FORBES TOWER PROGRESS REPORT About the Project:
Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.
Title of Project Forbes Tower
Project Reference BFFB/14/0105-3105/2016
Design & Supervision Consultant
Arab Architects
Interior Design Consultant
Horizon Interiors
Main Contractor United Arab Construction Company (U.A.C.C.)
About Progress Report:
Title of Document Progress Report of Forbes Tower
Reporting Period May 1, 2017 to May 31, 217
Authors & project role United Arab Construction Company (U.A.C.C.)
Date June 21, 2017
DESCRIPTION PERCENTAGE
(%) OF COMPLETION
REMARKS
MOBILIZATION
1. Fencing 100% Completed 2. Site Offices (Consultant Engineer) 100% Completed 3. Car Park 100% Completed 4. Site Offices (Contractors) 100% Completed 5. Labour rest room & Toilets 100% Completed 6. Store Room 100% Completed 7. Signboard Works 100% Completed
SUPER STRUCTURE
1. Piling Works 100% Completed 2. Pilecap Concrete Works 100% Completed 3. Tile beam Concrete Work 100% Completed 4. Backfilling for grade slab 100% Completed 5. Grade Slab Concreting works 100% Completed
SUB STATION 1. Concreting Works 100% Completed 2. Rough Finish 100% Completed 3. Final Finish 100% Completed 4. Handing Over 100% Completed
SUPER STRUCTURE Ground Floor (+0.800 LVL)
1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 90% In Progress 4. Internal Plastering 60% In Progress 5. Epoxy Painting on floor 20% In Progress
Mezzanine Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Epoxy Painting on floor 30% In Progress
1st Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed
4. Internal Plastering 100% Completed 5. Marble Floor Tiles fixing 50% In Progress 6. Epoxy Painting on floor 30% In Progress
2nd Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Epoxy Painting on floor 30% In Progress
4. Block Work 100% Completed
5. Internal Plastering 100% Completed 6. Marble Floor Tiles Fixing 100% Completed
3rd and 4th Parking Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 30% In Progress 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Marble Cladding Fixing in Walls 85% In Progress 7. Marble Floor Tiles Fixing 100% Completed
1st Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 95% In Progress 8. Marble Cladding Fixing in walls 100% Completed 9. Marble Floor Tiles Fixing 100% Completed
2nd to 6th Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 90% In Progress 9. Marble Floor Tiles Fixing 100% Completed
7th Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed
3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Mable Cladding fixing in walls 95% In Progress 9. Marble Floor Tiles Fixing 100% Completed
8th to 28th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Ceramic Floor Tiles Fixing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 100% Completed 9. Marble Floor Tiles Fixing 100% Completed
29th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 60% In Progress 9. Marble Floor Tiles Fixing 100% Completed
30th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 40% In Progress 9. Marble Floor Tiles fixing 100% Completed
31st to 32nd Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed
5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 95% In Progress 8. Marble Floor Tiles Fixing 100% Completed
33rd Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 90% In Progress 9. Marble Floor Tiles Fixing 100% Completed
34th to 35th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 9. Marble Floor Tiles Fixing 100% Completed
Gymnasium Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed
Roof Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Painting 75% In Progress
Lift Machine Room Slab 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed
On-site Photos: cv \
(Front Side Elevation) (Left Side Elevation)
5. Painting 75% In Progress Head Room for Machine Room & Staircase, Head Roof for Staircase 2
1. Column & Shear Wall Concrete 100% Completed 2. Beam and Slab Concrete 100% Completed 3. Parapet Blockwork 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Painting 90% In Progress
Parapet Wall Beams 1. Columns and Shear Wall Concrete 100% Completed 2. Beam and Slab Concrete 100% Completed 3. Painting 75% In Progress
(Right Elevation Side) (Rear Elevation Side)
(GF – Entrance Lobby Ceiling Grid and Lobby Plastering)
(Mezzanine Floor Corridor marble flooring) (3rd Parking – Lift lobby marble flooring)
(Parking Area – Front Elevation aluminum cladding work and lovers fixing)
(4th Parking – Iso Board fixing for lift lobby and staircase wall on progress)
(Rebar’s fixing for roof diamond support additional beam)
(Inspection for Cantilever Platform for Roof Parapet level Diamond) (Parking Area – Paint Preparation for epoxy flooring) (Cement board partition between offices)