Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
KINGDOM OF CAMBODIA
Nation Religion King
Ministry of Water Resources
and Meteorology Asian Development Bank
Flood Damage Emergency Reconstruction Project – Additional Financing
Output 3: Irrigation Rehabilitation and Flood Management
ADB Loan Number : 3125-CAM(SF)
GoA (DFAT) Grant Number: 0285-CAM(EF)
MONTHLY REPORT Version 1
September 2014
In association with
KEY CONSULTANTS (CAMBODIA)
Egis Eau Document quality information
Page 2 Output 3: Irrigation Rehabilitation and Flood Management
Document quality information
General information
Author(s) Leighton Williams, Egis Eau Team Leader; Cheam Sar, Deputy TL (KCC)
Project name Output 3: Irrigation Rehabilitation and Flood Management
Document name MONTHLY REPORT
Date
Reference FDERP-AF MR03-0914
Addressee(s)
Sent to:
Name Organisation Sent on (date):
Mr. Chann Sinath Project Director, PIU 17 Sep 14
Copy to:
Name Organisation Sent on (date):
3 PIU 17 Sep 14
2 PCMU 17 Sep 14
1 ADB 17 Sep 14
History of modifications
Version Date Written by Verified by:
Draft Cheam Sar, Deputy TL
Version 1 Leighton Williams, TL Thierry Delobel, Project Director, Egis
Egis Eau Contents
Page 3 Output 3: Irrigation Rehabilitation and Flood Management
Contents
Chapter 1 - Summary................................................................................... 7
1. Introduction .......................................................................................... 7 2. FDERP-AF ............................................................................................. 9
2.1. Flood Damage 2013....................................................................................... 9 2.2. Conception of Project................................................................................... 10 2.3. Administrative arrangements ....................................................................... 10
3. Key Activities and Issues this Month.................................................10 3.1. Consultant Mobilisation................................................................................ 10 3.2. Implementation Plan .................................................................................... 11 3.3. Stage 2 Works Construction ........................................................................ 11 3.4. Hydromet and Automatic Weather Stations................................................. 11 3.5. Stage 3 Implementation ............................................................................... 11 3.6. Reports......................................................................................................... 11
Chapter 2 - Consultants Activities............................................................ 13
1. Mobilisation .........................................................................................13 2. Field Visits ...........................................................................................14 3. Persons Met and Formal Meetings Attended ....................................15 4. Stage 2 Activities.................................................................................15 5. Stage 3 Activities.................................................................................15 6. Assistance with Project Management................................................15
6.1. Assistance with FDERP-AF ......................................................................... 15 6.2. Procurement of Civil Works ......................................................................... 16 6.3. Procurement of Goods and Services ........................................................... 16
Chapter 3 - Implementation Status........................................................... 17
1. Stage 2 Progress .................................................................................17 1.1. FDERP-AF-MOWRAM-CW02 ..................................................................... 19 1.2. FDERP-AF-MOWRAM-CW03A ................................................................... 20 1.3. FDERP-AF-MOWRAM-CW04 ..................................................................... 20 1.4. FDERP-AF-MOWRAM-CW05 ..................................................................... 22 1.5. FDERP-AF-MOWRAM-CW03B ................................................................... 23 1.6. Contractor’s Report/ Quality Control ............................................................ 23 1.7. Construction Progress Photos (Stage 2) ..................................................... 26
2. Hydromet and AWS Progress.............................................................33 3. Stage 3 Progress .................................................................................34
3.1. Implementation Plan .................................................................................... 35 3.2. Subproject Profiles ....................................................................................... 36 3.3. Engineering Design...................................................................................... 37 3.4. Procurement of Civil Works ......................................................................... 38 3.5. Socio-economics.......................................................................................... 38 3.6. FWUC Development .................................................................................... 38
4. Safeguards...........................................................................................38
Chapter 4 - Project Management Issues .................................................. 39
1. Procurement ........................................................................................39 1.1. Procurement of Civil Works ......................................................................... 39 1.2. Procurement of Hydromet and AWS............................................................ 39
2. Consultants Services ..........................................................................40
Egis Eau List of appendices
Page 4 Output 3: Irrigation Rehabilitation and Flood Management
3. Issues...................................................................................................40 3.1. Soil Investigation Study................................................................................ 40 3.2. Transport...................................................................................................... 40 3.3. Office Furniture ............................................................................................ 40 3.4. Services ....................................................................................................... 41 3.5. Printing, scanning and copying. ................................................................... 41 3.6. Internet ......................................................................................................... 41
List of appendices
Appendix 1: Subprojects Location Map...................................................................42
Appendix 2: Summary of Consultant Staff Mobilisation...........................................43
Appendix 3: Reports Submitted to Date ..................................................................44
Appendix 4: Person Met and Formal Meetings Attended ........................................45
Appendix 5: Consultancy Services Staffing Schedule .............................................47
Appendix 6: Procurement Dates for Civil Works .....................................................48
Appendix 7: Procurement Dates for Hydromet and AWS........................................49
Appendix 8: Procurement Plan ...............................................................................50
Appendix 9: Implementation Plan ...........................................................................52
List of tables
Table 1: Output 3 features ....................................................................................... 8
Table 2: Mobilisation dates of DDIS Consultant staff ..............................................13
Table 3: Field visits during month of September 2014 ............................................14
Table 4: Summary of Implementation Status of Stage 2 Construction.....................18
Table 5: Stage 2 Quality control test results............................................................23
Table 6: Proposed Hydromet Sites .........................................................................34
Table 7: Proposed AWS Sites.................................................................................34
Table 8: List of subproject profiles. .........................................................................37
Table 9: Payment Certificates Stage 2 Contracts....................................................39
List of figures
Figure 1: Construction Progress for Srae Loor subproject Stage 2 .........................19
Figure 2: Construction Progress for Chork Reservoir subproject Stage 2 ...............20
Figure 3: Construction Progress for Tumnub O Ang Krang sub-project Stage 2 .....21
Figure 4: Construction Progress for Tumnub Rolous sub-project Stage 2...............22
Egis Eau Acronyms and Abbreviations
Page 5 Output 3: Irrigation Rehabilitation and Flood Management
Acronyms and Abbreviations
ADB Asian Development Bank
AusAid Australian Agency for International Development
AWS Automatic Weather Stations
CARM Cambodian Resident Mission (of ADB)
DC Direct Contracting
DMF Design and Monitoring Framework
DS Dry Season
EA Executing Agency
FDERP-AF Flood Damage Emergency Reconstruction Project- Additional Financing
FGIA First Generation Imprest Account
FWUC Farmer Water User Community
GoA (DFAT) Government of Australia (Department of Foreign Affairs and Trade)
IA Implementing Agency
IEE Initial Environmental Examination
LFIS Loan Financial Information Services (ADB)
MEF Ministry of Economy and Finance
MLMUPC Ministry of Land Mapping Urban Planning and Construction
MOU Memorandum of Understanding
MOWRAM Ministry of Water Resources and Meteorology
MPWT Ministry of Public Works and Transport
MRD Ministry of Rural Development
NCB National Competitive Bidding
NOL No Objection Letter
NPD National Project Director
NWISP Northwest Irrigation Sector Project
PAM Project Administration Manual
PCMU Project Coordination and Monitoring Unit (MEF)
PDLMUPC Provincial Dep. of Land Mapping Urban Planning and Construction
PDWRAM Provincial Department of Water Resources and Meteorology
PIMD Participatory Irrigation Management and Development
Egis Eau Acronyms and Abbreviations
Page 6 Output 3: Irrigation Rehabilitation and Flood Management
PIU Project Implementation Unit
PRC Procurement Review Committee
PP Procurement Plan
RFP Request for Proposal
RGC Royal Government of Cambodia
ROW Right-of-way
RRP Report and Recommendation of the President (to the board of
directors)
SAH Severely Affected Households
SGIA Second Generation Impress Account
SSS Single Source Selection
TA Technical Assistance
TOR Terms of Reference
Egis Eau Monthly Report – September 2014
Page 7 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Chapter 1 - Summary
1. Introduction
The Flood Damage Emergency Reconstruction Project - Additional Financing
(FDERP-AF) consists of emergency reconstruction of infrastructure damaged during
the extreme flood event of 2013, as defined in the Asian Development Bank’s (ADB’s)
Report and Recommendation of the President (RRP) comprising four outputs, three of
which are for physical implementation by sector:
� Output 1: National and Provincial Roads implemented by Ministry of Public
Works and Transport (MPWT)
� Output 2: Rural Roads implemented by Ministry of Rural Development (MRD)
� Output 3: Irrigation Rehabilitation and Flood Management implemented by
Ministry of Water Resources and Meteorology (MOWRAM)
� Output 4: Project Management and Facilitation- through Ministry of Economy
and Finance (MEF) as the Executing Agency (EA).
Furthermore the emergency repairs were categorised into 3 phases, Stage 1 to 3 as:
� Stage 1: Immediate repairs to re-establish use of the infrastructure on a
temporary basis and restore communications.
� Stage 2: Fast track repairs where it was considered necessary to repair the
damage before the next wet season to secure the existing (undamaged) works
� Stage 3: Remaining flood damage restoration to complete the remaining
damage repairs, preferably within the following two to three dry season
construction periods.
This report covers progress on the activities of the Detailed Design and Implementation
Supervision (DDIS) (Technical Assistance (TA)) Consultant (the Consultant) and of
the MOWRAM component of the FDERP-AF for the period 1 to 30 September 2014.
The main features for Output 3 for MOWRAM are shown at Table 1.
The FDERP-AF Project started 30 May 2014 when the ADB Loan No.3125-CAM(SF)
became effective, and according to the original implementation schedule, it is due to be
completed by 31 March 2017, and the loan closing date is 30 September 2017.
The contract agreement for services between the Consultant and MOWRAM was
signed 27 August 2014. However, the Consultant team mobilized staff from 24
February 2014. This was to provide urgent services for Stage 2 for review of designs
and cost estimates, preparation of contractor selection report for direct contract (DC),
bidding document preparation, bid evaluation report, contract preparation for civil
works, prepare report on proposed hydromet works, and bidding document for
hydromet.
Egis Eau Monthly Report – September 2014
Page 8 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Table 1: Output 3 features
OVERALL SUMMARY
Total number of sub-projects selected 11
Total irrigated area WS & DS 68,964.00 ha*
Provinces 6
Damaged infrastructure reconstructed 12 % to date.
STAGE 2
Direct Contracts 6
Contracts value US$ 4,857,815.98
Value of advances/ IPCs disbursed US$ 307,007.86
No of sub-projects 7
No of Provinces 4
Irrigated area 66,194.00 ha†
HYDROMET STRENGTHENING
Hydromet stations 10
Automatic weather stations (AWS) 8
Value of Contracts US$ 500,000 (estimate)
ICB 1
Number of Provinces 7
STAGE 3
Number of subprojects to be designed 11
Number of subproject profiles approved 0
Number of Provinces 6
No of contracts awarded/value 0/US$ 0
NCB 0
ICB 0
Estimated value of total procurement
Irrigated area 68,964.00 ha‡
Subproject locations are shown at Appendix 1.
* The command area is referred to sub-project under reconstruction/ rehabilitation for stage 2 and some
sub-projects are moved to Stage 3. † The command area is referred to sub-project under reconstruction/ rehabilitation for Stage 2 in 2014. ‡ The command area is referred to sub-project under reconstruction/ rehabilitation for Stage 3 in 2015.
Egis Eau Monthly Report – September 2014
Page 9 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
The Asian Development Bank (ADB) issued a no-objection letter (NOL) to Contract
Variation No.3§ for Consultant services for FDERP-AF on 25 August 2014. Details of
staff mobilised, dates and time worked are given in Chapter 2 and at Appendix 2.
According to the Memorandum of Understanding (MOU) signed on 21 February 2014,
before loan effectiveness: the Royal Government of Cambodia (RGC) will advance the
funds required to undertake advance actions and implementation of subprojects to be
financed under retroactive financing (Stage 2).
The Terms of Reference (TOR) included in the ADB’s MOU state that the consultant
services are required to assist MOWRAM in the selection and design (reviewing and
improving) of subproject works, the procurement of construction and equipment
contracts and the management of the civil works contracts, construction supervision,
reporting, performance monitoring, financial management and safeguards compliance
for efficient implementation of subprojects. For the hydromet system, ADB’s advance
actions team will assist PIU to get the works started during Stage 2. Once the
MOWRAM consultant services contract is approved, the Consultant will then provide
ongoing support for the continued design, procurement, supervision of installation and
commissioning of the hydromet system. Consultancy Services are required over about
3 years and estimated to include 31.5 and 186 person-months of international and
national consultants respectively. The site construction supervisors’ input are required
over about 3 years and estimated 178 person-months of national consultants.
The scope of the work anticipates up to eleven subprojects in six provinces:
Battambang, Banteay Meanchey, Oddar Meanchey, Siem Reap, Preah Vihear and
Kampong Thom. The Consultant reports to the head of the Project Implementation
Unit (PIU) of FDERP-AF within MOWRAM, which is the Implementing Agency (IA) for
Output 3.
This report presents the key issues and current progress status as explained below,
and complies with TOR for the Consultant to prepare the monthly progress reports.
2. FDERP-AF
2.1. Flood Damage 2013
During the period September to November 2013, Cambodia and neighbouring
countries suffered floods from the Mekong River and heavy rainfall in river catchments
at similar levels to the floods which affected Cambodia in 2011. The 2013 flooding
triggered RGC/ADB/GoA (DFAT)** emergency aid actions leading to FDERP-AF as well
as a review of damage to recently repaired infrastructure for FDERP and NWISP.
§ The formal signed document for the variation is actually entitled Contract Variation No.AF-1 but the NOL
refers to it as Contract Variation No.3.
** Formerly AusAID
Egis Eau Monthly Report – September 2014
Page 10 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
2.2. Conception of Project
An ADB fact finding mission on the 2013 flood damage undertaken in January 2014
produced a proposal for the Additional Financing to Flood Damage Emergency
Reconstruction Project. The Bank and RGC initiated an emergency approach similar
to the FDERP project to formulate a new project. The final MOU for Joint Mid-term
Review Mission (25 November - 13 December 2013) was signed on 28 January 2014.
The mission met with the line ministries and proposed that the RGC continues to
employ services of the existing consultants. The loan agreement for FDERP-AF, Loan
No.3125-CAM (SF) between RGC and ADB was finally signed 23 April 2014 and the
loan became effective on the 30 May 2014.
2.3. Administrative arrangements
The new project was renamed Flood Damage Emergency Reconstruction Project-
Additional Financing (FDERP-AF) and has impacted on the present FDERP. In
accordance with the MOU the existing consultants for FDERP are to be recruited for
FDERP-AF through Single Source Selection (SSS). Even though the FDERP-AF is in
fact not really an extension of the existing project the strategy is to use the existing
agreement with the service provider. It has a separate and distinct loan agreement and
to some extent different scope although the overall implementation strategy is the
same. Furthermore, the two projects will be implemented in parallel at least until March
2015 for the consulting services. A separate PIU has been set up in MOWRAM to
manage FDERP-AF.
The Consultant received the Request for Proposal (RFP) on the 9 June 2014 for SSS
procedure for this project. The Consultant’s proposal was submitted on 19 June 2014.
The contract variation for FDERP-AF for consultant service agreement between
MOWRAM and Egis Eau International in association with KCC was signed and
approved as of the 27 August 2014.
3. Key Activities and Issues this Month
3.1. Consultant Mobilisation
The Consultant began mobilisation of staff immediately following signature of Contract
Variation FDERP-AF No.AF-1. Table 2 provides staff mobilisation dates as at
30 September 2012. The Deputy Team Leader/Irrigation Design Engineer was already
mobilised under urgent services providing support to the PIU for construction
supervision of Stage 2 works and Contract Engineer #5/Structural Design Engineer
resumed work on 28 August. The Team Leader/Irrigation Engineer travelled on 28
August and worked throughout September but spent two days on the hydrology task.
Other staff were mobilised at various dates during September: Contract Engineer #1,
Contract Engineer #2, Resettlement Specialist, Socio-Agric. Economist, Procurement
(Bid Documents), CD/FWUC Specialist, Environmental Specialist, and Site
Egis Eau Monthly Report – September 2014
Page 11 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Inspectors #1 and #2. The International Irrigation/Dam Design Engineer remobilised
24 September 2014.
3.2. Implementation Plan
The Implementation Plan was prepared during September 2014 and passed to the PIU
for review, see Chapter 3 -3.1.
3.3. Stage 2 Works Construction
During September construction works proceeded under four works packages for six
subprojects. Work on a seventh subproject under a separate works package will
formerly start 1 October 2014.
To date the total value of construction contracts awarded under Stage 2 civil works is
USD 4,857,815.98 (see Table 4).
3.4. Hydromet and Automatic Weather Stations
During September the DDIS Consultant assisted the PIU for receipt and opening of the
technical offers for the Hydromet and Automatic Weather Stations (AWS), IFB
No.FDERP-AF-MOWRAM-ICB01. The Consultant then proceeded with bid evaluation
which was ongoing at 30 September 2014 (see Chapter 3 -2).
3.5. Stage 3 Implementation
The initial focus for Stage 3 was to start preparation of subproject profiles to gain
PCMU and ADB approval to proceed with subprojects to procurement of works
contracts and construction (see Chapter 3 -3.2). The mobilised Consultant’s staff
commenced desk studies upon joining the team and on 29 September 2014 departed
to the field for subprojects Chork Reservoir, Basac Irrigation System and Trapaing
Thmor Irrigation System.
3.6. Reports
The report requirements for the Consultant are stated in the TOR as follows:
� Implementation Plan (within 1 month)
� Hydromet Review and Final Plan
� Contract Reports – design, procurement, bid evaluation and completion
� O&M and Flood Management Plan (by scheme)
� Monthly Progress Reports††
††
The Terms of Reference states Quarterly Progress Reports but this was subsequently changed to
Monthly.
Egis Eau Monthly Report – September 2014
Page 12 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
� Project Completion Report
The reports submitted to date are listed at Appendix 3.
The Implementation Plan was completed during September 2014 but is pending
discussion with the PIU before formal issue (see Chapter 3 -3.1).
The Hydromet Review and Final Plan was issued on 12 May 2014 during the Urgent
Services period.
For Contract Reports these will comprise: subproject profiles, bidding documents,
design report, and bid evaluation report (by works package not subproject), and
supplementary reports as may be required.
The O&M and Flood Management Plans will be prepared by scheme.
Monthly progress reports were prepared and submitted for July and August 2014.
Although these were not strictly required prior to signature of Contract Variation No.AF-
1 they are valuable as a record of Stage 2 construction progress.
Egis Eau Monthly Report – September 2014
Page 13 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Chapter 2 - Consultants Activities
1. Mobilisation
Mobilisation prior to signature of Contract Variation No AF-1 27 August 2014 was for
Urgent Services. Full mobilisation commenced 28 August 2014 immediately upon
signature of the Contract Variation. Table 2 provides the mobilisation dates of team
members and Appendix 2 the time spent on the Project by each expert to date. The
Consulting Service Staffing Schedule from the Implementation Plan is included in
Appendix 5.
Table 2: Mobilisation dates of DDIS Consultant staff
Mobilisation Date No. Name Position
from to
International Experts
1 Mark SCHIELE Team Leader/Irrigation Engineer 1 Mar 2014*
4 Jun 2014
Intermittent
24 Jun 2014
Leighton WILLIAMS Team Leader/Irrigation Engineer 28 Aug 2014
19 Sep 2014
16 Sep 2014
30 Sep 2014
2 Piyush GUPTA Senior Procurement Specialist 29 Mar 2014 30 Apr 2014
3 Jaindra KARKI Irrigation/ Dam Design Engineer 29 Mar 2014 10 May 2014
Gir Bahadur K.C. Irrigation/ Dam Design Engineer 24 Sept 2014 30 Sep 2014
4 Leighton WILLIAMS Hydrologist/ Hydromet Specialist 1 Apr 2014
9 Jun 2014
17 Sep 2014
30 Apr 2014
30 Jun 2014
18 Sep 2014
National Experts
1 Sar CHEAM Deputy Team Leader/ Irrigation Design Engineer
1 Jul 2014
30 Sep 2014
2 Sar CHEAM Contract Engineer #1/ Acting Deputy TL
24 Feb 2014*
30 Jun 2014
Sokkong HENG Contract Engineer #1 04 Sept 2014 30 Sep 2014
3 Seat THIM Contract Engineer #2 24 Feb 2014*
8 Sep 2014
13 Jun 2014
30 Sep 2014
4 Savy PRAK Contract Engineer #3 Not yet mobilised
5 Chandaro MAM Contract Engineer #4 Not yet mobilised
6 Sen SIM Contract Engineer #5/ Structural Design Engineer
1 Apr 2014*
28 Aug 2014
13 Jun 2014
30 Sep 2014
7 Sophanna Mel Resettlement Specialist 29 Sep 2014 30 Sep 2014
8 Chanthea Lang Socio-Agric. Economist 15 Sep 2014 30 Sep 2014
9 Pheaktra KVAN Hydrologist 1 Apr 2014 21 May 2014
10 Chamroeun PRAK Surveyor Not yet mobilised
Egis Eau Monthly Report – September 2014
Page 14 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Mobilisation Date No. Name Position
from to
11 Sin Kosal Procurement (Bid Documents),
6 days only.
5 Jul 2014 20 Jul 2014
Sokchea EM Procurement (Bid Documents) 17 Sep 2014 30 Sep 2014
12 Mavuth IM CD/FWUC Specialist 15 Sep 2014 30 Sep 2014
13 Reasei EL O&M Engineer Not yet mobilised
14 Motha HEM GIS/ AutoCAD Specialist Not yet mobilised
15 May Simorn Environmental Specialist 26 Sep 2014 30 Sep 2014
National Site Construction Supervisors
1 Hor Den Site Inspector #1 18 Sep 2014 30 Sep 2014
2 Ro Rosbunnat Site Inspector #2 18 Sep 2014 30 Sep 2014
* Pre-agreement mobilisation for Urgent Services
2. Field Visits
Table 3 below shows the subprojects and facilities visited by team members during this
reporting period.
Table 3: Field visits during month of September 2014
Date Sub-project Province Facilities visited Remarks
08 Sep 14 Chork Reservoir Battambang, Construction site visit to check the construction progress by PIU’s Technical Assistance Officers and DDIS Consultant
Stage 2
09 Sep 14 � Tumnub Srae Loor
� Tumnub O Ang Krang
Banteay Meanchey, Oddor Meanchey
Construction site visit to check the construction progress by PIU’s Technical Assistance Officers and DDIS Consultant
Stage 2
10 Sep 14 � Tumnub Kork Srok
� Ta Saom � Kork Thnong � Tumnub 95
Siem Reap Siem Reap Siem Reap Preah Vihear
Subproject sites to check existing site conditions by PIU’s Technical Assistance Officers and DDIS Consultant as instructed by National Project Director.
Move to Stage 3
11 Sep 14 Tumnub Rolous Kampong Thom Construction site visit to check construction progress by PIU’s Technical Assistance Officers and DDIS Consultant
Stage 2
26 Sep 14 Tumnub Rolous Kampong Thom Construction site visit to check construction progress by PIU’s Technical Officers and DDIS Consultant
Stage 2
27 Sep 14 � Chork Reservoir � Basac Reservoir
Irrigation System
Battambang Construction site visit to check construction progress by PIU’s Technical Assistance Officers and DDIS Consultant
Stage 2
29 Sep 14 � Chork Reservoir � Basac Reservoir
Irrigation System
Battambang For preparation of subproject profiles. DDIS Consultant team.
Stage 3
Egis Eau Monthly Report – September 2014
Page 15 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
3. Persons Met and Formal Meetings Attended
The DDIS Consultant is most grateful for the assistance provided by the PIU,
MOWRAM and PDWRAM personnel during this report period. People met during the
reporting period for discussions and formal meetings attended are listed in Appendix 4.
4. Stage 2 Activities
During September construction works proceeded under five works packages for six
subprojects. Work on a seventh subproject under a separate works package will
formerly start 1 October 2014.
The subproject locations are shown on the map included as Appendix 1. The
implementation status is shown in Table 4.
The Consultant has supported the PIU for construction supervision of ongoing
construction. This included evaluation of an extension of time for Tumnub Louk
subproject because the work site had flooded. It also included instructions for
additional works for Srae Loor subproject, namely the addition of culvert gates and
construction of a FWUC office; but remaining within the Contract Sum.
5. Stage 3 Activities
The Consultant’s Stage 3 activities have included:
� mobilisation of staff;
� preparation of the Implementation Plan;
� bid evaluation for Hydromet and AWS;
� commence preparation of subproject profiles including first field work;
� issue monthly reports for July and August 2014; and
� assistance to the PIU including project management
6. Assistance with Project Management
6.1. Assistance with FDERP-AF
Having throughout assisted the ADB TA and MOWRAM in the formulation of the new
FDERP-AF, in particular the Consultant was expected to provide services as part of
Advance Services cited in the MOU (28 January 2014). In good faith the Consultant
immediately mobilised two national staff to assist with advance actions for the selected
FDERP-AF Stage 2 projects and prepared the Addendum #2 to the agreement for
reducing FDERP resources for providing agreed resources for the advance actions as
described above.
Egis Eau Monthly Report – September 2014
Page 16 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Although resources for advance services were allocated through the Addendum #2, in
fact the contract engineers continued to work beyond the original allocation.
6.2. Procurement of Civil Works
During September the Consultant assisted the PIU in award of two works packages by
DC:
� FDERP-AF-MOWRAM-CW 01A for Trapaing Thmor Irrigation System in
Banteay Meanchey Province; and
� FDERP-AF-MOWRAM-CW 03B for Basac Irrigation System in Battambang
Province.
Procurement of the civil works has complied with ADB requirements set out in the
project documents in particular the project Procurement Plan (PP) as presented in the
Project Administration Manual (PAM) March 2014. Initially during May 2014 and for
these two subprojects the Consultant provided specific assistance to the PIU in
preparation of the procurement including preparation of bid documents, bid process
and bid evaluation. During the month of August 2014, the Consultant Team revised the
contract documents for the two contract packages. The scope of works for FDERP-AF-
MOWRAM-CW 01 was revised to meet the budget limitation for Stage 2. The revised
contract documents were sent to the PIU for review and were forwarded to the PCMU
for endorsement and onward submission to ADB for NOL. The ADB NOL to proceed
with contract signing for CW03B Basac Irrigation System was issued on 4 September
2014 and for CW01A Trapaing Thmor Irrigation System on 18 September 2014.
6.3. Procurement of Goods and Services
The final bidding document IFB No.FDERP-AF-MOWRAM-ICB-01 for the Procurement
of Goods for Supply, installation and commissioning of Hydromet Stations and AWS,
including on-site training, was revised on 31 July 2014.
The announcement for the invitation for bids ICB01 for the above procurement of
goods was advertised in the Phnom Penh Post on Monday, 4 August 2014. Nine
companies purchased bidding documents before the due time and date for delivery of
bids, 3:00pm on 18 September 2014. Four bids were received and the technical offers
are currently being evaluated for compliance prior to opening of the financial offers for
compliant bids (see Chapter 3 -2).
Egis Eau Monthly Report – September 2014
Page 17 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Chapter 3 - Implementation Status
1. Stage 2 Progress
As of 30 September 2014 civil works have been in progress for the seven Stage 2
subprojects selected and approved by ADB. As noted in Chapter 2 -6.1 for Basac
subproject works only commenced 15 September 2014 and for Trapaing Thmor
subproject the Contractor started mobilization in late September for the formal Contract
start 1 October 2014. The procurement implementation dates for civil works are shown
at Appendix 6.
Site inspection for contract packages CW02, CW03A, CW03B, CW04 and CW05 were
conducted on 8-11 and 26-27 September 2014 (see Table 3). The purpose of the site
inspections was to check construction progress and the quality control for the
earthworks, Laterite pavement and structures. The inspection team comprised PIU
officer, PDWRAM, TA/Consultant and Contractors.
Table 4 below presents the basic data for all the Stage 2 contracts procured by DC.
Progress against the contract programmes for CW02 and CW03A is ahead of
schedule. Progress on CW05 is a little behind schedule. Progress for CW04 which is
for two subprojects is significantly behind schedule because for one of the subprojects
Tumnub Luok works had to be suspended until 1 December due to flooding of the site
caused by wet season rainfall; but progress on the other subproject Tumnub O Ang
Krang is also behind schedule. In the two weeks since CW03B started progress has
been without apparent delay.
Additional works for a FWUC building have been proposed for contract package CW02
Srae Loor subproject. The works will be completed within the Contact Sum and it is
anticipated that the National Project Director will issue formal instruction to the
Contractor early October.
By the end of September, the estimated average overall completion of civil works
construction is 80% for contract CW02, CW03A, CW04 and CW05, except the CW04A
of Tumnub Luok where work is suspended due to flooding.
Egis Eau Monthly Report – September 2014
Page 18 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Table 4: Summary of Implementation Status of Stage 2 Construction
Contract Schedule Actual Construction Schedule
No Sub-projects Name Contract No. Name of
Contractor
Contract
Award Price
Advance
Payment
Claim Start Complet-
ion
Defects
Liability
Complet-
ion Delay
Defects
Liability
FDERP-AF-MOWRAM USD USD Date Date date Date Months Date
1 Trapaing Thmor Irrigation System CW 01A
Ung Simsia
Construction Co.,
LTD
1,499,961.10 01-Oct-14 31-Jan-15 31-Jan-16
2 Tumnub Srae Loor CW 02
Ung Simsia
Construction Co.,
LTD
474,731.46 71,209.72 26-Jun-14 26-Oct-14 26-Oct-15
3 Chork Reservoir Rehabilitation CW 03A Seak Chheav Leng
Enterprise Co., LTD 244,955.93 36,743.39 25-Jul-14 25-Nov-14 25-Nov-15
Basac Reservoir Rehabilitation CW 03B Seak Chheav Leng
Enterprise Co., LTD 1,066,179.88 159,926.98 15-Sep-14 15-Jan-15 15-Jan-16
Tumnub Luok 3 months
4
Tumnub O Ang Krang
CW 04
SBPH Engineering
and Construction
Co., LTD
1,025,407.09 153,811.06 26-Jun-14 26-Oct-14 26-Oct-15
5 Tumnub Rolous CW 05
Ung Simsia
Construction Co.,
LTD
546,580.52 81,987.08 26-Jun-14 26-Oct-14 26-Oct-15
TOTAL
4,857,815.98 503,678.23
Note: The Contract Award Price includes Contingencies Item
Egis Eau Monthly Report – September 2014
Page 19 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
1.1. FDERP-AF-MOWRAM-CW02
Tumnub Srae Loor subproject: Construction started 26 June 2014. By the end of the
September 2014 overall completion was 94.3% and in advance of the target 78.7%
(See Figure 1). Earthworks were 100% completed; the Laterite pavement, grass
sodding and structures were 100% completed. On 9 September 2014 the works were
inspected by a PIU Technical Assistance Officer, a Technical Officer of PDWRAM in
Banteay Meanchey Province and the Consultant in the presence of the Contractor. At
that time the placing of fill for Reservoir No 1 embankment dam was completed up to
final design elevation for the full length of 3,415 m and the placing of fill for Reservoir
No.2 embankment dam was completed up to final design elevation for the full length of
1,750 m, both as per the design drawings.
During construction it became apparent that an existing box culvert and a pipe culvert
required gates otherwise the reservoir could not impound water during the 2014 wet
season. The culverts are along the dam Reservoir No.1, the box culvert at station
1+158 m and the pipe culvert at station 2+236 m. The Contractor was formally
instructed to provide and install the required gates on 26 September 2014. The local
authority has requested as additional works a Farmer Water User Community (FWUC)
building with plan area 64 m2. Since sufficient funds remain from the Contract Sum the
PIU has decided to provide the requested building and the Contractor was to be
formally instructed to proceed at the beginning of October. A single Variation Order #1
will be prepared for the additional works comprising the gates and FWUC building.
Figure 1: Construction Progress for Srae Loor subproject Stage 2
0
10
20
30
40
50
60
70
80
90
100
PE
RC
EN
TA
GE
OF P
RO
GR
ES
S %
Target 0.9 24.1 51.6 78.7 100.0 100.00
Actual 0.9 40.0 80.8 94.3
Jun Jul Aug Sep Oct Nov
Egis Eau Monthly Report – September 2014
Page 20 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
1.2. FDERP-AF-MOWRAM-CW03A
Chork Reservoir subproject: Construction started 25 July 2014. By the end of
September 2014 overall completion was 89.6% and in advance of the target 63.2%
(See Figure 2). The earthworks were 100% completed, and slope protection by riprap
and the bottom beam by rock filled gabion box were 100% completed, concrete work
was 62% completed. The outstanding tasks are completion of the concrete works,
placing Laterite pavement for the road along the dam crest, and clearing the site on
completion. On 8 and 27 September 2014 the works were inspected by a PIU
Technical Assistance Officer and the Consultant in the presence of the Contractor (see
Table 3).
Figure 2: Construction Progress for Chork Reservoir subproject Stage 2
0
10
20
30
40
50
60
70
80
90
100
PE
RC
EN
TA
GE
OF P
RO
GR
ES
S %
Target 0.9 40.6 63.2 100.0 100.0
Actual 1.4 46.1 89.6
Jul Aug Sep Oct Nov
1.3. FDERP-AF-MOWRAM-CW04
Contract package FDERP-AF-MOWRAM-CW04 comprises two subprojects both
located in Uddor Meanchey province namely; Tumnub Luok and Tumnub O Ang
Krang. The construction start date was 26 June 2014. The overall progress for
contract package FDERP-AF-MOWRAM-CW04 is estimated at 55%, which is behind
the target of 88% for the overall scope of works. However, work on for Tumnub Luok
subproject has been suspended since August 2014 due to flooding although work on
Tumnub O Ang Krang has continued throughout September 2014.
� Tumnub O Ang Krang: Construction started 26 June 2014, with site
establishment, bush clearance along the dike and earthwork along the dam.
On 9 September 2014 the works were inspected by a PIU Technical Assistance
and the Consultant. By the end of September 2014, the Contractor had
completed 85.7% of the earthworks. Filling of the embankment dam had been
completed up to final design elevation as per the drawing over a length of
Egis Eau Monthly Report – September 2014
Page 21 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
4,300 m. No work had be completed for the spillway structure rehabilitation,
because this could not proceed while fill for the dam was being transported
along the crest of the dam. By the end of September 2014 the overall progress
is estimated at 81.6%, which is behind the schedule (see Figure 3), the
outstanding works principally comprise Laterite pavement and repairs to the
spillway structure.
Figure 3: Construction Progress for Tumnub O Ang Krang sub-project Stage 2
0
10
20
30
40
50
60
70
80
90
100
PE
RC
EN
TA
GE
OF P
RO
GR
ES
S %
Target 0.5 27.0 57.7 88.2 100.0 100.0
Actual 0.5 31.9 72.8 81.6
Jun Jul Aug Sep Oct Nov
� Tumnub Luok: Since July 2014 the Contractor could not access the borrow pit
because all the surrounding areas have been flooded and the reservoir is full
and spilling (see photographs of Tumnub Luok). Consequently negligible
progress was made during August 2014 and work has been suspended
throughout September 2014. The progress made had mostly been achieved by
the end of July 2014 and comprised work on rehabilitation of the dam which
included spreading the existing dam fill over a length 2.80 km and bush
clearance along the dam, with some layers of fill and compaction. For
excavation of the main canal excavation and filling the canal embankment there
is 0% progress up to date. By the end of August 2014, the Contractor had
completed 21.1% earthworks, but 0% structure rehabilitation. On 18 August
2014 the Contractor formally requested a postponement of the construction
works. The reasons given are that the site and surrounding area is flooded and
it is not possible to access the borrow pits. Throughout July 2014 there had
been heavy rainfall in the catchments draining to Tumnub Luok and this has
caused the flooding. Overall progress is estimated at 20%, which is behind the
target of 58%. However, some of the progress made will be lost due to
regrowth of cleared vegetation and damage to unfinished earthworks from rain
Egis Eau Monthly Report – September 2014
Page 22 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
and flood. On 10 September 2014 the PIU responded to the Contractor’s
request for postponement and Extension of Time, works to restart of 1
December 2014 for completion 21 March 2015.
1.4. FDERP-AF-MOWRAM-CW05
Tumnub Rolous Rehabilitation: Construction started 26 June 2014, with site
establishment, bush clearance along the dam, detour road construction; placing fill to
the dam over a total length 4,761 m. Structure work has included demolition of the
parapet wall on the existing structures at five locations which is finished; and for the
spillway structure preparation of the foundation, placing base slab rebar and concrete
placing for the stilling basin and glacis slab of the spillway. By the end of
September 2014, the earthwork is 80% completed, except the Laterite pavement and
grass sodding. The structures are 79% completed. Overall progress by the end of
September 2014 is estimated at 77.2% completed against a planned 82.9%, and
therefore the works are behind the schedule.
Figure 4: Construction Progress for Tumnub Rolous sub-project Stage 2
0
10
20
30
40
50
60
70
80
90
100
PE
RC
EN
TA
GE
OF P
RO
GR
ES
S %
Target 0.3 16.7 44.5 82.9 100.0 100.0
Actual 0.4 19.2 50.0 77.2
Jun Jul Aug Sep Oct Nov
During construction it became apparent that the existing dam crest width of 3.60 m
needed to be widened to 5 m because the dam is used as a public road. The widening
has changed the side slope of the dam on the downstream side requiring bush
clearance, removal trees and benching cut to place and compact fill on the slope.
Since sufficient funds remain from the Contract Sum the PIU has decided to provide
the additional works for clearance and placing of fill along the dam. Also included is an
additional gate at station 2+935 m along the dam. A single Variation Order #1 will be
issued during October 2014 for the additional works comprising the bush clearance,
removal of trees and the additional gate.
Egis Eau Monthly Report – September 2014
Page 23 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
1.5. FDERP-AF-MOWRAM-CW03B
Basac Irrigation System subproject: Construction started 15 September 2014, with
site establishment, bush clearance along the main canal MC-2, canal excavation for a
distance 1,000 m. By the end of September 2014 no structure work had started but the
earthworks were 13% completed. Overall progress by the end of September 2014 is
estimated at 10% completed.
1.6. Contractor’s Report/ Quality Control
Construction supervision for Stage 2 subprojects contract packages CW-02, CW-03A,
CW04 and CW05 has been done by PDWRAM Staff and PIU-MOWRAM. The
Consultant has attended site on noted at Table 3.
Soil testing reports, concrete mix design and testing, reinforcement testing have been
received for Tumnub Srae Loor subproject under Contract FDERP-AF-MOWRAM-CW
02, from Ung Sim Sia Construction Co., Ltd. One Contractor of SBPH Engineering and
Construction Co., Ltd submitted concrete mix design and testing, and reinforcement
testing in this month for Tumnub Luok and O Ang Krang subprojects under Contract
package FDERP-AF-MOWRAM-CW04.
Soil testing reports, concrete mix design and testing, reinforcement testing have been
received for Chork Reservoir Rehabilitation subproject under Contract FDERP-AF-
MOWRAM-CW 03A, from Seak Chheav Leng Enterprise Co., Ltd.
Contractors under three contact packages of CW02, CW03A and CW05 are submitting
soil compaction test results for earthworks, Laterite and concrete test result for the
structures during September 2014. The contractor SBPH is looking for a source of
Laterite which will comply with the technical specification for the Laterite pavement on
the crest of the dam. During September all the known and usual sources of Laterite in
Oddor Meanchey Province were flooded.
A full list of quality control testing is shown at Table 5.
Table 5: Stage 2 Quality control test results
Contract Contractor Quality control report Submittal
date
Pass/f
ail Comments
Proposed for steel testing 17 Jul 14 P Pomina SD390,
Accepted
Proposed design mix concrete 17 Jul 14 P
Concrete
strength,
Accepted
Proposal for Borrow pit 17 Jul 14 P Accepted
Proposal for Borrow pit BP-2,
BP-3 4 Jul 14 P Accepted
CW 02
Ung Sim Sia
Construction
Co., Ltd
Concrete test for Intake no.1 for
cut-off and base slab 28 Jul 14 P Accepted
Egis Eau Monthly Report – September 2014
Page 24 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Contract Contractor Quality control report Submittal
date
Pass/f
ail Comments
Concrete test for Intake no.1 for
right wing wall 31 Jul 14 P Accepted
Concrete test for Intake no.2 2 Aug 14 P Accepted
CW 02
Ung Sim Sia
Construction
Co., Ltd Concrete test for Intake no.1,
wing wall and top slab and
Concrete test for Intake no.2 for
top slab
30 Sep 14 P Accepted
Proposed for borrow pit no.1and
borrow pit no.2 (Tumnub O Ang
Krang subproject)
2 Jul 14 P Accepted
Compaction test result 15 Jul 14 P Accepted
Proposed design mix concrete 15 Jul 14 P Accepted
Proposed for steel testing 21 Jul 14 P V Steel SD390,
Accepted
Compaction test result 08 Aug 14 P Accepted
Compaction test result 10 Aug 14 P Accepted
Compaction test result 15 Aug 14 P Accepted
Compaction test result 16 Aug 14 P Accepted
CW 04
SBPH
Engineering
and
Construction
Co., Ltd
Compaction test result 18 Aug 14 P Accepted
Proposed design mix concrete
17 Jul 14 P Accepted
Proposed for steel testing 17 Jul 14 P Pomina SD390,
Accepted
Compaction for field density test 24 Jul 14 P Accepted
Compaction for field density test 3 Aug 14 P Accepted
Compaction for field density test 4 Aug 14 P Accepted
Compaction for field density test 6 Aug 14 P Accepted
Compaction for field density test 13 Aug 14 P Accepted
Compaction for field density test 14 Aug 14 P Accepted
Compaction for field density test 20 Aug 14 P Accepted
Compression Test of Concrete
for cut-off of spillway structure 28 Jul 14 P Accepted
Compression Test of Concrete
for base slab of spillway
structure
11 Aug 14 P Accepted
CW 05
Ung Sim Sia
Construction
Co., Ltd
Compression Test of Concrete
for cut-off of spillway structure 18 Aug 14 P Accepted
Egis Eau Monthly Report – September 2014
Page 25 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Contract Contractor Quality control report Submittal
date
Pass/f
ail Comments
Compression Test of Concrete
for base slab and wing wall of
spillway structure
30 Sept 14 P Accepted
Proposed laterite pavement for
dam 30 Sept 14 P Accepted
CW 05
Ung Sim Sia
Construction
Co., Ltd
Field density test for the laterite
pavement for dam 30 Sept 14 P Accepted
Proposed for borrow pit BP-1 29 Jul 14 P Accepted
Proposed for borrow pit BP-2 29 Jul 14 P Accepted
Proposed Laterite pavement for
dam 29 Jul 14 P Accepted
Proposed design mix concrete 03 Sep 14 P Accepted
CW 03A
Seak Chheav
Leng
Enterprise
Co., Ltd
Compaction for field density test 29 Jul 14 P Accepted
Egis Eau Monthly Report – September 2014
Page 26 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
1.7. Construction Progress Photos (Stage 2)
Intake No.1 on the Dam Reservoir No.1 of Srae Loor
subproject, looking from u/s (CW02)
Intake No.1 on the Dam Reservoir Dam No.1 of
Srae Loor subproject, looking from d/s (CW02)
Modification of the box culvert on Srae Loor Dam
Reservoir No.2, with wet stone masonry at u/s of
structure (CW02)
Grass sodding for Srae Loor Dam Reservoir No.2
(CW02)
Slide gates and spindle was hauled to the worksite for
the gate installation on 6 September 2014 for Srae
Loor subproject (CW02)
Dam Reservoir No.1 for Srae Loor subproject
(CW02)
Egis Eau Monthly Report – September 2014
Page 27 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Dam Reservoir No.2 for the Srae Loor subproject
(CW02)
Preparation the Slide gate installation for Srae Loor
subproject (CW02)
Modified box culvert structure awaiting slide gate
installation, Srae Loor Dam Reservoir No.1 (CW02)
Slide Gate installation for box culvert on Dam
Reservoir No. 1 for Srae Loor subproject (CW02)
Galvanised steel for steel ladder and hand rail
installation (CW02)
Galvanised steel and slide gate for the installation to
the gate structure (CW02)
Egis Eau Monthly Report – September 2014
Page 28 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Washout location at Chork Reservoir Dam, after
rehabilitation in August 2014 (CW03A)
Washout location at Chork Reservoir Dam, after
rehabilitation in August 2014 (CW03A)
Riprap protection on side slope of Chork Reservoir
Dam (CW03A)
Riprap protection on side slope of Chork Reservoir
Dam (CW03A)
Riprap protection works with concrete beam, Chork
Reservoir (CW03A)
Riprap protection works with concrete beam at
Chork Reservoir Dam (CW03A)
Egis Eau Monthly Report – September 2014
Page 29 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Flood Situation on September 2014, at Tumnub Luok
Dam (CW04)
Flooded surroundings at Tumnub Luok worksite
during September 2014 (CW04)
Tumnub O Ang Krang worksite during September
2014 (CW04)
Tumnub O Ang Krang Dam, after Reconstruction in
September 2014 (CW04)
Tumnub O Ang Krang Dam, after reconstruction in
September 2014 (CW04)
Tumnub O Ang Krang Dam, after reconstruction
(CW04)
Egis Eau Monthly Report – September 2014
Page 30 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Tumnub O Ang Krang dam at the end (CW04)
Tumnub O Ang Krang dam after grass sodding
(CW04)
Rolous Dam after completion (CW05)
DDIS Consultant measuring the top width of Dam
(CW05)
Placing concrete for the spillway stilling basin base
slab at Rolous Dam (CW05)
Rock filled gabion box installation at d/s of spillway
Rolous Dam (CW05)
Egis Eau Monthly Report – September 2014
Page 31 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Grass sodding on d/s side slope of Rolous Dam
(CW05)
Placing concrete for the spillway glacis slab and
placing rock filled gabion boxes d/s (CW05)
Placing concrete for the spillway glacis slab (CW05)
Placing concrete for the spillway glacis slab (CW05)
Formwork for column of hoist deck of head regulator
(CW05)
Trimming side slope of Dam at d/s (CW05)
Egis Eau Monthly Report – September 2014
Page 32 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Main Canal (MC-2) after bush and shrub clearance,
Basac subproject (CW03B)
Bush and shrub clearance along MC-2, Basac
subproject (CW03B)
Excavation for MC-2, Basac subproject (CW03B)
Excavation for MC-2, Basac subproject (CW03B)
Dewatering excavation MC-2, Basac subproject
(CW03B)
Rock excavation for MC-2, Basac subproject
(CW03B)
Egis Eau Monthly Report – September 2014
Page 33 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Excavation for MC-2, Basac subproject (CW03B)
Trimmed side slope MC-2, Basac subproject
(CW03B)
Excavation for MC-2, Basac subproject (CW03B)
Access road along MC-2, Basac subproject
(CW03B)
2. Hydromet and AWS Progress
The Hydromet Review and Final plan was presented in the Report on Proposed
Hydromet Works and AWS for the FDERP-AF submitted on 12 May 2014. The
proposed locations for hydromet stations are listed in Table 6 and the locations for
AWS are listed in Table 7.
The announcement for the invitation for bids IFB No.FDERP-AF-MOWRAM-ICB01 for
the above procurement of goods was advertised in the Phnom Penh Post on Monday,
4 August 2014 and the closing date for submission was 15:00 (local time)
18 September 2014. Nine companies purchased bidding documents.
At the due time and date the bid evaluation committee convened at the designated
office of MOWRAM for the receipt and opening of technical bids. Four bids were
received. The technical offers were opened by the bid evaluation committee in the
presence of representatives of three bidders (the fourth bidder did not send a
representative); also present were observers.
Egis Eau Monthly Report – September 2014
Page 34 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Table 6: Proposed Hydromet Sites
Station code River basin Station name Province
550104 Stung Dauntry Prek Chik Battambang
550103 Stung Sangkar Stung Kra Nhoung Battambang
None* Stung Sangkar Or Treng Battambang
520102 Stung Monkol Borey Kdol Leu Battambang
530102 Stung Sisphon O Khay Dorn Banteay Meanchey
530103 Stung Sisphon O Bei Chharn Banteay Meanchey
530104 Stung Sisphon Svay Chek (Up) Banteay Meanchey
530105 Stung Ou Memay Svay Chrum Banteay Meanchey
540103 Stung Sreng Stung Krasang Oddar Meanchey
540102 Stung Sreng Stung Sreng (Up) Oddar Meanchey
540101 Stung Sreng Kralanh Kampong Thkov Siem Reap
* This is the eleventh site which will not now be provided under FDERP-AF
Table 7: Proposed AWS Sites
Codes
WMO HYMOS Location Town Province
- 120303 District Office Moung Russey Battambang
- 130209 District Office O Chrov Banteay Meanchey
48963 120202 PDOWRAM* Office Pailin Pailin
- - PDOWRAM Office Samraong Oddar Meanchey
48966 130325 PDOWRAM Office Siem Reap Siem Reap
- 130328 District Office Varin Siem Reap
48964 - PDOWRAM Office Tbaeng Meanchey Preah Vihear
48965 120404 PDOWRAM Office Kampong Thom Kampong Thom
The Consultant’s national procurement expert started immediately evaluation of the
technical offers. After initial checking it was found that two of the bids were non-
responsive. At that stage the other two bids were considered substantially responsive
but clarification from these two bidders was required for several differing issues.
Letters were sent to the two bidders requesting clarification by 6 October 2014.
3. Stage 3 Progress
The Consultant commenced Stage 3 services 1 September 2014 following signature of
Contract Variation No.AF-1 on 27 August 2014. At that time the Urgent Services phase
had been completed on 2 June 2014 and Stage 2 construction was ongoing as
reported at Section Chapter 3 -1. Monthly reports had been prepared for July and
August 2014 and these were issued during September 2014.
During September 2014 the Consultant has focused on Project Establishment,
specifically preparation of the Implementation Plan. Notwithstanding the requirement
for the Implementation Plan work started on assisting the PIU for Stage 3 subproject
implementation and mobilisation of staff for required activities.
Egis Eau Monthly Report – September 2014
Page 35 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
For the subprojects there are two major activities for the Consultant in Stage 3.
1. Assist the PIU for Stage 3 subproject preparation comprising: preparation of
subproject profiles; design review with suggestions for improvement; and
preparation of bidding documents incorporating all required safeguards and
FWUC activities.
2. Assist the PIU in project implementation: procurement of works contracts
including bid evaluation; and construction supervision and completion of all
works contracts including safeguards and FWUC activities.
3.1. Implementation Plan
The Consultant’s TOR requires submission of the Implementation Plan within one
month of commencing services. The Plan was submitted to the PIU for review
30 September 2014. Comments have been received relating to contract package
FDERP-AF-MOWRAM-CW06 which had not proceeded under Stage 2 and for support
for FWUC for selected subprojects. The Consultant has requested the PIU to clarify
these issues before finalising and distribution of the Implementation Plan to the PCMU
and ADB. However these issues will not substantially alter the Plan which has
effectively been followed since mid September.
The implementation plan has been prepared using Microsoft (MS) Project Professional
2013.
MS Project is a project management software program, designed to assist in
developing a plan, assigning resources to tasks, tracking progress, managing the
budget, and analyzing workloads. It is an interactive tool which can present charts and
reports in many ways.
The implementation plan is presented as a MS Project Gantt chart. This replaces the
work schedule Appendix A, Contract Variation No.AF-1. Tasks are described in
successive levels of detail which can be viewed as detailed or summary tasks.
Progress can be recorded against individual tasks and then automatically calculated
through summary tasks up to project level.
MS Project is particularly useful for projects such as FDERP-AF comprising several
stages, multiple subprojects and multiple construction packages.
The Implementation Plan also includes a separate Consultancy Services Staffing
Schedule. This is an updated version the personnel schedule Appendix B, Contract
Variation No.AF-1 prepared in MS Excel.
3.1.1. Overview of Implementation plan
Appendix 9 provides an overview of the Project Implementation Plan showing selected
summary tasks for design and construction activities and highlighting as milestones the
projected start dates for Stage 3 construction. More detailed description and Gantt
charts are included with the Implementation Plan.
Egis Eau Monthly Report – September 2014
Page 36 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
The project start date is the date on which the consultant mobilised staff for urgent
services; 24 February 2014. The urgent services ran through May 2014 (Task 1).
Upon signature of Contract Variation No.AF-1, 27 August 2014 immediate mobilisation
resulted in an effective work start date 1 September 2014. The completion date for
Consultancy Services is 31 March 2017.
Stage 2 construction supervision started 26 June 2014 and is ongoing (Task 9). Two
Stage 2 construction packages started later: CW03B Basac IS (Task 19) started
15 September 2014; CW01A Trapaing Thmor IS (Task 10) started 1 October 2014.
CW06A-D (Tasks 31-37) originally planned for Stage 2 have been deferred to Stage 3
for procurement by NCB and therefore the four subprojects in this works package
require full assessment as required by the PAM for Stage 3 subprojects.
Assistance to the PIU for Stage 3 subproject preparation (Task 87) is divided by
subproject. Only the rolled up summary is shown at Appendix 9. The activities for
each subproject include the preparation of the subproject assessment reports, review
of the design and suggestions for improvement, preparation of procurement
documents, project preparation FWUC activities, hydrology, agric-socio economics,
O&M, screening for resettlement and environment.
Assistance to the PIU for subproject implementation (Task 627) includes: procurement,
supply, installation, commissioning and operational support for hydromet and AWS;
procurement of construction works contracts; and assistance with supervision of
construction including safeguards and support for FWUC.
Construction start milestones (Task 935) highlight the target dates for start of
construction for each subproject.
3.1.2. Consultancy Services Staffing Schedule
Appendix 5 presents the Consultancy Services Staffing Schedule. The timing of staff
inputs is controlled by the detailed tasks in the Implementation Plan.
The schedule shows the staff mobilised for Urgent Services from 24 February 2014
and the balance of time available for each expert as at 31 August 2014.
The times tabulated in the staffing schedule generally adhere to Contract Variation
No.AF-1. However, the PIU has obtained additional separate funding under FDERP-
AF for FWUC in ten subprojects and has requested the Consultant to support this work.
At this stage it is anticipated this would require 14 months input from the national
CD/FWUC expert; which is eight months additional to the six months allowed by the
Contract Variation. The activity bar for the CD/FWUC expert reflects the longer input.
3.2. Subproject Profiles
The requirements for subproject profiles are stated in the PAM. They are required to
provide description of the facilities and proposed interventions of the subproject and
include safeguards screening. The PAM requires that subproject profiles are submitted
to the PCMU, and for no-objection from ADB, before proceeding to design. However,
Egis Eau Monthly Report – September 2014
Page 37 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
the PIU has already prepared designs for all subprojects therefore the no-objection, if
granted, will be to proceed to preparation of bidding documents.
Preparation of subproject profiles requires a mixture of desk study and field work. It
also requires input from most disciplines including engineering, hydrology,
resettlement, agric-socio economic, CD/FWUC, water management/O&M, and
environment.
The field work will be completed in three campaigns each estimated two week duration
separated by periods in the office for writing-up. The planning has also taken
cognisance of the twelve public holidays between September and December 2014.
The first field campaign commenced 29 September 2014 for the Chork, Basac and
Trapaing Thmor subprojects. The complete list of subproject profiles to be prepared
and their status is given in Table 8.
Table 8: List of subproject profiles.
Subproject Status Submitted to PIU NOL ADB
1. Trapaing Thmor In preparation No No
2. Tumnub Srae Loor Pending No No
3. Basac IS Field work No No
4. Chork Reservoir In preparation No No
5. Tumnub O Ang Krang Pending No No
6. Tumnub Luok Pending No No
7. Tumnub Rolous Pending No No
8. Tumnub 95 IS Pending No No
9. Tumnub Kork Srok Pending No No
10. Kork Thnong Pending No No
11. Ta Saom Pending No No
3.3. Engineering Design
As of 30 September 2014 no Stage 3 engineering designs had been received from the
PIU. However, it was expected that designs for Basac Irrigation System and Chork
Reservoir would be received early October. Also the balance of former Stage 2 work
for Trapaing Thmor to be executed under construction package FDERP-AF-
MOWRAM-CW01B by NCB‡‡.
In addition the PIU had previously submitted designs for Tumnub 95, Tumnub Kork
Srok, Kork Thnong and Ta Saom. It needs to be clarified that these designs can be
used or not.
‡‡
This contract package will not require submission of a subproject profile to proceed because (a) the
works were previously approved for Stage 2, and (b) the much larger ICB contract package CW11 for
Trapaing Thmor will follow requiring subproject profile, safeguards and FWUC support.
Egis Eau Monthly Report – September 2014
Page 38 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
3.4. Procurement of Civil Works
No procurement has yet been carried out under Stage 3. All procurement will be by
NCB with the exception of FDERP-AF-MOWRAM-CW11 which will be by ICB because
of the higher contract value.
3.5. Socio-economics
The national agric-socio economist was mobilised in September and is initially
participating in the preparation of subproject profiles. The requirements for baseline
data survey and additional crop production surveys will be determined during
preparation of the subproject profiles.
3.6. FWUC Development
The national CD/FWUC expert was mobilised in September and is initially participating
in the preparation of subproject profiles. This will establish the status of existing FWUC
and define requirements for training and support to ensure project sustainability.
4. Safeguards
The PCMU is responsible for preparation of the project’s quarterly safeguards report
based on information received from the IAs.
The national resettlement and environmental experts were mobilised during
September. Their initial activity is to participate in the preparation of the subproject
profiles. Specifically they will screen the proposals for each subproject for potential
resettlement and environmental impacts. There should be no significant impacts
because the FDERP-AF subprojects are repair of flood damage to existing irrigation
infrastructure not new works, and therefore should not have new resettlement and
environmental impacts. Nevertheless the screening is essential to comply with ADB
safeguards requirements and more importantly to ensure identification, elimination or
mitigation of any potential negative impacts.
Assuming the subprojects proceed without resettlement or environmental impacts, the
situation will be monitored during implementation and construction. The environmental
expert will prepare and monitor the environmental management plans (EMP) for each
contract package.
Egis Eau Monthly Report – September 2014
Page 39 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
Chapter 4 - Project Management Issues
1. Procurement
1.1. Procurement of Civil Works
The Stage 2 contractors payments processed to date are listed in Table 9.
Table 9: Payment Certificates Stage 2 Contracts
Contract Price Payment Claims1 Disbursed Contract Contractor
USD
Sub-project
Type Date USD Date USD
Advance
IPC1 CW 01A Ung Simsia Construction Co., Ltd
$1,499,961.10 Trapaing Thmor Irrigation System
IPC2
Advance 07 Jul 14 $71,209.72 28 Aug 14 $71,209.72
IPC1 14 Aug 14 $227,195.11 CW 02 Ung Simsia Construction Co., Ltd
$474,731.46 Tumnub Srae Loor
IPC2 10 Sep 14 $105,714.33
Advance 29 Jul 14 $36,743.39
CW 03A
Seak Chheav Leng Enterprise Co., Ltd
$244,955.93 Chork Reservoir Rehabilitation IPC1 02 Sep 14 $109,994.60
Advance 16 Sep 14 $159,926.98
CW 03B
Seak Chheav Leng Enterprise Co., Ltd
$1,066,179.88 Basac Reservoir Irrigation System IPC1
Advance 08 Jul 14 $153,811.06 28 Aug 14 $153,811.06
IPC1 15 Aug 14 $400,404.50 CW 04
SBPH Engineering and Construction Co., Ltd
$1,025,407.09
Tumnub Luok
Tumnub O Ang
Krang
Advance 07 Jul 14 $81,987.08 28 Aug 14 $81,987.08 CW 05
Ung Simsia Construction Co., Ltd
$546,580.52 Tumnub Rolous IPC1 26 Aug 14 $259,665.77
$4,857,815.98 Total $1,606,652.54 $307,007.86
1 Total claim not including deduction for retention or advance payment adjustment
1.2. Procurement of Hydromet and AWS
The Contract for Hydromet and AWS is not yet awarded therefore there are no
payments made to date.
Egis Eau Monthly Report – September 2014
Page 40 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
2. Consultants Services
No Consultant invoices have been submitted to date. Invoices for the period February
to September will be submitted during October 2014.
3. Issues
3.1. Soil Investigation Study
At Trapaing Thmor FDERP-AF-MOWRAM-CW01A, poor ground conditions and
unsuitable material are being encountered at the bottom of the clay cut-off trench. It
has been necessary to remove the unsuitable material and replace with suitable
material before proceeding to place the clay core. The depth of unsuitable material has
not exceeded 1.0 m but greater depths may be encountered as the work proceeds.
The additional cost to date is within the Contract Contingency sum.
3.2. Transport
MEF/ADB has agreed that no vehicles shall be purchased for FDERP-AF and that
MOWRAM must make use of the FDERP vehicles. This disregards the fact the two
distinct projects are being implemented in parallel, and that No FDERP vehicles will be
released to FDERP-AF until after 31 March 2015 at the earliest.
To date the PIU has allocated a single vehicle from another source for the Consultant’s
use in the field use. The vehicle is not continuously available and written request to the
PIU must be made to use the vehicle. This has worked to date but a single vehicle will
not be sufficient, e.g. two vehicles were required and provided by the PIU for field work
preparing subproject profiles from 29 September 2014. During the period October
2014 to March 2015 there will be times when two to four vehicles would be needed in
the field on some days. The requirement is not continuous but can be predicted from
the Implementation Plan. The good cooperation of the PIU for provision of vehicles will
need to continue to ensure the Consultant can travel to the field to satisfy the project
requirements.
3.3. Office Furniture
The consultant has five international and 15 national staff, an office administrator plus
ten supervision inspectors who will attend the office for short periods. Not all these
staff will be present at any one time but during the period ending 31 March 2013 up to
16 staff needed to be accommodated. As of 30 September 2014 the office has eight
useable desks, two older desks are occupied by printers and binding machine, etc.
There are also two larger desks used as a meeting and layout table. For good
operation an additional eight desks and sufficient chairs are required.
Egis Eau Monthly Report – September 2014
Page 41 Output 3: Irrigation Rehabilitation and Flood Management
Version 1
3.4. Services
Stationary must be requested from the PIU. Office services such a cleaner are not
provided. The FDERP offices are serviced by a cleaner.
3.5. Printing, scanning and copying.
The printers provided are a colour A4/A3 inkjet with maximum output 1-2 ppm and an
A4 monochrome laser. There is no PC for printing. The printers are old models and do
not have WiFi, USB stick, or memory card capability. It is impossible to produce the
volume of contract documents and reports which will be required for FDERP-AF using
these printers.
There is no scanner and no photocopier. FDERP-AF cannot use FDERP printers,
scanners and copiers.
Solutions are required.
3.6. Internet
The FDERP-AF does not have Internet connection. The FDERP office Internet
connection cannot be used by FDERP-AF.
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 42
Appendix 1: Subprojects Location Map
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 43
Appendix 2: Summary of Consultant Staff Mobilisation
Person months
Contract Total used Balance Expert
To 30 Sep 2014
Remarks
1. International Experts
1 Team Leader/ Irrigation Engineer 20 1.56 18.44
2 Procurement/ Contract Specialist 1 1.00 0.00
3 Irrigation/ Dam Design Engineer 5 1.66 3.34
4 Hydraulic Gate Specialist 1 0.00 1.00
5 Socio-Economist 2 0.00 2.00
6 Hydrologist/ Hydromet Specialist 2.5 1.64 0.86
Total 1- International 31.5 5.86 25.64
2. National Experts
1 Deputy Team Leader/ Irrigation Engineer
32 2.00 30.00
2 Contract Engineer #1 22 5.07 16.93
3 Contract Engineer #2 20 4.37 15.63
4 Contract Engineer #3 20 0.00 20.00
5 Contract Engineer #4 18 0.00 18.00
6 Contract Engineer #5/ Structural Design Engineer
20 3.56 16.44
7 Resettlement Specialist 6 0.07 5.93
8 Agric. Socio-Economist 6 0.53 5.47
9 Hydrologist 8 1.70 6.30
10 Surveyor 3 0.00 3.00
11 Procurement (Bid Documents) 9 0.67 8.33
12 CD/ FWUC Specialist 6 0.53 5.47
13 Water Management/ O&M Engineer
6 0.00 6.00
14 GIS/ AutoCAD and Mapping Specialist
3 0.00 3.00
15 Environmental Specialist 7 0.17 6.83
Total 2- National Experts 186 18.66 167.34
3. National Site Construction Supervisors
16 Site Inspector #1 4 0.43 3.57
17 Site Inspector #2 4 0.43 3.57
18 Site Inspector #3 6 0.00 6.00
19 Site Inspector #4 4 0.00 4.00
Total 3- National Supervisors 18 0.86 17.14
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 44
Appendix 3: Reports Submitted to Date
Document date Name Remarks
12 May 2014 Hydromet Review and Final Plan
2 June 2014 Stage 2 Bid Evaluation Report
3 September 2014 Monthly Report – July 2014
9 September 2014 Monthly Report – August 2014
30 September 2014 Implementation Plan Draft to PIU
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 45
Appendix 4: Person Met and Formal Meetings Attended
PCMU/MEF/EA
� Mr Vann Savath National Engineer
MOWRAM/IA
� Mr Chann Sinath Project Director
� Mr Huy Vantha Project Manager
� Mr Mao Hak Director DHRW
� Mr Oum Ryna Director DOM
� Mr Im Soursdey Technical Assistance Officer, PIU-MOWRAM
� Mr Sok Boren Procurement Assistance Officer, PIU-MOWRAM
PDWRAM/IA
� Mr. Long Phalkun Director of PDWRAM, Battambang Province
� Mr. Noun Kresna Director of PDWRAM, Siem Reap Province
� Mr. Khen Nhan Director of PDWRAM, Oddor Meanchey Province
� Mr. Yem Bunrong Director of PDWRAM, Banteay Meanchey Province
� Mr. Hak Puthy Acting Director of PDWRAM, Kampong Thom Province
� Mr. Chab Koy Director of PDWRAM, Preah Vihear Province
� Mr. Vong Lo Deputy Director of PDWRAM, Preah Vihear Province
� Mr. Tem Narong Technical Officer of PDWRAM, Banteay Meanchey
Province
� Mr. He Koeun Technical Officer of PDWRAM, Kampong Thom
Province
Local Authority/FWUC/Contractor
� Mr. Chan Thy Director of Ung Sim Sia Construction Co.,Ltd
� Mr. Sreng Chanthy Director of SBPH Engineering and Construction Co.,Ltd
� Mr. Seak Leng Director of Seak Chheav Leng Enterprise Co.Ltd
� Mr. Run Pao Chief of Kork Romeat Commune, Thmar Pouk District,
Banteay Meanchey Province
� Mr. Yean Sareth Chief of Srae Loor Village, Kork Romeat Commune,
Thmar Pouk District, Banteay Meanchey Province
� Mrs. Mong Sam An Chief of Sangkat Palhal, Preah Vihear Province
� Mr. Loeung Noch Chief of Sangkat Kon Kreal, Krong Samraong, Oddor
Meanchey Province
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 46
� Mrs. Khut Chanra First Commune Council, Lvea Krang Commune, Varin
District, Siem Reap Province
� Mr. Ya Beang Chief of Ta Saom Commune, Angkor Chum District,
Siem Reap Province
� Mr. Lak Loch Chief of FWUC, Kork Thnong subproject, Char Chhouk
Commune, Angkor Chum District, Siem Reap Province
� Mr. Thlong Pang Chief of Char Chhouk Commune, Angkor Chum District,
Siem Reap Province
� Mr. Sea Sy Chief of Basac Commune, Rokhakiri District,
Battambang Province
� Mr. Vat Savorn First Commune Council, Basac Commune, Rokhakiri
District, Battambang Province
� Mr. Ou Vorn First Commune Council, Kokoh Commune, Moung
Russey District, Battambang Province
Formal Meetings Attended
Technical bid opening for Hydromet and AWS 18 September 2014 at PIU
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 47
Appendix 5: Consultancy Services Staffing Schedule
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 48
Appendix 6: Procurement Dates for Civil Works
Bidding Process Contract Process
Bidding Document Bid Evaluation Report Contract Package
No. Description
Total Estimated
Cost PP/ Eng. Est. (USD)
Method of Procurement
Prior/ Post
Review
Plan versus Actual
Submitted Date
NOL Date
Invitation for Bids
Date
Bid Opening
Date Submitted Date
NOL Date
Contract Signature
Date
Contract Completio
n Date
Contract Amount (USD)
Supplier/ Contractor
Name
STAGE 2 CIVIL WORKS
Emergency Reconstruction Work of Trapaing Thmor sub-project in Banteay Meanchey Province
1,500,000 FDERP-AF MOWRA- CW01A
Engineer's Estimate 1,499,961.10
DC NA 06-May-14 07-May-14 19-May-14 02-Jun-14 18-Sep-14 19-Sep-14 31-Jan-15 1,499,961.10 Ung Sim Sia Construction
Co.,Ltd
Emergency Reconstruction Work of Trapaing Thmor sub-project in Banteay Meanchey Province
1,000,000 FDERP-AF MOWRA- CW01B
Engineer's Estimate 1,000,000
NCB NA Actual 06-May-14 07-May-14 19-May-14 02-Jun-14 Moved to
stage 3 for NCB
Emergency Reconstruction Work of Tumnub Srae Loor sub-project in Banteay Meanchey Province
500,000 FDERP-
AF-MOWRAM
-CW02 Engineer's Estimate 450,470.65
DC NA Actual 06-May-14 07-May-14 19-May-14 02-Jun-14 23-Jun-14 26-Jun-14 26-Oct-14 474,731.46 Ung Sim Sia Construction
Co.,Ltd
Emergency Reconstruction Work for Chork Reservoir Rehabilitation sub-project in Battambang Province
250,000 FDERP-
AF-MOWRAM-CW03A Engineer's Estimate 226,422.57
DC NA Actual 24-Apr-14 06-May-14 07-May-14 19-May-14 02-Jun-14 22-Jul-14 25-Jul-14 25-Nov-14 244,955.93 Seak Chheav
Leng Enterprise Co.,Ltd
Emergency Reconstruction Work for Basac Reservoir Irrigation System sub-project in Battambang Province
1,060,000 FDERP-
AF-MOWRAM-CW03B Engineer's Estimate 1,017,659.28
DC NA Actual 24-Apr-14 06-May-14 07-May-14 19-May-14 02-Jun-14 4-Sep-14 5-Sep-14 15-Jan-15 1,066,179.88 Seak Chheav
Leng Enterprise Co.,Ltd
Emergency Reconstruction Work of Tumnub Luok and Tumnub O Ang Krang sub-projects in Oddor Meanchey Province
1,020,000 FDERP-
AF-MOWRAM
-CW04 Engineer's Estimate 1,002,790.68
DC NA Actual 06-May-14 07-May-14 19-May-14 02-Jun-14 23-Jun-14 26-Jun-14 26-Oct-14 1,025,407.09
SBPH Engineering and
Construction Co.,Ltd
Emergency Reconstruction Work for Tumnub Rolous Irrigation sub-project in Kampong Thom Province
450,000 FDERP-
AF-MOWRAM
-CW05 Engineer's Estimate 532,774.29
DC NA Actual 06-May-14 07-May-14 19-May-14 02-Jun-14 23-Jun-14 26-Jun-14 26-Oct-14 546,580.52 Ung Sim Sia Construction
Co.,Ltd
Emergency Reconstruction Work for Tumnub 95 in Preah Vihear in Preah Vihear Province, Tumnub Ta Saom, Tumnub Kork Srok & Kork Thnong in Siem Reap Province
1,370,000 FDERP-
AF-MOWRAM
-CW06 Engineer's Estimate 1,138,591.87
DC NA Actual 06-May-14 07-May-14 19-May-14 02-Jun-14 Moved to
stage 3 for NCB
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 49
Appendix 7: Procurement Dates for Hydromet and AWS
Bidding process Contract process
Bidding documents Bid evaluation report Contract
Package
No.
Description
Estimated
cost
PP/Engineer’s
Estimate
(USD)
Method of
Procurement
Prop/post
review
Plan
versus
actual Submitted
date NOL Date
Invitation
for bids
date
Bid
opening
date Submitted
date NOL Date
Contract
signature
date
Contract
amount
(USD)
Supplier/
Contractor
name
Comment
Procurement, installation, commissioning and training for Hydromet and AWS
1,000,000 ICB Prior Plan FDERP-AF-MOWRAM-
ICB01
Engineer's Estimate 472,916 Actual
21 May 2014 30 Jun 2014 4 Aug 14 18 Sep 14
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 50
Appendix 8: Procurement Plan
Note: Procurement Plan in as in PAM. Separate plans for Stage 2 and Stage 3.
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 51
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 52
Appendix 9: Implementation Plan Summary only, see Implementation Plan document for expanded views.
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 53
Egis Eau Monthly Report – September 2014
Output 3: Irrigation Rehabilitation and Flood Management Page 54