1. Report No. 2. Government Acce •• ion No. FHWA/TX-86/79+350-2 •. Title and Subtitle DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE 7. Author") C. W. Elling, R. E. Klingner, and N. H. Burns 9. Perlorming Organization Name and Addre .. TECHNICAL REPORT STANDARD TITLE PAGE 3. Recipient', Catalog No. December 1985 5. Report Date 8. Performing Orgonilotion Report No. 1 Research Report 350-2 10. Work Unit No. 11. Contract Or Gront No. Research Study 3-5-83-350 Center for Transportation Research The University of Texas at Austin Austin, Texas 78712-1075 13. Type of Report and Period Covered 12. Spon.oring Agency Name and Addre .. Texas State Department of Highways and Public Transportation; Transportation Planning Division P.O. Box 5051 Interim 1 •. Spon.oring Agency Code Austin, Texas 78763 15. Supplementary Not .. Study conducted in cooperation with the U. S. Department of Transportation, Federal Highway Administration. Research Study Title: of Concrete Bridge Decks on Steel Beams--Verification of the Ontario Bridge Deck Design (With and Without Panels)" 16. Ab.troct Background material on refined and simplified methods for the analysis of bridge superstructures was presented. Seven methods were briefly described: five refined methods and two simplified methods. USing the full-scale experimental specimen of Project 350, subjected to vertical loads at 4 points on the deck surface, the variation of bending moments along the length of center girder was determined, both before and after deck cracking. These experimentally determined girder moments were compared with the moments obtained from the AASHTO Specifi- cations, from the Ontario Highway Bridge Design Code, and from a finite element model of the bridge. The experimentally determined values were approximated fairly closely by those of the Ontario Code and the finite element analysis. The peak moment predicted using the AASHTO procedure exceeded the corresponding experimental value by about 80 percent. In assessing the proper role of these methods for estimating girder moments, it is important to recognize that each method has its place. An AASHTO-type method (or perhaps a simplification of the Ontario procedure) is necessary for preliminary design. After preliminary deck and girder sizes have been picked, an Ontario-type procedure can be used to produce a more efficient revised design. The finite element method appears advantageous primarily for checking local behavior. 17. K.yWord, bridge, composite, girder, load, distribution, tests 18. Distribution Stot_ent No restrictions. This document is available to the public through the National Technical Information Service, Springfield, Virginia 22161. 19. S.curity Clo .. il. (of !hi, r.port) 20. S.curlty CI ... lf. (of thi. p .... l 21. No. of Pag.. 22. Price Unc1ass ified Unclassified 164 Form DOT F 1700.7 (8-1t)

Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

  • Upload
    lamdat

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

1. Report No. 2. Government Acce •• ion No.

FHWA/TX-86/79+350-2

•. Title and Subtitle

DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE

7. Author")

C. W. Elling, R. E. Klingner, and N. H. Burns 9. Perlorming Organization Name and Addre ..

TECHNICAL REPORT STANDARD TITLE PAGE

3. Recipient', Catalog No.

December 1985 5. Report Date ~

8. Performing Orgonilotion Report No. 1

Research Report 350-2

10. Work Unit No.

11. Contract Or Gront No.

Research Study 3-5-83-350

Center for Transportation Research The University of Texas at Austin Austin, Texas 78712-1075

13. Type of Report and Period Covered ~~~--------~--~~--------------------------~ 12. Spon.oring Agency Name and Addre ..

Texas State Department of Highways and Public Transportation; Transportation Planning Division

P.O. Box 5051

Interim

1 •. Spon.oring Agency Code

Austin, Texas 78763 15. Supplementary Not ..

Study conducted in cooperation with the U. S. Department of Transportation, Federal Highway Administration. Research Study Title: '~ehavior of Concrete Bridge Decks on Steel Beams--Verification of the Ontario Bridge Deck Design (With and Without Panels)"

16. Ab.troct

Background material on refined and simplified methods for the analysis of bridge superstructures was presented. Seven methods were briefly described: five refined methods and two simplified methods. USing the full-scale experimental specimen of Project 350, subjected to vertical loads at 4 points on the deck surface, the variation of bending moments along the length of center girder was determined, both before and after deck cracking. These experimentally determined girder moments were compared with the moments obtained from the AASHTO Specifi­cations, from the Ontario Highway Bridge Design Code, and from a finite element model of the bridge.

The experimentally determined values were approximated fairly closely by those of the Ontario Code and the finite element analysis. The peak moment predicted using the AASHTO procedure exceeded the corresponding experimental value by about 80 percent.

In assessing the proper role of these methods for estimating girder moments, it is important to recognize that each method has its place. An AASHTO-type method (or perhaps a simplification of the Ontario procedure) is necessary for preliminary design. After preliminary deck and girder sizes have been picked, an Ontario-type procedure can be used to produce a more efficient revised design. The finite element method appears advantageous primarily for checking local behavior.

17. K.yWord,

bridge, composite, girder, load, distribution, tests

18. Distribution Stot_ent

No restrictions. This document is available to the public through the National Technical Information Service, Springfield, Virginia 22161.

19. S.curity Clo .. il. (of !hi, r.port) 20. S.curlty CI ... lf. (of thi. p .... l 21. No. of Pag.. 22. Price

Unc1ass ified Unclassified 164

Form DOT F 1700.7 (8-1t)

Page 2: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE

by

C. W. Elling, R. E. Klingner, and N. H. Burns

Research Report No. 350-2

Research Project 3-5-83-350

"Behavior of Concrete Bridge Decks on Steel Beams - Verification of the Ontario Bridge Deck Design (With and Without Panels)"

Conducted for

Texas

State Department of Highways and Public Transportation

In Cooperation with the U.S. Department of Transportation

Federal Highway Administration

by

CENTER FOR TRANSPORTATION RESEARCH BUREAU OF ENGINEERING RESEARCH

THE UNIVERSITY OF TEXAS AT AUSTIN

December 1985

Page 3: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

The contents of this report reflect the view of the authors who are responsible for the facts and accuracy of the data presented herein. The contents do not necessarily reflect the views or policies of the Federal Highway Administration. This report does not constitute a standard, speCification, or regulation.

ii

Page 4: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

PRE F ACE

Recent research in the U.S. and Canada has suggested that the flexural capacity of bridge decks is increased by in­plane compressive forces, created when the cracked deck is res­trained by supports that cannot move laterally. This phenomenon, commonly referred to as "arching action," is the basis for the semi-empirical design provisions of the current Ontario (Canada) Bridge Design Code. That code permits the use of less flexural steel than would be required by current AASHTO Specifications, resulting in bridge decks which are generally more economical and resistant to corrosion.

Previous research on arching action has been carried out mainly using small-scale models with artificial boundary conditions. The overall objective of Research Project 3-5-83-350 was to study the performance of full-scale bridge decks designed taking arching action into account. Using a full-scale model of a realistic prototype highway bridge, both cast-in-place and precast, prestressed panel decks were considered.

During the course of Project 3-5-83-350, an opportunity became available to study the distribution of loads to the gir­ders of the bridge. In the United States, slab and girder brid­ges are usually designed according to the AASHTO Specifications, which consider the slab and girders to act independently, and involve the use of empirical moment distribution coefficients. Several other procedures are also available. The specific objec­tives addressed in Report 350-2 were:

1. To measure the girder loads and bending moments in a full-scale bridge;

2. To compare the girder bending moments with those predicted using some of the available methods;

3. Based on this comparison, to assess the relative merits of the procedures studied.

iii

Page 5: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 6: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

SUMMARY

Background material on refined and simplified methods for the analysis of bridge superstructures was presented. Seven methods were briefly described: five refined methods and two simplified methods. Using the full-scale experimental specimen of Project 350, subjected to vertical loads at 4 points on the deck surface, the variation of bending moments along the length of center girder was determined, both before and after deck cracking. These experimentally determined girder moments were compared with the moments obtained from the AASHTO Specifica­tions, from the Ontario Highway Bridge Design Code, and from a finite element model of the bridge.

The experimentally determined values were approximated fairly closely by those of the Ontario Code and the finite ele­ment analysis. The peak moment predicted using the AASHTO pro­cedure exceeded the corresponding experimental value by about 80 percent.

In assessing the proper role of these methods for estimating girder moments, it is important to recognize that each method has its place. An AASHTO-type method (or perhaps a simplification of the Ontario procedure) is necessary for preliminary design. After preliminary deck and girder sizes have been picked, an Ontario-type procedure can be used to produce a more efficient revised design. The finite element method appears advantageous primarily for checking local behavior.

v

Page 7: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 8: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

IMP L E MEN TAT ION

While the results discussed in this report were not included in the original objectives of Project 350, they were obtained during that Project's investigation into the behavior of Ontario­type bridge decks. The distribution of girder loads and moments in composite highway bridges is a current topic of several re­search projects being conducted in the United States. Because the results discussed here represent a valid set of data re­garding the distribution of moments in composite bridges, it was believed worthwhile to present them in the form of a research report.

vii

Page 9: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 10: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

Chapter

2

3

TABLE OF CONTENTS

Page

INTRODUCTION

, .. 1 General.. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. , 1.20bjectives ......................................... 3 , .. 3 SeQ pe ............................................................................................ 5

THEORETICAL BACKGROUND ......•.....•.•................... 7

2.1 Refined Methods of Analysis ..•..•.......•.........• 7 2.2 Simplified Methods of Analysis ...........•......... 8

EXPERIMENTAL TEST PROGRAM •.••••.•...•.•.•.•.•...........

3.1 3.2

3.3

3.4 3.5

3.6

General ...................................................................................... .. Specimen Description .•.•..•...•..•....•.........••• 3 .. 2 .. 1 Steel Girders ............................................................ .. 3.2.2 Cast-in-Place Deck •.•..•....••...••.•....... 3.2.3 Precast, Prestressed Panels •....•.•......... Construction ............................................................................ .. 3.3.1 Steel Girders .....•............•.•.......... 3.3.2 Precast, Prestressed Panels ....•.........•.. 3 .. 3 .. 3 Formwor k ...................................................................... .. 3.3.4 Reinforcement for Cast-in-Place Deck ...••••. 3.3.5 Placement and Curing of Concrete ........... . 3.3.6 Removal of Formwork •.........••.•...•..•.... Tes t Set up ................................................................................ .. Instrumentation ...................................................................... .. 3.5.1 3.5.2 3.5.3

Beam Strain Measurement .•.......•........... Deflection and Slip Measurement ............ . Crack Measurement ............................................ .

Loading Sequence and Testing Procedure •...•••.•....

TEST RESULTS

II • 1 1l.2

1l.3 ll.ll 1l.5

General Deflections ....................................... . 1l.2.1 Load vs. Deflection •...••.•.••..•••.•.•..••. 4.2.2 Variation of Deflection in

Longitudinal Direction •....•••••••...•..•.•• Slip Between Deck and Girders •..•..........••••.•.. Cracking Patterns in Deck •......•....••............ Calculation of Girder Loads from Strain Data •...... lJ .5.1 General .................................... .

ix

11

11 11 11 1 1 21 21 21 21 21 21 24 211 24 211 211 33 33 33

111

II 1 42 112

112 49 52 52 52

Page 11: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

Chapter

5

6

TABLE OF CONTENTS (continued)

Page

4.5.2 Load-Strain Diagrams ••••••••.•••••..•••••••• 55 4.5.3 Strain Gradient Diagrams •••••••••••••.••.•.• 55 ij. 5. ~ Moment Diagrams ..••.•..•••.•.•..•...•.....•. 58 14.5.5 Load Diagrams............................... 59

4.6 Computed vs. Experimentally Determined Load Diagrams ....•...•.••..•...•...•.........•.•... 64

COMPARISON OF EXPERIMENTALLY DETERMINED MOMENTS WITH THEORY ••••••••••••••••••••••••••••••••••••• 67

5.1 General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 5.2 Design Moments from AASHTO •••• ••• ••. ••• •.• ••••..•.• 67 5.3 Design Moments from Ontario Highway Bridge Code •••. 67 5.4 Moments from Finite Element Method ••••••••.••.•••.• 71

SUMMARY AND CONC LUSIONS ••••••••••••.••••••••••.....•••.•

6.1 6.2 6.3

Summary ••••.••••••••.•••••••••••••••.•••••••••••••• Conclusions Suggestions for Further Research •••••..••••.•••••••

73

73 73 75

APPENDIX A: MATERIAL PROPERT! ES •.••••.•••••••••••••••••••••.•••• 77

83

97

APPENDIX B: LOAD-SLIP PLOTS ••••.•••••••••••••••••••••.••••.•••••

APPENDIX C: PRE-CRACKING LOAD-STRAIN PLOTS

APPENDIX D: POST-FATIGUE LOAD-STRAIN PLOTS 113

APPENDIX E: STRAIN GRADIENT DIAGRAMS 129

APPENDIX F: CALCULATIONS FOR DETERMINING GIRDER DESIGN MOMENTS BY THE ONTARIO BRIDGE CODE •••••••••..••...•. 135

REFERENCES ....................................................... 141

NOTATION •.••.•••••.•••.•.•••.•••••••••.•••.••••••••••.••••••••.•• 1 47

x

Page 12: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LIST OF TABLES

Table Page

1.1 AASHTO Empirical Load Distribution Factors •.•..••.••..•.... 2

4.1 Comparison of Calculated Load with Actual Appli ed Load ..... 64

A.l Concrete Mix Design for Cast-in-Place Deck •••••••.••••..••. 78

A.2 Cast-in-Place Deck Properties ••••••••••••..••.•.••••••••.•. 78

A.3 Precast, Prestressed Panel Properties •••••••••••.••••••.••• 80

A.4 Seven-Day Modulus of Rupture Data ••••.••.•....•••.•••..•.•• 81

xi

Page 13: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 14: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LIST OF FIGURES

Figure Page

1.1 Qualitative example of AASHTO load distribution procedure ~

3.1 Elevation view of laboratory specimen •.•.•.......•..•.••.•. 12

3.2 Plan view of laboratory specimen •..••.••...•..•.•••.•.•.••• 13

3.3 Cross section of laboratory specimen showing precast, prestressed panels ••••••••••••••••••••.••.••.••.••••.•••••• 1~

3.4 Cross section of laboratory specimen showing cast-in-place deck ••••••••••••.••.••••.•••..•.••••••••••••• 15

3.5 Typical shear stud ................................................... 16

3.6 Layout of shear studs on the steel girders ••.•.•••.•••••••• 17

3.7 Detail of connection between girders and panels .••••••••.•• 18

Typical exterior diaphragm 19

Typical interior diaphragm ............................................. 20

3.10 Precast, prestpessed panels................................ 22

3.11 Layout of steel reinforcement •.•••.••••••••••••••.••••.•.•• 23

3.12 Elevation of test setup •••.•..••••••••••••••••.••••••••...• 25

3.13

3. 1 ~

Cross-section of test setup

Schematic of loading system

....................................... 26

........................................ 27

3 .. 15 React ion beam ......................................................... 28

3.16 Side view of reaction beam ......................................... 29

3.17 Location of strain gage on the steel girder .•.•.•..•.••.•.• 30

3.18 Plan view of strain gage location .......................... 31

3.19 Typical strain gage on steel girder .••••••.•.•.•.•.•••••..• 32

3.20 Layout of deflection and slip instrumentation 311

xiii

Page 15: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LIST Of fIGURES (continued)

Figure Page

3.21 Dial gage and linear potentiometer to measure vertical deflection of steel girders .••••••••••.•••••••••.• 35

3.22 Dial gage to measure slip between deck and girder •.••..•••• 36

3.23 Clip gage to measure slip between deck and girder .......... 36

3.2~ Clip gages used for measuring slip between deck and girder. 37

3.25 History of loading ••••••••••.••••••••••.••••••..•••....•.•• 38

3.26 Failed diaphragm weld...................................... 39

3.27 Range of loading during fatigue test •••••.•...••••..••••..• ~O

~ • 1 Midspan deflection of exterior girder

4.2 Midspan deflection of interior girder

~.3 Computed and measured deflections (pre-cracking), 25 kips, exterior girder ••••...•••••••••.•...••••••.•••••.. 45

4.~ Computed and measured deflections (pre-cracking), 25 kips, interior girder ••..••..••..••.•.•••.••...•.•..•..• ~6

~.5 Computed and measured deflections (post-fatigue), 25 kips, exterior girder •••••••••••••••••••••••••••••••••.• 47

4.6 Computed and measured deflections (post-fatigue), 25 kips, interior girder •••..•..•..••••..•...••••••••••...• 48

4.7 Pre-cracked load-slip data, center girder, north end ..•.•.• 50

~.8 Post-fatigue load-slip data, center girder, north end •••.•• 51

~.9 Crack patterns in deck before testing .•.•••..•••..•••••.••• 53

4.10 Crack patterns in deck after testing •••••.•••••••.••••••••• 54

~.11 Pre-cracking load vs. strain plot, strain gage 19 •••....••. 56

~.12 Pre-cracking and post-fatigue strain gradient diagrams (25 kips, interior girder. gage line 2) .................... 57

x:f.v

Page 16: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LIST O~ ~IGURES (continued)

~igure Page

~.13 Pre-cracking and post-fatigue moment diagrams (25 kips, exterior girder) •....•..••.•.••...........•••..•. 60

4.1~ Pre-cracking and post-fatigue moment diagrams (25 kips, interior girder) •.•••.........•.•.•.•...•..•.•... 61

4.15 Pre-cracking and post-fatigue load diagrams (25 kips, exterior girder) .••.•.•.••.•••.•••.......•..•..•. 62

4.16 Pre-cracking and post-fatigue load diagrams (25 kips, interior girder) •..••••....•.•................... 63

5.1 Design moments from AASHTO Code, center girder of laboratory specimen ........................................ 68

5.2 Comparison of moment diagrams from experiment, AASHTO Code, Ontario Code, and finite element analysis (235 kips, interior girder, pre-cracking) •••..•.•••..•.•••.•.•••..•.•. 69

5.3 Comparison of moment diagrams from experiment, AASHTO Code, Ontario Code, and finite element analysis (25 kips, interior girder, post-fatigue) .••..•••..••••.•....••••••••• 70

A.l Strengths vs. age for cast-in-place concrete •.••.•..••••••• 79

F.l Charts for C and D (Fig. 3-7.1.2.2(b) Ref. 2) ............ 138

xv

Page 17: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 1

INTRODUCTION

1.1 General

Slab and girder bridges, which carry loads by the combined action of the slab and the girders, are a common element in modern highway systems. Because such structures are usually statically indeterminate, girder moments and loads cannot easily be determined. Estimates of girder loads in slab and girder bridges are important both for evaluating eXisting bridges and for designing new ones. As will be discussed later, the theoretical methods which can be used to analyze slab and girder bridges are rather complicated.

In the United States, slab and girder bridges are usually designed according to the Specifications of the American Association of State Highway and Transportation Officials (AASHTO) [1]. This design procedure for slab and girder bridges, described in Section 3 of Reference 1, considers the slab and girders to act independently.

The deck slab is usually designed as a one-way slab spanning transversely between the girders. In computing design moments for the sl3b, no longitudinal distribution of live load bending moments is assumed. Under live load, transverse moments per foot of width of slab are calculated using the load on one rear wheel of a truck. Once the transverse moments in the slab are obtained, the size and spacing of the main transverse reinforcement are determined. Longitudinal distribution reinforcement, placed perpendicular to the main reinforcement, is calculated as a percentage of the transverse reinforcement.

Bending moments in the longitudinal girders are calculated according to Section 3.23 of the AASHTO Specifications. An individual girder is first isolated from the structure; if shear connectors are used to provide composite action, then an effective wldth of the slab is included as part of the girder. A single line of wheel loads from one truck is applied to the girder. The loads are placed on the span so as to produce maximum stress, and multiplied by an empirical distribution factor. Values of these empirical distribution factors for various types of bridges are listed in Table 3.23.1 of the AASHTO Specification (Table 1.1 on the following page). Design moments for the girder are calculated from these factored loads.

1

Page 18: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

2

TABLE 1.1 AASHTO Empirical Load Distribution Factors (Table 3.23.1, Ref. 1)

TABLE 3.23.1 Dlslrlbutlon of Wheel Loads In Lonaitudlnal Beams

Brid!o!c Designed for Bridge Dcsign~d for T\\'o or MOI'c

Kind of Floor One Traffic Lane Traffic Llltes

Timber:" Plankb S/4.0 S • .3.75 Nail laminated" '" thick or multiple layer~ floon over 5' thick Si4.S S/4.0 Nail laminated" o' or more thick S/5.0 S/4.25

Glued Laminated' Panels On Glued Laminated Stringers 4' thick 6' or more thick

On Steel Stringers 4' thick 6' or more th ick

Concrete: On Steel I·Beam Stringers- and Prestressed Concrete Girders

On Concrete T·Beams

On Timber Stringers

Concrele Box Girders"

If S exceeds 5' use footnote f.

5/4.5 5/6.0 If S exceeds b' use footnote f.

S/4.5 5/5.25 If S exceeds 5.5' use footnote f.

517.0 If S exceeds 10' use foolnole f.

S/6.5 If 5 exceeds o' use footnote f.

S/o.O If 5 exceeds 6' use footnote f.

If S exceeds 0.5' use footnote f.

S/4.0 S/5.0 If 5 exceeds 7.5' use foolnote f.

S/4.0 S/4.5 If S exceeds i' use footnote f.

S/5.5 If S exceeds 1-1' use footnote f.

5/6.0 If S eltceeds 10' use (ootnote f.

5/5.0 If 5 exceeds 10' use footnote f.

S/8.0 511.0 If S exceeds 12' If S exceeds 1 b •

use footnote f. use footnote (. On Steel Box Girden See Anicle 10 . .39.2. On Prestressed Con·

crete Spread Box Beams See Article 3.28.

Bridge Designed for Bridge Designed for Two or More

Kind of Floor One Traffic Lime Traffic lanes

Steel Grid: ILess than 4' thick) S/-I.5 14' or more) S/o.O

Steel Bridge Corrugated Plank'

If S exceeds o· use footnote f.

(2' min. depth) S.5.5

5 .:::: average stringer >pacing in feet.

51-1.0 S/S.O If S ~xceeds 10.5' use footnOle f.

5/-1.5

"Timber dimension~ \hown are for nominal thickn~s. 'Plank floors consist of pie~e~ of lumber laid edge to ed~c with the

wide faces bearing on the suppons I see Anicle 20.17-DilOision Ill. '!'>Iaillaminated floors conSI~1 of pieces of lumber laid face to face

"'ilh the narro .. ' edges bfDring nn the ~uppons. each picce beinl! nailed 1<) the preceding piece hce Article lO.IS-Division Ill.

"\1Uitipl~ lawr nOor\ con~ist of tl\'O or more layers of planks. ~:Ich layer bcing laid at an angl!.! to the other (sec Article 20. I 7-Di"ision [I).

<Glued laminated panel floors consist of vertically glued iaminated members with the narrol\' edges of the laminations bearing on the suppons (see Ankle 20.1. I-Division II I.

iln this case the load on each ~tringer shall be the reDction of the ,. heel loads. as,uming the flooring between the stringers to act as a simple beam.

g"Design of I·Beam Bridges" by N. M. Newmark-Proceedings. ASCE. March 1'148.

hThe sidewalk live load (see Anicle .3.15) shall be omitted for inte· rior and exterior box girders designed in accordance with the wheel load distribution indicated herein.

'Distribution factors for Sleel Bridge Corrugated Plank set fonh above are based substanlially on Ihe following reference:

Jut/mal uf W"shillgrull Acuuf'III,I' uf SC'it!'II(·t!'S. Vol. 67. No.2. 1'177 "Wheel Load Distribution of Sleel Bridge Plank." by Conrad P. Heins. Professor of Civil Engineering. University of Maryland.

These distribution factors were developed based on studies us· ing 6' x 2' steel corrugated plank. The faetors should yield safe results for other cOlTIJgalion configurations provided primary bend· ing stiffness is the same as or greater than the o· x 2' corrugated plank used in the studies.

Page 19: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

3

A qualitative example of this AASHTO procedure is illustrated in Fig. 1.1, and described below. The structure is a slab and steel girder bridge, simply supported, and loaded by four concentrated loads P which could represent the concentrated loads from a standard AASHTO H-20 truck loading. In this example, the center girder is chosen for design. As shown in Fig. 1.1 b. two wheel loads are applied to that girder 50 as to produce maximum stress. The loads are multiplied by a distribution factor SIC, where S is the stringer spacing in ft, and C is a constant whose value depends on the bridge type. In the case of a slab and steel girder bridge designed for two or more lanes of traffic, the constant is 5.5, resulting in a distribution factor of about 1.0 for typical girder spacings. The resulting moments (Fig. 1.1c) are used to design the center (interior) girder. The design moments in the exterior girders can be obtained similarly. Girder design moments can also be calculated using the lane loading described in Section 3.6 of the AASHTO Specifications. The larger moment from elther the lane loading or the truck loading should be used for design.

In addition to the AASHTO procedure, distribution factors can be obtained from the Ontario Highway Bridge Design Code [2]. Alternatively, the designer can calculate girder moments using one of the more accurate analytical techniques described in Chapter 3 of this thesis.

1.2 Objectives

As will be discussed subsequently, the current AASHTO procedure for determining girder moments usually provides a conser'vative estimate of the actual moments. To assess the validity of the AASHTO procedure, it was decided to investigate experimentally the distribution of girder moments and loads in a typical bridge. The speCimen selected for study was a full-scale composite highway bridge on steel girders, constructed in the laboratory as part of another investigation [3]. In this thesis, some aspects of the testing of that bridge model will be described. The experimentally determined girder moments will be compared with the values obtained by theoretical analyses. both exact and approximat~. This study has the following objectives:

1. to measure the girder loads and bending moments in a full-scale bridge;

2~ to compare the girder bending moments with those predicted using some of the available methods; and

3. based on this comparison. to assess the relative merits of the procedures studied.

Page 20: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

4

REINfORCED CONCRETE DECK

STEEL GIRDERS

SIUPLE SUPPORTS

P • (D.f.)

(A)

(8)

P-P;--__ ~ P--;- J, J, .J, J..

P • (O.f.)

CENTER GIRDER

P • ( D. F' .) • L 13

Af11111l1111111111~ LONGITUDINAL "'O~NTS (C)

IN CENTER GIRDER

UAXIWN UOt.£NT IN CENTER GIRDER - PL • (S/C)(1/3)

- PL • (SIs. 5) (1/3)

Fig. 1.1 Qualitative example of AASHTO load distribution procedure

Page 21: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

5

In Chapter 2, background material is presented on various theoretical methods used to analyze bridge superstructures. The experimental test program and test results are discussed in Chapters 3 and 4, and the observed and predicted girder moment distributions are compared in Chapter 5. In Chapter 6, the findings are summarized, and conclusions are presented.

Page 22: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 23: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 2

THEORETICAL BACKGROUND

2.1 Refined Methods of Analysis

Refined methods of analysis for analyzing highway bridge superstructures and determining girder moments and loads can be classified into six categories:

1. orthotropic plate theory methods [4,5,6] ;

2. harmonic analysis methods [7] ;

3. grillage analogy methods r8,9,10,11];

4. finite element methods [12,13,14];

5. finite strip methods [15,16,17]; and

6. folded plate methods [18,19,20] •

Refined methods of analysis with general applications are well reported in the technical literature. The references listed above are representative of a large number of published papers.

The orthotropic plate approach idealizes the actual bridge structure as an equi valent orthotropic plate, which is then treated by classical theory [21]. This approach was first developed by Guyon for grillages with negligible torsional stiffness [22] and later for isotropic slabs [23]. Massonnet [24] extended this approach by including the effects of torsion. The combined work of Guyon and Massonnet, referred to as the Guyon-Massonnet load distribution theory [25]~ has been extended by others [26,27,28,29].

The harmonic analysis procedure, developed in the 1950 's by Hendry and Jaeger [7], considers the same flexural and torsional rigidities as the orthotropic plate analysis, but neglects the torsional rigidity in the transverse direction [30]. Loads are distributed to the individual girders as though the slab were a continuous beam over non­deflecting supports. The loading is expressed as a harmonic series or Fourier sine series. Expressions for shear, moment, slope, and deflection are found by successive integration of this load series. Girder bending moments are determined by considering the above series in conjunction with transverse force equilibrium and slope-deflection expressions in the transverse direction [30].

7

Page 24: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

8

The grillage analogy method idealizes the bridge structure using an equivalent grid system, which is then analyzed [30] by:

a) slope-deflection and compatibility equations;

b) moment or torque distribution;

c) shear distribution; or

d) reaction distribution.

This method usually involves the solution of a large number of simultaneous equations or numerous arithmetic calculations [30].

The finite element and finite strip methods are widely used in the analysis of structures. A discussion of the theory and application of the finite element method to two-dimensional and three-dimensional systems involving plane stress, plane strain, plate bending, shells, and solids is given by Zienkiewicz [31]. The finite element and finite strip methods are general techniques for obtaining numerical solutions to boundary value problems. As discussed in Ref. 31, the finite element method involves dividing the structure to be analyzed into a finite number of simple elements, whose deformations are assumed to follow prescribed basis functions. The basis functions are selected to ensure compat i bi 11 ty between adj acent elements. Using var iational concepts, the combination of basis functions (for each element) is found which minimizes the static potential of the entire idealized structure. The resulting solution is an approximation to the exact response.

Folded plate theory can be divided into two categories: a) the ordinary method [32J, in which the longitudinal behavior of the plate is calculated according to beam theory, and the transverse behavior according to one-way theory; and b) the stiffness method [33] J which combines slab theory and plane stress theory. The bridge is considered as an assembly of individual, elastic, isotropiC rectangular plate elements interconnected at the longitudinal joints, and simply supported at the ends [34].

Six refined methods of analysis have been briefly discussed. A more rigorous description of these methods can be found in the ci ted references. As will be discussed later, the power and versatility of the finite element method led to its choice for modeling the bridge specimen described in this report.

2.2 Simplified Methods of Analysis

Simplified methods have been developed from these more complex theories. The AASHTO distribution procedure, discussed in Section 1.1,

Page 25: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

9

was developed over several years. The first edition of the AASHTO Specifications, published in 1931 [35], provided load fractions to be used for calculating design moments in interior stringers (of any type) with concrete or timber floors. The 7th edition of the AASHTO Speci f i cat ions [36] i ntrod uced a separate mod ifi cat ion factor for moments in interior steel stringers. This modification resulted from analytical and experimental studies conducted in the 1940's by Newmark [37]. The load distribution fractions ror concrete decks on steel or prestressed concrete stringers in the current 13th edition of the AASHTO Speci fications [1] are based on Newmark's work. According to that procedure, each girder is designed to carry a fraction, K, of the wheel load, where

K = SIC (1 • 1 )

and S average girder spacing in ft; and

c specified constant depending on bridge type.

The constant C is 5.5 for a slab and girder bridge designed for two or more lanes of traffic, and is 7.0 for one lane. Equation 1.1 usually provides a conservative estimate of the actual girder loads, and is easy for the designer to apply to specific bridge types [34].

Another simpli fied method, developed in the 1970's by the Ontario (Canada) Ministry of Transportation and Communication, is described in Section 3.7 of the Ontario Bridge Design Code [2J. The distribution factor procedure of this method is comparable to that described in Section 3 of the current AASHTO Specifications, except that the distribution factors are selected from charts. Most of the key parameters affecting load distribution are considered: bridge span, bridge geometry, bridge width, girder spacing, number of loaded lanes, and bridge stiffness properties [34]. This is intended to provide improved accuracy. The charts were derived using orthotroplc plate theory, and checked using the grillage analogy method.

Page 26: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 27: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 3

EXPERIMENTAL TEST PROGRAM

3.1 General

As explained in the introduction, one objective of this study was to measure the girder loads and bending moments in a full-scale highway bridge. As part of another investigation [3], a full-scale composite highway bridge was constructed and tested at the Phil M. Ferguson Structural Engineering Laboratory at The University of Texas at Austin. In the following sections, a description will be given of the bridge components, the construction procedure, the testing procedure, and the instrumentation. Appendix A lists the material properties.

3.2 Specimen Description

3.2.1 Steel Girders. As shown in Figs. 3.1 through 3.4, the three steel girders were W36x150 sections, 60 ft long, simply supported on a 48-ft span. The girders, donated to the project by the Texas State Department of Highways and Public Transportation (District 14), had been recovered from a bridge that had been replaced, and were in excellent condition. To ensure composite action, 7/8-in. diameter studs were welded to the top flange of each girder. The studs were placed in rows of three along the top flange, as shown in Figs. 3.5, 3.6 and 3.7. In the southern half of the bridge, the rows of studs were placed diagonally to allow adequate spacing between the panels. The girders were connected by steel diaphragms, shown in Figs. 3.8 and 3.9. The girders were simply supported on neoprene bearing pads, resting on anchor blocks, which in turn rested on the laboratory floor.

3.2.2 Cast-In-Place Deck. Cast-In-place concrete with #4 reinforcement was used for the entire deck on the northern half of the bridge, the deck above the precast, prestressed panels, and the cantilever overhangs. The design strength of the concrete was 4000 psi. The concrete used for the deck, supplied by Texas Readymix (Austin) met the Specifications of the Texas Department of Highways and Public Transportation for Class C concrete [38]. The deck thickness averaged 7-1/2 in. To facilitate construction and subsequent evaluation of test results, the deck was cast with a uniform thickness.

11

Page 28: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

~ I

SUPPORT I

I t I

SUPPORT . . ! REINFORCED

CONCRETE DECK = i§ii dE :::::::~Ii'''ii;iii 4 ['_ H •••

- . . .~.MtJ W 36 • 150 ---'

-<-- .. ~ .~- . .;:a-I I

8 FT 48 FT - 0 IN ! I 8 FT

Fig. 3.1 Elevation view of laboratory specimen

..... N

Page 29: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

~

SUPPORT

--~ 6 IN . I I-

r • • r • • 6 IN

~ SUPPORT

.I ........ 'I N

~'!- 3 FT - 3 IN

EXTERIOR I PRECAST. PRESTRESSED PANELS GI ROE R ---fS- 1:;;;:;~~;;;;~;:;::::::i::::::I::~:::~:~::~~%~-::.:::::~::;:::~ii::;:::::::i:~::::~;:t~:::;::~.::::~:i:CAST:"I N-PL ACE SL AS

INTERIOR I ~ GIRDER I· ~~X~:

7 FT

---- I i I 7 FT

-~-l-.' .' ___ .L

13FT - 3 IN

NOTE

~ rE­, FT - 6 IN

....e

PANELS ® PANELS ®

4 -48 FT - 0 IN

ARE 7 FT • 6 FT - 6 IN

ARE 8 FT • 6 FT - 6 IN

• • l....)

Fig. 3.2 Plan view of laboratory specimen

->-t

t-' W

Page 30: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

f 4 BARS AT 4 3/8 IN C.C. IN BOTH DIRECTIONS

f 4 BARS AT 8 3/4 IN C.C.

PRECAST. PRESTRESSED PANELS IN BOTH DIRECTIONS

2 IN ClEAR

TOP COVER t~: :~ Wp~£:::::4%::k SHE~ ~ECTORS - I *

#4 BARS AT

8 3/4 IN. C.C. IN BOTH

DIRECTIONS

....... -..... ,....

.......... ~\ .... -:- INTERIOR ~ ....

DIAPHRAGU

~- .~ .>t<. I

~ I

7 '/2 IN

~ 3 FT - 3 IN 7 FT 7 FT 3 FT - 3 IN

Fig. 3.3 Cross section of laboratory specimen showing precast, prestressed panels

t-J ~

Page 31: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

I • BARS AT • 3/8 IN C.C. IN BOTH DIRECTIONS,

CAST-IN-PLACE SLAB

, • BARS AT 8 3/. IN C.C. IN BOTH DIRECTIONS

SHEAR CONNECTORS 2 IN CLEAR I

TOP COVER eTYP) ~ ~ t J I~ --'!-i~ II I ' f 1::A!:Ii :i: C I. +

. 7 '/2 IN -:TE:S--01 APHRAGU

3 FT - 3 IN 7 FT 7 FT 3 FT - 3 IN

Fig. 3.4 Cross section of laboratory specimen showing cast-in-place deck

I-' VI

Page 32: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

16

6 IN

1 1/4 IN DIA

3/B IN H

7/8 IN DIA

Fig. 3.5 Typical shear stud

Page 33: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

12 I

N .. 48 FT - 0 IN --I

6 FT - 0 6 FT - 0 IN I 24 fT-O IN 24 FT-O IN

lIN f $_ N . ,--

1 IN

T , I

j

~o 0 0 00 00 0 00 0 oooo~ -t=::--~8d'886> 86> c? cO 0' 86> c? 00 0 0 0 0 0 00 0 0 0 0 000 QCXX)-, -

I--- -- 00 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 000 oa:o 1---

I

ct SUPPORT

SYUUETRIC 3 AT 12 IN I

24 IN

£ STRUCTURE

5 AT 18 IN

\ '\ + 3 AT 3 AT

15 IN 12 IN

~ SUPPORT

Fig. 3.6 Layout of shear studs on the steel girders

,

• I I

r 2 A

9 IN

IN

4 IN 4 IN

T 6 IN

I-' ......

Page 34: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

18

CAST-IN-PLACE CONCRETE

, 4 BARS AT 8 3/4 (BOTH DIRECTIONS~

\ \-----------r--~~

\

1 IN BY 1/2 IN I

fIBERBOARD STRIP

J

~ ;- ! - I I :2 I~ , . ! p- \ / )' I I.

i ! " I ,.

I i

1 IN

SHEAR CONNECTORS (3/RO\lJ)

PRECAST. PRESTRESSED PANELS

Fig. 3.7 Detail of connection between girders and panels

Page 35: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

ANGlE 4 • 4 • 12 IN LONG

CHANNEL 12 • 30 • 82 IN LONG

7 FT - 0 IN ~ ~

Fig. 3.8 Typical exterior diaphragm

W 38 .150

,...... \0

Page 36: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOCATION Of fAILED DIAPHRAGU v.£LD

ANGLE 4 1/2 • 15 • 1/2 • 12 IN LONG

1 5 I N I I ANGL E 5 • 3 1 /2 • 1 /4 • 6 f T - 8 IN LONG

1 IN ! "'~ _ 1 J

12 IN

W 36 • 150

2 INl ~__ _~~

. 7 fT - 0 IN . t< >1

w . <2- .c .......... ~"Q 3 • 5 • 3/8 I £ii> » -......::..--- ;

It (TVP)

EXTERIOR GIRDER INTERIOR GIRDER

Fig. 3.9 Typical interior diaphragm

N o

Page 37: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

21

3.2.3 Precast, Prestressed Panels. Six precast, transversely­prestressed panels, fabricated by J.D. Abrams Precast (Austin) spanned between the longitudinal girders. These panels, illustrated in Figs. 3.2 and 3.10, rested on 1 x 1/2-in., asphalt-impregnated fiberboard strips. The panels were 6.5 ft wide by either 7 or 8 ft long. They were of 6000-psi concrete, 4 in. thick, and were later covered by a 3-1/2 in. topping of 4000-psi concrete.

3.3 Construct ion

3.3.1 Steel Girders. Construction began in the summer of 1983 with the placement of the three girders on top of the neoprene pads and anchor blocks. After pos i tioning the three girders at a 7-ft spacing, the interior and exterior diaphragms were welded to the girder webs. The shear studs were then welded to the top flanges of the girders with a portable stud welding machine, and all welds were checked for soundness.

3.3.2 Precast, Prestressed Panels. The six precast, prestressed paneis-weretransported-by-truckto- the laboratory, lifted into position with an overhead crane, and placed between the girders as shown in Fig. 3.7.

3.3.3 Formwork. The bridge was unshored. Wooden formwork was installed between the girders on the northern (cast-in-place) half of the bridge, and was supported by the girders using steel hangers. On the southern half of the bridge, the panels spanned between the girders, and served as formwork. Wooden formwork was used for short sections of deck underneath the north and south ends, and along the entire length of the bridge for the cantilever overhangs.

Wooden formwork consisted of 1/2-in. plywood stiffened with 2x4 and 2x6 lumber, lacquered and oiled. Care was exercised to prevent the form oil from getting onto the steel reinforcement. Caulking and styrofoam were used to seal cracks and prevent leaks, and all removable bolts and inserts were coated with grease to facilitate removal.

3.3.4 Reinforcement for Cast-in-Place Deck. Steel reinforcement for -the-cast-ln=-pfacedeck-wasslippiiEi'd.-by Alamo Steel and Machine Company (Austin). Chairs provided 1-112 in. cover between the bottom formwork and the bottom layer of reinforcement. Top reinforcement was supported on 4-1/2 in. chairs. The mat of reinforcement lying on top of the precast, prestressed panels was elevated 112 in. above the surface of the panels with short lengths of #4 bar placed between the panels and the mat. Most of the deck was reinforced by 114 bars at 8-3/4 in. in both directions. The cantilever overhangs had 114 bars at 4-3/4 in. spacing in both directions, top and bottom. The layout of the steel reinforcement, shown in Fig. 3.11, conformed to Texas Standard Department of Highways and Public

Page 38: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

22

--ft.,--------,

, 3 BAR

AT 8 IN C. C.

.~

I

!

8 FT - 8 IN

4 IN Y (TVP) _. -. -.. .... --- ...... -+-+-+-+--r-

I -----t-2 IN (TVP) 1 ~;/8 IN DIAo. STRANDS A~l 3 IN STRAND

8 IN c.c. EXTENSION

PLAN

...--- BROOU FINISH TOP

1 IN (TVP) ~l U - BARS

Ii I! 2 IN I

r::::~::::::===~===:E:::::3-i .-t-r ~~r:-+ 4 IN i I . 8 FT - 0 IN PANELS ~ 2 IN ~--

; 7 FT - 0 IN PANEL S ® ~

SECTION

Fig. 3.10 Precast, prestressed panels

Page 39: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

23

Fig. 3.11 Layout of steel reinforcement

Page 40: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

24

Transportation Drawing Number 1284 (Texas State Department of Highways and Public Transportation, Bridge Division, Drawing File 1284, Research Project 3-5-83-50, April 14, 1982) [39].

The tr"ansverse and longitudinal bars were continuous (without splices). The additional transverse steel in the overhangs extended 21 in. inside of the top edge of the exterior girders.

3.3.5 Placement and Cur ing of Concrete. The concrete deck was cast monolithically using ready-mix concrete, placed with a 1-yd. bucket on an overhead travelling crane. The concrete was vibrated with two portable vi brators, and finished with a 25-ft long vi bratory screed, moved longitudinally. Additional finishing was unnecessary Twenty-one standard 6x12-in. cylinders were cast, as well as nine 6x6x18-in. beams. Polyethylene sheets as well as a membrane curing compound were used to cure the deck. The test cylinders and beams were cured under the same conditions as the deck.

3.3.6 Removal of Formwork. Wooden formwork was removed about seven days after the deck was cast. Four 3-in. diameter cores were removed from the deck to permit attachment of the hydraulic loading rams.

The test setup, shown in Figs. 3.12 and 3.13, consisted of four identical 72-kip hydraUlic rams attached to two reaction beams. The rams were supplied by two hydraulic pumps with a combined capacity of 55 gpm at 3000 psi [40,41]. The hydraulic lines on the rams were interconnected to a single servoval ve, so that an equal pressure could be applied to all four rams, producing an equal load in each ram. A schematic diagram of the loading system is shown in Fig. 3.14. A servocontroller and strain gage actuated load cell controlled the loading.

Each of the two 21-ft reaction beams consisted of two S10x24.5 sections attached together, and bolted at 4-ft intervals to the tie-down points on the test slab (Figs. 3.15 and 3.16).

3.5 Instrumentation

3.5.1 Beam Strain Measurement. The distribution of loads to the girders was determined using 54 electrical resistance strain gages, located as shown in Figs. 3.17, 3.18, and 3.19. Before the strain gages were applied, the steel surface was polished and cleaned. The strain gages were Precision Measurements W32 [42], attached to the steel with M-Bond 200 adhesive. The lead wires for these strain gages were soldered to shielded cable. The connection to the lead wires, and the

Page 41: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

t SUPPORT

r­I

8 IN • 20 IN I LOADING PLATE --+1------.

24 f"T __ L ~--I

I

10 f"T I 10 f"T

24 f"T

20 IN

~ SUPPORT

-..l

l

7 '/2 IN in h I !! n=t M* $"!iii I' 1==t36 IN

HYORAUL I C RAU

REACTION BEAU

ANCHOR BLOCI(

J!6 IN

TEST SLAB

THREADED ROD INTO TEST SLAB

Fig. 3.12 Elevation of test setup N VI

Page 42: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

NOTE ANCHOR BLOCK IS CUT AWAY TO SHOW THE REACTION BEAU

~ I

STRUCTURE I : ~-.~ ,

8 IN :

I

HYDRAULIC RAU ,

THREADED ROD INTO

8 IN • 20 IN LOADING PLATE

REACTION BEAM

'TEST fLOOR " _'.. v. _' ~ ... ....: I : I of. 1 ! .n.. J. +_.... 'un fL_. n

3 fT - 6 IN 4 fT 3 fT 3 fT 4 fT 3fT - 6 IN

2 1 fT-O IN

Fig. 3.13 Cross-section of test setup

N 0\

Page 43: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

~ SERVO

INPUT PROGRAUWER /' CONTROLLER

/ ~

I' V I SERVO VAL VE

rL

LOAD CELL ]~ r- ~ I"""" ~ r- joo-,

rt-~ ... ~ ~ t'\ ~ .Vj

iL- rt--. "" -

Fig. 3.14 Schematic of loading system

I

r-

~

HYDRAULIC POIER

SUPPLY

1-1

.... tLJ .l.

""

N "-J

Page 44: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

28

Fig. 3.15 Reaction beam

Page 45: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

EYEBRACKET MOUNTING FOR HYDRAULIC RAY ------

2-S10. 24.5

6 IN ~_I ~~8 I~

~

SYUUETRIC I I

1 ,3FT - 0 IN , ~-.----.--- ------~I r- , i ' I

5 IN I 5 IN ~-T1-

IYo'. I

12'IN. 12 IN PLATE

1~ :~2}c!2 - -=:Ji 3- j q Ii i11r r~.> - I "II

IN I "'"IIIIIMlillmiill ! i 'I II

I

o o o (\

i STIFFENER

o

THREADED ROD INTO TEST FLOOR

4 IN--++t.- 4 IN 4 IN -=-; I r 4 IN ~-- - ---- --- - ------- ---~ ------~

4 FT - 0 IN 2 FT - 0 IN

IooI!: 10 FT - 6 IN --I

Fig. 3.16 Side view of reaction beam

TEST SLAB

N \0

Page 46: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

30

5/8 IN

12 IN

1 IN --..!--14-

1 IN

24 IN

lI~ 1 IN

36 IN

Fig. 3.17 Location of strain gage on the steel girder

Page 47: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

t-- N

GAGE LINE NUMBER ~ 1 2 3 .. 5 8 7 8 8

4FT - 8 IN s-rtI .. FT - e IN

6 IN II 1 5 F r 1re IN (TVP) I

--I--I---{.>-G-G-G-G-G-G--G----G II

II ~-1-t-;Q-Q--0-+-~~ : I

I

I 1

~ SUPPORT

;d,:111+1 I LOADING

PLATE

~ STRUCTURE

NOTE : 0 DENOTES THE LOCATION OF 3 STRAIN GAGES ON THE STEEL GIRDER

Fig. 3.18 Plan view of strain gage location

~ SUPPORT

w ......

Page 48: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

32

Fig. 3.19 Typical strain gage on steel girder

Page 49: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

33

strain gage itself, were protected with M-Coat D waterproofing compound, and a Barrier-E rubber pad.

The data acquisition system for these 54 strain gages consisted of 6 switch and balance units and 2 strain indicator boxes. Three switch units, wired to one strain indicator unit, were used to read the gages for each girder.

3.5.2 Deflection and Slip Measurement. Vertical deClections along the steel girders were measured with dial gages and linear potentiometers, as shown in Figs. 3.20 and 3.21. Horizontal slip between the deck and girders was measured with dial gages and clip gages, as illustrated in Figs. 3.22 through 3.24.

3.5.3 Crack !:!easur~!!!.ent. Crack widths in the concrete deck were measured visually with a crack template. Crack propagation was followed by marking cracks as the test progres'$ed.

3.6 Loading Sequence and Testing Procedure

Figure 3.25 outlines the loading sequence. The bridge was first loaded statically to 30 kips per ram in increments of 5 kips. The loading continued from 30 kips to a maximum of 60 kips in increments of 2.5 kips. The weld between the center diaphragm and the east girder failed when the peak load of 60 kips was attained, as shown in Figs. 3.9 and 3.26. The load was then decreased from 60 kips to 0 kips in increments of 20 kips. At each of these load stages, all gages were read. About 8 minutes were required per load stage to scan 54 channels on the switch and balance units and record the strains.

After re-welding the broken diaphragm, the structure was then subjected to 5 million cycles of fatigue loading. The load varied sinusoidally from 5 kips to 26 kips, the average load being 15.5 kips. The loading frequency was about 2 ~ycles per second, as shown in Fig. 3.27. The diaphragm welds broke again in several locations during the fatigue loading.

After the 5 million cycles had been attained, the diaphragms were again re-welded. The bridge was then loaded statically to 40 kips per ram in increments of 5 kips, and unloaded in increments of 10 kips. Readings were again taken at each load stage.

Page 50: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

N t--

--'IW"t~ P ? 10 ~ I ~ Ii t ' + ~ LOADING ~ t'V,-----H! ~~ ~

II PLATE._____ I ~-H--. ------'i'\7 'V pO

• , I II'"

~ L P (VERTICAL DEFLECTION)

o DIAL GAGE (VERTICAL DEFLECTION)

• DIAL GAGE (SLIP BETWEEN DECK AND GIRDER) o DIAL GAGE (SLIP BETWEEN DECK AND GIRDER)

Fig. 3.20 Layout of deflection and slip instrumentation

1 I

w ~

Page 51: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

,

I •

I

Fig. 3.21 Dial gage and linear potentiometer to measure vertical deflection of steel girders

35

Page 52: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

36

Fig. 3.22 Dial gage to measure slip between deck and girder

Fig. 3.23 Clip sage to measure slip between deck and girder

Page 53: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

1

1

SPRING HINGES-~

'-----STRAIN GAGE

SIDE VIEW

STEEL BEAU

END VIEW

Fig. 3.24 Clip gage used for measuring slip between deck and girder

37

Page 54: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

38

u ..... e:( ..... (/)

0.. ..... -(/) XW }IIIII 0 .....

ti q-W ..... e: III

W .2 t» ~ --:::::> - u ~ 5:2 .- >-

:Eo ti ..... It) (/) ..... LL o..(/) _LLI .. xl-

I 0 <D

o 000 0 0 000 en ...... <D It) q- rt) C\J

(Sdl)4) W~~ ~'3d a~Ol

en lLI

~ o

'178-1£-8 '178 -LZ-8

'I78-£I-L 'I78-01-L 'I78-90-L

'178-1 £-S

t:lO Co

-,-.4

"0 <U 0 ~

c... 0

>. s... 0 .,., III

-,-.4

::c

\.('\ ('\1 . M . t:lO

-,-.4 t.t..

Page 55: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

39

Fig. 3.26 Failed diaphragm weld

Page 56: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

APPLIED LOAD

i

p 1 1 p

rim Tffn

P = PSTATIC + Po SIN ft 26 K

15.5 K'I--:;77""\\~T\~\ ----,T\~, -----:17\"::--, ~T\--1 Po

5 K PSTATIC

TIME

Fig. 3.21 Range of loading during fatigue test

~ o

Page 57: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 4

TEST RESULTS

4.1 General

The results of the pre-cracking and post-fatigue tests are presented in this chapter. The pre-cracking test was conducted in July 1984. The post-fatigue test was conducted in August 1984, after the structure had been subjected to several static tests (to a maximum load of 60 kips/ram), 5 million cycles of fatigue loading, and several more static tests to a maximum load of 40 kips/ram.

The distribution of girder loads was determined from strain readings. The procedure for doing this, discussed in detail in Section 4.5, involved the following steps:

1. longitudinal strains were measured in the girders at a series of evenly spaced pOints along the bridge, at 3 different heights at each pOint:

2. at each pOint, the strain variation with height was used to compute the curvatures of the girders along the bridge:

3. at each point, these curvatures were multiplied by the calculated flexural stiffness (El) of the girder to determine the moment variations along the length of each girder; and

4. the moment variations were numerically differentiated twice to obtain the load applied to each girder over its length.

As will be discussed in Section 4.6, errors were introduced by the strain gages, and also from approximations used 1n the data reduction. Such errors are generally increased by the process of differentiation. In order to assess the accuracy of the above procedures for calculating girder loads, other types of data were also collected during the testing: vertical deflections of the steel girders; slip between the deck and the girders; and cracking patterns in the deck. These were used to check the validity of the numerical procedure, and also to check the internal consistency of the strain readings. These data are analyzed in Sections 4.2, 4.3 and 4.4, and the results are compared with the strain data in Section 4.5.

41

Page 58: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

42

!l.2 Deflections

!l.2.1 Load vs. Deflection. Figures !l.1 and 4.2 show the curves of load vs. midspan deflection for the exterior and interior girders. Girder deflections varied linearly with applied load. One assumption (which will be discussed in Section 4.5), involving the procedure used to smooth the strain readings, was that the structure was linear and elastic. The lineari ty of Figs. 4.1 and !l.2 clearly substantiates this assumption.

In Fig. 4.1, the resul ts of the pre-cracking test are shown by the solid line, and the post-fatigue test, by the dashed line. Vertical deflections of the girders were measured with dial gages, which registered deflections at the bottom flange of the steel girders, and were placed at the center of the span, at the loaded points, and over the supports. During the pre-cracking test, the dial gage at the center of the interior girder malfunctioned at the !lO-kip load stage. Consequently, Figs. 4.1 and 4.2 show load-deflection data for both tests up to a maximum load of only 40 kips.

During the pre-cracking test, the girders had a linear load­deflection relationship under loads ranging from 0 kips up to about 35 kips. When the cracking load of 38 kips was attained, the solid lines shown in Figs. 4.1 and 4.2 exhibited a decrease in slope, reflecting the decreased flexural stiffness of the cracked deck.

The load-deflection plots for the post-fatigue test were similar to those for the pre-cracking test. Because the deck was already cracked, the load-deflection behavior was linear throughout the entire test. At each load stage, corresponding deflections increased by about 6 percent after the 5 million fatigue cycles, reflecting some softening as a result of the fatigue loading.

4.2.2 Variation of Deflection in Longitudinal Direction. The deflections shown n gs. 4.1 and 4.2 were obtained from dial gages located at the girder midspans. As will be explained subsequently, vertical deflections at other points along the length of the girders were calculated from measured girder strains, in order to compare the calculated deflections with the experimentally determined ones, and to assess the accuracy of the strain gage readings.

The vertical deflections were calculated from measured girder strains (curvatures) using the moment-area theorems, and included the experimentally measured deformations of the bearing pads. The measured midspan deflections are compared with the calculated values in Figs. 4.3 through 4.6, and the centerline values are seen to agree within about 5 percent.

The fact that these deflections agreed so closely is important. The variation of deflection in the longitudinal direction was calculated

Page 59: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

43

MIDSPAN DEFLECTION OF EXT. GIRDER

• ,

PRE-CRACKING

POST -F ATIGUE

,

!' o .....

O~----~----------T-----~-------0.00 O. 10 O. 20

DEFLECTION (IN)

Fig. 4.1 Midspan deflection of exterior girder

Page 60: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

44

MIDSPAN DEFLECTION OF INT. GIRDER

o 1"')1

Q !

~ I -' 1

I

PRE-CRACKING TEST

POST-FATIGUE TEST

0' K ('111 /, , ,

~ I /'

~1 .? I

Oe-------~--I~--~---I----~----'---0.00 0.10 0.20 0.30

DEFLECTION (IN)

Fig. 4.2 Midspan deflection of interior girder

Page 61: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

It)

z~ g9 I­o L&J ....J u...o L&J­o·

9

It)

PANEL

LOAD = 25 KIPS EXTERIOR GIRDER PRE-CRACKING

CAST IN PLACE

DISTANCE ALONG BEAM (FT)

COMPUTED DEFLECTIONS

-. -~ MEASURED 9 ~ DEFLECTIONS

Fig. 4.3 Computed and measured deflections (pre-cracking), 25 kips, exterior girder

45

Page 62: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

46

PANEL

LOAD = 25 KIPS INTERIOR GIRDER PRE-CRACKING

CAST IN PLACE

DISTANCE ALONG BEAM (FT)

-. y

. y

Fig. 4.4

r 10

r r 20 30

COMPUTED DEFLECTIONS - .......

I

40

~--MEASURED

DEFLECTIONS

Computed and measured deflections (pre-cracking), 25 kips, interior girder

Page 63: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

,..... Z t-I

.......... U') o

z· ocr t-I t­O LaJ -'0 l4.­laJ· Ocr

U') -. cr

PANEL

LOAD = 25 KIPS EXTERIOR GIRDER POST-FATIGUE

CAST IN PLACE

DISTANCE ALONG BEAM (FT)

COMPUTED DEFLECTIONS --.

~ MEASURED .,v' DEFLECTIONS

Fig. 4.5 Computed and measured deflections (post-fatigue), 25 kips, exterior girder

47

Page 64: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

48

.... . ~

o N . ~

PANEL

LOAD = 25 KIPS INTERIOR GIRDER POST- FATIGUE

CAST IN PLACE

DISTANCE ALONG BEAM (FT)

I 10

I 20

I 30

COMPUTED DEFLECTIONS

I 40

Fig. 4.6 Computed and measured deflections (post-fatigue), 25 kips, interior girder

Page 65: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

49

using curvatures obtained from girder strain readings, and a comparison with the experimental deflections provides a check on the accuracy of the strain gage readings.

These strain gage readings are used in Section ~.5 to calculate the variation of moment and load in the longitudinal direction. Error was introduced by approximating the loads from the moments, and from several other sources. Based on the comparison of deflections presented here, it is concluded that a relatively small percentage of the total error was contributed by the strain gages themselves.

4.3 Slip Between Deck and Girders

The pre-cracking and post-fatigue slip between the deck and the steel girders is shown in Appendix B. In most cases the slip was small (less than 0.01 in.) indicating that the bridge was behaving as a composi te structure.

Two typical load-slip diagrams, shown in Figs. 4.1 and 4.8, correspond to the northern (cast-in-place) end. Figure 4.1 shows the pre-cracked load-slip relationship, and Fig. 4.8 illustrates the load­slip behavior at the same point after fatigue loading.

The slip between the deck and the steel beams can be described by [43]:

(4" 1)

where: y slip between the deck and steel beam,

x = distance along the beam,

€S - longitudinal strain in the slab, and

€b longitudinal strain in the beam.

The slip is zero at the center of the bridge, and increases to a maximum at the ends.

The pre-cracked plots indicate that the slip increased nonlinearly with increasing load. In general, the cast-in-place end seemed to slip more than the panel end, and the slab over the center girder slipped more than the slab over either of the two exterior girders. The largest slip occurred at the north end of the center girder.

The post-fatigue load-slip plots, shown in Appendix B, were also nonlinear, and the maximum slip was only 0.005 in. Slip at all load stages showed a slight but consistent decrease after 5 million

Page 66: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

50

LOAD VS SLIP NORTH END CENTER GIRDER PRE-F ATIGUE

-1 0 1 2 3 4 5 6 7 8 9 10111213 SLIP (THOUSANDTHS OF AN INCH)

Fig. 4.7 Pre-cracked load-slip data, center girder, north end

Page 67: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP NORTH END CENTER GIRDER POST-FATIGUE

-1 0 1 2 SLIP (THOUSANDTHS OF AN INCH)

Fig. ~.8 Post-fatigue load-slip data, center girder, north end

51

Page 68: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

52

cycles of fatigue loading. This decrease in slip under fatigue loading suggests that the composite behavior of the bridge did not deteriorate under fatigue. The reasons for the decrease are not clear. Although it might have been expected to result from a decrease in the in-plane stiffness of the deck owing to cracking, little change in overall bridge stiffness is apparent In Figs. 4.1 and 4.2.

4.4 Cracking Patterns in Deck

Cracking patterns in the deck are shown in Fig. 4.9 and 4.10. Strains and deflections were originally assumed to be equal in both exterior girders, and the symmetry of the cracking patterns about the center girder substantiated this assumption. The cracking patterns were non-symmetric about midspan, and the strains and deflections also differed from one end of the bridge to the other.

Most of the cracking occurred in the bottom of the deck at the cast-in-place end. Four short cracks formed on the bottom of the panel end, near the loaded pOints, and some cracks formed on the top surface of the deck over the panel jOints. The 5 million cycles of fatigue loading extended many of the cracks, and produced several new ones.

Crack widths under load ranged from less than 0.005 in. to about 0.05 in. The narrowest cracks formed on the top of the deck, and were caused primarily by shrinkage of the concrete. The widest cracks were observed near the loaded pOints on the bottom of the cast-in-place deck. These wide cracks opened up as the load was applied, and closed almost completely when the load was removed.

The absence of longitudinal cracks over the exterior girder's indicated that the slabs there, and the girders supporting them, rotated parallel to the longitudinal axis of the bridge as the load was applied. The pattern of cracks on the bottom of the cast-in-place end suggested the start of yield line fans on each side of the north end.

4.5 Calculation of Girder Loads from Strain Data

4.5.1 Q~~~!:.~!'. The distribution of girder loads was determined from steel strain readings. Usefulness of raw strain data was decreased by significant scatter as a result of errors caused by the gages themselves, and also by errors introduced in reading the data. Scatter was particularly noticeable for the gages near the supports, which registered small strains. As will be discussed subsequently, the steel strain readings were first smoothed, and the smoothed values were used to calculate girder curvatures and the longitudinal variation of girder moments and loads.

Page 69: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

- - -

-~- -l t:' ~

-~- --I ... -

~ .. --

CA

-

~ N

I

ST- IN- PLACE END

PANEL END

KEY

TOP CRACK

Fig. 4.9 Crack patterns in deck before testing

53

Page 70: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

54

--~- .. - --

'i

\ * \ '* \ I

*1 :/" \ \. I ,~ , -* I * : *

f':' , f

"r..

-0-1 •

- 1-- -

'* :I: ? 4:-

"',

* \ -I, \ " \

( *' $

-$ I !

~

t-Q-•

C

t N

I

AST-IN -PLACE END

-- .-~.-

-

PANEL END

KEY = - - - - BOTTON CRACK - TOP CRACK +*'if"+ EXTE NSION OF

BOTTON CRACK AFTER FATIGUE LOADING

Fig. 4.10 Crack patterns in deck after testing

Page 71: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

55

4.5.2 Load-Strain Diagrams. The 108 plots of load va. girder strain data are shown in Appendices C and D. The plots in Appendix C correspond to the pre-cracking test, and the plots in Append i x D correspond to the post-fatigue test. A typical pre-cracking load-strain plot (for Strain Gage 19) is shown in Fig. 4.11. This strain gage was located on gage line 7, on the top flange of the west girder (refer to Fig. 3.18).

The triangles in Fig. 4.11, representIng original load-strain data points, were rather scattered. It was reasoned that load-strain data from an ideal gage would lie on a straight line passing through the origin. The line shown in Fig. 4.11 represents load-strain data from such an ideal gage. It passes through the origin, and is drawn to minimize the sum of the squares of the deviations on the horizontal axis. This smoothing procedure ~as used for all 108 load-strain plots in Append ices C and D.

The smoothing procedure of Fig. 4.11 forced the experimentally recorded load-strain behavior of the girders to be linear and elastic. As noted earli er, this ass umption is cons is tent with the li near tty of the br idge's behav ior as evidenced by load-deflection plots (Figs. 4.1 and 4.2), and the correspondence between measured deflections and those computed using linear elastic theory (Figs. 4.3 through 4.6).

4.5.3 Strain Gradient Diagrams. The strain gradients over the depth of the girders for the pre-cracking and post-fatigue tests are shown in Appendix E. Fig. 4.12 shows a typical strain gradient diagram for the interior girder near the supports on the panel end, at the 25-kip load stage. The three points on each strain gradient diagram are smoothed strains corresponding to the 25-kip load stage. Each gradient was then obtained as that line which would result in the smallest least­square error for the three strain readings. Because the smoothed load­strain curves were straight lines passing through the origin, the strain gradients at each point were proportional to the applied loads. If the load of 25 kips per ram were increased to 50 kips, then all smoothed strains would double, and so would the strain gradients. The location of the neutral axis of the composite section, read directly from the plots in Appendix E, ranged from 24 to 34 in. above the bottom fiber of the steel girders, with an average value of about 31 in.

The position of the neutral axis was also calculated assuming a fully composi te section wi th an effecti ve width of 84 in. as gi ven by the AASHTO Specifications [1]. Because the concrete strains were small under the applied loads, it was thought that the initial tangent modulus should be used for concrete. The initial tangent modulus was calculated by modifying the current ACI formula [44] for the secant modulus at 0.5 fd as explained below:

Page 72: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

56

STRAIN GAGE 19

II) II)

~ 11)0 • 0..11) .... ~ ,-"II) • °0 <. 0 .J

II) • ",

• 0 ",

II)

~

0 N

II) -0 -

(COMPRESSION POSITIVE)

o~-------------------------------o 5 10 CHANGE IN STRAIN

15 20 25 (MICRO IN/IN)

Fig. 4.11 Pre-cracking load vs. strain plot, strain gage 19

Page 73: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

-:z .... ....,

Ct: W al .... I&.

'2 o t­t­O al

'2 o Ct: I&.

W o :z < t­en .... Q

LOAD = 25 KIPS GAGE LINE 2

~~ INTERIOR GIRDER ~ ~ PRE-CRACKING

o 20 40 60 f 100 STRAIN (MICRO IN IN)

57

Fig. 4.12 Pre-cracking and post-fatigue strain gradient diagrams (25 kips, interior girder, gage line 2)

Page 74: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

58

1. Ec was calculated using the current ACI formula [441,

Ec = Wc1 •5 33 (fc)0.5

2. Assuming a stress-strain curve of the form suggested by Hognestad [45], the ratio between Ec and ET was calculated.

when E: C

f = f'[2(8 Ie ) - (8 Ie )2], c ceo C 0

0.5 fc', 2(8 Ie ) C 0

(8 Ie ) C 0

2x - x2 = 0.5, x = 0.293

ETIEc = 21(0.5/0.293) = 1.17

0.5

3. ET was computed by multiplying the current ACI value for Ec by that ratio:

Young's modulus for the steel girders was taken as 29,000 ksi, glVlng tangent modular ratios (EslEr) of 5.76 and 4.86 for the cast-in-place and panel ends of the bridge, respectively. Using the AASHTO effective ~idth of 84 in., and considering the contribution of the reinforcement in the deck, the theoretical position of the neutral axis was calculated to be about 33 in. from the bottom of the girder. This number was close to the average experimental value of 32 in. The calculation of the position of the neutral axis according to the AASHTO Specification assumes complete composite action. This assumption was substantiated by the slip data in Section 4.3. The small slip between the deck and the girders, shown in Figs. 4.7 and 4.8, indicated that the bridge was indeed behaving as a composite structure.

4.5.4 Moment Diagrams. Once the strain gradients had been determined, the-longitudinal distribution of girder moments was calculated using the following procedure:

1. the curvatures (strain gradients in Fig. 4.12) were calculated at each point along the girder;

2. these curvatures ~ere multiplied by the corresponding theoretical transformed EI values (calculated as discussed above) to obtain the moments according to Eq. 4.2 below:

(4.2)

Page 75: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

where ES Young's modulus for steel;

IS = moment of inertia of the composite section transformed to steel;

M(x) = moment

59

The calculated moment diagrams for the exterior and interior girders are shown in Figs. 4.13 and 4.14, for an applied load of 25 kips per ram. As a result of the smoothing procedure used for the load-strain data, the ordinates of each diagram are proportional to the applied load, and the moment at any other load stage can be obtained by scaling. The pre­cracking moment diagram is shown by the solid line, and the post-fatigue diagram, by the dashed line. Because the panel end experienced little cracking, the moment diagrams for that end were about the same before and after the fatigue loading. Adjacent to the loads, cracks formed over the girders on the cast-in-place end. These reduced the transverse stHfness of the deck near the loads, and transferred the load longitudinally to adjacent transverse slab strips. As a result, the load was smoothed out along the length of the girder after cracking; the moment diagrams reflected this behavior by also becoming smoother and more rounded after fatigue loading.

4.5.5 Load Diagrams. Girder loads were computed from the moments in Section 4.5.4 using the differential equation of a beam deforming in flexure:

W(x) (4.3)

where W(x) load, and

M(x) moment.

The previously discussed moment diagrams were numerically differentiated twice using the central difference operator:

where Wi

Wi ~ (Mi-1 - 2Mi + Mi+l)/h2

load at the ith point on the girder;

Mi - moment at the ith point on the gIrder; and

h = uniform dIstance between pOints on the girder.

(4.4)

The load diagrams for the exterior and interior girders are shown in Figs. 4.15 and 4.16 for an applied load of 25 kips per ram. The pre­cracking load diagram is shown by the solid line, and the post-fatigue diagram, by the dashed line.

Page 76: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

60

......... 0 o (/)0

0..'" H ~

'0 Zo HO _N

PANEL END

LOAD = 25 KIPS EXTERIOR GIRDER

CAST-IN-PLACE END

O~~------------~--~~---------R o '0 20 30

DISTANCE ALONG BEAM 40 (FT)

50

Fig. 4.13 Pre-cracking and post-fatigue moment diagrams (25 kips, exterior girder)

Page 77: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

o o

.......... 0

PANEL END

LOAD = 25 KIPS INTERIOR GIRDER

CAST-IN-PLACE END

~--POST-FATIGUE

61

(/)-.t 0.. HO ~O

PRE-CRACKING

1 0 Z", H

.......,0 o o

1-<"1 Z W O ~O 0 0 ~.-

o~~r-~--~~~~--~~~~--~~

o '0 20 30 DISTANCE ALONG BEAM

40 (FT)

50

Fig. ~.1~ Pre-cracking and post-fatigue moment diagrams (25 kips, interior girder)

Page 78: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

62

......... 0 Zo H ....

o O~ «I o -' o

o ~

o o 7 o o ..,. I

PANEL END

\ \ \ \ I \ I \ I ~

LOAD = 25 KIPS EXTERIOR GIRDER

CAST-IN-PLACE END

\ / \ I

PRE-CRACKING

50

~~POST-FATIGUE

Fig. 4.15 Pre-cracking and post-fatigue load diagrams (25 kips, exterior girder)

Page 79: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

00

<C~ 01 ...J o

o ~ o o 7 o o T

PANEL END

LOAD == 25 KIPS INTERIOR GIRDER

CAST-IN-PLACE END

PRE-CRACKING

'---POST-F ATIGUE

Fig. 4.16 Pre-cracking and post-fatigue load diagrams (25 kips, interior girder)

63

Page 80: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

64

The panel deck on the southern end of the bridge was stiffer than the totally cast-in-place deck on the northern end, did not crack much, and did not exhibit the longitudinal redistribution of load shown by the cast-in-place end. As a result, the load diagrams for the panel end had peaks at the loaded points that were consistently higher than the corresponding peaks on the cast-in-place end.

Before the cast-in-place end cracked, it transferred the load transversely (between the girders), as shown in Figs. 4.15 and 4.16: the peak value at the loaded point was -110 Ibs/in. for the exterior girder, and -150 lbs/in. for the interior girder. After the deck over the interior girder cracked, its transverse stiffness was reduced. and more load was transferred from the interior to the exterior girder. This behavior is shown in Fig. 4.15 by the increase in load on the exterior girder at the cast-in-place end from -110 lbs/in. to -190 lbs/in. at the loaded pOint.

4.6 Computed vs. Experimentally Determined Load Diagrams

The load diagrams shown in Figs. 4.15 and 4.16 were used for checking the accuracy of the techniques used to measure and reduce the experimental data. Using the trapezoidal rule, the area under the load diagrams was calculated (for both the interior and exterior girders). and the total load so calculated was compared with the total load actually applied at each load stage. This comparison, shown in Table 4.1. provided an overall check on the procedure used to compute girder loads from smoothed curvatures.

As shown in Table 4.1, the calculated load was 13 percent low in the pre-cracked test. and 6 percent low in the post-fatigue test.

TABLE 4.1 Comparison of Calculated Load with Actual Applied Load

Pre-Cracking

Post-Fatigue

Exterior Girder

24.7

26.5

Interior Girder

37.6

41.0

Total

87.0

94.0

Actual Applied Load, % kips Error

100 13

100 6

One possible source of error was the approximation of the actual area under the load diagram by a series of trapezoids. Another possible source of error was the fact that the data were collected from strain

Page 81: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

65

gages using switching and balance units. Errors were introduced from the strain gages themselves, and from the recording of the strains during the testing.

The reduction in percent error (Table 4.1)- from 13 percent before cracking to 6 percent after fatigue loading could be explained by the fact that the post-fatigue load plots are smoother than the pre­cracking plots. The smoothness would be expected to reduce the error in approximating the curved load diagrams by straight lines. The error in the experimentally determined loads was between 6 and 13 percent. Since the experimental load diagrams were obtained by differentiating the moments, the error in the moment diagrams is believed to be at most 6 to 13 percent. Because of this small error, the experimentally determined moment diagrams are used as a reference for the moment comparisons shown in the next chapter.

Page 82: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 83: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 5

COMPARISON OF EXPERIMENTALLY DETERMINED MOMENTS WITH THEORY

5.1 General

In this chapter, the moment diagrams derived using the procedures of the AASHTO Code, the Ontario Highway Bridge Design Code, and those obtained from a finite element model w ill be compared. As discussed in Chapter 1, the AASHTO design moments for a bridge girder are determined by loading the bridge with part of a truck load so as to produce a maximum stress in a particular girder, and the design moments in that girder are then calculated using a distribution factor times the moment in that girder acting alone. Because the loads on the test bridge were placed so as to produce a maximum stress in the center girder, those girder moments can meaningfully be compared with predicted code val ues.

5.2 Design Moments from AASHTO

The AASHTO procedure used to calculate girder moments for a bridge was outlined quantitatively in Chapter 1. This procedure is illustrated numerically in Fig. 5.1 for the center girder of the laboratory specimen. A pair of 25-kip loads were applied to the center girder, and multiplied by a distribution factor of (715.5), producing a peak design moment in the center girder of 5730 in.-kips. The experimental and theoretical moments are compared in Figs. 5.2 and 5.3. The shapes of the curves are clearly different, and the peak moment exceeds the experimentally determined value by about 80 percent.

5.3 Design Moments from Ontario Highway Bridge Code

The Ontario design approach for determining girder loads for a highway bridge is similar to that of the AASHTO Code, except that the distribution constant C is determined from charts. The design procedure for calculating the moments in the interior girder of the laboratory specimen is illustrated in Appendix F. The design moment for the center girder is also shown in Figs. 5.2 and 5.3. The peak value of 4230 in.­kips is higher than the experimental value by about 30 percent.

67

Page 84: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

68

25 KIPS • (D. r) 25 KIPS. (D.F.)

20 FT

25 •

LC1111fIIl11111111I1~

CENTER GIRDER

(D. F.) • 15

LONGITUDINAL MOMENTS

IN CENTER GIRDER

DESIGN MOMENT FOR CENTER GIRDER - 25 • (7.0/5.5) • 15 • 12

- 5730 IN-KIPS

Fig. 5.1 Design moments from AASHTO Code, center girder of laboratory specimen

Page 85: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

o o o II)

PANEL END

LOAD = 25 KIPS INTERIOR GIRDER PRE-CRACKING

CAST-IN-PLACE END

69

·AASHTO CODE

ONTARIO CODE

F.E. SOLUTION EXPERIMENTAL

SOLUTION

O~--r-~--~--T-~---r--T-~~--T--·

o 10 20 30 DISTANCE ALONG BEAM

40 (FT)

50

Fig. 5.2 Comparison of moment diagrams from experiment, AASHTO, Ontario Code, and finite element analysis (25 kips, interior girder, pre-cracking)

Page 86: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

70

o o o 1.1)

o o o "lit

l­zo W o ~o 0-~

PANEL END

LOAD = 25 KIPS INTERIOR GIRDER POST-fATIGUE

CAST-IN-PLACE END

A/I.SHTO CODE

'-F.E. SOLUTION EXPERIMENTAL

SOLUTION

o~--------~--------~--~~~~ o 10 20 30

DISTANCE ALONG BEAM 40 (FT)

50

Fig. 5.3 Comparison of moment diagrams from experiment, AASHTO, Ontario Code, and finite element analysis (25 kips, interior girder, post-fatigue)

Page 87: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

71

5.q Moments from Finite Element Method

The laboratory specimen was modeled using the finite element method, which can closely approximate the actual solution for a wide range of structures with complex geometry, connecti vi ty, and material characteristics.

The finite element model was developed as part of another investigation [46]. In this finite element model, two types of elements are used to model the composite bridge. The reinforced concrete deck is modeled by two layers of thick shell elements in order to follow the cracking of the deck at top and bottom surfaces. The steel girder is modeled by three-dimensional beam elements. The computer program used for this analysis, SAPIV [47], was designed for linear elastic analyses only, and its application to the nonlinear analysis of reinforced concrete was achieved using a sequential linear elastic technique. Cracking of the deck was modeled using a smeared cracking model [48].

The finite element program gave moments for the steel girders, but computation of overall longitudinal moments in the composite girders was difficult and time-consuming. Examination of the output from the finite element program showed that transverse sections through the steel girder and concrete deck remained plane under load. Because plane sections remained plane. composite girder moments were calculated from steel beam moments by multiplying the steel beam moments by the ratio of the flexural stiffness of the compos i te gi rders to the flexural stiffness of the steel beam.

Moments so obtained from the finite element model are shown in Figs. 5.2 and 5.3. The fini te element moment diagrams follow the experimental diagrams in the outer two 15-ft sections of the bridge. nearest the supports. Adjacent to the loaded points, the finite element solution is still close to the experimental solution. In the middle 20 ft, however, between the loaded points, the peak finite element moments are 40 percent lower than the experimental values for the precracked case, and 28 percent lower after cracking. In this middle portion, the shape of the finite element solution also differs significantly from the experimental data.

The reasons for this are not clear. Other comparisons [46] showed that local finite element results agreed very well with experimental values. The most logical explanation is that the procedure used to calculate overall girder moments (multiplying steel beam moments by the ratio of overall girder EI to steel beam EI) was not sufficiently accurate in regions of the bridge subjected to higher local deformations under concentrated loads. While it might have been possible to use more precise procedures, this was not attempted due to lack of time. and because a more exact comparison was not essential to the scope of this study.

Page 88: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 89: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

C HAP T E R 6

SUMMARY AND CONCLUSIONS

6.1 Summary

The objectives of this thesis, given in Chapter 1, were as follows:

1. to measure the girder loads and bending moments in a full-scale bridge;

2. to compare the experimental girder bending moments with those predicted using some of the available analytical methods; and

3. based on this comparison, to assess the relative merits of the procedures studied.

Background material on refined and simplified methods for the analysis of bridge superstructures was presented in Chapter 2. Seven methods were briefly described: five refined methods and two simplified methods. An experimental test program for a slab and girder bridge was described in Chapter 3, and the test data were presented and discussed in Chapter 4. Although many plots and figures were described in Chapter 4, the test data were used primarily to obtain plots of the longitudinal moments (both pre-cracking and post-fatigue) for the center girder. In order to confirm the validity of the data reduction program, computed girder loads were compared with those actually applied. Other data, such as load-deflection or load-slip plots, were useful for checking purposes. The experimentally determined girder moments of Chapter 4 were compared with the moments obtained from the AASHTO Specifications, from the Ontario Highway Bridge Design Code, and from a finite element model of the bridge. These comparisons are presented in Chapter 5.

6.2 Conclusions

No method for determining girder design moments is clearly superior for all applications. Each has advantages and disadvantages.

One advantage of the experimental procedure is its accuracy. The error in girder moments (probably within 13 percent) was considered low enough to permit the use of the experimental moment diagrams as a basis against which to compare the other moment diagrams. A disadvantage of this approach, however, was the time and expense involved in testing

73

Page 90: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

74

a full-scale model, and the difficulty in applying the laboratory results to other structures.

The finite element method is more suited for analysis than typical design. One advantage of the finite element method was that the predicted moments were very close to the experimental values for some regions along the girder. It is believed that more precise procedures for computing overall girder moments from finite element results would have given good accuracy for the entire girder span. A second advantage of the finite element method was its ability to predict the cracking behavior of the deck. Disadvantages included: the need to use a computer; the time required to develop a model; and the need for prior knowledge of member sizes and material properties.

The AASHTO load distribution method is a simplified design procedure which calculates girder design moments as though each girder were acting alone. As a result, the shape of the AASHTO-predicted moment diagram will not match the shape of the experimental diagram, and predicted peak moments can be expected to differ significantly from actual values. In the experiment described here, the peak moment value predicted by AASHTO was 80 percent higher than the experimental value (uncracked case). One advantage of the AASHTO load distribution method, however, is its speed. The load distribution fractions are simply read from a table. A second advantage is the fact that the designer does not have to know the relative stiffnesses of the bridge members. The only parameters needed for design are the beam type, the stringer spacing, and the number of lanes. The convenience of the AASHTO Code, and its long history of successful use in this country have led to general acceptance by U.S. highway designers.

Like the AASHTO Code, the Ontario Bridge Code provides a simplified method of design that determines the girder design moments assuming the girder to act alone. It can therefore be expected to show the same kinds of inaccuracies as the AASHTO procedure. The Ontario procedure attempts to offer the designer more precise moment estimates. For the bridge studied here, Ontario-predicted peak moments were 30 percent higher than experimental values. This prediction was not only much more accurate than that of AASHTO, it also compares favorably with the solution obtained using the fini te element method. However, the Ontario Bridge Code has several disadvantages: 1) determination of girder moments required much more extensive calculations than needed for AASHTO; and 2) the designer had to know beforehand the relative stiffnesses of the girders and deck.

Accuracy should not be the only criterion by which these methods are judged. When predicted moments are used for design, the overall factor of safety of the resulting structure will depend on the accuracy of the analysis and the conservatism of the design, and also on the degree of indeterm inacy and quali ty of construct ion of the

Page 91: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

75

structure. Without looking at this total picture, it is not possible to define the desired degree of accuracy of a given method.

In assessing the proper role of these methods for estimating girder moments, it is important to recognize that each method has its place. A method such as AASHTO (or perhaps a simplification of the Ontario procedure) is necessary for preliminary design. After preliminary deck and girder sizes have been picked, a method such as the Ontario procedure can be used to produce a more efficient revised design. The finite element method appears advantageous primarily for Checking local behavior.

6.3 Suggestions for Further Research

In the course of this experiment, a number of questions arose which were not directly within the scope of this thesis. While time was not available to answer them here, the author feels that the following issues deserve further study:

1. The behavior of the clip gages. In this and other related studies, clip gages (used here for detecting slip) showed erratic behavior at low strain levels. Ways of reduCing this erratic behavior should be found, or the gages should be supplemented with surface strain gages.

2. Finite element girder moments. Different techniques should be investigated for calculating overall composite girder moments from the finite element output. Results achieved here (by multiplying by EI ratios) were reasonably successful, but less accurate than would have been expected based on other comparisons of finite element and experimental results.

3. Use of finite element procedures for design. Using parameter studies with finite element bridge models, it should be possible to develop design charts similar to, and perhaps more accurate than, those currently used in the Ontario Code.

4. Diaphragm behavior. It would be useful to know more about diaphragm behavior, in order to improve diaphragm design and detailing, and to prevent the early diaphragm failures observed in these tests.

5. DeSign procedures for other situations. It would be useful to conduct studies similar to this one on a bridge with continuous girders.

Page 92: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

1 1 1

1 1

1 1

1 1

1 1 1 1

1 1 1

1 1

1 1 1 1

1 1 1 1

1 1

1 1

1 1

1 1

1 1

1 1 1 1

1 1

1 1

1 1

1 1

1 1

1 1 1 1

1

1 1

1 1

1 1 1 1

Page 93: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN 0 I X A

MATERIAL PROPERTIES

Page 94: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

78

TABLE A.l Concrete Mix Design for Cast-in-Place Deck

Design Strength: 3600 psi

Water-Cement Ratio: 0.485

Slump: 3 in.

Type I Cement: 0.36%

Water: 0.42%

Aggregate: 0.22%

Added Water: 0%

Admixture: 6% air entrained

TABLE A.2 Cast-in-Place Deck Properties

.-----------Concrete

Cast date: 2/28/84

fc: 14 day: 3510 psi

28 dny: 4240 psi

180 day: 5160 psi

Slump: 3 in.

Steel

Si ze:

Grade:

Tested yield strength:

1/4

60

73 ksi

Page 95: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

-o o o q-

o o o (\J

o

79

14 28 180

AGE (days)

Fig. A.l Strength vs. age for cast-in-place C()l1';i:'~':~

Page 96: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

80

TABLE A.3 Precast, Prestressed Panel Properties

Concrete

Release strength:

Design strength:

Type:

Cast ins date:

7 day:

Sl ump:

Prestressing Steel:

Size of strand:

Type:

Grade:

Prestress force per strand:

4000 psi

6000 psi

Texas Class H, Type III (high early strength) cement, 6-1/2 sacks/cu.yd.

2/2/84

5104 psi

6593 psi

4 in.

3/8-in. diameter

7-wire

270, stress relieved

16.1 l<ips

Page 97: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

81

TABLE A.4 Seven-Day Modulus of Rupture Data

Breaking r~odulus

Beam Load P of Rupture No. ( lbs) (psi)

1 3465 1133 2 3470 434 3 4050 506 4 3890 486 5 2880 360 6 3080 385 7 3040 380 8 3580 448 9 3700 463

Average: 433 psi S. D.: 49.6 psi

C in

p

Page 98: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

Page 99: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN D I X B

LOAD VS. SLIP PLOTS

Page 100: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

84

LOAD VS SLIP NORTH END EAST GIRDER PRE-FATIGUE

-1 0 1 2 3 4 5 6 7 8 9 10 11 SLIP (THOUSANDTHS OF AN INCH)

Page 101: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP NORTH END CENTER GIRDER PRE-FATIGUE

-1 0 1 2 3 4 5 6 7 8 9 10111213 SLIP (THOUSANDTHS OF AN INCH)

85

Page 102: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

86

LOAD VS SLIP NORTH END WEST GIRDER PRE-FATIGUE

-1 0 1 2 3 4 SLIP (THOUSANDTHS OF AN INCH)

Page 103: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP SOUTH END EAST GIRDER PRE- FATIGUE

-1 0 1 2 3 4 SLIP (THOUSANDTHS Of AN INCH)

87

Page 104: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

88

""""0 (1)&0 0.. t-I ~

o c"ld-< o -J

LOAD VS SLIP SOUTH END CENTER GIRDER PRE-FATIGUE

-1 0 1 2 3 4 5 6 7 8 SLIP (THOUSANDTHS OF AN INCH)

Page 105: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP SOUTH END WEST GIRDER PRE-FATIGUE

-1 0 1 2 3 4-SLIP (THOUSANDTHS OF AN INCH)

89

Page 106: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

90

LOAD VS SLIP NORTH END EAST GIRDER POST-FATIGUE

L~~ ~-,----------------~ ........

o ",

c « o --'

o N

o -

-1 0 1 2 SLIP (THOUSANDTHS OF AN INCH)

Page 107: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP NORTH END CENTER GIRDER POST-FATIGUE

-1 0 1 2 SLIP (THOUSANDTHS OF AN INCH)

91

Page 108: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

92

LOAD VS SLIP NORTH END WEST GIRDER POST-FATIGUE

012 SLIP (THOUSANDTHS OF AN INCH)

Page 109: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP SOUTH END EAST GIRDER POST- FATIGUE

o 1 2 3 SLIP (THOUSANDTHS OF AN INCH)

93

Page 110: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

94

I

,......, (/)

a.. H ~ '-'"

o ",

o c( o ..J

o ('II

o -

LOAD VS SLIP SOUTH END CENTER GIRDER POST- FATIGUE

-1 0 1 2 3 4 5 6 SLIP (THOUSANDTHS OF AN INCH)

Page 111: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

LOAD VS SLIP SOUTH END WEST GIRDER POST-FATIGUE

o 1 2 3 SLIP (THOUSANDTHS OF AN INCH)

95

Page 112: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j j

j j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

j

I j

j

Page 113: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN D I X C

LOAD VS. STRAIN PLOTS

PRE-CRACKING

Page 114: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

98

STRAIN GAGE 1 STRAIN GAGE 2

:I .. .. .. ..... 'fit tl .. ... ... .. ~ ~ .. It It -' ... .. .. .. .. .. ..

== :it ..

.. .. .. .. • .. 0 .. .. : = = = ..

(CCIII'IIISSZaN NSnIW) .. .. (TE.IaN I'OUTIW)

0 • 0 S 10 0 I 4 • CIWIO[ IN STRAIN (.aCltO INI:tN) CHANGE IN STRAIN (.aCRO IN/IN)

STRAIN GAGE :5 STRAIN GAGE 4 .. .. .. .. .. 'fa ....

Ill. L .. ... ...

~ x .. .. It !io o· -' ... :: :: :it It .. .. .. .. ==

0 .. : :

= !

.. (TEBlaN HIITlYE) .. (CCIII'IIISSZaN !'OIlnYE)

• 0 0 15 )0 4J 1/ 0 1 til 11 10 II ~

CHANG[ IN STRAIN (.aCltO IN IN) CHANG[ IN STRAIN (.aCRO IN IN)

Page 115: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

99

STRAIN GAGE 5 STRAIN GAGE 6

: .. : f: ...... "' . .... ... ... ~ ~ ... It I' -' -' .. .. .. .. a • .. .. .. .. .. :: • .. = = ! ! .. (11l1li. I'GnTtWl .. (TlIIIJ. I'OI:rTXIII)

0 • 0 I ,0 'S to II: H 0 ;so .0 .., "A0 CtWIGl£ IN STWN (.aCRO IN IN) CtWIGl£ IN STRAIN (.aCftO IN IN)

STRAIN GAGE 7 STRAIN GAGE 8

.. .. .. .. .. .. .. ... ..... :1 .... .. .... toO ... ~ ~ ... I. It -' -' .. .. .. ..

lit 0 .. .. .. .. .. 0 0 .. .. , ..

~

! !

.. (c.w:sn. I'OIIT%W) .. (1I111J. I'OInllll)

• • 0 '0 to H 40 D 10 20 ;so 40 CHAHGE IN STRAIN (IiliCRO INIJN) CtWIGt IN STRAIN (IIIICRO IN/IN)

Page 116: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

100

STRAIN GAGE 9 STRAIN GAGE 10

.. .. .. .. fa -M.

L-... ... ~ .. ~ .. I: Is -' -' - .. .. .. • =t .. - .. .. .. • • .. .. = :!

: !

.. (TENaIll I'OIIlTJ"IE, .. (CCII'IIIISION POn1l1ll)

• 0 0 40 to UIO '::i: 200 0 " 20 :SO 40

CHAHO£ IN STRAIN (WlClO I IN) CHANGE IN STRAIN (WlClO INi:tN)

STRAIN GAGE 11 STRAIN GAGE 12

.. .. .. .. fa

...... .... L-... ...

~ ~ .. .. at as -' -' - .. .. .. a =t .. .. .. .. := 0 .. = :

! !

.. (UMll111 I'OIIl1M) .. (TENnIll I'OI%TI1II)

• • 0 '0 20 :so "",0 0 10 100 '10 J00

CIWfGI: IN STRAIN (WlClO I IN) CHANGE IN STItAIN (WI ClO IN IN)

Page 117: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

101

STRAIN GAGE 13 STRAIN GAGE 1.

"' • "' • "' "' - .... • ~: 11'0

L"' ... ... ~ ~ • I: I: • ~ ~

"' .. • .. .. •

:it 0 • .. "' "' .. .. 0 0 • .. .. : : ~

"' (COII'IIImCIN I'OI2nVE) .. (TINSICIN I'OSlnVE)

0 0 0 )0 .0 .0 lao 0 4 • 12 11 20

CHANGE IN STRAIN (MICRO INIzN) CHANGE IN STRAIN (MICRO INIIN)

STRAIN GAGE 15 STRAIN GAGE 16

.. .. .. .. .... .... tS 1110

L" ... ... ~ ~ • • I: I: ~ ~ .. .. .. ..

:it :it .. .. .. .. = 0 .. : : ~ ~

.. (TUllCIN I'OI2T1VE) .. (COII'IIIISZCIN I'OSITlVE)

0 0

0 so 100 lSO an 0 S 10 15 20 AS CHANGE IN STRAIN (MICRO IN IN) CHANGE IN STRAIN (MICRO IN IN)

Page 118: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

102

STRAIN GAGE 17 STRAIN GAGE 18

.. .. .. .. ..... ,... .. 0 ~:1 L" ... ... ~ ~ .. ~o 0"

~o 0"

~ ~ .. ~ .. X X .. .. .. .. 0 0 .. .. ~ ~

0 ~ p

.. (TENIION 'OSITIVE) "' (TENIlON 'OSITlVE)

0 0 0 10 20 :10 40 10 0 10 100 110 rxo

CHANG[ IN STRAIN (MICRO IN7IN) CHANCE IN STRAIN (MICRO IN IN)

STRAIN GAGE 19 STRAIN GAGE 20

"' • .. "' ..

,... ,... ",0 1110 L"' L" .. .. ~ ~ .. j: j: ~ ~ .. .. .. ..

0 0 .. .. .. .. .. .. 0 0 .. .. ~ ..

p

~ ~

(CCII'MnION 'OiIUVE) .. (TEIISlON ,onUVE)

0 0 0 • 10 I' 20 as 0 10 20 :10 40

CHANO[ IN STRAIN (MICRO INIIN) CHANG[ IN STRAIN (MICRO INIIN)

Page 119: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

103

STRAIN GAGE 21 STRAIN GAGE 22

.. .. .. .. .... ..... fl fl ... ... ~ ~ • •

I' Is ..J ..J .. :II ...

J III .. .. .. .. :: co .. : = ~ ~

• (TlMltON I'OIlTlVl:) .. " (CIIIiI'II£UlON I'OSITlVI:)

.. .. 0 10 '00 '10 2~ 250 0 5

'0 " CHANG[ IN STRAIN (MIellO IN IN) CHANG! IN STRAIN (MIellO INIIN)

STRAIN GAGE 23 STRAIN GAGE 24

.. "

.. .. .. ;;0

..... 0. • fl ... ... ~ • ~ • Is I, ..J .... .. .. .. ..

:t ~ .. .. .. .. 0 .. .. .. e : ~ ~

(TIMltON I'OIITSVI:) .. (TiMaON I'OSITSVl:)

0 .. 0 10 ao AO 0 25 SO 75 100 125

CHAHG! IN STRAIN (MICRO IN IN) CHAHG! IN STRAIN (MIellO IN/IN)

Page 120: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

104

STRAIN GAGE 25 STRAIN GAGE 26 .. .. .. .. .. .. .. 0'. ..... L" := ... .. ~

... .. ~ .. ...

at at .. .... .. ... .. .. :: .. • ..

~ .. .. .. .. .. .. .. • • .. .. : • = ! :

(CClll'tllmON I'OSIUVE) .. (TENSION ~TlVE)

.. 0 0

(lIIatO INI1N) 0 2 • • • CHNoIGf IN STIIIAIN CHNoiGE IN STRAIN (lIIatO INIIN)

STRAIN GAGE 27 STRAIN GAGE 28

.. .. .. .. .... .-",. 1/>0 • L'" 0." ... ... ~ &. ... a: at • .... ... •

'" .. .. .. 0 ~ • .. .. .. .. .. • .. .. .. : : ! !

(TEIIIJON I'OI1UVE) .. (CClll'tllmON I'OSlnVE)

.. 0 0 10 aD :so 40 so 0 1 2 ~ . s

CHNoICE IN STRAIN ClIIatO IN/IN) CHNoiCE IN STIIIAIN ClIIatO IN/IN)

Page 121: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

105

STRAIN tAtE 29 STRAIN GAGE 30

.. • .. .. -..... ..... ,,"0 L- ~= ... ... ~ .. ~ .. I: I: ..I ..I - .. ... ... ~ ~

.. .. .. .. 0 0 .. .. = = , !

.. (TEIIIlOll POUTtW) .. (TENSlOII 'OSlTlVE)

• 0 0 • '0 ,. 20 0 21 SO 75

CfWIGt IN STRAlN (WJCltO IN/IN) CHAHGE IN STRAIN (IIlCRO INIIN)

STRAIN tAtE 31 STRAIN GAGE 32

- .. "' ..

..... it. IIlO L"' L" ... ... ~ ~ .. .. I: I: ..l ..l .. .. .. ...

0 • .. .. .. .. .. H

0 0 H .. = = , ! .. (CCIIII'II£SUOll POUTlW) .. (TIIIIlOll POSITIVE)

0 • 0 I to ,. 0 '0 20 30 40 ~ to CfWIGt IN STRAIN (IIlCltO INIIN) CHANCE IN STRAIN (WJCRO IN IN)

Page 122: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

106

STRAIN GAGE 33 STRAIN GAGE 34

:: R - 'fa := ... ~

... ~ • •

~t ~: ..l

..l .. .. .. .. := K .. .. .. .. 0 ::: .. : .. -! ! .. (lINnON POS%UW) .. (CCIIiI'III:mON "OIX1'tW)

0 0 0 so 100 150 AOO 0 5 10 15 20 CHANGE IN STRAIN (IIICRO IN IN) CHANGE IN STRAIN (IIICRO INIIN)

STRAIN GAGE 35 STRAIN GAGE 36

.. .. .. .. ..... -1110 := .... .. ... ~ ~ • ~: ~t ..l ..l .. .. .. ..

K 0 .. .. .. .. .. 0 ::: .. : = ! !

.. (TINnON ,,"roW) .. (TINnON POIXTIW)

.. .. 0 to 40 to 10 0 TS 150 225 ~o

CHANGE IN STRAIN (IIICRO INIIN) CtWIOE IN STRAIN (IIICRO IN IN)

Page 123: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

STRAIN GAGE 37

... '"

'iilo 0. ... ... ~ ... ~o o· -' .. • ....

• 0

'" If> ... 0 .. ~

!

"'iC c. .

(COWPRESSION POSITIVE)

. , . . o 5 10

CHANCE IN STRAIN '("'IC~g IN;fIN) 30

WI STRAIN GAGE 39 ... '" 0.

B~ c'" ",," c "'0 .. " n

~I .. ~

~

.. CUNSlON POSITIvt)

15.00 150.00 225.00 300.00 IN STRAIN (IAICRO IN/IN)

STRAIN GAGE 38

j.

" }

~:1 ./' "1 / 21 /

""/ -1 ! !1

/'

/"

:V (TENSION POSlilVE)

o 10 20 CHANCE IN STRAIN

STRAIN GAGE 40

'" .. '" I. 'iilo

0.'" ... .. ~ ... °0 ~.

.. .. ... II> .. .., .. '" ..,

~l· 2l • ~1

~~ " I

"'~ I (COWPRESSION posn:VE)

0 0 20 40 10

CHANCE IN STRAIN ("'ICRO INIIN)

107

Page 124: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

108

STRAIN GAGE 41 STRAIN GAGE 42

'" , 0 "' '" "' .. - ..... 1/1'" I' litO 0.'" L"' ..... " ... lI<

~ -'" , "" f

°0 ~t ~"" i

; ...

:1 "' .; ...

J 0 .. ~1 01 ..

/ ..

0 1

I 0 .... 1 .. I

. ~i ) ~ , I

I e~ ..

I I

I / (TENSION POSITIVE) (TlNSION POSITIVE) "', /. ..

ok I I I I I I 0 o 10 20 30 40 50 60 0 100 200 300

CHANCE IN STRAIN (MICRO IN/IN' CHAHGE IN STRAIN (WICRO INIIN)

STRAIN GAGE 43 STRAIN GAGE 44

"' :::1 .! "' ..... U>O 1 lito , Go"' e:" ] ... , ~ ~'" .. ""'

0/ , oj ~o l~i .1 o· ... .:; I

"' ~1 ... 0 0' ·1 ... ~1

.,J I .. / .. .... , / i I

0 o. -; N .... 1

j ~ ,

~,

eJ /

! / i !

"' (CCIIIItIlIUCII POSlTIIIl) 1t'i1 6/ (TENSIOO POS:TIVE)

0 01 I I I

0 5 10 15 20 25 :10 0 20 40 de CHANGE IN STRAIN (MICRO IN1IN) CHANCE IN STRAIN (MICRO INIIN)

Page 125: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

109

STRAIN GAGE 45 STRAIN GAGE 46 ",

:: 14 ",

--. I

/ ~~ ~~~ ~ ~ ! ",

-~, ,.

~:I I ~

~o~ ""] ~:J

:j :J "I ::1

~1 01

N1 ~~ :i oj -I I

/ (TENSION POSIT.VE) "'1 I (COIIPRESSION POSITIVE)

oV 0 1 1 1 1 0.00 ',00 '0.00 '5, CO 20.00

0 7S .SO 22S 30e CHANGE IN STRA1N (toAICRO IN/IN) CHANGE IN STRAIN (IAICRC INIrN)

STRAIN GAGE 47 STRAIN GAGE 48

", 4

~:J ",

-",0 CI.'" CI.'" .. .. ~ :.: ....." -'" .. .. °0 ~ .. °0

~ .. "" "" II'> II'> ,., ,.,

0 0 ,., ,., on ", N N

0 0 N N

~ ~

e !:

II'> (TENSION POSITIVE) (TENSION POSITIVE)

0 0 0 20 40 10 aD 0 7S 'SO 225 300

CHANCE IN STRAIN (IAICRO INIIN) CHANCE IN STRAIN (IAICRO INIIN)

Page 126: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

110

STRAIN GAGE 49

"' "' STRAIN GAGE 50 "' "'

V>O V>O 11."' 11."' ... ... ~ ~

~"' . • °0 ~.

°0 ~. •

...J ...J

"' "' .., .., •

0 0 .., ..,

"' "' N N

0 0 N N

~ ~

e e

"' (C~RESSION POSITIVE) "' (TENSION POSITIVE)

0 0

0 5 10 15 20 I N

2JIN)

30 0 10 20 30 40 50 CHANGE IN STRAIN (MICRO CHANGE IN STRAIN (MICRO INIIN)

STRAIN GAGE 51 STRAIN GAGE 52

"' "' /' "' "' V>O V>O • 11."' 11."' ... ... ~"' '" ~"' • . °0 ~ . °0

~. ...J

"' "' • .., ..,

0 0 .., ..,

"' "' • N N

0 0 N N

~ ~

e e (TENSION POSITIVE) "' (C~RESSION POSITIVE)

0 0

0 50 100 150 200 0 5 10 15

CHANGE IN STRAIN (MICRO INIIN) CHANGE IN STRAIN (MICRO INIIN)

Page 127: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

III

STRAIN GAGE 53 STRAIN GAGE 54

on .. on ..

.-. <no 11>0 0. ... 0. ... ... ... ~ ~ ... ~~ ~o o· -' ....

... .. ... .. 0 li: .. on .. N .. 0 0 N .. :! ~

: :

'" (UNSIOII POSITtllt) .. {T£IISIOtI POSITllIt}

0 .,

0 to 20 0 25 SO 75 t~ fl:HANGE IN STRAIN (IlICRO INIIN) CHANGE IN STRAIN (IlICRO IN IN)

Page 128: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 129: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN D I X D

LOAD VS. STRAIN PLOTS

POST-FATIGUE

Page 130: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

114

STRAIN GAGE 1 STRAIN GAGE 2 0 .. 0 .. ... ... ., .. -.

III a..", .. a.. .. ... ., ..... .. ~ .. ~ 0 0

~~ ~ ... 0 ... ...

'" .. .. .. .. 0 .. 0 .. e .. e

~ .. ~ ..

.. .. .. (COMPRESSION POSITIVE) (TENSION POSITIVE)

0 0 0 II 0 2 .. • e 10 ~ 14 CHANC£ IN STRAIN (MICRO 11'1/11'1) CHANCE IN STRAIN (MICRO IN IN)

STRAIN GAGE 3 STRAIN GAGE 4

0 0 .. ... ... ., -. .. III a..", Q.", .. ...... .....

~ .. ~

~~ • ~~ 0 ... ... .. .. .. ..

0 0 .. .. ~ e

~ .. .. ..

(TENSION POSITIVE) (COMPRESSION POSITIVE)

0 I' 30 45 10 5 10 )5

0 CHANC£ IN STRAIN (MICRO IN/IN) IN STRAIN (MICRO IN IN)

Page 131: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

115

STRAIN GAGE 5 STRAIN GAGE 6

:

/ .. ...

.-. .-. 1/1 1/1 11. .. 0.. ..

g" ... .... ~

~= ~g 0 0 ... ... .. .. .. N

.. 0 N N

~ ~

~ ~

If> ., (TENSION POSITIVE) (TENSION POSITIVE)

.. .. 0 I 10 HI 20 25 0 30 .0 .0 120

CHANG[ IN STRAIN (IoIICftO INIIN) CHANCE IN STRAIN (MICRO INIIN)

STRAIN GAGE 7 STRAIN GAGE 8

.. .. .. .. ... ... .- .-. I/> 1/1 11. ... 0..., .... g~ ~

1= ~:'i: 0 ... ... .. .. .. ..

.. .. .. N

: ~ ..

~ ~ .. .. ..

(COWPAESS1ON POSITIVE) (TENSION POSITIVE)

.. .. 0 10 10 30 0 10 20 30 40 50 ~ 10

CHANCIE IN STRAIN (MICIIO IN/IN) CHANCE IN STRAIN (MICRO IN IN)

Page 132: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

116

STRAIN GAGE 9 STRAIN GAGE 10

.. .. .. .. iii" iii"

0.. .. .. 0.. .. "'''' ~.., ~ -~~ ~~

0 0 ... ... .. .. .. .. .. .. to ..

: :

o~ -:

~

.. .. -(TENSION POSITIVE) (COIoPIInSION POSITIVE)

.. .. ~ 10 120 180 0 10 20 30 0 40 CHANGE: IN STRAIN (MICRO INhN) CHANGE IN STRAIN (MICRO IN/IN)

STRAIN GAGE 11 STRAIN GAGE 12

.. .. .. .. 'iii .....

'" ..... ... .. ..... ....., >0: ~ -

CO ~~ ~ ...

0 0 ... ... '" .. N to

0 .. .. .. : :

~ ~

.. .. (TENSION POSITIVE) (TENSION POSITIVE)

0 .. 0 10 20 30 40 0 !l0 '00 1!10 200 CHANGE IN STRAIN (MICRO IN/IN) CHANCE IN STRAIN (MICRO INhN)

Page 133: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

117

STRAIN GAGE 13 STRAIN GAGE 14

0 .. • • -;:; -;:; L. Q.. .. ... ., g" ¥ --~=: 0 ali: ... ... .. .. .. ..

.. .. .. .. ~ ~ ..

~ l?

.. (COIo1I'II£SSION f'OSI n VE) (TENSION POSITIVE)

0 .. 0 30 0 4 a 12 " 20 24 18 3} 3a 40

CHNfCE IN STRAIN (MICRO INIIN) CHANCE IN STRAIN (MICRO IN IN)

STRAIN GAGE 15 STRAIN GAGE 16

:J .. ..

"'" VI 0.. ..

g'" ...... :.: -

CO i~ ~ ... 0 ... ... .. .. ., .. ..

2l .. .. .. ~

:1 2

(TENSION f'OS1TlVE) (CCIIoPRES$ION POSITIVE)

.. .. 0 50 '00 !50 0 5 10 15 20

CHANG[ IN STRAIN (IoIICRO IN/IN) CHANG[ IN STRAIN (UICRO IN/IN)

Page 134: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

118

STRAIN GAGE 17 STRAIN GAGE 18

co 0 • • 1i> .....

VI 11. .. 11. ..

E" ~ .... -~g ~:;: 0 0 -' -' .. .. .. ...

0 co .. .. = = ~ ~

... ... (TENSION POSITIIIE) (TENSION POSITlllE)

0 .. 0 10 20 30 40 0 50 100 HIO 200

CHANGE IN STRAIN (WICRO IN/IN) CHANGE IN STRAIN (WICRO INIIN)

STRAIN GAGE 19 STRAIN GAGE 20

~ • I O.

/' 1i> Ii ""I 1i>j 11. ..

g~i g~

~~ QO .c .... 0 0 -' -' ..

=:: N

.. '" .. N

I

~

=1 •

~ oi ~1

I 1 ... "'l • (COWPR£S51ON POSITlllE) (TENSION POSITIVE) i .. Q

0 5 10 15 20 25 0 10 20 30 40 CHANGE IN STRAIN (WICRO IN/IN) CHANGE IN STRAIN (MICRO INhN)

Page 135: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

119

STRAIN GAGE 21 STRAIN GAGE 22 0 • 0 •

Ui' Ui' Go .. Go .. .... .. .. ~ ~

~~ QO 0 ~ .. oJ

oJ .. .. .. .. 0 .. 0 .. ::! ::!

~ ~

.. (TENSION 'OSITIVE) ."

(COWPR[$SION POSITIVE)

0 100 150 0 0 50

0 5 10 15 CHANe;[ IN STRAIN (MICRO IN/IN) CHANGE IN STRAIN ( .. ICRO INIIN)

STRAIN GAGE 23 STRAIN GAGE 24

• 0 0 . . ,... Vi' en

Q.." A. ... ........ ..... '" '" ~ • QO QO < .... <" 0 0

oJ .... ... on N N

0

:: .. ~

I ~

on (TENSION POSITIVE) (TENSION POSITIVE)

0 25 50 75 '00

0 20 INJ~N) 0 0 10

CHANGE 1N STRA1N ("lCRO INI!N) CHANCE IN STRAIN ( .. ICRO

Page 136: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

120

STRAIN GAGE 25 STRAIN GAGE 25

.. .. .. .. u; • u; • A.., a. ... • ... ", ...... .. :.:

• - • CO • ll~ c ... 0 0 -' -' ., .. .. ..

.. .. ... .. ~ • ~

~ ~

.. ... a (COlI'RUSION POSITIVE) (TENSION POSITIVE)

.. 0 0 2

INIIN) 0 2 4 • • 10 12 14

CHANGE IN STRAIN (IAICRO CHANGE IN STRAIN (IAICRO IN/IN)

STRAIN GAGE 27 STRAIN GAGE 28

~ !ll • .. /a .. u; •

1/'1 '

0."'1 a.." • ~ ... B.'" -

~:l ~g • 0 -' .. ..

.. N, ...

~J ~ •

!~ .~ •

.. .. (TENSION POSITIVE) (COMPRESSION POSITIVE)

.. .. 0 10 20 30 40 50 0 1 2 3 " 5 • 7

CHANGE IN STRAIN (IAICRO IN/IN) CHANGE IN STRAIN (MICRO INhN)

Page 137: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

121

STRAIN GAGE 29 STRAIN GAGE 30

~~I !' 0

I ..

,,/ ii> '" e. .. e. ... .. ...", ... ",

~ :.: I - "/

~g ) ~g I 0 0

-' ...

... r .. " .. .. .I 0 c .. ... /

/

/ ~ ~ / ~ 2 /A

I .. ., I" (TENSION POSITIV.: (TENSION POSITIVE)

0 c

0 5 '0 0 2S so CHANGE IN STRAIN (MICRO IN/IN) CHANGE IN STRAIN (MICRO INIIN)

STRAIN GAGE 3~ STRAIN GAGE 32

ii> ~ I .' 0 ..

ii> A

"1 ; .. e..,

~ .... ! .....,

I lie - / -QO .. ~g <'" / 0

I 0 - I ... '" " / '" N N

0 / 0 N ...

~ "I ~

2 / ~

'" / .. (CQY>R£SSION POSITl\1:) .,

(TENSION POSITIVE)

j i i C

I) 5 10 0 10 20 30 47 CHANGE IN STRAIN (MICRO IN/IN) CHANGE IN STRAIN (MICRO IN IN)

Page 138: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

122

STRAIN GAGE 33 STRAIN GAGE 34

c

/ c • ... ..

V> V> a.., ... .., X

11. .. ...... ¥

~ -~~ ~g 0 0 ...J ...J

'" .. .. ... c 0 .. ...

I I

~1 :!

I

~ ~

'" .. (TENSION POSITIVE) (COWPRESS%ON POSITIVE)

Ci .. 0 50 '00 )50 0 $ '0 15 20

CHANGE IN STRAIN (MICRO IN, IN) CHANC! IN STRAIN (IotICRO INIIN)

STRAIN GAGE 35 STRAIN GAGE 36

Ci 0 .. .. V> V> 11.., a. ... ... .., ... .., '" x

~

~~ QO <'"

0 0 ...J ...J .. on .. ..

0 0 N .. !!! ~

~ ~

.. ., (TENSION POSITIVE) (TENSION POSITIVE)

Ci 0 0 20 40 0 7$ ISO n~

CHANGE IN STRAIN (IIiIICRO IN/IN) CHANGE IN STRAIN (IotICRO INIIN)

Page 139: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

123

STRAIN GAGE 37 STRAIN GAGE 38

.. 0 ... ...

Ui' Ui' 0..",

0.. .. ....... ...... lI<

~ ~

0 0

i:1l ~ ... 0

0 -' -' ., ... • N

N

.. .. N ...

:!! ~

~ ~

., .. (C~e'SlON ~OSlTlVE) (TENSION POSIT IVE)

0 0

0 II 10 15 ZO jll 30 0 10 20 30

CHANQE IN STRAIN (MICRO IN IN) CHANGE IN STRAIN (t.lICRO IN7IN)

STRAIN GAGE 39 STRAIN GAGE 40

0 .. ... .. Ui' --U\ 11.., !Lon

~~ g" i~ i~ 0 0 -' -' .. ., .. N

.. .. .. N

~ ., ~

~ ~

.. (TeNSlON POSITIVE) (COII'RUUON POSITIVE)

co co 0 15 150 225 0

(t.lICRO INHN) CHANQE IN STRAIN (MICRO IN/IN) CHANQE IN STRAIN

Page 140: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

124

STRAIN GAGE 4' STRAIN GAGE 42

.. "

0 ... ... .....

ii> 10/1 Go", Q"",

g" ... .., ~

¥

" ~

~= CO c.., 0 0 ..J -'

'" .. .. .. N

.. 0 .. N

~ :e

~ ~

.. .. {TENSION POSITIVE} (TENSION POSITIVE)

.. 0 0 10 20 30 .0 0 100 200

CHANG[ IN STRAIN (IAtCRO INIIN) CHANCE IN STRAIN (MICRO INhN)

STRAIN GAGE 43 STRAIN GAGE 44

.. ~I I" ... "

I /. ii> ii> I Go .. "

Q"",I

~ .. .... "', ¥ ' - " ~I •

~= OOi <'" 0 0 ..J .... I ..

~l ...

0

:J " ..

:! "

~ j -i

.. (COWPRESSION POSITIVE) "'~ .j (T£NSION POSITIVE)

oV 1 .. 1

0 5 10 15 20 25 30 0 20 40

CHANGE IN STRAIN (IAtCRO IN/IN) CHANCE IN STRAIN (MICRO IN/IN)

Page 141: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

125

STRAIN GAGE 45 STRAIN GAGE 46

0 0 .. • ;;- ;;-A. .. A.., ... .., ...... !.. :.: -~~ 0 0 c ...

0 ... ... ., ., .. ... 0 0 .. ...

~ :! •

! ;! •

(TtNS1ON POSlT1W) .,

(COMPRESSION POSITIVE)

.. HID US

0 0 75 0 5 10 15 20

CHANG[ IN STRAIN ( .. IeRO INhN) CHANGE IN STRAIN (MICRO INhN)

STRAIN GAGE 47 STRAIN GAGE 48

0 • .. .. .. ;;- iii A. .. A. .. ; .. ... .. - !..

~~ 0

~~ ... ... .. ... ... .. 0 0 .. .. ~ !!

~ !

.. .. (TENSION POSITIW) (TENSION POSITIW)

0 0 0 20 40 .0 0 75 150 225

CHANGE IN STRAIN ( .. ICRO INIIN) CHANGE IN STRAIN (MICRO INIIN)

Page 142: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

126

0 • U\ "-on .... .., '" ~ QO <" 0 -'

on .. 0 .. ~

~

on

0 0

CHANCE

o .

QO <" o

.. ..

!

STRAIN GAGE 49

• (CC*PIIESSION POSITIVE)

5 '0 '5 %0 %5 IN STRAIN (MICRO INhN)

STRAIN GAGE 51

, /

~/

j'

/ I ,

,/ /

l

"

". /

/ (TENSION PCSPI\'('

O.-------~------_r------_r--o 50 '00 ,50

CHANCE IN STRAIN (MICRO INIIN)

0 • U\ "- .. ..... '" ~ ~~ 0 -'

on .. 0 .. ~

e •

on

0 0

CHANCE

o .

.. .. o ..

STRAIN GAGE 50

• •

(TENSION POSITIVE)

'0 %0 IN STRAIN (MICRO INhN)

STRAIN GAGE 52

(COMPRESSION POSITIVE)

04---------------r------------o 5 CHANCE IN STRAIN (MICRO IN/IN)

Page 143: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

127

STRAIN GAGE 53 STRAIN GAGE 54

.. .. .. .. .. iii ~ .....

In CL., CL", ..... ....... ~ .. ~

~~ ~l!l 0 0 .J .J ., .. .. N

0 .. .. N

: :

~ 2

III .. (T[NSION POSITIVE) (TENSION POSITIVE)

.. 0 0 to 20 0 25 50 ~ CHANGE IN STRAIN (UletlO INiIN) CHANGE IN STRAIN (MICRO IN IN)

Page 144: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 145: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN D I X E

STRAIN GRADIENT DIAGRAMS

Page 146: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

130

~ LOAD - 25 KIPS LOAD - 25 KIPS

~ pt GAGE LINE 1 GAGE LINE 1 pt EXTERIOR GIRDER 'i' INTERIOR GIRDER - e

'"' .. '"' :: .. ... ... .. ::

8 .. ... ~ ::; ... .. ... 0

~ ~ .. '"' it ... PRE-CRACKING '"'

PRE-CRACKING 1M ... ~ I:! < POST-f ATIGUE .. .. I :: .. 0 III

::;

4 0 20 40

(MICRO IN/IN) STRAIN (MICRO IN/IN)

"'& LOAD - 25 KIPS LOAD - 25 KIPS ... GAGE LINE 2 ... GAGE LINE 2 %'

.... EXTERIOR GIRDER

... e %' ~ INTERIOR GIRDER .. - ~

'"' ~ PRE-CRACKING 1M '"' :: PRE-CRACKING ... .. ... !!l .. it

... ~~POST-rATIGUE ... ~ ~ ::; .. ~

... ~ .. i ~ ~

~

~ :\ '"' \ ... .. 1M

... \ ~ tI \ < • 'Z .. \ .. < \ ... ... :; ... :\ ..

0 \ \

0 20 40 .0 0 20 40 eo , 100 STRAIN (UICRO IN/IN) STRAIN (MICRO IN IN)

Page 147: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

131

~ LOAD • 25 KIPS

"" LOAD. 25 KIPS

'i' GAGE LINE J .. GAGE LINE .3 .. .. \ EXTERIOR GIRDER 'i' INTERIOR GIRDER - \ ., \ ::. II \

"~POST-rATIQU£ .. .. .. Id ... ..

I .. ... E \ I \ .. .. , .. f ~ , 0 ~ ..

\ J ... \

g , c ... , tJ .. • \ 1 • 1/1 \ ..

0 , .. .. , .. , .. ..

0 20 .0 to ., 100 0 20 '0 eo eo lOa UO 140 STRAIN (MICRO IN IN) STRAIN (MICRO IN/IN)

~~ LOAD • 25 KIPS

~ .. LOAD. 25 KIPS GAGE LINE 4 GAGE LINE 4 EXTERIOR GIRDER

..... INTERIOR GIRDER

'£ Z " .. .. " .... .... " • II • .. ~" PR£-CRACKINO .. ... .. .. II ~ .. ..

~ ... ... ! I .. Ii ~

.. ~ z ! ! c ... ... i • i • .. .. 1/1 1/1 .. .. 0 ..

o 20 40 10 10 '~ 120 0 20 40 .0 eo 100 '7 140 STRAIN (MICRO IN IN) STRAIN (MICRO IN IN)

Page 148: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

132

~" LOAD - 25 KIPS LOAD - 25 KIPS GAGE LINE 5 GAGE LINE 5 " .. EXTERIOR GIRDER INTERIOR GIRDER

~ " .. " ... :\

" .. .. .. :: .. .. .. 11\ .. .. ... ... B B .. ..

~ i ~ ~ ~ -.: ..

" B " B " /1\ POST-F ATIGUEJ" .. "

... ... " i i • " • " ... PRE-<:RACKING

" .. .. .. .. " ~ Q .. " .,....,....,.-- -r-r--

20 40 80 aJ 100 -20 0 20 40 80 ao lao 120 140/ 180 STRAIN (MICRO IN IN) STRAIN (MICRO IN IN)

~ ... J LOAD - 25 KIPS LOAD - 25 KIPS GAGE LINE 6 GAGE LINE 6

"' EXTERIOR GIRDER 'i INTERIOR GIRDER 'i :\ ::. .:: " " .. /1\ " .. .. .. ~~POST-FATIGUE .. PRE-CRACKING .. .. .. .. .. .. .. ... " ! ! " ..

" t to

" i e .. ~

" I I " " ... " ... " i ~ • , • " .. .. :! ... " .. PAE-<:AACKING

, Q POST -F A TI GUE .. .. , , 0 20 40 80 10 'YO 110 0 20 40 ao ao 100 '~ .. 0 STRAIN (MICRO IN IN) STRAIN (MICRO IN IN)

Page 149: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

133

".! LOAD - 25 KIPS LOAD - 25 KIPS GAGE LINE 7 ,.; GAGE LINE 7 ... EXTERIOR GIRDER

.. INTERIOR GIRDER

'i 'i " ... !: " ... " '"

~ '" ~

... .. ~~POST-fATlGUE .. ..

• " • .. .. .. .... ... ! '\ ! .. '\ .. S ~

'\ S ~ • '\ • ! '\ ! '" '\ '" ... '\ ...

i '\ .. • '\ ~ • .. '\ .. .. '\

.. ... PRE-<:RACKINO

... PRE-CRACKING ~ Q '\ Q

~ '\ ~

0 20 40 10 AO 100 0 20 4Q 10 80 100 120' 140

STRAIN (MICRO IN IN) STRAIN (MICRO INiIN)

Page 150: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

134

LOAD - 2S KIPS

" LOAD - 2S KIPS

Z GAGE LINE 9 Z ::: GAGE LINE 9 .. EXTERIOR GIRDER e INTERIOR GIRDER ....

• • .. III • .. .. ... ...

i i ~ ... .. ~ i I; • ~ a i t ~

'"' PRE-CRACKING • ~ PRE-CRACKING ... ... ~

~ ; ~rPOST-FATICUE

.. c ... .. Iii .. .. ... ..

~ Q

G

~ ~

0< 20 0 20. 40 STRAIN (MICRO IN/IN)

STRAIN (MICRO IN/IN)

Page 151: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

A P PEN D I X F

CALCULATIONS FOR DETERMINING GIRDER DESIGN MOMENTS

BY THE ONTARIO BRIDGE CODE

Page 152: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

136

CALCULATIONS FOR INTERIOR GIRDER OF HIGHWAY BRIDGE MODEL

The design procedure for calculating the moments in the

interior girder of the laboratory specimen according to the Ontario

Highway Bridge Design Code [2] are shown below. The notation used is

listed at the end of this appendix, and is taken directly from Ref. 2.

The first step in the Ontario procedure is to calculate the

parameter Dx for the interior girder:

D is

Dx = EI I beam spacing

Ox = (E • (25,000 in.4) • <3 beams) • (2.54 cm/in.)4) 1213.4 cm

Dx = 14,630 • E cm4

then calculated as:

Dy = (E x (slab thickness) 3) I 12

Dy = (E (19.05 cm)3) I 12

Dy = 576 . E

Neglecting the contribution of the steel beam to the torsional moment

of inertia:

Dxy = Dyx = (G (slab thic kness) 3) I 6

DXY = (E x (1 9. 05 ) 3 ) I (2 . ( 1 + 0.15) • 6)

Dxy = 501 . E

D1 = °2 = V x (lesser of Dx and Dy)

D1 = 0.15 (576 . E)

D1 = 86 • E

Page 153: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

137

The parameter s a. and ~ are then calcul ated as:

a. = «501 + 501 + 86 + 86) • E) I (2«14,630 • E) • (516E»O.5)

a. = 0.202

~ = b/L (D 10 )0.25 x y

~ = 305cm/1524cm «14,530 • E)/(516 • E)O.25

~ = 0.449

Witha = 0.202 and g. = 0.449, the values of 0 and Ct can be read from

Fig. 3.1.1.2.2(b) of Ref. 2 (Fig. F.1):

o = 2.35

The width of a design lane is calculated as:

vie = vlclo

\~e = 6.10m/2

We = 3.05m

The value of IJ. is calculated as:

IJ. = (We - 3.3)/0.6 ~ 1.0

IJ. = (3.05 - 3.3)/0.6

IJ. = -0.411

The Ontario load distribution factor, which is analogous to the value

5.5 from the AASHTO Specifications, is calculated as:

Page 154: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

138

3-7.1.2.2(b)

8

Din metres

C,. percent

2.5

2.25

---;. 17~ i I ! ! II I ' I!! II! ...r I ! I V: I . I.! I I i ! ~ :/ 11: '/

'I/i , I . , 'j

2.0 "'-'1.BO __ I" i : i / , I I

1.75 , . y I

/1 'i :/

1.5

1.25

1.0

0.75

0.50

0.25

I / /.' {., i / i ; /,,'0/

./1 I I Z~x= ,/ ,

I V,' I:l' , / I ./. V ..r:tt

,\~y I /f V "v t?.r .-- ; : / ./ y: i /').."() --- ! ./ /" )( ;y 'f)«)~ , . '/ '/ 1/ /'~0C) . . ./ /' / YV..L ........ ~J.C)

" ~/? ____ .......-1~~.~AO ~.~~~~:-60

0.125 0.001 0.01 0.05 0,1

ex

3.7

0.5 1.0 1 .5 2.0

2.5 :-:::::' ...,O".....O.".. ..... ·Q: lir !::::r:=:+iX:I' III ::::::::rJI:r::r::::;.:~ .- -,- :.1' 1

2.25 1--~---r"-4.,-L--"'--:'~--4--...,.-+--'~~I--c-l ,

0.01 0.05 0.1 ex

0.5 1.01.52.0

Fig. F.l Charts for C and D (Fig. 3-7.1.2.2(b) Ref. [2])

Page 155: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

Dd :: D (1 + (I-L Ct /100»

Dd :: 2.35 (1 - (0.417 (9)/100»

Dd :: 2.26 m

Dd :: 7.41 ft (3.280 ft :: 1 in.)

139

According to the Ontario Code, the design moment for the center girder

1s then:

Design moment:: P (15 ft) (SIC)

:: 25 k (15 ft) <7.017.41) 12

:: 4230 In.-k

Page 156: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

140

The following notation is used in the calculation of girder

design moments by the Ontario Bridge Code:

C1 a correction factor used to adjust the D value for longitudinal moment and longitudinal shear

D the load distribution factor

Dd the load distribution factor modified for design

D, the coupling rigidity per unit width

D2 the coupling rigidity per unit length

Dx the longitudinal flexural rigidity per unit width

Dxy the longitudinal torsional rigidity per unit width

Dy the transverse flexural rigidity per unit length

Dyx the transverse torsional rigidity per unit length

E the modulus of elasticity

G the shear modulus

L the span of a bridge

Wc the bridge deck width, m

We the width of a design lane, m

b the half-width of a bridge

a. torsional parameter

Q a flexural parameter

= (Dxy + Dyx + D1 + D2)/2([DxDy]O.5

= (b/L) [D ID ]0.25 x y

~ (We - 3.3)/0.6 > 1.0

v Poisson's ratio

Page 157: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

REF ERE N C E S

1. Standard Specification for Highw~ Bridges, Thirteenth Edition, American Association of State Highway and Transportation Officials, Washington, D.C., 1984.

2. Ontario Highway Bridge Design Code and Commentary, Second Edition, Ontario Ministry of Transportation and Communication, Ontario, Canada, 1983.

3. Burns, N.H., and Klingner, R.E., "Research Study Proposal, Project 3-5-83-350 to Texas Department of Highways and Public Transportation from Center for Transportation Research, The University of Texas at Austin," 1982, pp. 1-14.

4. Chu, Kuang-Han, and Kr ishn amoorthy, C., "Bridge An al ysi s Using Orthotropic Plate Theory," Journal of the Structural Division, ASCE, February 1968.

5. Cusens, A.R., and Pama, R.P., "Distribution of Concentrated Loads on Orthotropic Bridge Decks," The Structural Engineer, September 1969.

6. Heins, C.P., and Looney, C.T.C., "Bridge Analysis Using Orthotropic Plate Theory," Journal of the Structural Division, ASCE, February 1968.

7. Hendry, A.W., and Jaeger, L.B., "The Analysis of Interconnected Bridge Girders by the Distribution of Harmonics," Structural Engineer, Vol. 34, No.7, 1956, pp. 241-266.

8. Jaeger, L.G., and Bakht, B., "The Grillage Analogy in Bridge Analysis," Canadian Journal of Civil Engineering, Vol, 9, No.3, 1982.

9. Sawko, F., and Mosley, W.H., "Grillage Analysis of Composite Box Girder Bridge Decks," Civil Engineering (London), Vol. 64, No. 759, October 1969.

10. West, R., "The Use of Grillage Analogy for the Analysis of Slab and Pseudo-Slab Bridge Decks," Research Report 21, Cement and Concrete Association, London, England, 1973.

11. Hambly, E.C., and Pannels, E., "Grillage Analysis Applied to Cellular Bridge Decks," The Structural Engineer, July 1975.

141

Page 158: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

142

12. Zienkiewicz, O.C., and Cheung, Y.K., "The Finite Element Method for Analysis of Elastic Isotropic and Orthotropic Slabs," Proc. Instn. Civil Engr., August 1964.

13. Moore, T.A., and Can, A.G., "Finite Element Analysis of Box and Plate Girder Bridges," Proc. of the International Conference of Finite Element Methods in Engineering, December 6-8, 1976.

14. Davies, J.D., Somerville, LJ., and Zienkiewicz, O.C., "Analysis of Various Types of Bridges by the Finite Element Method ," Proc. Conference on Developments in Bridge Design and Construction, Cardiff, March-April 1971, Crossby Lockwood, London.

15. Cheung, M.S., and Cheung, Y.K., "Analysis of Curved Box Girder Bridges by Finite Strip t1ethod," IABSE Publications, Vol. 31-1, Zurich, June 1971.

16. Loo, Y.C., and Cusens, A.R., "Development of the Finite Strip Hethod in the Analysis of Bridge Decks," Proc. Conference on Developments in Bridge Design and Construction, Cardiff, 1971, Crossby Lockwood, London.

17. Cheung, M.S., Cheung, Y.K., and Ghali, A., "Analysis of Slab and Girder B!'"idges by the Finite Strip Method," Building Science, 5, p. 95, 1970.

18. Scordelis, A.C., "A Matric Formulation of the Folded Plate Equations," Journal of the Structural Division, ASCE, ST-l0, October 1960.

19. Scordelis, A.C., "Analysis of Continuous Box Girder Bridges," University of California, Berkeley, Structural Engineering and Structural Mechanics, No. SESM 6.7-5, November 1967.

20. EVuns, H.R., and Rockley, K.C., "A Folded Plate Approach to the Analysis of Box Girders," Proc. Conference on Developments in Bridge Design and Construction, Cardi ff, 1971, Crossby Lockwood, London.

21. Timoshenko, S., and Hoinowsky-Kreiger, S., Theory of Plates and Shells (Engineering Society Monographs), 2nd Edition, McGraw-Hill, New York, 1959.

22. Guyon, Y., "Calcul des ponts larges a poritres multiples solidarisees par des entretoises," Annales des Ponts et Chaussees, No. 24, Septerllber-October 1946.

Page 159: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

143

23. Guyon, Y., "Calcul des ponts dalls," Annales des Ponts et Chaussees, Vol. 119, No. 29, 1949.

24. Massonnet, C., "Methode de calcul des ponts a poutres multiples tenant compte de leur resistance a la torsion," (Methods of Calculation of Bridges with Several Longitudinal Beams, Taking into Consideration Their Torsional Resistance), Zurich, International Association for Bridge and Structural Engineering, Publications Vol. lQ, 1950.

25. Leyendecker, E.V., and Breen, J.E., "Behavior of Concrete Slab and Girder Bridges," Research Report 94-3F, Center for Transportation Research, The University of Texas at Austin, May 1969.

26. Mouce, P.B., and Little, G., "Load Distribution in Prestressed Concrete Bridge Systems," The Structural Engineer, Vol. 32, No.3, March 1954.

27. Morris, P.B., and Little, G., "Analysis of Right Bridge Decks Subjected to Abnormal Load ing," Cem ent and Concrete Assoc iat ion, London, England, July 1956.

28. Rowe, R.E., "A Load Distribution Theory for Bridge Slabs Allowing for the Effect of Poisson's Ratio," Magazine of Concrete Research, Vol. 7, No. 20, July 1955.

29. Morris, P.B., Little, G., and Rowe, R.E., "Design Curves for the Effects of Concentrated Loads on Concrete Bridge Decks," Cement and Concrete Association, London, July 1956.

30. Arendts, J.G., "Study of Experimental and Theoretical Load Distribution in Highway Bridges," unpublished M.S. Thesis, Iowa State University, 1968.

31. Zienkiewicz, D.C., The finite Element Method of Engineering Science, McGraw-Hill Publishing Company, LTD., London, 1971.

32. Motarjemi, D., and Van Horn, D.A., "Theoretical Analysis of Load Distribution in Prestressed Concrete Box-Beam Bridges," Fritz Engineering Laboratory Report No. 315.9, Lehigh University, October 1969.

33. Goldberg, J.E., and Leve, H.L., "Theory of Prismatic Folded Plate Structures," International Association of Bridge and Structural Engineers, Publication Vol. 17, 1957, pp. 59-86.

Page 160: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

144

34. Sanders, ~/.W., "Distribution of Uhee1 Loads on Highway Bridges," Report furnished for review by members of the National Cooperative Highway Research Program, Transportation Research Board, 1983.

35. Stand ard Spec i ficat ions for H i gh~~ Brid ges and I nci dental Structures, First Edition, American Association of State Highway Officials, Washington, D.C., 1931.

36. Standard Specifications for High~~ Bridges, Seventh Edition, American Association of State Highway Official s, Washington, D.C., 1957.

37. Newmark, N.M., "A Distribution Procedure for the Anal ysis of Slabs Continuous over Flexible Beams," Engineering Experiment Station Bulletin 304, University of Illinois, Urbana, 1938.

38. Texas Highway Department, "Standard Specifications for Construction of Highways, Streets, and Bridges," September 1, 1982.

39. Texas State Department of Highways and Public Transportation, Bridge Division, Drawing File 1284, Research Project 3-5-83-350, Apr i1 1 4, 1 982 •

40. Operating Manual, Dennison 800 Series Variable Volume Pump, Model No. PV08-035-51R, 02-X381, Abex Corp., 1160 Dudlin Rd., Columbus, Ohio 43216.

41. Operating Manual, Sundstrand 1200RPM, Pressure COr.lpensated Variable Volume Pump, Model No. S/SPV22-7012, Sundstrand Company, Ames, Iowa.

42. Precision Heasurement Company, P.O. Box 7676, Ann Arbor, Michigan.

43. Newmark, N.M., et a1., "Tests and Analysis of a Composite I-Beam," Proceedings of the Society for Experimental Stress Analysis, Vol. IX, No.1, 1951, pp. 75-92.

44. Building Code Requirements for Reinforced Concrete, ACI Standard 318-83, American Concrete Institute, Detroit, Michigan, 1984.

45. Hognestad, E., "A Study of Combined Bending and Axial Load in Reinforced Concrete Members," University of Illinois Bulletin No. 399, 1951.

46. Fang, I-Kuang, "The Verification of Ontario Highway Bridge Deck Design on Steel Girders (With and Without Precast Panels)," Ph.D. Dissertation (in progress), The University of Texas at Austin, January 1985.

Page 161: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

145

47. Bathe, K.J., \H1son, E.L., and Peterson, F.E., "SAPVI: A Structural Analysis Program for Static and Dynamic Response of Linear Systems," Report No. EERC 73-11, Earthquake Engineering Research Center, University of California at Berkeley, 1973.

48. Finite Element Analysis of Reinforced Concrete, American Society of Civil Engineers, New York, 1982.

Page 162: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E
Page 163: Form DOT F 1700 - CTR Librarylibrary.ctr.utexas.edu/digitized/TexasArchive/phase2/350-2-CTR.pdf · DISTRIBUTION OF GIRDER LOADS IN A COMPOSITE HIGHWAY BRIDGE by C. W. Elling, R. E

NOT A T ION

C = specified constant for various bridge types

D.F. = distribution factor

Ec = secant modulus of elasticity of concrete at O.5f6

ES = modulus of elasticity of steel (29,000 ksi)

EI = calculated flexural stiffness of girder

ET = initial tangent modulus of elasticity of concrete

fc = compressive stress in concrete

Q = 28-day compressive strength of 6-in. by 12-in. concrete cylinders

S = average girder spacing (ft)

h = uniform distance between points on the girder

IS = calculated moment of inertia of composite girder section,

L

M(x)

p

W(x)

y

€ c

transformed to steel

= span length

= moment at the ith point on the girder

= moment at distance x along girder

= concentrated load

= unit weight of concrete (pcf)

= load at the ith point on the girder

= load at distance x along girder

= slip between deck and steel beam

= longitudinal strain in the beam

= strain in concrete

= compressive strain in concrete corresponding to maximum stress

= longitudinal strain in the slab

147