26
1 PROJECT: CHAD-CAMEROON 225 KV ELECTRICAL GRID INTERCONNECTION PROJECT COUNTRY: MULTINATIONAL: CHAD-CAMEROON FULL RESETTLEMENT PLAN (FRP) SUMMARY July 2017 Appraisal Team Team Leader Jean-Pierre MUTSINZI Principal Energy Operations Officer RDGC.1 2300 Team Members N. Thioye DIALLO Regional Financial Management Coordinator SNFI2/RDGC 6833 Pierre Hassan SANON Principal Social Development Specialist SNSC 5828 Salim BAIOD Consulting Environmentalist SNSC 5813 C. L. DJEUFO Procurement Officer SNFI1/COCM 6809 D. TILENGUAR Procurement Officer SNFI1/COTD 6207 Division Manager Ibrahima KONATE, OIC RDGC.1 3418 Sector Director Regional Director Ousmane DORE RDGC 4902 AFRICAN DEVELOPMENT BANK GROUP

FULL RESETTLEMENT PLAN (FRP) SUMMARY - … · B.11 Support to the operation of the CEP ... which had a population of about 775 000 in 2009 ... surface area of 54 square metres,

Embed Size (px)

Citation preview

1

PROJECT: CHAD-CAMEROON 225 KV ELECTRICAL GRID INTERCONNECTION

PROJECT

COUNTRY: MULTINATIONAL: CHAD-CAMEROON

FULL RESETTLEMENT PLAN (FRP) SUMMARY

July 2017

Appraisal

Team

Team Leader Jean-Pierre

MUTSINZI

Principal Energy

Operations Officer

RDGC.1 2300

Team Members

N. Thioye DIALLO Regional Financial

Management

Coordinator

SNFI2/RDGC 6833

Pierre Hassan

SANON

Principal Social

Development Specialist

SNSC 5828

Salim BAIOD Consulting

Environmentalist

SNSC 5813

C. L. DJEUFO Procurement Officer SNFI1/COCM 6809

D. TILENGUAR Procurement Officer SNFI1/COTD 6207

Division Manager Ibrahima KONATE, OIC RDGC.1 3418

Sector Director

Regional Director Ousmane DORE RDGC 4902

AFRICAN DEVELOPMENT BANK GROUP

2

FULL RESETTLEMENT PLAN (FRP) SUMMARY

Project Name : Chad-Cameroon 225 KV Electrical Grid Interconnection Project

Project No. : P-Z1-FA0-072

Country : Multinational: Chad-Cameroon

Department : RDGC Division: RDGC.1

INTRODUCTION

At the request of the Governments of Chad and Cameroon, the African Development Bank will support

the implementation of the Chad-Cameroon 225 kV Electrical Grid Interconnection Project.

Environmentally and socially, the project has been classified under Environmental Category 1, given its

scope and the main environmental and social impacts identified.

The execution of works on the transmission line, substations and access roads will cause the

displacement of households, disruption of socio-economic activities and harm to the means of livelihood

of people living in the existing infrastructure right-of-way and its easements.

Consequently, in accordance with the African Development Bank’s involuntary displacement policy

(Operational Safeguard 2 – OS 2), the Governments of Chad and Cameroon have respectively submitted

to the Bank a Full Resettlement Plan (FRP) for compensating and resettling project-affected persons

(PAPs). The objectives of the FRP are to: (i) reduce involuntary displacements to the minimum; (ii)

avoid the destruction of property as much as possible; and (iii) compensate affected persons for the loss

of housing plots, farmland, buildings and equipment, as well as income.

The FRP which is the subject of this summary lays down the principles and conditions for compensating

and resettling project-affected persons, and establishes an approximate budget and its indicative

implementation schedule.

1. DESCRIPTION AND RATIONALE OF THE PROJECT AND ITS IMPACT AREA

1.1 Project Description and Rationale

- Project Rationale

The Chad-Cameroon 225 kV Electrical Grid Interconnection Project underscores the determination of

both countries to optimize the use of their energy resources by integrating their electric power

generation, transmission and distribution infrastructure. It is also in line with the overall framework for

the interconnection of the electrical grids of member countries of the Economic Community of Central

African States (ECCAS).

- Project Description

The Chad-Cameroon 225 kV Electrical Grid Interconnection Project is among the priority projects of

the Central Africa Power Pool (CAPP). It mainly concerns the: (i) construction of a 225 kV high-voltage

(HV) line to transmit electric power between Cameroon and Chad, over a distance of 1 024 kilometres,

of which 786 kilometres in Cameroon and 238 kilometres in Chad. It passes through 7 high-voltage

(HV) transformer substations located in Ngaoundere (Adamouawa Region), Lagdo (North Region) and

Maroua (Far-North Region) in Cameroon, and Bongor, Guelendeng (Mayo-Kebbi Est), Kousseri (Far-

North) and Gassi (N’Djamena) in Chad; (ii) construction of rural electrification infrastructure in 478

villages located along these high-voltage transmission lines and on a 25km-long corridor on both sides

of the high-voltage transmission line, 409 in Cameroon and 69 in Chad. Electricity is supplied to these

localities through 15 kV to 30 kV medium-voltage transmission lines connected to 225 kV substations

and a low-voltage network.

- Project Objectives

The project’s specific objective is to contribute to attaining electric power supply and demand

equilibrium in Cameroon and in Chad, and enable the project area population to have access to electricity

within a sub-regional framework.

3

- Project Components

The project comprises the following components:

Components Description

Electricity

Infrastructure

Construction

(i) Construction of a 1 024 km-long 225 kV high-voltage (HV) transmission line, including 786

kilometres in Cameroon and 238 kilometres in Chad; (ii) Construction of 7 high-voltage transformer

substations in Ngaoundere (Adamaoua Region), Lagdo (North Region) and Maroua (Far-North

Region) in Cameroon, and Bongor, Guelendeng (Mayo-Kebbi Est), Kousseri (Far-North) and Gassi

(N’Djamena) in Chad; (iii) Construction of rural electrification infrastructure (15 kV to 30 kV

medium-voltage transmission lines connected to 225 kV substations and a low-voltage network)

in 478 villages, 409 of them in Cameroon and 69 in Chad.

Project

Management

B.1 Technical and financial audit of the project

B.2 Environmental and social audit

B.3 Procedures Manual

B.4 Acquisition and installation of management software (accounting, project management) &

Training

B.5 Monitoring project activities

- Monitoring and control of studies, manufacturing and infrastructure construction (Consulting Ing.)

- Implementation of the ESMP (HT lines)

- Implementation of the PAR (HT lines)

- Implementation of the ESMP (Rural Electrification)

- Logistical support to National Institutions

B.7 Insertion of young graduates

B.8 Institutional support CHAD (in particular MPE and SNE)

B.9 Institutional support CAMEROON (including MINEE, ARSEL, SONATREL and AER)

B.10 Youth and Women Empowerment Program

B.11 Support to the operation of the CEP

- Project Cost and Financing

The overall project cost is estimated at UA 333.29 million.

The project will be financed by: (i) the African Development Bank Group (AfDB) to the tune of UA

215.88 million (ADF Loan and Grant); (ii) other donors, including the Islamic Development Bank (IsDB

– UA 87 million) and the European Commission (EU- AFIF – UA 24 million); and (iii) the

Governments of Chad and Cameroon.

1.2 Project Impact Area

1.2.1 In Chad

The project impact area comprises 9 cantons in 4 divisions and 3 regions, namely: (i) Mayo-Kebbi Est,

which had a population of about 775 000 in 2009 (representing 7% of the total population of Chad), and

a population density of 42 inh./km2; (ii) Chari-Baguirmi, which had about 580 000 inhabitants in 2009

(that is 5 % of the country’s total population), and a population density of 12 inh./km2; (iii) N’Djamena,

which had a population of close to 1 million in 2009 (or 9 % of Chad’s population), and a population

density of 1 903 inh./km2. The transmission line passes through 75 villages.

1.2.2 In Cameroon

The project impact area covers 30 municipal councils in 8 divisions and 3 regions, namely: (i) the

Adamaoua Region, which had a population of more than 1 million in 2010 (or 5 % of the total population

of Cameroon), with a population density of 16 inh./km2; (ii) the North Region, which had more than 2

million people in 2010 (representing 11 % of the country’s total population), with a population density

of 31 inh./km2; (iii) the Far-North Region, which had close to 3.5 million inhabitants in 2010 (that is 18

% of Cameroon’s population), with a population density of 102 inh./km2. The line passes through about

140 villages.

4

1.3 Project Beneficiaries

The transmission infrastructure will benefit the national electricity corporations of Chad (SNE) and

Cameroon (EDC) which will operate it.

The project will benefit 478 villages, 409 of them in Cameroon and 69 in Chad, as well as the inhabitants

of these villages who will have access to electricity, thus improving their living conditions. The project

will connect 350000 households.

About 350 temporary jobs will be created of which at least 15% will be occupied by women / girls.

About 250 direct and indirect permanent jobs will be created of which at least 15% will be occupied by

women / girls. In terms of socio-professional integration, at least 150 young graduates with at least 50%

of girls (50 in Chad and 100 in Cameroon) will be able to perform pre-employment internships to

promote their employability.

Regionally, the project will enable the industries and enterprises of the respective countries to develop

and increase their production and commercial activities.

Central Africa’s regional and economic integration will be enhanced.

2. POTENTIAL IMPACTS

Given that the potential impacts on the human and natural environments have been exhaustively dealt

with in the Environmental and Social Impact Assessment (ESIA), this paragraph will focus on the human

environmental impacts in terms of expropriation and the economic harm resulting from the freeing of

5

the route right-of-way and the execution of works by reducing to the maximum the nuisances that they

may cause.

It should be noted that the scope and location of works have been limited to minimize the harm that

could be caused to the population having property in the project right-of-way.

2.1. Impact Sources

The area of project works (for the high-voltage transmission line) covers the 30 metre-wide corridor on

both sides of the high-voltage line that is a 60 metre-wide corridor.

In Chad, the project right-of-way comprises 1 439 ha of transmission line corridor, 4.4 ha of pylons and

11.4 ha of substations. In Cameroon, the project right-of-way comprises 4 702 ha of transmission line

corridor, 13.6 ha of pylons and 17.4 ha of substations. Most of this surface area is found in a farming

and herbaceous or shrubby savannah zone.

Many activities during the construction phase could have impacts. These activities are: trench clearing;

opening and developing access roads and the high-voltage transmission line, opening forest paths;

transporting and handling equipment, installing construction site offices and storage areas, and planting

pylons.

Positive Social Impacts

Project positive impacts during the preparation, construction and operation phases will be:

Rural electrificationwill have several benefits for the population, notably the improvement of living

conditions, temporary job opportunities for the local population during works, consolidation and

increased development of economic activities and social services, etc.

The integration of power generation, transmission and distribution infrastructure of Cameroon and Chad

will help both countries to optimize the use of their national energy resources.

The project will help to maintain electric power supply and demand equilibrium in both countries, and

to substantially reduce annual generation costs. For Chad, such reduction would be essentially the result

of replacing costly thermal power with less costly hydroelectric power. The project will also generate

considerable socio-economic benefits for both countries, thus contributing to the improvement in the

living conditions of the people.

The project will enable the urban and rural populations of the areas concerned to have access to

electricity at reduced cost. It will boost craft works and promote the creation of small-size enterprises.

It will support women’s activities, create better conditions for promoting education and health, and

slowing down rural/urban migration. The project will therefore contribute to poverty reduction.

The project has a regional scope. It will contribute to developing cooperation and constitute a

springboard for sub-regional integration, thereby proving the complementary nature of Central Africa’s

societies and economies.

Negative Social Impacts

The project’s negative impacts on the human environment will be:

In Chad, the project will affect 990 people. About 926 private buildings, each covering an average

surface area of 54 square metres, will be affected. They are mostly homes, but also other facilities such

as mounted water tanks, as well as 14 557 trees, mainly those of mango, guava, lemon and acacia. The

census also identified 37 community assets (especially wells and boreholes) and 67 graves.

In Cameroon, the project will affect 1 311 people outside the Maroua-Kousseri road section (mainly in

the North Region) and 330 households along the Maroua-Kousseri section. Some 2 409 private

buildings, each covering an average surface area of 10 square metres, will be affected outside the

Maroua-Kousseri section. They are mostly homes, but also other facilities such as mounted water tanks.

Ten houses will be affected in the Maroua-Kousseri section. The number of private trees that will be

affected outside and within the Maroua-Kousseri section stands at 13 733 and 1 110 respectively. They

6

are mainly neem, acacia, eucalyptus and mango trees. The census also identified 135 community assets

comprising trees, wells and some buildings such as churches and schools, and 96 graves.

The less significant impacts will be the destruction of crops or plantations along the works passage and

in the traditional gold washing area.

The landscape of the very high-voltage transmission line and around the substations will be degraded.

During the operation phase, the transmission lines will require surveillance and periodic maintenance,

and this may: (i) contaminate the environment because of the use of weed killers, or burning woody

debris from periodic clearing, (ii) disrupt wildlife habitats due to many access roads.

3. ORGANIZATIONAL RESPONSIBILITY

The organizational framework proposed for FRP implementation comprises the following:

3.1 In Chad

The Project Management Unit (PMU) which has a project management expert will be responsible for

implementing the FRP. MATDHU and DEELPN will steer procedures for assessing and paying

compensation for land and other facilities found within the project right-of-way. State services and local

communities will be systematically involved in accordance with their prerogatives.

Entity Function Responsibilities

Government of Chad

Project Ownership Mobilization of funds required for compensation

Signature and approval of compensation financing

documents

MATDHU Ministry Signature of public interest statements (DUPs) and

demarcation of project right-of-way

Preparation of expropriation and compensation

instruments

Project Implementation Unit

Engineering Firm

Project Supervision Preparation of works start-up schedule

Supervision of RAP implementation

African Development Bank International Donor/

Support

Validation of RAPs

Disclosure of RAP summaries

Ensuring compliance with the requirements of

Operational Safeguard 2

Monitoring and evaluation of RAP implementation

DEELPN Administration Assessment of losses and related compensation

Identification of PAPs

Signature of compensation agreements with PAPs

Chiefdoms Local Authorities PAP information and sensitization

Management of conflicts and litigations

Participation in the monitoring of RAP

implementation

Courts Administration Final settlement of conflicts

The project promoter, CAPP, will be responsible for supervision to ensure the smooth implementation

of FRP, in accordance with the commitments made with donors.

3.2 In Cameroon

Project resettlement activities will be carried out under the responsibility of the Ministry of State

Property, Survey and Land Tenure (MINDCAF) and Findings and Assessment Committees (FACs)

which steer land assessment and compensation procedures. This will be done with the full cooperation

of the PMU, notably through the socio-economist responsible for FRP implementation. State services

and local communities will be systematically involved according to their prerogatives.

7

Entity Function Responsibilities

Ministry of Energy Project Ownership Mobilization of funds required for

compensation

Signature and approval of compensation

financing documents

MINDCAF Ministry Signature of DUPs and demarcation of

project right-of-way

Preparation of expropriation and

compensation instruments

Project Implementation Unit

Engineering Firm

Project Supervision Preparation of works start-up schedule

Supervision of RAP implementation

African Development Bank International Donor/Support Validation of RAPs

Disclosure of RAP summaries

Ensuring compliance with the

requirements of Operational Safeguard 2

Monitoring and evaluation of RAP

implementation

Divisional Offices Local Administration Establishment of FACs and Sub-

committees

FAC Administration Assessment of losses and related

compensation

Identification of PAPs

Signature of compensation agreements

with PAPs

Chiefdoms Local Authorities PAP information and sensitization

Management of conflicts and litigations

Courts Administration Final settlement of conflicts

The project promoter, CAPP, will be responsible for supervision to ensure the smooth implementation

of FRP, in accordance with the commitments made to donors.

4. COMMUNITY PARTICIPATION

Consultation was conducted as part of the preparation of ESIAs and FRPs in Cameroon and in Chad, in

compliance with the domestic legislations and the requirements of AfDB’s operational safeguards 1 and

2. Consultations were conducted publicly (in the regions crossed by the project) and individually with

PAPs in particular.

Free and Transparent Consultation

The following groups and persons were consulted: all categories of persons who may be affected by the

project; elected representatives (mayors and their deputies); local and divisional authorities, especially

representatives of Divisional Officers (assistants), Sub-divisional Officers of the sub-divisions

concerned and the Divisional Delegates of Cameroon’s Ministry of Water Resources and Energy

(MINEE); traditional authorities (chiefs of the various villages concerned); the national authorities

concerned such as MINEE and the Ministry of Environment, Nature Protection and Sustainable

Development (MINEP).

8

The persons and groups consulted freely expressed their concerns and expectations, and asked questions

during public meetings held in the towns and villages concerned and household surveys. In household

surveys, time was provided at the end of the questionnaire for the respondent to express his/her

expectations and fears or ask questions in a more confidential manner than during public consultations.

Prior Consultation

Twenty-eight public meetings were organized in Cameroon in December 2016, and 11 in Chad in

November and December 2016, that is, prior to any project works or preparation or construction activity.

The minutes of the public meetings are presented in an annex to the FRP.

During consultations, the consultants presented the project, its negative and positive impacts and its

implementation schedule.

Consultation Results

The questions asked and comments made by participants during public or individual consultations with

PAPs reflected their expectations, concerns and perception of the project. The results are presented for

the entire project and by country. There was no open protest or opposition to the project. While many

PAPs expressed fears about compensation and resettlement terms and conditions, as well as the risks

posed by the electric transmission lines to health, the majority of the inhabitants of the regions concerned

welcomed the project.

The concerns expressed during public consultations are relatively similar from one region to another,

and from one country to another. They are:

- risks posed by electric lines to health (electrocution, magnetic fields, etc.) and safety

(fire outbreaks);

- risks posed by electric lines (electrocution) to domestic and wild animals;

- loss of land and resettlement difficulties: many people expressed the fear of being

resettled out of their village of origin;

- inappropriate compensation procedures and terms and conditions in relation to potential

losses (crops, houses, etc.).

The main fears expressed by PAPs consulted individually concerned compensation and resettlement

terms and conditions. Many expressed doubts about the effectiveness of the mechanisms to be

established (assessment of property and payment of compensation before displacement). Some referred

to other projects under which the procedures were not smooth (late payment of compensation, for

example). Affected persons nurse the feeling of injustice and the fear that these compensation flaws may

reoccur. The results of individual consultations are presented below.

Expectations of the project: just like concerns, the expectations expressed during public consultations

and by PAPs consulted individually are relatively similar. All of those consulted expect positive impacts

of rural electrification. The inhabitants of villages crossed by the 225 kV high-voltage transmission line

who will not benefit from rural electrification will certainly be very frustrated.

Significant improvement in living standards as a result of rural electrification with:

- access to consumer goods such fans, refrigerators, electric light, television, etc.;

- increased school enrolment as a result of rural electrification and hence a drop in

illiteracy level;

- improved health infrastructure and healthcare delivery capacity.

Economic development of the villages concerned and in particular, the development of income-

generating activities, especially commercial activities:

- transformation of production methods with the availability of electricity (mills, hulling

machines, welding, mechanics, sawmills, boiler shops, etc.);

- creation of direct construction site-related jobs (high youth expectations) and jobs

created as a result of new rural electrification-related opportunities;

9

- development of women’s economic activities, with new opportunities (sewing

workshops, etc.);

- better possibilities of preserving food and processing food products;

- improved safety conditions, especially thanks to street lighting;

- better access to information.

Public Participation and Consultation during Project Implementation

In Chad and in Cameroon, this participatory approach will be maintained and reinforced during project

implementation through a regional Stakeholder Engagement Plan (SEP). This will be implemented by

the PMU in close collaboration with project-impacted communities, local authorities and authorities of

decentralized and external institutions. It will help to establish a social peace and transparency drive. It

consists in: (i) operationalizing the complete system for recording and processing complaints and

grievances as well as a mechanism for managing grievances by providing all stakeholders or citizens

with the possibility of making comments, voicing their concerns and, hence, acceding to information

and, where necessary, lodging an appeal and seeking redress under the redress mechanism. Its proper

functioning, the rapid processing of complaints at various levels and the quality of information

disseminated will guarantee the integration of the project within the communities. Any dysfunction in

the processing of complaints may rapidly cause serious deterioration of inter-actor relations and stall

project implementation; (ii) formalizing working partnerships, agreements and conditions with

stakeholders according to the roles and limits of each and everyone; (iii) coordinating the activities of

the various stakeholders; (iv) ensuring information building, pooling and dissemination among all

stakeholders; and (v) supporting the actors in this process and, more generally, in monitoring.

AfDB will also post ESIA and RAP summaries on its FRP and ESMP website.

5. INTEGRATION IN HOST COMMUNITIES

AfDB’s principles of integration in host communities are not applicable because PAPs will not be

resettled on a site or in a village other than the one they occupied prior to displacement. PAPs expressed

concerns in this regardThey wish to remain in their villages of origin or residence. All necessary

measures will be taken to comply with this option and to identify appropriate solutions together with the

customary owners.

6. SOCIO-ECONOMIC STUDIES

6.1 Population Census Covering the Current Occupants of the Affected Area

6.1.1 In Chad

The number of project-affected persons stands at 990. Among these potential PAPs, 404 are affected

only because they own low-growing crops in the right-of-way. PAPs are equitably distributed between

the Chari-Baguirmi and Mayo-Kebbi Est regions, and, to a lesser extent, N’Djamena.

The types of property lost are:

Buildings: 926 buildings, each covering an average surface area of 54 square metres,

were identified along the corridor. In addition, 2 mounted water tanks, 3 wells and 23

boreholes were identified as individual property;

Fruit trees: the number of fruit trees identified along the corridor stands at 14 557. The

most common trees along the corridor are mango, guava, lemon and acacia trees;

Crops: food crop losses will result from land acquisition at the location of pylons,

substations and access roads. The most common food crops along the corridor are

sorghum, beans and millet;

Community infrastructure: the number of community assets identified stands at 37,

mostly wells and boreholes;

10

Graves: PAPs identified 67 graves along the corridor. They are distributed

geographically as follows: 4 graves in Chari-Baguirmi, 60 in Mayo-Kebbi Est and 3 in

N’djamena Region. All are earth graves.

6.1.2 In Cameroon

The number of project-affected persons is as follows: along the corridor, outside the Maroua-Kousseri

section: 1 311 PAPs, more than two-thirds of them living in the North Region; in the Maroua-Kousseri

section: 330 affected households were identified in 2010, all of them in the Far-North Region.

The types of property lost are:

Buildings: along the corridor, outside the Maroua-Kousseri section: 2 409 buildings,

each covering an average surface area of 10 square metres (they are mostly dwelling

houses, see Table 9 - ). In addition, 2 mounted water tanks, 15 wells and 23 boreholes

were also identified as individual property. In the Maroua-Kousseri section: 10 homes

were identified in 2010, in addition to 10 local wells;

Fruit trees: along the corridor, outside the Maroua-Kousseri section: 13 733 trees. In the

Maroua-Kousseri section: 1 110 trees with economic value were identified in 2010;

Crops: food crop losses will result from land acquired at the location of pylons (with

safety buffers), substations and roads;

Community infrastructure: along the corridor, outside the Maroua-Kousseri section:

135 community assets, mostly trees, wells, churches and schools. In the Maroua-

Kousseri section, the 2010 survey concluded that no community property was located

in the route right-of-way;

Graves: along the corridor, outside the Maroua-Kousseri section, the number of graves

identified by PAPs stands at a total of 96 for Cameroun and distributed as follows: 1 in

the Adamaoua Region, 43 in the North Region and 52 in the Far-North Region. There

are 6 plastered graves, 11 cemented graves and 79 earth graves. In the Maroua-Kousseri

section: no grave was identified along the corridor.

6.2 Socio-economic Features of PAPs

6.2.1 In Chad

Household composition: the affected households comprise an average of 5 to 6 persons, which

corresponds to the national average. Most of the men affected by the project are married to one wife: 1

out of 10 men is a bachelor, 5 have one wife and 4 have many wives. On average, one household has 3

children aged below 10 years (with quasi-equality between girls and boys). Five per cent of household

survey respondents are disabled.

Sex and age: the average age of household survey respondents is 42 years and 14 % are elderly persons.

Over 9 out of 10 persons are men.

Place and duration of residence: PAPs are equitably distributed between the Chari-Baguirmi (44 %)

and Mayo-Kebbi Est (48 %) Regions. Less than one out of ten persons lives in N’Djamena. Four out of

5 PAPs have been living in their locality for at least 10 years and only 1% of them had been settled for

less than one year.

Ethnic groups and religions: the most represented ethnic groups among PAPs are the Massas, Saras

(Ngambaye / Madjingaye / Mbaye), Arabs and Kanembous (Bournou/Boudouma). The main religions

practised by PAPs are Christianity, Islam and animism.

School enrolment and literacy education: close to half of the project-affected persons have never

being to school. There are great disparities between women and men in terms of access to education: 57

% of women have not being to school, against 41 % of men. Five out of 10 household survey respondents

11

cannot read or write. There are great disparities in the level of literacy between men and women: 76 %

of women are illiterate, against 47 % of men.

Professional activity: close to half of vocational training courses were organized in the areas of

teaching, bricklaying and iron-bending, health and machine operation. Community and rural

development activities, the military sector and mechanics came next. One-third of training courses

concerned other areas. Agriculture and livestock breeding are the two main economic activities of 65 %

of persons surveyed. In addition, there are other trades, mainly in the handicrafts, petty trade, services

and fishery sectors. Nine out of 10 households rear poultry, 6 rear goats, 5 sheep, 4 cattle and 3 horses.

Dog, donkey, pig, cat, camel and monkey breeding is common, with close to one-quarter of households

involved.

Monthly income of households: the average monthly income of a household, depending on the period,

ranges from CFAF 210 000 to CFAF 300 000. The average monthly income of affected households is

CFAF 250 000. Five out of 10 affected households earn less than CFAF 100 000 and 2 earn less than

CFAF 50 000 F CFA per month.

Source of lighting: more than 7 out of 10 persons use a flashlight as a means of lighting, thereby making

it the main source of lighting used by affected persons. Two out of 10 affected households use a

hurricane lamp for lighting, 1 uses a solar lamp and 1 a generator. The use of electric power is very rare.

Functional household appliances: one-third of affected households do not have any functional

household appliance (television set, radio set, refrigerator, blender, pressing iron and electric stove).

One-third of households own a household appliance, and one-third own at least two. The most common

appliance is the radio set (close to half of households own one), followed by the refrigerator, pressing

iron, television set and electric stove. Less than one out of ten households has a blender.

Type of fireplace used for cooking: most households (65 %) use one type of fireplace for cooking,

although one-third (32 %) use at least two or more. Three per cent of households do not use any type of

fireplace for cooking. Close to 7 out of 10 households use the traditional fireplace (three stones) for

cooking. Charcoal, kerosene and improved stoves are also used by a significant proportion of the

population. In contrast, gas and electric stoves are used by less than one out of 10 households.

Access to basic social infrastructure: four out of 5 households (81 %) cover at least 1 kilometre to

have access to health infrastructure: half of them (43 %) are located at a distance of between 1 kilometre

and 5 kilometres from this type of infrastructure and the other half (38 %) at over 5 kilometres. The vast

majority of households (95 %) cover less than 5 kilometres to have access to educational infrastructure:

half of them (48 %) are located less than 1 kilometre from this type of infrastructure and the other half

(47 %) at a distance of between 1 kilometre and 5 kilometres. Five per cent of households live more

than 5 kilometres away from an educational infrastructure. The majority of households (57 %) cover

between 1 kilometre and 5 kilometres to have access to a market. Nineteen per cent of households live

at a distance of less than 1 kilometre from this type of infrastructure, while 24 % are located more than

5 kilometres away.

6.2.2 In Cameroon

Household composition: project-affected households comprise 8 persons on average, with significant

regional disparities: 6 persons per household in the Adamaoua Region against 9 in the North and Far-

North Regions. The majority of project-affected men are married to one wife: 1 out of 10 men is a

bachelor, 6 have one wife and 3 have many wives. A household has an average of 3 children aged below

10 years (with a quasi-equality between girls and boys). One per cent of household survey respondents

are disabled.

Sex and age: the average age of household survey respondents is 44 years and 12 % are elderly persons.

Close to 9 out of 10 persons are men.

12

Place and duration of residence: more than two-thirds of project-affected persons live in the North

Region. One-quarter of PAPs live in the Far-North Region and less than one out of ten persons lives in

the Adamaoua Region. Two-thirds of PAPs have been living in their locality for at least 10 years and

only 2 % of them have been settled there for less than a year.

Ethnic groups and religions: the project covers regions with great ethnic diversity. The distribution of

the ethnic groups of project-affected persons is as follows: in the Adamaoua Region, the majority of

them belong to the Fulani/Foulbé (22 %), Mboum (16 %), Mafa (10 %) and Toupouri (9 %) ethnic

groups. In the North Region, the project-affected population is mainly made up of Guidars (19 %),

Toupouris (17 %), Mafas (11 %), Fulanis/Foulbés (8 %) and Guizigas (7 %). In the Far-North Region,

PAPs mainly belong to the Fulani/Foulbé (30 %), Massa/Mousoye (22 %), Guiziga (21 %) and Toupouri

(8 %) ethnic groups. The main religions practised by PAP are Christianity, Islam and animism.

School enrolment and literacy education: close to half of project-affected persons have never been to

school. There are great disparities between women and men in terms of access to education: 53 % of

women have not being to school, against 36 % of men. Six out of 10 household survey respondents

cannot read or write. There are great disparities in literacy education between women and men: 81 % of

women are illiterate, against 55 % of men.

Professional activity: only 4.6 % of persons surveyed declared having a diploma. The main training

areas are: building and construction (joiner, plumber, civil engineering technician, etc.), teaching

(teacher), security (gendarme, soldier, customs officer, etc.), agriculture (technician, engineer, rural

development worker, etc.), trade (butcher, cook, etc.) and health (nurse, first-aid worker, nursing

assistant, etc.). Agriculture and livestock breeding are the two main economic activities carried out by

79 % of persons surveyed. In addition, there are other trades, mainly in the handicrafts, petty trade and

services sectors. Sixty-five per cent of household survey respondents are engaged in stockbreeding.

They are mostly concentrated in the northern part of the route: only 23 % of persons surveyed in the

Adamaoua Region rear animals, while 63 % and 86 % rear animals in the North and Far-North Regions

respectively. Close to three-quarters of affected households rear poultry and half rear goats. Sheep and

cattle rearing is widespread, with more than two-thirds of households involved. There are also donkeys,

pigs and horses in the area, but to a lesser extent.

Monthly income of households: the average monthly income of a household, depending on the period,

ranges from CFAF 110 000 and CFAF 150 000. The average monthly income of affected households is

CFAF 130 000. Six out of 10 affected households earn less than CFAF 100 000 F and 3 earn less than

CFAF 50 000.

Source of lighting: more than 8 out of 10 persons use a flashlight as a means of lighting, thereby making

it the main source of lighting used by affected persons. Two out of 10 affected households use the

hurricane lamp for lighting, 1 uses the solar lamp and 1 electric power. The use of generators as a source

of lighting is very rare.

Functional household appliances: 7 out of 10 households do not have any functional household

appliance (television set, radio set, refrigerator, blender, pressing iron and electric stove). Only 1 out of

10 households has more than one appliance. The most common appliance is the radio set (one-quarter

of households have it), followed by television set. Refrigerators and pressing irons are scarce. Blenders

and electric stoves are non-existent.

Type of fireplace used for cooking: the vast majority of households (84 %) use one type of fireplace

for cooking, although a few (10 %) use two or more. Six per cent of households do not use any type of

fireplace for cooking. Close to 9 out of 10 households use the traditional fireplace (threes stones) for

cooking.

13

Access to basic social infrastructure: the majority of households (58 %) cover between 1 kilometre

and 5 kilometres to accede to a health infrastructure. Twenty-seven per cent of households are less than

1 kilometre away from this type of infrastructure, while 15% are more than 5 kilometres away. Eighty-

two per cent of households have access to a water point within a 1 kilometre radius and 17% cover

between 1 kilometre and 5 kilometres. Only 1% of households live more than 5 kilometres away from

a water point. The vast majority of households (96%) cover less than 5 kilometres to have access to

educational infrastructure: half of them (53 %) live less than 1 kilometre away from this type of

infrastructure and the other half (43 %) live at a distance of between 1 kilometre and 5 kilometres. Four

per cent of households live more than 5 kilometres away from an educational infrastructure. Close to

half of households (46 %) cover between 1 kilometre and 5 kilometres to accede to a market. Thirty per

cent of households live less than 1 kilometre away from a market, while 24 % are more than 5 kilometres

away.

6.3 Gender Issues

Financial compensation has often had a destabilizing effect on households and had even broken them

up. Women PAPs are pressured by their entourage to share or hand over all the money paid to them.

The wives of PAPs are often excluded from decisions regarding the use of the financial compensation

and may be isolated in impoverishment when their husbands would have spent all the money without

meeting the needs of the household, or abandoned them and the children without resources. Increase in

the number of separation and divorce cases is common in areas where financial compensation is paid.

The level of women’s education, which is often lower than that of men, their day-to-day household

chores (time consuming) and their low mobility are obstacles or impediments to participation in

consultations and to coping with the changes that the project may cause.

A series of measures should be put in place to prevent these negative social effects. They are information,

sensitization and social support. Women are eligible for these measures just like men.

6.4 Assistance to Vulnerable Persons

6.4.1 Identification of Vulnerable Persons

Vulnerability of PAPs means the level of exposure to the negative impacts of displacement,

compensation and resettlement. Vulnerable persons can be more seriously affected than other PAPs and

may not have the resources required to face project-induced situation changes (physical displacement,

with loss of housing and/or economic loss, loss of means of livelihood such as access to a cultivated

farm). It is difficult to establish categories of vulnerable groups because vulnerability relates more to

individual situations. However, many potential (and frequent) sources of vulnerability were identified

during socio-economic surveys, namely:

illiteracy or low level of education which, in a situation of isolation, restricts access to

information and the capacity to enforce one’s rights;

gender-related vulnerability can be particularly high in situations of project impact-

related physical and/or economic displacement. Owing to their social status and

traditional roles within households, women are exposed to the risk of impoverishment

or deterioration of their living conditions. In addition, they often have limited access to

information and decision-making mechanisms, which does not allow them to enforce

their rights as project-affected persons;

migrant populations (for example, households recently settled on fertile lands for

farming) are also potentially more exposed to project negative impacts. Their status and

ownership rights to the land they occupy are fragile and can be questioned by the

“indigenous” inhabitants during compensation procedures;

displaced persons such as those who have fled from their land due to the presence of

Boko Haram in the far-north region may meet the vulnerability criteria laid down in

this RAP. In the lamidat of Rey Bouba for example, many of them face difficulties in

14

paying the taxes imposed by the Lamido in order to keep the land allocated to them.

The inhabitants of Tokombéré 11 are another example. Persons whose property in the

Bénoué flood-prone area that was expropriated, were resettled in this village by the

Government. Any physical or economic displacement of these persons must be avoided

where possible. Where it is not possible, targeted measures will accompany the

compensation and resettlement process;

generally, persons using land with insecure tenure status are exposed to a major risk of

impoverishment if the necessary measures are not put in place during the compensation

and resettlement process. The project will also take the necessary measures to support

these persons;

vulnerability related to age or particular health problems may also be an aggravating

factor for project negative impacts on some members of the population.

6.4.2 Assistance to vulnerable households

Assistance to affected vulnerable households comprises the following measures:

• identification of vulnerable households and the cause of their vulnerability;

• identification of supplementary assistance required at the various stages of the

process, with the possibility of negotiating ;

• monitoring and continuation of assistance after resettlement and/or supplementary

compensation, where necessary;

• encouragement of connection to the power grid;

• other specialized assistance, according to the requests and needs of vulnerable

households.

Depending on the case, assistance may comprise:

• assistance for understanding expropriation and compensation procedures;

• assistance for relocation;

• assistance for school enrolment of children;

• assistance for social integration.

7. LEGAL FRAMEWORK, INCLUDING DISPUTES SETTLEMENT AND APPEAL

MECHANISMS

7.1 National Regulatory Framework

In Cameroon, the national legal framework governing the environmental aspect of the project mainly

comprises the following laws and regulations: (i) Framework Law No. 96/12 of 5 August 1996 on

environmental management; (ii) Decree No. 2013/171/PM of 14 February 2013 laying down the terms

and conditions for conducting environmental and social impact assessments; (iii) Order No. 70 /MINEP

of 22 April 2005 establishing the various categories of operations subject to the conduct of a full impact

assessment and an initial environmental assessment; (iii) Decree No. 2011/2582/PM of 23 August 2011

laying down the terms and conditions for atmospheric protection; (iv) Decree No. 2011/2583/PM of 23

August 2011 to regulate sound and odour nuisances; (v) Decree No. 2011/2584/PM of 23 August 2011

laying down the terms and conditions for soil and sub-soil protection; (vi) Decree No. 2011/2585/PM

of 23 August 2011 establishing the list of harmful or hazardous substances and the regime of their

discharge into continental waters; (vii) Order No. 001/MINEP of 3 April 2013 laying down the

organization and functioning of Divisional Committees for Monitoring the Implementation of

Environmental and Social Management Plans (ESMPs); (viii) Law No. 94/1 of 20 January 1994 laying

down the forestry, wildlife and fisheries regime; (ix) Decree No. 95/531/ PM of 23 August 1995 laying

down the terms and conditions for applying the forestry regime; (x) the Forestry Operation Standards of

January 1998; (xi) Law No. 98/5 of 14 April 1998 establishing the water regime; (xii) Order No.

15

39/MTPS/IMT of 26 November 1984 laying down general workplace hygiene and safety measures;

(xiii) Law No. 91/8 of 30 July 1991 on the protection of cultural and natural heritage owing to the

importance that must be given to tourism and tourist sites, and archaeological heritage that could be

discovered during works.

Concerning affected property, the national legal framework governing compensation comprises: Law

No. 85/9 of 4 July 1985 on expropriation in the public interest and the terms and conditions for paying

compensation; Order No. 832/4.15.1/MINUH/D 000 laying down the terms and conditions for applying

Law No. 85/9 of 4 July 1985 on finished and unfinished buildings; Decree No. 2003/418/PM of 25

February 2003 fixing the rates of compensation paid to owners of crops and planted trees destroyed in

the public interest.

The three orders on public interest statement (DUP) for the Chad-Cameroon Electrical Grid

Interconnection Project signed on 25 April 2016 by the Minister of State Property, Surveys and Land

Tenure (MINDCAF) authorize expropriation for project needs. They are:

Order No. 364/MINDCAF/SG/D1/D14/D142: Adamaoua Region (Ngaoundéré to

Ndom);

Order No. 365/MINDCAF/SG/D1/D14/D142: North Region (Ndom to Lam);

Order No. 366/MINDCAF/SG/D1/D14/D142: Far-North Region (Lam to Maroua,

Maroua to Gassi and Maroua to Garoua).

These instruments provide for the establishment of regional Findings and Assessment

Committees (FACs) whose role is to conduct an investigation to identify and assess property

that is affected as well as identify their owners or holders. DUP orders determine the FAC’s

sphere of competence (divisional, provincial, regional or national), depending on the project’s

scope, nature and importance. The Findings and Assessment Committee for this project will

have a regional dimension. Its operating costs will be included in MINDCAF’s budget.

In Chad, State property and land tenure are governed by Laws Nos. 23, 24 and 25 of 22 July

1967 respectively on the status of State property, land ownership and customary rights and

limitation of land rights, and their implementing decrees Nos. 186, 187 and 188 of 1 August

1967. The instruments form the legal basis for the administration of private and public lands in

Chad. In addition, the 1996 Constitution of the Republic of Chad (revised in 2005) lays down

the basic principles of private property which recognize and protect property right. Article 43

of the 1996 Constitution of Chad states that “every Chadian shall have the right to establish

their domicile or residence freely and in any place whatsoever on the national territory.”

The Land Code provides that “when an operation in the public interest requires expropriation,

it shall be preceded by an investigation lasting at least one (1) month and at most four (4)

months.”

The 1996 Constitution of Chad underpins the expropriation mechanism by stipulating in Article

41(2) that “no one may be dispossessed other than for reasons of public interest, duly

established, and against the payment of fair and prior compensation.”

7.2 Applicable African Development Bank Regulatory Framework

Project implementation must meet the Integrated Safeguards System (ISS) requirements,

particularly Operational Safeguard 2 (OS2): involuntary resettlement: land acquisition,

population displacement and compensation which seeks to clarify all issues related to physical

and economic displacement that, however, do not specifically relate to land acquisition. The

specific objectives of OS2 are to: (i) avoid involuntary resettlement where feasible, or minimise

resettlement impacts where involuntary resettlement is deemed unavoidable after all alternative

project designs have been explored; (ii) ensure that displaced people are meaningfully consulted

16

and given opportunities to participate in the planning and implementation of resettlement

programmes; (iii) ensure that displaced people receive significant resettlement assistance under

the project, so that their standards of living, income-earning capacity, production levels and

overall means of livelihood are improved beyond pre-project levels; (iv) provide explicit

guidance to borrowers on the conditions that need to be met regarding involuntary resettlement

issues in Bank operations to mitigate the negative impacts of displacement and resettlement,

actively facilitate social development and establish a sustainable economy and society; and (v)

guard against poorly prepared and implemented resettlement plans by setting up a mechanism

for monitoring the performance of involuntary resettlement programmes in Bank operations

and remedying problems as they arise.

Project implementation is also aligned with Operational Safeguard 5: labour conditions, health

and safety.

Other relevant Bank policies and guidelines are applicable once triggered within the ISS

framework. These include: (i) Bank Gender Policy (2001) – Bank Group Gender Strategy 2014

- 2018 (2014); (ii) Framework for Enhanced Commitment with Civil Society Organizations

(2012); (iii) Disclosure and Access to Information Policy (2012); (iv) Handbook on Stakeholder

Consultation and Participation in Bank Operations (2001); (v) Policy on Population and

Strategies for Implementation (2002); and (vi) Environmental and Social Assessment

Procedures for Bank Operations (2015).

7.3 Complaint and Conflict Management Process

Principles

To be efficient, inspire confidence and be operational, the mechanism must comply with some

basic principles, namely:

Participation: the representatives of various stakeholders, particularly those of PAPs and local

government and traditional authorities, participate in the mechanism which mainstreams gender

issues and encourages women’s participation.

Contextualization and Relevance: the mechanism is suitable for the project context and

consistent with local governance entities.

Safety and Confidentiality: anyone who so wishes can safely file a complaint. The potential

risks faced by users were mainstreamed into the design of the mechanism which guarantees the

confidentiality of procedures (confidentiality helps to ensure the safety and protection of those

filing complaints and those concerned by such complaints). In this regard, the number of people

with access to sensitive information should be limited.

Transparency: users clearly understand how to gain access to the mechanism whose purpose

and function are communicated in a transparent manner.

Accessibility: the mechanism will be accessible to as many people as possible, particularly

those who are often excluded or most marginalized or vulnerable.

Main Phases

The complaint management mechanism will involve Local Resettlement Committees

comprising representatives of PAPs and local government and traditional authorities. These

committees will be established in each municipal council. The mechanism will operate in two

main phases, namely:

17

Recording of Complaints or Disputes in a Complaints Register

PAPs may file their complaints:

with the Local Resettlement Committee of their municipal council which has a

complaints register; or

directly with the Project (the Complaints Management Officer’s contact address

will be communicated to and displayed in the areas concerned).

Complaints will be managed in a consistent manner, irrespective of the channel chosen.

To live up to complainants’ expectations, response time limits will be set and users clearly

informed thereof.

Amicable Settlement of Complaints

Once a complaint is recorded, it will be examined by the FAC and the Project Complaints

Management Officer. The conclusions may lead to:

the rejection of the complaint (Option 1)

Additional explanations are provided to the complainant to enable him to understand the

reasons for rejecting the complaint.

- If he accepts the rejection, his complaint is closed.

- If he challenges the rejection, he may l appeal against the decision. A mediation

body will then try to reach an agreement or compromise among the various

parties involved.

o If the mediation is successful => Option 3.

o If the mediation fails, the complainant may resort to legal action.

conduct of a supplementary investigation (Option 2)

This may, for example, be re-examination by the FAC resulting in the revision of the

assessment. Whatever the outcome of the investigation, it is necessary to clearly communicate

the findings of the review process to the complainant and duly inform him of the measures to

be taken based on the decision adopted. This supplementary investigation can lead to:

o the rejection of the complaint => Option 1.

o a favourable opinion => Option 3.

favourable opinion and signing of an agreement (Option 3)

The complainant is satisfied with the fair and proper handling of the complaint. All the parties

concerned by the complaint reach and sign an agreement which is guaranteed by the Local

Resettlement Committee through its signature.

8. INSTITUTIONAL FRAMEWORK

8.1 Institutions Involved

8.1.1 In Chad

The institutional responsibilities applicable to this Full Resettlement Plan particularly concern

five institutions which will be responsible for its preparation, validation and implementation.

These are the Ministry of Petroleum and Energy (MPE) which ensures that involuntary

resettlement measures during the preparation, implementation, monitoring and evaluation

phases are implemented in accordance with Chadian legislation and AfDB Guidelines on

Involuntary Displacement and Resettlement; the Ministry of Finance and Budget which is in

18

charge of disbursing the funds needed to pay compensation to project-affected persons; the

Ministry of Environment and Fisheries which ensures the viability of technical data within its

sphere of competence and the fair treatment of cases of expropriation; the ministries in charge

of territorial administration, and of public security which will be the administrative supervisory

authorities of expropriation and compensation of project-affected persons, as well as police and

gendarmerie services which will ensure the safety of operations; the Ministry of Regional

Development, Town Planning and Housing which will participate in the Committee through its

regional delegations to ensure the quality of assessments according to its sphere of competence;

local authorities whose mission is to manage municipal councils and civil society organizations.

8.1.2 In Cameroon

Many institutions are, in one way or another, concerned by involuntary displacement. These

are the Ministry of State Property, Surveys and Land Tenure (MINDCAF) which has the sole

authority to issue public interest statement (DUP) orders for operations implemented by any

ministry necessitating expropriations; the Ministry of Urban Development and Housing

(MINHDU) which determines the rates of compensation for buildings; the Ministry of

Agriculture and Rural Development (MINADER) which determines the rates of compensation

for crops; the Ministry of Economy, Planning and Regional Development (MINEPAT); the

Ministry of Finance (MINFI) which disburses the funds required to pay compensation after the

Committee has completed its expert assessment; the Ministry of Energy and Water Resources

(MINEE); the Ministry of Territorial Administration and Decentralization (MINATD) whose

representatives, namely governors and senior divisional officers, chair expropriation

commissions, respectively at the regional and divisional levels; the Ministry of Social Affairs

(MINAS) which is responsible for ensuring better consideration of vulnerable social groups;

the Ministry of Labour and Social Security; municipal councils; local non-governmental

organizations (NGOs) which participate in facilitating, supervising and training communities

and other actors, and in providing advisory support; local professional organizations;

chiefdoms; and the Findings and Assessment Committee which is responsible for preparing

investigation reports, in accordance with decrees on public services.

8.2 Institutional Capacity Building

Technical assistance is needed to strengthen the capacity of RAP implementation entities,

particularly in ensuring compliance with AfDB requirements. International consultants will

organize training sessions for the institutional actors involved in the implementation of

compensation and resettlement measures.

9. ELIGIBILITY

9.1 Conditions of Eligibility for Compensation and General Provisions

An eligibility matrix was prepared in accordance with AfDB’s Operational Safeguard 2. The

principles of eligibility, compensation and assistance were defined, with special emphasis on

vulnerable persons.

Eligible persons will be men and women who are negatively affected by the project living

within the transmission line right-of-way. By definition, a person is said to be negatively

affected by the project when he or she loses sources of income, property rights, user rights or

other rights to a building, a piece of land or any other chattel or building, in whole or in part

and permanently or temporarily due to project implementation.

19

Eligible persons will therefore be those who: (i) have legal rights over land, including

customary and traditional rights; (ii) have no legal rights over land at the time of conduct of the

census, but have recognized right of enjoyment or claims over such land or property; (iii)

occupy land, though they do not have legal rights over it.

Project-affected persons will be entitled to indemnification or compensation; that is, they will

be expected to benefit from the measures adopted to mitigate losses. The measures may be

indemnification or compensation depending on the status of occupation of the affected area,

rehabilitation, relocation allowance, and disturbance allowance.

Rightful claimants of deceased persons who are formally recognized will also be eligible for

compensation during the interval between the identification of assets and payment of

compensation. Project-affected persons should benefit from compensation calculated with

effect from the date known as the rights adjudication eligibility date.

9.2 Eligibility Deadline

As no deadline has been formally set, the de facto eligibility deadline is the period from

November to December 2016, which corresponds to the period of identification of PAPs on the

ground. This date was communicated to the local authorities concerned and during public

information meetings organized by the Consultant in communities located along the

transmission line route. Anyone undertaking a development activity on the corridor after this

date will not be eligible for compensation measures as spelt out in this FRP.

10. ASSESSMENT AND COMPENSATION FOR LOSSES

10.1 Method of Calculating Compensation

The principles of compensation will be that:

irrespective of the form (in kind or cash), compensation will be paid before

physical and/or economic displacement;

compensation will be calculated based on the full replacement cost for property

lost (plus transaction costs). The estimate will be based on the 2003 legal

schedule of rates adjusted for inflation, while ensuring that the schedule

guarantees market value equivalence.

When this report was being prepared, the Findings and Assessment Committee (FAC) had not

carried out the census of PAPs and inventory of property. The Committee’s work will give rise

to the publication of decrees relating to the compensation of PAPs. Generally, the FAC applies

legal rates. To ensure compliance with AfDB requirements regarding compensation, the rates

proposed in the RAP should be applied.

Adjustments will be made based on the rate of inflation in the Central African Economic and

Monetary Community (CEMAC) zone published in various annual reports of the Franc Zone

by the Bank of France, and those announced by the Bank of Central African States (BEAC) for

2016 and 2017 estimates.

20

10.2 Valuation Bases

Buildings: the project has taken all the necessary measures to optimize the transmission line

route and minimize impacts in terms of economic and physical displacement. The schedule of

compensation for buildings that will be unavoidably destroyed, as identified by the Consultant

during surveys carried out in November and December 2016, will be the full replacement value,

excluding depreciation. Tenants will be compensated for a transition period equivalent to 6

months’ rents.

Land: the RAP budget will include a provision for the replacement of residential land at the

rate of CFAF 4 000 per square metre. It is considered that a household needs at least 500 square

metres to rebuild its house. Regarding farmland, CFAF 200 per square metre is earmarked as

compensation for the cost of clearing and preparing replacement land.

Crops and trees: a schedule of rates is used to estimate the value of perennial and annual crop

losses, notably trees and medicinal plants. Reference rates applied to other projects were taken

into account.

Income of traders and artisans: losses of income by traders, artisans and other professionals

concerned are calculated for an average of 6 months during the transition period pending the

resumption of activity.

11. IDENTIFICATION OF POTENTIAL RESETLEMENT SITES, SELECTION

OF SITE(S), PREPARATION OF SITE AND RESETTLEMENT

Within the framework of the project, affected houses will be rebuilt within the original locality.

There will be no land issues. The exact site for each PAP will be determined and developed in

line with the preparation and implementation of the FRP prior to the displacement of

households.

12. HOUSING, INFRASTRUCTURE AND SOCIAL SERVICES

Water and sanitation infrastructure such as boreholes and wells will be systematically replaced.

To improve the living conditions of the population of the area, the project plans to

systematically improve access to electricity and contribute to improving public lighting, in

collaboration with the municipalities.

13. ENVIRONMENTAL PROTECTION

Environmental protection actions will be carried out in keeping with the Environmental and

Social Management Plan (ESMP) contained in the Environmental and Social Impact

Assessment.

14. IMPLEMENTATION SCHEDULE

The table below shows the overall Full Resettlement Plan implementation schedule.

Description of activities Month

1 2 3 4 5 6 7 8 9 10 11 12

Constitution of the ad hoc committee

Capacity building of administrations

21

Awareness of PAP's

Checking PAPs and rapid updating of

economic data

Verification of the amounts of

compensation per PAP

Payment of compensation

Construction of houses

Assistance to vulnerable

Moving people

Supervision and monitoring

15. COSTS AND BUDGET

15.1 Full Resettlement Plan (FRP) Cost

15.1.1 Chad

The budget, including all measures adopted under this Plan and the operation implementation

and monitoring and evaluation costs, stands at EUR 6 604 995 or CFAF (XAF) 4 345 391 713.

Budget Item Total in CFAF Total in EUR

1. Compensation

1.1 Perennial or cash crops and fruit trees

Citrus (lemon, grapefruit, mandarin, orange, pomelo, and similar

plant) trees 134 020 000 203 710

Mango and avocado trees 144 415 000 219 511

Pine, custard-apple, guava, and apple trees 50 188 200 76 286

Other fruit trees 9 077 600 13 798

Dom palm trees 8 618 000 13 099

Banana trees 285 400 434

Shade trees 15 620 100 23 743

Other trees grown 97 857 900 148 744

Sub-total Perennial Crops 460 082 200 699 325

1.2 Provision for Other Crops

Leguminous plants (groundnuts, bambara groundnuts, soybeans, and

similar crops) 5 580 488 8 482

Grain (corn, millet, sorghum, rice and similar crops) 23 180 488 35 234

Tubers 1 639 024 2 491

Market garden crops 106 243 902 161 491

Other crops 880 000 1 338

Irrigation areas (provision for investment) 7 000 000 10 640

Sub-total Other Crops 144 523 902 219 676

1.3 Houses

Permanent houses 473 200 000 719 264

Semi-permanent houses 378 560 000 575 411

Temporary houses (rebuilt with semi-permanent materials) 1 439 750 000 2 188 420

22

Budget Item Total in CFAF Total in EUR

Kitchen 18 060 000 27 451

Toilets (and annexes) 9 500 000 14 440

Shower 4 000 000 6 080

Veranda 600 000 912

Worksite/foundations 8 000 000 12 160

Fences 7 000 000 10 640

Provision for tenants 9 720 000 14 774

Sub-total Houses 2 348 390 000 3 569 553

1.4 Other Private Buildings

Commercial buildings 3 000 000 4 560

Sheep barn 675 000 1 026

Shed 4 500 000 6 840

Stable 225 000 342

Sheep barn 9 675 000 14 706

Granary 2 280 000 3 466

Poultry house 225 000 342

Sub-total Other Buildings 20 580 000 31 282

1.5 Community Buildings

School 75 000 000 114 000

Church 5 000 000 7 600

Shed/drying area 300 000 456

Cemetery 3 000 000 4 560

Mosque 5 000 000 7 600

Wharf 2 000 000 3 040

Other buildings 6 000 000 9 120

Initiation site (sacred place) 400 000 608

Sub-total Community Buildings 96 700 000 146 984

1.6 Graves

Earth graves 6 700 000 10 184

Roughcast graves 0 0

Cement graves 0 0

Cost of ceremony without exhumation 5 360 000 8 147

Sub-total Graves 12 060 000 18 331

1.7 Wells/boreholes (community-owned or privately-owned)

Wells/boreholes 208 000 000 316 160

Elevated water tank 30 000 000 45 600

Sub-total Wells/Boreholes 238 000 000 361 760

1.8 Permanent Acquisition of Land in the Project Right-of-way (replacement)

Housing lots 388 000 000 589 760

Cultivated/potential agricultural land (provision for clearing) 31 600 000 48 032

Sub-total Permanent Acquisition of Land 419 600 000 637 792

1.9 Others

Loss of income by traders (6 months) 40 000 61

Provision for tenants 2 880 000 4 378

Sub-total Acquisition of Land 2 920 000 4 438

Sub-total Compensation 3 742 856 102 5 689 141

2. Project Supervision

Compensation/Resettlement Measures Implementation Unit 60 000 000 91 200

Institutional capacity building 50 000 000 76 000

Facilitation: administration, elected representatives and chiefdoms

(transportation costs, etc.) 15 000 000 22 800

Sensitization meetings 22 500 000 34 200

Assistance to vulnerable persons 15 000 000 22 800

Worksite monitoring and legal Counsel 8 000 000 12 160

Monitoring and evaluation 20 000 000 30 400

External audit 17 000 000 25 840

Sub-total Project Supervision 207 500 000 315 400

23

Budget Item Total in CFAF Total in EUR

395 035 610 600 454

Total RAP Budget Chad 4 345 391 713 6 604 995

15.1.2 Cameroon

The budget, including all measures adopted under this Plan and the operation implementation

and monitoring and evaluation costs, stand at EUR 14 914 961 or CFAF (XAF) 9 812 474 100. Budget Item Total CFAF Total EUR

1. Compensation

1.1 Perennial crops

Citrus (lemon, grapefruit, mandarin, orange, pomelo, and similar plant)

trees 19 320 000 29 366

Mango and avocado trees 69 547 000 105 711

Papaw trees 240 900 366

Pine, custard-apple, guava, and apple trees 7 501 400 11 402

Other fruit trees 21 961 600 33 382

Shade trees 49 275 800 74 899

Other trees grown 145 956 300 221 854

Sub-total Perennial Crops 313 803 000 476 981

1.2 Provision for other Crops

Leguminous plants (groundnuts, bambara groundnuts, soybeans, and

similar crops) 31 284 000 47 552

Grain (corn, millet, sorghum, rice, and similar crops) 31 284 000 47 552

Other crops (tubers, cotton, sugar cane, etc.) 6 320 000 9 606

Market garden crops 82 160 000 124 883

Sub-total Other Crops 151 048 000 229 593

1.3 Houses

Permanent houses 236 600 000 359 632

Semi-permanent houses 334 880 000 509 018

Temporary houses (rebuilt with semi-permanent materials) 5 778 500 000 8 783 320

Kitchen 21 900 000 33 288

Toilets (and annexes) 17 920 000 27 238

Provision for tenants 122 040 000 185 501

Sub-total Houses 6 511 840 000 9 897 997

1.4 Other Private Buildings

Commercial buildings 24 000 000 36 480

Sheep barn 5 175 000 7 866

Shed 0 0

Granary 1 320 000 2 006

Piggery 385 000 585

Poultry house 900 000 1 368

Sub-total Other Buildings 31 780 000 48 306

1.5 Community Buildings

Health centre 70 000 000 106 400

School 300 000 000 456 000

Church 80 000 000 121 600

Mosque 5 000 000 7 600

Market 5 000 000 7 600

Sub-total Community Buildings 460 000 000 699 200

1.6 Graves

Earth graves 7 900 000 12 008

Roughcast graves 750 000 1 140

Cement graves 1 650 000 2 508

Cost of ceremony without exhumation 7 680 000 11 674

Sub-total Graves 17 980 000 27 330

1.7 Wells/boreholes

Wells/boreholes 544 000 000 826 880

24

Elevated water tank 20 000 000 30 400

Sub-total Wells/Boreholes 564 000 000 857 280

1.8 Permanent Acquisition of Land in the Project Right-of-way (replacement)

Housing lots 378 000 000 574 560

Cultivated/potential agricultural land (provision for clearing) 62 000 000 94 240

Sub-total Permanent Acquisition of Land 440 000 000 668 800

1.9 Others

Loss of income by traders (6 months) 1 920 000 2 918

Provision for tenants 93 060 000 141 451

Destruction of buildings 0 0

Sous-total Acquisition of Land 94 980 000 144 370

Sub-total Compensation 8 585 431 000 13 049 855

2. Project Supervision

Compensation/Resettlement Measures Implementation Unit 120 000 000 182 400

Institutional capacity building 50 000 000 76 000

Facilitation: administration, elected representatives and chiefdoms

(transportation costs, etc.) 30 000 000 45 600

Sensitization meetings 45 000 000 68 400

Assistance to vulnerable persons 30 000 000 45 600

Worksite monitoring, legal counsel 10 000 000 15 200

Monitoring and evaluation 30 000 000 45 600

External audit 20 000 000 30 400

Sub-total Project Supervision 335 000 000 509 200

892 043 100 1 355 906

Total RAP Budget Cameroon 9 812 474 100 14 914 961

15.2 Financing Plan

Institution Amount

Government of Chad EUR 6 604 995

Government of Cameroon EUR 14 914 961

16. MONITORING AND EVALUATION

16.1 Overall Approach

Monitoring and evaluation are major components of resettlement actions.

Monitoring seeks to examine what is effective and what is not, identify difficulties or

impediments, understand the reasons and respond by making appropriate adjustments. It

focuses on three main aspects, namely, resources mobilized, activities implemented and

outcomes of such activities.

For its part, evaluation seeks to verify if general policy objectives have been met and to draw

lessons from the operation implemented in order to adjust strategies and implementation in the

longer term.

16.2 Monitoring

The aim will be to carry out internal monitoring, with monthly, quarterly or half-yearly

reporting according to indicators, resource utilization, implementation of planned activities and

outcomes.

The PMU will monitor project implementation in each of the two countries. The FACs will

participate in the identification of indicator. Copies of reports will be forwarded to it.

In line with AfDB’s OS2, monitoring will include:

25

the availability of adequate financial resources required for RAP

implementation, as indicated in the budget;

the review of the grievance settlement of redress mechanism;

the physical progress of the impact of the Resettlement Action Plan.

The table below presents some examples of indicators.

Table: Resource, Activity and Impact Monitoring Indicators

Indicators Sources of Verification Frequency

Resources (inputs)

% of overall execution of the estimated budget

(expenditure) Internal financial documents Quarterly

% of execution by budget head (amount of

compensation paid to PAPs, assistance to vulnerable

persons, etc.)

Internal financial documents Quarterly

Activities (Outputs)

Number and % of compensation agreements signed with

PAPs

PAP databases

Internal documents

Reporting by partners

Monthly

Number and % of complaints handled

PAP databases

Internal documents

Reporting by partners

Monthly

Number and % compensation paid

PAP databases

Internal financial documents

Reporting by partners

Monthly

Impacts (Outcomes)

Number and % of PAPs displaced

PAP databases

Internal documents

Reporting by partners

Monthly

Number and % of PAPs who have received

compensation (by category and amount)

PAP databases

Internal documents

Reporting by partners

Monthly

Quality of buildings constructed PAP databases

Internal documents Half-yearly

Rate of replacement of fruit trees PAP databases

Internal documents Half-yearly

16.3 Evaluation

- Internal Evaluation

An internal evaluation will be carried out immediately after project completion. It will be very

necessary to ensure that:

displaced persons have been resettled and to the extent possible, near their

former location ;

26

displaced persons are provided with houses of a quality at least equal to that of

their former houses;

land security is respected;

all compensation due has been paid.

- External Project Completion Audit

An external completion audit will also be carried out upon project completion. It will be

undertaken by independent evaluators with wide experience in the domain and, if possible, with

sound knowledge of the specificities of Cameroon. Besides analysing internal monitoring

documents, they will carry out their own field analyses through investigations among

stakeholders and project-affected persons.

Lessons drawn from this evaluation could be useful in RAP implementation in future projects

of the kind. Furthermore, as stated in AfDB’s OS2, it should “compare the real situation with

the envisaged or expected situation, including, in particular, the number of affected persons,

and review the assumptions, associated risks and those induced by the resettlement process, as

well as the difficulties faced”.

17. REFERENCES AND CONTACTS

17.1 References

The summary was prepared based on the following documents:

ESIA Reports on the Chad-Cameroon Electrical Grid Interconnection Project - May

2017 - ARTELIA/HATCH.

ESMP Reports on the Chad-Cameroon Electrical Grid Interconnection Project - May

2017 - ARTELIA/HATCH.

Reports on the Resettlement Action Plan (RAP) of the Chad-Cameroon Electrical Grid

Interconnection Project - May 2017 - ARTELIA/HATCH.

17.2 Contacts

For further information, please contact:

For the African Development Bank (AfDB)

Ibrahima KONATE, Division Manager OIC, email. [email protected]

Jean-Pierre MUTSINZI, Principal Electrical Engineer, e-mail: [email protected];

Pierre Hassan SANON, Principal Social Development Specialist, e-mail.:

[email protected];

Modeste KINANE, Principal Environntal Specialist, email. [email protected];

Salim BAIOD, Environmental Specialist, SNSC Consultant, e-mail: [email protected].