COMPANY PROPRIETARY INFORMATION g GE POWER SYSTEMS Gas Turbine Service Manual

Issued by: Authorized by: Date Issued: PGSE Power Generation Services Engineering April 30, 1996 COMPANY PROPRIETARY INFORMATION

MS6001FA GAS TURBINE MECHANICAL INSTALLATION

& MAINTENANCE CLEARANCE FORMS

(DN436)

Page 2: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 2 April 30, 1996

GE Power Generation Service Engineering

NOTICE OF INTENT

This document provides information concerning the major tasks and typical responsibilities associated with the installation of GE supplied equipment. It describes much of the overall scope of unit installation, but does not detail specific methods used to complete each activity. The primary purpose of this document is to provide an overview of the installation process for this unit type in typical configurations available at the time of publication. Subsequent design advances or changes in configuration may not be reflected in this guide.

This document does not purport to cover all aspects of a particular installation. Unit-specific details are provided in the document and drawing packages supplied with each requisition per contract of sale. All sketches, descriptions, and dimensions are to be considered “Typical” of this type of unit. This document is the property of General Electric and is considered Company Proprietary Information.

Page 3: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 3 April 30, 1996

GE Power Generation Service Engineering

Contents

Figure # Form name Page # 1 Turbine to Load Gear Alignment Form 4 2 Generator To Load Gear Alignment Form 5 3 Starting Means/Generator Alignment Form 6 4 Load Gear Foundation Locking Devise Form 7 5 Generator Foundation (Collector End) Locking Device Form 8 6 Generator Foundation (Load Gear End) Locking Device Form 9 7 Turbine Aft Support Leg Drop Check Form 10 8 Aft Turbine Gib Block Bolt Setting (as found) Form 11 9 Aft Turbine Gib Block Bolt Setting (as left) Form 12 10 Front Turbine Gib Block Bolt Setting (as found) Form 13 11 Front Turbine Gib Block Bolt Setting (as left) Form 14 12 Turbine (inlet end) Foundation Locking Device Form 15

Page 4: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 4 April 30, 1996

GE Power Generation Service Engineering

6FA TURBINE TO LOAD GEAR ALIGNMENT REPORT FORM

Page 5: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 5 April 30, 1996

GE Power Generation Service Engineering

Figure 1

Page 6: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 6 April 30, 1996

GE Power Generation Service Engineering

7A6 GENERATOR TO LOAD GEAR ALIGNMENT REPORT FORM

Page 7: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 7 April 30, 1996

GE Power Generation Service Engineering

Figure 2

Page 8: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 8 April 30, 1996

GE Power Generation Service Engineering

STARTING MEANS/GENERATOR ALIGNMENT REPORT FORM

Page 9: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 9 April 30, 1996

GE Power Generation Service Engineering

Figure 3

Page 10: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 10 April 30, 1996

GE Power Generation Service Engineering

LOAD GEAR FOUNDATION LOCK DEVISE READINGS REPORT FORM

Page 11: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 11 April 30, 1996

GE Power Generation Service Engineering

Figure 4

Page 12: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 12 April 30, 1996

GE Power Generation Service Engineering

7A6 GENERATOR FOUNDATION CENTERLINE DEVICE REPORT FORM

Page 13: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 13 April 30, 1996

GE Power Generation Service Engineering

Figure 5

Page 14: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 14 April 30, 1996

GE Power Generation Service Engineering

7A6 GENERATOR FOUNDATION CENTERLINE DEVICE REPORT FORM

Page 15: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 15 April 30, 1996

GE Power Generation Service Engineering

Figure 6

Page 16: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 16 April 30, 1996

GE Power Generation Service Engineering

AFT TURBINE SUPPORT LEG SHIM PACK READINGS REPORT FORM

Page 17: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 17 April 30, 1996

GE Power Generation Service Engineering

Figure 7

Page 18: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 18 April 30, 1996

GE Power Generation Service Engineering

AFT TURBINE GIB BLOCK BOLT SETTINGS (AS FOUND) REPORT FORM

Page 19: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 19 April 30, 1996

GE Power Generation Service Engineering

Figure 8

Page 20: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 20 April 30, 1996

GE Power Generation Service Engineering

AFT TURBINE GIB BLOCK BOLT SETTINGS (AS LEFT) REPORT FORM

Page 21: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 21 April 30, 1996

GE Power Generation Service Engineering

Figure 9

Page 22: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 22 April 30, 1996

GE Power Generation Service Engineering

TURBINE GIB BLOCK BOLT SETTINGS (AS FOUND) REPORT FORM

Page 23: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 23 April 30, 1996

GE Power Generation Service Engineering

Figure 10

Page 24: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 24 April 30, 1996

GE Power Generation Service Engineering

TURBINE GIB BLOCK BOLT SETTINGS (AS LEFT) REPORT FORM

Page 25: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 25 April 30, 1996

GE Power Generation Service Engineering

Figure 11

Page 26: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 26 April 30, 1996

GE Power Generation Service Engineering

GAS TURBINE FOUNDATION LOCK DEVISE READINGS REPORT FORM

Page 27: Formas Instalacion Turbina 6000

COMPANY PROPRIETARY INFORMATION

PGSE Gas Turbine Service Manual g Subject

MS6001FA Gas Turbine Mechanical Installation No. DN436 & Maintenance Clearance Forms Page 27 April 30, 1996

GE Power Generation Service Engineering

Figure 12