Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
From the substratum to the substation –
a central London substation upgrade Ian Cox – London Programme Manager
2011. UK Power Networks. All rights reserved
End Customers
Millions
Service Area
km²
Underground
Network km
Overhead
Network km
Energy Distributed
TWh
Peak Demand
MW
New Connections
UK Power Networks overview
8.1
29,165
138,000
46,000
16,229
100,000
86.4
2
2011. UK Power Networks. All rights reserved
Location of primary substations in London
Leicester
Square
2011. UK Power Networks. All rights reserved
From the substratum to the substation –
A central London substation upgrade
• Scheme approval:
–Substation
–Cable route (open cut and or cable tunnel)
• Detailed design development
• Legal considerations and approvals
• Supply chain appointment
• Delivery and commissioning phase
• Project completion and handover to Network
Operations
Progamme Key Milestones
From the substratum…constructing a
cable tunnel
Key facts about the variety of tunnels in London:
• London’s tunnel infrastructure dates back 150 years
• Some tunnels are subject to the Official Secrets Act
• The pace of development in London has resulted in
even more complex and deeper tunnel construction,
for example Crossrail
• The clay on which London sits makes it an ideal
substratum in which to construct tunnels
• Where practical UK Power Networks design our
tunnel routes to follow the main roads at ground level
(this is to reduce the number of consents required)
2011. UK Power Networks. All rights reserved
Typical cable tunnel route in central London (currently under construction)
O2 Arena
Existing Grid Supply Point
Existing substation
New substation (under construction)
Tower
Bridge
New cable
tunnel (under construction)
2011. UK Power Networks. All rights reserved
Key facts about the tunnel
River Thames
Existing GSP
Intermediate shaft
Total length of 6.5km with 2.85m diameter tunnel
Jubilee Line
• Tunnel boring machine is 30m long and weighs 50 tons
• 3x30m deep, 7.4m diameter shafts provide permanent access
• Machine burrows at a speed of 50m per week
• It will contain 23km of 132kV cables
• Miners reach the cutting face by train, taking around 25 mins
• Extra space in the tunnels for future cable capacity
• 6,000 concrete rings will line the interior of the tunnel
• 5,000 brackets installed to support the cables on the tunnel
walls
2011. UK Power Networks. All rights reserved
Some of the challenges….
Liverpool St train
station
Central line
Distance of
1.80M
Distance of
6.50M
2011. UK Power Networks. All rights reserved
TBM being lowered
down the shaft
Tunnel under
construction
Breakthrough
at a shaft
View from the
front of the TBM
Tunnel extension being created
inside an existing substation
Typical cable tunnel fit out with
steel brackets
Construction stage photographs
To the substation – constructing a
central London primary substation
Typical construction of a central London primary substation:
• Two to three storey basements connected to tunnel
shaft creating confined space challenges.
• Reduced footprint to incorporate the above ground
two storey building with mezzanine floors.
• Brown field development or incorporated into a
‘developers’ commercial high rise.
• Piled foundations, steel structures with cladding or
traditional brick finish.
• Stakeholder influence, heritage sites, customer
requirements.
To the substation – constructing a
central London primary substation
Typical assets being installed:
• 3x132/11/11kV 66MVA transformers complete with
cooling system
• 12 -15 no. sections of 132kV Gas Insulated
Switchgear
• 50 – 80 no. panels of 11kV switchgear
• Kilometres of 11kV and 132kV cable
• Batteries and telecontrols systems
• Secondary network distribution transformers
2011. UK Power Networks. All rights reserved
Some history to the sites:
• Some substations are built on former power
stations, with some dating back to the 1900’s
and other on more prominent sites such as
Bankside (Tate Modern Gallery)
• The network has to be able to cope with the
increasing demands and changing skyline of
London
London in the 1900’s
London one hundred years later
2011. UK Power Networks. All rights reserved
The challenges of working in London….
• In 2013 over seven consecutive weekends the UK
Power Networks Capital Programme team delivered
7x 132kV transformers into central London.
• This required numerous consent and co-ordination
with Transport for London, Thameslink, borough
councils and the Police.
• The following short video provides a brief insight into
the construction of some of our substations,
including delivery of the transformers through central
London.
2011. UK Power Networks. All rights reserved
What next for London’s electrical network?
• Identifying growth hotspots and areas of existing network that
require strategic infrastructure investment.
• Working with key stakeholders to consider the potential for
decentralised energy systems to reduce electricity distribution
infrastructure costs.
• Continued innovation both in technology and collaboration with
the supply chain and our customers.
• Increasing shared land use with prominent developers in key
central locations.
• Continuation of stay safe culture to achieve a target of zero
harm.
• To be recognised as setting the standard for construction of
major city electrical infrastructure.
2011. UK Power Networks. All rights reserved
And why do they say London is different?
The size of the investment and
the outputs achieved is
equivalent to delivering the
primary network required for
London 2012 Olympics every
year!