17
FRA GRATISPASSASJER TIL AKTIV PARTNER Rune Frafjord, Hess Norge

FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

FRA GRATISPASSASJER TIL AKTIV PARTNERRune Frafjord, Hess Norge

Page 2: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

See To It Duty

See to it duty

• the licensee must ensure that the operator is able to fulfil its responsibilities

• The licensee has a duty to see to it that these obligations are discharged in accordance with the regulations

Page 3: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

See To It Duty

See to it duty

• the licensee is under an obligation to act should any conditions fail to conform with the regulatory requirements.

• the licensee must see to it that the operator is properly equipped in key areas – such as; appropriate management system, qualified organisation

sufficient capacity.

• The licensee is also required to check the operator’s work on issues given particular priority by the authorities, and for key applications to the authorities.

Page 4: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Ptil-tilsyn av Hess Norge i oktober 2013

Ptil’s tilsynsrapport av 27.11.2013;

• Hess har ikke et fungerende

styringssystem for å ivareta krav til

helse, miljø og sikkerhet.

• Hess kjenner ikke grunnlaget for sitt

eget system for styring av risiko.

• Hess har ikke et fungerende

dokumentasjonssystem

4

Page 5: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Fra gratispassasjer til aktiv partner

5

Page 6: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

How to balance the «see to it duty»

6

SupportContribute

Drinking coffeeExperience transfer

ChallengeVerifyAuditLSV

.... Utilising our knowledge and experience

Page 7: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Hess Norge Management System

7

Processes: Who does What and When

Procedures/Activity descriptions: How

Page 8: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Fra gratispassasjer til aktiv partner

8

Page 9: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Ingen gratispassasjer lenger ................

9

Page 10: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Eksempler på aktiv partner……….

10

Page 11: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Eksempler på aktiv partner……….

11

Page 12: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

JV EHS Workshop

AGENDA 02.11.2016

• Goals of Workshop and deliverables (Per Mikal Hauge, Operation Manager Valhall)

• Review of HSE performance Ytd in 2016 (R.Frafjord/B.Skulstad/Iselin Håland)

• Insights and learning from incidents 2016(K. Serigstad)

• HSE plans 2017(K. Serigstad/K. Milne/I. Håland)

• Audit and Verification, Findings and Plan (P.I. Hansen)

• IP drilling and XLE4 start up plans 2017 (Ivar Dæhli)

• PSA Main Topics(Rune Frafjord)

• JV HSE Plan 2017 (Outcome) All.

Page 13: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

See-to-it Plan

13

No Type Audits / Assessment Description / Scope Focus Area

Jan

uary

Feb

ruary

Marc

h

Ap

ril

May

Ju

ne

Ju

ly

Au

gu

st

Sep

tem

ber

Octo

ber

No

vem

ber

Decem

ber

Status Synergi No. Notes

1 JV Audit Annual JV Financial Audit FM 2015 spend on Valhall Finance X X Completed

Documents in

HN New Drive -

Finance folder

Hess Corporate Audit

2

BP internal

audit (with

Hess

Participation)

Incident Investigation - Learning

efficiencyEHS

Communicating and learning from incidents/HIPOs – Access to/Sharing of

final reports to relevant staff/ contractors. Why do we have repeating

incidents (falling objects). Regulatory requirement. Ref. Fuzzy Bitar’s

expression about this being an area of improvement.EHS X X Completed # 90453

Kick off meeting 09.03.2016. Interviews in 11. Rune Frafjord

attended from Hess Norge. Final report distributed in week

20

3

BP internal

audit (with

Hess

Participation)

Contract Management OM/SSM

Verifying that BPN are managing contracts and suppliers in line with

regulatory and BP requirements, including contract HSE management,

role of CAM/PSCM in performance monitoring, supplier auditing, PHCA

management etc

Contractor Management X X X At Risk

Ref invitation from BP - Internal Audit Program, 22.12.15.

Awaiting feedback from BP

4

BP internal

audit (with

Hess

Participation)

Risk Management – How can site

management obtain an holistic view of

risk and barrier efficiency?OM / DM

Ongoing actions related to safety and barrier management are widely

spread at different sources/databases, with the potential of difficulty in

obtaining the overall and real risk picture. Ref. approved deviations, e-

MoC, Hazid, Hazop, RAT, ORA, Maintweb etc.

PSA audit in 2014 resulting in an improvement suggestion regarding how

to obtain an holistic view of results from follow-up activities . Any cross-

functional aspects hindering the holistic overview?

Risk Management X X X Cancelled by BP 15.04.2016: Information from BP that this audit is cancelled

5 Site Visits Leadership Site Visits Hess ManagerPerform 8 structured and focused Leadership Site Visits. Ensure good

planning, proactively implementation and adequately documentedEHS/Risk Management

D

M

O

M

D

A

P

A

P

&

A

M

D

/

P

&

A

D

M

/

E

H

S

O

MOn Plan

# 88152

# 90270

# 92436

# 92434

# 94902

# 94903

Two LSV performed by P&A Advisor in Sept/Oct: AF Decom

in Vats and Aker Solution in Eigersund

Four LSV scheduled (MD, P&A Advisor, Production Advisor

and EHS)

6 Verification Day-to-day Risk Management in GWO DMEnsure updated D&C Risk Management system in place according to BP

Standards and Hess expectationsRisk Management X X Completed # 88989

Verification meeting with BP was performed March 1. For

further information, documents etc - see Synergi # 88989

7 Verification Emergency Response EHS

Review BP Emergency Response Plan - perform Gap Analyse to Hess

Norge IMP. Plan and execute common Emergency Response Exercise -

Major Incident at Valhall

Emergency Response X X Completed # 90454

Common Emergency Response Exercise May 11th. May

Lessons learned from barge incident 31 Dec 2015. Updates

in BP's and HN ER procedures.

8 Verification Shallow Gas Update /VOIP action plans OM/SSM

Review of current risk scenario and follow-up actions from "2015 Shallow

Gas Week".

Particular attention to be paid to addressing the surveillance program and

reactions to undesirable/unpredictable results.

Integrity Management X Completed # 89650

2016 Shallow Gas Week carried out in May. Relevant

documents in Synergi. Awaiting actions from 2016 Shallow

Gas week.

9 Verification Global Wave in Deck impacts OM/SSMSpecific focus during JV risk workshop to ensure that BP is executing risk

action plans (RAPs) on WP, PCP and DPRisk Management X Completed

Documents in

L2S

JV Risk workshop 06.04.2016. Final summary report

presented in Q3 TC/MC meetings.

10 Verification Process Safety / SIMOPS OM/SSM

Scope updated 19.9.2016. Initial intent with this action was to develope a

set of bow-tie related to valhall Process Safety, ref HN Must Do.

Due to change in Must Do's for non-operated assets, scope redefined to

review SimOps risk, control of Work (COW) during a LSV.

Barrier Management X Ongoing

Bow-Tie training completed (LOL HN Champion).

Covered in Reidars LSV to Valhall, week 42.

Awaiting LSV report

11 Verification Barrier Management OM/SSM

Review 4Q15 BP internal audit report, review against BP BM strategy and

BP OMS and regulations, identify gaps and determine need for

independent Hess audit.

Integrity Management/

Risk ManagementX X At Risk

Awaiting BP report on Internal Audit Results (performed

4Q15)

12 Verification High Risk Contractor Management OM/DM

Two steps according to 2016 Must Do:

1. Agree on Process for JV engagement

2. Attend 6 PRM's (4 to be covered in TC-meeting, 2 of Archer) Contractor Management X X X X X X On Plan

Documents in

L2S (TC mom)

PRM's of Archer

in # 94907

1. Agreed on JV engagement

2. Aker reviewed in Q1/TC

CHC reviewed in Q2/TC

LOL attended Archer Safety meeting in Q2 and Q3

Force reviewed in Q3/TC

Next (TC/Q4): Score

13 Verification BP Inventory count DA Participate in BP "Inventory counts". Contractor Management X OngoingLars Olav Lien to visit GE Oil and Gas September 20.

Report will be sent to Hess late October

14 Verification P&A Execution DM Review of BP's authority-reporting of final P&A status of the wells Risk Management X Ongoing WIP - to be finalized by end of October

15 Partner Audit Overheads and Logistics Audit FM Partner Audit of BP Norge Overhead & Logistics 2015 expenditures Finance X X Ongoing

16 Partner Audit Management of Change EHSInvite all BP-partners (EON/Dea, Dong, PGNIG, Statoil) to attend a partner

audit. Topic MOC with regards to massive organizational changes. MOC X X

Postponed to 2017

due to Aker BP

Transition

Audit against BP OMS and PSA regulations.

Discussed with Pgnig, Dong and Dea - positive to do the

partner audit, but put on hold due to Aker BP transition

17 Internal Audit EHS & SR Management System EHS Hess Corporate Audit X Completed # 92092 Carried out in week 23 and 24.

Page 14: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Eksempel på aktiv partner….

14

Page 15: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Risk Management – BP versus Hess Norge

15

Page 16: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

JV Risk Workshop

16

Page 17: FRA GRATISPASSASJER TIL AKTIV PARTNER · Ensure updated D&C Risk Management system in place according to BP Standards and Hess expectations Risk Management X X Completed # 88989 Verification

Hva gjør en aktiv partner når operatøren blir kjøpt opp?

17