] 31 January 2011 QUARTERLY ACTIVITIES REPORT December 2010 Highlights Iron Ore Further drilling at Mt Webber planned by JV manager, Atlas Iron during 2011, which is expected to significantly increase the ore reserve estimations Coal Mining approvals process continues at Tabalong Coal Project. Further assessment and planning for product coal transport and route approval continued in preparation for coal production. Lithium Field mapping work undertaken in the quarter in preparation for drilling in Q1 2011 A follow up drilling program commenced in January 2011 to establish the extent and the resource potential of this highly mineralised spodumene pegmatite. Garnet Review of mine plan and mining method to address a strengthening Australian Dollar Altura Mining Limited Australian Project Locations For personal use only

For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Embed Size (px)

Citation preview

Page 1: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

]

31 January 2011

QUARTERLY ACTIVITIES REPORT December 2010

Highlights 

Iron Ore 

Further drilling at Mt Webber planned by JV manager, Atlas Iron during 2011, which is expected to significantly increase the ore reserve estimations 

Coal 

Mining approvals process continues at Tabalong Coal Project.  

Further assessment and planning for product coal transport and route approval continued in preparation for coal production. 

Lithium 

Field mapping work undertaken in the quarter in preparation for drilling in Q1 2011 

A follow up drilling program commenced in January 2011 to establish the extent and the resource potential of this highly mineralised spodumene pegmatite.    

Garnet 

Review of mine plan and mining method to address a strengthening Australian Dollar 

Altura Mining Limited – Australian Project Locations 

For

per

sona

l use

onl

y

Page 2: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 2 of 12

IRON ORE  MT WEBBER (Pilbara – Western Australia) 30% Altura Mining Limited, 70% Atlas Iron Limited  The Mt Webber Iron Ore Project is located 150 kilometres south‐southeast of Port Hedland in the world’s  premier  iron  ore  province,  the  Pilbara.    It  is  approximately  40  kilometres  east  of  the Fortescue Metals Group railway  line and  immediately north of Woodstock Road, which connects Marble Bar to the Great Northern Highway (see Figure 1).  Altura  has  a  30%  interest  in  the  Mt  Webber  Iron  Ore  DSO  project  (and  five  other  Pilbara tenements that form part of the joint venture agreement) in the Pilbara.  Atlas Iron is Altura’s joint venture partner for this project.  Under the terms of the agreement, Altura remains the owner of the Mt Webber and other tenements, totalling 333 square kilometres.  

Figure 1 – Mt Webber DSO Project Location                                 

For

per

sona

l use

onl

y

Page 3: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 3 of 12

The project has the potential to be developed either as a stand‐alone operation, or as a satellite mine delivering run‐of‐mine ore to a central processing facility.  Atlas currently operates iron ore mines  at  Wodgina  and  Pardoo  and  will  provide  expertise  in  the  development  and  eventual operation of Mt Webber.  Atlas  as  the managing partner had planned  to  complete  (by Q4 2010)  further drilling  aimed at upgrading  further Mineral Resources  to Ore Reserves, however due  to delays  this work  is now expected to complete by end of Q1 2011 (see Figure 2 below).  

Figure 2 – Reserve, Resource and Prospect Location, Mt Webber DSO Project                           In December 2010 Atlas announced a recommended off‐market takeover offer for all of the shares in Giralia Resources (ASX: GIR).   Giralia own 75% of the Daltons DSO Joint Venture neighbouring Mt Webber along with other Pilbara iron ore prospects.  Atlas has indicated to Altura that at this stage  there  is  no  planned  change  to  Atlas’  previously  announced  development  schedule  of commencing production at the Mt Webber Iron Ore Project in 2012.        

For

per

sona

l use

onl

y

Page 4: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 4 of 12

COAL  TABALONG (South Kalimantan – Indonesia) Thermal Coal (100% AJM)   The  Tabalong  Coal  Project  consists  of  two  (2) Mining  Licences  (IUPs)  in  the  province  of  South Kalimantan on the island of Borneo.  Currently both IUPs are granted for exploration purposes and Altura is seeking the necessary approvals to have them granted for operation production status.  Altura is awaiting grant of the two (2) Mining Licences in accordance with the current legislation.  The  pre‐requisite  documentation  required  for  grant  consisting  of  the  Environmental  Impact Statement and the Government Feasibility Study has been submitted to both Regency Councillor and Mines Department.   The documents have been approved  in principle and now await formal submission  to support operational approval, however  there  is no definitive  timeframe  for  these approvals.   Subsequent  to operational approval  the Company will be  required  to gain clearance from  the Minister of Forestry prior  to commencement however  the project does not cover any protected forest areas.  During the quarter further assessment and planning for product coal transport and route approval has continued in preparation for coal production.  Currently two (2) options remain with the first entailing  approximately  120km  haul  to  an  offload  point  in  the  Barito  River, whilst  the  second entails an approximately 25km haul to a discharge point to another mining entity.  The current cost of production estimate (FOB barge) is US$60 per tonne for the 120km haul option however a reduction of US$13 per tonne  is forecast  if the shorter route  is chosen.   Thermal coal prices have firmed in Indonesia during the quarter with price yields greater than US$90 per tonne for Tabalong grade coal being achieved.  The Company aims to develop Tabalong as a stand‐alone operation  initially at a planned annual production  rate of 300,000  to 400,000  tonnes per annum of premium  thermal grade coal.   The location of the Tabalong project also lends itself to satellite development of other mining permits.  The  area  consists  of  numerous  other  smaller  resource  areas  that  have  the  potential  to  be operated  simultaneously  to  provide  increased  tonnages  and  blended  coal  products.    Altura  is considering  a  number  of  potential  adjacent  projects  that  could  be  amalgamated  into  the development.  COAL ‐ Indonesia   During  the  quarter,  Altura  continued  to  source  and  review  a  number  of  other  potential  coal acquisitions  in  Indonesia.    Following  an  extensive  review,  a  short  list  of  potential  targets was compiled  and  discussions  are  continuing with  a  number  of  parties.    The  Company will  inform shareholders  and  the market  if  an  agreement  can  be  reached  and  remains  confident  that  a suitable coal project can be delivered in 2011.  About Thermal Coal  Thermal  coal  forms  the  backbone  of worldwide  energy  supplies with  Indonesia  now  the world’s  largest exporter of thermal coal products.  Recent innovations in coal beneficiation and clean coal technology point toward a strong future for coal to remain a reliable energy generation commodity. 

For

per

sona

l use

onl

y

Page 5: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 5 of 12

LITHIUM  PILGANGOORA (Western Australia) Lithium, Tantalum (100% AJM)    The Pilgangoora project is located approximately 120 kilometres to the south east of Port Hedland and  is  readily  accessible  from  the  Port  Hedland  ‐  Newman  Road  (see  Figure  1).    The  Talison Minerals Wodgina tantalum mine is located about 25 kilometres to the west of the project area.  During mid 2010 Altura undertook a Reverse Circulation (RC) drilling program at its wholly owned Pilgangoora Lithium Project  in the Pilbara region of Western Australia.   The drilling comprised 28 holes for a total of 1,510 metres and targeted three (3) areas (A, B and C) that were identified by geological mapping, rock chip sampling and costeaning (see Figure 4).  This initial drilling revealed relatively narrow width pegmatites in areas A and C however area B is considered  to  be  highly  prospective  with  significantly  elevated  lithium  mineralisation  and substantial  thicknesses  of  spodumene  pegmatite.    Updated  results  reported  during  November 2010  included  drill  hole  PRC  027  intersected  60  metres  (end  of  hole)  of  an  average  1.65% downhole, drill hole PRC028 assayed 51m @ 1.77% Li2O and drill hole PRC022 an aggregated 22 metres @ 1.31% Li2O.  Table 1 below summarises these results.  

Table 1 – Pilgangoora Drilling Results – Assays greater than 0.3% Li2O  

Area  Hole No. East 

GDA94 (m) 

North GDA94 (m) 

Dip/Az (Deg.) 

From (m) 

To     (m) 

Thickness (m) 

Li2O% 

A  PRC 011  697,232  7,669,126 ‐60/310  0  6  6  0.45% 

                 

B  PRC 026  697,368  7,668,677 ‐60/340  0  5  5  1.17% 

          6  23  17  1.45% 

        Including 7 metres @ 2.13% 

                 

B  PRC 027  697,380  7,668,675 ‐60/042  0  60  60  1.65% 

        Including 14 metres @ 2.00%  

        and 11 metres @ 2.06% 

                 

B  PRC 028  697,401  7,668,679 ‐60/360  5  56  51  1.77% 

        Including 4 metres @ 3.17% 

        and 5 metres @ 2.11% 

        and 9 metres @ 2.07% 

 Following  the  receipt of  these  significant assay  results Altura  fast  tracked  its application  for  the adjacent tenement, Prospecting Licence PL45/2758, and this was granted on 29 October 2010.  The Department of Minerals and Petroleum (DMP) also advised on 13 September 2010 that it had granted the amalgamation  into E45/2287 of the dead mining tenements M45/334 and M45/335.  The  incorporation  of  these  areas  considerably  extends  the  area  available  for  exploration  and possible extensions to known lithium‐bearing pegmatites. 

For

per

sona

l use

onl

y

Page 6: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 6 of 12

In December 2010 Altura completed  field mapping within the area of the mineralised drill holes and identified areas of pegmatite outcrop intruded into the mafic schist greenstone rocks over an area covering 200 metres in an east‐west direction and 150 metres in a north‐south direction.  In order  to establish  the orientation of  the pegmatites and  their depth extent a  follow up drilling program has  commenced early  in  January 2011.   Approval  for  the  current drilling program was received in early December 2010.   Figure 3 below shows the current pegmatite target area along with a diagrammatic cross section through the initial target area.  

Figure 3 – Diagrammatic Cross Section – Resource Evaluation Drilling    

                                    

For

per

sona

l use

onl

y

Page 7: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 7 of 12

Figure 4 – Pilgangoora Prospect Areas A, B and C, Planned Drill Holes January 2011 and August 2010 drill hole locations 

           

For

per

sona

l use

onl

y

Page 8: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 8 of 12

The results from this work will provide the basis of determining the  inferred  lithium resources  in this one prospect area and provide a basis for extending exploration to other areas where there are comparable geological lithologies and structure.   The results from the current program are expected to be announced in Q1 2011.  FINNISS RANGE (Northern Territory) Lithium, Tantalum (100% AJM)   Altura  has  undertaken  regional  and  prospect  geochemical  evaluation  studies  and  a  number  of areas have been identified for more detailed follow up with drilling.  In June 2010 Altura submitted a Mine Management  Plan  (MMP)  to  the  Northern  Territory  Department  of  Resources  for  the proposed drilling of the 7 Up prospect, however there were delays in getting all the pre‐requisite planning approvals and existing commitments of Altura’s drilling rig.  It is planned that this drilling be included in the programs for the 2011 field season which will commence in April ‐ May 2011.  About Lithium  Lithium  (Li)  is  recovered  from  the mineral  spodumene  and  lithium‐rich  brines.  It  is  used  in  a  range  of products such as ceramics, glass, batteries and pharmaceuticals. Lithium use has expanded significantly  in recent years due to  increasing use  in rechargeable batteries  in portable electronic devices and  in batteries and electric motors for hybrid and electric cars.   

GARNET  BALLINE (Western Australia) Alluvial Garnet Mineral Sands (100% AJM)   The  Balline  Garnet mineral  sands  project was  reviewed  by  the  Board  of  Directors  during  the quarter with  an  objective  of  determining whether  to  continue  to  pursue  development  of  the project.    The  results  of  the  review  revealed  that  the  project  could  operate  to  produce  an economically positive cashflow but  the  impacts of  the appreciating Australian Dollar provided a considerable challenge.  The Balline Project Team  remain  focussed on producing a  suitable mine development plan and schedule  to  deliver  a  suitable  grade  garnet  required  for  positive  returns  from  the  proposed operation.   This will  involve further mine scheduling and mining method evaluation studies to be completed as soon as practicable.  Statutory  approvals  relating  to  the Mining  Proposal  and  the  5C  license  application  for  water extraction are still outstanding but expected during Q1 2011.   About Garnet  Garnet is a naturally occurring material that is mined in a similar method to mineral sands.  Garnet sand is a good abrasive and a common replacement  for silica sand  in sand blasting. Mixed with very high pressure water, garnet is used to cut steel and other materials in water jets. 

  

For

per

sona

l use

onl

y

Page 9: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 9 of 12

URANIUM  LONG ISLAND (Mt Shoobridge – Northern Territory) Uranium (100% AJM)   The  permitting  and  ground  clearance  for  the  drilling  of  this  Long  Island  uranium  prospect was undertaken during the December 2010 quarter, however with the early onset of the wet season and  a  delay  in  securing  the  drilling  rig  suitable  to  undertake  this work,  Altura  has  reluctantly postponed  the drilling until  the end of  the wet season.   The evaluation of  this exciting uranium prospect is a high priority one for Altura and will be undertaken as soon as access conditions will allow.  

Figure 5 – Long Island Uranium Prospect – Uranium contours shown on satellite imagery                            

BASE AND PRECIOUS METALS  SHOOBRIDGE (Mt Shoobridge – Northern Territory) Lead, Copper. Zinc, Silver, Gold (AJM 100%)  The exploration for base and precious metals (mainly copper, lead, zinc, silver and gold) within the Mt  Shoobridge  project  was  advanced  considerably  in  the  latter  part  of  2009  following  the completion of an airborne VTEM (Versatile Time Domain Electromagnetic) survey.  The processing and  imaging  of  this  data  produced  a  number  of  target  areas  that  were  interpreted  to  be 

For

per

sona

l use

onl

y

Page 10: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 10 of 12

prospective  for  base  and  precious  metals  including  the  Full  Hand,  Kultha,  Phillip  Greets, Shoobridge and Long Island North.    A summary of the work completed to date is as follows: 

 Full Hand Prospect – The planned third hole was not drilled on the basis that the VTEM anomaly represented the same target and that comparable results would be obtained.  No further work is planned for this prospect area.  Kultha Prospect – The VTEM survey identified about seven discrete areas that were shown to have surface geochemical anomalism – particularly  for copper  lead and zinc.    In September / October 2010  four  reverse  circulation  drillholes  were  completed  on  two  of  the  VTEM  conductors  to establish  the source and base metal prospectivity.   Three of  the  four holes  intersected graphitic sediments with elevated  lead,  zinc,  copper and arsenic values and  confirmed  the  source of  the VTEM  conductor,  however  the  tenor  of  the  base metal  values were  not  considered  to  be  of significance.  Shoobridge Prospect – As  reported  in  the previous quarter one 40m hole was drilled  to  test a moderate VTEM conductor to the east of the main Shoobridge gold and base metal prospect.  The hole  intersected  graphitic  and  pyritic  meta‐sediments  with  assay  samples  recording  elevated values for gold, lead, zinc and arsenic.  No further work is planned for this prospect.   

Figure 6 – Mt Shoobridge Project – Tenements, Geology and Prospect Locations 

         

    

       

     

For

per

sona

l use

onl

y

Page 11: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 11 of 12

MINING SERVICES  The Indonesian mining services division has produced revenues of US$4.1 million for the first half of the financial year and remain on target for annual revenue of between US$8 to US$9 million.  INDONESIA (PT Asiadrill Bara Utama) (100% AJM)  The mining service group of Asiadrill Bara Utama  (Asiadrill) and Velseis  Indonesia  (Velseis – 50% Altura) continued exploration  support  services during  the quarter.   The drilling operations were confined to Indonesia with a primary focus in coal exploration and development.  Drill rig deployment further increased during the quarter via new contract awarding and expansion of drill units existing contracts.  Asiadrill operated up to twenty (20) individual drill units consisting of track and skid mounted and man portable units during the quarter.  Asiadrill  has  equipment  deployed  in  South  and  East  Kalimantan  on  the  island  of  Borneo with offices in Jakarta (West Java), Balikpapan (East Kalimantan) and Tanjung (South Kalimantan).  About PT Asiadrill Bara Utama 

 Asiadrill operates a varied  fleet of  truck and  track mounted drills; supplemented by a  fleet of heli‐lift and man‐portable units for environmentally sensitive areas.  The current fleet totals sixteen (16) larger units and fifteen (15) man‐portable drills.  Asiadrill’s predominantly Indonesian workforce totals 48 permanent and up to 150 contract staff. 

 INDONESIA (PT Velseis Indonesia) (50% AJM)  Velseis  Indonesia (Veleis  ‐ 50% Altura) operated up to eight (8) wireline units during the quarter out  of  a  total  fleet  of  eleven  (11)  units.    Velseis  has  operated  primarily  in  East  and  South Kalimantan provinces on the island of Borneo.  Velseis continues to partner Asiadrill on a number of projects to provide clients with both drilling and geophysical services on their coal exploration projects.  About PT Velseis Indonesia 

 Velseis Indonesia is joint venture company between Altura and Velseis Pty Ltd (Brisbane based wireline and seismic  service  provider).   Velseis  operates  a  fleet  of  eleven  (11)  portable  and  vehicle mounted wireline logging units in Indonesia.  The Velseis Indonesian workforce totals 24 permanent staff. 

 AUSTRALIA (Altura Drilling Pty Ltd) (100% AJM)  Early in the quarter the Maxdrill 2000 multipurpose drill was utilised at the Mt Shoobridge Project in the Northern Territory.  More recently, the rig has been redeployed to the Pilgangoora Lithium Prospect  in Western Australia’s Pilbara region, and  it will continue  in  this role during  the March quarter 2011.     

For

per

sona

l use

onl

y

Page 12: For personal use only - ASX · Altura Mining Limited – Australian Project Locations For ... good abrasive and a common replacement for silica sand in sand blasting. Mixed with very

Altura Mining Limited – Quarterly Activities Report December 2010     

 

Page 12 of 12

 About Altura Mining Limited (ASX:AJM)  Altura has a diverse mineral portfolio  in Australia and  Indonesia  coupled with  cash  flow positive mining services units  in  Indonesia.    The  company aims  to  systematically  evaluate and develop  the  key  resource projects commencing with Balline Garnet and Mt Webber JV (30% Altura / 70% Atlas Iron Limited).  Key Projects and Prospects: 

Iron Ore:  Mt Webber DSO Joint Venture (30% Altura). 

Coal:  Tabalong Coal Project – South Kalimantan, Indonesia – mining approval process underway. 

Garnet:  Balline Mineral Sands Project WA, mining approvals in progress. 

Lithium:  Pilgangoora Prospect WA, Finniss Range Prospect NT – exploration stage. 

Uranium:  Mt Shoobridge NT, exploration stage with key uranium targets in Hayes Creek region. 

Base/Precious Metals:   Mt Shoobridge NT,  lead, copper, zinc, gold and silver prospect at exploration stage. 

 For additional information about Altura, please visit the Company’s website www.alturamining.com   

 COMPETENT PERSONS STATEMENTS 

 Pilgangoora (WA)  The information in this report that relates to the Pilgangoora exploration results is based on information compiled by Mr Bryan Bourke, who  is a member of  the Australian  Institute of Geoscientists and a  full‐time  employee of Altura Mining Limited.   Bryan Bourke has sufficient experience, which  is  relevant  to  the style of mineralisation and  type of deposit under consideration and  to  the activity he  is undertaking,  to qualify as a Competent Person  in  terms of  the ‘Australasian  Code  for  Reporting  of  Exploration  Results,  Mineral  Resources  and  Ore  Reserves’  (JORC  Code  2004 Edition).  Bryan Bourke consents to the inclusion of such information in this Report in the form and context in which it appears.  Shoobridge and Finniss Range (NT)  The  information  in  this  report  that  relates  to  the  Shoobridge  and  Finniss  Range  exploration  results  is  based  on information compiled by Mr Bryan Bourke, who is a member of the Australian Institute of Geoscientists and a full‐time employee  of  Altura  Mining  Limited.  Bryan  Bourke  has  sufficient  experience,  which  is  relevant  to  the  style  of mineralisation and type of deposit under consideration and to the activity he is undertaking, to qualify as a Competent Person  in terms of the  ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code 2004 Edition).   Bryan Bourke consents to the  inclusion of such  information  in this Report  in the form and context in which it appears. 

  

For further information, please contact: 

James Brown, Managing Director       Ph: + 61 7 3814 6900 

Paul Mantell, Executive Director       Ph: + 61 7 3814 6900 

  