30
F2-) Cooper Industries Cooper-Bessemer Reciprocating Products Division 150 Lincoln Avenue Grove City, PA 16127-1898 412 458-8000 July 23, 1991 Our Ref: QCG-8309 COOPER U. S. Nuclear Regulatory Commission e .4-k 11555 Rockville Pike Rockville, MD 20852 Subject: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports Gentlemen: The following provides a status of activities and corrective actions associated with the subject 10 CFR Part 21 that have taken place since the initial report dated April 5, 1991. Several interim reports have been delivered to Mr. Walter Haass by telephone since that date. A meeting took place on was being performed by June 14, 1991 to review the status of analysis that Houston Light and Power. ATTENDEES: A. E. Bice Joe Burack Tom Drews W. Ferguson Richard Kessler Steve Shin S. Timmaraju C-B HL&P HL&P C-B HL&P HL&P HL&P Quality Assurance STP Engineering Metallurgy Metallurgy Metallurgy Metallurgy STP Metallurgy DISCUSSION: 1. Data gathered from tests performed by HL&P was reviewed during the meeting. It was determined that there are several attributes that contribute to the failed fuel nozzle tips. However, not all of the attributes are present in every failure. Those that contribute to fuel nozzle tip failures (i.e. cracked in operation, cracks identified during 10 CFR Part 21 investigation, failed dimensional inspection performed at Haynes to support 10 CFR part 21 investigation) include:

Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

F2-)Cooper Industries Cooper-Bessemer Reciprocating Products Division 150 Lincoln Avenue Grove City, PA 16127-1898 412 458-8000

July 23, 1991

Our Ref: QCG-8309

COOPER

U. S. Nuclear Regulatory Commission e .4-k

11555 Rockville Pike Rockville, MD 20852

Subject: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports

Gentlemen:

The following provides a status of activities and corrective actions associated with the subject 10 CFR Part 21 that have taken place since the initial report dated April 5, 1991. Several interim reports have been delivered to Mr. Walter Haass by telephone since that date.

A meeting took place on was being performed by

June 14, 1991 to review the status of analysis that Houston Light and Power.

ATTENDEES:

A. E. Bice Joe Burack Tom Drews W. Ferguson Richard Kessler Steve Shin S. Timmaraju

C-B HL&P HL&P C-B HL&P HL&P HL&P

Quality Assurance STP Engineering Metallurgy Metallurgy Metallurgy Metallurgy STP Metallurgy

DISCUSSION:

1. Data gathered from tests performed by HL&P was reviewed during the meeting. It was determined that there are several attributes that contribute to the failed fuel nozzle tips. However, not all of the attributes are present in every failure. Those that contribute to fuel nozzle tip failures (i.e. cracked in operation, cracks identified during 10 CFR Part 21 investigation, failed dimensional inspection performed at Haynes to support 10 CFR part 21 investigation) include:

Page 2: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

Page 2 • QCG-8309

July 23, 1991

0 Ligament thickness at the tip. "* Ligament thickness at the base. "* Ligament area in square inches. "* Ratio of case hardening depth to core size. * Engine induced stress and clogged injector holes (isolated

occurrence). Manganese sulfide inclusions in the base metal (isolated occurrence).

2. It was suggested that the nitride depth be minimized and possibly eliminated.

Subsequent to the Houston meeting this subject was addressed to Mr. Bill Morton of Hayes Corporation Engineering. He stated that the nitride operation is required for improved wear characteristics and hardness of the seat. He indicated that it could not be eliminated.

3. Current Haynes process controls were discussed. They perform a first part destructive test after set up of the nozzle fuel holes drilling process. In addition they perform 100% bore scope examination of the fuel nozzle tips; and, inspect them with a special gauge to ensure that the location and angle of the fuel holes is within tolerance.

4. HL&P personnel stated that the NRC had visited them during the previous week. An isolated failure has been detected in lot number 150009. This went undetected during the eddy current NDE that was performed by HL&P. Discussion with the NRC personnel and application of a conservative approach has prompted HL&P to remove all fuel nozzle tips from stock that fall into the 1500xx lot number series. The following lots have been removed by HL&P.

150003 removed this year (No failure noted) 150004 removed this year (No failure noted) 150006 removed this year (Generic failure) 150008 removed earlier (Generic failure) 150009 removed this year (Isolated failure) 150010 removed this year (Isolated failure)

001110 removed this year (No failure noted) 001124 removed earlier (Generic failure)

Page 3: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

Page 3 QCG-8309 July 23, 1991

Thirty-six nozzle tips were selected from various lot numbers and transmitted to Haynes Corporation for inspection. Haynes Corporation was asked to use tool gauge #44-703039 to verify the dimensional location of the fuel port holes. The inspection took place on June 14th, 1991 and was witnessed by Mr. Corliss U. Laisure, a contract auditor that works for Cooper-Bessemer. The attached report documents the results of that inspection. It is noted that all fuel nozzle tips from the 150006 lot failed the dimensional inspection. In addition, one fuel nozzle tip from lot number 150003 failed the inspection. The gauge was introduced after manufacture and deliver of the failed nozzle tips.

A tool gauge patterned after the one used by Haynes Corporation has been ordered by Cooper-Bessemer to verify the dimensional location of the fuel port holes. It's usage will be incorporated into appropriate quality control receiving inspection plans.

Cooper-Bessemer has performed an investigation to identify and locate all fuel nozzle tips (i.e. part number 2-50F-003-023) and holder assemblies (i.e. part numbers KSV-13-2A#4 and KSV-13-2A#6) purchased from Bendix Corporation and/or Haynes Corporation. A total of 2417 fuel nozzle tips were identified by CES serial numbers. 197 Of the 2417 were not traceable to a specific customer. This is explained by the fact that Cooper-Bessemer has delivered 26 commercial KSV engines to various customers. Fuel nozzle tip traceability is not maintained for commercial customers.

Cooper-Bessemer has a high degree of confidence that the attached investigation results capture the total population of fuel nozzle tips delivered to nuclear customers.

Further activities relative to determination of the full scope of the problem are being considered by involved organizations. As corrective action plans/recommendations are further developed a status report will be forwarded to you.

Sincerely,

Controller 7!

/kll

Attachments

Page 4: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

Page 4 QCG-8309 July 23, 1991

c: J. S. Baron - CES/GC A. E. Bice - CES/GC D. T. Blizzard - CES/GC W. 0. Ferguson - CES/MV A. D. Gillette - CES/GC C. E. Hallman - CES/MV J. M. Home - CES/GC R. R. Kiener - CES/GC M. A. Schleigh - CES/GC B. R. Sedelmyer - CES/GC P. J. Shimek - CES/GC F. B. Stolba - CES/GC File: K-5fal 9 Fuel Nozzle Tips

c: Walter Haass - NRC One White Flint North Mailstop 9D4 Washington, D.C. 20555

R. L. Pettis Nuclear Regulatory Commission One White Flint North Washington, DC 20555

S. Timmaraju Houston Lighting and Power Co. South Texas Project 8 Miles West Wadsworth, TX 77483

OWNERS GROUP:

A. G. Killinger MPR Associates, Inc. 1050 Connecticut Avenue, NW Washington, DC 20036

Neil Thibodaux Arizona Public Service P. 0. Box 52034 Phoenix, AZ 85072-2034

Frank Czysz Pennsylvania Power and Light 2 North Ninth Street A6-3 Allentown, PA 18101

Darren Dageforde Nebraska Public Power District Cooper Nuclear Station P. 0. Box 98 Brownville, NE 68321

Ted Fryer Houston Light and Power Co. P. 0. Box 308 Wadsworth, TX 77483

Terry O'Brien Commonwealth Edison Co. 1400 Opus Place Suite 400 Downers Grove, IL 60515

Keith Ward Niagara Mohawk Power Corp. 301 Plainfield Rd. Syracuse, NY 13212

Thomas Watkins Louisiana Power & Light P. 0. Box B Killona, LA 70066-0751

Page 5: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

9/26/799K2001 -02 001124 2

9K2002------

6B1 001-29

6B1001,02,05,07,09,15,21, 24,29

6B1003,06,10-13,17-19,23 RRlflR.14_16.20.22.25-28

D87001HLP

APS

Ceco/Bvron

1/10/86

I Ni-Mo II

QCG-8160 Page 1

Page 6: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

5/10/84 4E1601-20 001222 20

UE1617,18 ~

I 087001

115

4/12/88 D81301-24 150009 24

II

QCG-8160 Page 2

Page 7: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

Dats CES SM Lot #Cty. Customer

8D1301,03,04,06,09,11, Ceco/Braidwood

15,16,18,21

8D1302,05,07,12,13,17, HL&P

19,20,23,24 ______________

8D1308,10,14,22 Ceco/Braidwood

3128/88 8C3001-29 150008 29Scapd#19

1/28/88 8A2801-20 150008 20.

8A2801 ,02,04,06-08, APS

10-13,15 ____________

_ _ _ _ _ _ _ _ _ _ _ _ 8A2819,20 _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ __ Ceco

8A2803,05,09,14,16-1 8 Scrapped #81497

...... .....

812301-14 __ __ _ __ __ _ __ __ _HL&P

812315-58 _ _ _ _ _ _ _ _ _ _ __HL&P

8L2359,61 ,63,64,70,73,80, Ceco/Bymron

85,94,96,100,104,108,109, 112,116,118,121,136,138, 140,141,149,161,164,168,

8L2360,77,84,90,97,99, Ce co/Bryon

___________________127,128,132,167,176____________ ___________

QCG-8160 Page 3

Page 8: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

M~le CAI Inimy. Customer

GUNr li m' L -UE 1"Date

8L2366,68,122,124,125, 134,137,157,162,165,175, 110,103

8L23177

8L23106,153,156,158,169, 89

i I APS

8L2362,72,74,81,86,93,95, 111,113,131,146,150,155, 163,174

8L2365,67,69,71,75,76,78, 79,82,83,87,88,91,92,98, 101,102,105,107,114, 115,117,119,120,123,126, 129,130,133,135,139,142145,147,151,152,154, 159,160,166,171-173

____________ I Ceco/ByronI I I -

7M1801-27 HL&P

7M1828-47 APS

7122/87 7H0701-14 150006 14

7H0701 -07,09-14 "•HL&P .... . APS

QCG-8160 Page 4

T

4. 1 Ceco/BraidwOod

ICeco/Byron

I

-t

CIIdo•mer0tv.

ICeco/Byron

APS

Ceco/Braidwood

Page 9: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

Date CES SIN Lot # Qty. Customer

6/29f79•9g 2301-04 001124 4 . ............. ..

9G2304 HL&P

9/2611 9K17o1-14 001124 14 ! !!iiiil iiii iii!i

9K17o1 ,•cEco/BRAIwooD 9K1706,09 APS

1/27/76 6C2201-08 001066 8

6C2207 PP&L

. . .. ......... . ........ ::.::..:..:.. . . .............

6130/78 8G2501 -20 None 20

8G2502 CECO

.............. ...... . ......... ..................

8G2510,12,17,19,20. .PP&L

........ .... ................................... ................. ......... ............................

1/2/4/75 702701-09 001073 94

001059

_____________702702,04 APS 9K2706,08 CECO

8K1601,07 _APS

____________8K1602,03,05 ____________HL&P

QCG-8160 Page 5

Page 10: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

0F0501-118 0F0518,53,55,66 F0F--7,39,77,87,92,116

0F0558,40,35,82,24, 111,101,46,86,16,89,43,10,30,

25,21,33,118,91,94,84, 13,60,32,73,99,49,34,81,47,29, 14,103, 72,112,09,05,51,114,63, 106,19,98,80,15,44,70, 97,85,71,57,26,93,22,83,96,45, 108,06,50

0F0501-04,7,8,11,12, 17,20, 23,28,31,36-38,41,42,48, 52, 54,56,59,61,62,64,65,67-69, 74-76,78,79,88,90,95, 100,102,104,105,107,109,110, 113. 11 117

ICH 19 1-- LAPS HL&P

I

10/9/89-9K2101-73 LCH 19 I73QCG-8160 Page 6

4/23/90 t118

Page 11: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

2-50F-003-023

Date CES S/H Lot # Oiy. Customer

9K2103,14,22,37,41,44,20, APS

29,30

9K2106,07,12,21,32,40 APS

9K2147-66, 68-73 HL&P

........

3/29/90 002901-71 LCH 19 71

0D2901-27,31-33,36-38, HL&P 41,44,50,51,55,65,42

3129/90 0 02928-30,34,35,39,45, APS 47,49,52-54,56,57,59,60,

___________________02,64,67,69,70____________

0D2940,46,48,58,61,63, PP&L 66,71,68,43 ~::~ SSS . 55:sS~5 ~~ .S......S..:5. ..... ... :. : : 1 ~ .:

S. 5 5 .5 5 : s 5 : .5... . .... .. . .. . .

8/3/89 9H2801-129 LCh 1 129.............

9H2801-03,05"09,15,21, Ceco/Braidwood 17-19,23-25,26,30,3234,36-43,46,47,49, 54,58,59,60,

QCG-8160 Page 7

Page 12: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV- 1 3-2A#4

7E1101-04

7/31/87 7H0501-36 7H0501,2,7,9,10,12,13, 14,16,17,18,20,24,28,29

7H0503,08,11,30,31-36

7H0504-06

7H0515,21,23,26

150006

APS

HL&P

HL&P

Ceco/Braidwood

QCG-8160 Page 8

4/22/87 150004 JS0005

4 HL&P

Page 13: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES SIN Lot # Qty. Customer

7H0519,22,25,27 HL&P

7/3/87 7H1801-02 150006 2 Ceco/Braidwood

121/67BO901-3 150004 30............................ JS0005................

7B901 Ceco/Braidwood

7B0902-06,08,10,12- Ceco/Byron

15,26-28,30,21

7B0907,11,16-19,22- Ceco/Braidwood

25,29

7B0909,20 HL&P 7 B 0 9 9 ,2 0... . .. . . ............ ............. ......................................................................................................................

IJIvI'J I �i I I I *1 t

QCG-8160 Page 9

OIVIu fI I"- I O,o---U-f-,-

Page 14: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES SIN Lot # Qty. Customer

4D1 602,03,05,06,08,09 PP&L

4D1607,10,11 Ceco/Byron

4E0801-12 4. PP&L

4E0813-1 6 PP&L

7A2001 ,02,04-06,09,1 1- Ceco/Bryon

13

7A2003,08, 10,14 LP&L

12/7/79 0F1701-50 None 50

0F1 701,03,05-10,33, ,,. Ni-Mo

36,49

0F1 702,04,12,20-26 __________ Ni-Mo

0F171 1,13,15,17,18,27, APS

28,30,31,37,38,39,40, 44,46,47,50

0F1 714,16,29,32,35,41 - APS

43,45__ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _

.... c..-....0

QCG-8160 Page 10I

I

Page 15: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES S/N Lot # Qty. Customer

0F1734 HL&P

0F1748 Ni-Mo

OFR719 Ceco

9/18/79 9L0701 -16 None 16 •;•••

9L0701,03,08,09, 12,15 Jj Ceco/B raidwood

9 L0702,04-07,10,1 1,13, Ceco/Braidwood

14,16.. ..

9/26/88 8M0501-10 150009 10 .. ecoB.a.dwood

10/31/86 6L1801-15 150004 15 i:: -i•l•iiiii:::•ii...ii;:ii-iii•3:

6L1801-10 . . APS

6L1811-15 HL&P

........... ... .. .............

11/24/86 612606-10 JS0003 5 HL&P

11/24/86 6L2611-20 150004 (7) 10 Ceco/Zion

150003 (3) 6L2601-05 JS0004 5

QCG-8160 Page 11

Page 16: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV- 1 3-2A#4

5L2101-60

5L2123,42,48,50,58

5L2146,47,57,45,49

r, 1 0 Or 0V7 '-217 A I 9A

I I_____________ I

I IF ,43 ',+,o

Ceco/Byron

Ceco/Braidwood

APS

512126,31 LP&L

5L2129,30,32-35,38, Ceco/Byron

39,52,54,55,59 K=I:IA

.m _

I 5L2140,51,53,60I

5L2101-22 I!,Ceco/Byron

QCG-8160 Page 12

11/11/85

Nebraska

NI-MO

iiII

i I

,J,Rl 919A AA AA RA

Page 17: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES SIN Lot # Oty. Customer

4E2502 Ceco/Byron

I 4E0401-08 I None

11/11/85 5L2501-56

5L2501-19,21,22,24, 25,28-36,38-47,49, 51,53-56

5L2520,23,26,27,37,48, 50.52

___________________ 4-

______________________________ -I- 1

PP&L

Ceco/Byron

1111/25/85 5M1101-03

1D1401,02,13,14t rVlV

PP&L

1D1403-08,15-20 Ceco/Zion

1 D 1421,22 Ceco

QCG-8160 Page 13

I Jsooo0

I

Page 18: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV- 1 3-2A#4

S6B2701-68

6B2701,02,04,05,14,19, 24,26,31,34,67

6B2703,06-08,10,11, 13,15,16-18,20,21,27,29

6B2712,22,23,25,28,30, 37-40,44,49,50

6B2732,36,43,45,46, 4 8 ,

51,60

6B2741 ,47,52-59,61-63, 65,66,68

68

Ceco/Byron

LP&L

LP&L

PP&L

PP&L

QCG-8160 Page 14

1/30/76 001058 001059

Page 19: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES S/N Lot # Qty. Customer

6/27/79 9G2701 -30 None 30

9G2701-15 APS

9G2716 Ni-Mo

9G2717-21,23-30 HL&P

12120/77 8 B0101-70 001104 70 !••••••ii•••!•! :::!`i:::!•••!!iiiii•:*::::::::::::

8B01 01,02,03,19,34,36, ",APS

52-56 __ _ __ _ __ _ __ _ _ __ _ _ _ __ _ _

8 B 0 1 1 4 , 2 6 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ N i -M o

8 B 0 1 1 5 -18 ,2 2 ,2 4 , 3 8 -4 2 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ H L & P

8B0128 Ni-Mo

8BO 129-33, 37,49, 50,58 __ _ _ _ _ _ _ _ _ _ _Ceco/Byron

8B01 70,43-46,48 _ _ _ _ _ _ _ _ _ __Ceco/Byron

8 B 0 12 0 _ _ _ _ _ _ _ _ _ _ _H L & P

8B0123 H L&P

8B0135 APS

.. . . . . . . . . . . . . . . . . . . . .. .... ........:

: : : ; : :, • • • • • • • • ̀ ̀ ; ; ; : : ; : ; ; ; :• : : % ; % : : : :: : : : : : : : : : :: : : : : : : : : : :: : : : : : : : : : :: : : : : : : : : : :: : : : : : : : : : :: : : : : : : : : : :: : : : : : : : : :

7H0101-70 001090 001094

70

QCG-8160 Page 15

6/20/77

III

Page 20: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV- 1 3-2A#4

Date CES SIN Lot # Qty. Customer

7H01001-06,08,09,19-22, 4, APS

30,32-34,37-41

7H01 43-50,57,58,65,66, ?

68,69,43-45,47-50___________

7H01 04,10-18,23-28, Ceco/Byron

53,56,63,07

7H0129,31,42 Ceco/Byron

7H0135,36,51,52,54,55, Ceco/Byron

59-62,64

7H0146,70 Ceco

7H0167 Ceco/Zion

12/1/86 6M1101-07 150003 7 Ni-Mo

12/11/86 6M1718-20 JS0004 3 Ni-Mo

12/11/86 6M1701-17 JS0005 17

6M 1701-05,11-14,16 , Ceco/Byron

6M1706,08 APS

6M1707 LP&L

QCG-8160 Page 16

Page 21: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV- 1 3-2A#4

Date CES S/N Lot # Qty. Customer

6M 1709 Ceco/Braidwood

6M 1710,17 JS0005 Ni-Mo

6M1715 4. #03962 5/90 SCRAP Ceco/Braidwood S. ... .... ..... ,, i i '• !i iiii ii i ',i!........... .. i i ..... i i ii......i

8/16179 9H2501-63 001135 63

9H2501-04,11,13,15,17- ,. Ceco/Braidwood

22,34,39-41,51,60-62,35___________

9H2505-1 0,12,14,16,23, HL&P

36-38,43, 50,53,57-59,63 ___________

9H2542,45,46,48 ___________APS

9H2544, 47 APS

9H2524-33,54-56 HL&P

....I ............. I

. ... ..... .. .. .. .. .. . . . .. ..S Ss:. . .:ss

8/12107 o92501-63 001104 75

9B0201,19-27,49 1, Ceco/Byron

8 B0202-06, 16-18,28-30, HL&P 42-45 1,51,60-62,35 8B0252-60,132 HL&P

8B0261 -66,73-75 ___________APS

8B0240 Ceco

QCG-8160 Page 17

Page 22: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

Date CES S/N Lot # Qty. Customer

8B0250 Ceco/Bryon

8B0233-36,38,39,46- PP&L

48,67-69,71,72,70

8B0237 Ceco ..... . . .. ..... .... ... *.*. .*.. .....**.~ .. .~. . .*. .*. .* .. .

.. ........ . . .. . .. ...... . . . . ... *..* .. * ... .. .* .**.*. .. :* *:* . **.

8B0251 Ceco/Zion

8B0207-15,31,41 HL&P

.. ..................... :::2....:. ................... . . . .......

12/20177 8A3101-70 001104 70

8A31 12,15-17,31,33,34 _____________________HL&P

8A31 13,43,70 ____ ______Ni-Mo

8A31 30,39,42,56,55 _____________________APS

8A31 44,62,64,66 ______________________Ni-Mo

8A31 54,57,63,65,69 ____________CecoiB raidwood

8A31 32 _______ ___HL&P

8A3129 HL&P

8A3111 Ni-Mo

8A31 08 Ceco

8A31 05 APS

8A3101 ,02,04,06,07,09, APS

10,14,21,45-53,67,68 _____________________

QCG-8160 Page 18

Page 23: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-1 3-2A#4

11

QCG-8160 Page 19

IDate CES S/N Lot # Qty. Customer ............................................................ ................ .... ................

1/30/76 6B2601-42 001067 42 001068

6B2601-06,08,12 PP&L

6B2607 PP&L

6B2609-11,13-20,22,25, PP&L

26,33,36,39

6B2621,23,24,27-32,34, PP&L 35,37,38,40-42

3537384042..... ............................ ....... .. . ...........

8/21/79 9J1901-18 001135 18 •i!~~~~~iiii•iiii•.ii!!iiiii~~iii'ii

9J1913-18 4, HL&P

9J 1902,04-09,12 ___________Ceco/B raidwood

9J 1911 ____________Ceco/Braidwood

9J 1901 ____________________APS

9J 1910 Ceco/B raidwood

Page 24: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

KSV-13-2A#6

Date CES S/N Lot # Oty. Customer

8/28/89 9J2301-70 Lch 1 70

9J2301-43 Ceco

9J2344-46,49,50,52

56,58-61,63,66,68-70,51

9J2362,47,67

9J2365

9J2348.57,64

1 4

APS

APS

APS Ni-Mo

2

I Lch 19 1 33 IAPS

QCG-8160 Page 20

Page 25: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

QCG-8160 Page 21

Page 26: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

Cooper Industries Cooper-Bessemer Reciprocating Products Division 150 Lincoln Avenue Grove City, PA 16127

Inter-Office Correspondence

Date: June 21, 1991

To: K-6e Haynes Corporation

From: Corliss U. Laisure

Subject: QCG-9095 Cooper Energy Services Purchase Order 3421N1537

Ref: QCG-9018

Surveillance over performance of the activities required by

the referenced purchase order was performed on June 14, 1991.

Requirements of the surveillance were basically to observe the

gauging of the fuel port holes in 36 nozzle tips using tool

gauge #44-703039, recording of results, and maintenance of

serialization of the individual tips. The following personnel

were contacted during this surveillance:

Mr. Dave Langford, Quality Control Manager Mr. Bill Morton, Senior Engineer Mr. Kurt Leutz, Customer Service Mr. Don Moore, Senior Inspector

Gauging of the nozzle tips was performed by Mr. Langford and

Mr. Morton.

Nozzle tips were manufactured to Drawing 10-375927A, "Blank,

Spray Nozzle Body Type N4SE". This drawing was created by The

Bendix Corporation, Electrical Components Division, Sidney,

New York, and was approved 7-25-75. The drawing specifies the

three fuel port holes be concentric with the center bore of

the tip on a circle with an "0.875" diameter. Fuel port holes

are bored at an angle of 5 degrees 5 minutes to the centerline

of the center bore. True position tolerances are used in the

manufacture and gauging of the fuel port holes.

Each nozzle tip was removed from its plastic bag and was

gauged using the specified gauging tool (Tool No. 44-703039).

Page 27: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

OCG-9095 June 21, 1991 Page 2

The tip lot number (Haynes lot number), identification

information on bag, including HL&P exam number and results of

the gauging were recorded on the data sheets provided. Upon

completion of the gauging, the nozzle tip was returned to its

original bag. When a bag contained more than one nozzle tip

an HL&P exam number was arbitrarily assigned to each one and

marked on the tip to correlate each tip with the data. A copy

of the data sheet is attached.

All nozzle tips from Lot Number 150006 failed this inspection.

In all cases with this lot, the gauge failed to go into all

three of the fuel port holes. Visual examination during

gauging indicates the holes are to close to the center bore as

noted on the data sheet.

One of two nozzle tips from Lot Number 150003 failed this

inspection (HL&P Exam Number 102). The gauge failed to go in

two of the three fuel port holes. As noted on the data sheet,

visual inspection indicates these fuel port holes are to far

from the center bore.

Both nozzle tips from Lot Number D87001 passed this

inspection, however, the gauge fit snugly in all holes in the

tip identified as HL&P Exam Number 211.

Tool gauge number 44-703039 was manufactured to drawing number

44-703039 dated 11-1-88 and is identified within the Haynes

Corporation calibration control system as functional gauge

number 54910. Calibration of this gauge was checked. The

gauge was entered into the Haynes Corporation calibration

control system on 11-13-89 and is on a 180 day calibration

cycle. Recalibration is due 6-30-91. At my request, three of

the drawing dimensions of this gauge were checked; diameter of

center pin, diameter of fuel port pin, and angle of fuel port

pin bushing with respect to centerline of center pin.

Diameters were checked at three locations along the length on

each pin using a calibrated micrometer. Dimensions were

within tolerance and indicate no taper:

Drawing Dim. Measurements

Gauge Center Pin .3070+/-.0001 .3071 .3071 .3071

Fuel Port Pin .1150+/-.0001 .1150 .1150 .1150

Page 28: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

OCG-9095 June 21, 1991 Page 3

Fuel port pin is inserted into the gauge through a hardened

bushing at an angle of 5 degrees 5 minutes to the centerline

of the tool. This angle was measured by inserting the pin

into the gauge and measuring the limits of the angle of the

pin and the gauge centerline on an optical comparator. (Note:

There is a small amount of play between the pin and the

bushing). This angle measured 5 degrees minimum and 5 degrees

10 minutes maximum.

Sinc rely,

r ri.s s4 suree Lead Audito

copy: A. E. Bice A. P. Stef fan Paul Shimek File QCG-9095

Page 29: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

5.

(D

0

CL

CD

CD

0

=3

CD

Page 30: Fuel Nozzle Tip 10 CFR Part 21 - Interim Reports. · Subject: Fuel Nozzle Tip 10 CFR Part 21 -Interim Reports Gentlemen: The following provides a status of activities and corrective

*This number is marked on the bag in which each tip is packaged.

Haynes MtlIspc~/

Date

00/I/O ý4#41 9(,!

4~c 00n10 7/ 0 ,,S O

___ __ ___ __ 8 i4)C,*h /2.4 V _ __ _ NO-r(0 O FloS C/05e -76

2Ro5

I-1 78070

LoT~~ 6~co 20 Z22ý

4_ _ _ _ _ _ cq '_<A /57A i

________/_7__7_ 8 020c?_________

IT0006OFEYA4 425 No Q47(

10 S~o'fO: 22S &

A.C 00IOC? 69. --*23 0j

W/9oo cazs29 _____-_6 2 Hc4F5 - l4,-ego

___________ ______ he~s IS~O fn.

Q-n60ec-C_