Upload
duongkiet
View
212
Download
0
Embed Size (px)
Citation preview
2
SW 10th Street ConnectorProject Development and Environment Study
Kick-Off Meeting, November 15, 2017
FM #439891-1-22-02, ETDM #14291
3
SW 10th Street Connector PD&E Kick-Off Meeting§ FM 439891-1,
SW 10th Street between Florida’sTurnpike/Sawgrass Expresswayto I-95
§ Adjacentstudies– I-95 from SW
10th to HillsboroBoulevardPD&E Study
– SawgrassExpresswayPD&E Study
4
§ Looking Back– SW 10th Street History– MPO Consensus Study & Recommendations
§ What’s been done since the MPOConsensus Study?§ The PD&E Study Process§ Moving Forward
PRESENTATION OUTLINE
5
LOOKING BACK…
» Community concerns
» Minimal political support
1970s 1986 1993 2008 2015
PlanningBegins
SawgrassConstructed
MPO VotesAgainst Project
FDOT CompletesFeasibility Study
MPO Declines toPrioritize Project
MPO FormsConsensus-Building
Team (COAT)
FDOT CompletesPD&E Study for
Missing Link
» No consensus
» Livability issues
6
§ Community Oversight Advisory Team– 15 members from 4 cities– 2 members from the county– Technical input
§ Outreach to the Community– Consensus on:
VisionRecommendations
§ Moving Forward– COAT to remain engaged during
PD&E Study
BROWARD MPO FORMS THE “COAT”
7
COAT Outcome
§ Recommendation to move forwardwith the project§ Provided recommendations related to:
– Creative engineering– Access improvements– Traffic operations and safety– Community aesthetics– Environmental concerns– Construction
8
1970s 1986 1993 2008 2015 2017
PlanningBegins
SawgrassConstructed
MPO VotesAgainst Project
FDOT CompletesFeasibility Study
MPO Declines toPrioritize Project
MPO FormsConsensus-Building
Team (COAT)
FDOT CompletesPD&E Study for
Missing Link
MPOPrioritizes
Project!
FDOTProgramsNew PD&EStudies!
COAT OUTCOME
9
So What’s Been Done Since the MPO Consensus Study?
§ Pre-work completed– Field survey– Traffic data collection– Traffic forecasting
STARTING POINT FOR THE PD&E STUDY!
§ PD&E Study is underway
10
Project Development Process Flowchart
Construction
§ Develop alternatives§ Impact evaluations§ Public outreach§ Preferred alternative
Planning
Final Design
Right-of-wayAcquisition
§ Develop final details§ Final right-of-way§ Public outreach
§ Acquire right-of-way(if needed)
§ Public outreach
Project Development& Environment Study
11
So What Is a PD&E Study?
§ Process to satisfy National Environmental Policy Act (NEPA)requirements for transportation projects
§ Social, environmental and engineering evaluations§ Many details developed to conceptual engineering level§ Identify a Preferred Alternative§ Public and agency outreach
12
The Process
§ Data Collection
§ Engineering Analysis
§ Environmental Evaluations
§ Public Involvement
Project Initiation
Public Kick-off Meeting:Introduce the Study to the Public & Receive Input
Environmental & Engineering Analysis
Alternatives Public Workshop: PresentAlternatives to the Public & Receive Input
Draft Environmental & Engineering Documents
Public Hearing: PresentPreferred Alternative to the Public & Receive Input
Final Environmental & Engineering Documents
Location and Design Concept Acceptance8
7
6
5
4
3
2
1
COM
MU
NITY
OU
TREACH
13
Purpose and Need
§ Address limited-access needs
§ Improve linkages of SIS facilities
§ Address local SW 10th Street needs
§ Address safety and operational issues
§ Enhance emergency response andevacuation
§ Enhance social demand, intermodaland economic development
14
Regional Connectivity
§ Close the network gap toimprove mobility
Missing Link
Regional Express LanesNetwork Gap
Existing/Future Regional ExpressLanes Network
SW 10th Street
16
Traffic Back Ups
Typical PM PeakOperatingConditions
EB, AM peak,queue spillbackonto Sawgrass
WB, PM peak,queue spillback
onto I-95
Typical AM PeakOperatingConditions
19
Alternatives Analysis
§ Develop/refine with input from thepublic, local governments andagencies§ Meet purpose and need§ Avoid or minimize impacts to the
community and environment§ Matrix for comparison§ No Action Alternative
20
Alternatives Analysis
§ Two facilities to be evaluated– Express Lanes
• Entrance / exit ramp locations betweenPowerline Road and Military Trail
§ Extent of the below-grade section beingevaluated
– Local roadway• Lower-speed• Bicycle lanes• Sidewalks
21
One Idea…
§ Center Express Lanes§ Local SW 10th Street on each side§ Extent of below-grade section being evaluated
22
Another idea…§ North-side Express Lanes§ Local SW 10th Street on south side§ Extent of below-grade section being evaluated
23
Environmental Analysis
§ Natural Environment– Threatened and endangered species– Wetlands habitat
§ Physical Environment– Air quality, contamination– Noise
§ Cultural and Socio-Cultural Environment– Historic and archaeologic– Parks and recreation– Multimodal accommodations
24
Noise Analysis§ Key Concern
– Future noise levels– Adjacent communities may
require noise abatement
§ Noise-Sensitive Sites– Seven residential communities– Three recreational– One commercial
§ Detailed Noise Analysis– Identify noise-sensitive sites– Measure noise– Noise modeling to determine if/
where and what type of abatement isneeded
= Residential
= Commercial
25
Future Landscape Projects
§ SW 10th Street from Powerline Road to Westof Military Trail– After roadway construction– Budget: $3M
§ I-95 from South of SW 10th Street to theBroward / Palm Beach County Line– After roadway construction– Budget: $1M
26
Schedule
Kick-Off Meeting
Alternatives Public Workshop
Public Hearing
Location and Design Concept Acceptance (LDCA)
27
Moving Forward…
§ PD&E– Alternatives development considering COAT
recommendations– Public Outreach throughout process– Alternatives Public Workshop: March 2018– Public Hearing: December 2018– LDCA: February 2019
§ Design - Spring 2019
§ Construction - Currently funded in 2025