Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
820 NW Cornell Avenue • Corvallis, Oregon 97330 • 541-757-7645
7587 SW Cirrus Drive, Bldg 24 • Beaverton, Oregon 97008 • 503-643-1541
Foundation Engineering, Inc. Professional Geotechnical Services
Steve Hodge, P.E. September 29, 2016
County Engineer
Lincoln County Public Works
880 NE 7th Street
Newport, Oregon 97365
Eckman Creek Culvert Replacement Project 2161081
Foundation Report
Lincoln County, Oregon
Dear Mr. Hodge:
We have completed the requested geotechnical investigation for the
above-referenced project in Lincoln County, Oregon. This report provides a
description of our work, a discussion of the site conditions, and recommendations
for the design and construction of shallow foundations.
BACKGROUND
Lincoln County plans to replace the culvert crossing Eckman Creek at MP 1.03 on East
Eckman Creek Road in Waldport, Oregon. The site location is shown on Figure 1A
(Appendix A).
The existing 12-foot diameter culvert became blocked by debris following a series of
severe winter storms in mid to late December 2015. Rising water eventually
overtopped the road and washed out a portion of the Eckman Road embankment.
The County installed a temporary bypass pipe and added rip rap to the face of the
embankment. Eckman Road provides the only paved access to two quarries,
residential homes, the City of Waldport’s portable water intake, and forest timber
lands.
Preliminary drawings provided by the County indicate a 30-foot long, precast concrete,
arch open-bottom culvert is planned that will be supported on continuous spread
footings. The drawings also show 8-foot wide wing walls at the ends of the culvert
to retain new approach fill.
Lincoln County is the project owner. The County retained Foundation Engineering, Inc.
to complete a geotechnical investigation for the replacement culvert. Our scope of
work was outlined in a proposal dated August 18, 2016, and authorized by a signed
agreement dated August 24, 2016.
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 2 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
EXPLORATION
Two exploratory borings (BH-1 and BH-2) were drilled on September 9, 2016, using
a CME 75, truck-mounted drill rig and mud-rotary drilling techniques. BH-1 was
drilled in the north-bound lane, ±25 feet north of the outside edge of the existing
culvert. BH-2 was drilled in the same lane, ±43 feet south of the edge of the
culvert. The approximate boring locations are shown on Figure 2A (Appendix A).
BH-1 extended to a depth of ±25.1 feet and BH-2 extended to ±31.5 feet.
Samples were obtained at 2.5-foot intervals to a depth of ±20 feet and at 5-foot
intervals thereafter. Disturbed samples were obtained with a split-spoon in
conjunction with the Standard Penetration Test (SPT). The SPT provides an
indication of the relative stiffness or density of the foundation soils.
The borings were continually logged during drilling. The final logs (Appendix B)
were prepared based on a review of the field logs, laboratory testing, and an
examination of the soil samples in our office. The sampling depths and SPT data
for each boring are summarized on the logs (Appendix B).
SURFACE AND SUBSURFACE CONDITIONS
Surface Conditions
The road runs approximately north-south. Topographic information provided by
Lincoln County indicates the road surface at the culvert crossing (±Sta. 3+00) lies
at El. 118.88. The ground surface east of the culvert slopes to ±El. 103.8. The
low point to the west lies at ±El. 106.5.
Subsurface Conditions
A brief discussion of the subsurface conditions is provided below. More detailed
soil and rock descriptions are provided on the boring logs in Appendix B.
BH-1 (North Side). The pavement section at BH-1 consists of 6 inches of asphalt
concrete (AC) over ±9 inches of ¾-inch minus, dense, angular, crushed rock (base
rock). The pavement section is underlain by fill consisting of dense silty gravel to
±5 feet, medium stiff to stiff silt with some sand and gravel to ±10 feet, and
medium stiff silty clay with trace sand and gravel and scattered organics to
±12.5 feet. SPT N-values ranged from 7 to 11 blows per foot (bpf) within the fill.
The fill is underlain by loose silty sand from ±12.5 to 17.5 feet. N-values of 5 and
11 were recorded in this strata. Dense silty gravel was encountered from ±17.5
to 20 feet. Residual soil was encountered at ±20 feet. Residual soil is bedrock
that has decomposed in place to the consistency of soil. The residual soil consists
of very dense silty rock fragments. A relict rock texture from the underlying
formation was apparent in the residual soil.
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 3 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
Grey, slightly weathered, very weak to weak (R1 to R2) basalt (Basalt of Yachats)
was encountered at ±24 feet. Practical sampling refusal (N>100) was recorded in
the basalt at 25.1 feet, the limits of our exploration.
BH-2 (South Side). The pavement section at BH-2 consisted of 6 inches of AC over
±9 inches of base rock. The pavement section is underlain by fill to ±10 feet.
The fill consists of dense silty gravel with trace sand to ±5 feet and dense silty sand
with trace gravel to ±10 feet. N-values in the fill ranged from 31 to 47.
Alluvium consisting of alternating layers of medium dense silty sand, soft clayey silt,
and loose silty sand was encountered to ±17.5 feet. N-values ranging from 3 to
16 were recorded in these layers. Gravel with some sand and silt follows to
±28 feet. The gravel was medium dense to ±20 feet and very dense from ±20
to 28 feet. Scattered cobbles up to 6 inches in diameter were noted between ±20
and 28 feet. Medium dense silty sand was encountered from ±28 to 31.5 feet,
the limits of our exploration. An N-value of 21 was recorded in the sand.
Ground Water
The use of mud-rotary drilling during exploration precluded the direct observation of
ground water levels in the borings at the time of the investigation. It would be
reasonable to assume the ground water levels beneath the road fluctuate seasonally
and approximately follow the creek level.
PROPOSED REPLACEMENT STRUCTURE
Drawings provided by Lincoln County indicate the culvert is to be replaced by a
Conspan O Series 0430 precast concrete arch bridge manufactured by Contech
Engineered Solutions LLC. The structure will have a height of 9.3 feet, a 30-foot span,
and an out-to-out width of 40 feet. The ends of the structure will have 8-foot long
wingwalls. An elevation of the outlet end shows the flowline of the structure will be
±14 feet below the road surface. We estimate the bottom of the footings supporting
the arch segments will extend a nominal 16 feet below the road surface.
HYDRAULICS/SCOUR
A hydraulic/scour study had not been completed at the time this report was prepared.
The County indicated the normal flows in the creek are relatively low. Also, there
is a culvert just upstream at the City’s water intake that limits the flow under
Eckman Road. The County reported that, based on conversations with the Oregon
Department of Fish and Wildlife, the culvert replacement structure must be one and
a half times the stream width, requiring a 30-foot span. An open-bottom arch
culvert was selected to meet this criterion.
FIELD AND LABORATORY TESTING
The laboratory testing included natural water contents and percent fines. Those
test results are summarized in Table 1C (Appendix C). The water contents are also
included on the boring logs (Appendix B).
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 4 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
In-situ resistivity testing was completed using a Nilsson 400, 4-pin, soil resistance
meter (ASTM G57). The resistivity test was located west of BH-2. The
approximate location is identified as R-1 on Figure 2A.
The 4-pin resistance meter provides an estimate of the average resistivity of a soil
profile extending to a depth equal to the spacing between the pins. The tests were
performed with the pins spaced at ±6, 9, and 12 feet. The resistivity values,
summarized in Table 2C (Appendix C), ranged from ±12,064 to 21,831 ohm-cm,
which are consistent with the presence of predominantly granular soils.
pH tests (ASTM G51) were completed on samples SS-1-4 from ±10 to 11.5 feet
and on SS-2-5 from ±12.5 to 14 feet. The results, summarized in Table 3C,
indicate pH values ranging from 5.8 to 5.9 (i.e., moderately acidic).
SEISMIC ANALYSIS AND EVALUATION
Bedrock Acceleration and Site Response
Culverts are often not designed for seismic loads. However, if seismic design is
required, we assume the culvert will be designed similar to a bridge in accordance
with the 2014 AASHTO LRFD Bridge Design Specifications. AASHTO (2014)
recommends all bridge structures be designed using earthquake ground motions
having a 1,000-year average return period. A response spectrum for the site was
established using the General Procedure in AASHTO (2014) Section 3.10 and seismic
design maps based on the USGS National Seismic Hazard Maps (2002). Based on
the anticipated depth of the new footings and the recommended site preparation, we
concluded the average subsurface conditions across the site correspond to an
AASHTO Site Class C. The AASHTO General Procedure Response Spectrum
established for a Site Class C are shown on Figure 3A (Appendix A).
Liquefaction, Settlement, and Lateral Spread
Liquefiable soils typically consist of loose sands and non-plastic silts below the
ground water table. The site is underlain by site fill consisting of predominantly
dense granular soils or stiff fine-grained soil, followed by predominantly dense
gravels. Bedrock was encountered at 24 feet in BH-1. Drilling was discontinued
at BH-2 at ±31.5 feet before bedrock was encountered. However, we anticipate
bedrock underlies the south side of the crossing at a relatively shallow depth below
the bottom of BH-2.
A ±4 to 5-foot thick layer of sand was encountered at BH-1 between the
embankment fill and the underlying dense gravels. An N-value of 5 was recorded
at a depth of ±12 to 13 feet, indicating the sand is loose. This layer is potentially
liquefiable during a large, long-duration seismic event. New footings for the
replacement structure will extend below most of the sand. Furthermore, we have
recommended herein that any sand remaining beneath the footings be removed and
replaced with compacted structural fill. As a result, new footings will bear on
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 5 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
relatively dense gravel extending to at least ±28 feet, or underlain bedrock.
Therefore, the risk of liquefaction and liquefaction-induces settlement will be
mitigated by the recommended site preparation for the new foundations.
Construction of the replacement structure will require a relatively large excavation
which will be backfilled with granular fill. Therefore, the risk of settlement and
lateral spread is low in the backfill zone. There is potential for loose sand to remain
beneath the existing road embankments outside the backfill zone. Therefore, lateral
spread could occur in portions of the approaches. We anticipate it will be most
practical to repair damages to the approaches due to liquefaction and lateral spread
(if needed), following an earthquake.
FOUNDATION ANALYSIS AND RECOMMENDATIONS FOR DESIGN AND
CONSTRUCTION
Anticipated Footings
The County would like to use precast continuous footings to support the replacement
structure. Drawings available on-line at the Contech website for the Series
O structure indicate the precast footing units are placed in segments on a thin
bedding of granular material and then filled with cast-in-place concrete.
Foundation Design and Construction
Bearing Resistance. If the foundation areas are prepared as specified in this report,
new footings will bear on a layer of compacted crushed rock followed by medium
dense to very dense alluvial gravel. The Contech technical literature indicates a
required bearing capacity of 4,000 psf for footing design. We assume this value
represents a working or allowable bearing pressure (based on ASD design). We
believe an allowable bearing pressure (ASD) of 4,000 psf is reasonable for the
anticipated material beneath the new footings. The allowable value typically
includes a factor of safety of 3 (i.e., an ultimate bearing capacity of 12,000 psf).
For Load Factor Resistance Design (LRFD), this nominal value corresponds to a
factored bearing pressure of 5,400 psf (assuming an LRFD resistance factor of 0.45).
For foundation design, we have assumed any remaining loose or soft soil will be
removed from the footing trenches and be replaced with compacted granular fill.
We recommend the footing trenches extend to dense gravel and backfilled with
granular fill. The granular fill should consist of crushed aggregate meeting the
requirements of ODOT Section 02630.10 Dense Graded Aggregate. We
recommend using material meeting the gradation of 1½’’-0, 1’’-0 or ¾’’-0 in
Table 02630-1. These gradations should allow field density testing.
The trenches should be at least 12 inches wider than the dimensions of the precast
footing units. All loose sand, disturbed soil, or clods should be removed from the
footing trenches prior to backfilling. The trench backfill should be placed in lifts and
compacted to at least 95% relative compaction (according to the maximum dry
density of ASTM D698 or AASHTO T-99).
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 6 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
Settlement. The footings will be underlain by predominately dense granular soil,
followed by bedrock. For purposes of design, we recommend assuming foundation
settlement in the range of ±½ to 1 inch. It is anticipated the settlement will occur
during construction as the foundations are loaded.
Lateral Resistance. We recommend using a coefficient of friction of 0.5 to evaluate
the sliding resistance between the base of the footings and the granular fill. The
sides of the footings will likely bear against compacted backfill comprised of angular
crushed rock. Assuming these conditions, we recommend calculating the nominal
passive resistance on the sides of the footings using an equivalent fluid density of
435 pcf. This value is based on a unit weight of 125 pcf and a passive earth
pressure coefficient (Kp) of 3.5. The passive resistance may be combined with the
sliding resistance at the base of the footings.
Wing Walls
Wing walls will retain the fill at the ends of the structure. Contech drawings indicate
the wing walls will be ±8 feet long and ±13.9 feet deep at the connection to the
spans, tapering to ±11.9 feet away from the structure.
The foundation design and construction recommendations provided above for the
culvert footings are also applicable to the retaining wall footings.
We calculated design earth pressures for the wall based on active conditions,
assuming the top of the wall will be unrestrained and allowed to rotate or translate
at least 0.002H at the time of backfilling (where H is the height of the wall).
A friction angle of 34 degrees and a unit weight of 125 pcf were assumed for the
backfill. Where the backfill has a level backslope, walls should be designed using
an active earth pressure coefficient (ka) 0.28 and an equivalent fluid density of
35 pcf. Where 2(H):1(V) backfill slopes are used, the walls should be designed
using a ka of 0.42 and an equivalent fluid density of 52 pcf.
Traffic surcharge loads should be assumed where the top of the wall will be within
±10 feet of the roadway. The AASHTO Bridge Design Specifications Manual
(2012) recommends estimating the traffic loads applied to the top of the walls parallel
to traffic using an equivalent soil surcharge with a minimum height of 2 feet. The
minimum surcharge height corresponds to a uniform surcharge pressure of
±250 psf. This results in an additional uniform lateral pressure of ±105 psf for
active conditions with a coefficient ka of 0.42 (sloping backfill).
Structural Backfill
Contech Technical Bulletin No. 4 provides specific recommendations for structural
backfill. They recommend a minimum structural backfill width of 6 feet for the
larger span structures. Tables 1 and 2 of the technical bulletin also provide
minimum requirements for the backfill material. The gradations listed in the tables
allow between 15 and 35% material passing the No. 200 sieve. Because of the
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 7 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
possibility of ground water, material containing relatively high amounts of fines may
have significant problems during placement. Instead, we recommend using ¾’’-0
crushed rock meeting the requirements of ODOT Section 02630.10 Dense Graded
Aggregate, Table 02630-1. The nearby quarries should be able to provide this
material with minimum haul distance.
Contech also provides recommendations for placing and compacting the structural
backfill to avoid unbalanced lateral loads. Those recommendations should be
incorporated in the project drawings and specifications. However, we do not
recommend using the “modified Proctor” specification (i.e., ASTM D1557 or
AASHTO T-180) for compaction.
APPROACHES AND EMBANKMENTS
Approach Construction
The approaches will be reconstructed after the culverts are built. The earthwork
should be completed with stripping, grubbing, benching, and fill placement done in
accordance with ODOT Section 00330 – Earthwork.
The road embankment at the approaches (i.e., outside of the 6-foot minimum
structural backfill zone) can be constructed with a wide variety of materials. Due
to the proximity of existing quarries, we anticipate crushed rock may be a
cost-effective approach fill. Such material is also relatively easy to place and
compact. The rock could consist of any of the materials specified in Table 02630-1,
including 2½’’-0 and 2’’-0 rock. Other materials could be considered as approach
fill, if approved by Foundation Engineering.
Granular fill typically compacts most efficiently using a smooth-drum vibratory roller
or a vibratory hoe pack. Embankment fill compacted using this equipment should
be placed in lifts ±1 foot thick or less. We recommend using light compaction
equipment (e.g., a jumping jack or plate compactor) within the controlled backfill
zone. Where light compaction equipment is used, the fill should be placed in thinner
lifts (6 inches or less).
Approach Settlement
The approaches are underlain by predominantly medium dense to dense gravels and
stiff fine-grained soil over shallow bedrock. These materials should have relatively
low compressibility. The finished grades will approximately match the existing
grades. With proper compaction of the approach fill, limited post-construction
approach settlement is anticipated.
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 8 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
CONSTRUCTION RECOMMENDATIONS
Specifications
We have assumed earthwork and fill material specifications for this project will
reference the Oregon Department of Transportation “Oregon Standard Specifications
for Construction (ODOT, 2015).
Seasonal Issues
Construction of the new culverts will require deep excavations including trenching
below the creek bed for the foundations. Construction during the dry summer
months (typically late June through the end of September) is recommended to reduce
dewatering requirements and the risk of sidewall caving and raveling. We
understand construction is scheduled to begin in July of next year. Therefore, the
work will be completed during dry weather.
Excavations/Shoring/Dewatering/Fill Slopes
The footings are expected to extend ±16 feet below the current road surface.
Therefore, we estimate footing excavations up to ±18 feet below the road surface
will be required for the footing trenches and removal of soft or loose soil. The
excavations should be laid back, benched or shored in accordance with Oregon OSHA
standards (OR OSHA, 2011).
We anticipate the excavations will be a layered profile that includes gravel, sand, silt,
and clay. Most of these materials are consistent with OR OSHA Type B soil based
on their observed stiffness or density. The loose silty sand layer encountered from
±12.5 to 17.5 feet in BH-2 corresponds to a Type C soil. OR OSHA recommends
a maximum cut slope of 1(H):1(V) for Type B soil and 1.5(H):1(V) for Type C soil.
This cut slope should be adjusted, as needed, if raveling or seepage are observed.
Where loose sand is encountered we recommend flattening the cut slope to
2(H):1(V). The appropriate cut slopes will need to be verified at the time of
construction. It is the contractor’s responsibility to maintain stable cut slopes and
to provide the necessary shoring.
Construction of the foundations will require excavations extending below the creek
bed. Ground water levels are not currently known, but are expected to reflect creek
levels and, therefore, will fluctuate seasonally. A temporary culvert could be placed
in the creek bed to transport most of the water through the work zone. However,
because the soils below the creek bed are relatively permeable, it should be assumed
ground water will still infiltrate into the footing excavations and dewatering will be
required.
Details of embankment construction are not available. We have assumed new
slopes will be constructed to match existing ones. We anticipate the embankments
will be constructed using predominantly imported granular fill. We also recommend
that any slopes exposed to creek water be protected from scour or erosion with
imported riprap.
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 9 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
LIMITATIONS
Construction Observation/Testing
We recommended a Foundation Engineering representative be present during
construction to observe the foundation conditions for the continuous footings and
confirm the material is consistent with the design assumptions. Any geotechnical
engineering judgment in the field should be provided by a Foundation Engineering
representative.
We anticipate the gradation of the recommended structural backfill and the granular
fill beneath footings will allow field density testing to monitor compaction.
Approach fills, however, may consist of materials that are too coarse for density
testing. Adequate compaction of this material will need to be evaluated by
observation of the compaction method and periodic proof-rolls using a loaded dump
truck or other approved heavy construction vehicle.
VARIATION OF SUBSURFACE CONDITIONS, USE OF THIS INFORMATION AND
WARRANTY
The analysis, conclusions, and recommendations contained herein assume the
subsurface profiles encountered in the borings are representative of the overall site
conditions. The above recommendations assume we will have the opportunity to
review final drawings and be present during construction to confirm the assumed
foundation conditions. No changes in the enclosed recommendations should be
made without our approval. We will assume no responsibility or liability for any
engineering judgment, inspection, or testing performed by others.
This report was prepared for the exclusive use of Lincoln County Public Works and
their design consultants for the Eckman Creek Culvert Replacement project in Lincoln
County, Oregon. Information contained herein should not be used for other sites or
for unanticipated construction without our written consent. This report is intended
for planning and design purposes. Contractors using this information to estimate
construction quantities or costs do so at their own risk. Our services do not include
any survey or assessment of potential surface contamination or contamination of the
soil or ground water by hazardous or toxic materials. It is assumed those services,
if needed, have been completed by others.
Our work was done in accordance with generally accepted soil and foundation
engineering practices. No other warranty, expressed or implied, is made.
Eckman Creek Culvert Replacement September 29, 2016
Foundation Report 11 Project 2161081
Lincoln County, Oregon Lincoln County Public Works
REFERENCES
American Association of State Highway and Transportation Officials (AASHTO),
2012, AASHTO LRFD Bridge Design Specifications.
FHWA, 2003, Standard Specifications for Construction of Roads and Bridges on
Federal Highway Projects: Federal Highway Administration Federal Lands
Highway (FHWA-FLD), Publication No. FHWA-FLH-03-002.
ODOT, 2015, Oregon Standard Specifications for Construction: Oregon Department
of Transportation (ODOT).
OR OSHA, 2011, Oregon Occupational Safety and Health Standards, Oregon
Administrative Rules, Chapter 437, Division 3 - Construction: Oregon
Occupational Safety and Health Administration (OR OSHA).
USGS, 2002, National Seismic Hazard Maps: U.S. Geological Survey (USGS),
http://eqhazmaps.usgs.gov.
Appendix A
Figures
Professional Geotechnical Services
Foundation Engineering, Inc.
4,0002,0001,000
SCALE IN FEET
0
SITE
2161081
Notes:1. The Design Response Spectrum is based on AASHTO 2014 Section 3.10.3 using the
following parameters:Site Class= C Damping = 5%
1,000-yr. PGA = 0.43 Fpga = 1.00 As = 0.43SS = 1.02 Fa = 1.00 SDS = 1.02S1 = 0.47 Fv = 1.33 SD1 = 0.62
2. PGA, SS and S1 values are based on USGS 2002 maps and information from the USGSwebsite. The 1,000-yr. values assume 7% probability of exceedence in 75 years.
3. Fpga, Fa and Fv were established based on AASHTO 2014, Tables 3.10.3.2-1, 3.10.3.2-2 and3.10.3.2-3 using the selected PGA, Ss and S1 values.
4. Site location: lattitude 44.3997, longitude -124.0310.
FIGURE 3AAASHTO 2014 GENERAL PROCEDURE RESPONSE SPECTRA
Eckman Creek Culvert ReplacementLincoln County, Oregon
Project No. 2161081
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
0 0.5 1 1.5 2 2.5 3
Elas
tic S
eism
ic C
oeffi
cien
t, C
sm(g
)
Period (seconds)
1,000-yr. Response Spectrum
Appendix B
Boring Logs
Professional Geotechnical Services
Foundation Engineering, Inc.
ASPHALTIC CONCRETE (±6 inches).Dense CRUSHED ROCK (GP); grey, damp, ±¾-inchminus, angular, (base rock).Dense silty GRAVEL (GM); brown, low plasticity silt,damp, fine to coarse gravel, angular to subangulargravel, (fill).
Medium stiff to stiff SILT, some sand and gravel (ML);brown, low plasticity, damp, fine to coarse sand, finegravel, subangular gravel, (fill).
Medium stiff silty CLAY, trace sand and gravel,scattered organics (CL); grey and brown, mediumplasticity silt, moist, fine to coarse sand, fine gravel,subangular gravel, organics consist of wood debris,(fill).Loose silty SAND (SM); brown, low plasticity silt, wet,fine to coarse sand, (alluvium).
Trace gravel, some organics, and wet below ±15 feet.
Dense silty GRAVEL, some sand, scattered organics(GM); grey-brown, low plasticity silt, wet, fine to coarsesand, fine to coarse gravel, subangular to subroundedgravel, organics consist of wood debris, (alluvium).
Very dense silty ROCK FRAGMENTS (GM);grey-brown, low plasticity silt, wet, fine to coarsesand-sized and fine to coarse gravel-sized basalt rockfragments, angular, relict rock texture, (residual soil).
Very weak to weak (R1 to R2) BASALT; grey, slightlyweathered, (Basalt of Yachats).BOTTOM OF BORING
0.5
1.3
5.0
10.0
12.5
17.5
20.0
24.0
25.1
SS-1-1
SS-1-2
SS-1-3
SS-1-4
SS-1-5
SS-1-6
SS-1-7
SS-1-8
SS-1-9
Capped withAC cold
patch andgravel
Backfilledwith
bentonitechips
Foundation Engineering, Inc.
Moisture, %
RQD., %
Foundation Engineering, Inc.
Elev.
Depth Water Table0 50 100
Depth
Feet
Soil and Rock Descriptionand
CommentsLog
SPT,
0 50 100
Depth
Feet
Soil and Rock Descriptionand
CommentsLog
SPT,N-Value
DepthSamples
Installations/N-Value
Water Table
Moisture, %
RQD., %Recovery
Elev.Samples
Installations/
Recovery
Surface Elevation:
Boring Log: BH-1
September 9, 2016
Surface Elevation: Eckman Creek Culvert Replacement
Lincoln County, Oregon
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Date of Boring:
2161081Project No.:
Eckman Creek Culvert Replacement
Project No.:
Page 1 of 1Page 1 of 1
Lincoln County, Oregon
Boring Log: BH-1
September 9, 2016Date of Boring:
2161081
N/A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
0.0
35
7
11
6
5
11
42
75
50/1st 1"
35
7
11
6
5
11
42
75
50/1st 1"
35
7
11
6
5
11
42
75
50/1st 1"
35
7
11
6
5
11
42
75
50/1st 1"
ASPHALTIC CONCRETE (±6 inches).Dense CRUSHED ROCK (GP); grey, damp, ±¾-inchminus, angular, (base rock).Dense silty GRAVEL, trace sand (GM); brown, lowplasticity silt, damp, fine to coarse sand, fine to coarsegravel, angular gravel, (fill).
Dense silty SAND, trace gravel (SM); brown, lowplasticity silt, moist, fine to coarse sand (?), finegravel, angular to subrounded gravel, (fill).
Medium dense silty SAND, trace gravel, scatteredorganics (SM); grey, low plasticity silt, wet, fine sand,fine gravel, subangular gravel, organics consist ofwood debris, (alluvium).
Soft clayey SILT, trace to some sand, scattered rockfragments (MH); grey and brown, medium plasticity,wet, fine to medium sand, coarse gravel-sizedsandstone rock fragments, (alluvium).
Loose silty SAND, some gravel, scattered organics(SM); grey-brown, low plasticity silt, wet, fine to coarsesand, fine to coarse gravel, subrounded to roundedgravel, organics consist of wood debris, (alluvium).
Medium dense GRAVEL, some sand, trace silt (GP);grey, wet, fine to coarse sand, fine to coarse gravel,subrounded gravel, (alluvium).
Very dense GRAVEL, some silt and sand, scatteredcobbles (GP); grey-brown, low plasticity silt, wet, fineto coarse sand, fine to coarse gravel, subrounded torounded gravel, cobbles up to ±6 inches in diameter,(alluvium).
Medium dense silty SAND, trace gravel (SM); grey,low plasticity silt, wet, fine to coarse sand, fine gravel,subrounded gravel, (alluvium).
BOTTOM OF BORING
0.5
1.3
5.0
10.0
12.5
15.0
17.5
20.0
28.0
31.5
SS-2-1
SS-2-2
SS-2-3
SS-2-4
SS-2-5
SS-2-6
SS-2-7
SS-2-8
SS-2-9
SS-2-10
Capped withAC cold
patch andgravel
Backfilledwith
bentonitechips
Foundation Engineering, Inc.
Moisture, %
RQD., %
Foundation Engineering, Inc.
Elev.
Depth Water Table0 50 100
Depth
Feet
Soil and Rock Descriptionand
CommentsLog
SPT,
0 50 100
Depth
Feet
Soil and Rock Descriptionand
CommentsLog
SPT,N-Value
DepthSamples
Installations/N-Value
Water Table
Moisture, %
RQD., %Recovery
Elev.Samples
Installations/
Recovery
Surface Elevation:
Boring Log: BH-2
September 9, 2016
Surface Elevation: Eckman Creek Culvert Replacement
Lincoln County, Oregon
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Date of Boring:
2161081Project No.:
Eckman Creek Culvert Replacement
Project No.:
Page 1 of 1Page 1 of 1
Lincoln County, Oregon
Boring Log: BH-2
September 9, 2016Date of Boring:
2161081
N/A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
0.0
31
36
47
16
3
8
27
50/1st 5"
56
21
31
36
47
16
3
8
27
50/1st 5"
56
21
31
36
47
16
3
8
27
50/1st 5"
56
21
31
36
47
16
3
8
27
50/1st 5"
56
21
Appendix C Laboratory Test Results
ProfessionalGeotechnicalServices
Foundation Engineering, Inc.
Foundation Engineering, Inc.
Eckman Creek Culvert
Project 2161081
Table 1C. Natural Water Contents and Percent Fines
Sample
Number
Sample
Depth (ft)
Natural Water
Content
(percent)
Percent
Fines
SS-1-1 2.5 – 4.0 19.0
SS-1-2 5.0 – 6.5 28.2
SS-1-3 7.5 – 9.0 24.6
SS-1-4 10.0 – 11.5 47.5
SS-1-5 12.5 – 14.0 34.3 26.2
SS-1-6 15.0 – 16.5 40.1
SS-1-7 17.5 – 19.0 14.9
SS-1-8 20.0 – 21.5 19.1
SS-1-9 25.0 – 25.5 11.5
SS-2-1 2.5 – 4.0 21.7
SS-2-2 5.0 – 6.5 24.4
SS-2-3 7.5 – 9.0 19.6
SS-2-4 10.0 – 11.5 38.4 39.8
SS-2-5 12.5 – 14.0 53.5
SS-2-6 15.0 – 16.5 45.4 24.9
SS-2-7 17.5 – 19.0 14.2
SS-2-8 20.0 – 20.4 11.5
SS-2-9 25.0 – 26.5 15.5
SS-2-10 30.0 – 31.5 29.4
Foundation Engineering, Inc.
Eckman Creek Culvert Replacement
Project 2161081
Table 2C. Summary of Resistivity Testing
Location Pin Spacing
(ft.)
Resistivity
(-cm)
West of BH-2
6 21,831
9 16,890
12 12,064
Table 3C. pH Test Results (ASTM G51)
Sample
Number
Sample
Depth (ft) Sample Description pH
SS-1-4 10.0 – 11.5 Stiff, silty CLAY with
scattered organics (CL) 5.9
SS-2-5 12.5 – 14.0 Soft, clayey SILT with
scattered rock fragments (MH) 5.8