25
1 FORM 1 I Basic Information S. No. Item Details 1. Name of the Project Lampiya Iron Ore, Copper and Associated Minerals Mine and preliminary processing plant (ML No.627/05) 2. S. No. in the schedule As per the Gazette Notification dated 14 th September, 2006 and subsequent amendment dated 01.12.09, the project is classified as Category “A” under S. No. 1 (a) (> 50 hectare of mining lease area) Mining of Minerals. 3. Proposed capacity/ area/ length/ tonnage to be handled /command area/lease area /number of wells to be drilled On submission of application, the mining lease area was demarcated by the Directorate of Mining & Geology, Govt. of Rajasthan, measuring 451 Hectares. Accordingly EC was granted for 451.00 ha area, Later on the Govt. noted that 17.8967 ha of the above demarcated area was overlapping the area of earlier applicant, therefore only 433.1033 ha was sanctioned and lease deed was executed for 433.1033 ha area. 30 lac tons/annum of ROM will be mined from Lampiya by open cast method after 13 th year. From 1 st year to 5 th year, ROM production will be from 6.0 to 15.00 lac tons per year. 4. New / Expansion / Modernization New mine 5. Existing capacity/ Area etc. It is a new mine having production capacity of 6.0 to 15.00 lac tons per year during first five year and then up to 30 lac tons per year after 13 th year. The lease has an area of 433.1033 hectares consisting of 127.7033 hectare agriculture land, 213.24 hectares of grazing land and 92.16 hectare of waste/ barren land. 6. Category of project i.e. 'A' or 'B' Category “A” 7. Does it attract the general condition? If yes, please specify. No

Form 1 lampiya - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/modification/previousTOR/... · E-mail [email protected] Telephone no. 014 82 -248417

  • Upload
    lamhanh

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

1

FORM 1

I Basic Information

S. No. Item Details

1. Name of the Project Lampiya Iron Ore, Copper and Associated Minerals Mine and

preliminary processing plant (ML No.627/05)

2. S. No. in the schedule As per the Gazette Notification dated 14th September, 2006

and subsequent amendment dated 01.12.09, the project is

classified as Category “A” under S. No. 1 (a) (>50 hectare of

mining lease area) Mining of Minerals.

3. Proposed capacity/ area/

length/ tonnage to be handled

/command area/lease area

/number of wells to be drilled

On submission of application, the mining lease area was

demarcated by the Directorate of Mining & Geology, Govt. of

Rajasthan, measuring 451 Hectares. Accordingly EC was

granted for 451.00 ha area, Later on the Govt. noted that

17.8967 ha of the above demarcated area was overlapping the

area of earlier applicant, therefore only 433.1033 ha was

sanctioned and lease deed was executed for 433.1033 ha area.

30 lac tons/annum of ROM will be mined from Lampiya by

open cast method after 13th year. From 1st year to 5th year,

ROM production will be from 6.0 to 15.00 lac tons per year.

4. New / Expansion /

Modernization

New mine

5. Existing capacity/ Area etc. It is a new mine having production capacity of 6.0 to 15.00 lac

tons per year during first five year and then up to 30 lac tons

per year after 13th year.

The lease has an area of 433.1033 hectares consisting of

127.7033 hectare agriculture land, 213.24 hectares of grazing

land and 92.16 hectare of waste/ barren land.

6. Category of project i.e. 'A' or

'B'

Category “A”

7. Does it attract the general

condition? If yes, please

specify.

No

2

8. Does it attract the specific

condition? If yes, please

specify.

No

9. Location Location of Lease Area-

Pillar Name Latitude (N) Longitude (E)

Y 25° 27' 33.09" 74° 39' 28.49"

A' 25° 27' 04.43" 74° 40' 22 "

B' 25° 26' 34.47" 74° 39' 27.39"

C 25° 26' 53.96" 74° 39' 05.82"

D’ 25° 26' 22.49" 74° 38' 31.34"

E 25° 26' 22.42" 74° 38' 04.27"

F 25° 26' 26.21" 74° 38' 07"

G 25° 26' 22.04" 74° 37' 55.9"

H 25° 26' 22.38" 74° 37' 46.11"

I 25° 26' 15.88" 74° 37' 46.13”

J 25 26 22.71 74 37 38.56

K 25 27 43.38 74 39 06.94

L 25 27 28.48 74 39 23.44

Y 25° 27' 33.09" 74° 39' 28.49"

Plot/ Survey/ Khasra no. The project occupies an area of 433 1033 hectares, covering

477 Khasra’s. Details of khasra’s of revenue villages are

enclosed as Annexure-I.

Village Lampiya, Devpura, Jaliyan, Chamanpura, Kamalpura and

Mahuwa Khurd.

Tehsil Banera

District Bhilwara

State Rajasthan

10. Nearest Railway station/

Airport along with distance in

kms.

Railway Station Mandal– 3.5 km towards West on Ajmer-

Chittorgarh Broad Guage Line of North Western Railway.

Airport Dabok (Udaipur) - 150 km towards SW.

11. Nearest Town, City, District

Headquarters along with

distance in kms.

Distt. Head Quarter- Bhilwara – 11 kms towards South.

12. Village Panchayat, Zilla

Parishad, Municipal

Corporation, Local body

Nagar Parishad - Bhilwara,

Near Rajendra School, P.O. – Bhilwara,

Telephone No. - 01482-232651, 52

3

(Complete postal address

with telephone no. to be

given)

13. Name of the applicant Jindal Saw Limited

14. Registered address Jindal Saw Ltd.,

A-1, UPSIDC Industrial Area, Nand Gaon Road, Kosi Kalan, Pin-

281 403, Distt. - Mathura, Uttar Pradesh.

15. Address for correspondence

Name Rajender Gaur

Designation (Owner /

Partner / CEO)

Head – Liaison

Address Araji No. 9607’6711, near Tiranga Hills, Vill. Pur, PO-Bhilwara.

Pin Code 3311802

E-mail [email protected]

Telephone no. 01482-248417

Fax No. 01482-248417

16. Details of alternative sites

examined, if any. Location of

these sites should be shown

on a Toposheet.

The project is site specific as the ore deposit occurs at this

location and therefore examination of alternate site is not

required. Considering the above aspect, mining lease has been

sanctioned for this site.

17. Interlinked projects This project is linked with Company’s Dhedwas Iron Ore,

Copper and Associated Minerals Mine; where beneficiation

plant has been established to produce Iron ore concentrate

from the ROM. The STP to treat Bhilwara waste water is also

linked with Dhedwas iron ore mine. For this mine 40 KLD water

will be obtained from STP near village Kewara in Bhilwara. The

RSPCB has issued consent to establish the STP and is attached

at Annexure –II. The EC for Dhedwas Mine (the linked project)

is annexed at Annexure –III.

18. Whether separate

application of interlinked

project has been submitted?

Yes, it was submitted. Mining Lease has been granted and the

mine is in operation.

19. If yes, date of submission 23.11.2009 (File No. J-11015/ 1209/ 2007-IA.II (M))

Final presentation of the project was done on 24.05.2010.

EC has been granted on 09.08.2010. Enclosed as Annexure-III.

4

20. If no, reason Not Applicable

21. Whether the proposal

involves approval/

Clearance under: if yes,

details of the same and their

status to be given.

(a) The Forest

(Conservation) Act,

(1980)?

(b) The Wildlife

(Protection) Act, 1972?

(c) The C.R.Z. Notification,

1991?

Not Applicable

22. Whether there is any

Government Order/Policy

relevant/relating to the site:

No.

23. Forest land involved

(hectares)

Nil

24. Whether there is any

litigation pending against

the project and/or land in

which the project is

proposed to be set up?

(a) Name of the Court

(b) Case No.

Orders/directions of the

court, if any and its

relevance with the proposed

project.

No litigation is pending in any court.

*Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease

area and production capacity for mineral production, area for mineral exploration, length for linear

transport infrastructure, generation capacity for power generation etc.,)

II Activity

1. Construction, operation or decommissioning of the Project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies,

5

etc.)

S. No. Information/Checklist

confirmation

Yes

/No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

1.1

Permanent or temporary change

on land use, land cover or

topography including increase

in intensity of land use (with

respect to local land use plan)

Yes There will be change in the land use and land cover of

the lease area. The lease area of 433.1033 hect, will be

subjected to some permanent changes. The area

currently is undulating hilly terrain with hummocky

ground on either side of the hill slopes. The land use at

the end of various phases of mine is proposed as

under. The figures are in Hectares.

S.

No.

Particulars Present

land use

At the end of

5th year

At the end of life of

mine

At the closure of

Mine

1. Pits

10.5 22.5 37.85 Reclaimed & grazing/

Planted.

2. Overburden Dumps

4.0

40.00 45.00 Reclaimed & Planted

3. Roads 6.77 8.26 8.26 Road - 6.00 ha,

Plantation 2.26

4. Villages and Buildings 2.40 2.40 2.40 2.40

5. Mineral beneficiation,

Ore stacking, office,

workshop and buildings

-- 4.00 4.00 Reclaimed & Planted

6. Plantation -- 5.00 10.00 99.11

7. Others: Tank, Canal,

Dam, Future use,

exploration, agriculture,

etc.

409.4333 350.9433 325.5933 333.9933

Total 433.1033 433.1033 433.1033 433.1033

Eventually, at the closure of mine the excavated pit areas (37.85 hectare) will be backfilled and reclaimed

for grazing and plantation. Dumping yard area (45.00 hectare), Mineral stacking & Office and workshop

and building (4.00 hectare) will be rehabilitated by reclamation by native plantation. Road (6.00 ha) and

villages and buildings (2.40 ha) will be used as a public use. Thus, the change in the topography of the area

will be localized and confined within the lease area.

Topography: - The lease area comprises of hilly tract in a rather flat terrain. This belt comprises of one

NE-SW trending hillock from village Chhatrikheda on south-west to village Lampiya in north-east

covering a length of 3.65 km and width of 0.352 to 1.8 km. Status of changes in topography are given

below:-

6

Pit Hill top level General

ground level

R.L. of lowest point of

working in five years

R.L. of final depth

at conceptual stage

Lampiya South 504 m AMSL 420 m AMSL 420 m AMSL 340 m AMSL

Lampiya North 473 m AMSL 430 m AMSL - 340 m AMSL

1.2 Clearance of existing land, vegetation

and buildings?

Yes The mineralized ore bodies are exposed on the

hill tops and the working areas are devoid of any

significant vegetation cover and have no

buildings. Top soil cover varies from a few cm to

20 cms.

1.3 Creation of new land uses? Yes There will be change in the existing land use.

The new land use at the end of 5th year and at

the end of life of mine is mentioned in section

1.1, page 5 of the Form-1. Types of land to be

used for above purpose are given below. (All the

figures are in Hectares)

S.

No.

Type of

land

Area

(Ha.)

Present land use At the end of 5th year Conceptual land use At the

closure of

mine

Un-

disturbed

Disturbe

d

Un-

disturbed

Disturbe

d

Un-

disturbed

Disturbe

d

1. Khatedar

i

127.703

3

127.7033 -- 127.7033 -- 127.7033 -- 127.7033

2. Govt.

waste

land

78.35 73.43 4.92 9.44 68.91 0.41 77.94 0.41

Un-

disturbed

2.40 village

6.00 road

69.54 R &

P

3. Grazing

land

(Govt.)

213.24 194.49 18.75 189.49 23.75 183.67 29.57 29.75 R & P

183.67

undisturbe

d

4. Surface

water

body

13.81 13.81 -- 13.81 -- 13.81 -- 13.81

Total 433.103

3

409.4333 23.67 340.4433 92.66 326.4133 106.69 433.1033

R = Reclaimed

P = Plantation

1.4 Pre-construction investigations e.g.

bore holes, soil testing?

No There will be no change in the area due to bore

holes and soil investigation. The bore holes have

been drilled by GSI during exploration of the area

in the year 1969-70 to 1976-77 and by the

7

Company in 2012-14.

The office building and workshop will have

foundation on hard bed-rocks, their bearing

capacity and geo-technical parameters will be

determined at the time of construction.

1.5 Construction works? Yes There will not be any significant construction at

the site except an office building complex and a

preliminary mineral beneficiation unit, which

will have total built up area of about 4.00

hectare.

1.6 Demolition works? No It is not envisaged.

1.7 Temporary sites used for

construction works or housing of

construction workers?

No No temporary sites will be created during

construction for workers. Modular house, septic

tanks and soak pit will be provided for housing of

construction labour, during construction period.

1.8 Above ground buildings, structures

or earthworks including linear

structures, cut and fill or

excavations

Yes The extensive mining activity will involve various

physical changes. Significant changes will be in

land use. At the end of the life of mine, the total

excavated area of 37.85 ha will be backfilled and

reclaimed by plantation. The area of waste

dumps of 45 ha will be rehabilitated by removing

the dumps for back filling pits and reclaimed by

plantation.

1.9 Underground works including

mining or tunneling?

No Mining will be done by open cast method.

1.10 Reclamation works? Yes At the end of life of mine, the total excavated area

of 37.85 ha will be backfilled and reclaimed by

native plantation. The area used for waste dumps

45.00 ha will be reclaimed by removing the

dumps for backfilling and then by native

plantation. The area of 4.00 ha, used for mineral

stacking & office, workshop and buildings will be

reclaimed by demolition and plantation and

8

planted area will be handed over to Govt.

1.11 Dredging? No It is not envisaged.

1.12 Offshore structures? No None.

1.13 Production and manufacturing

processes?

Yes During first 5 years, production of ROM Ore of

this mine will vary from 6.0 to 15.0 lac tons and

generation of about 7.2 to 60.0 lac tons of

overburden/ waste rock per year. Ultimate

production of ROM will be about 30 lac tons per

year after 13th year. Mining will be done by

mechanized opencast mining method.

The ROM ore produced from this mine will be

crushed and ground to (-) 6 mm size and

subjected to primary magnetic separation in dry

state where the major part of non-magnetic

material will be separated from the magnetic

ores. Here 50 to 55 % of non-magnetic gangues

will liberate, pass on as coarse tailing and will be

dumped as dry tailing in the lease area.

The (-) 6 mm size magnetic ores separated by the

Primary Magnetic Separator will be beneficiated

in the beneficiation plant located in the mining

lease area of Dhedwas mine of the Company

located at a distance of about 24 km from this

mine.

1.14 Facilities for storage of goods or

materials?

Yes Goods and materials will be stored in the stock

yard near the crusher plant over an area of 0.5

ha.

1.15 Facilities for treatment or disposal

of solid waste or liquid effluents?

Yes Solid Waste:-

The activity will temporarily involve the

generation of dumps to occupy an area of 40.00

hectare in five years and about 45.00 hectare at

the end of life of mine. The total (overburden)

generated over the life of mine will be 49.394

9

million m3 from mining.

Liquid Effluent:-

There will be around 400 persons deployed in

the mine and rest rooms will be provided with

toilet facility. The sewage to the tune of 21 KLD

will be generated, which will be channelized into

a common Sewage Treatment plant to be

installed at the mine.

1.16 Facilities for long term housing of

operational workers?

Yes There will be no long term housing provided

within the lease area. The housing for

operational workers will be outside the lease

area in Bhilwara town or nearby villages. Most of

the workers will be from nearby villages.

1.17 New road, rail or sea traffic during

construction or operation?

Yes There will be about 7-10 trucks per hour

additional on the road. The existing road

network will be strengthened by the State Govt.

and the funding will be done by the Company.

Within the lease area the roads will be developed

by the Company. The existing roads passing

through the lease area cover 5.14 hectare land

with cumulative length of 4.8 km. For mining

purpose about 4.0 km of road will be constructed

to connect the existing roads within the mining

sites. The roads will be 15 m wide covering 5.86

hectare area.

1.18 New road, rail, air waterborne or

other transport infrastructure

including new or altered routes

and stations, ports, airports etc?

No There will be no new road, rail, air, waterborne

or other transport infrastructure including new

or altered routes and stations, ports, airports etc.

for the project; except that the existing road

network will be strengthened by the State Govt.

and the funding will be done by the Company.

This will facilitate the surrounding villagers and

the impact on physical environment on long term

10

basis will be positive.

1.19 Closure or diversion of existing

transport routes or infrastructure

leading to changes in traffic

movements?

No There will be no change in the existing transport

routes.

1.20 New or diverted transmission lines

or pipelines?

Yes The power will be drawn from the nearest GSS

grid of R.S.E.B Bhilwara. An 11 KV line will be

provided to meet the power demand of 2.00 MW.

The nearest GSS grid is at Bhairukhera near

Danta which is at 7km.

12 km long pipe line will be laid from Kewara

STP to the Mine for getting treated water.

1.21 Impoundment, damming,

culverting, realignment or other

changes to the hydrology of

watercourses or aquifers?

No It is an existing project and the same is not

envisaged.

1.22 Stream crossings? No No stream crossing is envisaged.

1.23 Abstraction or transfers of water

from ground or surface waters?

Yes 10 KLD of ground water will be abstracted for

domestic consumption. Ground water that will

seep into the open cast pit from 7th year onward

will amount to 26.47 KLD during 7th year to

204.25 KLD during 20th year (at conceptual

stage).

1.24 Changes in water bodies or the

land surface affecting drainage or

run-off?

No There will be no change in water bodies. The

change in the land surface due to mining will not

affect the surface drainage or run off.

1.25 Transport of personnel or

materials for construction,

operation or decommissioning?

Yes There will be transport of personnel and material

at the site during the erection and

commissioning of the project. About 100

personnel’s will be involved in the construction

phase of the preliminary processing unit. Pooling

of vehicles is proposed to avoid excess load on

the road.

11

1.26 Long-term dismantling or

decommissioning or restoration

works?

No Not applicable.

1.27 Ongoing activity during

decommissioning which could

have an impact on the

environment?

No Not applicable.

1.28 Influx of people to an area in either

temporarily or permanently?

Yes During pre-commissioning and post

commissioning activities, influx of manpower

will be there, which is estimated to be as under:

Temporary - Pre commissioning - 100 Persons

Permanent - Post commissioning - 398 Persons

Since 70% to 80% of the people will be from

surrounding villages, the influx will have

negligible effect.

1.29 Introduction of alien species? No None.

1.30 Loss of native species or genetic

diversity?

No There will be no loss of native species and there

will be no genetic diversity as the local species

will be chosen for plantation.

1.31 Any other actions? No Nil

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short

supply):

Information/checklist

confirmation

Yes/No Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

2.1 Land especially undeveloped or

agricultural land (ha)

Yes The mining lease area of 433.1033 hectare

consists of 127.7033 hectare agricultural land,

213.24 hectare Grazing land and 92.16 hectare of

government barren/ waste land. Mining and

allied activities will be confined to waste land .

12

2.2 Water (expected source &

competing users) unit: KLD

Yes Daily water demand will be 70 KLD for drinking,

domestic, plantation and dust suppression on

haul road and mining area. The 40 KLD of water

demand will be met from the treated water of

Kewara STP of the Company by laying a pipe line

of 12 Km length, 10 KLD will be abstracted from

ground water for domestic use and 20 KLD

requirements for plantations and dust

suppression will be met from recycling of treated

domestic waste water at the mine.

2.3 Minerals (MT) Yes It is a mining project for excavation of iron-ore

ROM upto the tune of 3800 tons and about 8200

tons of overburden per day in the initial stage.

This will increase to 10,000 tons ROM and

40,500 tons OB/day after 13th years,

respectively.

2.4 Construction material – stone,

aggregates, sand / soil (expected

source – MT)

Yes The basic materials to be used are cement, bricks,

stones, steel, hollow pre-cast concrete blocks,

composite Ferro-cement, bricks, stones, ready

mix concrete, sand, gypsum, ply wood, hard

wood aluminum, glass etc.

All the items to be used in the proposed project

will be as per the National Building Code – 2005.

2.5 Forests and timber (source – MT) Yes The use of timber will be minimized. It will be

obtained from the authorized local timber

merchants, if required.

2.6 Energy including electricity and

fuels (source, competing users)

Unit: fuel (MT), energy (MW)

Yes Energy:-

The power will be drawn from the nearest GSS

grid of R.S.E.B, Bhilwara. An 11 KV line will be

laid to meet the power demand of 2.00 MW.

Fuel Diesel :-

- Shovels, Dumpers/ Trucks, Drills, Road Roller,

Dozer, Grader etc. (About 25,000 litres per day).

13

- D.G. set(s) having total capacity of 1000 KVA

for back–up power.will be provided.

Requirement of fuel will be 500 liters/day.

2.7 Any other natural resources (use

appropriate standard units)

No Not applicable.

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived

risks to human health.

S.

No.

Information/Checklist

confirmation

Yes/No Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

3.1 Use of substances or materials,

which are hazardous (as per

MSIHC rules) to human health or

the environment (flora, fauna, and

water supplies)

No About 25,500 litres per day of diesel fuel will be

used.

3.2 Changes in occurrence of disease

or affect disease vectors (e.g. insect

or water borne diseases)

No It is not envisaged.

3.3 Affect the welfare of people e.g. by

changing living conditions?

No The project will have following positive effect on

the people: -

1. The socio-economic conditions of the

surrounding villages are poor as there is no

significant source of earning. The

occupational activities are agriculture, cattle

rearing and employment in textile

industries and near by masonry stone

mines. The project will provide employment

(round the year) to some 300 local people

which will improve the economical status of

the area.

2. The transportation of minerals will be

carried out from this mine to Dhedwas

Beneficiation Plant using 180 to 190 trips

14

per day, thus creating employment

opportunity for truck drivers and cleaners.

3. Free medical camps will be organized for

villagers regularly.

4. The company will cooperate with the govt.

for the development of area in opening of

schools and providing basic

facilities/amenities.

5. A number of schools, private as well as Govt.

will come up in the core as well as buffer

zone.

6. The project will provide revenue to the State

and the Central Govt. by way of royalty and

taxes.

7. Market, Carpentry, black-smithy and vehicle

repair shops will come up in the locality

giving employment to a large number of

persons.

8. Local students will be given scholarships for

pursuing higher studies.

9. Annual sports will be arranged on

Panchayat levels to promote sportsmanship.

10. Donation will be given for local festivals.

11. Fodder will be supplied to villagers in the

core zone. CREP guidelines will be followed.

3.4 Vulnerable groups of people who

could be affected by the project e.g.

hospital patients, children, the

elderly etc.,

No There is no vulnerable group of people who

could be affected by the project.

3.5 Any other causes No Nothing significant.

4. Production of solid wastes during construction or operation or decommissioning

(MT/month)

S. No. Information/Checklist Yes/ Details thereof (with approximate

15

confirmation No quantities/rates, wherever possible) with

source of information data

4.1 Spoil, overburden or mine wastes Yes The O.B. generated will be to the tune of 0.20

million tons per month. The dry tailing (calc

silicate) after first stage magnetic separation of -

6mm size will be around 0.06 million tons per

month. Thus total waste production will be 0.26

million ton per month. These will be dumped

separately at respective dumping yards.

4.2 Municipal waste (domestic and or

commercial wastes)

Yes The solid waste to be generated from the office

premises will be as under –

Bio-degradable: 20 to 30 kg/day.

Non-biodegradable : 5 to 7 kg/day

The biodegradable waste will be taken to organic

converter and the non-biodegradable waste will

be collected in an isolated area and disposed off

to Bhilwara Municipal Corporation as per

schedule.

4.3 Hazardous wastes (as per Hazardous

Waste Management Rules)

Yes The hazardous waste such as spent oil, lube oil

and transformer oil will be sold to actual

registered users.

4.4 Other industrial process wastes. No Waste generated from the workshop,

transformers etc. will be disposed off as per the

norms of Rajasthan State Pollution Control

Board.

4.5 Surplus product. No --

4.6 Sewage sludge or other sludge from

effluent treatment.

Yes The sludge generated from STP will be disposed

off as manure after appropriate treatment.

4.7 Construction or demolition wastes. No None.

4.8 Redundant machinery or equipment. No None.

4.9 Contaminated soils or other

materials.

No None.

16

4.10 Agricultural wastes. No None. It is a mining project.

4.11 Other solid wastes. No None.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S. No. Information/ Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

5.1 Emissions from combustion of fossil

fuels from stationary or mobile

sources.

Yes There will be emissions from transportation,

drilling, overburden handling, crushing etc.

Source Management

Loading

180 liters diesel

per hour for

shovel.

The shovel using diesel will

be maintained properly to

reduce consumption of

diesel and control of

emission of pollutant from

exhaust.

Transportation

900 liters diesel

per hour for

dumpers

Proper maintenance of

vehicles with effective

loading.

Effective water sprinkling

on haul road will be done to

arrest haul road dust.

Drilling

110 liters per

hour

The compressors used for

generating air use diesel for

running compressor engine.

Proper stack height and

maintenance of engine will

be ensured.

5.2 Emissions from production

processes.

No Dust is the main pollutant which will be

generated from vehicle movement, blasting of

rocks, crushing of ores. The dust particles shall

be so small to be suspended or carried by wind.

Deposited dust particles of different sizes that

are greater than about 10 to 20 microns settle

17

out of the air.

Suspended particulate matter remains

suspended in the air for significant period of

time, for several minutes.

Dust is managed by the following methods:-

Watering haul roads.

Wet drilling.

Water sprays where required.

Emission of total suspended particulate matter from different mining activities

Activity Type of

source

Emission factor Emission rate

Blasting Area Not applicable Negligible

Drilling Point 0.10 kg/hole (mineral working)

0.59 kg/hole (OB working)

6 kg/day (mineral working)

35.4 kg/day (OB working)

Excavation Area 24.9 kg/hr (mineral working)

0.50 kg/hr (OB working)

498 kg/day (mineral working)

10 kg/day (OB working)

Truck loading Area 0.0318 kg/tonne of material

0.0168 kg/ tonne of OB

318 kg/day (mineral working)

672 kg/day (OB working)

Transportation

(haulage road)

Line 1.24 kg/ vehicle-km-travelled

(Mineral)

0.70 kg/ vehicle-km-travelled

(OB)

620 kg/day (mineral working)

1398.6 kg/day (OB working)

Note: values represent the uncontrolled emission (without EMP), calculation based on USEPA- AP 42

series.

18

5.3 Emissions from materials

handling including storage or

transport

Yes There will be fugitive emission generated during

material handling, drilling, blasting,

transportation etc. Dust will be generated while

handling material by shovels/ excavators,

transportation by dumpers on haul roads and

unloading at mineral stacks and waste dumps.

Regular water sprinkling on haul roads will

suppress the dust particles and prevent them

from getting air-borne.

Transportation

Movement of vehicles like dumper trucks,

tankers etc. will also generate dust from the

agitation of unpaved surface. The transportation

activities on unpaved area results in fugitive

emissions to the tune of 0.108 kg/sq.m/hr.

Loading

Dust emission is generated as the material is

loaded into dumpers by excavators.

Haul road/ Overburden handling

The mineral mass will be fragmented and

released by blasting and carried over to stacks

loaded into haulage trucks. These operations will

produce dust emissions during loading,

unloading and transportation of the material

from the pit.

5.4 Emissions from construction

activities including plant and

equipment

Yes The level of construction in the area will be

around 40,000 sq. meters, which will generate

fugitive emission during the construction phase

only to the tune of 0.000805 kg/sq.m/hr (USEPA

standards for fugitive emissions during

construction) .This will be controlled by

cordoning the construction area.

5.5 Dust or odors from handling of Yes The sewage treatment plant will be of anaerobic

19

materials including construction

materials, sewage and waste.

nature followed by aerobic process, which will

have negligible odour. The dust generation

during construction activities will be restricted

within permissible limits.

5.6 Emissions from incineration of

waste

No No waste will be incinerated.

5.7 Emissions from burning of waste

in open air (e.g. slash materials,

construction debris)

No None.

5.8 Emissions from any other

sources

No None.

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.

No.

Information/Checklist

confirmation

Yes/N

o

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data with source of

information data

20

6.1 From operation of equipment

e.g. engines, ventilation plant,

crushers

Yes The major sources of noise will be during

operation of D.G. sets, crushers, transportation,

drilling, loading and unloading of minerals and

waste.

The following measures will be adopted to

control the noise and vibration : -

a. Regular maintenance of machinery.

b. Tree plantation along haul road and around

beneficiation plant.

c. Equipments like earmuffs, ear plugs are

commonly used devices for hearing

protection.

d. Controlled blasting will be practiced, which

produces very less noise.

e. Blasting will be avoided in the morning and

evening hours, on foggy days, at night time

and at the times of high wind velocity and

low cloud cover.

f. Drilling will be carried out with the help of

sharp drill bits and water injection system.

6.2 From industrial or similar

processes

Yes There will be noise during the process activities

viz. grinding, crushing, screening etc.

6.3 From construction or demolition Yes There will be no significant noise and vibration

during construction period.

6.4 From blasting or piling Yes One round containing 3 rows @ 20 holes per row

will be blasted in the mine. Blasting will be done

in sequence by delay detonators, one for each

row and having different delay numbers for

controlling blasting and vibration.

6.5 From construction or

operational traffic

yes Due to vehicular traffic and material

transportation within the lease area, noise will

be generated. However, the expected noise levels

will be well maintained within the DGMS and

21

CPCB norms.

6.6 From lighting or cooling systems Yes The area is devoid of any kind of industrial

activities in the area, however, coming up of the

project will cause night illumination in the area

causing:

• Light pollution which will be restricted using

cut-off shield fixtures on site.

• Ensuring that all lights strike a surface

directly and do not point at the sky or

surroundings. It will be kept minimum,

conforming to safety norms.

• EMF radiations at site will be reduced by

ensuring that construction supply

connection is adequate for the task, using

line filters on the mains connecting cables,

installing power factor correction

equipments.

6.7 From any other sources No Nothing significant.

7. Risks of contamination of land or water from releases of pollutants into the ground or

into sewers, surface waters, groundwater, coastal waters or the sea:

S. No. Information/Checklist

confirmation

Yes/N

o

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

7.1 From handling, storage, use or

spillage of hazardous materials

No None.

7.2 From discharge of sewage or

other effluents to water or the

land (expected mode and place

of discharge)

Yes The domestic waste water generated to the tune

of 21 KLD will be systematically treated in a well

designed STP and eventually 20 KLD water will

be collected in storage tanks and will be used for

plantation/ dust suppression.

7.3 By deposition of pollutants

emitted to air into the land or

into water

No There will be no considerable impact as the dust

receptors will have large leaf canopy cover to

arrest the dust and frequent sprinkling of water

22

will suppress the dust.

7.4 From any other sources No None.

7.5 Is there a risk of long term build

up of pollutants in the

environment from these

sources?

No None.

8. Risk of accidents during construction or operation of the Project, which could affect

human health or the environment

S.

No.

Information/Checklist

confirmation

Yes/No Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

8.1 From explosions, spillages, fires

from storage, handling, use or

production of hazardous

substances

Yes Explosion hazards are envisaged due to

mishandling of explosives. However, an expert

team including competent blasters, having

experience in handling explosives will be

designated for this project. The explosives will be

brought from the magazine to the mine in

licensed Explosive van.

8.2 From any other causes

Yes The risk of accidents is envisaged due to

operation of HEMM, failure of mine pit etc.

However, good safety practices will be applied at

the proposed project. All precautionary

measures will be adopted and use of protective

equipments will be mandatory. However, to meet

the minor incidences and accidents first aid

measures at site will be provided.

8.3 Could the project be affected by

natural disasters causing

environmental damage (e.g

Floods, earthquakes, landslides,

cloudburst etc)?

No The project is located in Seismic Zone II; hence

no severe earthquake is anticipated.

There is no risk of flood, as the area lies much

above the highest flood level (410m AMSL) and

the pit entry will be above 420m AMSL. In

Bhilwara region, there is no history of cloud

burst.

23

9. Factors which should be considered (such as consequential development) which could

lead to environmental effects or the potential for cumulative impacts with other

existing or planned activities in the locality

S. No. Information/Checklist

confirmation

9.1 Lead to development of

supporting cities, ancillary

development or development

stimulated by the project which

could have impact on the

environment e.g.:

• Supporting infrastructure

(roads, power supply, waste or

waste water treatment, etc.)

• housing development

• extractive industries

• supply industries

• other

Yes The coming up of the project will add to the

positive impact in the area as there will be

various other activities coming up due to

proposed project.

9.2 Land use after use of the site,

which could have an impact on

environment

No The land used for mining will be reclaimed by

back filling the pits and plantation causing no

adverse impact on the environment.

9.3 Set a precedent for later

developments

Yes There will be other ancillary developments

which will spring up due to coming of the project,

resulting in setting a precedent for later

development.

9.4 Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No None.

II Environmental Sensitivity (within 15 km radius – detailed as under): Study area map of 15

km radius is enclosed as Annexure – IV.

S.

No.

Areas Name/

Identity

1 Areas protected under No --

24

international conventions,

national or local legislation for

their ecological, landscape,

cultural or other related value

2 Areas which are important or

sensitive for ecological reasons -

Wetlands, watercourses or other

water bodies, coastal zone,

biospheres, mountains, forests

No The map of study area is enclosed as Annexure

IV .

The area does not depict any wetlands,

biospheres and coastal zone.

Reserved Forest – 1.0 km NE and 1.0 km SE of

the core zone.

Mandal Talav – 7.2 km towards W

Meja Talav – 8.9 km towards SW.

Kothari River – 1.5km towards SW

Left Main canal from Meja Dam to village

Mahuwa Khurd passes from NW to SE along the

south western boundary of the lease area.

3 Areas used by protected,

important or sensitive species

of flora or fauna for breeding,

nesting, foraging, resting, over

wintering, migration

No None.

4 Inland, coastal, marine or

underground waters

No None within study area.

5 State, National boundaries No None within study area.

6 Routes or facilities used by the

public for access to recreation or

other tourist, pilgrim areas

No No such route or facility exists in mining area.

7 Defense installations No None within study area.

8 Densely populated or built-up

area

Yes Bhilwara Town - 11 km towards S.

Mandal Town - 5 km towards W.

9 Areas occupied by sensitive

man-made land uses (hospitals,

schools, places of worship,

Yes In the core zone, there is a primary school and a

temple in village Jaliyan. In nearby villages

primary, middle and secondary schools are there

25

community facilities) at Arjiya, Mahuwa Khurd, Kamalpura and

Lampiya.

10 Areas containing important, high

quality or scarce resources

(ground water resources,

surface resources, forestry,

agriculture, fisheries, tourism,

minerals)

Yes The area is classified as O.E. Zone for ground

water. No Ground water will be abstracted for

mining or beneficiation. Only 10.0 KLD ground

water will be abstracted for domestic use.

Mineral to be mined is low grade magnetite ore

found in abundance in our country, waiting its

use after development of viable technology.

11 Areas already subjected to

pollution or environmental

damage. (those where existing

legal environmental standards

are exceeded)

Yes Bhilwara town has many industrial activities, but

the AAQM carried out reveals the standard to be

within permissible limits.

12 Areas susceptible to natural

hazard which could cause the

project to present environmental

problems (earthquakes,

subsidence, landslides, erosion,

flooding or extreme or adverse

climatic conditions)

No Seismic Zone – II: According to BMTPC’s

vulnerability atlas, II edition, the area falls in a

region of low damage risk zone.

There is no incidence of subsidence, landslides,

erosion, flooding or extreme or adverse climatic

conditions in the area so far.

“I hereby give undertaking that the data and information given in the application and enclosure are

true to the best of my knowledge and belief and I am aware that if any part of the data and

information submitted is found to be false or misleading at any stage, the project will be rejected

and clearance given, if any to the project will be revoked at our risk and cost.”

Date: 15.02.2017

Place: Bhilwara

Authorised signatory

M/S Jindal Saw Limited,

Araji No.9697/6711, Vill. Pur, Bhilwara

***********