FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS CASSIE B. STINSON Partner, ANDREWS KURTH LLP

FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

  • Upload
    jacqui

  • View
    31

  • Download
    0

Embed Size (px)

DESCRIPTION

FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS. CASSIE B. STINSON Partner, ANDREWS KURTH LLP. BASIC CONCEPTS. A. Acquisition Concepts 1. Standard Approach Survey & Title Appraisal Environmental Phase 1 Make Offers Condemnation. - PowerPoint PPT Presentation

Citation preview

Page 1: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

FROM DIRT TO DELIVERY:

ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

CASSIE B. STINSONPartner,

ANDREWS KURTH LLP

Page 2: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

2

I. BASIC CONCEPTS

A. Acquisition Concepts

1. Standard Approach– Survey & Title

– Appraisal

– Environmental Phase 1

– Make Offers

– Condemnation

Page 3: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

3

2. Major Objectives– Project Schedule

– Project Costs

Page 4: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

4

1. Environmental Site Assessments (ESAs)• ESA Phase I: non-invasive; identifies Recognized

Environmental Concerns (RECs)

• ESA Phase 2: involves sampling; identifies Chemicals of Concern (COCs)

• ESA Phase 3: more tests to delineate extent of COCs; generate Environmental Cost Estimate (ECE)

B. Environmental Concepts

Page 5: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

5

2. Remediation Standards• TRRP—residential• TRRP—commercial/industrial• UST rules• Groundwater

― MSD― PMZ― Pump and Treat

Page 6: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

6

C. Appraisal Considerations for Contaminated Property

Contaminant constituents: • COCs (Chemicals of Concern)

• Pathways of exposure

• Institutional controls

• Remediation standards

• ECE (Environmental Cost Estimate)

1. USPAP AO-9 and Env’l Terms:

Contamination conveyance:

Limitations on use:

Highest and best use:Cost and timing ofsite remediation plan:

Page 7: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

7

2. Appraisals Are “Professional Opinions”

Page 8: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

8

II. SOURCES OF CONTAMINATION

A. Leaking Petroleum Storage Tanks (LPSTs)

Page 9: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

9

Results of LPST

Page 10: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

10

Cessation of Operations Essential During Remediation

Page 11: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

11

B. Chlorinated Solvent Leaks

Page 12: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

12

Pump and Treat (Just Shoot Me Now!)

Page 13: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

13

A. Modified Takes

• Requires input and approval from Project engineering group

• Must use modified take consistently for entire Project

III. ADVANCED CONCEPTS

Page 14: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

14

• Air rights (e.g., minimum elevation = 24 ft.)

• Upward limitation to surface rights (e.g., max. elevation = 24 ft.)

• Surface level (at grade? sea level?)

• Downward limitation of surface rights (e.g., max. depth = 10 ft.)

• Subsurface rights (e.g., minimum depth = 10 ft.)

pipe

gunk

1. 3D Easements—A Slice of the Vertical Column of Property

Page 15: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

15

2. Bisected and Excluded Improvements• describe specifically• pay for fuel system components, but

don’t title 3. Get a Temporary Easement on

remainder• area needed• time needed

Page 16: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

16

Ofc &

C-Store

PumpIsland

Pump IslandTanks

Partial Take at Gas Station

Sign

Page 17: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

17

1. Identify Impaired Property EarlyCurrent uses having RECs:

• Gas stations (currently operating, abandoned)

• Small industrial: auto repair, machine shop, paint shop, battery shop, car wash

• Dry cleaners

• Former rail yards

• Landfills

• Old improvements (pre-1978): friable asbestos, lead

B. Plan Ahead on Impaired Property

Page 18: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

18

2. Coordinate Team Work

Environmental:

• Order ESA Ph. 1 and 2 at same time

• Define RECs asap and inform Appraiser

Appraiser:

• Plan for initial appraisal “as if clean” and supplemental appraisal “as is”

• Define Highest and Best Use asap and inform Environmental

Tip: Schedule early site visit with FULL Team

Page 19: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

19

1. No such thing as a “standard” contaminated property – every case is unique!

C. Standard Documents Don’t Work for Non-Standard Property

Page 20: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

20

2. Use Your Documents as Tools

• You can negotiate special terms in voluntary acquisitions that are not available in eminent domain

• If it’s not in writing, you don’t have a deal• Get legal help on non-standard docs

Page 21: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

21

• Bisected or excluded improvements (don’t forget the TCE!)

• Environmental escrow agreement

• Seller’s post-closing obligations

3. Special Provisions in Offers and Purchase Agreements

Page 22: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

22

4. Deed (Fee Simple)

Standard language:

The tract or parcel of land, together with all improvements situated thereon, ….

Special Provisions:

• Include bisected improvements

• Exclude title to certain improvements

Page 23: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

23

Standard language:“... a strip of land, 20 feet wide, more particularly described in Exhibit A, …”

Special provision:3D Easement

5. Grant of Easement

Page 24: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

24

YES:

• Fee simple• Permanent easement• Temporary easement• Improvements in take

area• Bisected improvements

NO:

• Escrow agreements

• Env’l Right of entry

• Post-closing Seller obligations (duty to interrupt operations)

D. Condemnation Concepts

1. Acquire Only “Interests in Real Property”

Page 25: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

25

2. Consistency: special provisions in thefinal offer must be reflected in pleadings:

• right to demolish certain improvements but not take title

• bisected improvements outside “take area”

• TCE (temporary construction easement)

Page 26: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

26

3. “Woodshed” the witnesses before the hearing:

• Appraiser

• Environmental Consultant

• Right of Way Agent

Page 27: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

27

IV. CLEAN PROPERTY – BUT ENVIRONMENTALLY IMPAIRED

Page 28: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

28

• FEDERAL: — Section 4(f), NEPA— US Fish & Wildlife— US Army Corps of Engineers

• STATE— Chapter 26, Texas Parks & Wildlife Code

• COMMON LAW RE REAL PROPERTY RIGHTS:— Restrictions and reversionary rights— Park amenities

A. Laws Protecting Parks, Open Space, Bugs and Bogs

Page 29: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

29

B. Federal Test: de Minimus Impact

Page 30: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

30

• No feasible alternative

• Locally preferred alternative

• Fun with public hearings –NOT!

C. State Law Tests

Page 31: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

31

• Loss of property tax exemption

• Restrictive covenants

• Reversionary rights

D. Private/Real Property Law Issues

Page 32: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

32

Enforcement only:• Injunction to prohibit

violation: Right to enforce restrictions is a property right

• Inverse condemnation claim: damages for loss of value of benefited property

Reversionary rights: • Acquire park interest from

public entity (appraise as park, no income potential)

• Acquire reversionary rights from donor’s heirs (appraise at highest and best use other than park, but subject to current right to use as park)

2. Deed Restrictions for Park Use Only

Page 33: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

33

3. Reversionary Rights can be scary: If the donor died 100 years ago, who and where are the heirs now?

Page 34: FROM DIRT TO DELIVERY: ENVIRONMENTAL AND CONDEMNATION PITFALLS IN CORRIDOR PROJECTS

34

Cassie B. Stinson

Andrews Kurth LLP600 Travis St., Ste. 4200Houston, TX 77002

[email protected]

Thank you