    THE BEACONARNAIZ AVE., CHINO ROCES AVE. COR PASAY ROAD, MAKATI CITYCOST PLAN NO. 2

    B. ELEMENTAL BREAKDOWN

    II. FOUNDATION AND SUBSTRUCTURE

    Total Area,(m²)= 45,241 November 2007

    ELEMENTS Element Total Elemental Cost %(Peso) (Peso/m²)

    1.0 Foundation and Substructure

    1.1 Substructure 72,294,100 1,597.97 91.74%72,294,100 1,597.97 91.74%

    2.0 Preliminaries 9% 6,506,469 143.82 8.26%