Upload
lamliem
View
218
Download
1
Embed Size (px)
Citation preview
Frequency Keeping Control Trial
Technical Review Report
June 2015
Version Date Change
1.0 29/05/15 Draft for system operator review
Date
Prepared By: Mike Phethean
Darren Pat
Nabil Adam
John Bartley
Reviewed By: Dan Twigg 05/06/15
Andrew Gard 05/06/15
IMPORTANT
Disclaimer
The information in this document is provided in good-faith and represents the opinion of Transpower
New Zealand Limited, as the System Operator, at the date of publication. Transpower New Zealand
Limited does not make any representations, warranties or undertakings either express or implied, about
the accuracy or the completeness of the information provided. The act of making the information
available does not constitute any representation, warranty or undertaking, either express or implied.
This document does not, and is not intended to; create any legal obligation or duty on Transpower New
Zealand Limited. To the extent permitted by law, no liability (whether in negligence or other tort, by
contract, under statute or in equity) is accepted by Transpower New Zealand Limited by reason of, or in
connection with, any statement made in this document or by any actual or purported reliance on it by
any party. Transpower New Zealand Limited reserves all rights, in its absolute discretion, to alter any of
the information provided in this document.
Copyright
The concepts and information contained in this document are the property of Transpower New Zealand
Limited. Reproduction of this document in whole or in part without the written permission of Transpower
New Zealand.
Contact Details
Address: Transpower New Zealand Ltd
96 The Terrace
PO Box 1021
Wellington
New Zealand
Telephone: +64 4 495 7000
Fax: +64 4 498 2671
Email: [email protected]
Website: http://www.systemoperator.co.nz
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
3
Contents Abbreviations ......................................................................................................................................... 5 Preface .................................................................................................................................................... 6 1. Executive Summary .................................................................................................................. 7 2. Introduction ................................................................................................................................ 8
Frequency Keeping Control ..................................................................................................... 8 2.1
The purpose of the FKC Trial .................................................................................................. 8 2.2
The purpose of this report ....................................................................................................... 8 2.3
The structure of this report ...................................................................................................... 9 2.4
3. Background .............................................................................................................................. 10 Normal frequency Requirements ........................................................................................... 10 3.1
Controls which vary HVDC transfer in response to frequency .............................................. 10 3.2
System dispatch .................................................................................................................... 11 3.3
Multiple frequency keeping .................................................................................................... 11 3.4
Round power control ............................................................................................................. 12 3.5
HVDC under frequency management ................................................................................... 12 3.6
Modulation risk ...................................................................................................................... 13 3.7
Reserve and frequency management programme ................................................................ 14 3.8
Security Tools Implementation for New HVDC Controls Project........................................... 14 3.9
4. Pre-FKC Trial findings ............................................................................................................. 16 Interaction of MFK and generator governors ......................................................................... 16 4.1
New purpose of MFK with FKC enabled ............................................................................... 16 4.2
Change to method of dispatch .............................................................................................. 17 4.3
Round Power under frequency risk management ................................................................. 17 4.4
Maximum HVDC transfer and FKC ....................................................................................... 18 4.5
FKC Trial start conditions ...................................................................................................... 18 4.6
Temporary manual operational procedures .......................................................................... 18 4.7
FKC Trial exit conditions ........................................................................................................ 19 4.8
Summary of possible modes of operation ............................................................................. 19 4.9
5. Benefits of FKC operation ...................................................................................................... 20 Reduced frequency keeping costs ........................................................................................ 20 5.1
Tighter control of normal frequency ....................................................................................... 21 5.2
Enables National Market for Instantaneous Reserves .......................................................... 21 5.3
Higher market capacity during energy shortfalls ................................................................... 22 5.4
6. FKC Trial technical issues with market impact .................................................................... 25 Increase in generator governor action ................................................................................... 25 6.1
Market cost of Modulation Risk ............................................................................................. 26 6.2
Appropriate quantities of frequency keeping ......................................................................... 27 6.3
Effectiveness of the MFK compliance calculation ................................................................. 29 6.4
Active power and reserve compliance with dispatch ............................................................. 30 6.5
7. FKC Trial Operational Issues ................................................................................................. 33 Automatic option no longer available for System dispatch .................................................... 33 7.1
Operational complexity of starting and stopping FKC operation ........................................... 33 7.2
Impact of HVDC Reclose Blocks on FKC operation ............................................................. 34 7.3
FKC exit conditions reassessed ............................................................................................ 34 7.4
8. Technical issues from the FKC trial ...................................................................................... 36 Frequency excursions during the trial ................................................................................... 36 8.1
Positive time error trend ........................................................................................................ 36 8.2
Time error separation between the North and South Islands................................................ 38 8.3
Causes of normal frequency band variations ........................................................................ 40 8.4
Back up frequency keeping ................................................................................................... 42 8.5
FKC performance during fast winter load pick ups ............................................................... 43 8.6
What is an appropriate normal frequency standard? ............................................................ 43 8.7
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
4
9. Future developments with FKC operation ............................................................................ 44 Reduction in the modulation risk ........................................................................................... 44 9.1
Quantity of Frequency Keeping purchased ........................................................................... 45 9.2
Automatic Governor Control .................................................................................................. 45 9.3
System operator dispatch strategy ........................................................................................ 46 9.4
10. Conclusion & recommendations ........................................................................................... 47 Recommendations for the Authority ...................................................................................... 47 10.1
Recommendations for the SO ............................................................................................... 48 10.2
Appendix A – Frequency analysis ..................................................................................................... 49 Appendix B – Generator off-dispatch data ....................................................................................... 56
North Island – South Island Comparison ........................................................................................... 63 Calculation diagram ........................................................................................................................... 66
Appendix C – frequency excursion details ....................................................................................... 67 Appendix D – Positive time error trend ............................................................................................. 73 Appendix E - Using HVDC frequency offset from HMI to minimise time error divergence ......... 79
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
5
ABBREVIATIONS
AGC – Automatic Governor Control
Authority - Electricity Authority
CAN – Customer Advice Notice
CE – Contingent Event
DCRS – DC Risk subtractor
ECE – Extended Contingent Event
EIPC – Electricity Industry Participation Code
FKC – Frequency Keeping Control
FIR – Fast Instantaneous Reserve
FSC – Frequency Stabiliser Control
GEN – Grid Emergency Notice
HMI – Human machine interface
ICCP – inter control centre protocol
IPS – Island power supply
MFK – Multiple Frequency Keeping
MOI – Market operator interface
MR – Modulation risk
MW - Megawatts
NCC – National Co-ordination Centre
NI – North Island
NRM – National reserves market
PI – Plant information
PMU – Phased Measurement Unit
PPOs – Principal Performance Obligations
PSD – Pre-solve deviation
RCBs – Reclose blocks
RFM – Reserve and Frequency Management
RIER – Regulation instruction error ratio
RMT – Reserve Management Tool
RP – Round power
RTD - Real Time Dispatch
SCADA – System Control and Data Acquisition
SI – South Island
SIR – Sustained Instantaneous Reserve
SO – system operator
SPD – Scheduling Pricing and Dispatch
SRS – Spinning Reserve Sharing
STLF – Short term load forecast
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
6
PREFACE
This report provides a detailed account of the market, operational and technical
observations collected by the system operator during the recent FKC trial. Whilst some
background on the controls and market tools associated with the trial is provided, the
report is written primarily for readers already relatively familiar with these aspects of the
New Zealand electrical system.
The report makes recommendations, intended for consideration by the system operator
and the Electricity Authority, in respect of possible developments to enhance future
power system operations with FKC enabled. The recommendations are drawn from the
technical observations recorded during the trial and from feedback from market
participants. As these future developments are of wider interest this report is made
available to market participants.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
7
1. EXECUTIVE SUMMARY
A trial of an advanced operating mode of the HVDC link started in mid-October 2014 and
ran through to 31 March 2015. During this Frequency Keeping Control mode (FKC) trial
period operations were predominantly with reduced MFK frequency keeping bands.
During the trial tests were also conducted of different dispatch arrangements to ascertain
performance of FKC under a wide range of operating conditions. These included 0MW
MFK (no frequency keeper), and FKC with backup SFK (a single national frequency
keeper). These tests gave the system operator (SO) more confidence with FKC
operations. They also showed what could be achieved with further development of the
arrangements for frequency keeping to exploit this new technical capability of the HVDC.
Retaining FKC with reduced MFK frequency keeping bands following the trial will result in
a continuation of the immediate savings in total frequency keeping costs. If these
savings are sustained for the next year there will be a reduction of up to $25 million in
the cost of frequency keeping. The benefits are not just monetary; FKC provides
improvements to power system quality and security. It has been demonstrated there is
tighter overall management of frequency within the normal +-0.2Hz band with FKC
enabled. Similarly, FKC operation reduces the amount of generation required for
frequency keeping, releasing capacity that can, for instance, assist management of island
and national energy shortfall situations.
This report also details market, operational and technical issues identified with FKC
operation. Generally there has been an increase in generator governor action. This
action has effects on generator plant and operating regimes and also impacts energy and
reserve dispatch compliance. Operationally, FKC can be challenging with the current
market system tools. This was apparent during live line work on the HVDC conductors.
Technical issues relating to the interaction of managing system frequency and
maintaining time error were observed during the trial.
Importantly, the SO has found no adverse impact on its ability to meet the combination
of objectives for delivering a secure power system with the required power quality (the
PPOs) during FKC operations throughout the FKC trial period.
Whilst none of the identified issues prevent continued FKC operation this report includes
recommendations to mitigate their effects. The recommendations also suggest further
areas of study, testing and development for the both the system operator and the
Electricity Authority (Authority).
The SO will continue to work with the Authority and industry on development of
frequency keeping arrangements as part of the wider Reserves and Frequency
Management (RFM) development programme.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
8
2. INTRODUCTION
FREQUENCY KEEPING CONTROL 2.1
The controls upgrade delivered as part of Transpower’s HVDC Pole 3 project included a
control system with an operating mode known as Frequency Keeping Control (FKC). FKC
varies the transfer on the HVDC to maintain the same system frequency in both islands.
It is an enabler for a potential national Frequency Keeping service to replace the use of
island based Frequency Keeping.
Introduction of this operating mode led to changes in power system operations and
methods of regulating system frequency.
System testing with FKC enabled (during and post HVDC commissioning) resolved some
initial issues discovered while operating with FKC, though uncertainties still existed. 1
The uncertainties were focused on:
the ability of the proposed method for FKC operation to maintain stable operation
at times of very light system load
the statistical significance of trends observed during the system testing. System
variations can mask trends even on data collected over a full day of operation
whether system testing had revealed all the technical and operational issues that
may exist when operating with FKC enabled.
FKC was placed into operation for a trial period from the 16th October 2014 through to
the 31st March 2015 to evaluate these issues further.
THE PURPOSE OF THE FKC TRIAL 2.2
The purpose of the FKC trial was to operate with FKC enabled for a longer duration so as
to:
collect additional data through a wider range of system conditions, allowing a full
assessment of FKC modulation risk and frequency keeping bands to be completed
allow the SO and the electricity industry an opportunity to gain operational
experience with FKC enabled.
THE PURPOSE OF THIS REPORT 2.3
This report:
provides an introduction to the key system aspects which influence or are
influenced by FKC
provides a summary of the findings from the pre-trial testing with FKC enabled
details the methods of operation with FKC enabled
provides a high level analysis of some market benefits of operating with FKC
enabled
identifies issues operating with FKC enabled and, where possible, make
recommendations to mitigate these issues
1 The FKC control had undergone initial testing, see pre-trial details in section 4
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
9
recommends how continued operation with FKC enabled can be enhanced
discusses future changes which may occur with FKC enabled operations.
THE STRUCTURE OF THIS REPORT 2.4
This report is divided into a number of sections as follows:
Section Section
No.
Purpose
Background 3.0 An introduction to the components of the electricity
market and the technical controls relevant to this report.
Pre-FKC trial findings 4.0 A summary of findings of the tests and investigations
carried out before the FKC trial began.
Benefits of FKC
operation
5.0 A description of benefits which have come from FKC
operation.
FKC technical issues
with market impact
6.0 A description of issues for market participants and for the
market tools from FKC being enabled.
FKC Trial operational
issues
7.0 A description of issues for system coordinators in
operating with FKC being enabled.
Technical issues from
the FKC Trial
8.0 A description of the engineering issues from FKC being
enabled.
Future development
with FKC operation
9.0 A description of possible developments associated with
FKC which may occur in the near future. The
developments may be market based, technical or
operational.
Recommendations
and conclusions
10.0 Recommendations made in sections 6 – 9 of this report
are denoted by a box. A summary of all recommendations
is in section 10.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
10
3. BACKGROUND
NORMAL FREQUENCY REQUIREMENTS 3.1
The EIPC requires normal system frequency be maintained in a band from 49.8 Hz to
50.2 Hz.
Under the EIPC part 7.2 the principal performance obligations of the system operator
are:-
b(i) … to act as a reasonable and prudent system operator with the objective of
maintaining frequency in the normal band…
(v) to act as a reasonable and prudent system operator with the objective of ensuring
that frequency time error is not greater than 5 seconds of New Zealand standard time;
also mandates that frequency time error is maintained between +/- 5 seconds.
To maintain the frequency within the normal band (within +/- 0.2Hz of the nominal
50Hz) the system operator purchases frequency keeping services.
CONTROLS WHICH VARY HVDC TRANSFER IN RESPONSE TO 3.2
FREQUENCY
The controls upgrade delivered by Transpower’s HVDC Pole 3 project included two modes
of frequency control:
1) Frequency Stabiliser Control (FSC) and Spinning Reserve Sharing (SRS) – that
operated together and were as part of the HVDC frequency control used pre
upgrade.
2) Frequency Keeping Control (FKC) – A new separate enhanced operating mode
that includes some of the functionality of FSC/SRS developed for managing
national frequency.
These control modes both measure frequency at Haywards and Benmore and use the
difference to calculate changes in the HVDC transfer.
The combined operation of FSC/SRS varies HVDC power transfer to assist in supporting
frequency when there is a difference in frequency between the two islands. FSC/SRS is
designed to change HVDC power transfer for about 30 seconds before the power transfer
returns to its dispatch value.
SRS has a slow but permanent reaction to frequency changes in either one or both
islands. SRS gradually increases the amount it changes the HVDC power transfer, as the
frequency stabiliser dies away, until either the frequency in both islands is restored to
within the range of 49.8 Hz to 50.2 Hz or the output of the controller reaches its limit.
FKC continuously varies the HVDC power transfer to maintain the same frequency in the
North and South islands. An implication of FKC’s continuous action is more variation in
the HVDC transfer than FSC/SRS.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
11
SYSTEM DISPATCH 3.3
One of the core duties of NCC system co-ordinators is to dispatch active power to
generators to balance the load on the power system.
Two key performance measures of this active power and load balancing are system
frequency and time error.
A high system frequency (greater than 50 Hz) indicates more generation is dispatched
than load. A low system frequency (less than 50 Hz) indicates less generation is
dispatched than load. Time error is a cumulative summation of the deviation of
frequency from 50 Hz.
System co-ordinators formulate dispatch instructions by taking into account:
system frequency and time error
current load
future industrial and residential load movements
the quantity of active power the frequency keeper has varied to maintain system
frequency and time error
generator compliance with previous dispatch instructions.
MULTIPLE FREQUENCY KEEPING 3.4
The Multiple Frequency Keeping (MFK) control system was implemented in the North
Island in 2013 and in the South Island in 2014. The purpose of MFK is to reduce
frequency keeping costs by allowing multiple parties to simultaneously contribute to
managing frequency and time error.
MFK control is based on the Automatic Governor Control (AGC) control philosophy. A
central controller calculates the variation in the power supply required to maintain
frequency and time error within the mandated targets. A central controller ensures
providers contribute equally and stably to frequency keeping.
Generators tender capacity offers into the market to provide the MFK service. The
market system selects the most economical generators to provide MFK services. These
generators then provide the required quantity of frequency keeping.
3.4.1
The MFK controller communicates the variation in power supply to the local generation
station control module. The station control module then sends a signal to the generator
governors. This communication path differs to an AGC system which sends the signal
directly from the MFK controller to the generator governor.
The MFK communication paths cause a significant time delay in reactions to changes in
system frequency and time error (compared to an AGC system). This time delay
introduces latency into the reaction of MFK to frequency variations.
3.4.2
The speed at which MFK can vary the power supply is limited to 0.4 MW / min for every 1
MW of MFK capacity purchased. This means that if 10 MW of capacity is dispatched to a
MFK generator, its power supply can be varied at a maximum of 4 MW / min.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
12
In an AGC system the governor can normally vary the power supply at a higher rate than
MFK.
3.4.3
To ensure the MFK controller provides a stable response to frequency, low gain factors
are applied to the error signal. More focus is given to the cumulative size of the error.
The latency of MFK to frequency changes and relatively slow speed of variation in power
supply require a highly damped control response.
ROUND POWER CONTROL 3.5
Round power (RP) control allows the HVDC to transit from north to south transfer and
vice versa almost seamlessly.
Prior to introduction of RP the HVDC could not be dispatched below 35 MW for transfer in
either direction as the HVDC convertor poles have a minimum transfer level of
approximately 35 MW.
RP allows the HVDC to be dispatched below this minimum by starting the second HVDC
convertor pole in the opposite direction to the HVDC convertor pole already in service.
The overall power transferred is then the transfer of one convertor pole minus the
transfer on the other convertor pole.
Another feature of RP is that it will automatically start a HVDC convertor pole to cover
the loss of transfer if the first HVDC convertor pole trips.
3.5.1
When in RP control there are three technical requirements relevant to modelling system
frequency risks:
the subsea cable must have residual current discharged for five minutes before
the convertor pole can be started in the opposite direction. This prevents a
convertor pole being immediately available to transfer power in the opposite
direction
when the poles are transferring in opposite directions and one HVDC convertor
pole trips the other convertor pole does not trip but stays connected at the
minimum transfer of 35 MW. The loss of supply to the island receiving the HVDC
transfer is therefore the dispatch plus 35 MW.
HVDC UNDER FREQUENCY MANAGEMENT 3.6
3.6.1
The system operator considers two event types as under frequency system risks:
Contingent Events (CE). Events where the impact, probability of occurrence and
estimated cost and benefits are considered to justify implementing policies to be
included into the scheduling and dispatch processes pre-event.
Extended Contingent Events (ECE). Events for which the impact, probability of
occurrence and estimated cost and benefits are not considered to justify the
controls required to totally avoid demand shedding and maintain the quality limits
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
13
defined for contingent events. For under frequency events demand shedding
includes Automatic Under Frequency Load Shedding (AUFLS).
3.6.2
The system operator has two HVDC under frequency risks:
1. HVDC CE risk. – The loss of one HVDC component. The HVDC component that is
usually the largest (critical) risk is the loss of a single HVDC convertor pole.
2. HVDC ECE risk – The loss of both HVDC convertor poles.
The HVDC is dispatched in terms of the power sent, as this is the value entered into the
HVDC controls. However the risk is to the island receiving the HVDC transfer if part or
all of the HVDC trips.
3.6.3
The DC risk subtractor (DCRS) is the maximum transfer value the HVDC can sustain for
15 minutes following the loss of the most critical HVDC component E.g. Pole, HVDC filter,
statcom etc.
For example, if the HVDC is fully available the loss of Pole 3 is the most critical
component. The remaining Pole 2 can send up to 560 MW for 15 minutes. In the
receiving island this will equate to 528 MW of received HVDC transfer. The risk subtractor
is therefore 528 MW.
3.6.4
The HVDC risk formulae are:
HVDC CE risk = HVDC received – DCRS
HVDC ECE risk = HVDC received.
MODULATION RISK 3.7
The system operator is required to provide sufficient under frequency reserve to cover
the loss of the HVDC.
When FKC is enabled it was noted the average difference between actual HVDC transfer
and the dispatched HVDC had increased compared to when only FSC/SRS control was in
operation.
This increase was to be expected as FKC fully matches the system frequencies between
the two islands whereas FSC/SRS only partially matches the frequencies.
This presented a risk to the way the system operator managed under frequency reserve
purchases. With FKC in operation, the actual magnitude of the loss of supply to the
system had a greater probability of being higher than the dispatched quantity.
To allow for the increase the system operator added a fixed quantity to the HVDC
reserve risk. This fixed quantity is called the Modulation Risk (MR). 2
The HVDC risk formula therefore becomes:
2 The loss of supply is now the dispatched HVDC transfer and the increase that FKC requires to control
frequency.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
14
HVDC CE risk = HVDC received – DCRS + MR
HVDC ECE risk = HVDC received + MR
Management of the MR value during the FKC trial was via manual processes using the
Market Operator Interface (MOI) HVDC display. This risk was modelled in both forward
looking schedules and the real time dispatch schedule.
RESERVE AND FREQUENCY MANAGEMENT PROGRAMME 3.8
The Reserves and Frequency Management (RFM) programme is a joint programme of
work between the SO and the Electricity Authority (Authority) to improve frequency
keeping and instantaneous reserve market arrangements given recent enhancements
available from the HVDC control system.
FKC is one of the key enhancements and its successful operation is critical to a number
of RFM projects.
The HVDC control enhancements enable the transfer of frequency keeping and reserves
between islands. This has culminated in a number of proposed capital projects.
The programme currently contains nine projects3 to contribute to this objective:
South Island MFK
RMT TSAT Implementation and RMT Re-Development
Inter-island Instantaneous Reserve Sharing: Implementation FIR & SIR
Normal Frequency Management Strategy
Quantity of Frequency Keeping Procured by Island under Frequency Keeping
Control
Security Tools Implementation for New HVDC Controls (Security Tools Project)
National Market for Instantaneous Reserve
National Market for Frequency Keeping
Under Frequency Management (Efficient Procurement of Extended Reserves
Implementation and Review of Instantaneous Reserves Markets).
SECURITY TOOLS IMPLEMENTATION FOR NEW HVDC CONTROLS 3.9
PROJECT
The project from the RFM programme having the greatest effect on the operation of the
system with FKC enabled is the Security Tools Project.
The Security Tools Project is delivering:
market system tools to automate current manual processes associated with RP
and FKC operation
new and modified market system and SCADA displays to facilitate greater
situational awareness for NCC system co-ordinators
training and process documentation for system co-ordinators.
3 Further information on these work streams can be found at:
http://www.systemoperator.co.nz/activites/current-projects/reserves-and-frequency-management-rfm-
programme.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
15
The market system tool changes are being driven by the need to efficiently operate the
FKC and RP functionality. The current manual processes are error prone and create
undesirable distraction from general operation of the electricity system. The project
design incorporates some of the findings from the pre-trial FKC testing.
The market system tool changes include improvements to the dispatch process include
the following new functionality:
dispatch algorithm inputs update. The algorithm in future will include, a
proportion of the difference between the HVDC transfer and the HVDC dispatch
set point and a time error factor
enhanced charts including generator governor response and HVDC off dispatch
trending (improving situational awareness)
This project is referenced further in this report as it provides some mitigations to issues
identified in both sections 7 and 8.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
16
4. PRE-FKC TRIAL FINDINGS
The findings from the system tests carried out on FKC during HVDC commissioning, prior
to the FKC trial, are documented in the report “FKC Trial – Pre Trial Approval Technical
Report.”4
A number of key points from this report are highlighted in the sections below. These key
findings were used to define the parameters for the FKC trial.
INTERACTION OF MFK AND GENERATOR GOVERNORS 4.1
System tests carried out with FKC enabled showed an opposing interaction between MFK
and generators with active governor control.
Most generator governors have two control elements which apportion response to correct
a frequency error:
1. proportional control – this increases or decreases power output depending on the
magnitude of the frequency deviation from the target frequency of 50 Hz.
2. integral control – this increases or decreases power output depending on the sum
over time of the frequency deviations from the target frequency of 50 Hz.
The integral control element provides damping to the governor response to ensure its
response is stable.
The difference between MFK and the governor control is that MFK corrects time error.
MFK control effectively adjusts its target frequency away from 50 Hz. Governor control
currently cannot adjust its target frequency.
Different target frequencies can cause MFK to respond in the opposite direction to the
generator governors. This causes the HVDC to be unnecessarily off dispatch as MFK in
the North Island is opposed by generator governor response in the South Island.
NEW PURPOSE OF MFK WITH FKC ENABLED 4.2
The MFK control has the same proportional and integral control elements as a generator
governor. Due to the latency in MFK (see section 3.4.1) governor control acts more
quickly to correct frequency changes. The generator governors therefore produce most
of the variation in active power required to correct frequency.
The latency in MFK varying active power output could on occasions cause an overreaction
to a frequency change. To manage this over reaction the proportional element of the
MFK control was effectively removed and MFK effectively became a mechanism to correct
time error.
A feature of MFK control is that in addition to the time error controls making an
automatic adjustment to the target frequency, a manual adjustment to the target
4 The report can be found at:
https://www.systemoperator.co.nz/sites/default/files/bulk-upload/documents/FKC%20Trial%20Report.pdf
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
17
frequency can also be made by the system co-ordinators. This manual adjustment is
used as a somewhat forceful control to ensure MFK acts to correct time error.
In short, MFK with FKC enabled was no longer being used to correct frequency; MFK was
solely correcting time error.
4.2.1
The change in use of MFK meant less frequency keeping capacity was required from MFK
generators. A number of different quantities were tested and it was concluded that
across both North and South Islands a capacity of 30 MW was required.
CHANGE TO METHOD OF DISPATCH 4.3
Prior to FKC operation for approximately fifty percent of the time new dispatch quantities
were calculated and dispatched using a SO automated dispatch tool.
Enabling FKC changed the way the power system behaved and ‘felt’ from a system co-
ordinator’s dispatch perspective. The variables taken into account by the system co-
ordinator in calculating the new dispatch quantity had changed. Two new variables were
now used:
HVDC off dispatch. The difference between the actual HVDC transfer and it’s
dispatched transfer
responsive generators off dispatch. The sum of the differences between actual
generator active power and generator dispatched active power.
These variables replaced the previous variable of “the quantity of active power the
frequency keeper has varied to maintain system frequency and time error.’
The existing market systems automated dispatch tool was not designed for these new
input variables. Therefore when FKC control is in operation system co-ordinators are
required to always calculate the new dispatch quantity manually.
ROUND POWER UNDER FREQUENCY RISK MANAGEMENT 4.4
When RP is in operation the additional risk issues identified in section 3.5.1 are
managed, where necessary, by use of manual processes. These processes are:
applied only to real time dispatch and do not appear in the schedules published to
the market
a simplified representation of RP.
While operating in RP mode the HVDC controls automatically select the appropriate pole
configuration for a given transfer, regardless of the dispatch set point.
It is not practical for system co-ordinators to manually update the market system
modelling of the pole configurations during the various states of RP operation.
System co-ordinators follow a simplified modelling process to ensure adequate reserves
are dispatched when the HVDC is dispatched by the market system through zero.
When HVDC transfer is ordered below 100 MW in either direction, system co-ordinators
are alerted via an alarm to adjust the market system HVDC to ‘round power mode’.
‘Round power mode’ sets the DCRS to zero to reflect the HVDC’s possible inability to
‘self-cover’ in the event of the loss of one of the HVDC convertor poles. The Security
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
18
Tools Project will model round power more comprehensively, reducing onerous manual
processes.
MAXIMUM HVDC TRANSFER AND FKC 4.5
FKC cannot increase HVDC transfer beyond the HVDC power limits. These limits are
dynamic but have a maximum of 1200 MW for HVDC north transfer and 850 MW for
HVDC south transfer. In addition, the limits change depending on the HVDC and AC
equipment offered and Wellington load.
Before the trial began, it was agreed FKC would be disabled when HVDC transfer reached
a value close to the HVDC power limit. Alarms were set-up to alert system co-ordinators.
The HVDC transfer level at which FKC is disabled also takes into account the modulation
risk and the reserve sharing in RMT as neither of these values are accounted for in the
current market system. The table below details when the alarm annunciates:
Table 1 Alarm Annunciation
Alarm Type Transfer at which alarm annunciates (X = HVDC Power Limit)
Warning X – MR – Reserve Sharing – 40 = X -130
Action X - MR – Reserve Sharing = X – 90
The warning alarm informs system co-ordinators HVDC transfer is close to where FKC will
need to be disabled. The action alarm annunciates FKC must be disabled.
System co-ordinators cannot practicably disable FKC frequently as it requires an onerous
manual process to be completed. Therefore, on receipt of the limit alarm, a system co-
ordinator will assess the non-response schedules to identify when FKC is next scheduled
under the limit for an extended period of time; the identified time will provide confidence
FKC can be re-enabled and will be the target time notified to participants when FKC
operations will be reinstated.
FKC TRIAL START CONDITIONS 4.6
Following acceptance of Pre-Trial Approval Technical Report, the FKC Trial commenced
with the following conditions:
MR = 40 MW
North Island MFK band = 20 MW
South Island MFK band = 10 MW
MFK operating in single frequency source mode
suitable temporary manual operational procedures developed and implemented.
TEMPORARY MANUAL OPERATIONAL PROCEDURES 4.7
Temporary manual operational procedures were implemented to manage the trial prior to
any SO tool changes being made. The manual processes managed the change to
dispatch, MR and RP modelling issues discussed in section 3.7 and 4.4.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
19
Tool changes are being made as part of the Security Tools Project, expected to be
delivered September 2015.
FKC TRIAL EXIT CONDITIONS 4.8
During the trial period a set of trial exit conditions were established. The trial was to be
stopped and FKC disabled when or for:
time error in either island exceeded 3.5s
loss of communications occurred between MFK controller and generator local
control systems (inter control centre protocol or ICCP)
high HVDC transfer north or south (HVDC power limit less margin) occurred
security constraint violations and/or contingency violations
bipole outage or trip occurred
monopole outage or trip occurred
RP was unavailable
system security issue identified or major system event occurred.
SUMMARY OF POSSIBLE MODES OF OPERATION 4.9
To assist the reader Figure 1 below shows the various modes of operation for HVDC
frequency controls. Some of the modes will be described in later sections. (The MR is set
to 30 MW the current value.)
Figure 1- Summary of HVDC Frequency Control operational conditions
InputsHVDC Frequency
ControlFrequency Keeper Type Market Tool Settings
Au
to
Dis
patc
h
Po
ssib
le
NI F
K
SI F
K
MR
MF
KS
FK
MF
KS
FK
Is Pole 2 and Pole 3
Available?
Is Round Power
enabled?
YesIs the DC near the power limits?
Yes Run in FKC Mode
No
Run in FSC Mode
Normal
Grid Emergency SI
Grid Emergency NI
North Island
South Island
Y
N
N
N
N
N
Y
20
0
30
50
0
50
50
10
30
0
0
25
25
25
30
30
30
30
30
0
0
No No
Yes
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
20
5. BENEFITS OF FKC OPERATION
REDUCED FREQUENCY KEEPING COSTS 5.1
FKC operations during the trial allowed reductions in the quantity of frequency keeping
purchased, from 75 MW to 30 MW. Although the trial commenced on October 16th 2014
FKC was only periodically available in November and December due to equipment and
plant outages associated with the HVDC.
The first full month of continuous FKC trial operation with reduced frequency keeping
quantities purchased was January 2015.
Figure 2, shows how frequency keeping costs have reduced during the period of
sustained, FKC trial operations. The graph shows the last 24 months of frequency
keeping costs. The last three months (in green) represent the first three continuous
months of a lower quantity of frequency keeping being purchased. If the trend continues
approximate market savings of approximately $25 million per annum may be realised.
An important caution is that frequency keeping duties have effectively been transferred
to generators with governors active in the normal band. Reduced frequency keeping
payments have not accounted for any additional cost incurred by the generators for this
apparent transfer of duty. See section 6.1 for a more detailed analysis of this issue.
Figure 2 Frequency Keeping Costs
0
1
2
3
4
5
6
7
Mo
nth
ly F
req
ue
ncy
Ke
ep
ing
Co
sts
($ M
illio
ns)
Time (months)
Frequency Keeping Costs
FSC enabled
FKC enabled partially
FKC enabled
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
21
TIGHTER CONTROL OF NORMAL FREQUENCY 5.2
The analysis in Appendix A shows that with FKC enabled overall frequency deviation
across New Zealand decreased. In the North Island there has been a significant
decrease in frequency deviation. In the South Island there has been a slight increase in
frequency deviation.
North Island frequency historically tended to have more deviations from 50 Hz than
South Island frequency, for the following reasons:
South Island generation is mostly hydro, where governors are normally quick to
respond to fluctuations in frequency
North Island generation has a lot of thermal, gas and geothermal units which
often have dead bands across the normal frequency keeping range
in the North Island, an industrial load site creates large variations in frequency
through its unpredictable load usage.
Once the two islands are tied together through FKC the experience is clear that
frequency deviation reduces for the North Island but increases slightly for the South
Island. Overall frequency deviations across New Zealand have decreased.
ENABLES NATIONAL MARKET FOR INSTANTANEOUS RESERVES 5.3
As part of the RFM programme a National Instantaneous Reserves Market (NIRM) is
planned for implementation in 2017.
Currently under frequency reserves are purchased on an island basis. A conservative
increase (60 MW) of HVDC transfer is assumed to come from the HVDC frequency
controls for the calculation of FIR. No increase in HVDC transfer is assumed in the
calculation of SIR.
The ability of FKC control to match the two island frequencies means SIR will now be
transferred via the HVDC from one island to the other island when an under frequency
event occurs. The SRS control on the previous HVDC control system would allow an
amount of SIR to be transferred but the levels were smaller and inconsistent.
The FKC control therefore enables reserves for AC system risks to be purchased in either
island. This could lead to a significant reduction in the overall quantity of reserve
purchased as presented below in Table 2.5
5 Table 2 assumes the largest North Island risk to be one of the three large gas fired power stations. These
stations are assumed to run at minimum output overnight. RMT currently uses a simplified representation of
the HVDC response. This response would be more accurately modelled after a national reserves market is
implemented which would lead to a reduction in the FIR required.
Currently SIR is purchased for the AC risk in each island. A national reserves market will also allow the sharing of SIR for AC risks across both islands.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
22
Table 2 Reserve Quantities Purchased with FKC Enabled
Daytime
(current)
Overnight
(current)
Daytime
(future)
Overnight
(future)
NI AC risk (MW) 380 240 380 240
NI AC FIR (MW) 240 140 140 70
NI AC SIR (MW) 380 240 200 140
SI AC risk (MW) 125 125 125 125
SI AC FIR (MW) 30 45 110 100
SI AC SIR (MW) 125 125 180 100
FIR Reduction (MW
/ %)
20 MW / 7% 15 MW / 8%
SIR Reduction (MW
/ %)
125 MW / 24% 125 MW / 34%
The NIRM could reduce the purchase cost of reserves not only by reducing quantities of
reserves but also by allowing South Island reserves to be sold in the North Island and
vice versa. Given the surplus of generation reserves in the South Island this is expected
to reduce the cost of purchasing under frequency reserves.6
As an interim measure the Inter-Island Reserve Sharing project, also part of the RFM
programme, will share SIR between the two islands when FKC is enabled, in a similar
manner to how FIR7 is already shared. This minor change to the market system is
scheduled to be completed in September 2015.
Both the NIRM and the Inter-Island Reserve Sharing project therefore require FKC to be
enabled to function. Without FKC expected benefits cannot be realised.
HIGHER MARKET CAPACITY DURING ENERGY SHORTFALLS 5.4
5.4.1
A single island energy shortfall occurs when:
there is high system demand
there are insufficient energy and reserve offers to supply the energy and reserve
requirements in either the North or South Island.
A shortfall will cause high prices and may have a significant effect on consumers of
electricity and those exposed contractually to electricity market spot prices.
A shortfall will usually mean HVDC transfer is limited to the amount of reserve available
to cover the HVDC transfer. The FKC MR will cause the HVDC transfer to limit at a lower
value than if FKC was not in operation.
6 http://www.ea.govt.nz/dmsdocument/3574 7 Up to 60 MW of increased HVDC transfer is assumed when modelling FIR.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
23
Under grid emergency the SO may purchase all system frequency keeping requirements
from the island without the shortfall, thereby increasing capacity in the island with the
shortfall.
Inter-island reserve sharing8, only available when FKC is enabled, will increase the
quantity of SIR available to cover AC risks in the island with a shortfall.
When there is a capacity shortfall in the North Island the larger AC risk setting plant
often have outputs significantly constrained to below full offered capability as there is
insufficient SIR to cover the under frequency risk of the full offered capability. Inter-
island reserve sharing will therefore allow increases of scheduled output of larger AC
risks during capacity shortfalls as more SIR is available.
An example for the North Island of what this means and how it increases capacity is
given below in Table 3.
Table 3 NI Capacity change with FKC enabled
Change in capacity due to
being FKC enabled (MW)
MR = 30 MW, limits HVDC transfer -30
Frequency keeping now 20 MW was 50 MW +30
Total under normal circumstances 0
Frequency keeping now 0 MW +20
Total under a grid emergency +20
Change due to inter island reserve sharing (assuming
two large risks and 60 MW SIR sharing)*
+120
Total under a grid emergency and inter island reserve
sharing
+140
* Assumes the SIR is the limiting risk which is typical and that two of the three large
(greater than 300 MW in capacity) generators are available.
Table 3 shows that with FKC control enabled there is more capacity available for single
island shortfalls.
8 Due for implementation by the end of 2015.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
24
5.4.2
If there is a capacity shortfall in both islands then frequency keeping is purchased
normally. An example of a capacity shortfall across both islands is given below in Table
4.
Table 4 Capacity change with FKC enabled
Change in capacity due to
being FKC enabled (MW)
MR = 30 MW, limits DC transfer -30
Frequency keeping now 30 MW was 75 MW +45
Total under normal circumstances +15
Change due to inter island reserve sharing (assuming
two large risks and 60 MW SIR sharing)*
+120
Total under a grid emergency and inter island reserve
sharing
+135
* Assumes the SIR is the limiting risk which is typical and that two of the three CCGT’s
are available.
Table 4 shows that with FKC control enabled there is more capacity available when the
capacity shortfall is in both islands.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
25
6. FKC TRIAL TECHNICAL ISSUES WITH MARKET
IMPACT
INCREASE IN GENERATOR GOVERNOR ACTION 6.1
Introduction of MFK increased the quantity of response expected from generator
governors to manage normal frequency. The use of FKC has further increased the
quantity of response expected from generator governors (see section 4.1 and Appendix
B).
Section 4.1 discusses the effect FKC has on frequency behaviour in the normal band
which the governor response is related to. FKC essentially shares the governor reaction
to frequency deviation across both islands.
Without FKC we know that despite having more system inertia the North Island has
larger deviations in frequency in the normal band than the South Island (see Appendix
A). With FKC enabled these North Island larger deviations are shared across the whole
system. This in turn leads to South Island governors being more off dispatch with FKC
enabled than with FKC disabled. The opposite is true for the North Island. Details are in
Appendix B.
Market participants have commented that increased generator governor action is
regarded as undesirable for various reasons including the following:
revenue may be affected as owners may be paid slightly more or less than their
cleared offer. It may also leave a generator exposed on a contract position
higher generation may come with a higher fuel cost
the governor action may cause the generator to move into an operating range
where mechanical vibrations can be higher
the constant fluctuation of output power from the governor can cause additional
wear on the generators with some generators more susceptible to this than others
generators may have to consider an inadvertent breach of relevant resource
consents, especially with minimum flows
a generator may increase its Historical Annual Maximum Injection quantity. This
will increase its transmission charges.
Market participants have also raised concern there is no market mechanism to directly
reflect the costs of increased governor action.
6.1.1
To avoid increased governor costs generators have the ability to implement a dead band
into their governor controls. The dead band usually prevents any governor response to
frequency movement in the normal band. There is currently no EIPC requirement on
whether or not generators should have dead bands.
A high proportion of North Island generators already have such dead bands
implemented. When the HVDC frequency controls are not in operation the consequent
lack of generation response leads to poor frequency control in the North Island within the
normal frequency band.
Market participants have commented they may fit a dead band to more of the remaining
generators governor controls. If this occurred it might lead to a material drop in the
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
26
quality of frequency control in the normal frequency range. In turn this might require
the purchase of extra under and over frequency reserves and a return to a frequency
keeping service with a significantly larger band.
One participant has suggested the proportion of frequency keeping purchased from each
island could be set to align more with the governor response provided by each island’s
generators. The participant suggested this alignment could be used as an interim
measure to compensate for generator governor action.
Recommendation 1 – The consequences of increased governor response should be
considered in a market context given the operational reliance now placed by SO on that
action during FKC operations.
MARKET COST OF MODULATION RISK 6.2
Market participants have raised concerns about two possible costs from the FKC MR:
a decrease in capacity leading to higher costs in times of capacity shortfall
an increase in market costs associated with HVDC reserve requirements.
6.2.1
The complexities of this subject have led to some confusion and therefore a perception
that capacity has decreased with FKC operation.
Section 5.4 details that there is actually a significant increase in capacity during energy
shortfalls when in FKC operation. Hence, no increased costs can arise during energy
shortfalls during FKC operations.
6.2.2
6.2.2.1 Increase in reserve quantities
The MR increases the size of the HVDC under frequency reserve risk. This means there
are more occasions when the HVDC becomes the binding market risk. A binding risk is
the risk requiring the largest quantity of reserves to be purchased.
The extra quantities of reserves result in an increase in cost to those participants who
are obliged to pay for the HVDC.
6.2.2.2 Increase in price separation between the two islands
When the HVDC risk becomes the binding risk in the market system the market
optimisation engine, Scheduling Pricing and Dispatch (SPD), co-optimises the cost of
additional energy and risk. Practically this means:
Price of additional HVDC transfer = Price of energy in sending island + Price of reserve in
the receiving island.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
27
The price of reserve therefore increases the price difference between the two islands.
This affects participants in the sending island as they get less for their generation and it
may affect their market trading positions.
The MR lowers the point at which price separation occurs and therefore increases cost to
market participants.
6.2.3
A number of ideas have been generated by both the SO and participants to alleviate
additional costs from the MR. These ideas are:
1) Redesign SPD so it co-optimises the use of FKC, balancing additional market costs
with savings made from reduced frequency keeping and reserves.
2) Turn off FKC when the HVDC reaches a certain level of transfer.
3) Buy a fourth cable for the HVDC to increase the single convertor pole overload
capability from currently 560 MW to 1000 MW.
No study of the technical or economic feasibility of ideas 1 and 2 has been commenced.
Recommendation 2: Study the feasibility of a market solution which could determine
when it is economically efficient to enable FKC.
APPROPRIATE QUANTITIES OF FREQUENCY KEEPING 6.3
6.3.1
As described in section 4.2 when FKC control is in operation MFK is effectively only
managing time error control. This has shown a lower quantity of frequency keeping was
required during FKC enabled operations.
From the commissioning FKC tests an initial frequency keeping figure of 30 MW was
selected for FKC operations. Time was allocated during the FKC trial for more extensive
tests with different quantities of MFK dispatched. Extensive tests were required as the
data being monitored during these tests could vary randomly from day to day. To draw
an accurate conclusion from the test sufficient data was required to eliminate these
random variations.
During the trial period tests were carried out with no MFK control (i.e. 0 MW) for three
weeks to measure the effects of the absence of MFK on the system. In all the tests the
frequency PPOs were always maintained.
The tests demonstrated a number of points:
overall frequency deviations with FKC enabled and 0 MW of MFK dispatched were
lower than when FSC/SRS was enabled and 75 MW of MFK dispatched (the normal
mode of operation before FKC operations were commenced). The deviations with
0 MW of MFK dispatched and FKC enabled were worse than with 30 MW of MFK
dispatched and FKC enabled. See Appendix A for details
time error deviation increased with FKC enabled and 0 MW of MFK dispatched.
Time error was still easily within the EIPC PPO limits. See Appendix A for details
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
28
the HVDC was off dispatch more with 0 MW of MFK dispatched than with 30 MW
of MFK dispatched
generator units with governor action were more off dispatch with 0 MW of MFK
dispatched than with 30 MW of MFK dispatched. See Appendix B for details.
The graph below shows how much the HVDC was off dispatch during the tests with 0 MW
of MFK dispatched. Weeks 2, 4 and 5 are the weeks with 0 MW of MFK dispatched. The
graphs show the HVDC was more off dispatch with 0 MW of MFK dispatched than with 30
MW of MFK dispatched. Week 5 shows that as system co-ordinators became more
familiar with dispatching in this scenario results improved.
Figure 3 - HVDC off dispatch quantities
As detailed in section 4.2 MFK is primarily used to correct time error. The test with
0 MW of MFK dispatched showed dispatch can be used to correct time error. The
problem with this approach is the increased number of manual calculated dispatches
required encroaches on the time system co-ordinators spend on other system and
market issues.
Figure 3 shows how dispatches generally increased across a week of operation. Overall
dispatches increased by 6%.
The SO is implementing the Security Tools Project which may enable elements of the
dispatch process to include more automation when FKC is enabled. More automated
dispatch will reduce the time system co-ordinators spend on calculating new dispatch
quantities. Some system tests will be required to confirm the effectiveness of the
changes in the market system tools. There is further discussion on automating manual
dispatch actions in section 7.1.
Additional market and operational issues need also to be addressed before further future
changes to frequency keeping quantities are considered. These are in section 9.2.
0
20
40
60
80
100
120
140
160
180
1 2 3 4 5 6
Min
ute
s th
e H
VD
C w
as o
ff d
isp
atch
Week
HVDC off dispatch Comparison
>50 MW
>60 MW
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
29
Figure 4 - Increase in dispatches with MFK = 0 MW
6.3.2
With FKC control enabled there is technically no limitation on which island frequency
keeping services are purchased from.
The current market system arrangements procure frequency keeping services to fulfill a
fixed quantity required per island. The quantities of frequency keeping per island were
set at the beginning of the trial based on a ratio of the frequency keeping normally
procured when FKC control is inactive, as follows:
Table 5
Island MFK purchased when FKC is
inactive
MFK purchased when
FKC is active
North 50 20
South 25 10
If frequency keeping continues to be purchased it may be more economically efficient to
purchase from a nationwide market. A nationwide market may allow the cheapest
providers to be selected. Such a change would require a significant change to the SO’s
market system tools. Further developments on establishing a national frequency
keeping services market are part of the RFM programme.
EFFECTIVENESS OF THE MFK COMPLIANCE CALCULATION 6.4
Since the introduction of MFK in the North Island in 2013, the SO has reported frequency
keeping performance using the Regulation Instruction Error Ratio (RIER).
0
50
100
150
200
250
300
350
400
450
fri sat sun mon tue wed thur
Nu
mb
er
of
dis
pat
che
s p
er
day
Day of the week
Comparison of number of dispatches depending on MFK dispatch
FKC on, 0 MFK
FKC on, 30 MFK
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
30
The RIER is specified as one of the frequency keeping principal performance obligations
(PPO’s) in the Ancillary Service Procurement Contracts the SO has with each frequency
keeping provider. The lower the RIER figure the better the frequency keeping provider is
judged to have performed.
The underlying calculation is a weighted standard deviation of the three minute average
difference between actual power output versus the energy dispatch set-point plus the
MFK regulation instruction. The calculation is made for each frequency keeping unit or
station.
Figure 5 - Monthly RIER values during the trial
The RIER does not take into account the unit governor response to system frequency.
When FKC is enabled the RIER results for many frequency keeping providers vary widely
between months and are significantly worse than when FKC is not enabled.
The poor RIER results are particularly pronounced in the South Island. It is believed this
is due to the greater deviations from MFK regulation caused by the frequency response
of generating units during FKC operation.
As a result, the SO no longer has confidence the RIER metric provides a meaningful
indication of the quality of the frequency keeping service provided. RIER performance
reporting has been suspended.
Recommendation 3 – When the future design for frequency keeping services has been
completed establish a new frequency keeping provider service performance metric.
ACTIVE POWER AND RESERVE COMPLIANCE WITH DISPATCH 6.5
The transfer of frequency keeping duty to generator governor action caused initially by
MFK and then increased with FKC operations can cause a generator’s output to not be
aligned with its dispatch instruction.
Concerns have been expressed by market participants this might impact on both legal
compliance and system security.
0
20
40
60
80
100
120
140
Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15
RIE
R (
%)
Months
MFK Monthly Regulating Instruction Error Ratios
Gen 1
Gen 2
Gen 3
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
31
6.5.1
There are three clauses of the EIPC 13.73, 13.82 and 8.17 which are relevant.
13.73 … Each dispatch instruction must instruct a generator to carry out one of the
following in relation to a generating plant, generating unit, block dispatch group or
station dispatch group:
(a) provide, increase or decrease active power:
(c) provide an amount and quantity of reserve power to regulate frequency continuously:
13.82 Each generator or ancillary service agent must comply with a dispatch instruction
properly given by the system operator in accordance with clauses 13.73 or 13.74 except
if,-
e) the generator deviates from a dispatch instruction for active power in order to comply
with clause 8.17:
8.17 Each generator (while synchronised) and the HVDC owner must at all times ensure
that its assets … make the maximum possible injection contribution to maintain
frequency within the normal band.
Clause 13.73 defines dispatch instruction to include energy and reserves. Clause 13.82
and 8.17 explain that a generator’s power output may not be aligned with its dispatch if
it is responding to frequency.
A governor control system will react to frequency and change the active power output of
the generator. This reaction is aligned with the EIPC code clauses above. This reaction
affects some governors more when FKC is enabled, due to the previously described
transfer of frequency keeping duties (see section 6.1).
For practical reasons the SO has relaxed its automatic monitoring of active power
compliance with dispatch instructions. The compliance monitoring thresholds in the
market system were changed from 15 MW to 30 MW. The ten minute monitoring period
remains the same.
The SO provided guidance to market participants on 23rd September 2014 on how it
intended to manage generator dispatch compliance during the FKC trial.9 Refer to link
below:
https://www.systemoperator.co.nz/sites/default/files/interfaces/can/CAN%20Guidance%
20regarding%20compliance%20during%20FKC%20Testing%201557159690.pdf
6.5.2
The SO purchases under frequency reserves to manage losses of supply to the system.
Some of these reserves are provided by generators.
In calculating reserves the SO assumes generators are at their dispatched power output.
If in reality a generator’s output is higher than dispatch the expected reserve response
will be slightly slower. If a generator’s output is higher than dispatch then the reserve
9 The SO increased the quantity a generator could be off dispatch before it made enquiries. This was to
recognise the effect of increased governor action for some generators.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
32
response could also become limited to a new lower maximum quantity as there is less
spare capacity on the generator.
Any material decrease in the expected reserve response of generators would impact on
the SO’s ability to meet its frequency PPOs. Further study is recommended to quantify
the magnitude of this issue.
Recommendation 4 – Investigate whether the increase in generator governors being
off dispatch has a material effect on the quantity of reserve available for under frequency
events.
If a generator’s output is lower than dispatch there is a consequential reduction in the
capacity for the generator to respond to an over frequency. The SO’s calculation of over
frequency reserves however relies on real time data not dispatched quantities in its
calculations. It can therefore recalculate quantities as generators react to frequency.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
33
7. FKC TRIAL OPERATIONAL ISSUES
AUTOMATIC OPTION NO LONGER AVAILABLE FOR SYSTEM 7.1
DISPATCH
As discussed in section 4.3 the automated formulation of dispatch instructions is no
longer available operational to system co-ordinators. This leads to extra work for system
co-ordinators who must issue dispatches manually during FKC- enabled operations.
Situational awareness is eroded by this narrowly focussed view when manually issuing
dispatch instructions.
This issue may be addressed by the Security Tools Project. This project will provide
more inputs to the market system allowing automatic calculation of dispatch quantities.
The effect of these new inputs on the dispatch quantity is not proportional and some
tuning will be required. Until the market system is tested with these new inputs, it is
uncertain whether the tuning will successfully enable automatic dispatch.
Recommendation 5: Once the Security Tools Project is completed, the system operator
should test if, with FKC enabled, automatic dispatch can be re-enabled.
OPERATIONAL COMPLEXITY OF STARTING AND STOPPING FKC 7.2
OPERATION
The FKC activation and deactivation processes were developed within the existing market
system design.
The process to enable and disable FKC is complicated and onerous. Experience during
and since the trial has shown the process to provide ongoing opportunities for error.
The process requires phone calls to the grid operators, manual actions across multiple
tools and communication to the industry (informing them of the change in FKC status).
In the market system manually-undertaken changes are made to the HVDC under
frequency risk, frequency keeping bands and the amount of SIR reserve that is procured.
This process has 15 manual steps and takes 3 system co-ordinators up to 20 minutes to
complete. With the current market system design, this is a substantial operational
overhead devoted to this task. Managing a concurrent system event would be more
difficult to manage.
The completion of the Security Tools Project will bring some reduction in the time to
complete the processes. The project will make transitions to and from FKC operations
easier and less prone to manual errors.
The improvements from this project are still not expected to sufficiently reduce the time
taken to complete the stopping and starting of FKC process. The lengthy process is a risk
to prudent operation of the electricity system.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
34
Recommendation 6 – Investigate a change to the business process and market system
tools associated with the activation and deactivation of FKC with a view to identifying
automation opportunities.
IMPACT OF HVDC RECLOSE BLOCKS ON FKC OPERATION 7.3
When live line work is undertaken on a circuit, any system which, following an electrical
fault, automatically reenergises the circuit is blocked from operating. This is implemented
for safety reasons in case the fault is caused by those working on the circuit. This block
is called a Reclose Block (RCB).
When RP is disabled FKC would have to be disabled whenever the HVDC transfer
approached the HVDC convertor pole minimum of 35 MW. The current complexity of the
manual processes to disable and enable FKC means FKC is disabled whenever RP is
disabled.
For safety reasons RCBs for live line work on the HVDC conductors require HVDC
automatic restarting, including RP, to be disabled during the period any RCB is required
to be in effect.
Currently, for the duration of the HVDC RCBs (typically one week) FKC is disabled. As
disabling FKC has a material market, impact notification of HVDC work requiring RCBs is
advised to participants one week from the start of work.
7.3.1
As discussed in section 7.2 the Security Tools Project will automate some of the manual
processes associated with enabling and disabling FKC. Following implementation the SO
will need to assess whether the project’s changes are sufficient to allow FKC to stay
enabled, even when RP is disabled.
Recommendation 7 – Following the Security Tools Project, investigate whether FKC can
remain enabled when RP is unavailable.
FKC EXIT CONDITIONS REASSESSED 7.4
The FKC trial exit conditions (refer section 4.8), for FKC operations to be terminated,
were reassessed following completion of the trial and once system co-ordinators had
growing operational experience and greater confidence in FKC operation.
The following exit conditions were deemed to be no longer required:
time error in either island exceeds 3.5s
security constraint violations and/or contingency violations.
The other exit conditions were deemed valid and FKC will continue to be disabled when
they are extant:
loss of communications between MFK controller and generator local control
systems (inter control centre protocol or ICCP)
high HVDC transfer north or south (HVDC power limit, less margin)
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
35
bipole outage or trip
monopole outage or trip
RP unavailable
system security issue identified or major system event occurs.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
36
8. TECHNICAL ISSUES FROM THE FKC TRIAL
FREQUENCY EXCURSIONS DURING THE TRIAL 8.1
There were a number of high and low frequency system excursions during the trial
period. The response of the HVDC controls and system frequency were stable and
showed no issues with FKC operation. Further detail on the excursions is in Appendix D.
POSITIVE TIME ERROR TREND 8.2
When FKC is enabled, time error appears to naturally trend in a positive direction. To
maintain time error to within the EIPC required limits of +/- 5 seconds system co-
ordinators use a combination of MFK and dispatch to:
adjust the target frequency in MFK controls. This is to reduce positive or negative
time error over time as the MFK controller drives to a frequency slightly higher or
lower than the standard frequency of 50 Hz for both islands
manually dispatch to correct time error. System co-ordinators can use PSDs for
the next real-time dispatch solution to reduce time error in both islands. (The
Security Tools Project will facilitate automatic calculation of PSDs using the time
error as one of its inputs.)
Figure 6 (below) shows the effect FKC operation has on time error. When the HVDC
frequency control mode was changed from FSC/SRS to FKC an immediate change was
noted. This saw time error changed from oscillating about zero to being a more refined
signal with ascending and descending trends. Time error can be seen ramping all the
way up to two seconds before being returned to zero. Many of the time error decreasing
periods in Figure 6 are due to system co-ordinator corrective action.
Figure 7 (below) shows an example of typical time error trending across a day. It also
shows the sudden increase in time error in a positive direction.
A discussion of some of the potential causes of the positive time error trend is included in
Appendix D – Positive time error trend.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
37
Figure 6 FKC effect on time error with time error trending positive
Figure 7 Time error trend example 20th October 2014
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
38
8.2.1
During the trial it was observed that time error would generally increase in a positive
direction.
A number of potential causes of positive time error were investigated during the FKC
trial. There are several relevant matters:
the time resolution of the historical data was insufficient to identify if a generator
was a cause of the problem or responding to the problem
the FKC control system has no time error input
the FKC control system does not control absolute frequency. It only controls
frequency separation between the North and South Island.
The latter two points support the reasonable assumption that FKC is not likely to be the
cause of the time error trend as it has no input related to time error. (Such an input
could cause a cumulative integration error.)
Despite a lengthy investigation into positive time error increase no cause of the issue has
yet been identified.
Further details of the investigation are in Appendix D – Positive time error trend.
8.2.2
During the trial time error was managed successfully using either manual dispatch or
adjusting the MFK frequency target. It has therefore been determined to continue to
manage time error this same way when FKC is enabled.
TIME ERROR SEPARATION BETWEEN THE NORTH AND SOUTH 8.3
ISLANDS
Whilst FKC aims to tie the two island frequencies together, the two island frequencies are
not truly synchronous. The error between the frequencies accumulates into a divergence
between the two island time errors.
Time error difference between the two islands can be corrected by system co-ordinators.
A frequency off-set is applied in the HVDC controls to either the North or South Island of
+/-10 mHz to rapidly converge the two island time errors.
The rate at which time error diverged between the two islands was observed to be very
consistent across extended periods of time.
Figure 8 and Figure 9 show the time error difference trend across different time periods.
In Figure 8 a clear difference and trend is observed when FKC is enabled, compared to
FKC disabled. In Figure 9 two gradients of time error are observed, one very steep
gradient from 16/12/2014 and one gentler gradient from 27/12/2014.
During the 16/12/2014 to 27/12/2014 period the correction of time error divergence was
very onerous for system co-ordinators and was noted to require a significant amount of
attention compared to a dispatch on a normal day. This problem led to system co-
ordinators trialling a fixed 1 mHz offset instead of periodically inputting a 10 mHz offset
to counter the time error divergence gradient. This was effective until the gradient
changed later the following day. This is discussed further in Appendix E - Using HVDC
frequency offset from HMI to minimise time error divergence.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
39
It is not clear what affects the gradient of the time error divergence. However, it has
been shown to be consistent over extended periods of time.
Figure 8 Time error difference plot 16/10/2014 – 11/11/2014 (South Island - North Island time error)
Figure 9 Time error difference plot 16/12/2014 - 12/01/2015 (South Island - North Island time error)
8.3.1
It would appear possible to eliminate time error separation between North and South
Island frequencies by inputting the correct frequency offset. This will require the ability
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
40
to enter values of less than 1 mHz into the HVDC controls, as even with a 1 mHz offset a
slow separation occurs.
A modification is being made to the HVDC controls to allow frequency offsets of less than
1 mHz to be made. A PI based application is being developed to calculate the required
frequency offset.
CAUSES OF NORMAL FREQUENCY BAND VARIATIONS 8.4
8.4.1
A major cause of frequency variation in the North Island and therefore in both islands
when FKC control is in service is a constantly varying large load. This is demonstrated in
Figure 9 and Figure 11 below.
Figure 10 below show the strong correlation between the HVDC being off dispatch for
frequency control and the average power taken by the varying load. Figure 11 shows
the strong correlation between North Island frequency and the average power taken by
the varying load.
Figure 10 - Graph of HVDC frequency response with a North Island Load
6
8
10
12
14
16
18
0
5
10
15
20
25
30
35
40
27-Dec 1-Jan 6-Jan 11-Jan 16-Jan 21-Jan 26-Jan 31-Jan 5-Feb
Dai
ly a
vera
ge H
VD
C is
off
dis
pat
ch (
MW
)
Ave
rage
dai
ly lo
ad (
MW
)
Time
Effect on the HVDC frequency response
Load
HVDC
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
41
Figure 11 - Graph of frequency deviation with North Island Load
The SO understands the variations in this load will reduce significantly towards the end
of 2015. If this expected reduction occurs the extent to which the HVDC is off dispatch
and the generation is off dispatch should materially reduce.
8.4.2
When examining the changes in modulation deviation from day to day another cause of
frequency deviations became apparent. More deviation appeared to arise when slow
ramping generators were altering their power output to achieve their dispatch set point.
An example is shown in Figure 12 (below). The shortfall in output by the slow ramping
generator is compensated for by the HVDC increase. The HVDC increase represents the
action of South Island generator governors. When the generator reaches dispatch the
HVDC also returns to dispatch.
Currently the EIPC requires generators need only comply with ramp rates over a period
of an hour. System dispatch assumes generators will follow their ramp rate over a five
minute period. When generators do not follow their ramp rate over the five minutes
assumed in dispatch there is a resultant imbalance in power supply. This imbalance
causes a deviation in frequency.
The SO uses the PI tool for analysis of historical generation data. Because PI does not
store dispatch instructions it was not possible to easily understand how much slow
generation ramping is causing the HVDC to be off dispatch.
Further investigation is therefore required to understand this effect, as follows:
arrange for the relevant dispatch points to be included in the PI database
0.015
0.017
0.019
0.021
0.023
0.025
0.027
0.029
0.031
0.033
0
5
10
15
20
25
30
35
40
27-Dec 1-Jan 6-Jan 11-Jan 16-Jan 21-Jan 26-Jan 31-Jan 5-Feb
Ave
rage
Dai
ly a
bso
lute
fre
qu
en
cy d
evi
atio
n (
Hz)
Ave
rage
Dai
ly L
oad
(M
W)
Time
Effect on system frequency
Load
frequency
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
42
calculate the correlation, if any, between generation shortfall and HVDC off
dispatch. (This is representative of generator governor action to correct
frequency.)
Recommendation 8 – Update the SO’s PI tool to receive generator dispatch data.
Undertake a study to consider how slow ramping generation affects the HVDC being off
dispatch with FKC enabled.
Figure 12 How a generator cause HVDC to be dispatched off
BACK UP FREQUENCY KEEPING 8.5
The system operator procures Back-up Single Frequency Keeping (SFK) ancillary services
to maintain PPOs should MFK fail. Single frequency keeping (SFK) performance with FKC
Although South Island SFK was tested with FKC in service it was felt desirable to test
both the North and South Island SFK to check there were no operational issues. The
tests were carried out with lower frequency keeping bands as per Table 6 below:
Table 6
Original FKC tests
August 2014
North Island SFK
test March 2015
South Island SFK
test April 2015
Frequency Keeping
band (MW) 75 50 25
With SFK operating and FKC enabled the PPOs were maintained with in their limits.
However, unexpectedly these tests showed SFK providers are not as familiar with the
SFK process as expected. There were several teething troubles with both the operational
and market utilisation of SFK. These issues impacted the data gathered from the tests.
-80
-60
-40
-20
0
20
40
60
80
100
0 5 10 15 20 25 30
Dif
fere
nce
be
twe
en
Act
ual
ou
tpu
t an
d d
isp
atch
(M
W)
Time (minutes)
How a Generator causes HVDC to be off dispatch
Thermal Generator HVDC
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
43
The data does not therefore sufficiently represent SFK operation for use in comparison
with MFK.
It is recommended the SO repeat the SFK tests on a six monthly basis to allow providers
to retain knowledge of SFK operation.
Recommendation 9 – The SO establishes a testing regime for a full day of SFK
operation every six months, (when market conditions are suitable.)
FKC PERFORMANCE DURING FAST WINTER LOAD PICK UPS 8.6
With completion of the FKC trial on 31st March 2015, the impact of fast winter load pick-
ups combined with slow ramping thermal plant has yet to be determined.
Notwithstanding this lack of experience, there is no evidence from the FKC trial to
suggest that there should be any winter issues. However, a review of the 30 MW FKC
MR will be conducted during winter loads to ensure this quantity of MR is still prudent.
WHAT IS AN APPROPRIATE NORMAL FREQUENCY STANDARD? 8.7
The EIPC requires only that frequency stays in the normal band of 49.8 Hz to 50.2 Hz.
As discussed in Appendix A the amount frequency deviates from 50 Hz varies with the
amount and type of frequency control available. The technical implications of the
frequency deviations are:
in calculating the purchases of under and over frequency reserves the SO
assumes a starting value of 50 Hz. As frequency will deviate from 50 Hz the SO
therefore needs to and does add a safety margin to calculating its requirements
for purchasing reserves. The higher the probability of frequency deviations the
larger the safety margin.
a steady frequency is also a requirement for generation units to easily connect to
the grid.
Whilst the technical implications of frequency deviations are clear, the economic impact
of these implications is not. An economic study of how frequency deviations in the
normal band change costs for market participants is desirable.
Recommendation 10 – Carry out economic studies to calculate the costs implications
of greater frequency deviations.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
44
9. FUTURE DEVELOPMENTS WITH FKC OPERATION
The following ideas indicate where future changes in FKC operations may occur. They do
not represent concluded thinking by the SO.
REDUCTION IN THE MODULATION RISK 9.1
The MR was reduced from 40 MW to 30 MW at the end of the FKC trial.
This number was achieved by taking into account the following factors:
how long the HVDC with FKC in service was above dispatch by a certain value
the comparative performance of the HVDC with FSC in service.
With FSC in service the HVDC varies from its dispatch value. This variation has not been
accounted for in the reserve calculation to date. With FKC enabled the HVDC variation
from its dispatch value increases. This variation was, during initial FKC operations,
greater and sustained for a longer period than previously when FSC was in service.
Through modifications to the MFK settings and changes to the dispatch process the SO
has reduced the value of the FKC MR from 75 MW prior to the trial to 30 MW with FKC
enabled.
There are a number of future developments which may be able to reduce modulation risk
further:
exit of a large highly variable North Island load towards the end of 2015
further improvements in dispatch compliance of ramping generation (see section
8.4.2).
Conversely, some of the reasons no additional reserve was required to cover the risk of
the HVDC being off dispatch, with FSC in service, may no longer be valid in the near
future:
the five second overload of a convertor pole to 840 MW is not now being
modelled.10 This overload may be modelled in RMT in the next year
the reduction in purchased reserves with the various initiatives within the RFM
programme (e.g. national reserves market).
The SO will undertake a review of the under frequency reserves required to cover all
HVDC risks of loss of supply. The review will include an examination of the modulation
risk for frequency controls and all levels of convertor pole overloads.
Recommendation 11 – Undertake a review of under frequency reserves requirements
to cover the HVDC risks of loss of supply.
10 Following the loss of Pole 3, Pole 2 will overload up to 840 MW for 5 seconds before reducing to a maximum
of 560 MW.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
45
QUANTITY OF FREQUENCY KEEPING PURCHASED 9.2
The technical success of tests with MFK dispatched to 0 MW enables consideration of a
future scenario where there is no frequency keeping service required.
Such change cannot be made immediately as there are several operational, tool and
market issues to resolve.
9.2.1
The MFK 0 MW tests have identified the following issues needing to be resolved before a
move to procuring no or materially lower frequency keeping services:
update of the dispatch inputs to allow automatic correction for time error
providing system co-ordinators with the ability to easily and quickly revert to
back-up frequency keeping when FKC is unavailable. The current process
involves too many steps requiring too much time. This implies some major
automation changes to system co-ordinator tool sets.
9.2.2
An important market issue to address is the FKC-induced increase in South Island
generator governor action.
9.2.3
Continued use of MFK as an operational method of correcting time error, whilst practical,
comes with a cost. Even with the reduced cost from FKC-enabled operations, frequency
keeping (i.e. MFK) costs are projected to be approximately $13 million per annum.11
Using dispatch to correct time error and purchasing less or no MFK might enable this cost
to be reduced.
Recommendation 12 - Once the consequences of increased governor response have
been considered in a market context (Recommendation 1), consider the quantity of MFK
required for operation with FKC.
AUTOMATIC GOVERNOR CONTROL 9.3
As detailed in section 4.2, the slow response time of MFK has made MFK ineffectual in
controlling frequency when FKC control is enabled. Some participants have suggested
that, instead of relying on governor action, a quicker responding frequency keeper could
be used. SFK would be one option; Automatic Generation Control (AGC) would be
another.
AGC has been implemented in a large number of power systems throughout the world.
MFK is a variation of AGC, the key difference being that with AGC the control signal is
11 This projection assumes the cost of frequency keeping over the year is the same proportionally as the cost
over the January to March 2015 period when FKC was fully enabled. The cost of frequency keeping for these first 3 months of the year was $3.3 million.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
46
sent directly into the governor control system. With MFK the signal is sent via the power
controller which introduces a significant time delay.
AGC was an option considered when MFK was selected. It was rejected due to
implementation cost, block dispatch in its current form is not compatible with AGC and
reluctance by participants to allow direct control of generator governors. An AGC system
would require the MFK system to be upgraded to decrease the signalling and processing
time delays of the central controller.
AGC might have the advantage of allowing more competition than SFK as a small
generator would be able to compete in an AGC market that might otherwise be excluded
from a SFK market. (This is why MFK was introduced as a replacement for SFK.)
Using AGC would be a longer term solution. First investigation steps would probably be
further SFK testing to examine whether a frequency keeper acting with FKC enabled
could take significant duty off generator governors.
Consideration of a developed AGC implementation would be for the Authority to lead.
SYSTEM OPERATOR DISPATCH STRATEGY 9.4
The SO is in the process of defining a strategy and vision for the future of the dispatch
function. This strategy will encapsulate the tools and processes used in the dispatch
function with an aim to drive efficiency and automation; moving from providing
situational awareness to developing situational intelligence. The strategy will drive the
removal or re-allocation of non-value adding tasks currently carried out in the co-
ordination centre, ensuring not only primary but also back-up processes and tools are
optimised for single person dispatch.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
47
10. CONCLUSION & RECOMMENDATIONS
The FKC trial ran from 16th October 2014 through to 31st March 2015. With FKC in
operation the SO was able to meet the EIPC PPOs for frequency and time error.
During the FKC trial the following benefits were noted:
frequency keeping costs reduced with frequency keeping duty transferred to
generators with governors active in the normal band
tighter control of normal frequency with overall frequency deviation across NZ
decreasing with, however, a decrease in the North Island and an increase in the
South Island
increases of capacity during energy shortfalls.
During the FKC trial the following market-relevant matters were noted:
increases in generator governor action for South Island generators
the modulation risk caused an increase in market costs
the RIER compliance measure is no longer effective
generator compliance with dispatch and reserves is impacted by FKC operation.
During the FKC trial the following operational and technical issues were noted:
automated sending of dispatch instructions is no longer possible
an increase in sending of dispatches with 0 MW of MFK
starting and stopping FKC is a complex and manual process for system co-
ordinators
there are new and significant processes associated with HVDC live line
maintenance (RCBs)
time error tended to increase positively
time error separation with FKC between the North and South Islands.
The further actions the SO considers to be necessary following the FKC trial are divided
into recommendations for the Authority and recommendations for the SO. The ability of
both the SO and the Authority to progress the recommendations will be dependent on
budget and work programme priorities.
RECOMMENDATIONS FOR THE AUTHORITY 10.1
Recommendation 1 –The consequences of increased governor response should
be considered in a market context given the operational reliance now placed by
SO on that action during FKC operations.
Recommendation 2: Study the feasibility of a market solution which could
decide when it is economically efficient to enable FKC.
Recommendation 6 – Investigate a change to the business process and market
system tools associated with the activation and deactivation of FKC.
Recommendation 10 – Carry out economic studies to calculate the costs
implications of greater frequency deviations.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
48
Recommendation 12: Once the consequences of increased governor response
have been considered in a market context (Recommendation 1), consider the
quantity of MFK required for operation with FKC.
The SO has already discussed recommendations 1 and 10 with the Authority. The
Authority has initiated work to investigate these issues, its Normal Frequency
Management Strategy investigation.
RECOMMENDATIONS FOR THE SO 10.2
Recommendation 3 – After the future design for frequency keeping has been
completed undertake a study into using a new performance metric.
Recommendation 4 – Investigate whether the increase in generator governors
being off dispatch has a material effect on the quantity of reserve available for
under frequency events.
Recommendation 5: Once the Security Tools Project is completed, the SO
should carry out tests to see if, with FKC enabled, automatic dispatch can be re-
enabled.
Recommendation 7 – Following the Security Tools Project, investigate whether
FKC can remain enabled when RP is unavailable.
Recommendation 8 – Update the PI tool to receive generator dispatch data.
Carry out a study to consider how slow ramping generation affects the HVDC
being off dispatch with FKC enabled.
Recommendation 9 – The SO puts in place a testing regime for a full day of SFK
operation every six months, (when market conditions are suitable.)
Recommendation 11 – Undertake a review of under frequency reserves
requirements to cover the HVDC risks of loss of supply.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
49
APPENDIX A – FREQUENCY ANALYSIS
Frequency data from the trial period was collected for analysis. For comparison, data
was also collected from the time when FKC was not enabled. Table 7 details when the
data was collected.
Table 7
Frequency Data type Time data was sourced
FSC/SRS and MFK January and September 2014
FKC and MFK =30 January 2015
FKC and MFK = 0 22nd Dec 2014 to 24th Dec 2014
10th Feb 2015 to 17th Feb 2015
24th Feb 2015 to 10th March 2015
The frequency data for the above time periods is plotted in Figure 13 to Figure 16.
Figure 16 Zero MFK test period frequency data
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
50
Figure 13 North and South Island Frequency January 2014 with FKC off
Figure 14 North and South Island Frequency September 2014 with FKC off
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
51
Figure 15 North and South Island Frequency January 2015 with FKC on
Figure 16 Zero MFK test period frequency data
Statistical data for frequency across the analysed time period is presented below inTable
8 and Table 9. This is represented graphically as a normal distribution curve in Figure 17
and Figure 18.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
52
Table 8 NI Frequency Statistical Information
Max Min Average Median Average (absolute deviation)
Median (absolute deviation)
Standard Deviation
NI Pre-FKC Jan-14 50.29 49.71 50 50 0.049 0.039 0.063
NI Pre-FKC Sep-14 50.25 49.72 50 50 0.050 0.040 0.064
NI FKC Jan-15 50.22 49.77 50 50 0.026 0.020 0.034
NI 0 MFK Tests 50.21 49.76 50 50 0.032 0.025 0.041
Table 9 SI Frequency Statistical Information
Max Min Average Median Average (absolute deviation)
Median (absolute deviation)
Standard Deviation
SI Pre-FKC Jan-14 50.34 49.77 50 50 0.020 0.015 0.028
SI Pre-FKC Sep-14 50.41 49.78 50 50 0.026 0.020 0.035
SI FKC Jan-15 50.33 49.78 50 50 0.022 0.017 0.028
SI 0 MFK Tests 50.17 49.79 50 50 0.027 0.022 0.035
The data in Table 8 and Table 9 shows that without FKC North Island frequency deviation
is greater than South Island frequency deviation. However, with FKC on the deviations
of North and South Island are very similar.
It is evident from the standard deviations and Figure 15 that even with FKC on North
Island frequency still has more variation than South Island. This is expected as the
frequencies are linked through the FKC control system, which will have some lag and a
small dead band, so the frequencies are not exactly synchronized and a small aspect of
the FKC-off trend will remain.
Another point in the initial hypothesis was that the variation in South Island frequency
may worsen with the activation of FKC. Looking at the standard deviation, the values for
South Island are 0.028, 0.035, and 0.028 in January 2014, September 2014, and
January 2015 respectively. System load impacts frequency deviation and the load profile
for September is very different than the load profile for January, while January 2014 and
January 2015 have similar load profiles. Taking this into account, the data suggests FKC
has not had a significant effect on the normal frequency deviation of the South Island.
Comparing January 2014 and September 2014 data, we see South Island frequency
deviation is significantly affected by load. The North Island, however, does not appear to
have been affected. A likely reason for this is that industrial loads, being the main
contributors for North Island frequency deviation, operate almost all year round so the
effect of the rest of the load is not significantly observed.
The 0 MFK test periods data shows the quality of frequency keeping is not significantly
compromised with removal of MFK. The North Island data shows that although it
worsens from the FKC and MFK combination, it is still well below the variation observed
with FKC deactivated. South Island data shows a more severe drop increase in variation
without the contribution of MFK, however it is far off the variation observed without FKC.
It is important to note the above analysis does not fully take account of the difference in
load between the two periods. September has a much higher load than January and the
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
53
impact of this is unclear. The section on “Weighted average frequency deviation”
(below) provides insights on the effect of load with a weighted average frequency
deviation analysis.
Figure 17 NI Frequency band normal distribution comparison FKC on/off and 0 MFK test period
Figure 18 SI Frequency and normal distribution FKC on/off and 0 MFK test period
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
54
With FKC enabled North Island frequency deviation has improved and South Island
frequency deviation has deteriorated. To establish whether FKC provides an overall
benefit to frequency deviation across New Zealand a weighted average was used. The
weighted average was based on load.
The three formulae below describe the weighted average frequency deviation analysis.
∆𝑓𝑆𝐼_𝑤𝑒𝑖𝑔ℎ𝑡𝑒𝑑_𝑎𝑣𝑒𝑟𝑎𝑔𝑒 =∑
(∆𝑓𝑆𝐼 × 𝐿𝑜𝑎𝑑𝑆𝐼)𝐿𝑜𝑎𝑑𝑁𝑍
𝑃𝐼_𝑑𝑎𝑡𝑎_𝑝𝑜𝑖𝑛𝑡𝑠
∆𝑓𝑁𝐼_𝑤𝑒𝑖𝑔ℎ𝑡𝑒𝑑_𝑎𝑣𝑒𝑟𝑎𝑔𝑒 =∑
(∆𝑓𝑁𝐼 × 𝐿𝑜𝑎𝑑𝑁𝐼)𝐿𝑜𝑎𝑑𝑁𝑍
𝑃𝐼_𝑑𝑎𝑡𝑎_𝑝𝑜𝑖𝑛𝑡𝑠
∆𝑓𝐴𝑣𝑒𝑟𝑎𝑔𝑒 = ∆𝑓𝑆𝐼𝑤𝑒𝑖𝑔ℎ𝑡𝑒𝑑𝑎𝑣𝑒𝑟𝑎𝑔𝑒+ ∆𝑓𝑁𝐼𝑤𝑒𝑖𝑔ℎ𝑡𝑒𝑑𝑎𝑣𝑒𝑟𝑎𝑔𝑒
Where ∆𝑓 is the absolute value of frequency deviation from 50 Hz.
Table 10 shows the weighted average frequency deviation calculated for the time periods
presented earlier in section 5.2.
Table 10 Weighted Average Frequency Deviation
North Island South Island New Zealand
FKC off Jan-14
Weighted Average
Frequency Deviation (Hz)
0.030 0.008 0.038
FKC off Sep-14
Weighted Average
Frequency Deviation (Hz)
0.032 0.01 0.041
FKC on Jan-15
Weighted Average
Frequency Deviation (Hz)
0.015 0.008 0.024
0 MFK test periods
Weighted Average
Frequency Deviation (Hz)
0.019 0.010 0.030
The table shows that with FKC enabled the overall New Zealand frequency deviation has
improved. With 0 MFK the overall frequency deviation increases but is still significantly
better than when FKC is disabled.
As discussed in 8.1, time error was observed to have a randomly occurring positive bias
when FKC was in operation. This section compares the behaviour of time error with MFK
at its normal MW allocation of 30 MW, and MFK during the 0 MW tests.
Table 11 shows the time error statistical data comparing periods during the 0 MFK tests
and normal operation of FKC and MFK. Here we can see a clear trend between the
0 MFK tests and a greater time error – both negative and positive.
This follows logically from the frequency deviation analysis which shows with MFK not
operating there is a greater frequency deviation than with MFK operational. A higher
frequency deviation will integrate into a higher time error.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
55
Table 11 Time error statistical data during the 0 MFK tests and FKC and MFK operating normally
Total 0 MFK Tests NI
Total 0 MFK Tests SI
FKC period Jan-2015 NI
FKC period Jan-2015 SI
FKC period Oct-2015 NI
FKC period Oct-2015 SI
Average 0.1885 0.1923 0.0129 0.1257 -0.0501 0.1201
Median 0.147 0.1723 -0.0092 0.089 -0.0767 -0.0070
Deviation 0.6636 0.646 0.3717 0.3738 0.3978 0.3701
Time Analysed (mins) 33123 33123 33121 33121 33121 33121
% Time Below -2 0.0019 0.0016 0 0 0.0002 0.0000
% Time Below -1 0.0462 0.0301 0.0023 0.0019 0.0101 0.0019
% Time Below 0 0.4372 0.356 0.5093 0.3742 0.5937 0.5124
% Time Above 0 0.5628 0.644 0.4907 0.6258 0.4063 0.4876
% Time Above 1 0.0958 0.1154 0.0073 0.016 0.0136 0.0310
% Time Above 2 0.0069 0.0088 0.0001 0.0003 0.0000 0.0002
Figure 19 Time Error pdf function comparing 0 MFK tests and normal FKC/MFK operation
0
0.2
0.4
0.6
0.8
1
1.2
-3 -2 -1 0 1 2 3
PD
F
Time Error (s)
Time Error Probability Distribution Function comparing 0 MFK and FKC/MFK normal
operation
Total 0 MFK Tests North Island
Total 0 MFK TestsSouth Island
FKC and MFK period Jan-2015North Island
FKC and MFK period Jan-2015South Island
FKC and MFK period Oct-2015North Island
FKC and MFK period Oct-2015South Island
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
56
APPENDIX B – GENERATOR OFF-DISPATCH DATA
During the FKC trial, different modes of frequency keeping have been in operation, with
MFK being the most dominant as stated above.
Other operating arrangements are:
MFK operating with both islands controlled independently before FKC was enabled
single frequency keeping (SFK) in each island well before the FKC trial began.
throughout the FKC trial, frequency keeping tests were run for single frequency
keeper for the whole system and MFK with 0 MW dispatched
Table 12 (below) has a breakdown of the HVDC and frequency keeping mode
combinations applied during the FKC trial period.
The main periods for this analysis are 3 and 4, as they show a comparison with and
without FKC, and 5, the 0 MFK test. Periods 1, 2, 6, and 7 did not have sufficient data
points for a meaningful comparison.
Table 12 Frequency keeping and HVDC modes of operation during the FKC trial
Period
Number
Period Description
1 SFK, FSC/SRS SFK in each island
HVDC in FSC/SRS mode
2 NI MFK, SI SFK,
FSC/SRS
North Island in MFK mode, South
Island in SFK mode
HVDC in FSC/SRS mode
3 NI MFK, SI MFK,
FSC/SRS
North Island in MFK mode,
South Island in MFK mode,
HVDC in FSC/SRS mode
4 NI MFK, SI MFK, FKC North Island in MFK mode,
South Island in MFK mode,
Single source used for MFK
HVDC in FKC mode
5 NI MFK, SI MFK, FKC
- 0 MFK test
Zero frequency keeping test
HVDC in FKC mode
6 NI SFK, FKC - SFK
test
Single frequency keeper in the North
Island test
HVDC in FKC mode
7 SI SFK, FKC - SFK
test
Single frequency keeper in the South
Island test
HVDC in FKC mode
Table 13 shows averages for governor off-dispatch absolute values in pu. Table 14 and
Table 15 show the governor off-dispatch data for the FKC trial period in per unit (pu),
average and standard deviation have been taken for the key operation periods. Table 16
and Table 17 show the same information in MW. Note that for the MW values, it is not a
direct translation back to the pu values as the MW rating varies with time, depending on
which units are on the system. This also makes comparison of MW off-dispatch values
between time periods and between generators slightly less meaningful than comparing
the pu values.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
57
Figure 20 to Figure 26 show the governor off-dispatch deviation probability distribution
functions constructed from the calculated MW off-dispatch average and standard
deviation. The absolute value MW off-dispatch is also plotted on the same graphs.
Recognising asset owner confidentiality, the generation groups will be referred to as “SI
Group 1 – 3” for South Island generator groups and “NI Group 1 – 4” for North Island
generator groups.
The most meaningful measure presented here for governor activity comparison is the per
unit standard deviation. Looking at the data in Table 15 we see, as expected, FKC
improves the situation for the North Island and worsens it for the South Island. NI
Generator Group 1 stands out as an exception to this rule. A likely reason for this is that
the data for this group was largely unavailable for the periods where FKC was
deactivated making a meaningful comparison between periods difficult to achieve. Also,
NI Generator Group 3 shows slightly more activity without FKC. However, the values are
essentially equal so it is within an expected margin on error. The absolute value of MW
off-dispatch average in per unit also reflects this trend clearly in Table 13.
We also see in this analysis data for the 0 MFK tests which were performed throughout
the FKC trial. Three trials were executed totalling a time period of about three weeks.
The data for these periods sensibly suggest that generally the governors were off
dispatch more than with MFK in operation, especially for the South Island units. MFK,
although a slower response than FKC and governor droop control, will return the system
to 50 Hz and hence, the governors, back to their dispatch value.
The methodology of the calculation for the governor off-dispatch data is included in the
“Calculation diagram” of Appendix B – Generator off-dispatch data.
Table 13 Absolute MW off-dispatch in per unit average
Period 3 Period 4 Period 5 Period 3 or 4 worse?
SI Generator Group 1 0.47% 0.63% 0.91% Period 4
SI Generator Group 2 0.59% 0.67% 0.94% Period 4
SI Generator Group 3 0.35% 0.45% 0.70% Period 4
NI Generator Group 1 1.21% 1.78% 1.42% Period 4
NI Generator Group 2 0.95% 0.70% 0.68% Period 3
NI Generator Group 3 1.01% 0.92% 1.10% Period 3
NI Generator Group 4 1.79% 1.08% 1.17% Period 3
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
58
Table 14 MW off-dispatch in per unit average
Period 3 Period 4 Period 5 Period 3 or 4 worse?
SI Generator Group 1 0.18% -0.27% -0.31% Period 4
SI Generator Group 2 -0.48% -0.37% -0.40% Period 3
SI Generator Group 3 -0.06% -0.05% -0.08% Period 3
NI Generator Group 1 0.74% 1.25% 0.99% Period 4
NI Generator Group 2 -0.59% -0.51% -0.53% Period 3
NI Generator Group 3 -0.65% -0.52% -0.89% Period 3
NI Generator Group 4 -0.15% -0.22% -0.47% Period 4
Table 15 MW off-dispatch in per unit standard deviation
Period 3 Period 4 Period 5 Period 3 or 4 worse?
SI Generator Group
1
0.65% 0.85% 1.13% Period 4
SI Generator Group
2
0.50% 0.79% 1.15% Period 4
SI Generator Group
3
0.48% 0.61% 0.89% Period 4
NI Generator Group
1
2.90% 4.04% 3.22% Period 4
NI Generator Group
2
1.21% 0.83% 0.73% Period 3
NI Generator Group
3
0.94% 0.94% 0.90% Period 4
NI Generator Group
4
2.23% 1.40% 1.48% Period 3
Table 16 MW off-dispatch in MW average
Period 3 Period 4 Period 5 Period 3 or 4 worse?
SI Generator Group 1 1.14 -1.19 -1.59 Period 4
SI Generator Group 2 -2.72 -2.65 -2.74 Period 3
SI Generator Group 3 -0.70 -0.63 -0.95 Period 3
NI Generator Group 1 0.17 0.25 0.20 Period 4
NI Generator Group 2 -0.79 -0.90 -0.85 Period 4
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
59
Period 3 Period 4 Period 5 Period 3 or 4 worse?
NI Generator Group 3 -0.73 -0.26 -0.39 Period 3
NI Generator Group 4 -1.07 -1.39 -3.11 Period 4
Table 17 MW off-dispatch in MW standard deviation
Period 3 Period 4 Period 5 Period 3
or 4
worse?
SI Generator Group 1 3.69 4.14 5.77 Period 4
SI Generator Group 2 3.32 4.99 8.65 Period 4
SI Generator Group 3 6.03 7.87 11.21 Period 4
NI Generator Group 1 0.67 0.62 0.40 Period 3
NI Generator Group 2 2.43 1.49 1.29 Period 3
NI Generator Group 3 0.99 0.54 0.39 Period 3
NI Generator Group 4 14.74 8.02 8.14 Period 3
Figure 20 SI Generation Group 1 MW off-dispatch pdf function
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
60
Figure 21 SI Generation Group 2 MW off-dispatch pdf function
Figure 22 SI Generation Group 3 MW off-dispatch pdf function
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
61
Figure 23 NI Generation Group 1MW off-dispatch pdf function
Figure 24 NI Generation Group 2MW off-dispatch pdf function
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
62
Figure 25 NI Generation Group 3MW off-dispatch pdf function
Figure 26 NI Generation Group 4 MW off-dispatch pdf function
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
63
NORTH ISLAND – SOUTH ISLAND COMPARISON
Figure 27 to Figure 29 below shows a comparison of generator off dispatch data for the
generation groups for each operation period. The South Island generation groups are
shown in shades of blue and North Island generation are shown in shades of red.
Per unit values are used rather than MW to meaningfully compare different generation
groups with each other. However, in this comparison between generation groups,
factors affecting governor response such as droop and dead bands have not been
normalized across the generators which will affect how the governors react to frequency.
It should also be noted that the comparison between North and South Island generator
governors is between these few generation groups only, which are sensitive to frequency
deviations in the normal band. The comparison cannot be extended to other generators
many of which are not responsive to frequency in the normal band.
Figure 27 shows period 3 with MFK and FSC/SRS operation configuration. This shows
that during this time period the North Island generators were off dispatch comparatively
more than South Island. As has been discussed earlier, the North Island has more
frequency variation than the South Island, so it follows that the governors of the North
Island will regulate MW more than in the South Island.
Figure 28 shows period 4 with MFK and FKC operation configuration. This shows during
this time period the North Island and South Island generators were off dispatch at a
similar rate, with SI Group 3 and NI Group 4 slightly more extreme either way. The
higher alignment of the generators being off dispatch between the two islands is a
sensible outcome of the two island frequencies being aligned with FKC.
Figure 29 shows period 5 with FKC operating during the 0 MFK trials. This shows a
similar trend to period 4 of the North and South Island governors having roughly the
same activity. Compared to period 4, all generators are found to be more off dispatch
during period 5.
In summary, for these generation groups, the North Island governors are more active
than the South Island without FKC, and with FKC they are quite similar.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
64
Figure 27 Period 3 – MFK + FSC/SRS – MW off dispatch (pu) pdf
Figure 28 Period 4 – MFK + FKC – MW off dispatch (pu) pdf
0
10
20
30
40
50
60
70
80
90
-0.05 -0.03 -0.01 0.01 0.03 0.05
Pro
bab
iliy
De
nsi
ty F
un
ctio
n
MW off dispatch (pu)
Period 3 MW off dispatch (pu) pdf function
PDF Function SIGeneration Group 1
PDF Function SIGeneration Group 2
PDF Function SIGeneration Group 3
PDF Function NIGeneration Group 2
PDF Function NIGeneration Group 3
PDF Function NIGeneration Group 4
0
10
20
30
40
50
60
70
80
90
-0.05 -0.03 -0.01 0.01 0.03 0.05
Pro
bab
iliy
De
nsi
ty F
un
ctio
n
MW off dispatch (pu)
Period 4 MW off dispatch (pu) pdf function
PDF Function SIGeneration Group 1
PDF Function SIGeneration Group 2
PDF Function SIGeneration Group 3
PDF Function NIGeneration Group 2
PDF Function NIGeneration Group 3
PDF Function NIGeneration Group 4
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
65
Figure 29 Period 5 – 0 MFK test + FKC – MW off dispatch (pu) pdf
0
10
20
30
40
50
60
70
80
90
-0.05 -0.03 -0.01 0.01 0.03 0.05
Pro
bab
iliy
De
nsi
ty F
un
ctio
n
MW off dispatch (pu)
Period 5 MW off dispatch (pu) pdf function
PDF Function SIGeneration Group 1
PDF Function SIGeneration Group 2
PDF Function SIGeneration Group 3
PDF Function NIGeneration Group 2
PDF Function NIGeneration Group 3
PDF Function NIGeneration Group 4
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
66
CALCULATION DIAGRAM
Figure 30 shows the analysis of PI data undertaken to produce the results presented in Appendix B – Generator off-dispatch data.
Figure 30 Governor off-dispatch calculation diagram
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
67
APPENDIX C – FREQUENCY EXCURSION DETAILS
This appendix lists frequency excursions which occurred during the FKC trial. In all cases,
where an HVDC tripping was not the cause of the excursion, the HVDC operated as
expected to arrest the frequency in the affected island, passing some of the frequency
management burden to the unaffected island.
The high and low frequency excursions have been separated into two sections.
Frequency excursions involving the HVDC result in a high frequency swing in one island
and a low frequency swing in the other. These events have been categorised as an over
or under frequency event based on whichever swing was larger.
Table 18 lists the values represented by the PI tags plotted in the frequency excursion
plots in the following sections.
Table 18 Represented quantities by PI tags in frequency excursion plots
PI Tag Represented Quantity
P:BENPMU0582.FREQ South Island frequency
P:HAYPMU0592.FREQ / P:HLYPMU0522.FREQ North Island frequency
P:HAYPMU0842.MW Pole 2 MW south
P:HAYPMU0922.MW Pole 3 MW south
Table 19 lists the over frequency excursions during the FKC trial period.
Figure 31 to Figure 34 show PMU data for frequency and HVDC power output during the
frequency excursion events graphically.
Table 19 List of excursions which occurred during the FKC trial 16/10/2014 – 31/03/2015
Date/Time Event North Island Freq (Hz)
South Island Freq (Hz)
HVDC modulation (MW)
Figure Reference
04-Nov-2014
02:06
Tiwai planned
reduction 115 MW
50.33 50.51 70 MW Figure 31
27-Feb-2015
17:44
Tiwai emergency
potline trip
50.36 50.61 110 MW Figure 32
03-Mar-2015
13:31
Haywards F3B switch
out – HVDC power
limit ramp back from
395 MW to 280 MW
49.37 51.01 Power limit
forced ramp
back of
115 MW
Figure 33
24-Mar-2015
18:35
Tiwai emergency
potline trip
50.41 50.62 120 MW Figure 34
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
68
Figure 31 Tiwai potline planned reduction event 04/11/2014
Figure 32 Tiwai emergency potline trip event 27/02/2015
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
49.8
49.9
50
50.1
50.2
50.3
50.4
50.5
50.6
04-Nov-14 02:05:17 04-Nov-14 02:06:43 04-Nov-14 02:08:10
Fre
qu
en
cy (
Hz)
Time
Tiwai Potline Planned Reduction Event 4/11/2014
P:BENPMU0582.FREQ
P:HLYPMU0522.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
-340
-330
-320
-310
-300
-290
-280
-270
-260
-250
49.8
49.9
50
50.1
50.2
50.3
50.4
50.5
50.6
50.7
27-Feb-15 17:43:26 27-Feb-15 17:44:18 27-Feb-15 17:45:10
Fre
qu
en
cy (
Hz)
Time
Tiwai Potline Trip Event 27/02/2015
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
M
W
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
69
Figure 33 HAY F3B switch event 03/03/2015
Figure 34 Tiwai emergency potline trip event 24/03/2015
Table 20 lists the under-frequency excursions during the FKC trial period.
Figure 35 to Figure 39 show PMU data for frequency and HVDC power output during the
frequency excursion events graphically.
-250
-200
-150
-100
-50
0
49.2
49.4
49.6
49.8
50
50.2
50.4
50.6
50.8
51
51.2
03-Mar-15 13:30:43 03-Mar-15 13:32:10 03-Mar-15 13:33:36
Fre
qu
en
cy (
Hz)
Time
HAY F3B Switch Event 03/03/2015
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
-300
-250
-200
-150
-100
-50
0
50
49.8
49.9
50
50.1
50.2
50.3
50.4
50.5
50.6
50.7
24-Mar-15 18:34:34 24-Mar-15 18:36:17 24-Mar-15 18:38:01
Fre
qu
en
cy (
Hz)
Time
Tiwai Potline Trip Event 24/03/2015
P:BENPMU0582.FREQ
P:HLYPMU0522.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
70
Table 20 List of excursions which occurred during the FKC Trial 16/10/2014 – 31/03/2015
Date/Tim
e
Event North
Island
Freq (Hz)
South
Island
Freq (Hz)
HVDC
modulatio
n (MW)
Figure
Reference
31-Oct-
2014
22:25
Generation co-
ordination centre data
entry issue
49.58 49.43 75 MW Figure 35
15-Nov-
2014
05:51
Pole 2 trip 50.40 48.81 Pole 2
tripped at
100 MW
Figure 36
15-Nov-
2014
06:13
Pole 3 stop 50.12 49.44 Pole 3
stopped at
35 MW
Figure 37
06-Jan-
2015
13:46
NI generation trip 49.43 49.55 60 MW Figure 38
23-Feb-
2015
01:51
NI generation trip 49.50 49.58 45 MW Figure 39
Figure 35 Co-ordination centre data entry issue event 31/10/2014
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
49.2
49.4
49.6
49.8
50
50.2
50.4
50.6
31-Oct-14 22:24:58 31-Oct-14 22:26:24 31-Oct-14 22:27:50
Fre
qu
en
cy (
Hz)
Time
Control Centre Data Entry Issue Event 31/10/2014
P:BENPMU0582.FREQ
P:HLYPMU0522.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
71
Figure 36 Pole 2 trip event 15/11/2014
Figure 37 Pole 3 stop event 15/11/2014
-50
0
50
100
150
200
250
48.6
48.8
49
49.2
49.4
49.6
49.8
50
50.2
50.4
50.6
15-Nov-14 05:51:22 15-Nov-14 05:52:05 15-Nov-14 05:52:48
Fre
qu
en
cy (
Hz)
Time
Pole 2 Trip Event 15/11/2014
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
-50
0
50
100
150
200
250
48.6
48.8
49
49.2
49.4
49.6
49.8
50
50.2
50.4
50.6
15-Nov-14 06:11:31 15-Nov-14 06:13:15 15-Nov-14 06:14:59
Fre
qu
en
cy (
Hz)
Time
Pole 3 Stop Event 15/11/2014
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
72
Figure 38 NI generation trip event 06/01/2015
Figure 39 NI generation trip event 23/02/2015
-270
-250
-230
-210
-190
-170
-150
49.3
49.4
49.5
49.6
49.7
49.8
49.9
50
50.1
50.2
06-Jan-15 13:45:50 06-Jan-15 13:46:34 06-Jan-15 13:47:17
Fre
qu
en
cy (
Hz)
Time
NI Generation Trip Event 06/01/2015
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
49.4
49.5
49.6
49.7
49.8
49.9
50
50.1
50.2
50.3
23-Feb-15 01:50:53 23-Feb-15 01:51:36 23-Feb-15 01:52:19
Fre
qu
en
cy (
Hz)
Time
NI Generation Trip Event 23/02/2015
P:BENPMU0582.FREQ
P:HAYPMU0592.FREQ
P:HAYPMU0842.MW
P:HAYPMU0922.MW
MW
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
73
APPENDIX D – POSITIVE TIME ERROR TREND
This appendix discusses some potential causes of the positive time error trend
investigated throughout the FKC trial. Most of the analysis was completed using PI data
which presents some difficulties:
when assessing historical data it is difficult to determine which behaviour occurs
naturally from the system and which behaviour is due to co-ordinator
intervention. Even if it could be inferred from the data, isolating that information
when looking at data statistically is difficult
PI data time stamps are not aligned completely so certain correlations may not be
represented correctly.
During the trial it was noted at times that time error appeared to increase more during
periods in which load was decreasing. This appears logical as when load is ramping
down generation will react to frequency increase due to the reduced load and adjust
MW’s accordingly. If this occurs continuously over an extended period of time the
momentary frequency increase would accumulate into an increasing time error.
To assess this, data from 16/10/2014 to 13/01/2015 was analysed during the periods
when FKC was on. A rate of change of load (∆𝑀𝑊
𝑑𝑡) – MW value normalized against peak
for the day - and a rate of change of time error (∆𝑇𝑖𝑚𝑒𝐸𝑟𝑟𝑜𝑟
𝑑𝑡) was taken for each time
instant and plotted against one another.
Note that ∆𝑇𝑖𝑚𝑒𝐸𝑟𝑟𝑜𝑟
𝑑𝑡 here is not frequency, it is the rate of change of time error trend from
PI data at a scale which is not meaningful to translate back to frequency values.
For this theory to have weight, we expect to see an approximately inverse linear
relationship between ∆𝑀𝑊
𝑑𝑡 and
∆𝑇𝑖𝑚𝑒𝐸𝑟𝑟𝑜𝑟
𝑑𝑡. Figure 40 and Figure 41 show
∆𝑇𝑖𝑚𝑒𝐸𝑟𝑟𝑜𝑟
𝑑𝑡 vs
∆𝑀𝑊
𝑑𝑡
plots for single days from the period mentioned above. Here a very rough trend can be
observed representing what is expected. Many other days were looked at and the trend
was not evident at all.
Figure 42 shows the ∆𝑇𝑖𝑚𝑒𝐸𝑟𝑟𝑜𝑟
𝑑𝑡 vs
∆𝑀𝑊
𝑑𝑡 plot for the whole period, here it is difficult to say
that a trend is observed.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
74
Figure 40 Rate of change of time error vs the rate of change of normalized MW over day 5/01/2015
Figure 41 Rate of change of time error vs the rate of change of normalized MW over day 14/01/2015
-0.02 -0.015 -0.01 -0.005 0 0.005 0.01 0.015 0.02-0.8
-0.6
-0.4
-0.2
0
0.2
0.4
0.6
Rate of change of MW (normalized)
Rate
of
change o
f T
ime E
rror
-0.04 -0.03 -0.02 -0.01 0 0.01 0.02 0.03 0.04-0.4
-0.2
0
0.2
0.4
Rate of change of MW (normalized)
Rate
of
change o
f T
ime E
rror
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
75
Figure 42 Rate of change of time error vs the rate of change of normalized MW
North Island industrial load has a significant effect on frequency behaviour. Time periods
were analysed with certain North Island industrial loads on and off and the effect on time
error deviation has been assessed. The periods North Island industrial loads are not
operational are weekends and the Christmas / New Year period.
The data, both with and without this North Island industrial load, shows:
the absolute value of the maximum time error is significantly larger than the
minimum
significantly more time is spent with time above 1 second than below 1 second
the ratio of time positive compared to time negative in each island is not
materially affected by the North Island industrial load.
The differences observed with and without North Island industrial load are:
standard deviation is significantly lower for both the North Island and South
Island with North Island industrial load off
time error barely exceed 2 seconds with North Island industrial load off
time error spends significantly more time greater than 1 second with North Island
industrial load on than with North Island industrial load off
Other conclusions may be drawn from the data, but it is difficult to determine what is
influenced by system co-ordinator intervention and what the power system’s natural
behavior is. Overall we can say that although North Island industrial load aggravates the
situation, the same pattern is observed even when the load is off.
-0.05 -0.04 -0.03 -0.02 -0.01 0 0.01 0.02 0.03 0.04-0.8
-0.6
-0.4
-0.2
0
0.2
0.4
0.6
0.8
1
Rate of change of MW (normalized)
Rate
of
change o
f T
ime E
rror
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
76
Table 21 Time Error Statistical Analysis NI/SI with North Island industrial load on and off
NI - North
Island
industrial load
Off
SI - North
Island
industrial load
Off
NI - North
Island
industrial load
On
SI - North
Island
industrial load
On
max 1.968 2.325 2.865 2.878
min -1.365 -1.295 -2.059 -2.014
average 0.000 0.137 0.096 0.246
median -0.020 0.122 0.014 0.157
standard
deviation
0.363 0.382 0.535 0.525
data points
(PI data 1
minute
resolution)
25445 25445 36005 36005
time above
2s %
0.00% 0.10% 0.41% 0.59%
time above
1s %
0.61% 1.72% 6.22% 8.18%
time positive
%
47.51% 63.98% 51.54% 67.61%
time
negative %
52.49% 36.02% 48.46% 32.39%
time below
1s %
0.13% 0.66% 1.44% 0.56%
time below
2s %
0.00% 0.00% 0.01% 0.00%
Asymmetries in governor gate opening/closing may rates cause a difference in
over/under frequency correction speed.
Some governors may have faster or slower gate opening rates than closing rates which
could affect the rate at which frequency was corrected whether it was high or low. If a
significant number of governors had slower closing rates than opening rates, over-
frequency would be corrected slower and hence accumulate into an increasing frequency
Looking into the governor models, this was not found to be so. For most governors
which had different opening and closing rates, they had faster closing than opening
rates. If they were having an effect faster closing rates would lead to a negative rather
than positive trending time error.
To examine whether the change in load was causing the time error issue a dynamic
power flow was undertaken in TSAT.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
77
In the power flow a load was stepped up, allowing the frequency to settle, then stepped
down. This was done repeatedly over about 600 seconds. The time error was extracted
from the data and not found have an increasing trend.
Figure 43 is an example of the simulation stepping Stoke-33 load up by 45 MW, and
down by 45 MW. This is done repeatedly in 60 second intervals over about 700 seconds.
Figure 43 shows the frequency, time error, and one of the two Stoke 33 active power
loads simulation results.
Looking at the frequency and time error plots, we can see there is no significant creeping
of time error and frequency stays roughly centred at 50 Hz.
The results show that, in the simulation, there was no link between FKC, load steps and
time error trending positive was found.
Figure 43 TSAT STK33 Load step simulation frequency, time error and STK33 load results
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
78
Other matters were considered and determined to have no conclusive link to the time
error issue:
MFK dead band:
the effect of the MFK dead band was considered. It was hypothesised
the time spent above/below 50 Hz and inside the MFK dead band may
contribute to accumulating time error
it was found the amount of time frequency was between 50 Hz and
within the 0.01 Hz MFK dead band was insignificant and could not be
contributing to accumulating time error.
the daily peak trend:
the daily peak trend was trending downwards towards the summer
trough period over Christmas and New Year. The load trending
downwards was analysed for an effect on time error trending positive.
No data suggested that the daily peak trend is a plausible cause.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
79
APPENDIX E - USING HVDC FREQUENCY OFFSET FROM
HMI TO MINIMISE TIME ERROR DIVERGENCE
As discussed in section 8.3, North and South Island time errors diverged consistently
during the FKC trial. While they consistently diverged, the gradient at which they
diverged was consistent for only a few days at a time. It is still unclear what affects the
gradient at which the time errors diverge. However, it has been observed the rate
remains consistent over extended periods of time.
During the FKC trial, whenever the time errors were separated by a significant amount a
10 mHz frequency offset in the HVDC HMI was applied to one of the island frequency
sources used by the HVDC. This caused the time error between the two islands to rapidly
converge. On the 27th December 2014, a 1 mHz offset was applied to attempt to counter
the time error divergence and prevent it from occurring at all, or at least reduce the
gradient as much as possible.
Looking at the data a gradient of time error divergence can be taken which can be back-
calculated to a constant frequency difference between the two islands. The formula
below describes the relationship between time error divergence and equivalent frequency
offset. The unit seconds/day for time error divergence has been chosen as it is
convenient for interfacing with MS Excel time format where “1” represents one day.
∫𝑓𝑒𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝑜𝑓𝑓𝑠𝑒𝑡
50𝑑𝑡 = 𝑇𝑖𝑚𝑒_𝐸𝑟𝑟𝑜𝑟_𝐷𝑖𝑣𝑒𝑟𝑔𝑒𝑛𝑐𝑒 (
𝑠𝑒𝑐𝑜𝑛𝑑𝑠
𝑑𝑎𝑦)
𝑆𝑒𝑐𝑜𝑛𝑑𝑠 𝑖𝑛 𝑑𝑎𝑦
0
On 27/12/2014 a 1 mHz offset was applied to the HVDC frequency offset. Looking at the
gradients we can analyse its effect. The following discussion is based on the data
presented graphically in Figure 44.
The initial gradient of time error divergence is -1.55 seconds/day. This corresponds to a
frequency offset of approximately -0.902 mHz.
A 1 mHz frequency offset was applied which resulted in time error drifting the opposite
direction at a measured rate of 0.13 seconds/day which is equivalent to a frequency
offset of about 0.075 mHz. This is expected as 0.075 + 0.902 = 0.977 mHz, which given
the noise in the measured gradient is close enough to the 1 mHz offset which was
applied to the HMI.
The gradient then changed at about midday on 28/12/2014 to 1.93 seconds/day which
corresponds to a frequency offset of about 1.115 mHz. The 1 mHz offset was then
removed and a gradient of 0.068 seconds/day was measured, corresponding to a
frequency offset of about 0.039 mHz. Once again this is expected, as 1.115 – 0.039 =
1.076 mHz which basically corresponds to the 1 mHz offset applied to the HMI. The
remaining 0.076 mHz is likely due to fluctuation in the 1.115 mHz measurement data, as
it is a short measurement time, the fluctuation has a greater impact on the accuracy of
the calculated gradient.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
80
Figure 44 Time error trend with 1 mHz offset applied 26/12/2014 – 30/12/2014
From this we can deduce the HVDC frequency offset input can be used to counter time
error divergence and will be effective.
Even before the offset was applied, the rate of divergence was very high and required
converging multiple times a day. The minimum offset of 1 mHz was still too course to
balance it out accurately. With lower rates of divergence this will be more of an issue.
Applying a frequency offset to the HVDC control can be effectively used to counter time
error drift. Also discussed in Appendix E - Using HVDC frequency offset from HMI to
minimise time error divergence was that the minimum 1 mHz step is too course to
provide for all but the most severe time error divergence gradients.
To allow the time error divergence gradient to be countered in a more refined way, an
update to the HVDC HMI is currently underway to allow decimal places to be input in the
“Frequency Offset from HMI” input fields (shown in Figure 45). The HVDC control system
was assessed for capability to be able to accurately process inputs in the µHz range, so
all that is required is to update the input field to accept decimal places.
Unlocking this capability will allow more accurate adjustments to be made. For example,
in the case study discussed in Figure 44, an offset of 0.9 mHz would have countered the
time error divergence to almost 0 seconds/day, rather than sending it in the opposite
direction at a reduced rate. More importantly, it would allow lower gradients of time
error divergence to be countered effectively.
SYSTEM OPERATOR REPORT: FREQUENCY KEEPING CONTROL TRIAL REPORT
81
Figure 45 HVDC HMI frequency offset to be adjusted
A tool is being developed to streamline the calculation of the correct value to be input
into the HVDC frequency offset field. When implemented the tool will automatically
generate a recommended value based on time error PI data. It will be made available to
system co-ordinators and provide consistent methodology for managing the time error
divergence issue.