7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
1/18
FOSTER ROAD CROSS SECTIONDRAFT ALTERNATIVESThe graphics illustrated below display different cross sectional alternatives for the three
representative segments of inner Foster Road. These segments include SE 52nd Avenue to SE 72ndAvenue, SE 72nd Avenue to SE 80th Avenue, and SE 84th Avenue to the Couplet. Each cross
section alternative is a typical block for its respective segment and is supported with a table that
conveys at a broad level modal tradeoffs as design features within the cross section that are either
introduced, removed, moved, expanded, or reduced. Each segment includes at least one cross
section option incorporating key values identified by the community and staff, including:
A 4-lane option A 3-lane option A 2-lane option Conventional bike lanes in both directions Separated bike facilities in both directions
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
2/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 52nd Avenue to SE 72nd Avenue: Option 1
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic.Center turn lane provides a dedicated space to separate left turning vehicles from through
traffic.Center turn lane offers opportunities for raised medians with landscape and manages land use
access.Existing sidewalk widths are maintained. Curb extensions could be provided.Enough furniture zone in sidewalks to introduce landscaping, stormwater, and placemaking
features.
C d h l l h ll l h h l C
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
3/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 52nd Avenue to SE 72nd Avenue: Option 2
Element Tradeoff
Maintains four travel lanes for motorized traffic.No center turn lane is provided.Requires narrowing the sidewalk to 12 feet. Curb extensions could be provided.Reduces furniture zone and the ability to introduce some types of landscaping, stormwater,
and placemaking features.
Cross section maintains multiple threat collision potential.Six-foot bike lanes are provided. No separation from motorized traffic or on-street parking
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
4/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 52nd Avenue to SE 72nd Avenue: Option 3
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic, becoming three duringpeak times (two in the peak direction).
Center turn lane provides a dedicated space to separate left turning vehicles from throughtraffic.
Center turn lane offers opportunities for raised medians with landscape and manages land useaccess.
Providing additional lane capacity for all modes requires narrowing the sidewalk to 14 feet.Slightly reduces furniture zone and the ability to introduce some types of landscaping,
stormwater and placemaking features
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
5/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 52nd Avenue to SE 72nd Avenue: Option 4
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic, becoming three duringpeak times (two in the peak direction).
Center turn lane provides a dedicated space to separate left turning vehicles from throughtraffic.
Center turn lane offers opportunities for raised medians with landscape and manages land useaccess.
Providing additional lane capacity for all modes requires narrowing the sidewalk to 14 feet.Slightly reduces furniture zone and the ability to introduce landscaping, stormwater, and
placemaking features
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
6/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 52nd Avenue to SE 72nd Avenue: Option 5
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic.No center turn lane is provided.17-foot sidewalks are maintained.Enough furniture zone to introduce wider range of landscaping, stormwater, and placemaking
features.
Cycle track configuration cannot support curb extensions.Wide cycle tracks are provided in both directions, each with a marked buffers with separation
from parking.
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
7/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 72nd Avenue to SE 80th Avenue: Option 1
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic.Center turn lane provides a dedicated space to separate left turning vehicles from through
traffic.
Center turn lane offers opportunities for raised medians with landscape and manages landuse access.
Requires narrowing the sidewalk to 10 feet, which reduces furniture zone and the ability tointroduce some types of landscaping, stormwater, and placemaking features.Cross section reduces multiple threat collision potential. Center turn lane can allow for wider
pedestrian refuge islands
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
8/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 72nd Avenue to SE 80th Avenue: Option 2
Element Tradeoff
Reduces number of travel lanes from four to two for motorized vehicles.Center turn lane provides a dedicated space to separate left turning vehicles from through
traffic.
Center turn lane offers opportunities for raised medians with landscape and manages landuse access.
13-foot sidewalks are maintained. Curb extensions could be provided on the side withparking.Limited furniture zone to introduce landscaping, stormwater, and placemaking features. C ti d i di t d th f ti d d lti l
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
9/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 72nd Avenue to SE 80th Avenue: Option 3
Element Tradeoff
Reduces number of travel lanes from four to two for motor vehicles.No center turn lane is provided.13-foot sidewalks are maintained. Curb extensions could be provided.Cross section reduces crossing distance, and therefore exposure time, and reduces multiple
threat collision potential.
Bikeway configuration can support curb extensions.Six-foot bike lanes are provided. No separation from motorized traffic or on-street parking
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
10/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 72nd Avenue to SE 80th Avenue: Option 4
Element Tradeoff
Reduces number of travel lanes from four to two for motorized traffic, becoming three duringpeak times (two in the peak direction).
Center turn lane provides a dedicated space to separate left turning vehicles from throughtraffic.
Center turn lane offers opportunities for raised medians with landscape and manages landuse access.
13-foot sidewalks are maintained.Limited furniture zone to introduce landscaping, stormwater, and placemaking features. Cross section maintains multiple threat collision potential during peak times Center turn lane
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
11/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 84th Avenue to Couplet: Option 1
Element Tradeoff
Maintains four-lane cross section.No center turn lane is provided.Sidewalks are expanded to 10-feet.Limited furniture zone to introduce landscaping, stormwater, and placemaking features.Cross section maintains multiple threat collision potential during peak times.No bicycle facilities are provided.
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
12/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 84th Avenue to Couplet: Option 2
Element Tradeoff
Maintains four-lane cross section.No center turn lane is provided.Five-foot sidewalk widths remain unchanged.No space for a defined furniture zone or the ability to introduce landscaping, stormwater, and
placemaking features without dedication of right-of-way from adjacent properties.
Cross section maintains multiple threat collision potentialNarrow bike lanes are provided. N ti f t i d t ffi
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
13/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 84th Avenue to Couplet: Option 3
Element Tradeoff
Reduces number of travel lanes from four to two for motorized vehicles.Center turn lane provides a dedicated space to separate left turning vehicles from through
traffic.
Center turn lane offers opportunities for raised medians with landscape and manages landuse access.
Five-foot sidewalk widths remain unchanged. Curb extensions could be provided on the sidewith parking.No space for a defined furniture zone or the ability to introduce landscaping, stormwater, and
placemaking features without dedication of right of way from adjacent properties
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
14/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 84th Avenue to Couplet: Option 4
Element Tradeoff
Reduces number of travel lanes from four to three for motorized traffic.Center turn lane provides a dedicated space to separate left turning vehicles from through
traffic.
Center turn lane offers opportunities for raised medians with landscape and manages landuse access.
Five-foot sidewalk widths remain unchanged. Currb extensions could be provided.No space for a defined furniture zone or the ability to introduce landscaping, stormwater, and
placemaking features without dedication of right-of-way from adjacent properties.
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
15/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION
ALTERNATIVES
Portland Bureau of Transportation
SE 84th Avenue to Couplet: Option 5
Element Tradeoff
Reduces number of lanes from four to two for motorized vehicles.No center turn lane is provided.Five-foot sidewalk widths remain unchanged. Curb extensions could be provided.No space for a defined furniture zone or the ability to introduce landscaping, stormwater, and
placemaking features without dedication of right-of-way from adjacent properties.
Cross section reduces crossing distance, and therefore exposure time, and reduces multiplethreat collision potential.
Conventional bike lanes are provided
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
16/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION ALTERNATIVES
Portland Bureau of Transportation
Nelson\Nygaard Consulting Associates Inc. | 16
SUMMARY OF TRADEOFFS BY SEGMENT
Segment 1: SE 52nd Ave to SE 72nd Ave
OptionCurb-to-
Curb Width
Sidewalk
Width
Bike Facilities
(both directions)Parking*
Travel Lanes
(both directions)
Center
Turn lane
Streetcar
ready?**
Moves
curb?***
Existing 60' 13' - 17' None Allowed both sides 4 lanes None No NA
Option 1 60' 17' Yes Allowed both sides 2 lanes Yes Yes No
Option 2 70' 12' Yes Allowed both sides 4 lanes None Yes Yes
Option 3 66' 14' Yes, with buffers Protime both sides2 lanes
(3 peak only)Yes No Yes
Option 4 66' 14' Yes, with buffers Protime both sides2 lanes
(3 peak only)Yes Yes Yes
Option 5 60' 17' Yes, cycletracks Allowed both sides 2 lanes None Yes No
*Protime parking: parking is allowed 22 hours a day. Parking lane is a travel lane during peak travel times (7-9 AM Westbound, 4-6 PM Eastbound).
** Streetcar requires an 11' travel lane. If adjacent to parking, the parking lane must be 8'
***Likely to be determined on a block-by-block basis given varying sidewalk widths along the corridor.
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
17/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION ALTERNATIVES
Portland Bureau of Transportation
Nelson\Nygaard Consulting Associates Inc. | 17
Segment 2: SE 72nd Ave to SE 80th Ave
OptionCurb-to-
Curb Width
Sidewalk
Width
Bike Facilities
(both directions)Parking*
Travel Lanes
(both directions)
Center
Turn lane
Streetcar
ready?**
Moves
curb?***
Existing 50' 13' NoneAllowed EB, WB
protime3 lanes
(4 peak only)None No No
Option 1 56' 10' Yes, with buffers Allowed EB only 2 lanes Yes Yes Yes
Option 2 50' 13' Yes Allowed EB only 2 lanes Yes Yes No
Option 3 50' 13' Yes Allowed both sides 2 lanes None Yes No
Option 4 50' 13' None Protime both sides2 lanes
(3 peak only)Yes No No
*Protime parking: parking is allowed 22 hours a day. Parking lane is a travel lane during peak travel times (7-9 AM Westbound, 4-6 PM Eastbound).
** Streetcar requires an 11' travel lane. If adjacent to parking, the parking lane must be 8'
***Likely to be determined on a block-by-block basis given varying sidewalk widths along the corridor.
7/30/2019 Foster Road DRAFT Cross-Section Alts+Tradeoffs
18/18
FOSTER ROAD STREETSCAPE AND TRANSPORTATION PLAN UPDATE | DRAFT CROSS SECTION ALTERNATIVES
Portland Bureau of Transportation
Nelson\Nygaard Consulting Associates Inc. | 18
Segment 3: SE 84th Ave to Couplet
OptionCurb-to-
Curb Width
Sidewalk
Width
Bike Facilities
(both directions)Parking*
Travel Lanes
(both directions)
Center
Turn lane
Streetcar
ready?**
Moves
curb?***
Existing 50' 5' NoneAllowed EB, WB
protime3 lanes (4 peak
only)None No No
Option 1 40' 10' None Protime both sides2 lanes (3 peak
only)None No Yes
Option 2 50' 5' Yes None 4 lanes None No No
Option 3 50' 5' Yes EB side only 2 lanes Yes No No
Option 4 50' 5' None Allowed both sides 2 lanes Yes Yes No
Option 5 50' 5' Yes Allowed both sides 2 lanes None Yes No
*Protime parking: parking is allowed 22 hours a day. Parking lane is a travel lane during peak travel times (7-9 AM Westbound, 4-6 PM Eastbound).
** Streetcar requires an 11' travel lane. If adjacent to parking, the parking lane must be 8'
***Likely to be determined on a bl ock-by-block basis given varying sidewalk widths along the corridor.