FORBES TOWER PROGRESS REPORT About the Project: Project Developer Bin Faqeeh Real Estate Investment Company S.P.C. Title of Project Forbes Tower Project Reference BFFB/14/0105-3105/2016 Design & Supervision Consultant Arab Architects Interior Design Consultant Horizon Interiors Main Contractor United Arab Construction Company (U.A.C.C.) About Progress Report: Title of Document Progress Report of Forbes Tower Reporting Period May 1, 2017 to May 31, 217 Authors & project role United Arab Construction Company (U.A.C.C.) Date June 21, 2017

FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

FORBES TOWER PROGRESS REPORT About the Project:

Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.

Title of Project Forbes Tower

Project Reference BFFB/14/0105-3105/2016

Design & Supervision Consultant

Arab Architects

Interior Design Consultant

Horizon Interiors

Main Contractor United Arab Construction Company (U.A.C.C.)

About Progress Report:

Title of Document Progress Report of Forbes Tower

Reporting Period May 1, 2017 to May 31, 217

Authors & project role United Arab Construction Company (U.A.C.C.)

Date June 21, 2017

Page 2: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

DESCRIPTION PERCENTAGE

(%) OF COMPLETION

REMARKS

MOBILIZATION

1. Fencing 100% Completed 2. Site Offices (Consultant Engineer) 100% Completed 3. Car Park 100% Completed 4. Site Offices (Contractors) 100% Completed 5. Labour rest room & Toilets 100% Completed 6. Store Room 100% Completed 7. Signboard Works 100% Completed

SUPER STRUCTURE

1. Piling Works 100% Completed 2. Pilecap Concrete Works 100% Completed 3. Tile beam Concrete Work 100% Completed 4. Backfilling for grade slab 100% Completed 5. Grade Slab Concreting works 100% Completed

SUB STATION 1. Concreting Works 100% Completed 2. Rough Finish 100% Completed 3. Final Finish 100% Completed 4. Handing Over 100% Completed

SUPER STRUCTURE Ground Floor (+0.800 LVL)

1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 90% In Progress 4. Internal Plastering 60% In Progress 5. Epoxy Painting on floor 20% In Progress

Mezzanine Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Epoxy Painting on floor 30% In Progress

1st Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed

Page 3: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

4. Internal Plastering 100% Completed 5. Marble Floor Tiles fixing 50% In Progress 6. Epoxy Painting on floor 30% In Progress

2nd Floor Parking 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Epoxy Painting on floor 30% In Progress

4. Block Work 100% Completed

5. Internal Plastering 100% Completed 6. Marble Floor Tiles Fixing 100% Completed

3rd and 4th Parking Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 30% In Progress 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Marble Cladding Fixing in Walls 85% In Progress 7. Marble Floor Tiles Fixing 100% Completed

1st Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 95% In Progress 8. Marble Cladding Fixing in walls 100% Completed 9. Marble Floor Tiles Fixing 100% Completed

2nd to 6th Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 90% In Progress 9. Marble Floor Tiles Fixing 100% Completed

7th Typical Floors 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed

Page 4: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Mable Cladding fixing in walls 95% In Progress 9. Marble Floor Tiles Fixing 100% Completed

8th to 28th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Ceramic Floor Tiles Fixing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 100% Completed 9. Marble Floor Tiles Fixing 100% Completed

29th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 60% In Progress 9. Marble Floor Tiles Fixing 100% Completed

30th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Floor Tiles Fixing 100% Completed 7. Ceramic Wall Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 40% In Progress 9. Marble Floor Tiles fixing 100% Completed

31st to 32nd Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed

Page 5: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 95% In Progress 8. Marble Floor Tiles Fixing 100% Completed

33rd Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 90% In Progress 9. Marble Floor Tiles Fixing 100% Completed

34th to 35th Typical Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Block Work 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Ceramic Wall Tiles Fixing 100% Completed 7. Ceramic Floor Tiles Fixing 100% Completed 8. Marble Cladding fixing in walls 9. Marble Floor Tiles Fixing 100% Completed

Gymnasium Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed

Roof Floor 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Painting 75% In Progress

Lift Machine Room Slab 1. Column & Shear Wall Concrete 100% Completed 2. Beam & Slab Concrete 100% Completed 3. Blockwork 100% Completed 4. Internal Plastering 100% Completed

Page 6: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

On-site Photos: cv \

(Front Side Elevation) (Left Side Elevation)

5. Painting 75% In Progress Head Room for Machine Room & Staircase, Head Roof for Staircase 2

1. Column & Shear Wall Concrete 100% Completed 2. Beam and Slab Concrete 100% Completed 3. Parapet Blockwork 100% Completed 4. Internal Plastering 100% Completed 5. Wet Area Waterproofing 100% Completed 6. Painting 90% In Progress

Parapet Wall Beams 1. Columns and Shear Wall Concrete 100% Completed 2. Beam and Slab Concrete 100% Completed 3. Painting 75% In Progress

Page 7: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

(Right Elevation Side) (Rear Elevation Side)

(GF – Entrance Lobby Ceiling Grid and Lobby Plastering)

Page 8: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

(Mezzanine Floor Corridor marble flooring) (3rd Parking – Lift lobby marble flooring)

(Parking Area – Front Elevation aluminum cladding work and lovers fixing)

(4th Parking – Iso Board fixing for lift lobby and staircase wall on progress)

Page 9: FORBES TOWER PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFFB.pdf · SUPER STRUCTURE 1. Piling Works 100% Completed 2. Pilecap Concrete Works

(Rebar’s fixing for roof diamond support additional beam)

(Inspection for Cantilever Platform for Roof Parapet level Diamond) (Parking Area – Paint Preparation for epoxy flooring) (Cement board partition between offices)