FROM CREATIVE POWER TO POWER GENERATION Corporate Presentation Moscow, 2018
2 FROM CREATIVE POWER TO POWER GENERATION
Группа «Интер РАО»
40 TPPs (including 6 mini TPPs), 12 HPPs (including 7 mini HPPs), 2 wind farms
32.7 GW of installed capacity
134,8 TWh generated*
Operating in more than 15 countries
4,3 GW of installed capacity
5 thousand km of power lines
9 electricity retailers
15.9% share of the Russian retail market
182,6 TWh sold*
25 new generation and rehabilitation projects
7.4 GW combined capacity of all facilities
Consolidated value of current projects: 188.5 billion RUB
Leading Russian electricity exporter with 97% market share.
16,7 TWh exported*
6,2 TWh imported*
GENERATION
SALES
TRADING
INTERNATIONAL ASSETS
ENGINEERING
2017 revenue (IFRS)
THE LARGEST ENERGY HOLDING IN RUSSIA FOCUSED ON ELECTRICITY AND HEAT GENERATION AND SALES, ELECTRICITY EXPORT AND IMPORT, AND ENGINEERING SERVICES
50 825 people
917 billion RUB total staff*
* As of 2017
INTER RAO GROUP
3 FROM CREATIVE POWER TO POWER GENERATION
ENGINEERING ASSETS OF INTER RAO GROUP
A leading engineering service provider focused on construction and rehabilitation of energy facilities in Russia and worldwide • 21 successful new construction projects with 6,4 GW of combined capacity • Current portfolio includes 1 GW of generation capacity spread across 4 projects • A team of 500 highly skilled professionals
100% affiliate
Sales of energy equipment and services in the international markets
• 9 active contracts for delivery of energy equipment, spare parts
and services for heat and hydro power projects • Large network of representative offices abroad • Key markets: Latin America, Africa, Middle East & Southeast
Asia
Manufactures 6FA gas turbines in Russia • Joint venture of JSC Inter RAO, General Electric and Rostec • Established in 2011 • Designed to manufacture 14 gas turbines per year, with potential
upgrades up to 20 gas turbines per year • Manufacturing site: Rybinsk, Yaroslavl Oblast
100% 25%
4 FROM CREATIVE POWER TO POWER GENERATION
INTER RAO – ENGINEERING IN FIGURES AND FACTS
Participation in the implementation of the Program for the Construction of Olympic Venues and the Development of the City of Sochi as a Mountain Climatic Resort: Construction of the Dzhubginskaya TPP
6,4 GW of implemented generating capacities
21 Completed projects
4 projects The size of current portfolio of new construction and modernization projects
1 GW of generating capacities to be implemented
7 branches in different regions of the Russian Federation
Experience of implemented projects based on the equipment of major world and home producers such as Siemens, GE Energy, Alstom Power, ABB, Power Machines, EMAlliance, etc.
The presence of its own project unit
Participation in the implementation of the Program for the Construction of New Generating Capacities for the Purpose of Ensuring the Energy Security of the Kaliningrad Region
5 FROM CREATIVE POWER TO POWER GENERATION
OUR VALUES
Inter RAO – Engineering pays particular attention to assurance of sustainable development and safety of production processes. The Company’s overriding priority is an assurance of its activity compliance with the best international practices in the sphere of the quality management, ecological safety and labor protection.
The Company takes full responsibility for carrying out its activities along the whole process chain – from designing a specific facility and ordering the maximum efficient and safe equipment to strict supervision of construction and installation and construction waste disposal.
Inter RAO – Engineering considers it mandatory that all production processes comply with international requirements and it is currently certified according to the following standards: OHSAS 18001:2007 — Occupational health and safety management systems, ISO 14001:2015 — Environmental management systems, ISO 9001:2015 — Quality management systems
The company is a member of the SRO - Association "Urban Planning and Design Association" and the Association "Association of General Contractors in Construction", and has the necessary permits for works that affect the safety of capital construction facilities.
01 02
03 04
6 FROM CREATIVE POWER TO POWER GENERATION
OUR SERVICES
BOT/BOO project organization
Sales of core and auxiliary equipment
Decommissioning of obsolete equipment
Start-up and adjustment of new facilities
Integrated offer based on 6FA gas
turbines
Owner's Engineering
Design of energy facilities
EPC/EPCM project management
7 FROM CREATIVE POWER TO POWER GENERATION
INTEGRATED SOLUTIONS BASED ON 6FA TURBINES
• full cycle engineering – from development of design documentation to project implementation on a turnkey basis • use of flexible financing schemes in project implementation • standard design solutions to cut costs and time required for design, construction and servicing of power generation facilities; • full delivery list of main and auxiliary equipment on optimum commercial conditions • equipment integration into a unified process diagram with a common guarantee of capacity and efficiency of the entire facility • long-term servicing of power island equipment, which includes development of a comprehensive service schedule, spare parts delivery,
maintenance, repair, and reconstruction
Inter RAO – Engineering is a supplier of integrated solutions based on the 6FA turbines, which involve the full range of work and services for all life cycle stages of a power generation facility:
main configurations of thermal power plants.
Inter RAO – Engineering experts have developed standard engineering solutions for 28
8 FROM CREATIVE POWER TO POWER GENERATION
1. Sochinskaya, 80 MW
2. Kaliningradkaya SDPP-2, 450 MW
3. Urengoyskaya SDPP-2, 491 MW
4. Kharanorskaya SDPP-2, 225 MW
5. Ivanovskiye CPP, 325 MW
6. Tomskaya TPP-1, 15 MW
7. Omskaya TPP-3, 85 MW
8. Gusinoozyorskaya SDPP, 210 MW
9. Dzhubginskaya TPP, 180 MW
10. Cherepetskaya SDPP, 2*225 MW
11. Yuzhnouralskaya SDPP-2, 2*400 MW
12. Nizhnevartovskaya SDPP, 413 MW
13. Verhhnetagilskaya SDPP, 447 MW
14. Permskaya SDPP, 861 MW
15. Zatonskaya TPP, 440 MW
16. Pregolskaya TPP, 456 MW
17. Talakhovskaya TPP, 156 MW
18. Mayakovskaya TPP, 156 MW
19. Primorskaya TPP, 195 MW
RUSSIAN PROJECTS
PROJECT GEOGRAPHY
УКРАИНА
Moscow RUSSIAN
FEDERATION
08
06 07
12
03
11
13 14
05 10
16,19
09 01
15
02,17,18
04
Projects in progress with combined capacity of 1 GW 4
Completed projects with combined capacity of 6,4 GW 21
Projects in progress
Completed projects
Tajikistan
20
RUSSIAN FEDERATION
Afghanistan 23 21-22
Bangladesh
20. Tajikistan Sangtuda HPP-1, 670 MW 21. Bangladesh Ghorasal TPP, 210 MW
PROJECTS ABROAD
22. Bangladesh Siddhirganj TPP, 210 MW 23. Afghanistan Naglu HPP, 2*25 MW
9 FROM CREATIVE POWER TO POWER GENERATION
PARTNERSHIP BENEFITS
Long-term partnerships with the leading equipment manufacturers, project managers and contractors
Comprehensive network of branches and sales offices
In-house design center
Proven project financing options
Optimized project timelines and costs
Standardization programs for projects and technology solutions
OUR PROJECTS
11 FROM CREATIVE POWER TO POWER GENERATION
Construction of power plants on the basis of two gas turbines with power capacity of 156 MW each
Key components : Two gas turbines PG6111 (FA)
manufactured by LLC Russian Gas Turbines
Mayakovskaya TPP, Gusev
Construction of the power plant consisting of three steam power plants with total capacity of 195 MW
Expected project completion: 2020
Primorskaya TPP , Svetliy
Key components : Three steam turbines UTZ K-65-12,8
manufactured by CJSC Ural Turbine Plant; Three turbine-generators TF-65-2UHL4,
manufactured by CJSC ELSIB Two steam boilers E-240-13,8-560KT,
manufactured by JSC Podolsk Machine-Building Plant
Construction of power plants on the basis of two gas turbines with power capacity of 156 MW each
Key components : Two gas turbines PG6111 (FA)
manufactured by LLC Russian Gas Turbines
Talakhovskaya TPP , Sovetsk
Construction of power plants on the basis of four combined cycle with total capacity of 456 MW
Expected project completion: 2019
Pregolskaya TPP , Kaliningrad
Key components : Four gas turbines PG6111 (FA) manufactured
by LLC Russian Gas Turbines Four generators TF-90G-2UZ manufactured
by CJSC ELSIB Four steam turbines K-38-8,0 manufactured
by JSC Power Machines; Four heat recovery steam generators PK-116
manufactured by JSC Podolsk Machine-Building Plant
CONSTRUCTION OF GENERATING CAPACITY IN KALININGRAD REGION
Construction of four power plants with a total capacity of 1 GW is the largest investment project in the Kaliningrad region. The projects are implemented in accordance with the approved Resolution of the Government of the Russian Federation of October 20, 2015 No. 1116 and Order of the Government of the Russian Federation of October 20, 2015 No. 2098-p.
New power sources will ensure the energy security of the Kaliningrad region and make its energy system more maneuverable.
Completed in 2018 Completed in 2018
12 FROM CREATIVE POWER TO POWER GENERATION
Construction of 440 MW thermal power plant
Completed in 2018
Key components: Two Power Machines GTE-160 gas turbines; Two Kaluga Turbine Works Т-60/73 steam turbines; • Two EMAlliance Е-220 boilers.
Russian Federation Zatonskaya TPP
Оverhaul of Unit, 210 MW in capacity
Expected project completion: 2018
Bangladesh Siddhirganj TPP
Key components: • Power Machines K-210-130-8 steam turbine; • TKZ (Power Machines Group) TGME-
206/BCO boiler; • State Enterprise Electrotyazmash (Ukraine)
generator TGV-200MTZ.
Rehabilitation of Unit No.1 and overhaul of Unit No.3, capacity of each Unit is 25 MW
Expected project completion: 2018
Afghanistan Naglu HPP
Key components: • Four Turboatom РО 75-В-225 water
turbines; • Four Energomash (Ekaterinburg)-
Uralelectrotyazhmash VGS 525/110-24 generators.
WORK IN PROGRESS
13 FROM CREATIVE POWER TO POWER GENERATION
Construction of 861 MW combined cycle Power Generation Unit #4
Completed in 2017
Key components: • 283 MW Siemens SST5-5000 steam
turbine; • Two 289 MW Siemens SGT5-4000F gas
turbines; • Two EMAlliance heat recovery boilers
Russian Federation Permskaya SDPP
Construction of 447 MW combined cycle Power Generation Unit #12
Completed in 2017
Russian Federation Verkhnetagilskaya
SDPP
Key components: Siemens SGT5-4000F gas turbine with Sgen5-1200A generator; • Power Machines K-130 steam turbine with
TZFP-160 generator.
Construction of two 225 MW Pulverized Coal Boilers, #8 and #9
Completed in 2014-2015
Key components: • Two Power Machines K-225-12.8-4P
steam turbines; • Two EMAlliance Еp-630-13.8-565/570KТ
boilers.
Russian Federation Cherepetskaya
SDPP
Construction of power plants on the basis of two combined cycle power capacity of 400 MW each
Completed in 2014
Russian Federation Yuzhnouralskaya
SDPP-2
Key components: • Two Siemens SGT-4000F gas turbines; • Two Siemens SSТ-3000 condenser turbines; • Two Atomenergomash P-140 heat recovery
steam boilers.
COMPLETED PROJECTS
14 FROM CREATIVE POWER TO POWER GENERATION
Construction of 413 MW combined cycle Power Generation Unit #3.1
Completed in 2014
Key components: • General Electric PG9351(FA) gas turbine
with 324H 50 Hz generator; • General Electric D12 steam turbine with
9А5 generator; • Atomenergomash P-143 heat recovery
steam boiler.
Russian Federation Nizhnevartovskaya
SDPP
Construction of 180 MW thermal power plant
Completed in 2013
Russian Federation Dzhubginskaya
TPP
Key components: • Two GE ENERGY LMS100 gas turbines.
Rehabilitation of 210 MW Pulverized Coal Boiler #4
Completed in 2013
Key components: • Steam turbine of К-210-130-3 type,
manufactured by JSC Power Machines; • Boiler БКЗ-640-140 ПТ-1, manufactured
by JSC Sibenergomash.
Russian Federation Gusinoozyorskaya
SDPP
Construction of an 85 MW combined cycle Power Generation Unit
Completed in 2013
Russian Federation Omskaya TPP-3
Key components: • Two GE ENERGY LM2500+G4 DLE gas
turbines; • Two EMAlliance Е-38.3/8.1-5.5/0.63 heat
recovery boilers; • Power Machines-KTZ Т-16.5/22-5.5/0.08
steam turbine.
COMPLETED PROJECTS
15 FROM CREATIVE POWER TO POWER GENERATION
Construction of a 15 MW power generation unit and a heat recovery boiler
Completed in 2012
Key components: • Turbomach TITAN-130 gas turbine; • ZiO Podolsk KUV 23.5/150 boiler.
Russian Federation Tomskaya TPP-1
Construction of 225 MW Pulverized Coal Boiler #3
Completed in 2012
Russian Federation Kharanorskaya SDPP
Key components: • Power Machines K-225-12.8-3P steam
turbine; • EMAlliance Ep-630-13.8 565BT (TPE-216M)
boiler.
Construction of a 460 MW combined cycle Power Generation Unit
Completed in 2012
Key components: • Two Power Machines GTE-160 gas
turbines; • Heat recovery steam generators (2х Е-
229/52-8/0,6-507/227), manufactured by JSC EMAlliance under the license of Nooter/Eriksen;
• 160 MW Power Machines K-160-7.5 steam turbine.
Russian Federation Urengoyskaya SDPP
Construction of 325 MW combined cycle Power Generation Unit #2
Completed in 2012
Russian Federation Ivanovskiye CPP
Key components: • NPO Saturn GTD-110 gas turbine; • Podolski Machine-Building Plant OJSC Е-
148/35-6.7/0.6-493/229 heat recovery boiler;
• Power Machines K-110-6.5 110 MW steam turbine.
COMPLETED PROJECTS
16 FROM CREATIVE POWER TO POWER GENERATION
Construction of a 80 MW combined cycle Power Generation Unit #3
Completed in 2009
Key components: • Siemens GT10C gas turbine; • Podolski Machine-Building Plant OJSC P-
103 dual pressure heat recovery boiler; • Power Machines-KTZ T-10/11-5.2 steam
turbine.
Russian Federation Sochinskaya TPP
COMPLETED PROJECTS
Turnkey construction of a 670 MW hydro project
Units 1, 2 and 3 were launched in 2008; unit 4 was launched in 2009
Key components: • Four Power Machines РО 75-В-600 water
turbines; • Four Power Machines СВ 1260/182-60
UHL4 generators; • Four ABB HECS-80S generator circuit
breakers; • Four AREVA OFAF-200000/230 generator
transformers.
Tajikistan Sangtuda HPP-1
Construction of a 450 MW combined cycle Power Generation Unit #2
Completed in 2011
Key components: • Two gas turbines GTE-160 (Siemens
SGT5-2000E(3) type), manufactured by JSC Power Machines;
• Two Podolski Machine-Building Plant OJSC PK63 heat recovery boilers;
• Power Machines K-150-7.7 steam turbine.
Russian Federation Kaliningradskaya
CHPP-2
Gorashal TPP
Completed in 2017
Оverhaul of Unit No. 5, 210 MW in capacity
Key components: • Power Machines K-210-130-8
steam turbine; • TKZ (Power Machines
Group) TGME-206 boiler; • State Enterprise
Electrotyazmash (Ukraine) generator TGV-200MTZ.