177
Polus Investments (Seychelles) Limited Shangri-La Resort at Long Island Seychelles First Interim Request for Extension of Time for Completion and Additional Payment Island Construction (Pty) Ltd

First Draft 013 June 08 - Final

Embed Size (px)

Citation preview

Page 1: First Draft 013 June 08 - Final

Polus Investments (Seychelles) Limited

Shangri-La Resort at Long IslandSeychelles

First Interim Request for Extension of Time for Completion and

Additional Payment

Island Construction (Pty) Ltd

June 2008

Page 2: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Table of Contents

page

1. Introduction........................................................................................................5

1.1. Background.................................................................................................51.2. Purpose of this Document.........................................................................61.3. Scope of this Document.............................................................................7

2. The Structure of the Contract...........................................................................8

2.1. The Contract Existing.................................................................................82.1.1. Lump Sum Contract Price vis-à-vis Scope of Works.............................82.1.2. Provisional Sums.................................................................................12

2.1.2.1. Tender Provisions.........................................................................122.1.2.2. Contract Provisions......................................................................132.1.2.3. Current Situation...........................................................................152.1.2.4. Conclusions..................................................................................16

2.2. Relevant Contract Provisions..................................................................172.2.1. Sub-clause 1.9 – Delayed Drawings or Instructions............................172.2.2. Sub-clause 3.3 – Instructions of the Project Manager.........................182.2.3. Sub-clause 4.7 – Setting Out...............................................................192.2.4. Sub-clause 4.12 – Unforeseeable Physical Conditions.......................192.2.5. Sub-clause 8.3 – Programme..............................................................202.2.6. Sub-clause 8.4 – Extension of Time for Completion............................222.2.7. Sub-clause 8.8 – Suspension of Works...............................................222.2.8. Sub-clause 8.9 – Consequences of Suspension.................................232.2.9. Sub-clause 12.1 – Works to be Measured...........................................232.2.10. Sub-clause 12.3 – Evaluation..........................................................242.2.11. Sub-clause 13.1 – Right to Vary......................................................252.2.12. Sub-clause 13.3 – Variation Procedure............................................262.2.13. Sub-clause 20.1 – Contractor’s Claims............................................27

2.3. Original Planning and Cash-flow.............................................................292.3.1. The Clause 8 Programme....................................................................292.3.2. Planned versus Actual Turnover..........................................................30

2.4. First Revised Programme of Works........................................................322.5. Second Revised Programme of Works...................................................322.6. Actual Progress........................................................................................34

3. Valuation of Variations....................................................................................35

3.1. Explanation of Heads of Claim................................................................353.2. Specific Heads of Claim...........................................................................353.3. Methods of Valuation of the Variations...................................................36

3.3.1. Use of Costs as Basis..........................................................................363.3.2. Addition for Profit.................................................................................363.3.3. Profit as Part of the Value of Variations...............................................36

3.3.3.1. Three Types of Variations............................................................363.3.3.2. Changes in Design of the Works..................................................37

page 2

Page 3: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

3.3.3.2.1. Technical Variations.................................................................373.3.3.2.2. Changes to Specified Sequence and Timing...........................38

3.3.3.3. Summary......................................................................................383.3.4. The Effects on Unvaried Work.............................................................393.3.5. For Uneconomic Working....................................................................39

3.3.5.1. Loss of Anticipated Income..........................................................403.3.5.2. Wasted Monthly Costs..................................................................403.3.5.3. Financing Wasted Monthly Costs.................................................41

3.3.6. Profit as Part of ‘Costs’........................................................................413.3.6.1. Authorities on the Basis of ‘Costs’................................................41

3.3.6.1.1. Powell-Smith’s ‘Some Building Contract Problems’.................423.3.6.1.2. Hudson and Minter v. WHTSO.................................................423.3.6.1.3. Hudson on the Scope of ‘Costs’...............................................433.3.6.1.4. The First Part of the Rule in Hadley v. Baxendale....................443.3.6.1.5. The Basic Measure of Damages..............................................45

3.3.6.2. Authorities on the Recovery of Profit............................................463.3.6.2.1. General Principle as to Claims.................................................463.3.6.2.2. Wraight v. PH&T (Holdings) Ltd...............................................463.3.6.2.3. Powell-Smith and Sims on Building Contract Claims...............47

3.3.6.3. Summary......................................................................................483.4. The Contractor’s Summary......................................................................48

4. Circumstances Giving Rise to Claim.............................................................49

4.1. Contractual Basis – Notification of Changes.........................................494.2. Late and Inaccurate Survey Data............................................................654.3. Late Receipt of Final Design Information...............................................664.4. Additional and Varied Work.....................................................................66

4.4.1. Excavation in Hard Rock.....................................................................664.4.1.1. Change in Sequence and Increased Cost....................................674.4.1.2. Increased Quantity.......................................................................67

4.4.2. Increased Quantity in Reinforced Concrete.........................................704.4.2.1. Villa Type A3 (Example)...............................................................704.4.2.2. Villa Type B2 (Example)...............................................................71

4.4.3. Suspension of Works...........................................................................714.4.4. Variations to Design.............................................................................72

4.5. Material Procurement Programme..........................................................724.6. Conclusion of Effects of Variations........................................................74

5. Time Analysis...................................................................................................75

5.1. Method of Analysis...................................................................................755.1.1. Mitigation by Contractor.......................................................................765.1.2. Time for Completion............................................................................765.1.3. Impact on Time - Analyses..................................................................775.1.4. The Events that Impacted Progress....................................................77

5.1.4.1. Event No 1 – Setting Out..............................................................795.1.4.2. Event No 2 – Unforeseen Ground Conditions..............................825.1.4.3. Event No 3 – Later Receipt of Design Information.......................915.1.4.4. Event No 4 – Increased Scope of Works....................................1015.1.4.5. Event No 5 – Partial Suspension of Works.................................1145.1.4.6. Event No 6 – Design Variations (Stainless Steel Items).............119

page 3

Page 4: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.2. Conclusion..............................................................................................121

6. Financial Analysis..........................................................................................122

6.1. Consequences........................................................................................1226.1.1. Direct Cost.........................................................................................1236.1.2. Indirect Cost.......................................................................................1236.1.3. Consequential Cost...........................................................................123

6.2. Costs in Extended Contract Period.......................................................1236.2.1. Nature of Loss and Expense.............................................................1236.2.2. Contractor’s Entitlement to Reimbursement......................................124

6.3. Finance Cost...........................................................................................1246.4. Conclusions............................................................................................125

7. Extension of Time Entitlement......................................................................126

8. Additional Payment........................................................................................127

8.1. Introduction.............................................................................................1278.2. Evaluation of the Financial Consequences..........................................127

8.2.1. Wasted Costs Arising from Delay and Disruption..............................1288.2.1.1. Staff and Labour.........................................................................1288.2.1.2. Equipment..................................................................................1298.2.1.3. Site and Head Office..................................................................1308.2.1.4. Summary of Wasted Costs.........................................................132

8.2.2. Additional Costs Arising from Acceleration........................................1328.2.3. Additional Costs in Extended Contract Period...................................1338.2.4. Other Costs........................................................................................134

8.2.4.1. Procurement of Permanent Materials.........................................1348.2.4.2. Temporary Materials including Equipment.................................135

8.2.5. Finance Costs....................................................................................1358.2.6. Grand Summary................................................................................136

9. Statement of Claim.........................................................................................138

10. Appendices.................................................................................................139

10.1. Wasted Costs.......................................................................................13910.1.1. Record of Resources – Staff and Labour.......................................13910.1.2. Record of Resources – Equipment................................................13910.1.3. Direct and Indirect Costs................................................................139

10.2. RFI and RFA.........................................................................................14010.3. Correspondence....................................................................................141

page 4

Page 5: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

1. Introduction

1.1. Background

A Contract for Building and Engineering Works Designed by the Employer was entered into on 27 April 2007 between the Polus Investments (Seychelles) Limited (hereinafter called “the Employer”) and Island Construction (PTY) Limited (hereinafter called “the Contractor”).

During the course of both the Employer’s design and the construction phases of the Contract to date, a number of events and factors have affected progress of both the design and construction processes. The Contractor’s view is that the delays were not his fault. Consequently, the Contractor believes he should be allowed an Extension of Time and Additional Payment to complete the work which is the subject of the Contract. He seeks reimbursement of his additional costs incurred otherwise not allowed in his tendered rates and prices.

For the Contractor, this is an important matter. He needs the Project Manager’s agreement to an extension of time requested and to an interim determination of his additional costs, in order to allow earliest compensation and to off-set increasing finance costs.

The Contractor’s further view is that Site conditions are in variance to that anticipated as the positions of buildings and the significant increase in hard rock excavation. In addition the Project Manager suspended progress of the Works and he has received much of the design phase late. This design when received shows a significant increase in the quantities of work to be performed. These facts entitle him to an extension of time. It would also entitle him to additional payment for the delay and disruption caused to date.

As will be seen from the sections following this introduction, the Employer and/or the Project Manager also required the Contractor to carry out Construction work to a varied timing and sequence, as opposed to that anticipated by his programme of works. This was as a result of unforeseen ground conditions.

The issues became clear from the very start of the construction process. Once the setting out delays was over-come the Contractor encountered hard rock in excavation at almost all building locations. This unforeseen circumstance caused a varied order of construction to that planned together with numerous late instructions as design evolved.

page 5

Page 6: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

All of these factors have caused the Contractor to have to carry out work in a disrupted and disordered manner, and over a longer period, than he contracted to do. The Employer’s/the Project Manager’s errors have caused the Contractor to incur significant higher costs of construction and in addition, significant costs arising from delay and disruption.

As will be seen from the following sections of this claim, almost all areas of the site fell behind programme. In addition, it is of worthy note that the Contract Price awarded was inclusive of 30% allowance for Provisional Sums. That means the Project Manager must introduce these works as a Variation to the Contract. The design and construction work are both now a long way behind programme.

The Contractor has given notice that he will have to make claims to achieve the relief and payment to which he believes he is entitled.

1.2. Purpose of this Document

During the course of the work, the Contractor has suffered delay and disruption through a number of causes. The consequences of these causes are the contractual responsibility of the Employer.

The Contractor has made a number of notice submissions to the Project Manager with regard to these causes. The Contractor has thereafter, impacted the programme of works to reflect the effect of these events and changed circumstances.

We acknowledge receipt of the Employer’s letter dated 19 May 2008 and to the Project Managers letters dated 2, 9 and 12 May 2008 referenced E19-02.05.08, E20-09.05.08 and E21-12.05.08 respectively.

In summary we disagree entirely with all interpretations, conclusions and what appears to be a determination made prior to receipt of the Contractor’s detailed particulars. In such a situation you are making a prediction on changed events and circumstances and their consequences without benefit of the position one Party to the Contract. This is contrary to the duties and obligations stated at sub-clause 3.1 and 3.5 of the General Conditions of Contract.

page 6

Page 7: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

In our letter of 14 April 2008 we indicated a time to complete the detailed particulars. However, with consideration to your position now outlined in these letters, we require more time to complete this exercise. As such, we will make our full and detailed submission of claims on Monday 9 June 2008.

The purpose of this document is, therefore, to provide the Project Manager with an initial analysis so that he may make an evaluation of the additional payment based on:

The delays and disruption experienced to May 2008 and arising additional costs in the form of Wasted Costs, and

The extensions time for completion requested by the Contractor in respect of the cause’s notified and consequent recovery of arising prolongation costs.

for which the Employer is contractually liable.

1.3. Scope of this Document

This document describes the:

1. Causes of delay and disruption to the Works;

2. Impact of these causes on contract completion;

3. Contractual position regarding the Contractor’s entitlement to extension of time and additional payment, and

4. Consequences of delay and disruption in terms of the additional time and additional payment due to the Contractor.

The scope of this claim submission is limited to known events to May 2008. As many of the changed events and circumstances that have given rise to extensions of time and additional cost continue, the Contractor will be updating this detailed submission.

page 7

Page 8: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2. The Structure of the Contract

2.1. The Contract Existing

2.1.1.Lump Sum Contract Price vis-à-vis Scope of Works

The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0:

“As per our agreement the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”

In practice this is inoperable and this soon became evident at early stages of the Contract

In a letter dated 24 October 2007 the Contractor gave notice:

Two important matters require your confirmation:

First, we draw your attention to the changes and variations that are regularly being instructed as works proceed. Although they are acceptable to the Contractor we also wish to record that these changes and variations are made prior to reaching agreement on the price. This is as you are aware, contrary to the terms and conditions of the Contract. In the circumstances, because of this continuing departure from the Contract, it is understood that the price and consequent additional cost will be added to the Contract Price.

Secondly, we have reviewed the estimated quantities in the Bills of Quantity against actual work depicted on the drawings issued for construction. It is apparent significant disparity exists between the measure and provision made in the Contract. As a result, either the scope must be adjusted in order to retain the Contract Price or, we require your agreement to perform these works at the price contained in the contract which additional cost will be added to the Contract Price. If you require detail of the variations discussed here, please have your quantity surveyor consult with ours as quickly as possible.

In conclusion, we require the Employer’s agreement to payment of these variations as a matter of urgency.

page 8

Page 9: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

In a further letter dated 23 November 2007 the Contractor recorded:

This Contract contains specific conditions in regard to Variations that would increase or decrease the Lump Sum Contract Price. We wrote on this matter on 24 October 2007 to which a reply has not been received.

In particular it states that “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”

It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”

Essentially this means a new or varied price or rate for all Variations must first receive agreement of the Employer together with, if relevant, a revised Contract Price prior to the issue of an instruction because they:

Introduce a design change;

Introduce additional works, and

Introduce an increase in the scope of work beyond the quantity stated in the Bills of Quantities.

As such, the purpose of this letter is to record several and significant Variations introduced since commencement where value and consequent Contract Price adjustment are not agreed despite the issue of an instruction. Consequently, we wish to schedule a “Variation Meeting” to discuss and agree a procedure that will ensure such increases in value are properly reported, valued and paid.

At this juncture we have identified the following Claims and Variations which have caused the Contract Price to increase:

1. Additional costs associated with delay and disruption not the responsibility of the Contractor;

2. Additional costs associated with the Project Manager’s instruction to accelerate the Works by working additional hours;

3. Additional costs arising from delays caused by late design information;

page 9

Page 10: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

4. Additional costs in excavation of hard rock and removal to spoil;

5. Additional costs that arise due to the construction of “mock-up” villas in a sequence that is in variance to original planning;

6. The increase in size of structural timber to roof structures where new rates need to be agreed prior to procurement;

7. Door timber type and finishing specifications have changed and new rates need to be agreed prior to procurement;

8. Window timber type and finishing specifications have changed and new rates need to be agreed prior to procurement;

9. Ironmongery specifications have changed and new rates need to be agreed prior to procurement;

10. Structural galvanised steel plates have changed to stainless steel and new rates need to be agreed prior to procurement.

11. Increased costs arising from additional site work described in Section B of the Principles of Measurement for Works of Construction.

This meeting must also acknowledge and agree the additional work being executed is in accordance with instructions and design details issued and that they are beyond the scope of the lump sum Contract Price. This presently includes:

Excavation in common material;

Excavation in rock;

Concrete in foundations to suit varied ground conditions; and

Reinforced concrete in columns, ring beams and suspended slabs.

In addition, all lump sums for works for which detailed bills of quantities do not exist need to be prepared and valued using detailed design drawings received in September 2007.

page 10

Page 11: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Please confirm as soon as possible when a meeting can be convened as these Claims and Variations must be recorded and valued as a matter of priority.

The last letter with regards Variations and increased scope of Works was dated 6 December 2007 and recorded:

We acknowledge receipt of your letter dated 4 December 2007 referenced E-09-04-12-07 and wish to confirm our position by the following extract from the Contract:

The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”

It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”

The Contract Agreement dated 27 April 2007 lists the documents forming the Agreement and the Letter of Acceptance takes priority over the Conditions of Contract.

Consequently, your reference to sub-clause 12.3 and 13.1 of the Conditions of Contract, although interesting, is not relevant in the introduction of Variations on this project, particularly as sub-clause 3.1 has been amended by the quoted specific conditions above.

We would point out that although the amendment is impractical it is a significant revision to both Clause 12 and 13 of the Conditions of Contract. In practise it means that no Variation arising from additional work or by design change can commence prior to receiving the agreement of the Employer.

In conclusion, the purpose of our letter dated 23 November 2007 on this subject matter was to bring these special circumstances to your attention.

A further existing condition of the Contract relates to Provisional Sums and their inclusion in the Contract as Variations.

page 11

Page 12: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2.1.2.Provisional Sums

Clause 13 empowers the Project Manager to issue instructions to the Contractor directing him how provisional sums are to be expended. Provisional sums are included in this Contract where the precise cost or extent of work is not known at time of tender. The purpose is to have the sum of money to cover the cost. When the instruction is issued, the sum inserted is omitted and the variation is then valued in accordance with the principles of Clause 12 and 13.

The “Building Contract Dictionary” written by Vincent Powell-Smith and David Chappell, explains the term provisional sum:

A term used to denote a sum of money included in the contract by the employer, normally as an amount in the bills of quantities. It is provided to cover the cost of something which cannot be foreseen or detailed accurately at the time tenders are invited. (Contractor’s profit is not added to this sum.) It may be expended as the architect instructs…

It is important that the Contractor receives proper valuation of variations measured in accordance with the provisions stated for Provisional Sums. In particular, all on-costs and overheads described and allowed in the existing Bill 1 will be equally relevant to any measured Variations valued under Clause 12 and 13 of the Contract conditions.

It is of worthy note that a very large percentage of the Contract Works and therefore, the Contract Price, had not been sufficiently designed at tender stage. The consequences of this situation will allow the Contractor to measure and value these works as an addition, within the provisions of Clause 12 and 13. As such, the value of items listed in Bill no 1 must be increased to include works falling under Variations. This would then allow the Contractor to be paid for the work performed.

2.1.2.1. Tender Provisions

At tender stage the value shown for Measured Work was (Bills 1 to 34 inclusive) SCR20,677,661.15, and the value of the Preliminaries (Bill 1) has been derived from this figure.

However, a value for Preliminary items is clearly not included as part of the Provisional Sum amount declared by the Employer at tender stage. The value of Provisional Sums included, amounts to SCR22,539,454.00, a figure which is greater than the value of the original Measured Works forming the Contract.

page 12

Page 13: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2.1.2.2. Contract Provisions

The contract provides as follows:

Under Clause 13.5, Provisional Sums; Each provisional sum shall only be used in whole or in part in accordance with the Project Managers instruction and that the contract sum shall be adjusted accordingly. It further provides that when the Project Manager instructs work to be provided by the contractor such work shall be valued under Clause 13.3 (Variation Procedure).

Under Clause 13.3, Variation Procedure: Each variation will be valued in accordance with Clause 12. This has been amended in the Particular Conditions where the measure and value is made in accordance with the RICS Principles of Measurement for Works of Construction. Consequently, the full wording of Clause 12 is:

Under Clause 12.3, Evaluation: a new rate or price shall be appropriate for an Item of Work if:

(a)

the measured quantity of the item is changed by more than 10% from the quantity of this item in the Bill of Quantities or other Schedule,

this change in quantity multiplied by such specified rate for this item exceeds 0.01% of the Accepted Contract Amount,

this change in quantity directly changes the Cost per unit quantity of this item by more than 1%, and

this item is not specified in the Contract as a “fixed rate item";

or (b)

i. the work is instructed under Clause 13 [Variations and Adjustments],

ii. no rate or price is specified in the Contract for this item, and

iii. no specified rate or price is appropriate because the item of work is not of similar

page 13

Page 14: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

character, or is not executed under similar conditions, as any item in the Contract.

Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.

With regard to which part of sub-clause 12.3 above is relevant, it is obvious the measured quantity of the Works originally included as a value under Provisional Sums complies with those conditions stated in paragraph (a). As such, all rates and prices from which the varied works are valued to date, for those Works not forming part of the original Measured Works, must be appropriately adjusted.

The procedure in the Contract for the valuation of a variation is described under sub-clause 13.3 and states:

If the Project Manager requests a proposal, prior to instructing a Variation, the Contractor shall respond in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the case) or by submitting:

a. a description of the proposed work to be performed and a programme for its execution,

b. the Contractor’s proposal for any necessary modifications to the programme according to Sub-Clause 8.3 [Programme] and to the Time for Completion, and

c. the Contractor’s proposal for evaluation of the Variation.

The Project Manager shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value Engineering] or otherwise), respond with approval, disapproval or comments. The Contractor shall not delay any work whilst awaiting a response.

Each instruction to execute a Variation, with any requirements for the recording of Costs, shall be issued by the Project Manager to the Contractor, who shall acknowledge receipt.

page 14

Page 15: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Each Variation shall be evaluated in accordance with Clause 12 [Measurement and Evaluation], unless the Project Manager instructs or approves otherwise in accordance with this Clause.

The procedure adopted by the Project Manager would appear to be a submission of a “Drawing for Construction”. Therefore, the three stage process described and allowed above has not been observed. Nonetheless, it is apparent as a consequence of these variations, that the value of the Works flowing from the Provisional Sums has not been determined at time of tender.

2.1.2.3. Current Situation

The Preliminaries had originally been calculated based on the value of Measured Works identified at tender. A breakdown of the Preliminaries shown below demonstrates that though certain items and their related cost therein, is considered fixed, the majority are of a variable nature. Consequently, the Preliminaries and their value are directly proportional to the value of Measured Works to be executed.

Item Nature of Cost Fixed Variable

1 Insurance 250,000.002 Foreign Staff, Labour Repatriation 450,000.003 Facilities for Staff and Labour 170,000.004 Measures against Insect and Pect Nuisance 60,000.005 Supply of Foodstuffs 660,000.006 Supply of Water 80,318.007 Shop Drawings 10,000.008 As-Built Documents 5,600.009 Temporary Site Office for Employers Consultants 65,250.00

10 Site Signboard 3,275.0011 Access to Site 35,000.0012 Site to be Tidy 12,727.0013 Co-ordination 14,727.0014 Site Records 3,275.0015 Site Records 29,913.0016 Safety Procedures 5,700.0017 Security at Site 13,426.0018 Contractors Site Operations 7,485.0019 Site Radio Communication 11,725.0020 Environmental Impact Assessment 5,000.0021 Taking Delivery from NS 50,000.0022 Contractors Temporary Accommodation 35,000.0023 Superintendence 15,000.0024 Transport of People 125,475.0025 Contractors Equipment 365,000.0026 Scaffolding 105,000.00

Total 85,250.00 2,503,646.00

page 15

Page 16: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

It is important to define the difference between a “fixed” and a “variable” item;

Fixed items are to cover elements of a cost of work or their value, which are not to be considered as proportional to the quantities of the Permanent Works; whereas

Variable items are to cover for elements of a cost of work which are considered proportional to the quantities of Permanent Work performed.

The distinction is clear and as example, Shop Drawings and Site Records is a typical Variable item which scope will increase on introduction of the Variations brought by expenditure of the provisional sums.

These variable preliminaries items amount to about 12% of the value of Measured Works. As a result the current situation is:

The original value of known Measured Works has varied in quantity and therefore, value, considerably;

The instructed varied works (which is the value provision at tender and known as “Provisional Sums”) has or will considerably increase the value of Measured Works; and

As a result of a) and b) above, there is a significant under-recovery of costs on measured works that should naturally flow from items contained in the Preliminary Bill.

2.1.2.4. Conclusions

The table below shows the various value elements making up the Contract Price. The known scope of work had been priced and valued at SR20,677,661.15.

However, the value of Preliminaries is SR2,537,894.00 of which SR2,503,646.00 is the value of Variable Costs. Therefore, SR2,503,646.00 as a percentage of the known measured works at time of tender was 12%. It is this percentage, 12% that must be added to the value of Variations introduced under Clause 12 and 13.

This means the value adjustment on the original Provisional Sum amount of SCR22,539,454.00 equates to SCR2,729,071.00 or such other sum valued in accordance with the Contract. This sum is to be paid in addition to the Contract Price.

page 16

Page 17: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

This signifies that all the Works measured to date are under-valued. Accordingly, the Conditions of the Contract dictate the following actions:

Notwithstanding delay and disruption costs caused by events notified to the Project Manager, further additional costs must be captured because:

The Contractor has entitlement to a varied rate for all unvaried Works,

The Contractor has entitlement to new rates and prices for all Works introduced as a Variation in accordance with sub-clause 12.3, and

the contractor has entitlement to the addition of 12% to all his measured work to cover his Preliminary and general items.

Consequently, the Contractor intends to add 12% to the value of measured works arising from Instructed Variations. The Contractor asks the Project Manager to certify payment applications in accordance with the Contract Conditions and for the reasons stated in the foregoing.

2.2. Relevant Contract Provisions

2.2.1.Sub-clause 1.9 – Delayed Drawings or Instructions

The Contractor shall give notice to the Project Manager whenever the works are likely to be delayed or disrupted if any necessary drawing or instruction is not issued to the Contractor within a particular time, which shall be reasonable. The notice shall include details of the necessary drawing or instruction, details of why and by when it should be issued, and details of the nature and amount of the delay or disruption likely to be suffered if it is late.

If the Contractor suffers delay and/or incurs Cost as a result of a failure of the Project Manager to issue the notified drawing or instruction within a time which is reasonable and is specified in the notice with supporting details, the Contractor shall give a further notice to the Project Manager and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:

page 17

Page 18: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(a) payment of any such Cost plus profit, which shall be included in the Contract Price.

After receiving this further notice, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

However, if and to the extent that the Project Manager's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.

2.2.2.Sub-clause 3.3 – Instructions of the Project Manager

The Project Manager may issue to the Contractor (at any time) instructions and additional or modified Drawings which may be necessary for the execution of the Works and the remedying of any defects, all in accordance with the Contract. The Contractor shall only take instructions from the Project Manager, or from an assistant to whom the appropriate authority has been delegated under this Clause. If an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.

The Contractor shall comply with the instructions given by the Project Manager or delegated assistant, on any matter related to the Contract. Whenever practicable, their instructions shall be given in writing. If the Project Manager or a delegated assistant:

(a) gives an oral instruction,

(b) receives a written confirmation of the instruction, from (or on behalf of) the Contractor, within two working days after giving the instruction, and

(c) does not reply by issuing a written rejection and/or instruction within two working days after receiving the confirmation,

page 18

Page 19: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

then the confirmation shall constitute the written instruction of the Project Manager or delegated assistant (as the case may be).

2.2.3.Sub-clause 4.7 – Setting Out

The Contractor shall set out the Works in relation to original points, lines and levels of reference specified in the Contract or notified by the Project Manager. The Contractor shall be responsible for the correct positioning of all parts of the Works, and shall rectify any error in the positions, levels, dimensions or alignment of the Works.

The Employer shall be responsible for any errors in these specified or notified items of reference, but the Contractor shall use reasonable efforts to verify their accuracy before they are used.

If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated by an error in these items of reference, and an experienced contractor could not reasonably have discovered such error and avoided this delay and/or Cost, the Contractor shall give notice to the Project Manager and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed,under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost plus profit, which shall be included in the Contract Price.

After receiving this notice, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent the error could not reasonably have been discovered, and (ii) the matters described in sub-paragraphs (a) and (b) above related to this extent.

2.2.4.Sub-clause 4.12 – Unforeseeable Physical Conditions

In this sub-clause, “physical conditions” means natural physical conditions and man-made and other physical obstructions and pollutants, which the Contractor

page 19

Page 20: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

encounters at the Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic conditions.

If the Contractor encounters adverse physical conditions which he considers to have Unforeseeable, the Contractor shall give notice to the Project Manager as soon as practicable.

This notice shall describe the physical conditions, so that they can be inspected by the Project Manager, and shall set out the reasons why the Contractor considers them to be Unforeseeable. The Contractor shall continue executing the Works, using such proper and reasonable measures as are appropriate for the physical conditions, and shall comply with any instructions which the Project Manager may give. If an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.

If and to the extent that the Contractor encounters physical conditions which are Unforeseeable, gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost, which shall be included in the Contract Price.

After receiving such notice and inspecting and/or investigating these physical conditions, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent these physical conditions were Unforeseeable, and (ii) the matters described in sub-paragraphs (a) and (b) above related to this extent.

2.2.5.Sub-clause 8.3 – Programme

The Contractor shall submit a detailed time programme to the Project Manager within 28 days after receiving the notice under Sub-Clause 8.1 [Commencement of Works]. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with

page 20

Page 21: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

actual progress or with the Contractor's obligations. Each programme shall include:

(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each stage of design (if any), Contractor's Documents, procurement, manufacture of Plant, delivery to Site, construction, erection and testing,

(b) each of these stages for work by each nominated Subcontractor (as defined in Clause 5 [Nominated Subcontractors]

(c) the sequence and timing of inspections and tests specified in the Contract, and

(d) a supporting report which includes:

(i) a general description of the methods which the Contractor intends to adopt, and of the major stages, in the execution of the Works, and

(ii) details showing the Contractor's reasonable estimate of the number of each class of Contractor's Personnel and of each type of Contractor's Equipment, required on the Site for each major stage.

Unless the Project Manager, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Employer's Personnel shall be entitled to rely upon the programme when planning their activities.

The Contractor shall promptly give notice to the Project Manager of specific probable future events or circumstances which may adversely affect the work, increase the Contract Price or delay the execution of the Works. The Project Manager may require the Contractor to submit an estimate of the anticipated effect of the future event or circumstances, and/or a proposal under Sub-Clause 13.3 [Variation Procedure].

If, at any time, the Project Manager gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a revised programme to the Project Manager in accordance with this Sub-Clause.

page 21

Page 22: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2.2.6.Sub-clause 8.4 – Extension of Time for Completion

The Contractor shall be entitled subject to Sub-clause 20.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking-Over of the Works and Sections] is or will be delayed by any of the following causes:

(a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]) or other substantial change in the quantity of an item of work included in the Contract,

(b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions,

(c) exceptionally adverse climatic conditions,

(d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions, or

(e) any delay, impediment or prevention caused by or attributable to the Employer, the Employer's Personnel, or the Employer's other contractors.

If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Project Manager in accordance with Sub-Clause 20.1 [Contractor's Claims]. When determining each extension of time under Sub-Clause 20.1, the Project Manager shall review previous determinations and may increase, but shall not decrease, the total extension of time.

2.2.7.Sub-clause 8.8 – Suspension of Works

The Engineer may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store andsecure such part or the Works against any deterioration, loss or damage.

The Engineer may also notify the cause for the suspension. If and to the extent that the cause is notified

page 22

Page 23: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

and is the responsibility of the Contractor, the following Sub-Clauses 8.9, 8.10 and 8.11 shall not apply.

2.2.8.Sub-clause 8.9 – Consequences of Suspension

If the Contractor suffers delay and/or incurs Cost from complying with the Engineer’s instructions under Sub-Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost, which shall be included in the Contract Price.

After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor’s faulty design, workmanship or materials, or of the Contractor’s failure to protect, store or secure in accordance with Sub-Clause 8.8 [Suspension of Work].

2.2.9.Sub-clause 12.1 – Works to be Measured

The Works shall be measured, and valued for payment, in accordance with this Clause.

Whenever the Project Manager requires any part of the Works to be measured, reasonable notice shall be given to the Contractor's Representative, who shall:

(a) promptly either attend or send another qualified representative to assist the Project Manager in making the measurement, and

(b) supply any particulars requested by the Project Manager.

page 23

Page 24: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

If the Contractor fails to attend or send a representative, the measurement made by (or on behalf of) the Project Manager shall be accepted as accurate.

Except as otherwise stated in the Contract, wherever any Permanent Works are to be measured from records, these shall be prepared by the Project Manager. The Contractor shall, as and when requested, attend to examine and agree the records with the Project Manager, and shall sign the same when agreed. If the Contractor does not attend, the records shall be accepted as accurate.

If the Contractor examines and disagrees the records, and/or does not sign them as agreed, then the Contractor shall give notice to the Project Manager of the respects in which the records are asserted to be inaccurate. After receiving this notice, the Project Manager shall review the records and either confirm or vary them. If the Contractor does not so give notice to the Project Manager within 14 days after being requested to examine the records, they shall be accepted as accurate.

2.2.10. Sub-clause 12.3 – Evaluation

Except as otherwise stated in the Contract, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine the Contract Price by evaluating each item of work, applying the measurement agreed or determined in accordance with the above Sub-Clauses 12.1 and 12.2 and the appropriate rate or price for the item.

For each item of work, the appropriate rate or price for the item shall be the rate or price specified for such item in the Contract or, if there is no such item, specified for similar work.

For each item of work included in the Bill of Quantities for which no rate or price was specified shall be considered as included in other rates and prices in the Bill of Quantities and will not be paid for separately. However, a new rate or price shall be appropriate for an item of work if:

(a) (i) the measured quantity of the item is changed by more than 25% from the quantity of this item in the Bill of Quantities or other Schedule,

page 24

Page 25: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

(ii) this change in quantity multiplied by such specified rate for this item exceeds 0.25% of the Accepted Contract Amount,

(iii) this change in quantity directly changes the Cost per unit quantity of this item by more than 1 %, and

(iv) this item is not specified in the Contract as a "fixed rate item";

Or

(b)(i) the work is instructed under Clause 13 [Variations and Adjustments],

(ii) no rate or price is specified in the Contract for this item, and

(iii) no specified rate or price is appropriate because the item of work is not of similar character, or is not executed under similar conditions, as any item in the Contract.

Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.

Until such time as an appropriate rate or price is agreed or determined, the Project Manager shall determine a provisional rate or price for the purposes of Interim Payment Certificates.

2.2.11. Sub-clause 13.1 – Right to Vary

Variations may be initiated by the Project Manager at any time prior to the issuing the Taking-Over Certificate for the Works, either by an instruction or by a request for the Contractor to submit a proposal.

Contractor shall execute and be bound by each Variation, unless the Contractor ptly gives notice to the Project Manager stating (with supporting particulars) that the Contractor cannot readily obtain the Goods required for the Variation. Upon receiving notice, the Project Manager shall cancel, confirm or vary the instruction.

page 25

Page 26: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Each Variation may include:

(a) changes to the quantities of any item of work included in the Contract (however, such changes do not necessarily constitute a Variation),

(b) changes to the quality and other characteristics of any item of work,

(c) changes to the levels, positions and/or dimensions of any part of the Works,

(d) omission of any work unless it is to be carried out by others,

(e) any additional work, Plant, Materials or services necessary for the Permanent Works, including any associated Tests on Completion, boreholes and other testing and exploratory work, or

(f) changes to the sequence or timing of the execution of the Works.

The Contractor shall not make any alteration and/or modification of the Permanent Works, unless and until the Project Manager instructs or approves a Variation.

2.2.12. Sub-clause 13.3 – Variation Procedure

If the Project Manager requests a proposal, prior to instructing a Variation, the Contractor shall respond in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the case) or by submitting:

(a) a description of the proposed work to be performed and a programme for its execution,

(b) he Contractor's proposal for any necessary modifications to the programme according to Sub-Clause 8.3 [Programme] and to the Time for Completion, and

(c) the Contractor's proposal for evaluation of the Variation.

The Project Manager shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value Engineering] or otherwise), respond with approval,

page 26

Page 27: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

disapproval or comments. The Contractor shall not delay any work whilst awaiting a response.

Each instruction to execute a Variation, with any requirements for the recording of Costs, shall be issued by the Project Manager to the Contractor, who shall acknowledge receipt.

Each Variation shall be evaluated in accordance with Clause 12 [Measurement and Evaluation], unless the Project Manager instructs or approves otherwise in accordance with this Clause.

2.2.13. Sub-clause 20.1 – Contractor’s Claims

If the Contractor considers himself to be entitled to any extension of time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.

If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply.

The Contractor shall also submit any other notices which are required by the Contract, and supporting particulars for the claim, all as relevant to such event or circumstance.

The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Project Manager. Without admitting the Employer's liability, the Project Manager may, after receiving any notice under this Sub-Clause, monitor the record-keeping and/or instruct the Contractor to keep further contemporary records. The Contractor shall permit the Project Manager to inspect all these records, and shall (if instructed) submit copies to the Project Manager.

page 27

Page 28: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Project Manager, the Contractor shall send to the Project Manager a fully detailed claim which includes full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed. If the event or circumstance giving rise to the claim has a continuing effect:

(a) this fully detailed claim shall be considered as interim;

(b) the Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Project Manager may reasonably require; and

(c) the Contractor shall send a final claim within 28 days after the end of the effects resulting from the event or circumstance, or within such other period as may be proposed by the Contractor and approved by the Project Manager.

Within 42 days after receiving a claim or any further particulars supporting a previous claim, or within such other period as may be proposed by the Project Manager and approved by the Contractor, the Project Manager shall respond with approval, or with disapproval and detailed comments. He may also request any necessary further particulars, but shall nevertheless give his response on the principles of the claim within such time.

Each Payment Certificate shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate.

The Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the extension (if any) of the Time for Completion (before or after its expiry) in accordance with Sub-Clause 8.4 [Extension of Time for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the Contract.

page 28

Page 29: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply to a claim. If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub-Clause.

2.3. Original Planning and Cash-flow

2.3.1.The Clause 8 Programme

The programme of works that appears below is summary task format was issued and approved for construction in XX 2007.

This programme of works considers the original scope of works depicted in the bills of quantities, including time provision for provisional sums. The provisional sum value included in the Contract allowed for inclusion by Variation all works not defined at time of tender. The Contractor’s original cash-flow was produced using this data.

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

1614 B223 Villas ( 7 nos)

1965 B4 Villa (2 nos.)

2056 Retail 1( subject to receipt of GFW drawings)

2094 Retail 2( subject to receipt of GFW drawings)

2132 Retail 3( subject to receipt of GFW drawings)

2170 Seafood resort( subject to receipt of GFW drawings)

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2664 B223 Villas ( 3 nos)

2808 B4 Standard Villas ( 2 nos)

2899 BC311 Executive Villa

3115 P3 Presidential suites ( 3 nos)

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct2007 2008

page 29

Page 30: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2.3.2.Planned versus Actual Turnover

The chart below provides a comparison between planned cash-flow, based on the programme of works, and actual income.

It can be seen the period through to XX, the first X-months of the construction programme, both planned and actual cash-flow remain reasonably constant. This is to be expected.

However, thereafter the gap widens because:

Excavations took longer because of hard rock;

Sub-structure work took longer due to greater scope of work;

Work slowed down waiting information and detailed design, and

Works were suspended

-5,000,000.00

0.00

5,000,000.00

10,000,000.00

15,000,000.00

20,000,000.00

25,000,000.00

30,000,000.00

Feb-07

Mar-07

Apr-07

May-07

Jun-07

Jul-07

Aug-07

Sep-07

Oct-07

Nov-07

Dec-07

Jan-08

Feb-08

Mar-08

Apr-08

May-08

PlanCumm ActualCumm

The following table provides the value of payment applications certified to end of May 2008.

page 30

Page 31: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month Planned PlanCumm Actual ActualCummFeb-07 3,100,000.00 3,100,000.00 0.00 0.00Mar-07 601,658.62 3,701,658.62 0.00 0.00Apr-07 1,352,295.74 5,053,954.37 0.00 0.00

May-07 1,852,720.48 6,906,674.85 3,100,000.00 3,100,000.00Jun-07 2,236,090.71 9,142,765.56 0.00 3,100,000.00Jul-07 2,684,335.78 11,827,101.34 682,032.85 3,782,032.85

Aug-07 2,189,910.64 14,017,011.97 351,989.15 4,134,022.00Sep-07 2,236,090.71 16,253,102.68 145,803.63 4,279,825.63Oct-07 2,258,038.74 18,511,141.42 357,556.62 4,637,382.25Nov-07 2,258,038.74 20,769,180.15 478,924.03 5,116,306.28Dec-07 1,754,288.50 22,523,468.65 0.00 5,116,306.28Jan-08 1,289,372.84 23,812,841.49 0.00 5,116,306.28Feb-08 1,040,280.70 24,853,122.19 274,355.16 5,390,661.44Mar-08 500,424.74 25,353,546.93 1,086,667.96 6,477,329.40Apr-08 2,575,212.46 27,928,759.39 0.00 6,477,329.40

May-08 0.00 27,928,759.39 0.00 6,477,329.40

It can be seen in the cumulative column how the gap widens as of almost the outset of the contract and has increased progressively in the period to date, May 2008. It is also of worthy note the “flatness” of the line showing cumulative income which results from:

A reduced income caused by the delays notified;

The fixed nature of the Advance repayment;

The value retained in retention.

The Contractor notified the financial imbalance being caused by the Advance repayment in his letters dated 19 November 2007:

Please refer to the Cash Flow Forecast dated 10 February 2007 included in the Contract Document Volume 1. As you are aware, this cash flow was preliminary and assumed payment of the Advance would occur in February 2007.

However, as payment of the Advance is the trigger to commencement of repayment, it is now necessary to amend this preliminary cash flow to reflect the actual date of receipt, which we record, was in May 2007.

Accordingly, please find attached the amended Cash Flow forecast adjusted to reflect the month the Advance was received and consequent 10-month repayment drawn-down against Interim Payments.

A further notice was issued on 21 November 2007:

Please refer to the amended Cash Flow Forecast submitted under cover of letter dated 19 November 2007.

page 31

Page 32: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

As you are aware, this cash flow was preliminary and assumed repayment of the Advance against projected income derived from the original programme of works.

However, the progress of works has been delayed and disrupted for reasons provided in separate notifications and as a result, income is significantly lower in the period to date.

Accordingly, please find attached an amended Cash Flow forecast adjusted to reflect a 15-month repayment drawn-down against Interim Payments consequent to the extended contract period shown on the revised programme of works.

2.4. First Revised Programme of Works

The Programme of Works above was issued under cover of letter dated 19 November 2007 in accordance with Clause 8 of the Contract Conditions.

In accordance with your request please find attached our revised programme reflecting actual progress achieved at 6 November 2007. This programme of works takes consideration of events and changed circumstances since commencement that caused original planned timing and sequence to vary.

Unless notice is received stating the extent to which it does not comply with the Contract, we shall proceed in accordance with this programme and will rely upon this programme when planning our activities.

Therefore, the Contractor’s timing, sequence are clearly explained in support of this programme. This programme of works indicated a revised completion date.

2.5. Second Revised Programme of Works

At the request of the Project Manager a second revised programme of works was issued on 14 March 2008.

In accordance with your recent request in the weekly progress meetings, please find attached revised programme of works for your consent.

page 32

Page 33: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The revised programme takes into consideration the various events and changed circumstances since commencement up to 29 February 2008.

These events and changed circumstances, as separately notified to you and further illustrated in our situation report dated 29 February 2009, have caused the original planned timing and sequence of works to vary. They include the following;

Unforeseen hard rock excavation including spoiling;

Suspension of works, except for the mock up villas, for two months and associated acceleration measures;

Instructed design variations, e.g. exchange of galvanised steel with stainless steel components for installation in the roof resulting into delays in procurement;

Late Instructions, e.g. several changes to the location, position and orientation of buildings by revision in the setting out details have delayed and disrupted the works;

Late Design Information resulting into delays in procurement thus preventing timely arrival of materials at site;

Increased scope of works occasioned by unforeseen site conditions and instructed additional works;

Inclement weather condition; unexpected high amounts of rainfall currently being experienced at site is slowing down progress of works.

The overall effect of all the above has been to delay the completion date for the works up to 24 March 2009 as indicated in the attached revised programme.

We therefore request extension of time to completion of the works.

As stated in the last paragraph of this notice, an extension of time had been requested.

page 33

Page 34: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2.6. Actual Progress

Since the outset of the Contract the Contractor suffered delay due to four major reasons;

Late and inaccurate survey data;

Unforeseen ground conditions;

Project Manager’s instruction to suspend Works (partial);

Late receipt of final design information, and

Additional and varied works.

As a result of Works did not commence as planned.

page 34

Page 35: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

3. Valuation of Variations

3.1. Explanation of Heads of Claim

In his various notifications the Contractor has made reference to at least three types of variations. One type is the changes to the scope of work, a second is the late receipt of design and the third is the changes to the sequence and timing of work. All of these have been sufficiently described and defined in these notifications.

During the currency of work, the first two types of change occurred simultaneously, as well as following consecutively. For example, design drawings which have been issued late, to allow the commencement of certain works, showed changes to the Contract drawings. Further these changes occurred when the Contractor encountered unforeseen ground conditions at most of the respective sites. That is simultaneous occurrence.

There were many instances of consecutive occurrence. For example, where drawings were revised a number of times over a period of several months and even over more than a year, those were consecutive.

3.2. Specific Heads of Claim

Where variations are the cause of delay, the costs associated with the delay have to be taken into account in the valuation of the variations. There are two types of cost to be taken into account. One is the cost of prolongation of work on site. This is the cost of (1) maintaining the site establishment and (2) off-site overheads.

The second type of cost is that of the uneconomic way of working, which results from incorporating the varied work into the Works. This includes the direct cost of the disrupted nature of work on site, and the loss of anticipated income at the times envisaged in the original cash-flow predictions.

page 35

Page 36: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

3.3. Methods of Valuation of the Variations

3.3.1.Use of Costs as Basis

In submitting these particulars of prolongation costs and particulars of slowdown Costs, the Contractor is providing what he is obliged to do by the Contract, which is to make use of contemporary records of costs. The costs were to be used as basis for valuing the variations.

3.3.2.Addition for Profit

It is evident that there are two generic types of claim. One is for ‘costs’ and the other is for value. Therefore, it is necessary to look at profit as a part of both value and cost. The Contractor’s entitlement to have profit added to his cost, to the extent that the costs claimed are included in variation valuations, profit must be added to those costs for inclusion in such valuations. It is noted that Clause 13 clearly indicates that all variations referred to shall be valued in accordance with Clause 12.

In compliance with this requirement of the Contract, the proposition that where the time related costs are indicative of loss of efficiency due to the variation in the timing and sequence of events and are used to formulate a new rate for a particular bill item, then they should include all expenditure, whether on or off the Site. Clause 12 states that the

a new rate or price shall be derived from the reasonable Cost of executing the work, together with reasonable profit

This clarifies that a valuation under Clause 12 must include profit on time related costs. Profit addition on this contract is 15%.

3.3.3.Profit as Part of the Value of Variations

3.3.3.1. Three Types of Variations

The three types of variation included in this submission:

1. Changes in design of parts of the Works,

2. Additional and Varied works, and

3. Changes in the timing and sequence

page 36

Page 37: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

As noted above, all such variations fall to be valued under Clause 13, with the possibility that Clause 12 can be invoked in respect of the effects of variations on unvaried work.

The Contractor confirms that costs claimed are the indirect costs of the delays to the Works, whilst the direct costs include the direct costs of performing the works. In other words, the Contractor’s claim is for the time-related costs to be rolled into the Clause 12 variation valuations.

It is helpful now to give some consideration to each type of variation in turn, so that the Employer can see how profit is included in the valuation of each.

3.3.3.2. Changes in Design of the Works

The first of those two speaks for itself. The claim is for the time-related costs of the variations to be included in the variation valuations. It is unnecessary to argue the point that any such valuation must include profit, under the valuation rules. All valuation rules, in Clauses 12, are founded in rates and prices. It is implicit that they already include profit. It follows that any new rate or price will also include profit.

Of the complaints notified, the first variation event relates to delayed setting out, the second to unforeseen ground conditions, the third to delayed and incomplete design drawings and the fourth to additional and varied Works. Those variations comprised:

1. The changes in the position of buildings, foundation design (partly arising from excavation in rock), unforeseen ground conditions, suspension of Works, late design information, and

2. The change to the specified sequence and timing of the Works

Again, it is helpful to consider each type separately.

3.3.3.2.1. Technical Variations

As example, the changes in design of the Works referred to immediately above; there can be no doubt that a valuation of this type of variation to the foundation works will have to include profit in any event. Similarly, changes in ground conditions must equally include profit.

page 37

Page 38: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

3.3.3.2.2. Changes to Specified Sequence and Timing

Clause 13.1 (f), Conditions of Contract Part I, confirms any change to the specified sequence or timing of construction of any part of the Works instructed by the Project Manager, constitutes a Variation.

In order to establish a Variation to sequence and time, it is therefore necessary to establish the specified sequence and timing of the Works. Clause 8.3, Conditions of Contract Part I, requires the Contractor to submit to the Project Manager for his approval, a program which illustrates the sequence and timing the Contractor intends on performing his Works.

Project Manager’s approval of the Contractor’s Clause 8.3 Program was received in XX 2007. Consequently, the Clause 8.3 Program approved by the Project Manager represents the specified sequence and timing of the Works and any change to this sequence and timing instructed by the Project Manager in writing represents a Variation in accordance with Clause 12.3 (b) (iii).

The Employer will agree that the late receipt of design information is a specified sequence or timing of work as envisaged by Clause 13.1(f) of the General Conditions of Contract. Similarly, the suspension of the works must be treated in the same manner.

Consequently, the Employer will agree that the Project Manager has changed those sequences or timings, and that the Contractor is entitled to have the change treated as variation within the meaning of the said Clause.

The Contractor’s claim to have the changes of sequence and timing brought within Clause 13.1(f) means that those changes also fall to be valued under Clause 12.3. As with the previous types of variation valuation, it must include profit.

3.3.3.3. Summary

When considering profit as part of the valuation of variations, the matters affected are:

1. Changes in the Design of the Works

page 38

Page 39: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

2. Variations to foundations, which splits into two further sub-divisions, namely (1) technical variations and (2) changes to the sequence and timing of work.

It is evident from the foregoing that all of the valuations of the variations referred to must include profit. Therefore, to the extent that the costs claimed are included in variation valuations, profit must be added to those costs.

Clearly, as the foundation work was one of the earliest site operations, the amount of costs, to which profit must be added, is considerable.

3.3.4.The Effects on Unvaried Work

As can be seen from the claims referred in this submission, numerous variations have either been issued or arisen as a consequence of unforeseen ground conditions. In addition, design drawings have generally been received much later than required as depicted on the programme of works. The extent of the variations is such that the original scope of the work included in the Contract has been changed considerably.

So profound have the effects of the changes to both the scope of work and to the sequence and timing of work been, that the relatively few areas of work, which were not varied, have been affected by those variations. The effects fall into the basic categories of (1) prolongation and (2) disruption of the unvaried work.

Clause 12.3 provides the mechanism for including the effects of prolongation and disruption of the unvaried work:

No rate or price is appropriate because the item of work is not of similar character, or is not executed under similar conditions, as any item in the Contract.

This term of the Contract provides an indemnity to the Contractor for all costs reasonably incurred in carrying out variations.

3.3.5.For Uneconomic Working

From the foregoing discussion and analysis, it is evident that a claim for uneconomic working comes within the ambit of Sub-clause 12.3, when the costs are caused directly by performing variations under Clause 13.1, when costs arise from carrying out

page 39

Page 40: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

the work described in the Contract. In practice, it is not possible to separate uneconomic working from the effects on unvaried working, due to the close proximity of site operations, and the continual interchange of resources between varied and unvaried work.

The types of costs of uneconomic working are:

1. The loss of anticipated income, by way of financing.

2. Wasted monthly costs.

3. Financing wasted monthly costs.

Each of those heads of claim is dealt with in turn.

3.3.5.1. Loss of Anticipated Income

This is the cost to the Contractor of financing the shortfall between the income he reasonably expected to receive, and what he actually received, in Interim Payment Certificates.

As to the suspension or slowdown costs, the Contractor claims in respect of lost income for the period from commencement in March 2007 to May 2008. That is because the Particulars included in this submission also relate to the delays in that period.

3.3.5.2. Wasted Monthly Costs

This is a measure of the waste of resources, caused by the disruption, dislocation and re-sequencing of work.

In this document the Contractor describes the cause which resulted in suspension or slowdown of the works. At this section he describes the effect of the cause that is what he means by wasted monthly costs:

One of the types of damage incurred by the Contractor would be the idle time, and/or reduced output, of resources. It is not possible to sever the damage incurred by reason of the delayed setting out of sites, unforeseen ground conditions, changes in scope of works, from that incurred by reason of the delayed design drawings.

The schedules showing the monthly labour and plant levels are evidence that the Contractor not only mobilised, but also maintained, levels of each, which should have ensured outputs

page 40

Page 41: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

at the level of anticipated monthly income referred to above. The schedules showing the amounts certified for each month are evidence that, notwithstanding the level of resources on site, the Contractor’s turnover was far less than he reasonably anticipated.

In order to arrive at a measure of the cost of idle time, and the reduced output, the Contractor has calculated the percentage, which the loss of income represents for each month, of the anticipated income. The Contractor has then applied the same percentage to the monthly cost of labour, equipment, both site and head office overheads, to arrive at the cost on which he has had no return.

The Contractor believes this is the most sensible way of approaching this head of claim. It uses evidence, as opposed to estimates, or supposition.

3.3.5.3. Financing Wasted Monthly Costs

This should be self-explanatory. However, a few words of explanation will help. The Contractor’s entitlement relies on the following:

The Employer should agree that the Contractor is entitled to either the financing charges for the wasted monthly costs if either these are agreed, in the form of interest on late payment in accordance with Clause 14.8 of the conditions of contract or finance charges incurred, whichever is the greater.

The application of finance charges as compensation for the Contractor being kept out of his money replaces interest on late payments. Accordingly, the Contractor claims to be entitled to financing charges on the wasted costs included in the valuation of the Variations.

3.3.6.Profit as Part of ‘Costs’

To the extent that profit on costs could become an issue, the Contractor’s contentions are as follows.

3.3.6.1. Authorities on the Basis of ‘Costs’

In order to appreciate what should be included in a determination of costs, it is necessary to grasp the concept of

page 41

Page 42: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

the expression as used in the contract claims machinery. There are a number of helpful authorities, which explain this.

3.3.6.1.1. Powell-Smith’s ‘Some Building Contract Problems’

The following passage from ‘Some Building Contract Problems’ (page 141), by the late Dr Vincent Powell-Smith, who was a well-known international lecturer, commentator and author, illustrates the purpose of what some construction contracts call ‘direct loss and/or expense’. The parallel in the Contract is ‘costs’:

The purpose of the contract claims machinery is to put the contractor back into the position he would have been but for the delay or disruption, and various cases establish that the term ‘direct loss and/or expense’ means in effect that what is recoverable is substantially the same as the damages recoverable at common law under the first rule in the old case of Hadley v. Baxendale (1854)

This fits directly with the criterion used in the Robinson v. Harman case (see below).

3.3.6.1.2. Hudson and Minter v. WHTSO

In the extract from Hudson’s Building and Project Managering Contracts, Eleventh Edition, Volume 1, on page 1020, there is a summary of the ruling in the case of F G Minter v. Welsh Health Technical Services Organisation (1980) 13BLR1:

By Clauses 11(6) and 24(1) respectively of the 1963 RIBA/JCT forms of contract, the contractor was entitled to be paid ‘direct loss and expense’ not reimbursable under the preceding variation valuation rules, in the one case, or as a result of disturbance of progress due to late receipt of drawings and information from the architect on the other. The contractor claimed financing charges on the additional expenditure in each case as sums due and to be certified by the architect under the two clauses.

Held, by the Court of Appeal, on preceding judicial authority the words ‘direct loss and expense’ meant such damages as would be recoverable as naturally flowing from a breach of contract under the first branch of the rule in Hadley v. Baxendale.

page 42

Page 43: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Again, although the extract refers to the expression ‘loss and/or expense’, it is the equivalent of the ‘costs’ suffered by the Contractor under the Contract.

The discussion of the judgment following the passage quoted from it in Hudson is at the heart of this issue in this Claim. In paragraph 8-096, the learned author says:

The wider importance of the Minter and Rees and Kirby cases in the Construction field cannot be ignored. The reasoning of the Court of Appeal in the Minter case was that previous authority showed that the contractual “direct loss and expense” expression meant the same as the measure of damage “arising naturally in the usual course of things” under the first branch of the Hadley v. Baxendale rule. The contract therefore expressly applied that test to both the Clause 11(6) basis of claim (variations and not, therefore, a breach of contract) and to the Clause 24(1)(a) basis (late information and, therefore, a breach of contract). [Author’s emphasis.]

The author’s discussion draws attention to the importance of the comparison of direct loss and expense, or, as in the Contract, ‘cost’, with damages envisaged by Hadley v. Baxendale. The costs referred to have been incurred as a result of denial of possession of parts of the site, and of late and varied information.

3.3.6.1.3. Hudson on the Scope of ‘Costs’

From the two foregoing authorities, it is evident that the more widely used expression ‘loss and expense’ is a direct parallel to the word ‘costs’ as used in the instant Contract. Underpinning this is the breadth of coverage given to the expression ‘loss and expense’. This is illustrated by the following extract from page 1096 of Hudson, paragraphs 8.213 to 8.216. In paragraph 8.213, the author draws attention to the coverage of ‘loss and expense’:

a. ‘Direct’ or ‘consequential’ damage provisions

… In this context, ‘consequential’ damage will sometimes be contrasted with ‘direct’ damage as the subject of exclusion, or sometimes used on its own to indicate an intended class of compensation. Thus, since 1963 the English standard forms, and in particular the RIBA/JCT forms, have employed the expression ‘direct loss and expense’ in the context of positive provisions for

page 43

Page 44: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

additional payment expressly permitted by these contracts. …

He then draws the parallel with Hadley v. Baxendale for the type of damage to be included in loss and expense, and what he calls ‘wording of this kind’, in paragraph 8.215:

These strict interpretations in the case of exclusions clauses have been paralleled by a correspondingly generous interpretation of ‘direct loss and expense’. Wording when used positively in compensation provisions. It has already been seen that interest in the form of financing charges has been held to be recoverable by contractors under this wording under Clauses 11(6) and 24 of the 1963 RIBA/JCT forms. Wording of this kind will include any damage recoverable under the first branch of the Hadley v. Baxendale rule, which it has been seen will include a wide range of heads of damage which might otherwise in a loose sense be described as ‘consequential’ or ‘indirect’.

It should be noted that, on page 1098 of the extract, in the reference to the second case, Wraight v. PH&T (Holdings) Ltd (1968), it says that it was held that a contractor was entitled to his loss of profit. This case is referred to specifically below.

This extract is included as Appendix 4.

3.3.6.1.4. The First Part of the Rule in Hadley v. Baxendale

The case of Hadley v. Baxendale is at the very heart of damages for breach of contract, and need not be quoted at length. Having established that a contractor’s claim for loss and expense, or cost, or indeed for anything covered by ‘wording of this kind’, it is helpful to refer to the judgment in Hadley v. Baxendale, to see exactly what the first part of the rule allows.

The Contractor reproduces here an extract from ‘Contract Cases and Materials’ by Hugh Beale, William Bishop and the very well-known and respected Prof Michael Furmston, who is also the author of the classic work on contract law, ‘Furmston, Cheshire and Fifoot’. The extract is in fact part of the judgment in the case, at page 395:

We think that there ought to be a new trial in this case; but, in so doing, we deem it to be expedient and necessary to state explicitly the rule which the Judge, at

page 44

Page 45: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

the next trial, ought, in our opinion, to direct the jury to be governed by when they estimate the damages. …

Now we think the proper rule in such a case as the present is this: - Where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e. according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it.

Thus, the first part of the rule is that:

… the damages which the other party ought to receive … should be such as may fairly and reasonably be considered … arising naturally, i.e. according to the usual course of things, from such breach of contract itself …

In the case of the matters claimed, the Contractor is therefore entitled to reimbursement of costs, which include costs, which arose naturally from the breach.

3.3.6.1.5. The Basic Measure of Damages

Having established that the Contractor is entitled to have his costs determined on the basis of what flowed naturally from the breach, it is necessary to alight upon the correct measure of damage. There is precise authority for this in the case of Robinson v. Harman (1848) 1Exch850, 855. The relevant passage is as follows:

The rule of the common law is, that where a party sustains loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.

The quoted passage is taken from page 11 of Beale, Bishop and Furmston’s book.

This the truly prescriptive rule for what should be in the determination of costs. It has been shown by logical steps that ‘costs’ in their generic sense equate to common law damages. From that, it is the common law rule that damages must put the offended party back in the same position he would have been in, but for the events complained of.

page 45

Page 46: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

It follows from this that a contractor, who suffers as a result of an act or omission of the employer or his agents, is entitled to recover his profit.

3.3.6.2. Authorities on the Recovery of Profit

Now that the basic premise for using the criterion applicable to common law damages for breach of contract has been presented, the Contractor will show that the recovery of profit comes within that criterion.

3.3.6.2.1. General Principle as to Claims

The general rule that claims for loss and expense or costs are to be treated as claims for damages at common law is expounded by Dr Powell-Smith on page 143 of ‘Some building Contract Problems’:

Claims under clause 26 can be equated with claims for damages at common law, and are governed by the same principles. On that basis, the consequences of the late instruction must have been within the reasonable contemplation of the contracting parties at the time the contract was made. The additional cost arises as a direct and natural result of the architect’s default and is thus claimable under the contract terms: see Hadley v. Baxendale (1854)

3.3.6.2.2. Wraight v. PH&T (Holdings) Ltd

In the case of Wraight v. PH&T (Holdings) Ltd (1968), a contractor pursued a claim for loss of profit, as a result of his own determination of his employment under a building contract.

The contractor in the case put his argument as summarised in the judgment on page 284, near the bottom:

It is said here on behalf of the [contractors] that quite plainly the loss of profit to the [contractors] was, in any ordinary sense of the word, a direct consequence of the determination of the contract. If the contract had not been determined, they would have gone on and done the work, continued their legal obligations thereunder and would have had their legal right to obtain their full contractual remuneration at the end of it, and therefore they have, by this determination, lost the right to receive that sum of

page 46

Page 47: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

money which they would have received if the contract had not been determined: what can be more direct than that?

Obviously, the event complained of in the case is determination of the contractor’s employment. However, that is not of importance. It is a type of event, which entitles the offended contractor to reclaim his losses, just as the denial of possession and late information in the Contract do.

The important thing is that the contractor in the case was looking to recover the sum of money he would have recovered, but for the event complained of. It is natural that such sum of money included profit.

The judge concluded, on page 285:

In my judgment, there are no grounds for giving to the words ‘direct loss and/or damage caused to the contractor by the determination’ any other meaning than that which they have, for example, in a case of breach of contract or other question of the relationship of a fault to damage in a legal context. Therefore it follows … that the [contractors] are, as a matter of law entitled to recover that which they would have obtained if this contract had been fulfilled in terms of the picture visualised in advance but which they have not obtained.

It was held (page 284) that:

The words direct loss and/or damage in clause 26 must be given the same meaning as they would have in the case of a breach of contract. The loss of profit was the direct and natural consequence of the determination of the contract, and the contractors were entitled to succeed.

3.3.6.2.3. Powell-Smith and Sims on Building Contract Claims

The authors of ‘Building Contract Claims’, Vincent Powell-Smith and John Sims, state unequivocally on page 110 of their book that:

Loss of profit, which the contractor would otherwise have earned but for the delay or disruption, is an allowable head of claim. It is recoverable under the rule in Hadley v. Baxendale (1854).

Pages 110 to 113 of the book are included in Appendix 9.

page 47

Page 48: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

It is worth noting that the authors refer to the Wraight case on page 111, and that they make a distinction between the profit normally to be expected, and exceptionally high profit. The Contractor is only claiming here the level of profit allowed for in his tender.

The extract also mentions the possibility of claiming for profit lost on other contracts. The Contractor is not claiming for that. He is only claiming for his profit on the Contract, which is much more direct than that lost on other projects.

3.3.6.3. Summary

There are plenty of authorities to show that:

1. A claim for payment of ‘costs’ is to be treated as a claim for common law damages.

2. Such damages should put the complaining party back into the position he would have been in, but for the event complained of.

3. Profit is an allowable head of claim under common law damages.

The Contractor’s claim is only for profit on the Contract work, not for other work, so it is within the first rule in Hadley v. Baxendale, and should be allowed.

3.4. The Contractor’s Summary

For all of the foregoing reasons, the Contractor contends that the profit claimed by him is allowable. It should be treated in the same way as damage within the meaning of the first rule in Hadley v. Baxendale, and fulfil the criterion in Robinson v. Harman.

There is no prohibition of it as a head of claim. If the Project Manager were to have the power to deprive the Contractor of profit on any claim he chose to treat as one for ‘costs’, then all contractors could be placed in the unacceptable position of doing a large proportion of work at cost. This is clearly not what the Contract stipulates, nor could it have been the intention of the parties.

page 48

Page 49: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

4. Circumstances Giving Rise to Claim

Performance of the construction activities required the availability of final setting out details and foundation design information (arising from unforeseen ground conditions) to permit execution of the Works. Records show that setting out was delayed and information with respect to rock excavation was neither evident from records available. These two initial events seriously impacted progress and caused significant delays. It was further and seriously compounded by the Project Manager’s instructions to suspend the Works which lasted 2 months.

Furthermore, it is a fundamental requirement of the Contract that detailed design information is made available in the times consistent with the Contractor’s programme of works. In the event, such information was late, and aggravated by incomplete and inconsistent design details that naturally caused a change in the planned methods of working. This is particularly evident at the two “Mock-up” villas that underwent numerous changes as works proceeded.

In addition to the above, payment for varied work performed was not fully received by the Contractor in accordance with the procedures and time stated in the contract.

4.1. Contractual Basis – Notification of Changes

The Contractual basis of the heads of claim is described in subsequent sections of this document. That is, the Contractor gave notice of the difficulties existing at the Site arising from delays and disruptions.

The Contractor issued notice of the following issues on

We acknowledge receipt of your letter dated 4 December 2007 referenced E-09-04-12-07 and wish to confirm our position by the following extract from the Contract:

The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”

page 49

Page 50: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”

The Contract Agreement dated 27 April 2007 lists the documents forming the Agreement and the Letter of Acceptance takes priority over the Conditions of Contract.

Consequently, your reference to sub-clause 12.3 and 13.1 of the Conditions of Contract, although interesting, is not relevant in the introduction of Variations on this project, particularly as sub-clause 3.1 has been amended by the quoted specific conditions above.

We would point out that although the amendment is impractical it is a significant revision to both Clause 12 and 13 of the Conditions of Contract. In practise it means that no Variation arising from additional work or by design change can commence prior to receiving the agreement of the Employer.

In conclusion, the purpose of our letter dated 23 November 2007 on this subject matter was to bring these special circumstances to your attention.

A further notice was issued on XX relating to the instruction to suspend the works:

Please refer to your letter dated 23 November 2007 referenced E-01-23.11.07 to which we wish to clarify this situation with regards to the cause for suspension of works.

First, the suspension of the Works, other than the two Mock-up villas occurred between 29 August 2007 and 29 November 2007. The reason for your suspension relies on work covered prior to inspection, but not with our site organisation. We have covered this aspect in our previous letter and pointed out remedies in the Contract available to the Engineer in these situations.

Secondly, although it was suggested in our email dated 28 August 2007 that concrete work would stop, in reality it did not and work continued until your instruction to suspend Works on 29 August 2007. This is all a matter of record and should be common ground.

Consequently, we disagree with contentions raised in your letter and reiterate our entitlement to extensions of time and additional payment arising from your instructions.

page 50

Page 51: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

A notice was issued in regards to several of the delaying events on XX

We acknowledge receipt of your letter dated 23 November 2007 referenced E-07-23.11.07 regarding records of meeting No. 27 held on 9 November 2007. We disagree with your position on the 3 points for the following reasons:

Point 3 – minute 6.2: It is impossible for the Project Manager to have knowledge of the Contractor’s management and manpower with respect to their ability to handle the complete site. This is complete conjecture and only the Contractor can have that knowledge. In any event, it is not a contractual provision to suspend work based upon the Project Manager’s perceived knowledge of the Contractor’s planning and operations. Even if this is your reason for suspension the provisions of sub-clause 8.9 remain relevant.

The facts are recorded in our letter dated 29 October 2007 where reasons for suspension were indeed because work was covered up prior to inspection and approval. Once again, if this is your remedy in these circumstances, then the same provisions at sub-clause 8.9 are relevant.

Point 4 – minute 6.2: We have recorded severally delays caused by setting-out, increased scope of work for normal excavation, rock excavation and fixing steel reinforcement, shuttering and volume of concrete. The combination of these issues had caused a delay to progress at the time of this meeting (which is in the same period the works were suspended) by at least 3 weeks.

Normally, the Project Manager would give notice to the Contractor in accordance with sub-clause 8.3 which last paragraph, states:

If, at any time, the Engineer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor’s stated intentions, the Contractor shall submit a revised programme to the Engineer in accordance with this Sub-Clause.

This revised programme is issued in accordance with the provisions of sub-clause 8.6, which states:

If, at any time:

page 51

Page 52: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

(a) actual progress is too slow to complete within the Time for Completion, and/or

(b) progress has fallen (or will fall) behind the current programme under Sub-Clause8.3 [Programme],other than as a result of a cause listed in Sub-Clause 8.4 [Extension of Time for Completion], then the Engineer may instruct the Contractor to submit, under Sub-Clause 8.3 [Programme], a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion. (Emphasis added)

Unless the Engineer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor’s Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7 below.

Please confirm if you intend to give a notice in accordance with this sub-clause? If that does remain your intention, then we must draw your attention to sub-clause 8.4, to paragraphs (a) and (b).

In the alternative, we confirm having issued a compliant notice in accordance with sub-clause 8.4 and provision of claims under sub-clause 20.1.

In conclusion, as we are not responsible for the delay and disruption to date, and the extended time to completion at 8 December 2007, we will not adopt any acceleration measures to recover earlier delays unless and until instructed.

At the request of the Project Manager a second revised programme of works was issued on 14 March 2008. In this notice the Contractor clearly indicated the various delays effecting impacting progress:

In accordance with your recent request in the weekly progress meetings, please find attached revised programme of works for your consent.

page 52

Page 53: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The revised programme takes into consideration the various events and changed circumstances since commencement up to 29 February 2008.

These events and changed circumstances, as separately notified to you and further illustrated in our situation report dated 29 February 2009, have caused the original planned timing and sequence of works to vary. They include the following;

Unforeseen hard rock excavation including spoiling;

Suspension of works, except for the mock up villas, for two months and associated acceleration measures;

Instructed design variations, e.g. exchange of galvanised steel with stainless steel components for installation in the roof resulting into delays in procurement;

Late Instructions, e.g. several changes to the location, position and orientation of buildings by revision in the setting out details have delayed and disrupted the works;

Late Design Information resulting into delays in procurement thus preventing timely arrival of materials at site;

Increased scope of works occasioned by unforeseen site conditions and instructed additional works;

Inclement weather condition; unexpected high amounts of rainfall currently being experienced at site is slowing down progress of works.

The overall effect of all the above has been to delay the completion date for the works up to 24 March 2009 as indicated in the attached revised programme.

We therefore request extension of time to completion of the works.

The Contractor wrote again on 21 April 2008 with a notice stating the events that delayed progress:

page 53

Page 54: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Reference is made to your letter dated 7 April 2008, E17-07.04.2008 to which this letter relates.

The purpose of this letter is to seek approval to accelerate progress to Completion in solution to recovery of earlier delays experienced which is made without prejudice to our current contractual position.

Progress To Date and Causes of Delay

We have written on several occasions about various events that caused delay and disruption to the regular progress of the work since the outset of this Contract. Some of these events and changed circumstances are described below and are significant by either their impact on time to completion or cost or both:

Late Design Information

Both survey data and final construction design are being issued late and this has naturally caused delay. As example, drawings for construction are required at commencement in order to allow procurement; however, drawings are still being issued or remain outstanding 12 months after commencement. The lateness of such information prevents rapid conclusion and timely arrival of materials at Site.

The Contractor also records he has not received any structural drawings that must in the first instant, be approved by the Ministry of National Development.

A further complication arises from having two structural engineers engaged to design different parts of the Contract. This has led to disruption in the design process.

Provisional Sums

Almost 30% of the Contract Price is derived from lump sum provisions for works not sufficiently detailed or identified at time of tender. The subsequent introduction of these works requires an instruction in accordance with the conditions stated in the Contract. As such, they are not works necessarily envisaged as forming part of the Works until and unless the Project Manager issues an instruction.

A further complication is that for these particular works neither detailed bill of quantities exists nor design drawings, although almost 12-months of the Contract period have elapse. In practise the Quantity Surveyor

page 54

Page 55: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

should have prepared these Bills for submission to the Contractor to enable pricing and material procurement. As a result, their value is not defined and detailed programming is not possible and that indicates the Contract Price and the time of Completion must change.

Material Procurement

In the absence of complete design information procurement has not proceeded as planned. Delays in procurement will undoubtedly cause delay to completion. In addition, prices quoted at tender stage cannot be secured because orders are confirmed much later than planned.

Suspension of work

The Works were suspended in the period from 29 August 2007 through to 29 October 2007 as recorded in minutes of monthly meeting No 27 held 9 November 2007. The reason for this suspension by the Project Manager relies on work covered-up before inspection (at one villa column base).

The Conditions of Contract contain provisions for breaking out and exposing work and this would have been the sensible solution, not suspension. As to progress, it is evident from the photographs taken of the site at that date excellent progress was being made at several locations. The impact of 2 months suspension has had on progress was significant.

Re-measurement Contract vis-à-vis Fixed Lump Sum

The Conditions of Contract adopted on this project is a standard form and allows re-measurement however, all Clauses that allow Variations have not been revised or amended as one would expect in order to suit a Fixed Lump Sum Contract.

In addition, the Letter of Acceptance states that:

“the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.” [Emphasis added]

It further states that:

page 55

Page 56: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

“Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”

Clearly, any alteration to the scope of work, introduction of additional work or design change, is very likely to influence a change in the Contract Price and the time to Completion. On this contract three areas of change will cause the Contract Price to vary and the time to Completion to extend, namely:

Variations to Scope of Works

Changes in the scope of work do arise by virtue of drawings issued for construction that automatically increase quantities shown in the Bills of Quantities. This is for two reasons; a) the correlation between substructure design and actual ground conditions are at variance, and b) a general enhancement of the reinforced concrete structure designed.

Flowing from variations generally introduced by final design drawings or drawings issued for construction, the scope of work has increased considerably, as example:

A significant increase in excavation of hard rock for which a small provision was made in the Contract;

A significant increase in the quantity of normal excavation to that indicated in the Contract, which is dictated by the topographic site conditions;

A significant increase in volume of reinforced concrete placed to that indicated in the Contract;

A significant increase in associated temporary works such as shuttering to that indicated in the Contract; and

A significant increase in steel reinforcement to that indicated in the Contract.

All these changes are not within the control of the Contractor, they are instructed Variations and naturally have time and cost considerations.

Instructed Design Variations

Mainly changes brought by a) interior design requirements, and b) because of superstructure variations. Once again, these variations are not within the control of the Contractor, they are instructed Variations.

page 56

Page 57: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

One example of a design change relates to the exchange of galvanised steel with stainless steel components for installation in the roof. Notwithstanding the delay in making procurement of this specialist item, the additional cost is significant.

Lump Sums

The values of many of the structures included in the Contract Price are based on a square-metre rate in the absence of a detailed bill of quantity. As design drawings are now issued (September 2007) these works need to be measured and valued. The outcome of this evaluation will undoubtedly cause the Contract Price to vary. In addition, the time required to complete these structures can only be evaluated once detailed design drawings are made available. At that juncture, the details of these structures can be introduced in the programme of works.

Other Factors Impacting Progress

Although the following issues were known and considered at time of tender and therefore, allowed in our programme of works, they clearly have an influence on progress. They are mentioned here because with the prevailing delays described in Points 1 and 2 above, their very existence compounds a situation that is already impacting progress.

Tidal Movement

Each and every day/month typical low-tide conditions exist that prevent movement of vessels delivering material to Long Island. This is not a situation that can change and such time considerations are incorporated in the programme of works. The situation is compounded as the immediate area to Long Island is a protected Marine Park.

Transport of Materials to Long Island

All materials are brought by sea via one large barge in deep water which off-loads to two small barges at shallower water. At times it is not uncommon for a barge to suffer mechanical failure and there is possibility of disruption in the material supply. There are no other methods available that allows bulk supply of materials to the island, so although these difficulties are present all efforts are made to ensure these operations are limited.

Procurement of Local Raw Materials

page 57

Page 58: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The level of construction in the Seychelles is quite substantial and demands for natural quarry materials places a considerable strain on the local supplier. The supply of quarry materials in the Seychelles are a monopoly and alternate sources are not available. Occasionally, a quarry product is in short supply, usually because of demand, and this will cause disruption in placement of concrete at site.

Wet Weather Conditions

The weather patterns are fairly regular and wet seasons can cause considerable difficulty at site, particularly prior to establishment of all-weather access roads. Once again, this is not a situation that can change and such time considerations are incorporated in the programme of works.

Suspension of Quarry Operations

In parallel with wet weather seasons all quarry operations do not function, particularly when rainfall is persistent over several days. As a consequence quarry products such as dust and aggregates and composite items as concrete blocks are not produced which interrupts the regular supply to Site.

Financial Considerations

The events and changed circumstances described in the foregoing have directly impacted the Contractor’s income which, together with Advance repayments has caused a negative cash flow.

Reduced Income

Regular progress of the works has been reduced significantly because of the delays occasioned by Variations, additional works and suspension of the whole Site (except the two mock-up villas). As a consequence, the value of work performed is significantly lower than anticipated and as indicated on the original cash flow chart. Therefore, costs are constantly greater than income derived for work performed.

Also, during these periods of delay and disruption direct and indirect costs are not fully recovered because planned progress has not been achieved. In addition, and as a result of a continuous shortfall in income, the value of the Advance to the Contractor has diminished at a rate

page 58

Page 59: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

greater than anticipated as it’s been consumed in loss and expense.

Repayment of Advance Loan

The repayment of the Advance is directly linked to projected income which is derived from the programme of works. However, because progress has not been achieved income is considerably lower and the time for completion has extended. As a result, the monthly value of repayment has to be adjusted in light of the change in income flowing from an extended time to completion.

Proposed Remedy

The revised programme of works issued under cover of our letter dated 14 March 2008 shows a revised completion date of 24 March 2009. This is the date substantial completion can be achieved and is based on two important criteria; a) an adjustment to the value and period of the initial Advance repayment and, b) the payment of a second Advance.

The programme considers delays experienced to date, which principally is the setting out, excavation in hard rock, delays in receipt of detailed design drawings and delayed arrival of major material components to site.

It is anticipated that with the measures to recover earlier delays explained below, this continuing delays will be halted and in some respects, time will be recovered.

For reasons provided in the foregoing, this situation with respect to cash flow is not sustainable. In order to rapidly and affectively halt escalation of this situation the Contractor proposes the following solutions:

Adjusting Repayment of Advance

The cash flow estimate has been adjusted once to date to meet changed circumstances on site and this must be done again. The monthly value and period of repayment will need to be aligned with the revised durations shown on the programme of works. A proposed revised recovery on this Advance is shown in the table below:

page 59

Page 60: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Cert. No. Month AdvancePayment Certified AdvanceRepayment

Advance May-07 3,100,000.00 1 Jun-07 682,032.852 Jul-07 351,989.15 200,000.00 3 Aug-07 145,803.63 200,000.00 4 Sep-07 357,556.62 200,000.00

Oct-07 0.00 357,142.86 5 Nov-07 478,926.03 214,285.71 6 Dec-07 0.00 214,285.71

Jan-08 0.00 214,285.71 7 Feb-08 1,276,534.91 100,000.00 8 Mar-08 1,276,534.91 100,000.00 9 Apr-08 1,276,534.91 100,000.00

10 May-08 1,276,534.91 100,000.00 11 Jun-08 1,276,534.91 100,000.00 12 Jul-08 1,276,534.91 100,000.00 13 Aug-08 1,276,534.91 100,000.00 14 Sep-08 1,276,534.91 100,000.00 15 Oct-08 1,276,534.91 100,000.00 16 Nov-08 1,276,534.91 100,000.00 17 Dec-08 1,276,534.91 100,000.00 18 Jan-09 1,276,534.91 100,000.00 13 Feb-09 1,276,534.91 100,000.00 14 Mar-09 1,276,534.91 100,000.00 15 Apr-09 1,276,534.91 100,000.01 16 May-09 1,276,534.9117 Jun-09 1,276,534.9118 Jul-09 1,276,534.9117 Aug-09 1,276,534.9118 Sep-09 1,276,534.9113 Oct-09 1,276,534.9114 Nov-09 1,276,534.91

Total 3,100,000.00 30,100,076.26 3,100,000.00

Measures to Recover Earlier Delays

To facilitate measures to accelerate progress the Contractor will enhance existing resources. This will involve bringing to site additional equipment and staff and labour resource over and above that planned at tender.

The table below lists planned additional staff and labour and equipment that will be deployed at Site. It also includes the delay and disruption costs arising during the 2-month period of suspension.

page 60

Page 61: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour

1 Senior Project Manager 168,630.002 Quality Assurance Manager 168,630.003 Senior Quantity Surveyor 107,250.004 Assistant Quantity Surveyor 99,000.005 Expatriate Workers 880,000.00 1,423,510.00

Equipment

1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Delay and Disruption Costs 565,714.29

Total additonal resources 2,524,415.29

In recognition of the additional cost flowing from deploying additional resources and loss and expense suffered during periods of delay and disruption, the Contractor requests reimbursement of a portion of these direct costs. These have been established in the above table and amounts to US$2,524,415.29. The Contractor asks payment in nine (9) equal interim Certificates starting from April 200 with the last in December 2008.

Second Secured Advance Payment

The major and immediate expense typically flows from material and equipment procurement. A subsidiary of that is increased staff and labour over and above that originally planned.

The first component, materials, is the critical element to achieving sustained progress and once 80% has been secured and delivered at Site, a major obstacle is overcome. This is particularly significant with respect to the geographic location of the Seychelles and the difficulties this presents for material procurement.

Material not ordered is either because design details have not been availed or that Bills of Quantities and respective designs flowing from Provisional Sums is still in abeyance.

page 61

Page 62: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The second component, equipment, dictates the methods and pace at which the works proceed. In other words, by increasing the number of certain pieces of equipment and by changing methods, progress can be improved significantly.

The last element considered is staff and labour, the major change will be deployment of two European Site Agents well experienced in this type of work. In addition, we will deploy further expatriates of all trades in order to meet the demands of a revised programme of works, which we will submit shortly.

As shown in the impacted programme issued 14 March 2008, because of earlier delays many operations have been delayed, therefore, commencement of most buildings have been compressed on the original programme of works. This means that site operations are not working sequentially but simultaneously and this is a major planning problem existing today. Consequently, all these resources will allow expansion of operations to many areas of site allowing work to proceed simultaneously and therefore achieve earliest completion.

To meet additional and immediate costs in this recovery program and to meet the changed circumstances, the Contractor requires a minimum Advance payment amounting to US$3,500,000.00. The proposed recovery on this Advance is shown in the table below:

Month Value Repaid

May-08 250,000.00Jun-08 250,000.00Jul-08 250,000.00Aug-08 300,000.00Sep-08 300,000.00Oct-08 350,000.00Nov-08 400,000.00Dec-08 550,000.00Jan-09 400,000.00Feb-09 450,000.00

Total 3,500,000.00

The next table is the projected combined recovery on both Advance payments:

page 62

Page 63: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month FirstAdvance SecondAdvance Combined

May-07 0.00 0.00Jun-07 0.00 0.00Jul-07 200,000.00 0.00 200,000.00

Aug-07 200,000.00 0.00 200,000.00Sep-07 200,000.00 0.00 200,000.00Oct-07 357,142.86 0.00 357,142.86Nov-07 214,285.71 0.00 214,285.71Dec-07 214,285.71 0.00 214,285.71Jan-08 214,285.71 0.00 214,285.71Feb-08 100,000.00 0.00 100,000.00Mar-08 100,000.00 0.00 100,000.00Apr-08 100,000.00 0.00 100,000.00

May-08 100,000.00 250,000.00 350,000.00Jun-08 100,000.00 250,000.00 350,000.00Jul-08 100,000.00 250,000.00 350,000.00

Aug-08 100,000.00 300,000.00 400,000.00Sep-08 100,000.00 300,000.00 400,000.00Oct-08 100,000.00 350,000.00 450,000.00Nov-08 100,000.00 400,000.00 500,000.00Dec-08 100,000.00 550,000.00 650,000.00Jan-09 100,000.00 400,000.00 500,000.00Feb-09 100,000.00 450,000.00 550,000.00Mar-09 100,000.00 100,000.00Apr-09 100,000.01 100,000.01

Total 3,100,000.00 3,500,000.00 6,600,000.00

The revised Organisation Chart is attached to which has been added the additional management staff. Evidence of projected expenditure for staff, labour and materials is provided in the table below and is likely to exceed US$5 million.

page 63

Page 64: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour (one month)

1 Senior Project Manager 15,330.002 Quality Assurance Manager 15,330.003 Senior Quantity Surveyor 9,750.004 Assistant Quantity Surveyor 9,000.005 Expatriate Workers 80,000.00 129,410.00

Equipment

1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Materials

1 Balau timber (special size) 1,764,705.882 Stainless steel roof components 2,559,900.003 Shingles 333,600.00 4,658,205.88

Total Second Advance 5,322,806.88

Conclusion

It is evident from the foregoing the considerable difficulties encountered on this project since the outset are not the responsibility of the Contractor.

The majority of changes and consequent difficulties exist because a significant portion of design was not developed at tender. Of worthy note, after expiry of almost 12 months of the Contract period close to 30% of the scope of works has not been identified through detailed Bills of Quantities; an essential requirement outwith prevents material procurement and disrupts planning.

Recent suggestions to engage other contractors to perform portions of the scope of works will have little effect because constraints imposed by operational logistics and design development are unlikely to diminish.

Consequently, with the valuable knowledge and experience gained it is our considered opinion drastic measures must be implemented by both the Contractor and Employer’s design teams. The respective responsibility of each party is important and the

page 64

Page 65: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Contractor has in this letter, set-out under paragraph 5 above, what he feels is required to bring this project to earliest completion.

First, the Contractor looks forward to receiving proposals from the Employer’s design team indicating what measures will be taken to address outstanding design issues. Secondly, the scope of works must be defined in order to establish the revised Contract Price outwith the Contract Completion date will remain at large.

Finally, payment of the Contractor’s acceleration costs and the Second Secured Advance is of paramount importance in the measures required to conclude this Contract thus allowing a reduction of the Contractor’s extended costs and indeed, the Employer’s losses.

We look forward to receiving approval in principle of the foregoing and subsequent instructions.

Accordingly, the Contractor is entitled to receive, under Sub-Clause 20.1, extensions of time and additional payment as described under Sub-Clause 8.4, 1.9 and 2.1 of the Contract Conditions.

4.2. Late and Inaccurate Survey Data

The completeness, accuracy and timely issue of survey information remain the responsibility of the Project Manager. Sub-clause 4.7 of the Contract Conditions is clear on this subject and it should be common ground as to the consequences of the Contractor being provided information inconsistent with design and site conditions.

The table below provides dates when setting-out was performed and reasons why for many the exercise was repeated. In most instances it was because the position and orientation were varied to suit site conditions.

Villa

Baseline Programme Setting Out Finish date Initial Setting Out Revised Setting Out

Delays due to Changes in Setting Out Details & Orientation (days)

A3/30 29-Mar-07 25-Apr-07 26-Jun-07 62.00A3/20 13-Apr-07 25-Apr-07 20-Jul-07 86.00A3/11 10-Apr-07 25-Apr-07 03-Jun-07 39.00A3/07 03-Apr-07 25-Apr-07 04-Jun-07 40.00

It can be seen in the table above critical delays occurred at four villas of between 40 and 86 calendar days. These delays are considered and included in the extension of time request.

page 65

Page 66: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

4.3. Late Receipt of Final Design Information

In addition to receiving design information late, the Contractor has had the inconvenience and time-consuming problem of dealing with design drawings issued that are either late or are revised.

Structure/Villa

Commencement Completion

Drwgs Required 120 days prior POW Start Date Structural Architectural Delay (Days)

A3 Pool Villa 02-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00B223 Standard Villa 28-May-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00B4 Standard Villa with Pool 16-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00C311 Executive Villas 12-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00P3 Presidential Villas 20-Jun-07 20-Mar-08 28-Feb-07 19-Oct-07 09-Mar-07 233.00Sunset Deck 23-Jul-07 14-Mar-08 25-Mar-07 09-Apr-08 22-Aug-07 381.00Employees Facilities Complex 14-Jun-07 19-Mar-08 28-Feb-07 31-Aug-07 22-Aug-07 92.00Excom Villa 14-Jun-07 17-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00GM Villa 14-Jun-07 15-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00Health club 14-Jun-07 15-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00Single Treatment room 02-Jul-07 17-Mar-08 04-Mar-07 10-Jun-07 28-May-07 98.00Couple treatment room 02-Jul-07 19-Mar-08 04-Mar-07 25-Jun-07 28-May-07 113.00Sanctum 02-Jul-07 15-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00Yoga Pavilion 02-Jul-07 14-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00BOH Building 02-Jul-07 17-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00Wedding chapel 02-Jul-07 14-Mar-08 04-Mar-07 09-Apr-08 28-May-07 402.00Seafood Resort 18-Jun-07 19-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00Retail Pavilion 18-Jun-07 14-Mar-08 28-Feb-07 11/06/2007 28-May-07 103.00Kid's club 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Recreation House 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Water sport Rental 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Dive Center 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Mechanical Area 22-Oct-07 09-Apr-08 24-Jun-07 Not Received Yet 08-Jan-08 326.003 Meal Restaurant 02-Jul-07 26-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00Signature Pool 02-Jul-07 15-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00Beach Pool Bar 02-Jul-07 17-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00

Drawing Receipt ScheduleBaseline Programme

The table above shows the timing of receipt of design drawings and is evidence of continuing delays. In some instances structural drawings are still outstanding where in others they have been issued late by between 14 and 438 calendar days.

Due to the lateness in receipt of design drawings, not only construction delayed but also procurement. Delays in procurement cause the Contractor to incur greater costs because prices secured at tender either expired or prices in the period increased.

4.4. Additional and Varied Work

4.4.1.Excavation in Hard Rock

Due to the nature of the ground and the topography of the Site, it was important to adhere to the Contractor’s original planning in terms of construction sequence.

Furthermore, the scope of this work was restricted to a) the numbers of buildings identified at tender stage and, b) the position of the buildings. Obviously, with a major part of the

page 66

Page 67: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Contract Price falling under Provisional Sums, both these factors had to change and, with that change (Variation), brought a number of unforeseen difficulties.

One such consequent change involved significant increase in excavation in hard rock. Furthermore, the change in timing and sequence exacerbated the difficulty in extraction and the method in which the work could be performed.

4.4.1.1. Change in Sequence and Increased Cost

Although the sequence change was caused by survey work, rock excavation and more specifically the suspension of Works, work at each site then became in variance to the contractor’s original planning, the conversion and expenditure of Provisional sums exacerbated its impact.

4.4.1.2. Increased Quantity

In addition to the complications of performing controlled blasting, the quantity of rock excavated to date has increased between 20% and over 300% to that anticipated. In these conditions the Contractor has entitlement to the additional time to perform these varied works.

The following tables are recorded evidence of the significant increased volume of rock excavation found at almost every villa site. The tender provision was clearly too low and that has been reflected in the Contractor’s planning.

As example, the first table below illustrates the quantities of rock excavated using blasting methods otherwise not foreseen. At villa B2/01 the volume of hard rock excavated has already reached close to 240m3 whereas the allowance in the Contract was zero. The time taken to remove this rock to date, as it is not finished, is already close to 200 calendar days. Consequently, the duration taken for this activity at this villa is already 200 calendar days and delay is considered critical.

The following table lists volume of rock excavated at each villa which, as stated above, is all unforeseen. As such at each villa the delay caused in performing this activity is critical and prevents commenced of subsequent dependant activities.

page 67

Page 68: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa Rock Blasting (m3) Increase

A3/02 95.00 100%A3/03 97.85 100%A3/04 23.00 100%A3/05 1.14 100%A3/06 12.69 100%A3/08 11.41 100%A3/09 54.50 100%A3/10 171.68 100%A3/11 139.00 100%A3/19 47.97 100%A3/20 65.10 100%A3/21 42.13 100%A3/28 4.17 100%A3/29 4.18 100%A3/31 2.31 100%B2/01 239.14 100%B2/04 147.55 100%B2/05 13.87 100%B2/06 48.40 100%B2/07 7.73 100%B2/08 5.04 100%B2/09 28.50 100%B2/10 52.50 100%

The next table provides a summary of volumes of hard rock excavated at the various sites. Once again it is apparent that the tender provision represents only between 8% and 55% of the actual quantity excavated. Once again with such a significant change it is obvious removing over 60m3 of rock takes significantly longer than 5m3.

Villa Rock Exc without blasting BOQ quantity Change

A3/01 9.05 5.00 81%A3/03 8.75 5.00 75%A3/04 18.75 5.00 275%A3/05 22.50 5.00 350%A3/06 19.50 5.00 290%A3/08 25.88 5.00 418%B2/01 60.62 5.00 1112%B2/02 64.28 5.00 1186%B2/04 60.45 5.00 1109%B2/07 4.74 5.00 -5%

The next table summarises excavated material volumes in common material. It can be seen volumes have increased significantly

page 68

Page 69: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa Exc other than rock BOQ quantity Change

A3/04 124.54 38.00 228%A3/05 141.12 38.00 271%A3/09 37.81 38.00 0%A3/30 112.02 38.00 195%A3/31 122.80 38.00 223%A3/32 75.82 38.00 100%B2/01 191.68 70.00 174%B2/02 345.02 70.00 393%B2/03 383.36 70.00 448%B2/04 230.02 70.00 229%B2/05 191.68 70.00 174%B2/06 191.68 70.00 174%B2/07 345.02 70.00 393%B2/08 191.68 70.00 174%

The next table consolidates all the changed quantities of all materials excavated at each villa. Comparing anticipated durations based on bills of quantities and actual, it can be seen in the extreme right hand column the significant variance in time.

The durations shown which range from 26 to 354 calendar days are considered critical, as all subsequent activities that follow excavation are equally delayed.

Villa Rock Blasting (m3)Rock Excavation without

Blasting (m3)Excavation, other than

rock (m3)Duration Taken To Date (Days)

Baseline Duration based on BQ quantities (Days) Critical Delay

Commencement Completion A3/01 9.05 15 October 2007 25 December 2007 71.00 3.00 68.00A3/02 95.00 20 December 2007 on progress 90% 147.00 3.00 144.00A3/03 97.85 8.75 11 September 2007 on progress 95% 247.00 3.58 243.42A3/04 23.00 18.75 124.54 04 June 2007 22 July 2007 48.00 2.00 46.00A3/05 1.14 22.50 141.12 07 June 2007 25 July 2007 48.00 2.63 45.38A3/06 12.69 19.50 09 June 2007 18 December 2007 192.00 2.08 189.92A3/08 11.41 25.88 05 May 2007 16 January 2008 256.00 1.04 254.96A3/09 54.50 37.81 01 January 2008 on progress 90% 135.00 1.04 133.96A3/10 171.68 16 April 2007 15 August 2007 121.00 1.04 119.96A3/11 139.00 14 June 2007 on progress 40% 336.00 1.04 334.96A3/19 47.97 15 June 2007 on progress 20% 335.00 1.04 333.96A3/20 65.10 19 November 2007 on progress 45% 178.00 1.04 176.96A3/21 42.13 14 June 2007 on progress 45% 336.00 1.04 334.96A3/26 120.00 18 April 2007 05 March 2008 322.00 322.00A3/27 125.00 27 August 2007 28 November 2007 93.00 93.00A3/28 4.17 25 June 2007 22 November 2007 150.00 2.08 147.92A3/29 4.18 23 June 2007 10 August 2007 48.00 2.08 45.92A3/30 112.02 04 June 2007 23 July 2007 49.00 2.00 47.00A3/31 2.31 122.80 09 June 2007 24 July 2007 45.00 2.08 42.92A3/32 75.82 04 June 2007 02 July 2007 28.00 2.00 26.00B2/01 239.14 60.62 191.68 20 October 2007 on progress 50% 208.00 1.04 206.96B2/02 64.28 345.02 09 July 2007 18 November 2007 132.00 1.04 130.96B2/03 383.36 11 June 2007 24 July 2007 43.00 1.00 42.00B2/04 147.55 60.45 230.02 11 May 2007 06 March 2008 300.00 1.04 298.96B2/05 13.87 191.68 25 May 2007 on progress 95% 356.00 1.04 354.96B2/06 48.40 191.68 03 December 2007 on progress 65% 164.00 1.04 162.96B2/07 7.73 4.74 345.02 27 May 2007 20 November 2007 177.00 1.04 175.96B2/08 5.04 191.68 24 December 2007 on progress 65% 143.00 1.04 141.96B2/09 28.50 21 November 2007 on progress 75% 176.00 1.04 174.96B2/10 52.50 15 November 2007 on progress 75% 182.00 1.04 180.96

Actual excavation schedule

Note: it has not been possible to separate the delays resulting from blasting and those arising out of increased quantities of other excavated materials. The works are executed at the same time. The table above therefore shows the combined delays arising from the above 3 changed events.

page 69

Page 70: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

4.4.2.Increased Quantity in Reinforced Concrete

The two examples below show changes in scope to standard villa, A3 and B2. The increase in quantities indicated relate to these two villas only. However, the Contract includes a further 32 number of type A and 10 number of Type B and the same change in scope is applicable to all villas. As a consequence, an equal or similar additional time will be required to perform the changed scope of work.

4.4.2.1. Villa Type A3 (Example)

Steel reinforcement, shuttering and the concrete volume has increased considerably and the example below is for one villa only. As detailed in the table, the duration to perform these works has extended from 12 calendar days as planned to 45 calendar days. Once again, the additional time is critical and has delayed dependant and subsequent activities shown on the programme of works.

Villa Type Item Unit Tender Quantity Design Quantities

A3 Frame Reinforcement kg 3,040.00 5,130.00

Concrete m3 32.00 43.00Formwork m2 305.85 351.00

Baseline duration for Tender Quantity 12 Days Actual Duration due to increased quantity 45 Days

The following table compares the planned and actual durations for completing various other concrete components of the building structure.

A3 Type Frame Baseline Duration Revised Duration

set kickers 1.00 2.00Conc. Columns & shear walls 2.00 11.00Conc. G. F Beams 2.00 6.00Conc. Plantroom 2.00 5.00Conc. Floor slab & swimming pool base 2.00 10.00Blockwork 2.00 9.00Conc. Swimming pool sides & overflow channels 3.00 7.00Conc. Ring & tie beams 2.00 7.00

page 70

Page 71: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

4.4.2.2. Villa Type B2 (Example)

Villa Type Item Unit Tender Quantity Design Quantities

B2 FrameReinforcement kg 5,826.00 9,645.00Concrete m3 84.00 102.00Formwork m2 727.00 730.00

Baseline duration based on Tender Quantity 70 Days Actual Duration due to increased quantity 80 Days

B2 Type Frame Baseline Duration Revised Duration

set kickers 1.00 2.00Conc. Columns & shear walls to GF 8.00 6.00Conc. Plantrooms 6.00 8.00Conc. GF slab and beams 4.00 10.00Blockwork up to FF slab 7.00 6.00set kickers on GF 1.00 2.00Conc. Columns & shear walls to FF 8.00 8.00Conc. FF slab & beams 8.00 10.00Blockwork up to roof 7.00 6.00set kickers on FF 1.00 2.00Conc. Columns & shear walls to roof 8.00 8.00Conc. Ring & tie beams 7.00 7.00

In the circumstances, these variations dictate significant divergence from original designs. Therefore, in order to comply with these variations the Contractor’s construction duration for this activity has increased significantly, from an estimated 17 days (substructure) to 37 days for column construction, an increase of 22 working days for each villa.

4.4.3.Suspension of Works

The Contractor was instructed to suspend the works, which suspension lasted 61 days and directly effected progress of the villas listed. This period of suspension is considered a critical delay.

The following table summarises the delay at each villa in progress at the time of the instruction to suspend. However, it should be noted that the effect of this instruction is to delay all the Works on the whole project (except mock-up villas for this particular event).

page 71

Page 72: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa Works Suspended From To Delay (Days)A3/03 Excavation 29-Aug-07 29-Oct-07 61.00A3/04 Concrete foundation 29-Aug-07 29-Oct-07 61.00A3/05 Concrete foundation 29-Aug-07 29-Oct-07 61.00A3/06 Excavation 29-Aug-07 29-Oct-07 61.00A3/08 Excavation 29-Aug-07 29-Oct-07 61.00A3/10 Concrete casting for foundation 29-Aug-07 29-Oct-07 61.00A3/27 Excavation 29-Aug-07 29-Oct-07 61.00A3/28 Excavation 29-Aug-07 29-Oct-07 61.00A3/29 Concrete works 29-Aug-07 29-Oct-07 61.00A3/30 Blinding 29-Aug-07 29-Oct-07 61.00A3/31 Blinding 29-Aug-07 29-Oct-07 61.00B2/02 Excavation 29-Aug-07 29-Oct-07 61.00

4.4.4.Variations to Design

The design drawings issued for construction show all steel roof members as stainless steel although the bill of quantities, as priced at tender, show galvanised steel. As a result the sourcing and procurement time consumed an additional 81 calendar days. This delayed roof construction at the 2 Mock-up Villas and is considered a critical delay.

Description Commenced Completion Delay (Days)Procurement, Fabrication & Installation of Stainless Steel Plates to complete roof structure 26-Nov-07 15-Feb-08 81

4.5. Material Procurement Programme

A critical feature of this project is timely supply of materials to site as most are being sourced off-shore. The timely arrival of materials is an integral part of his planning and any delay in the design and procurement process will automatically have a detrimental impact on his programme of works.

The current situation relative major material procurement is shown in the table below:

page 72

Page 73: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Des c ription of MaterialsQuantity Ordered Date Ordered Amount rec eived B alanc e C omments

F OR AL L 55 VIL L AS

50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order subject to payment to supplierP lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order subject to payment to supplierC rusher Dust 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order subject to payment to supplierAggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order subject to payment to supplierP las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order subject to payment to supplier150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order subject to payment to supplier100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order subject to payment to supplierA252 Weld Mesh (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order subject to payment to supplierHigh tens ile s teel-8,10,12,16,25mm (tons) 500.00 14/01/07 158.00 342.00 B alance on order subject to payment to supplierC edar S hingles (sqm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order subject to payment to supplierIroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order subject to payment to supplier12mm G ypsum boards (S HE E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.DS tainless s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order subject to payment to supplier (Not B .O .Q item)S tainless s teel gusset plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order subject to payment to supplier (Not B .O .Q item)B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order subject to payment to supplierT reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order subject to payment to supplier

The following table summarises the dates drawings have been received. It is clear many drawings were not issued at commencement and therefore, complete procurement of all major materials was not possible.

It is also clear that drawings have been issued progressively throughout the Contract period; again this is contrary to planning expectations. Finally, it is also clear the majority of Interior Design drawings have yet to be issued.

Item Structure/Villa Structural Architectural Interior Design

1 A3 Pool Villa 14-Mar-07 09-Mar-07 09-Apr-072 B223 Standard Villa 14-Mar-07 09-Mar-07 09-Apr-073 B4 Standard Villa with Pool 14-Mar-07 09-Mar-07 09-Apr-074 C311 Executive Villas 14-Mar-07 09-Mar-07 09-Apr-075 P3 Presidential Villas 19-Oct-07 09-Mar-07 09-Apr-076 Sunset Deck 09-Apr-08 22-Aug-07 Not received 7 Employees Facilities Complex 31-Aug-07 22-Aug-07 "8 Excom Villa 19-Oct-07 22-Aug-07 "9 GM Villa 19-Oct-07 22-Aug-07 "

10 Health club 11-Jun-07 28-May-07 "11 Single Treatment room 10-Jun-07 28-May-07 "12 Couple treatment room 25-Jun-07 28-May-07 "13 Sanctum 19-Oct-07 28-May-07 "14 Yoga Pavilion 19-Oct-07 28-May-07 "15 BOH Building 19-Oct-07 28-May-07 "16 Wedding chapel 09-Apr-08 28-May-07 "17 Seafood Resort 11-Jun-07 28-May-07 "18 Retail Pavilion 11-Jun-07 28-May-07 "19 Kid's club 20-Dec-07 08-Jan-08 "20 Recreation House 20-Dec-07 08-Jan-08 "21 Water sport Rental 20-Dec-07 08-Jan-08 "22 Dive Center 20-Dec-07 08-Jan-08 "23 Mechanical Area Not Received Yet 08-Jan-08 "24 3 Meal Restaurant Not Received Yet 08-Jan-08 "25 Signature Pool Not Received Yet 08-Jan-08 "26 Beach Pool Bar Not Received Yet 08-Jan-08 "

Drawing Receipt Register

page 73

Page 74: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

For all the foregoing reasons stated above, the Contractor could not have progressed major material procurement because he was constrained by two issues:

First. Cash flow prevented completion of orders to allow shipment, and

Second. Design drawings were not available at the times consistent with his programme of works.

4.6. Conclusion of Effects of Variations

Additional work is, under the Contract provisions, is also caused by Provisional Sums converted to Variations under Clause 13, by comparison with the value of work envisaged at tender. Nevertheless, additional work executed to date is certain to affect progress because the scope of such variations has only been defined post tender.

The degree of change reflects the changed requirements of the Employer after the award of the project. Although the Contractor received instructions throughout the project to include work anticipated under the Provisional Sums, this has been compounded by the delaying events described even for known works defined at award.

With so many variations, it is not possible to make an attribution of the overall delay to each item. It is true to say that the earlier variations were critical to the Contractor’s progress, and that any delays caused by them are subsumed into the latter period.

However, the delays caused by the changes to the setting out and rock excavation together with suspension of Works, and to other areas of the Works as all the design information, as listed in the tables above, are evident and the primary cause for remaining on site longer.

All the issues described above generally run consecutively, despite late information relative design is continuing simultaneously together with rock excavation. The factual matrix of variation instructions and late information is one of interwoven facts and events. It is not possible to disconnect them. However, the latest programme of works is evidence that work to most of the buildings and villas is in progress at the time of compiling this claim.

page 74

Page 75: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5. Time Analysis

5.1. Method of Analysis

As some of the effects of unforeseen events are concurrent, not all of them will carry an automatic extension of time entitlement. The purpose of the form of analysis described below is to demonstrate which events have contributed to the project over-run and the precise amount of time attributable to each event. At time of preparing this document a Second Request for an Extension of Time has been submitted.

Furthermore, additional costs have arisen as a result of various notified delay and disruption events. The loss and expense are recoverable as:

direct costs in the period when resources suffered delay and disruption, and

indirect costs that will arise in the extended period of the Contract.

The time analysis has been carried out in three stages for each claimable event:

1. At the date immediately prior to the event, the progress status of the project has been established from the progress records. The Programme of Works has been updated with this information, to give a project completion date that was likely to have been achieved if the delay had not occurred. This element of the analysis takes into account and eliminates any delays that might have occurred before the point in time in question, for which the Contractor might be responsible.

2. Next, the effect of the claimable event on the scheduled activities has been calculated. These effects have been inserted into the time scheduled and the network re-analysed. This gives a revised project completion date, assuming that the work proceeds in the same sequence and with the same resources as were originally planned. The difference between this completion date and the progress completion date is the extension of time for the event if it is not reasonably possible to achieve any mitigation of its delaying impact.

3. Finally, there is an obligation on a contractor to attempt to mitigate the effects of any delaying event, if it is reasonably feasible. Accordingly, such opportunities for

page 75

Page 76: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

mitigation have been considered in the evaluation of extension of time entitlement.

Any mitigation measures that the Contractor took, such as additional resources, re-sequencing of work etc., has been detailed and inserted into the schedule. The re-analysis of this programme gives the final assessment of additional time that the Contractor is entitled to claim for the cause under consideration.

These three stages have been repeated for each of the events in turn and the results are reflected in the Contractor’s two requests made to date for an extension of time.

5.1.1.Mitigation by Contractor

The Contractor mitigated the effects of the late supply of design information by starting work on a particular activity without waiting for the whole of the design needed for a particular piece of work. This was particularly noticeable at the Mock-up villas where architectural details were constantly revised as works progressed. The success in taking this phase-advanced approach to work has not produced the results anticipated.

These mitigation measures will be shown in the Programme of Works analysis by changing the logic links between design activities and construction activities.

5.1.2.Time for Completion

It is shown in the subsequent sections of this submission the impact of the changed events and circumstances of the various parts of the Site has caused to the planned progress. In addition, the failure by the Project Manager to provide the necessary design details in due time and the subsequent alterations in mode and manner of execution has also caused the Contractor, because of these events, to be delayed to such an extent that completion of the Contract Works has been unavoidably prolonged and will extend the date set for its completion.

Accordingly, the Contractor is entitled to treat the date for completion as no longer being fixed. That is to say, he is entitled to be allowed such additional time for completion as is reasonably necessary for him to accommodate and deal with the

page 76

Page 77: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Project Manager’s and Employer’s fault to discharge the remainder of his obligations.

5.1.3.Impact on Time - Analyses

The purpose of this exercise is to determine the overall delay to the contractual completion date as indicated in the approved base programme of works. The impacted programme of works will establish the contractor’s entitlement to a delayed completion date for the project. This can then be used to evaluate the financial loss incurred by the contractor and the amount of acceleration required in the event that the client requires the project to be completed earlier.

Events are impacted on the programme according to chronological order to determine the effect in the sequence that the delays took place. When the Event is impacted correctly only the activity is affected and those which are dependent on its completion are delayed. If this activity falls in the critical path of the project then the completion date of the project is also delayed. The critical path of a project may change due to delay in a particular set of activities.

5.1.4.The Events that Impacted Progress

There has been initial delay in receipt of final setting out details for various parts of the project without which it was not possible for the contractor to start construction of that relevant section of the works. Additionally it will be seen that unforeseen ground conditions, the partial suspension of Works caused severe disruption to the contractors planned sequence of execution of the works. Initial events impacted will show the effect that these delays had on the execution of the works.

Furthermore there has been a substantial change to the scope of works as originally anticipated as shown on drawings and what the Contractor encountered on site. A significant variance is attributed to unknown site conditions, as for example, quantity of rock excavated required achieving foundation depth.

The rest of the changes will be attributed to changes in original design other than depicted on tender drawings such as the increased quantities of reinforced concrete. Needless to say the extra volume requires more time to secure placement of steel reinforcement, timber shuttering and concrete placement to columns and slabs, hence more time being required to

page 77

Page 78: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

completion of activity and an overall delay experienced on this section.

The overall effect of these delays and disruptions can be evidenced by a reduced cash flow, and by his current position on site with regards completion of the works. It can be clearly evidenced that not only has the contractor taken steps to mitigate the delays experienced he has also in his eagerness to recover lost time already taken acceleration measures into account and deployed extra resources over and above his planned and contractually required resources.

This exercise serves to establish the contractor’s entitlement to additional time for completion of the project and the cause and effect on his progress to date.

The order of the impacted charts that follow are in the sequence each event occurred at Site.

page 78

Page 79: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.1. Event No 1 – Setting Out

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

184 Villa A3/01

228 Villa A3/02

273 Villa A3/03

318 Villa A3/04

363 Villa A3/05

408 Villa A3/06

453 C311 Executive Villas ( 1 nos)

454 Villa C3/01

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

849 Villa A3/07

850 substructure

851 set out

852 Excavate

853 Conc. Foundation

854 Backfill

855 termite treatment

856 DPC (where applicable)

857 M&E inlet/outlet works - first fix

858 frame

859 set kickers

860 Conc. Columns & shear walls

861 Conc. G. F Beams

862 M&E first fix

863 Conc. Plantroom

864 Conc. Floor slab & swimming pool base

865 Blockwork

866 Conc. Swimming pool sides & overflow channels

867 Conc. Ring & tie beams

868 Roof & Ceiling

869 Fix wall plate & truss

870 Fix purlins and rafters

871 Fix shingles ( subject to receipt of timber)

872 Fix ceiing battens & joists

873 Fix ceiling boards

874 M&E first fix

875 Finishes

876 Wall plaster (internal & External)

877 M&E 1st fix

878 Floor finishes

879 Fix windows & doors

880 Swimming pool finishes

881 M&E final fix

882 Fix fittings and Fixtures

883 M&E Installations

884 Cable Tray, Conduit and Wiring

885 Electrical boards and connections

886 Electrical accessories

887 Light fittings and ceiling fans

888 Hot and cold water

889 Waste and sewage incl. biobox

890 Electric water heater

891 Swimming pool

892 Split unit installation

893 Toilet ventilation, grilles

894 Villa A3/08

939 Villa A3/09

984 Villa A3/10( mock up)

1029 Villa A3/11

1030 substructure

1031 set out

1032 Excavate

1033 Conc. Foundation

1034 Backfill

1035 termite treatment

1036 DPC (where applicable)

1037 M&E inlet/outlet works - first fix

1038 frame

1039 set kickers

1040 Conc. Columns & shear walls

1041 Conc. G. F Beams

1042 M&E first fix

1043 Conc. Plantroom

1044 Conc. Floor slab & swimming pool base

1045 Blockwork

1046 Conc. Swimming pool sides & overflow channels

1047 Conc. Ring & tie beams

1048 Roof & Ceiling

1049 Fix wall plate & truss

1050 Fix purlins and rafters

1051 Fix shingles ( subject to receipt of timber)

1052 Fix ceiing battens & joists

1053 Fix ceiling boards

1054 M&E first fix

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008

page 79

Page 80: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1055 Finishes

1056 Wall plaster (internal & External)

1057 M&E 1st fix

1058 Floor finishes

1059 Fix windows & doors

1060 Swimming pool finishes

1061 M&E final fix

1062 Fix fittings and Fixtures

1063 M&E Installations

1064 Cable Tray, Conduit and Wiring

1065 Electrical boards and connections

1066 Electrical accessories

1067 Light fittings and ceiling fans

1068 Hot and cold water

1069 Waste and sewage incl. biobox

1070 Electric water heater

1071 Swimming pool

1072 Split unit installation

1073 Toilet ventilation, grilles

1074 Villa A3/12

1119 Villa A3/13

1164 Villa A3/18

1209 Villa A3/19

1254 Villa A3/20

1255 substructure

1256 set out

1257 Excavate

1258 Conc. Foundation

1259 Backfill

1260 termite treatment

1261 DPC (where applicable)

1262 M&E inlet/outlet works - first fix

1263 frame

1264 set kickers

1265 Conc. Columns & shear walls

1266 Conc. G. F Beams

1267 M&E first fix

1268 Conc. Plantroom

1269 Conc. Floor slab & swimming pool base

1270 Blockwork

1271 Conc. Swimming pool sides & overflow channels

1272 Conc. Ring & tie beams

1273 Roof & Ceiling

1274 Fix wall plate & truss

1275 Fix purlins and rafters

1276 Fix shingles ( subject to receipt of timber)

1277 Fix ceiing battens & joists

1278 Fix ceiling boards

1279 M&E first fix

1280 Finishes

1281 Wall plaster (internal & External)

1282 M&E 1st fix

1283 Floor finishes

1284 Fix windows & doors

1285 Swimming pool finishes

1286 M&E final fix

1287 Fix fittings and Fixtures

1288 M&E Installations

1289 Cable Tray, Conduit and Wiring

1290 Electrical boards and connections

1291 Electrical accessories

1292 Light fittings and ceiling fans

1293 Hot and cold water

1294 Waste and sewage incl. biobox

1295 Electric water heater

1296 Swimming pool

1297 Split unit installation

1298 Toilet ventilation, grilles

1299 Villa A3/21

1344 Villa A3/22

1389 Villa A3/23

1434 Villa A3/24

1479 Villa A3/25

1524 Villa A3/26

1569 Villa A3/27

1614 B223 Villas ( 7 nos)

1615 Villa B2/01

1665 Villa B2/02

1715 Villa B2/04 (mock up villa)

1765 Villa B2/05

1815 Villa B2/06

1865 Villa B2/07

1915 Villa B2/08

1965 B4 Villa (2 nos.)

1966 Villa B4/01

2011 Villa B4/02

2056 Retail 1( subject to receipt of GFW drawings)

2094 Retail 2( subject to receipt of GFW drawings)

2132 Retail 3( subject to receipt of GFW drawings)

2170 Seafood resort( subject to receipt of GFW drawings)

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2264 Villa A3/14

2309 Villa A3/15

2354 Villa A3/16

2399 Villa A3/17

2444 Villa A3/28

2489 Villa A3/29

2534 Villa A3/30

2535 substructure

2536 set out

2537 Excavate

2538 Conc. Foundation

2539 Backfill

2540 termite treatment

2541 DPC (where applicable)

2542 M&E inlet/outlet works - first fix

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009

page 80

Page 81: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2543 frame

2544 set kickers

2545 Conc. Columns & shear walls

2546 Conc. G. F Beams

2547 M&E first fix

2548 Conc. Plantroom

2549 Conc. Floor slab & swimming pool base

2550 Blockwork

2551 Conc. Swimming pool sides & overflow channels

2552 Conc. Ring & tie beams

2553 Roof & Ceiling

2554 Fix wall plate & truss

2555 Fix purlins and rafters

2556 Fix shingles ( subject to receipt of timber)

2557 Fix ceiing battens & joists

2558 Fix ceiling boards

2559 M&E first fix

2560 Finishes

2561 Wall plaster (internal & External)

2562 M&E 1st fix

2563 Floor finishes

2564 Fix windows & doors

2565 Swimming pool finishes

2566 M&E final fix

2567 Fix fittings and Fixtures

2568 M&E Installations

2569 Cable Tray, Conduit and Wiring

2570 Electrical boards and connections

2571 Electrical accessories

2572 Light fittings and ceiling fans

2573 Hot and cold water

2574 Waste and sewage incl. biobox

2575 Electric water heater

2576 Swimming pool

2577 Split unit installation

2578 Toilet ventilation, grilles

2579 Villa A3/31

2624 Villa A3/32

2664 B223 Villas ( 3 nos)

2665 Villa B2/03

2708 Villa B2/09

2758 Villa B2/10

2808 B4 Standard Villas ( 2 nos)

2809 Villa B4/03

2854 Villa B4/04

2899 BC311 Executive Villa

2900 Villa C3/02

2943 Villa C3/03

2986 Villa C3/04

3029 Villa C3/05

3072 Villa C3/06

3115 P3 Presidential suites ( 3 nos)

3116 Villa P3/01

3159 Villa P3/02

3202 Villa P3/03

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009

The following table provides a summary of the delay caused by late setting out at each of the buildings.

Villa commencement completion commencement completion Baseline duration Revised Duration A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08A3/11 09-Apr-07 02-Jun-08 09-Apr-07 15-Mar-08 341.13 420.08A3/20 25-Apr-07 23-Jun-08 12-Apr-07 15-Mar-08 338.13 425.08A3/30 25-Apr-07 29-Mar-08 28-May-07 15-Mar-08 292.13 339.13

Baseline ProgrammeImpacted Programme

As a result of this delaying event the time for completion has been extended from 16 May 2008 to 9 August 2008, a period of 85 calendar days.

page 81

Page 82: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.2. Event No 2 – Unforeseen Ground Conditions

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

184 Villa A3/01

185 Substructure

186 set out

187 Excavate

188 Conc. Foundation

189 Backfill

190 termite treatment

191 DPC (where applicable)

192 M&E inlet/outlet works - first fix

193 Frame

203 Roof & Ceiling

210 Finishes

217 M&E Installations

228 Villa A3/02

229 substructure

230 set out

231 Excavate

232 Conc. Foundation

233 Backfill

234 termite treatment

235 DPC (where applicable)

236 M&E inlet/outlet works - first fix

237 frame

247 Roof & Ceiling

254 Finishes

262 M&E Installations

273 Villa A3/03

274 substructure

275 set out

276 Excavate

277 Conc. Foundation

278 Backfill

279 termite treatment

280 DPC (where applicable)

281 M&E inlet/outlet works - first fix

282 frame

292 Roof & Ceiling

299 Finishes

307 M&E Installations

318 Villa A3/04

363 Villa A3/05

408 Villa A3/06

409 substructure

410 set out

411 Excavate

412 Conc. Foundation

413 Backfill

414 termite treatment

415 DPC (where applicable)

416 M&E inlet/outlet works - first fix

417 frame

427 Roof & Ceiling

434 Finishes

442 M&E Installations

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

849 Villa A3/07

894 Villa A3/08

895 substructure

896 set out

897 Excavate

898 Conc. Foundation

899 Backfill

900 termite treatment

901 DPC (where applicable)

902 M&E inlet/outlet works - first fix

903 frame

913 Roof & Ceiling

920 Finishes

928 M&E Installations

939 Villa A3/09

940 substructure

941 set out

942 Excavate

943 Conc. Foundation

944 Backfill

945 termite treatment

946 DPC (where applicable)

947 M&E inlet/outlet works - first fix

948 frame

958 Roof & Ceiling

965 Finishes

973 M&E Installations

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

page 82

Page 83: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

984 Villa A3/10

985 substructure

986 set out

987 Excavate

988 Conc. Foundation

989 Backfill

990 termite treatment

991 DPC (where applicable)

992 M&E inlet/outlet works - first fix

993 frame

1003 Roof & Ceiling

1010 Finishes

1018 M&E Installations

1029 Villa A3/11

1030 substructure

1031 set out

1032 Excavate

1033 Conc. Foundation

1034 Backfill

1035 termite treatment

1036 DPC (where applicable)

1037 M&E inlet/outlet works - first fix

1038 frame

1048 Roof & Ceiling

1055 Finishes

1063 M&E Installations

1074 Villa A3/12

1119 Villa A3/13

1164 Villa A3/18

1209 Villa A3/19

1210 substructure

1211 set out

1212 Excavate

1213 Conc. Foundation

1214 Backfill

1215 termite treatment

1216 DPC (where applicable)

1217 M&E inlet/outlet works - first fix

1218 frame

1228 Roof & Ceiling

1235 Finishes

1243 M&E Installations

1254 Villa A3/20

1255 substructure

1256 set out

1257 Excavate

1258 Conc. Foundation

1259 Backfill

1260 termite treatment

1261 DPC (where applicable)

1262 M&E inlet/outlet works - first fix

1263 frame

1273 Roof & Ceiling

1280 Finishes

1288 M&E Installations

1299 Villa A3/21

1300 substructure

1301 set out

1302 Excavate

1303 Conc. Foundation

1304 Backfill

1305 termite treatment

1306 DPC (where applicable)

1307 M&E inlet/outlet works - first fix

1308 frame

1318 Roof & Ceiling

1325 Finishes

1333 M&E Installations

1344 Villa A3/22

1389 Villa A3/23

1434 Villa A3/24

1479 Villa A3/25

1524 Villa A3/26

1525 substructure

1526 set out

1527 Excavate

1528 Conc. Foundation

1529 Backfill

1530 termite treatment

1531 DPC (where applicable)

1532 M&E inlet/outlet works - first fix

1533 frame

1543 Roof & Ceiling

1550 Finishes

1558 M&E Installations

1569 Villa A3/27

1570 substructure

1571 set out

1572 Excavate

1573 Conc. Foundation

1574 Backfill

1575 termite treatment

1576 DPC (where applicable)

1577 M&E inlet/outlet works - first fix

1578 frame

1588 Roof & Ceiling

1595 Finishes

1603 M&E Installations

1614 B223 Villas ( 7 nos)

1615 Villa B2/01

1616 substructure

1617 set out

1618 Excavate

1619 Conc. Foundation

1620 Backfill

1621 termite treatment

1622 DPC (where applicable)

1623 M&E inlet/outlet works - first fix

1624 frame

1640 Roof & Ceiling

1647 Finishes

1654 M&E Installations

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 83

Page 84: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1665 Villa B2/02

1666 substructure

1667 set out

1668 Excavate

1669 Conc. Foundation

1670 Backfill

1671 termite treatment

1672 DPC (where applicable)

1673 M&E inlet/outlet works - first fix

1674 frame

1690 Roof & Ceiling

1697 Finishes

1704 M&E Installations

1715 Villa B2/04

1716 substructure

1717 set out

1718 Excavate

1719 Conc. Foundation

1720 Backfill

1721 termite treatment

1722 DPC (where applicable)

1723 M&E inlet/outlet works - first fix

1724 frame

1740 Roof & Ceiling

1747 Finishes

1754 M&E Installations

1765 Villa B2/05

1766 substructure

1767 set out

1768 Excavate

1769 Conc. Foundation

1770 Backfill

1771 termite treatment

1772 DPC (where applicable)

1773 M&E inlet/outlet works - first fix

1774 frame

1790 Roof & Ceiling

1797 Finishes

1804 M&E Installations

1815 Villa B2/06

1816 substructure

1817 set out

1818 Excavate

1819 Conc. Foundation

1820 Backfill

1821 termite treatment

1822 DPC (where applicable)

1823 M&E inlet/outlet works - first fix

1824 frame

1840 Roof & Ceiling

1847 Finishes

1854 M&E Installations

1865 Villa B2/07

1866 substructure

1867 set out

1868 Excavate

1869 Conc. Foundation

1870 Backfill

1871 termite treatment

1872 DPC (where applicable)

1873 M&E inlet/outlet works - first fix

1874 frame

1890 Roof & Ceiling

1897 Finishes

1904 M&E Installations

1915 Villa B2/08

1916 substructure

1917 set out

1918 Excavate

1919 Conc. Foundation

1920 Backfill

1921 termite treatment

1922 DPC (where applicable)

1923 M&E inlet/outlet works - first fix

1924 frame

1940 Roof & Ceiling

1947 Finishes

1954 M&E Installations

1965 B4 Villa (2 nos.)

1966 Villa B4/01

1967 substructure

1968 set out

1969 Excavate

1970 Conc. Foundation

1971 Backfill

1972 termite treatment

1973 DPC (where applicable)

1974 M&E inlet/outlet works - first fix

1975 frame

1976 set kickers

1977 Conc. Columns & shear walls

1978 Conc. G. F Beams

1979 M&E first fix

1980 Conc. Plantroom

1981 Conc. Floor slab & swimming pool base

1982 Blockwork

1983 Conc. Swimming pool sides & overflow channels

1984 Conc. Ring & tie beams

1985 Roof & Ceiling

1986 Fix wall plate & truss

1987 Fix purlins and rafters

1988 Fix shingles ( subject to receipt of timber)

1989 Fix ceiing battens & joists

1990 Fix ceiling boards

1991 M&E first fix

1992 Finishes

1993 Wall plaster (internal & External)

1994 M&E 1st fix

1995 Floor finishes

1996 Fix windows & doors

1997 Swimming pool finishes

1998 M&E final fix

1999 Fix fittings and Fixtures

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 84

Page 85: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2000 M&E Installations

2001 Cable Tray, Conduit and Wiring

2002 Electrical boards and connections

2003 Electrical accessories

2004 Light fittings and ceiling fans

2005 Hot and cold water

2006 Waste and sewage incl. biobox

2007 Electric water heater

2008 Swimming pool

2009 Split unit installation

2010 Toilet ventilation, grilles

2011 Villa B4/02

2012 substructure

2013 set out

2014 Excavate

2015 Conc. Foundation

2016 Backfill

2017 termite treatment

2018 DPC (where applicable)

2019 M&E inlet/outlet works - first fix

2020 frame

2021 set kickers

2022 Conc. Columns & shear walls

2023 Conc. G. F Beams

2024 M&E first fix

2025 Conc. Plantroom

2026 Conc. Floor slab & swimming pool base

2027 Blockwork

2028 Conc. Swimming pool sides & overflow channels

2029 Conc. Ring & tie beams

2030 Roof & Ceiling

2031 Fix wall plate & truss

2032 Fix purlins and rafters

2033 Fix shingles ( subject to receipt of timber)

2034 Fix ceiing battens & joists

2035 Fix ceiling boards

2036 M&E first fix

2037 Finishes

2038 Wall plaster (internal & External)

2039 M&E 1st fix

2040 Floor finishes

2041 Fix windows & doors

2042 Swimming pool finishes

2043 M&E final fix

2044 Fix fittings and Fixtures

2045 M&E Installations

2046 Cable Tray, Conduit and Wiring

2047 Electrical boards and connections

2048 Electrical accessories

2049 Light fittings and ceiling fans

2050 Hot and cold water

2051 Waste and sewage incl. biobox

2052 Electric water heater

2053 Swimming pool

2054 Split unit installation

2055 Toilet ventilation, grilles

2056 Retail 1( subject to receipt of GFW drawings)

2057 substructure

2058 set out

2059 Excavate (Drill in rock to anchor steel rods)

2060 Conc. Foundation

2061 Backfill ( where applicable )

2062 termite treatment

2063 DPC (where applicable)

2064 M&E inlet/outlet works

2065 frame

2066 set kickers

2067 Conc. Columns & shear walls

2068 Conc. G. F Beams

2069 Conc. Plantroom

2070 Conc. Floor slab

2071 Blockwork

2072 Conc. Ring & tie beams

2073 Roof & Ceiling

2074 Fix wall plate & truss

2075 Fix purlins and rafters

2076 Fix shingles ( subject to receipt of timber)

2077 Fix ceiing battens & joists

2078 Fix ceiling boards

2079 Finishes

2080 Wall plaster (internal & External)

2081 M&E 1st fix

2082 Floor finishes

2083 Fix windows & doors

2084 M&E final fix

2085 Fix fittings and Fixtures

2086 M&E Installations

2087 Cable Tray, Conduit and Wiring

2088 Electrical boards and connections

2089 Electrical accessories

2090 Light fittings and ceiling fans

2091 Hot and cold water

2092 Waste and sewage incl. biobox

2093 Fan coil unit

2094 Retail 2( subject to receipt of GFW drawings)

2095 substructure

2096 set out

2097 Excavate (Drill in rock to anchor steel rods)

2098 Conc. Foundation

2099 Backfill ( where applicable )

2100 termite treatment

2101 DPC (where applicable)

2102 M&E inlet/outlet works

2103 frame

2104 set kickers

2105 Conc. Columns & shear walls

2106 Conc. G. F Beams

2107 Conc. Plantroom

2108 Conc. Floor slab

2109 Blockwork

2110 Conc. Ring & tie beams

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 85

Page 86: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2111 Roof & Ceiling

2112 Fix wall plate & truss

2113 Fix purlins and rafters

2114 Fix shingles ( subject to receipt of timber)

2115 Fix ceiing battens & joists

2116 Fix ceiling boards

2117 Finishes

2118 Wall plaster (internal & External)

2119 M&E 1st fix

2120 Floor finishes

2121 Fix windows & doors

2122 M&E final fix

2123 Fix fittings and Fixtures

2124 M&E Installations

2125 Cable Tray, Conduit and Wiring

2126 Electrical boards and connections

2127 Electrical accessories

2128 Light fittings and ceiling fans

2129 Hot and cold water

2130 Waste and sewage incl. biobox

2131 Fan coil unit

2132 Retail 3( subject to receipt of GFW drawings)

2133 substructure

2134 set out

2135 Excavate (Drill in rock to anchor steel rods)

2136 Conc. Foundation

2137 Backfill ( where applicable )

2138 termite treatment

2139 DPC (where applicable)

2140 M&E inlet/outlet works

2141 frame

2142 set kickers

2143 Conc. Columns & shear walls

2144 Conc. G. F Beams

2145 Conc. Plantroom

2146 Conc. Floor slab

2147 Blockwork

2148 Conc. Ring & tie beams

2149 Roof & Ceiling

2150 Fix wall plate & truss

2151 Fix purlins and rafters

2152 Fix shingles ( subject to receipt of timber)

2153 Fix ceiing battens & joists

2154 Fix ceiling boards

2155 Finishes

2156 Wall plaster (internal & External)

2157 M&E 1st fix

2158 Floor finishes

2159 Fix windows & doors

2160 M&E final fix

2161 Fix fittings and Fixtures

2162 M&E Installations

2163 Cable Tray, Conduit and Wiring

2164 Electrical boards and connections

2165 Electrical accessories

2166 Light fittings and ceiling fans

2167 Hot and cold water

2168 Waste and sewage incl. biobox

2169 Fan coil unit

2170 Seafood resort( subject to receipt of GFW drawings)

2171 substructure

2172 set out

2173 Excavate (Drill in rock to anchor steel rods)

2174 Conc. Foundation

2175 Backfill ( where applicable )

2176 termite treatment

2177 DPC (where applicable)

2178 M&E inlet/outlet works

2179 frame

2180 set kickers

2181 Conc. Columns & shear walls

2182 Conc. G. F Beams

2183 Conc. Plantroom

2184 Conc. Floor slab

2185 Blockwork

2186 Conc. Ring & tie beams

2187 Roof & Ceiling

2188 Fix wall plate & truss

2189 Fix purlins and rafters

2190 Fix shingles ( subject to receipt of timber)

2191 Fix ceiing battens & joists

2192 Fix ceiling boards

2193 Finishes

2194 Wall plaster (internal & External)

2195 M&E 1st fix

2196 Floor finishes

2197 Fix windows & doors

2198 M&E final fix

2199 Fix fittings and Fixtures

2200 M&E Installations

2201 Cable Tray, Conduit and Wiring

2202 Electrical boards and connections

2203 Electrical accessories

2204 Light fittings and ceiling fans

2205 Hot and cold water

2206 Waste and sewage incl. biobox

2207 Kitchen extraction duct

2208 Chilled water piping

2209 Fan coil unit

2210 Toilet ventilation, grilles

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2212 substructure

2213 set out

2214 Excavate (Drill in rock to anchor steel rods)

2215 Conc. Foundation

2216 Backfill ( where applicable )

2217 termite treatment

2218 DPC (where applicable)

2219 M&E inlet/outlet works

2220 frame

2221 set kickers

2222 Conc. Columns & shear walls

2223 Conc. G. F Beams

2224 Conc. Plantroom

2225 Conc. Floor slab

2226 Blockwork

2227 Conc. Ring & tie beams

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2008 2009 2010 2011

page 86

Page 87: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2228 Roof & Ceiling

2229 Fix wall plate & truss

2230 Fix purlins and rafters

2231 Fix shingles ( subject to receipt of timber)

2232 Fix ceiing battens & joists

2233 Fix ceiling boards

2234 Finishes

2235 Wall plaster (internal & External)

2236 M&E 1st fix

2237 Floor finishes

2238 Fix windows & doors

2239 M&E final fix

2240 Fix fittings and Fixtures

2241 M&E Installations

2242 Cable Tray, Conduit and Wiring

2243 Electrical boards and connections

2244 Electrical accessories

2245 Light fittings and ceiling fans

2246 Hot and cold water

2247 Waste and sewage incl. biobox

2248 Fan coil unit

2249 Toilet ventilation, grilles

2250 External works ( subject to receipt of GFW drawings)

2251 Infrastructures

2252 Set out road (cabbies), vehicular

2253 Set out Pedestrian walkways

2254 Set out main water pipe alignment

2255 Set out main electricity network

2256 landscaping

2257 Villas milieu

2258 Main access road milieu

2259 Drainage works ( subject to receipt of EME details)

2260 Set out/implement main sewerage network

2261 Set out/implement main rain water drainage alignment

2262 Lot 3

2263 A3 Villas ( 9 nos)

2264 Villa A3/14

2309 Villa A3/15

2354 Villa A3/16

2399 Villa A3/17

2444 Villa A3/28

2445 substructure

2446 set out

2447 Excavate

2448 Conc. Foundation

2449 Backfill

2450 termite treatment

2451 DPC (where applicable)

2452 M&E inlet/outlet works - first fix

2453 frame

2463 Roof & Ceiling

2470 Finishes

2478 M&E Installations

2489 Villa A3/29

2490 substructure

2491 set out

2492 Excavate

2493 Conc. Foundation

2494 Backfill

2495 termite treatment

2496 DPC (where applicable)

2497 M&E inlet/outlet works - first fix

2498 frame

2508 Roof & Ceiling

2515 Finishes

2523 M&E Installations

2534 Villa A3/30

2535 substructure

2536 set out

2537 Excavate

2538 Conc. Foundation

2539 Backfill

2540 termite treatment

2541 DPC (where applicable)

2542 M&E inlet/outlet works - first fix

2543 frame

2553 Roof & Ceiling

2560 Finishes

2568 M&E Installations

2579 Villa A3/31

2624 Villa A3/32

2625 substructure

2626 set out

2627 Excavate

2628 Conc. Foundation

2629 Backfill

2630 termite treatment

2631 DPC (where applicable)

2632 frame

2641 Roof & Ceiling

2647 Finishes

2653 M&E Installations

2664 B223 Villas ( 3 nos)

2665 Villa B2/03

2666 substructure

2667 set out

2668 Excavate

2669 Conc. Foundation

2670 Backfill

2671 termite treatment

2672 DPC (where applicable)

2673 frame

2686 Roof & Ceiling

2692 Finishes

2697 M&E Installations

2708 Villa B2/09

2709 substructure

2710 set out

2711 Excavate

2712 Conc. Foundation

2713 Backfill

2714 termite treatment

2715 DPC (where applicable)

2716 M&E inlet/outlet works - first fix

2717 frame

2733 Roof & Ceiling

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 87

Page 88: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2740 Finishes

2747 M&E Installations

2758 Villa B2/10

2759 substructure

2760 set out

2761 Excavate

2762 Conc. Foundation

2763 Backfill

2764 termite treatment

2765 DPC (where applicable)

2766 M&E inlet/outlet works - first fix

2767 frame

2783 Roof & Ceiling

2790 Finishes

2797 M&E Installations

2808 B4 Standard Villas ( 2 nos)

2809 Villa B4/03

2810 substructure

2811 set out

2812 Excavate

2813 Conc. Foundation

2814 Backfill

2815 termite treatment

2816 DPC (where applicable)

2817 M&E inlet/outlet works - first fix

2818 frame

2819 set kickers

2820 Conc. Columns & shear walls

2821 Conc. G. F Beams

2822 M&E first fix

2823 Conc. Plantroom

2824 Conc. Floor slab & swimming pool base

2825 Blockwork

2826 Conc. Swimming pool sides & overflow channels

2827 Conc. Ring & tie beams

2828 Roof & Ceiling

2829 Fix wall plate & truss

2830 Fix purlins and rafters

2831 Fix shingles ( subject to receipt of timber)

2832 Fix ceiing battens & joists

2833 Fix ceiling boards

2834 M&E first fix

2835 Finishes

2836 Wall plaster (internal & External)

2837 M&E 1st fix

2838 Floor finishes

2839 Fix windows & doors

2840 Swimming pool finishes

2841 M&E final fix

2842 Fix fittings and Fixtures

2843 M&E Installations

2844 Cable Tray, Conduit and Wiring

2845 Electrical boards and connections

2846 Electrical accessories

2847 Light fittings and ceiling fans

2848 Hot and cold water

2849 Waste and sewage incl. biobox

2850 Electric water heater

2851 Swimming pool

2852 Split unit installation

2853 Toilet ventilation, grilles

2854 Villa B4/04

2855 substructure

2856 set out

2857 Excavate

2858 Conc. Foundation

2859 Backfill

2860 termite treatment

2861 DPC (where applicable)

2862 M&E inlet/outlet works - first fix

2863 frame

2864 set kickers

2865 Conc. Columns & shear walls

2866 Conc. G. F Beams

2867 M&E first fix

2868 Conc. Plantroom

2869 Conc. Floor slab & swimming pool base

2870 Blockwork

2871 Conc. Swimming pool sides & overflow channels

2872 Conc. Ring & tie beams

2873 Roof & Ceiling

2874 Fix wall plate & truss

2875 Fix purlins and rafters

2876 Fix shingles ( subject to receipt of timber)

2877 Fix ceiing battens & joists

2878 Fix ceiling boards

2879 M&E first fix

2880 Finishes

2881 Wall plaster (internal & External)

2882 M&E 1st fix

2883 Floor finishes

2884 Fix windows & doors

2885 Swimming pool finishes

2886 M&E final fix

2887 Fix fittings and Fixtures

2888 M&E Installations

2889 Cable Tray, Conduit and Wiring

2890 Electrical boards and connections

2891 Electrical accessories

2892 Light fittings and ceiling fans

2893 Hot and cold water

2894 Waste and sewage incl. biobox

2895 Electric water heater

2896 Swimming pool

2897 Split unit installation

2898 Toilet ventilation, grilles

2899 BC311 Executive Villa

2900 Villa C3/02

2943 Villa C3/03

2986 Villa C3/04

3029 Villa C3/05

3072 Villa C3/06

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010

page 88

Page 89: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3115 P3 Presidential suites ( 3 nos)

3116 Villa P3/01

3159 Villa P3/02

3202 Villa P3/03

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3290 Set out/implement main sewerage network

3291 Set out/implement main rain water drainage alignment

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2008 2009 2010 2011

The following table provides summary of the current delay caused by unforeseen ground conditions at each of the buildings. This change involved significant delay and difficulty excavating hard rock.

Villa commencement completion commencement completion Baseline duration Revised Duration A3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13A3/32 28-May-07 16-Nov-07 28-May-07 16-Nov-07 172.04 172.04B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08B2/03 28-May-07 25-Dec-07 28-May-07 04-Dec-07 190.17 211.13B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13

Impacted Programme Baseline Programme

The next table records the delays to other buildings as a consequence of the delays to the current to preceding tasks. In retaining the original planned sequence depicted on the original programme of works, the completion date is extended to 9 September 2009.

page 89

Page 90: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa commencement completion commencement completion Delay P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-08 367.00Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-08 367.00Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-08 290.00Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-08 290.00GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-08 367.00Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-08 367.00Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 372.00Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-08 440.00Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-08 440.00Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00

Impacted Programme Baseline Programme

It should be noted that rock excavation is continuing at various sites where excavation activities is yet to start. Consequently, the delay attributed to this event is continuing.

As a result of the current delay caused by this event the time for completion has been further extended from 9 August 2008 to 9 September 2009, a period of 396 calendar days.

However, in recognition of more rock excavation at other areas of the Site it is anticipated further delays will be experienced. Accordingly, the Contractor gives notice of further delays likely at the remaining areas of the site where buildings will be positioned.

The revised completion date is now 9 September 2009.

page 90

Page 91: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.3. Event No 3 – Later Receipt of Design Information

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

498 substructure

499 set out ( subject to receipt of GFW dwg by Mid June 07)

500 Excavate (Drill in rock to anchor steel rods as required)

501 Conc. Foundation

502 Backfill ( where applicable )

503 termite treatment

504 DPC (where applicable)

505 M&E inlet/outlet works

506 frame

507 set kickers

508 Conc. Columns & shear walls upto roof

509 Conc. G. F Beams

510 Conc. Floor slab GF

511 Blockwork upto roof

512 Conc. Ring & tie beams

513 Roof & Ceiling

514 Fix wall plate & truss

515 Fix purlins and rafters

516 Fix shingles ( subject to receipt of timber)

517 Fix ceiing battens & joists

518 Fix ceiling boards

519 Finishes

520 Wall plaster (internal & External)

521 M&E 1st fix

522 Floor finishes

523 Fix windows & doors

524 M&E final fix

525 Fix fittings and Fixtures

526 M&E Installations

527 Cable Tray, Conduit and Wiring

528 Electrical boards and connections

529 Electrical accessories

530 Light fittings and ceiling fans

531 Hot and cold water

532 Waste and sewage incl. biobox

533 Electric water heater

534 Swimming pool

535 Split unit installation

536 Toilet ventilation, grilles

537 Employees Facilities ( subject to receipt of GFW drawings)

538 substructure

539 set out

540 Excavate

541 Conc. Foundation

542 Backfill ( where applicable )

543 termite treatment

544 DPC (where applicable)

545 M&E inlet/outlet works

546 frame

547 set kickers

548 Conc. Columns & shear walls upto GF floor level

549 Conc. G. F Beams

550 Conc. G.F Floor slab

551 Conc. Columns & shear walls upto FF level

552 Blockwork upto FF level

553 Conc. F. Floor slab

554 Conc. Columns & shear walls upto roof level

555 Blockwork upto roof

556 Conc. Ring & tie beams

557 Roof & Ceiling

558 Fix wall plate & truss

559 Fix purlins and rafters

560 Fix shingles ( subject to receipt of timber)

561 Fix ceiing battens & joists

562 Fix ceiling boards

563 Finishes

564 Wall plaster (internal & External)

565 M&E 1st fix

566 Floor finishes

567 Fix windows & doors

568 M&E final fix

569 Fix fittings and Fixtures

570 M&E Installations

571 Cable Tray, Conduit and Wiring

572 Electrical boards and connections

573 Electrical accessories

574 Light fittings and ceiling fans

575 Hot and cold water

576 Waste and sewage incl. biobox

577 Boiler

578 Chiller

579 Fan coil unit

580 Toilet ventilation, grilles

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

626 substructure

627 set out

628 Excavate (Drill in rock to anchor steel rods)

629 Conc. Foundation

630 Backfill ( where applicable )

631 termite treatment

632 DPC (where applicable)

633 M&E inlet/outlet works

634 frame

635 set kickers

636 Conc. Columns & shear walls

637 Conc. G. F Beams

638 Conc. substructure

639 Conc. Floor slab

640 Blockwork

641 Conc. Ring & tie beams

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

page 91

Page 92: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

642 Roof & Ceiling

643 Fix wall plate & truss

644 Fix purlins and rafters

645 Fix shingles ( subject to receipt of timber)

646 Fix ceiing battens & joists

647 Fix ceiling boards

648 Finishes

649 Wall plaster (internal & External)

650 M&E 1st fix

651 Floor finishes

652 Fix windows & doors

653 M&E final fix

654 Fix fittings and Fixtures

655 M&E Installations

656 Cable Tray, Conduit and Wiring

657 Electrical boards and connections

658 Electrical accessories

659 Light fittings and ceiling fans

660 Hot and cold water

661 Waste and sewage incl. biobox

662 Boiler

663 Chiller

664 Fan coil unit

665 Toilet ventilation, grilles

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

708 substructure

709 set out

710 Excavate

711 Conc. Foundation

712 Backfill ( where applicable )

713 termite treatment

714 DPC (where applicable)

715 M&E inlet/outlet works

716 frame

717 set kickers

718 Conc. Columns & shear walls upto GF floor level

719 Conc. G. F Beams

720 Conc. G.F Floor slab

721 Conc. Columns & shear walls upto FF level

722 Blockwork upto FF level

723 Conc. F. Floor slab

724 Conc. Columns & shear walls upto roof level

725 Blockwork upto roof

726 Conc. Ring & tie beams

727 Roof & Ceiling

728 Fix wall plate & truss

729 Fix purlins and rafters

730 Fix shingles ( subject to receipt of timber)

731 Fix ceiing battens & joists

732 Fix ceiling boards

733 Finishes

734 Wall plaster (internal & External)

735 M&E 1st fix

736 Floor finishes

737 Fix windows & doors

738 M&E final fix

739 Fix fittings and Fixtures

740 M&E Installations

741 Cable Tray, Conduit and Wiring

742 Electrical boards and connections

743 Electrical accessories

744 Light fittings and ceiling fans

745 Hot and cold water

746 Waste and sewage incl. biobox

747 Electric water heater

748 Split unit installation

749 Toilet ventilation, grilles

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

1614 B223 Villas ( 7 nos)

1965 B4 Villa (2 nos.)

2056 Retail 1( subject to receipt of GFW drawings)

2057 substructure

2058 set out

2059 Excavate (Drill in rock to anchor steel rods)

2060 Conc. Foundation

2061 Backfill ( where applicable )

2062 termite treatment

2063 DPC (where applicable)

2064 M&E inlet/outlet works

2065 frame

2066 set kickers

2067 Conc. Columns & shear walls

2068 Conc. G. F Beams

2069 Conc. Plantroom

2070 Conc. Floor slab

2071 Blockwork

2072 Conc. Ring & tie beams

2073 Roof & Ceiling

2074 Fix wall plate & truss

2075 Fix purlins and rafters

2076 Fix shingles ( subject to receipt of timber)

2077 Fix ceiing battens & joists

2078 Fix ceiling boards

2079 Finishes

2080 Wall plaster (internal & External)

2081 M&E 1st fix

2082 Floor finishes

2083 Fix windows & doors

2084 M&E final fix

2085 Fix fittings and Fixtures

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 92

Page 93: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2086 M&E Installations

2087 Cable Tray, Conduit and Wiring

2088 Electrical boards and connections

2089 Electrical accessories

2090 Light fittings and ceiling fans

2091 Hot and cold water

2092 Waste and sewage incl. biobox

2093 Fan coil unit

2094 Retail 2( subject to receipt of GFW drawings)

2095 substructure

2096 set out

2097 Excavate (Drill in rock to anchor steel rods)

2098 Conc. Foundation

2099 Backfill ( where applicable )

2100 termite treatment

2101 DPC (where applicable)

2102 M&E inlet/outlet works

2103 frame

2104 set kickers

2105 Conc. Columns & shear walls

2106 Conc. G. F Beams

2107 Conc. Plantroom

2108 Conc. Floor slab

2109 Blockwork

2110 Conc. Ring & tie beams

2111 Roof & Ceiling

2112 Fix wall plate & truss

2113 Fix purlins and rafters

2114 Fix shingles ( subject to receipt of timber)

2115 Fix ceiing battens & joists

2116 Fix ceiling boards

2117 Finishes

2118 Wall plaster (internal & External)

2119 M&E 1st fix

2120 Floor finishes

2121 Fix windows & doors

2122 M&E final fix

2123 Fix fittings and Fixtures

2124 M&E Installations

2125 Cable Tray, Conduit and Wiring

2126 Electrical boards and connections

2127 Electrical accessories

2128 Light fittings and ceiling fans

2129 Hot and cold water

2130 Waste and sewage incl. biobox

2131 Fan coil unit

2132 Retail 3( subject to receipt of GFW drawings)

2133 substructure

2134 set out

2135 Excavate (Drill in rock to anchor steel rods)

2136 Conc. Foundation

2137 Backfill ( where applicable )

2138 termite treatment

2139 DPC (where applicable)

2140 M&E inlet/outlet works

2141 frame

2142 set kickers

2143 Conc. Columns & shear walls

2144 Conc. G. F Beams

2145 Conc. Plantroom

2146 Conc. Floor slab

2147 Blockwork

2148 Conc. Ring & tie beams

2149 Roof & Ceiling

2150 Fix wall plate & truss

2151 Fix purlins and rafters

2152 Fix shingles ( subject to receipt of timber)

2153 Fix ceiing battens & joists

2154 Fix ceiling boards

2155 Finishes

2156 Wall plaster (internal & External)

2157 M&E 1st fix

2158 Floor finishes

2159 Fix windows & doors

2160 M&E final fix

2161 Fix fittings and Fixtures

2162 M&E Installations

2163 Cable Tray, Conduit and Wiring

2164 Electrical boards and connections

2165 Electrical accessories

2166 Light fittings and ceiling fans

2167 Hot and cold water

2168 Waste and sewage incl. biobox

2169 Fan coil unit

2170 Seafood resort( subject to receipt of GFW drawings)

2171 substructure

2172 set out

2173 Excavate (Drill in rock to anchor steel rods)

2174 Conc. Foundation

2175 Backfill ( where applicable )

2176 termite treatment

2177 DPC (where applicable)

2178 M&E inlet/outlet works

2179 frame

2180 set kickers

2181 Conc. Columns & shear walls

2182 Conc. G. F Beams

2183 Conc. Plantroom

2184 Conc. Floor slab

2185 Blockwork

2186 Conc. Ring & tie beams

2187 Roof & Ceiling

2188 Fix wall plate & truss

2189 Fix purlins and rafters

2190 Fix shingles ( subject to receipt of timber)

2191 Fix ceiing battens & joists

2192 Fix ceiling boards

2193 Finishes

2194 Wall plaster (internal & External)

2195 M&E 1st fix

2196 Floor finishes

2197 Fix windows & doors

2198 M&E final fix

2199 Fix fittings and Fixtures

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2008 2009 2010 2011

page 93

Page 94: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2200 M&E Installations

2201 Cable Tray, Conduit and Wiring

2202 Electrical boards and connections

2203 Electrical accessories

2204 Light fittings and ceiling fans

2205 Hot and cold water

2206 Waste and sewage incl. biobox

2207 Kitchen extraction duct

2208 Chilled water piping

2209 Fan coil unit

2210 Toilet ventilation, grilles

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2664 B223 Villas ( 3 nos)

2808 B4 Standard Villas ( 2 nos)

2899 BC311 Executive Villa

3115 P3 Presidential suites ( 3 nos)

3116 Villa P3/01

3117 substructure

3118 set out

3119 Excavate

3120 Conc. Foundation

3121 Backfill ( where applicable )

3122 termite treatment

3123 DPC (where applicable)

3124 M&E inlet/outlet works

3125 frame

3126 set kickers

3127 Conc. Columns & shear walls

3128 Conc. G. F Beams

3129 Conc. Plantroom

3130 Conc. Floor slab & swimming pool base

3131 Blockwork

3132 Conc. Swimming pool sides & overflow channels

3133 Conc. Ring & tie beams

3134 Roof & Ceiling

3135 Fix wall plate & truss

3136 Fix purlins and rafters

3137 Fix shingles ( subject to receipt of timber)

3138 Fix ceiing battens & joists

3139 Fix ceiling boards

3140 Finishes

3141 Wall plaster (internal & External)

3142 M&E 1st fix

3143 Floor finishes

3144 Fix windows & doors

3145 Swimming pool finishes

3146 M&E final fix

3147 Fix fittings and Fixtures

3148 M&E Installations

3149 Cable Tray, Conduit and Wiring

3150 Electrical boards and connections

3151 Electrical accessories

3152 Light fittings and ceiling fans

3153 Hot and cold water

3154 Waste and sewage incl. biobox

3155 Electric water heater

3156 Swimming pool

3157 Split unit installation

3158 Toilet ventilation, grilles

3159 Villa P3/02

3160 substructure

3161 set out

3162 Excavate

3163 Conc. Foundation

3164 Backfill ( where applicable )

3165 termite treatment

3166 DPC (where applicable)

3167 M&E inlet/outlet works

3168 frame

3169 set kickers

3170 Conc. Columns & shear walls

3171 Conc. G. F Beams

3172 Conc. Plantroom

3173 Conc. Floor slab & swimming pool base

3174 Blockwork

3175 Conc. Swimming pool sides & overflow channels

3176 Conc. Ring & tie beams

3177 Roof & Ceiling

3178 Fix wall plate & truss

3179 Fix purlins and rafters

3180 Fix shingles ( subject to receipt of timber)

3181 Fix ceiing battens & joists

3182 Fix ceiling boards

3183 Finishes

3184 Wall plaster (internal & External)

3185 M&E 1st fix

3186 Floor finishes

3187 Fix windows & doors

3188 Swimming pool finishes

3189 M&E final fix

3190 Fix fittings and Fixtures

3191 M&E Installations

3192 Cable Tray, Conduit and Wiring

3193 Electrical boards and connections

3194 Electrical accessories

3195 Light fittings and ceiling fans

3196 Hot and cold water

3197 Waste and sewage incl. biobox

3198 Electric water heater

3199 Swimming pool

3200 Split unit installation

3201 Toilet ventilation, grilles

3202 Villa P3/03

3203 substructure

3204 set out

3205 Excavate

3206 Conc. Foundation

3207 Backfill ( where applicable )

3208 termite treatment

3209 DPC (where applicable)

3210 M&E inlet/outlet works

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 94

Page 95: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3211 frame

3220 Roof & Ceiling

3226 Finishes

3234 M&E Installations

3235 Cable Tray, Conduit and Wiring

3236 Electrical boards and connections

3237 Electrical accessories

3238 Light fittings and ceiling fans

3239 Hot and cold water

3240 Waste and sewage incl. biobox

3241 Electric water heater

3242 Swimming pool

3243 Split unit installation

3244 Toilet ventilation, grilles

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3246 substructure

3247 set out

3248 Excavate

3249 Conc. Foundation

3250 Backfill ( where applicable )

3251 termite treatment

3252 DPC (where applicable)

3253 M&E inlet/outlet works

3254 frame

3255 set kickers

3256 Conc. Columns & shear walls

3257 Conc. G. F Beams

3258 Conc. Plantroom

3259 Conc. Floor slab

3260 Blockwork

3261 Conc. Ring & tie beams

3262 Roof & Ceiling

3263 Fix wall plate & truss

3264 Fix purlins and rafters

3265 Fix shingles ( subject to receipt of timber)

3266 Fix ceiing battens & joists

3267 Fix ceiling boards

3268 Finishes

3269 Wall plaster (internal & External)

3270 M&E 1st fix

3271 Floor finishes

3272 Fix windows & doors

3273 M&E final fix

3274 Fix fittings and Fixtures

3275 M&E Installations

3276 Cable Tray, Conduit and Wiring

3277 Electrical boards and connections

3278 Electrical accessories

3279 Light fittings and ceiling fans

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3294 substructure

3295 set out

3296 Excavate

3297 Conc. Foundation

3298 Backfill ( where applicable )

3299 termite treatment

3300 DPC (where applicable)

3301 M&E inlet/outlet works

3302 frame

3303 set kickers

3304 Conc. Columns & shear walls

3305 Conc. G. F Beams

3306 Conc. Plantroom

3307 Conc. Floor slab

3308 Blockwork

3309 Conc. Ring & tie beams

3310 Roof & Ceiling

3311 Fix wall plate & truss

3312 Fix purlins and rafters

3313 Fix shingles ( subject to receipt of timber)

3314 Fix ceiing battens & joists

3315 Fix ceiling boards

3316 Finishes

3317 Wall plaster (internal & External)

3318 M&E 1st fix

3319 Floor finishes

3320 Fix windows & doors

3321 M&E final fix

3322 Fix fittings and Fixtures

3323 M&E Installations

3324 Cable Tray, Conduit and Wiring

3325 Electrical boards and connections

3326 Electrical accessories

3327 Light fittings and ceiling fans

3328 Hot and cold water

3329 Waste and sewage incl. biobox

3330 Electric water heater

3331 Water feature

3332 Split unit installation

3333 Toilet ventilation, grilles

3334 Single treatment room( subject to receipt of GFW drawings)

3335 substructure

3336 set out

3337 Excavate

3338 Conc. Foundation

3339 Backfill ( where applicable )

3340 termite treatment

3341 DPC (where applicable)

3342 M&E inlet/outlet works

3343 frame

3344 set kickers

3345 Conc. Columns & shear walls

3346 Conc. G. F Beams

3347 Conc. Plantroom

3348 Conc. Floor slab

3349 Blockwork

3350 Conc. Ring & tie beams

3351 Roof & Ceiling

3352 Fix wall plate & truss

3353 Fix purlins and rafters

3354 Fix shingles ( subject to receipt of timber)

3355 Fix ceiing battens & joists

3356 Fix ceiling boards

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011

page 95

Page 96: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3357 Finishes

3358 Wall plaster (internal & External)

3359 M&E 1st fix

3360 Floor finishes

3361 Fix windows & doors

3362 M&E final fix

3363 Fix fittings and Fixtures

3364 M&E Installations

3365 Cable Tray, Conduit and Wiring

3366 Electrical boards and connections

3367 Electrical accessories

3368 Light fittings and ceiling fans

3369 Hot and cold water

3370 Waste and sewage incl. biobox

3371 Electric water heater

3372 Water feature

3373 Split unit installation

3374 Toilet ventilation, grilles

3375 Dive Centre( subject to receipt of GFW drawings)

3376 substructure

3377 set out

3378 Excavate

3379 Conc. Foundation

3380 Backfill ( where applicable )

3381 termite treatment

3382 DPC (where applicable)

3383 M&E inlet/outlet works

3384 frame

3385 set kickers

3386 Conc. Columns & shear walls

3387 Conc. G. F Beams

3388 Conc. Plantroom

3389 Conc. Floor slab

3390 Blockwork

3391 Conc. Ring & tie beams

3392 Roof & Ceiling

3393 Fix wall plate & truss

3394 Fix purlins and rafters

3395 Fix shingles ( subject to receipt of timber)

3396 Fix ceiing battens & joists

3397 Fix ceiling boards

3398 Finishes

3399 Wall plaster (internal & External)

3400 M&E 1st fix

3401 Floor finishes

3402 Fix windows & doors

3403 M&E final fix

3404 Fix fittings and Fixtures

3405 M&E Installations

3406 Cable Tray, Conduit and Wiring

3407 Electrical boards and connections

3408 Electrical accessories

3409 Light fittings and ceiling fans

3410 Hot and cold water

3411 Waste and sewage incl. biobox

3412 Toilet ventilation, grilles

3413 Kid's club( subject to receipt of GFW drawings)

3414 substructure

3415 set out

3416 Excavate

3417 Conc. Foundation

3418 Backfill ( where applicable )

3419 termite treatment

3420 DPC (where applicable)

3421 M&E inlet/outlet works

3422 frame

3423 set kickers

3424 Conc. Columns & shear walls

3425 Conc. G. F Beams

3426 Conc. Plantroom

3427 Conc. Floor slab

3428 Blockwork

3429 Conc. Ring & tie beams

3430 Roof & Ceiling

3431 Fix wall plate & truss

3432 Fix purlins and rafters

3433 Fix shingles ( subject to receipt of timber)

3434 Fix ceiing battens & joists

3435 Fix ceiling boards

3436 Finishes

3437 Wall plaster (internal & External)

3438 M&E 1st fix

3439 Floor finishes

3440 Fix windows & doors

3441 M&E final fix

3442 Fix fittings and Fixtures

3443 M&E Installations

3444 Cable Tray, Conduit and Wiring

3445 Electrical boards and connections

3446 Electrical accessories

3447 Light fittings and ceiling fans

3448 Hot and cold water

3449 Waste and sewage incl. biobox

3450 Electric water heater

3451 Toilet ventilation, grilles

3452 Recreation House( subject to receipt of GFW drawings)

3453 substructure

3454 set out

3455 Excavate

3456 Conc. Foundation

3457 Backfill ( where applicable )

3458 termite treatment

3459 DPC (where applicable)

3460 M&E inlet/outlet works

3461 frame

3462 set kickers

3463 Conc. Columns & shear walls

3464 Conc. G. F Beams

3465 Conc. Plantroom

3466 Conc. Floor slab

3467 Blockwork

3468 Conc. Ring & tie beams

3469 Roof & Ceiling

3470 Fix wall plate & truss

3471 Fix purlins and rafters

3472 Fix shingles ( subject to receipt of timber)

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011

page 96

Page 97: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3473 Fix ceiing battens & joists

3474 Fix ceiling boards

3475 Finishes

3476 Wall plaster (internal & External)

3477 M&E 1st fix

3478 Floor finishes

3479 Fix windows & doors

3480 M&E final fix

3481 Fix fittings and Fixtures

3482 M&E Installations

3483 Cable Tray, Conduit and Wiring

3484 Electrical boards and connections

3485 Electrical accessories

3486 Light fittings and ceiling fans

3487 Hot and cold water

3488 Waste and sewage incl. biobox

3489 Electric water heater

3490 Toilet ventilation, grilles

3491 Watersports rental( subject to receipt of GFW drawings)

3492 substructure

3493 set out

3494 Excavate

3495 Conc. Foundation

3496 Backfill ( where applicable )

3497 termite treatment

3498 DPC (where applicable)

3499 M&E inlet/outlet works

3500 frame

3501 set kickers

3502 Conc. Columns & shear walls

3503 Conc. G. F Beams

3504 Conc. Plantroom

3505 Conc. Floor slab

3506 Blockwork

3507 Conc. Ring & tie beams

3508 Roof & Ceiling

3509 Fix wall plate & truss

3510 Fix purlins and rafters

3511 Fix shingles ( subject to receipt of timber)

3512 Fix ceiing battens & joists

3513 Fix ceiling boards

3514 Finishes

3515 Wall plaster (internal & External)

3516 M&E 1st fix

3517 Floor finishes

3518 Fix windows & doors

3519 M&E final fix

3520 Fix fittings and Fixtures

3521 M&E Installations

3522 Cable Tray, Conduit and Wiring

3523 Electrical boards and connections

3524 Electrical accessories

3525 Light fittings and ceiling fans

3526 Hot and cold water

3527 Waste and sewage incl. biobox

3528 Toilet ventilation, grilles

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3530 substructure

3531 set out

3532 Excavate

3533 Conc. Foundation

3534 Backfill ( where applicable )

3535 termite treatment

3536 DPC (where applicable)

3537 M&E inlet/outlet works

3538 frame

3539 set kickers

3540 Conc. Columns & shear walls

3541 Conc. G. F Beams

3542 Conc. Plantroom

3543 Conc. Floor slab

3544 Blockwork

3545 Conc. Ring & tie beams

3546 Roof & Ceiling

3547 Fix wall plate & truss

3548 Fix purlins and rafters

3549 Fix shingles ( subject to receipt of timber)

3550 Fix ceiing battens & joists

3551 Fix ceiling boards

3552 Finishes

3553 Wall plaster (internal & External)

3554 M&E 1st fix

3555 Floor finishes

3556 Fix windows & doors

3557 M&E final fix

3558 Fix fittings and Fixtures

3559 M&E Installations

3560 Cable Tray, Conduit and Wiring

3561 Electrical boards and connections

3562 Electrical accessories

3563 Light fittings and ceiling fans

3564 Hot and cold water

3565 Waste and sewage incl. biobox

3566 Boiler

3567 Chiller

3568 Fan coil unit

3569 Ducting and fans

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3571 substructure

3572 set out

3573 Excavate

3574 Conc. Foundation

3575 Backfill ( where applicable )

3576 termite treatment

3577 DPC (where applicable)

3578 M&E inlet/outlet works

3579 frame

3580 set kickers

3581 Conc. Columns & shear walls

3582 Conc. G. F Beams

3583 Conc. Plantroom

3584 Conc. Floor slab

3585 Blockwork

3586 Conc. Ring & tie beams

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011

page 97

Page 98: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3587 Roof & Ceiling

3588 Fix wall plate & truss

3589 Fix purlins and rafters

3590 Fix shingles ( subject to receipt of timber)

3591 Fix ceiing battens & joists

3592 Fix ceiling boards

3593 Finishes

3594 Wall plaster (internal & External)

3595 M&E 1st fix

3596 Floor finishes

3597 Fix windows & doors

3598 M&E final fix

3599 Fix fittings and Fixtures

3600 M&E Installations

3601 Cable Tray, Conduit and Wiring

3602 Electrical boards and connections

3603 Electrical accessories

3604 Light fittings and ceiling fans

3605 Hot and cold water

3606 Waste and sewage incl. biobox

3607 Electric water heater

3608 Beach Pool

3609 Split unit installation

3610 Toilet ventilation, grilles

3611 Signature Pool area( subject to receipt of GFW drawings)

3612 substructure

3613 set out

3614 Excavate

3615 Conc. Foundation

3616 Backfill ( where applicable )

3617 termite treatment

3618 DPC (where applicable)

3619 M&E inlet/outlet works

3620 frame

3621 set kickers

3622 Conc. Columns & shear walls

3623 Conc. G. F Beams

3624 Conc. Plantroom

3625 Conc. Floor slab

3626 Blockwork

3627 Conc. Ring & tie beams

3628 Roof & Ceiling

3629 Fix wall plate & truss

3630 Fix purlins and rafters

3631 Fix shingles ( subject to receipt of timber)

3632 Fix ceiing battens & joists

3633 Fix ceiling boards

3634 Finishes

3635 Wall plaster (internal & External)

3636 M&E 1st fix

3637 Floor finishes

3638 Fix windows & doors

3639 M&E final fix

3640 Fix fittings and Fixtures

3641 M&E Installations

3642 Cable Tray, Conduit and Wiring

3643 Electrical boards and connections

3644 Electrical accessories

3645 Light fittings and ceiling fans

3646 Hot and cold water

3647 Waste and sewage incl. biobox

3648 Electric water heater

3649 Signature Pool

3650 Wedding Chapel( subject to receipt of GFW drawings)

3651 substructure

3652 set out

3653 Excavate

3654 Conc. Foundation

3655 Backfill ( where applicable )

3656 termite treatment

3657 DPC (where applicable)

3658 M&E inlet/outlet works

3659 frame

3660 set kickers

3661 Conc. Columns & shear walls

3662 Conc. G. F Beams

3663 Conc. Plantroom

3664 Conc. Floor slab

3665 Blockwork

3666 Conc. Ring & tie beams

3667 Roof & Ceiling

3668 Fix wall plate & truss

3669 Fix purlins and rafters

3670 Fix shingles ( subject to receipt of timber)

3671 Fix ceiing battens & joists

3672 Fix ceiling boards

3673 Finishes

3674 Wall plaster (internal & External)

3675 M&E 1st fix

3676 Floor finishes

3677 Fix windows & doors

3678 M&E final fix

3679 Fix fittings and Fixtures

3680 M&E Installations

3681 Cable Tray, Conduit and Wiring

3682 Electrical boards and connections

3683 Electrical accessories

3684 Light fittings and ceiling fans

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3686 substructure

3687 set out

3688 Excavate

3689 Conc. Foundation

3690 Backfill ( where applicable )

3691 termite treatment

3692 DPC (where applicable)

3693 M&E inlet/outlet works

3694 frame

3695 set kickers

3696 Conc. Columns & shear walls

3697 Conc. G. F Beams

3698 Conc. Plantroom

3699 Conc. Floor slab

3700 Blockwork

3701 Conc. Ring & tie beams

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011

page 98

Page 99: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

3702 Roof & Ceiling

3703 Fix wall plate & truss

3704 Fix purlins and rafters

3705 Fix shingles ( subject to receipt of timber)

3706 Fix ceiing battens & joists

3707 Fix ceiling boards

3708 Finishes

3709 Wall plaster (internal & External)

3710 M&E 1st fix

3711 Floor finishes

3712 Fix windows & doors

3713 M&E final fix

3714 Fix fittings and Fixtures

3715 M&E Installations

3716 Cable Tray, Conduit and Wiring

3717 Electrical boards and connections

3718 Electrical accessories

3719 Light fittings and ceiling fans

3720 Hot and cold water

3721 Waste and sewage incl. biobox

3722 Electric water heater

3723 Pond

3724 Split unit installation

3725 Toilet ventilation, grilles

3726 Chi Sanctum( subject to receipt of GFW drawings)

3727 substructure

3728 set out

3729 Excavate

3730 Conc. Foundation

3731 Backfill ( where applicable )

3732 termite treatment

3733 DPC (where applicable)

3734 M&E inlet/outlet works

3735 frame

3736 set kickers

3737 Conc. Columns & shear walls

3738 Conc. G. F Beams

3739 Conc. Plantroom

3740 Conc. Floor slab

3741 Blockwork

3742 Conc. Ring & tie beams

3743 Roof & Ceiling

3744 Fix wall plate & truss

3745 Fix purlins and rafters

3746 Fix shingles ( subject to receipt of timber)

3747 Fix ceiing battens & joists

3748 Fix ceiling boards

3749 Finishes

3750 Wall plaster (internal & External)

3751 M&E 1st fix

3752 Floor finishes

3753 Fix windows & doors

3754 M&E final fix

3755 Fix fittings and Fixtures

3756 M&E Installations

3757 Cable Tray, Conduit and Wiring

3758 Electrical boards and connections

3759 Electrical accessories

3760 Light fittings and ceiling fans

3761 Hot and cold water

3762 Waste and sewage incl. biobox

3763 Electric water heater

3764 Pond

3765 Split unit installation

3766 Toilet ventilation, grilles

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3768 substructure

3769 set out

3770 Excavate

3771 Conc. Foundation

3772 Backfill ( where applicable )

3773 termite treatment

3774 DPC (where applicable)

3775 M&E inlet/outlet works

3776 frame

3777 set kickers

3778 Conc. Columns & shear walls

3779 Conc. G. F Beams

3780 Conc. Plantroom

3781 Conc. Floor slab

3782 Blockwork

3783 Conc. Ring & tie beams

3784 Roof & Ceiling

3785 Fix wall plate & truss

3786 Fix purlins and rafters

3787 Fix shingles ( subject to receipt of timber)

3788 Fix ceiing battens & joists

3789 Fix ceiling boards

3790 Finishes

3791 Wall plaster (internal & External)

3792 M&E 1st fix

3793 Floor finishes

3794 Fix windows & doors

3795 M&E final fix

3796 Fix fittings and Fixtures

3797 M&E Installations

3798 Cable Tray, Conduit and Wiring

3799 Electrical boards and connections

3800 Electrical accessories

3801 Light fittings and ceiling fans

3802 Hot and cold water

3803 Waste and sewage incl. biobox

3804 Electric water heater

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011

page 99

Page 100: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

The following table summarises the timing of receipt of design drawings and information. It has been shown that although these drawings are significantly late, it has not affected progress at site.

The reason for this is the earlier delays caused by setting out and unforeseen ground conditions extended and revised the original start dates of many activities. Consequently, as the buildings revised schedule start date is much later than originally planned drawings issued for construction had no impact.

However, as a consequence of the lateness in receipt of detailed drawings, procurement of materials could not proceed as originally planned.

Item Building commencement completion commencement completion 1 P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-082 Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-083 Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-084 Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-085 GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-086 Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-087 Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-088 Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-089 Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-0810 Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0811 BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-0812 Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0813 Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-0814 Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-0815 Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0816 Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0817 Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0818 Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0819 Mechanical Area 24-Oct-08 09-Jan-09 22-Oct-07 19-Feb-0820 3 Meal Restaurant 04-Sep-08 28-Mar-09 02-Jul-07 26-Mar-0821 Signature Pool 04-Sep-08 18-Mar-09 02-Jul-07 15-Mar-0822 Beach Pool Bar 04-Sep-08 19-Mar-09 02-Jul-07 17-Mar-08

Impacted Programme Baseline Programme

Delays’ resulting from hard rock excavation is a parallel delay to design drawings.

Items 1 - 18 relates to critical delays caused by hard rock excavation for preceding structures. Items 19 – 22 relates to delay arising from late design drawings, which is critical. More delays will be encountered once excavation works proceed at remaining locations.

As a result of the current delay caused by this event the time for completion has not extended the current revised date of 9 September 2009.

Consequently, the revised completion date remains at 9 September 2009.

page 100

Page 101: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.4. Event No 4 – Increased Scope of Works

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

184 Villa A3/01

185 Substructure

193 Frame

194 set kickers

195 Conc. Columns & shear walls

196 Conc. G. F Beams

197 M&E first fix

198 Conc. Plantroom

199 Conc. Floor slab & swimming pool base

200 Blockwork

201 Conc. Swimming pool sides & overflow channels

202 Conc. Ring & tie beams

203 Roof & Ceiling

210 Finishes

217 M&E Installations

228 Villa A3/02

229 substructure

237 frame

238 set kickers

239 Conc. Columns & shear walls

240 Conc. G. F Beams

241 M&E first fix

242 Conc. Plantroom

243 Conc. Floor slab & swimming pool base

244 Blockwork

245 Conc. Swimming pool sides & overflow channels

246 Conc. Ring & tie beams

247 Roof & Ceiling

254 Finishes

262 M&E Installations

273 Villa A3/03

274 substructure

282 frame

283 set kickers

284 Conc. Columns & shear walls

285 Conc. G. F Beams

286 M&E first fix

287 Conc. Plantroom

288 Conc. Floor slab & swimming pool base

289 Blockwork

290 Conc. Swimming pool sides & overflow channels

291 Conc. Ring & tie beams

292 Roof & Ceiling

299 Finishes

307 M&E Installations

318 Villa A3/04

319 substructure

320 set out

321 Excavate

322 Conc. Foundation

323 Backfill

324 termite treatment

325 DPC (where applicable)

326 M&E inlet/outlet works - first fix

327 frame

328 set kickers

329 Conc. Columns & shear walls

330 Conc. G. F Beams

331 M&E first fix

332 Conc. Plantroom

333 Conc. Floor slab & swimming pool base

334 Blockwork

335 Conc. Swimming pool sides & overflow channels

336 Conc. Ring & tie beams

337 Roof & Ceiling

338 Fix wall plate & truss

339 Fix purlins and rafters

340 Fix shingles ( subject to receipt of timber)

341 Fix ceiing battens & joists

342 Fix ceiling boards

343 M&E first fix

344 Finishes

345 Wall plaster (internal & External)

346 M&E 1st fix

347 Floor finishes

348 Fix windows & doors

349 Swimming pool finishes

350 M&E final fix

351 Fix fittings and Fixtures

352 M&E Installations

353 Cable Tray, Conduit and Wiring

354 Electrical boards and connections

355 Electrical accessories

356 Light fittings and ceiling fans

357 Hot and cold water

358 Waste and sewage incl. biobox

359 Electric water heater

360 Swimming pool

361 Split unit installation

362 Toilet ventilation, grilles

363 Villa A3/05

364 substructure

365 set out

366 Excavate

367 Conc. Foundation

368 Backfill

369 termite treatment

370 DPC (where applicable)

371 M&E inlet/outlet works - first fix

372 frame

373 set kickers

374 Conc. Columns & shear walls

375 Conc. G. F Beams

376 M&E first fix

377 Conc. Plantroom

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

page 101

Page 102: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

378 Conc. Floor slab & swimming pool base

379 Blockwork

380 Conc. Swimming pool sides & overflow channels

381 Conc. Ring & tie beams

382 Roof & Ceiling

383 Fix wall plate & truss

384 Fix purlins and rafters

385 Fix shingles ( subject to receipt of timber)

386 Fix ceiing battens & joists

387 Fix ceiling boards

388 M&E first fix

389 Finishes

390 Wall plaster (internal & External)

391 M&E 1st fix

392 Floor finishes

393 Fix windows & doors

394 Swimming pool finishes

395 M&E final fix

396 Fix fittings and Fixtures

397 M&E Installations

398 Cable Tray, Conduit and Wiring

399 Electrical boards and connections

400 Electrical accessories

401 Light fittings and ceiling fans

402 Hot and cold water

403 Waste and sewage incl. biobox

404 Electric water heater

405 Swimming pool

406 Split unit installation

407 Toilet ventilation, grilles

408 Villa A3/06

409 substructure

410 set out

411 Excavate

412 Conc. Foundation

413 Backfill

414 termite treatment

415 DPC (where applicable)

416 M&E inlet/outlet works - first fix

417 frame

418 set kickers

419 Conc. Columns & shear walls

420 Conc. G. F Beams

421 M&E first fix

422 Conc. Plantroom

423 Conc. Floor slab & swimming pool base

424 Blockwork

425 Conc. Swimming pool sides & overflow channels

426 Conc. Ring & tie beams

427 Roof & Ceiling

434 Finishes

442 M&E Installations

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

849 Villa A3/07

850 substructure

851 set out

852 Excavate

853 Conc. Foundation

854 Backfill

855 termite treatment

856 DPC (where applicable)

857 M&E inlet/outlet works - first fix

858 frame

859 set kickers

860 Conc. Columns & shear walls

861 Conc. G. F Beams

862 M&E first fix

863 Conc. Plantroom

864 Conc. Floor slab & swimming pool base

865 Blockwork

866 Conc. Swimming pool sides & overflow channels

867 Conc. Ring & tie beams

868 Roof & Ceiling

869 Fix wall plate & truss

870 Fix purlins and rafters

871 Fix shingles ( subject to receipt of timber)

872 Fix ceiing battens & joists

873 Fix ceiling boards

874 M&E first fix

875 Finishes

876 Wall plaster (internal & External)

877 M&E 1st fix

878 Floor finishes

879 Fix windows & doors

880 Swimming pool finishes

881 M&E final fix

882 Fix fittings and Fixtures

883 M&E Installations

884 Cable Tray, Conduit and Wiring

885 Electrical boards and connections

886 Electrical accessories

887 Light fittings and ceiling fans

888 Hot and cold water

889 Waste and sewage incl. biobox

890 Electric water heater

891 Swimming pool

892 Split unit installation

893 Toilet ventilation, grilles

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 102

Page 103: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

894 Villa A3/08

895 substructure

896 set out

897 Excavate

898 Conc. Foundation

899 Backfill

900 termite treatment

901 DPC (where applicable)

902 M&E inlet/outlet works - first fix

903 frame

904 set kickers

905 Conc. Columns & shear walls

906 Conc. G. F Beams

907 M&E first fix

908 Conc. Plantroom

909 Conc. Floor slab & swimming pool base

910 Blockwork

911 Conc. Swimming pool sides & overflow channels

912 Conc. Ring & tie beams

913 Roof & Ceiling

920 Finishes

928 M&E Installations

939 Villa A3/09

940 substructure

941 set out

942 Excavate

943 Conc. Foundation

944 Backfill

945 termite treatment

946 DPC (where applicable)

947 M&E inlet/outlet works - first fix

948 frame

949 set kickers

950 Conc. Columns & shear walls

951 Conc. G. F Beams

952 M&E first fix

953 Conc. Plantroom

954 Conc. Floor slab & swimming pool base

955 Blockwork

956 Conc. Swimming pool sides & overflow channels

957 Conc. Ring & tie beams

958 Roof & Ceiling

965 Finishes

973 M&E Installations

984 Villa A3/10

985 substructure

986 set out

987 Excavate

988 Conc. Foundation

989 Backfill

990 termite treatment

991 DPC (where applicable)

992 M&E inlet/outlet works - first fix

993 frame

994 set kickers

995 Conc. Columns & shear walls

996 Conc. G. F Beams

997 M&E first fix

998 Conc. Plantroom

999 Conc. Floor slab & swimming pool base

1000 Blockwork

1001 Conc. Swimming pool sides & overflow channels

1002 Conc. Ring & tie beams

1003 Roof & Ceiling

1010 Finishes

1018 M&E Installations

1029 Villa A3/11

1030 substructure

1031 set out

1032 Excavate

1033 Conc. Foundation

1034 Backfill

1035 termite treatment

1036 DPC (where applicable)

1037 M&E inlet/outlet works - first fix

1038 frame

1039 set kickers

1040 Conc. Columns & shear walls

1041 Conc. G. F Beams

1042 M&E first fix

1043 Conc. Plantroom

1044 Conc. Floor slab & swimming pool base

1045 Blockwork

1046 Conc. Swimming pool sides & overflow channels

1047 Conc. Ring & tie beams

1048 Roof & Ceiling

1055 Finishes

1063 M&E Installations

1074 Villa A3/12

1075 substructure

1076 set out

1077 Excavate

1078 Conc. Foundation

1079 Backfill

1080 termite treatment

1081 DPC (where applicable)

1082 M&E inlet/outlet works - first fix

1083 frame

1084 set kickers

1085 Conc. Columns & shear walls

1086 Conc. G. F Beams

1087 M&E first fix

1088 Conc. Plantroom

1089 Conc. Floor slab & swimming pool base

1090 Blockwork

1091 Conc. Swimming pool sides & overflow channels

1092 Conc. Ring & tie beams

1093 Roof & Ceiling

1094 Fix wall plate & truss

1095 Fix purlins and rafters

1096 Fix shingles ( subject to receipt of timber)

1097 Fix ceiing battens & joists

1098 Fix ceiling boards

1099 M&E first fix

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 103

Page 104: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1100 Finishes

1101 Wall plaster (internal & External)

1102 M&E 1st fix

1103 Floor finishes

1104 Fix windows & doors

1105 Swimming pool finishes

1106 M&E final fix

1107 Fix fittings and Fixtures

1108 M&E Installations

1109 Cable Tray, Conduit and Wiring

1110 Electrical boards and connections

1111 Electrical accessories

1112 Light fittings and ceiling fans

1113 Hot and cold water

1114 Waste and sewage incl. biobox

1115 Electric water heater

1116 Swimming pool

1117 Split unit installation

1118 Toilet ventilation, grilles

1119 Villa A3/13

1120 substructure

1121 set out

1122 Excavate

1123 Conc. Foundation

1124 Backfill

1125 termite treatment

1126 DPC (where applicable)

1127 M&E inlet/outlet works - first fix

1128 frame

1129 set kickers

1130 Conc. Columns & shear walls

1131 Conc. G. F Beams

1132 M&E first fix

1133 Conc. Plantroom

1134 Conc. Floor slab & swimming pool base

1135 Blockwork

1136 Conc. Swimming pool sides & overflow channels

1137 Conc. Ring & tie beams

1138 Roof & Ceiling

1139 Fix wall plate & truss

1140 Fix purlins and rafters

1141 Fix shingles ( subject to receipt of timber)

1142 Fix ceiing battens & joists

1143 Fix ceiling boards

1144 M&E first fix

1145 Finishes

1146 Wall plaster (internal & External)

1147 M&E 1st fix

1148 Floor finishes

1149 Fix windows & doors

1150 Swimming pool finishes

1151 M&E final fix

1152 Fix fittings and Fixtures

1153 M&E Installations

1154 Cable Tray, Conduit and Wiring

1155 Electrical boards and connections

1156 Electrical accessories

1157 Light fittings and ceiling fans

1158 Hot and cold water

1159 Waste and sewage incl. biobox

1160 Electric water heater

1161 Swimming pool

1162 Split unit installation

1163 Toilet ventilation, grilles

1164 Villa A3/18

1165 substructure

1166 set out

1167 Excavate

1168 Conc. Foundation

1169 Backfill

1170 termite treatment

1171 DPC (where applicable)

1172 M&E inlet/outlet works - first fix

1173 frame

1174 set kickers

1175 Conc. Columns & shear walls

1176 Conc. G. F Beams

1177 M&E first fix

1178 Conc. Plantroom

1179 Conc. Floor slab & swimming pool base

1180 Blockwork

1181 Conc. Swimming pool sides & overflow channels

1182 Conc. Ring & tie beams

1183 Roof & Ceiling

1184 Fix wall plate & truss

1185 Fix purlins and rafters

1186 Fix shingles ( subject to receipt of timber)

1187 Fix ceiing battens & joists

1188 Fix ceiling boards

1189 M&E first fix

1190 Finishes

1191 Wall plaster (internal & External)

1192 M&E 1st fix

1193 Floor finishes

1194 Fix windows & doors

1195 Swimming pool finishes

1196 M&E final fix

1197 Fix fittings and Fixtures

1198 M&E Installations

1199 Cable Tray, Conduit and Wiring

1200 Electrical boards and connections

1201 Electrical accessories

1202 Light fittings and ceiling fans

1203 Hot and cold water

1204 Waste and sewage incl. biobox

1205 Electric water heater

1206 Swimming pool

1207 Split unit installation

1208 Toilet ventilation, grilles

1209 Villa A3/19

1210 substructure

1211 set out

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 104

Page 105: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1212 Excavate

1213 Conc. Foundation

1214 Backfill

1215 termite treatment

1216 DPC (where applicable)

1217 M&E inlet/outlet works - first fix

1218 frame

1219 set kickers

1220 Conc. Columns & shear walls

1221 Conc. G. F Beams

1222 M&E first fix

1223 Conc. Plantroom

1224 Conc. Floor slab & swimming pool base

1225 Blockwork

1226 Conc. Swimming pool sides & overflow channels

1227 Conc. Ring & tie beams

1228 Roof & Ceiling

1235 Finishes

1243 M&E Installations

1254 Villa A3/20

1255 substructure

1256 set out

1257 Excavate

1258 Conc. Foundation

1259 Backfill

1260 termite treatment

1261 DPC (where applicable)

1262 M&E inlet/outlet works - first fix

1263 frame

1264 set kickers

1265 Conc. Columns & shear walls

1266 Conc. G. F Beams

1267 M&E first fix

1268 Conc. Plantroom

1269 Conc. Floor slab & swimming pool base

1270 Blockwork

1271 Conc. Swimming pool sides & overflow channels

1272 Conc. Ring & tie beams

1273 Roof & Ceiling

1280 Finishes

1288 M&E Installations

1299 Villa A3/21

1300 substructure

1301 set out

1302 Excavate

1303 Conc. Foundation

1304 Backfill

1305 termite treatment

1306 DPC (where applicable)

1307 M&E inlet/outlet works - first fix

1308 frame

1309 set kickers

1310 Conc. Columns & shear walls

1311 Conc. G. F Beams

1312 M&E first fix

1313 Conc. Plantroom

1314 Conc. Floor slab & swimming pool base

1315 Blockwork

1316 Conc. Swimming pool sides & overflow channels

1317 Conc. Ring & tie beams

1318 Roof & Ceiling

1325 Finishes

1333 M&E Installations

1344 Villa A3/22

1345 substructure

1346 set out

1347 Excavate

1348 Conc. Foundation

1349 Backfill

1350 termite treatment

1351 DPC (where applicable)

1352 M&E inlet/outlet works - first fix

1353 frame

1354 set kickers

1355 Conc. Columns & shear walls

1356 Conc. G. F Beams

1357 M&E first fix

1358 Conc. Plantroom

1359 Conc. Floor slab & swimming pool base

1360 Blockwork

1361 Conc. Swimming pool sides & overflow channels

1362 Conc. Ring & tie beams

1363 Roof & Ceiling

1364 Fix wall plate & truss

1365 Fix purlins and rafters

1366 Fix shingles ( subject to receipt of timber)

1367 Fix ceiing battens & joists

1368 Fix ceiling boards

1369 M&E first fix

1370 Finishes

1371 Wall plaster (internal & External)

1372 M&E 1st fix

1373 Floor finishes

1374 Fix windows & doors

1375 Swimming pool finishes

1376 M&E final fix

1377 Fix fittings and Fixtures

1378 M&E Installations

1379 Cable Tray, Conduit and Wiring

1380 Electrical boards and connections

1381 Electrical accessories

1382 Light fittings and ceiling fans

1383 Hot and cold water

1384 Waste and sewage incl. biobox

1385 Electric water heater

1386 Swimming pool

1387 Split unit installation

1388 Toilet ventilation, grilles

1389 Villa A3/23

1390 substructure

1391 set out

1392 Excavate

1393 Conc. Foundation

1394 Backfill

1395 termite treatment

1396 DPC (where applicable)

1397 M&E inlet/outlet works - first fix

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 105

Page 106: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1398 frame

1399 set kickers

1400 Conc. Columns & shear walls

1401 Conc. G. F Beams

1402 M&E first fix

1403 Conc. Plantroom

1404 Conc. Floor slab & swimming pool base

1405 Blockwork

1406 Conc. Swimming pool sides & overflow channels

1407 Conc. Ring & tie beams

1408 Roof & Ceiling

1409 Fix wall plate & truss

1410 Fix purlins and rafters

1411 Fix shingles ( subject to receipt of timber)

1412 Fix ceiing battens & joists

1413 Fix ceiling boards

1414 M&E first fix

1415 Finishes

1416 Wall plaster (internal & External)

1417 M&E 1st fix

1418 Floor finishes

1419 Fix windows & doors

1420 Swimming pool finishes

1421 M&E final fix

1422 Fix fittings and Fixtures

1423 M&E Installations

1424 Cable Tray, Conduit and Wiring

1425 Electrical boards and connections

1426 Electrical accessories

1427 Light fittings and ceiling fans

1428 Hot and cold water

1429 Waste and sewage incl. biobox

1430 Electric water heater

1431 Swimming pool

1432 Split unit installation

1433 Toilet ventilation, grilles

1434 Villa A3/24

1435 substructure

1436 set out

1437 Excavate

1438 Conc. Foundation

1439 Backfill

1440 termite treatment

1441 DPC (where applicable)

1442 M&E inlet/outlet works - first fix

1443 frame

1444 set kickers

1445 Conc. Columns & shear walls

1446 Conc. G. F Beams

1447 M&E first fix

1448 Conc. Plantroom

1449 Conc. Floor slab & swimming pool base

1450 Blockwork

1451 Conc. Swimming pool sides & overflow channels

1452 Conc. Ring & tie beams

1453 Roof & Ceiling

1454 Fix wall plate & truss

1455 Fix purlins and rafters

1456 Fix shingles ( subject to receipt of timber)

1457 Fix ceiing battens & joists

1458 Fix ceiling boards

1459 M&E first fix

1460 Finishes

1461 Wall plaster (internal & External)

1462 M&E 1st fix

1463 Floor finishes

1464 Fix windows & doors

1465 Swimming pool finishes

1466 M&E final fix

1467 Fix fittings and Fixtures

1468 M&E Installations

1469 Cable Tray, Conduit and Wiring

1470 Electrical boards and connections

1471 Electrical accessories

1472 Light fittings and ceiling fans

1473 Hot and cold water

1474 Waste and sewage incl. biobox

1475 Electric water heater

1476 Swimming pool

1477 Split unit installation

1478 Toilet ventilation, grilles

1479 Villa A3/25

1480 substructure

1481 set out

1482 Excavate

1483 Conc. Foundation

1484 Backfill

1485 termite treatment

1486 DPC (where applicable)

1487 M&E inlet/outlet works - first fix

1488 frame

1489 set kickers

1490 Conc. Columns & shear walls

1491 Conc. G. F Beams

1492 M&E first fix

1493 Conc. Plantroom

1494 Conc. Floor slab & swimming pool base

1495 Blockwork

1496 Conc. Swimming pool sides & overflow channels

1497 Conc. Ring & tie beams

1498 Roof & Ceiling

1499 Fix wall plate & truss

1500 Fix purlins and rafters

1501 Fix shingles ( subject to receipt of timber)

1502 Fix ceiing battens & joists

1503 Fix ceiling boards

1504 M&E first fix

1505 Finishes

1506 Wall plaster (internal & External)

1507 M&E 1st fix

1508 Floor finishes

1509 Fix windows & doors

1510 Swimming pool finishes

1511 M&E final fix

1512 Fix fittings and Fixtures

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 106

Page 107: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1513 M&E Installations

1514 Cable Tray, Conduit and Wiring

1515 Electrical boards and connections

1516 Electrical accessories

1517 Light fittings and ceiling fans

1518 Hot and cold water

1519 Waste and sewage incl. biobox

1520 Electric water heater

1521 Swimming pool

1522 Split unit installation

1523 Toilet ventilation, grilles

1524 Villa A3/26

1525 substructure

1526 set out

1527 Excavate

1528 Conc. Foundation

1529 Backfill

1530 termite treatment

1531 DPC (where applicable)

1532 M&E inlet/outlet works - first fix

1533 frame

1534 set kickers

1535 Conc. Columns & shear walls

1536 Conc. G. F Beams

1537 M&E first fix

1538 Conc. Plantroom

1539 Conc. Floor slab & swimming pool base

1540 Blockwork

1541 Conc. Swimming pool sides & overflow channels

1542 Conc. Ring & tie beams

1543 Roof & Ceiling

1550 Finishes

1558 M&E Installations

1569 Villa A3/27

1570 substructure

1571 set out

1572 Excavate

1573 Conc. Foundation

1574 Backfill

1575 termite treatment

1576 DPC (where applicable)

1577 M&E inlet/outlet works - first fix

1578 frame

1579 set kickers

1580 Conc. Columns & shear walls

1581 Conc. G. F Beams

1582 M&E first fix

1583 Conc. Plantroom

1584 Conc. Floor slab & swimming pool base

1585 Blockwork

1586 Conc. Swimming pool sides & overflow channels

1587 Conc. Ring & tie beams

1588 Roof & Ceiling

1595 Finishes

1603 M&E Installations

1614 B223 Villas ( 7 nos)

1615 Villa B2/01

1616 substructure

1617 set out

1618 Excavate

1619 Conc. Foundation

1620 Backfill

1621 termite treatment

1622 DPC (where applicable)

1623 M&E inlet/outlet works - first fix

1624 frame

1625 set kickers

1626 Conc. Columns & shear walls to GF

1627 Conc. Plantrooms

1628 M&E first fix GF

1629 Conc. GF slab and beams

1630 Blockwork up to FF slab

1631 set kickers on GF

1632 Conc. Columns & shear walls to FF

1633 M&E first fix FF

1634 Conc. FF slab & beams

1635 Blockwork up to roof

1636 set kickers on FF

1637 Conc. Columns & shear walls to roof

1638 M&E first fix roof

1639 Conc. Ring & tie beams

1640 Roof & Ceiling

1647 Finishes

1654 M&E Installations

1665 Villa B2/02

1666 substructure

1667 set out

1668 Excavate

1669 Conc. Foundation

1670 Backfill

1671 termite treatment

1672 DPC (where applicable)

1673 M&E inlet/outlet works - first fix

1674 frame

1675 set kickers

1676 Conc. Columns & shear walls to GF

1677 Conc. Plantrooms

1678 M&E first fix GF

1679 Conc. GF slab and beams

1680 Blockwork up to FF slab

1681 set kickers on GF

1682 Conc. Columns & shear walls to FF

1683 M&E first fix FF

1684 Conc. FF slab & beams

1685 Blockwork up to roof

1686 set kickers on FF

1687 Conc. Columns & shear walls to roof

1688 M&E first fix roof

1689 Conc. Ring & tie beams

1690 Roof & Ceiling

1697 Finishes

1704 M&E Installations

1715 Villa B2/04

1716 substructure

1717 set out

1718 Excavate

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 107

Page 108: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1719 Conc. Foundation

1720 Backfill

1721 termite treatment

1722 DPC (where applicable)

1723 M&E inlet/outlet works - first fix

1724 frame

1725 set kickers

1726 Conc. Columns & shear walls to GF

1727 Conc. Plantrooms

1728 M&E first fix GF

1729 Conc. GF slab and beams

1730 Blockwork up to FF slab

1731 set kickers on GF

1732 Conc. Columns & shear walls to FF

1733 M&E first fix FF

1734 Conc. FF slab & beams

1735 Blockwork up to roof

1736 set kickers on FF

1737 Conc. Columns & shear walls to roof

1738 M&E first fix roof

1739 Conc. Ring & tie beams

1740 Roof & Ceiling

1747 Finishes

1754 M&E Installations

1765 Villa B2/05

1766 substructure

1767 set out

1768 Excavate

1769 Conc. Foundation

1770 Backfill

1771 termite treatment

1772 DPC (where applicable)

1773 M&E inlet/outlet works - first fix

1774 frame

1775 set kickers

1776 Conc. Columns & shear walls to GF

1777 Conc. Plantrooms

1778 M&E first fix GF

1779 Conc. GF slab and beams

1780 Blockwork up to FF slab

1781 set kickers on GF

1782 Conc. Columns & shear walls to FF

1783 M&E first fix FF

1784 Conc. FF slab & beams

1785 Blockwork up to roof

1786 set kickers on FF

1787 Conc. Columns & shear walls to roof

1788 M&E first fix roof

1789 Conc. Ring & tie beams

1790 Roof & Ceiling

1797 Finishes

1804 M&E Installations

1815 Villa B2/06

1816 substructure

1817 set out

1818 Excavate

1819 Conc. Foundation

1820 Backfill

1821 termite treatment

1822 DPC (where applicable)

1823 M&E inlet/outlet works - first fix

1824 frame

1825 set kickers

1826 Conc. Columns & shear walls to GF

1827 Conc. Plantrooms

1828 M&E first fix GF

1829 Conc. GF slab and beams

1830 Blockwork up to FF slab

1831 set kickers on GF

1832 Conc. Columns & shear walls to FF

1833 M&E first fix FF

1834 Conc. FF slab & beams

1835 Blockwork up to roof

1836 set kickers on FF

1837 Conc. Columns & shear walls to roof

1838 M&E first fix roof

1839 Conc. Ring & tie beams

1840 Roof & Ceiling

1847 Finishes

1854 M&E Installations

1865 Villa B2/07

1866 substructure

1867 set out

1868 Excavate

1869 Conc. Foundation

1870 Backfill

1871 termite treatment

1872 DPC (where applicable)

1873 M&E inlet/outlet works - first fix

1874 frame

1875 set kickers

1876 Conc. Columns & shear walls to GF

1877 Conc. Plantrooms

1878 M&E first fix GF

1879 Conc. GF slab and beams

1880 Blockwork up to FF slab

1881 set kickers on GF

1882 Conc. Columns & shear walls to FF

1883 M&E first fix FF

1884 Conc. FF slab & beams

1885 Blockwork up to roof

1886 set kickers on FF

1887 Conc. Columns & shear walls to roof

1888 M&E first fix roof

1889 Conc. Ring & tie beams

1890 Roof & Ceiling

1897 Finishes

1904 M&E Installations

1915 Villa B2/08

1916 substructure

1917 set out

1918 Excavate

1919 Conc. Foundation

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 108

Page 109: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1920 Backfill

1921 termite treatment

1922 DPC (where applicable)

1923 M&E inlet/outlet works - first fix

1924 frame

1925 set kickers

1926 Conc. Columns & shear walls to GF

1927 Conc. Plantrooms

1928 M&E first fix GF

1929 Conc. GF slab and beams

1930 Blockwork up to FF slab

1931 set kickers on GF

1932 Conc. Columns & shear walls to FF

1933 M&E first fix FF

1934 Conc. FF slab & beams

1935 Blockwork up to roof

1936 set kickers on FF

1937 Conc. Columns & shear walls to roof

1938 M&E first fix roof

1939 Conc. Ring & tie beams

1940 Roof & Ceiling

1947 Finishes

1954 M&E Installations

1965 B4 Villa (2 nos.)

2056 Retail 1( subject to receipt of GFW drawings)

2094 Retail 2( subject to receipt of GFW drawings)

2132 Retail 3( subject to receipt of GFW drawings)

2170 Seafood resort( subject to receipt of GFW drawings)

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2264 Villa A3/14

2265 Substructure

2266 set out

2267 Excavate

2268 Conc. Foundation

2269 Backfill

2270 termite treatment

2271 DPC (where applicable)

2272 M&E inlet/outlet works - first fix

2273 Frame

2274 set kickers

2275 Conc. Columns & shear walls

2276 Conc. G. F Beams

2277 M&E first fix

2278 Conc. Plantroom

2279 Conc. Floor slab & swimming pool base

2280 Blockwork

2281 Conc. Swimming pool sides & overflow channels

2282 Conc. Ring & tie beams

2283 Roof & Ceiling

2284 Fix wall plate & truss

2285 Fix purlins and rafters

2286 Fix shingles ( subject to receipt of timber)

2287 Fix ceiing battens & joists

2288 Fix ceiling boards

2289 M&E first fix

2290 Finishes

2291 Wall plaster (internal & External)

2292 M&E 1st fix

2293 Floor finishes

2294 Fix windows & doors

2295 Swimming pool finishes

2296 M&E final fix

2297 Fix fittings and Fixtures

2298 M&E Installations

2299 Cable Tray, Conduit and Wiring

2300 Electrical boards and connections

2301 Electrical accessories

2302 Light fittings and ceiling fans

2303 Hot and cold water

2304 Waste and sewage incl. biobox

2305 Electric water heater

2306 Swimming pool

2307 Split unit installation

2308 Toilet ventilation, grilles

2309 Villa A3/15

2310 substructure

2311 set out

2312 Excavate

2313 Conc. Foundation

2314 Backfill

2315 termite treatment

2316 DPC (where applicable)

2317 M&E inlet/outlet works - first fix

2318 frame

2319 set kickers

2320 Conc. Columns & shear walls

2321 Conc. G. F Beams

2322 M&E first fix

2323 Conc. Plantroom

2324 Conc. Floor slab & swimming pool base

2325 Blockwork

2326 Conc. Swimming pool sides & overflow channels

2327 Conc. Ring & tie beams

2328 Roof & Ceiling

2329 Fix wall plate & truss

2330 Fix purlins and rafters

2331 Fix shingles ( subject to receipt of timber)

2332 Fix ceiing battens & joists

2333 Fix ceiling boards

2334 M&E first fix

2335 Finishes

2336 Wall plaster (internal & External)

2337 M&E 1st fix

2338 Floor finishes

2339 Fix windows & doors

2340 Swimming pool finishes

2341 M&E final fix

2342 Fix fittings and Fixtures

2343 M&E Installations

2344 Cable Tray, Conduit and Wiring

2345 Electrical boards and connections

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 109

Page 110: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2346 Electrical accessories

2347 Light fittings and ceiling fans

2348 Hot and cold water

2349 Waste and sewage incl. biobox

2350 Electric water heater

2351 Swimming pool

2352 Split unit installation

2353 Toilet ventilation, grilles

2354 Villa A3/16

2355 substructure

2356 set out

2357 Excavate

2358 Conc. Foundation

2359 Backfill

2360 termite treatment

2361 DPC (where applicable)

2362 M&E inlet/outlet works - first fix

2363 frame

2364 set kickers

2365 Conc. Columns & shear walls

2366 Conc. G. F Beams

2367 M&E first fix

2368 Conc. Plantroom

2369 Conc. Floor slab & swimming pool base

2370 Blockwork

2371 Conc. Swimming pool sides & overflow channels

2372 Conc. Ring & tie beams

2373 Roof & Ceiling

2374 Fix wall plate & truss

2375 Fix purlins and rafters

2376 Fix shingles ( subject to receipt of timber)

2377 Fix ceiing battens & joists

2378 Fix ceiling boards

2379 M&E first fix

2380 Finishes

2381 Wall plaster (internal & External)

2382 M&E 1st fix

2383 Floor finishes

2384 Fix windows & doors

2385 Swimming pool finishes

2386 M&E final fix

2387 Fix fittings and Fixtures

2388 M&E Installations

2389 Cable Tray, Conduit and Wiring

2390 Electrical boards and connections

2391 Electrical accessories

2392 Light fittings and ceiling fans

2393 Hot and cold water

2394 Waste and sewage incl. biobox

2395 Electric water heater

2396 Swimming pool

2397 Split unit installation

2398 Toilet ventilation, grilles

2399 Villa A3/17

2400 substructure

2401 set out

2402 Excavate

2403 Conc. Foundation

2404 Backfill

2405 termite treatment

2406 DPC (where applicable)

2407 M&E inlet/outlet works - first fix

2408 frame

2409 set kickers

2410 Conc. Columns & shear walls

2411 Conc. G. F Beams

2412 M&E first fix

2413 Conc. Plantroom

2414 Conc. Floor slab & swimming pool base

2415 Blockwork

2416 Conc. Swimming pool sides & overflow channels

2417 Conc. Ring & tie beams

2418 Roof & Ceiling

2419 Fix wall plate & truss

2420 Fix purlins and rafters

2421 Fix shingles ( subject to receipt of timber)

2422 Fix ceiing battens & joists

2423 Fix ceiling boards

2424 M&E first fix

2425 Finishes

2426 Wall plaster (internal & External)

2427 M&E 1st fix

2428 Floor finishes

2429 Fix windows & doors

2430 Swimming pool finishes

2431 M&E final fix

2432 Fix fittings and Fixtures

2433 M&E Installations

2434 Cable Tray, Conduit and Wiring

2435 Electrical boards and connections

2436 Electrical accessories

2437 Light fittings and ceiling fans

2438 Hot and cold water

2439 Waste and sewage incl. biobox

2440 Electric water heater

2441 Swimming pool

2442 Split unit installation

2443 Toilet ventilation, grilles

2444 Villa A3/28

2445 substructure

2446 set out

2447 Excavate

2448 Conc. Foundation

2449 Backfill

2450 termite treatment

2451 DPC (where applicable)

2452 M&E inlet/outlet works - first fix

2453 frame

2454 set kickers

2455 Conc. Columns & shear walls

2456 Conc. G. F Beams

2457 M&E first fix

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010

page 110

Page 111: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2458 Conc. Plantroom

2459 Conc. Floor slab & swimming pool base

2460 Blockwork

2461 Conc. Swimming pool sides & overflow channels

2462 Conc. Ring & tie beams

2463 Roof & Ceiling

2470 Finishes

2478 M&E Installations

2489 Villa A3/29

2490 substructure

2491 set out

2492 Excavate

2493 Conc. Foundation

2494 Backfill

2495 termite treatment

2496 DPC (where applicable)

2497 M&E inlet/outlet works - first fix

2498 frame

2499 set kickers

2500 Conc. Columns & shear walls

2501 Conc. G. F Beams

2502 M&E first fix

2503 Conc. Plantroom

2504 Conc. Floor slab & swimming pool base

2505 Blockwork

2506 Conc. Swimming pool sides & overflow channels

2507 Conc. Ring & tie beams

2508 Roof & Ceiling

2515 Finishes

2523 M&E Installations

2534 Villa A3/30

2535 substructure

2536 set out

2537 Excavate

2538 Conc. Foundation

2539 Backfill

2540 termite treatment

2541 DPC (where applicable)

2542 M&E inlet/outlet works - first fix

2543 frame

2544 set kickers

2545 Conc. Columns & shear walls

2546 Conc. G. F Beams

2547 M&E first fix

2548 Conc. Plantroom

2549 Conc. Floor slab & swimming pool base

2550 Blockwork

2551 Conc. Swimming pool sides & overflow channels

2552 Conc. Ring & tie beams

2553 Roof & Ceiling

2560 Finishes

2568 M&E Installations

2579 Villa A3/31

2624 Villa A3/32

2625 substructure

2626 set out

2627 Excavate

2628 Conc. Foundation

2629 Backfill

2630 termite treatment

2631 DPC (where applicable)

2632 frame

2633 set kickers

2634 Conc. Columns & shear walls

2635 Conc. Ground Beams

2636 Conc. Plantroom

2637 Conc. Floor slab & swimming pool base

2638 Blockwork

2639 Conc. Swimming pool sides & overflow channels

2640 Conc. Ring & tie beams

2641 Roof & Ceiling

2647 Finishes

2653 M&E Installations

2664 B223 Villas ( 3 nos)

2665 Villa B2/03

2666 substructure

2667 set out

2668 Excavate

2669 Conc. Foundation

2670 Backfill

2671 termite treatment

2672 DPC (where applicable)

2673 frame

2674 set kickers

2675 Conc. Columns & shear walls to GF

2676 Conc. Plantrooms

2677 Conc. GF slab and beams

2678 Blockwork up to FF slab

2679 set kickers on GF

2680 Conc. Columns & shear walls to FF

2681 Conc. FF slab & beams

2682 Blockwork up to roof

2683 set kickers on FF

2684 Conc. Columns & shear walls to roof

2685 Conc. Ring & tie beams

2686 Roof & Ceiling

2692 Finishes

2697 M&E Installations

2708 Villa B2/09

2709 substructure

2710 set out

2711 Excavate

2712 Conc. Foundation

2713 Backfill

2714 termite treatment

2715 DPC (where applicable)

2716 M&E inlet/outlet works - first fix

2717 frame

2718 set kickers

2719 Conc. Columns & shear walls to GF

2720 Conc. Plantrooms

2721 M&E first fix GF

2722 Conc. GF slab and beams

2723 Blockwork up to FF slab

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010

page 111

Page 112: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2724 set kickers on GF

2725 Conc. Columns & shear walls to FF

2726 M&E first fix FF

2727 Conc. FF slab & beams

2728 Blockwork up to roof

2729 set kickers on FF

2730 Conc. Columns & shear walls to roof

2731 M&E first fix roof

2732 Conc. Ring & tie beams

2733 Roof & Ceiling

2740 Finishes

2747 M&E Installations

2758 Villa B2/10

2759 substructure

2760 set out

2761 Excavate

2762 Conc. Foundation

2763 Backfill

2764 termite treatment

2765 DPC (where applicable)

2766 M&E inlet/outlet works - first fix

2767 frame

2768 set kickers

2769 Conc. Columns & shear walls to GF

2770 Conc. Plantrooms

2771 M&E first fix GF

2772 Conc. GF slab and beams

2773 Blockwork up to FF slab

2774 set kickers on GF

2775 Conc. Columns & shear walls to FF

2776 M&E first fix FF

2777 Conc. FF slab & beams

2778 Blockwork up to roof

2779 set kickers on FF

2780 Conc. Columns & shear walls to roof

2781 M&E first fix roof

2782 Conc. Ring & tie beams

2783 Roof & Ceiling

2790 Finishes

2797 M&E Installations

2808 B4 Standard Villas ( 2 nos)

2899 BC311 Executive Villa

3115 P3 Presidential suites ( 3 nos)

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010

The following table summarises the revised durations to perform a significantly revised scope of work depicted on the design drawings issued for construction. It should be noted the delay indicated on the extreme right column also includes the earlier delays caused by the setting out, unforeseen ground conditions and design drawings.

Once again, the revised durations are not critical to completion but activities typically take longer than planned.

page 112

Page 113: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13 261.00A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08 370.96A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13 214.00A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08 33.00A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08 416.96A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08 428.96A3/12 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00A3/13 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00A3/14 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/15 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/16 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/17 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/18 12-Apr-07 15-Mar-08 12-Apr-07 15-Mar-08 338.13 338.13 0.00A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13 455.00A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13 427.00A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13 440.00A3/22 12-Apr-07 13-Sep-08 12-Apr-07 15-Mar-08 338.13 520.33 182.21A3/23 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/24 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/25 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08 296.96A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/32 28-May-07 10-Dec-07 28-May-07 16-Nov-07 172.04 196.38 24.33B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08 403.96B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08 178.96B2/03 28-May-07 17-Jan-08 28-May-07 04-Dec-07 190.17 234.17 44.00B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13 287.00B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13 377.00B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13 155.00B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13 362.00B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13 368.00

Impacted Programme Baseline Programme

As a result of the extended durations caused by this event the time for completion has not been extended and the revised completion date remains at 9 September 2009.

The revised completion date remains at 9 September 2009.

page 113

Page 114: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.5. Event No 5 – Partial Suspension of Works

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

184 Villa A3/01

228 Villa A3/02

273 Villa A3/03

274 substructure

275 set out

276 Excavate

277 Conc. Foundation

278 Backfill

279 termite treatment

280 DPC (where applicable)

281 M&E inlet/outlet works - first fix

282 frame

283 set kickers

284 Conc. Columns & shear walls

285 Conc. G. F Beams

286 M&E first fix

287 Conc. Plantroom

288 Conc. Floor slab & swimming pool base

289 Blockwork

290 Conc. Swimming pool sides & overflow channels

291 Conc. Ring & tie beams

292 Roof & Ceiling

299 Finishes

307 M&E Installations

318 Villa A3/04

319 substructure

320 set out

321 Excavate

322 Conc. Foundation

323 Backfill

324 termite treatment

325 DPC (where applicable)

326 M&E inlet/outlet works - first fix

327 frame

328 set kickers

329 Conc. Columns & shear walls

330 Conc. G. F Beams

331 M&E first fix

332 Conc. Plantroom

333 Conc. Floor slab & swimming pool base

334 Blockwork

335 Conc. Swimming pool sides & overflow channels

336 Conc. Ring & tie beams

337 Roof & Ceiling

338 Fix wall plate & truss

339 Fix purlins and rafters

340 Fix shingles ( subject to receipt of timber)

341 Fix ceiing battens & joists

342 Fix ceiling boards

343 M&E first fix

344 Finishes

345 Wall plaster (internal & External)

346 M&E 1st fix

347 Floor finishes

348 Fix windows & doors

349 Swimming pool finishes

350 M&E final fix

351 Fix fittings and Fixtures

352 M&E Installations

353 Cable Tray, Conduit and Wiring

354 Electrical boards and connections

355 Electrical accessories

356 Light fittings and ceiling fans

357 Hot and cold water

358 Waste and sewage incl. biobox

359 Electric water heater

360 Swimming pool

361 Split unit installation

362 Toilet ventilation, grilles

363 Villa A3/05

364 substructure

365 set out

366 Excavate

367 Conc. Foundation

368 Backfill

369 termite treatment

370 DPC (where applicable)

371 M&E inlet/outlet works - first fix

372 frame

373 set kickers

374 Conc. Columns & shear walls

375 Conc. G. F Beams

376 M&E first fix

377 Conc. Plantroom

378 Conc. Floor slab & swimming pool base

379 Blockwork

380 Conc. Swimming pool sides & overflow channels

381 Conc. Ring & tie beams

382 Roof & Ceiling

383 Fix wall plate & truss

384 Fix purlins and rafters

385 Fix shingles ( subject to receipt of timber)

386 Fix ceiing battens & joists

387 Fix ceiling boards

388 M&E first fix

389 Finishes

390 Wall plaster (internal & External)

391 M&E 1st fix

392 Floor finishes

393 Fix windows & doors

394 Swimming pool finishes

395 M&E final fix

396 Fix fittings and Fixtures

397 M&E Installations

398 Cable Tray, Conduit and Wiring

399 Electrical boards and connections

400 Electrical accessories

401 Light fittings and ceiling fans

402 Hot and cold water

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep2007 2008 2009

page 114

Page 115: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

403 Waste and sewage incl. biobox

404 Electric water heater

405 Swimming pool

406 Split unit installation

407 Toilet ventilation, grilles

408 Villa A3/06

409 substructure

410 set out

411 Excavate

412 Conc. Foundation

413 Backfill

414 termite treatment

415 DPC (where applicable)

416 M&E inlet/outlet works - first fix

417 frame

418 set kickers

419 Conc. Columns & shear walls

420 Conc. G. F Beams

421 M&E first fix

422 Conc. Plantroom

423 Conc. Floor slab & swimming pool base

424 Blockwork

425 Conc. Swimming pool sides & overflow channels

426 Conc. Ring & tie beams

427 Roof & Ceiling

434 Finishes

442 M&E Installations

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

849 Villa A3/07

894 Villa A3/08

895 substructure

896 set out

897 Excavate

898 Conc. Foundation

899 Backfill

900 termite treatment

901 DPC (where applicable)

902 M&E inlet/outlet works - first fix

903 frame

904 set kickers

905 Conc. Columns & shear walls

906 Conc. G. F Beams

907 M&E first fix

908 Conc. Plantroom

909 Conc. Floor slab & swimming pool base

910 Blockwork

911 Conc. Swimming pool sides & overflow channels

912 Conc. Ring & tie beams

913 Roof & Ceiling

920 Finishes

928 M&E Installations

939 Villa A3/09

984 Villa A3/10

985 substructure

986 set out

987 Excavate

988 Conc. Foundation

989 Backfill

990 termite treatment

991 DPC (where applicable)

992 M&E inlet/outlet works - first fix

993 frame

994 set kickers

995 Conc. Columns & shear walls

996 Conc. G. F Beams

997 M&E first fix

998 Conc. Plantroom

999 Conc. Floor slab & swimming pool base

1000 Blockwork

1001 Conc. Swimming pool sides & overflow channels

1002 Conc. Ring & tie beams

1003 Roof & Ceiling

1010 Finishes

1018 M&E Installations

1029 Villa A3/11

1074 Villa A3/12

1119 Villa A3/13

1164 Villa A3/18

1209 Villa A3/19

1254 Villa A3/20

1299 Villa A3/21

1344 Villa A3/22

1389 Villa A3/23

1434 Villa A3/24

1479 Villa A3/25

1524 Villa A3/26

1569 Villa A3/27

1570 substructure

1571 set out

1572 Excavate

1573 Conc. Foundation

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

page 115

Page 116: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

1574 Backfill

1575 termite treatment

1576 DPC (where applicable)

1577 M&E inlet/outlet works - first fix

1578 frame

1579 set kickers

1580 Conc. Columns & shear walls

1581 Conc. G. F Beams

1582 M&E first fix

1583 Conc. Plantroom

1584 Conc. Floor slab & swimming pool base

1585 Blockwork

1586 Conc. Swimming pool sides & overflow channels

1587 Conc. Ring & tie beams

1588 Roof & Ceiling

1595 Finishes

1603 M&E Installations

1614 B223 Villas ( 7 nos)

1615 Villa B2/01

1665 Villa B2/02

1666 substructure

1667 set out

1668 Excavate

1669 Conc. Foundation

1670 Backfill

1671 termite treatment

1672 DPC (where applicable)

1673 M&E inlet/outlet works - first fix

1674 frame

1675 set kickers

1676 Conc. Columns & shear walls to GF

1677 Conc. Plantrooms

1678 M&E first fix GF

1679 Conc. GF slab and beams

1680 Blockwork up to FF slab

1681 set kickers on GF

1682 Conc. Columns & shear walls to FF

1683 M&E first fix FF

1684 Conc. FF slab & beams

1685 Blockwork up to roof

1686 set kickers on FF

1687 Conc. Columns & shear walls to roof

1688 M&E first fix roof

1689 Conc. Ring & tie beams

1690 Roof & Ceiling

1697 Finishes

1704 M&E Installations

1715 Villa B2/04

1765 Villa B2/05

1815 Villa B2/06

1865 Villa B2/07

1915 Villa B2/08

1965 B4 Villa (2 nos.)

2056 Retail 1( subject to receipt of GFW drawings)

2094 Retail 2( subject to receipt of GFW drawings)

2132 Retail 3( subject to receipt of GFW drawings)

2170 Seafood resort( subject to receipt of GFW drawings)

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2264 Villa A3/14

2309 Villa A3/15

2354 Villa A3/16

2399 Villa A3/17

2444 Villa A3/28

2445 substructure

2446 set out

2447 Excavate

2448 Conc. Foundation

2449 Backfill

2450 termite treatment

2451 DPC (where applicable)

2452 M&E inlet/outlet works - first fix

2453 frame

2454 set kickers

2455 Conc. Columns & shear walls

2456 Conc. G. F Beams

2457 M&E first fix

2458 Conc. Plantroom

2459 Conc. Floor slab & swimming pool base

2460 Blockwork

2461 Conc. Swimming pool sides & overflow channels

2462 Conc. Ring & tie beams

2463 Roof & Ceiling

2470 Finishes

2478 M&E Installations

2489 Villa A3/29

2490 substructure

2491 set out

2492 Excavate

2493 Conc. Foundation

2494 Backfill

2495 termite treatment

2496 DPC (where applicable)

2497 M&E inlet/outlet works - first fix

2498 frame

2499 set kickers

2500 Conc. Columns & shear walls

2501 Conc. G. F Beams

2502 M&E first fix

2503 Conc. Plantroom

2504 Conc. Floor slab & swimming pool base

2505 Blockwork

2506 Conc. Swimming pool sides & overflow channels

2507 Conc. Ring & tie beams

2508 Roof & Ceiling

2515 Finishes

2523 M&E Installations

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

page 116

Page 117: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2534 Villa A3/30

2535 substructure

2536 set out

2537 Excavate

2538 Conc. Foundation

2539 Backfill

2540 termite treatment

2541 DPC (where applicable)

2542 M&E inlet/outlet works - first fix

2543 frame

2544 set kickers

2545 Conc. Columns & shear walls

2546 Conc. G. F Beams

2547 M&E first fix

2548 Conc. Plantroom

2549 Conc. Floor slab & swimming pool base

2550 Blockwork

2551 Conc. Swimming pool sides & overflow channels

2552 Conc. Ring & tie beams

2553 Roof & Ceiling

2560 Finishes

2568 M&E Installations

2579 Villa A3/31

2580 substructure

2581 set out

2582 Excavate

2583 Conc. Foundation

2584 Backfill

2585 termite treatment

2586 DPC (where applicable)

2587 M&E inlet/outlet works - first fix

2588 frame

2589 set kickers

2590 Conc. Columns & shear walls

2591 Conc. G. F Beams

2592 M&E first fix

2593 Conc. Plantroom

2594 Conc. Floor slab & swimming pool base

2595 Blockwork

2596 Conc. Swimming pool sides & overflow channels

2597 Conc. Ring & tie beams

2598 Roof & Ceiling

2599 Fix wall plate & truss

2600 Fix purlins and rafters

2601 Fix shingles ( subject to receipt of timber)

2602 Fix ceiing battens & joists

2603 Fix ceiling boards

2604 M&E first fix

2605 Finishes

2606 Wall plaster (internal & External)

2607 M&E 1st fix

2608 Floor finishes

2609 Fix windows & doors

2610 Swimming pool finishes

2611 M&E final fix

2612 Fix fittings and Fixtures

2613 M&E Installations

2614 Cable Tray, Conduit and Wiring

2615 Electrical boards and connections

2616 Electrical accessories

2617 Light fittings and ceiling fans

2618 Hot and cold water

2619 Waste and sewage incl. biobox

2620 Electric water heater

2621 Swimming pool

2622 Split unit installation

2623 Toilet ventilation, grilles

2624 Villa A3/32

2664 B223 Villas ( 3 nos)

2665 Villa B2/03

2708 Villa B2/09

2758 Villa B2/10

2808 B4 Standard Villas ( 2 nos)

2899 BC311 Executive Villa

3115 P3 Presidential suites ( 3 nos)

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009

The following table shows the individual delays arising at each villa suspended which also incorporates the delays described in Event 1 through to 4.

page 117

Page 118: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/06 09-Apr-07 05-Aug-08 23-Jul-07 15-Mar-08 236.13 484.38 248.25A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00B2/02 16-Apr-07 13-Sep-08 03-Jul-07 15-Mar-08 256.13 516.33 260.21

Impacted Programme Baseline Programme

As a result the delay caused by this event is not critical and the time for completion has not extended the revised date of 9 September 2009.

Consequently, the revised completion date remains at 9 September 2009.

page 118

Page 119: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.1.4.6. Event No 6 – Design Variations (Stainless Steel Items)

ID Task Name

1 SHANGRI-LA , Long Island Resort Seychelles

2 General Conditions and Preliminaries

17 Site establishment

41 Material/equipment procurement

182 Lot 1

183 A3 Villas ( 6 nos)

184 Villa A3/01

228 Villa A3/02

273 Villa A3/03

318 Villa A3/04

363 Villa A3/05

408 Villa A3/06

453 C311 Executive Villas ( 1 nos)

497 GM Villa ( subject to receipt of GFW drawings)

537 Employees Facilities ( subject to receipt of GFW drawings)

581 Laundry F& B service office ( subject to receipt of GFW drawings)

625 Health Club/ Medical Centre( subject to receipt of GFW drawings)

666 Administration Block ( subject to receipt of GFW drawings)

707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)

750 Main Lobby ( subject to receipt of GFW drawings)

791 Tennis Courts ( subject to receipt of GFW drawings)

807 External works ( subject to receipt of GFW drawings)

816 Drainage works ( subject to receipt of EME details)

819 Fuel Farm ( subject to receipt of EME details)

823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)

827 Desalination plant( subject to receipt of EME details)

831 MLV Panel( subject to receipt of EME details)

835 Step Up Transformer( subject to receipt of EME details)

839 Incinerator/ Garbage room( subject to receipt of EME details)

843 Sewer treatement plant( subject to receipt of EME details)

847 Lot 2

848 A3 Villas (17 nos)

849 Villa A3/07

894 Villa A3/08

939 Villa A3/09

984 Villa A3/10

1029 Villa A3/11

1074 Villa A3/12

1119 Villa A3/13

1164 Villa A3/18

1209 Villa A3/19

1254 Villa A3/20

1299 Villa A3/21

1344 Villa A3/22

1389 Villa A3/23

1434 Villa A3/24

1479 Villa A3/25

1524 Villa A3/26

1569 Villa A3/27

1614 B223 Villas ( 7 nos)

1615 Villa B2/01

1665 Villa B2/02

1715 Villa B2/04

1765 Villa B2/05

1815 Villa B2/06

1865 Villa B2/07

1915 Villa B2/08

1965 B4 Villa (2 nos.)

2056 Retail 1( subject to receipt of GFW drawings)

2094 Retail 2( subject to receipt of GFW drawings)

2132 Retail 3( subject to receipt of GFW drawings)

2170 Seafood resort( subject to receipt of GFW drawings)

2211 Greeting Pavillion( subject to receipt of GFW drawings)

2250 External works ( subject to receipt of GFW drawings)

2259 Drainage works ( subject to receipt of EME details)

2262 Lot 3

2263 A3 Villas ( 9 nos)

2264 Villa A3/14

2309 Villa A3/15

2354 Villa A3/16

2399 Villa A3/17

2444 Villa A3/28

2489 Villa A3/29

2534 Villa A3/30

2579 Villa A3/31

2624 Villa A3/32

2625 substructure

2626 set out

2627 Excavate

2628 Conc. Foundation

2629 Backfill

2630 termite treatment

2631 DPC (where applicable)

2632 frame

2633 set kickers

2634 Conc. Columns & shear walls

2635 Conc. Ground Beams

2636 Conc. Plantroom

2637 Conc. Floor slab & swimming pool base

2638 Blockwork

2639 Conc. Swimming pool sides & overflow channels

2640 Conc. Ring & tie beams

2641 Roof & Ceiling

2642 Fix wall plate & truss

2643 Fix purlins and rafters

2644 Fix shingles ( subject to receipt of timber)

2645 Fix ceiing battens & joists

2646 Fix ceiling boards

2647 Finishes

2648 Wall plaster (internal & External)

2649 Floor finishes

2650 Fix windows & doors

2651 Swimming pool finishes

2652 Fix fittings and Fixtures

2653 M&E Installations

2654 Cable Tray, Conduit and Wiring

2655 Electrical boards and connections

2656 Electrical accessories

2657 Light fittings and ceiling fans

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep2007 2008 2009

page 119

Page 120: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Task Name

2658 Hot and cold water

2659 Waste and sewage incl. biobox

2660 Electric water heater

2661 Swimming pool

2662 Split unit installation

2663 Toilet ventilation, grilles

2664 B223 Villas ( 3 nos)

2665 Villa B2/03

2666 substructure

2667 set out

2668 Excavate

2669 Conc. Foundation

2670 Backfill

2671 termite treatment

2672 DPC (where applicable)

2673 frame

2674 set kickers

2675 Conc. Columns & shear walls to GF

2676 Conc. Plantrooms

2677 Conc. GF slab and beams

2678 Blockwork up to FF slab

2679 set kickers on GF

2680 Conc. Columns & shear walls to FF

2681 Conc. FF slab & beams

2682 Blockwork up to roof

2683 set kickers on FF

2684 Conc. Columns & shear walls to roof

2685 Conc. Ring & tie beams

2686 Roof & Ceiling

2687 Fix wall plate & truss

2688 Fix purlins and rafters

2689 Fix shingles ( subject to receipt of timber)

2690 Fix ceiing battens & joists

2691 Fix ceiling boards

2692 Finishes

2693 Wall plaster (internal & External)

2694 Floor finishes

2695 Fix windows & doors

2696 Fix fittings and Fixtures

2697 M&E Installations

2698 Cable Tray, Conduit and Wiring

2699 Electrical boards and connections

2700 Electrical accessories

2701 Light fittings and ceiling fans

2702 Hot and cold water

2703 Waste and sewage incl. biobox

2704 Electric water heater

2705 Swimming pool ( not applicable)

2706 Split unit installation

2707 Toilet ventilation, grilles

2708 Villa B2/09

2758 Villa B2/10

2808 B4 Standard Villas ( 2 nos)

2899 BC311 Executive Villa

3115 P3 Presidential suites ( 3 nos)

3245 Hilltop sunset deck( subject to receipt of GFW drawings)

3280 External works ( subject to receipt of GFW drawings)

3289 Drainage works ( subject to receipt of EME details)

3292 Lot 4

3293 Couple treatment room( subject to receipt of GFW drawings)

3334 Single treatment room( subject to receipt of GFW drawings)

3375 Dive Centre( subject to receipt of GFW drawings)

3413 Kid's club( subject to receipt of GFW drawings)

3452 Recreation House( subject to receipt of GFW drawings)

3491 Watersports rental( subject to receipt of GFW drawings)

3529 3 Meals restaurant( subject to receipt of GFW drawings)

3570 Beach Pool Bar( subject to receipt of GFW drawings)

3611 Signature Pool area( subject to receipt of GFW drawings)

3650 Wedding Chapel( subject to receipt of GFW drawings)

3685 BOH/Admin Building( subject to receipt of GFW drawings)

3726 Chi Sanctum( subject to receipt of GFW drawings)

3767 Yoga Pavillion( subject to receipt of GFW drawings)

3805 External works ( subject to receipt of GFW drawings)

3814 Drainage works ( subject to receipt of EME details)

3817 M&E Installations- External

3828 Sundries

3829 Site cleaning & demobilisation

3830 Project Commissioning

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2007 2008 2009

Similarly, the following table shows the delay which occurred at the Mock-up Villas. Again, this delay is not critical to completion because of the earlier delays.

Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/32 28-May-07 19-Mar-08 28-May-07 16-Nov-07 172.04 296.17 124.13B2/03 28-May-07 12-May-08 28-May-07 04-Dec-07 190.17 350.38 160.21

Impacted Programme Baseline Programme

page 120

Page 121: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

5.2. Conclusion

At the outset of the Contract the Contractor suffered delays in setting out the works. This was followed by significant disruption caused by excavation in hard rock and partial suspension of Works. With respect to the Contract and the Contractor’s Programme of Works to which consent has been given, such departure from his original planning has caused significant increased cost. In addition, significant increases in quantities of work caused the Contractor to fall further behind his programme.

The Project Manager also required the Contractor to perform his work in accordance with the Programme of Works. In addition, he has the duty to provide correct design details, in conformance with site conditions, to the Contractor in good time for him to be able to perform his material procurement and construction work in accordance with that programme.

By altering the sequence, timing and quality of the design details supplied to the Contractor, the Project Manager has acted outside the boundaries of the existing Contract provisions.

In failing to provide final survey data, unnecessarily suspending Works, failing to have identified and have taken account site conditions, and not providing design information to the Contractor in accordance with the Programme of Works, the Employer is in breach of his obligations (through the Project Manager in respect of design information) under the terms of the Contract.

Furthermore, by altering the sequence, timing and quality of the design information, when it was eventually provided to the Contractor, the Project Manager has required the Contractor to operate in a manner different from, slower and more expensive than had been shown on the Programme of Works than he had reasonably anticipated at the time of tender.

The consequences of this breach and variance of the Contract, in terms of time for completion and financial compensation, are explained in previous and subsequent sections of this submission.

page 121

Page 122: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

6. Financial Analysis

6.1. Consequences

During the periods of delay and disruption which results directly from the varied site circumstances, varied scope of work, piece-meal work or an adverse condition, the Contractor has incurred costs of reduced and non-productive work necessitated by retaining levels of resources, which otherwise would have been decreased or deployed elsewhere. The Contractor would maintain that it was not reasonable to discharge Staff and Labour and remove equipment off Site for those periods. These costs include idle equipment and labour and other direct costs, and are recoverable under the terms and conditions of contract.

Furthermore, in response to the change in timing and sequence of the Works, the Contractor has reorganised his resources to meet the varied circumstances. As a consequence of such measures to improve his production, loss of efficiency costs caused by overtime, extra crews, larger crews, crowding or stacking of trades, are recoverable costs under the terms and conditions of contract. These additional costs are Wasted Costs (in order to use one title to capture all delaying events) and are recoverable as a Variation under the terms of the Contract.

Finally, because of the delays, which are not the fault of the Contractor, substantial completion of the whole Works can only be achieved beyond the original date. Consequently, the Contractor will incur additional costs in the extended period that is not recovered through the rates and prices of the contract.

An aspect of delay-induced expense is the cost of continuing work on a project over a longer time than first anticipated. Additional costs of labour, equipment and overhead has been incurred due to the fact that performance had to be spread out, sometimes leaving the Contractor’s resources idle or forced personnel and equipment to remain thus postponing other work sites.

Therefore, the amount of recovery is based on the total amount of cost expended during the period the contract was delayed. At the time of preparing this claim submission, delays and disruption continue and consequently, additional costs.

The Contractor is entitled to recover the cost of his resources, overheads and profit for this period. The additional costs will fall under three categories:

page 122

Page 123: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

6.1.1.Direct Cost

The direct cost of this event, delay and disruption, is the cost of labour, staff and equipment directly employed at the Site including profit.

6.1.2.Indirect Cost

Indirect cost flows from on-site establishments such as the Contractor’s head and site offices and yard, which overheads are only partially recovered during the periods of planned construction operations when extended.

6.1.3.Consequential Cost

The consequential cost is the effect on the work in terms of disruption to the various activities and prolongation of the Contractor’s time related resources arising from re-sequencing the planned work.

This cause occurred at the outset of the project and disruption has been assessed as significant. The change, impacts planned logic and links of many tasks shown on his Programme of Works on which, the Contractor is heavily dependant if he is to retain his original tender cost provisions.

6.2. Costs in Extended Contract Period

6.2.1.Nature of Loss and Expense

The loss and expense flowing from the causes described in this Document are time-related. The loss and expense attributable to these causes has been incurred over all of the Periods identified in this claim. However, the major period in which variations have caused loss and expense is:

In the period of construction to date, May 2008, and

In the extended construction period.

page 123

Page 124: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

6.2.2.Contractor’s Entitlement to Reimbursement

Instructions issued are covered by the first paragraph of Clause 13.1 of the Conditions. This refers to Instructions in regard to:

Revised setting out details;

Suspension of Work;

Design drawings issued for construction; and

Additional and varied works.

The criteria for allowing the Contractor reimbursement are given in the penultimate paragraph of Clause 12.3:

Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.

The loss and expense were not provided for, nor reasonably contemplated by, the Contract. The Instructions did not result from a breach by the Contractor. Accordingly, the loss and expense must be added to the Contract Price.

6.3. Finance Cost

As this is a claim for breach of contract, the Contractor’s approach to the quantum, or the measure of damage, is to follow the common law rule. This is that the damages should put the complaining party in the position he would have been, had the breach not taken place, insofar as damages can do that.

In order to attain this, the Contractor has approached the calculation of the quantum of the damages by asking what would have happened, had the breach not taken place, and comparing that with what did actually happen. The measure of the damage is the financial consequences flowing from the difference between the two positions.

There is one generic type of potential direct damage suffered while the other is the financing of the work. Those two aspects are summarised in the two points below:

page 124

Page 125: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

1. Loss of anticipated income by way of financing. This is the cost to the Contractor of financing the shortfall between the income he reasonably expected to receive, and what he actually received.

2. The idle time, and/or reduced output, of resources from the outset of the contract to the present date.

In addition, for the purpose of satisfying the Employer’s requirements for identifying additional costs, the Contractor has also included additional costs anticipated to January 2010. This date is the latest the Contractor anticipates reaching substantial completion given all the varying circumstances existing at site.

6.4. Conclusions

In failing to provide final survey data and all the various design details, the unforeseen ground conditions, instructing suspension of the Works and subsequently altering the sequence, timing and logic of his original planning, the Employer has caused the Contractor to unavoidably incur greater costs, loss and expense than would have been the case had the failure not occurred. These costs are evaluated in subsequent sections of this submission.

Since these costs, losses and expense have flowed directly from the Employer’s failure and subsequent deviation from the terms of the Contract, the Contractor is entitled to be compensated for them by the Employer paying a fair value for the different type of work that has been performed.

page 125

Page 126: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

7. Extension of Time Entitlement

The Project Manager is requested to refer to the Contractor’s two separate submissions for extensions of time and the detailed analysis included in those submissions.

The Contractor had planned that all his resources would be deployed at Site from 7 March 2007 through to 31 May 2008. In the event, because of circumstances beyond his control and not his responsibility, it is anticipated resources of the Contractor will be delayed at Site until 31 January 2010.

Therefore, in order to complete the whole Works, the Contractor requires a further 20 months to reach substantial completion. This includes the first and second requests for an interim extension of the period to Completion, whereas:

First. Requested on 21 November 2007 for an extension of time amounting to 191-calendar days from 31 May 2008 to 8 December 2008. The Project Manager’s determination has not been issued at time of compiling this submission;

Second. Requested on 14 March 2008 for an extension of time amounting to 106-calendar days from 8 December 2008 to 24 March 2009. The Project Manager’s determination has not been issued at time of compiling this submission.

The Contractor on 19 November 2007 had also updated his programme of works showing progress achieved at 6 November 2007. In the final paragraph he stated:

Unless notice is received stating the extent to which it does not comply with the Contract, we shall proceed in accordance with this programme and will rely upon this programme when planning our activities.

The Project Manager has not responded to this notice at time of compiling this submission or to making an interim determination for an extension of time requested in neither the Contractor’s First request nor his Second Request.

Consequently, the Extension of Time to which the Contractor is now fairly entitled to receive amounts to 20 months from 31 May 2008 to 31 January 2010 as substantiated in this submission. This is the date on which it is anticipated substantial Completion will be achieved.

page 126

Page 127: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

8. Additional Payment

8.1. Introduction

Each of the sections in this document briefly describes the events that have occurred that are contrary to those envisaged at time of tender. Therefore, allowance for the event so described has not been made in the tender rates and prices. This Chapter of the document contains the financial details, demonstrating the reimbursable additional value or cost of these disruptive events.

This unforeseen difficulty has impacted all the Contractor's resources that were on site during the periods of delay and disruption. In addition, the same resources are, as a consequence of the varied circumstances, to be retained on Site for a further 20 months. That is from the original Completion date to 31 January 2010.

8.2. Evaluation of the Financial Consequences

The delay and disruption has been caused by late survey data, unforeseen ground conditions, suspension of works, varied scope of work and to incomplete and late design information.

Although the Contractor continued to perform as much work as possible in these periods, the unforeseen conditions and changed circumstances will cause the original time to completion to extend from 31 May 2008 to 31 January 2010.

The extension of time and associated loss and expense the Contractor has suffered falls into five categorises:

In the original construction period when equipment and labour resources were under-utilised and recovery of overheads were not secured because of a reduced income;

In an extended period when again the equipment and labour resources will be retained on Site for longer than planned and overheads are not recovered;

In measures taken to recover earlier delays by the addition of resources and working longer hours; and

Other Direct and Indirect Costs

page 127

Page 128: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

In the original and extended period of construction where the cost of financing construction increased due to the longer period to completion.

8.2.1.Wasted Costs Arising from Delay and Disruption

These costs arise in the period from commencement to May 2008.

8.2.1.1. Staff and Labour

The following table provides a summary of planned revenue against actual. The fourth column records the shortfall value which is expressed as a percentage on planned.

Forecast Actual Shortfall as aMonth Monthly Monthly Shortfall % of Forecast

Feb-07 3,100,000.00 0.00 3,100,000.00 100%Mar-07 601,658.62 0.00 601,658.62 100%Apr-07 1,352,295.74 0.00 1,352,295.74 100%

May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%Jun-07 2,236,090.71 0.00 2,236,090.71 100%Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%

Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%Dec-07 1,754,288.50 0.00 1,754,288.50 100%Jan-08 1,289,372.84 0.00 1,289,372.84 100%Feb-08 1,040,280.70 274,355.16 765,925.54 74%Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%Apr-08 2,575,212.46 0.00 2,575,212.46 100%

May-08 0.00 0.00 0.00 0%

The next table provides a summary of the actual cost of labour from commencement to end of May 2008. Against these values the percentage calculated representing the shortfall on revenue has been applied to arrive at the value of wasted costs. To this figure 15% profit has been added in order to properly value the Variation.

page 128

Page 129: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 100% 26,831.00 4,024.65 30,855.65Apr-07 47,046.00 100% 47,046.00 7,056.90 54,102.90

May-07 52,890.00 -67% -35,606.35 -5,340.95 -40,947.30Jun-07 60,384.00 100% 60,384.00 9,057.60 69,441.60Jul-07 60,984.00 75% 45,489.26 6,823.39 52,312.65

Aug-07 61,812.00 84% 51,876.82 7,781.52 59,658.34Sep-07 61,812.00 93% 57,781.57 8,667.24 66,448.80Oct-07 67,056.00 84% 56,437.80 8,465.67 64,903.47Nov-07 80,944.00 79% 63,775.99 9,566.40 73,342.39Dec-07 86,068.00 100% 86,068.00 12,910.20 98,978.20Jan-08 86,709.00 100% 86,709.00 13,006.35 99,715.35Feb-08 85,629.00 74% 63,045.90 9,456.89 72,502.79Mar-08 90,629.00 -117% -106,171.08 -15,925.66 -122,096.75Apr-08 90,629.00 100% 90,629.00 13,594.35 104,223.35

May-08 115,007.00 0% 0.00 0.00 0.00

Total 683,441.44

8.2.1.2. Equipment

The following table provides a summary of planned revenue against actual. The fourth column records the shortfall value which is expressed as a percentage on planned.

Forecast Actual Shortfall as aMonth Monthly Monthly Shortfall % of Forecast

Feb-07 3,100,000.00 0.00 3,100,000.00 100%Mar-07 601,658.62 0.00 601,658.62 100%Apr-07 1,352,295.74 0.00 1,352,295.74 100%

May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%Jun-07 2,236,090.71 0.00 2,236,090.71 100%Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%

Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%Dec-07 1,754,288.50 0.00 1,754,288.50 100%Jan-08 1,289,372.84 0.00 1,289,372.84 100%Feb-08 1,040,280.70 274,355.16 765,925.54 74%Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%Apr-08 2,575,212.46 0.00 2,575,212.46 100%

May-08 0.00 0.00 0.00 0%

The next table provides a summary of the actual cost of equipment from commencement to end of May 2008. Against these values the percentage calculated representing the shortfall on revenue has been applied to arrive at the value of wasted costs. To this figure 15% profit has been added in order to properly value the Variation

page 129

Page 130: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Apr-07 262,545.19 100% 262,545.19 39,381.78 301,926.96

May-07 262,545.19 -67% -176,749.40 -26,512.41 -203,261.81Jun-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Jul-07 262,545.19 75% 195,838.02 29,375.70 225,213.72

Aug-07 262,545.19 84% 220,345.72 33,051.86 253,397.58Sep-07 262,545.19 93% 245,426.01 36,813.90 282,239.91Oct-07 262,545.19 84% 220,971.60 33,145.74 254,117.34Nov-07 262,545.19 79% 206,860.05 31,029.01 237,889.06Dec-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Jan-08 262,545.19 100% 262,545.19 39,381.78 301,926.96Feb-08 269,952.60 74% 198,757.50 29,813.62 228,571.12Mar-08 293,656.30 -117% -344,015.79 -51,602.37 -395,618.16Apr-08 293,656.30 100% 293,656.30 44,048.44 337,704.74

May-08 293,656.30 0% 0.00 0.00 0.00

Total 2,729,888.31

8.2.1.3. Site and Head Office

The following table provides the wasted costs associated with the indirect staff and labour costs arising from the Site Office overheads. The value of overheads is estimated to be at 3%.

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 3% 804.93 120.74 925.67Apr-07 47,046.00 3% 1,411.38 211.71 1,623.09

May-07 52,890.00 3% 1,586.70 238.01 1,824.71Jun-07 60,384.00 3% 1,811.52 271.73 2,083.25Jul-07 60,984.00 3% 1,829.52 274.43 2,103.95

Aug-07 61,812.00 3% 1,854.36 278.15 2,132.51Sep-07 61,812.00 3% 1,854.36 278.15 2,132.51Oct-07 67,056.00 3% 2,011.68 301.75 2,313.43Nov-07 80,944.00 3% 2,428.32 364.25 2,792.57Dec-07 86,068.00 3% 2,582.04 387.31 2,969.35Jan-08 86,709.00 3% 2,601.27 390.19 2,991.46Feb-08 85,629.00 3% 2,568.87 385.33 2,954.20Mar-08 90,629.00 3% 2,718.87 407.83 3,126.70Apr-08 90,629.00 3% 2,718.87 407.83 3,126.70

May-08 115,007.00 3% 3,450.21 517.53 3,967.74

Total 37,067.84

Similarly, the table below provides the wasted costs associated with indirect staff and labour costs arising from the Head Office overheads. The value of overheads is estimated to be 9%.

page 130

Page 131: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 9% 2,414.79 362.22 2,777.01Apr-07 47,046.00 9% 4,234.14 635.12 4,869.26

May-07 52,890.00 9% 4,760.10 714.02 5,474.12Jun-07 60,384.00 9% 5,434.56 815.18 6,249.74Jul-07 60,984.00 9% 5,488.56 823.28 6,311.84

Aug-07 61,812.00 9% 5,563.08 834.46 6,397.54Sep-07 61,812.00 9% 5,563.08 834.46 6,397.54Oct-07 67,056.00 9% 6,035.04 905.26 6,940.30Nov-07 80,944.00 9% 7,284.96 1,092.74 8,377.70Dec-07 86,068.00 9% 7,746.12 1,161.92 8,908.04Jan-08 86,709.00 9% 7,803.81 1,170.57 8,974.38Feb-08 85,629.00 9% 7,706.61 1,155.99 8,862.60Mar-08 90,629.00 9% 8,156.61 1,223.49 9,380.10Apr-08 90,629.00 9% 8,156.61 1,223.49 9,380.10

May-08 115,007.00 9% 10,350.63 1,552.59 11,903.22

Total 111,203.51

The following table provides the wasted costs associated with the indirect Equipment costs arising from the Site Office overheads. The value of overheads is estimated to be at 3%.

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Apr-07 262,545.19 3% 7,876.36 1,181.45 9,057.81

May-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jun-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jul-07 262,545.19 3% 7,876.36 1,181.45 9,057.81

Aug-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Sep-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Oct-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Nov-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Dec-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jan-08 262,545.19 3% 7,876.36 1,181.45 9,057.81Feb-08 269,952.60 3% 8,098.58 1,214.79 9,313.36Mar-08 293,656.30 3% 8,809.69 1,321.45 10,131.14Apr-08 293,656.30 3% 8,809.69 1,321.45 10,131.14

May-08 293,656.30 3% 8,809.69 1,321.45 10,131.14

Total 139,342.69

Similarly, the table below provides the wasted costs associated with indirect staff and labour costs arising from the Head Office overheads. The value of overheads is estimated to be 9%.

page 131

Page 132: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Apr-07 262,545.19 9% 23,629.07 3,544.36 27,173.43

May-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jun-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jul-07 262,545.19 9% 23,629.07 3,544.36 27,173.43

Aug-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Sep-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Oct-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Nov-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Dec-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jan-08 262,545.19 9% 23,629.07 3,544.36 27,173.43Feb-08 269,952.60 9% 24,295.73 3,644.36 27,940.09Mar-08 293,656.30 9% 26,429.07 3,964.36 30,393.43Apr-08 293,656.30 9% 26,429.07 3,964.36 30,393.43

May-08 293,656.30 9% 26,429.07 3,964.36 30,393.43

Total 418,028.07

8.2.1.4. Summary of Wasted Costs

Item Category Amount

Staff and Labour 683,441.44Equipment 2,729,888.31Site Overheads Staff and Labour 37,067.84

Equipment 139,342.69Head Office Overheads Staff and Labour 111,203.51

Equipment 418,028.07

Total 4,118,971.85

8.2.2.Additional Costs Arising from Acceleration

In order to recover part of the earlier delays the Contractor has already implemented steps to improve and increase his staff, labour and equipment.

At this juncture the Contractor has ordered and organised the following additional resources shown in the table below.

page 132

Page 133: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour

1 Senior Project Manager 168,630.002 Quality Assurance Manager 168,630.003 Senior Quantity Surveyor 107,250.004 Assistant Quantity Surveyor 99,000.005 Expatriate Workers 880,000.00 1,423,510.00

Equipment

1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Total additonal resources 1,958,701.00

8.2.3.Additional Costs in Extended Contract Period

The Contractor has entitlement to recovery of his indirect costs arising in the extended contract period. These costs arise in the period the Contract is extended as a result of critical delays.

Consequently, this allowance has no relation to additional expenditure arising in the original contract period as a result of non-critical delays. That is to say, those costs that are attributed to delay and disruption, the first period, are separate to costs flowing in an extended period, the second period.

The Contractor has entitlement to payment of additional indirect costs in the period they arise. However, this recovery would exclude his indirect costs not paid through his rates and prices for doing the work which remain recoverable in the extended period. These costs are detailed below:

page 133

Page 134: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Item Nature of Cost Fixed Variable PlannedCost ExtendedPeriod

1 Insurance 250,000.00 17,857.14 321,428.572 Foreign Staff, Labour Repatriation 450,000.00 32,142.86 578,571.433 Facilities for Staff and Labour 170,000.00 12,142.86 218,571.434 Measures against Insect and Pect Nuisance 60,000.00 4,285.71 77,142.865 Supply of Foodstuffs 660,000.00 47,142.86 848,571.436 Supply of Water 80,318.00 5,737.00 103,266.007 Shop Drawings 10,000.00 714.29 12,857.148 As-Built Documents 5,600.00 400.00 7,200.009 Temporary Site Office for Employers Consultants 65,250.00 0.00 0.0010 Site Signboard 3,275.00 0.00 0.0011 Access to Site 35,000.00 2,500.00 45,000.0012 Site to be Tidy 12,727.00 909.07 16,363.2913 Co-ordination 14,727.00 1,051.93 18,934.7114 Site Records 3,275.00 233.93 4,210.7115 Site Records 29,913.00 2,136.64 38,459.5716 Safety Procedures 5,700.00 407.14 7,328.5717 Security at Site 13,426.00 959.00 17,262.0018 Contractors Site Operations 7,485.00 534.64 9,623.5719 Site Radio Communication 11,725.00 0.00 0.0020 Environmental Impact Assessment 5,000.00 0.00 0.0021 Taking Delivery from NS 50,000.00 3,571.43 64,285.7122 Contractors Temporary Accommodation 35,000.00 2,500.00 45,000.0023 Superintendence 15,000.00 1,071.43 19,285.7124 Transport of People 125,475.00 8,962.50 161,325.0025 Contractors Equipment 365,000.00 26,071.43 469,285.7126 Scaffolding 105,000.00 7,500.00 135,000.00

Total 3,218,973.43

8.2.4.Other Costs

The following activities caused the Contractor to incur additional costs because of the changed events described in this document. At time of preparing this submission these costs have yet to be ascertained and will therefore, be part of future claim submissions.

8.2.4.1. Procurement of Permanent Materials

The following table provides a summary of all major materials ordered on the project to date. It will be noted that all major materials required for 55 number villas are ordered although the constraint to receiving the complete order is payment.

The inability to complete full payment to the supplier has been explained in various notifications, particularly the Advance recovery which is disconnected from progress payments. This compounded an existing reduced income generated each month because progress could not be achieved as planned due to as example, unforeseen ground conditions.

page 134

Page 135: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Des c ription of MaterialsQuantity Ordered Date Ordered Amount rec eived B alanc e C omments

F OR AL L 55 VIL L AS

50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order subject to payment to supplierP lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order subject to payment to supplierC rusher Dust 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order subject to payment to supplierAggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order subject to payment to supplierP las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order subject to payment to supplier150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order subject to payment to supplier100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order subject to payment to supplierA252 Weld Mesh (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order subject to payment to supplierHigh tens ile s teel-8,10,12,16,25mm (tons) 500.00 14/01/07 158.00 342.00 B alance on order subject to payment to supplierC edar S hingles (sqm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order subject to payment to supplierIroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order subject to payment to supplier12mm G ypsum boards (S HE E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.DS tainless s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order subject to payment to supplier (Not B .O .Q item)S tainless s teel gusset plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order subject to payment to supplier (Not B .O .Q item)B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order subject to payment to supplierT reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order subject to payment to supplier

Consequently, it is likely initial materials ordered and not secured by full payment will attract a different cost at a later date. The additional cost arising is not the responsibility of the Contractor. These costs will be identified and evidenced at a later date as they arise.

8.2.4.2. Temporary Materials including Equipment

A similar situation exists with temporary materials whereby orders could not be made to enhance productivity at Site.

8.2.5.Finance Costs

The additional costs defined within the preceding sections of this chapter on claim for additional payment have been borne and financed by the Contractor. The Contractor has paid the costs by obtaining bank loans or overdrafts, or by the use of working capital that would have been employed in profitable work. These financing costs are an additional cost incurred as a consequence of the circumstances herein and, become part of the reimbursable sum.

The Contractor has carried this additional cost since the outset of the Contract to the present date, end of May 2008, a period of about 14 months.

Compound interest over this period is against the heads of cost amount to:

page 135

Page 136: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Month Labour Equipment Sub-total SiteO/H H/Q Total Sub-total Total

Mar-07 26,831.00 262,545.19 289,376.19 3.00% 9.00% 12.00% 34,725.14 324,101.33 Apr-07 47,046.00 262,545.19 309,591.19 3.00% 9.00% 12.00% 37,150.94 346,742.13 May-07 52,890.00 262,545.19 315,435.19 3.00% 9.00% 12.00% 37,852.22 353,287.41 Jun-07 60,384.00 262,545.19 322,929.19 3.00% 9.00% 12.00% 38,751.50 361,680.69 Jul-07 60,984.00 262,545.19 323,529.19 3.00% 9.00% 12.00% 38,823.50 362,352.69 Aug-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05 Sep-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05 Oct-07 67,056.00 262,545.19 329,601.19 3.00% 9.00% 12.00% 39,552.14 369,153.33 Nov-07 80,944.00 262,545.19 343,489.19 3.00% 9.00% 12.00% 41,218.70 384,707.89 Dec-07 86,068.00 262,545.19 348,613.19 3.00% 9.00% 12.00% 41,833.58 390,446.77 Jan-08 86,709.00 269,952.60 356,661.60 3.00% 9.00% 12.00% 42,799.39 399,460.99 Feb-08 85,629.00 293,656.30 379,285.30 3.00% 9.00% 12.00% 45,514.24 424,799.53 Mar-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53 Apr-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53 May-08 115,007.00 0.00 115,007.00 3.00% 9.00% 12.00% 13,800.84 128,807.84

Interest Finance TotalMonth/Year Days Monthly Cummulative Gross Rate Value Amount

Mar-07 31.00 324,101.33 324,101.33 324,101.33 11.00% 3,027.91 327,129.23Apr-07 30.00 346,742.13 327,129.23 673,871.36 11.00% 6,092.54 679,963.90May-07 31.00 353,287.41 679,963.90 1,033,251.31 11.00% 9,653.11 1,042,904.42Jun-07 30.00 361,680.69 1,042,904.42 1,404,585.11 11.00% 12,698.99 1,417,284.10Jul-07 31.00 362,352.69 1,417,284.10 1,779,636.79 11.00% 16,626.20 1,796,262.98Aug-07 31.00 363,280.05 1,796,262.98 2,159,543.03 11.00% 20,175.46 2,179,718.49Sep-07 30.00 363,280.05 2,179,718.49 2,542,998.54 11.00% 22,991.49 2,565,990.03Oct-07 31.00 369,153.33 2,565,990.03 2,935,143.36 11.00% 27,421.48 2,962,564.84Nov-07 30.00 384,707.89 2,962,564.84 3,347,272.73 11.00% 30,263.01 3,377,535.74Dec-07 31.00 390,446.77 3,377,535.74 3,767,982.51 11.00% 35,202.25 3,803,184.76Jan-08 31.00 399,460.99 3,803,184.76 4,202,645.74 11.00% 39,263.07 4,241,908.82Feb-08 28.00 424,799.53 4,241,908.82 4,666,708.35 11.00% 39,379.35 4,706,087.70Mar-08 31.00 430,399.53 4,706,087.70 5,136,487.23 11.00% 47,987.46 5,184,474.69Apr-08 30.00 430,399.53 5,184,474.69 5,614,874.22 11.00% 50,764.62 5,665,638.84May-08 31.00 128,807.84 5,665,638.84 5,794,446.68 11.00% 54,134.42 5,848,581.10

Total Amount 415,681.34

Period Principle Amount

Finance Costs will continue on this amount and in the remaining contract period unless these additional costs are paid.

8.2.6.Grand Summary

The additional costs defined within the preceding sections of this chapter are summarised below:

page 136

Page 137: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

Gategory of Additional Cost Amount

Wasted Monthly Costs in Original Contract Period 4,118,971.85Acceleration Costs 1,958,701.00Finance Costs in Period 415,681.34Extended Costs 3,218,973.43

Total Additional Costs to May 2008 9,712,327.62

page 137

Page 138: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

9. Statement of Claim

During the course of performing the Contract Works to May 2008, the Contractor has drawn the Project Manager’s attention to the fact that the Employer has deviated from certain of the contractual requirements established in the Contract. He has required the Contractor to perform the Contract Works in a manner significantly different from that laid down in the Contract Conditions and Specifications. These deviations are:

1. The Project Manager failed to provide setting out data in variance to the Contract or the timing depicted on the Programme of Works;

2. The Project Manager unnecessarily instructed a partial suspension of the Works;

3. The Project Manager did not issue construction design details in accordance with the Contract or the Contract Programme of Works;

4. The discovery of significant had rock at many of the Villa locations, which occurrence is an unforeseen condition as allowed and described in the Contract;

5. The Project Manager did not issue construction design details free from significant errors in accordance with the Contract; and

6. The Project Manager has not properly measured, valued, or paid for changes to the scope of work in respect of additional time and cost.

The Contractor is entitled to payment, in respect of the above matters for the reasons stated. In addition he is also entitled to an extension of time all as summarised below:

Head of Claim EOT Months ValueExtension of time (31 May 08 – 31Jan 09) 20 3,218,973.43Wasted Costs to May 2008 In period 4,118,971.85Acceleration Costs In extended period 1,958,701.00Finance Costs To May 2008 415,681.34Total Entitlement USD 9,712,327.62

page 138

Page 139: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

10.Appendices

10.1. Wasted Costs

10.1.1. Record of Resources – Staff and Labour

10.1.2. Record of Resources – Equipment

10.1.3. Direct and Indirect Costs

The following table provides figures from the Contractor’s audited accounts.

The next table shows the average indirect costs for the head office (Victoria, Mahe) and site office expressed as a percentage. The Contractor expects to recover as a return on turnover, approximately 9% on the head office costs and 3% for the site office costs.

page 139

Page 140: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

10.2. RFI and RFAID Date Reference From To Subject EventType Location EventDescription Notes

001 10-Mar-08 RFI-001 Island Construction Polus Investments

Roof trusses - Stainless steel plates - Detailed drawings required

Request for Information Villas & Buildings

Contractor requested for detailed designs for stainless steel plates for all the remaining buildings

PM stated the designs shall follow those of the mock up villas already constructed

002 10-Mar-08 RFI-002 Island Construction Polus Investments Thermal Roof Insulation - Design details required

Request for Information

Mock up villas and other buildings

Contractor requested the detailed design and insulation details for thermal roof insulation

PM provided the required information on 16 Mar '08. Information was required by 15 March 2008

003 12-Mar-08 RFI-003 Island Construction Polus Investments A3 Villas - Decking Span - Clarification Required

Request for Information A3 Villas

Contractor requested clarification on the span of the timber decking

PM provided clarification on 13 March 2008. Information was required by 15 March 2008

004 10-Mar-08 RFI-004 Island Construction Polus Investments Request for clarification on socket position at B2/03

Request for Information B2/03

Contractor requested clarification on the socket position at B2/03 Clarification provided

005 12-Mar-08 RFI-005 Island Construction Polus Investments A3 Villas - Lanai screens - designs required

Request for Information A3 Villas

Contractor requested design for lanai screens

Clarification provided on 13 Mar '08. Information was required by 15 Mar '08

006 12-Mar-08 RFI-006 Island Construction Polus Investments

All Villas – Bathroom Entrance Door Type DO.02 – Infill Bamboo Resin Panel – Discrepancy in Size

Request for Information Villas

Clarification required on the descrepancy in sizes of the bamboo resing panel Clarification provided

007 13-Mar-08 RFI-007 Island Construction Polus Investments

Mock Up Villas – Window Sill & Lining Details – Cut Stone Cladding – Discrepancy in Size

Request for Information

Mock up villas A3/32 and B2/03

Clarification required on the desrepancy in sizes of window sill shown in the desgn and the one supplied

Clarification provided on 16 Mar '08. Information was required by 16 Mar 08

008 14-Mar-08 RFI-008 Island Construction Polus Investments Ironmongery – Supplier – Other Contact Details Required

Request for Information Villas

Further contact details of ironmongery supplier required Not yet provided

page 140

Page 141: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

10.3. CorrespondenceID Date Reference From To Subject EventType Location EventDescription Notes

001 05-Jul-07 FIN/PS/POLUS/83PS, Ministry of

Finance Polus Investments Concessions Granted for the Project Information

Shangri-La Resort Project

Concessions granted during the construction phase of the project

002 11-Jul-07 LIHRD/env/05 Island Construction Polus Investments Environment Visit Report - 10 July 2007 Environmental

Shangri-La Resort Project

Contractor's response to Environmental visit report

003 30-Aug-07 LIHRD/VO/01 Island Construction Polus Investments

Quotation for Retaining Wall along CHI-SPA area/Restaurant Area Quotation

Shangri-La Resort Project

Quotation for Retaining wall along CHI-SPA area/Restaurant area

004 30-Aug-07 LIHRD/VO/02 Island Construction Polus Investments List of Variations Variations Shangri-La Resort Project

PM requested to approve the list of variations

005 03-Sep-07 Angel Fish Island Construction New Rates for Boat Transport Information Shangri-La Resort Project

New rates for boat transport as a result of increased fuel prices

006 12-Sep-07 Island Construction Angel Fish Transfer Boat to Long Island Information Shangri-La Resort Project

Schedules for boat transport from Mahe to Long Island and back

007 19-Sep-07 Island Construction Polus Investments Inquiry from Independent Engineer Information

Shangri-La Resort Project

Submission of the company's technical profile

008 24-Oct-07 Island Construction Polus Investments

Lump Sum Contract Price - Variations to Scope of Works - Instructions Variations

Shangri-La Resort Project

Request for Employer's agreement to payment of changes and variations

Instructed variations and changes are being made prior to reaching agreement on the price contrary to terms and conditions of the contract. There exists disparities between BQ quantities and quantities measured from construction drawings.

009 24-Oct-07 Island Construction Polus Investments Mock-up Villas - Variation Instruction - Additional Costs

Variation & Notification

Shangri-La Resort Project

The requirement to complete Mock up villas is a variation. Detailed particulars of associated delays and additional costs shall be submitted once ready

Timing and sequence for the mock up villas is not allowed in the POW, material procurement and labour requirements are in variance to original planning, advance construction of the mock-up villas continues to be an impediment on the rate of progress for other parts of works.

010 24-Oct-07 Island Construction Polus Investments

Minutes of Meeting No.23 - Recorded Minutes - Not Approved Information

Shangri-La Resort Project

Disagreement to Minutes of meeting No. 23 and all previous minutes. Proposal by the Contractor to verify and comment on the minutes before circulation

The minutes are in Contractor's view inaccurate and have not received Contractor's concurrence.

011 26-Oct-07 Island Construction Polus Investments

Suspension of Works-Extension of Time & Additional Payment-Notice Notification

Shangri-La Resort Project

Notification of Contractor's entitlement to time extension and additional costs occassioned by suspension of works.

In addition, the Contractor awaits PM's instruction to proceed with all the works affected by the suspension notice

012 26-Oct-07 Island Construction Polus Investments Setting Out - Late Instructions & Variations - Additional Costs

Notification & Variation

Shangri-La Resort Project

Notification of delay and disruption occassioned by varied location, position and orientation of buildings

The changes constiture variation. Associated delays and costs to be submitted once ready

013 26-Oct-07 Island Construction Polus Investments

Advance Payment - Unfixed Materials & Goods - Payment Application Payment

Shangri-La Resort Project

Request for PM's concurrence with Contractor's intention to raise a separate statement for payment of Unfixed Materials and Goods

014 26-Oct-07 Island Construction Polus Investments Earth Filling to CHI-SPA area QuotationShangri-La Resort Project

Quotation for earth filling to CHI-SPA area

page 141

Page 142: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

015 26-Oct-07 Island Construction Polus Investments Quotation for Rock Excavation QuotationShangri-La Resort Project Quotation for rock excavation

016 29-Oct-07 Island Construction Polus Investments Setting Out - Late Instructions & Variations - Additional Costs Variation

Shangri-La Resort Project

Contractor maintains changes in the location, position and orientation of buildings constitute variation, hence delays and additional costs, detailed particulars of which will be submitted once available

017 29-Oct-07 Island Construction Polus Investments

Suspension of Works-Extension of Time & Additional Payment-Entitlement Determination

Shangri-La Resort Project

Contractor maintains he has entitlement to extensions of time and recovery of costs due to suspension. Awaiting PM's determination

018 19-Nov-07 Island Construction Polus Investments

Programme - Revision 1 Dated 6th Nov 2007 - Progress of Works

Programme of Works

Shangri-La Resort Project

Submission of Revised Programme of Works

019 19-Nov-07 Island Construction Polus Investments

Interim Statement No. 3 - Issue of Interim Payment Certificate - Contract Procedure Payment

Shangri-La Resort Project

Undercertification shall subsequently attract finance costst

020 19-Nov-07 Island Construction Polus Investments Cash Flow Forecast - Advance Repayment - Ammendment Cash Flow

Shangri-La Resort Project Ammended cash flow forecast

021 20-Nov-07 LIHRD/PC/05 Island Construction Polus Investments Interim Statement No. 3 Statement Shangri-La Resort Project Application for Payment for works

022 21-Nov-07 Island Construction Polus Investments

Extension of Time for Completion-First Interim Entitlement-Claim Claim

Shangri-La Resort Project

The Contractor claims extension of time for completion up to 8 Dec 08 and additional costs amounting to US$ 857,145.00

023 21-Nov-07 Island Construction Polus Investments

Cash Flow Forecast - Advance Repayment - Proposed Revisions Cash Flow

Shangri-La Resort Project

Ammeded cash flow forecast consequent to the extended contract period as per the revised programme of works

024 21-Nov-07 Island Construction Polus Investments Minutes of Meeting Nr. 27 - Clarification - Notice

Clarification & Notice

Shangri-La Resort Project

Clarification on time and money issues contained in the minutes and notification of intention to submit additional costs for acceleration of works

025 23-Nov-07 Island Construction Polus Investments

Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation

Claims & Variations

Shangri-La Resort Project

Contractor requests a Variation Meeting to discuss and agree on all the variations and claims on the project to date

The Variations and claims identified so far are listed

026 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Suspension of works Claim Shangri-La Resort Project

PM states it is the Contractor who suspended the works hence refuse to approved any Extension of time and Additional Costs

The PM encloses previous email correspondences with the Contractor over the issue

027 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Minutes of Meeting Information Shangri-La Resort Project

PM will endeavour to issue meeting minutes by every Wednesday

page 142

Page 143: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

028 23-Nov-07 E-03-23.11.07 Polus Investments Island Construction Measurement and Payment for Variations Variations

Shangri-La Resort Project

Instruction to vary any part of the works whether for the specification or quantities is additional work entitled to additional payment

PM agrees to have mutual measurement of variation and payment thereof

029 23-Nov-07 E-04-23.11.07 Polus Investments Island Construction Mock-up Villas Variations Shangri-La Resort Project

The PM states mock up villas do not comprise variation

030 23-Nov-07 E-05-23.11.07 Polus Investments Island Construction Clients Address AddressShangri-La Resort Project

All communications must be addressed to the Project Manager

031 23-Nov-07 E-06-23.11.07 Polus Investments Island Construction Setting out at Site - Changes in Positions, Orientation

Variation & Claim

Shangri-La Resort Project

PM requires detailed particulars for associated delays and costs

032 23-Nov-07 E-07-23.11.07 Polus Investments Island Construction Minutes of Meeting Clarification & Notice

Shangri-La Resort Project

PM awaits detailed document regarding Variations and claims so far identified

033 04-Dec-07 E-09-04.12.07 Polus Investments Island Construction

Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation Variations

Shangri-La Resort Project

PM agrees to value changes in design and quantities as Variations

034 04-Dec-07 E-08-04.12.07 Polus Investments Island Construction

Interim Statement No.3 - Issue of Interim Payment Certificate - Contract Procedure Payment

Shangri-La Resort Project

The Invoice required is not contractual but solely for accounting purposes

035 07-Dec-07 Island Construction Polus Investments

General Contractor's Obligations-Performance Security-Reduction of Amount

Performance Security

Shangri-La Resort Project

Contractor proposes the amount in the Performance Security is reduced equal to the amount of cover included in the EME's performance security

036 08-Dec-07 Island Construction Polus Investments

Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation Variations

Shangri-La Resort Project

The Letter of Acceptance takes priority over the conditions of contract. As such, in practice it means that no variation arising from aditional work or design change can commence prior to receiving the agreement of the Employer

037 19-Dec-07 E-13-19.12.07 Polus Investments Island Construction List of Plants for A3/32 - B2/03 LandscapingShangri-La Resort Project Enclosed list of plants

038 24-Dec-07 Island Construction Polus Investments

Interim Statements for Payment - Issue of Interim Payment Certificate-Payment Payment

Shangri-La Resort Project

The PM can still issue a payment certificate even when the amount falls below the minimum payable by the Employer

039 24-Dec-07 Island Construction Polus Investments Mock-up Villas - Variation Instruction - Additional Costs Variation

Shangri-La Resort Project

Contractor maintains Mock-up villas is a variation because the procurement process is in complete variance to original planning

040 15-Jan-08 Polus Investments Island Construction Specification for Door panelling SpecificationShangri-La Resort Project Specification for door panelling

041 17-Jan-08 E-14-17.01.08 Polus Investments Island Construction Environment Visit Report - 13 Dec 2007 Environmental

Shangri-La Resort Project

Contractor required to take necessary measures to improve the situation

page 143

Page 144: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

042 21-Jan-08 Island Construction Polus Investments

Environmental - Monitoring visit for Class 1 Project and SPA at Long Island Environmental

Shangri-La Resort Project

Steps being taken to address the environmental issues

043 22-Jan-08 Island Construction Polus Investments Roof structure gusset plate design Design

Shangri-La Resort Project

The proposed 4.5mm thick gusset plate is appropriate for use

044 29-Jan-08 Polus Investments Island Construction Revised cash flow Cash FlowShangri-La Resort Project PM forwards a revised cashflow

045 29-Jan-08 E-14-29.01.08 Polus Investments Island Construction Mock-up Villas - Variation Variation Shangri-La Resort Project

PM requires the mock-up villas completed as per original programme

046 30-Jan-08 E-15-30.01.08 Polus Investments Island Construction Certification and Payment Payment Shangri-La Resort Project

Payment has been made to the Main Contractor

047 30-Jan-08 Polus Investments Island Construction Approved Balustrade Design Shangri-La Resort Project Pictures of approved balustrade

048 04-Feb-08 E-16-04.02.08 Polus Investments Island Construction Statement Statement Shangri-La Resort Project

2 Hard copies of the statement required

049 06-Feb-08 Polus Investments Island Construction Site Issues General Shangri-La Resort Project

Minutes of meeting between Zsolt and Wilson. Action by Contractor required

050 07-Feb-08 Island Construction Polus Investments Site Issues General Shangri-La Resort Project Response to issues raised above

051 13-Feb-08 E-18-13.02.08 Polus Investments Island Construction Revised Programme of works Programme of Works

Shangri-La Resort Project

Contractor required to submit revised programme of works

052 13-Feb-08 E-19-13.02.08 Polus Investments Island Construction Payment Certificate & Rate of Progress Certificate

Shangri-La Resort Project

The negative amount reflects very slow progress at site. Submit revised POW and supporting report outlining methods to expedite progress

053 26-Feb-08 Island Construction Polus Investments

Nominated Subcontractor EME Overseas Ltd - Design and Build Subcontract Conditions - Objection to Nomination Subcontract

Shangri-La Resort Project

Existing contractual matters that prevent execution of agreement between Island Construction Pty ltd and EME overseas

054 27-Feb-08 Island Construction Polus Investments

Suspension of Works - Extension of time and Additional Payment - Entitlement

Suspension of Works

Shangri-La Resort Project

Entitlement to Extensions of time and additional payment arising from instruction to suspend works

055 01-Mar-08 Island Construction Polus Investments Situation ReportDelaying Events Details

Shangri-La Resort Project

Delaying Events and Proposed Financial Arrangements

057 14-Mar-08 Island Construction Polus Investments

Delaying Events & Changed Circumstances - Revised Programme of works - Extension of time for completion

Request for Extension of Time

Shangri-La Resort Project

Request for extension of time for completion to 24 March 2009

058 19-Mar-08 Island Construction Polus Investments

Cash Flow Forecast - Advance Repayment - Proposed Revision

Revision of Advance Recovery

Shangri-La Resort Project

Proposed amendment of cashflow with revised advance recovery

059 07-Apr-08 Island Construction Polus Investments Extension of time Time Extension Shangri-La Resort Project Detailed particulars required

page 144

Page 145: First Draft 013 June 08 - Final

Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment

056 08-Apr-08 Island Construction Polus Investments Interim Report on Programme of Works, Progress & Valuation

Programme & Valuation Report

Shangri-La Resort Project

Report on Programme of Works and Request for Time Extension

060 09-Apr-08 E-18-09.04.08 Polus Investments Island Construction Nominated Subcontractor Subcontract Shangri-La Resort Project

PM responds to ICCL's objection to enter into nominated subcontract with EME

061 14-Apr-08 E-17-07.04.2008 Polus Investments Island Construction

Nominated Subcontract - Subcontract Agreement - Reason for Objection Subcontract

Shangri-La Resort Project

Reason for Objection of nominated subcontract agreement

062 15-Apr-08 Island Construction Polus Investments

Extension of Time for Completion - First Interim Entitlement - Detailed Particulars

Detailed particulars for Extension of time

Shangri-La Resort Project

Request for approval to submit detailed particulars within 45 days from 15 April 2008

063 15-Apr-08 Island Construction Polus Investments Interim Statement Nr. 08 Statement Shangri-La Resort Project

Statement for works done up to End of March 2008

064 17-Apr-08 Island Construction Polus Investments

Interim Statement Nr. 08 - Materials On & Off site - Amendment Statement

Shangri-La Resort Project

Amended statement incorporating off site Balau timber

065 17-Apr-08 Island Construction Polus Investments Landscaping - Additional Work - Confirmation of Oral Instruction Additional Works

Shangri-La Resort Project

Confirmation of oral instruction to execute landscaping works

066 21-Apr-08 Island Construction Polus Investments

Delay to Completion - Recovery Programme - Approval to Accelerate Programme

Shangri-La Resort Project

Request for approval to accelerate works

067 02-May-08 E19-02.05.08 Polus Investments Island Construction Delays Extension of Time

Shangri-La Resort Project

PM states ICCL has not demonstrated entitlement to time extension

068 05-May-08 E-21-05.05.08 Polus Investments Island Construction Valuation Certificate Payment Shangri-La Resort Project Valuation certificate No. 08

069 06-May-08 Island Construction Polus Investments Interim Payment - Invoice No. 7 Payment Shangri-La Resort Project Invoice for Interim Payment

070 07-May-08 Island Construction Polus Investments

Valuation No. 8 - Cession of Right for Material On and Off Site Materials On Site

Shangri-La Resort Project

Cession of right for materials on and off site

071 09-May-08 E20-09.05.08 Polus Investments Island Construction Accelerative measures Programme of Works

Shangri-La Resort Project

The Employer is contemplating engaging others to expedite progress of works

072 12-May-08 E21-12.05.08 Polus Investments Island Construction Recovery Measures Programme of Works

Shangri-La Resort Project

PM outlines ways of putting the recovery measures into effect

073 19-May-08 Polus Investments Island Construction Delays and Completion of works Delays

Shangri-La Resort Project

Employer proposes the contractor engages in discussions with PM on the ammendment of the contract and the remedial measures

074 28-May-08 Island Construction Polus Investments

Claim for Time and Additional Payment - Entitlement - Determination Claim

Shangri-La Resort Project

ICCL informs PM detailed particulars will be submitted on 09 June 2008

page 145