Flinders Island Renewable Energy Pty Ltd (FIRE) Project history and learnings Presented by: Paul Fulton, [email protected]

Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Flinders Island Renewable Energy Pty Ltd (FIRE)

Project history and learnings

Presented by:Paul Fulton, [email protected]

Page 2: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Joule Logic Pty Ltd – A consultancyA renewable energy consultancy now in its 11th year. Provides Energy project development engineering and environmental and planning services.

FIRE Developments Pty Ltd A renewable energy company set up in 2012 specifically for the Flinders Island Project. It is a joint venture owned by Joule Logic and Nichols Farms.

Page 3: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Fire Developments’ only asset – a wind turbine

• A 300 kW Enercon wind turbine on a 30 metre high tower, installed on Flinders Island

• Purchased “as is where is” off the wharf in Hobart from the Australian Antarctic Division in 2012. It had been sitting there for 8 years.

• Generates 1100 MWh per year –Approximately 25% of Flinders Island load.

Page 4: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 5: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Planning, design and construction management• The Development Permit and all other regulatory requirements were

produced by Joule Logic

• Joule Logic negotiated the Connection Agreement and the Power Purchase Agreement with Hydro Tasmania

• ABB designed the control and communications interface between Hydro Tasmania’s power station and the wind turbine

• URS (now AECOM) designed the foundations

• Joule Logic did the protection studies, voltage control studies, earthing design, connection switchboard design and commissioned the wind turbine.

Page 6: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Transport• Thirteen semi-trailer loads

of turbine components and construction equipment had to be transported.

• Roll-on roll-off transport to Flinders Island was available but expensive

• Prime movers were not transported, just the trailers. A single prime mover was left on the island for the duration of the construction.

Page 7: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 8: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 9: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 10: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 11: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Foundation construction• Two stage pour used (not

typically done).

• A special concrete mix was developed to avoid having to import sand onto the island

• No concrete batching plant was available on the island

• Two agitator trucks and pre-mixed aggregates avoided the need for a batching plant

Page 12: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 13: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 14: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 15: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 16: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 17: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Turbine erection• Managed erection with

a single crane

• Erection took two days of crane time

• Special lifting gear was required to manage the rotor “flip”

• Approximately $30K of special tooling required to be purchased.

Page 18: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 19: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 20: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 21: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators
Page 22: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

CommissioningTests were done to demonstrate technical aspects such as:

1. The ability of the wind turbine to follow a power limiting setpoint provided to it by Hydro Tasmania’s Power Station

2. Set point step change response

3. Power factor compliance

4. Low voltage ride through performance

5. Behaviour of turbine on loss of communications with the power station control system

Page 23: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Power limit set point tracking

49.5

49.6

49.7

49.8

49.9

50

50.1

50.2

50.3

50.4

0

50

100

150

200

250

0 20 40 60 80 100 120

Fre

qu

en

cy (

Hz)

Po

we

r O

utp

ut

-A

ctu

al a

nd

Se

tpo

int

(kW

)

Seconds

WTG.kW Setpoint PM_752_Realtime.Frequency

Breaker opened on a diesel get-set, sending the setpoint for the turbine higher

Page 24: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

75kW set point step change response

0

20

40

60

80

100

120

140

160

180

110 112 114 116 118 120 122 124 126 128 130

Po

we

r -

Win

d t

urb

ine

ou

tpu

t an

d s

et-

po

int

(kW

)

Time (seconds)

WTG.kW Setpoint

Data recording sample rate was 0.1 seconds, but SCADA data refresh rate was not that high – hence “steps” in the trace of wind turbine output

Page 25: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Enercon control systems (2003 vintage!)Some other Enercon control system capabilities that are helpful for isolated power system operation include:

1. Storm control – the turbine de-rates at 25m/s but doesn’t stop generating until 35m/s

2. dP/dt control, also called “ramp rate control” limits the rate that power output is increased under all circumstances

3. Extreme frequency power limitation response

4. No stopping of turbine to change generator windings from the low speed to high speed or star/delta change

5. Low voltage ride through performance of full power converter system

Page 26: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Operation – Evolution of generation

Page 27: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Operation – Why has generation increased?Fire’s wind turbine’s output is less constrained because:

1. Some other wind turbines, installed in 1988, have been de-commissioned after 30 years of operation;

2. Flinders Island’s load has increased;

3. Hydro Tasmania have installed a battery, diesel uninterruptible power supply (DUPS) and dynamic resistor bank enabling “diesel off” operation. This means that there isn’t a diesel running on minimum output during high renewable energy output times;

4. Under the connection rules, FIRE’s wind turbine gets dispatched prior to any subsequently installed generation;

5. We now have more critical spares to reduce downtime.

Page 28: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Operation – What caused low generation months?Generally caused by failures that we don’t have spares for in Australia. It typically takes 4-6 weeks to get parts from Germany. Examples are:

1. The battery box, which powers the blades into the feathered position during emergency stops) failed;

2. The slip ring unit which transfers power and information to the rotor, failed;

3. Multiple lightning strikes causing damage;

4. Multiple printed circuit board failures;

5. A pole shoe failed in the generator.

The mechanical parts of the turbine have run faultlessly. All faults have been due to electrical/electronic parts mostly printed circuit boards.

Page 29: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Key learnings - construction1. Crane costs and transport costs are high in remote areas. Roads and

bridges are problematic for larger wind turbines. If possible utilise multiple smaller wind turbines rather than a single large turbine.

2. Managing quality of construction is essential. Having “doubt” about the quality of concrete (as an example) is not acceptable.

3. Have the wind turbine manufacturer’s support during construction and commissioning.

4. Make sure that the protection systems, control systems, metering systems, earthing systems are designed and installed properly. Poor design makes operation and maintenance unsafe and expensive and more prone to lightning damage.

Page 30: Flinders Island Renewable Energy Pty Ltd (FIRE) Project ......1. Keep looking for ways to increase renewable energy penetration so renewables are not constrained. 2. Train your operators

Key learnings - operation1. Keep looking for ways to increase renewable energy penetration so

renewables are not constrained.

2. Train your operators to maintain the turbine/s. Give them an incentive based on availability of the turbine, or its energy output.

3. Keep a comprehensive set of spares of electrical components such as printed circuit boards. Spares are cheap compared to lost generation.

4. Buy the right technology. Make sure that the turbine’s manufacturer (OEM) is reputable and competent and supportive, and spares will be available for the life of the project from the OEM or others. Remember Senvion, NEG-Micon, AN Bonus, Gamesa, Enron, Zephyros?