32
RIU GOOD OIL CONFERENCE 2015 3 September 2015 For personal use only

For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

RIU GOOD OIL CONFERENCE 2015 3 September 2015 F

or p

erso

nal u

se o

nly

Page 2: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

§  This presentation does not constitute investment advice. Neither this presentation not the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in Elk Petroleum Ltd – ABN (the “Company”) - in any jurisdiction.

§  Shareholders should not rely on this presentation. This presentation does not take into account any person’s particular investment objectives, financial resources or other relevant circumstances and the opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.

§  The information set out in this presentation does not purport to be all inclusive or to contain all the information which its recipients may require in order to make an informed assessment of the Company. You should conduct your own investigations and perform your own analysis in order to satisfy yourself as to the accuracy and completeness of the information, statements and opinions contained in this presentation.

§  To the fullest extent permitted by law, the Company does not make any representation or warranty, express or implied, as to the accuracy or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of the negligence or otherwise is accepted.

§  This presentation may include forward looking statements. Forward looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of the Company. These risks, uncertainties and assumptions include commodity prices, currency fluctuations, economic and financial market conditions in various countries and regions, environmental risks and legislative, fiscal or regulatory developments, political risks, project delay or advancement, approvals and cost estimates.

§  Actual values, results or events may be materially different to those expressed or implied in this presentation. Any forward looking statements in this presentation speak only at the date of issue of this presentation. Subject to any continuing obligations under applicable law and the ASX Listing Rules, the Company does not undertake any obligation to update or revise any information or any of the forward looking statements in this presentation or an changes in events, conditions or circumstances on which any such forward looking statement is based.

§  The reserves and resources assessment follows the guidelines set forth by the Society of Petroleum Engineers – Petroleum Resource Management System (SPE-PRMS).

§  The Reserves and Contingent Resources in this announcement relating to the Grieve CO2 EOR project, operated by Denbury Resources, is based on an independent review and audit conducted by Pressler Petroleum Consultants, Inc. and fairly represents the information and supporting documentation reviewed. The review and audit was carried out in accordance with the SPE Reserves Auditing Standards and the SPE-PRMS guidelines under the supervision of Mr. Grant Olsen, a Director of Pressler Petroleum Consultants, Inc., an independent petroleum advisory firm. Mr. Olsen is a Registered Professional Engineer in the State of Texas and his qualifications include a Bachelor of Science and Master of Science (both in Petroleum Engineering) from Texas A&M University. He has more than 10 years of relevant experience. Mr. Olsen is a member of the Society of Petroleum Engineers (SPE) and an Associate Member of the Society of Petroleum Evaluation Engineers. Mr. Olsen meets the requirements of Qualified Petroleum Reserve and Resource Evaluator as defined in Chapter 19 of the ASX Listing Rules and consents to the inclusion of this information in this report.

§  The information in this presentation that relates to Reserve and Contingent Resources estimates for the Grieve CO2 EOR project and the Contingent Resource estimates for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of Elk Petroleum USA who is a qualified person as defined under the ASX Listing Rule 5.11 and has consented to the use of the reserves figures in the form and context in which they appear in this presentation. Mr. Dolan is a full-time employee of the company. Mr. Dolan earned a degree in Mechanical Engineering from the University of Colorado at Boulder and has more than 23 years of relevant experience. Mr. Dolan has sufficient experience that is relevant to the company’s Reserves and Resources to qualify as a Reserves and Resources Evaluator as defined in the ASX Listing Rules. Mr. Dolan consents to the inclusion in this presentation of the matters based on the information in the form and context in which it appears

2

Disclaimer & Important Notice F

or p

erso

nal u

se o

nly

Page 3: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Who are we?

§  Only ASX-listed, Enhanced Oil Recovery (EOR) company with 10-years focused EOR experience

§  Strong leadership team with proven track record of value creation

§  Focused on oil field redevelopment in North American proven EOR production fairways

§  Oil price pressures presents a unique opportunity for low-cost asset accumulation

§  Substantial growth potential within core EOR production fairways

§  Potential for Elk to acquire up to 100% ownership and operatorship of Grieve Project

§  Longer-term growth strategy of applying EOR in largely untapped areas of Australia, Indonesia and Malaysia

3

Miro Advisors appointed to assist with targeting potential acquisitions and associated financing

For

per

sona

l use

onl

y

Page 4: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Corporate Summary

Capital Structure ASX code ELK

Ordinary Shares 201.1m

52-week Low-High (A$ cps) 0.02-0.12

Market cap @ 12cps A$24m

Enterprise Value (USD 1: AUD 0.73) A$43m

Cash (30 June 2015) A$1.6m

Reserves + Resources (2P+2C) ~6.5 mmbls

Elk one-year share price chart 12-months ending 28 August 2015

Major shareholders Robert Healy 20.85%

HSBC (Including Republic Investment Management)

10.89%

Begley Superannuation 8.98%

Board & Management 3.4% - Pre Placement 7.0% - Post Placement

0

0.02

0.04

0.06

0.08

0.1

0.12

Grieve EOR Project - CO2 injector facility

4

For

per

sona

l use

onl

y

Page 5: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Enhanced & Improved Oil Recovery EOR & IOR

5

For

per

sona

l use

onl

y

Page 6: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

What is EOR / IOR ?

§  Specialised oil recovery methods

§  Secondary – Improved Oil Recovery

§  Tertiary – Enhanced Oil Recovery

§  Proven technology since 1960s

§  Extracts up to 40% of original oil in place (OOIP)

§  Substantially increases oil field life

§  Attractive economics in low oil price

§  Used extensively in North America and the Middle East

§  Largely under-utilised in Australasia

20-­‐25%

10-­‐20%

10-­‐20%

35-­‐60%

Overall  Oil  Recovery

Primary  Recovery Secondary  Recovery  -­‐  IOR

Tertiary  Recovery  -­‐  EOR Remaining  Oil

Our Focus

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

6

For

per

sona

l use

onl

y

Page 7: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Primary & Secondary Oil Recovery Processes

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

CONVENTIONAL OIL RECOVERY PROCESS

PRIMARY OIL RECOVERY Natural Reservoir Drive Mechanisms

SECONDARY OIL RECOVERY

Rock/Liquid Expansion

Depletion Drive

Gas Cap Drive

Water Drive

Gravity Drainage

Combination Drive

Waterflooding

Immiscible Gas Injection

7

For

per

sona

l use

onl

y

Page 8: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Primary & Secondary Oil Recovery Processes

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

CONVENTIONAL OIL RECOVERY PROCESS

PRIMARY OIL RECOVERY Natural Reservoir Drive Mechanisms

SECONDARY OIL RECOVERY

Rock/Liquid Expansion

Depletion Drive

Gas Cap Drive

Water Drive

Gravity Drainage

Combination Drive

Waterflooding

Immiscible Gas Injection

Most efficient natural drive

Most widely applied secondary

8

For

per

sona

l use

onl

y

Page 9: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Tertiary Oil Recovery Process – EOR

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

EOR Processes

Miscible Gas

Injection

Thermal

Chemical

Other

Mobility Control

CO2 Flood

Flue Gas

LPG

Enriched Gas

High Pressure Gas

Nitrogen

Steam Flood

In-situ Combustion

Surfactant Flooding

Alkaline or Caustic Flood

Rock Effective Permability Reduction

Polymer Augmented Waterflood

Microbial EOR

Mechanical

Electrical

Chemical Leaching

In-situ Conversion

9

A broad array of tools!

For

per

sona

l use

onl

y

Page 10: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Tertiary Oil Recovery Process – EOR

Source: Advances in Enhanced Oil Recovery Processes – Romero-Zeron – University of New Brunswick (2012)

10

EOR Processes

Miscible Gas

Injection

Thermal

Chemical

Other

Mobility Control

CO2 Flood

Flue Gas

LPG

Enriched Gas

High Pressure Gas

Nitrogen

Steam Flood

In-situ Combustion

Surfactant Flooding

Alkaline or Caustic Flood

Rock Effective Permability Reduction

Polymer Augmented Waterflood

Microbial EOR

Mechanical

Electrical

Chemical Leaching

In-situ Conversion

ELK experience

CO2 EOR - Most efficient approach

For

per

sona

l use

onl

y

Page 11: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

How does CO2 EOR work?

§  Known as ‘Green Oil’ as it can deliver carbon negative oil

§  Most commonly-used form of EOR

§  Most efficient EOR – recovers most oil

§  Accounts for ~60% of US EOR production

§  CO2 often sourced from natural deposits

§  CO2 can be supplied from man-made sources

§  Only profitable form of carbon capture & storage (CCS) without subsidy

Secure CO2 supply

Transport via pipeline

or truck Inject into

oil field

Putting a cost on carbon emissions will only further enhance CO2 EOR potential

11

For

per

sona

l use

onl

y

Page 12: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Current Projects

12

For

per

sona

l use

onl

y

Page 13: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Overview

ELK PROJECTS

Grieve Singleton

Location of current CO2 EOR projects and pipeline infrastructure Source: NETL 2010

13

For

per

sona

l use

onl

y

Page 14: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Where we are….

14

For

per

sona

l use

onl

y

Page 15: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

And the CO2 Resource & Infrastructure….

15

For

per

sona

l use

onl

y

Page 16: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Flagship Grieve Oil Field CO2 EOR Development

16

For

per

sona

l use

onl

y

Page 17: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

§  Elk currently holds 35% interest

§  Opportunity to acquire Operator’s 65% interest and resume full Project ownership

§  Miro Advisors appointed to assist with acquisition & financing

§  Estimated Gross Project Cost = ~US$125m §  Investment to date = ~US$70m §  Elk remaining CAPEX to First Oil = ~US$12-13m

§  Project approximately 70%+ complete

§  Most major production facilities complete with only CO2 Recycling Facility to be completed

§  First oil targeted for Q1 CY2017

§  CO2 supply contract with ~60% injected necessary to reach first oil production

§  Attractive economics and material cash flow

Grieve CO2 EOR Project - Overview

Source: Elk ASX Release 29 January 2015 – Grieve Reserve Update

Reserve Summary at 31 December 2014

Scenario Net Oil to Elk (Mbbls)

Capital Expenditures (US$MM)

2P (Probable Reserves) 3,455 25.8

3P (Probable + Possible Reserves) 4,660 22.4

3C (Contingent Resources) 4,685 21.1

Source: Elk ASX Release 29 January 2015 – Grieve Reserve Update

100

1,000

10,000

Gross  Oil  Ra

te,  B

bls/D

Time,  Years

Grieve  -­‐  3C

Grieve  -­‐  3P

Grieve  -­‐  2P

17

For

per

sona

l use

onl

y

Page 18: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Grieve CO2 EOR Project – A Field-level View

* Based on Elk’s own estimates

CO2 INJECTORS / WATER INJECTORS

FEET

2,0470

PRODUCERS

10 Existing wells

8 New Wells

9 Existing Wells

2 New Wells

Central Facilities Location - Office - Power - Oil storage - Processing & compression - Distribution and gathering manifold centre

Elk 100% owned crude oil export pipeline

to Casper

CO2 Metering Station

18

For

per

sona

l use

onl

y

Page 19: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Grieve CO2 EOR Project – Activities

19

§  Work Completed §  New injection and production wells

§  In-field CO2/water injection& Oil production flow lines

§  Power supply from local grid installed

§  Site works & production manifold

§  3-mile CO2 supply line

§  Crude oil export pipeline upgrade

§  Reservoir re-pressurising §  10+ million barrels of water injected

§  17+ Bcf of CO2 injected

§  Est 30 BCF CO2 required to achieve first oil

§  Currently injecting CO2 at 40 MMCFD

§  Reservoir pressure rising in line or ahead forecast

§  Remaining Steps to First Oil §  Construction of oil processing & CO2

recompression facilities

§  Continue injection of water and CO2 to re-pressurise the reservoir F

or p

erso

nal u

se o

nly

Page 20: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Singleton Oil Field CO2 EOR Development

20

For

per

sona

l use

onl

y

Page 21: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Singleton Oil Field – Overview

§  100% Elk-owned & operated project

§  Located in oil-prolific Denver-Julesburg Basin

§  Targeting same excellent quality sands as in Grieve Project

§  Setting ideal for CO2-oil miscibility

§  Modest acquisition cost – less than $500k

§  Utilise existing wells for field redevelopment

§  Expect rapid response to injected CO2

§  Field in close proximity to CO2 supply source

§  Potential development on near-by satellite fields to improve overall economics

Singleton Base Case Reserves – Development Case MI3

(2014)

Resources – 2C (mmbbls) 3.0

Gross Project Investment (US$ million) 48

Capex + Opex (US$/bbl) 42

F&D (US$/bbl) 15

Undiscounted PV (US$ million) 47

Undiscounted PIR 1.0

Discounted PV10% (US$ million) 10

Discounted PIR 0.2

IRR% 15 See Elk Corporate Presentation of 10 August 2015 page 42 for reference to oil price forecast used in economic analysis

21

For

per

sona

l use

onl

y

Page 22: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Singleton AOI CO2 EOR Development Hub

§  Area of Interest (AOI) has 10 oil fields

§  AOI Fields produced a combined 51 mmbbls

§  AOI Goal to develop 5 largest fields on a staged CO2 project

§  AOI Indicative CO2 EOR Potential 25 mmbbls

§  Potential Bridgeport CO2-source sufficient to supply AOI Hub

§  Development of CO2 EOR Hub markedly improves overall economics

Singleton

Bridgeport

22

For

per

sona

l use

onl

y

Page 23: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Corn Ethanol Producers – A Potential New Large-Scale CO2 Supply

POWDER RIVERBASIN

DENVER-JULESBURGBASINCOLORADO

WYOMING

NEBRASKA

SOUTH DAKOTA

KANSAS

MISSOURI

IOWA

MINNESOTA

WISCONSIN

ILLINOIS

MI

IOWA

MOVE CO2 WEST TO EOR OPPORTUNITIES IN PRB & DJB

Existing & planned CO2distribution pipeline

Corn-Ethanol Plants

Oil Fields

23

For

per

sona

l use

onl

y

Page 24: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Denver-Julesburg Basin – Significant Growth Area for Elk

§  DJ Basin has over 1000 oil fields (shown in yellow) in Colorado and Nebraska

§  Intensive drilling activity began in 1950

§  More than 52,000 wells drilled

§  Similar to Grieve Project:

§  Primary producing formation is the Lower Cretaceous Muddy (“J”) Sandstone

§  Conventional “J” sandstone reservoirs are stratigraphic traps

§  Water flooding of the “J” reservoirs began in the early 1960’s

§  Most fields are nearing end of secondary recovery efforts and approaching abandonment without EOR

DJ Basin is a mature oil basin that has not had any tertiary oil recovery projects

HA

RTV

ILLE

U

PLIF

T

105°00' 104°30' 104°00' 103°30' 103°00' 102°30'

DAWES

42°15'

Torrington SIOUX BOX BUTTE SHERIDAN

42°00' Wheatland SCOTTS BLUFF MORRILL GARDEN

41°45' PLATTE GOSHEN

BANNER

41°30' LARAMIE Horse Creek

Silo Chivington KIMBALL

41°15'

ALB

AN

Y Cheyenne

Borie WYOMING NEBRASKA CHEYENNE DEUEL

41°00' LARIMER WELD COLORADO LOGAN

Wellington SEDGWICK

40°45' PHILLIPSFort Collins Pierce Black Hollow Sterling

New Windsor 40°30' Windsor

Loveland Greeley MORGAN

Wattenberg 40°15' Brush

BOULDER Longmont Fort Morgan

Yuma 40°00' Boulder

Spindle Denver

Beecher 39°45' ADAMS

Island

ARAPAHOE WASHINGTON YUMA

39°30'

JEFF

ER

SO

N ELBERT LINCOLN KIT CARSON

Parker

Bethune0 10 20 30 MILES Castle Rock

39°15' 0 10 20 30 40 KILOMETERS DOUGLAS

2 Assessment of Undiscovered Oil and Gas in the Denver Basin Province

Figure 1. The northern two-thirds of the Denver Basin of Colorado, Nebraska, and Wyoming. Shown are oil (yellow-green), oil and gas (blue), and gas (red) wells across the basin. Major fields within the Front Range area are labeled (white text). The white line shows the northern and eastern boundaries of the study area. Western boundary is the approximate eastern limit of Precambrian rock exposures in the Rocky Mountain foothills. Vertical scales of the underlying digital elevation model (DEM) are 30 and 90 meters.

Bridgeport CO2 Supply

24

For

per

sona

l use

onl

y

Page 25: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Market Opportunity

25

For

per

sona

l use

onl

y

Page 26: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Global EOR Potential

BCC Research, August 2013

Global EOR market* •  Projected to grow at 8.8%

CAGR •  Estimated to be worth

$34.4bn by 2019

~40 bn barrels

~16 bn barrels

~40 bn barrels

~475 bn barrels

~11 bn barrels

~50 bn barrels

~58 bn barrels

~120 bn barrels

Source: Society of Petroleum Engineers

26

For

per

sona

l use

onl

y

Page 27: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Market Opportunity - US

§  First commercial CO2 EOR production commenced in 1972 §  ~100bn to 160bn barrels of stranded oil forecast for recovery by EOR technology* §  1.5bn barrels produced through CO2 EOR over past 25 years**

*US Department of Energy **Visiongain Research, October 2014

2630 2425

542 431

191 46 29

Cumulative Oil Production (MMBO)

Basin  Name Total  CO2  EOR  Candidate  ReservoirsPowder  River 289Bighorn 105Wind  River 45Greater  Green  River 49Overthrust  Belt 12Laramie 11Denver-­‐Cheyene 6

Source: SPE-122921-MS-Estimates of Potential CO2 Demand for CO2 EOR in Wyoming Basins

27

For

per

sona

l use

onl

y

Page 28: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

658

64

297 513

408

75 858

Market Opportunity – Australasia

“To date the recovery has been only 3-4% of the original-oil-in-place, and simulation studies indicate a recovery at abandonment of some 5-10%. Hence, it is envisaged that a suitable EOR scheme may help improve recovery. With a suitable gas injection process, it is estimated that the ultimate recovery would increase to 20-30% implying that some 2.5 MMstb of oil could be recovered”

Area of interest

0 8km NNorthern Cooper

Basin

Field B

Field A

QLD

VIC

SA NSW

WA

NT

Company Fields Reservoirs Miscible Immiscible

Medco 14 76 18 25 Conoco Philips 8 27 18 5 EP Prabumulih 3 59 55 0 Ubep Adera 3 181 181 0 Ubep Ramba 12 8 6 2 Ubep Limau 3 10 10 0 Prabumulih & Pendopo 10 154 92 62 TAC/KSO 5 20 2 2 Pertamina 5 36 1 16

Total 63 571 383 112 Source: SPE-165487-Opportunities and Challenges of CO2 Flooding in Indonesia

NAD

Gas Processing facilitates

North Sumatra

Central Sumatra

South Sumatra

West Java East

Java

East Kalimantan

Sulawesi

Maluku

Papua

Natuna 99

59 427

519

309

168

29 10

111

457

59 898

1,256

17,438 12,293

1,830

7,327

1,212

5,707

1,757

2,136

EOR target in Indonesia (status January 2010)

Indonesia (in MMSTB)

Cumulative production Discovered, unrecoverable by current development (potential for EOR) Proved reserves

42,793 22,336

3,609

4 2

35

3,183 6,598

28

For

per

sona

l use

onl

y

Page 29: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Summary

29

For

per

sona

l use

onl

y

Page 30: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Near-term Activity Pipeline

CY2015 CY2016 CY2017

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Commence construction of Grieve Facility

Potential acquisition of additional Grieve interest

Complete Singleton bio-CO2 EOR prefeasibility study

Secure support from CSM for final pre-FID Singleton pilot

Grieve Field re-pressurisation complete

Commence commissioning of Grieve Facility

First oil production - Grieve CO2 EOR Project

30

For

per

sona

l use

onl

y

Page 31: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

§  Only ASX-listed EOR company with 10-years focused EOR experience

§  Strong leadership team with proven track record of value creation

§  Focused on oil field redevelopment in North American proven EOR production fairways

§  Oil price pressures presents a unique opportunity for low cost project asset accumulation

§  Miro Advisors appointed to assess acquisition opportunities

§  Substantial growth potential within core EOR production fairways

§  Potential for Elk to acquire up to 100% ownership and operatorship of Grieve Project

§  Longer-term growth strategy of applying EOR in largely untapped areas of Australia, Indonesia and Malaysia

31

Summary

First oil from Grieve CO2 EOR Project targeted within next 12-18 months

For

per

sona

l use

onl

y

Page 32: For personal use only · for the Singleton CO2 EOR project have been compiled or in the case of the Singleton CO2 EOR project prepared by Mr. Brian Dolan, COO and VP-Engineering of

Contact: Level 9, 341 George St, Sydney, 2000

02 9299 9690

32

For

per

sona

l use

onl

y