more diversified expected future power gridFel! Hit-

tar inte referenskälla.

2.3 Motivation to a Power Quality study

Why, then, should any problems with power quality be expected approaching this

future view of the grid? Below follows a theoretical example and other reasoning

intended to illustrate how this diversified generation might affect the end user. The

example is of course greatly simplified but aims to describe a real phenomenon in

the grid today.

2.3.1 Voltage drop

When moving down in voltage, the current must be increased in order to transmit

the same amount of power. This leads to an increase of

thermal losses. Thermal losses causes a voltage drop over

the given transmission line. In areas with a weak grid these

losses can be of a non negligible magnitude and will result in

a lower voltage at the end user than at the substations low

voltage side. This is traditionally dealt with by upping the

voltage at the transformer to give the end user a good volt-

age[I].

14

Substation

n

230V

240V 240V

250V

User Producer

Fig 4. Over voltage at end consumer

when back-feeding the grid

Now we consider the case of the end user becoming a small

scale producer of electricity. If he produces a larger amount of

electricity than he consumes he will probably try to export the

excess onto the grid. This means that he will have to overtake

this voltage differential. Twice. This will effectively put him at

250V in the example illustrated. If the production originates

from a stochastic energy source, such as solar photovoltaic, it

would also give large instant fluctuations when quickly switch-

ing between 250V and 230V.

This voltage drop can be seen in the grids of today, see fig 5.

Fig 5. Screenshot from the computer program “Power Grid” used by Fortum

15

2.3.2 Less traditional loads

The deviations from nominal power properties do not only depend on the feeding

from the substation. They also heavily depend on the properties of the electrical

load that the power is supposed to drive. The example above with voltage fluctua-

tions is greatly simplified. For example, a grid with many electrical motors as

loads has energy stored in the rotating mass of both the motor itself and its con-

nected mechanical load. The grid therefore has an inertia counteracting the sudden

voltage change described above. This phenomenon is a stabilizing factor in large

interconnected grids and works better the higher the short circuit power is.

However, the continuing trend regarding the composition of electrical loads

points toward a lower percentage of mechanical loads and motors and a higher

percentage of micro and macro electronical loads[IV]. The mentioned regulating

inertia, also known as frequency regulation, is therefore predicted to have a some-

what smaller impact in the future. This suggests that an external support for grid

stabilization might have to be considered.

2.3.3 Phase asymmetry

The ideal state of power is perfectly symmetrical three phase at nominal sinusoidal

voltage. But not all equipment we use run on three phase power. In practice, the

tradition has been to roughly divide the one phase loads between the phases. This

works quite well. However, in the case of small scale production one might not

consider the idea of three different inverter systems for one installation to be rea-

sonable. To add production in one phase would potentially cause symmetry prob-

lems.

16

Fig 6.Schematic view of different Power Quality phenomena

3 Power Quality

3.1 General and definition

The concept of power quality is not strictly defined. It varies with the requirements

of the consumer and the electrical characteristics of the load of the consumer.

Therefore the responsibility of maintaining a good electrical environment falls

upon both the distributor, the manufacturer of the application and the user of the

application.

There are, however, several phenomena that can cause problems of different mag-

nitude for a grid connected user. Examples of these are harmonics, voltage varia-

tions, asymmetry between phases, frequency deviations and so on. All of these

phenomena describe states that in some way deviate from the nominal state of the

electrical characteristics, see fig 6.

- One can therefore define power quality as the absence of these phenom-

ena.

Frequency

variations

Distorted

Phase Angle (Active/Reactive

power)

Voltage

characteris-

tics

Asymmetry

Harmonics Transients

Flicker Voltage

variations

Power

Quality

Outage

17

3.2 A brief description of the phenomena [V]

3.2.1 Outage

Outage describes a state where the power supply is cut. This is defined as below

10% of nominal voltage. Outages are in many documents labelled “service reli-

ability” and treated as a different kind of problem not really related to power qual-

ity issues.

3.2.2 Frequency variations

Deviances from the nominal frequency which is in Sweden set to 50 Hz. Theo-

retically, any node of an interconnected (AC) grid should have the exact same fre-

quency. This is not the whole truth in reality. Weak parts of the grid have more

local frequency issues in general than strong parts of the grid. Frequency devia-

tions also tends to become an issue when dealing with islanding or closing in on

such a state.

3.2.3 Phase angle

Refers to a situation where the voltage and current goes slightly out of phase to

one another. This is created by the inductive part of the impedance of both trans-

mission equipment and loads where motors and generators are significant con-

tributors.

3.2.4 Transients

A temporary increase in voltage. Usually occurs when large units are connected

or disconnected from the grid or by the act of thunder. A transient can increase the

voltage by an order of magnitude lager than the nominal voltage. This does not

however mean that they contain a large amount of energy as they are usually very

short in time and low on current.

3.2.5 Harmonics

Signals of a frequency that is a multiple of the nominal frequency are called

harmonics and are potentially very harmful.

3.2.6 Voltage variations

Called ”Swells” in the case of an increase and ”dips” in the case of a decrease.

Needs to be in effect over a couple of periods to qualify as swells rather than tran-

sients.

18

Fig 7. Citation of the Swedish law of electricity

3.2.7 Flicker

A quite subjective phenomena. The term “flicker” refers to the variations in

light emitted by light bulbs. It is hard to define electrically and has a definition

based on the perception of the human eye.

3.2.8 Asymmetry

The unbalance between the phases of a three phase system. An unbalance oc-

curs when one or more of the phases displays a slightly different voltage, current

or deviates from the 120 degrees phase shift supposed to be there.

3.3 Regulations and Guidelines

Ellagen 3 kap §9:

” 9 § Den som har nätkoncession är skyldig att på skäliga villkor överföra el

för annans räkning.

Överföringen av el skall vara av god kvalitet.

En nätkoncessionshavare är skyldig att avhjälpa brister hos överföringen i

den utsträckning kostnaderna för att avhjälpa bristerna är rimliga i förhål-

lande till de olägenheter för elanvändarna som är förknippade med bristerna.

Regeringen eller den myndighet som regeringen bestämmer får meddela

föreskrifter om vilka krav som skall vara uppfyllda för att överföringen av el

skall vara av god kvalitet. Lag (2005:1110).”

3.4 Official documents

Fig 7 is a quote from the Swedish legislation. It states that the transmission of

power should be of good quality. Furthermore it states that the operator is obli-

gated to remedy possible faults of the transmission to an extent that the benefit is

reasonable in proportion to the cost[VII]. The legislation is in other words open to

interpretation. The operator is legally obligated to measure amount of consumed

electrical energy and its distribution over time for a connected consumer. There

are however not any legal obligation to measure voltage quality[VI].

What is considered to be good power quality in Sweden is commonly agreed to be

in line with the guidelines provided in the European standard EN 50160; “Voltage

characteristics of electricity supplied by public distribution systems”. This stan-

19

dard provides threshold values for the supply voltage of a given grid. All of the

phenomena in fig 6 are described there. It is however erroneous to only discuss the

supply side of a given node. The electrical environment is also dependant of the

dynamics of the load connected. Therefore, another series of standards have been

developed called EN 61000 “Electromagnetic Compatibility (EMC)” with many

subdocuments called EN 61000-1-2 etc. This series of standards specify how the

connected equipment should behave electrically.

Together these sets of documents paint a picture of how the electrical envi-

ronment should behave.

3.5 Crude guidelines

Many large installations require better power quality than the values allowed by

the EN 50160[I]. Such installations may be process industry or something alike

and are generally also large consumers. In those cases it is common for the pro-

vider, consumer and manufacturer to through a discussion reach a level of quality

that is most beneficial. This is the most cost effective way to deal with power qual-

ity issues but puts high demands on the competence of the consumer in order to be

feasible.

3.6 Actual threshold values

A good overview of the document EN 50160 can be found in an interpretational

document called “voltage disturbances”[VIII]. Here we also see the comparison to

the EN 61000 document sets which gives a better perspective on the regulations

for electrical environment.

20

Fig 8.Table of threshold values of EN 50160 and EN 61000 [VIII]

21

3.7 Comments to EN 50160

It is important to keep in mind that the strife for good power quality should not be

a goal in itself. Many (or actually most) applications do not require perfect power

quality and it is therefore unreasonable and uneconomical to create an environ-

ment with perfect power quality. The stakeholders should instead, through a dis-

cussion, settle on a level that is most beneficial for all parts. Industries and com-

mercial consumers also in general require a higher level of power quality.

The EN 50160 is under revision. A European cooperation is undergoing to re-

vise this standard and a set of recommendations have been presented by ERGEG

and is supposed to be accepted as changes to the existing version[VII].

The above mentioned EN 50160 set to describe the properties of the supply vol-

tage is limited to only apply under normal operating conditions. This of course

means that when an event occurs, planned or unforeseen, the grid is immediately

outside of normal operating conditions and a customer cannot claim the protection

of EN 50160.

22

4 Dangers and implications of bad power quality

To further motivate the conduction of this study some words regarding the conse-

quences of bad power quality should be mentioned.

4.1 Fortums distributing role

Fortum is because of their position as electricity provider responsible for the prod-

uct they deliver, namely electricity. Therefore they occasionally get damage

claims from customers who have in some way received a bad product. Since the

legislation in Sweden is open to interpretation[VI] and measurements at a single

user are very seldom carried out, a big lack of information is common in such

cases. A section within Fortum that works with damage claims handles the re-

ceived claims and cross check the time of the reported incident with records of non

ordinary behaviour in that region of the grid. This can be due to repairs, malfunc-

tions of equipment or new installations in the area. But over all the information is

scarce, especially specific details about exactly what has electrically happened at

the feeding point of an end consumer.

4.2 Protection

The low voltage grid is protected only by breakers that react to large currents and

short circuits. There is traditionally no protection against voltage variations[IX].

This is due to the fact that the voltage is relatively stable which means that high

currents represent high powers. High powers are what is dangerous to persons and

property. This is regulated by elsäkerthetsverket in Sweden and follows more

strictly defined regulations than power quality since it is considered a safety issue.

The simple principal of this is that the series of interconnected conductors that

constitutes the grid always are dimensioned for a maximum power flow. A breaker

is installed as the weakest link of a section of conductors and will hence trip and

cut power at a set value of current flow to protect the installation. This principal is

23

used in all voltage levels of the grid and manifests itself at the end consumer as a

fuse.

4.3 Common customer damage claims

Many of the problems reported to Fortums damage claim coincide with faults on

the zero conductor. Modern installations in buildings include a residual-current

device (jordfelsbrytare), required by law on public buildings and outdoor installa-

tions. The design of the residual-current device is made to cut power when a dif-

ference between phase current and PEN current is detected, i.e. current leakage.

Older installations are not protected in this way and are susceptible to zero con-

ductor faults. Such a fault often occurs together with maintenance or repair work.

Such a fault can potentially give 1 phase equipment a voltage of 400V instead of

the nominal 230V[IV]. This often leads to extensive equipment damage but can

also be a safety hazard.

Fig 9. Left: PEN conductor lost. Right: short circuit between a line and neu-

tral[IV].

Claims can then typically include domestic equipment such as dishwashers, refrig-

erators etc. In some cases, claims can include virtually all electrical equipment in

the house [X]. A received damage claim is treated by Fortums personnel who open

a case for investigation. The case is then revised and the incident is cross checked

versus known incidents in the grid matching the time interval given such as main-

tenance work or detected faults. If the claim is for a larger amount of money, in-

surance companies usually handles the process of juridical responsibilities. For-

tums investigators also do this for claims of lesser values. The previously men-

tioned lack of information is however a big issue. In cases where there are no in-

ternal records of deviances from normal operation it is a case-to-case decision.

24

Since all decisions needs to be backed up by documentation, installation electri-

cians and entrepreneurs are consulted for a professional statement. In cases where

there is no relevant data to consult a decision is made on a probability estimation.

4.4 A theoretical example

Problems may arise when consumers connect large temporary loads, especially if

they are one phase connected. A good example can be a part of a suburban grid

with a few villas connected to the same substation where the grid is not too strong.

If one of the consumers connects a welding machine running on one phase power

it will probably affect his neighbours in a negative way. Such a load is an intense

power consumer and is also rapidly switched on and off. Visual effects will be

flicker in lights connected to the same phase and possibly a brief hiccup in electri-

cal motors such as fans. Unnoticed effects might be three phase connected motors

damages such as washing machines, dryers, water pumps etc. who receive an un-

balanced power input. This will be extra bad if the electrical characteristics of the

load contain a big inductive part, in which case three phase motors will be sub-

jected to a counteracting magnetic field which will lower its efficiency and cause

more wear and tare. Such a scenario is clearly caused by the introduction of an

exceptional load but the responsibilities are not clearly defined, see section Power

Quality. The welding machine should obey the emission standard SS-EN 61000-3-

2 [XI]but even if it does so the neighbours might experience problems in a weak

grid. This results is a situation where the electricity provider has kept up his end,

the welder producer has kept up his end but some customers still experience a de-

generation of their power supply. This knowledge of the behaviour of the low

voltage grid is far from general knowledge among house owners. From a custom-

ers point of view the product they are buying is suddenly changing from good to

bad without them changing anything. A survey carried out by Elforsk shows that

customers put responsibility foremost on the electricity provider, secondly on the

electrical installation entrepreneur. The device manufacturer comes in third place

and on fourth neighbouring consumers[XII].

4.5 Costs related to power quality on a national scale

Elforsk has in December of 2006 put together an evaluating report about power

quality and its implications[I]. This report evaluates the full national electrical sys-

tem from small apartment consumer to major processing industries, but it still

helps us to put economical figures on the issue of power quality in the low voltage

grid. A good overview table can be found on page 44

25

Fig 10. x-axis reads “process industry, production industry, commerce, office, real

estate, public, rural, households”, y-axis reads “long outages, short outages, tran-

sients, voltage variations, harmonics, voltage asymmetry, flicker” . Digits are in

million SEK. “begr” means “limited”[I]

4.6 Discussion about power quality costs

Dissecting this table we can see that outages in general are by far the most expen-

sive power quality problem. This is also the most well-documented phenomena.

The cost is mainly due to production interruptions. The high figures for short out-

ages is because a short interruption or power dip often trips safety equipment and

takes some time to restore. In this way, a power cut of half a second can result in

production interruption of several hours. This is obviously not desired and many

large power consumers have supporting equipment of their own to guard them-

selves against this.

When looking at domestic households, transients and voltage variations stand out

as big expenses. This is interesting for the topic of this thesis. The figures pre-

sented correspond almost exclusively to damaged equipment. A big part of this is

equipment connected to two or more electrically signalling grids, e.g. distributing

network and tele network. An over voltage in one of them gives an unnatural volt-

age difference between the two systems. This difference will be present inside of

26

the device which the device is generally not constructed for. More on this in sec-

tion “Detailed description”. Even though these estimations are quite rough they

still provide some idea of what good power quality at the end consumer could be

worth. This of course has to be weighed against the investment needed to re-

duce/eliminate the given problem.

Another report from Statens Energimyndighet dated 2003[XIII] states:

Fire in property due to over voltages:

xa100 x 1 million

100

Damages to domestic and office electronic devices etc covered by

home- and property- insurances:

22 000 x 10 000 kr

220

Damages covered by product warranty: 50

Damages to electronic devices not covered by insurance: 150

Sum 520

As we can see, Fortum does not carry the heavy financial burden of bad power

quality. The Cost is distributed among all the actors. This can be considered rea-

sonable given the previous discussion about the shared responsibility regarding the

electrical environment. All documents regarding power quality stress the fact that

a reasonable electric environment must be achieved through cooperation between

the parts involved. But when looking at the financial part of the problem, an addi-

tional actor enters the scene. Insurance companies. There are examples of cases

when legal processes are carried out between Fortum and insurance companies

regarding financial compensation to a customer. This can be a hot subject if for

example a full out fire has occurred in a real estate worth very much money. If the

fire is severe, the evidence is probably damaged and a lengthy legal process may

be the result.

4.7 Good power quality is sought

As a final word to conclude it can be said that that a good electrical environment,

good power quality, is worth a significant amount of money for all parts involved.

The price for bad power quality is divided among the stakeholders with an over-

weight on the consumer and commercial players. The price to achieve good power

quality, the investments needed to be made, is also divided among the players[I].

27

28

5 Solar cells

5.1 History

Electricity production from solar cells is also called PhotoVoltaic generation. The

phenomenon was first discovered by Alexandre-Edmond Becquerel (father of

Henry B.) in 1839 . This is about the time when humanity first started to discover

electricity (Faraday’s law of induction in 1831) and the vast possibilities of elec-

trical energy was not yet known. The first selenium solid-state cell was invented in

1876. The next big leap comes with the introduction of semi conductors in the

1950:ies. The modern silicon solar cell was invented at Bell Labs in 1954. It found

a natural niche in the space program and the first silicon solar cell was launched in

1958. Power generated from sunlight and without moving parts is of course ideal

for this purpose. This helped the development greatly because of the abundant fi-

nancial funding of the likes of NASA[XIV].

5.2 Functionality

A solar cell is essentially a diode. It utilizes the photoelectric effect which means

that electrons are energized by photons; light. In a semi conducting material such

as silicon, with four out of eight possible electrons in its outer shell, this means

that an excess electron is knocked loose to move freely in the crystal structure. As

the electron is knocked loose, a gap appears where it was located. This gap also

moves freely and is labelled a “hole” and treated as a particle of its own. The pho-

ton has thus created an electron-hole pair.

The natural thing for the electron and the hole to do is to quite soon find each

other and free the energy now bound in them into dissipating heat. To prevent this,

the silicon is doped. Doping means that some impurities are introduced in the crys-

talline structure. Materials introduced include one extra, or one less, electron in its

outer shell. This shortage / excess of electrons create an electric field between

29

Fig 11.Schematic view of a Solar Cell

them. This electric field separates the electrons from the holes which are attracted

to opposite sides of the cell. When the two sides are connected by an external con-

ductor a current arises. The solar cell is complete see fig 11.

5.3 Electrical characteristics

A single solar cell is, as shown in figure above, has only one voltage level. In a

silicon cell it is 0.6-0.7 V. This is a quantum mechanical property of the semicon-

ducting element silicon. The distinct value corresponds to the potential difference

between the valence band and the conducting band within the silicon and corre-

sponds to any photon carrying an energy of 1.2 eV or higher. This means light of

wavelength 1022 nm or shorter1 . An increase of the area of this theoretical cell

will increase the irradiance of light fallen upon it which will increase the number

of electron-hole pairs created. This will increase the current that can be drawn

from the cell but will not affect the voltage.

Since a voltage level of 0.6 V is very low something must be done to up the

level. This is done by connecting several cells in series into modules. Theoretically

this principle can be used to reach any voltage level desired. But the trade off in

doing so is that the module, being a closed electrical circuit will have its current

limited by its least conducting cell, the “weakest link of the chain”. This practi-

cally means that if an obstacle located as illustrated in cell “B” in fig 12 below will

1 E = h * f → E = h * c / λ → λ = h * c / E = 4.13 * 10-15 [eVs]* 2.97 * 108 [m/s ]/ 1.2 [eV]= 1022

* 10-9 [m]

30

Fig 12. Solar cells and batteries connected in series

limit the array to about 95% of its capacity, whereas an obstacle as illustrated in

cell “C” in fig 12 will make the whole array dead[XIV].

The electricity production of solar cells is also temperature dependant. The hotter

the cells get, the lower efficiency they get. Efficiency is also limited by obstacles

(as illustrated above), malfunctioning or inferior cells and of course whether the

sunlight is direct or indirect. Fig 13 below shows a theoretical solar cell’s electri-

cal variances.

31

Fig 13. I-V curve of a solar cell [XIV]

In figure 11 X-axis shows voltage, Y-axis shows current. The green curve illus-

trates a cells ability to conduct current without being hit by sunlight. This curve

resembles the conducting curve of a diode. The blue curve, which is almost identi-

cal to the green curve except a constant is added, shows a solar cells ability to

conduct (create) current when illuminated by light. The point marked “ISC” on the

Y-axis is a theoretical maximum current the cell can create when short circuited.

Similarly the point marked “VSC” on the X-axis is the voltage across the cell when

no closed circuit is made and the voltage is measured across the cell. This voltage

should in the ideal case be the previously mentioned 0.7V but is in reality closer to

0.5V. Depending on ISC, VSC and the shape of the blue curve, the red curve is de-

rived. The red curve stands for output power, I * V, and is of course what we are

looking for in electricity production. As shown in picture there is an optimal rela-

tion between current and voltage at which we want to operate in order to reach

maximum efficiency. This is achieved by controlling the load in the circuitry to

draw the exact amount of current that corresponds to the cell’s, or rather the array

of cells’, “IMP”.

32

5.4 Output of power

The load in this case is a power inverter. An inverter takes DC power as input

and inverts it to AC power, in this case 230V 50Hz to feed the grid. In order to be

able to feed the grid, and not have power fed from the grid to the inverter, the in-

verter needs to keep a slightly higher voltage than the grid has at the point of con-

nection. In the same way the DC input voltage from the solar modules must be

slightly higher than the input at the inverter. (For the same reasons a similar con-

trol system is also required when charging batteries from solar cells even though

both batteries and solar cells operate on DC power.) This obviously introduces the

need for a dynamic control system in order to be kept working at a good effi-

ciency. It is usually this full control system and its power electronics that is called

inverter.

From the grids point of view there is just an inverter. The electricity is “created”

in the inverter and one can therefore make the argument that it is an electrically

robust installation. Disturbances and deviations (however unlikely) in the main

producing PV-arrays would not carry through to the AC power output.

The inverter furthermore inverts the power created by the installation. If less

power is created the inverter stays with the same voltage level but lowers its power

output. Therefore the system will affect the grid the most when the power output is

the highest. Thus, the thesis is focused on the installations maximum rated power.

33

6 Other components in Stockholm Royal Seaport

6.1 General

The previous chapter about solar cells was chosen because it is the main new

component close to the end user. It was also chosen because it serves as a good

example of other components. Since the objective of the thesis was to look into

possible power quality issues at the end consumer, it does not exclusively concern

solar power. However, there is a lot to be learned by studying the properties of

solar power.

6.2 PV generation and batteries

The power electronics controlling the cells and making proper power output

from them are the key. These power electronics are very much the alike the con-

trolling electronics for batteries. They have an energy source operating in a certain

voltage interval. For solar cells the voltage varies within the interval with obsta-

cles, temperature and other minor aspects. For a battery it varies with the charge

percentage, age, temperature and so forth. The electricity sources are in other

words very similar. The inverter then takes this as input, keeps it at optimum volt-

age level and transforms the power to nominal grid AC. (A big difference obvi-

ously being that the electronics for the batteries needs to be able to charge the bat-

teries as well as draw power from them.)

The figure below shows the schematic outline of the “passive house” and its

properties thought to be implemented in Stockholm Royal Seaport. Worth noting

is that 100m2 of solar cells corresponds to roughly 14kW power (peak effect)

which is strikingly close to the 13kW suggested for the batteries[II].

The yellow square with a blue lid in the apartments represent controllable loads

that the smart grid operator can use to balance power consumption over time.

34

Fig 14. Schematic view of the “active house” of Stockholm Royal Seaport

6.3 Electric cars

The electric cars are thought to be a key component in grid management. They

are thought to be charged at night to balance power consumption over the 24 hours

of the day. But electric cars are still a few years into the future and have therefore

not been a main focus in this thesis.

• 1 Building

• 40 apartments

• Normalized consumption pro-file according to research in Elforsk report 8:54,

• Estimated consumption of 4100 kWh per house-hold/year

• Controllable loads dishwash-er and textile washing/dryer, Total 43 kWh/daily

• Photovoltaic generation, 10 000 kWh/year (100m2), 48kWh 200 days/year

• Battery size 13 kW, 54 kWh recycled daily, approx 1500 kg batteries

35

36

Fig 15.Schematic view of different Power Quality phenomena

7 Detailed descriptions of PQ phenomena and its effects

7.1 Outage

Outage is the most dominant part of quality issues and also the easiest to measure

and find data records of. Outages are always caused by a fault, either spontaneous or

as a result of human error. An outage is comparably easy to cost-estimate. An outage

effects industry the hardest, especially production industry where a lack of production

of course leads to significant costs[I].

The costs for a domestic user are harder to estimate. There are of course examples

though. A case from damage claims tells a story where an outage to a summer cabin in

Dalarna caused the pipes to freeze and Fortum paid damages for 37000SEK[X]

An outage of more than 12 hours is compensated economically with a minimum of

900SEK and a maximum of 300% of the customers’ estimated yearly feeFel! Hittar

inte referenskälla.. Outages of this magnitude are generally rare and very rare in

urban areas.

Frequency

variations

Distorted

Phase Angle (Active/Reactive

power)

Voltage

characteris-

tics

Asymmetry

Harmonics Transients

Flicker Voltage

variations

Power

Quality

Outage

37

It is harder to estimate the cost of short outages, but these are on the other hand

easier to visualize. The time loss of equipment not functioning when needed (stove,

washing machine etc) and the scenario of work lost on the computer. Most often a

blackout is not depending on bad feeding from the grid but from safety tripping within

the house or property.

7.1.1 Outages in Stockholm Royal Seaport

The introduction of new electrical components poses a somewhat enlarged risk for

outages due to the lack of experience. However, ABB who provides the control system

for the smart grid has expressed the reliability of the grid to be a priority. It is therefore

the authors’ opinion that there will not be an enlarged risk of outages within the test

area Stockholm Royal Seaport.

7.2 Frequency variations

The frequency in the Swedish grid is set to 50Hz. This means that all synchronous

machinery electrically connected to the grid operates at this frequency. A variation in

this frequency is the grids natural response to a change in production or consumption

in the over all national balance of power. If a big production unit, e.g. a major hydro

power plant or a nuclear reactor, the frequency will drop a little. If on the other hand a

big power consumer falls off the grid the frequency is slightly increased. This is

managed on a national level by Svenska Kraftnät who are put in charge of balancing

production and consumption at all times.

Many direct connected motors and generators give the grid a certain mechanical

inertia. A way to visualize this is to imagine a big rotating motor rotating at a speed

corresponding to 50Hz. If there is a sudden lapse in production, the rotating mass of

the motor will in accordance to all physical theory want to keep spinning at the same

speed and will therefore make the sudden change more smooth.

Deviations in frequency affect clocks that use the electrical frequency of the grid to

know what time it is. Such clocks are common. Robotics with direct driven motors

would also go out of sync if fed with bad frequency.

In weak parts of the grid frequency variations are uncommon but possible. When

approaching islanding operational mode frequency deviations are more likely. If

absolutely zero power is exchanged in a node connecting a self sustaining grid part

and the overlaying grid it is theoretically possible for that part to have a frequency of

its own.

38

7.2.1 Frequency deviations in Stockholm Royal Seaport

Although island state could be considered due to the local production in SRS, the

generation is of such low magnitude that no problems are expected. Studies have

shown that a ratio of 70% local production nominal power of the feeding transformers

power is quite manageable by the grid. Also, as mentioned above, the local power

produced would be manufactured on site with near perfect properties.

7.3 Phase angle

The concept of a phase angle is a mathematical way to deal with a slight time lag

between voltage and current. The word “phase” in this section does not correspond to

a “phase” used in the below description of three “phase” systems but simply represents

the previously mentioned time lag, voltage and current are “out of phase”. Phase angle

directly correspond to the concept of active and reactive power in the way that cosine

of the phase angle equals the fraction of the apparent power that is active. Analogy,

sine of the phase angle gives the fraction of reactive power.

Reactive power is something useful for some applications, especially induction

motors require some reactive power to magnetize their rotor. When transporting

electricity, reactive power leads to losses and is therefore something that one wants to

avoid. Reactive power is dealt with by capacitor banks installed at key points in the

grid. Industrial power users sometimes create reactive power of which they are

charged with a fee by the distributing company. Many large power consumers there-

fore have their own phase compensation.

7.3.1 Phase angle in Stockholm Royal Seaport

Given the characteristics of the solar cell invertors, who creates power with a power

factor of 1 (no reactive power), it is considered unlikely that Stockholm Royal Seaport

will have a larger risk of reactive power problems than any regular part of the grid.

There is also not to the authors knowledge any electrical device with a particular large

inductive part considered to be introduced.

7.4 Transient over voltages

Voltage transients are in many ways interconnected with voltage variations. The

definition of a voltage transient according to EN 50160 is a “brief oscillating or non-

oscillating over voltage, usually heavily dampened with a duration of a few millisec-

39

onds or less”[V]. Transients are caused by lightning or switching operations, for

example when a high inductive current is switched off [VIII]. The standard does in this

case express itself a bit unclear. It states “transient over voltages does normally not

exceed 6kV peak value, but can occasionally reach higher levels”. It does not actually

give a recommendation that transient voltages should not exceed this value, or any

other.

While 6kV seems like an extremely high voltage level compared to the nominal

voltage of 230V its effects are not as dire as expected from such a deviance. Given the

time span of maximum 5 milliseconds and down to microsecond level they do not

carry much energy[V]. A period is 20 milliseconds in a 50Hz AC power system.

These high frequency and low energy transients constitute the kind of transients that

presents lesser danger. Transients of low frequency and higher energy present more of

a problem. They can slip though protections because of their lesser height of the spike.

This is in reality an energy pulse carried by the grid. Voltage transients are in many

ways connected to current transients; see section below under “voltage variations”.

Voltage transients are dangerous in equipment connected to two or more electrical

signalling networks. Phones, faxes, computers and TV’s are all connected to the power

grid but also to either data network, tele network or TV network. If one of these

networks are carrying a transient into a device there will be a potential difference

within the device between the two signalling networks and a flashover, a discharge,

will probably occur which is harmful to the device [XIII].

7.4.1 Transients in Stockholm Royal Seaport

To control the smart grid in Stockholm Royal Seaport a signalling system called

SCADA (Supervisory Control And Data Acquisition) is planned to be installed. It is

not yet decided whether this will be a physical network or information will be sent via

the wireless GSM network. A physical network parallel to the power grid will pose an

increased risk of transient damages to the SCADA system. This risk increase is

however considered marginal by the author. For one, there traditionally are very few

transient problems in urban areas especially in urban areas newly constructed. The

high short circuit power of the grid also works to an advantage to decrease voltage

transients. Current transients may however pose a problem, see section “voltage

variations” below. A second reason is the previous experience from SCADA systems.

7.5 Harmonics

Harmonics have historically been considered a lesser problem in Sweden than in the

rest of Europe. This is because Sweden has been a heavy power consumer per capita

with electric heating. Electric heating is electrically a very nice linear load and a

system built up of many of those helps to smooth out and reduce harmonics. As we

40

move forward into the future with more environmental awareness and a changing

energy system striving for more efficient power use we gradually try to eliminate this

use of electricity, and hence approach the continental situation[I].

Harmonics are voltage or current components of a multiple of the grid base fre-

quency 50Hz. They are created almost exclusively at the consumer. With no regulating

equipment they travel upwards and spread in the grid. Harmonics are created by non

linear loads that draw a current of another plotted shape than the one of the voltage.

Depending on the strength of the grid, the impedance, the non linear current affects the

voltage and distorts the sine shape of the voltage too.

Harmonics are harmful to equipment and causes heat losses. They also have an

unwanted effect to occasionally create resonances between inductive and capacitive

parts in the grid which leads to non useful power transportation which means unneces-

sary losses. The 3:rd over tone is especially harmful since it adds itself up in the PEN-

conductor which can then lead to vagabond currents. Another aspect which is hard to

estimate economically is pulsating torque effect that occurs in motors fed with power

tainted by overtones. Equipment using clocks that are based on the grids 50Hz fre-

quency can also experience problems from harmonics with amplitude big enough to

create false intermediate crossing of zero potential. Harmonics are generally dealt with

by filters. This erases or restrains the harmonics by dissipating it as heat, which are

obviously losses.

7.5.1 Harmonics in Stockholm Royal Seaport

It is estimated that 70% of all global electrical power pass through rectifiers[I]. All

rectifiers are non linear loads. Rectifiers using PWM-switching are becoming more

common and use a very high switching frequency. Generally a higher switching

frequency creates less harmonics but there is a risk for the high order switching to

interact with other equipment of the same type. Resonance between two or more

components can in its own create harmonics. Different switching apparatuses can also

counteract each other. The author would suggest some thought would be given to this

matter in selection of apparatuses.

7.6 Voltage variations

Voltage variations are, together with frequency variations, the grids natural reaction

to a change in load or production. Voltage increases are called “swells” and decreases

are called “dips. As stated in the section “Power Quality” we are approaching an

environment with less grid inertia as the fraction of electronic loads compared to

electric machinery is increased.

41

7.6.1 Swells

Swells are in general dangerous to equipment[IV]. A device constructed for 230V

will in most cases function normally on 240V but is not healthy in over long stretches

of time.

In high voltage parts of the grid some protections against over voltage is installed. It

is simply put a device between two conductors that short circuit them[I]. This device,

called over voltage protector, starts conducting at a certain threshold value but is an

isolator at nominal voltage. In low voltage parts of the grid there are no such protec-

tions since the cost does not motivate the benefit [IV].

Swells are related to transients. The difference is one of definition, a transient is

very short whereas a swell endures several seconds or is permanent. Swells are

uncommon.

7.6.2 Dips

Dips are however more common. On a national average there occur about 20 dips

every year in Sweden[IV]. Dips are indeed the sign that the protection systems within

the grid are functioning properly. Dips are caused by switching operations in the grid,

operations mostly caused by faults such as short circuits or PEN-faults. This can be

because of thunder, trees or man-made breaks on cables and the following disconnects

and circumventions of the fault.

A report by Elforsk suggests that dips are especially dangerous to electronic equip-

ment[IV]. A, at the time of its publishing, still not practically proven theory is intro-

duced that suggests dips as the indirect reason of several malfunctions on electronical

devices.

7.6.3 Current transients

Large over currents on a large scale are limited in the grid. This is because protec-

tions are installed to cut faulty parts or components of the grid if they draw an unnatu-

rally large current. Since the voltage pretty much keeps steady it is the current drawn

that determines the power delivered/used. Therefore safety breakers are installed

mainly in the substation but also in different nodes in the grid and this eliminates the

danger of excessively large transient currents.

It does not however cover small fluctuations and current surges. For this we obvi-

ously have a personal safety legislation that guides how to safeguard a home with

domestic breakers. But they still might allow a current transient high enough to

damage electrical equipment.

Elforsk did in 2006 write a report investigating the sensitivity of electrical equip-

ment with the main focus on equipment connected to two different signal networks,

e.g. power grid and tele grid. The investigation shows that current transients can occur

very locally and damage or destroy electrical equipment which is not sufficiently

42

protected . An identified weakness is that the conventional rectifier contains a protec-

tion for cold starts, but not for sudden current rushes following a voltage dip in the

grid. When a local or more spread out voltage dip occurs in the grid due to a start-up

of a significant additional load or similar, the grid quickly strives to balance it and

return to nominal voltage. During the dip, capacitors in the conventional rectifier have

emptied out its energy and now receive a sudden current rush which damages the

equipment.

Generally, equipment is protected against cold starts to limit inrush currents. These

protectors are however set out of play in the case of temporary dips[IV].

7.6.4 Voltage variations in Stockholm Royal Seaport

Dips are less common in urban areas than in rural areas, mean value of 0.8 per

month compared to 3.5. The phenomenon in its own however becomes more danger-

ous because of the high short circuit power in urban grids. A high short circuit power,

low grid impedance, makes current rushes larger and more instant. Since dips are

mainly caused by switching operations in the grid and a smart grid such as the one

considered for Stockholm Royal Seaport will probably have more switching opera-

tions per given time unit than an ordinary grid this phenomenon might have to be

given some consideration. There is technical protection equipment that can be installed

to circumvent this. The author does not however believe that there will in practical

reality be a real problem with voltage fluctuations. A part of this is that the battery

buffer will help keep the grid stable at end customer.

7.7 Flicker

Flicker is a very visual type of power quality problem. It originates from fast volt-

age fluctuations and makes a visual impact in light bulbs. The definition of “flicker” is

not electrical, but constitutes of a subjective perception of the human eye. It is still

measured by a device and has two types of values; Pst and Plt (short- respectively

long- term severity). Flicker is typically created by electrical emmittance from facto-

ries using arc cutting elctrodes in the high voltage region. In low voltage grids emit-

tance sources can be welding machines, elevators, heat pumps etc. The grid impedance

is a big factor here.

Flicker is mostly unpleasant to the human eye/brain but does not constitute much of

a danger to equipment. In fact, the voltage fluctuations causing the flicker is usually

very much within the margins of what is considered good voltage levels. It is treated

as a power quality issue of its own due to its resonance with what the human eye is

43

sensitive to. It is easily reduced by the use of low energy light bulbs instead of regular

light bulbs[XVI].

7.7.1 Flicker in Stockholm Royal Seaport

Flicker is a phenomenon generally occurring in weak grids. The grid planned for

Stockholm Royal Seaport will be designed to be strong and somewhat over dimen-

sioned to meet possible future demands. It is therefore the authors opinion that flicker

levels will not be a problem in Stockholm Royal Seaport.

7.8 Asymmetry

In the three phase system we have today we say that the system is balanced when

the phases are equal in magnitude, sine-shape and lags exactly 120 degrees (or 1/3

period) after each other. An unbalanced system is called asymmetrical. Virtually all

tools of calculation used by electrical engineer today are based on a balanced system.

Calculations on asymmetrical systems quickly become very complex and very soon

become incomprehencible. As a tool of to be able to calculate related problems, a

system of symmetrical components is introduced. It is an estimate of an unbalanced

system that consists of a zero, positive and negative sequence components . Unbalance

is measured as the ratio between positive and negative sequence components ex-

pressed in percentage.

An unbalance larger than 1% is uncommon. EN 50160 allows 2% for 95% of a

weeks measurement but leaves room for an occasional 3% at certain points[V].

Unbalance in the high voltage transmission grid is caused by unsymmetrical loads

which mean that the conductors for the three phases for some reason have slightly

different impedance. Unbalance is more common in the low voltage grid where local

values of 2% may occur[XVI]. The unbalance here is mostly due to non evenly

distributed one phase loads.

Unbalanced power affects three phase motors and transformers and leads to excess

heat losses. This is because two different magnetic fields create resisting torques, one

rotating and one stationary. This causes induction heating of the motor and makes the

motor run on a lower efficiency than normal with excessive heat development as a side

effect. A result of this is a shorter life of the motor as well as more expensive opera-

tion . Frequency rectifiers are more sensitive. Frequency rectifiers are used to drive

motors of a different frequency than the nominal 50Hz and are mostly used in indus-

tries. Even at an unbalance of 1.5% the equipment may trip because it at that point

44

Fig 16. Evaluated view of different Power Quality phenomena

only draws power from the two strong phases which makes breakers react to an

abnormal current consumption[XVI].

7.8.1 Asymmetry in Stockholm Royal Seaport

Even though we are moving in a direction of traditional three phase loads becoming

one phase loads it is not suspected that there will be a higher unbalance in Stockholm

Royal Seaport compared to traditional domestic areas. This is also based on the

assumption that the solar power installed will generate three phase power which seems

to be a reasonable assumption.

7.9 Summary

Areas marked yellow symbolize areas that may require extra attention in the realiza-

tion of Stockholm Royal Seaport due to reasons stated above. Green areas are areas

that in the authors opinion does not require special attendance for this particular

project compared to ordinary new constructions.

This is all evaluated from the end customer’s point of view, at the very end of the

vast national electric distribution grid.

Frequency

variations

Distorted

Phase Angle (Active/Reactive

power)

Voltage

characteris-

tics

Asymmetry

Harmonics Transients

Flicker Voltage

variations

Power

Quality

Outage

45

46

8 Conclusions

It is the authors over all opinion that solar electricity production will not deterio-

rate the customers’ experience of their electricity supply. This standpoint is further

backed up by investigations carried out at some European locations which have

had electricity production from solar power for several years [XVII].

The reasoning behind the introduction of solar power can in many ways be ap-

plied to any power source using modern rectifiers. Since Stockholm Royal Seaport

is planning on implementing energy storage in the form of Lithium batteries, many

parallels can be drawn. The conclusion here is also that there will be no deteriora-

tion of power quality for the end user.

The author also believes that the energy storage will have a buffering effect that

can help stabilizing fluctuations of different kind in the power flow. This will

however probably not be noticeable within the research area of Stockholm Royal

Seaport because of the robust grid planned for the area.

There are however some details that can be worth some attention moving in on

the realization of the project. These are mentioned in chapter “detailed descrip-

tions” and boil down to:

- Monitor smart grid switching operations to not create unnecessary voltage

dips resulting in inrush currents

- Choose inverter equipment with some attention in order to avoid equipment

interaction

- Protect SCADA-system (Supervisory Control And Data Acquisition), the

smart grid command and communication system, the same way as the power

grid against thunder and faults. This in order to avoid transients carried by

SCADA system.

Of the above mentioned bulletins, the last is a bit of a question mark. The author

deems there not to be a significant risk of material damage due to transients car-

ried by an alternative network, this because of the improbability of such an event.

The cost of the protections should be weighed against the risk of an event occur-

ring and its potential costs.

47

List of references [I] Clinton Climate Initiative Summer newsletter 2010

[II] Presentation Stockholm Royal Seaport, May 2010

[III] Elforsk 06:81; Elöverföring av god kvalitet

[IV] Elforsk 06:08; Skadade apparater

[V] EN 50160: Voltage characteristics of electricity supplied by public distri-

bution systems

[VI] Ellagen 3 kap. 9§ second piece

[VII] Förstudie leveranskvalitet delrapport 3 – Energimarknadsinspektionen

[VIII] Voltage Disturbances, Henryk Markiewicz, Antoni Klajn, Wroclaw Uni-

versity of Technology

[IX] Nätanvisningar, Fortums mall över lågspänningsnätskonstruktion

[X] Fortums skadeståndsavdelnings ärendekatalog

[XI] Svensk standard SS EN 61 000elektromagnetic compatatibility (EMC)

part 3-2: Limits – Limits for harmonic current emissions (equipment in-

put current up to and inclucing 16A per phase) – See section PQ

[XII] Elforsk 08:48; Elektronisk last – Skadade apparater

[XIII] Åkerlund John, avbrottsfria kraftnät UPN AB, beskrivning av immunitets-

läget mot transienter och överspänningar i elanvändares elektriska appara-

ter, system och anläggningar”, Gpr Eölvaöotet redovisning av regerings-

uppdrag 2003-10-27”, Statens Energimyndighet, oktober 2003

[XIV] Lecture notes by Uwe Zimmermann, Uppsala Universitet 2010

[XV] Fortum´s ”Villkor för avbrottsersättning” March 2010

[XVI] EMC, elkvalitet och elmiljö – guide för elanvändare och allmänt sakkun-

niga inom elområdet. Elforsk, Energimyndigheten, Elsäkerhetsverket,

Teknikföretagen 2007

[XVII] PV upscale – Impact of photovoltaic generation on power quality in urban

areas with high PV population; Sjef Cobben (Continuon), Bruno Gaiddon

(Hespul), Hermann Laukamp (Fraunhofer ISE)

48

49

Acknowledgements

I would like to thank Fortum Distribution AB, especially the local network plan-

ning unit, for your contributions of knowledge, guidance, financial help and your

company.

I would like to thank my two supervisors Jan-Olof Olsson at Fortum and Johan

Lundin at the department of electricity for sharing their time and expertise that

lead to the making of this thesis.

I would also like to thank prof. Mats Leijon for his quality control of this thesis

as well as inspiration during my years at the university.

A word of recognition also goes to Gustaf Nissen who helped out many a time

with clever input and moral support.

A special thanks is also directed towards Marcus Krell for his final review of

the thesis. Plus for keeping me alive for half a year at sea.

On a personal note I would also like to thank Jane Summerton and Ove

Långström for lifelong tutorship that directed me to this point in my life.

Stockholm – December 2010

mårten einarsson