Upload
ifeanyi-ezenandu
View
33
Download
0
Embed Size (px)
DESCRIPTION
INTENSIVE FACILITIES ENGINEERS DEVELOPMENT PROGRAM- FEDP
Citation preview
EPCM ENGINEERS LIMITEDLINE HEATER FOUNDATION DESIGN
DESIGN CODECRITERIA FOR SELECTION AND DESIGN OF RESIDENTIAL SLABS-ON-GROUND: BRAB REPORT #33
VARIABLE SYMBOL
CONCENTRATED LOAD
PLASTICITY INDEX PI
ALLOWABLE SOIL BEARING PRESSURE
CLIMATIC RATINGSLAB LENGTH L
SLAB WIDTH L'
STEP 1: DETERMINE TOTAL AVERAGE LOADVARIABLE SYMBOL
TOTAL SLAB AREA
ESTIMATED DEAD WEIGHT OF SLAB
w
STEP 2: ESTABLISH CONTROLLING SOIL PROPERTIESVARIABLE SYMBOL
NOTE: (2.5<qu/w<7.5) THE SOIL IS COMPRESSIBLE, qu/W>7.5 THE SOIL IS EXPANSIVE AND qu/w<2.5 THE FOUNDATION NEEDS PILES.
STEP 3: DETERMINE SUPPORT INDEXVARIABLE SYMBOL
SUPPORT INDEX C
STEP 4: ASCERTAIN THE DEFLECTION RATIOVARIABLE SYMBOL
DEFLECTION RATION ∆/L
TOTAL WEIGHT OF SUPERSTRUCTURE (ALL DEAD AND LIVE WEIGHT) WS
WC
ULTIMATE STRENGTH OF CONCRETE AFTER 28 DAYS
fY
ULTIMATE STRENGTH OF CONCRETE AFTER 28 DAYS
fC'
MAXIMUM ALLOWABLE SHEAR STRESS IN CONCRETE
VC
qU
CW
ASLAB
SUPERSTRUCTURE LOAD PER SQUARE FOOT OF SLAB AREA
wS
wd
TOTAL SUPERSTRUCTURE AND SLAB DEAD LOAD
RATIO OF SOIL BEARING PRESSURE TO TOTAL LOAD
qu/w
STEP 5: DETERMINE OUTSIDE SLAB DIMENSIONSVARIABLE SYMBOL
LONG DIRECTION(LENGTH) LSHORT DIRECTION(WIDTH) L'
STEP 6: DETERMINE EFFECTIVE LOAD FOR SLABVARIABLE SYMBOL
ϕ
STEP 7: DEVELOP LAYOUT OF STIFFENING BEAMSVARIABLE SYMBOL
DESIGN OF SLAB
VARIABLE SYMBOL
ASSUMED LENGTH TO DIAMETER RATIOL/d
BEAM DEPTH d
B
B'
STEP 9: EXECUTE RECOMMENDED DESIGN COMPUTATIONSVARIABLE SYMBOL
DEPTH RATIO IN THE LONG DIRECTION L/d
DEPTH RATIO IN THE SHORT DIRECTIONL'/d
LOAD INDEX IN THE LONG DIRECTIONLOAD INDEX IN THE SHORT DIRECTION
COEFFICIENT ϕ FOR THE LONG DIRECTION
EFFECTIVE LOADS FOR SLAB IN THE SHORT DIRECTION
EFFECTIVE LOADS FOR SLAB IN THE LONG DIRECTION
NUMBER OF WEB OF STIFFENING BEAMS ON THE LONG DIRECTION
nL
NUMBER OF WEB OF STIFFENING BEAMS ON THE SHORT DIRECTION
nS
STEP 8: SELECT/TEST TENTATIVE DESIGN VALVES FOR d, bS, B, AND B'
WIDTH OF WEB OF STIFFENING BEAM IN THE LONG DIRECTION
bs
WIDTH OF WEB OF STIFFENING BEAM IN THE SHORT DIRECTION
bs
SUM OF WIDTHS OF ALL BEAMS RUNNING PARALLEL TO THE LONG DIRECTION(L) OF SLAB
SUM OF WIDTHS OF ALL BEAMS RUNNING PARALLEL TO THE SHORT DIRECTION(L') OF SLAB
v
v
p
p
z
z
THEREFORE, THE STEEL RATIO IN THE SHORT DIRECTION IS p=
2 No. 10mm
2 No. 10mm
2 No. 10mm
2 No. 10mm
STEP 10: CHECK SLAB DEAD LOADVARIABLE SYMBOL
TOP SLAB DESIGN THICKNESS t
ADJUSTED BEAM DEPTH
VOLUME OF CONCRETE IN THE BEAMS
SLAB AREA
SHEAR CRITERION IN THE LONG DIRECTION
SHEAR CRITERION IN THE SHORT DIRECTION
MOMENT CRITERION IN THE LONG DIRECTION
MOMENT CRITERION IN THE SHORT DIRECTION
DEFLECTION CRITERION IN THE LONG DIRECTION
NOTE: FROM FIG. 17, FOR Z, p1 =
COMPARING p1 AND p
THEREFORE, THE STEEL RATIO IN THE LONG DIRECTION IS p = p1
DEFLECTION CRITERION IN THE SHORT DIRECTION
NOTE: FROM FIG. 17, FOR Z, p1 =
COMPARING p1 AND p
REINFORCING REQUIRED PER BEAM IN THE LONG DIRECTION: BOTTOM STEEL AS
REINFORCING REQUIRED PER BEAM IN THE LONG DIRECTION: TOP STEEL A'S
REINFORCING REQUIRED PER BEAM IN THE SHORT DIRECTION: BOTTOM STEEL AS
REINFORCING REQUIRED PER BEAM IN THE SHORT DIRECTION: TOP STEEL A'S
LINEAL FEET OF BEAM IN THE LONG DIRECTION
LF
LINEAL FEET OF BEAM IN THE SHORT DIRECTION
L'F
ddepth
VCON
ASLAB
SLAB THICKNESS EQUIVALENT TO BEAM VOLUME
tBV
EQUIVALENT UNIFORM SLAB THICKNESS
AVERAGE SLAB LOADESTIMATED TOTAL AVREAGE LOAD w
ACTUAL TOTAL AVREAGE LOAD
tUNI
wAV
wT
RATIO OF ESTIMATED LOAD TO ACTUAL LOAD
EPCM ENGINEERS LIMITEDLINE HEATER FOUNDATION DESIGN
DESIGN CODECRITERIA FOR SELECTION AND DESIGN OF RESIDENTIAL SLABS-ON-GROUND: BRAB REPORT #33
VALUE UNIT
52.91 kips
0 kips
60000 psi
4000 psi
75 psi
292500 psf
2526.25 ft8000 mm6.56 ft2000 mm
STEP 1: DETERMINE TOTAL AVERAGE LOADCALCULATION VALUE UNIT
172.222566667356
307.2187404 psf
82.49343832021 psf
389.71217872021 psf
STEP 2: ESTABLISH CONTROLLING SOIL PROPERTIESCALCULATION VALUE UNIT
6.41499069443978
NOTE: (2.5<qu/w<7.5) THE SOIL IS COMPRESSIBLE, qu/W>7.5 THE SOIL IS EXPANSIVE AND qu/w<2.5 THE FOUNDATION NEEDS PILES.
STEP 3: DETERMINE SUPPORT INDEXCALCULATION VALUE UNIT
0.89
STEP 4: ASCERTAIN THE DEFLECTION RATIOCALCULATION VALUE UNIT
REF TO TABLE III 0.0027777777777778
ft2
REF TO FIG. 6(USING CW AND PI)
STEP 5: DETERMINE OUTSIDE SLAB DIMENSIONSCALCULATION VALUE UNIT
SAME AS ABOVE 26.246719160105 ftSAME AS ABOVE 6.56167979002625 ft
STEP 6: DETERMINE EFFECTIVE LOAD FOR SLABCALCULATION VALUE UNIT
0.5
63.1647239984986 psf
31.5823619992493 psf
STEP 7: DEVELOP LAYOUT OF STIFFENING BEAMSCALCULATION VALUE UNIT
REF TO THE DRAWING
REF TO THE DRAWING 2
REF TO THE DRAWING 3
CALCULATION VALUE UNIT
REF TO STEP 8 ON THE CHART TAB(USING w G) 10.6654
29.5310658691901 in750.089073077428 mm
9.05511811023622 in
230 mm
9.05511811023622 in
230 mm
18.1102362204724 in
27.1653543307087 in
STEP 9: EXECUTE RECOMMENDED DESIGN COMPUTATIONSCALCULATION VALUE UNIT
10.6654
2.66635
137.314617388041 psf732.34462606955 psf
STEP 8: SELECT/TEST TENTATIVE DESIGN VALVES FOR d, bS, B, AND B'
1464.51532029041 psf
1952.68709372054 psf
0.0007809820848513
0.0002603273616171
0.002897212635747
-0.00036864787634
-0.0011496299611913
0.0007809820848513
0.0002414343863123
-0.0008379140688585
-0.0010982414304756
THEREFORE, THE STEEL RATIO IN THE SHORT DIRECTION IS p= 0.0002603273616171
0.208840302354017
134.735409466717
0
USE IN ADDITION TO THE STEEL BAR ON THE SLAB 0
0.0696134341180056
44.9118031555725
0
USE IN ADDITION TO THE STEEL BAR ON THE SLAB 0
STEP 10: CHECK SLAB DEAD LOADCALCULATION VALUE UNIT
10mm at 12in o.c. Each way placed 1/3 of the slab thickness 9.80392156862745 in250 mm
52.49343832021 ft
15.1574803149606 ft
22.7271443005626 ft
96.6830171899724
172.222566667356
6.73660965999052 in
NOTE: FROM FIG. 17, FOR Z, p1 =
THEREFORE, THE STEEL RATIO IN THE LONG DIRECTION IS p = p1
NOTE: FROM FIG. 17, FOR Z, p1 =
in2
mm2
in2
mm2
in2
mm2
in2
mm2
ft3
ft2
16.540531228618 in
113.707107724292 psfAS GIVEN ABOVE 389.71217872021 psf
420.925848124292 psf
1.0800941595066
0
COMPRESSIBLE SOIL
TRUELONG DIRECTION
SHORT DIRECTION
WC/w
If C > 0.65 - wc/w
IF C <= 0.65 - wC/w
FALSE
C = Cr IN THE SHORT DIRECTION WHEN THE SOIL IS COMPRESSIBLE
C = Cr IN THE LONG DIRECTION WHEN THE SOIL IS COMPRESSIBLE
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
MUST BE < 21,600 psf
MUST BE < 21,600 psf
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
4 No. 12mm No. of Steel:
steel thickness (Diameter in millimeter):
2 No. 12mm AREA:
2 No. 12mm
1 No. 12mm
since all squares of the top slab have spans smaller than 12 feet.
82.49343832021
MUST BE GREATER THAN 0.95
MUST BE < wd
0.83791955333
0.83791955333
0.89
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
2
10 mmsteel sizes readily available are: 6,8,10,12,16,20,25,32mm
157.079632679 mm2
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
SELECT A BEAM SPACING NOT GREATER THAN 15FEET, NOR SMALLER THAN 8 FEET-PREFERABLE 9-12FEET. SELECT A BEAM WIDTH BETWEEN 8 AND 14 INCHES, PREFERABLE 8 TO 10 INCHES.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction. INITAL VALUE OF C INITAL VALUE OF C DIFFERENCE
LONG DIRECTION
BOTTOM 91.44 134.73
TOP 0 43.29
SHORT DIRECTION
BOTTOM 30.48 44.91
TOP 0 14.43
NO
TE: NO
ADD
ITION
TOP REIN
FORCM
ENT
WILL BE N
EEDED
IF THE D
IFFERENCE IS ZERO
O
R LESS, WH
EREAS AN AD
DITIO
NAL
REINFO
RCEMEN
T WILL BE N
EEDED
IF THE
DIFFEREN
CE IS POSITIVE
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.
This value is compared with the value of P obtained for the moment criterion. If P1 > P and P1 does not exceed P by more than 0.0015, P1 is the controlling steel ratio or else P. If P1 > P and P1-P >0.0015, a considerable percentage of steel is needed to impart stiffness rather than strength to the beam. This means that the dimensions of the beam must be increased in order to reduce p1-p. Therefore, a wider beam is needed in the long direction.