    CONSERVATION OF OLD FREE MASONS LODGE /

    ESTABLISHMENT OF WILD LIFE MUSEUMKARACHI 35.291 (M)

  • 8/8/2019 Free Mason Lodge Karachi

    2/74

    2

  • 8/8/2019 Free Mason Lodge Karachi

    3/74

    CONSERVATION OF OLD FREE MASONS LODGE /

    ESTABLISHMENT OF WILD LIFE MUSEUM KARACHI

  • 8/8/2019 Free Mason Lodge Karachi

    4/74

    4

    MAIN BUILDING VIEWS BEFORE

    CONSERVATION PROCESS

  • 8/8/2019 Free Mason Lodge Karachi

    5/74

    5

  • 8/8/2019 Free Mason Lodge Karachi

    6/74

    6

  • 8/8/2019 Free Mason Lodge Karachi

    7/74

    AA Issued on 11th-March,08

    (a) Special project management/consultant arrangement got approved

    (b) Project management awarded

    (c) Tenders Invited

    CONSERVATION OF OLD FREE MASONS

    LODGE / ESTABLISHMENT OF WILD LIFE

    MUSEUM KARACHI

  • 8/8/2019 Free Mason Lodge Karachi

    8/74

    Conservation issues

    Many rooms & hall are still in wild lifes Department

    possession, causing hindrance in the process of

    conservation of the building

    Encroached Party adjacent to the protected

    monument

    Extension of landscaping zone in the eastern-

    southern area

    Major Issues

  • 8/8/2019 Free Mason Lodge Karachi

    9/74

  • 8/8/2019 Free Mason Lodge Karachi

    10/74

    adjacent to the protected monument

    Extension of landscaping zone in theeastern-southern area

  • 8/8/2019 Free Mason Lodge Karachi

    11/74

    REMOVAL OF NEW ADDITIONS BY WILD LIFEDEPARTMENT

    Masonry WallsServant Quarters Wash Rooms Marble & Mosaic Tiles

    RCC ceilings Replacement of GrillsElectrification, Plumbers & Sewerage Work Wash Rooms, Servant QuartersNewly concrete Structure

  • 8/8/2019 Free Mason Lodge Karachi

    12/74

    12

  • 8/8/2019 Free Mason Lodge Karachi

    13/74

    13

    Existing Ground Floor

    Existing First Floor

  • 8/8/2019 Free Mason Lodge Karachi

    14/74

    14

    EXISTINGELEVATIONS

  • 8/8/2019 Free Mason Lodge Karachi

    15/74

    15

  • 8/8/2019 Free Mason Lodge Karachi

    16/74

    16

  • 8/8/2019 Free Mason Lodge Karachi

    17/74

    17roposed Site Plan

  • 8/8/2019 Free Mason Lodge Karachi

    18/74

    18

    Proposed Ground Plan

  • 8/8/2019 Free Mason Lodge Karachi

    19/74

    19

    Proposed First Floor

  • 8/8/2019 Free Mason Lodge Karachi

    20/74

    20

    Proposed First Floor(Flooring)

  • 8/8/2019 Free Mason Lodge Karachi

    21/74

  • 8/8/2019 Free Mason Lodge Karachi

    22/74

    22

    Proposed Section 1

  • 8/8/2019 Free Mason Lodge Karachi

    23/74

    23

    Proposed Section 2

  • 8/8/2019 Free Mason Lodge Karachi

    24/74

    24

    Cafeteria, Lecture Hall ,Rest Rooms

  • 8/8/2019 Free Mason Lodge Karachi

    25/74

    REMOVAL OF OLD MORTAR & CEMENT & LIME PLASTER

    STONE WORK

    PLUMBING WORK

    CONTROLLING OF DAMPNESS RISING

    ALTERATION OF ARCHES

    REMOVAL OF ADDITIONAL ROOMS

    WOOD WORK TREATMENT

    ADDITIONS OF MISSING ELEMENTS

    Work Plan for Entire Building

  • 8/8/2019 Free Mason Lodge Karachi

    26/74

    26

    ISSUES: LAYERS OF

    PLASTER

    Wrong Application of Multilayers of Plaster is done withthe passage of time

  • 8/8/2019 Free Mason Lodge Karachi

    27/74

    27

    ISSUE: PILASTER REMOVING

  • 8/8/2019 Free Mason Lodge Karachi

    28/74

    28

    REMOVING OF INNER LIBARAYS

    PILASTER

    The inner cemented pilasterlayer is removed from thelibrary later lime pilaster wouldbe applied

  • 8/8/2019 Free Mason Lodge Karachi

    29/74

    29

    LIME PILASTER

    Aggregates of lime pilaster which areusing are

    1. Lime2. Jute3. Sand

    4. Water

    After mixing of aggregates an initiallayer of pilaster around 1.5 inch

    thick is applied on the wall of rareside of library after one week

    another layer of pilaster will beapplied

  • 8/8/2019 Free Mason Lodge Karachi

    30/74

    APPLYING NEW LIME PILASTER

  • 8/8/2019 Free Mason Lodge Karachi

    31/74

    31

    ISSUE: TRACES of RISING DAMPNESS

    DRAIN FOR CONTROLLING A drain was excavated to control rising

  • 8/8/2019 Free Mason Lodge Karachi

    32/74

    32

    DRAIN FOR CONTROLLING

    RISING DAMP

    A drain was excavated to control risingdampness in parallel with the foundationof the building

  • 8/8/2019 Free Mason Lodge Karachi

    33/74

    33

    REMOVAL OF WOODEN PARTITION

    BEFORE AFTER

  • 8/8/2019 Free Mason Lodge Karachi

    34/74

    34

    REMOVAL OF CORRUGATED GI SHEETAdditional roof of GI sheets at verandah or passages are removed

    and it will serve as open to sky which was its original form

    AFTER BEFORE

    f f

  • 8/8/2019 Free Mason Lodge Karachi

    35/74

    35

    Removal of improper Installation of Air Conditioning Units:

    Outdoor units are removed

    which are placed in thewindows and proper space isdefined for outlet units

  • 8/8/2019 Free Mason Lodge Karachi

    36/74

    REMOVAL OF WASH ROOM AREA

    Removal of newly addition washroomWould be removed to get the originalityOf the building

    REMOVAL OF CEMENT PLASTER FROM ROOF

  • 8/8/2019 Free Mason Lodge Karachi

    37/74

    37

    REMOVAL OF CEMENT PLASTER FROM ROOF

    A layer of cement pilaster

    around 2 inches thick isremoved from the top of theroof of library

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    38/74

    38

    REMOVING OF EXISTING

    ECLECTIC CHANNELING

    WIRING

    Removing of existingeclecticchanneling wiring is

    happening from the libraryas the wires are damage andnew installation will be doneof electric wiring

  • 8/8/2019 Free Mason Lodge Karachi

    39/74

    39

    UNWANTED VEGETATIONS CUTTING

  • 8/8/2019 Free Mason Lodge Karachi

    40/74

    BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    41/74

    AFTER UNWANTED VEGETATIONS CUTTING

    REPLACING PLINTHS STONE

  • 8/8/2019 Free Mason Lodge Karachi

    42/74

    REPLACING PLINTHS STONE

    During Working Before

  • 8/8/2019 Free Mason Lodge Karachi

    43/74

    REPLACING PLINTHS STONE

  • 8/8/2019 Free Mason Lodge Karachi

    44/74

  • 8/8/2019 Free Mason Lodge Karachi

    45/74

    The newly stone is manually chiseledand then applied at the plinth of thebuilding

    MANUAL CHIESELING OF DRESSED STONE

  • 8/8/2019 Free Mason Lodge Karachi

    46/74

    46

    STONE CHISLING

    Stone of exterior faade is chiseled from the entire building And limepointing is done on overall faade

    AFTER BEFORE

    MORTAR POINTING

  • 8/8/2019 Free Mason Lodge Karachi

    47/74

    47

    MORTAR POINTINGThree types of Sampling of grouting is donebetween the stone block1. Flash2. Recessed

    3. EjectedOne of it will be applied on the walls wherever

    necessary

    Causes to the erosion ofmortar joint is presence ofsalt, crystallization, scouringaction of winds; anddisintegrating effect ofplants growing on a wall andwater penetration leading tothe concentration ofmoisture and dampness.

    POINTING OF STONE MASONRY

  • 8/8/2019 Free Mason Lodge Karachi

    48/74

    48

    POINTING OF STONE MASONRY

    Due to later intervention alayer of cement pilasterwhich was used earlier is

    removed now

    Now the pointing betweenstone would be used

  • 8/8/2019 Free Mason Lodge Karachi

    49/74

  • 8/8/2019 Free Mason Lodge Karachi

    50/74

    DURING WORKING

  • 8/8/2019 Free Mason Lodge Karachi

    51/74

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    52/74

  • 8/8/2019 Free Mason Lodge Karachi

    53/74

    STONE CHIESELING AT FACADE

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    54/74

    STONE CHIESELING AT FACADE

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    55/74

    NEW FLOOR IS INSTALL

    New floor is laying of same pattern

    of original one which was usedearlier having same color andcomposition

    Before After

  • 8/8/2019 Free Mason Lodge Karachi

    56/74

    57

    FLOORING

    BEFOREAFTER

    TERMITE ATTACKS WOOD:

  • 8/8/2019 Free Mason Lodge Karachi

    57/74

    58

    Insect or termite attack is a majorproblem in wild life building it happensin a damp and digestible timber. It

    causes soften a timber and formfurther cracksit is dangerous to leave the timberwhich may insects or termite holebecause they may soften the timberand form further cracks.

    The decayed timber is removed andnew frames were fixed with anti termitesolution

    NEW FRAMES OF DOORS & WINDOWS

  • 8/8/2019 Free Mason Lodge Karachi

    58/74

    59

    NEW FRAMES OF DOORS & WINDOW S

    Some of the frames are badlyabused with serious damagedon surfaces and deteriorated;

    leading to further structuralproblem and unsafe tooccupants the main cause to thedeterioration are insects andtermite attacks and unqualifiedhuman intervention

    New frames for doors &windows are fixing at groundand first floor

    NEW PANELS AND FRAMES FOR WINDOWS

  • 8/8/2019 Free Mason Lodge Karachi

    59/74

    NEW PANELS AND FRAMES FOR WINDOWS

    New panels and frames for windows

    Are making at the site of samereplicasOf original one

  • 8/8/2019 Free Mason Lodge Karachi

    60/74

    NEW POLISHED DOORS

    New doors are fixed and polished at

    Sindh Wild Life

    PARAPET AT FIRST FLOOR

  • 8/8/2019 Free Mason Lodge Karachi

    61/74

    62

    Existing parapet would be

    removed and new parapetwould be built with samedesign and pattern

    DURING WORKING

    BEFORE

    PARAPET AT FIRST FLOOR

  • 8/8/2019 Free Mason Lodge Karachi

    62/74

    63AFTER BEFORE

    WATER OUTLET PIPE

  • 8/8/2019 Free Mason Lodge Karachi

    63/74

    WATER OUTLET PIPE

    USED AT THE PARAPET

    A water outlet pipe for drainage isusedFixed at the parapet wall

    Removing of inner library's pilaster

  • 8/8/2019 Free Mason Lodge Karachi

    64/74

    65

    The inner cemented pilasterlayer is removed from thelibrary later lime pilaster

    would be applied

    BEFORE

    DURING WORKING

    Removing of inner library's pilaster

  • 8/8/2019 Free Mason Lodge Karachi

    65/74

    66

    The inner cemented pilaster layer is removedfrom the library later lime pilaster would beapplied

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    66/74

  • 8/8/2019 Free Mason Lodge Karachi

    67/74

  • 8/8/2019 Free Mason Lodge Karachi

    68/74

    CENTRAL HALL OPENING ON TOP OF

    DOOR

    wooden Framing is done on top of archopenings of display hall

    Before After

  • 8/8/2019 Free Mason Lodge Karachi

    69/74

    RE-CREATION OF MISSINGARCHITECTURAL FEATURES

  • 8/8/2019 Free Mason Lodge Karachi

    70/74

    RE STRENGTHING OF CENTRAL STAIRCASE

  • 8/8/2019 Free Mason Lodge Karachi

    71/74

    RE-STRENGTHING OF CENTRAL STAIRCASE

    Temporary support for centralstaircase

    Is provided as the staircase is leaningalong one side

    BEFORE AFTER

  • 8/8/2019 Free Mason Lodge Karachi

    72/74

    CLEANING OF PLAQUE

  • 8/8/2019 Free Mason Lodge Karachi

    73/74

    AFTER BEFORE

  • 8/8/2019 Free Mason Lodge Karachi

    74/74

    THANK YOU

    For More detail please Visit:www.sindh.gov.pk/dpt/Antiquities/index.htmOr contact atDepartment of Antiquities