82
FORD ROAD ELEMENTARY SCHOOL PAINTING RESTORATION Division of Facilities and Maintenance Department of Minor Construction Craig Evans Facilities Specialist

FORD ROAD ELEMENTARY SCHOOL - Shelby County Schools 1474... · FORD ROAD ELEMENTARY SCHOOL PAINTING RESTORATION ... equipment and - tools. The principal or their representative shall

Embed Size (px)

Citation preview

FORD ROAD ELEMENTARY SCHOOL PAINTING RESTORATION

Division of Facilities and Maintenance

Department of Minor Construction

Craig Evans Facilities Specialist

FORD ROAD ELEMENTARY SCHOOL PAINTING RESTORATION

TABLE OF CONTENTS 1 of 1

SPECIFICATIONS TABLE OF CONTENTS DIVISION 1 01000 - GENERAL REQUIREMENTS 01100 - SUMMARY 01250 - CONTRACT MODIFICATION PROCEDURES 01290 - PAYMENT PROCEDURES 01310 - PROJECT MANAGEMENT AND COORDINATION 01330 - SUBMITTAL PROCEDURES 01600 - PRODUCT REQUIREMENTS 01731 - CUTTING AND PATCHING 01732 - SELECTIVE DEMOLITION 01770 - CLOSEOUT PROCEDURES DIVISION 4 04900 - MASONRY CLEANING AND RESTORATION DIVISION 6 06201- EXTERIOR FINISH CARPENTRY DIVISION 9 09250 - FIBRE PANEL BOARDS 09640 - WOOD FLOOR REFINISHING 09911 - EXTERIOR PAINTING 09992 - INTERIOR PAINTING ATTACHMENTS ASBESTOS IN SCHOOLS-FORMAL NOTIFICATION ATTACHMENT “A” – ACCOMPLISHING MAINTENANCE/ REPAIRS OR INSTALLING EQUIPEMENT ATTACHMENT “B” – ASBESTOS REPORT ATTACHMENT- SCS POLICY NO. 1.803 – TOBACCO-FREE ENVOIRMENT END OF TABLE OF CONTENTS

FORD ROAD ELEMENTARY PAINTING RESTORATION

GENERAL REQUIREMENTS 01000-1

SECTION 01000 - GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 GENERAL INTENT. It is the declared and acknowledged intention and meaning

to provide materials and labor to complete all work, described and set forth in these specifications and attached drawings.

1.2 PRE-BID REQUIREMENTS.

A. Pre-Bid Conference. There will be a mandatory Pre-Bid Conference at the work

site 10 work days prior to the bid due date. This Pre-Bid Conference date will be posted in the Notice to Bidders. All attendees are required to be in attendance at the time stated on Procurement Service’s “Notice to Bidders”. Persons arriving after the stated time will not be allowed to sign in or to submit a bid on the project. 1. The site is available to prospective bidders for the inspection and examination

of the area and conditions under which the work is to be performed. Prior to the bid, the prospective bidders will notify the Owner of any conditions detrimental to the timely and proper accomplishment of the work. Lines shown on plans are for bidding purposes only. The successful bidder shall be responsible for taking of all field measurements for the proper installation of all materials.

2. Errors and Omissions. The prospective bidder shall not be allowed to take

advantage of any errors or omissions in these specifications and attached drawings. Where errors or omissions occur in the specifications and drawings, the bidder shall promptly notify the contact person listed in the “Notice to Bid”, and report the identified errors or omissions. Inconsistencies in the specifications or drawings are to be reported in a timely manner before the bids are submitted to Shelby County Schools.

1.3 BID REQUIREMENTS.

A. Required Items at Bid Opening.

1. Standard bid documents in accordance with the “Notice to Bidders”.

1.4 BID EVALUATION. All submitted bids will be reviewed and evaluated for content of required bid documents, cost, and compliance with local and state required licensing requirements, federal regulations, and the bidder’s past performance of work completion and workmanship with Shelby County Schools.

1.5 PRE-CONSTRUCTION REQUIREMENTS.

A. After the Owner’s issuance of the Purchase Order to the Contractor, the

Contractor shall provide the Owner with an acceptable sequence of work which must be approved by the Owner prior to the scheduling of the Pre-Construction Conference.

FORD ROAD ELEMENTARY PAINTING RESTORATION

GENERAL REQUIREMENTS 01000-2

B. After the Owner’s approval of the sequence of work, the Owner shall schedule a Pre-Construction Conference, to be held at the work site, to discuss the work requirements.

C. The Contractor shall provide the date that the work is to start at the Pre-

Construction Conference.

1.6 PROJECT REQUIREMENTS. A. The Contractor shall comply with Tennessee Code Annotated, Section 49-5-413,

which requires that all of their employees and their subcontractors’ employees, who will be on Shelby County Schools’ properties, have a State approved Background Check and Fingerprinting. When each employee has complied with the above and received approval from Authorities Having Jurisdiction, an identification badge will be issued to that employee. All contractors’ employees shall wear this badge at shirt pocket height, at all times while on the Shelby County Schools' property.

B. Shelby County Schools’ Board Policy No. 1.803 “Tobacco-Free Environment”

restricts the use of any and all tobacco products on all of its properties. The Contractor shall make each of their employees aware of this policy. See attached policy.

C. The contractor shall comply with the Civil Rights Act of 1964, as amended,

prohibits discrimination on the basis of race, color, national origin or sex. D. Asbestos.

1. Asbestos in Schools - Formal Notification See Attachment “A”. 2. Asbestos-Containing Materials.

a. The Contractor shall avoid disturbing any asbestos or suspected asbestos-containing materials. Refer to the Attachment “B” statement regarding asbestos-containing materials report.

b. If the Contractor encounters asbestos or suspected asbestos-containing materials that are not shown on the attached drawing, or if a method of installation to avoid asbestos areas cannot be determined, the Contractor shall request guidance from the Owner's representative as to how to proceed.

c. The Contractor is advised that current regulations require all work and/or abatement on asbestos containing materials be accomplished under the direction of the SCS asbestos abatement personnel. In the event disturbance of any asbestos containing building material is necessary, the Contractor shall contact Owner’s representative and request an asbestos control specialist to make the penetration. Provide at least a 72-hours advance notice if this is required. The Contractor shall avoid disturbing any asbestos or suspected asbestos- containing materials.

d. The school has an asbestos plan, showing probable asbestos problem locations and the Contractor will be made aware of these locations during

FORD ROAD ELEMENTARY PAINTING RESTORATION

GENERAL REQUIREMENTS 01000-3

the Pre-Bid Conference. If the Contractor encounters asbestos or suspected asbestos-containing materials that are not shown on the asbestos plans or not made known to him during the Pre-Bid Conference, he shall request guidance from the Owner's representative as to how to proceed.

E. Compliance with all local, state and federal codes, ordinances, regulations and

laws applicable to the work to be done shall be considered as minimum requirements, and everything shown or specified in excess of these minimum requirements shall be installed in excess thereof. No instructions given in the contract documents shall be construed as an authorization to violate any code, ordinance, regulation or law.

F. Design, Permits, and Fees.

1. If required by code or the Authorities Having Jurisdiction, the Contractor shall

provide design and necessary design documents for all work in these specifications and indicated on the attached drawings. Design documents must be prepared and stamped by the appropriate professional designer as required by state and local codes. All designs shall incorporate all code requirements and the special requirements set forth in the appropriate sections of this document. All costs associated with these requirements shall be the responsibility of the Contractor.

a. The design and design documents must be submitted to and approved by the Owner prior to submittal to the Authorities Having Jurisdiction.

2. If required by code or the Authorities Having Jurisdiction, the Contractor shall

be responsible for obtaining all licenses and permits, and the payment of all required fees. Copies of all permit applications shall be submitted to the Owner’s representative prior to the start of the project. Copies or proof of all final inspection approvals by the Authorities Having Jurisdiction shall be furnished to the Owner's representative prior to final acceptance.

3. It shall be the responsibility of the contractor to provide personnel to

meet the perspective code-enforcement inspectors on-site for all required code inspections. When the inspector’s access to the project’s area, that must be inspected, is not continually manned by the owner’s personnel during regular business hours, it is the contractor’s responsibility to notify the owner’s representative, in advance, to gain access.

G. Work once started shall be diligently carried out toward completion. All work shall

be done in a workmanship-like manner in accordance with standard practices, local codes and ordinances, applicable statutes and in accordance with manufacturer’s recommendations, where applicable.

H. The Contractor is required to perform this work within the precepts of

OSHA/TOSHA guidelines for a safe working environment. The Contractor shall erect and maintain, as required by conditions and progress of the work, all reasonable safeguards for safety and protection, including signs, dust barriers, barricades, temporary lights and warning lights. Further, the job site will be

FORD ROAD ELEMENTARY PAINTING RESTORATION

GENERAL REQUIREMENTS 01000-4

continuously kept clear of hazardous conditions. Conditions, which in the opinion of the Owner's representative are unsafe and correctable, shall be immediately corrected. Failure to do so will result in a job stoppage until the situation has been cleared.

I. The Owner may, at his discretion, engage the services of a testing laboratory to

ensure that all materials and workmanship are in accordance with the plans and specifications. The testing expense will revert to the Contractor should the material or workmanship fail to comply with requirements.

J. The Contractor shall provide entire copies of these specifications and plans to

the installing lead craftsman. The specifications and plans’ copy shall be kept on the job site for referral by the installing craftsmen and the Owner's representative.

K. If no storage space is available on site, the Contractor shall provide adequately

sized, on-site storage trailer(s) to store and protect all materials, equipment and tools. The principal or their representative shall determine the location of the storage trailer(s).

L. All materials demolished and salvaged, unless otherwise directed by the Owner’s

representative, are to become the property of the Contractor and will be promptly removed from the site.

M. The Contractor shall provide an adequate size trash container on site during the

duration of the project. The trash container shall not be allowed to overflow and shall be dumped regularly. Demolished materials and trash shall not be placed on the ground around or about the trash container. The principal or their representative shall determine the location of the trash container. The school's trash containers shall not be used for disposal.

N. Tennessee Hazardous Chemical Right to Know Law. The Owner will provide the

Contractor, at his request, with a list of chemicals that have been identified as being present in the areas involved in this contract.

O. The Contractor will be expected to protect all existing amenities currently

incorporated into or adjacent to the facility, including Public and Owner's utility services, shrubbery, sidewalks, etc. Any and all damage to the facility shall be the responsibility of the Contractor and shall be restored by him at no additional expense to the Owner.

P. Water and toilet facilities are available, with the assignment by the facility’s

Principal or Supervising Building Engineer (SBE). The Contractor may use available 120VAC, 20 Amp electrical power in the operation of their hand tools.

END OF SECTION 01000

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUMMARY 01100 - 1

SECTION 01100 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Time of Completion

3. Work under other contracts.

4. Use of premises.

5. Owner's occupancy requirements.

6. Specification formats and conventions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: PAINTING RESTORATION

B. Project Location: Ford Road Elementary 3336 Ford Rd. Memphis, TN 38109

C. Owner: Shelby County Schools, Board of Education (SCS). Memphis, Tennessee.

D. Owner’s Representative. The Owner will designate, at the time the purchase order is issued to the Contractor, the names and telephone numbers of its representatives. These will serve as the point of contact between the Contractor and Owner.

E. The Work included within this specification will generally be as depicted on SCS Drawing E-2210-54-001 Sheet 1, as attached hereto and includes, but is not necessarily limited to the following work elements:

1. Provide labor and materials to repair and replace plywood ceilings as shown. Refer to Section 06201 of the Specifications.

2. Provide labor and materials to replace and finish deteriorated drywall sections as shown. Refer to Section 09250 of the Specifications.

3. Provide labor and materials to pressure wash, tuck-point mortar joinery, and paint all exterior painted amenities per Specifications.

4. Provide labor and materials to paint all interior areas as shown for buildings 1 through 5 of facility.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUMMARY 01100 - 2

5. Refinish the Raised-Platform located in cafeteria. Refer to Section 09640 of the Specifications.

6. The General Contractor shall provide an onsite full time Superintendent from its own staff to directly supervise its subcontractor’s and to maintain constant communication and order with the school and its officials. Failure to do so will result in a back charge to the General Contractor for the added expenses to the Owner for maintaining proper project supervision.

7. The contractor shall provide and install ALL ASPECTS OF THE

SPECIFICATIONS, SCOPE OF WORK, and DRAWINGS to the most stringent standard to satisfy the general meaning and intent of Shelby County Schools.

8. Other work not specifically mentioned, but necessary to satisfy the general

intent and meaning.

F. Project will be constructed under a single contract.

1.3 TIME OF COMPLETION

A. The work shall be completed within 50 working days after issuance of a “Notice to Proceed”. This completion time will be extended should unforeseen problems create bona fide and unavoidable delays in the diligent pursuit of the project completion. Should the completion date elapse, the contractor may be assessed $500.00 in agreed damages per day until the projects are completed.

B. Owner’s Representative shall issue the “Notice to Proceed” at the time of scheduled Pre-construction conference. The total amount of working days of project has been designed to include lead time for manufacturing materials, ordering equipment, professional design, and all aspects to satisfy the Time of Completion.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

1.5 USE OF PREMISES

A. Work on Shelby County Schools facilities may be conducted as follows:

1. Elementary Schools’ Regular Scheduled School Year: 7:00 A.M. to 4:00 P.M., Monday through Friday, except for recognized Shelby County Schools' holidays.

2. High School and Middle Schools’ Regular Scheduled School Year: 7:00 A.M. to 10:00 P.M., Monday through Friday, except for recognized Shelby County Schools' holidays.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUMMARY 01100 - 3

3. All Schools’ Scheduled Summer Vacation: 7:00 A.M. to 4:00 P.M., except for recognized Shelby County Schools' holidays.

4. Should the contractor desire to work outside of the above hours, a request must be submitted at least 48 hours in advance of the desired work period.

B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

C. Owner Occupancy: Allow for Owner occupancy of Project site.

1. Driveways and Entrances: Keep driveways, loading areas and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

2. Schedule deliveries to minimize use of driveways and entrances.

3. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Use of Existing Building: Maintain existing building in a weather-tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

1.6 OWNER'S OCCUPANCY REQUIREMENTS

A. Owner Occupancy: Owner will occupy site and existing buildings during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with the educational process. Maintain existing exits, unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.

B. Contractor shall obtain approval from authorities having jurisdiction for each specific portion of the Work to be occupied before Owner occupancy.

1. Before partial Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

2. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of building.

1.7 SPECIFICATION FORMATS AND CONVENTIONS

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUMMARY 01100 - 4

A. Specification Format: The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "Master Format" numbering system.

B. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

END OF SECTION 01100

FORD ROAD ELEMENTARY PAINTING RESTORATION

CONTRACT MODIFICATION PROCEDURES 01250 - 1

SECTION 01250 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

1.2 MINOR CHANGES IN THE WORK

A. Owner will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: When requested by the Owner, the Contractor will draft a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests by Owner are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include costs of labor and supervision directly attributable to the change.

b. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to Owner.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include costs of labor and supervision directly attributable to the change.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CONTRACT MODIFICATION PROCEDURES 01250 - 2

3. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

1.4 CHANGE ORDER PROCEDURES

A. A Change Order will be issued upon the Owner's approval of a Proposal Request, Owner

END OF SECTION 01250

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAYMENT PROCEDURES 01290 - 1

SECTION 01290 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 SCHEDULE OF VALUES.

A. The contractor shall prepare and use the Schedule of Values for projects whose total contract amount equals or is in excess of $500,000.00.

B. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

C. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

D. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

1. Each item in the Schedule of Values and Applications for Payment shall be completed. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items i.e., Bid Performance Bonding Fees, that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

b. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

E. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

F. Submit the Schedule of Values to Owner at earliest possible date but no later than ten (10) days before the date scheduled for submittal of initial Applications for Payment.

1.3 APPLICATIONS FOR PAYMENT.

A. Refer to these specifications’ Section 01000, Part 1.6, Paragraph B, and attached Shelby County Schools’ Board Policy No. 2.8063 “Prevailing Wages and Benefits” regarding the requirement to submit a “Certified Payroll”.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAYMENT PROCEDURES 01290 - 2

B. Include the following Project identification on the Applications for Payment:

1. Project name and Purchase Order Number.

2. Contractor's name and address.

3. Contractor’s Invoice number

4. Date of submittal.

C. All applications for payments shall be made to the attention of the Owner’s representative, Shelby County Schools’ Department of Minor Construction, 1364 Farmville Rd., Memphis TN 38122.

D. Payment Application Times.

1. Partial payments up to 95% of the total contract amount will be approved based on which of the following (a) or (b) applies to this project.

a. Schedule of Values.

b. Amount of work completed.

2. A final payment of 5% of the total contract amount will be approved when the Contractor has presented the Owner with evidence of completion of Project closeout requirements as in Section 01770 “Closeout Procedures”.

PART 2 - (Not applicable)

PART 3 - (Not applicable)

END OF SECTION 01290

FORD ROAD ELEMENTARY PAINTING RESTORATION

PROJECT MANAGEMENT AND COORDINATION 01310 - 1

SECTION 01310 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Pre-Bid Conference

2. Pre-Construction Conference.

3. Project meetings.

1.2 PROJECT MEETINGS

A. General: Owner will schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Owner shall notify all invited attendees of scheduled meeting dates and times.

2. Agenda: Owner will prepare the meeting agenda and distribute the agenda to all invited attendees.

3. Minutes: Owner will record significant discussions and agreements achieved, distribute the meeting minutes to everyone concerned, within three (3) days of the meeting.

B. Pre-Bid Meeting: Refer to Section 01000 – General Requirements, Part 1.2 of these documents.

C. Preconstruction Meeting: Refer to Section 01000 – General Requirements, Part 1.5 of these documents, and to items below.

1. Attendees: Authorized representatives of Owner and Contractor and its major subcontractors and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Project will not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

C. Progress Meetings will be established at the Pre-Construction Conference.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PROJECT MANAGEMENT AND COORDINATION 01310 - 2

1. Attendees: Authorized representatives of Owner and Contractor and its major subcontractors and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

END OF SECTION 01310

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 1

SECTION 01330 -

PART 1 - GENERAL

SUBMITTAL PROCEDURES

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. See Division 1 Section "Closeout Procedures" for submitting warranties.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

1.3 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals as noted in Division 2 through Division 16.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Owner's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Submittals: Submittals will be reviewed by Owner and returned to Contractor within five (5) work days.

C. Identification: Place a permanent label or title block on each submittal for identification.

Include the following information on label for processing and recording action taken:

1. Project name.

2. Date.

3. Name and address of Contractor.

4. Name and address of subcontractor.

5. Name and address of supplier.

6. Name of manufacturer.

7. Submittal number or other unique identifier, including revision identifier.

8. Number and title of appropriate Specification Section.

9. Drawing number and detail references, as appropriate.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 2

10. Location(s) where product is to be installed, as appropriate.

11. Other necessary identification.

C. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.

D. Additional Copies: Unless additional copies are required for final submittal, and unless Owner observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

1. Additional copies submitted for maintenance manuals will not be marked with action taken and will be returned.

E. Re-submittals: Make re-submittals in same form and number of copies as initial submittal.

F. Distribution: Contractor shall furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

G. Use for Construction: Use only final submittals with mark indicating Owner’s approval.

1.4 CONTRACTOR'S USE OF OWNER'S CAD FILES

A. General: At Contractor's written request, copies of Owner's CAD files will be provided to Contractor for Contractor's use in connection with Project, subject to the following conditions:

1. Limitation of CAD system formats.

2. Cost of providing files in various Medias.

3. Delivery time.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 3

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Compliance with specified referenced standards.

f. Testing by recognized testing agency.

4. Number of Copies: Submit two copies of Product Data, unless otherwise indicated. Owner will return one copy. Mark up and retain one returned copy as a Project Record Document.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of Owner's CAD Drawings is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Shop work manufacturing instructions.

f. Templates and patterns.

g. Schedules.

h. Notation of coordination requirements.

i. Notation of dimensions established by field measurement.

j. Relationship to adjoining construction clearly indicated.

k. Seal and signature of professional engineer if required.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches .

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 4

3. Number of Copies: Submit two opaque (bond) copies of each submittal. Owner will return one copy.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Number and title of appropriate Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Owner will return submittal with options selected.

5. Samples for Verification: Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit two sets of Samples. Owner will retain one Sample set; remainder will be returned. Mark up and retain one returned Sample set as a Project Record Sample.

E. Product Schedule or List: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

1. Number of Copies: Submit two copies of product schedule or list, unless otherwise indicated. Architect will return one copy.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 5

2.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. Owner will not return copies.

B. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

C. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

D. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

E. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

F. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

G. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:

1. Statement on condition of substrates and their acceptability for installation of product.

2. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

3. Results of operational and other tests and a statement of whether observed performance complies with requirements.

H. Material Safety Data Sheets (MSDSs): Submit information directly to Owner.

2.3 DELEGATED DESIGN

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. Refer to Division 1, Section 01000, Part 1.6.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SUBMITTAL PROCEDURES 01330 - 6

B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit two copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01330

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-1

SECTION 01600 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

B. See Division 1 Section 1770 "Closeout Procedures" for submitting warranties for Contract closeout.

C. See Divisions 2 through 16 Sections for specific requirements for warranties on products and installations specified to be warranted.

D. The contractor is to supply all materials required to complete the work. All materials are to be new and of top quality.

1.2 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

C. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-2

1.3 SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Contractor shall make all Substitution Requests on the Contractor’s letterhead.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified material or product cannot be provided.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

h. Research/evaluation reports evidencing compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction.

i. Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating lack of availability or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Sum.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-3

k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents and is appropriate for applications indicated.

l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Owner's Action: If necessary, Owner will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution. Owner will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Use product specified if Owner cannot make a decision on use of a proposed substitution within time allocated.

B. Comparable Product Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Owner's Action: If necessary, Owner will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Owner will notify Contractor of approval or rejection of proposed comparable product request within 15 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Division 1 Section 1330 "Submittal Procedures."

b. Use product specified if Owner cannot make a decision on use of a comparable product request within time allocated.

C. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 1 Section 1330 "Submittal Procedures." Show compliance with requirements.

1.4 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project; product selected shall be compatible with products previously selected, even if previously selected products were also options.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-4

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

B. All equipment used at the job site shall be in first-class condition and incorporate all safety appliances required by TOSHA. Adequate means shall be taken to lock, secure or otherwise safeguard the equipment from misuse or vandalism when not being used. Equipment not meeting these requirements will be removed from the job site.

C. All construction materials delivered to the site shall be subject to inspection by the owner's representative, who shall have the right to examine the supplier's documentation to establish compliance with these specifications.

D. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.

E. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weather-tight enclosure above ground, with ventilation adequate to prevent condensation.

4. Store cementitious products and materials on elevated platforms.

5. Store foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

6. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

7. Protect stored products from damage and liquids from freezing.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-5

1.6 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Owner will make selection.

5. Where products are accompanied by the term "match sample," sample to be matched is Owner's.

6. Descriptive, performance, and reference standard requirements in the Specifications establish "salient characteristics" of products.

B. Product Selection Procedures:

1. Product: Where Specifications name a single product and manufacturer, provide the named product that complies with requirements.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements.

3. Products: Where Specifications include a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

4. Manufacturers: Where Specifications include a list of manufacturers’ names, provide a product by one of the manufacturers listed that complies with requirements.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-6

5. Available Products: Where Specifications include a list of names of both products and manufacturers, provide one of the products listed that complies with requirements. Comply with provisions in Part 2 "Comparable Products" Article for consideration.

6. Available Manufacturers: Where Specifications include a list of manufacturers, provide a product by one of the manufacturers listed that complies with requirements. Comply with provisions in Part 2 “Comparable Products” Article for consideration.

7. Product Options: Where Specifications indicate that sizes, profiles, and dimensional requirements on Drawings are based on a specific product or system, provide the specified product or system. Comply with provisions in Part 2 "Product Substitutions" Article for consideration.

8. Basis-of-Design Product: Where Specifications name a product and include a list of manufacturers, provide the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in Part 2 "Comparable Products" Article for consideration of a product by the other named manufacturers.

9. Visual Matching Specification: Where Specifications require matching an established Sample, select a product that complies with requirements and matches Owner’s sample. Owner’s decision will be final on whether a proposed product matches.

a. If no product available within specified category matches and complies with other specified requirements, comply with provisions in Part 2 "Product Substitutions" Article for proposal of product.

10. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies with other specified requirements.

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Owner will select color, pattern, density, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Owner will select color, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.2 PRODUCT SUBSTITUTIONS

A. Timing: Owner will consider requests for substitution if received within 7 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Owner.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PRODUCT REQUIREMENTS 01600-7

B. Conditions: Owner will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Owner will return requests without action, except to record noncompliance with these requirements:

1. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

2. Requested substitution does not require extensive revisions to the Contract Documents.

3. Requested substitution is consistent with the Contract Documents and will produce indicated results.

4. Substitution request is fully documented and properly submitted.

5. Requested substitution will not adversely affect Contractor's Construction Schedule.

6. Requested substitution has received necessary approvals of authorities having jurisdiction.

7. Requested substitution is compatible with other portions of the Work.

8. Requested substitution has been coordinated with other portions of the Work.

9. Requested substitution provides specified warranty.

2.3 COMPARABLE PRODUCTS

A. Conditions: Owner will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, Owner will return requests without action, except to record noncompliance with these requirements:

1. Evidence that the proposed product does not require extensive revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty.

4. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested.

5. Samples, if requested.

END OF SECTION 01600

FORD ROAD ELEMENTARY PAINTING RESTORATION

CUTTING AND PATCHING 01731 - 1

SECTION 01731 -

PART 1 - GENERAL

CUTTING AND PATCHING

1.1 SUMMARY

A. This Section includes procedural requirements for cutting and patching.

B. See Divisions 2 through 16 Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.

C. See Division 7 Section "Through-Penetration Fire-stop Systems" for patching fire-rated construction.

1.2 QUALITY ASSURANCE

A. Structural Elements: Prior to project commencement, the Contractor shall provide designed, stamped drawings and calculations by a licensed, professional engineer, competent in structural design. There shall not be any saw cutting, drilling, etc. that will disrupt the existing structure.

B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety.

1. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.

C. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in Owner's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

1.3 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Comply with requirements specified in other Sections.

B. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CUTTING AND PATCHING 01731 - 2

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.

1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers.

2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Temporary Support: Provide temporary support of Work to be cut.

B. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

D. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

3.3 PERFORMANCE

A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CUTTING AND PATCHING 01731 - 3

3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Excavating and Backfilling: Comply with requirements in applicable Division 2 Sections where required by cutting and patching operations.

5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

6. Proceed with patching after construction operations requiring cutting are complete.

C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

4. Ceilings: Patch, repair, or re-hang in-place ceilings as necessary to provide an even-plane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weather-tight condition.

D. Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.

END OF SECTION 01731

FORD ROAD ELEMENTARY PAINTING RESTORATION

SELECTIVE DEMOLITION 01732 - 1

SECTION 01732 -

PART 1 - GENERAL

SELECTIVE DEMOLITION

1.1 SUMMARY

A. This Section includes the following:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

B. See Division 1, Section 01000, Part 1.6 for disposal of demolished materials.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner.

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 SUBMITTALS

A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, interruption of utility services, use of elevator and stairs, and locations of temporary partitions and means of egress.

B. Pre-demolition Digital Photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by selective demolition operations. Submit before Work begins.

C. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1.4 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SELECTIVE DEMOLITION 01732 - 2

B. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

C. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

D. Standards: Comply with ANSI A10.6 and NFPA 241.

1.5 PROJECT CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. None.

C. Notify Owner of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: Hazardous materials are present in construction to be selectively demolished. A report on the presence of hazardous materials is on file for review and use. Examine report to become aware of locations where hazardous materials are present.

1. Hazardous material remediation is specified elsewhere in the Contract Documents.

2. Do not disturb hazardous materials or items suspected of containing hazardous materials except under procedures specified elsewhere in the Contract Documents.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.6 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SELECTIVE DEMOLITION 01732 - 3

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Architect.

E. Engage a professional engineer to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.

F. Survey of Existing Conditions: Record existing conditions by use of preconstruction digital photographs. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations.

B. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies.

2. If services/systems are required to be removed, relocated, or abandoned, before proceeding with selective demolition provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.

3.3 PREPARATION

A. Site Access: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SELECTIVE DEMOLITION 01732 - 4

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

5. Dispose of demolished items and materials promptly.

B. Reuse of Building Elements: Project has been designed to result in end-of-Project rates for reuse of building elements as follows. Do not demolish building elements beyond what is indicated on Drawings without Architect's approval.

1. Building Structure and Shell: 100 percent.

2. Non-shell Elements: 50 percent.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area on-site and designated by Owner.

5. Protect items from damage during transport and storage.

FORD ROAD ELEMENTARY PAINTING RESTORATION

SELECTIVE DEMOLITION 01732 - 5

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.

3.5 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.

3.6 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 01732

FORD ROAD ELEMENTARY PAINTING RESTORATION

CLOSEOUT PROCEDURES 01770-1

SECTION 01770 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Inspection procedures.

2. Warranties.

3. Final cleaning.

B. See Division 1 Section 1290 "Payment Procedures" for requirements for Applications for Payment for Substantial and Final Completion.

C. See Divisions 2 through 16 Sections for specific closeout and special cleaning requirements for the Work in those Sections.

1.2 SUBSTANTIAL COMPLETION

A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Owner of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Obtain and submit releases permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

5. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable.

6. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions.

7. Complete startup testing of systems.

8. Submit test/adjust/balance records. Submit as-built drawings, two (2) hard copies and one (1) digital copy in Auto-Cad 2009 or later.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CLOSEOUT PROCEDURES 01770-2

9. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.

10. Advise Owner of changeover in heating/cooling and other utilities.

11. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.

12. Complete final cleaning requirements, including touchup painting.

13. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, Owner will either proceed with inspection or notify Contractor of unfulfilled requirements. Owner will approve the Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Owner, that must be completed or corrected before approval will be given.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

1.3 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit a final Application for Payment according to Division 1 Section "Payment Procedures."

2. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems.

3. Completion shall be subject to a final inspection by the owner's representative.

4. Copies or proof of final inspection approvals by the authorities having jurisdiction shall be delivered to the owner's representative.

5. The Contractor shall provide a written guarantee that all products, materials and workmanship will be free from inherent defects for a period of one year from the date of acceptance by the Owner. This written guarantee shall be made on the Contractor’s letterhead. Defects arising during this period shall be promptly corrected by the Contractor, at his own expense, upon notice from the Owner. This guarantee shall include all materials and labor. The Contractor shall describe the project as titled in these documents, including

FORD ROAD ELEMENTARY PAINTING RESTORATION

CLOSEOUT PROCEDURES 01770-3

the contract's purchase order number and stating the specific warranty date(s) in the body of this guarantee statement.

6. The Contractor shall supply a written statement, on company letterhead, to the owner, stating that no asbestos-containing building materials were used in this work. The Contractor shall describe the project as titled in these documents, including the contract's purchase order number in the body of this statement.

7. All items on the Owner’s punch list shall be addressed and completed.

NOTE: Final payment will not be approved until all of the above requirements are completed.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Owner will either proceed with inspection or notify Contractor of unfulfilled requirements. Owner will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. Contractor’s Punch List shall be submitted to Owner on the Contractor’s letterhead.

1. Organize list of spaces in sequential order, starting with exterior areas first and proceeding from lowest floor to highest floor.

2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

1.5 WARRANTIES

A. Submittal Time: Submit written warranties to Owner for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated.

B. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CLOSEOUT PROCEDURES 01770-4

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

C. Provide Owner with three copies of each warranty, including Operation and Maintenance manuals.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for approval of Substantial Completion for entire Project or for a portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Remove tools, construction equipment, machinery, and surplus material from Project site.

d. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

FORD ROAD ELEMENTARY PAINTING RESTORATION

CLOSEOUT PROCEDURES 01770-5

e. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

f. Sweep concrete floors broom clean in unoccupied spaces.

g. Vacuum carpet and similar soft surfaces, removing debris and excess nap; shampoo if visible soil or stains remain.

h. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials. Polish mirrors and glass, taking care not to scratch surfaces.

i. Remove labels that are not permanent.

j. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

k. Do not paint over “UL” and similar labels, including mechanical and electrical nameplates.

l. Leave Project clean and ready for occupancy.

3.2 WARRANTY WORK

A. Defects arising during the warranty period shall be promptly corrected by the Contractor, at his own expense, upon notice from the Owner. All warranty work shall be scheduled with the Owner’s Representative.

END OF SECTION 01770

FORD ROAD ELEMENTARY PAINTING RESTORATION

MASONRY RESTORATION AND CLEANING 04900 - 1

SECTION 04900 -

PART 1 - GENERAL

MASONRY CLEANING AND RESTORATION

1.1 SUMMARY

A. This section includes the exterior cleaning of brick masonry, stone sills, wood and metal decked covered walkways, plaster entrance ceilings, and wood soffits as shown on attached drawings for:

1. Buildings 1 through 5.

PRODUCTS

2.1 Cleaning and Sealing Products:

A. Trisodium Phosphate, TSP (Masonry Cleaner)

B. Clorox® (Exterior mold and mildew)

C. Water Repellant Sealer, Farrell Calhoun 1107, or approved equal.

D. Sure Klean® Heavy Duty Restoration Cleaner. From Prosoco Inc., or approved equal

E. Sika® Latex R: Bonding agent from RAMTOOL supply, or approved equal.

F. Mortar: Buff color, Type N from Lonestar®, or approved equal.

G. Mortar Repair: Masonry Joint; “QUIKRETE” #8620, 8620-05. Commercial Grade.

H. Sika® Concrete Repair: #223 Vertical and Horizontal applications. From RAMTOOL Supply, or item I.

I. ARDENT TWP™: Concrete tilt wall and patching compound, from local vendors.

J. “Naval-Jelly”, rust remover; Manufactured by Loctite® Corp. From local vendors.

K. X.I.M. #400 Clear; Solvent-Born Primer/Sealer. From X.I.M. Products, Inc.

PART 2 - EXECUTION; CLEANING EXTERIOR SURFACES

3.1 Pressure Washing the exterior of described building(s).

A. Pressure wash; all previously painted wood and metal covered walks, concrete entrances and ceilings, stonework sills, and brick masonry.

FORD ROAD ELEMENTARY PAINTING RESTORATION

MASONRY RESTORATION AND CLEANING 04900 - 2

B. Cleaning consists of Hot water pressure washing.

C. Pressure washing shall start at top of building and work to bottom. Use a cleaning solution such as TSP on all concrete and masonry. Use Clorox® on mold and mildew areas.

D. Contractor shall protect windows, traffic, and aluminum frames at all times from water overspray at all times.

E. Refer to 2.1 D, Products, for extensive mildew and mold cleaning on stonework.

3.2 REPAIR of MASONRY

A. Masonry and Tuck-pointing

B. Repair all cracks, surface damage, and/or spalled areas on the exterior concrete. All loose concrete must be removed until firm substrate is exposed.

C. Identify and repair damaged and missing brick masonry mortar joinery.

1. New mortar shall be struck flush, slightly concave and tinted to match existing mortar. Refer to Part 2, 2.1 items F. & G. of this section for Approved Mortar Joint repair products.

END OF SECTION 04900

FORD ROAD ELEMENTARY PAINTING RESTORATION

EXTERIOR FINISH CARPENTRY 06201 - 1

SECTION 06201 -

PART 1 - GENERAL

EXTERIOR FINISH CARPENTRY

1.1 SUMMARY

A. This Section includes the following:

1. Exterior standing and running trim.

2. Plywood soffits.

1.2 SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product.

B. Samples: For each type of siding indicated.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Lumber: DOC PS 20 and applicable grading rules of inspection agencies certified by ALSC's Board of Review.

B. Softwood Plywood: DOC PS 1.

2.2 WOOD-PRESERVATIVE-TREATED MATERIALS

A. Preservative Treatment by Pressure Process:

1. Lumber: AWPA C2. Kiln dry after treatment to a maximum moisture content of 19 percent.

2. Plywood: AWPA C9. Kiln dry after treatment to a maximum moisture content of 18 percent.

3. Preservative Chemicals: Acceptable to authorities having jurisdiction and containing no arsenic or chromium.

4. Application: All exterior lumber.

2.3 STANDING AND RUNNING TRIM

A. Lumber Trim:

1. Species and Grade: Southern pine, pressure-preservative treated; B & B; SPIB.

2. Maximum Moisture Content: 19 percent.

3. Face Surface: Surfaced (smooth).

B. Moldings: WMMPA WM 4, N-grade wood moldings, without finger jointing. Made from kiln-dried stock to patterns included in WMMPA WM 12.

FORD ROAD ELEMENTARY PAINTING RESTORATION

EXTERIOR FINISH CARPENTRY 06201 - 2

1. Species: Redwood, Western red cedar, Eastern white, Idaho white, lodgepole, ponderosa, radiata, or sugar pine (available).

2.4 PLYWOOD SOFFITS

A. Plywood Type: Exterior, Grade A-C.

B. Thickness: Match existing.

C. Face Species: Southern pine or fir.

D. Surface: Smooth.

2.5 MISCELLANEOUS MATERIALS

A. Fasteners for Exterior Finish Carpentry: Provide nails or screws, in sufficient length to penetrate not less than 1-1/2 inches

1. For prefinished items, provide matching prefinished aluminum fasteners where face fastening is required.

into wood substrate.

2. For applications not otherwise indicated, provide stainless-steel, hot-dip galvanized steel or aluminum fasteners (compatible with wood preservative).

PART 3 - EXECUTION

3.1 PREPARATION

A. Prime lumber to be painted, including both faces and edges. Cut to required lengths and prime ends. Comply with requirements in Section 09911 "Exterior Painting."

3.2 INSTALLATION, GENERAL

A. Install exterior finish carpentry level, plumb, true, and aligned with adjacent materials. Use concealed shims where necessary for alignment.

1. Scribe and cut exterior finish carpentry to fit adjoining work. Refinish and seal cuts as recommended by manufacturer.

3.3 STANDING AND RUNNING TRIM INSTALLATION

A. Install flat grain lumber with bark side exposed to weather.

B. Install trim with minimum number of joints practical, using full-length pieces from maximum lengths of lumber available. Do not use pieces less than 24 inches

1. Use scarf joints for end-to-end joints.

long except where necessary.

2. Stagger end joints in adjacent and related members.

C. Fit exterior joints to exclude water. Cope at returns and miter at corners.

END OF SECTION 06201

FORD ROAD ELEMENTARY PAINTING RESTORATION

GYPSUM BOARD 09250 - 1

SECTION 09250 –

PART 1 - GENERAL

FIBER PANEL BOARD

1.1 SUMMARY

A. This Section includes the following:

1. Fiber panel board-finishing.

2. Repair of damaged drywall.

1.2 SUBMITTALS

A. Product Data: For each type of product indicated.

PART 2 - PRODUCTS

2.1 FIBER PANEL BOARD

A. General: Complying with ASTM C 36/C 36M or ASTM C 1396/C 1396M, as applicable to type of fiber panel board indicated and whichever is more stringent.

B. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: 1. USG Interiors, Inc.; Fiberock®

C. Regular Type:

1. Thickness: 5/8 inch2. Size: 48” wide. Length as required.

.

3. Long Edges: Tapered.

2.2 JOINT TREATMENT MATERIALS

A. General: Comply with ASTM C 475/C 475M.

B. Joint Tape:

1. Interior Fiber Panel Board: As recommended by Manufacturer

2. USG Ready Mixed drywall compound, from United States Gypsum Co, or approved other.

C. Joint Compound for Fiber Panel board: For each coat use formulation that is compatible with other compounds applied on previous or for successive coats.

1. Pre-filling: At open joints and damaged surface areas, use setting-type taping compound.

2. Embedding and First Coat: For embedding tape and first coat on joints, fasteners, and trim flanges, use drying-type, all-purpose compound.

3. Fill Coat: For second coat, use drying-type, all-purpose compound. 4. Finish Coat: For third coat, use drying-type, all-purpose compound.

FORD ROAD ELEMENTARY PAINTING RESTORATION

GYPSUM BOARD 09250 - 2

5. Sand finish coat to a smooth taper at joints and screw holes. Owner’s Representative

2.3 AUXILIARY MATERIALS

shall inspect prior to prime coat of paint.

A. General: Provide auxiliary materials that comply with referenced installation standards and manufacturer's written recommendations.

B. Steel Drill Screws: ASTM C 1002, unless otherwise indicated.

1. Use screws complying with ASTM C 954 for fastening panels to steel members from 0.033 to 0.112 inch

C. Corner Bead: Remove and replace all damaged corner bead with “Hot-Dipped” Galvanized 1 1/4 in. corner bead.

thick.

1. Corner bead shall be attached with Steel screws as described in Part 2, 2.3 B of this Specification. Use of “clinch-on” tool shall not be permitted.

PART 3 - EXECUTION

3.1 APPLYING AND FINISHING PANELS, GENERAL

A. Comply with ASTM C 840.

B. Examine panels before installation. Reject panels that are wet, moisture damaged, and mold damaged.

C. Isolate perimeter of gypsum board applied to non-load-bearing partitions at structural abutments, except floors. Provide 1/2-inch-

3.2 APPLYING FIBER PANEL BOARD

wide spaces at these locations, and trim edges with edge trim where edges of panels are exposed. Seal joints between edges and abutting structural surfaces with acoustical sealant.

A. Install fiber panel board in the following locations:

1. Receiving area at Bay # 3. See attached drawings.

2. Dry Storage of Bay # 3. West wall. See attached drawings.

3. Repairing all damaged drywall, holes, perforations, etc. in these areas.

FORD ROAD ELEMENTARY PAINTING RESTORATION

GYPSUM BOARD 09250 - 3

3.3 INSTALLING TRIM ACCESSORIES

A. General: For trim with back flanges intended for fasteners, attach to framing with same fasteners used for panels. Otherwise, attach trim according to manufacturer's written instructions.

3.4 FINISHING FIBER PANEL BOARD

A. General: Treat fiber panel board joints, interior angles, edge trim, control joints, penetrations, fastener heads, surface defects, and elsewhere as required to prepare gypsum board surfaces for decoration. Promptly remove residual joint compound from adjacent surfaces.

B. Pre-fill open joints and damaged surface areas.

C. Apply joint tape over fiber panel board joints, except those with trim having flanges not intended for tape.

D. Fiber panel board Finish Levels: Finish Panels and damaged Drywall to levels indicated below: 1. Level 5: At panel surfaces that will be exposed to view.

a. Primer/Paint and its application to surfaces are specified in Section 09912.

3.5 PROTECTION

A. Protect installed products from damage from weather, condensation, direct sunlight, construction, and other causes during remainder of the construction period.

B. Remove and replace panels that are wet, moisture damaged, and mold damaged.

1. Indications that panels are wet or moisture damaged include, but are not limited to, discoloration, sagging, or irregular shape.

2. Indications that panels are mold damaged include, but are not limited to, fuzzy or splotchy surface contamination and discoloration.

END OF SECTION 09250

FORD ROAD ELEMENTARY PAINTING RESTORATION

WOOD FLOORING REFINISHING 09640 - 1

SECTION 09640 -

PART 1 - GENERAL

WOOD FLOORING REFINISHING

1.1 SUMMARY

A. This Section includes procedures to refinish wood flooring.

B. Refinish the Raised Platform’s entire wood floor, risers, apron, handrails, and steps located in cafeteria.

C. Work shall be performed by craftsmen with at least 10 years experience in hardwood floor finishing. The General Contractor will be responsible for verifying this information to the Owner’s Representative.

1.2 Submittals A. Product Data: For each type of product indicated. B. Samples: For each exposed finish.

PART 2 - PRODUCTS

2.1 WOOD FLOORING SEALERS AND FINISHES

A. Products must be MFMA approved.

B. Sealer: WORLD CLASS SANDING SEALER, from POLOPLAZ COATINGS.

1. Sanding Sealer or Fast Dry Sanding Sealer.

C. Finish: WORLD CLASS COURT & GYM FINISH, from POLOPLAZ COATINGS.

D. Finish shall be a High-Gloss sheen.

PART 3 - EXECUTION

3.1 WOOD PLATFORM PREPERATION AND FINISHING

A. Preparation and Sanding:

B. Fill any holes or imperfections with wood filler that matches floor color. Sanding shall be accomplished in three phases and shall consist of course, medium and fine paper finishing with no less than #2/0 grit paper. Follow operations as recognized by standard

FORD ROAD ELEMENTARY PAINTING RESTORATION

WOOD FLOORING REFINISHING 09640 - 2

sanding practices. Heavy-duty drum sanding machines designed specifically for the purpose and which incorporate vacuum devices shall accomplish sanding. Places not reached with sander shall be sanded with an edger using the same paper sequence. Accumulations of sanding dust must not be allowed to accumulate in any degree. The floor shall be inspected for suitability before application of floor finishes.

C. All areas of work having previously had a stain finish shall be re-stained prior to applying finishes. Owner’s Representative shall approve color samples.

D. Applying Finishes: The platform floor shall be sealed using two coats of specified sealer and the finish shall be two coats of specified finish. Sand with proper grit per manufacturers instructions to break surface tension for bonding with the next coat. Allow 24 hours between coats.

E. It shall be the contractor’s responsibility to provide a licensed electrical contractor to make connection/disconnection of power for floor finishing machines.

F. Contractor will pre-inspect Stage Curtains including; front panels, valances, side panels, back panels and all track and hardware prior to start of work. Contractor shall be responsible for discoloration, dust, wrinkles, and any incurred damages.

1. Contact Owner’s Representative.

2. Use of photo equipment for record purposes.

Note: If the final coat of finish fails to retain gloss and coverage, the work

shall be covered by additional coats or reworked entirely until the finish is uniform in appearance, and coverage is satisfactory to The Owner. The contractor shall be responsible for protection of finished surfaces until such time the project is released to Administration.

END OF SECTION 09640

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 1

SECTION 09911 -

PART 1 - GENERAL

PAINTING RESTORATION, EXTERIOR

1.1 PREPARATION OF THE EXTERIOR OF THE BUILDING. Before pressure washing, sealing, or painting, all trees, tree limbs, and bushes shall be cut back from the building. Bushes around the building shall be trim back a minimum of 3 feet, trees and tree limbs shall be cut back a minimum of 4 feet. Contractor will be responsible for protecting the flower beds. Heavy equipment (lifts), when in operation, shall have yellow barrier tape around the work area. Equipment that causes ruts in the grounds or damage to sidewalks, walkways, or fencing will be the responsibility of the Contractor.

NOTE: Contractor will cut tree limbs, bushes, and remove trees as needed.

1.2 MINOR REPAIRS. The Contractor is expected to make minor repairs in the execution of this work as directed and approved by the Owner. Minor repairs are defined as those items less than ½ square foot in areas that must be patched before the surface can be properly coated.

1.3 COLORS: The colors of the paint product to be used will be selected by the Owner at a later time. One color is to be selected for ferrous metal, and one color for painted concrete and wood; with the exception of listed items to be painted with Aluminum coating and Safety colors.

1.4 MANUFACTURER’S INSTRUCTIONS. Notwithstanding the requirements of this specification, the manufacturer’s instructions concerning the application/use of their product shall be adhered to. In cases where there is an apparent conflict in these instructions, the Contractor shall stop work until a resolution to the problem is determined. 1.5 MIX FORMULAS. Upon determining the color of the finish coats of paint, the Contractor will furnish to the Owner the tint formula for that paint so that touch-up might be made at a later date. . 1.6 PAINT RECORD. Upon completion of this paintwork, the Contractor shall supply the Owner with a dry sample for each color of field paint applied and a dry sample for each color of paint applied. This requirement does not apply to white, black, or aluminum colors nor to standard safety/information colors; e.g., fire red, warning yellow, etc. The Contractor is also responsible for supplying the Owner with the locations, color.

description, and formula of the paint on a written or typed 3” x 5” index cards for record purposes.

1.7 APPLICATION. Paint materials shall be applied in even coats without streaks, runs, sags or holidays. Previous coats of paint shall be thoroughly dry before applying succeeding coats and inspected by the Owner prior to re-coating. 1.8 APPLICATION CONDITIONS. Apply paint products only when the surface and air temperatures are between 50 and 90 deg. F., unless otherwise permitted by the manufacturer’s printed instructions. Paint products shall not be applied when the

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 2

relative humidity is more than 85%. Paint shall not be applied to damp surfaces or to wood surfaces containing more than 12% moisture. 1.9 THINNING. Thinning of paint products will not be allowed, except as specifically recommended by the manufacturer for certain application procedures; i.e.,spraying, and as approved by the Owner’s representative. 1.10 COATING OF SURFACES. Coating of surfaces may be by brush, roller, and spray. 1.11 NUMBER OF COATS. The intent of this specification is that all surfaces mentioned shall have one primer and two finish coats of paint or, all bare spots, concrete patch and newly repaired areas shall be spot primed and receive two coats of paint, or Elastomeric Concrete coating. If the final coat fails to retain coverage, additional coats shall be applied to achieve uniform coverage in appearance. 1.12 NON-FERRIC METAL SURFACES. Non-ferric metal; e.g., copper, lead, brass, plastic, etc. surfaces shall not be painted unless specifically directed. These surfaces shall be washed using solutions and techniques developed by the

Contractor and approved for that purpose by the Owner.

1.13 PAINTING OMISSIONS.

A. Omit all HVAC and Chiller units.

B. Omit all exterior aluminum and stainless steel wall vents and windows. C. Omit painting chain-link fencing, with exception to meter enclosures. D. Omit painting of vinyl soffit, aluminum siding trim, and aluminum roof flashing. E. Omit painting Aluminum cover on fire-exit stairwell located on Building 5.

F. Refer to respective drawing for additional language and illustrations.

1.14 SPRAY EQUIPMENT OPERATOR EXPERIENCE.

A. The following is a list of experience required for the spray equipment operator:

B. The spray operator must have a minimum of five years experience in spray painting.

C. The owner will verify this experience through references and interviews of the spray operator prior to the painting of any of the exterior.

1.15 SUBMITTALS: Required by Owner prior to Pre-construction Conference.

A. Product Data: For each paint material indicated.

B. Samples: For each color and material to be applied.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 3

1.16 QUALITY ASSURANCE

A. All areas of completed work must be inspected and approved by The Owner.

1.17 EXTRA MATERIALS

A. Furnish extra paint materials from the same production run as the materials applied and in the quantities described below. Package with protective covering for storage and identify with labels describing contents. Deliver extra materials to Owner.

B. Quantity: Furnish an additional (1 gallon) of each material and color. This material shall be left at the school with the Building Engineer.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products listed in other Part 2 articles. 1. Farrell Calhoun Paint Company 2. PPG Industries, Pittsburgh Paints 3. The Sherwin-Williams Company

4. Tremco® Sealants; SWS, local vendor.

2.2 PAINT MATERIALS:

A. The products hereinafter described are used as a means of describing the type and quality of materials to be used and not an endorsement of a particular product. These products include:

1. Industrial Enamel: Farrell Calhoun #800 Enamel, or approved equal. 2. Metal Primer: Farrell Calhoun Rust Inhibitor #1024-1069, or approved equal. 3. Exterior Latex Primer: Farrell Calhoun Acrylic Primer #235, or approved equal. 4. Exterior Latex: Farrell Calhoun Acrylic Latex Gloss #2400, or approved equal. 5. Exterior Latex: Elastomeric Coating #2300, 100% Acrylic-smooth, or approved

equal.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 4

6. Caulking Compound: Farrell Calhoun Acrylic Latex caulking #3006, or approved equal.

7. Caulking Compound: Exterior door/window perimeters, Vulkem® 116, Tremco®

Sealants. From SWS, local vendor.

8. SHERWIN-WILLIAMS B-66-200 DTM Acrylic Coating, No Substitute. 9. Paint, Oil-based Aluminum: SHERWIN-WILLIAMS Silver Brite Aluminum B-59-S-

11.

10. PORTER-GUARD® Industrial Aluminum PP293 from PPG/Porter Paints. 11. Caulking, Expansion Joints. Dymonic® FC, Tremco® Sealants. From SWS,

local vendor.

12. Backing Rod: Denver Foam. Closed cell-soft rod. From SWS, local vendor. 13. Primer; X.I.M. Flash Bonder. White 400, from local vendors. 14. Primer; for Galvanized Metal. PORTERGUARD® PP290 FROM PPG/Porter

Paint.

2.3 PATCHING MATERIALS:

A. Wood Patching Compound: 2-part polyester or epoxy-resin wood compound with a 10- to 15-minute cure at 70 deg F

B. Metal Patching Compound: 2-part polyester-resin metal patching compound with a 10- to 15-minute cure at

, in knife grade formulation and recommended by manufacturer for type of wood repair indicated.

70 deg F

PART 3 - EXECUTION

, in knife grade formulation and recommended by manufacturer for type of metal repair indicated.

3.1 SURFACE PREPARATION, GENERAL REQUIREMENTS

A. Prepare existing surfaces as follows:

1. Clean existing surfaces to remove loose dirt and dust. 2. Remove surface films that will prevent proper adhesion. 3. Remove loose, blistered, or otherwise defective paint; smooth edges with

sandpaper. 4. Clean corroded iron or steel surfaces to bright metal. 5. Prime bare surfaces.

B. If existing surfaces cannot be prepared to an acceptable condition for proper finishing by using specified surface-preparation methods, notify Owner in writing.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 5

C. Clean and prepare surfaces to be painted according to surface-preparation schedule at the end of Part 3 and with manufacturer's written instructions for each substrate condition.

1. Provide barrier coats over incompatible previously painted surfaces or primers or remove coats and prime prepared surfaces. Notify Owner in writing about possible problems resulting from using the specified finish-coat material over substrates previously finished.

2. Sound Existing Paint, Including Tightly Adhered Paint Film: No evidence of

cracking, checking, blistering, or lack of adhesion; slight chalking and mildew may be present.

a. Pressure wash Stainless Steel decking, Standing “T” metal panels

(mansard), and Gazebo. b. Refer to 3.5 C of this Specification and treat the above items accordingly. c. Refer to Part 3, 3.3 for preparation of covered wood-deck walkway.

3. Slightly to Moderately Deteriorated Paint Including Cracked or Loose Paint Film: Moderate cracking, checking, blistering, erosion, and loss of adhesion. a. Treat areas as specified for sound existing paint above. b. After washing, carefully examine surface for cracking, blistering, peeling, or

flaking paint. c. Remove cracked, blistered, and non-adhering paint. d. Scrape and sand edges smooth so that edges will not telegraph through

new paint finish. e. Wipe surface clean to remove remaining dust.

4. Severely Deteriorated Paint Including Extensive Cracked and Loose Paint Film: Considerable cracking, checking, blistering, erosion, loss of adhesion, and severe chalking or mildew. a. Remove old paint film down to bare substrate by using hand-tool removal,

scraping and sanding, chemical removal, or a combination of all three methods.

D. Selection of surface-preparation tools and methods shall be the responsibility of painting contractor, provided surface preparation complies with requirements specified for type of existing surface condition.

3.2 SURFACE-PREPARATION METHODS

A. General: Use the cleaning methods specified in this article, using the gentlest appropriate method necessary to clean the surface

B. Hand-Tool Cleaning: Use wet sanding and wet scraping methods only. Lightly mist substrate before sanding or scraping. Acceptable hand-tools include scrapers, wire brushes, sandpaper, steel wool, nonmetallic pads, and dusters. Because of varying substrates, selection of tools shall be the responsibility of Contractor. After hand-

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 6

cleaning is attempted, power tool cleaning may be required to complete cleaning and surface preparation.

C. Solvent Cleaning: Solvent cleaning may be used to remove oil, grease, smoke, tar, and asphalt from painted or unpainted surfaces before preparation work begins. In addition, if necessary, spot-solvent cleaning may be employed just prior to the commencement of paint application, provided enough time is allowed for complete evaporation. Clean solvent and clean rags shall be used for the final wash to ensure that all foreign materials have been removed.

D. Power Tool Cleaning: Do not use power-operated cleaning equipment without Owner’s written approval based on submission by Contractor of a satisfactory quality-control program and demonstrated ability of operators to use tools without damaging historic surfaces. Quality-control program shall include provisions for supervising performance. Power tool equipment shall be used with vacuum filter attachments. The substrate to be cleaned and its existing condition will dictate the specific tools to be employed. Contractor shall select and use a combination of tools appropriate to the substrate.

E. Commercial Blast Cleaning: Surfaces, when viewed without magnification, are free of all visible oil, grease, dirt, dust, mill scale, rust, and paint. Generally; evenly dispersed very light shadows, streaks, and discolorations may remain on no more than 33% of the surface.

Blast Cleaning Methods Are:

a. Dry abrasive blasting using compressed air, blasting equipment, and abrasive.

b. Dry abrasive blasting using a closed cycle with a recirculating system of compressed air and abrasive, with or without a vacuum or recovery system.

c. Dry abrasive blasting using compressed air, water, and abrasive followed by a chemical rinse.

3.3 SURFACE PREPARATION FOR EXISTING PAINTED WOOD

A. Repair damaged wood areas including dents, holes, and cracks by filling with patching compound and wet sand smooth. Reset or remove protruding nail heads.

B. Clean as required to remove existing deteriorated coatings and any foreign matter. Thick build-up of paint and runs and sags shall be wet sanded to achieve a smooth edge.

C. Clean wood surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits, and sandpaper.

3.4 SURFACE PREPARATION FOR EXISTING PAINTED CEMENTITIOUS MATERIALS

A. Concrete, Concrete Masonry Block, Plaster, and Mineral-Fiber-Reinforced Cement Panels: Remove efflorescence, chalk, dust, dirt, grease, oils, and release agents.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 7

1. If surfaces are sufficiently alkaline to cause the finish paint to blister and burn, correct this condition before applying paint.

2. If there is no evidence of efflorescence, pressure wash area according to specifications. Remove oil and grease by solvent cleaning.

3.5 SURFACE PREPARATION FOR EXISTING BARE AND PAINTED METAL

A. Bare Metal Solvent Cleaning: Clean with a solvent degreaser such as Xylene to remove oil, grease, and other contaminants before other cleaning treatments are used. Do not use: solvents, including primer thinner and turpentine that leave residue.

B. Ferrous Metals: Clean un-galvanized ferrous-metal surfaces; remove rust, oil, grease, dirt, and other foreign substances. Use removal or cleaning methods that comply with paint manufacturer's written recommendations.

1. Touch up bare areas and prime coats that have been damaged. Wire-brush, clean with solvents recommended by paint manufacturer, and touch up with primer and finish coats.

C. Galvanized Surfaces: Clean galvanized surfaces with non-petroleum-based solvents until surfaces are free of oil and surface contaminants.

D. Metal Conditioner (Apply to Bare Metal): Apply phosphoric acid-based, etching-type surface treatments after solvent cleaning and according to manufacturers' written instructions. Rinse with clear water when reaction is complete. Allow at least 15 to 30 minutes but not less time than recommended by manufacturer for metal conditioner to condition the metal surface. Do not allow conditioner to dry before rinsing. If white rust (zinc oxide) appears after drying, wash clean with denatured alcohol immediately before priming.

E. Surface-Preparation Methods: Remove loose rust and mill scale, spatter, slag, and flux deposits. Prepare surfaces as follows:

1. SSPC-SP 2, "Hand Tool Cleaning." 2. SSPC-SP 3, "Power Tool Cleaning." 3. SSPC-SP 11, "Power Tool Cleaning to Bare Metal." 4. SSPC-SP 6, “Commercial Blast Cleaning”

F. Priming: Immediately after surface preparation, apply primer according to manufacturer's instructions and at rate to provide a dry film thickness of not less than 1.5 mils. Use priming methods that result in full coverage of joints, corners, edges, and exposed surfaces.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 8

3.6 APPLICATION, GENERAL

A. Comply with manufacturers' requirements for application methods and with other Division 9 painting Sections.

B. In addition to the number of coats specified in schedules in other Division 9 painting Sections, provide additional coats as required to produce the finishes to match sample and mockup finishes.

C. Blending: When painting new substrates patched into existing surfaces, furnish finishes specified for the specific substrate. Final finish coat shall be applied over entire surface from edge to edge and corner to corner.

3.7 CLEANING

A. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from Project site.

1. After completing painting, clean glass and paint-spattered surfaces. Remove spattered paint by washing and scraping without scratching or damaging adjacent finished surfaces.

3.8 PROTECTION

A. Protect work of other trades, whether being painted or not, against damage from painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by Owner.

B. Provide "Wet Paint" signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work.

1. After work of other trades is complete, touch up and restore damaged or defaced painted surfaces.

3.9 SURFACE-PREPARATION SCHEDULE

A. General: Prepare existing surfaces according to applicable requirements specified in this Schedule, which include descriptions of existing surface conditions before restoration painting begins.

B. Surface-Preparation Class SP-1:

1. Description: Existing paint film in good condition and tightly adhered. 2. Surface Preparation: Pressure wash with specified cleaning methods and

roughen existing paint surfaces to ensure adhesion.

C. Surface-Preparation Class SP-2:

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 9

1. Description: Paint film cracked or broken but adhered. 2. Surface Preparation: Following removal methods, pressure wash. Sand

surfaces to smooth remaining paint film edges. Prepare bare cleaned surfaces to be repainted according to specified surface-preparation methods for substrate construction materials.

D. Surface-Preparation Class SP-3:

1. Description: Paint film loose, flaking, or peeling. 2. Surface Preparation: Following removal methods, pressure wash. Sand

surfaces to smooth remaining paint film edges. Prepare bare cleaned surfaces to be repainted according to specified surface-preparation methods for substrate construction materials.

E. Surface-Preparation Class SP-4:

1. Description: Painted surface indicated to have paint completely removed. 2. Surface Preparation: Following paint removal, prepare bare cleaned surfaces to

be repainted according to specified surface-preparation methods for substrate construction materials.

F. Surface-Preparation Class SP-5:

1. Description: Missing material, including small holes, openings, and deteriorated or corroded substrate.

2. Surface Preparation: Replace missing material by patching with compounds or splicing new material with old material. After patching, refinish new surface complying with surface preparation and painting specified for new construction materials. Provide surface preparation of adjacent existing materials to comply with surface-preparation class required for description of existing surface.

3.11 EXECUTION: SPECIFIC DESCRIPTIONS. A. Exterior Painting:

1. Paint all exterior door/frame, transoms, and hollow metal units, ferrous metal windows, canopy supports, handrails, attached metal, roof ladders, downspouts and guttering (building #2 only

a. Refer to Part 3 3.2, B of the Specifications for preparation schedule.

), downspout boots, canopy and walkway structural supports, crawl access covers, and steel security doors.

b. Prime Ferrous metal: Farrell-Calhoun #1024-1069 Rust Inhibitor primer. c. Prime Galvanized metal: One coat PORTERGUARD® PP290. d. Finish: Two coats of Farrell-Calhoun Industrial Enamel #800.

2. Covered Walkways, porch decking’s, painted soffit/freeze-board: a. Refer to Part 3 3.1, C. 3 & 4 of this Specification for preparation schedule. b. Prime with Farrell-Calhoun #235 Acrylic Latex. c. Finish: Two coats Farrell-Calhoun #2300 Elastomeric Coating. d. Refer to drawing for repairs/replacement of porch ceilings.

FORD ROAD ELEMENTARY PAINTING RESTORATION

PAINTING RESTORATION 09911 - 10

3. Covered Breezeway: a. Located between Buildings I and 3.

b. Refer to Part 3 3.2, E of this Specification for preparation schedule. c. Prime with Farrell-Calhoun #1034-1069 Rust Inhibitor Primer. d. Finish. Two coats Farrell-Calhoun #800 Industrial Enamel.

4. Paint Following items two coats with PORTER-GUARD® PP293 Industrial Aluminum: a. Sidewalk covers b. Manhole covers c. Thru-cables and posts at all areas d. Ferrous-metal roof vents and exhausts e. Gas supply piping at all areas. f. Gas meter enclosure. B. PAINT, MISCELLANEOUS

1. Remove and replace all deteriorated caulking on expansion joints, vents, and door-frames. Refer to Section 09911, 2.2 A. 7&11 of these Specifications. Use 3/8”-3/4” Closed Cell backing rod to achieve proper depth on expansion joints. Do not caulk over existing caulk.

2. Special/Safety colors: Industrial Enamel.

a. Fire-Plug, bollards, and fire bells-Fire Safety Red. b. School Yard Sign-Gloss White.

END OF SECTION 09911

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 1

SECTION 09992 – INTERIOR

PART 1 - GENERAL

PAINTING RESTORATION

1.1 MOVEMENT OF FURNISHINGS. The Contractor will be expected to protect all existing amenities. Within the subject school, there will be certain semi-fixed items which will either have to be removed by the Contractor prior to painting and then replaced, or which will have to be protected during painting operations. In general, Shelby County Schools personnel will handle items that can be removed from surfaces to be painted. The Contractor is also advised that the “School Staff” shall remove and replace all items in closets and storage rooms. The use of adequate drop cloths is encouraged. Facilities that have been damaged by the Contractor’s operation shall be subject to replacement at his expense. Moveable items such as desks, tables, bookcases, chairs, file cabinets, etc. will be moved to the center of each area by the Contractor’s personnel. Any computers to be moved shall be pulled away from the wall only as far as connections will allow. If this is not sufficient area to allow for work, then the computers shall be disconnected, moved, and reconnected by Memphis City School’s personnel.

1.2 MINOR REPAIRS. The Contractor is expected to make minor repairs in the execution of this work as directed and approved by the Owner. Minor repairs are defined as those items less than ½ square foot in areas that must be patched before the surface can be properly coated.

1.3 REINSTALLATION OF METAL, GRILLS, AND SCREENS. In locations where appurtenances such as screens, grill work, and other items must be removed to complete the paint work, the removal shall be done by the Contractor in a manner to prevent damage and maintain the intent and integrity of the facility. The Contractor in a manner approved by the Owner shall reinstall such screens, grills, etc.

1.4 Colors: The colors of the paint product to be used will be selected by the Owner at a later time. A maximum of four colors are to be selected for the interior, excluding matching colors as directed in Specifications,

1.5 MANUFACTURER’S INSTRUCTIONS. Notwithstanding the requirements of this specification, the manufacturer’s instructions concerning the application/use of their product shall be adhered to. In cases where there is an apparent conflict in these instructions, the Contractor shall stop work until a resolution to the problem is determined.

and standard colors such as ceiling white, fire safety red, aluminum, and locker colors. The Contractor will be provided with chips of the colors required. On multi-coat paint systems, the color of each coat shall vary from lighter to darker for ease in application and inspection. Primer paints shall not be tinted more than ½ of finish paint formula.

1.6 MIX FORMULAS. Upon determining the color of the finish coats of paint, the Contractor will furnish to the Owner the tint formula for that paint so that touch-up might be made at a later date.

1.7 PAINT RECORD. Upon completion of this paintwork, the Contractor shall supply the Owner with a dry sample for each color of field paint applied and a dry sample for

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 2

each color of paint applied. This requirement does not apply to white, black, or aluminum colors, nor to standard safety/information colors; e.g., fire red, warning yellow, etc. The Contractor is also responsible for supplying the Owner with the locations, color, description, and formula of the paint on a written or typed 3” x 5” index card for record purposes.

1.8 APPLICATION. Paint materials shall be applied in even coats without streaks, runs, sags or holidays. Previous coats of paint shall be thoroughly dry before applying succeeding coats and inspected by the Owner prior to re-coating.

1.9 APPLICATION CONDITIONS. Apply paint products only when the surface and air temperatures are between 50 and 90 deg. F., unless otherwise permitted by the manufacturer’s printed instructions. Paint products shall not be applied when the relative humidity is more than 85%. Paint shall not be applied to damp surfaces or to wood surfaces containing more than 12% moisture.

1.10 THINNING. Thinning of paint products will not be allowed, except as specifically recommended by the manufacturer for certain application procedures; i.e.,spraying, and as approved by the Owner’s representative. Dry paint film thickness shall be as recommended by the paint manufacturer.

1.11 COATING OF SURFACES. Coating of surfaces may be by brush, roller, or spray. Spray painting will not be permitted during normal school hours and when children are present. The Owner’s Representative must approve spray application. Note: If the final coat of finish fails to retain gloss and coverage, the work shall be covered by additional coats or reworked entirely until the finish is uniform in appearance, and coverage is satisfactory to the Owner’s Representative.

1.12 NUMBER OF COATS. The intent of this specification is that all surfaces mentioned shall have one primer and two finish coats of paint or varnish. All bare spots, spackling, and newly repaired areas shall be spot primed and receive two coats of paint or varnish. Notwithstanding, wall and trim colors requiring multiple coats to achieve complete coverage shall not be used in this facility. These are typically depicted as neutral, accent, and deep base colors by the paint industry.

1.13 NON-FERRIC METAL SURFACES. Non-ferric metal; e.g., copper, lead, brass, plastic, etc. surfaces shall not be painted unless specifically directed. These surfaces shall be washed using solutions and techniques developed by the Contractor and approved for that purpose by the Owner.

1.14 PREVIOUSLY VARNISHED SURFACES. All previously varnished, alkyd, semi-gloss or high-gloss surfaces must be washed with a strong, water-based solvent and lightly sanded before new varnish is applied. Clean with Water-Soluble Cleaner, No Rinse Pre paint Cleaner from PPG / Porter Paints.

1.15 PAINTING OMISSIONS.

A. Omit all unpainted brick and ceramic wall tiles in various locations.

B. Omit acoustical suspended ceilings tile, grid, vents, and grills in all areas.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 3

C. Omit painting of various ceilings as reflected on attached drawings.

D. Omit all unpainted aluminum and stainless steel wall vents, corner expansion covers and light fixtures.

E. Omit aluminum and stainless steel windows and trim throughout the building.

F. Omit painting of Mechanical and Boiler rooms.

G. Omit painting of HVAC units in classrooms.

H. Refer to the drawings for reflective language on omitted areas.

1.16 SUBMITTALS

A. Material submittals are to be submitted to Owner’s Representative prior to Pre-construction meeting.

1.17 SPRAY EQUIPMENT OPERATOR EXPERIENCE.

B. The following is a list of experience required for the spray equipment operator:

1. The spray operator must have a minimum of five years experience in spray painting.

2. The spray operator must have demonstrated knowledge in working with two-part epoxy paints.

B. The Owner will verify this experience through references and interviews of the spray operator prior to the painting of any lockers.

1.18 SUBMITTAL

A. Product Data: For each paint material indicated.

C. Samples: For each color and material to be applied.

1.19 QUALITY ASSURANCE

A. All areas of completed work must be inspected and approved by The Owner’s Representative.

1.20 EXTRA MATERIALS

A. Furnish extra paint materials from the same production run as the materials applied and in the quantities described below. Package with protective covering for storage and identify with labels describing contents. Deliver extra materials to Owner.

B. Quantity: Furnish an additional (1 gallon) of each material and color. This material shall be left at the school with the Building Engineer.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 4

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products listed in other Part 2 articles.

1. Farrell Calhoun Paint Company

2. PPG Industries, Pittsburgh Paints

3. The Sherwin-Williams Company

2.2 PAINT CLEANING AND REMOVAL MATERIALS

A. The products hereinafter described must meet or exceed the Specifications as listed:

1. Paint, Polyurethane Varnish: a. Color-Clear Gloss b. WFT of 4.0 Mils and DFT 1.8 Mils; applied at 350-450 Sq. ft. per gallon. c. Solids: 53.8% by weight/46.7% by volume.

2. Paint, Stain Blocking Primer-Acrylic Latex:

a. Color-White b. WFT of 4.6 Mils and DFT 1.6 Mils; applied at 300-400 Sq. ft. per gallon. c. Solids: 56.0% by weight/40.1% by volume.

3. Spackling Compound: Sinclair Muralo-681-4 (asbestos free).

4. Paint, Interior Latex Semi-Gloss: a. Color-White/Tinted b. WFT of 4.6 Mils and DFT of 1.6 Mils; applied at 300-400Sq. ft. per gallon. c. Solids: 47.6% by weight/36.3% by volume.

5. Caulking Compound: Latex; Siliconized Acrylic.

a. Color; White b. Solids by weight; 82% Minimum.

6. Paint: Interior Flat Latex; Premium-Commercial Grade. a. Color; see Specification for application. b. WFT of 4.6 Mils and DFT of 1.7 Mils; applied at 300-400 Sq. ft. per gallon. c. Solids; 50% by weight/36.5% by volume.

7. Paint, Oil-based Aluminum: a. WFT of 2.5 Mils and DFT of 1.0 Mils; applied at 438 Sq. ft. per gallon. b. Solids: 52% by weight/42% by volume.

8. Water-Soluble Cleaner: ‘No Rinse’, Pre-paint Cleaner.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 5

9. Paint, Oil based-Metal Primer; Interior/Exterior: a. Color; White, Red, or Gray. b. WFT of 4.6 Mils and DFT of 2.3 mils; applied at 300-400 Sq. ft. per gallon. c. Solids: 68.6% by weight and 48.7% by volume.

10. Paint, Industrial-oil based gloss enamel.

a. Color: Standard or Selected per Specifications. b. WFT of 3.6 Mils and DFT of 1.9 Mils; applied at 400-500 Sq. ft. per gallon. c. Solids: 52.7% by weight/41.6% by volume.

11. Primer and bond coat (alcohol-base):

a. Color-White b. WTF of 1.9 Mils and DFT of 1.0; applied at 464 SQ. ft. per gallon. c. Solids: 51.0% by weight/29% by volume.

12. Paint, Acrylic Epoxy Water-Borne.

a. Color: Component A tinted to Specifications. Gloss sheen. b. WFT of 5.4 Mils and DFT of 2.0; applied at 195 Sq. ft. per gallon. c. Solids: 48.6 by weight/36.8% by volume.

13. Paint, Block Filler:

a. Color-White b. WFT of 32 Mils and DFT of 16.1 Mils; applied at 50-100 Sq. ft. per gallon. c. Solids: 67.1% by weight/46.7% by volume.

14. Paint, Enamel under coater-oil based.

a. Color-White b. WFT of 4.0 Mils and DFT of 2.2 Mils; applied at 350-450 Sq. ft. per gallon. c. Solids: 77.0% by weight/55.0% by volume.

15. Wood Filler: Latex-Base.

a. Color-Beige b. Weight Solids: 81@ 2%.

16. High-Temp. Aluminum RED-HOT®, FROM Sheffield Products.

17. Paint, Water-Base Dry Fog-flat.

a. Color-White/ Off White b. WFT of 8.0 Mils and DFT Mils; applied at 200 Sq. ft. per Gallon. c. Solids: 68.8% by weight/39.6% by volume.

18. Paint, Satin Enamel-Oil Base

a. Color-White/Tinted b. WFT of 4.0 Mils and WFT of 2.0 Mils; applied at 400-500 Sq. ft. per gallon c. Solids: 66.4% weight/50.2% volume.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 6

2.3 VOC:

A. VOC Content of Interior Paints and Coatings: Provide products that comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

1. Flat Paints, Coatings, and Primers: VOC content of not more than 96 g/L.

2. Semi-Gloss Latex Enamel: VOC content of not more than 250 g/L.

3. Anticorrosive and Anti-Rust Metal Primers applied to Ferrous Metals: VOC content of not more than 380 g/L.

4. Industrial Enamel-Gloss: VOC not more than 380 g/L.

5. Polyurethane Varnishes: VOC not more than 450 g/L.

6. Interior-Exterior Water-Based Stain Killer: VOC as supplied not more than 350 g\L.

7. Water-Born Two Component Epoxy: VOC as supplied not more than 400 g/l.

8. Oil-Based Enamel Under-coater: VOC as supplied not more than 250 g/l.

2.4 PATCHING MATERIALS

A. Wood Patching Compound: 2-part polyester or epoxy-resin wood compound with a 10- to 15-minute cure at 70 deg F

B. Metal Patching Compound: 2-part polyester-resin metal patching compound with a 10- to 15-minute cure at

, in knife grade formulation and recommended by manufacturer for type of wood repair indicated.

70 deg F

C. Interior Cementations Patching Compound Materials: Provide cementitious patching compounds and repair materials specifically manufactured for surface preparation and sanding prior to repainting.

, in knife grade formulation and recommended by manufacturer for type of metal repair indicated.

D. Wood Filler for Wood Doors: One component, quick drying and easily sandable. Use on areas of nail holes, staple holes, and vandalism;

MISCELLANEOUS MATERIALS:

Acrylic-Latex base with water cleanup. Knife or trowel spreading grade.

A. Detergent Cleaning Solution: Mix 2 cups of tetrasodium polyphosphate, 1/2 cup of laundry detergent, 5 quarts of 5 percent sodium hypochlorite bleach, and 15 quarts of warm water for each 5 gal. o

B. Job-Mixed Mold, Mildew, and Algae Remover: Mix

f solution required.

2 cups of tetrasodium polyphosphate, 5 quarts of 5 percent sodium hypochlorite bleach, and 15 quarts of hot water for every 5 gal of solution required.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 7

PART 3 - EXECUTION

3.1 SURFACE PREPARATION, GENERAL REQUIREMENTS

A. Prepare existing surfaces as follows:

1. Clean existing surfaces to remove loose dirt and dust.

2. Remove surface films, (ex); staples, contact paper, glue, paper shards, that will prevent proper adhesion.

3. Treat paint finishes with gloss sheen to dull the surface with de-glosser.

4. Remove loose, blistered, or otherwise defective paint; smooth edges with sandpaper.

5. Clean corroded iron or steel surfaces to bright metal.

6. Spackle and sand gypsum and plaster surfaces.

7. Prime bare surfaces.

B. If existing surfaces cannot be prepared to an acceptable condition for proper finishing by using specified surface-preparation methods, notify Owner in writing.

C. Clean and prepare surfaces to be painted according to surface-preparation schedule at the end of Part 3 and with manufacturer's written instructions for each substrate condition.

1. Provide barrier coats over incompatible previously painted surfaces or primers or remove coats and prime prepared surfaces. Notify Owner in writing about possible problems resulting from using the specified finish-coat material over substrates previously finished.

2. Sound Existing Paint, Including Tightly Adhered Paint Film: No evidence of cracking, checking, blistering, or lack of adhesion; slight chalking and mildew may be present.

a. Wash areas to be repainted; use mild detergent solution, and rinse with clean water until all detergent has been removed.

b. Remove dirt and chalking from the surface without damaging the substrates or adjacent areas.

c. Allow washed areas to dry before painting.

3. Slightly to Moderately Deteriorated Paint Including Cracked or Loose Paint Film: Moderate cracking, checking, blistering, erosion, and loss of adhesion.

a. Treat areas as specified for sound existing paint above. b. After washing, carefully examine surface for cracking, blistering, peeling, or

flaking paint. c. Remove cracked, blistered, and non-adhering paint.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 8

d. Scrape and sand edges smooth so that edges will not telegraph through new paint finish.

e. Wipe surface clean to remove remaining dust.

4. Severely Deteriorated Paint Including Extensive Cracked and Loose Paint Film: Considerable cracking, checking, blistering, erosion, loss of adhesion, and severe chalking or mildew.

a. Remove old paint film down to bare substrate by using hand-tool removal, scraping and sanding, chemical removal, or a combination of all three methods.

D. Selection of surface-preparation tools and methods shall be the responsibility of painting contractor, provided surface preparation complies with requirements specified for type of existing surface condition.

3.2 SURFACE-PREPARATION METHODS

A. General: Use the cleaning methods specified in this article, using the gentlest appropriate method necessary to clean the surface.

B. Wash surfaces by hand cleaning using clean rags, sponges, water, and detergent.

C. Hand-Tool Cleaning: Use wet sanding and wet scraping methods only. Lightly mist substrate before sanding or scraping. Acceptable hand-tools include scrapers, wire brushes, sandpaper, steel wool, nonmetallic pads, and dusters. Because of varying substrates, selection of tools shall be the responsibility of Contractor. After hand-cleaning is attempted, power tool cleaning may be required to complete cleaning and surface preparation.

D. Solvent Cleaning: Solvent cleaning may be used to remove oil, grease, smoke, tar, and asphalt from painted or unpainted surfaces before preparation work begins. In addition, if necessary, spot-solvent cleaning may be employed just prior to the commencement of paint application, provided enough time is allowed for complete evaporation. Clean solvent and clean rags shall be used for the final wash to ensure that all foreign materials have been removed.

E. Power Tool Cleaning: Do not use power-operated cleaning equipment without Owner’s written approval based on submission by Contractor of a satisfactory quality-control program and demonstrated ability of operators to use tools without damaging historic surfaces. Quality-control program shall include provisions for supervising performance. Power tool equipment shall be used with vacuum filter attachments. The substrate to be cleaned and its existing condition will dictate the specific tools to be employed. Contractor shall select and use a combination of tools appropriate to the substrate

3.3 SURFACE PREPARATION FOR EXISTING PAINTED WOOD

A. Repair damaged wood areas including dents, holes, and cracks by filling with patching compound and wet sand smooth. Reset or remove protruding nail heads.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 9

B. Clean as required to remove existing deteriorated coatings and any foreign matter. Thick build-up of paint and runs and sags shall be wet sanded to achieve a smooth edge.

C. Clean wood surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits, and sandpaper.

3.4 SURFACE PREPARATION FOR EXISTING PAINTED CEMENTITIOUS MATERIALS

A. New and Bare Plaster: Neutralize surface of plaster with mild acid solution as recommended by paint manufacturer. In lieu of acid neutralization, provide manufacturer's written recommendation for plaster primer over alkaline plaster surfaces.

B. Concrete, Concrete Masonry Block, Plaster, and Mineral-Fiber-Reinforced Cement Panels: Remove efflorescence, chalk, dust, dirt, and grease, oils, and release agents.

1. If surfaces are sufficiently alkaline to cause the finish paint to blister and burn, correct this condition before applying paint.

2. If there is no evidence of efflorescence, scrub with mild detergent solution. Remove dirt and other foreign matter. Remove oil and grease by solvent cleaning.

3.5 SURFACE PREPARATION FOR EXISTING PAINTED PLASTER OR GYPSUM BOARD

A. Sound Existing Paint System: Wash all areas to be painted with a mild detergent solution; rinse with clean water until all detergent has been removed. Remove dirt and chalk from the surface without damaging the substrates or adjacent areas. Allow washed areas to dry thoroughly before painting.

B. Rout out surface cracks to remove loose, unsound material; fill with patching compound and wet sand; spot-prime with specified primer.

3.6 SURFACE PREPARATION FOR EXISTING BARE AND PAINTED METAL

A. Bare Metal Solvent Cleaning: Clean with solvents to remove oil, grease, and other contaminants before other cleaning treatments are used. Do not use solvents, including primer thinner and turpentine that leave residue.

B. Ferrous Metals: Clean un-galvanized ferrous-metal surfaces; remove rust, oil, grease, dirt, and other foreign substances. Use removal or cleaning methods that comply with paint manufacturer's written recommendations.

1. Touch up bare areas and prime coats that have been damaged. Wire-brush, clean with solvents recommended by paint manufacturer, and touches up with primer and finish coats.

C. Galvanized Surfaces: Clean galvanized surfaces with non-petroleum-based solvents until surfaces are free of oil and surface contaminants.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 10

D. Metal Conditioner (Apply to Bare Metal): Apply phosphoric acid-based, etching-type surface treatments after solvent cleaning and according to manufacturers' written instructions. Rinse with clear water when reaction is complete. Allow at least 15 to 30 minutes but not less time than recommended by manufacturer for metal conditioner to condition the metal surface. Do not allow conditioner to dry before rinsing. If white rust (zinc oxide) appears after drying, wash clean with denatured alcohol immediately before priming.

E. Surface-Preparation Methods: Remove loose rust and mill scale, spatter, slag, and flux deposits. Prepare surfaces as follows:

1. SSPC-SP 2, "Hand Tool Cleaning."

2. SSPC-SP 3, "Power Tool Cleaning."

3. SSPC-SP 11, "Power Tool Cleaning to Bare Metal."

F. Priming: Immediately after surface preparation, apply primer according to manufacturer's instructions and at rate to provide a dry film thickness of not less than 1.5 mils

G. Surface-Preparation Class SP-6:

. Use priming methods that result in full coverage of joints, corners, edges, and exposed surfaces.

1. Description: Severe Vandalism on Wood Door surfaces.

2. Surface Preparation: Clean and remove nails, staples, tape backing, and adhesives with an appropriate cleaner. Sand and apply one coat of Enamel Under-coater. Apply a filler coat from Section 2.2, A, 15 to the areas with imbedded vandalism per manufactures instructions. Product described in 09992 2.4 D. Sand to smooth finish and spot prime these areas. Finish as described in 09992 3.11, F 2.

3.7 APPLICATION, GENERAL

A. Comply with manufacturers' requirements for application methods and with other Division 9 painting Sections.

B. In addition to the number of coats specified in schedules in other Division 9 painting Sections, provide additional coats as required to produce the finishes to match sample and mockup finishes.

C. Blending: When painting new substrates patched into existing surfaces, furnish finishes specified for the specific substrate. Final finish coat shall be applied over entire surface from edge to edge and corner to corner.

3.8 CLEANING

A. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from Project site.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 11

1. After completing painting, clean glass and paint-spattered surfaces. Remove spattered paint by washing and scraping without scratching or damaging adjacent finished surfaces.

3.9 PROTECTION

A. Protect work of other trades, whether being painted or not, against damage from painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by Owner.

B. Provide "Wet Paint" signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work.

1. After work of other trades is complete, touch up and restore damaged or defaced painted surfaces.

3.10 SURFACE-PREPARATION SCHEDULE

A. General: Prepare existing surfaces according to applicable requirements specified in this Schedule, which include descriptions of existing surface conditions before restoration painting begins.

B. Surface-Preparation Class SP-1:

1. Description: Existing paint film in good condition and tightly adhered.

2. Surface Preparation: Detergent wash with specified cleaning methods. Roughen or de-gloss existing paint surfaces to ensure adhesion.

C. Surface-Preparation Class SP-2:

1. Description: Paint film cracked or broken but adhered.

2. Surface Preparation: Following removal methods, detergent wash. Sand surfaces to smooth remaining paint film edges. Prepare bare cleaned surfaces to be repainted according to specified surface-preparation methods for substrate construction materials.

D. Surface-Preparation Class SP-3:

1. Description: Paint film loose, flaking, or peeling.

2. Surface Preparation: Following removal methods, detergent wash. Sand surfaces to smooth remaining paint film edges. Prepare bare cleaned surfaces to be repainted according to specified surface-preparation methods for substrate construction materials.

E. Surface-Preparation Class SP-4:

1. Description: Painted surface indicated to have paint completely removed.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 12

2. Surface Preparation: Following paint removal, prepare bare cleaned surfaces to be repainted according to specified surface-preparation methods for substrate construction materials.

F. Surface-Preparation Class SP-5:

1. Description: Missing material, including small holes, openings, and deteriorated or corroded substrate.

2. Surface Preparation: Replace missing material by patching with compounds or splicing new material with old material. After patching, refinish new surface complying with surface preparation and painting specified for new construction materials. Provide surface preparation of adjacent existing materials to comply with surface-preparation class required for description of existing surface.

3.11 SPECIFIC DESCRIPTIONS.

A. WALLS. Clean and paint all walls throughout the facility and annex as indicated in A through G below, except areas specifically omitted. Apply Syncolaid Muralo-681-4 spackling compound if needed, plus one coat of Stain Blocking Primer and two coats of specified finish topcoat.

1. Wood and wood paneling walls.

2. Note: Previously Painted Concrete. All previously-painted concrete, concrete block, and plaster surfaces coated with alkyd semi-gloss or high-gloss enamels must be washed with a strong, water-based solvent cleaner and lightly sanded before new paint is applied.

a. Rubbed Concrete. b. Exposed Concrete Spandrel beams. c. Textured Concrete. d. Concrete blocks.

2. Plaster walls and ceilings.

3. Metal walls. a. Metal Panel Walls. Fixed and moveable. b. Previously painted sliding room dividers.

4. Gypsum Board walls and ceilings.

B. Door and trim finish schedule:

1. Prime painted doors/frames, restroom stall doors, and handrail systems with one

coat from Section 2.2, A, 9 or 14. Refer to Sec.09992 Part 3 3.6, G. of the specifi-cations. Finish with two coats of Industrial Oil Enamel. Refer to Section 2.2, A, 10.

2. Miscellaneous painted amenities: Prime with one coat from Section 2.2, A, 9 or 14 and finish with two coats Industrial Enamel. Refer to Section 2.2, A, 10.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 13

3. Natural doors, handrails, cabinets, and trim shall be cleaned and receive two coats of Gloss varnish. Refer to Section 2.2, A, 1.

4. Prepare and paint ferrous metal window assemblies, stairwell hollow metal exit door/frames and transoms, and glazed hollow metal storefronts. Refer to Item 2 above.

C. CLASSROOMS/OFFICE AREAS: Approximately 46 classrooms. Prime walls with one coat of Stain-Blocking Primer. See Section 2.2 A., item 2. Finish with two coats of Semi-Gloss Latex. See Section 2.2 A., item 4. Finish all window casings, doors and frames, chalk rails, built-in cabinets, and miscellaneous trim items. Refer to Section 3 11, B. items 1-4 for system Specifications.

D. FOYERS AND CORRIDORS: Prime walls with one coat of Stain-Blocking Primer. See Section 2.2 A., item 2. Finish with two coats of Semi-Gloss Latex. See Section 2.2 A., item 4. Refinish all doors and doorframes, handrails, sink basins and supports, unit ventilators, and ferrous metal items in these areas. Refer to finish schedule in Painting Restoration 09992 3. 11 B. of the specifications for these items.

E. LIBRARY (MEDIA CENTER): Clean and Varnish the attached book shelves and cases, book caddies and book islands in the Media Center. Use two coats of Gloss Polyurethane Varnish. See Section 2.2 A., item 1. Refinish all doors and doorframes, window casings, transoms windows, and trim items. Refer to finish schedule 09992 3.11 B. of these specifications. Prime walls, posts, and beams in Media Center and offices. See Section 2.2 A., item 2. Finish with two coats Acrylic, Semi-Gloss Latex. See Section 2.2 A., item 4.

F. CAFETERIA/KITCHEN, SERVING: Prime walls and ceilings with one coat Stain-Blocking primer. See Section 2.2 A., item 2. Apply two coats of Semi-Gloss latex. See Section 2.2 A., item 4. Refer to Section 3.11, B. for doors/frames and all trim items. Refinish Raised Platform. Refer to Section 09640 of the Specifications.

G. SPECIAL ITEMS AND LOCATIONS:

1. Wood Shelving: Typically in classrooms. Refinish all previously painted wood shelving, permanent wood cabinets, and trim in all areas. Refer to Section 3, 11, B. 2.

2. Restrooms: Paint ceilings, attached piping, and walls. Prime with one coat of

Stain-Blocking Primer. See Section 2.2 A., item 2. Finish with two coats of Latex Semi-Gloss enamel. See Section 2.2 A., item 4. Paint the plaster stall patricians, stall doors, and any attached ferrous metal. Prime with one coat Primer. See Sec-tion 2.2 A., item 9. Finish with two coats of Industrial Enamel. See Section 2.2 A., item 10. Finish all doors, doorframes, wood window casements, and unit ventilators in accordance with Paint Restoration 09992 3. 11 B. Paint soil-drain pipes with two coats of Aluminum. Use product in Section 2.2 A., item 7.

3. Stairwells: Prime C.M.U and smooth concrete, see Section 2.2 A, 2. Finish with two topcoats, see Section 2.2 A., item 4. Door/frames, heat ventilators, hand rails, window casings refer to 3.11 B. Omit painting aluminum window systems. Prime handrail system, risers, pans, and stringers with one coat primer. See Section 2.2 A., item 9. Finish with two coats Of Industrial Enamel. See Section 2.2 A., item 10.

FORD ROAD ELEMENTARY PAINTING RESTORATION

09992 - 14

4. PAINT; MISCELLANEOUS:

1. Repair all cracks and/or spalled areas. Use product Syncolaid Muralo-681-4 spackling compound.

2. Caulk all voids and cracks in adjacent and uneven substrates. Refer to Part 2. 2.2, A., item 5.

3. Unpainted masonry block shall receive two coats of Block-Filler prior to finish painting.

4. Paint all custodial closets, book storage rooms, book store, and roof access ladders throughout the building. Paint all wood shelving located in these areas. Refer to Sec. 09992 3 11. A. Par. 1 of these specifications. Finish all doors and doorframes in accordance with Sec. 09992 3.11 B.

5. Note: Refer to drawing for drywall/plaster damaged areas. Remove all deterio-rated substrates and replace drywall sections and tape joints to make a com-plete sound repair. Refer to Section 09250 Gypsum Board in the Specifica-tions.

END OF SECTION 09992

Office of Eddie Miller, Director General Services Department

Department of Facilities and Maintenance

1364 Farmville Road. Memphis, Tennessee 38122 . (901) 416-0049

Date: February 13, 2014 To: Craig Evans, Project Facilitator Division of Facilities Management From: Eddie Miller, AHERA / LEA Designated Person Division of Facilities Management Subject: Ford Road ES – Interior and Exterior Painting / Asbestos Report The following areas have been identified with Asbestos-containing materials as defined by OSHA and EPA.

1. Interior Door and Window Frame Caulking 2. Exterior Door and Window Frame Caulking 3. Window Putty or Glazing 4. Expansion Joint Caulking 5. All Non-Fiberglass or rubber Thermal Insulation – this includes the pipe insulation

under metal-wrap, Boiler Insulation throughout campus and piping in crawlspaces (if applicable)

6. Transite Walls in Annex Building It should be noted that ALL plaster materials on walls and ceilings have been inspected and sampled for asbestos. These materials are asbestos-free. Please contact me at (901) 416-0049 or email [email protected] and let me know if I can be of any further assistance.

1.803 Tobacco-Free Environment Policy______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Original Adoption: 06/01/87 Effective Date: 07/10/06Revision Dates: 03/18/91, 04/19/93, 07/01/93; 07/10/06______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

I. PURPOSETo provide a safe and healthy environment for all employees, students, and visitors and to serve as apositive example to all students concerning the use of tobacco.

II. SCOPEThis policy applies to all employees, students, and visitors.

III. POLICY STATEMENTThe Board of Education recognizes that smoking represents a major health and safety hazard which canhave serious consequences for the smoker and nonsmoker alike. The Board believes that the health andwellness of employees, students, and visitors are of primary importance; therefore, smoking and/or the useof all tobacco products, including smokeless tobacco, are prohibited in all Board of Education buildings1

(schools and other facilities); in any public seating areas, including but not limited to, bleachers used forsporting events, or public restrooms2; and in all vehicles, owned, leased or operated by the district at alltimes.

Signs will be posted throughout the district's facilities to notify students, employees and all other personsvisiting the school that the use of tobacco and tobacco products is forbidden.1 A Smoking is prohibited bylaw in seating areas and in restrooms sign shall be prominently posted for elementary or secondary schoolsporting events (including at each ticket booth).2

Any student who possesses tobacco products shall be issued a citation by the school principal.3Parents and students shall be notified of this citation requirement at the beginning of each school year.

IV. RESPONSIBILITY A. Employees, students, and visitors are responsible for abiding by the provisions of this policy. B. Senior management and supervisors are responsible for ensuring that areas over which they have control are aware of the policy and are in compliance.

C. Principals are responsible for notifying parents and students of this policy.

D. The Superintendent or designee, in cooperation with the juvenile court and the local police/sheriff'sdepartment, is responsible for developing procedures for issuance of citations.

E. The Superintendent is responsible for ensuring that this policy is followed.

___________________ ___________________Legal Reference: Cross Reference:1. Section 1042 of the Environmental Tobacco Smoke/Pro-Children Act of 19942. TCA 39-17-1604(6)(10); TCA 39-17-1605; TCA 39-17-16063. TCA 39-17-1505

DRAWING NO.SCHOOL

DRAWN

BY

OF

SHEET

AS SHOWN

SCALE

DATENAME

BY

CK 'D

OF THE