Upload
phungminh
View
232
Download
1
Embed Size (px)
Citation preview
1
Flicker Analysis and Case Studies
Jim Rossman, P.E.Senior Manager of Power Quality
Gerald Johns, P.E.Senior Power Utilization Engineer
TVAAugust 2008
2
Voltage Drop Creating Visible Light FlickerVoltage Drop Creating Visible Light Flicker
Voltage Flicker Is:Voltage Drop as Seen by
OthersVisible With Incandescent
lights and some CFLsComplaints Normally From
Residential CustomersMuch lower in magnitude
than a fault related voltage sag – usually only a few volts on 120-V system
Noticeable at low levels and downright annoying at higher levels
Voltage Flicker Does Not:Normally does not cause
equipment downtimeDoes not damage other
folks equipment
3
Flicker is Perceived Voltage DropVoltage Drop is Graphically Shown Below
Drawing Copied from IEEE 141
Flicker is Perceived Voltage DropVoltage Drop is Graphically Shown Below
Drawing Copied from IEEE 141
Φ+Φ≅ sincos IXIRVdrop
4
Per Unit Approach to Calculating FlickerPer Unit Approach to Calculating Flicker
100)1(%)1(%% XMVARswingRMWswingVdrop +
≅
Hand calculations often work best in percent on an MVA baseTVA uses 100-MVA as our base so the following is the same approach but written on a percent basis:
Example: Large motor draws 25-MW and 40-MVAR on startup. With a system Thevenin equivalent Of Z= 0.988% +j 7.170% (100-MVA base), What is the expected voltage swing on startup?
%1.3100
%)170.7(40%)988.0(25=
+≅
MVARMWVdrop
Φ+Φ≅ sincos IXIRVdrop
5
Perceived Voltage Drop in LightsGE Flicker Curves
Copied From IEEE 141
Perceived Voltage Drop in LightsGE Flicker Curves
Copied From IEEE 141
6
TVA Flicker CurveTVA Flicker Curve
7
Flicker CurvesIEEE 141 and TVA
Flicker CurvesIEEE 141 and TVA
TVACurveInRed
8
Three Key Flicker ComponentsThree Key Flicker Components
Recipe for Complaints:1. Start with - Varying load/generation equipment2. Serve from a - High System Impedance3. Repeat variations until annoying
9
Component 1:Equipment with Load Swings Leading to
Possible Flicker Issues
Component 1:Equipment with Load Swings Leading to
Possible Flicker Issues
• Motors and Compressors– Rock Crushers– Saw Mills– Large Motors (Car Shredders, pumping systems)– HVAC systems
• Welders• Process ARC Furnaces• Process Induction Furnaces• Wind Generators• Others
10
Mitigation Systems Reducing Load SwingsMitigation Systems Reducing Load Swings
Dynamic Var Systems– Static Var Compensators– Dstatcom– Intellivar– Thyristor-Controlled Capacitor Systems
Motor Impact Reduction– Reduced Voltage Starters– Wound Rotor Motor Resistors– DC Motor Systems
Sequencing Multiple Welder SystemsArc Furnace Reactors
11
Component 2:Impedance Issues Important to Flicker Critical
Point of Common Coupling (PCC) for Flicker Studies
Component 2:Impedance Issues Important to Flicker Critical
Point of Common Coupling (PCC) for Flicker Studies
+
161kVRMSLL /_0
AC1
RL+
PI1
1 2
69/13.2
20_MVA2
3
1
161/69/13
60_MVA
RL+
PI2
.287Ohm
ZZ_1
+
RL1
Transmission Sub-transmission Distribution Distribution Level Circuit Level Bus Level Circuit Level
My PCC Definition:Closest Interconnection Location Where Another Customer Can See The Voltage Drop From The Disturbing Load
12
Component 2:Series Impedance to PCC –
Shown in Percent (100-MVA Base)
Component 2:Series Impedance to PCC –
Shown in Percent (100-MVA Base)
+
161kVRMSLL /_0
AC2
RL+
PI3
+
RL3
RL+
PI4
+
RL4+
RL2
Distribution Circuit – 13-kV
Distribution Bus – 13-kV
Sub-transmission – 69-kV
Transmission – 161-kV
Possible PCC Interconnection
(30.47+j138.9)% – total to DD
(1.75+32.6)% – total to CC
(1.08+j12.6)% – total to BB
(0.70+j4.82)% – total to AA
% Series Circuit Impedance 100-MVA base
A B C D
Hopkinsville, KY Facility - Services Went From 13-kV to 161-kV
13
Mitigation Approaches With Impedance Reductions
Mitigation Approaches With Impedance Reductions
Historical Solution to Flicker Problems – Reduce Impedance and percent voltage drop by Moving PCC upstream:
– General Distribution to Dedicated Distribution Feed– Dedicated Distribution Feed to Sub-transmission Feed– Sub-transmission Feed to Transmission Feed
Add Series Capacitors In Line
14
Component 3:Frequency of Voltage Variation Swings
Component 3:Frequency of Voltage Variation Swings
• Startup Related (once per season, month, week, day)– Pump Motors– Process Systems– Energizing Transformers
• Low Frequency Process cyclic (multiple times per day or hour)
– Air compressors– Refrigeration Compressors
• High Frequency Process cyclic (many times per hour of second)
– Rock crusher cycling– Shredders– Welders– Arc Furnaces
15
GE Flicker CurvesCopied From IEEE 519
GE Flicker CurvesCopied From IEEE 519
16
Drawbacks of IEEE 141/519 CurveDrawbacks of IEEE 141/519 Curve
280 300 320 340 360 380
116
117
118
119
120
121
122
123
124
125
126
seconds
RM
S V
olts
16:04:0203/13/2008Thursday
16:04:04 16:04:06 16:04:08 16:04:10
272.5
275.0
277.5
280.0
282.5
285.0
287.5
290.0
Volts
A Vrms (val)
230 230.5 231 231.5 232 232.5
119.99
119.995
120
120.005
120.01
seconds
RM
S v
olts
2530.5 2531 2531.5 2532 2532.5 2533 2533.5 2534 2534.5
270
272
274
276
278
280
282
284
286
288
seconds
RM
S V
olts
17
IEEE 1453IEEE 1453
• Based on IEC 61000-4-15 (adopts the IEC standard).
• Provides specifications for the measurement of flicker based on IEC 61000-4-15.
• Provides recommended flicker limits on medium-voltage, high-voltage, and extra-high voltage systems based on IEC 61000-3-7.
18
Advantages of using IEEE 1453 over IEEE 141/519 curvesAdvantages of using IEEE 1453 over IEEE 141/519 curves
• Measurement that directly represents flicker level in terms of human perception.
• Provides a way of measuring flicker when voltage fluctuation is anything but a rectangular change.
• Impact of modulations caused by modern solid-state converters (interharmonics) on voltage fluctuations taken into account.
• Can be incorporated into simulation models to provide future flicker estimates and the effectiveness of various flicker mitigation options.
19
UIE/IEC FlickermeterUIE/IEC Flickermeter
First 4 blocks produce a signal that collectively represent:• Response of a lamp to a supply voltage variation.• Perception ability of the human eye• Memory tendency of the human brain.
Block 5 is a statistical calculation that emulates human irritability to the flicker level.
Figure Source: J.C. Gomez, M.M. Morcos, “Flicker Measurement and Light Effect”, Power Engineering Review, Nov. 2002.
20
IEEE 1453 DefinitionsIEEE 1453 Definitions
• Pst – “A measure (statistical) of short-term perception of flicker obtained for a ten-minute interval. “
• Plt – “A measure (statistical) of long-term perception of flicker obtained for a two-hour period. This value is made up of 12 consecutive Pst values per the following formula.” - Necessary when duty cycle varies or multiple loads operating simultaneously.
N33
1
1Plt = PstNwhere N = The nunber of Pst readings.
jj=
×∑
N should be based on the duty cycle of the fluctuating load. If exact duty cycle is unknown, assume N=12 to represent 2 hours.
21
IEC FlickermeterIEC Flickermeter
• Pst of 1.0 represents a magnitude and frequency of voltage fluctuation that is generally considered to be objectionable.
• Measurement based on luminous fluctuation associated with 60-watt, 60-Hz 120-VAC or 50-Hz 240-VAC incandescent lamps.
22
Comparison of IEEE 141 and IEC Flickermeter CurvesComparison of IEEE 141 and IEC Flickermeter Curves
*1 dip = 2 changes
23
IEEE 1453 Recommended Flicker LevelsIEEE 1453 Recommended Flicker Levels
However, levels that are not objectionable may still be perceivable.
Represents the levels below which complaints are not generally received.
24
1453 Statistical Guidelines1453 Statistical Guidelines
• As a general guideline, when designing, Pst and Plt should not exceed the planning levels more than 1% of the time (99% probability level), with a minimum assessment period of one week.
• IEEE 1453 recommends that Pst and Plt not exceed 1.0 pu 5% of the time in existing low voltage and medium voltage systems (95% probability level.
25
Other Points To Note About FlickerOther Points To Note About Flicker
• People most sensitive to fluctuation frequency of 2 to 10 Hz with flicker visible up to 35 Hz.
• Any change in voltage 6.0 % or greater results in objectionable flicker, regardless of frequency. [1]
• Lower-wattage incandescent bulbs produce more flicker for a given change in voltage. At the same rated wattage, a 230-volt bulb will flicker more than a 120-volt bulb for a given change in voltage.
• Dimmers can exacerbate the flicker problem because flicker becomes more perceptible as baseline lumen levels are reduced.
• Fluorescent lamps typically flicker less for a given voltage input [2].
[1] R.Dugan, et al., Electrical Power Systems Quality, 2nd Ed., 2002.
[2]T.A. Short, Electric Power Distribution, 2005.
26
EPRI Studies of Compact Fluorescent Lamp Gain FactorsEPRI Studies of Compact Fluorescent Lamp Gain Factors
The gainfactor is defined as the ratio of relative lightchanges to relative voltage changes.
27
EPRI Studies of Linear T8 Fluorescent Lamp Gain FactorsEPRI Studies of Linear T8 Fluorescent Lamp Gain Factors
28
How About a Break!
Lets Keep It to 15 Minutes – The Best is Yet to Come!
29
Case #1 Sawmill on Rural FeederCase #1 Sawmill on Rural Feeder7.2/12.47 kV distribution source @ mill
Primary Z = 12.94 + j10.45 ohms
9.47 miles of 14.4/24.9 kV
3.76 miles of 7.2/12.47 kV
Flicker caused by load fluctuations as well as motor starts.
30
14:49:30.012/17/2007
Monday
14:49:30.5 14:49:31.0 14:49:31.5 14:49:32.0 14:49:32.5
100
200
300
400
500
kW
TOT P(kW) (val)
300400500600700800
kVAR
TOT Q(kVAR)
255260265270275280
Vol
ts
A Vrms (val) B Vrms (val) C Vrms (val)
-1500
-500
500
1500
Am
ps
A I B I C I
Real power draw starts to increase due to increase load torque (large log), but then declines because of reduced speed.
Reactive power draw increases substantially due to extreme speed reduction.
Significant voltage reduction due to reactive power draw.
Event #1 – 150-hp head saw abruptly loaded up – data collected at utility metering point
Case #1 - Head-Saw Load Up – 9.6% Vdrop @ Mill Secondary and 6.6 % Vdrop On PrimaryCase #1 - Head-Saw Load Up – 9.6% Vdrop @ Mill Secondary and 6.6 % Vdrop On Primary
31
12:22:5012/17/2007
Monday
12:22:52 12:22:54 12:22:56
300
500
700
900
1100
Am
ps
A Irms (val) B Irms (val) C Irms (val)
260265270275280285
Vol
ts
A Vrms (val) B Vrms (val) C Vrms (val)
100
150
200
250
300
kW
TOT P(kW) (val)
300400500600700800
kVA
R
TOT Q(kVAR)
Softstart programmed to start motor @ 330 % FLA
Case #1 – 200 hp Chipper Startup w/softstart 7.5 % instantaneous Vdrop at Sawmill and app. 5 % corresponding drop at residenceCase #1 – 200 hp Chipper Startup w/softstart 7.5 % instantaneous Vdrop at Sawmill and app. 5 % corresponding drop at residence
32
Initial 1-Week Pst ProfileInitial 1-Week Pst Profile
33
Initial GoalsInitial Goals
• Reduce flicker Pst on utility system to < 1.0.• Reduction in voltage sags caused by sawmill
operations on utility system to no more than 2.0 percent.
• Mitigation mechanisms must not cause greater than 2.0 percent voltage rise on utility system.
34
S & C’s AVC (Adaptive VarCompensator)
ABB’s DynaComp (Dynamic-VarCompensator
Examples of Products Providing Fast Reactive Power CompensationExamples of Products Providing Fast Reactive Power Compensation
35
More Examples of Products Providing Fast Reactive Power CompensationMore Examples of Products Providing Fast Reactive Power Compensation
Eaton-CH Active Filter
Square-D Active Filter
Square-D Hybrid-VarCompensator
36
Case Study #1 – Examples of Motor Starts with AutoXFMR startersCase Study #1 – Examples of Motor Starts with AutoXFMR starters
12:17:5512/17/2007
Monday
12:18:00 12:18:05 12:18:10
260
265
270
275
280
285
290
Vol
ts
A Vrms (val) B Vrms (val) C Vrms (val)
250
500
750
1000
Am
ps
A Irms (val) B Irms (val) C Irms (val)
Headsaw(150hp) w/67% tap
Edger (150hp) w/50 & 67% taps
37
Starter ModificationsStarter Modifications
Set all taps to 50% on all autotransformer starters.
Programmed 200hp softstart to start at 250 % of FLA.
After starter modifications, Max starting Vdrop on primary ~3%
38
Findings of Additional Recording at the SawmillFindings of Additional Recording at the Sawmill
Fluctuations were more frequent and of higher magnitude overall due to type of wood being sawed.
12:0005/12/2008
Monday
00:0005/13/2008
Tuesday
12:00 00:0005/14/2008Wednesday
12:00 00:0005/15/2008Thursday
12:00 00:0005/16/2008
Friday
012345
B VPst
0
200
400
600
kW
TOT P(kW) (val)
0200400600800
kVA
R
TOT Q(kVAR)
Dran-View 6.5.00 OEM Site License Tennessee Valley Authority
39
Case Study #1 – Sawmill on Rural FeederCase Study #1 – Sawmill on Rural Feeder
Worst-case primary fluctuation = 8%
40
Calculations - Converting 3.9 miles to 14.4/24.9 kV Calculations - Converting 3.9 miles to 14.4/24.9 kV
New worst-case primary fluctuation = 2.8%
41
Pst Calculations and Estimated Pst with Voltage ConversionPst Calculations and Estimated Pst with Voltage Conversion
06:0005/13/2008
Tuesday
08:00 10:00 12:00 14:00 16:00 18:00 20:00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
B VPst
Created with DranView 6.5.0
Residence
Sawmill
42
Estimating Future Pst After Voltage ConversionEstimating Future Pst After Voltage Conversion
• Max Pst at residence for day shown = 1.34
• Corresponding Pst at sawmill secondary metering point = 1.74
• Typical ratio “every other interval” ~ 0.7-0.75
• Impedance Ratio =
• By converting last 3.76 miles to 14.4/24.9 kV
@
@
1.34 0.771.74
Max residence
Corresponding sawmill
PstPst
= =
_ _ _ Pr
_ _ _
0.1070 0.70.1535
To XFMR Sawmill imary
To XFMR Sawmill Secondary
ZZ
= =
_ _ _ Pr
_ _ _
0.0448 0.480.0933
To XFMR Sawmill imary
To XFMR Sawmill Secondary
ZZ
= =
With Impedance Ratio = 0.48 PstMax @ Residence Due to Sawmill Load = 0.84
43
Case Study #2a & #2b – Residential Air-Conditioning StartingCase Study #2a & #2b – Residential Air-Conditioning Starting
• Customer complaints at their worst have resulted in service drop/lateral changeout or possibly even transformer upsizing
• HVAC technicians often install “hard start” kits• On average, electric consumers understand
that flicker is simply going to occur when their A/C starts.
• Members sharing secondary conductors and sometimes transformer may result in one member seeing another member’s A/C startup.
44
A/C Starting Case Study #2aA/C Starting Case Study #2a
19:55:25.307/11/2007Wednesday
19:55:25.4 19:55:25.5 19:55:25.6 19:55:25.7
-150
-50
50
150
Vol
ts
A V
-150-100
050
150
Am
ps
A I
110.0112.5115.0117.5120.0
Vol
ts
A Vrms
20:09:57.307/11/2007Wednesday
20:09:57.4 20:09:57.5 20:09:57.6 20:09:57.7
-150
-50
50
150
Vol
ts
A V
-150-100-50
0
100150
Am
ps
A I C I
110.0112.5115.0117.5120.0
Vol
ts
A Vrms (val)
Before hard start installed
After hard start installed
45
Results of Using Hard Start DevicesResults of Using Hard Start Devices
• Hard start results in increased starting torque• Compressor accelerates to full speed more
quickly, thereby reducing startup duration• Magnitude of initial inrush current and voltage
drop still the same as before – capacitor provides phase shift but no voltage rise
46
Minimum Voltage Magnitude Profile and Corresponding Pst for A/C Startups Case StudyMinimum Voltage Magnitude Profile and Corresponding Pst for A/C Startups Case Study
Min Max 95% 99%AVrms 113.3 124.8 N/A N/AAVPst 0.06869 0.8114 0.7575 0.8114
20:0006/15/2008
Sunday
22:00 00:0006/16/2008
Monday
02:00 04:00 06:00
115.0
117.5
120.0
122.5
125.0
Vol
ts
A Vrms (min)
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
A VPst
Flicker could be considered objectionable although Pst<1.0
47
A/C Startup Case Study #2bA/C Startup Case Study #2b
• Customer complained about flickering lights, number of interruptions occurring, and damaged electronics.
• Distributor power-quality monitoring revealed nothing problematic.
• Distributor changed 50 kVA to 75 kVA transformer and concerns were not resolved.
• Relationship between customer and distributor was tense and customer wondered why the transformer had been changed out if no problem could be detected.
• HVAC technician told customer that the A/C unit needed a “booster” (hard-start kit).
48
A/C Startup Case #2b Power Quality Monitoring A/C Startup Case #2b Power Quality Monitoring
-400
-300
-200
-100
0
100
200
300
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14
T ime (sec)
Switchbounce associated with the mercury-bulb thermostat resulted in multiple A/C starts
A/C unit starting current
49
Case Study - Raw Water Pumping Station – Original Design Case Study - Raw Water Pumping Station – Original Design
• Original study began in 2004– Design incorporated 1 pump driven by 1250 hp
4,160 V AC induction motor– Provision for additional pump installation– 4,160 VAC Electronic softstarter– 2,125 kVAr 2-stage capacitor bank switched
simultaneously on with motor (electromechanical contactor-switched)
– 1,800 kVAr switched off just as motor about to reach full speed
50
Original Design – Circuit CharacteristicsOriginal Design – Circuit Characteristics
• Fed from 161/69/12.47 sub off of 12.47-kV system
• App. 3.5 miles with 8 line sections of distribution line
• 12.47 kV to 4,160 V 2,500 kVA padmountXFMR
• 0.1 miles from riser pole to XFMR, but distributor wanted PCC to still be at primary terminals of XFMR
51
Original Objectives and ConstraintsOriginal Objectives and Constraints
• Determine if original design with both electronic softstartand simultaneously-switched cap bank:
– Result in less than 2.0 % voltage drop at PCC during motor start?
• Use softstart manufacturer’s stated inrush current values for calculations
• Perform calculations by hand and/or using steady-state type analysis program
52
Original Calculations from 2004-2005Original Calculations from 2004-2005
2.0 % limit exceeded but distributor willing to go to 3.0 % withunderstanding that pump not started more than once per week
53
2006 Design Changes2006 Design Changes
• Latest starter mfr/consultant analysis indicated voltage drop will exceed 4.0 percent at PCC during startup.
• New design called for 2 pumps operating simultaneously
• Increased runtime/# of startups• Customer contemplating generator because distributor
does not want to allow more than 3% fluctuation under any circumstances
54
Tm
ST
D EV4
+
1 6 1 k VR MSL L /_ 0? v
AC 1
s c opes c p 3
v(t)
p1sc
ope
scp4
scop
e
scp5
scop
esc
p6
rmso u tin
tr_ 1
rmso u tin
tr_ 2
rmso u tin
tr_ 3
s c opeSe c o n d a ry Vo lta tTra n s fo rme r
s c opes c p 8
s c opes c p 9
s c opes c p 1 0
rmso u tin
tr _ 4
s c opeMo to rN o 2 R MSC u r r e n t
+
7 |1 E1 5 |0
? i
SW 1
1 2
1 2 .4 7 /4 .1 6
Yg Yg _ n p 2
2 3
1
YgYg
D_n
p1
?
161/
12.4
7/69
+
? v
2 3
1
YgYg
D_n
p2
?16
1/12
.47/
69
+
?v
s c ope
Pr ima ry _ C u r r e n t_ A
i(t)
p3
v(t)
p2
rmso u tin
tr _ 9
rmso u tin
tr _ 1 0
rmso u tin
tr _ 1 1
s c opeC a d iz Su b Vo lta g e
s c opes c p 1 7
s c opes c p 1 8
s c opeSp e e d 2
rmso u tin
tr_ 5s c ope
Mo to r N o 1 R MSC u r re n t
f(u)1
Fm2
Fm3
f(u)
Fm1
+c SW 1
+c SW 3
+
C 1? i
2 7 6 u F
+
C 2? i
2 7 6 u F
+
C 3? i
2 7 6 u F
+
c SW 2
f(u)
1
Fm
f(u)
1
Fm6
rmso u tin
tr_ 1 2
s c opePr ima ry Vo lta g e a tTra n s fo r me r
s c opeSe c Vo ltD ro p a tTra n s fo rme r
s c opePr ima ry Vo ltD ro p a tTr a n s fo rme r
v ( t )p 4
f(u)1
Fm4
s c opeMo to rN o 2 Sp e e d
f(u)
Fm9
+c SW 4
+c SW 5
+
C 4? i
4 5 .9 8 u F
+
C 5? i
4 5 .9 8 u F
+
c SW 6
+
C 6? i
4 5 .9 8 u F
f(u)1
2
Fm7 P Q
s c opePF
c1 0 0 0 0
C 8
Tm_ 1
+
? v
+
C 7? i
4 5 .9 8 u F
rmso u tin
tr_ 6
s c ope
Pr ima ry _ C u r r e n t_ Brmso u tin
tr_ 7
s c ope
Pr ima ry _ C u r r e n t_ Crmso u tin
tr_ 8
f(u)1
Fm5 s c ope
Pe rc e n tVd r o p a tC a d iz Su b s ta tio n
AS MS
4 .1 6 0 k V1 2 5 0 h p
? m
ASM1Sp e e dia
AS MS
4 .1 6 0 k V1 2 5 0 h p
? m
ASM2Sp e e dia
BU S1
a
cba
BU S2
BU S2
BU S2
•EMTP used to simulate motor start using dedicated feed from substation
•Analysis of across-the-line start with and without simultaneous cap switching
55
With Cap Bank Switched - ResultsWith Cap Bank Switched - Results
Max 1.4 % drop during start at substation with caps
56
Without 1,800 kVAr Cap Bank Switched - ResultsWithout 1,800 kVAr Cap Bank Switched - Results
Max 1.7 % drop during start at substation without caps
57
Case Study #4 – Automotive Component Manufacturer with Welders (Reactive Power)Case Study #4 – Automotive Component Manufacturer with Welders (Reactive Power)
Estimated 400-kVAr swings per phase based on 1-minute max/avg/min data
58
Case Study #4 – Automotive Component Manufacturer with Welders (Real Power)Case Study #4 – Automotive Component Manufacturer with Welders (Real Power)
Estimated 200-kW swings per phase based on 1-minute max/avg/min data
59
Case Study #4 – Automotive Component Manufacturer with Welders (Voltage)Case Study #4 – Automotive Component Manufacturer with Welders (Voltage)
3 to 4.7-volt swings based on 1-minute max/avg/min data
60
Case Study #4 – Corresponding Pst on Bus Feeding Welders (Dirty Feed)Case Study #4 – Corresponding Pst on Bus Feeding Welders (Dirty Feed)
Generally, Max Pst ~ 1.5Due to voltage sag
61
Case Study #4 – Corresponding Pst on Bus Fed By Separate Transformer Bank (Clean Feed)Case Study #4 – Corresponding Pst on Bus Fed By Separate Transformer Bank (Clean Feed)
Generally, Max Pst ~ 0.5
62
Vdrop Calculation and Comparison of Welder Bus Pst to That of Separately Fed BusVdrop Calculation and Comparison of Welder Bus Pst to That of Separately Fed Bus
• Max Pst on welding bus = 1.5• Max Pst on separately fed bus = 0.5• Utility-supplied SCC = 4,127 A @ 7.2/12.47 kV• Welding bus XFMR %Z = 6 % • Assume X/R of utility circuit = 7 and X/R of XFMR = 12
32.0350111
350j363.111j16
Bus Welding to ZTotal ZSourceCommon
3.05.15.0
Pst Bus dingWelPst Bus Fedarately Sep
%4.4100
239)(111.31.220)(160.6 Drop %Voltage Expected
percent 239j20 base)MVA -100(on r ZTransforme
percent 3.111j16
1012470
73.1j25.0 Zbase,MVA 100On
ohms 73.125.0)))7(sin(tanj))7((cos(tan41277200
8
2 source
11
≈≈++
=
==
=+×++×
=
+=
+=+
=
+=+× −−
63
Case 5 – Wind Generation
64
Buffalo Mountain Wind Farm Generation -Flicker Case
Buffalo Mountain Wind Farm Generation -Flicker Case
TVA originally contacted for three small windmills to be fed from a local distributor’s 13-kV system. Occasionally during windmill startup, the distributor received flicker complaints. When the 15-1.8-MW units went in service, it was decided to serve the new load at 161-kV.
65
Aggregate Load Swings for 15-1.8-MW Wind Generators
Aggregate Load Swings for 15-1.8-MW Wind Generators
Voltage
MW
MVAR
66
Case 6 – Large Motor System
Evaluate Possibility ofServing a 3000-hp Wound Rotor Motor
Metal ShredderAt Two Possible Locations
– XXX 69-kV: Z1 = 23.989 + j 52.618%– YYY 161-kV: Z1 = 1.559 + j 9.048%
67
Characteristics of ShredderProvided by Vendor
Characteristics of ShredderProvided by Vendor
3 times per minuteShred Load Cycling
3.1-MVA swings at 78%p.f.
2.4-MW swing1.9-MVAR swing
68
Hand Calculation Used for Approximation and EMTP Model Used for More Exact Solution
Hand Calculation Used for Approximation and EMTP Model Used for More Exact Solution
Site XXX Hand Calculation:Z1 = 23.99 + j 56.6 % (100-MVA base)MVA swing = 2.4 + j1.9
%VDrop 2.4-MW (23.99)/100 + 1.9-MVAR (56.6)/100 = 1.65%
+
AC1
69kVRMSLL /_0
s3 s4
DEV1
MW_MVAR_MW_METER
Tm
Gain2
9.549297
scopeRPM
c
0.25
C2
c
1.0
C3
Timer
3/7
tmr1
c
2
C4
1
2
select
Sel1?s
+
2.5
R1+
0.0e+0m
R2
i(t) p1
scope
IArms_Corrected
SpeedTeg scope
Torque
+
184uF C1
ASMS R
N
4.16kV3000hp
ASM1
i(t) p2
outTACS type-66
rms meter
inDEV3
scope
IArms_Uncorrected
outTACS type-66
rms meter
inDEV5
+RL1
1 2DYg_1
69/4.16
v(t)
p3
outTACS type-66
rms meter
inDEV6
f(u)1Fm1
scopePercent_V
++-
sum1
+SW1
500ms|1E15|0
≅
Use EMTPModelingFor MoreExactSolution
69
EMTP Simulation ResultsVoltage Drops As Shredder Cycles
EMTP Simulation ResultsVoltage Drops As Shredder Cycles
XXX -69-kV1.75%
YYY – 161-kV0.3%
70
Applying Results to TVA Flicker Curve Shows YYY is OK and XXX is Not Recommended
Applying Results to TVA Flicker Curve Shows YYY is OK and XXX is Not Recommended
TVA
XXX 69-kV – Above Curve – Ruled Out
YYY 161- Below Curve - OK
71
Case 7
My Town Needs a Steel Rolling MillWhat do we need to do to allow us to run
this mill?Remote Community Fed at 46-Kv – Impedance to Substation - Z1 = 74.9 +j113.5%
At 26-kV Substation Transformer Secondary (PCC) - Z1=76.3 +j169.0%
72
Company Choose IntelliVar as Mitigation System
Company Choose IntelliVar as Mitigation System
Not actualInstallationBut ShowsAll Major Components
TransformersValvesFiltersControls
73
IntelliVAR System at 1500-KVARControls Not Working Properly
IntelliVAR System at 1500-KVARControls Not Working Properly
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
13 WedJun 2007
14 Thu 15 Fri
46kV - Pst Afrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®
Pst
A
Time
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
13 WedJun 2007
14 Thu 15 Fri
26kV - Pst Afrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®
Pst
A
Time
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
13 WedJun 2007
14 Thu 15 Fri
26kV - P Totalfrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®Time
Min[P Total] (kW) Avg[P Total] (kW) Max[P Total] (kW)
-1000
-500
0
500
1000
1500
2000
2500
3000
3500
4000
13 WedJun 2007
14 Thu 15 Fri
26kV - Q Fund Allfrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®Time
Min[Q Fund All] (kvar) Avg[Q Fund All] (kvar) Max[Q Fund All] (kvar)
PST(95) – 1.47
PST(95) – 1.17
74
IntelliVAR Sizing Doubled to 3000-KVARControl System Finally Tuned
IntelliVAR Sizing Doubled to 3000-KVARControl System Finally Tuned
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
24 ThuApr 2008
25 Fri 26 Sat
26kV - P Totalfrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®Time
Min[P Total] (kW) Avg[P Total] (kW) Max[P Total] (kW)
-4000
-3500
-3000
-2500
-2000
-1500
-1000
-500
0
500
1000
24 ThuApr 2008
25 Fri 26 Sat
26kV - Q Fund Allfrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®Time
Min[Q Fund All] (kvar) Avg[Q Fund All] (kvar) Max[Q Fund All] (kvar)
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
24 ThuApr 2008
25 Fri 26 Sat
26kV - Pst Afrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®
Pst
A
Time
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
24 ThuApr 2008
25 Fri 26 Sat
46kV - Pst Afrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®
Pst
A
Time
26-kV - PST(95) - 1.18
46-kV - PST(95) – 0.82
75
Before and After Intellivar ChangesBefore and After Intellivar Changes
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
24 ThuApr 2008
25 Fri 26 Sat
26kV - Pst Afrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®
Pst
A
Time
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
13 WedJun 2007
14 Thu 15 Fri
26kV - Pst Afrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®
Pst
A
Time
13600
13800
14000
14200
14400
14600
14800
15000
15200
15400
13 WedJun 2007
14 Thu 15 Fri
Kosciusko - Attala Steel 26kV Kosciusko - V RMS Afrom 06/13/2007 to 06/15/2007
EPRI/Electrotek PQView®Time
Min[V RMS A] (V) Avg[V RMS A] (V) Max[V RMS A] (V)
13600
13800
14000
14200
14400
14600
14800
15000
15200
15400
24 ThuApr 2008
25 Fri 26 Sat
Kosciusko - Attala Steel 26kV Kosciusko - V RMS Afrom 04/24/2008 to 04/26/2008
EPRI/Electrotek PQView®Time
Min[V RMS A] (V) Avg[V RMS A] (V) Max[V RMS A] (V)
PST(95) - 1.18 – Not Under 1.0But No Routine Complaints
76
Case 8
My Largest Industry Has Us in a Bad Situation Due to Flicker, What Are Our
Options?
77
Distributor Not Routinely Serving Any Customer From 46-kV Winding Due to Flicker Complaints
Distributor Not Routinely Serving Any Customer From 46-kV Winding Due to Flicker Complaints
T Equivalent
+
161kVRMSLL /_0
AC1+
PI1
+
RL1+
RL2
+
RL3
2
3
1
161/46/13
YgYgD_np1
+
RL4
Arc Furnace
DEV1
Arc Furnace
DEV2
Arc Furnace
DEV3
Other Customers Normally FedFrom 46-kV SystemDistributor Removed Them Due to Flicker Complaints
PCCIs LocatedWithinTransformerAt T EquivalentTie Point
Site Fed FromDedicated13-kV Winding161/46/13Transformer
78
PST Estimate – Traditional Hand CalculationPST Estimate – Traditional Hand Calculation
161-kV MVAsc at Sub – 1558 MVAsc or 3.85% at 60 MVA Base
161-kV:46-kV:13:kV Transformer Nameplate:Z161-46 = 9.7% at 60-MVA, Z161-13 = 5.8% at 21-MVA (16.57% at 60-MVA)Z46-13 = 2.1% at 21-MVA (6.0% at 60-MVA)Convert to T equivalentZ161 = ½ (9.7% +16.57%-6.0%) = 10.135% at 60 MVAZ46 = ½ (9.7% + 6.0% -16.57%) = -0.435% at 60 MVAZ13 = ½ (16.57%+6.0% -9.7%) = 6.435% at 60-MVA
PCC Includes TVA plus 161-kV portion of winding to 46/13-kV T pointPCC = 3.85% + 10.135% = 13.985% = 429-MVAsc
Estimated AF Swing = 2 x 4-MW = 8-MVA3 3Swing with 3 AF = x 8-MVA = 11.54-MVAsc for 3 units operating
46-kV Short Circuit Voltage Depression (SCVD) = 11.54/429 = 0.0269161-kV Short Circuit Voltage Depression (SCVD) = 11.54/1558 = 0.0074
46-kV PST Estimate = 0.0269 x KST = 0.0269 x 60 = 1.61
161-kV PST Estimate = 0.0074 x KST = 0.0074 x 60 = 0.44
79
Event #25 at 06/25/2007 08:10:30.067AVrms RMS and Waveform
Timeplot
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
A FDPst
06/12/2007 06/14/2007 06/16/2007 06/18/2007 06/20/2007 06/22/2007 06/24/2007 06/26/2007 06/28/2007
Event #1 at 05/23/2007 14:04:48.349AVrms RMS and Waveform
Timeplot
06/12/2007 06/14/2007 06/16/2007 06/18/2007 06/20/2007 06/22/2007 06/24/2007 06/26/2007 06/28/2007
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
A FDPst
161-kV PST (a phase)
46-kV PST (a phase)
161-kV Flicker0.44 per hand calc.
46-kV Flicker1.61 per hand calc.
PST Measurements of 46-kV and 161-kV Bus Confirm Hand Calculations - Target – PST Under 1.0
Moving to 161-kV Accomplishes This Objective
PST Measurements of 46-kV and 161-kV Bus Confirm Hand Calculations - Target – PST Under 1.0
Moving to 161-kV Accomplishes This ObjectivePST Measurements at 161-kV
PST Measurements at 46-kV - PCC
80
Option 1 – Add Transformer at SubstationUse Existing 13-kV Feed to Plant
Option 1 – Add Transformer at SubstationUse Existing 13-kV Feed to Plant
T Equivalent
+
161kVRMSLL /_0
AC1+
PI1
+
RL1+
RL2
+
RL3
2
3
1
161/46/13
YgYgD_np1
+
RL4
Arc Furnace
DEV1
Arc Furnace
DEV2
Arc Furnace
DEV3
1 2
161/13
DYg_1
Other Customers FedFrom 46-kV System
NewPCCAt161-kV Existing 13-kV LineDedicated 161:13-kV
Transformer at Sub
Remove PlantLoad FromExisting 3-windingTransformer
81
Move PCC Up to 161-kVOption 1 - Install Dedicated Transformer
Move PCC Up to 161-kVOption 1 - Install Dedicated Transformer
$1,742 Grand Total - New Transformer System
$124 Misc. cost not currently identified - 20% of cost (excluding transformer)
$123 $23 $100 Two-Step - 4.5 (4.0 effective) -MVAR Harmonic Filter1e
$20 $10 $10 Routing Existing 13-kV Wiring to New System 1d
$75 $25 $50 13-kV Distribution Breaker with relays1c
$400 $150 $250 161-kV SF-6 breaker w/ bay and relays1b
$1,000 $150 $850 New 16-MVA Transformer, oil containment, foundations, bus1a
TotalInstallEquip.
All cost below in $1000s
Move PCC up to 161-kV System at Substation1
Option
82
Option 2Build 161-kV Line to Plant Site and Add
Transformer at That Site
Option 2Build 161-kV Line to Plant Site and Add
Transformer at That Site
T Equivalent
+
161kVRMSLL /_0
AC1+
PI1
+
RL1+
RL2
+
RL3
2
3
1
161/46/13
YgYgD_np1
Arc Furnace
DEV1
Arc Furnace
DEV2
Arc Furnace
DEV3
1 2
161/13
DYg_1
+
PI2
NewPCCAt161-kV Dedicated 161:13-
kV Transformer at Plant
New 161-kV LineTo Plant Site
Other Customers FedFrom 46-kV System
Remove PlantLoad FromExisting 3-windingTransformer
83
Move PCC to 161-kV Option 2 - Install Dedicated 161-13-kv Substation at
Plant Site
Move PCC to 161-kV Option 2 - Install Dedicated 161-13-kv Substation at
Plant Site
$1,683 Grand Total - Used Transformer System
$2,183 Grand Total - New Transformer System
$210 Misc. cost not currently identified - 20% of cost (excluding transformer)
$123 $23 $100 Two-Step - 4.5 (4.0 effective) -MVAR Harmonic Filter2f
$75 $25 $50 13-kV Distribution Breaker at Plant with relays2e
$125 $25 $100 161-kV Circuit Switcher at Plant with relays 2d
$400 161-kV Feed to Plant (existing row - big unknown ??)2c
$325 $75 $250 161-kV SF-6 breaker w/ bay and relays2b
$425 $75 $350 Used 18-MVA Transformer, oil containment, foundations, bus2a
$925 $75 $850 New 16-MVA Transformer, oil containment, foundations, bus2a
TotalInstallEquip.
All cost below in $1000s
Move PCC Up to 161-kV System at Plant2
Option
84
Option 3 - Install Quick, Dynamic VAR Correction and Harmonic Filter System at Plant Site
Option 3 - Install Quick, Dynamic VAR Correction and Harmonic Filter System at Plant Site
T Equivalent
+
161kVRMSLL /_0
AC1+
PI1
+
RL1+
RL2
+
RL3
2
3
1
161/46/13
YgYgD_np1
+
RL4
Arc Furnace
DEV1
Arc Furnace
DEV2
Arc Furnace
DEV3
3x1x
1 2 SVC
_1
Other Customers FedFrom 46-kV System
Add Dynamic VarCorrection at PlantSite
No Transmission orDistribution SystemChanges Needed!
85
Fix Flicker at Plant 13-kV Bus Option 3 - Install Quick, Dynamic VAR Correction and
Harmonic Filter System at Plant Site
Fix Flicker at Plant 13-kV Bus Option 3 - Install Quick, Dynamic VAR Correction and
Harmonic Filter System at Plant Site
$1,370 Grand Total
$125 Misc. cost not currently identified - 10% of cost
$125 $25 $100 13-kV Switchgear Integrated Into Existing System3c
$145 $25 $120 Two Step - 6.6/6.3 (6.0 effective)-MVAR Harmonic Filter3b
$1,100 $100 $1,000 Install +10 /- 2-MVAR Var Compensator3a
TotalInstallEquip.
All cost below in $1000s
Install ABB Mincomp or S&C Purewave Dstatcom3
Option
86
Economic Summary:Installing Dynamic Var Compensation is Best Choice
Economic Summary:Installing Dynamic Var Compensation is Best Choice
2.9$1,370$479.4$415.0$31.6$32.8Option3
33.9$2,183$64.4$0$31.6$32.8Option2
27.0$1,742$64.4$0$31.6$32.8Option1
SimplePayback(years)
TotalCost
(1000s)
TotalSavings
(1000s)
ProductionProfitIncrease(1000s)
Electronic Equip.Savings(1000s)
Power FactorCorrectionSavings(1000s)
Option#
Option 1 – Transformer Isolation at Substation, filter at PlantOption 2 – Transformer Isolation at Plant, filter at PlantOption 3 – Install Filter/Dynamic VAR Compensation at Plant
87
Case 9
A Large Steel Mill Has an SVC, Why is it Creating More Flicker When On
Compared to When its Off?
Arc Furnace
DEV1
1 2
161/33
DY_1
+
10
R1
+0.804,2.3585Ohm
RL1
+
161kVRMSLL /_0
AC1+
0.285,4.004Ohm
RL2
IECFLickermeter
FLICKERMETER_PCC
1 2
33/0.7
DD_1
s3
Super_Voltmeter1
DEV2
PCC
88
Phase A Voltage(Max, Min, Avg)
Flicker SummaryPCC Monitor SiteWithout SVC/ FiltersPST(95) = 0.93
Base Case Without SVC System Operating2 Days
Base Case Without SVC System Operating2 Days
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
29 FriOct 2004
30 Sat 31 Sun
161PCC - Pst Afrom 10/29/2004 to 10/31/2004
EPRI/Electrotek PQView®
Pst A
Time
89
Phase A Voltage(Max, Min, Avg)
Flicker SummaryPCC Monitor SiteWithout SVC/ FiltersPST(95) = 1.22
Base Case With SVC System Operating2 Days
Base Case With SVC System Operating2 Days
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
26 TueOct 2004
27 Wed 28 Thu
161PCC - Pst Afrom 10/26/2004 to 10/28/2004
EPRI/Electrotek PQView®
Pst
A
Time
90
Flicker Reduced by Approximately 24% by Switching Off SVC/Filters
Flicker Reduced by Approximately 24% by Switching Off SVC/Filters
What is the reason for lower flicker levels with the SVC out of service?
Without SVC With SVC
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
29 FriOct 2004
30 Sat 31 Sun
161PCC - Pst Afrom 10/29/2004 to 10/31/2004
EPRI/Electrotek PQView®
Pst
A
Time
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
26 TueOct 2004
27 Wed 28 Thu
161PCC - Pst Afrom 10/26/2004 to 10/28/2004
EPRI/Electrotek PQView®
Pst
A
Time
PST (95) – 0.93 PST (95) – 1.22
91
Flicker SummaryPCC Monitor SiteWithout SVC/ Filters PST(95) = 1.86
Base Case With SVC System Operating -Weakened TVA System - 2 Days
Base Case With SVC System Operating -Weakened TVA System - 2 Days
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
9 SatFeb 2008
10 Sun 11 Mon
161PCC - Pst Afrom 02/09/2008 to 02/11/2008
EPRI/Electrotek PQView®
Pst
A
Time
Complaints Ramped Up During This Period
92
Comparison of Voltage Swings at PCC Both With and Without SVC Operation
Comparison of Voltage Swings at PCC Both With and Without SVC Operation
ControlsOvershoot –One PossibilityForFlicker Swing
No SVC
SVC
93
GE Flicker CurvesCopied From IEEE 519
GE Flicker CurvesCopied From IEEE 519
Voltage Swing Possible By TCR Overshoot = 1.1%
94
Case 10
A Large Steel Mill Has an SVC and DC Electric Arc Furnace, Here is The Way
Things Should Operate!
95
EAF Operation with Great SVC Control PerformanceEAF Operation with Great SVC Control Performance
92000
92500
93000
93500
94000
94500
95000
95500
96000
96500
97000
3 TueJun 2008
3AM 6AM 9AM 12PM 3PM 6PM 9PM 4 Wed
161PCC- V RMS Afrom 06/03/2008 to 06/04/2008
EPRI/Electrotek PQView®Time
Min[V RMS A] (V) Avg[V RMS A] (V) Max[V RMS A] (V)
0.05
0.10
0.15
0.20
0.25
0.30
0.35
3 TueJun 2008
3AM 6AM 9AM 12PM 3PM 6PM 9PM 4 Wed
161PCC- Pst Afrom 06/03/2008 to 06/04/2008
EPRI/Electrotek PQView®
Pst A
Time
-30000
-25000
-20000
-15000
-10000
-5000
0
5000
10000
15000
20000
25000
30000
3 TueJun 2008
3AM 6AM 9AM 12PM 3PM 6PM 9PM 4 Wed
161PCC- Q Fund Allfrom 06/03/2008 to 06/04/2008
EPRI/Electrotek PQView®Time
Min[Q Fund All] (kvar) Avg[Q Fund All] (kvar) Max[Q Fund All] (kvar)
PST
VOLTAGE
REACTIVEPOWER
96
Questions/Comments
If not, then lets eat!!