WP4 Urban Programming
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the
Pescasseroli-Candela Tratturo area- Provincia di Foggia
ERDF PP6
Version 01
Prepared by:
Provincia di Foggia
www.territorio.provincia.foggia.it
Reviewed by:
STATUS Content Management
URBASOFIA
www.urbasofia.eu
Urban Planning Institute
of the Republic of Slovenia
www.uirs.si
Workpackage 4 Urban Programming
Activity 4.2 Definition of planning scenarios:
prioritization design of urban strategic agenda
D4.7 Integrated Strategic Territorial/Urban Agenda in
the Pescasseroli-Candela Tratturo area
ERDF PP6 – Provincia of Foggia (IT)
2/116
Project number: SEE/D/0297/4.1/X
Project acronym: STATUS
Project title: Strategic Territorial Agendas for "Small and Middle-Sized Towns" Urban Systems
Instrument: INTERREG IV B SEE
Call identifier: South East Europe Call D
Activity code:
Start date of Project: 2012-12-01
Duration: 24 month
Deliverable reference number and title (as in Annex 1): D4.7 Integrated Strategic
Territorial/Urban Agenda in
Pescasseroli-Candela Tratturo area
Due date of deliverable (as in Annex 1): 2014-11-30
Actual submission date: see “History” Table below
Revision:
Organisation name of lead contractor for this deliverable:
Municipality of Kavala
Project co-funded by the European Commission within the INTERREG IVB
South East Europe Programme (2007-2013)
Dissemination Level
PU Public PU
PP Restricted to other programme participants (including the
Commission Services)
RE Restricted to a group specified by the consortium
CO Confidential, only for members of the consortium (including the
Commission Services)
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
3
Title:
D 4.7 - Integrated Strategic Territorial/Urban Agenda in Pescasseroli-Candela Tratturo area
ERDF PP6 – Provincia of Foggia (IT)
Author(s)/Organisation(s):
ERDF PP6 – Provincia of Foggia (IT)
Working Group:
WP4
References:
STATUS Final Application Form (INTRA-5108827)
STATUS Project and financial management handbook
Short Description:
Output 4.2, 4.5 and 4.6 are going to be combined and presented as the final Strategic Territorial / Agenda.
Content manager coordinates. Scientific and technological partners provide methodologies and techniques, tools
necessary to facilitate the exchange of ideas, knowledge and expertise in the activated participatory planning process
leading to the final Agendas design.
Keywords:
Strategic territorial agenda, strategy, workshops, participatory tool, geoblog, stakeholders, working groups, solutions,
problems
History:
Version Author(s) Status Comment Date
00 Barbara Music (UIRS) 1. Draft Template of the report 16/09/2014
01 Giovanna Caratù and
Adele Celino
1. Draft Draft of the report 17/10/2014
Review:
Version Reviewer Comment Date
01
Sabina Dimitriu (As. CM)
Pietro Elisei (CM)
Review of Report Template 2014
xx/xx/2014
01 Barbara Mušič (UIRS) Review of the v01 of the report 17/11/2014
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
4
Table of Contents
Table of Contents................................................................................................................................... 4
Table of Figures ..................................................................................................................................... 5
Abbreviation List ................................................................................................................................... 5
1 The importance/purpose of the Strategic Territorial Agenda (STA) ....................................... 6
2 Scope and vision of the STA 2030 ................................................................................................ 6
3 The process leading to design of the STA in Provincia of Foggia area ..................................... 7
4 Goals and projects of the STA .................................................................................................... 15
5 Implementation of the STA ........................................................................................................ 19
6 Project Fiches: Priority projects corresponding to each goal/objective of the STA .............. 23
7 The Poster Plan ............................................................................................................................ 34
8 Conclusions .................................................................................................................................. 37
9 References .................................................................................................................................... 37
10 Annexes......................................................................................................................................... 37
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
5
Table of Figures
Tables
Table 1: List of prioritized projects ....................................................................................................... 18
Table 2: STA´s Action Plan of Provincia of Foggia area ...................................................................... 19
Table 3: STA´s Action Plan of Provincia of Foggia area in a timeline ................................................. 21
Table 4: Risk assessment ....................................................................................................................... 23
Table 5: Monitoring and evaluation framework of the STA .................. Error! Bookmark not defined.
Figures
Figure 1: The process of designing STA (source: own design) .............................................................. 7
Figure 2: Timeline of the process of STA design (source: own design) ............................................... 10
Figure 3: Timeline of the process of STA design .................................................................................. 12
Abbreviation List
CKP - cities knowledge platform
STA - Strategic Territorial Agenda
TP – Territorial Partner
SEE – South Eastern Europe
UC – Urban Centers
TTF – Territorial Task Forces
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
6
1 The importance/purpose of the Strategic
Territorial Agenda (STA)
The Tratturi System is an interregional network of pathways along which the historical
phenomenon of transhumance took place. Today such paths have a strategic value from
territorial and historical point of view. The theme of their recovery and enhancement is not a
new theme in the Agenda of local institutions, association, agricultural actors, and of local
community. Anyway, at the moment, there is not a strong strategy that can support a real
development of the area based on the valorization of the extensive network of tratturi.
In the STATUS project, the Provincia of Foggia has proposed the goal of protection and
enhancement of the tratturo Pescasseroli-Candela as a pilot case. The area of the Pescasseroli-
Candela tratturo covers around 450 hectares, as main way, and 2.500 hectares, as annexed
area. It is a poor and marginal area with subsistence economy grounded essentially on
traditional farming. Income per capita are the lowest among European countries and in
particular we are highlighting the Municipality of Anzano di Puglia with an income per capita
of 4.265 euro per year. On the other hand, the territory is rich both, natural and landscape
resources of high value and in widespread cultural resources. There is also a good presence of
associations whose main mission is the dissemination of this natural and cultural heritage.
The problem is the lack of: 1) entrepreneurial initiatives that help to develop such a capital; 2)
coordination and planning actions that could guide the activities towards the preservation and
development of the tratturo; 3) consistent use of the areas; 4) strategies and projects aimed at
enhancing the area.
Many local projects have been proposed in this direction for their funding but only few of
them were realized.
The Province of Foggia has proposed to design the STA for the area of the Tratturo
Pescasseroli-Candela in order to plan a coordinated and collaborative strategy that really can
help to implement (or to support) actions for the protection and enhancement of the area and
that can be represented, in the future, as a good practice, as an interesting and effective
example/way to follow, in similar conditions, for other tratturo of the “System”.
Finally, with reference to the topic of "tratturo", the local actors (institutions, associations,
entrepreneurs, etc.) seem to be "structurally isolated". Such "isolation" is probably a
contributing factor to the lack of strategies and projects shared and/or developed in
cooperation/collaboration and it may, in part, be overcome with the participatory process
activated in support of the design process of the STA.
2 Scope and vision of the STA 2030
The Strategic Agenda faces two types of territorial issues:
process issues such as: lack of coordination, activation of an effective participation
process, selection of key stakeholders;
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
7
content issues such as: lack of an overall strategic improvement project, promotion of
actions oriented to the operational plan (POI) implementation, coordination of
programs and actions, selection of planning or programs instruments able to support
the strategic agenda
The goals of STA are essentially: procedural goals and content goals.
From the procedural point of view, the ambition of the Agenda is to activate different
networks of action with variable geometry that can also work independently from each other
in order to identify implementation strategies for the recovery and valorization of the area and
to discover implementation tools. At the beginning of the STATUS process, the Provincia of
Foggia has recognized some stakeholders (output 3.1), but the STA was designed taking into
account that the partnership and networks are adaptive and evolving, depending on
occurrences. In structuring and designing the STATUS process, the key idea was that the STA
could contribute to create new action networks in an area poor of opportunities to collaborate.
In designing the strategic vision of the tratturo area, stakeholders have to recognize their role,
their resources and their potential for the enhancement of the tratturo.
From the content point of view , starting from the existing planning tools and mainly from the
POI (Integrated Operational Plans "Renovation and development of Pescasseroli-Candela)
(see output 3.5), the STA 2030 of the area of tratturo Pescasseroli-Candela is built on a
strategic vision (and a challenge) oriented to make tratturo’s areas:
identifiable/visible: to ensure its formal recognizability as a territorial object;
usable: to promote it as an attractive area;
continuous: to safeguard unity of its different dimensions from cultural, ecological and
physical point of view.
3 The process leading to design of the STA in the
area of the Provincia of Foggia
The process of designing the Strategic Territorial Agenda follows three mayor steps:
Figure 1: The process of designing STA
(source: UIRS design)
The STATUS workshops were organized as a sequence of events in a continuous, evolving,
and action-oriented process. These workshops have been considered as a great opportunity to
support the generation of a Strategic Territorial Agenda (STA) which aims to implement the
Provincial Operational Plan (POI) and, therefore, to share and verify action strategies
Identification of problems
Finding solutions
Designing the STA
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
8
proposed in the POI. In considering such action strategies as open objects, the expectations of
the workshops were:
revision of proposed action strategies or searching for new ones;
identifying of priority in actions;
discovering implementation tools.The workshop have been organized based on the original
STATUS workshop methodology provided for the WP4, with a few modifications.
The first public workshop was organized as a workshop of coordination between the
institutions involved (region, municipalities and representative of the union or association of
farmers). The main goal was to generate the appropriate conditions to produce the snowball
effect. It was held in the Provincia di Foggia and there have been 18 participants, all identified
by the Province. Such first workshop was organized to achieve the following objectives:
to attract and address the interest of the actors on the Tratturo issues;
to identify conceptual axis of the Strategic Agenda;
to identify problems for the Tratturo Governance (set of governance problems to face
within (and with) the Agenda and the new key stakeholders);
to discuss on problems in managing territorial agenda and territorial center;
to discover ways to integrate institutional/administrative policies and sectoral
issues/actions.
The first workshop, as a coordination workshop, was spent on discussing about the
governance issues. Consequently all the participants have worked in a single group created for
the conceptual axis: “Governance and Stakeholders”. During the meeting, participants were
able to identify the other conceptual axes and the other working groups (“Accessibility”,
“Landscape”, “Property”) and to suggest a list of new participants.
In the days following the first workshop, participants were involved in the organization of the
second workshop. In total, 38 persons have attended the workshop.
Taking into consideration the outputs produced during the first workshop by the Working
Group 1 (“Governance and Stakeholders”), the objectives of the second workshop have been:
to identify problems/issues for the conceptual axes recognized by participants;
to propose a number of solutions for the problems identified;
to provide a prioritization of the projects; to identify the financial instruments.
The workshop has lasted four days during which a number of participants have been
recognized as a reliable group of territorial actors capable and willing to sustain a long-term
dialogue with the institutions (region, province and municipalities). On the first day, in a
plenary session, sharing their significant practical experience in planning and public policy,
the key actors (participants in the first workshop) presented, in turn:
1. critical issues in terms of: accessibility (not just physical), landscape (in general terms),
properties (management of -), governance;
2. 2014-2020 programming and the programming at regional, provincial and local levels;
3. projects that are considered interesting, already implemented and/or being implemented,
and which have had a positive impact (or perhaps even negative) on the area;
4. remarks on dialogue, cooperation between actors (institutional and otherwise) and
community participation.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
9
The work conducted during the second, third and fourth workshop days has taken place
within workgroups divided on major themes (Governance and Stakeholders”, “Accessibility”,
“Landscape”, and “Property”) and focused on:
discussion on the findings of the first WS and the first day;
summary of the critical issues;
possible solutions;
definition of priorities;
evidence of the possible positive or negative externalities (conflicts, difficulties, etc.);
opportunities for funding.
In addition to the problems raised in the first workshop in the Province of Foggia (19
Novembre 2013), several other aspects/issues/problems have been discussed in the plenary
session and separate workgroups throughout the 4 days of the event. In this way, the new
participants had the opportunity to think beforehand and complete the list with additional
remarks and problems,
During and after, the days of the second workshop, a draft of the agenda (a sort of report of
the discussions – see Annex 5) has been regarded as a "working in progress" (an "open
content") and sent to the mailing list in order to show all participants the results achieved in
each of the four days of the workshop. In addition, all participants were involved in engaging
other stakeholders and encouraged to share documents and work on them.
The third workshop, hosted by the Province of Foggia, was aimed to the design, presenta and
discuss on the draft of the Strategic Territorial Agenda and to the elicitation of feedback on
the ideas proposed in the last 2 workshops.
The main topics of discussion during the 3th workshop were:
the draft of the strategic agenda;
the public participation in the processes of Agenda´s adoption (also addressed to civil
society);
the forms of institutionalization of the future common endeavors.
In particular the discussion focused on the way to assure, in the actions of the Agenda,
sustainable (in financial and commitment terms) and long-term involvement of the
stakeholders. The meeting highlighted the difficulties and challenges but the participants have
shared with enthusiasm the starting work program (6 months) (including the public
presentation of the Strategic Agenda).
During the day of the workshop, participants discussed about such a vision and agreed on the
opportunity to work on the priority actions (in the short time, 6 months), that are considered
the interventions aimed at increasing both the recognizability of the tratturo and the
commitment of participants and of the whole community.
In the days that proceeded and those that followed the day of the third workshop, some
participants worked on some actions considered as priorities.
3.1 Timeline of the overall process of the STA design
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
10
Figure 2: Timeline of the process of STA design
(source: UIRS design)
The 1st local workshop was held in the Provincia di Foggia, on the November 19th, 2013.
The 2nd local workshop was held in the Municipality of Anzano di Puglia, (one of the five
municipalities of the tratturo area) on February, 25 2014 and in the Province of Foggia,
spanning 3 more days (March 11-18-25).
The 3th local workshop was held in the Province of Foggia on July 7th, 2014.
3.2 Operational Analysis
Qualitative analyses (see outline 3.1.) and SWOT analysis (see outline 3.2) are used as an
opportunity to achieve knowledge of the state of the art of local urban issues.
In particular the current planning tools were the input to start discussions: existing plans,
policies, strategies, and politics had a big influence on designing the STA and on discuss how
projects and actions can be realized.
The only policy that really was carried out in the past, was the protection policy: at the
national level, the existing legal framework sees the tratturi as an archaeological and
landscape restriction; at the regional level , the establishment of the Regional Park of Tratturi
(R.L. 29/2003) did not define policies and strategies to approach them.
Recently, a regional law assigns to Apulia Region the task to form an "framework structure”
(which is not yet drafted) for the whole network of the tratturi, in order to avoid a fragmented
approach of such territorial resource.
In the Apulia Region, the linear protected area of the tratturi is a widespread network that is
constituted above all by public areas. They can be the meaningful places where to experiment
and test the strategies and actions of regional and provincial territorial plans. In particular
every track of tratturi can have its own role in different strategic territorial visions proposed
by the regional plan (Piano Territoriale di Coordinamento Provinciale-PPTR) which was
adopted in 2010 (the vision of the "Ecological Network territorial project", the "Low Mobility
territorial project" and the "City-Country agreement territorial project").
The provincial territorial plan (Piano Territoriale di Coordinamento Provinciale - PTCP),
approved in 2009, also sees the network of tratturi as a green path network and as historical
landscapes to protect and to improve.
2013WP3 Inception
November 2013
WP4 Workshop 1
February-March 2014
WP4 Workshop 2
July 2014WP4 Workshop 3
WP5 UTC + UC
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
11
Both the plans, PPTR and PTCP, give a special attention to the Tratturo Pescasseroli-Candela
The first one identifies it as an experimental project where testing proposed strategies; the
other one establishes an executive plan (Piano Operativo Integrato - POI) as a pilot project.
in particular, the starting point of the Agenda discussion were the existing planning tools and,
mainly, the POI (Integrated Operational Plans "Renovation and development of Pescasseroli-
Candela) (see output 3.5).
3.3 Territorial programming and Territorial Task Forces (TTF)
The STATUS workshop was the first opportunity where the involved participants could
discuss, all together, the future of the tratturo area. However, at the beginning, the Province of
Foggia was able to involve only institutional actors (Region and Municipalities) and the
representatives of unions or of associations of farmers (Coldiretti, Confagricoltura, etc.). So,
even if the first workshop was a great opportunity to discuss on procedural/governance issues,
there has been an over representation of institutional actors.
There are many other stakeholders (mainly at local level) really important in order to develop
a strategic agenda, however the Province of Foggia had some difficulties to recognize them
and, besides, to identify the conceptual axes that can support/orient the discussion.
For such a reason, in the first workshop, we chose to work with only one group ("Governance
and Stakeholders") and move discussion in workgroups at the second workshop. In the first
workshop, participants were able to identify, together with the Province of Foggia, the other
conceptual axes and the other working groups; in such way they actively attended in the
organization of the second workshop and they suggested a list of new stakeholders to involve
in the next workshop (associations and others organized stakeholders, experts, schools, etc).
The comparison between the initial stakeholders list and the one following to Workshop n.1
has revealed some changes in composition of the working groups, as well as, in the total
number of attendees.
In the first workshop, the actors, the Province of Foggia has been able to engage the
institutional actors (Region and Municipalities) and the representative of the trade union or an
association of farmers.
Other stakeholders (mainly at local level), really important in order to develop a strategic
agenda, were engaged in the second workshop; they were involved by the same participants.
The number of representatives of associations and activists in the area increased significantly.
The presence of the institutions has been almost constant (although represented by less
attendance, as in the case of the Apulia Region).
Almost all participants to the second workshop (consisting in the most interested and
qualified territorial actors) have been invested in keeping the task force alive and functioning
beyond the project deadline (perhaps in a form of consortium). In all days of the second
workshop, the participants discussed the shape of the Task Force; in order to ensure an
adequate commitment and involvement, they have proposed various institutionalized forms.
A lower presence of civil society is due to the large scale of the territorial issues that is able to
attract, more easily, institution or private sectors.
Mailing list, telephone callings and word of mouth were used in order to organize the
workshops. All the participants have been involved in organizing the workshops and they
have been engaged in engaging other stakeholders.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
12
After each day of workshops, participants have been provided with a summary of the
discussion, a document considered as "working in progress " (a kind of " open content "). In
addition, they were asked to contribute with more input. They were encouraged to share
documents and to working on them.
Figure 3: Timeline of the process of STA design
Due to the spatial scale of the proposed interventions, the problems and solutions have been
difficult to represent on the map or on geoblog.
The key focus of the the 1st and the 2nd workshop were in term of identified problems and
proposed solutions, the followings:
a. Collaboration at different levels
Identified problem: There is a lack of coordination and planning oriented to the
preservation and development of the tratturo and a comprehensive and coherent strategy
to make the individual actions of local actors efficient
Proposed solutions:
Phase 01
Phase 02
stakeholders
Phase 03
stakeholders
Phase 04
stakeholders
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
13
• The vision of the tratturo of Pescasseroli-Candela must be introduced in a system
vision, at the regional, interregional, and transactional levels;
• A consortium and a “control booth”, for the functions of coordination
• Thematic groups could be set up.
b. Funding and programming
Identified problem: The current funding and programming do not consider the tratturo as
common goods to be improved and do not allocate financial resources for activities in
that area. There is difficulty in identifying the tools that allow you to work in a more
coordinated way.
Proposed solutions
• It is necessary to prepare a document proposing the tratturo Pescasseroli-Candela as a
priority and to bring to the negotiating table to the next programming 2014-2020.
c. Recognizability
Identified problem: Even if the tratturo is a good of inestimable value, it is not always
visible by the local community that seems to be indifferent to the issues of its protection
and valorization.
Proposed solutions
• The tratturo has to be clearly identified in order to enhance the community ability to
recognize it.
• Installations by land art along the Pescasseroli-Candela track may contribute to focus
on the most significant places and make the area of tratturo an open-air museum
• Promotional events could contribute to focus on the protection and valorization issues
• Educational programs should be based on active citizenship and on the ability of
community to maintain the territory.
d. Physical accessibility
Identified problems: Not all the tratturo is practicable because of the several interruptions
along the route. It lacks a continuous maintenance of the area and there is often
abandoned waste.
Proposed solutions
• Some interventions are necessary for the physical protection of the territory, including
an appropriate system management and maintenance
• The local nature and culture must be promoted by trained guides
• Everyone should have the opportunity to walk along the tratturo, perhaps using new
technologies
• The farmers "concessions" must be sustainable and must be controlled to achieve the
planned goals.
• The slow mobility has to be organized: the tratturos are natural equestrian road and
they can become cycling routes, hiking routes and for people with disabilities.
• The critical and the potential issues of tratturo, proposed as a path, must be shown
going through the tratturo; only in such a way cycling routes and hiking routes could
be organized.
• Actions are needed to ensure both the cleaning of micro landfills that now exist along
the path, and safety
• The tratturo must have the access gates to the park; if one, it could be in the middle of
the track.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
14
AccessibilityGovernance
and stakeholders
Landascape Property
e. Negative impacts on the environment and landscape
Identified problems The path along the tratturo is fragmented and there are many human
activities that have had, and still have, a negative impact on the environment and the
landscape. Not always the political and administrative choices have also been oriented to
the safeguard of the tratturo. Farmers have often occupied the central part of the tratturo,
have left the pasture and have chosen crops (or monocultures) that are not compatible
with measures to protect the tratturo.
Proposed solutions
• The maintenance of tratturo and its areas pertaining must be organized to ensure the
physical security of the tratturo.
• Shares of landscape protection and of maintenance of the areas of the tratturo
• Interventions of recovery/mitigation can reduce the visual impact of industrial areas.
• In order to structure an integrated tourist offer, local guides must be trained and
guided tours should be organized on the territory.
f. Instability of soil
Identified problems:_ Instability of soil
Proposed solutions
• Engineering projects to counteract natural hydro-geomorphological hazards
g. Property
Identified problems: Successful actions have to deal with the complexity of the different
administrative use and ownership. In addition to agricultural soils there is also an
urbanized part and a part that still preserves its naturalness
Proposed solutions
• The opportunities offered by regional park, DRP, European funds and by the NOP
must be exploited.
• In concession areas, current agricultural practices must be oriented towards the
protection and preservation of the landscape.
In accordance with the results of the first workshop, the working groups were the following:
Governance and stakeholders
Landscape (natural and anthropic-man made)
Accessibility (not only physical)
Property systems management (public, private and granted)
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
15
Figure 4: working group
(source: the Provincia of Foggia design)
The topics of discussion for each working group have been the following:
1. Working Group 1 – Governance and Stakeholders.
Collaboration at different levels: connection of the tratturo must to infrastructures at
regional, interregional and international level (Complete the sentence.)
Function of coordination: a consortium and a public-private management group as
tools to both participate to the negotiating tables and to have direct access to
European funding
Funding and programming: negotiating document, that proposes, to the next
programming 2014-2020, the tratturo Pescasseroli-Candela as a priority
2. Working Group 2 – Accessibility.
Recognizability: Appropriate signs to increase its fruition and to focus on the most
significant places
Enhancement of the community ability to recognize it: promotional events in order to
focus on the protection and valorization issues
Educational programs: active citizenship and ability of community to maintain the
territory
Physical protection of the territory: appropriate system management and maintenance,
trained guides, farmers’ "concessions" more sustainable, cleaning of micro landfills
Slow mobility: a different organization, the use of new technologies, access gates to
the park,
3. Working Group 3 – Landscape.
Maintenance of tratturo: native plants along the border, tree-lined avenues of access
to the cities, wildflower
Interventions of recovery / mitigation: reduction of visual impact of industrial areas,
integrated tourist offer
Instability of soil: engineering projects to counteract natural hydro-geomorphologic
hazards
4. Working Group 4 – Property.
agricultural practices: practices for the protection and preservation of the landscape,
access to the benefits of the RDP
incentives to change: access to the benefits of the RDP, multiple lines of financing.
4 Goals and projects of the STA
In the past, the routes of transhumance have forged the territory, namely the territory was
transformed in function of the pastoral activity but today they have lost their original function.
The Pescasseroli-Candela tratturo is, and remains, a path but it has other recognizable
features; these are the features of: terrestrial ecological corridor, natural course (on foot, on
horseback, by bicycle and for different types of users), open-air museum. Therefore, the
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
16
possible interventions on the area: on the one hand should bring the tratturo to its original
appearance (or at least keep it), giving him again its identity characteristics and, above all, his
spatial view; on the other hand they should propose the usability of tratturo according to the
new orientations and needs of the community.
In order to assure such new functions/features, preserving the original appearance of the
tratturo, the Agenda aims the following objectives:
creation the path (or paths for sustainable mobility) and, at the same time, the "open air
museum" (to guarantee the preservation of historical memory) and a contribution to the
network of ecological corridors;
ensure the safety of the tratturo and its maintenance (also through incentives to dealers, or
the establishment of figures as that of guardian of the sheep-track, etc.)
ensure the physical recognition of the path;
promote and create "expectations";
create a tourism product (routes, services, places of exchange, etc.);
improve the culture of the community and the education of the younger generation
The STA for recovery and enhancement of the Pescasseroli-Candela tratturo is regarded as
"global project" (A COMMON VISION) consisting of a series of actions (COORDINATED
ACTIONS/PROJECTS), all important, which would act almost simultaneously. The vision
proposed by the STA could be summarized as below:
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
17
Tratturo as a greenway of the memory…
visible, recognizable, continuous and accessible
secure and maintained
equipped for the new features/new services
promoted and advertised
… for which all coordinate and collaborate
Figure 5: Strategic Agenda
(source: Provincia of Foggia design)
In the scenario of the tratturo as a visible, recognizable, continuous and accessible greenway
of the memory:
the tratturo is clearly identified in order to enhance the community ability to recognize it;
appropriate signs increase its fruition;
everyone should have the opportunity to walk along the tratturo, perhaps using new
technologies (virtual recognizability are aimed at increasing the viability physical);
local actors plan and program in a coordinate and collaborative way.
In the scenario of the tratturo as a secure and maintained greenway of the memory,
some interventions are necessary for the physical protection of the territory, including an
appropriate system management and maintenance of the tratturo and its areas pertaining;
the farmers "concessions" are sustainable and controlled to achieve the planned goals;
incentives are provided in order to orient current agricultural practices towards the
protection and preservation of the landscape.
In the scenario of the tratturo as an equipped for the new features/new services greenway of
the memory:
the slow mobility is organized: the tratturi are natural equestrian road and they became
cycling routes, hiking routes and for people with disabilities;
the tratturo is connected to the regional network of the tratturi, to the infrastructures
system for soft mobility of the regional ecological network; at interregional level, the
track of tratturo is connected: to the natural Italian paths of the tratturo and to the other
paths; at transactional and European level the path of the Tratturo Pescasseroli-Candela is
connected with the other trails of transhumance in Europe;
the local nature and culture are promoted by trained guides;
local guides are trained and guided tours are organized on the territory, in order to
structure an integrated tourist offer (an offer with also certified quality).
In the scenario of the tratturo as a promoted and advertised greenway of the memory:
promotional events contribute to focus on the protection and valorization issues;
the receptivity is organized in the farms and taverns, which are currently uninhabited but
all surveyed, to become a path, the historical tratturo requires places of exchanges and
facilities for all kind of users. Markets of close proximity;
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
18
educational programs are based on active citizenship and on the ability of community to
maintain the territory.
Table 1: List of prioritized projects
Priority nr. Name of the project Topic Funding
opportunities
Opportunities for
partnership
1 Drafting of a
document, for the RDP
and ERDF negotiation
table
Territorial
planning
RDP
ERDF
Region, GAL, Famers
Associations
2 Sharing the content of
the POI.10
"Renovation and
development of
Pescasseroli-Candela”
Territorial
planning
RDP 2007-
2020
Region, Municipalities
3 Participation to the
drafting of the
"framework structure"
of the “Park of
Tratturi”
Territorial
planning
RDP 2007-
2020
Region, Municipalities
4 Recovery of the signs
that make
recognizable the path
Natural and
cultural
resources
Regional funds PPP
5 Installation of signage
and informational
panels
Accessibility Regional funds PPP, Municipalities
6 Reconstitution of the
physical continuity of
the area of tratturo
Accessibility –
natural and
cultural
resources
Regional funds PPP and Municipalities
7 Organizing “The
national day of
tratturo"
Territorial
promotion
Municipalities
funds
Associations and
Municipalities
8 Creating an
interregional
consortium
Co-operation
and
management
Private funds PPP
9 Applications for
virtual visits and
assistance
Tourism Provincial funds PPP
10 Land art event Tourism –
Landscape
PO FESR 2007-
2013 Axis IV,
Actions 4.2.2 and
4.4.2
Region, Associations
11 Management and
maintenance system
Maintenance Municipalities and
Regional funds
Municipalities, PPP
12 Agricultural practices
towards protection
Environmental
protection
Regional funds Private
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
19
and preservation of
the landscape
13 Integrated network of
soft mobility
Mobility Regional funds
14 Creating connections
with other paths
Tourism European funds PPP, Municipalities, Region
15 Training of guides Tourism Regional funds Private, Municipalities,
Region
16 Promotion and
dissemination
Territorial
promotion
Regional and
municipalities
funds
Private, PPP and
Municipalities
17 Multi-functionality of
the agricultural
entrepreneur
Agriculture RDP and regional
funds
Private
18 Education programs Education Regional funds Region, Private, Schools
5 Implementation of the STA
5.1 Key actors responsible for the implementation of the STA
Table 2: STA´s Action Plan of Provincia of Foggia area
Action
priority
nr.
Action Name Person
responsible
(member of
the UTF)
Status
(preparatory
phase/active/
not active)
Due
date
Date
completed
Funding
opportunitie
s
Opportunities
for partnership
1 Organizing the
first TTF
operational
meeting
Provincia di
Foggia
Preparatory
phase
Nov.
2014
- Provincial
Funds
2 Make known and
public the
creation of the
TTF and of the
signed
Partnership
Agreement
Provincia di
Foggia
Active Nov.
2014
I quarter
2015
Provincial
Funds
3 Presentation of
the STA to the
local community
Provincia di
Foggia
Active Dic.
2014
Provincial
Funds
4 Promoting the
Actions of the new
2014-2020
Programming
GAL (Local
Action
Group)
Meridaunia)
Active Jan
2015
- RDP 2014-
2020
(ERDF
2014-2020)
Region, GAL,
Famers
Associations
5 Adjustment of
Municipal Master
Provincia di
Foggia
Not active Jan
2015
IV quarter
2018
Municipality
funds
Region,
Municipalities
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
20
Plans to POI
6 Organizing
meetings to
participate to
"framework
structure"
contents
Office “Park
of Tratturi”
– Apulia
Region
Active II
quarter
2014
IV quarter
2016
Regional
funds
Region,
Municipalities
7 Fit out the
Territorial Center
at the “Museo del
Territorio”
Provincia di
Foggia
Active Nov.
2014
Associations
8 Checking and
completing of the
recognition of
“signs” that make
recognizable the
path
Archeologic
a S.r.l.
Preparatory
phase
I quarter
2015
III quarter
2015
Regional
founds
PPP,
Municipalities
9 Executive projects
of any “signs”
identified as
priorities
Provincia of
Foggia
Not active III
quarter
2015
II quarter
2016
Regional
founds
PPP
10 Installation of
signage and
informational
panels
GAL (Local
Action
Group)
Meridaunia
Not active III
quarter
2015
IV quarter
2016
Regional
founds
PPP and
Municipalities
11 Monitoring phase
for the
reconstitution of
the physical
continuity of the
area of tratturo
Cicloamici Active III
quarter
2015
II quarter
2016
Regional
founds
PPP and
Municipalities
12 Organizing the
first National day
of tratturo” event
CAI (Italian
Alpine
Club)
Active II
quarter
2014
II quarter
2015
Municipalitie
s funds
Associations and
Municipalities
13 Applications for
virtual visits and
assistance
Provincia of
Foggia
Active II
quarter
2014
IV quarter
2014
Provincial
funds
PPP
14 Award of contract
for the Land Art
"60 Steps in
nature" activity
Provincia of
Foggia
Active IV
quarter
2014
II quarter
2015
PO FESR
2007-2013
Axis IV,
Actions 4.2.2
and 4.4.2
Region,
Associations
15 “Lab and Art"
sub-activities of
Land Art event
Provincia of
Foggia
Not active III
quarter
2015
II quarter
2020
PO FESR
2007-2013
Axis IV,
Actions 4.2.2
and 4.4.2
Region,
Associations
16 “Target land art”
sub-activities of
Land Art event
Provincia of
Foggia
Not active III
quarter
2015
II quarter
2020
PO FESR
2007-2013
Axis IV,
Actions 4.2.2
and 4.4.2
Region,
Associations
17 Drafting a
experimental
cultivation plan
“Azienda
agricola -
Russo
Preparatory
phase
I quarter
2015
IV quarter
2015
Regional and
private funds
Private
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
21
and its economic
evaluation
Francesco”
18 Experimentation
in the field for
experimental
cultivation
“Azienda
agricola -
Russo
Francesco”
Not active I quarter
2016
IV quarter
2017
Regional Private
19 Monitoring the
status of places
for an integrated
network of soft
mobility
“Cicloamici
Association
” and “CAI
Foggia”
Active III
quarter
2014
III quarter
2015
Regional and
provincial
funds
Private,Associati
ons
20 Final design for
soft mobility
Provincia of
Foggia
Not active II
quarter
2015
II quarter
2016
Regional and
provincial
funds
21 Study of
connections with
other paths
“Promodaun
ia” and
“CAI
Foggia”
Not active I quarter
2015
IV quarter
2017
European
funds
PPP,
Municipalities,
Region
22 Training of guides Archeologic
a S.r.l.”
Not active III
quarter
2015
IV quarter
2016
Regional
funds
Private,
Municipalities,
Region
23 Schedule for
promotion and
dissemination
Apulia Felix
Foundation
Not active I quarter
2015
IV quarter
2017
Regional and
municipalitie
s funds
Private, PPP and
Municipalities
24 Finding lists of
economic
operators and
their activities
“Rete del
Mediterrane
o”
Not active I quarter
2015
II quarter
2015
Private funds Private,
Municipalities
25 Experimentation
with use of the
App
“Rete del
Mediterrane
o”
Not active III
quarter
2015
IV quarter
2017
Provincial
funds
Associations,
Private
26 Creating
multifunctional
networks
“Rete del
Mediterrane
o”
Not active I quarter
2015
DRP and
regional
funds
Private,
Associations,
Municipalities
27 Schedule for
education
programs
Centro Studi
Naturalistici
O.N.L.U.S.”
Not active II
quarter
2015
II quarter
2016
Regional
funds
Region, Private,
Schools
Table 3: STA´s Action Plan of Provincia of Foggia area in a timeline
nr Actions 2014 2015 2016 2017
3quarter 4quarter 1quarter 2quarter 3quarter 4quarter 1quarter 2quarter 3quarter 4quarter 1quarter 2quarter 3quarter 4quarter
1 Organize the first TTF
operational meeting
2 Make known and public
the creation of the TTF
and of the signed
Partnership Agreement
3 Presentation of the STA
to the local community
4 Promote the Actions of
the new 2014-2020
Programming
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
22
5 Adjustment of Municipal
Master Plans to POI
6 Organize meetings to
participate to
"framework structure"
contents
7 Fit out the Territorial
Center at the “Museo del
Territorio”
8 Check and completing of
the recognition of
“signs” that make
recognizable the path
9 Executive projects of any
“signs” identified as
priorities
10 Installation of signage
and informational panels
11 Monitore phase for the
reconstitution of the
physical continuity of the
area of tratturo
12 Organize the first
National day of tratturo”
event
13 Applications for virtual
visits and assistance
14 Award of contract for the
Land Art "60 Steps in
nature" activity
15 “Lab and Art" sub-
activities of Land Art
event
16 “Target land art” sub-
activities of Land Art
event
17 Draft a experimental
cultivation plan and its
economic evaluation
18 Experimentation in the
field for experimental
cultivation
19 Monitor the status of
places for an integrated
network of soft mobility
20 Final design for soft
mobility
21 Study of connections
with other paths
22 Training of guides
23 Schedule for promotion
and dissemination
24 Finding lists of economic
operators and their
activities
25 Experimentation with
use of the App
26 Creating multifunctional
networks
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
23
27 Schedule for education
programs
5.2 Risk assessment
Table 4: Risk assessment
Identification of the risk Qualitative risk
assessment
Responding on the
risk
Monitoring and control
Priority
nr.
Identification of the risk Reason Potential
effects
Probability
of occurance
(high /
medium /
low)
Impact
(high /
medium /
low)
Strategy
(Avoidance /
Reduction /
Sharing /
Acceptance)
Measure Person responsible Timeline
(monthly,
weekly,…)
1 Lack of founds Avoidance
2 Lack of co-
ordination
Reduction
3 Political change Acceptance
4
5
5.3 Recommendations for the implementation of the STA
During the strategy implementation process, Regions, Province, Municipalities and stakeholders will collaborate in order to ensure the alignment of actions. The phases that are to be gone through during the implementation period of the strategy are summarized below:
Creating partnerships
Monitoring the strategy implementation
6 Project Fiches: Priority projects corresponding
to each goal/objective of the STA
Priority project nr. 1: Drafting of a document, for the RDP and ERDF negotiation table
Description
The project includes the participation to the negotiating table of Rural Development Program
(RDP 2014-2020) and Puglia Regional Operational Programme (ERDF 2014-2020), through the
drafting of a document to be submitted to the competent bodies during the negotiating table.
The project aims to orient or guide strategic policy choices of the next regional program 2014-
2020 in order to promote initiatives in support of all tratturi in the Provincia of Foggia. Among
other possible initiatives, the regional program could promote appropriate actions to guide the
agricultural practices or to improve the slow mobility in the area.
The actions of the STA are particularly consistent with the following priorities for the next RDP
2014-2020:
PRIORITY 2:
Strengthening the competitiveness of agriculture in all its forms and profitability of farms
PRIORITY 4:
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
24
Restoring, preserving and enhancing ecosystems dependent on agriculture and forestry
Preserve and restore biodiversity including Natura 2000 sites, the high nature value
farming and the natural landscape of the European
Location
All the Apulian area of the tratturo Pescasseroli-Candela
Status
The document was already drawn up, signed by the local institutions (Municipalities and
representative of union or association of farmers) and sent to the Apulia Region (Annex 6).
The document identifies opportunities for strategic enhancement of the Apulian tratturo and asks
that can be transposed into programming the new PSR Region Puglia, the following useful
indications for restoration, maintenance and enhancement of areas of the tratturi:
for measures 213 and 214, the extension of the areas eligible for funding to areas of tratturi,
both in the areas of "pertinence" in the "annexed" areas ;
for measures 211, 212, 214, greater premium for the areas used for grazing; such a premium
could be approximated to that of the homologous measures implemented by the DSP of the
Campania and Molise Regions;
under the measure 216, introduction of an action providing for the creation of buffer strips,
tree lines, hedges and dry stone walls along the bands of the tratturi, in consideration of their
recognized function of terrestrial ecological corridors;
under measure 221, the introduction of a specific action aimed at the restoration of "mezzane",
planting specific tree species;
under measure 311, between the various criteria for diversification measures in non-
agricultural activities, the introduction of rewarding for the "subsistence farm near the
tratturo";
adopt a slight signage for the purpose of tourist use of the cattle track, through the nature trails
(measure 313)
enhancing the tratturo with intangible assets (communication, measuring 421 etc.)
The document has been signed by:
The Extraordinary Commissioner of the Provincia di Foggia
The Mayor of Comune di Anzano
The Mayor of Comune di Monteleone di Puglia
The Mayor of Comune di Rocchetta S.Antonio
The Mayor of Comune di S.Agata di Puglia
The Mayor of Comune di Candela
Local Action Group Meridaunia
Confagricoltura Foggia (union of farmers)
Copagri Foggia (union of farmers)
Coldiretti Foggia (union of farmers)
Confederazione Italiana Agricoltori (union of farmers)
ConfCoperative Foggia (union of farmers)
Timeline
-
Investments costs estimation
The project have no cost
Funding opportunities
RDP and ERDF 2007-2020
Opportunities for partnership (if applicable)
Region, GAL, Famers Associations
Priority project nr. 2: Sharing the content of the POI10 "Renovation and development of
Pescasseroli-Candela”
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
25
Description
Because the existing instruments for programming don’t consider the tratturo as a territorial
resource around which to build recovery and enhancement actions, the project considers strategic
to share and co-ordinate territorial planning tools in order to take action more coherent and aligned
with the common goal.
The action involves the review and the sharing of the planning strategies of the Integrated
Operational Plan) proposed by the Province of Foggia as executive plan of the regional landscape
plan. In such a way local institution can co-ordinate their territorial planning tools in order to take
action more coherent and aligned with the common goal.
Location
All the Apulian area of the tratturo Pescasseroli-Candela
Status
The September 29, 2014, the institutional stakeholders (the concerned Municipalities) attended the
“conferenza dei servizi” (a sort of public agencies meeting) and signed the POI (Integrated
Operational Plan, (provided in the Apulian new landscape plan) devoted to safeguard and
valorization the tratturo Pescasseroli-Candela. (Annex 7)
Timeline
-
Investments costs estimation
The project have no cost
Funding opportunities
RDP 2007-2020
Opportunities for partnership (if applicable)
Region, Municipalities
Priority project nr. 3: Participation to the drafting of the "framework structure" of the “Park
of Tratturi”
Description
Because the existing instruments for programming don’t consider the tratturo as a territorial
resource around which to build recovery and enhancement actions, the project considers strategic
to share and co-ordinate territorial planning tools in order to take action more coherent and aligned
with the common goal.
The project expect the participation of local institutions to the drafting of the "framework
structure" of the “Park of Tratturi”; such a plan, together with the "document of valorization”, that
will introduce the elements to enhance the system of tratturo, is the general framework for
programming by the Apulia Region.
Location
All the Apulian area of the tratturo Pescasseroli-Candela
Status
In preparatory phase
Timeline
-
Investments costs estimation
The project have no cost
Funding opportunities
RDP 2007-2020
Opportunities for partnership (if applicable)
Region, Municipalities
Priority project nr. 4: Recovery of the signs that make recognizable the path
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
26
Description
The tratturo has to be clearly identified in order to enhance the community ability to recognize it.
The project expects to recovery those signs that made recognizable the pathway:
o the “cippi” – ancient stones boundary- are signals of the tratturo;
o works destined to make viable infrastructure, such as bridges
o artifacts of service to the shepherds and to their flocks, as the fountains
o properties for service and refreshments, such as taverns
o properties and artifacts of popular devotion linked to the pastoral life, such as churches,
sanctuaries, shrines and crosses road.
Making the tratturo recognizable and continuous could increase its fruition.
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase.
In particular the “Archeologica S.r.l.”(a spin-off of the University of Foggia) is committed to
make the tratturo more visible, recognizable and usable as well as to make tratturo equipped for
the new features / services, through the study of signs that made it recognizable path.
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Public Private Partnerships
Priority project nr. 5: Installation of signage and informational panels
Description
The tratturo has to be clearly identified in order to enhance the community ability to recognize it.
The signage and the informational panels will be installed along the way of tratturo (referring to
the signs of the cadastre of the Apulia Network Trekking and to the conventional signage of the
CAI (Italian Alpine Club).
Making the tratturo recognizable and continuous could increase its fruition.
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase.
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Public Private Partnerships, Municipalities
Priority project nr. 6: Reconstitution of the physical continuity of the area of tratturo
Description
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
27
The tratturo has to be clearly identified in order to enhance the community ability to recognize it.
The action expects some interventions devoted to the physical protection of the territory,
including:
o securing of pedestrian and bicycle paths and of bridleways
o restoration of trails and/or runs on tracks that no longer exist
o projects of greenways and cycle routes that constitute the base of an integrated network of
soft mobility (ref. regional law 21/2003 "Norms on activities and excursions networks of
Puglia " and Regulation n.23/2007 “Regulation for the implementation of the Apulian
excursions networks”)
o recovering of cultural heritage and of the sparse buildings
Three phases are provided: the monitoring, the designing, the execution of works.
In the monitoring phase (already started), the bikers and the walkers followed the track of
the tratturo trying to highlight what may be the problems and the potential of the path. Such
an assessment is finalized to the organization of cycle paths but, more importantly, to
identify the type of services needed. (see Annex 8 and 9)
In the designing phase will be identified the type of services needed.
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase.
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Public Private Partnerships, Municipalities
Priority project nr. 7: Organizing “The national day of tratturo”
Description
The “day of tratturi" is an interregional event of trekking that will held annually; such event
involves the associations of the walkers, the riders, the cyclists but also the schools and their
students.
It is organized by the CAI (of the Apulia, Campania and Abruzzo regions) and promoted and
advertised also by the Municipalities.
The CAI is the coordinator of the organization of the "National Day of Tratturo", that will take
place along the entire length of the Regio tratturo Pescasseroli-Candela.
As promotional event, it will contribute to focus on the protection and valorization issues.
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In progress.
The description of the activities: At the moment, the CAI produces an outline of the event that that
it is sharing with the other involved stakeholders (see Annex 10) e that and which includes the
following actions:
the "National Day of Tratturi" is publicized through a communication system that starts from
the regions involved and see that the municipalities in the front row, along the Pescasseroli -
Candle; associations and schools are involved and the latters will have a "theme/search" on the
culture-history that the tratturo left to our generation;
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
28
at the same time, in all organized events, we kick off to the path to the sound of a "bell" that
symbolically indicated in Agnone;
every municipality welcomes walkers crossed with a "simple and pastoral refreshment" in a
festive crossing the town;
arriving at the end of each path with a simple demonstration pastoral background.;
each municipality is free to organize the event in the way that best characterizes their
contextual reality.
The first "National Day of Tratturi" will be held in Spring 2015
Timeline
-
Investments costs estimation
The costs will be borne by the organizers and of the involved associations and municipalities
Funding opportunities
Municipalities funds
Opportunities for partnership (if applicable)
Associations, Municipalities
Priority project nr. 8: Creating an interregional consortium
Description
The project expects the creation of an interregional consortium that could have a direct access to
European funding, provide immediate guidance for the promotion of goods and involve the private
sector (Confescercenti, Confconsumatori, agricultural structures, etc.).
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
Not active.
Timeline
-
Investments costs estimation
-
Funding opportunities
Private funds
Opportunities for partnership (if applicable)
Public Private Partnership
Priority project nr. 9: Applications for virtual visits and assistance
Description
The project expects to realize applications (basically building an app and a website) for virtual
visits and assistance with navigation tablet. The idea is that everyone should have the opportunity
to walk along the tratturo, and that the virtual recognizability should be aimed at increasing the
viability physical.
The applications realized with this project aims to: support the process of participation and
involvement of local communities, identify the pathways, organize events, and, still, support the
monitoring actions. (Annex 11)
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase. The Provincia of Foggia is selecting experts to involve in the project.
Timeline
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
29
-
Investments costs estimation
-
Funding opportunities
Provincial funds
Opportunities for partnership (if applicable)
Public Private Partnerships
Priority project nr. 10: Land art event
Description
The project expects to make the area of tratturo an open-air museum through the installations by
land art along the tratturo Pescasseroli-Candela. Such a project may contribute to focus on the
most significant places; the installations will be inspired by the themes of farming and the rural
world and made with eco-sustainable materials. The project of SAC (Environment and Cultural
Systems) “Monti Dauni e Lucera” is currently working on such an idea).
The project, which will last for five years, involves the activity entitled "60 Steps in nature"; it is
an enhancement activity of a portion of the royal tratturo Candela-Pescasseroli. In detail, such
project involves the construction of the following sub-activities:
1 "Lab and Art" - land art laboratories:
2 "Target land art" - photo-video stories: the creation of groups of individuals passionate about
photography and video. (Annex 12)
Location
A limited area of the tratturo.
Status
-
Timeline
-
Investments costs estimation
-
Funding opportunities
PO FESR 2007-2013 Axis IV, Actions 4.2.2 and 4.4.2
Opportunities for partnership (if applicable)
Region, Associations
Priority project nr. 11: Management and maintenance system
Description
The “system for management and maintenance the tratturo” is a project that involves the
collaboration between institutions. Such a system includes:
Constant cleaning of the areas of tratturo from waste and weed species
modest interventions of water regulation of surface runoff
recovery of ancient sources, of existing sources and of troughs along the tratturo
facilities for the granting of grazing
control of the territory
recovery / visual mitigation of the impact of industrial areas (production areas along the SS 89
and SS 16);
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
30
recovery of the landscape through the maintenance areas of tratturo: native plants along the
edge of tratturo and actions of naturalization; buffer strips, tree lines, hedges and dry stone
walls along the bands of tratturo, in consideration of their recognized function of terrestrial
ecological corridors; avenues of access to the city; wildflower (peri-urban areas and / or fringe
roads).
The system for management and maintenance the tratturo also includes:
native plants along the border of tratturo and actions of naturalization (see funding of RDP);
buffer strips, tree lines, hedgerows and dry stone walls along the bands of tratturo (because of
their recognized function of terrestrial ecological corridors);
tree-lined avenues of access to the cities;
wildflower (in peri-urban areas and / or fringe road) - aesthetic and landscape enhancement
and environmental restoration at low energy input of anthrop environments through the
characterization and use of wildflowers originated by species and ecotypes.
Location
All the area of the Region tratturo Pescasseroli-Candela
Status
Not active.
Timeline
-
Investments costs estimation
-
Funding opportunities
Municipalities and Regional funds
Opportunities for partnership (if applicable)
PPP and Municipalities
Priority project nr. 12: Agricultural practices towards protection and preservation of the
landscape
Description
The project expects to orient the agricultural practices (e.g. plowing, crop basis) towards the
protection and preservation of the landscape, through the provision of incentives and the
concession of the areas of the tratturo. The granting of the concession to farmers could be
conditioned with the commitment to act in order to safeguard the legibility of tratturo (e.g. through
plants and, in the case of use of arable land, respecting the direction of plowing parallel to the
longitudinal axis of the tratturo). Such a condition would be compensated, with the possibility of
access to the benefits of the RDP, extended not only to the owners of the funds, but also to those
having non-ownership title to lead the funds, thus including tenants and licensees.
In particular the “Azienda agricola - Russo Francesco” is committed to:
make available to stakeholders their experience and expertise in the field of coexistence
between the ecosystems reconstruction and biodiversity and the economic exploitation of the
agricultural resource;
the promotion and the non-economic sustenance of proposed initiatives;
broaden their field trials to reach new goals of coexistence between the natural and agricultural
crops, based on the needs that emerge from the work of the task force.
The “Azienda agricola - Russo Francesco” will experience the closing of a short chain.
The GAL Meridaunia will ensure the widest possible dissemination of news, of the activities and
initiatives related to the tratturo, through its tools and partnership networks.
Location
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
31
The agricultural area of pertinence of the tratturo
Status
Not active
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Private
Priority project nr. 13: Integrated network of soft mobility
Description
The project tries to organize the slow mobility: the tratturos are natural equestrian road and they
can become cycling routes, hiking routes and for people with disabilities. Walkers need a special
signage, safety, receptivity (water for wash, minimal accommodation) a stopping every 30 miles
(also every 10), the accessibility to the near villages, the “certification of walker”. Bikers need an
inventory of existing little fountains, small oasis with trees, a stopping every 10-15 miles, stopping
areas, technical assistance services with an even minimal endowment of tools and equipment for
the repair kit. Horsemen need to: space and resources for stopping, for the care and feeding of the
horses; services as horseshoer, veterinary, etc.
The receptivity should be organized in the farms and taverns, which are currently uninhabited but
all surveyed, to become a path, the historical tratturo requires places of exchanges and facilities
for all kind of users.
In particular the “Apulia Felix Foundation” is committed to involving citizenship to share and
implement an open consultation on the design of the works of slow mobility or of other ways of
using the path.
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase.
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
-
Priority project nr. 14: Creating connection with other paths
Description
The Pescasseroli-Candela tratturo must be connected:
at the regional level the tratturo:
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
32
o to the regional network of the tratturo; it has a cultural, environmental, and ecological
relevance and it could have important implications in both the touristic and transportation
sectors
o to the infrastructures system for soft mobility tratturi can host most of the mobility system
slow) (rif. Regional Landscape Plan)
o to the regional ecological network (the tratturi are “rivers of grass” that unite the two main
poles: the Gargano and the mountains Dauni
at interregional level, the track of tratturo to the other paths (eg.: path of the Francigena route,
funding from the Region for the signs; homologation paths CAI)
at transactional and European level:
o by relating the path of the Tratturo Pescasseroli-Candela with the other trails of
transhumance in Europe; by sharing projects and experiences with other EU countries;
o by protecting the tratturo as world heritage site (Unesco)
In particular the “Archeologica S.r.l.” is committed to those activities devoted to make the tratturo
equipped for the new features / services, through the study of the connections with other cultural
routes.
Location
-
Status
Not active.
Timeline
-
Investments costs estimation
-
Funding opportunities
European funds
Opportunities for partnership (if applicable)
PPP, Municipalities, Region
Priority project nr. 15: Training of guides
Description
In order to structure an integrated touristic offer (an offer with also certified quality), local guides
must be trained and guided tours should be organized on the territory:
youth cooperatives,
network businesses,
educational farms
Trained guides, that can be organized as business, may manage information points for visitors, and
may articulate proposals for stay.
In particular the “Archeologica S.r.l.”(a spin-off of the University of Foggia) is committed to make
the tratturo equipped for the new features / services, through the the training of tourist guides.
Location
-
Status
Not active
Timeline
-
Investments costs estimation
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
33
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Private, Municipalities, Region
Priority project nr. 16: Promotion and dissemination
Description
Promotional events could contribute to focus on the protection and valorization issues. The project
expects:
promotional events, participation in trade fairs
promotion through the instrument of the web and using new technologies
In particular:
the GAL (Local Action Group) Meridaunia is committed to ensure the widest possible
dissemination of news, of the activities and initiatives related to the tratturo, through its tools
and partnership networks;
the Apulia Felix Foundation ” is committed to inviting artistically talented young people to
rethink the tratturo and promoting contests of ideas for its enhancement;
Promodaunia is committed to shoot movies for popularizing and promoting of the tratturo
Location
All the area of the Regio tratturo Pescasseroli-Candela
Status
In preparatory phase
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional and municipalities funds
Opportunities for partnership (if applicable)
Private, PPP and Municipalities
Priority project nr. 17: Multi-functionality of the agricultural entrepreneur
Description
The project aims to develop and stimulate the multifunctionality of the agricultural entrepreneurs
through incentives for:
receptivity, forms of agritourism, rural tourism, bed & breakfast, picnic areas for the bivouac
catering and sales of agricultural products
markets of proximity
In particular:
the “Centro Studi Naturalistici O.N.L.U.S.” si committed to provide their own professional
experience in the field of animal sciences and plant sciences through organization of
promotional touristic packages;
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
34
the “Rete del Mediterraneo” is committed to market the guided tours in order to improve the
economic impact of the attractors and organize courses for the inclusion of "best practices" for
innovation in processes, for the purpose of a territorial integration and a social cohesion
Location
Agricultural areas
Status
Not active.
Timeline
-
Investments costs estimation
-
Funding opportunities
RDP and regional funds
Opportunities for partnership (if applicable)
Private
Priority project nr. 18: Education programs
Description
The project includes educational programs for children and schools.
In particular the “Centro Studi Naturalistici O.N.L.U.S.” is committed to provide their own
professional experience in the field of animal sciences and plant sciences through educational
outreach activities.
Location
-
Status
Not active.
Timeline
-
Investments costs estimation
-
Funding opportunities
Regional funds
Opportunities for partnership (if applicable)
Region, Private, Schools
7 The PosterPlan
The Poster Plan represents the summary of the STA in Provincia di Foggia area.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
35
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
36
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
37
8 Conclusions
The findings of the working groups and plenary discussions lead to the idea that a strategic
Agenda for recovery and enhancement of the tratturo should provide a "global project"
consisting of a series of actions, all important, which should act almost simultaneous. The
tratturo is, and remains, a path whose original functions were lost but that has other
recognizable features; these are the features of: a terrestrial ecological corridor, a natural
course (on foot, on horseback, by bicycle and for different types of users), an open-air
museum. These new features should be, of course, ensured. In order to assure such new
functions/features, during the meetings, participants in the workshop proposed many actions
that could be summarized in the followings:
Actions to create the path (or the paths) and, at the same time, both the "open air museum"
(to guarantee the preservation of historical memory) and its contribution to the network of
ecological corridors;
Actions to ensure the safety of the tratturo and its maintenance (also through incentives to
dealers, or the establishment of figures as that of guardian of the sheep-track, etc.)Azioni
volte a garantire la riconoscibilità fisica del tratturo;
Actions aimed at the promotion and at the creation of "expectations";
Actions aimed at creating a tourism product (routes, services, places of exchange, etc.);
Action to improve the culture of the community and the education of the younger
generation;
Among all these actions there are no priority actions in relation to the other ones. However,
all the participants agree that, perhaps, the interventions that have priority (if of priority we
want to speak) are interventions aimed at increasing recognizability of the tratturo.
9 References
Regional Landscape and Territorial Plan (PPTR) adopted in 2010
Provincial Territorial Plan (PTCP) approved in 2009
‘Monti Dauni’ Local Development Plan (LDP) drafted by Local Action Group ‘Meridaunia’in
2010 (30 municipalities involved) http://www.meridaunia.it/
Documento Programmatico per la rigenerazione territoriale – I borghi della Cultura (Edited
by Meridaunia scarl)
http://www.reterurale.it/flex/cm/pages/ServeBLOB.php/L/IT/IDPagina/3545/UT/systemPrint
10 Annexes
Annex 1. Attendance lists
Annex 2. Agenda of the workshops
Annex 3. Pictures of the workshops
Annex 4. Graphical outputs (like maps, drawings, etc)
Annex 5. Summary of discussions of 2th workshop (the working progress document sent to
participants) 1
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
38
Annex 6. Signed document for the RDP and ERDF negotiation table
Annex 7. “Conferenza dei servizi” for the signature of the POI
Annex 8. Contribution edited by “FIAB Foggia Cicloamici” and “Associazione Culturale
Lanterne” (cover)
Annex 9. Monitoring the state of tratturo edited by “FIAB Foggia Cicloamici” (executive
summary)
Annex 10. First agenda of the “National Day of Tratturo” edited by “CAI Foggia”
Annex 11. Invitation letter to public tender with technical annexes for APP implementation
Annex 12. Letter and technical annexes for starting competitive public tender on “60 passi nella
natura“ project
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
39
Annex 1 - Attendance lists
First Workshop
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
40
Second Workshop
Workgroup – 25 febbraio 2014
NO. INSTITUTION ADDRESS CONTACT
PERSON
CONTACT DETAILS
1. Istituto Comprensivo di
Accadia
Via Roma, 24 -
71021 Accadia (Fg)
Silvana Addesa 340.5690406
2. Confagricoltura - Foggia V.le Manfredi , 1,
Foggia
Emidio Ursitti 339.5329845
3. Associazione P.S.
Mancini
Bartolomeo
Distefano
0827.93009
4. Maria Valentina
Lorusso
348.4706725
5. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Giuseppe Baia 328.4280370
6. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Vincenza Nigri 328.2667661
7. Dalmazia
Puopolo
339.3864084
8.
Start Up, Cooperativa
sociale CAI Foggia
Michele Del
Giudice
393.8917725
0881.687975
9. Borghi d’Eccellenza, Vie
Francigene
Maurizio
Varriano
333.6600619
10. Borghi d’Eccellenza, Vie
Francigene
Margherita
Quercia
335.5310583
11.
Pro loco Sepino Piazza Nerazio
Prisco n.40a Sepino
(CB),86017
Michelino
Napolitano
327.7439131
12. Comune di Anzano di
Puglia
Piazza Municipio,
2, Anzano di Puglia
Foggia
Michele Rossi 349.8167537
13.
Comune di Anzano di
Puglia
Piazza Municipio,
2, Anzano di Puglia
Foggia
Giuseppe Di
Paola
348.0855673
ia.fg.it
14.
Comune di Anzano di
Puglia
Piazza Municipio,
2, Anzano di Puglia
Foggia
Paolo Lavanga 0881.982037
349.3255494
a.fg.it
15.
Provincia di Foggia –
Ufficio Assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Stefano Biscotti 335.7441367
0881.791347
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
41
16.
Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Giovanna Caratù 0881.791328
349.1547973
17. Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Adele Celino 347.5759540
Workgroup – 11 marzo 2014
NO. INSTITUTION ADDRESS CONTACT
PERSON
CONTACT DETAILS
1. Centro Studi Naturalistici
ONLUS
Via Vittime Civili,
64, 71121 Foggia
Matteo Caldarella 347.3037851
2.
Comune di Anzano di
Puglia
Piazza Municipio,
2, Anzano di Puglia
Foggia
Michele Rossi 349.8167537
3. Andrano
Vincenzo
333.1687352
4.
Soprintendenza Beni
Archeologici Puglia -
Centro Operativo per
l'Archeologia della
Daunia - Foggia
Via De Nittis, 7 -
71100 Foggia
Antonio
Gaudiano
328.7267893
antonio.gaudiano@beniculturali.
it
5.
Soprintendenza Beni
Archeologici Puglia -
Centro Operativo per
l'Archeologia della
Daunia - Foggia
Via De Nittis, 7 -
71100 Foggia
Italo M. Muntoni 0881725458
italomaria.muntoni@benicultura
li.it
6.
Regione Puglia -
Provinciale Agricoltura di
Foggia
Piazza U.
Giordano, 1 (Pal.
Uffici Statali) -
71100 Foggia
Antonio Ursitti 0881.706549
349.8601148
7.
FIAB- Federazione
Italiana Amici Bicicletta,
Ass. di Vol. Cicloamici
Foggia
Via P. Telesforo,
140 – 71122 Foggia
Giuseppe
Dimunno
329.3157647
8.
Comune di Rocchetta
Sant’Antonio
Piazza A. Moro
n.12, Rocchetta
Sant’Antonio
Angeloantonio
Mastropietro
328.4205675
0885.654007
9.
Start Up, Cooperativa
sociale CAI Foggia
Michele Del
Giudice
393.8917725
0881.687975
10. Borghi d’Eccellenza, Vie Maurizio 333.6600619
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
42
Francigene Varriano [email protected]
11. Borghi d’Eccellenza, Vie
Francigene
Margherita
Quercia
335.5310583
12.
FIAB- Federazione
Italiana Amici Bicicletta,
Ass. di Vol. Cicloamici
Foggia
Via P. Telesforo,
140 – 71122 Foggia
Antonio Dembech 348.8822041
13. Centro Ippico Fitetrec “La
Contessa”
Località "La
Contessa", Foggia
Franco Cuttano 320.2514797
14. Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Stefano Biscotti 335.7441367
0881.791347
15.
Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Giovanna Caratù 0881.791328
349.1547973
16. Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Adele Celino 347.5759540
Workgroup – 18 marzo 2014
NO. INSTITUTION ADDRESS CONTACT
PERSON
CONTACT DETAILS
1. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Anna Maria
Demilio
0881.706581
2. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Maria Rosaria
Settimo
0881.706583
3. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Lucia De Luca 0881.706565
4.
Start Up, Cooperativa
sociale CAI Foggia
Via Ernesto
Petrone, 60, Foggia
Michele Del
Giudice
393.8917725
0881.687975
5. Antonello Del
Giudice
380.1261158
6.
Soprintendenza Beni
Archeologici Puglia -
Centro Operativo per
l'Archeologia della
Daunia - Foggia
Via De Nittis, 7 -
71100 Foggia
Antonio
Gaudiano
328.7267893
antonio.gaudiano@beniculturali.
it
7.
Soprintendenza Beni
Archeologici Puglia -
Centro Operativo per
l'Archeologia della
Daunia - Foggia
Via De Nittis, 7 -
71100 Foggia
Italo M. Muntoni 0881725458
italomaria.muntoni@benicultura
li.it
8. ANPCI (Associazione UN.COM.ALTO Orazio Ciummo 335.8418400
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
43
nazionale Piccoli Comuni
d’Italia) - Molise
VOLTURNO (Is)
9.
Associazione Terre e
Uomini dei Monti Dauni
Via Favata'
Giovanni, Candela
Francesca
Capaldo
329.9854530
10. Associazione Terre e
Uomini dei Monti Dauni
Via Favata'
Giovanni, Candela
Francesca
Buccino
329.9854530
11. Borghi d’Eccellenza, Vie
Francigene
Maurizio
Varriano
333.6600619
12. Borghi d’Eccellenza, Vie
Francigene
Margherita
Quercia
335.5310583
13. Provincia di Foggia –
Ufficio Assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Stefano Biscotti 335.7441367
0881.791347
14.
Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Giovanna Caratù 0881.791328
349.1547973
15. Provincia di Foggia –
Ufficio assetto del
Territorio
Via Paolo
Telesforo, 53,
Foggia
Adele Celino 347.5759540
Workgroup – 25 marzo 2014
NO. INSTITUTION ADDRESS CONTACT
PERSON
CONTACT DETAILS
1. Associazione Terre e
Uomini dei Monti Dauni
Via Favata'
Giovanni, Candela
Vito Malgieri [email protected]
2.
Associazione Terre e
Uomini dei Monti Dauni
Via Favata'
Giovanni, Candela
Francesca
Capaldo
329.9854530
3.
Associazione Terre e
Uomini dei Monti Dauni
Via Favata'
Giovanni, Candela
Francesca
Buccino
349.96928742
4. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Anna Maria
D’Emilio
0881.706581
5. Regione Puglia – Ufficio
parco tratturi
P.zza Cavour, 23 -
71121 Foggia
Vincenza Nigri 328.2667661
6.
Start Up, Cooperativa
sociale CAI Foggia
Via Ernesto
Petrone, 60, Foggia
Michele Del
Giudice
393.8917725
0881.687975
7. Borghi d’Eccellenza, Vie
Francigene
Maurizio
Varriano
333.6600619
8. Borghi d’Eccellenza, Vie
Francigene
Margherita
Quercia
335.5310583
9. GAL Meridaunia Piazza Municipio, Laura Mariano 0881.912007
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
44
2, Bovino
10. Confagricoltura - Foggia V.le Manfredi , 1,
Foggia
Emidio Ursitti 339.5329845
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
45
Annex 2 - Agenda of the workshops
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
46
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
47
Agenda of the second workshop
Martedì 25 febbraio 2014
Sede: Comune di Anzano di Puglia
Registrazione dei partecipanti
Apertura dei
lavori
15.30
Benvenuto da parte dell’istituzione ospite
Presentazione degli obiettivi del workshop
Introduzione all’Agenda dei lavori
Interventi
programmati
16.15
Presentazione dei nuovi partecipanti
Presentazione delle conclusioni del precedente workshop
(report STATUS)
Interventi programmati
Gli interventi programmati avranno l’obiettivo di introdurre i
partecipanti alle questioni sollevate durante il primo incontro
offrendo l’occasione di approfondirle. Tra gli altri, interverranno:
Regione Puglia, Provincia, Comuni e Associazioni di categoria
Formazione
Gruppi di lavoro
18.00
Sintesi dei temi da affrontare nei gruppi di lavoro
FORMAZIONE E PRESENTAZIONE DEI GRUPPI DI LAVORO
Accessibilità
Paesaggio
Proprietà
Governance
Plenaria e
chiusura dei
lavori
19.00
Discussione plenaria
CHIUSURA DEI LAVORI
Martedì 11 marzo 2014
Sede: Provincia di Foggia
Registrazione dei partecipanti
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
48
Apertura dei
lavori
15.30
Benvenuto da parte dell’istituzione ospite
Introduzione all’Agenda dei lavori
Lavoro in gruppo Presentazione dei nuovi partecipanti
GRUPPO DI LAVORO: Paesaggio
Discussione sulle conclusioni del primo WS e della prima giornata
Sintesi delle criticità
Possibili soluzioni
Definizione delle priorità
Evidenza delle possibili esternalità negative o positive (conflitti,
difficoltà, etc.)
Opportunità di finanziamento delle nuove proposte
CHIUSURA DELLA SESSIONE
Martedì 18 marzo 2014
Sede: Provincia di Foggia
Registrazione dei partecipanti
Apertura dei
lavori
15.30
Benvenuto da parte dell’istituzione ospite
Introduzione all’Agenda dei lavori
Lavoro in gruppo Presentazione dei nuovi partecipanti
GRUPPO DI LAVORO: Accessibilità
Discussione sulle conclusioni del primo WS e della prima giornata
Sintesi delle criticità
Possibili soluzioni
Definizione delle priorità
Evidenza delle possibili esternalità negative o positive (conflitti,
difficoltà, etc.)
Opportunità di finanziamento delle nuove proposte
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
49
CHIUSURA DELLA SESSIONE
Martedì 25 marzo 2014
Sede: Provincia di Foggia
Registrazione dei partecipanti
Apertura dei
lavori
15.30
Benvenuto da parte dell’istituzione ospite
Introduzione all’Agenda dei lavori
Lavoro in gruppo Presentazione dei nuovi partecipanti
GRUPPO DI LAVORO: Proprietà
Discussione sulle conclusioni del primo WS e della prima giornata
Sintesi delle criticità
Possibili soluzioni
Definizione delle priorità
Evidenza delle possibili esternalità negative o positive (conflitti,
difficoltà, etc.)
Opportunità di finanziamento delle nuove proposte
CHIUSURA DELLA SESSIONE
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
50
Annex 3 - Pictures of the workshops
First Workshop
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
51
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
52
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
53
Second workshops
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
54
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
55
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
56
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
57
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
58
25 March 2014 – Provincia di Foggia
25 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
59
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
60
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
61
25 February 2014 – Comune di Anzano di Puglia
25 February 2014 – Comune di Anzano di Puglia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
62
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
63
18 March 2014 – Provincia di Foggia
18 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
64
25 March 2014 – Provincia di Foggia
25 March 2014 – Provincia di Foggia
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
65
Annex 4 - Graphical outputs of the second workshop
Figure: The graphical output discussed in the workgroup “Governance and Stakeholders”
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
66
Figure: The graphical output discussed in the workgroup “Accessibility”.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
67
Figure: The graphical output discussed in the workgroup “Landscape
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
68
Annex 5 – Summary of discussions of 2th workshop
first Workshop – November 19, 2013
second Worshop – February 25, 2014
March 11
March 18
March 25
The network of the tratturi …
• It is the story of the large flows of people and sheep that moved from the Abruzzo Region and they arrived
in the Apulian Region
• It is a park, the most important park of the Region; it is a particular park: branched, reticular ... a public
property
• It is a common good made up of many things, including of history
A strategic Agenda for recovery and enhancement of the tratturo should provide a "global project" consisting of
a series of actions, all important, which should act almost simultaneously. The tratturo is, and remains, a path
whose original functions were lost but that has other recognizable features; these are the features of: a terrestrial
ecological corridor, a natural course (on foot, on horseback, by bicycle and for different types of users), an open-
air museum. These new features should be, of course, ensured. In order to assure such new functions/features,
during the meetings, participants in the workshop proposed many actions (ref meeting of November 19) that
could be summarized in the followings:
Actions to create the path (or the paths) and, at the same time, both the "open air museum" (to guarantee the
preservation of historical memory) and its contribution to the network of ecological corridors;
Actions to ensure the safety of the tratturo and its maintenance (also through incentives to dealers, or the
establishment of figures as that of guardian of the sheep-track, etc.)
Actions aimed at the promotion and at the creation of "expectations";
Actions aimed at creating a tourism product (routes, services, places of exchange, etc.);
Action to improve the culture of the community and the education of the younger generation;
To ensure both the creation of this strategic agenda and the start of its implementation, it is necessary, of course,
the establishment of a task force with design skills, able to connect with the bodies and the competent
authorities.
Among all these actions there are no priority actions in relation to the other ones. However, all the participants
agree that, perhaps, the interventions that have priority (if of priority we want to speak) are interventions aimed
at increasing recognizability of the tratturo.
The actions that the participants consider important to be carried out (which, in truth, are already being planned
by the working group of the project STATUS) are:
1. Drafting a document, for the negotiation table, in which it is proposed the tratturo Pescasseroli-Candela as a
priority for the next programming CAP (PSR in the first place). The document should identify opportunities
for strategic enhancement of the Apulian tratturi, that have to be submitted to the attention of both local
governments and the Apulia Region. Such a document could orient or guide strategic policy choices of the
next regional program 2014-2020. Such a document could identify, among other things, the appropriate
actions to guide the agricultural practices.
2. Creating an interregional consortium, a "control booth" (with its operating unit) with coordination functions.
The consortium can sit at the negotiating table, to be accredited by the Ministry, have direct access to
European funding, provide immediate guidance for the promotion of goods and involve the private sector
(Confescercenti, Confconsumatori, agricultural structures, etc.)
3. Using technology (basically building an app and a website): to support the process of participation and
involvement of local communities, to identify the pathways, to organize events, and, still, to support the
monitoring actions.
4. Organizing the "day of tratturi", involving the associations of the walkers, the riders, cyclists but also
schools and students. The CAI proposes an interregional event (with CAI and the regions of Puglia,
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
69
Campania and Abruzzo) of trekking; this event should be organized and promoted also by the
Municipalities. On the same day the event will be proposed for cyclists and riders.
5. Organizing the land art event.
GOVERNANCE
h. Critical issues
• there is a lack of coordination and planning • there is a lack of a comprehensive and coherent strategy to make the individual actions of local actors
efficient • the proposed development of a tratturo, as a great opportunity for territorial development, inevitably
requires the cooperation of local actors • we often talk of a segment of the tratturo, that one of the Puglia region, and not of the entire royal
tratturo Proposals
• The vision of the Pescasseroli-Candela tratturo must be introduced in a system vision: o at the regional level the tratturo must be connected:
to the regional network of the tratturi (for the park of tratturi, the Apulia region is currently drafting the "framework structure", which will be the general framework for programming, and the "document of valorization" that will introduce the elements to enhance the system of tratturi); the Regional Park of Tratturi is a regional park that would need the same
incentives of the other regional parks. On the other hand, it has a cultural, environmental, and
ecological relevance and it could have important implications in both the touristic and
transportation sectors
to the infrastructures system for soft mobility tratturi can host most of the mobility system slow) (rif. PPTR)
to the regional ecological network (the tratturi are “rivers of grass” that unite the two main poles: the Gargano and the mountains Dauni
o at interregional level, the track of tratturo must be connected: at interregional level, the track of tratturo must be connected; to the other paths (eg.: path of the Francigena route, funding from the Region for the signs;
homologation paths CAI) o at transactional and European level:
by relating the path of the Tratturo Pescasseroli-Candela with the other trails of transhumance in Europe; by sharing projects and experiences with other EU countries;
by protecting the tratturo as world heritage site (Unesco)
The Council of Europe has added the Via Francigena and the tratturi between the priority
paths . (The Municipality of Formello opened an info point)
You should refer to national and international users; in this vision, the path must be proposed in its
completeness.
• A consortium and a “control booth”, for the functions of coordination, are needed both to participate in the negotiating tables and to be accredited by the Ministry; with the Consortium and its design skills you might have direct access to European funding. It will be proposed as a tool that is able to access to different types and forms of financing for the enhancement of the tratturo. The Consortium would
allow a public dialogue. The consortium may give directions for the immediate promotion of the
products. The Consortium should be interregional and directed by trade associations (eg. Confescercenti, Confconsumatori, agricultural structures) and by local governments. Preparing a draft with the main features of the Consortium could be the first step towards the
certification by the Department of Tourism (Ministry of BBCC). Such a draft has to be organized in
order to access to 2014-2020 funding. The signing of an agreement by the various parties would be
important to carry out this initiative and establish a plan of action on tratturo
• Thematic groups could be set up; for these groups, the practice of reconstructing the landscape should be one of the strategic objectives to be pursued together.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
70
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
i. Critical issues • The current funding and programming do not consider the tratturo as common goods to be improved
and do not allocate financial resources for activities in that area. Greater efforts are needed to change such an idea.
• There is difficulty in identifying the tools that allow you to work in a more coordinated way. Proposals
• In the STATUS process it may be appropriate to prepare a document proposing the tratturo Pescasseroli-Candela as a priority and to bring to the negotiating table to the next programming 2014-2020. This document should identify opportunities for strategic valorization of the tratturi of Puglia, in order to guide strategic policy choices of the next regional program 2014-2020. The
associations of the agricultural world, together with the Regional Offices and the LAG Meridaunia,
must be interpreters and promoters of this initiative to get to the final draft of the negotiation document.
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
ACCESSIBILITY
a. Critical issue: - Vi è una percezione limitata del tratturo
• The tratturo is a good of inestimable value, it is not always visible by the local community; This is, in part, because the tratturo has lost its original function
• The local community that seems to be indifferent to the issues of its protection and valorization • The agriculture, with its practices, is contributing to the modification of the original “river of grass • It is increasingly losing its accessibility, its continuity and the set of elements that make it recognizable • Much public money has been spent in the area, but this has not changed such a trend Proposals
• Make the area of tratturo an open-air museum Installations by land art along the Pescasseroli-Candela track may contribute to focus on the most significant places; such installations may be inspired by the themes of farming and the rural world and made with eco-sustainable materials. The project of SAC (Environment and Cultural Systems) “Monti Dauni e Lucera” is currently working on such an idea)
• The tratturo has to be clearly identified in order to enhance the community ability to recognize it. Appropriate signs could increase its fruition (ref. the signs on the paths for the formation of the cadastre of the Apulia Network Trekking; the signage conventional of the CAI (Italian Alpine Club); the use of “cippi” – ancient stones boundary)
• Promotional events could contribute to focus on the protection and valorization issues; the “tratturo
day” could become an interregional organized event involving the associations of trekkers, of knights,
of bikers but also the schools at all levels • Educational programs, also in schools, should be based on active citizenship and on the ability of
community to maintain the territory
• The “cippi” – ancient stones boundary- are signals of the tratturo
• We need to "grow" the riders, cyclists and walkers.
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
71
With what resources or tools?
b. Critical issue - Vi è una limitata fruibilità del tratturo Physical accessibility
• Not all the tratturo is practicable
• The area of tratturo is not always visible and physically perceived • Along the tratturo the morphological features are very different • The farmers, during plowing operations, divert the waters on tratturo making it not usable; in some
cases, occupying it with their crops.
Proposals
• Some interventions are necessary for the physical protection of the territory, including an appropriate
system management and maintenance; these are:
o securing of pedestrian and bicycle paths and of bridleways
o restoration of trails and/or runs on tracks that no longer exist
o projects of greenways and cycle routes that constitute the base of an integrated network of soft
mobility (ref. regional law 21/2003 "Norms on activities and excursions networks of Puglia " and
Regulation n.23/2007 “Regulation for the implementation of the Apulian excursions networks”)
o recovering of cultural heritage and of the sparse buildings
• The local nature and culture must be promoted by trained guides (youth cooperatives, network
businesses, educational farms)
• Everyone should have the opportunity to walk along the tratturo, perhaps using new technologies (eg
realizing applications for virtual visits and assistance with navigation tablet). The virtual recognizability
should be aimed at increasing the viability physical
• The farmers "concessions" must be sustainable and must be controlled to achieve the planned goals.
E.g.: the sod seeding could help to avoid the hydro-geological instability; in fact, during the plowing
actions, the drains (channels) of the surface are closed. It should only decide the better type of incentive
in order to change the practice.
• The slow mobility has to be organized: the tratturos are natural equestrian road and they can become
cycling routes, hiking routes and for people with disabilities. The receptivity should be organized in the
farms and taverns, which are currently uninhabited but all surveyed, to become a path, the historical
tratturo requires places of exchanges (eg. The park of Mezzane) and facilities for all kind of users.
Walkers need a special signage, safety, receptivity (water for wash, minimal accommodation) a
stopping every 30 miles (also every 10), the accessibility to the near villages, the “certification of
walker”. Bikers need an inventory of existing little fountains, small oasis with trees, a stopping every
10-15 miles, stopping areas.
• The critical and the potential issues of tratturo, proposed as a path, must be shown going through the
tratturo; only in such a way cycling routes and hiking routes could be organized The association
"Cicloamici" of Foggia proposes to follow the track of the tratturo trying to highlight what may be the
problems and the potential of the path. Such an assessment would be finalized to the organization of
cycle paths but, more importantly, to identify the type of services needed. Even for the bike stops and
services are needed. A few miles from the territory of Rocchetta, the tratturo could be to connected
with the European cycle route network.
• Actions are needed to ensure both the cleaning of micro landfills that now exist along the path, and
safety
• Establish the role of "guardian/keeper of the tratturo." Would be sufficient to ensure 1 keeper for every
30 km of track. The caretaker could ensure cleanliness and control.
• The tratturo must have the access gates to the park; if one, it could be in the middle of the track
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
LANDSCAPE -
a. Critical issue – There are some activities that have a negative impacts on the environment and landscape
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
72
• The path along the tratturo is fragmented
• Not always the political and administrative choices have also been oriented to the safeguard of the
tratturo; many of the political and administrative choices are irreversibly transforming the landscape.
The existing wind farms, for example, are now difficult to displace and there are still political initiatives
that insist in such projects.
• Farmers have often occupied the central part of the tratturo, have left the pasture and have chosen crops
(or monocultures) that are not compatible with measures to protect the tratturo. There are not incentives
and opportunities for change such agricultural practices.
• The farmers practice monoculture too much
• The area of the tratturo is, in large part, occupied by paved roads (mainly road managed by the
Provincia di Foggia)
• The areas of the tratturo that are occupied by urban areas are irretrievably lost
• Landfills are everywhere; the abandonment of waste is an issue of sensitivity and culture; adults and
children should be behaved.
• there is no supervisory
• The process of fragmentation and trivialization of the landscape has caused a contraction and dwindling
of habitats
Proposals
• The maintenance of tratturo and its areas pertaining must be organized to ensure the physical security
of the tratturo. At the same time, the sensitivity to the issues of recovery and enhancement must grow.
In fact, recent maintenance actions have not produced the desired effect because they had not involved
the local community and farmers. The safety and maintenance may be a consequence of the recognition
of tratturo resource.
• Shares of landscape protection and of maintenance of the areas of the tratturo, could include:
o Native plants along the border of tratturo and actions of naturalization (see funding of RDP); buffer
strips, tree lines, hedgerows and dry stone walls along the bands of tratturo (because of their
recognized function of terrestrial ecological corridors);
o Tree-lined avenues of access to the cities;
o Wildflower (in peri-urban areas and / or fringe road) - aesthetic and landscape enhancement and
environmental restoration at low energy input of anthropic environments through the
characterization and use of wildflowers originated by species and ecotypes.
• Interventions of recovery / mitigation can reduce the visual impact of industrial areas (production areas
along the SS 89 and SS 16).
• In order to structure an integrated tourist offer (an offer with also certified quality), local guides must
be trained and guided tours should be organized on the territory.
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
b. Critical issue – Instability of soil
Proposals
• Engineering projects to counteract natural hydro-geomorphological hazards
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
PROPERTY MANAGEMENT
The royal tratturo is 110 meters wide; two-thirds side (the famous 60 steps from Naples) are given in
concession from Apulia region to farms and about 1/3 is still state-owned. This is a complex system to
manage.
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
73
a. Critical issue – Land instability
• Successful actions have to deal with the complexity of the different administrative use and ownership
• Every action needs to involve the dealers, the state and all stakeholders.
• In addition to agricultural soils there is also an urbanized part and a part that still preserves its
naturalness (remnant of the "river of grass")
• The stakeholders are many
Proposals
• Multi-functionality of the agricultural entrepreneur. The opportunities offered by regional park,
PSR, European funds and by the NOP must be exploited: the projects must be integrated across multiple
lines of financing (mainly PON and in agreement with the neighboring Regions)
• In concession areas, current agricultural practices (e.g. plowing, crop basis) must be oriented
towards the protection and preservation of the landscape (eg through the provision of incentives and
the concession of the areas of the tratturo). At the end of the "avenue armentizio", which now appears to
be largely illegally occupied by frontists resulting in compromised of continuity and readability of the
tratturo, the chaotic turf should be restored. The granting of the concession to farmers could be
conditioned with the commitment to act in order to safeguard the legibility of tratturo (e.g. through
plants and, in the case of use of arable land, respecting the direction of plowing parallel to the
longitudinal axis of the tratturo). Such a condition would be compensated, for example, with the
possibility of access to the benefits of the RDP, extended not only to the owners of the funds, but also to
those having non-ownership title to lead the funds, thus including tenants and licensees.
• Markets of close proximity
To move forward …
What are the possible interventions?
What are the subjects that can achieve them?
With what resources or tools?
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
74
Annex 6 – Signed document for the RDP and ERDF negotiation table
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
75
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
76
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
77
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
78
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
79
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
80
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
81
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
82
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
83
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
84
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
85
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
86
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
87
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
88
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
89
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
90
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
91
Annex 7 - “Conferenza dei servizi” for the signature of the POI
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
92
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
93
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
94
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
95
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
96
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
97
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
98
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
99
Annex 8 - Contribution edited by “FIAB Foggia Cicloamici” and “Associazione Culturale Lanterne” (cover)
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
100
Annex 5 – Monitoring the state of tratturo edited by “FIAB Foggia Cicloamici” (executive summary)
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
101
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
102
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
103
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
104
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
105
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
106
Annex 10 - First agenda of the “National Day of Tratturo” edited by “CAI Foggia
RECUPERO E VALORIZZAZIONE DEL TRATTURO PESCASSEROLI - CANDELA
AZIONE: 1) Indire la "Giornata nazionale dei Tratturi" - Con un sistema comunicativo che inizi dalle Regioni coinvolte e veda i Comuni lungo il Pescasseroli - Candela in prima fila a pubblicizzare l'evento con l'interessamento delle Associazioni e delle scuole che svolgano un "tema/ricerca" relativo alla cultura-storia che i tratturi hanno lasciato alle nostre generazioni; 2) Nello stesso momento, in tutti gli eventi organizzati, si dà il via al percorso al suono di una "campana" simbolicamente indicata in quella di Agnone; 3) Ogni Comune attraversato accoglie i camminatori con un "semplicissimo e pastorale rinfresco" in un festoso attraversamento del centro abitato; 4) Arrivo al termine di ogni percorso con semplice manifestazione a sfondo pastorale.
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx Ovviamente ogni Amministrazione è libera di organizzare l'evento che caratterizzi meglio la propria realtà sociale/tratturale.
A
T
T
O
R I
C.A.I. Club Alpino Italiano
Gruppi Regionali di: Abruzzo Molise
Campania Puglia
Sezioni coinvolte: Pescasseroli
Castel di Sangro Isernia
Campobasso Benevento
Avellino Foggia
Associazioni sportive di Cavalieri e Bikers
Associazioni coinvolte: Proloco, ………………….
A M M I N I S T R A Z I O N I P U B B L I C H E
Regione Provincia Comune
ABRUZZO
L'Aquila
Pescasseroli Opi
Civitella Alfedena Villetta Barrea
Barrea Alfedena
Scontrone Castel di Sangro
MOLISE
Isernia
Rionero Sannitico Forlì del Sannio
Isernia Pettoranello del Molise
Castel Petroso Santa Maria del Molise Cantalupo del Sannio
Campobasso
San Massimo Bojano
San Polo Matese Campochiaro Guardiaregia
Sepino
CAMPANIA
Benevento
Morcone Santa Croce del Sannio
Circello Reino
Pesco Sannita San Marco dei Cavoti San Giorgio la Molara
Buonalbergo
Avellino
Casalbore Montecalvo Irpino
Ariano Irpino Villanova del Battista
Zungoli
PUGLIA Foggia
Monteleone di Puglia Anzano di Puglia
Sant'Agata di Puglia Rocchetta Sant'Antonio
Candela
Criticità da affrontare Non vi sono particolari criticità al momento: tutte le Sezioni CAI coinvolte dovranno individuare, con la collaborazione degli uffici comunali competenti, il/i tratto/i ragionevolmente lungo/hi (10 – 15 km) già percorribile/i
Possibili soluzioni
Opportunità di finanziamento delle nuove proposte
Possibili effetti positivi o negativi
definizioni delle priorità
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
107
Annex 11 - Invitation letter to public tender (with technical annexes for APP implementation)
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
108
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
109
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
110
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
111
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
112
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
113
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
114
Output 4.7 Integrated Strategic Territorial/Urban Agenda of the Pescasseroli-Candela Tratturo area
ERDF PP6 - Province of Foggia(IT)
115
Annex 12 - Letter for starting competitive public tender on “60 passi nella natura“ project (technical annexes omissis)