Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Submitted by:
Madhya Pradesh Power Management Company Limited
Block no. 15, Shakti Bhawan, Vidyutnagar, Jabalpur
Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited
Block No. 7, Shakti Bhawan, Vidyutnagar, Jabalpur
Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited
Bijlee Nagar Colony, Nishtha Parisar, Govindpura, Bhopal
Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited
GPH Compound, Pologround, Indore
TRUE UP PETITION
FOR
FY 2017-18
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 1
BEFORE THE MADHYA PRADESH
ELECTRICITY REGULATORY COMMISSION, BHOPAL
Petition No. ________of 2019
(1) Madhya Pradesh Power Management Company Limited (MPPMCL)
Shakti Bhawan, Vidyut Nagar, Jabalpur (MP) -------- Petitioner
(2) Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited (MPPoKVVCL)
Shakti Bhawan, Vidyut Nagar, Jabalpur (MP) --------- Petitioner
(3) Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited (MPPaKVVCL)
GPH, Polo Ground, Indore (MP) -------- Petitioner
(4) Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited (MPMKVVCL)
Nishtha Parisar, Bijlee Nagar, Govindpura, Bhopal (MP) -------- Petitioner
IN THE MATTER OF:
Filling up of application for True up of the ARR for FY 2017-18 under the principles
laid down in the “The Madhya Pradesh Electricity Regulatory Commission (Terms
and Conditions for Determination of Tariff for Distribution and Retail Supply of
Electricity and Methods and Principles for Fixation of Charges) Regulations, 2015
(RG-35 (II) of 2015) dated 17th December 2015” by MPPMCL and MPPoKVVCL,
MPPaKVVCL& MPMKVVCL as the Distribution Licensee.
The Petitioners above respectfully submit as under: -
1. Madhya Pradesh Power Management Company Ltd., (hereinafter referred to as the
'Petitioner', MPPMCL, 'the Company' or 'the Licensee'), is a Company incorporated under
the Companies Act, 1956 (now Companies Act 2013) and having its registered office at
Block No.11, Shakti Bhawan, Vidyut Nagar, Jabalpur.
2. Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Ltd., (hereinafter referred to as
the 'Petitioner', MPPKVVCL, 'the Company' or 'the Licensee' or ‘East Discom’), is a
Company incorporated under the Companies Act, 1956 (now Companies Act 2013) and
having its registered office at Block No.7, Shakti Bhawan, Vidyut Nagar, Jabalpur. The
Petitioner is a deemed licensee under the Fifth Proviso to Section 14 of the Electricity
Act, 2003. The area of supply of the Petitioner comprises Jabalpur, Rewa, Sagar and
Shahdol Commissionary within the State of Madhya Pradesh ('MP').
3. Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Ltd., (hereinafter referred to
as the 'Petitioner', MPPaKVVCL, 'the Company' or 'the Licensee' or ‘West Discom’), is a
Company incorporated under the Companies Act, 1956 (now Companies Act 2013) and
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 2
having its registered office at GPH, Polo Ground, Indore. The Petitioner is a deemed
licensee under the Fifth Proviso to Section 14 of the Electricity Act, 2003. The area of
supply of the Petitioner comprises Indore and Ujjain Commissionary within the State of
Madhya Pradesh ('MP').
4. Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Ltd. (MPMKVVCL),
(hereinafter referred to as the 'Petitioner', MPMKVVCL, 'the Company' or 'the Licensee'
or ‘Central Discom’), is a Company incorporated under the Companies Act, 1956 (now
Companies Act 2013) and having its registered office at NishthaParisar, Bijlee Nagar
Colony, Govindpura, Bhopal. The Petitioner is a deemed licensee under the Fifth Proviso
to Section 14 of the Electricity Act, 2003. The area of supply of the Petitioner comprises
Bhopal, Gwalior, Hoshangabad and Chambal Commissionary within the State of Madhya
Pradesh ('MP').
5. The Government of Madhya Pradesh (‘GoMP or ‘State Government’), vide an Order No.
3679 FRS-18-13- 2002 dated 31stMay, 2005, published in the gazette of Madhya Pradesh
dated 31st May 2005, have restructured the functions and undertakings of Generation,
Transmission, Distribution and Retail Supply of electricity earlier carried out by the
Madhya Pradesh State Electricity Board (‘MPSEB’ or the ‘Board’) and transferred the
same to five Companies to function independently. The five Companies are as under: -
1) M.P. Power Generating Company Ltd., Jabalpur (MPPGCL) / (GENCO)
2) M.P. Power Transmission Company Ltd., Jabalpur (MPPTCL) / (TRANSCO)
3) M.P. Poorv Kshetra Vidyut Vitaran Company Ltd., Jabalpur (MPPKVVCL) / (EAST
DISCOM)
4) M.P. Madhya Kshetra Vidyut Vitaran Company Ltd. Bhopal (MPMKVVCL) /
(CENTRAL DISCOM)
5) M.P. Paschim Kshetra Vidyut Vitaran Company Ltd., Indore (MPPKVVCL) / (WEST
DISCOM)
6. With the issuance of the said Order dated 31st May 2005, the Operation and Management
Agreement that existed between MPSEB and the Five Companies came to end with
effect from 1st June 2005. The three Vidyut Vitaran Companies viz. East Discom,
Central Discom and West Discom, started functioning independently as Distribution
Licensees in their respective area of license and from the said date are no longer
operating as an agent of or on behalf of the Board, subject to Cash Flow Mechanism
(CFM) provided in the said Order.
7. On 3rd June 2006, GoMP, in exercise of its powers under Section 23 (Sub-section (1), (2)
and (3)) and Section 56 (Sub-section (2)) of Madhya Pradesh Vidyut Sudhar Adhiniyam,
2000 read with Section 131 (Sub-sections (1), (2), (5), (6) and (7) of Electricity Act,
2003, effected the transfer of and vesting of the functions, properties, interests rights and
obligations of MPSEB relating to the Bulk Purchase and Bulk Supply of Electricity in
the State Government and simultaneously re-transferred and re-vested the same to MP
Power Trading Company (‘Tradeco’ or 'MP Tradeco'). Since then, MP Tradeco is
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 3
discharging the responsibilities of procurement of power in bulk and supplying to the
three Discoms, including the Petitioner herein. The transfer was effected through “M.P.
Electricity Reforms Transfer Scheme Rules 2006” (Transfer Scheme Rules) vide
Notification No.3474 /FRS/17/XIII/2002 dtd. 3rd June 2006 (Transfer Scheme Rules).
8. In accordance with GoMP decision the name of MP Power Trading Company Ltd has
been changed to MP Power Management Company Ltd. The MP Power Management
Company has been made holding companies for all the three discoms of MP. The
Registrar of Companies, MP has issued the Certificate of Incorporation consequent upon
change of name on 10.04.2012. The MPPMCL has been vested with several of functions
and powers that were earlier vested with the erstwhile M.P. State Electricity Board.
9. GoMP has entrusted the MPPMCL with the responsibility inter alia of representing the
Discoms before the Commission with regard to filing the tariff petition and facilitating
all proceedings thereon. The Management and Corporate functions agreement signed by
the MPPMCL with the three Discoms of MP also provide for the same.
10. Hon’ble Commission had notified the Tariff Order for the period FY 2017-18 dated 31st
March 2017 while deciding the joint petition no. 73/2015 filed by East Discom, Central
Discom, West Discom and MPPMCL for the determination of tariff for distribution and
retail supply of electricity to the consumers in respective areas of supply during FY
2017-18.
11. In the backdrop of the above facts and circumstances, the present petition is being made
by the Petitioners (MPPMCL, East Discom, Central Discom and West Discom) under
Section 61 and Section 62 (1) (d) of the Electricity Act 2003, read with Clause 8.1 to
8.16 of the “The Madhya Pradesh Electricity Regulatory Commission (Terms and
Conditions for Determination of Tariff for Distribution and Retail Supply of Electricity
and Methods and Principles of Fixation of Charges) Regulations, 2015 (RG-35 (II) of
2015)” dated 17thDecember 2015” for truing up of the ARR for the Distribution and
Retail Supply Business for the period FY 2017-18.
12. Based on the information available, the Petitioners have made sincere efforts to comply
with the Regulations of the Hon’ble Commission and discharge its obligations to the best
of its abilities and resources in its command. However, should any further material
information become available during the process of determination, the petitioners may
be permitted to reserve the right to file such additional information and consequently
amend/ revise the petition.
13. The Petitioners have estimated net ARR of Rs. 9,708.06 Crores for East Discom, Rs.
10,344.57 Crores for Central Discom & Rs. 11,648.26 Crores for West Discom
aggregating to a total ARR of Rs. 31,700.89 Crores for MP State. The Revenue deficit
after considering the impact of True-up’s is Rs. 2,215.58 Crores for East Discom, Rs
2,613.58 Crores for Central Discom, Rs. 498.38 Crores for West Discom aggregating to
a total revenue deficit of Rs.5,327.54 Crores for MP State. The summary of the
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 4
Petitioner’s Claim is shown below:
Sr.
no.
Particulars Discom Approved in
Tariff
Order
Claimed in
True up
Petition
Variation
1 Power Purchase Cost Including
MPPMCL Cost
EZ 6,937.73 8,001.86 (1,064.13)
CZ 7648.31 8,570.05 (921.74)
WZ 9,262.40 9,970.19 (707.79)
MP State 23,848.44 26,542.10 (2,693.66)
2 Employee Cost (including
terminal benefit cash outflow)
EZ 1,037.28 822.48 214.80
CZ 997.17 1,127.85 (130.68)
WZ 1,067.45 731.24 336.21
MP State 3,101.90 2,681.57 420.33
3 A&G Cost
EZ 179.50 218.90 (39.40)
CZ 103.50 133.55 (30.05)
WZ 138.50 152.73 (14.23)
MP State 421.50 505.18 (83.68)
4 R&M Cost
EZ 151.40 168.84 (17.44)
CZ 183.94 145.58 38.36
WZ 135.14 136.32 (1.18)
MP State 470.49 450.74 19.75
5 Depreciation
EZ 116.50 335.28 (218.78)
CZ 159.54 300.71 (141.17)
WZ 105.05 244.33 (139.28)
MP State 381.09 880.33 (499.24)
6 Interest on Project Loans
EZ 106.69 150.08 (43.39)
CZ 238.10 6.37 231.73
WZ 67.53 44.51 23.02
MP State 412.32 200.96 211.36
7 Interest on Working Capital
EZ 85.97 72.61 13.36
CZ 46.38 35.69 10.69
WZ 63.99 37.73 26.26
MP State 196.34 146.03 50.31
8 Interest on Consumer Security
Deposit
EZ 31.69 55.79 (24.10)
CZ 56.16 52.89 3.27
WZ 54.50 63.59 (9.09)
MP State 142.34 172.27 (29.93)
9 Return on Equity EZ 219.05 307.16 (88.11)
CZ 302.14 318.61 (16.47)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 5
Sr.
no.
Particulars Discom Approved in
Tariff
Order
Claimed in
True up
Petition
Variation
WZ 177.63 174.41 3.22
MP State 698.82 800.17 (101.35)
10 Bad and Doubtful Debts
EZ 2.00 14.75 (12.75)
CZ 2.00 23.28 (21.28)
WZ 2.00 237.00 (235.00)
MP State 6.00 275.03 (269.03)
11 Other Expenses
EZ
-
CZ
- -
WZ
0.52 (0.52)
MP State
0.52 (0.52)
12 Less: Expenses Capitalized
EZ
(122.92) 122.92
CZ
(27.75) 27.75
WZ
-
MP State
(150.67) 150.67
13 Total Expenses
EZ 8,867.82 10,024.83 (1,157.01)
CZ 9,737.25 10,686.83 (949.58)
WZ 11,074.19 11,792.57 (718.38)
MP State 29,679.25 32,504.23 (2,824.98)
14 Less: Other Income - Retail &
Wheeling
EZ 243.40 316.77 (73.37)
CZ 268.57 342.26 (73.69)
WZ 349.37 144.32 205.05
MP State 861.34 803.35 57.99
16 Net Total Expenses for FY 2017-
18
EZ 8,624.42 9,708.06 (1,083.64)
CZ 9,468.68 10,344.57 (875.89)
WZ 10,724.82 11,648.26 (923.44)
MP State 28,817.91 31,700.89 (2,882.98)
17 Add: Impact of True-Ups
EZ 795.03 840.40 (45.37)
CZ 810.09 864.09 (54.00)
WZ 638.98 687.98 (49.00)
MP State 2,244.10 2,392.47 (148.37)
18 Total ARR for FY 2017-18
EZ 9,419.45 10,548.46 (1,129.01)
CZ 10,278.76 11,208.66 (929.90)
WZ 11,363.80 12,336.24 (972.44)
MP State 31,062.01 34,093.36 (3,031.35)
19 Revenue from sale of Power EZ 9,419.45 8,332.88 1,086.57
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 6
Sr.
no.
Particulars Discom Approved in
Tariff
Order
Claimed in
True up
Petition
Variation
CZ 10,278.76 8,595.08 1,683.68
WZ 11,363.80 11,837.85 (474.05)
MP State 31,062.01 28,765.81 2,296.20
20 Revenue Deficit/(Surplus)
EZ - 2,215.58 (2,215.58)
CZ - 2,613.58 (2,613.58)
WZ - 498.38 (498.38)
MP State - 5,327.54 (5,327.54)
14. Shri Firoj Kumar Meshram, Chief General Manager (Revenue Management) of
MPPMCL; Shri Girdhar Wasnik, General Manager (Commercial) of MPPoKVVCL;
Gangaram Patele, General Manager (Regulatory Affairs) of MPMKVVCL and Shri
Shailendra Jain, Deputy Director (Commercial) of MPPaKVVCL have been authorized to
execute and file all the documents on behalf of the respective petitioners in this regard.
Accordingly, the current true up petition filing is signed and verified by, and backed by
the affidavit of respective authorized signatories.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 7
PRAYER
In view of the aforesaid facts and circumstances, the Petitioners request that the Hon'ble
Commission may be pleased to:
a) Take the accompanying True-up petition for the period FY 2017-18 of East Discom,
Central Discom and West Discom on record and treat it as complete;
b) Consider and approve True-up amount of Rs. 2,215.58 Crores for East Discom, Rs
2,613.58 Crores for Central Discom and Rs. 498.38 Crores for West Discom
aggregating to Rs. 5,327.54 Crores for MP state which shall be incorporated in ARR
for FY 2020-21 on the mechanism for recovery of same, as may be decide by the
Hon’ble Commission.
c) Condone any inadvertent omissions / errors / shortcomings and permit the petitioners
to add / change / modify / alter portions of this filing and make further submissions
as may be required at a later stage;
d) Condone any delay caused in filing of the instant true-up petition.
e) Pass on such an order as the Hon'ble Commission may deem fit and proper in the
facts and circumstances of the case.
Dated: 15th October’2019
For M.P. Power Management Co. Ltd.
Jabalpur
For M.P. Poorv Kshetra Vidyut Vitaran
Co. Ltd, Jabalpur
Shri Firoj Kumar Meshram
CGM (Revenue Management)
Shri Girdhar Wasnik
GM (Commercial)
For M. P. Madhya Kshetra Vidyut
Vitaran Co. Ltd, Bhopal
For M.P. Pashchim Kshetra Vidyut
Vitaran Co. Ltd, Indore
Shri Gangaram Patele
GM (Regulatory Affairs)
Shri Shailendra Jain,
Dy. Director (Commercial)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 8
TABLE OF CONTENTS
T1: COMPARISON OF CLAIMED AND ALLOWED ARR FOR FY2017-18 ....... 10
T2: POWER PURCHASE COST ........................................................................ 13
T3: ENERGY SALES ........................................................................................ 31
T4: OPERATION & MAINTENANCE COST..................................................... 45
T5: INTEREST & FINANCE CHARGES ........................................................... 47
T6: DEPRECIATION AND RELATED DEBITS ................................................ 53
T7: BAD AND DOUBTFUL DEBTS ................................................................... 55
T8: OTHER EXPENSES .................................................................................... 56
T9: RETURN ON EQUITY ................................................................................ 57
T10: TAXES ....................................................................................................... 59
T11: OTHER EXPENSES CAPITALISED ........................................................... 59
T12: OTHER INCOME ....................................................................................... 60
T13: INCOME FROM SALE OF POWER ........................................................... 62
T14: SUMMARY OF TRUE UP ARR FOR FY 2017-18 ........................................ 65
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 9
LIST OF TABLES
Table 1: Comparison of ARR claimed and Allowed for FY 2017-18 ......................................................... 10
Table 2: Details of True Up allowed ............................................................................................................ 12
Table 3: Details of power purchase quantum and cost – Allowed and As per Audited Accounts ............... 28
Table 4: Number of Consumer for the FY 2017-18 ..................................................................................... 31
Table 5: Connected Load for the FY 2017-18 (kW) .................................................................................... 31
Table 6: Sale for FY 2017-18 (MUs) ........................................................................................................... 32
Table 7: Month & Category wise Sale for FY 2017-18 (MUs) ................................................................... 33
Table 8: Assumptions ................................................................................................................................... 37
Table 9: Calculation of disallowed units as per existing methodology ........................................................ 37
Table 10: Calculation of Energy Balance as per Existing methodology of MPERC ................................... 37
Table 11: Calculation of Power Purchase Cost as per Existing Methodology of MPERC .......................... 38
Table 12: Calculation of Energy Balance considering UI Sale .................................................................... 39
Table 13: Calculation of disallowed units as per proposed methodology .................................................... 39
Table 14: Calculation of cost of disallowed power purchase units as per proposed methodology .............. 41
Table 15: Details of power purchase cost to be allowed for East Discom FY 2017-18 (Rs Cr) .................. 42
Table 16: Details of power purchase cost to be allowed for Central Discom FY 2017-18 (Rs Cr) ............. 42
Table 17: Details of power purchase cost to be allowed for West Discom FY 2017-18 (Rs Cr) ................. 43
Table 18: Comparison of Costs – Commission’s Methodology Vs Petitioner’s Methodology (Rs Cr.) ..... 44
Table 19: Details of O&M cost claimed towards true up of FY 2017-18 .................................................... 45
Table 20: Details of Finance Charges Claimed by East Discom for True-up FY 2017-18 (Rs Cr) ............ 47
Table 21: Details of Finance Charges Claimed by Central Discom for True-up FY 2017-18 (Rs Cr) ........ 48
Table 22: Details of Finance Charges claimed by West Discom for True-up of FY 2017-18 ..................... 48
Table 23: Details of Interest on Working Capital Claimed by East Discom in True up of FY 2017-18 ..... 49
Table 24: Details of Interest on Working Capital Claimed by West Discom in True up of FY 2017-18 .... 51
Table 25: Details of Interest on Consumer Security Deposit claimed for the year FY 2017-18 .................. 52
Table 26: Summary of Interest and Finance Charges claimed towards True up of FY 2017-18 ................. 52
Table 27: Details of Depreciation Claimed by petitioners for FY 2017-18 ................................................. 53
Table 28: Details of Bad and Doubtful debts Claimed by petitioners for FY 2017-18 ................................ 55
Table 29: Other Expenses Claimed as true up for FY 2017-18 ................................................................... 56
Table 30: ROE Claimed by EZ as true up for FY 2017-18 .......................................................................... 57
Table 31: ROE Claimed by CZ as true up for FY 2017-18.......................................................................... 57
Table 32: ROE Claimed by WZ as true up for FY 2017-18 ........................................................................ 58
Table 33: ROE Claimed by Petitioners for FY 2017-18 .............................................................................. 59
Table 34: Other expenses capitalized claimed by East Discom for FY 2017-18 ......................................... 59
Table 35: Other expenses capitalized claimed by West Discom for FY 2017-18 ........................................ 60
Table 36: Other expenses capitalized claimed by West Discom for FY 2017-18 ........................................ 60
Table 37: Other income claimed by Petitioners for FY 2017-18 ................................................................. 61
Table 38: Revenue from Sales for East Discom FY 2017-18 ...................................................................... 62
Table 39: Revenue from Sales for Central Discom FY 2017-18 ................................................................. 63
Table 40: Revenue from Sales for West Discom FY 2017-18 ..................................................................... 64
Table 41: Summary of True Up Claimed for FY 2017-18 (Rs Cr) .............................................................. 65
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 10
T1: COMPARISON OF CLAIMED AND ALLOWED ARR FOR FY2017-18
1.1 East Discom, Central Discom and West Discom in their Tariff petition no. 71/2016,
dated 8th December 2016 had submitted the claim for ARR of Rs. 9950 Crs, Rs. 10586
Crs and Rs. 11,537 Crs respectively. Hon’ble Commission in its Tariff Order dated
31st March 2017 had allowed the ARR of Rs 9419.45 Crs, Rs. 10,278.76 Crs and Rs
11,363.80 Crs for East, Central and West Discoms respectively. The head-wise
comparison is given in following table:
Table 1: Comparison of ARR claimed and Allowed for FY 2017-18
Sr.
no.
Particulars Discom Claimed in
ARR Petition
Approved Disallowance
1 Power Purchase Cost
Including MPPMCL Cost
EZ 7,750 6,938 812
CZ 8,176 7,648 528
WZ 9,364 9,262 102
MP State 25,290 23,848 1,442
2
Employee Cost (including
terminal benefit cash
outflow)
EZ 998 1,037 (39)
CZ 1,012 997 15
WZ 1,029 1,067 (38)
MP State 3,039 3,102 (63)
3 A&G Cost
EZ 184 180 5
CZ 105 104 2
WZ 153 139 15
MP State 442 422 21
4 R&M Cost
EZ 166 151 15
CZ 184 184 0
WZ 140 135 5
MP State 490 470 20
5 Depreciation
EZ 324 117 208
CZ 349 160 189
WZ 254 105 149
MP State 927 381 546
6 Interest on Project Loans
EZ 191 107 84
CZ 329 238 91
WZ 159 68 91
MP State 679 412 267
7 Interest on Working Capital
EZ 57 86 (29)
CZ 36 46 (11)
WZ 51 64 (13)
MP State 144 196 (53)
8 Interest on Consumer
Security Deposit
EZ 36 32 4
CZ 64 56 8
WZ 63 55 9
MP State 142 142 -
9 Return on Equity EZ 264 219 45
CZ 301 302 (1)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 11
Sr.
no.
Particulars Discom Claimed in
ARR Petition
Approved Disallowance
WZ 256 178 78
MP State 821 699 122
10 Bad and Doubtful Debts
EZ 84 2 82
CZ 99 2 97
WZ 101 2 99
MP State 284 6 278
11 Other Expenses
EZ
-
CZ
-
WZ
-
MP State
-
12 Less: Expenses Capitalised
EZ
-
CZ
-
WZ
-
MP State
-
13 Total Expenses
EZ 10,054 8,868 1,186
CZ 10,655 11,074 (420)
WZ 11,570 9,737 1,833
MP State
29,679 (29,679)
14 Less: Other Income - Retail
& Wheeling
EZ 177 243 (66)
CZ 150 349 (199)
WZ 151 269 (118)
MP State 478 861 (383)
15 Net Total Expenses for FY
2016-17
EZ 9,877 8,624 1,253
CZ 10,505 10,725 (220)
WZ 11,419 9,469 1,950
MP State
28,818 (28,818)
16 Add: Impact of True-Ups
EZ 74 795 (721)
CZ 82 639 (557)
WZ 119 810 (691)
MP State 275 2,244 (1,969)
17 Total ARR for FY 2016-17
EZ 9,951 9,419 531
CZ 10,587 11,364 (777)
WZ 11,538 10,279 1,259
MP State
31,062 (31,062)
18 Revenue from sale of Power
EZ 8,376 9,419 (1,043)
CZ 9,114 11,364 (2,250)
WZ 10,054 10,279 (225)
MP State 27,544 31,062 (3,518)
19 Revenue Deficit/Surplus
EZ 1,574 - 1,574
CZ 1,472 - 1,472
WZ 1,483 - 1,483
MP State 4,529 - 4,529
1.2 Hon’ble Commission has included the impact of various true up/final orders on ARR
for FY 2017-18 as per the following table:
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 12
Table 2: Details of True Up allowed
1.3 Out of the total impact of Rs. 2244.10 Cr for the State as a whole, impact to the tune
of Rs. 795.03 Crs, Rs 810.09 Crs and Rs 638.98 Crs was allowed in the ARR of East
Discom, Central Discom and West Discom respectively for FY 2017-18.
1.4 On finalisation of the Audited Accounts of the petitioners for the period FY 2017-18,
the actual head wise cost has been compared with the allowed costs and details of
which have been provided in the subsequent Chapters.
Sr.no. Particulars Impact (Rs. Cr)
1 Impact of True-Up of Discoms for FY 2006-07 423.00
2 Impact of True-Up of MP Transco for FY 2014-15 413.63
3 Impact of True-Up of MP Genco for FY 2014-15 (562)
4 Impact of True-Up of MP Genco for FY 2007-08 to FY 2011-12 1969.47
Total Power Purchase Cost 2244.10
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 13
T2: POWER PURCHASE COST
2.1 The Petitioners purchase power from MPPGCL generating stations, Central
generating stations and other sources such as Captive Power Plants, Bio-mass units,
CPPs/IPPs, Solar and other RE sources and short-term sources to meet the energy
requirement of the State.
2.2 The Petitioners would like to submit that, on the basis of normative loss level
specified in the tariff regulations, the Hon’ble Commission in its Tariff Order dated
31st March 2017 had determined the Energy requirement of 19,434 MUs for East
Discom, 20,627 MUs for Central Discom, 23,022 MUs for West Discom aggregating
to 63,083 MUs for the MP State for FY 2017-18 at a cost of Rs. 6,937.73 Cr for the
East Discom, Rs. 7,648.31 Cr for the Central Discom and Rs. 9,262.39 Cr for the
West Discom thus aggregating to Rs. 23,848.44 Cr for the MP State for FY 2017-18
respectively.
2.3 The Petitioners submits that based on annual audited accounts and actual distribution
losses, power purchase cost (including transmission charges) arrives at Rs.8,374.22 Cr
for the East Discom, Rs.9,404.47 Cr for the Central Discom and Rs.10,019.20 Cr for
the West Discom aggregating to Rs. 27,797.89 Cr for the MP State for FY 2017-18 as
shown in the Table below:
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 14
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
I Purchase from Power Stations
1 KSTPS
3,575.00 233.10 453.47 - - 27.87 - 0.37 714.82
EZ 0.39 1,394.25 90.91 176.86 - - 10.87 - 0.15 278.78
CZ 0.28 1,001.00 65.27 126.97 - - 7.80 - 0.10 200.15
WZ 0.33 1,179.75 76.92 149.65 - - 9.20 - 0.12 235.89
2 KSTPS III
569.43 77.87 70.87 - - 4.48 - 0.06 153.28
EZ 0.29 162.80 22.27 20.32 - - 1.27 - 0.02 43.88
CZ 0.36 205.44 28.32 25.58 - - 1.63 - 0.02 55.55
WZ 0.35 201.19 27.28 24.97 - - 1.58 - 0.02 53.85
3 VSTPS - I
3,004.81 247.43 443.20 - - 56.42 - 0.44 747.49
EZ 0.36 1,081.73 89.08 159.55 - - 20.31 - 0.16 269.10
CZ 0.34 1,021.64 84.13 150.69 - - 19.18 - 0.15 254.15
WZ 0.30 901.44 74.23 132.96 - - 16.93 - 0.13 224.25
4 VSTPS-II
2,448.73 154.25 329.93 - - 44.45 - 0.22 528.85
EZ 0.36 881.54 55.53 118.77 - - 16.00 - 0.08 190.39
CZ 0.32 783.59 49.36 105.58 - - 14.22 - 0.07 169.23
WZ 0.32 783.59 49.36 105.58 - - 14.22 - 0.07 169.23
5 VSTPS-III
1,973.16 189.54 265.38 - - 33.31 - 0.17 488.40
EZ 0.33 651.14 62.55 87.57 - - 10.99 - 0.06 161.17
CZ 0.31 611.68 58.76 82.27 - - 10.33 - 0.05 151.40
WZ 0.36 710.34 68.23 95.54 - - 11.99 - 0.06 175.82
6 VSTPS-IV
2,235.40 319.70 300.79 - - 40.32 - 0.20 661.00
EZ 0.28 628.34 90.81 85.04 - - 11.31 - 0.06 187.23
CZ 0.36 810.10 116.74 109.55 - - 14.92 - 0.07 241.29
WZ 0.36 796.96 112.15 106.19 - - 14.08 - 0.07 232.49
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 15
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
7 VSTPS-V
1,121.07 164.07 153.73 - - 20.59 - 0.10 338.48
EZ 0.28 315.95 46.32 43.59 - - 5.80 - 0.03 95.74
CZ 0.36 408.74 59.94 56.30 - - 7.66 - 0.03 123.92
WZ 0.35 396.38 57.82 53.84 - - 7.13 - 0.03 118.82
8 Kawas
519.31 87.13 125.04 - - - 0.05 0.15 212.36
EZ 0.35 181.76 30.49 43.76 - - - 0.02 0.05 74.33
CZ 0.25 129.83 21.78 31.26 - - - 0.01 0.04 53.09
WZ 0.40 207.72 34.85 50.01 - - - 0.02 0.06 84.95
9 Gandhar
512.66 90.85 128.48 - - - 0.07 1.70 221.10
EZ 0.32 164.05 29.07 41.11 - - - 0.02 0.55 70.75
CZ 0.30 153.80 27.25 38.54 - - - 0.02 0.51 66.33
WZ 0.38 194.81 34.52 48.82 - - - 0.03 0.65 84.02
10 SIPAT I
2,648.76 319.95 302.95 - - 16.97 - 0.24 640.11
EZ 0.29 756.01 91.22 87.21 - - 4.85 - 0.07 183.34
CZ 0.37 968.59 117.24 110.82 - - 6.34 - 0.08 234.47
WZ 0.35 924.16 111.50 104.92 - - 5.79 - 0.08 222.29
11 SIPAT II
1,456.72 170.53 177.48 - - 10.85 - 0.51 359.37
EZ 0.39 568.12 66.51 69.22 - - 4.23 - 0.20 140.15
CZ 0.26 378.75 44.34 46.14 - - 2.82 - 0.13 93.44
WZ 0.35 509.85 59.69 62.12 - - 3.80 - 0.18 125.78
12 TARAPUR
1,092.84 - 332.53 - - (0.01) - 0.98 333.50
EZ 0.34 371.57 - 113.06 - - (0.00) - 0.33 113.39
CZ 0.31 338.78 - 103.08 - - (0.00) - 0.30 103.38
WZ 0.35 382.49 - 116.38 - - (0.00) - 0.34 116.72
13 Kahalgaon II
333.05 57.29 76.05 - - 0.00 - 0.08 133.42
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 16
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ 0.27 89.92 15.47 20.53 - - 0.00 - 0.02 36.02
CZ 0.20 66.61 11.46 15.21 - - 0.00 - 0.02 26.68
WZ 0.53 176.52 30.36 40.31 - - 0.00 - 0.04 70.71
14 Mauda-I
525.47 204.47 131.54 - - - - 13.52 349.53
EZ 0.28 147.52 59.58 37.18 - - - - 3.59 100.35
CZ 0.36 191.62 75.64 48.14 - - - - 4.62 128.40
WZ 0.35 186.33 69.25 46.23 - - - - 5.31 120.78
15 Mauda-II
427.17 93.91 100.30 - - - - 1.03 195.24
EZ 0.27 113.79 26.26 26.92 - - - - 0.27 53.45
CZ 0.36 152.88 34.12 35.95 - - - - 0.35 70.42
WZ 0.38 160.50 33.53 37.43 - - - - 0.41 71.37
16 Solapur I
236.13 75.09 57.54 - - - - 13.38 146.01
EZ 0.26 61.97 20.16 14.53 - - - - 3.99 38.68
CZ 0.35 82.43 25.80 20.62 - - - - 4.17 50.60
WZ 0.39 91.73 29.12 22.38 - - - - 5.23 56.73
Total (I)
22,679.69 2,485.18 3,449.25 - - 255.24 0.12 33.16 6,222.95
EZ
7,570.45 796.23 1,145.23 - - 85.63 0.04 9.62 2,036.74
CZ
7,305.47 820.13 1,106.70 - - 84.91 0.03 10.73 2,022.50
WZ
7,803.77 868.83 1,197.32 - - 84.70 0.05 12.81 2,163.70
II Purchase from Other Sources
1 NHDC-Indira Sagar
836.69 492.09 - - - 13.35 - - 505.44
EZ 0.22 184.07 108.26 0.00 - - 2.94 - - 111.20
CZ 0.25 209.17 123.02 (0.00) - - 3.34 - - 126.36
WZ 0.53 443.45 260.81 (0.00) - - 7.08 - - 267.88
2 SSP
519.51 162.75 42.60 - - - - - 205.35
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 17
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ 0.32 166.24 52.08 13.63 - - - - - 65.71
CZ 0.25 129.88 40.69 10.65 - - - - - 51.34
WZ 0.43 223.39 69.98 18.32 - - - - - 88.30
3 OMKARESHWAR
441.93 349.08 0.00 - - 6.72 - - 355.80
EZ 0.30 132.58 104.73 (0.00) - - 2.01 - - 106.74
CZ 0.25 110.48 87.27 0.00 - - 1.68 - - 88.95
WZ 0.45 198.87 157.09 0.00 - - 3.02 - - 160.11
4 ISP NVDA
0.02 - 0.01 - - - - - 0.01
EZ 0.22 0.01 - 0.00 - - - - - 0.00
CZ 0.25 0.01 - 0.00 - - - - - 0.00
WZ 0.53 0.01 - 0.01 - - - - - 0.01
5 Wind Energy
3,676.52 - 2,045.47 - - - - - 2,045.47
EZ 0.30 1,090.09 - 606.48 - - - - - 606.48
CZ 0.33 1,220.97 - 679.30 - - - - - 679.30
WZ 0.37 1,365.46 - 759.69 - - - - - 759.69
6 DVC (Mejia)
528.60 140.06 125.41 - - - - 0.62 266.09
EZ 0.33 174.44 46.22 41.39 - - - - 0.20 87.81
CZ 0.14 74.00 19.61 17.56 - - - - 0.09 37.25
WZ 0.53 280.16 74.23 66.47 - - - - 0.33 141.03
7 DVC (Chandrpur)
1,115.35 197.29 204.45 - - - - 2.82 404.57
EZ 0.33 368.07 65.11 67.47 - - - - 0.93 133.51
CZ 0.14 156.15 27.62 28.62 - - - - 0.40 56.64
WZ 0.53 591.14 104.56 108.36 - - - - 1.50 214.42
8 DVC (Durgapur)
64.35 15.97 13.16 - - - - 0.01 29.14
EZ 0.32 20.64 5.14 4.22 - - - - 0.00 9.36
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 18
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
CZ 0.34 22.07 5.47 4.52 - - - - 0.00 9.99
WZ 0.34 21.64 5.37 4.43 - - - - 0.00 9.80
9 Torrent
44.40 66.59 17.56 - - 0.11 - 0.24 84.51
EZ 0.26 11.45 18.35 4.45 - - 0.03 - 0.06 22.89
CZ 0.37 16.62 23.60 6.52 - - 0.04 - 0.09 30.26
WZ 0.37 16.33 24.64 6.58 - - 0.04 - 0.09 31.36
10 Sasan
11,235.39 166.42 1,291.62 - - 198.41 - 178.57 1,835.03
EZ 0.28 3,182.93 47.25 365.91 - - 56.20 - 52.25 521.62
CZ 0.36 4,088.14 60.73 469.97 - - 72.20 - 64.88 667.78
WZ 0.35 3,964.32 58.44 455.74 - - 70.01 - 61.44 645.63
11 RDM Care
2.20 - 0.67 - - - - - 0.67
EZ 0.30 0.65 - 0.20 - - - - - 0.20
CZ 0.33 0.73 - 0.22 - - - - - 0.22
WZ 0.37 0.82 - 0.25 - - - - - 0.25
12 JP Bina
1,263.71 426.92 299.71 - - 19.67 - (0.34) 745.96
EZ 0.28 348.51 121.05 81.94 - - 5.58 - (0.11) 208.45
CZ 0.35 442.11 155.30 106.81 - - 7.34 - (0.13) 269.32
WZ 0.37 473.10 150.58 110.96 - - 6.75 - (0.10) 268.19
13 BLA
- - - - - - - - -
EZ - - - - - - - - - -
CZ - - - - - - - - - -
WZ - - - - - - - - - -
14 MB Power Unit - I
932.78 237.28 184.96 - - 14.98 - 0.86 438.08
EZ 0.29 266.48 67.79 52.80 - - 3.82 - 0.24 124.65
CZ 0.36 337.29 86.46 66.75 - - 5.43 - 0.31 158.95
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 19
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
WZ 0.35 329.01 83.03 65.41 - - 5.73 - 0.31 154.48
15 MB Power Unit - II
926.10 162.77 185.75 - - 15.26 - - 363.78
EZ 0.28 257.16 45.31 51.51 - - 3.92 - - 100.74
CZ 0.37 342.29 60.35 68.50 - - 5.51 - - 134.36
WZ 0.35 326.64 57.12 65.74 - - 5.83 - - 128.69
16 Hindalco
- - - - - - - - -
EZ #DIV/0! - - - - - - - - -
CZ #DIV/0! - - - - - - - - -
WZ #DIV/0! - - - - - - - - -
17 LancoAmarkantak
1,773.51 239.05 293.33 - - 13.09 - 8.49 553.95
EZ 0.28 500.13 69.83 82.02 - - 3.70 - 2.41 157.96
CZ 0.36 634.36 87.47 104.40 - - 4.73 - 3.04 199.63
WZ 0.36 639.02 81.75 106.91 - - 4.66 - 3.05 196.36
18 Arya
- - - - - - - - -
EZ #DIV/0! - - - - - - - - -
CZ #DIV/0! - - - - - - - - -
WZ #DIV/0! - - - - - - - - -
19 M/s Orient Green
- - - - - - - - -
EZ #DIV/0! - - - - - - - - -
CZ #DIV/0! - - - - - - - - -
WZ #DIV/0! - - - - - - - - -
20 JP Nigrie
3,324.62 612.72 160.99 - - 59.34 - 0.00 833.05
EZ 0.28 946.09 174.21 46.37 - - 17.08 - 0.00 237.66
CZ 0.36 1,204.46 222.85 57.98 - - 21.63 - 0.00 302.47
WZ 0.35 1,174.06 215.65 56.63 - - 20.63 - 0.00 292.92
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 20
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
21 Jhabua Power
440.39 143.57 98.32 - - 5.59 - - 247.48
EZ 0.27 116.95 39.50 26.10 - - 1.42 - - 67.02
CZ 0.36 157.50 50.88 35.01 - - 1.98 - - 87.87
WZ 0.38 165.94 53.19 37.21 - - 2.19 - - 92.59
22 Jabalpur MSW
47.89 - 25.87 - - - - - 25.87
EZ 0.30 14.20 - 7.67 - - - - - 7.67
CZ 0.33 15.90 - 8.59 - - - - - 8.59
WZ 0.37 17.78 - 9.61 - - - - - 9.61
23 Solar Energy
1,277.07 - 786.64 - - - - - 786.64
EZ 0.30 378.65 - 233.24 - - - - - 233.24
CZ 0.33 424.11 - 261.24 - - - - - 261.24
WZ 0.37 474.30 - 292.16 - - - - - 292.16
24 IEX/PXI
554.82 - 216.02 - - - - - 216.02
EZ 0.30 165.83 - 64.57 - - - - - 64.57
CZ 0.32 176.60 - 68.76 - - - - - 68.76
WZ 0.38 212.38 - 82.69 - - - - - 82.69
25 Essar Power (5%)
73.53 - 17.29 - - 1.77 - 2.28 21.33
EZ 0.30 21.91 - 5.13 - - 0.53 - 0.68 6.33
CZ 0.35 25.42 - 5.96 - - 0.61 - 0.79 7.36
WZ 0.36 26.19 - 6.20 - - 0.63 - 0.81 7.64
Others-Total (II)
29,079.36 3,412.57 6,009.82 - - 348.29 - 193.56 9,964.24
EZ
8,347.08 964.82 1,755.08 - - 97.23 - 56.67 2,873.81
CZ
9,788.28 1,051.32 2,001.37 - - 124.48 - 69.46 3,246.64
WZ
10,944.00 1,396.43 2,253.36 - - 126.58 - 67.43 3,843.80
A Grand Total other than Genco(I+II)
51,759.05 5,897.75 9,459.06 - - 603.53 0.12 226.72 16,187.19
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 21
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ
15,917.53 1,761.04 2,900.31 - - 182.86 0.04 66.29 4,910.55
CZ
17,093.74 1,871.45 3,108.07 - - 209.39 0.03 80.19 5,269.14
WZ
18,747.77 2,265.26 3,450.68 - - 211.28 0.05 80.24 6,007.50
I MP Genco - Thermal
1 ATPS-Chachai (210MW)
1,572.36 221.67 259.94 - - 3.11 - 1.18 485.91
EZ 0.27 424.54 59.85 70.18 - - 0.84 - 0.32 131.20
CZ 0.40 628.95 88.67 103.98 - - 1.25 - 0.47 194.36
WZ 0.33 518.88 73.15 85.78 - - 1.03 - 0.39 160.35
2 STPS Sarni
1,517.98 298.46 379.65 - - 3.64 - 2.00 683.74
EZ 0.29 440.21 86.23 110.10 - - 1.05 - 0.58 197.96
CZ 0.39 592.01 116.72 148.06 - - 1.42 - 0.78 266.99
WZ 0.32 485.75 95.51 121.49 - - 1.16 - 0.64 218.80
3 SGTPS Birsingpur
4,041.57 355.73 866.33 - - 7.08 - 1.33 1,230.46
EZ 0.28 1,131.64 99.60 242.57 - - 1.98 - 0.37 344.53
CZ 0.40 1,616.63 142.29 346.53 - - 2.83 - 0.53 492.19
WZ 0.32 1,293.30 113.83 277.22 - - 2.26 - 0.43 393.75
4 SGTPS Birsingpur (500MW)
2,860.99 350.13 577.11 - - 4.21 - 0.79 932.25
EZ 0.28 801.08 98.04 161.59 - - 1.18 - 0.22 261.04
CZ 0.40 1,144.40 140.05 230.84 - - 1.68 - 0.32 372.89
WZ 0.32 915.52 112.04 184.68 - - 1.35 - 0.25 298.32
5 STPS Sarni # 10 & 11
3,009.11 654.74 590.88 - - 2.19 - 1.20 1,249.01
EZ 0.28 849.48 184.88 167.01 - - 0.62 - 0.34 352.84
CZ 0.36 1,078.71 235.99 211.32 - - 0.80 - 0.44 448.55
WZ 0.36 1,080.92 233.87 212.55 - - 0.77 - 0.42 447.62
6 SSTPS SingajiKhandwa 1 & 2
3,578.68 998.74 872.16 - - 17.82 - 0.61 1,889.34
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 22
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ 0.28 997.11 286.82 242.47 - - 5.06 - 0.17 534.52
CZ 0.36 1,288.06 359.23 312.62 - - 6.46 - 0.22 678.53
WZ 0.36 1,293.50 352.69 317.07 - - 6.30 - 0.22 676.28
M.P. Genco Thermal-Total (I)
16,580.69 2,879.47 3,546.08 - - 38.05 - 7.13 6,470.72
EZ
4,644.06 815.42 993.92 - - 10.74 - 2.01 1,822.09
CZ
6,348.75 1,082.95 1,353.36 - - 14.44 - 2.77 2,453.52
WZ
5,587.88 981.10 1,198.79 - - 12.87 - 2.35 2,195.11
II MPGenco - Hydel
1 Gandhi Sagar
173.84 3.40 2.92 - - 7.24 - 0.03 13.60
EZ 0.23 39.98 0.78 0.67 - - 1.67 - 0.01 3.13
CZ 0.50 86.92 1.70 1.46 - - 3.62 - 0.02 6.80
WZ 0.27 46.94 0.92 0.79 - - 1.96 - 0.01 3.67
2 R P Sagar
187.12 - 28.25 - - - - - 28.25
EZ 0.20 37.42 - 5.65 - - - - - 5.65
CZ 0.50 93.56 - 14.13 - - - - - 14.13
WZ 0.30 56.14 - 8.48 - - - - - 8.48
3 JawaharSagar
129.00 - 19.48 - - - - - 19.48
EZ 0.20 25.80 - 3.90 - - - - - 3.90
CZ 0.50 64.50 - 9.74 - - - - - 9.74
WZ 0.30 38.70 - 5.84 - - - - - 5.84
4 Pench
101.10 9.31 4.51 - - - - 0.05 13.87
EZ 0.20 20.22 1.86 0.90 - - - - 0.01 2.77
CZ 0.40 40.44 3.73 1.80 - - - - 0.02 5.55
WZ 0.40 40.44 3.73 1.80 - - - - 0.02 5.55
5 Ban Sagar (I+II+III)
659.75 70.99 40.34 - - 13.97 - 0.12 125.42
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 23
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ 0.30 197.93 21.30 12.10 - - 4.19 - 0.04 37.63
CZ 0.30 197.93 21.30 12.10 - - 4.19 - 0.04 37.63
WZ 0.40 263.90 28.40 16.13 - - 5.59 - 0.05 50.17
6 Jhinna HPS
66.47 8.63 6.39 - - 0.98 - 0.01 16.00
EZ 0.30 19.94 2.59 1.92 - - 0.29 - 0.00 4.80
CZ 0.30 19.94 2.59 1.92 - - 0.29 - 0.00 4.80
WZ 0.40 26.59 3.45 2.56 - - 0.39 - 0.00 6.40
7 Brinsingpur Hydro
24.47 1.87 4.60 - - 0.63 - 0.01 7.11
EZ 0.30 7.34 0.56 1.38 - - 0.19 - 0.00 2.13
CZ 0.20 4.89 0.37 0.92 - - 0.13 - 0.00 1.42
WZ 0.50 12.23 0.94 2.30 - - 0.31 - 0.00 3.56
8 Bargi
129.00 8.14 2.01 - - 12.85 - 0.03 23.03
EZ 0.25 32.25 2.04 0.50 - - 3.21 - 0.01 5.76
CZ 0.25 32.25 2.04 0.50 - - 3.21 - 0.01 5.76
WZ 0.50 64.50 4.07 1.01 - - 6.42 - 0.01 11.51
9 Rajghat
28.59 1.94 3.37 - - - - 0.01 5.31
EZ 0.20 5.72 0.39 0.67 - - - - 0.00 1.06
CZ 0.40 11.44 0.77 1.35 - - - - 0.01 2.13
WZ 0.40 11.44 0.77 1.35 - - - - 0.01 2.13
10 Madhikheda HPS
21.74 14.87 4.53 - - 2.54 - 0.02 21.96
EZ 0.30 6.52 4.46 1.36 - - 0.76 - 0.01 6.59
CZ 0.20 4.35 2.97 0.91 - - 0.51 - 0.00 4.39
WZ 0.50 10.87 7.44 2.27 - - 1.27 - 0.01 10.98
M.P. GencoHydel Total (II)
1,521.08 119.16 116.40 - - 38.21 - 0.27 274.04
EZ
393.12 33.98 29.05 - - 10.31 - 0.07 73.42
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 24
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
CZ
556.21 35.47 44.82 - - 11.95 - 0.09 92.34
WZ
571.74 49.71 42.52 - - 15.94 - 0.11 108.29
B MP Genco TOTAL (I+II)
18,101.77 2,998.63 3,662.48 - - 76.26 - 7.40 6,744.77
EZ
5,037.18 849.40 1,022.97 - - 21.05 - 2.08 1,895.50
CZ
6,904.97 1,118.42 1,398.19 - - 26.40 - 2.86 2,545.86
WZ
6,159.62 1,030.81 1,241.32 - - 28.82 - 2.46 2,303.40
C Total Power Purchased (A+B)
69,860.82 8,896.38 13,121.54 - - 679.79 0.12 234.13 22,931.96
EZ
20,954.71 2,610.44 3,923.29 - - 203.91 0.04 68.37 6,806.05
CZ
23,998.71 2,989.87 4,506.26 - - 235.79 0.03 83.05 7,815.00
WZ
24,907.39 3,296.07 4,691.99 - - 240.09 0.05 82.70 8,310.90
D Total Inter-State transmission
charges
1 PGCIL
- 1,463.70 - - - - - - 1,463.70
EZ 0.30 - 438.34 - - - - - - 438.34
CZ 0.34 - 503.38 - - - - - - 503.38
WZ 0.36 - 521.98 - - - - - - 521.98
2 POSCO
- 4.86 - - - - - - 4.86
EZ 0.30 - 1.46 - - - - - - 1.46
CZ 0.34 - 1.68 - - - - - - 1.68
WZ 0.35 - 1.72 - - - - - - 1.72
3 Torrent Transmission
- - - - - - - - -
EZ #DIV/0! - - - - - - - - -
CZ #DIV/0! - - - - - - - - -
WZ #DIV/0! - - - - - - - - -
4 LancoAmarkantak Transmission
- 63.11 - - - - - - 63.11
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 25
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
EZ 0.28 - 17.84 - - - - - - 17.84
CZ 0.36 - 22.95 - - - - - - 22.95
WZ 0.35 - 22.32 - - - - - - 22.32
D Total Transmission charges ( 1 to 4)
- 1,531.68 - - - - - - 1,531.68
EZ
- 457.65 - - - - - - 457.65
CZ
- 528.00 - - - - - - 528.00
WZ
- 546.03 - - - - - - 546.03
E TOTAL COST FOR ENERGY
PURCHASE (C+D) 69,860.82 10,428.06 13,121.54 - - 679.79 0.12 234.13 24,463.63
EZ
20,954.71 3,068.09 3,923.29 - - 203.91 0.04 68.37 7,263.70
CZ
23,998.71 3,517.87 4,506.26 - - 235.79 0.03 83.05 8,343.00
WZ
24,907.39 3,842.10 4,691.99 - - 240.09 0.05 82.70 8,856.93
F Supplementary Bills
1,849.27 1,849.27
EZ
- - - - - - - 514.26 514.26
CZ
- - - - - - - 606.40 606.40
WZ
- - - - - - - 728.61 728.61
G
TOTAL COST FOR ENERGY
PURCHASE INCLUDING
SUPPLEMENTRY BILLS (E+F)
69,860.82 10,428.06 13,121.54 - - 679.79 0.12 2,083.39 26,312.90
EZ
20,954.71 3,068.09 3,923.29 - - 203.91 0.04 582.63 7,777.96
CZ
23,998.71 3,517.87 4,506.26 - - 235.79 0.03 689.45 8,949.40
WZ
24,907.39 3,842.10 4,691.99 - - 240.09 0.05 811.32 9,585.54
H
Other costs passed to Discoms -
which cannot be apportioned
station wise-
454.76 454.76
EZ 0.31 - - - - - - - 139.75 139.75
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 26
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
CZ 0.34 - - - - - - - 153.48 153.48
WZ 0.36 - - - - - - - 161.53 161.53
I TOTAL COST FOR ENERGY
PURCHASE (G+H) 69,860.82 10,428.06 13,121.54 - - 679.79 0.12 2,538.16 26,767.66
EZ
20,954.71 3,068.09 3,923.29 - - 203.91 0.04 722.38 7,917.71
CZ
23,998.71 3,517.87 4,506.26 - - 235.79 0.03 842.93 9,102.88
WZ
24,907.39 3,842.10 4,691.99 - - 240.09 0.05 972.85 9,747.07
J Less: Other Income
730.34
730.34
EZ 0.31 - - 224.43 - - - -
224.43
CZ 0.34 - - 246.49 - - - -
246.49
WZ 0.36 - - 259.42 - - - -
259.42
K Less: Sale of Power
3,855.89
1,213.90
1,213.90
EZ 0.30 1,145.86 - 362.61 - - - -
362.61
CZ 0.32 1,252.14 - 397.50 - - - -
397.50
WZ 0.38 1,457.89 - 453.78 - - - -
453.78
L Net Total Purchase cost (I-J-K)
66,004.93 10,428.06 11,177.30 - - 679.79 0.12 2,538.16 24,823.42
EZ 0.30 19,808.85 3,068.09 3,336.24 - - 203.91 0.04 722.38 7,330.66
CZ 0.34 22,746.58 3,517.87 3,862.26 - - 235.79 0.03 842.93 8,458.89
WZ 0.36 23,449.50 3,842.10 3,978.79 - - 240.09 0.05 972.85 9,033.87
Other Cost based on MPPMCL
Reconciliation (0.00) (0.00)
EZ
29.49 29.49
CZ
37.02 37.02
WZ
(66.51) (66.51)
MPPMCL Power Purchase Cost
66,004.93 10,428.06 11,177.30 - - 679.79 0.12 2,538.16 24,823.42
EZ
19,808.85 3,068.09 3,336.24 - - 203.91 0.04 751.87 7,360.15
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 27
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
CZ
22,746.58 3,517.87 3,862.26 - - 235.79 0.03 879.95 8,495.91
WZ
23,449.50 3,842.10 3,978.79 - - 240.09 0.05 906.34 8,967.36
Supplementary Bills
- - - - - - - 37.11 37.11
EZ
1.73 1.73
CZ
35.38 35.38
WZ
- -
Power Purchase from others
- - - - - - - 4.14 4.14
EZ
4.14 4.14
CZ
-
WZ
-
UI/DSM Charges (Rs Cr)
- - - - - - - 187.53 187.53
EZ
158.82 158.82
CZ
9.39 9.39
WZ
19.32 19.32
Reactive Energy Charges (Rs Cr)
- - - - - - - (2.10) (2.10)
EZ
(4.27) (4.27)
CZ
3.48 3.48
WZ
(1.31) (1.31)
Intra state Transmission Charges
(Rs. Cr) - - - - - - - 2,738.35 2,738.35
EZ
850.83 850.83
CZ
857.30 857.30
WZ
1,030.22 1,030.22
SLDC Charges
- - - - - - - 9.44 9.44
EZ
2.82 2.82
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 28
S.No Source of Power Purchase Allocation
Ratio
MU
Purchased
Total
Capacity
Charges
Total
Energy
Charges
Total
FPA
charges
Income
Tax
ED, Cess,
Heavy
Water
charge,
water
charges
MOPA,
Insurance
Any
Other
Total of all
Charges
CZ
3.01 3.01
WZ
3.61 3.61
Total Power Purchase Cost
66,126.46 10,428.06 11,177.30 - - 679.79 0.12 5,512.63 27,797.89
EZ
20,347.44 3,068.09 3,336.24 - - 203.91 0.04 1,765.94 8,374.22
CZ
22,328.20 3,517.87 3,862.26 - - 235.79 0.03 1,788.51 9,404.47
WZ
23,450.82 3,842.10 3,978.79 - - 240.09 0.05 1,958.18 10,019.20
2.4 As per the power purchase statement of MPPMCL, the quantum of the actual ex-bus power purchased by East, Central and West
Discoms for FY 2017-18 was 19,808.85 MUs, 22,746.58 MUs and 23,449.50 MUs respectively which aggregate to 66,004.93 MUs for
MP State. This quantum does not include the quantum of UI and Inter-Discom Sale / Purchase at Discom periphery. The comparison of
Power Purchase as per audited accounts and that allowed in the tariff order is given in the table below:
Table 3: Details of power purchase quantum and cost – Allowed and As per Audited Accounts
Sr.
No Particulars
Quantum (MUs) Amount (₹ Crores)
Approved Actual Deviation Approved Actual Deviation
A Power Purchase Cost
1 MP State 63,083.00 69,860.82 6,777.82 19,910.07 22,931.96 3,021.89
i East Discom 19434 20,954.71 1,520.71 5746.67 6,806.05 1,059.38
ii Central Discom 20627 23,998.71 3,371.71 6422.29 7,815.00 1,392.71
iii West Discom 23022 24,907.39 1,885.39 7741.11 8,310.90 569.79
B Inter State Transmission Charges
1 MP State
1,406.00 1,531.68 125.68
i East Discom
434.39 457.65 23.26
ii Central Discom
419.97 528.00 108.03
iii West Discom
551.64 546.03 (5.61)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 29
Sr.
No Particulars
Quantum (MUs) Amount (₹ Crores)
Approved Actual Deviation Approved Actual Deviation
C Intra State Transmission Charges including SLDC
1 MP State
2,532.37 2,747.79 215.42
i East Discom
756.67 853.65 96.98
ii Central Discom
806.05 860.31 54.26
iii West Discom
969.65 1,033.83 64.18
D Supplementary Bill Charges
1 MP State
1,849.27 1,849.27
i East Discom
514.26 514.26
ii Central Discom
606.40 606.40
iii West Discom
728.61 728.61
E Costs which cannot be apportioned station wise to
be passed on to Discom's- MPPMCL Cost
1 MP State
454.76 454.76
i East Discom
139.75 139.75
ii Central Discom
153.48 153.48
iii West Discom
161.53 161.53
F Other Charges- UI/DSM and RE Charges
1 MP State
121.53 121.53
226.68 226.68
i East Discom
538.59 538.59
160.42 160.42
ii Central Discom
(418.37) (418.37)
48.25 48.25
iii West Discom
1.32 1.32
18.01 18.01
G Less: Other Income
1 MP State
730.34 730.34
i East Discom
224.43 224.43
ii Central Discom
246.49 246.49
iii West Discom
259.42 259.42
H Less: Sale of Surplus Power
1 MP State
3,855.89
1,213.90 1,213.90
True-up Petition of MP Discoms for FY 2017-18
MPPMCL, East Discom, Central Discom, West Discom P a g e | 30
Sr.
No Particulars
Quantum (MUs) Amount (₹ Crores)
Approved Actual Deviation Approved Actual Deviation
i East Discom 1,145.86
362.61 362.61
ii Central Discom 1,252.14
397.50 397.50
iii West Discom 1,457.89
453.78 453.78
I Other Adjustment Based on Reconciliation
1 MP State
(0.00) (0.00)
i East Discom
29.49 29.49
ii Central Discom
37.02 37.02
iii West Discom
(66.51) (66.51)
J Net Power Purchase Cost
1 MP State
66,126.46 66,126.46 23,848.44 27,797.89 3,949.46
i East Discom
20,347.44 20,347.44 6,937.73 8,374.22 1,436.49
ii Central Discom
22,328.20 22,328.20 7,648.31 9,404.47 1,756.16
iii West Discom
23,450.82 23,450.82 9,262.39 10,019.20 756.81
Note: Approved Quantum of Energy after consideration of sale of surplus power
2.5 Variance from approved cost in Tariff Order:
2.5.1 Power purchase Cost as per accounts for East Discom: For power procured during FY 2017-18, the power purchase cost incurred by
the Discom (as per audited accounts) inclusive of power purchase cost, inter-transmission cost, RE Charges, UI Charges and PMCL cost
was Rs. 8,374.22 Cr. which is higher by Rs. 1436.49 Cr. than the cost approved in the Tariff Order FY 2017-18.
2.5.2 Power purchase Cost as per accounts for Central Discom: For power procured during FY 2017-18, the power purchase cost incurred
by the Discom (as per audited accounts) inclusive of power purchase cost, inter-transmission cost, RE Charges, UI Charges and PMCL
cost was Rs. 9,404.47 Cr. which is higher by Rs. 1756.16 Cr. than the cost approved in the Tariff Order FY 2017-18.
2.5.3 Power purchase Cost as per accounts for West Discom: For power procured during FY 2017-18, the power purchase cost incurred by
the Discom (as per audited accounts) inclusive of power purchase cost, inter-transmission cost, RE Charges, UI Charges and PMCL cost
was Rs. 10,019.20 Cr. which is higher by Rs. 756.81 Cr. than the cost approved in the Tariff Order FY 2017-18.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 31
T3: ENERGY SALES
3.1 Number of Consumers, Connected Load and Energy Sales within the State
3.1.1 The Discoms served nearly 14,311,051number of consumers at LT level and has
around 7,032number of consumers connected at HT level during FY 2017-18. The
Petitioners aims at managing the energy procurement and sales in the most efficient
manner so that conflicting objectives of availability and cost are balanced to the
benefit of consumers. The Commission in its Tariff Order for FY 2017-18 dated 31st
March 2017 has approved the sales as projected by the Petitioners. The Petitioners has
also shown the actual numbers of consumers and connected load as reported during
the FY 2017-18.
3.1.2 The actual Number of Consumer as per prevailing tariff categories viz.-a-viz. as
approved is shown in table below:
Table 4: Number of Consumer for the FY 2017-18
Sr.no. Category Approved Actual Deviation
A LT
NO
T A
VA
ILA
BL
E I
N T
AR
IFF
OR
DE
R
NO
T A
PP
LIC
AB
LE
1 MP State 14,311,051
i East Discom 5,317,121
ii Central Discom 3,900,059
iii West Discom 5,093,871
B HT
1 MP State 7,032
i East Discom 1,480
ii Central Discom 2,240
iii West Discom 3,312
C Total
1 MP State 14,318,083
i East Discom 5,318,601
ii Central Discom 3,902,299
iii West Discom 5,097,183
3.1.3 The actual connected load as per prevailing tariff categories viz.-a-viz. as approved is
shown in table below:
Table 5: Connected Load for the FY 2017-18 (kW)
Sr.no. Category Approved Actual Deviation
A LT
NO
T A
VA
ILA
BL
E I
N
TA
RIF
F O
RD
ER
NO
T A
PP
LIC
AB
LE
1 MP State 21,325,147
i East Discom 5,958,033
ii Central Discom 6,373,685
iii West Discom 8,993,429
B HT
1 MP State 2,831,948
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 32
Sr.no. Category Approved Actual Deviation
i East Discom 847,319
ii Central Discom 856,324
iii West Discom 1,128,305
C Total
1 MP State 24,157,095
i East Discom 6,805,352
ii Central Discom 7,230,009
iii West Discom 10,121,734
3.1.4 The commission has approved the sales of 15,278 MUs, 16021 MUs and 18,426 MUs
for East Discom, Central Discom and West Discom respectively for FY 2017-18.
3.1.5 The actual sales as per prevailing tariff categories viz.-a-viz. as approved is shown in
table below:
Table 6: Sale for FY 2017-18 (MUs)
Sr.no. Category Approved Actual Deviation
A LT
1 MP State 38,330.00 35,174.17 (3,155.83)
i East Discom 12,015.00 11,008.58 (1,006.42)
ii Central Discom 12,034.00 9,908.62 (2,125.38)
iii West Discom 14,281.00 14,256.98 (24.02)
B HT
1 MP State 11,395.00 10,826.19 (568.81)
i East Discom 3,263.00 3,094.15 (168.85)
ii Central Discom 3,987.00 3,367.80 (619.20)
iii West Discom 4,145.00 4,364.25 219.25
C Total
1 MP State 49,725.00 46,000.37 (3,724.63)
i East Discom 15,278.00 14,103 (1,175.27)
ii Central Discom 16,021.00 13,276 (2,744.59)
iii West Discom 18,426.00 18,621 195.23
3.2 Hon’ble Commission in its Tariff Regulations, 2015 had defined Sales as
uncontrollable in nature which is beyond the control of the Petitioners. The category
wise sale as recorded is provided shown in the Table below:
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 33
Table 7: Month & Category wise Sale for FY 2017-18 (MUs)
B Category Wise
Low Voltage High Voltage
Total Domestic Non-
Domestic
PWW &
St. Lt.
Indl. Agri. &
Allied
Service
Railways Coal
Mines
Indl. &
Non-Indl
Seasonal
Ind.
Irrig.,
PWW &
Ors
BS Start Up
& Sync
I MP State 11,800.84 2,890.13 1,209.56 1,213.78 18,059.86 - 479.54 8,964.81 21.76 894.74 424.85 40.50 46,000.37
1 East 4,170.44 967.33 427.68 354.02 5,089.11 - 453.33 2,256.60 8.00 110.25 265.97 - 14,102.73
2 Central 3,790.38 885.26 345.78 273.43 4,613.77 - 26.21 2,976.47 1.60 207.42 146.64 9.45 13,276.41
3 West 3,840.02 1,037.54 436.10 586.33 8,356.99 - - 3,731.74 12.16 577.06 12.24 31.04 18,621.23
3.3 The Petitioners hereby request the Hon’ble Commission to approve sales as i.e. 14,102.73 MUs for the East Discom, 13,276.41 MUs for
Central Discom and 18,621.23 MUs for the West Discom aggregating to a total 46,000.37 MUs for the MP State for FY 2017-18 which
is about 3,724.63 MUs lower than that approved in the Tariff Order dated 31st March 2017 for the MP State, 1,175.27 MUs for East
Discom, 2,744.59 MUs for the Central Discom and 195.23 MUs higher for the West Discom respectively.
3.4 Method of determination of Power Purchase Cost
3.4.1 Owing to any variation in the actual loss level, the expenses towards power purchase is proposed to be shared equally between the
distribution licensee and the consumer, as the excessive loss which is a composite of technical & commercial components is not only due
to the licensee’s efficiency, in fact an active role of consumers is also required for reduction in the commercial component of the loss.
3.4.2 The method of calculation of power purchase cost for excessive loss over and above the normative loss is proposed to be as below:
3.4.3 The quantum of power purchase and the costs to be allowed or disallowed should be based on actual quantum of power purchase which
is a real authentic and verifiable item and not a derivative or notional item. The quantum of sale comprises of both Metered sales and
Un-metered sales. The un-metered sales consist of sale to agricultural pumps & BPL Domestic consumer and such quantum is an
estimate only. Therefore, there is an overlapping between un-metered sale and losses and it is always difficult to determine correctly the
percentage of un-metered sale and percentage of losses. Thus, the sales & losses to a certain extent are inter-changeable because of
estimation of un-metered sale. The sales as may not therefore be the correct basis for deciding the rate of Power Purchase Cost of
Discom.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 34
3.4.4 The quantum of power purchase and the costs to be allowed or disallowed should be
based on actual quantum of power purchase which is a real authentic and verifiable
item and not a derivative or notional item. The quantum of sale comprises of both
Metered sales and Un-metered sales. The un-metered sales consist of sale to
agricultural pumps & BPL Domestic consumer and such quantum is an estimate only.
Therefore, there is an overlapping between un-metered sale and losses and it is always
difficult to determine correctly the percentage of un-metered sale and percentage of
losses. Thus, the sales & losses to a certain extent are inter-changeable because of
estimation of un-metered sale. The sales as may not therefore be the correct basis for
deciding the rate of Power Purchase Cost of Discom.
3.4.5 Accordingly, so long as the quantum of actual power purchase is more than the
quantum of power purchase approved, no adjustments in the quantum of power
purchase need to be carried. Without prejudice to the above, even if any adjustment is
to be carried out ignoring the mixing up of un-metered sales and losses, the variation
should be solely derived from actual quantum of power purchase and not from any
other derivative numbers. The vital issues and positions are now considered more
elaborately, as below:-
The actual quantum of power purchase is to be adjusted for three elements namely:
Sales
Loss Level allowed;
Loss level not allowed.
3.4.6 In accordance with the above, loss level in excess of normative loss level ought not to
be allowed. This means energy equivalent to excessive loss level should be reduced
from actual power purchase and the balance quantum should be allowed.
(a) If we consider quantum of power purchase derived from the sale allowed (Both are
derivative quantities, however actual power purchase quantum is a real number) by
adopting a reverse calculation, it will give cumulative and double effect. The double
effect is elaborated as below:-
(b) The figure of energy sales – that is metered plus estimated unmetered sales- is in
itself, a derived quantity arising out of estimation of unmetered sales. To make it
more illustrative, we can consider all the quantities involved together in a balance
equation, as follows:
Energy purchased (actual) and served = Losses (estimated) + Energy sales
(estimated)
(c) It is very clear from the above equality, that, the only reasonably fixed and concrete
quantity is the total energy purchased (and served) and the other two quantities
appearing on the R.H.S. are complementary to each other- that is reducing one
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 35
quantity results in an equal increase in the other to maintain the balance of the
equation. That is, one of these quantities, if assumed to be known with a certain
degree of certainty, can be used to derive the other. However, this is not the case.
Under the present scenario, precise and independent measurement of both the
quantities is not possible. Hence, either one of them has to be considered as a derived
quantity based on the value of the other, and neither should be used as a reliable
decision variable from the point of view of cost determination. The result of such use
can be anomalous and unfair either to the consumers or the licensee.
(d) In the context of the explanation given above, we can consider the following two
equations to demonstrate the anomaly involved in the methodology for determination
of allowed quantum and hence the cost of power purchase, as follows:
We define,
Allowed sale = Esale
Energy allowed (Normative quantum of energy) = Enorm
Actual Energy purchase = Eact
Normative loss level (in pu) = Lnorm
Actual loss level (in pu) = Lact
It is assumed, that, the actual loss level is known with a reasonable accuracy and the
allowed sale is based on reasonable estimates and parameters of consumption.
From the definitions
Esale = Enorm *(1 - Lnorm), where Lnorm is expressed in per unit ………(1)
Also,
Esale = Eact *(1 - Lact) ………....(2)
Therefore, from (1) and (2)
Eact*(1- Lact) = Enorm* (1- Lnorm)
=>> Enorm = {Eact * (1-Lact)} / {(1-Lnorm)}
=>> Energy disallowed = Eact – Enorm
= Eact- [{Eact * (1-Lact)} / {(1- Lnorm)}]
= Eact*[1-{(1- Lact) / (1-Lnorm)}]
= Eact *[Lact-Lnorm) / (1-Lnorm)]
Finally,
Energy Disallowed = Eact*(Excess losses over normative loss level) / (1- Lnorm)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 36
(e) It is very clear from the above expression, that, working out the normative quantum of
power purchase by applying the normative loss level constraint on the allowed sales,
results in a twofold penalty – one due to the excess of loss level over the prescribed
normative loss level, and another “compounding effect” due to the factor “(1-
Lnorm)”, which is less than 1, in the denominator. The compounding effect is due to
the assumption of limiting the sales and thus assuming equivalent enhancement in
losses, which is actually a complementary quantity derived out of the allowed sales a
more or less assumed quantity (i.e. this becomes a circular feedback or merry-go-
round type of effect). In the final analysis, the allowed sale is not an independent and
a precisely determined quantity and, as such, it should not be used to determine the
allowed costs.
(f) In the last expression for disallowed quantum of power purchase, a fair and more
even-handed approach would be to simply disallow the quantum of energy
corresponding to the excess of loss level over the prescribed normative loss level. In
algebraic terms, following the notations indicated earlier, the expression can be
written as
Energy Disallowed = Eact *(Excess losses over normative loss level)
= Eact *(Lact–Lnorm),
where loss levels are expressed in per unit values (percentage values/100)
3.5 Hon’ble Tribunal of electricity in Karnataka Power Transmission Corporation Limited
vs Karnataka Electricity Regulatory Commission (Appeal No. 9 of 2008) by Order
dated 9.5.2008 has laid down as under:-
“36. …………….While arriving at the quantum of power purchase to be allowed for
revenue requirement, KERC should first reduce the disallowed T&D losses from the
quantum of power purchase entered in the audited accounts of KPTCL. From the
figure so arrived, the Commission has to reduce the allowed T&D losses which will
give the quantum of power available for sale yielding revenue. Moreover, KERC has
to realize that the audited sale quantum includes metered sale and unmetered sale
which also includes agricultural pumping sets and, therefore, there is an overlapping
between the unmetered sale and loss. In this view of the matter, we are of the opinion
that calculations should be carried out on the basis of the methodology given by
KPTCL in its Memo of Appeal at para ‘W’. We order accordingly.”
3.6 The variation in power purchase in quantum to be considered should begin with and
based on actual quantum of power purchase which is a real item and not a derivative
or notional item. The fallacy in the approach is discussed as under:-
Example:
If Licensee has procured 100 units of electricity, then a sale of 64.5 units would be
registered owing to a normative loss of 34.5%. However the licensee has actually sold
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 37
only 60 units, which would mean that the actual loss levels are at 40%, an excess loss
of 5.5% needs to be disallowed.
Table 8: Assumptions
Actual power purchase 100 units
Actual Sales 60 units
Normative loss 34.5%
Actual loss 40% (i.e. [100-60]/100)
Excess loss incurred 5.5% (i.e. 40%-34.5%)
From the aforementioned information, the power purchase and loss levels that need to
be allowed by the Hon’ble Commission can be calculated in two ways. They are:
Existing methodology:
In this methodology, the actual sales are grossed up with the normative losses to
calculate the actual power purchases. The difference between the actual power
purchases and the calculated power purchases will then be disallowed accordingly.
The calculations are shown as under:
Table 9: Calculation of disallowed units as per existing methodology
Estimated power purchase
= Sales / (1-normative loss)
= 60 units / (1-34.5%)
= 91.6 units
Total disallowed units
= Actual power purchase – Estimated power purchase
= 100 units – 91.6 units
= 8.4 units (1)
Using this methodology, total units that are to be disallowed are calculated to be 8.4
units.
3.7 The petitioners are submitting the energy balance and power purchase cost that will be
approved if the existing methodology is adopted by Commission towards the true up
exercise for FY 2017-18.
Table 10: Calculation of Energy Balance as per Existing methodology of MPERC
A Particulars Index East Central West MP State
1 Actual Sales MUs 14,102.73 13,276.41 18,621.23 46,000.37
2 Normative Loss % 17.00% 18.00% 15.50% 16.69%
3 Input at T&D Periphery (A1/1-A2) MUs 16,991.24 16,190.75 22,036.95 55,218.94
4 MP Transco Loss - Approved % 2.87% 2.87% 2.87% 2.87%
5 Input at G-T Interface (A3/1-A4) MUs 17,493.30 16,669.15 22,688.10 56,850.55
6 Inter- Transmission Losses- Approved MUs 482.00 511.00 571.00 1,564.00
7 Power Purchase Requirement (A5+A6) MUs 17,975.30 17,180.15 23,259.10 58,414.55
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 38
Table 11: Calculation of Power Purchase Cost as per Existing Methodology of MPERC
B Particulars Legend East Central West MP State
1 Total Energy Procured as per Petition MUs 20,347.44 22,328.20 23,450.82 66,126.46
2 Cost of Power Purchase as per Audited
Accounts Rs Cr 8,374.22 9,404.47 10,019.20 27,797.89
3 Supplementary Bills of Previous FYs Rs Cr 514.26 606.40 728.61 1,849.27
4 Net Power Purchase Cost (B2-B3) Rs Cr 7,859.96 8,798.07 9,290.59 25,948.63
5 Fixed Cost for FY 2017-18 Rs Cr 2,610.44 2,989.87 3,296.07 8,896.38
6 Inter Transmission Charges for FY
2017-18 Rs Cr 457.65 528.00 546.03 1,531.68
7 Intra Transmission Charges for FY
2017-18 Rs Cr 850.83 857.30 1,030.22 2,747.79
8 Other Cost of MPPMCL which cannot
be apportioned Rs Cr 139.75 153.48 161.53 454.76
9 Variable Cost for FY-17 (B4-B5-B6-B7-
B8) Rs Cr 3,801.29 4,269.42 4,256.74 12,318.02
10 Pooled Variable Rate (B9/B1*1000) Paisa/kWh 186.82 191.21 181.52 186.28
11 Quantum of Power Purchase as per
Normative Losses MUs 17,975.30 17,180.15 23,259.10 58,414.55
12 Variable Cost to be Admitted
(B10*B9/1000) Rs Cr 3,358.13 3,285.05 4,221.94 10,856.74
13 Supplementary Bills of Previous FYs
added back Rs Cr 514.26 606.40 728.61 1,849.27
14 Total Power Purchase Cost to be
Admitted (B5+B6+B7+B8+B12+B13) Rs Cr 7,931.06 8,420.10 9,984.40 26,336.61
3.8 To avoid such circumstance the following methodology is being proposed by the
Petitioners for allowing the power purchase cost on normative basis.
In the above methodology for estimating the power purchase quantum, only the
energy sale to consumer has been considered while the quantum of energy sale to
other Discoms and UI energy at Discom periphery have not been factored. Further,
the Petitioners cannot have any material control on the losses outside their periphery
i.e. M.P. Transco and PGCIL losses as they are external to their periphery and involve
complex interconnected grid. Therefore it will be appropriate to determine average per
unit rate based on the net actual energy input at Discom periphery for sale to retail
consumers only, which is a real and authentic item and may not change even after the
closure of financial year. This would also take into account the sale and purchase of
electricity between the Discom including UI within the State and also banking of
power to other States. It is to be noted that calculation of average per unit rate should
not be based on purchase at ex-bus, which may be revised by way of reconciliation of
regional/State Energy Accounts even after the closure of the financial year for which
true-up has already been carried out.
3.9 Further the petitioners state that the Hon’ble Commission’s methodology for
calculation of energy balance calculation doesn’t account for the UI sales. This results
in erroneous calculation of energy balance and the UI quantum of each Discom is left
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 39
unattended. This anomaly may kindly be considered by Hon’ble Commission. The
computation of energy balance considering the UI sales is submitted by petitioners for
Hon’ble Commission’s perusal.
Table 12: Calculation of Energy Balance considering UI Sale
Sr.no. Particulars East Central West MP state
1 Sales 14,102.73 13,276.41 18,621.23 46,000.37
2 Actual Distribution Loss (%) 27.05% 37.51% 16.57% 26.86%
3 Actual Distribution Loss (MU) 5,229.32 7,968.82 3,698.35 16,896.50
4 Input at T-D interface- Actual Drawl as
per DSM/UI Sheet 19,316.12 21,316.74 22,627.29 63,260.16
5 Input at T-D interface as per Energy
Audit/Approved by the Commission 19,332.05 21,245.24 22,319.58 62,896.86
6
Difference of MUs between Energy Audit
and Input at T-D interface including Direct
Purchase due to BUS Losses
10.71 (71.50) (307.72) (368.50)
7 Inter State UI at Discom Periphery 538.59 (418.37) 1.32 121.53
8 Total Schedule Energy at T-D interface
including UI 18,777.54 21,735.11 22,625.97 63,138.62
9 External & Transmission Losses (MUs) 593.09 824.85 (343.16) 1,569.90
10 Ex-Bus Requirement Schedule Energy as
per MPPMCL Statement 20,347.44 22,328.20 23,450.82 66,126.46
Proposed methodology:
3.10 In this methodology, the licensee adopts the Hon’bleAptel’s judgement, which states
that the actual power purchases are to be considered for computation of excess losses.
Illustrative calculations are shown below:
Table 13: Calculation of disallowed units as per proposed methodology
Actual power purchase = 100 units
Excess loss% as per Table 26 = 5.5%
Excess loss incurred = 5.5 units (i.e. 100 units x 5.5%)
Allowable power purchases
= Actual power purchase – Excess loss incurred
= 100 units – 5.5 units
= 94.5 units
Total disallowed units = 100 units – 94.5 units
= 5.5 units (2)
It can be observed from Table 9: Calculation of disallowed units as per existing
methodology and Table 13: Calculation of disallowed units as per proposed
methodology that there is a difference of 2.9 units (i.e. 8.4 units – 5.5 units) in the
total disallowed losses. As a result, the licensee has to bear the cost of additional
disallowance of 2.9 units. Therefore quantum of power purchase should be disallowed
by only 5.5 units by adopting the top down approach that starts with power purchases
on which losses are calculated.
3.11 To sum up the bottom to top methodology results in a compounded effect which
unfairly enhances the amount of disallowed costs. It may be further highlighted, that,
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 40
the terms and phrases like “normative quantum” or “allowed or disallowed quantum”
of energy are erroneous and inappropriate and they have been used only to illustrate
the logic and reasoning involved. The only concrete terms are total energy purchased,
the total cost of power procurement, disallowed costs and allowed costs. Hence, the
Hon’ble Commission should consider the total quantum of power procured as the
given quantity and deal only in terms of allowed and disallowed costs corresponding
to excess of loss level over the normative loss level. The terms “allowed” or
“disallowed quantum” of energy may be altogether dispensed with and the entire
actual quantum of energy purchased should be accepted and recognized- a quantity
which is indisputable and which cannot and should not be altered retrospectively
without any adequate reference to the various factors and situations existing at the
time.
3.12 In light of the above discussions, the loss levels mentioned pertain only to the losses
occurring within the Discoms’ periphery. However, MPERC may not disallow losses
occurring outside the Discom periphery (i.e. the inter-state and intra-state transmission
losses) on the basis of the normative quantum of energy required at the Discoms’
periphery. In principle, this approach requires proper attention to the factors and
mechanisms involved. The Discoms cannot have any material control over the losses
occurring outside their periphery- not the least because they are external to its
boundaries and involving a complex interconnected grid with numerous points,
directions and routes for entry and exit of power, but also because they actually are
“apportioned losses”, or so to say, “deemed losses” based on a working rule or
formula adopted for State-wise and Discom-wise segregation of the pooled energy
losses occurring in the inter-regional/state and intra-state transmission systems. As a
matter of a significant detail, the inter-region/state transmission losses are themselves
apportioned to a particular state from the energy appearing as pooled transmission
losses under the inter-region/state energy accounting mechanism (i.e. the so called
balancing and settlement mechanism). Thus, these losses are, so to say “re-
apportioned” and allocated to the Discoms operating in a particular state- that is
energy “apportioned” out of energy already “apportioned”- that is, it involves
cascaded apportioning. Similarly, the intra-state transmission losses have to be
apportioned to the Discoms according to some working rule- rather than a precise
measurement. In this sense, the transmission losses, with reference to a particular
Discom, are entirely a notional quantity – with one of its component being a “doubly
notional” quantity- rather than a real measured variable. Therefore, it can be stated
firmly and with proper reasoning, that the Hon’ble Commission may not tamper with
and modify the quantum of energy loss apportioned to the licensee which is
traditionally termed and indicated as the losses occurring in the inter/intra state
transmission systems.
Proposed methodology for calculating power purchase cost for disallowed units:
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 41
3.13 As per the existing methodology, the Hon’ble Commission allows an average power
purchase cost that includes both fixed cost as well as variable cost for the power
purchase quantum at ex-bus (which excludes UI, inter-Discom, inter-State sales and
Banking). Further, the Petitioners cannot have any material control on the losses
outside their periphery i.e. M.P. Transco and PGCIL losses as they are external to
their periphery and involve complex interconnected grid. Therefore it will be
appropriate to determine average per unit rate based on the net actual energy input at
Discom periphery for sale to retail consumers only, which is a real and authentic item
and may not change even after the closure of financial year. This would also take into
account the sale and purchase of electricity between the Discom including UI within
the State and also banking of power to other States. It is to be noted that calculation of
average per unit rate should not be based on purchase at ex-bus, which may be revised
by way of reconciliation of regional/State Energy Accounts even after the closure of
the financial year for which true-up has already been carried out.
3.14 The Hon’ble Commission is required to determine the cost of power purchase to be
adjusted (disallowed) in the revenue requirement of the Petitioners for the quantum of
power purchase disallowed by applying the basic principle that all such costs and
expenses on average basis, which the appellant may have avoided if the quantum of
power purchase disallowed has not been purchased. The fixed charges such as
capacity charges and other related commitment charges are payable to the generating
companies for long term and medium term contracted capacity, irrespective of actual
drawal of electricity. In addition the transmission and related charges payable to CTU,
STU and Load Despatch Centre, reimbursement of taxes, duties and other levies to
generating companies and transmission companies and similar such cost and expenses
ought not to be disallowed as they cannot be avoided by reducing the power purchase.
The variable charge (energy charge) that could have been saved on such purchase can
only be disallowed for adjustment in ARR.
3.15 To avoid such complex method, it would be appropriate to disallow the % of variable
cost of power purchase which is more than the % of normative loss level and thus
balance cost of power purchase ought to be allowed, which is elaborated as per the
calculation as given below.
Table 14: Calculation of cost of disallowed power purchase units as per proposed methodology
Actual power purchase cost = Rs. 100
Fixed charges = Rs. 30
Variable charges = Rs. 70
Excess loss% as per Table 26 = 5.5%
Cost to be disallowed on account
of excess loss
= 5.5% * Rs. 70
= Rs. 3.85
Allowable power purchase cost
= Actual power purchase cost – Cost towards excess loss
= Rs. 100 – Rs. 3.85
= Rs. 96.15
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 42
3.16 In view of above the Power Purchase cost for the year 2017-18 may please be
considered as indicated in the following tables:-
Table 15: Details of power purchase cost to be allowed for East Discom FY 2017-18 (Rs Cr)
Sr.no. Particulars Actual PP to be
allowed
Variance
1 Normative loss level 17.00% - -
2 Actual loss level 27.05% - -
3 Loss over and above the normative loss 10.05% - -
4 Fixed cost (Rs. Cr) 2,610.44 2,610.44 -
5 Previous years' supplementary bills of Generators
(Rs Cr) 514.26 507.52 6.74
6 Variable cost (Rs. Cr) 3,923.29 - -
Sale of additional power (Rs. Cr) 362.61 - -
Other Income (Rs. Cr) 224.43 - -
Variable cost after adjusting Sale of additional
Power & Other income (Rs. Cr) 3,336.24 3,000.95 335.29
Other Charges (Total FPA charges +Income
Tax+ED, Cess, Heavy Water charge, water
charges+MOPA, Insurance+Any Other charges)
272.32 244.96 27.37
Other costs passed to Discoms - which cannot be
apportioned station wise- 139.75 139.75 -
7 Inter state Transmission charges for FY 2013-14
(Rs. Cr) 457.65 457.65 -
9 Supplymetnory Cost of FY 2014-15 &FY 2015-16
based on Reconcialation of MPPMCL (Rs Cr) 29.49 26.53 2.96
MPPMCL Power Purchase Cost (Rs Cr) 7,360.15 6,987.79 372.36
Supplymentory bills of Previous year 1.73 1.73 -
10 Power Purchase from others 4.14 4.14 -
11 UI/DSM Charges (Rs Cr) 158.82 158.82 -
12 Reactive Energy Charges (Rs Cr) -
4.27 -
4.27 -
13 Intra state Transmission Charges (Rs. Cr) 850.83 850.83 -
14 SLDC Charges 2.82 2.82 -
Other adjustments - - -
Total Power Purchase Cost to be allowed (Rs Cr) 8,374.22 8,001.86 372.36
Table 16: Details of power purchase cost to be allowed for Central Discom FY 2017-18 (Rs Cr)
Sr.no. Particulars Actual PP to be
allowed
Variance
1 Normative loss level 18%
2 Actual loss level 37.51%
3 Loss over and above the normative loss 19.51%
4 Fixed cost (Rs. Cr) 2,989.87 2,989.87 -
5 Previous years' supplementary bills of Generators
(Rs Cr) 606.40 594.89 11.51
6 Variable cost (Rs. Cr) 4,506.26
Sale of additional power (Rs. Cr) 397.50
Other Income (Rs. Cr) 246.49
Variable cost after adjusting Sale of additional 3,862.26 3,108.78 753.48
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 43
Sr.no. Particulars Actual PP to be
allowed
Variance
Power & Other income (Rs. Cr)
Other Charges (Total FPA charges +Income
Tax+ED, Cess, Heavy Water charge, water
charges+MOPA, Insurance+Any Other charges)
318.87 256.66 62.21
Other costs passed to Discoms - which cannot be
apportioned station wise- 153.48 153.48 -
7 Interstate Transmission charges for FY 2013-14 (Rs.
Cr) 528.00 528.00 -
9 Supplementary Cost of FY 2014-15 &FY 2015-16
based on Reconciliation of MPPMCL (Rs Cr) 37.02 29.80 7.22
MPPMCL Power Purchase Cost (Rs Cr) 8,495.91 7,661.49 834.42
Supplementary bills of Previous year 35.38 35.38 -
10 Power Purchase from others
- -
11 UI/DSM Charges (Rs Cr) 9.39 9.39 -
12 Reactive Energy Charges (Rs Cr) 3.48 3.48 -
13 Intra state Transmission Charges (Rs. Cr) 857.30 857.30 -
14 SLDC Charges 3.01 3.01 -
Other adjustments
Total Power Purchase Cost to be allowed (Rs Cr) 9,404.47 8,570.05 834.42
Table 17: Details of power purchase cost to be allowed for West Discom FY 2017-18 (Rs Cr)
Sr.no. Particulars Actual PP to be
allowed
Variance
1 Normative loss level 15.50%
2 Actual loss level 16.57%
3 Loss over and above the normative loss 1.07%
4 Fixed cost (Rs. Cr) 3,296.07 3,296.07 -
5 Previous years' supplementary bills of Generators
(Rs Cr) 728.61 724.90 3.71
6 Variable cost (Rs. Cr) 4,691.99
Sale of additional power (Rs. Cr) 453.78
Other Income (Rs. Cr) 259.42
Variable cost after adjusting Sale of additional
Power & Other income (Rs. Cr) 3,978.79 3,936.22 42.57
Other Charges (Total FPA charges +Income
Tax+ED, Cess, Heavy Water charge, water
charges+MOPA, Insurance+Any Other charges)
322.84 319.39 3.45
Other costs passed to Discoms - which cannot be
apportioned station wise- 161.53 161.53 -
7 Interstate Transmission charges for FY 2013-14 (Rs.
Cr) 546.03 546.03 -
9 Supplementary Cost of FY 2014-15 &FY 2015-16
based on Reconciliation of MPPMCL (Rs Cr) (66.51) (65.80) (0.71)
MPPMCL Power Purchase Cost (Rs Cr) 8,967.36 8,918.33 49.03
Supplementary bills of Previous year
- -
10 Power Purchase from others
- -
11 UI/DSM Charges (Rs Cr) 19.32 19.32 -
12 Reactive Energy Charges (Rs Cr) (1.31) (1.31) -
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 44
Sr.no. Particulars Actual PP to be
allowed
Variance
13 Intra state Transmission Charges (Rs. Cr) 1,030.22 1,030.22 -
14 SLDC Charges 3.61 3.61 -
Other adjustments
Total Power Purchase Cost to be allowed (Rs Cr) 10,019.20 9,970.17 49.03
3.17 Comparison of power purchase cost as per Commission Methodology &
Proposed Methodology by petitioners
3.17.1 There is an overall difference of Rs 205.47 Cr which may be allowed additionally to
the petitioners if the proposed methodology as proposed by the petitioners is adopted
by Hon’ble Commission.
3.17.2 Petitioners humbly request Hon’ble Commission to consider the methodology as
proposed by it for allowance of power purchase cost. The details of variation is
tabulated as shown below.
Table 18: Comparison of Costs – Commission’s Methodology Vs Petitioner’s Methodology (Rs Cr.)
Sr.no Particulars East Central West MP State
1 Power Purchase Cost as per Commission’s
Methodology 7,931.39 8,420.80 9,984.43 26,336.61
2 Power Purchase Cost as per proposed
Methodology by petitioners 8,001.86 8,570.05 9,970.17 26,542.08
3 Difference 70.47 149.25 (14.26) 205.47
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 45
T4: OPERATION & MAINTENANCE COST
4.1 The Commission‘s Regulations on Terms and Conditions for Determination of Tariff
for Supply and Wheeling of Electricity and methods and Principles for Fixation of
Charges) Regulations, 2015 define the norms of O&M Expenses of each licensee.
4.2 As per para 34.1 of above mentioned regulations, 2015, O&M expenses shall be
determined for the Tariff Period based on normative O&M expenses specified by the
Commission in these Regulations. The O&M expenses comprise of employee cost,
repairs & maintenance (R&M) cost and administrative & general (A&G) cost. The
norms for O&M expenses have been fixed on the basis of past audited figures of the
Distribution Licensees. These norms exclude dearness allowance, pension, terminal
benefits and incentive to be paid to employees, taxes payable to the Government,
MPSEB expenses and fee payable to MPERC. The Distribution Licensee shall claim
the dearness allowance, pension and terminal benefits, taxes payable to the
Government and fees to be paid to MPERC separately as actual. The claim of
expenses towards pension and terminal benefits shall be dealt with as indicated in the
MPERC (Terms and Conditions for allowing pension and terminal benefits liabilities
of personnel of Board and successor entities) regulations, 2012.
4.3 Hon’ble Commission had approved net O&M Expenses to the extent of Rs. 1368.18
Cr, Rs1284.61 and Rs1341.09Cr for East Discom, Central Discom and West Discom
respectively in its Tariff order for FY 2017-18, which was based on the norms as
provided in the Terms and Conditions of Tariff Regulation, 2015.
4.4 The claim of the petitioners towards the true up of O&M cost for FY 2017-18 is
submitted as below for Hon’ble Commission’s kind perusal and consideration.
Table 19: Details of O&M cost claimed towards true up of FY 2017-18
Sr.
no.
Particulars Index Discom Allowed in
TO
(A)
Claimed
(B)
Variance
(B-A)
1
Employee Cost
(Including terminal
benefits)
Rs Cr EZ 1,037.28 822.48 214.80
Rs Cr CZ 997.17 1,127.85 (130.68)
Rs Cr WZ 1,067.45 731.24 336.21
Rs Cr MP State 3,101.90 2,681.57 420.33
3
Administrative &
General Expenses
including MPERC Fees
Rs Cr EZ 179.50 218.90 (39.40)
Rs Cr CZ 103.50 133.55 (30.05)
Rs Cr WZ 138.50 152.73 (14.23)
Rs Cr MP State 421.50 505.18 (83.68)
4 Repair & Maintenance
Expenses
Rs Cr EZ 151.40 168.84 (17.44)
Rs Cr CZ 183.94 145.58 38.36
Rs Cr WZ 135.14 136.32 (1.18)
Rs Cr MP State 470.48 450.74 19.74
5 Total O&M Charges
Rs Cr EZ 1,368.18 1,210.22 157.96
Rs Cr CZ 1,284.61 1,406.98 (122.37)
Rs Cr WZ 1,341.09 1,020.29 320.80
Rs Cr MP State 3,993.88 3,637.49 356.39
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 46
4.5 Submission of East Discom:
4.5.1 For FY 2017-18, O&M expenses are Rs 1,210.22 Cr. which comprises of employee’s
expenses to the tune of Rs. 822.48Cr (expense capitalised Rs28.91 Cr and net expense
is Rs 793.57 Cr), R&M expenses to the tune of Rs. 168.84Cr (expense capitalised
Rs7.06Cr and net expense is Rs161.78 Cr)and A&G expenses Rs218.90Cr. The
petitioner is also claiming the cost of actual cash outflow towards terminal benefits to
the tune of Rs41.28Cr which is not a part of Transco’s ARR.
4.5.2 Therefore, it is submitted that O&M expenses as per the claim of the petitioner to
the tune of Rs 1210.22 Cr. for FY 2017-18may please be considered towards true
up.
4.6 Submission of Central Discom:
4.6.1 The petitioner hereby requests the Hon’ble Commission to allow Rs. 1,127.85Cr
including of terminal benefits of Rs. 5.09 Cr towards Employee expenses, A&G
expenses of Rs. 133.55Cr, and R&M expenses of Rs. 145.58Cr for FY 2017-18.
4.6.2 Therefore, it is submitted that O&M expenses as per the claim of the petitioner to
the tune of Rs 1,406.98 Cr for FY 2017-18 may please be considered towards true
up.
4.7 Submission of West Discom
4.7.1 The petitioner hereby requests the Hon’ble Commission to allow Rs. 731.24Cr
including of terminal benefits of Rs. 14.84 Cr towards Employee expenses, A&G
expenses of Rs. 152.73Cr, and R&M expenses of Rs. 136.32Cr for FY 2017-18.
4.7.2 Therefore, it is submitted that O&M expenses as per the claim of the petitioner to
the tune of Rs 1,019.99 Cr. for FY 2017-18 may please be considered towards
true up.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 47
T5: INTEREST & FINANCE CHARGES
5.1 Interest on Project Loans
The Hon’ble Commission in its Tariff Order dated 31st March 2017 had approved
Interest on Project Loans as Rs.106.69 Cr for the East Discom, Rs. 238.10Cr for the
Central Discom, Rs 67.53 Cr for the West Discom and Rs. 412.32 Cr for the MP State
respectively.
5.2 Submission of East Discom:
5.2.1 The actual/accrued interest on project loans of the petitioner for the year FY 2017-18
is Rs922.81 Cr. The weighted average rate of interest worked out based on the actual
project loans has been utilised for the calculation of interest on project loans as per the
normative basis.
5.2.2 The details of the claim of the petitioner towards interest and finance charges is
shown as below in the following table
Table 20: Details of Finance Charges Claimed by East Discom for True-up FY 2017-18 (Rs Cr)
Particulars
As per
Audited
Accounts
As Approved
in Tariff
Order
Claimed
Opening Debt associated with GFA (as on 01st April
2017 as Per Tariff Order for FY 2017-18)
94.75 1,611.30
GFA Addition During the FY 485
Consumer Deposit and Grants utilized during the FY 243.89
Net GFA Addition during the FY 241.26
70% of addition to net GFA considered as funded
through debt
168.88
Debt repayment during the FY (Equal to Depreciation) 335.28
Closing debt associated with GFA 1,444.90
Average debt associated with GFA 1,528.10
Weighted Average Interest Rate (%) 8.97%
Interest on Project Loan 137.13
11.95
Add: Other Finance Cost
On loans from banks 30.47
On loans from government 82.94
On Perpetual loans from government 880.41
Bank Commission & Other Charges 5.11 5.11
Cost of Raising Finance, Gurantee Charges & Stamp
Duty, Commitment Charges
3.82 3.82
Penalty Charges of Delayed Payment or Rebate to
Consumers on Timely Payment
4.02 4.02
Total Interest on Project Loan 1006.77
Interest expenses capitalsed -83.96 -
Net Interest on Project Loan 922.81 106.69 150.08
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 48
5.3 Submission of Central Discom
5.3.1 The actual net interest payments against current dues in FY 2017-18 (excluding any
payments against previous year defaults of principal or interest or any penal charges
on such defaults) is Rs. 6.37 Cr.
5.3.2 The details of the claim of the petitioner towards interest and finance charges for
project loans is shown as below in the following table
Table 21: Details of Finance Charges Claimed by Central Discom for True-up FY 2017-18 (Rs Cr)
Particulars Approved in
Tariff
Order
Claimed
Total interest payments against current dues in financial year (not
including any payments against previous year defaults of
principal or interest or any penal charges on such defaults)
6.37
Interest capitalized to project works -
Net Interest on Project Loan 238.10 6.37
5.4 Submission of West Discom
5.4.1 The actual/accrued interest on project loans of the petitioner for the year FY 2017-18
is Rs906.96 Cr. The weighted average rate of interest worked out based on the actual
project loans has been utilised for the calculation of interest on project loans as per the
normative basis.
5.4.2 The details of the claim of the petitioner towards interest and finance charges is
shown as below in the following table
Table 22: Details of Finance Charges claimed by West Discom for True-up of FY 2017-18
Particular Approved in
Tariff Order
Claimed Variance
A Opening Debt associated with GFA (as on 01st April
2017 as Per FY 2016-17 True-up Petition) 465.85
B GFA Addition During the FY
603.94
C Consumer Deposit and Grants
utilized during the FY 517.45
D Net GFA Addition during the FY
86.49
E 70% of addition to net GFA
considered as funded through debt 60.54
F Debt repayment during the FY (Equal to
Depreciation) 244.33
G Closing debt associated with GFA
282.06
H Average debt associated with GFA
373.96
I Weighted Average Interest Rate (%)
9.16%
J Interest on Project Loan 58.58 34.24
-
K Add: Other Finance Cost
10.27
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 49
Particular Approved in
Tariff Order
Claimed Variance
i Bank Commission & Other Charges
8.95
6.74
ii Cost of Raising Finance, Gurantee Charges & Stamp
Duty, Commitment Charges 0.45
iii Penalty Charges of Delayed Payment or Rebate to
Consumers on Timely Payment 3.08
II Net Interest on Project Loan 67.53 44.51 - 23.02
5.4.3 West Discom thus requests the Hon’ble Commission for the approval of Interest and
Finance Charges of Rs. 44.51 Cr on account of true up towards Interest on project
loan.
5.5 Interest on Working Capital Loans
5.5.1 The Commission in the Tariff Order for FY 2017-18 has allowed Rs. 85.97 Cr for
East Discom, Rs. 46.38 Cr for Central Discom and Rs. 63.99 Cr for West Discom as
interest on the working capitalas per the norms specified in the Regulation.
5.6 Submission of East Discom:
5.6.1 The petitioner submits that the interest on working capital approved in the tariff order
was Rs85.97 Cr which was based on the norms as specified in the terms and
conditions of tariff regulations, 2015.
5.6.2 The petitioner submits that it has computed the interest on working capital component
as per the provisions of regulations. The interest on working capital as claimed by the
petitioner towards true up of FY 2017-18 is Rs72.61Cr.
5.6.3 The detailed computation of the same is submitted hereby for Hon’ble Commission’s
kind perusal.
Table 23: Details of Interest on Working Capital Claimed by East Discom in True up of FY 2017-18
For Wheeling activity
Sr.
No.
Particulars Allowed in
Tariff Order
Actual
A) 1/6th of annual requirement of inventory for previous year at 1 %
GFA for previous year (80%)
8.78 55.94
B) Total of O&M expenses 1,368.18 1,210.22
B) i) 1/12th of total 114.02 100.85
C) Receivables - -
C) i) Annual Revenue from wheeling charges** - -
C) ii) Receivables equivalent to 2 months average billing of wheeling
charges
- -
D) Total Working capital 122.80 156.79
(A), B) i), C) ii))
E) Rate of Interest * 14.00% 13.85%
F) Interest on Working capital -wheeling 17.19 21.72
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 50
For Retail Sale activity
Sl. No. Particulars Allowed in
Tariff Order
Actual
A) 1/6th of annual requirement of inventory for previous year (20%) 2.19 13.98
B) Receivables -
B) i) Annual Revenue 8,624.42 8,332.88
B) ii) Receivables equivalent to 2 months average billing 1,437.40 1,388.81
C) Power Purchase expenses 5,746.67 5,611.39
C) i) 1/12th of power purchase expenses 478.89 467.62
D Consuner Security Deposit 469.42 724.51
E) Total Working capital (A+B ii) - C i) - D) 491.29 210.67
F) Rate of Interest * 14.00% 13.85%
G) Interest on Working capital -Retail 68.78 29.18
Total Interest on Working capital -Wheeling 17.19 21.72
Net Interest on Working capital -Retail 68.78 50.89
Total Interest on Working Capital(Wheeling+Retail) 85.97 72.61
5.7 Submission of Central Discom
5.7.1 Interest on Working Capital as approved in the Tariff order for the period FY17-18
was Rs. 46.38 Cr. However, the actual interest on Working Capital for the Licensee is
Rs. 35.69 Cr as per Actuals for FY 2017-18.
5.7.2 It is worthwhile to mention that every organization needs funds for short-term
purposes to finance current Investment in short term assets like cash, inventories,
debtors etc. Every organization needs working capital for carrying out day-to-day
operations smoothly. Even an organization which is fully equipped with all types of
fixed assets required is bound to collapse without adequate Working capital. Working
Capital is thus like the lifeline for a business. It is submitted that licensees have also
borrowed fund as Working Capital Loan from GoMP/Banks & FI’s to meet out their
day-to-day expenses, on which GoMP charges interest and is payable by the licensees.
5.7.3 Thus, the licensee hereby prays to Hon’ble Commission to allow interest on
working capital as per actuals of the audited accounts to meet out its actual
expenditure incurred in FY 2017-18 and allow expenses on account of interest on
Working Capital to the tune of Rs. 35.69 Cr.
5.8 Submission of West Discom
5.8.1 The petitioner submits that Hon’ble Commission in its tariff order dated 31st
March’2017 has allowed Rs. 63.99 Cr towards interest on working capital in respect
of West Discoms as per the norms specified in the Terms & Conditions of Tariff
Regulations, 2015.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 51
5.8.2 The petitioner submits that it has computed the interest on working capital component
as per the provisions of regulations. The interest on working capital as claimed by the
petitioner towards true up of FY 2017-18 is Rs 37.73 Cr.
5.8.3 The detailed computation of the same is submitted hereby for Hon’ble Commission’s
kind perusal.
Table 24: Details of Interest on Working Capital Claimed by West Discom in True up of FY 2017-18
A Interest on Working Capital - Retail As per the
Tariff
Order
As per the
Regulations
Variance
Inventory - 20% of 2 Month Proportionate of 1% GFA 1.96 1.98
O&M Expenses - 10% of 1 Month Proportionate - 8.50
Revenue from Retail -2 Month 1,787.47 2,007.42
Gross Working Capital Requirement 1,789.43 2,017.90
Less: Power Purchase Cost - 1 Month 645.09 830.85
Less: Consumer Security Deposit 807.34 973.29
Net Working Capital Requirement 337.00 213.76
Interest Rate on Working Capital (%) 14.00% 12.60%
Interest - Retail 47.18 26.93
B Interest on Working Capital - Wheeling
Inventory - 80% of 2 Month Proportionate of 1% GFA 7.83 7.90
O&M Expenses - 90% of 1 Month Proportionate 111.76 76.50
Revenue from Wheeling - 2 Month 0.48 1.28
Net Working Capital Requirement 120.07 85.68
Interest Rate on Working Capital (%) 14.00% 12.60%
Interest - Wheeling 16.81 10.80
C Interest on Working capital 63.99 37.73 (26.26)
5.9 Interest on Consumer Security Deposit
5.9.1 Interest on Consumer Security Deposit (CSD) approved in the Tariff Order for the
period FY 2017-18 was Rs31.69 Cr, Rs56.16 Cr and Rs54.50 Cr for East Discom,
Central Discom and West Discom respectively.
5.9.2 Hon’ble Commission approved the interest on consumer security deposit which was
based on the Security Deposit Regulations, 2005 read with subsequent Amendments
to the Regulations and the Terms and Conditions of Tariff Regulation, 2015.
5.9.3 However, the actual Interest on consumer security deposits for the period FY 2017-18
for the East Discom was Rs55.79 Cr, Central Discom was Rs52.89Cr and West
Discom was Rs63.59Cr.
5.9.4 The details of the consumer security deposit and the interest paid on the same for the
year is submitted hereby for Hon’ble Commission’s kind perusal.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 52
Table 25: Details of Interest on Consumer Security Deposit claimed for the year FY 2017-18
Discom Allowed in the
Tariff Order
Actual as per
Accounts
Variance
EZ 31.69 55.79 (24.10)
CZ 56.16 52.89 3.27
WZ 54.50 63.59 (9.09)
MP State 142.34 172.27 (29.93)
5.9.5 The petitioners thus prays to allow Rs. 172.27 Cr on account of Interest on Consumer
Security Deposits for FY 2017-18.
5.10 Summary of Interest and Finance Charges
5.10.1 The petitioners hereby submit that an amount of Rs278.48 Cr, Rs94.95 Cr and Rs
145.83 Cr may be kindly approved against interest and finance charges for East
Discom, Central Discom and West Discom respectively towards true up of FY 2017-
18.
5.10.2 The summary of the interest and finance charges is shown in the table below:
Table 26: Summary of Interest and Finance Charges claimed towards True up of FY 2017-18
Sr.
no.
Source Index Discom Allowed in
the Tariff
Order
Actual as
per
Accounts/
regulation
Variance
1 Interest and Finance
charges on Project Loans
Rs Cr EZ 106.69 150.08 (43.39)
Rs Cr CZ 238.10 6.37 231.73
Rs Cr WZ 67.53 44.51 23.02
Rs Cr MP State 412.32 200.96 211.36
2
Interest on Working
Capital Loan Claimed as
per regulation/audited
accounts
Rs Cr EZ 85.97 72.61 13.36
Rs Cr CZ 46.38 35.69 10.69
Rs Cr WZ 63.99 37.73 26.26
Rs Cr MP State 106.88 146.03 (39.15)
3
Interest on consumer
Security Deposit as per
accounts
Rs Cr EZ 31.69 55.79 (24.10)
Rs Cr CZ 56.16 52.89 3.27
Rs Cr WZ 54.50 63.59 (9.09)
Rs Cr MP State 225.28 172.27 53.01
4 Total Interest & Finance
Charges (1+2+3)
Rs Cr EZ 224.35 278.48 (54.13)
Rs Cr CZ 340.64 94.95 245.69
Rs Cr WZ 186.02 145.83 40.19
Rs Cr MP State 751.01 519.26 231.75
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 53
T6: DEPRECIATION AND RELATED DEBITS
6.1 Hon’ble Commission in its Tariff Order dated 31st March, 2017 had approved
depreciation net of consumer contribution & grants as Rs. 116.50 Cr for the East
Discom, Rs. 159.54 Cr for the Central Discom and Rs. 105.05 Cr for the West
Discom respectively
6.2 As per the Second Amendment to MPERC (Recovery of expenses and other charges
for providing Electric Line or Plant used for the purpose of giving Supply)
(Revisions-I) Regulations, 2009 (RG-31(I) of 2009), the manner of the recognition of
asset created through consumer contribution as well as depreciation thereon has been
elaborated. Further Accounting Standard 12, provides guidance on the asset created
through government grant. Accordingly, as per provision of the Regulation,
Discomcan charge depreciation on the full amount of asset and amortizes the
corresponding amount from grant to the P&L account. Therefore, treatment given by
the Discom in the accounts is in line with the Regulation (RG-31) and prevailing
Accounting Standards.
6.3 Further, the Petitioner’s adopted the rate of depreciation notified by the Hon’ble
Commission in Regulation from the FY 2010-11 as per the clarification issued by the
Ministry of Corporate Affairs vide general circular No 31/2011 dated 31st May 2011.
Since, Discoms adopted rate of Regulation only from FY 2010-11, a separate
depreciation model was used to consider depreciation as per regulation since FY
2006-07. Accordingly, the Petitioner’s (West Discom) has considered the
Depreciation for FY 2017-18.
6.4 Depreciation has been charged in the books of the Licensee for the Assets capitalized
during the year and as the beginning of the year in consistent with the rates of
depreciation specified in MPERC (Terms and Conditions for Determination of Tariff
for Supply and Wheeling of Electricity and Methods and Principles for Fixation of
Charges) Regulations, 2015 regulation, details are as given in the table below:
Table 27: Details of Depreciation Claimed by petitioners for FY 2017-18
Sr.
no.
Discom Allowed in the
Tariff Order
(A)
Actual Claimed
now as Per
Regulation /
Accounts
(B)
Variance
(A-B)
1 EZ 116.50 335.28 (218.78)
2 CZ 159.54 300.71 (141.17)
3 WZ 105.05 244.33 (139.28)
4 MP State 381.09 880.33 (499.24)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 54
6.5 Submission of East Discom:
6.5.1 The Licensee hereby prays to the Hon’ble Commission to allow depreciation of
Rs335.28 Cr as per the audited accounts over against the approved depreciation of
Rs.116.50for East Discom in the Tariff Order for the period FY 2017-18.
6.6 Submission of Central Discom
6.6.1 The Licensee hereby prays to the Hon’ble Commission to allow depreciation of
Rs300.71 Cr as per the audited accounts over against the approved depreciation of
Rs.159.54 for Central Discom in the Tariff Order for the period FY 2017-18.
6.7 Submission of West Discom
6.7.1 The petitioner has calculated the depreciation of Rs. 244.33Cr as per regulations for
FY 2017-18 based on the detailed depreciation model used for working out is also
being submitted as an Annexure.
6.7.2 In view of the above, the petitioner requests the Hon’ble Commission may kindly
approve the amount of Rs244.33 towards true up of depreciation for FY 2017-18.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 55
T7: BAD AND DOUBTFUL DEBTS
7.1.1 The Hon’ble Commission in its Tariff Order for FY 2017-18 dated 31st March 2017
had approved bad debts amounting to Rs. 2 Cr for each Discom. The Petitioners has
considered the bad debts as per audited accounts for FY 2017-18 as shown below:
7.2 Submission of East Discom
7.2.1 Actual Bad and Doubtful Debts as per Annual Accounts is Rs14.75Cr.The Petitioner
has claimed only the actual bad debts to the tune of Rs14.75 Cr. that were actually
written off in the annual accounts of FY 2017-18, which may be allowed in true-up of
FY 2017-18.
7.3 Submission of Central Discom
7.3.1 The petitioner submits that the actual bad and doubtful debts written off during the FY
2017-18 was Rs 23.28 Cr and the petitioner humbly submits the Hon’ble Commission
that it may kindly consider the claim of the petitioner in this regard towards true up o
f bad debts for FY 2017-18.
7.4 Submission of West Discom
7.4.1 The petitioner submits that the actual bad and doubtful debts written off during the FY
2017-18 was Rs237 Cr and the petitioner humbly submits the Hon’ble Commission
that it may kindly consider the claim of the petitioner in this regard towards true up of
bad debts for FY 2017-18.
7.4.2 The claim of the petitioners is shown in the table for Hon’ble Commission’s kind
perusal and further consideration.
Table 28: Details of Bad and Doubtful debts Claimed by petitioners for FY 2017-18
Sr.no. Discom Allowed in the
Tariff Order
Actual Claimed
As Per
Accounts
Variance
1 East Discom 2.00 14.75 (12.75)
2 Central Discom 2.00 23.28 (21.28)
3 West Discom 2.00 237.00 (235.00)
4 MP State 6.00 275.03 (269.03)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 56
T8: OTHER EXPENSES
8.1 Submission of West Discom
8.1.1 The licensee submits that the amount towards prior period credits including other
expenses is Rs0.52 Cr. The details of the same are as shown in the table below:
Table 29: Other Expenses Claimed as true up for FY 2017-18
Sr.no. Particulars Allowed in the
Tariff Order
Actual Claimed
As Per
Accounts
1 Sundry Expenses/Miscellaneous Losses - 0.52
8.1.2 In view of the position explained above, the petitioner prays to the Hon’ble
Commission to approve the other expenses amounting to Rs0.52 Cr on account of true
up of FY 2017-18.
8.2 Exceptional Items
8.2.1 Submission of East Discom
8.2.1.1 It is submitted that with reference to a letter no. 7045/R-4197/2015/XIII, from PS
Energy, Bhopal dated 06/11/2017, M. P. Power Transmission Co. Ltd., Jabalpur has
written off liabilities of Discom to an extent of Rs. 141.06 Cr. This liability of
wheeling charges towards MPPTCL has reflected in P&L as other expenses item and
has not been claimed for the purpose of true-up.
8.2.2 Submission of Central Discom
8.2.2.1 It is submitted that with reference to a letter no. 7045/R-4197/2015/XIII, from PS
Energy, Bhopal dated 06/11/2017, M. P. Power Transmission Co. Ltd., Jabalpur has
written off liabilities of Discom to an extent of Rs. 123.66 Cr. This liability of
wheeling charges towards MPPTCL has reflected in P&L as other expenses item and
has not been claimed for the purpose of true-up.
8.2.3 Submission of West Discom
8.2.3.1 It is submitted that with reference to a letter no. 7045/R-4197/2015/XIII, from PS
Energy, Bhopal dated 06/11/2017, M. P. Power Transmission Co. Ltd., Jabalpur has
written off liabilities of Discom to an extent of Rs. 180.48 Cr. This liability of
wheeling charges towards MPPTCL has reflected in P&L as other expenses item and
has not been claimed for the purpose of true-up.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 57
T9: RETURN ON EQUITY
9.1 The Hon’ble Commission in its Tariff Order for FY 2017-18 dated 31st March 2017
had approved return on equity as Rs. 219.05 Cr for East Discom, Rs. 302.14 Cr for
Central Discom and Rs. 177.63 Cr for West Discom respectively.
9.1.1 Submission of East Discom
The Petitioners submits that it has computed Return on Equity as per Tariff
Regulations, 2015. The Petitioners hereby submits that it has considered the closing
equity associated with Actual GFA. Equity component of GFA addition equal to 30%
of net addition in FY 2017-18 has been considered as the equity addition. The
Petitioners submits that it has computed Return on Equity as per Section 30.2 of the
Tariff Regulations, 2015 which specifies that Return on Equity shall be computed on
pre-tax basis @ 16% as below:
Table 30: ROE Claimed by EZ as true up for FY 2017-18
Sr.
no.
Particulars Approved in
the Tariff
Order
(A)
Actuals
(B)
A Gross Fixed Assets at the beginning of year (net of consumer
contributions)
5,425.05
A1 Opening balance of equity 1,883.54
B Actual capitalization of assets as per Annual Accounts (net of
consumer contribution) 241.26
B1 Addition of equity, internal reserves during the year for
capitalized assets 1,557.88
C1 Normative additional Equity (30% of B) 72.38
D1 Excess / shortfall of additional equity over normative (B1-C1) 1,485.50
E Equity eligible for Return (A1+(C1/2)) OR (A1+(B1/2)),
whichever is lower 1,919.73
F Return on Equity - (16% on E) 219.05 307.16
9.1.2 Submission of Central Discom
The Petitioners submits that it has computed Return on Equity as per Tariff
Regulations, 2015. The Petitioners hereby submits that it has considered the closing
equity associated with actual GFA. Equity component of GFA addition equal to 30%
of net addition in FY 2017-18 has been considered as the equity addition. The
Petitioners submits that it has computed Return on Equity as per Section 30.2 of the
Tariff Regulations, 2015 which specifies that Return on Equity shall be computed on
pre-tax basis @ 16% as below:
Table 31: ROE Claimed by CZ as true up for FY 2017-18
Sr.
no.
Particulars Approved in
the Tariff
Order
(A)
Actuals
(B)
A Gross Fixed Assets at the beginning of year (net of consumer
4,893.07
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 58
Sr.
no.
Particulars Approved in
the Tariff
Order
(A)
Actuals
(B)
contributions)
A1 Opening balance of equity 1,961.12
B Actual capitalization of assets as per Annual Accounts (net of
consumer contribution) 201.18
B1 Addition of equity, internal reserves during the year for
capitalized assets 1,750.22
C1 Normative additional Equity (30% of B) 60.35
D1 Excess / shortfall of additional equity over normative (B1-
C1) 1,689.87
E Equity eligible for Return (A1+(C1/2)) OR (A1+(B1/2)),
whichever is lower 1,991.30
F Return on Equity - (16% on E) 302.14 318.61
9.1.3 Submission of West Discom
The Petitioners submits that it has computed Return on Equity as per Tariff
Regulations, 2015. The Petitioners hereby submits that it has considered the closing
equity associated with GFA (as on 31st March 2017 as per True-up Order for FY
2016-17). Since the True-up Order for FY 2016-17 is still awaited the Petitioners has
followed the same methodology as per Tariff Regulations, 2015 and followed by the
Hon’ble Commission in previous True-Up Order to arrive at closing equity associated
with GFA for FY 2014-15 which inter-alia would be the opening equity associated
with GFA for FY 2017-18 .Equity component of GFA addition equal to 30% of net
addition in FY 2017-18 has been considered as the equity addition. The Petitioners
submits that it has computed Return on Equity as per Section 30.2 of the Tariff
Regulations, 2015 which specifies that Return on Equity shall be computed on pre-tax
basis @ 16% as below:
Table 32: ROE Claimed by WZ as true up for FY 2017-18
Sr.
no.
Particulars Approved in
the Tariff
Order
(Rs. Crs.)
Actuals in
(Rs. Cr)
A Opening Equity Identified with GFA (as on 01st April 2017
as Per FY 2016-17 True-up Petition)
1,077.08
B GFA Addition During the FY 603.94
C Consumer Deposit and Grants utilized during the FY 517.45
D Net GFA Addition during the FY 86.49
E 30% of addition to net GFA considered as funded through
Equity 25.95
F Closing Equity Identified with GFA (as on 31st March 2017) 1,103.03
G Average Equity associated with GFA 1,090.06
H Rate of Return on Equity (%) 16% 16%
I Return on Equity 177.63 174.41
9.2 The petitioners, thus prays the Hon’ble Commission to allow Return on Equity
amounting to Rs307.16 Cr, Rs318.61 and Rs174.41 for East Discom, Central Discom
and West Discom respectively for FY 2017-18 as shown in below table .
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 59
Table 33: ROE Claimed by Petitioners for FY 2017-18
Sr.
no.
Discom Allowed in the
Tariff Order
Actual Claimed
Now As Per
Regulation
/ Accounts
Variance
1 East Discom 219.05 307.16 (88.11)
2 Central Discom 302.14 318.61 (16.47)
3 West Discom 177.63 174.41 3.22
4 MP State 698.82 800.17 (101.35)
T10: TAXES
10.1 The petitioners submits that for the period FY 2017-18 they have incurred a loss of Rs
2190.46 Cr & Rs 2,716.79 Cr for respective East Discom & Central Discom and a
profit of Rs. 157 Cr for West Discom before tax and hence were not required to pay
any Income Tax.
T11: OTHER EXPENSES CAPITALISED
11.1 Submission of East Discom:
11.1.1 As per the Audited Accounts of FY 2017-18 the licensee has capitalised 122.92 Cr as
other expenses capitalised includes the capitalised employee expenses, capitalised
R&M Expenses and capitalised A&G Expenses.
Table 34: Other expenses capitalized claimed by East Discom for FY 2017-18
Sr.
no.
Particulars As Approved
in Tariff
Order
Actual as per
audited
accounts
1 Capitalization of base investment
-
2 Capitalization of expenses:--
Interest & Finance charges Capitalized
(83.96)
Employee expenses Not (28.91)
R&M Expenses indicated in (7.06)
A&G Expenses Tariff Order (3.0)
Others, if any
-
3 Capitalization of depreciation, if any
-
Grand Total (1+2+3)
(122.92)
11.1.2 The licensee hereby prays to the Hon’ble commission to allow the other expenses
capitalised of Rs. 122.92 for FY 2017-18.
11.2 Submission of Central Discom:
11.2.1 As per the Audited Accounts of FY 2017-18 the licensee has capitalised 27.75 Cr as
other expenses capitalised includes the capitalised employee expenses, capitalised
R&M Expenses and capitalised A&G Expenses and interest and finance charges
capitalised.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 60
Table 35: Other expenses capitalized claimed by West Discom for FY 2017-18
Sr.
no.
Particulars As Approved
in Tariff
Order
Actual as per
audited
accounts
1 Capitalization of base investment
-
2 Capitalization of expenses:--
Interest & Finance charges Capitalized
Employee expenses Not (27.75)
R&M Expenses indicated in
A&G Expenses Tariff Order
Others, if any
-
3 Capitalization of depreciation, if any
-
Grand Total (1+2+3)
(27.75)
11.2.2 The licensee hereby prays to the Hon’ble commission to allow the other expenses
capitalised of Rs. 27.75 for FY 2017-18.
11.3 Submission of West Discom:
11.3.1 As per the Audited Accounts of FY 2017-18 the licensee has capitalised 65.46 Cr as
other expenses capitalised includes the capitalised employee expenses, capitalised
R&M Expenses and capitalised A&G Expenses and interest and finance charges
capitalised.
Table 36: Other expenses capitalized claimed by West Discom for FY 2017-18
Sr.
no.
Particulars As Approved
in Tariff
Order
Actual as per
audited
accounts
1 Capitalization of base investment
-
2 Capitalization of expenses:--
Interest & Finance charges Capitalized
33.34
Employee expenses Not 24.53
R&M Expenses indicated in 0.46
A&G Expenses Tariff Order 7.12
Others, if any
3 Capitalization of depreciation, if any
-
Grand Total (1+2+3)
65.46
11.3.2 The licensee hereby prays to the Hon’ble commission to allow the other expenses
capitalised of Rs. 65.46 for FY 2017-18.
T12: OTHER INCOME
12.1 The Hon’ble Commission in its Tariff Order for FY 2017-18 dated 31st March 2017
had approved other income and non-tariff income as Rs. 243.40 Cr for the East
Discom, Rs. 268.57 Cr for the Central Discom and Rs. 349.37 Cr for the West
Discom respectively.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 61
12.2 The Petitioners have claimed other income and non-tariff income as per the audited
accounts of FY 2017-18 as per below table.
Table 37: Other income claimed by Petitioners for FY 2017-18
Sr.
no.
Discom Allowed in the
Tariff Order
Actual Claimed
Now As Per
Regulation
/ Accounts
Variance
1 East Discom 243.40 316.77 (73.37)
2 Central Discom 349.37 342.26 7.11
3 West Discom 268.57 144.32 124.25
4 MP State 861.34 803.35 57.99
12.3 The Petitioners hereby pray to the Hon’ble Commission to approve Rs. 316.77 Cr for
the East Discom, Rs. 342.26 Cr for the Central Discom and Rs. 144.32 Cr for the
West Discom respectively for FY 2017-18 as other income and non-tariff income as
submitted above.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 62
T13: INCOME FROM SALE OF POWER
13.1 Submission of East Discom
13.1.1 The Licensee hereby submits that the Hon’ble Commission had considered sales of
15,278 MU for the period FY 2017-18. However, the actual sales were14102.73 MU,
which are lower by 1,176.27 MU than what has been approved in the Tariff order for
FY 2017-18. The revenue from sales has also been lower by Rs. 1086.12 Cr. The
details are shown in the table below:
Table 38: Revenue from Sales for East Discom FY 2017-18
Particulars
As per Tariff
Order (A)
Actuals (B) Variance (B-A)
Sales
(MU)
Revenue
(Rs. Cr)
Sales
(MU)
Revenue
(Rs. Cr)
Sales
(MU)
Revenue
(Rs. Cr)
LOW TENSION 12,015.00 6,929.00 11,008.58 5,986.20 (1,006.42) (942.80)
LV 1: Domestic 4,262.00 2,493.00 4,170.44 2,079.32 (91.56) (413.68)
LV 2: Non-Domestic 1,051.00 848.00 967.33 726.43 (83.67) (121.57)
LV 3: Public Water Works & Street
Lights 408.00 238.00 427.68 194.93 19.68 (43.07)
LV 4: LT Industry 365.00 291.00 354.02 273.06 (10.98) (17.94)
LV 5: Irrigation pump for
Agriculture 5,929.00 3,059.00 5,089.11 2,712.45 (839.89) (346.55)
HIGH TENSION 3,264.00 2,492.00 3,094.15 2,285.16 (169.85) (206.84)
HV 1: Railway Traction - - - - - -
HV 2: Coal Mines 463.00 376.00 453.33 353.37 (9.67) (22.63)
HV-3: Industrial & Non-Industrial 2,344.00 1,830.00 2,256.60 1,684.46 (87.40) (145.54)
HV-4: Seasonal 9.00 7.00 8.00 7.66 (1.00) 0.66
HV-5: HT Irrigation & Water
Works 162.00 96.00 110.25 70.28 (51.75) (25.72)
HV 6: Bulk Residential Users 286.00 183.00 265.97 169.40 (20.03) (13.60)
HV 7: Start-Up power - - - - - -
GRAND TOTAL HT + LT 15,278.00 9,419.00 14,102.73 8,271.36 (1,176.27) (1,149.64)
GRAND TOTAL HT + LT as per
R-15 (Including ED, Cess, Meter
Rent, Surcharge, Misc Charges
etc)
14,102.73 -
GRAND TOTAL HT + LT as per
Audited Accounts
9,419.00 7,060.16
(1,086.12)
Subsidy as per audited Accounts 1,272.72
Total Revenue from Sales of
power including subsidy 9,419.00
8,332.88
(1,086.12)
13.1.2 The Actual income from sale of power indicated in the audited accounts including
subsidy is Rs 8332.88 Cr.
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 63
13.1.3 The Licensee thus prays to the Hon’ble Commission to consider Rs. 8332.88 Cr. as
Income from sales of power as per the audited accounts of the company, for the
purpose of deciding of True-up.
13.2 Submission of Central Discom
13.2.1 The Licensee hereby submits that the Hon’ble Commission had considered sales of
16,021 MU for the period FY 2017-18. However, the actual sales were13,276.41MU,
which are lower by 2743 MU than what has been approved in the Tariff order for FY
2017-18. The revenue from sales has also been lower by Rs. 1626 Cr. The details are
shown in the table below:
Table 39: Revenue from Sales for Central Discom FY 2017-18
Particulars
As per Tariff
Order (A) Actuals (B) Variance (B-A)
Sales
(MU)
Revenue
(Rs. Cr)
Sales
(MU)
Revenue
(Rs. Cr)
Sales
(MU)
Revenue
(Rs. Cr)
LOW TENSION 12,032.00 7,314.00 9,908.62 6,195.13 (2,123.38) (1,118.87)
LV 1: Domestic 4,005.00 2,487.00 3,790.38 2,343.84 (214.62) (143.16)
LV 2: Non-Domestic 970.00 829.00 885.26 761.61 (84.74) (67.39)
LV 3: Public Water Works &
Street Lights 361.00 210.00 345.78 211.58 (15.22) 1.58
LV 4: LT Industry 283.00 221.00 273.43 233.62 (9.57) 12.62
LV 5: Irrigation pump for
Agriculture 6,413.00 3,567.00 4,613.77 2,644.47 (1,799.23) (922.53)
HIGH TENSION 3,988.00 2,966.00 3,367.80 2,320.86 (620.20) (645.14)
HV 1: Railway Traction - - - - - -
HV 2: Coal Mines 44.00 37.00 26.21 24.48 (17.79) (12.52)
HV-3: Industrial & Non-Industrial 3,513.00 2,669.00 2,976.47 2,071.58 (536.53) (597.42)
HV-4: Seasonal 2.00 1.00 1.60 1.56 (0.40) 0.56
HV-5: HT Irrigation & Water
Works 255.00 149.00 207.42 123.87 (47.58) (25.13)
HV 6: Bulk Residential Users 174.00 110.00 146.64 93.81 (27.36) (16.19)
HV 7: Start-Up power - - 9.45 5.56 9.45 5.56
GRAND TOTAL HT + LT 16,020.00 10,280.00 13,276.41 8,515.99 (2,743.59) (1,764.01)
GRAND TOTAL HT + LT as
per R-15 (Including ED, Cess,
Meter Rent, Surcharge, Misc
Charges etc)
13,276.41 -
GRAND TOTAL HT + LT as
per Audited Accounts 10,280.00 6,787.28
Subsidy as per audited Accounts
2,258.93
Less: Electricity Duty
451.13
Total Sales of power including
subsidy
10,280.00
8,595.08
(1,684.92)
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 64
13.2.2 The actual income as per the audited accounts including subsidy is Rs. 8,595.08 Cr.
Accordingly the Licensee prays the Hon’ble Commission to consider Rs. 8,595.08 Cr
as Income from sales of power for the purpose of deciding of True up.
13.3 Submission of West Discom
13.3.1 The Licensee hereby submits that the Hon’ble Commission approved total sales of
18,426 MU’s. Actual sales during FY 2017-18 was 17565 MU which is lower by 227
MU than approved in the tariff order for FY 2017-18.
13.3.2 The actual revenue as per audited accounts is Rs. 11,837.85 Cr. Details of the same
are as shown in the table below:
Table 40: Revenue from Sales for West Discom FY 2017-18
Particulars As per Tariff Order
(A)
Actuals
(B)
Variance
(B-A)
Sales
(MU)
Revenues
(Rs. Cr)
Sales
(MU)
Revenues
(Rs. Cr)
Sales
(MU)
Revenues
(Rs. Cr)
LOW TENSION
7,519.88
LV 1: Domestic 3,661 2,141 3,840 (179.02)
LV 2: Non-domestic/Commercial 1,029 882 1,038 (8.54)
LV 3: Public Water Works and Street
Lights 455 272 436 18.90
LV 4: LT Industry 591 455 586 4.67
LV 5: Irrigation Pump for
Agriculture 8,545 4,585 8,357 188.01
LT TOTAL 14,281 8,335.00 14,256.98 24.02
HIGH TENSION
HV 1: Railway Traction 0 0 0.00 0.00
HV 2: Coal Mines 0 0 0.00 0.00
HV 3: Industrial and Non-Industrial 3,565 2,683 3,731.74 (166.74)
HV-4: Seasonal 12 9 12.16 (0.16)
HV-5: HT Irrigation & Water Works 536 316 577.06 (41.06)
HV 6: Bulk Residential Users 31 20 12.24 18.76
HV 7: Bulk Supply to Exemptees
(RE Co-op society) 1 1 31.04 (30.04)
HT TOTAL 4,145 3,028.80 4,364.25 - (219.25)
GRAND TOTAL HT + LT 18,426 11,363.80 18,621.23 7,519.88 (195.23) 3,843.92
GRAND TOTAL Revenue from
Sale of Power as per Audited
Accounts
7,519.88
Net of subsidy
4,317.97
Revenue From Sale Of Power As
Per Audited Accounts (Including
Subsidy and excluding revenue
from sale of services)
11,837.85
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 65
T14: SUMMARY OF TRUE UP ARR FOR FY 2017-18
14.1 East Discom submits that in accordance with the normative parameters of MPERC,
the gross ARR of East Discom for the period FY 2017-18 is Rs 10,024.83 Cr, which
is Rs 1,157.01 Cr higher than the approved ARR in the Tariff Order for the period FY
2017-18.The income from sale of power including the subsidy was Rs. 8,332.88 Cr
which is lesser by Rs 1,086.57 Cr and other income was Rs. 316.77 Cr which is
higher by Rs. 73.37 Cr as assessed in Tariff order 2017-18. Thus, the total gap works
out as Rs 2,215.58 Cr.
14.2 Central Discom submits that in accordance with the normative parameters of MPERC,
the gross ARR of Central Discom for the period FY 2017-18 is Rs 10,686.83 Cr,
which is Rs 949.58 Cr higher than the approved ARR in the Tariff Order for the
period FY 2017-18. The income from sale of power including the subsidy was Rs.
8,595.08 Cr which is lesser by Rs 1,683.68 Cr and other income was Rs. 342.26Cr
which is higher by Rs. 73.69 Cr as assessed in Tariff order 2017-18. Thus, the total
gap works out as Rs 2,613.58 Cr.
14.3 West Discom submits that in accordance with the normative parameters of MPERC,
the gross ARR of West Discom for the period FY 2017-18 is Rs 11,792.57 Cr, which
is Rs 718.38 Cr higher than the approved ARR in the Tariff Order for the period FY
2017-18. The income from sale of power including the subsidy was Rs. 11,837.85 Cr
which is higher by Rs 474.05 Cr and other income was Rs. 144.32 Cr which is lesser
by Rs. 205.05 Cr. as assessed in Tariff order 2017-18. Thus, the total gap works out as
Rs 498.38Cr.
14.4 Summary of the petitioner’s claim towards true up for the period FY 2017-18 is as
follows:
Table 41: Summary of True Up Claimed for FY 2017-18 (Rs Cr)
Sr.
no.
Particulars Discom Approved
in Tariff
Order
Claimed in
True up
Petition
Variation
1 Power Purchase Cost Including
MPPMCL Cost
EZ 6,937.73 8,001.86 (1,064.13)
CZ 7648.31 8,570.05 (921.74)
WZ 9,262.40 9,970.19 (707.79)
MP State 23,848.44 26,542.10 (2,693.66)
2 Employee Cost (including terminal
benefit cash outflow)
EZ 1,037.28 822.48 214.80
CZ 997.17 1,127.85 (130.68)
WZ 1,067.45 731.24 336.21
MP State 3,101.90 2,681.57 420.33
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 66
Sr.
no.
Particulars Discom Approved
in Tariff
Order
Claimed in
True up
Petition
Variation
3 A&G Cost
EZ 179.50 218.90 (39.40)
CZ 103.50 133.55 (30.05)
WZ 138.50 152.73 (14.23)
MP State 421.50 505.18 (83.68)
4 R&M Cost
EZ 151.40 168.84 (17.44)
CZ 183.94 145.58 38.36
WZ 135.14 136.32 (1.18)
MP State 470.49 450.74 19.75
5 Depreciation
EZ 116.50 335.28 (218.78)
CZ 159.54 300.71 (141.17)
WZ 105.05 244.33 (139.28)
MP State 381.09 880.33 (499.24)
6 Interest on Project Loans
EZ 106.69 150.08 (43.39)
CZ 238.10 6.37 231.73
WZ 67.53 44.51 23.02
MP State 412.32 200.96 211.36
7 Interest on Working Capital
EZ 85.97 72.61 13.36
CZ 46.38 35.69 10.69
WZ 63.99 37.73 26.26
MP State 196.34 146.03 50.31
8 Interest on Consumer Security
Deposit
EZ 31.69 55.79 (24.10)
CZ 56.16 52.89 3.27
WZ 54.50 63.59 (9.09)
MP State 142.34 172.27 (29.93)
9 Return on Equity
EZ 219.05 307.16 (88.11)
CZ 302.14 318.61 (16.47)
WZ 177.63 174.41 3.22
MP State 698.82 800.17 (101.35)
10 Bad and Doubtful Debts
EZ 2.00 14.75 (12.75)
CZ 2.00 23.28 (21.28)
WZ 2.00 237.00 (235.00)
MP State 6.00 275.03 (269.03)
11 Other Expenses
EZ
-
CZ
- -
WZ
0.52 (0.52)
MP State
0.52 (0.52)
12 Less: Expenses Capitalised EZ
(122.92) 122.92
True-up Petition of MP Discoms for FY 2017-18
MPPMCL / MPPoKVVCL/MPMKVVCL/MPPaKVVCL P a g e | 67
Sr.
no.
Particulars Discom Approved
in Tariff
Order
Claimed in
True up
Petition
Variation
CZ
(27.75) 27.75
WZ
-
MP State
(150.67) 150.67
13 Total Expenses
EZ 8,867.82 10,024.83 (1,157.01)
CZ 9,737.25 10,686.83 (949.58)
WZ 11,074.19 11,792.57 (718.38)
MP State 29,679.25 32,504.23 (2,824.98)
14 Less: Other Income - Retail &
Wheeling
EZ 243.40 316.77 (73.37)
CZ 268.57 342.26 (73.69)
WZ 349.37 144.32 205.05
MP State 861.34 803.35 57.99
16 Net Total Expenses for FY 2017-18
EZ 8,624.42 9,708.06 (1,083.64)
CZ 9,468.68 10,344.57 (875.89)
WZ 10,724.82 11,648.26 (923.44)
MP State 28,817.91 31,700.89 (2,882.98)
17 Add: Impact of True-Ups
EZ 795.03 840.40 (45.37)
CZ 810.09 864.09 (54.00)
WZ 638.98 687.98 (49.00)
MP State 2,244.10 2,392.47 (148.37)
18 Total ARR for FY 2017-18
EZ 9,419.45 10,548.46 (1,129.01)
CZ 10,278.76 11,208.66 (929.90)
WZ 11,363.80 12,336.24 (972.44)
MP State 31,062.01 34,093.36 (3,031.35)
19 Revenue from sale of Power
EZ 9,419.45 8,332.88 1,086.57
CZ 10,278.76 8,595.08 1,683.68
WZ 11,363.80 11,837.85 (474.05)
MP State 31,062.01 28,765.81 2,296.20
20 Revenue Deficit/(Surplus)
EZ - 2,215.58 (2,215.58)
CZ - 2,613.58 (2,613.58)
WZ - 498.38 (498.38)
MP State - 5,327.54 (5,327.54)
14.5 The petitioners hereby submit that the total revenue gap works out to be Rs 2,215.58
Cr, Rs 2,613.58 Cr, Rs 498.38 Cr and Rs 5,327.54 Cr for East Discom, Central
Discom, West Discom and MP State respectively. This gap may be included in the
ARRs of subsequent years or as the Hon’ble commission may deem fit for recovery of
the same.