6
1 GREEN MINE INFRASTRUCTURE PLAN; FUNDAMENTALLY SCENARIO DESIGN TO DETERMINE MINE BLOCK OPTIMIZATION AND MINERAL SECURITY (Case Study : PT Vale Indonesia Pit Compartment 02 Blok 1a5a1517 Bahodopi, Middle of Sulawesi) Rahmat Muallim *)Mine engineering, Hasanuddin University *) Persatuan Insinyur Indonesia *)Makassar, Indonesia *)[email protected] ABSTRACT : Land disputes and opening area of mines are number of international issues in modern business nowadays. The increasing of export mineral reserve to another consumer country made it will not be controlled to exploit this resource to fulfill their industrial be fit and develop. Government, investor, and society should be have same purpose to bring this mineral to touch all of stakeholders. Uncertainly law among them made mineral industry be an enemy to break environment and did not give an advantage to society because bad government decision to give permitted for opening mine area. PT Vale Indonesia Bahodopi Middle of Sulawesi especially in Pit compartment 02 Blok 1a5a1517 is a far boundary to plan material movement. The located was closing with number of IUP (mine Legality permitted) area gave a pressure to this company to integration a plan who can be united among legal certainly concept and good mining practice by environment-friendly mining thinking so that born a trust and responsibility to secure this mineral from company and government will be believed it . Green Mine infrastructure Plan have number of methods namely identify location of block model, evaluation of block model reserved by compartment block method, Pit shell optimization, green sustainability concept that consist of three parts namely existing scenario plan designed, new scenario plan designed and Mine out plan designed. Every designed in this researched used software Vulcan 7.5 to give a simulation this plan. Therefore, resulted from this researched namely we got mine green infrastructure sustainability concept and it project concession will be saved and opened. Keywords : Good mining practise, Green mine infrastructure plan, Vulcan 7.5, sustainability, and scenario. 1. PREFACE PT Vale Indonesia Bahodopi middle of Sulawesi in generally has two challenges namely internal challenges and external challenges. Internal challenges explained PT Vale Indonesia have not a best plan to convince company to develop mine in projected area because the located of block 1a5a1517 too far so mine engineer doubt to opening this area and uncertainly law from government to control mineral project in Bahodopi area. The prove are 333 IUP has risen in Bahodopi area emphasized PT Vale Indonesia concession area will be smaller and beside that, nickel supplier in china in last 2009 years is 600.000 wmt will be achieved 10.500.000 wmt in 2013. These case make PT Vale Indonesia has not be brave to take a risk develop this area. External challenges explained that UU Minerba No 4 Th 2004 emphasized two thinks namely add values of mineral within smelter building has more strongest rule by Kepmen ESDM no 7 about smelter building for IUP in 2014, PP No 23 Th 2010 about smaller concession rule by limitation area for exploiting namely 2500 Ha, and UU No 32 Th 2004 about otoda has been changed government paradigm to be a king in every single area who have mineral resources. This challenges have implicated to any mineral business must keep their related to every stakeholders so that every actvitiviy will be justice in all of mine society and pressured to PT Vale Indonesia to think more to solve its mine. Opening area pit compartment 02 Block 1a5a1517 Bahodopi middle of Sulawesi needed good strategy of plan because mine opening has implicated to environment. Beside that, the located of Block 1a5a1517 to Soroako smelter area soo far namely 65 Km and 55 Km to Set up petea. Enivironment and far of block gave a sense to think a solution how we can make a good mining sustainability strategy who will be united among environment decision and policy of company decision by conducted of mine opening area by number of strategy namely design infrastructure, distanced location of infrastructure, capacity of each infrastructure, and scenario material of infrastructure. These case, will be resulted green infrastructure plan that emphasized to green suistainablity. This concept, try to make a scenario of mine plan who was focusing green mine infrastructure plan in Bahodopi PT Vale Indonesia.

Full of Paper CAFEO 31

Embed Size (px)

Citation preview

Page 1: Full of Paper  CAFEO 31

1

GREEN MINE INFRASTRUCTURE PLAN; FUNDAMENTALLY SCENARIO DESIGN

TO DETERMINE MINE BLOCK OPTIMIZATION AND MINERAL SECURITY

(Case Study : PT Vale Indonesia Pit Compartment 02

Blok 1a5a1517 Bahodopi, Middle of Sulawesi)

Rahmat Muallim

*)Mine engineering, Hasanuddin University

*) Persatuan Insinyur Indonesia

*)Makassar, Indonesia

*)[email protected]

ABSTRACT : Land disputes and opening area of mines are number of international issues in modern business

nowadays. The increasing of export mineral reserve to another consumer country made it will not be controlled to

exploit this resource to fulfill their industrial be fit and develop. Government, investor, and society should be have

same purpose to bring this mineral to touch all of stakeholders. Uncertainly law among them made mineral industry

be an enemy to break environment and did not give an advantage to society because bad government decision to give

permitted for opening mine area. PT Vale Indonesia Bahodopi Middle of Sulawesi especially in Pit compartment 02

Blok 1a5a1517 is a far boundary to plan material movement. The located was closing with number of IUP (mine

Legality permitted) area gave a pressure to this company to integration a plan who can be united among legal

certainly concept and good mining practice by environment-friendly mining thinking so that born a trust and

responsibility to secure this mineral from company and government will be believed it . Green Mine infrastructure

Plan have number of methods namely identify location of block model, evaluation of block model reserved by

compartment block method, Pit shell optimization, green sustainability concept that consist of three parts namely

existing scenario plan designed, new scenario plan designed and Mine out plan designed. Every designed in this

researched used software Vulcan 7.5 to give a simulation this plan. Therefore, resulted from this researched namely

we got mine green infrastructure sustainability concept and it project concession will be saved and opened.

Keywords : Good mining practise, Green mine infrastructure plan, Vulcan 7.5, sustainability, and scenario.

1. PREFACE

PT Vale Indonesia Bahodopi middle of Sulawesi in

generally has two challenges namely internal challenges

and external challenges. Internal challenges explained

PT Vale Indonesia have not a best plan to convince

company to develop mine in projected area because the

located of block 1a5a1517 too far so mine engineer

doubt to opening this area and uncertainly law from

government to control mineral project in Bahodopi area.

The prove are 333 IUP has risen in Bahodopi area

emphasized PT Vale Indonesia concession area will be

smaller and beside that, nickel supplier in china in last

2009 years is 600.000 wmt will be achieved 10.500.000

wmt in 2013. These case make PT Vale Indonesia has

not be brave to take a risk develop this area. External

challenges explained that UU Minerba No 4 Th 2004

emphasized two thinks namely add values of mineral

within smelter building has more strongest rule by

Kepmen ESDM no 7 about smelter building for IUP in

2014, PP No 23 Th 2010 about smaller concession rule

by limitation area for exploiting namely 2500 Ha, and

UU No 32 Th 2004 about otoda has been

changed government paradigm to be a king in

every single area who have mineral resources.

This challenges have implicated to any mineral

business must keep their related to every stakeholders

so that every actvitiviy will be justice in all of mine

society and pressured to PT Vale Indonesia to think

more to solve its mine.

Opening area pit compartment 02 Block 1a5a1517

Bahodopi middle of Sulawesi needed good strategy of

plan because mine opening has implicated to

environment. Beside that, the located of Block

1a5a1517 to Soroako smelter area soo far namely 65

Km and 55 Km to Set up petea. Enivironment and far of

block gave a sense to think a solution how we can make

a good mining sustainability strategy who will be united

among environment decision and policy of company

decision by conducted of mine opening area by number

of strategy namely design infrastructure, distanced

location of infrastructure, capacity of each

infrastructure, and scenario material of infrastructure.

These case, will be resulted green infrastructure plan

that emphasized to green suistainablity. This concept,

try to make a scenario of mine plan who was focusing

green mine infrastructure plan in Bahodopi PT Vale

Indonesia.

Page 2: Full of Paper  CAFEO 31

2

Green Mine infrastructure Plan will be implemented to

far of mine block in any location

in ASEAN because reminded that all of ASEAN

country especially Indonesia is a prosperous country

and needed mineral resourced to develop their country.

This project has described schema of material

movement scenario to fulfill good scheduling to run this

project systematically within number of scenario

namely existing plan scenario, new plan scenario, and

mine out scenario. The number of scenario will be

explained the resulted of green mine infrastructure plan

so that we will be knew pit compartment 02 Block

1a5a1517 Bahodopi middle of Sulawesi in the end of

mine scenario. .

2. METODOLOGY

Project methods in Pit compartment 02 Block 1a5a1517

bahodopi middle of Sulawesi namely take the scenario

plan data who consist of historical data location of block

1a5a1517, topography data, block model data, boundary

ore Bahodopi data, main haul road data, and

geometrical bahodopi design data. After all of data

fulfilled, continue with data analyzed by decided map

distance among pit compartment 0 2 to soroako

bahodopi and Set up Petea, evaluation of pit

compartment 02 Block 1a5a1517 reserved by

compartment pit methods, Pit shell optimization

methods, green mine scheduling scenario who consist of

three schemes namely existing scenario plan, new

scenario plan, and Mine out scenario plan. The number

of this methods will be explained green sustainability to

this project will be running well in mine opening area.

3. REPORTING RESEARCHED

3.1. Concession Bahodopi Area

Concession area is PT Vale Indonesia mining authority

who will be explored and exploited. In generally,

concession area PT Vale Indonesia will be showed in

figure 3.1 namely:

Figure 3.1 Soroako smelter distanced to compartment 02

Besed on figure above distanced among soroako smelter

to compartment 02 namely 65 Km. this case showed

that to conduct material movement from compartment

02 to Soroako smelter is too long road. Specified of

location set up Petea to compaertment 02 namely 55

Km who showed in figure 3.2 by Vulcan 7.5 namely:

Figure 3.2 distanced Set up Petea to Block 1a5a1517

In figure 3.2 above explained that distanced to move

material pit compartment 02 Blok 1a5a1517 too far and

we need scenario to make this scenario more simple

smaller plan so that made a simplify scenario to

describe sustainability of green mine infrastructure.

3.2. Green mine Infrastructure Plan design

Pit compartment 02 Block 1a5a1517 Bahodopi

middle of Sulawesi designed by Green mine

infrastructure plan consist of three methods

namely evaluation of mineral reserve pit

compartment 02 block 1a5a1517, Pit shell

methods, and scheduling of schemes pit

compartment 02 such as existing plan scenario,

new plan scenario, and mine out plan scenario.

Those case, will be explained accordance to their

steps namely:

1. Evaluation of mineral reserve block

1a5a1517 Bahodopi middle of Sulawesi

Block model 1a5a1517 divided in three

boundary of evaluation namely

compartment. Every compartment in block

1a5a1517 can be showed in figure 3.3

namely:

Figure 3.3 Block model compartment 1a5a1517

Soroako smelter

Block

1a5a1517

area set up petea

Blok 1a5a1517

Comp 02

Page 3: Full of Paper  CAFEO 31

3

Based on figure 3.3 compartments of block model

1a5a1517 have reserved 9.579.750 with cut of

grade 1.7% Ni. This research has been focused to

Pit compartment 02 withinmaterial reserved who

showed in table 3.1 namely:

Table 3.1 Reserved of pit compartment 02

2. Pit shell optimization method

Pit block 1a5a1517 who has been planed by use pit

compartment method and schemes of existing road

showed that pit compartment 02 as a first

compartment will be opened in block 1a5a1517.

We will show in figure 3.4 namely :

Figure 3.4 schemes of scheduling comp. 02

Figure 3.4 has explained that comp 02 is the first

scheduling target by used Vulcan 7.5. Pit shell

compartment 02 namely pit optimization who

formed by outside design of Pit namely manual pit

and boundary of inside design of pit namely pit

shell it self. This case showed in figure 3.5:

Figure 3.5 schemes of pit shell comp 02

Based on this design we will be gotten pit level

every bench from level 820 up – 775 ultimate pit

limit. It will be showed in figure 3.6 namely:

Figure 3.6 mine push back pit comp 02

3. Scheduling of pit compartment 02 block 1a5a1517.

The importance thinks from this case namely there

are 3 schemes of scheduling such as existing plan

scenario, New plan scenario, and Mine out

scenario. Those of are will be explained namely :

1) Existing plan scenario

In this step, plan work based historical data

bahodopi for knowing effective distance to get

a maximize distance scenario. This planed will

be showed in figure 3.7 namely:

Figure 3.7 existing plan Bahodopi

Based on figure 3.7 scenario of material

movement, value of distance namely face to

existing Rompile 12.41 Km, Face to existing

disposal 12.95 Km, and face to LGOpile

14.028 Km.

2) New plan scenario

New plan scenario is way to solve long

distanced area from existing plan so that be

happened new map distance and new dumping

infrastructure design to get maximize concept

in mine planning. This scenario, will be

showed in figure 3.8 namely:

Material Bah_1a5a1517 Comp_02 Unit

ob_vol 105470 Wmt

waste_vol 0.00 Wmt

ore_vol 59851 Wmt

lgo1_vol 16455 Wmt

lgo2_vol 18629 Wmt

lgo3_vol 0.00 Wmt

Total Material Move (- Civil) 200,405.00 Wmt

SR (OB/(Ore+LGO)) 1.11 Wmt

summary of Reserve Pit Comp_02

Comp 02

Page 4: Full of Paper  CAFEO 31

4

Figure 3.8 New plan scenario

Based on this data explained two thinks

namely firstly, effective distance from existing

plan. It case will be showed in table 3.2

namely:

Table 3.2 Distance comparison scenario

Table above has explained that new plan has a

maximize distance than existing plan so that

more advantage to open mine. Secondly,

infrastructure design of new dumping point

such as New Disposal, New Rompile, and New

LGOpile namely :

a. New Disposal Plan

Disposal plan used as Over Burden (OB)

material movement. Total OB in pit

compartment 02 is 105470 Wmt.

Therefore, New disposal plan should be

fulfilled its material. New disposal plan

will be showed in figure 3.9 namely:

Figure 3.9 New disposal plan

b. New Rompile Plan

Rompile plan used as Ore material

movement. Total Ore in pit compartment

02 is 59851 Wmt. Therefore, new rompile

plan should be fulfilled its material. New

rompile plan will be showed in figure 3.10

namely:

Figure 3.10 New rompile plan

c. New LGOpile plan

LGOpile used as Low Grade Ore (LGO)

material movement. Total LGO in pit

compartment 02 is 35084 Wmt. New

LGOpile will be showed in figure 3.11

namely:

Figure 3.11 New LGOpile plan

Based on new dumping point infrastructure all of

material had fulfilled to opening mine area in pit

compartment 02 block 1a5a1517 Bahodopi middle

of Sulawesi.

3) Mine out scenario

Mine out pit compartment 02 is a big hole in

after finishing mine activity. It will be solved

with run sustainability scheduling by looking

infrastructure design from pit compartment 02

block 1a5a1517 as existing scenario to run next

scheduling. According to road infrastructure

and far of compartment in this block, Pit

compartment 01 is continuing scheme to

opening new opening mine. In this case, It will

be showed that this mine responsible to take

care pit compartment 02 be used in this

scenario so this is we called by Green mine

infrastructure plan. It will be showed in figure

3.12 namely:

Figure 3.12 Mine out scheduling comp 01

Distance comparison among existing plan dan New Plan

from pit comp 02

face pit comp 02 - disposal existing plan 12.95

face pit comp 02 - rompile existing plan 12.41

faca pit comp 02 - LGOpile existing plan 14.028

New Plan pemindahan material pit Comp 02

Face - new disposal 5.25

Face - new Rompile 4.92

Face - new LGOpile 7.2

existing plan disp -> New Disp = 7.7 Km

existing plan Rompile -> New Rompile = 7.49 Km

existing plan LGOpile -> New LGOpile = 6.828 Km

existing Plan of material movement pit comp 02 distance (km)

NEW PLAN DISPOSAL

Triangulation Volume(M3)

s_bdisp_st_01 14772

s_bdisp_st_02 39665

s_bdisp_st_03 150493

total 204930

Triangulation Volume(M3)

dyke_disp_01 443.633

angle 45/26 derajat

project_level R-5

Height 5 meter

angle 45 derajat

berm 1 meter

project_level R-5

Height 5 meter

Disposal_01

dyke_dsp_01

Geometri Design

Geometri Design

access road

s_disp_st_03

s_disp_st_02

s_disp_st_01

dyke_disp

U

NEW PLAN ROMPILE

Triangulation Volume(M3) Luas_area

scut_rompile_01 157179.414 1.5 ha

sfill_rompile_01 136589.473

Triangulation Volume(M3)

bundwall_rom_01 6935.848

angle 45 derajat

berm 3 meter

project_level R5(cut)/R-5(fill)

Height 5 meter

angle 45 derajat

berm 1 meter

project_level R1(cut)/R-5(fill)

Height 5 meter

berm 1 meter

project_level R1(cut)/R-5(fill)

Height 5 meter

bundwall_Rom_01

Geometri Design

bundwall_Rom_01

Geometri Design

Rompile_01

access road

Cut Rompile

Fill Rompile

Bundwall_Rompile

U

NEW PLAN LGOPILE

Triangulation Volume(M3) Luas_area

scut_LGOpile 37822.472 1.42 ha

sfill_LGOpile 35407.568

Triangulation Volume(M3)

bundwall_LGOpile 3056.803

angle 45 derajat

berm 3 meter

project_level R5(cut)/R-5(fill)

Height 5 meter

angle 45 derajat

berm 1 meter

project_level R1(cut)/R-5(fill)

Height 5 meter

bundwall_LGOpile_01

LGOpile_pit comp_02

Geometri Design

Geometri Design

access road

Bundwall_LGOpile

Cut LGOpile

Fill LGOpile

U

Page 5: Full of Paper  CAFEO 31

5

Based on figure 3.12 pit compartment 02 has

over burden is 571783 Wmt. To fulfilled over

burden so we need disposal plan near in this

scheduling so that pit compartment 02 will be

used as usual area before mine activity. this

scenario conducted within use mine out pit

compartment 02 as Inpit disposal to load over

burden from pit compartment 01. Transition

design from mine out compartment 02 be inpit

disposal plan and pond will be showed in

figure 3.13 namely:

Inpit_disposal_dyke_pond_comp_02_

Triangulation Volume(M3) angle 45/26 derajat

s_bdisp_inpit_comp_01 22977 project_level R-5

s_bdisp_inpit_comp_02 72996 Height 5 meter

s_bdisp_inpit_comp_03 115795

s_bdisp_inpit_comp_04 36202

total 247969

Triangulation Volume(M3) angle 45 derajat

dyke_inpit_dsp 8199.772 berm 1 meter

project_level R-5

Height 5 meter

Triangulation Volume(M3) angle 45derajat

s_bpond_inpit_dsp.00 8879.703 project_level R-5

Height 5 meter

Inpit_Disposal

dyke_inpit_dsp.00t

Pond_inpit_dsp_comp_02

Geometri Design

Geometri Design

Geometri Design

Figure 3.13 Inpit disposal and pond plan

Based on this case, there are two point of view

namely firstly, distances among pit

compartment 02 to inpit disposal namely 2.35

Km nearer than new disposal plan 4.95 Km

and secondly, green infrastructure will be

happened because we used mine out pit

compartment 02 as inpit disposal where

disposal will be as reclamation area.

Therefore, if green mine infrastructure plan

will be implemented company, society and

government stayed in one vision and all of

problem in mine especially about mineral

security and uncertainly law will be solved

because mine society saved with this plan.

4. CONCLUTION

Based on The resulted of this research so will

be represented that green mine infrastructure

plan can be implemented in block 1a5a1517 by

number of fundamentally conclution namely :

1. Opening mine of Pit compartment 02 block

1a5a1517 Bahodopi middle of sulawesi can

be opened with new plan scenario until the

end of mine push back from level 820 up -

775 ultimate pit limit.

2. Green sustainability will happened with

signed mine out pit compartment 02 will

use as inpit disposal and fulfilled mine

scenario by effective distance and effective

infrastructure.

ACKNOWLEDGEMENT

Writer said thanks fullness to Contract of Work

(CoW) project mine development PT Vale

Indonesia especially mine plan team as great

division and Mine Engineering Hasanuddin

University for their chance and guidance for me

can be finished this researched . Hopefully your

kindness will be paid to Allah SWT.

REFERENCES

(1) Adiwagara, Gary. 2008. Evaluasi Efisiensi Tambang Terbuka (Open Pit) Menggunakan evaluasi Envelopment. ITS: Surabaya

(2) Amstrong, Margaret,. 1998. Basic Linear Geostatistik.

Springler-Verlag: Berlin Heidelberg,New york.

(3) Bar, Drew. 2012. Stochastic Dynamic Optimization of Cut-off Grade in Open Pit Mines. Queen’s University:

Canada.

(4) Christina, N.B. 2008. An Optimisation Aproach To Materials Handling in Surface Mines. Departement of

Mathematic and Statistic Curten University of

Tecnology: Switzerland.

(5) Dagleden, K. 2001. Open Pit Optimization Starategic For Improving Economic of Mining Project through Mine Planing. 17th International Mining Congress and

Exhibition:Turkey.

(6) Fuykschot, J. 2009. Strategic Mine Planning ; Flexible Planning to Meet Changes in the Business Environment. SRK Consulting: MINEX Conference.

(7) Ghost W.R, Zantop.H, Eggert R.G. 1998. International mineral Economic. Springler-Verleg: Berlin Heidelberg,

Newyork, London, Paris and Tokyo.

(8) Khustrulid, W, Kuchta, M. 2004. Open Pit Mine Planning & Design. London: Balkema Publishers

(9) Milan, B. 2009. Bulk Material Transportation System In Open Pit Mines With Improve Energy Eficiency.

University In Belgrade journal : Serbia.

(10) MGX, 2011. Mine geology training PT Vale Indonesia.

Soroako (Unpublished report)

(11) Mayor Hazard Standart (MHS) 4 dan 10 PT Vale Indonesia. 2000.Slope Stability.Soroako (Unpublished

report)

(12) PT. Vale Indonesia. 2012. Feasibility Study 3 – Cepat . Mine Plan Section. Soroako. (Unpublished report)

(13) Runge, Ian.C. 1998. Mining Economic and Strategy.

Society for mining,metallurgy,and exploration,inc. :

USA

(14) Stermole, F. 2001. Economic and Evaluation Decision Methods. Investment Evaluations Cooperation 3070 :

South Newcombe Way, Colorado

(15) Standar Operasional Prosedur (SOP) Pit Design dan CoG sensitivity PT Vale Indonesia. 2011. Soroako.(

Unpublished report)

(16) Torris, F.1998. Evaluating Mineral Project ; Aplication an Misconception. Society for Mining, Metalurgy, and

exploration,inc.USA.

(17) Waheed Ahmad.2005. Mine Geology at PT INCO. PT

Vale Indonesia : Soroako.

(18) Whittle,G., and Burk.S. 2010. Simultaneous Mining and Mineral Processing Enterprise Optimization For The Platinum Industry. The 4th International Platinum

Conference : Southern of Africa.

Page 6: Full of Paper  CAFEO 31

6