7
UWA FM Planning and Design Section Project Management & Design Guidelines Manual Edition September 2003 Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework APPENDIX TO SECTION D. D9 REFRIGERATION PIPEWORK CONTENTS 1.0 PIPEWORK 2.0 SUPPORTS 2.1 General 2.2 Support Material 2.3 Fixing to Masonry 2.4 Support Spacing 2.5 Hanging Rods 2.6 Pipe Support Attachments 2.7 Straps PVC Drains 2.8 Straps – Copper Piping 2.9 Saddle Type Supports 2.10 Copper Packing 3.0 BUILDING PENETRATIONS 3.1 Set out 3.2 Sleeves 3.3 Fire Barriers 3.4 Roof Penetrations 3.5 Underground Installations 3.5.1 Excavation and backfilling 3.5.2 Bedding 3.5.3 Minimum Cover Over Pipe 3.5.4 Pipework under slabs 4.0 PIPEWORK INSULATION 4.1 Pipework to be insulated 4.2 Insulation Material 4.3 Flexible Insulation, Application 4.4 Aluminium Cladding 4.5 Painting of Insulation is required: - 5.0 REFRIGERATION SYSTEMS TESTING 5.1 General 5.2 Pressure Tests 5.3 Evacuation Tests 5.4 Charging

FM Handbook - D9 Refrigeration Pipework

Embed Size (px)

Citation preview

Page 1: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 1/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

APPENDIX TO SECTION D.

D9 REFRIGERATION PIPEWORK

CONTENTS

1.0  PIPEWORK

2.0  SUPPORTS2.1 General2.2 Support Material2.3 Fixing to Masonry2.4 Support Spacing2.5 Hanging Rods2.6 Pipe Support Attachments2.7 Straps PVC Drains2.8 Straps – Copper Piping2.9 Saddle Type Supports2.10 Copper Packing

3.0  BUILDING PENETRATIONS3.1 Set out3.2 Sleeves3.3 Fire Barriers3.4 Roof Penetrations3.5 Underground Installations3.5.1 Excavation and backfilling3.5.2 Bedding

3.5.3 Minimum Cover Over Pipe3.5.4 Pipework under slabs

4.0  PIPEWORK INSULATION4.1 Pipework to be insulated4.2 Insulation Material4.3 Flexible Insulation, Application4.4 Aluminium Cladding4.5 Painting of Insulation is required: -

5.0 REFRIGERATION SYSTEMS TESTING 5.1 General

5.2 Pressure Tests5.3 Evacuation Tests5.4 Charging

Page 2: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 2/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

APPENDIX TO SECTION D.

D9 REFRIGERATION PIPEWORK

1.0  PIPEWORK 

To AS 1571 Refrigeration Grade, copper, clean, dehydrated andhermetically sealed. Supplied in straight lengths and in the 'Hard-Drawn'temper unless annealed tubes (supplied in straight lengths or coiled) arenecessary to meet a specific purpose, installed in accordance withAS.1677.

Brass fittings with flare, internal flare, capillary brazing or threaded ends,or combinations to ANSI B70.1 or equivalent. Flare type fittings to ASD26.

Flare nuts:- of frost proof design when used in refrigerant suction piping.

- of the long pattern type wherever prone to vibration.

Copper flare gaskets and flare seal bonnets: To ANSI B70.1.

2.0 SUPPORTS 

2.1  General:Provide supports including hangers, saddles, bolted clips and the like,sufficient to secure the pipework to adjacent surfaces, to restrain theinternal forces of pressure piping, and to support it to joints, at changesof direction, and at intervals suitable to the size and type of pipe, and asnecessary to prevent sagging of pipework. Make provision for

adjustment of gradient as required.

2.2  Support Material:Use galvanised or non-ferrous metals, with bonded PVC or fibreglasssleeves to separate dissimilar metals. Provide fixings of compatiblematerial. Remove all sharp edges and provide plastic stops at unistrutends.

2.3  Fixing to Masonry:Use galvanised steel or non-ferrous metal bolts or screws into expandingmasonry anchors. Do not use explosive powered fixings.

2.4  Support Spacing:Space pipe supports, hangers, anchors as shown on drawings, adjacentto all valves, not more than 600 mm from changes in direction or at thedistances shown in the table:

`PIPE SUPPORT SPACINGSIZE (mm)

Horizontal Vertical(m) (m)

10 1.5 215 2 2.520 2 2.5

25 2 332 2.5 3

Page 3: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 3/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

2.5  Hanger Rods:Provide hanger rods for pipe supports as listed in the table below:-

PIPE SIZE (mm) HANGER DIAMETER (mm)

10 615 620 625 1032 10

2.6  Pipe Support Attachments:Provide pipe support attachments for hanger type supports of thefollowing type:-

- Uninsulated pipe: Clamp clips direct to uninsulated pipes.

- Insulated pipe: Clamp mild steel clips over metal sheathed highdensity cork or hardwood ferrules of length not less than twice theclip width and of thickness as specified for insulation.Ensure continuity of vapour barrier over the ferrule and insulation.

2.7  Straps PVC Drains:Provide mild steel straps or clips minimum 25 wide x 1 thick for securingpiping:-

2.8  Straps - Copper Piping:Provide straps or clips as above with nylon or other suitable inserts:-- Copper material 25 mm x 1.6 mm thick.

2.9 Saddle Type Supports Fix saddle to building member or supporting structure at each side of thepipe. Material of saddles as for STRAPS.

2.10  Copper Packing:Provide a 1.6 mm thick soft copper packing where the pipe may besubject to chafing. Packing dimensions to suit the saddle. Securely fixpacking between the pipe and the building member or supportingstructure. Fit a 1.6 mm thick soft copper liner between the pipe andsaddle.

3.0 BUILDING PENETRATIONS

3.1  Set out core holes and sleeves in floors, walls, beams and columns.Obtain approval of set out prior to placing of concrete.

3.2  Sleeves:Sleeves are to:- be provided at all piping penetrations of floors, walls, roof and

equipment casings.- be metal in fire rated elements- have 12mm clearance all round pipe and insulation- have the clearance packed with self extinguishing grade joint

sealer.

Page 4: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 4/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

3.3  Fire Barriers: Provide the following where pipelines penetrate firebarriers.- Insulated pipes: Insulate the pipes with high temperature fibreglass

or ceramic fibre insulation within the thickness of the barrier and fora minimum distance of 50 mm on either side. Size sleeves to suit

the specified thickness of pipe insulation and extend sleeves 50mm on either side of the barrier. Insulate pipes with an approvedhigh temperature sectional pipe insulation for a distance of 250 mmbeyond the sleeves on both sides of the barrier. Where the pipeinsulation is required to be sheathed, overlap the sheathing overthe sleeve by not less than 32 mm and firmly strap to the sleeve.

- Uninsulated pipes: Extend the sleeve 50 mm on either side of thebarrier and provide a 13 mm radial annular clearance around thepipe. Pack high temperature fibreglass or ceramic fibre insulationinto the annular space and tamp into place.

3.4  Roof Penetrations:Flash pipes which pass through the roof with 19.5 kg/m

2sheet lead, or

other material (as required by zincanneal roofs) to approval, orproprietary Dektite fittings installed to manufacturer's recommendations.

3.5  Underground Installations:

3.5.1 Excavation and backfilling:Provide open trench excavation and backfilling.

3.5.2 Bedding:Bedding on trench bottom: Lay pipes without underlay provided thetrench:

- is free from hard objects such as stones, sharp projecting rocks ortree roots.

- bottom is trimmed to provide continuous, uniform and adequatesupport to the pipe. Include chases where necessary to preventsockets, flanges or the like from bearing on the trench bottom.

Bedding on underlay: Bed pipes if the excavation is excessive or isunstable ground or rock on a continuous cushion of underlay material of75 mm minimum thickness.

Underlay material is to be:- to AS 2032, clause 4.222.1.2 sand or selected excavated material

free from hard sharp objects or lumps.

Form chases where necessary to prevent sockets, flanges or the likefrom bearing on the trench bottom or the bedding. Fill and compact thechases after the laying and testing of the pipes.

Fill to 150 mm above the top of the pipes with underlay materialcompacted in layers of not more than 150 mm.

3.5.3 Minimum cover over pipe:Apply the following unless overridden by regulatory authorityrequirements.

Pipes not subject to vehicular loading: 450 mm

Page 5: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 5/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

Pipes subject to vehicular loading:- not in roadways 600 mm- under sealed roadways 600 mm- under unsealed roadways 750 mm

Pipes in embankments or subject to- construction equipment loading:750 mm

3.5.4 Pipework under slabs:Protect copper pipework laid in the ground beneath a concrete floor slabby:- encasing in continuous UPVC pipework sleeves or- encasing in PVC coated tube sealed to prevent ingress of moisture

or- support on compacted underlay material 150 mm thick, and provide

compacted overlay and side support of fine crushed rock, gradingup to a maximum size of 14 mm, to not less than 150 mm above

the top of the pipe.

4.0  PIPEWORK INSULATION

4.1  Pipework to be InsulatedGenerally any pipework where the absence of insulation would increaseenergy requirements during normal system operation and exposedpipework where the surface temperature is liable to be below ambient airdewpoint. e.g.

• Refrigerant Suction Lines not located in coolrooms or freezers

• Refrigerant Liquid Lines strapped to suction lines for sub-cooling

4.2  Insulation Material The preferred pipework insulating material is:

Preformed closed cell synthetic elastomer with smooth vapour barrier outsurface;

to AS 4426 Table 2.1 - Nitrile rubber (closed cell), as manufactured byAeroflex, Armaflex or approved equivalent:

applied with adhesive and finish as recommended by the insulationmaterial manufacturer, Aeroseal, Aerocoat, Armstrong 520, WB Armaflexor approved equivalent.

4.3  Flexible Insulation, Application 

- Apply to straight lengths, formed sets and bends prior to erectionwithout longitudinal joints

- neatly cut and form around fittings

- seal at all joints with adhesive and finish as recommended by theinsulation material manufacturer, Aeroseal, Aerocoat, Armstrong520, WB Armaflex or approved equivalents,

to provide effective vapour seal and UV protection.

Insulate with preformed tubular sections, selected to accurately match

the pipe O.D. for a tight fit without longitudinal joints.

Page 6: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 6/7

Page 7: FM Handbook - D9 Refrigeration Pipework

8/3/2019 FM Handbook - D9 Refrigeration Pipework

http://slidepdf.com/reader/full/fm-handbook-d9-refrigeration-pipework 7/7

UWA FM Planning and Design Section

Project Management & Design Guidelines Manual Edition September 2003

Section D: Mechanical Services Guidelines - Appendix D9 - Refrigeration Pipework 

Nitrogen manifold gauges will not be accepted for checking minorpressure variations.

Pressure test shall be repeated after leaks are corrected.

5.3  Evacuation tests:

The refrigeration system (including the compressor) shall be dehydrated,by means of a high vacuum pump to a pressure of 300 microns.

Line connections from the pump to the system shall be as short aspossible and of as large a diameter as is practicable eg 10mm.

The pump and compressor shall be isolated and the system swept withdry nitrogen to a pressure of 350 kPa.

Evacuate the system (not including the compressor) to 100 microns andhold for a minimum of two hours with the pump off. Break the vacuumwith dry nitrogen gas.

Before further evacuation is commenced the compressor oil shall beadded, line filters fitted, all valves open and controls connected.

The refrigeration system shall be again dehydrated to 100 microns andheld in this condition for one hour with the vacuum pump off. Pressureshould not rise above 250 microns during this period and shouldcorrespond to standard system pressure rise curves.

If the system fails to hold these conditions below 250 microns, the pumpshall be brought back on line and the system further dehydrated until therequirements are met.

Purging nitrogen gas from the system shall be made from a point in the

system as far away from the nitrogen inlet connections as possible. Thiswill tend to sweep moisture and any particles out of the system.

5.4  Charging. On completion of the tests, the vacuum shall be broken by the addition ofthe refrigerant to pressurise the system.

The system should then be started and refrigerant added until the sightglass is clear of bubbles. Beware of overcharging the system

The system shall then be operated at full load for fifteen minutes, orlonger if necessary whilst the operating pressures are established.