FSS BW Operations - Descheduling of Process Chain

Embed Size (px)

Citation preview

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    1/6

    Descheduling of Process Chain

    Document Version / Dtails : Ver 1.0 / 16-FEB-11

    Record Of Release

    VersionNo.

    Created /Modified By

    Reviewed By Release Date Modifications Done

    1.0 Saurabh Gupya/Sanjay Dubey

    Kush 16/02/2011

    Project ID: E6806 Project Name: FSS BW Operation

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    2/6

    Descheduling of Process Chain

    PM-03-04

    Ver 1.0/16-Feb-2011

    Page 2 of 6

    Scope of Document: This document helps us understand the steps to be followed in case we want to

    deschedule a process chain. Some of our process chains run on weekdays or particular workdays. So theyhave to be descheduled and rescheduled accordingly.

    Here we are taking the example of descheduling the data layer process chain for Banking Services(ZBSMETACHAIN).

    Step1: Open the process chain in RSPC or RSPC1There are two ways of opening the process chain. If we know the name of the process chain to be

    descheduled then go to transaction RSPC1.

    Enter the name of the process chain.

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    3/6

    Descheduling of Process Chain

    PM-03-04

    Ver 1.0/16-Feb-2011

    Page 3 of 6

    Step2: After entering the process chain name, click on execute. Process chain will open.

    But if we dont know the name of the chain then we can use transaction RSPC to search for it. Searchfor the required chain by opening the corresponding node.

    Below screen will open after execution of transaction RSPC.

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    4/6

    Descheduling of Process Chain

    PM-03-04

    Ver 1.0/16-Feb-2011

    Page 4 of 6

    After searching for process chain, double click on it. Process chain will open as shown below:

    Step3: There are two ways of descheduling a process chain,a. Remove from scheduleb. Deleting the next scheduled job

    If the process chain is currently running and we use first method to deschedule it, then along with thenext schedule job, currently running job will also be cancelled. We should use this method only if the

    current run is completed.If we use the second method to deschedule the job, then only the next scheduled job will be cancelled.It will not affect the currently running job.

    a. Remove from ScheduleClick on Execution tab, click on Remove from Schedule.

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    5/6

    Descheduling of Process Chain

    PM-03-04

    Ver 1.0/16-Feb-2011

    Page 5 of 6

    b. Deleting the next schedule job1. Right click on process step Start of process chain, click on Displaying Scheduled Jobs.

    2. After clicking on Displaying Scheduled Jobs, Job overview screen will appear. Select the job.

    3. Now Go to Job tab and click on Delete.

  • 8/22/2019 FSS BW Operations - Descheduling of Process Chain

    6/6

    Descheduling of Process Chain

    PM-03-04

    Ver 1.0/16-Feb-2011

    Page 6 of 6

    4. After clicking on Delete, below pop up will open. It will ask to delete selection. Click on Yes.

    5. After clicking on Yes, the scheduled job will disappear from the Job Overview screen.

    Step4: Now go back to the process chain and refresh it. The process step Start will turn Grey. It showsthat the process chain has been descheduled.