FREDERICKSBURG DISTRICTDistrict Engineer Marcie Parker, P.E.
May 8, 2018
3
Interstate 95 ProjectsFredericksburg Area
Fredericksburg region
will see greatest degree
of I-95 construction
since widening in 1980s
4
Interstate 95 ProjectsFredericksburg Area
7 major I-95 projects finished by 2023:
• Exit 140 Diverging Diamond Interchange and Widening
• I-95 Express Lanes Fredericksburg Extension
• I-95 Rappahannock River Crossing – Southbound and Northbound (2)
• I-95 Safety Improvements at Route 3
• Exit 118 Reconstruction
• I-95 Bridges Rehabilitation
PLUS: New commuter parking, regional road projects and bridge
replacements
$1 billion in highway corridor investment
5
6
Calendar Year
2018 2019 2020 2021 2022 2023 2024
Exit 140 – Diverging Diamond Interchange
I-95 Express Lanes Fredericksburg Extension “Fred Ex”
I-95 Southbound Rappahannock River Crossing
I-95 Northbound Rappahannock River Crossing (estimated)
Route 3 Safety
at Exit 130
Exit 118 Interchange at
Thornburg
I-95 Bridge
Rehabilitation
All
new
lanes
open
to
traffic
7
Exit 140 Diverging Diamond Interchange, Stafford County
$185.3 million
Widens
Courthouse Road
to 4 lanes
New interchange
design reduces
conflict points,
improves
traffic flow
Complete July
2020
8
I-95 Express Lanes Fredericksburg Extension (FredEx)
9
• Fully funded by Transurban
• Extends I-95 Express Lanes 10 miles south to Route
17 interchange
• Two reversible lanes – tolled facility
• Connects with I-95 Rappahannock River Crossing
projects
• Replaces American Legion and Truslow Road
overpasses
• New Express Lanes access at I-95 interchanges at
Route 17, Courthouse Road, and Quantico (Russell
Road)
• Construction Spring 2019 - Fall 2022
10
I-95 Southbound Rappahannock River Crossing
• Construction on $125 million project begins August 2018
• Converts 3 existing lanes to local lanes on I-95
southbound
• In the median, 3 thru traffic lanes will be built on I-95
southbound
• New lanes start north of Route 17 interchange in
Stafford and continue south past Route 3 interchange in
Fredericksburg/Spotsylvania
• New bridge to be built over the Rappahannock River to
carry thru lanes in the median
• Replaces Route 17 overpasses in Stafford
11
I-95 Southbound Rappahannock River Crossing
12
I-95 Northbound Rappahannock River Crossing
Funding
announced
January 10, 2018
$132 million
budget
Adds lane capacity
to I-95 northbound
between Route 3
and Route 17
Interchange
Modification Report
(IMR) underway
13
I-95 Safety Improvements at Route 3$21 million federally-
funded safety project
Reduces merging and
weaving at Exit 130
and Route 3
interchange
Triple right turn lanes
to Route 3 westbound,
controlled by signal
New free-flow lane to
Central Park tracking
to open in June 2018
14
I-95 Safety Improvements at Route 3
Triple left turn lanes
on Route 3 eastbound
to I-95 NB
New signal at I-95
northbound ramp
entrance
Current cloverleaf
ramp will close
Project completion by
January 2019
15
Exit 118 Overpass and Interchange Improvements
New 4-lane overpass
improves sight distance on
Mudd Tavern Road
Replaces structurally
deficient bridge
Improves
interchange ramp
configuration
Aligns with SMART SCALE
widening, access
management project to west
Completion of $22.4 million
project by September 2019
16
Maryland Transportation Authority (MDTA)
owned, operated
Type: Design-Build Procurement
Project Budget: $765 million
Request for Qualifications: October 2018
Request for Proposals: March 2019
Virginia Commitment: $13 million
Governor Harry W. Nice Bridge Replacement
17
Route 301 and Route 207 CorridorArterial Management Plan
18
• 42-mile corridor
• Potomac River in King George County to
Route 1 in Caroline County
• Prepare for heavier traffic anticipated with opening
of new, expanded Nice Bridge
• Alternative to Interstate 95
• Set expectations for future economic development
• Reduces need for retrofit projects
• Recommends access, intersection and crossover
improvements
• Final report in June 2018
Chatham Bridge Rehabilitation ProjectCity of Fredericksburg, Stafford County
$22 million
Improves bridge condition by
replacing superstructure
Adds 10 ft. wide shared use path
separated from traffic by barrier
Two travel lanes in each direction –
10 ft. wide
Construction begins early 2021
Bridge will be closed during
construction
19
Virginia Department of Transportation
Chatham Bridge Rehabilitation Project
20
Virginia Department of Transportation
Chatham Bridge Rehabilitation Project: Detour Map
21
• Route 1 and Telegraph Road/Woodstock Lane
• Route 1 and Courthouse Road
• Route 1 and Potomac Creek Drive
• Route 301 Northbound and Southbound Turn Lanes at Dahlgren
• Courthouse Road and Hood Drive Intersection
• Lafayette Boulevard and Harrison Road
• Ladysmith Road and Partlow Road Safety Improvements
Fredericksburg District ProjectsIntersection, Turn Lanes
22
Stafford
King George
Spotsylvania
Caroline
• Route 606 (Mudd Tavern Road) Widening
• Route 639 (Ladysmith Road) Widening
• Virginia Central Railway Bridge
• Twin Lake Drive – Kensington Pedestrian Connector
23
Fredericksburg District Projects
Spotsylvania
Caroline
Widening Projects
Pedestrian and Trail Projects
City of Fredericksburg
I-95 Southbound Ramp, Route 1
24
Exit 126 Area Improvements
• After construction, there will be 2 right turn lanes from I-95 southbound exit ramp to Route 1 southbound
• Also, 2 right turn lanes from Route 1 southbound to Southpoint Parkway
• Construction advertised June 2021
Route 17 Overpass Replacement, Widening
25
Exit 126 Area Improvements
• Builds new 4-lane overpass
• Widens Route 17 to east of Hospital Boulevard
• Sidewalks
• Project completed fall 2022
26
Route 1 and Commonwealth Drive
Park & Ride
• $16.6 million
• Approximately 700 new spaces in
Massaponax area
• Construction advertised in
spring 2020
• Lot opens summer 2021
Follow us on Twitter: @VaDOTFRED