Upload
pat-kirimi
View
307
Download
7
Embed Size (px)
Citation preview
Polus Investments (Seychelles) Limited
Shangri-La Resort at Long IslandSeychelles
First Interim Request for Extension of Time for Completion and
Additional Payment
Island Construction (Pty) Ltd
June 2008
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Table of Contents
page
1. Introduction........................................................................................................5
1.1. Background.................................................................................................51.2. Purpose of this Document.........................................................................61.3. Scope of this Document.............................................................................7
2. The Structure of the Contract...........................................................................8
2.1. The Contract Existing.................................................................................82.1.1. Lump Sum Contract Price vis-à-vis Scope of Works.............................82.1.2. Provisional Sums.................................................................................12
2.1.2.1. Tender Provisions.........................................................................122.1.2.2. Contract Provisions......................................................................132.1.2.3. Current Situation...........................................................................152.1.2.4. Conclusions..................................................................................16
2.2. Relevant Contract Provisions..................................................................172.2.1. Sub-clause 1.9 – Delayed Drawings or Instructions............................172.2.2. Sub-clause 3.3 – Instructions of the Project Manager.........................182.2.3. Sub-clause 4.7 – Setting Out...............................................................192.2.4. Sub-clause 4.12 – Unforeseeable Physical Conditions.......................192.2.5. Sub-clause 8.3 – Programme..............................................................202.2.6. Sub-clause 8.4 – Extension of Time for Completion............................222.2.7. Sub-clause 8.8 – Suspension of Works...............................................222.2.8. Sub-clause 8.9 – Consequences of Suspension.................................232.2.9. Sub-clause 12.1 – Works to be Measured...........................................232.2.10. Sub-clause 12.3 – Evaluation..........................................................242.2.11. Sub-clause 13.1 – Right to Vary......................................................252.2.12. Sub-clause 13.3 – Variation Procedure............................................262.2.13. Sub-clause 20.1 – Contractor’s Claims............................................27
2.3. Original Planning and Cash-flow.............................................................292.3.1. The Clause 8 Programme....................................................................292.3.2. Planned versus Actual Turnover..........................................................30
2.4. First Revised Programme of Works........................................................322.5. Second Revised Programme of Works...................................................322.6. Actual Progress........................................................................................34
3. Valuation of Variations....................................................................................35
3.1. Explanation of Heads of Claim................................................................353.2. Specific Heads of Claim...........................................................................353.3. Methods of Valuation of the Variations...................................................36
3.3.1. Use of Costs as Basis..........................................................................363.3.2. Addition for Profit.................................................................................363.3.3. Profit as Part of the Value of Variations...............................................36
3.3.3.1. Three Types of Variations............................................................363.3.3.2. Changes in Design of the Works..................................................37
page 2
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
3.3.3.2.1. Technical Variations.................................................................373.3.3.2.2. Changes to Specified Sequence and Timing...........................38
3.3.3.3. Summary......................................................................................383.3.4. The Effects on Unvaried Work.............................................................393.3.5. For Uneconomic Working....................................................................39
3.3.5.1. Loss of Anticipated Income..........................................................403.3.5.2. Wasted Monthly Costs..................................................................403.3.5.3. Financing Wasted Monthly Costs.................................................41
3.3.6. Profit as Part of ‘Costs’........................................................................413.3.6.1. Authorities on the Basis of ‘Costs’................................................41
3.3.6.1.1. Powell-Smith’s ‘Some Building Contract Problems’.................423.3.6.1.2. Hudson and Minter v. WHTSO.................................................423.3.6.1.3. Hudson on the Scope of ‘Costs’...............................................433.3.6.1.4. The First Part of the Rule in Hadley v. Baxendale....................443.3.6.1.5. The Basic Measure of Damages..............................................45
3.3.6.2. Authorities on the Recovery of Profit............................................463.3.6.2.1. General Principle as to Claims.................................................463.3.6.2.2. Wraight v. PH&T (Holdings) Ltd...............................................463.3.6.2.3. Powell-Smith and Sims on Building Contract Claims...............47
3.3.6.3. Summary......................................................................................483.4. The Contractor’s Summary......................................................................48
4. Circumstances Giving Rise to Claim.............................................................49
4.1. Contractual Basis – Notification of Changes.........................................494.2. Late and Inaccurate Survey Data............................................................654.3. Late Receipt of Final Design Information...............................................664.4. Additional and Varied Work.....................................................................66
4.4.1. Excavation in Hard Rock.....................................................................664.4.1.1. Change in Sequence and Increased Cost....................................674.4.1.2. Increased Quantity.......................................................................67
4.4.2. Increased Quantity in Reinforced Concrete.........................................704.4.2.1. Villa Type A3 (Example)...............................................................704.4.2.2. Villa Type B2 (Example)...............................................................71
4.4.3. Suspension of Works...........................................................................714.4.4. Variations to Design.............................................................................72
4.5. Material Procurement Programme..........................................................724.6. Conclusion of Effects of Variations........................................................74
5. Time Analysis...................................................................................................75
5.1. Method of Analysis...................................................................................755.1.1. Mitigation by Contractor.......................................................................765.1.2. Time for Completion............................................................................765.1.3. Impact on Time - Analyses..................................................................775.1.4. The Events that Impacted Progress....................................................77
5.1.4.1. Event No 1 – Setting Out..............................................................795.1.4.2. Event No 2 – Unforeseen Ground Conditions..............................825.1.4.3. Event No 3 – Later Receipt of Design Information.......................915.1.4.4. Event No 4 – Increased Scope of Works....................................1015.1.4.5. Event No 5 – Partial Suspension of Works.................................1145.1.4.6. Event No 6 – Design Variations (Stainless Steel Items).............119
page 3
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.2. Conclusion..............................................................................................121
6. Financial Analysis..........................................................................................122
6.1. Consequences........................................................................................1226.1.1. Direct Cost.........................................................................................1236.1.2. Indirect Cost.......................................................................................1236.1.3. Consequential Cost...........................................................................123
6.2. Costs in Extended Contract Period.......................................................1236.2.1. Nature of Loss and Expense.............................................................1236.2.2. Contractor’s Entitlement to Reimbursement......................................124
6.3. Finance Cost...........................................................................................1246.4. Conclusions............................................................................................125
7. Extension of Time Entitlement......................................................................126
8. Additional Payment........................................................................................127
8.1. Introduction.............................................................................................1278.2. Evaluation of the Financial Consequences..........................................127
8.2.1. Wasted Costs Arising from Delay and Disruption..............................1288.2.1.1. Staff and Labour.........................................................................1288.2.1.2. Equipment..................................................................................1298.2.1.3. Site and Head Office..................................................................1308.2.1.4. Summary of Wasted Costs.........................................................132
8.2.2. Additional Costs Arising from Acceleration........................................1328.2.3. Additional Costs in Extended Contract Period...................................1338.2.4. Other Costs........................................................................................134
8.2.4.1. Procurement of Permanent Materials.........................................1348.2.4.2. Temporary Materials including Equipment.................................135
8.2.5. Finance Costs....................................................................................1358.2.6. Grand Summary................................................................................136
9. Statement of Claim.........................................................................................138
10. Appendices.................................................................................................139
10.1. Wasted Costs.......................................................................................13910.1.1. Record of Resources – Staff and Labour.......................................13910.1.2. Record of Resources – Equipment................................................13910.1.3. Direct and Indirect Costs................................................................139
10.2. RFI and RFA.........................................................................................14010.3. Correspondence....................................................................................141
page 4
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
1. Introduction
1.1. Background
A Contract for Building and Engineering Works Designed by the Employer was entered into on 27 April 2007 between the Polus Investments (Seychelles) Limited (hereinafter called “the Employer”) and Island Construction (PTY) Limited (hereinafter called “the Contractor”).
During the course of both the Employer’s design and the construction phases of the Contract to date, a number of events and factors have affected progress of both the design and construction processes. The Contractor’s view is that the delays were not his fault. Consequently, the Contractor believes he should be allowed an Extension of Time and Additional Payment to complete the work which is the subject of the Contract. He seeks reimbursement of his additional costs incurred otherwise not allowed in his tendered rates and prices.
For the Contractor, this is an important matter. He needs the Project Manager’s agreement to an extension of time requested and to an interim determination of his additional costs, in order to allow earliest compensation and to off-set increasing finance costs.
The Contractor’s further view is that Site conditions are in variance to that anticipated as the positions of buildings and the significant increase in hard rock excavation. In addition the Project Manager suspended progress of the Works and he has received much of the design phase late. This design when received shows a significant increase in the quantities of work to be performed. These facts entitle him to an extension of time. It would also entitle him to additional payment for the delay and disruption caused to date.
As will be seen from the sections following this introduction, the Employer and/or the Project Manager also required the Contractor to carry out Construction work to a varied timing and sequence, as opposed to that anticipated by his programme of works. This was as a result of unforeseen ground conditions.
The issues became clear from the very start of the construction process. Once the setting out delays was over-come the Contractor encountered hard rock in excavation at almost all building locations. This unforeseen circumstance caused a varied order of construction to that planned together with numerous late instructions as design evolved.
page 5
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
All of these factors have caused the Contractor to have to carry out work in a disrupted and disordered manner, and over a longer period, than he contracted to do. The Employer’s/the Project Manager’s errors have caused the Contractor to incur significant higher costs of construction and in addition, significant costs arising from delay and disruption.
As will be seen from the following sections of this claim, almost all areas of the site fell behind programme. In addition, it is of worthy note that the Contract Price awarded was inclusive of 30% allowance for Provisional Sums. That means the Project Manager must introduce these works as a Variation to the Contract. The design and construction work are both now a long way behind programme.
The Contractor has given notice that he will have to make claims to achieve the relief and payment to which he believes he is entitled.
1.2. Purpose of this Document
During the course of the work, the Contractor has suffered delay and disruption through a number of causes. The consequences of these causes are the contractual responsibility of the Employer.
The Contractor has made a number of notice submissions to the Project Manager with regard to these causes. The Contractor has thereafter, impacted the programme of works to reflect the effect of these events and changed circumstances.
We acknowledge receipt of the Employer’s letter dated 19 May 2008 and to the Project Managers letters dated 2, 9 and 12 May 2008 referenced E19-02.05.08, E20-09.05.08 and E21-12.05.08 respectively.
In summary we disagree entirely with all interpretations, conclusions and what appears to be a determination made prior to receipt of the Contractor’s detailed particulars. In such a situation you are making a prediction on changed events and circumstances and their consequences without benefit of the position one Party to the Contract. This is contrary to the duties and obligations stated at sub-clause 3.1 and 3.5 of the General Conditions of Contract.
page 6
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
In our letter of 14 April 2008 we indicated a time to complete the detailed particulars. However, with consideration to your position now outlined in these letters, we require more time to complete this exercise. As such, we will make our full and detailed submission of claims on Monday 9 June 2008.
The purpose of this document is, therefore, to provide the Project Manager with an initial analysis so that he may make an evaluation of the additional payment based on:
The delays and disruption experienced to May 2008 and arising additional costs in the form of Wasted Costs, and
The extensions time for completion requested by the Contractor in respect of the cause’s notified and consequent recovery of arising prolongation costs.
for which the Employer is contractually liable.
1.3. Scope of this Document
This document describes the:
1. Causes of delay and disruption to the Works;
2. Impact of these causes on contract completion;
3. Contractual position regarding the Contractor’s entitlement to extension of time and additional payment, and
4. Consequences of delay and disruption in terms of the additional time and additional payment due to the Contractor.
The scope of this claim submission is limited to known events to May 2008. As many of the changed events and circumstances that have given rise to extensions of time and additional cost continue, the Contractor will be updating this detailed submission.
page 7
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2. The Structure of the Contract
2.1. The Contract Existing
2.1.1.Lump Sum Contract Price vis-à-vis Scope of Works
The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0:
“As per our agreement the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”
In practice this is inoperable and this soon became evident at early stages of the Contract
In a letter dated 24 October 2007 the Contractor gave notice:
Two important matters require your confirmation:
First, we draw your attention to the changes and variations that are regularly being instructed as works proceed. Although they are acceptable to the Contractor we also wish to record that these changes and variations are made prior to reaching agreement on the price. This is as you are aware, contrary to the terms and conditions of the Contract. In the circumstances, because of this continuing departure from the Contract, it is understood that the price and consequent additional cost will be added to the Contract Price.
Secondly, we have reviewed the estimated quantities in the Bills of Quantity against actual work depicted on the drawings issued for construction. It is apparent significant disparity exists between the measure and provision made in the Contract. As a result, either the scope must be adjusted in order to retain the Contract Price or, we require your agreement to perform these works at the price contained in the contract which additional cost will be added to the Contract Price. If you require detail of the variations discussed here, please have your quantity surveyor consult with ours as quickly as possible.
In conclusion, we require the Employer’s agreement to payment of these variations as a matter of urgency.
page 8
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
In a further letter dated 23 November 2007 the Contractor recorded:
This Contract contains specific conditions in regard to Variations that would increase or decrease the Lump Sum Contract Price. We wrote on this matter on 24 October 2007 to which a reply has not been received.
In particular it states that “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”
It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”
Essentially this means a new or varied price or rate for all Variations must first receive agreement of the Employer together with, if relevant, a revised Contract Price prior to the issue of an instruction because they:
Introduce a design change;
Introduce additional works, and
Introduce an increase in the scope of work beyond the quantity stated in the Bills of Quantities.
As such, the purpose of this letter is to record several and significant Variations introduced since commencement where value and consequent Contract Price adjustment are not agreed despite the issue of an instruction. Consequently, we wish to schedule a “Variation Meeting” to discuss and agree a procedure that will ensure such increases in value are properly reported, valued and paid.
At this juncture we have identified the following Claims and Variations which have caused the Contract Price to increase:
1. Additional costs associated with delay and disruption not the responsibility of the Contractor;
2. Additional costs associated with the Project Manager’s instruction to accelerate the Works by working additional hours;
3. Additional costs arising from delays caused by late design information;
page 9
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
4. Additional costs in excavation of hard rock and removal to spoil;
5. Additional costs that arise due to the construction of “mock-up” villas in a sequence that is in variance to original planning;
6. The increase in size of structural timber to roof structures where new rates need to be agreed prior to procurement;
7. Door timber type and finishing specifications have changed and new rates need to be agreed prior to procurement;
8. Window timber type and finishing specifications have changed and new rates need to be agreed prior to procurement;
9. Ironmongery specifications have changed and new rates need to be agreed prior to procurement;
10. Structural galvanised steel plates have changed to stainless steel and new rates need to be agreed prior to procurement.
11. Increased costs arising from additional site work described in Section B of the Principles of Measurement for Works of Construction.
This meeting must also acknowledge and agree the additional work being executed is in accordance with instructions and design details issued and that they are beyond the scope of the lump sum Contract Price. This presently includes:
Excavation in common material;
Excavation in rock;
Concrete in foundations to suit varied ground conditions; and
Reinforced concrete in columns, ring beams and suspended slabs.
In addition, all lump sums for works for which detailed bills of quantities do not exist need to be prepared and valued using detailed design drawings received in September 2007.
page 10
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Please confirm as soon as possible when a meeting can be convened as these Claims and Variations must be recorded and valued as a matter of priority.
The last letter with regards Variations and increased scope of Works was dated 6 December 2007 and recorded:
We acknowledge receipt of your letter dated 4 December 2007 referenced E-09-04-12-07 and wish to confirm our position by the following extract from the Contract:
The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”
It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”
The Contract Agreement dated 27 April 2007 lists the documents forming the Agreement and the Letter of Acceptance takes priority over the Conditions of Contract.
Consequently, your reference to sub-clause 12.3 and 13.1 of the Conditions of Contract, although interesting, is not relevant in the introduction of Variations on this project, particularly as sub-clause 3.1 has been amended by the quoted specific conditions above.
We would point out that although the amendment is impractical it is a significant revision to both Clause 12 and 13 of the Conditions of Contract. In practise it means that no Variation arising from additional work or by design change can commence prior to receiving the agreement of the Employer.
In conclusion, the purpose of our letter dated 23 November 2007 on this subject matter was to bring these special circumstances to your attention.
A further existing condition of the Contract relates to Provisional Sums and their inclusion in the Contract as Variations.
page 11
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2.1.2.Provisional Sums
Clause 13 empowers the Project Manager to issue instructions to the Contractor directing him how provisional sums are to be expended. Provisional sums are included in this Contract where the precise cost or extent of work is not known at time of tender. The purpose is to have the sum of money to cover the cost. When the instruction is issued, the sum inserted is omitted and the variation is then valued in accordance with the principles of Clause 12 and 13.
The “Building Contract Dictionary” written by Vincent Powell-Smith and David Chappell, explains the term provisional sum:
A term used to denote a sum of money included in the contract by the employer, normally as an amount in the bills of quantities. It is provided to cover the cost of something which cannot be foreseen or detailed accurately at the time tenders are invited. (Contractor’s profit is not added to this sum.) It may be expended as the architect instructs…
It is important that the Contractor receives proper valuation of variations measured in accordance with the provisions stated for Provisional Sums. In particular, all on-costs and overheads described and allowed in the existing Bill 1 will be equally relevant to any measured Variations valued under Clause 12 and 13 of the Contract conditions.
It is of worthy note that a very large percentage of the Contract Works and therefore, the Contract Price, had not been sufficiently designed at tender stage. The consequences of this situation will allow the Contractor to measure and value these works as an addition, within the provisions of Clause 12 and 13. As such, the value of items listed in Bill no 1 must be increased to include works falling under Variations. This would then allow the Contractor to be paid for the work performed.
2.1.2.1. Tender Provisions
At tender stage the value shown for Measured Work was (Bills 1 to 34 inclusive) SCR20,677,661.15, and the value of the Preliminaries (Bill 1) has been derived from this figure.
However, a value for Preliminary items is clearly not included as part of the Provisional Sum amount declared by the Employer at tender stage. The value of Provisional Sums included, amounts to SCR22,539,454.00, a figure which is greater than the value of the original Measured Works forming the Contract.
page 12
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2.1.2.2. Contract Provisions
The contract provides as follows:
Under Clause 13.5, Provisional Sums; Each provisional sum shall only be used in whole or in part in accordance with the Project Managers instruction and that the contract sum shall be adjusted accordingly. It further provides that when the Project Manager instructs work to be provided by the contractor such work shall be valued under Clause 13.3 (Variation Procedure).
Under Clause 13.3, Variation Procedure: Each variation will be valued in accordance with Clause 12. This has been amended in the Particular Conditions where the measure and value is made in accordance with the RICS Principles of Measurement for Works of Construction. Consequently, the full wording of Clause 12 is:
Under Clause 12.3, Evaluation: a new rate or price shall be appropriate for an Item of Work if:
(a)
the measured quantity of the item is changed by more than 10% from the quantity of this item in the Bill of Quantities or other Schedule,
this change in quantity multiplied by such specified rate for this item exceeds 0.01% of the Accepted Contract Amount,
this change in quantity directly changes the Cost per unit quantity of this item by more than 1%, and
this item is not specified in the Contract as a “fixed rate item";
or (b)
i. the work is instructed under Clause 13 [Variations and Adjustments],
ii. no rate or price is specified in the Contract for this item, and
iii. no specified rate or price is appropriate because the item of work is not of similar
page 13
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
character, or is not executed under similar conditions, as any item in the Contract.
Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.
With regard to which part of sub-clause 12.3 above is relevant, it is obvious the measured quantity of the Works originally included as a value under Provisional Sums complies with those conditions stated in paragraph (a). As such, all rates and prices from which the varied works are valued to date, for those Works not forming part of the original Measured Works, must be appropriately adjusted.
The procedure in the Contract for the valuation of a variation is described under sub-clause 13.3 and states:
If the Project Manager requests a proposal, prior to instructing a Variation, the Contractor shall respond in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the case) or by submitting:
a. a description of the proposed work to be performed and a programme for its execution,
b. the Contractor’s proposal for any necessary modifications to the programme according to Sub-Clause 8.3 [Programme] and to the Time for Completion, and
c. the Contractor’s proposal for evaluation of the Variation.
The Project Manager shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value Engineering] or otherwise), respond with approval, disapproval or comments. The Contractor shall not delay any work whilst awaiting a response.
Each instruction to execute a Variation, with any requirements for the recording of Costs, shall be issued by the Project Manager to the Contractor, who shall acknowledge receipt.
page 14
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Each Variation shall be evaluated in accordance with Clause 12 [Measurement and Evaluation], unless the Project Manager instructs or approves otherwise in accordance with this Clause.
The procedure adopted by the Project Manager would appear to be a submission of a “Drawing for Construction”. Therefore, the three stage process described and allowed above has not been observed. Nonetheless, it is apparent as a consequence of these variations, that the value of the Works flowing from the Provisional Sums has not been determined at time of tender.
2.1.2.3. Current Situation
The Preliminaries had originally been calculated based on the value of Measured Works identified at tender. A breakdown of the Preliminaries shown below demonstrates that though certain items and their related cost therein, is considered fixed, the majority are of a variable nature. Consequently, the Preliminaries and their value are directly proportional to the value of Measured Works to be executed.
Item Nature of Cost Fixed Variable
1 Insurance 250,000.002 Foreign Staff, Labour Repatriation 450,000.003 Facilities for Staff and Labour 170,000.004 Measures against Insect and Pect Nuisance 60,000.005 Supply of Foodstuffs 660,000.006 Supply of Water 80,318.007 Shop Drawings 10,000.008 As-Built Documents 5,600.009 Temporary Site Office for Employers Consultants 65,250.00
10 Site Signboard 3,275.0011 Access to Site 35,000.0012 Site to be Tidy 12,727.0013 Co-ordination 14,727.0014 Site Records 3,275.0015 Site Records 29,913.0016 Safety Procedures 5,700.0017 Security at Site 13,426.0018 Contractors Site Operations 7,485.0019 Site Radio Communication 11,725.0020 Environmental Impact Assessment 5,000.0021 Taking Delivery from NS 50,000.0022 Contractors Temporary Accommodation 35,000.0023 Superintendence 15,000.0024 Transport of People 125,475.0025 Contractors Equipment 365,000.0026 Scaffolding 105,000.00
Total 85,250.00 2,503,646.00
page 15
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
It is important to define the difference between a “fixed” and a “variable” item;
Fixed items are to cover elements of a cost of work or their value, which are not to be considered as proportional to the quantities of the Permanent Works; whereas
Variable items are to cover for elements of a cost of work which are considered proportional to the quantities of Permanent Work performed.
The distinction is clear and as example, Shop Drawings and Site Records is a typical Variable item which scope will increase on introduction of the Variations brought by expenditure of the provisional sums.
These variable preliminaries items amount to about 12% of the value of Measured Works. As a result the current situation is:
The original value of known Measured Works has varied in quantity and therefore, value, considerably;
The instructed varied works (which is the value provision at tender and known as “Provisional Sums”) has or will considerably increase the value of Measured Works; and
As a result of a) and b) above, there is a significant under-recovery of costs on measured works that should naturally flow from items contained in the Preliminary Bill.
2.1.2.4. Conclusions
The table below shows the various value elements making up the Contract Price. The known scope of work had been priced and valued at SR20,677,661.15.
However, the value of Preliminaries is SR2,537,894.00 of which SR2,503,646.00 is the value of Variable Costs. Therefore, SR2,503,646.00 as a percentage of the known measured works at time of tender was 12%. It is this percentage, 12% that must be added to the value of Variations introduced under Clause 12 and 13.
This means the value adjustment on the original Provisional Sum amount of SCR22,539,454.00 equates to SCR2,729,071.00 or such other sum valued in accordance with the Contract. This sum is to be paid in addition to the Contract Price.
page 16
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
This signifies that all the Works measured to date are under-valued. Accordingly, the Conditions of the Contract dictate the following actions:
Notwithstanding delay and disruption costs caused by events notified to the Project Manager, further additional costs must be captured because:
The Contractor has entitlement to a varied rate for all unvaried Works,
The Contractor has entitlement to new rates and prices for all Works introduced as a Variation in accordance with sub-clause 12.3, and
the contractor has entitlement to the addition of 12% to all his measured work to cover his Preliminary and general items.
Consequently, the Contractor intends to add 12% to the value of measured works arising from Instructed Variations. The Contractor asks the Project Manager to certify payment applications in accordance with the Contract Conditions and for the reasons stated in the foregoing.
2.2. Relevant Contract Provisions
2.2.1.Sub-clause 1.9 – Delayed Drawings or Instructions
The Contractor shall give notice to the Project Manager whenever the works are likely to be delayed or disrupted if any necessary drawing or instruction is not issued to the Contractor within a particular time, which shall be reasonable. The notice shall include details of the necessary drawing or instruction, details of why and by when it should be issued, and details of the nature and amount of the delay or disruption likely to be suffered if it is late.
If the Contractor suffers delay and/or incurs Cost as a result of a failure of the Project Manager to issue the notified drawing or instruction within a time which is reasonable and is specified in the notice with supporting details, the Contractor shall give a further notice to the Project Manager and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:
page 17
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
(a) payment of any such Cost plus profit, which shall be included in the Contract Price.
After receiving this further notice, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
However, if and to the extent that the Project Manager's failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor's Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.
2.2.2.Sub-clause 3.3 – Instructions of the Project Manager
The Project Manager may issue to the Contractor (at any time) instructions and additional or modified Drawings which may be necessary for the execution of the Works and the remedying of any defects, all in accordance with the Contract. The Contractor shall only take instructions from the Project Manager, or from an assistant to whom the appropriate authority has been delegated under this Clause. If an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.
The Contractor shall comply with the instructions given by the Project Manager or delegated assistant, on any matter related to the Contract. Whenever practicable, their instructions shall be given in writing. If the Project Manager or a delegated assistant:
(a) gives an oral instruction,
(b) receives a written confirmation of the instruction, from (or on behalf of) the Contractor, within two working days after giving the instruction, and
(c) does not reply by issuing a written rejection and/or instruction within two working days after receiving the confirmation,
page 18
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
then the confirmation shall constitute the written instruction of the Project Manager or delegated assistant (as the case may be).
2.2.3.Sub-clause 4.7 – Setting Out
The Contractor shall set out the Works in relation to original points, lines and levels of reference specified in the Contract or notified by the Project Manager. The Contractor shall be responsible for the correct positioning of all parts of the Works, and shall rectify any error in the positions, levels, dimensions or alignment of the Works.
The Employer shall be responsible for any errors in these specified or notified items of reference, but the Contractor shall use reasonable efforts to verify their accuracy before they are used.
If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated by an error in these items of reference, and an experienced contractor could not reasonably have discovered such error and avoided this delay and/or Cost, the Contractor shall give notice to the Project Manager and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed,under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost plus profit, which shall be included in the Contract Price.
After receiving this notice, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent the error could not reasonably have been discovered, and (ii) the matters described in sub-paragraphs (a) and (b) above related to this extent.
2.2.4.Sub-clause 4.12 – Unforeseeable Physical Conditions
In this sub-clause, “physical conditions” means natural physical conditions and man-made and other physical obstructions and pollutants, which the Contractor
page 19
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
encounters at the Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic conditions.
If the Contractor encounters adverse physical conditions which he considers to have Unforeseeable, the Contractor shall give notice to the Project Manager as soon as practicable.
This notice shall describe the physical conditions, so that they can be inspected by the Project Manager, and shall set out the reasons why the Contractor considers them to be Unforeseeable. The Contractor shall continue executing the Works, using such proper and reasonable measures as are appropriate for the physical conditions, and shall comply with any instructions which the Project Manager may give. If an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.
If and to the extent that the Contractor encounters physical conditions which are Unforeseeable, gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be included in the Contract Price.
After receiving such notice and inspecting and/or investigating these physical conditions, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent these physical conditions were Unforeseeable, and (ii) the matters described in sub-paragraphs (a) and (b) above related to this extent.
2.2.5.Sub-clause 8.3 – Programme
The Contractor shall submit a detailed time programme to the Project Manager within 28 days after receiving the notice under Sub-Clause 8.1 [Commencement of Works]. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with
page 20
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
actual progress or with the Contractor's obligations. Each programme shall include:
(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each stage of design (if any), Contractor's Documents, procurement, manufacture of Plant, delivery to Site, construction, erection and testing,
(b) each of these stages for work by each nominated Subcontractor (as defined in Clause 5 [Nominated Subcontractors]
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the Contractor intends to adopt, and of the major stages, in the execution of the Works, and
(ii) details showing the Contractor's reasonable estimate of the number of each class of Contractor's Personnel and of each type of Contractor's Equipment, required on the Site for each major stage.
Unless the Project Manager, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Employer's Personnel shall be entitled to rely upon the programme when planning their activities.
The Contractor shall promptly give notice to the Project Manager of specific probable future events or circumstances which may adversely affect the work, increase the Contract Price or delay the execution of the Works. The Project Manager may require the Contractor to submit an estimate of the anticipated effect of the future event or circumstances, and/or a proposal under Sub-Clause 13.3 [Variation Procedure].
If, at any time, the Project Manager gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a revised programme to the Project Manager in accordance with this Sub-Clause.
page 21
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2.2.6.Sub-clause 8.4 – Extension of Time for Completion
The Contractor shall be entitled subject to Sub-clause 20.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking-Over of the Works and Sections] is or will be delayed by any of the following causes:
(a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]) or other substantial change in the quantity of an item of work included in the Contract,
(b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions,
(c) exceptionally adverse climatic conditions,
(d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions, or
(e) any delay, impediment or prevention caused by or attributable to the Employer, the Employer's Personnel, or the Employer's other contractors.
If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Project Manager in accordance with Sub-Clause 20.1 [Contractor's Claims]. When determining each extension of time under Sub-Clause 20.1, the Project Manager shall review previous determinations and may increase, but shall not decrease, the total extension of time.
2.2.7.Sub-clause 8.8 – Suspension of Works
The Engineer may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store andsecure such part or the Works against any deterioration, loss or damage.
The Engineer may also notify the cause for the suspension. If and to the extent that the cause is notified
page 22
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
and is the responsibility of the Contractor, the following Sub-Clauses 8.9, 8.10 and 8.11 shall not apply.
2.2.8.Sub-clause 8.9 – Consequences of Suspension
If the Contractor suffers delay and/or incurs Cost from complying with the Engineer’s instructions under Sub-Clause 8.8 [Suspension of Work] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be included in the Contract Price.
After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
The Contractor shall not be entitled to an extension of time for, or to payment of the Cost incurred in, making good the consequences of the Contractor’s faulty design, workmanship or materials, or of the Contractor’s failure to protect, store or secure in accordance with Sub-Clause 8.8 [Suspension of Work].
2.2.9.Sub-clause 12.1 – Works to be Measured
The Works shall be measured, and valued for payment, in accordance with this Clause.
Whenever the Project Manager requires any part of the Works to be measured, reasonable notice shall be given to the Contractor's Representative, who shall:
(a) promptly either attend or send another qualified representative to assist the Project Manager in making the measurement, and
(b) supply any particulars requested by the Project Manager.
page 23
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
If the Contractor fails to attend or send a representative, the measurement made by (or on behalf of) the Project Manager shall be accepted as accurate.
Except as otherwise stated in the Contract, wherever any Permanent Works are to be measured from records, these shall be prepared by the Project Manager. The Contractor shall, as and when requested, attend to examine and agree the records with the Project Manager, and shall sign the same when agreed. If the Contractor does not attend, the records shall be accepted as accurate.
If the Contractor examines and disagrees the records, and/or does not sign them as agreed, then the Contractor shall give notice to the Project Manager of the respects in which the records are asserted to be inaccurate. After receiving this notice, the Project Manager shall review the records and either confirm or vary them. If the Contractor does not so give notice to the Project Manager within 14 days after being requested to examine the records, they shall be accepted as accurate.
2.2.10. Sub-clause 12.3 – Evaluation
Except as otherwise stated in the Contract, the Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine the Contract Price by evaluating each item of work, applying the measurement agreed or determined in accordance with the above Sub-Clauses 12.1 and 12.2 and the appropriate rate or price for the item.
For each item of work, the appropriate rate or price for the item shall be the rate or price specified for such item in the Contract or, if there is no such item, specified for similar work.
For each item of work included in the Bill of Quantities for which no rate or price was specified shall be considered as included in other rates and prices in the Bill of Quantities and will not be paid for separately. However, a new rate or price shall be appropriate for an item of work if:
(a) (i) the measured quantity of the item is changed by more than 25% from the quantity of this item in the Bill of Quantities or other Schedule,
page 24
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
(ii) this change in quantity multiplied by such specified rate for this item exceeds 0.25% of the Accepted Contract Amount,
(iii) this change in quantity directly changes the Cost per unit quantity of this item by more than 1 %, and
(iv) this item is not specified in the Contract as a "fixed rate item";
Or
(b)(i) the work is instructed under Clause 13 [Variations and Adjustments],
(ii) no rate or price is specified in the Contract for this item, and
(iii) no specified rate or price is appropriate because the item of work is not of similar character, or is not executed under similar conditions, as any item in the Contract.
Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.
Until such time as an appropriate rate or price is agreed or determined, the Project Manager shall determine a provisional rate or price for the purposes of Interim Payment Certificates.
2.2.11. Sub-clause 13.1 – Right to Vary
Variations may be initiated by the Project Manager at any time prior to the issuing the Taking-Over Certificate for the Works, either by an instruction or by a request for the Contractor to submit a proposal.
Contractor shall execute and be bound by each Variation, unless the Contractor ptly gives notice to the Project Manager stating (with supporting particulars) that the Contractor cannot readily obtain the Goods required for the Variation. Upon receiving notice, the Project Manager shall cancel, confirm or vary the instruction.
page 25
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Each Variation may include:
(a) changes to the quantities of any item of work included in the Contract (however, such changes do not necessarily constitute a Variation),
(b) changes to the quality and other characteristics of any item of work,
(c) changes to the levels, positions and/or dimensions of any part of the Works,
(d) omission of any work unless it is to be carried out by others,
(e) any additional work, Plant, Materials or services necessary for the Permanent Works, including any associated Tests on Completion, boreholes and other testing and exploratory work, or
(f) changes to the sequence or timing of the execution of the Works.
The Contractor shall not make any alteration and/or modification of the Permanent Works, unless and until the Project Manager instructs or approves a Variation.
2.2.12. Sub-clause 13.3 – Variation Procedure
If the Project Manager requests a proposal, prior to instructing a Variation, the Contractor shall respond in writing as soon as practicable, either by giving reasons why he cannot comply (if this is the case) or by submitting:
(a) a description of the proposed work to be performed and a programme for its execution,
(b) he Contractor's proposal for any necessary modifications to the programme according to Sub-Clause 8.3 [Programme] and to the Time for Completion, and
(c) the Contractor's proposal for evaluation of the Variation.
The Project Manager shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value Engineering] or otherwise), respond with approval,
page 26
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
disapproval or comments. The Contractor shall not delay any work whilst awaiting a response.
Each instruction to execute a Variation, with any requirements for the recording of Costs, shall be issued by the Project Manager to the Contractor, who shall acknowledge receipt.
Each Variation shall be evaluated in accordance with Clause 12 [Measurement and Evaluation], unless the Project Manager instructs or approves otherwise in accordance with this Clause.
2.2.13. Sub-clause 20.1 – Contractor’s Claims
If the Contractor considers himself to be entitled to any extension of time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.
If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim. Otherwise, the following provisions of this Sub-Clause shall apply.
The Contractor shall also submit any other notices which are required by the Contract, and supporting particulars for the claim, all as relevant to such event or circumstance.
The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Project Manager. Without admitting the Employer's liability, the Project Manager may, after receiving any notice under this Sub-Clause, monitor the record-keeping and/or instruct the Contractor to keep further contemporary records. The Contractor shall permit the Project Manager to inspect all these records, and shall (if instructed) submit copies to the Project Manager.
page 27
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Project Manager, the Contractor shall send to the Project Manager a fully detailed claim which includes full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed. If the event or circumstance giving rise to the claim has a continuing effect:
(a) this fully detailed claim shall be considered as interim;
(b) the Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Project Manager may reasonably require; and
(c) the Contractor shall send a final claim within 28 days after the end of the effects resulting from the event or circumstance, or within such other period as may be proposed by the Contractor and approved by the Project Manager.
Within 42 days after receiving a claim or any further particulars supporting a previous claim, or within such other period as may be proposed by the Project Manager and approved by the Contractor, the Project Manager shall respond with approval, or with disapproval and detailed comments. He may also request any necessary further particulars, but shall nevertheless give his response on the principles of the claim within such time.
Each Payment Certificate shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate.
The Project Manager shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the extension (if any) of the Time for Completion (before or after its expiry) in accordance with Sub-Clause 8.4 [Extension of Time for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the Contract.
page 28
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply to a claim. If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub-Clause.
2.3. Original Planning and Cash-flow
2.3.1.The Clause 8 Programme
The programme of works that appears below is summary task format was issued and approved for construction in XX 2007.
This programme of works considers the original scope of works depicted in the bills of quantities, including time provision for provisional sums. The provisional sum value included in the Contract allowed for inclusion by Variation all works not defined at time of tender. The Contractor’s original cash-flow was produced using this data.
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
1614 B223 Villas ( 7 nos)
1965 B4 Villa (2 nos.)
2056 Retail 1( subject to receipt of GFW drawings)
2094 Retail 2( subject to receipt of GFW drawings)
2132 Retail 3( subject to receipt of GFW drawings)
2170 Seafood resort( subject to receipt of GFW drawings)
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2664 B223 Villas ( 3 nos)
2808 B4 Standard Villas ( 2 nos)
2899 BC311 Executive Villa
3115 P3 Presidential suites ( 3 nos)
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct2007 2008
page 29
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2.3.2.Planned versus Actual Turnover
The chart below provides a comparison between planned cash-flow, based on the programme of works, and actual income.
It can be seen the period through to XX, the first X-months of the construction programme, both planned and actual cash-flow remain reasonably constant. This is to be expected.
However, thereafter the gap widens because:
Excavations took longer because of hard rock;
Sub-structure work took longer due to greater scope of work;
Work slowed down waiting information and detailed design, and
Works were suspended
-5,000,000.00
0.00
5,000,000.00
10,000,000.00
15,000,000.00
20,000,000.00
25,000,000.00
30,000,000.00
Feb-07
Mar-07
Apr-07
May-07
Jun-07
Jul-07
Aug-07
Sep-07
Oct-07
Nov-07
Dec-07
Jan-08
Feb-08
Mar-08
Apr-08
May-08
PlanCumm ActualCumm
The following table provides the value of payment applications certified to end of May 2008.
page 30
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month Planned PlanCumm Actual ActualCummFeb-07 3,100,000.00 3,100,000.00 0.00 0.00Mar-07 601,658.62 3,701,658.62 0.00 0.00Apr-07 1,352,295.74 5,053,954.37 0.00 0.00
May-07 1,852,720.48 6,906,674.85 3,100,000.00 3,100,000.00Jun-07 2,236,090.71 9,142,765.56 0.00 3,100,000.00Jul-07 2,684,335.78 11,827,101.34 682,032.85 3,782,032.85
Aug-07 2,189,910.64 14,017,011.97 351,989.15 4,134,022.00Sep-07 2,236,090.71 16,253,102.68 145,803.63 4,279,825.63Oct-07 2,258,038.74 18,511,141.42 357,556.62 4,637,382.25Nov-07 2,258,038.74 20,769,180.15 478,924.03 5,116,306.28Dec-07 1,754,288.50 22,523,468.65 0.00 5,116,306.28Jan-08 1,289,372.84 23,812,841.49 0.00 5,116,306.28Feb-08 1,040,280.70 24,853,122.19 274,355.16 5,390,661.44Mar-08 500,424.74 25,353,546.93 1,086,667.96 6,477,329.40Apr-08 2,575,212.46 27,928,759.39 0.00 6,477,329.40
May-08 0.00 27,928,759.39 0.00 6,477,329.40
It can be seen in the cumulative column how the gap widens as of almost the outset of the contract and has increased progressively in the period to date, May 2008. It is also of worthy note the “flatness” of the line showing cumulative income which results from:
A reduced income caused by the delays notified;
The fixed nature of the Advance repayment;
The value retained in retention.
The Contractor notified the financial imbalance being caused by the Advance repayment in his letters dated 19 November 2007:
Please refer to the Cash Flow Forecast dated 10 February 2007 included in the Contract Document Volume 1. As you are aware, this cash flow was preliminary and assumed payment of the Advance would occur in February 2007.
However, as payment of the Advance is the trigger to commencement of repayment, it is now necessary to amend this preliminary cash flow to reflect the actual date of receipt, which we record, was in May 2007.
Accordingly, please find attached the amended Cash Flow forecast adjusted to reflect the month the Advance was received and consequent 10-month repayment drawn-down against Interim Payments.
A further notice was issued on 21 November 2007:
Please refer to the amended Cash Flow Forecast submitted under cover of letter dated 19 November 2007.
page 31
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
As you are aware, this cash flow was preliminary and assumed repayment of the Advance against projected income derived from the original programme of works.
However, the progress of works has been delayed and disrupted for reasons provided in separate notifications and as a result, income is significantly lower in the period to date.
Accordingly, please find attached an amended Cash Flow forecast adjusted to reflect a 15-month repayment drawn-down against Interim Payments consequent to the extended contract period shown on the revised programme of works.
2.4. First Revised Programme of Works
The Programme of Works above was issued under cover of letter dated 19 November 2007 in accordance with Clause 8 of the Contract Conditions.
In accordance with your request please find attached our revised programme reflecting actual progress achieved at 6 November 2007. This programme of works takes consideration of events and changed circumstances since commencement that caused original planned timing and sequence to vary.
Unless notice is received stating the extent to which it does not comply with the Contract, we shall proceed in accordance with this programme and will rely upon this programme when planning our activities.
Therefore, the Contractor’s timing, sequence are clearly explained in support of this programme. This programme of works indicated a revised completion date.
2.5. Second Revised Programme of Works
At the request of the Project Manager a second revised programme of works was issued on 14 March 2008.
In accordance with your recent request in the weekly progress meetings, please find attached revised programme of works for your consent.
page 32
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The revised programme takes into consideration the various events and changed circumstances since commencement up to 29 February 2008.
These events and changed circumstances, as separately notified to you and further illustrated in our situation report dated 29 February 2009, have caused the original planned timing and sequence of works to vary. They include the following;
Unforeseen hard rock excavation including spoiling;
Suspension of works, except for the mock up villas, for two months and associated acceleration measures;
Instructed design variations, e.g. exchange of galvanised steel with stainless steel components for installation in the roof resulting into delays in procurement;
Late Instructions, e.g. several changes to the location, position and orientation of buildings by revision in the setting out details have delayed and disrupted the works;
Late Design Information resulting into delays in procurement thus preventing timely arrival of materials at site;
Increased scope of works occasioned by unforeseen site conditions and instructed additional works;
Inclement weather condition; unexpected high amounts of rainfall currently being experienced at site is slowing down progress of works.
The overall effect of all the above has been to delay the completion date for the works up to 24 March 2009 as indicated in the attached revised programme.
We therefore request extension of time to completion of the works.
As stated in the last paragraph of this notice, an extension of time had been requested.
page 33
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2.6. Actual Progress
Since the outset of the Contract the Contractor suffered delay due to four major reasons;
Late and inaccurate survey data;
Unforeseen ground conditions;
Project Manager’s instruction to suspend Works (partial);
Late receipt of final design information, and
Additional and varied works.
As a result of Works did not commence as planned.
page 34
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
3. Valuation of Variations
3.1. Explanation of Heads of Claim
In his various notifications the Contractor has made reference to at least three types of variations. One type is the changes to the scope of work, a second is the late receipt of design and the third is the changes to the sequence and timing of work. All of these have been sufficiently described and defined in these notifications.
During the currency of work, the first two types of change occurred simultaneously, as well as following consecutively. For example, design drawings which have been issued late, to allow the commencement of certain works, showed changes to the Contract drawings. Further these changes occurred when the Contractor encountered unforeseen ground conditions at most of the respective sites. That is simultaneous occurrence.
There were many instances of consecutive occurrence. For example, where drawings were revised a number of times over a period of several months and even over more than a year, those were consecutive.
3.2. Specific Heads of Claim
Where variations are the cause of delay, the costs associated with the delay have to be taken into account in the valuation of the variations. There are two types of cost to be taken into account. One is the cost of prolongation of work on site. This is the cost of (1) maintaining the site establishment and (2) off-site overheads.
The second type of cost is that of the uneconomic way of working, which results from incorporating the varied work into the Works. This includes the direct cost of the disrupted nature of work on site, and the loss of anticipated income at the times envisaged in the original cash-flow predictions.
page 35
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
3.3. Methods of Valuation of the Variations
3.3.1.Use of Costs as Basis
In submitting these particulars of prolongation costs and particulars of slowdown Costs, the Contractor is providing what he is obliged to do by the Contract, which is to make use of contemporary records of costs. The costs were to be used as basis for valuing the variations.
3.3.2.Addition for Profit
It is evident that there are two generic types of claim. One is for ‘costs’ and the other is for value. Therefore, it is necessary to look at profit as a part of both value and cost. The Contractor’s entitlement to have profit added to his cost, to the extent that the costs claimed are included in variation valuations, profit must be added to those costs for inclusion in such valuations. It is noted that Clause 13 clearly indicates that all variations referred to shall be valued in accordance with Clause 12.
In compliance with this requirement of the Contract, the proposition that where the time related costs are indicative of loss of efficiency due to the variation in the timing and sequence of events and are used to formulate a new rate for a particular bill item, then they should include all expenditure, whether on or off the Site. Clause 12 states that the
a new rate or price shall be derived from the reasonable Cost of executing the work, together with reasonable profit
This clarifies that a valuation under Clause 12 must include profit on time related costs. Profit addition on this contract is 15%.
3.3.3.Profit as Part of the Value of Variations
3.3.3.1. Three Types of Variations
The three types of variation included in this submission:
1. Changes in design of parts of the Works,
2. Additional and Varied works, and
3. Changes in the timing and sequence
page 36
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
As noted above, all such variations fall to be valued under Clause 13, with the possibility that Clause 12 can be invoked in respect of the effects of variations on unvaried work.
The Contractor confirms that costs claimed are the indirect costs of the delays to the Works, whilst the direct costs include the direct costs of performing the works. In other words, the Contractor’s claim is for the time-related costs to be rolled into the Clause 12 variation valuations.
It is helpful now to give some consideration to each type of variation in turn, so that the Employer can see how profit is included in the valuation of each.
3.3.3.2. Changes in Design of the Works
The first of those two speaks for itself. The claim is for the time-related costs of the variations to be included in the variation valuations. It is unnecessary to argue the point that any such valuation must include profit, under the valuation rules. All valuation rules, in Clauses 12, are founded in rates and prices. It is implicit that they already include profit. It follows that any new rate or price will also include profit.
Of the complaints notified, the first variation event relates to delayed setting out, the second to unforeseen ground conditions, the third to delayed and incomplete design drawings and the fourth to additional and varied Works. Those variations comprised:
1. The changes in the position of buildings, foundation design (partly arising from excavation in rock), unforeseen ground conditions, suspension of Works, late design information, and
2. The change to the specified sequence and timing of the Works
Again, it is helpful to consider each type separately.
3.3.3.2.1. Technical Variations
As example, the changes in design of the Works referred to immediately above; there can be no doubt that a valuation of this type of variation to the foundation works will have to include profit in any event. Similarly, changes in ground conditions must equally include profit.
page 37
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
3.3.3.2.2. Changes to Specified Sequence and Timing
Clause 13.1 (f), Conditions of Contract Part I, confirms any change to the specified sequence or timing of construction of any part of the Works instructed by the Project Manager, constitutes a Variation.
In order to establish a Variation to sequence and time, it is therefore necessary to establish the specified sequence and timing of the Works. Clause 8.3, Conditions of Contract Part I, requires the Contractor to submit to the Project Manager for his approval, a program which illustrates the sequence and timing the Contractor intends on performing his Works.
Project Manager’s approval of the Contractor’s Clause 8.3 Program was received in XX 2007. Consequently, the Clause 8.3 Program approved by the Project Manager represents the specified sequence and timing of the Works and any change to this sequence and timing instructed by the Project Manager in writing represents a Variation in accordance with Clause 12.3 (b) (iii).
The Employer will agree that the late receipt of design information is a specified sequence or timing of work as envisaged by Clause 13.1(f) of the General Conditions of Contract. Similarly, the suspension of the works must be treated in the same manner.
Consequently, the Employer will agree that the Project Manager has changed those sequences or timings, and that the Contractor is entitled to have the change treated as variation within the meaning of the said Clause.
The Contractor’s claim to have the changes of sequence and timing brought within Clause 13.1(f) means that those changes also fall to be valued under Clause 12.3. As with the previous types of variation valuation, it must include profit.
3.3.3.3. Summary
When considering profit as part of the valuation of variations, the matters affected are:
1. Changes in the Design of the Works
page 38
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
2. Variations to foundations, which splits into two further sub-divisions, namely (1) technical variations and (2) changes to the sequence and timing of work.
It is evident from the foregoing that all of the valuations of the variations referred to must include profit. Therefore, to the extent that the costs claimed are included in variation valuations, profit must be added to those costs.
Clearly, as the foundation work was one of the earliest site operations, the amount of costs, to which profit must be added, is considerable.
3.3.4.The Effects on Unvaried Work
As can be seen from the claims referred in this submission, numerous variations have either been issued or arisen as a consequence of unforeseen ground conditions. In addition, design drawings have generally been received much later than required as depicted on the programme of works. The extent of the variations is such that the original scope of the work included in the Contract has been changed considerably.
So profound have the effects of the changes to both the scope of work and to the sequence and timing of work been, that the relatively few areas of work, which were not varied, have been affected by those variations. The effects fall into the basic categories of (1) prolongation and (2) disruption of the unvaried work.
Clause 12.3 provides the mechanism for including the effects of prolongation and disruption of the unvaried work:
No rate or price is appropriate because the item of work is not of similar character, or is not executed under similar conditions, as any item in the Contract.
This term of the Contract provides an indemnity to the Contractor for all costs reasonably incurred in carrying out variations.
3.3.5.For Uneconomic Working
From the foregoing discussion and analysis, it is evident that a claim for uneconomic working comes within the ambit of Sub-clause 12.3, when the costs are caused directly by performing variations under Clause 13.1, when costs arise from carrying out
page 39
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
the work described in the Contract. In practice, it is not possible to separate uneconomic working from the effects on unvaried working, due to the close proximity of site operations, and the continual interchange of resources between varied and unvaried work.
The types of costs of uneconomic working are:
1. The loss of anticipated income, by way of financing.
2. Wasted monthly costs.
3. Financing wasted monthly costs.
Each of those heads of claim is dealt with in turn.
3.3.5.1. Loss of Anticipated Income
This is the cost to the Contractor of financing the shortfall between the income he reasonably expected to receive, and what he actually received, in Interim Payment Certificates.
As to the suspension or slowdown costs, the Contractor claims in respect of lost income for the period from commencement in March 2007 to May 2008. That is because the Particulars included in this submission also relate to the delays in that period.
3.3.5.2. Wasted Monthly Costs
This is a measure of the waste of resources, caused by the disruption, dislocation and re-sequencing of work.
In this document the Contractor describes the cause which resulted in suspension or slowdown of the works. At this section he describes the effect of the cause that is what he means by wasted monthly costs:
One of the types of damage incurred by the Contractor would be the idle time, and/or reduced output, of resources. It is not possible to sever the damage incurred by reason of the delayed setting out of sites, unforeseen ground conditions, changes in scope of works, from that incurred by reason of the delayed design drawings.
The schedules showing the monthly labour and plant levels are evidence that the Contractor not only mobilised, but also maintained, levels of each, which should have ensured outputs
page 40
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
at the level of anticipated monthly income referred to above. The schedules showing the amounts certified for each month are evidence that, notwithstanding the level of resources on site, the Contractor’s turnover was far less than he reasonably anticipated.
In order to arrive at a measure of the cost of idle time, and the reduced output, the Contractor has calculated the percentage, which the loss of income represents for each month, of the anticipated income. The Contractor has then applied the same percentage to the monthly cost of labour, equipment, both site and head office overheads, to arrive at the cost on which he has had no return.
The Contractor believes this is the most sensible way of approaching this head of claim. It uses evidence, as opposed to estimates, or supposition.
3.3.5.3. Financing Wasted Monthly Costs
This should be self-explanatory. However, a few words of explanation will help. The Contractor’s entitlement relies on the following:
The Employer should agree that the Contractor is entitled to either the financing charges for the wasted monthly costs if either these are agreed, in the form of interest on late payment in accordance with Clause 14.8 of the conditions of contract or finance charges incurred, whichever is the greater.
The application of finance charges as compensation for the Contractor being kept out of his money replaces interest on late payments. Accordingly, the Contractor claims to be entitled to financing charges on the wasted costs included in the valuation of the Variations.
3.3.6.Profit as Part of ‘Costs’
To the extent that profit on costs could become an issue, the Contractor’s contentions are as follows.
3.3.6.1. Authorities on the Basis of ‘Costs’
In order to appreciate what should be included in a determination of costs, it is necessary to grasp the concept of
page 41
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
the expression as used in the contract claims machinery. There are a number of helpful authorities, which explain this.
3.3.6.1.1. Powell-Smith’s ‘Some Building Contract Problems’
The following passage from ‘Some Building Contract Problems’ (page 141), by the late Dr Vincent Powell-Smith, who was a well-known international lecturer, commentator and author, illustrates the purpose of what some construction contracts call ‘direct loss and/or expense’. The parallel in the Contract is ‘costs’:
The purpose of the contract claims machinery is to put the contractor back into the position he would have been but for the delay or disruption, and various cases establish that the term ‘direct loss and/or expense’ means in effect that what is recoverable is substantially the same as the damages recoverable at common law under the first rule in the old case of Hadley v. Baxendale (1854)
This fits directly with the criterion used in the Robinson v. Harman case (see below).
3.3.6.1.2. Hudson and Minter v. WHTSO
In the extract from Hudson’s Building and Project Managering Contracts, Eleventh Edition, Volume 1, on page 1020, there is a summary of the ruling in the case of F G Minter v. Welsh Health Technical Services Organisation (1980) 13BLR1:
By Clauses 11(6) and 24(1) respectively of the 1963 RIBA/JCT forms of contract, the contractor was entitled to be paid ‘direct loss and expense’ not reimbursable under the preceding variation valuation rules, in the one case, or as a result of disturbance of progress due to late receipt of drawings and information from the architect on the other. The contractor claimed financing charges on the additional expenditure in each case as sums due and to be certified by the architect under the two clauses.
Held, by the Court of Appeal, on preceding judicial authority the words ‘direct loss and expense’ meant such damages as would be recoverable as naturally flowing from a breach of contract under the first branch of the rule in Hadley v. Baxendale.
page 42
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Again, although the extract refers to the expression ‘loss and/or expense’, it is the equivalent of the ‘costs’ suffered by the Contractor under the Contract.
The discussion of the judgment following the passage quoted from it in Hudson is at the heart of this issue in this Claim. In paragraph 8-096, the learned author says:
The wider importance of the Minter and Rees and Kirby cases in the Construction field cannot be ignored. The reasoning of the Court of Appeal in the Minter case was that previous authority showed that the contractual “direct loss and expense” expression meant the same as the measure of damage “arising naturally in the usual course of things” under the first branch of the Hadley v. Baxendale rule. The contract therefore expressly applied that test to both the Clause 11(6) basis of claim (variations and not, therefore, a breach of contract) and to the Clause 24(1)(a) basis (late information and, therefore, a breach of contract). [Author’s emphasis.]
The author’s discussion draws attention to the importance of the comparison of direct loss and expense, or, as in the Contract, ‘cost’, with damages envisaged by Hadley v. Baxendale. The costs referred to have been incurred as a result of denial of possession of parts of the site, and of late and varied information.
3.3.6.1.3. Hudson on the Scope of ‘Costs’
From the two foregoing authorities, it is evident that the more widely used expression ‘loss and expense’ is a direct parallel to the word ‘costs’ as used in the instant Contract. Underpinning this is the breadth of coverage given to the expression ‘loss and expense’. This is illustrated by the following extract from page 1096 of Hudson, paragraphs 8.213 to 8.216. In paragraph 8.213, the author draws attention to the coverage of ‘loss and expense’:
a. ‘Direct’ or ‘consequential’ damage provisions
… In this context, ‘consequential’ damage will sometimes be contrasted with ‘direct’ damage as the subject of exclusion, or sometimes used on its own to indicate an intended class of compensation. Thus, since 1963 the English standard forms, and in particular the RIBA/JCT forms, have employed the expression ‘direct loss and expense’ in the context of positive provisions for
page 43
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
additional payment expressly permitted by these contracts. …
He then draws the parallel with Hadley v. Baxendale for the type of damage to be included in loss and expense, and what he calls ‘wording of this kind’, in paragraph 8.215:
These strict interpretations in the case of exclusions clauses have been paralleled by a correspondingly generous interpretation of ‘direct loss and expense’. Wording when used positively in compensation provisions. It has already been seen that interest in the form of financing charges has been held to be recoverable by contractors under this wording under Clauses 11(6) and 24 of the 1963 RIBA/JCT forms. Wording of this kind will include any damage recoverable under the first branch of the Hadley v. Baxendale rule, which it has been seen will include a wide range of heads of damage which might otherwise in a loose sense be described as ‘consequential’ or ‘indirect’.
It should be noted that, on page 1098 of the extract, in the reference to the second case, Wraight v. PH&T (Holdings) Ltd (1968), it says that it was held that a contractor was entitled to his loss of profit. This case is referred to specifically below.
This extract is included as Appendix 4.
3.3.6.1.4. The First Part of the Rule in Hadley v. Baxendale
The case of Hadley v. Baxendale is at the very heart of damages for breach of contract, and need not be quoted at length. Having established that a contractor’s claim for loss and expense, or cost, or indeed for anything covered by ‘wording of this kind’, it is helpful to refer to the judgment in Hadley v. Baxendale, to see exactly what the first part of the rule allows.
The Contractor reproduces here an extract from ‘Contract Cases and Materials’ by Hugh Beale, William Bishop and the very well-known and respected Prof Michael Furmston, who is also the author of the classic work on contract law, ‘Furmston, Cheshire and Fifoot’. The extract is in fact part of the judgment in the case, at page 395:
We think that there ought to be a new trial in this case; but, in so doing, we deem it to be expedient and necessary to state explicitly the rule which the Judge, at
page 44
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
the next trial, ought, in our opinion, to direct the jury to be governed by when they estimate the damages. …
Now we think the proper rule in such a case as the present is this: - Where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e. according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it.
Thus, the first part of the rule is that:
… the damages which the other party ought to receive … should be such as may fairly and reasonably be considered … arising naturally, i.e. according to the usual course of things, from such breach of contract itself …
In the case of the matters claimed, the Contractor is therefore entitled to reimbursement of costs, which include costs, which arose naturally from the breach.
3.3.6.1.5. The Basic Measure of Damages
Having established that the Contractor is entitled to have his costs determined on the basis of what flowed naturally from the breach, it is necessary to alight upon the correct measure of damage. There is precise authority for this in the case of Robinson v. Harman (1848) 1Exch850, 855. The relevant passage is as follows:
The rule of the common law is, that where a party sustains loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.
The quoted passage is taken from page 11 of Beale, Bishop and Furmston’s book.
This the truly prescriptive rule for what should be in the determination of costs. It has been shown by logical steps that ‘costs’ in their generic sense equate to common law damages. From that, it is the common law rule that damages must put the offended party back in the same position he would have been in, but for the events complained of.
page 45
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
It follows from this that a contractor, who suffers as a result of an act or omission of the employer or his agents, is entitled to recover his profit.
3.3.6.2. Authorities on the Recovery of Profit
Now that the basic premise for using the criterion applicable to common law damages for breach of contract has been presented, the Contractor will show that the recovery of profit comes within that criterion.
3.3.6.2.1. General Principle as to Claims
The general rule that claims for loss and expense or costs are to be treated as claims for damages at common law is expounded by Dr Powell-Smith on page 143 of ‘Some building Contract Problems’:
Claims under clause 26 can be equated with claims for damages at common law, and are governed by the same principles. On that basis, the consequences of the late instruction must have been within the reasonable contemplation of the contracting parties at the time the contract was made. The additional cost arises as a direct and natural result of the architect’s default and is thus claimable under the contract terms: see Hadley v. Baxendale (1854)
3.3.6.2.2. Wraight v. PH&T (Holdings) Ltd
In the case of Wraight v. PH&T (Holdings) Ltd (1968), a contractor pursued a claim for loss of profit, as a result of his own determination of his employment under a building contract.
The contractor in the case put his argument as summarised in the judgment on page 284, near the bottom:
It is said here on behalf of the [contractors] that quite plainly the loss of profit to the [contractors] was, in any ordinary sense of the word, a direct consequence of the determination of the contract. If the contract had not been determined, they would have gone on and done the work, continued their legal obligations thereunder and would have had their legal right to obtain their full contractual remuneration at the end of it, and therefore they have, by this determination, lost the right to receive that sum of
page 46
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
money which they would have received if the contract had not been determined: what can be more direct than that?
Obviously, the event complained of in the case is determination of the contractor’s employment. However, that is not of importance. It is a type of event, which entitles the offended contractor to reclaim his losses, just as the denial of possession and late information in the Contract do.
The important thing is that the contractor in the case was looking to recover the sum of money he would have recovered, but for the event complained of. It is natural that such sum of money included profit.
The judge concluded, on page 285:
In my judgment, there are no grounds for giving to the words ‘direct loss and/or damage caused to the contractor by the determination’ any other meaning than that which they have, for example, in a case of breach of contract or other question of the relationship of a fault to damage in a legal context. Therefore it follows … that the [contractors] are, as a matter of law entitled to recover that which they would have obtained if this contract had been fulfilled in terms of the picture visualised in advance but which they have not obtained.
It was held (page 284) that:
The words direct loss and/or damage in clause 26 must be given the same meaning as they would have in the case of a breach of contract. The loss of profit was the direct and natural consequence of the determination of the contract, and the contractors were entitled to succeed.
3.3.6.2.3. Powell-Smith and Sims on Building Contract Claims
The authors of ‘Building Contract Claims’, Vincent Powell-Smith and John Sims, state unequivocally on page 110 of their book that:
Loss of profit, which the contractor would otherwise have earned but for the delay or disruption, is an allowable head of claim. It is recoverable under the rule in Hadley v. Baxendale (1854).
Pages 110 to 113 of the book are included in Appendix 9.
page 47
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
It is worth noting that the authors refer to the Wraight case on page 111, and that they make a distinction between the profit normally to be expected, and exceptionally high profit. The Contractor is only claiming here the level of profit allowed for in his tender.
The extract also mentions the possibility of claiming for profit lost on other contracts. The Contractor is not claiming for that. He is only claiming for his profit on the Contract, which is much more direct than that lost on other projects.
3.3.6.3. Summary
There are plenty of authorities to show that:
1. A claim for payment of ‘costs’ is to be treated as a claim for common law damages.
2. Such damages should put the complaining party back into the position he would have been in, but for the event complained of.
3. Profit is an allowable head of claim under common law damages.
The Contractor’s claim is only for profit on the Contract work, not for other work, so it is within the first rule in Hadley v. Baxendale, and should be allowed.
3.4. The Contractor’s Summary
For all of the foregoing reasons, the Contractor contends that the profit claimed by him is allowable. It should be treated in the same way as damage within the meaning of the first rule in Hadley v. Baxendale, and fulfil the criterion in Robinson v. Harman.
There is no prohibition of it as a head of claim. If the Project Manager were to have the power to deprive the Contractor of profit on any claim he chose to treat as one for ‘costs’, then all contractors could be placed in the unacceptable position of doing a large proportion of work at cost. This is clearly not what the Contract stipulates, nor could it have been the intention of the parties.
page 48
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
4. Circumstances Giving Rise to Claim
Performance of the construction activities required the availability of final setting out details and foundation design information (arising from unforeseen ground conditions) to permit execution of the Works. Records show that setting out was delayed and information with respect to rock excavation was neither evident from records available. These two initial events seriously impacted progress and caused significant delays. It was further and seriously compounded by the Project Manager’s instructions to suspend the Works which lasted 2 months.
Furthermore, it is a fundamental requirement of the Contract that detailed design information is made available in the times consistent with the Contractor’s programme of works. In the event, such information was late, and aggravated by incomplete and inconsistent design details that naturally caused a change in the planned methods of working. This is particularly evident at the two “Mock-up” villas that underwent numerous changes as works proceeded.
In addition to the above, payment for varied work performed was not fully received by the Contractor in accordance with the procedures and time stated in the contract.
4.1. Contractual Basis – Notification of Changes
The Contractual basis of the heads of claim is described in subsequent sections of this document. That is, the Contractor gave notice of the difficulties existing at the Site arising from delays and disruptions.
The Contractor issued notice of the following issues on
We acknowledge receipt of your letter dated 4 December 2007 referenced E-09-04-12-07 and wish to confirm our position by the following extract from the Contract:
The Letter of Acceptance dated 7 March 2007 referenced SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.”
page 49
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
It further states that “Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”
The Contract Agreement dated 27 April 2007 lists the documents forming the Agreement and the Letter of Acceptance takes priority over the Conditions of Contract.
Consequently, your reference to sub-clause 12.3 and 13.1 of the Conditions of Contract, although interesting, is not relevant in the introduction of Variations on this project, particularly as sub-clause 3.1 has been amended by the quoted specific conditions above.
We would point out that although the amendment is impractical it is a significant revision to both Clause 12 and 13 of the Conditions of Contract. In practise it means that no Variation arising from additional work or by design change can commence prior to receiving the agreement of the Employer.
In conclusion, the purpose of our letter dated 23 November 2007 on this subject matter was to bring these special circumstances to your attention.
A further notice was issued on XX relating to the instruction to suspend the works:
Please refer to your letter dated 23 November 2007 referenced E-01-23.11.07 to which we wish to clarify this situation with regards to the cause for suspension of works.
First, the suspension of the Works, other than the two Mock-up villas occurred between 29 August 2007 and 29 November 2007. The reason for your suspension relies on work covered prior to inspection, but not with our site organisation. We have covered this aspect in our previous letter and pointed out remedies in the Contract available to the Engineer in these situations.
Secondly, although it was suggested in our email dated 28 August 2007 that concrete work would stop, in reality it did not and work continued until your instruction to suspend Works on 29 August 2007. This is all a matter of record and should be common ground.
Consequently, we disagree with contentions raised in your letter and reiterate our entitlement to extensions of time and additional payment arising from your instructions.
page 50
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
A notice was issued in regards to several of the delaying events on XX
We acknowledge receipt of your letter dated 23 November 2007 referenced E-07-23.11.07 regarding records of meeting No. 27 held on 9 November 2007. We disagree with your position on the 3 points for the following reasons:
Point 3 – minute 6.2: It is impossible for the Project Manager to have knowledge of the Contractor’s management and manpower with respect to their ability to handle the complete site. This is complete conjecture and only the Contractor can have that knowledge. In any event, it is not a contractual provision to suspend work based upon the Project Manager’s perceived knowledge of the Contractor’s planning and operations. Even if this is your reason for suspension the provisions of sub-clause 8.9 remain relevant.
The facts are recorded in our letter dated 29 October 2007 where reasons for suspension were indeed because work was covered up prior to inspection and approval. Once again, if this is your remedy in these circumstances, then the same provisions at sub-clause 8.9 are relevant.
Point 4 – minute 6.2: We have recorded severally delays caused by setting-out, increased scope of work for normal excavation, rock excavation and fixing steel reinforcement, shuttering and volume of concrete. The combination of these issues had caused a delay to progress at the time of this meeting (which is in the same period the works were suspended) by at least 3 weeks.
Normally, the Project Manager would give notice to the Contractor in accordance with sub-clause 8.3 which last paragraph, states:
If, at any time, the Engineer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor’s stated intentions, the Contractor shall submit a revised programme to the Engineer in accordance with this Sub-Clause.
This revised programme is issued in accordance with the provisions of sub-clause 8.6, which states:
If, at any time:
page 51
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
(a) actual progress is too slow to complete within the Time for Completion, and/or
(b) progress has fallen (or will fall) behind the current programme under Sub-Clause8.3 [Programme],other than as a result of a cause listed in Sub-Clause 8.4 [Extension of Time for Completion], then the Engineer may instruct the Contractor to submit, under Sub-Clause 8.3 [Programme], a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion. (Emphasis added)
Unless the Engineer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor’s Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7 below.
Please confirm if you intend to give a notice in accordance with this sub-clause? If that does remain your intention, then we must draw your attention to sub-clause 8.4, to paragraphs (a) and (b).
In the alternative, we confirm having issued a compliant notice in accordance with sub-clause 8.4 and provision of claims under sub-clause 20.1.
In conclusion, as we are not responsible for the delay and disruption to date, and the extended time to completion at 8 December 2007, we will not adopt any acceleration measures to recover earlier delays unless and until instructed.
At the request of the Project Manager a second revised programme of works was issued on 14 March 2008. In this notice the Contractor clearly indicated the various delays effecting impacting progress:
In accordance with your recent request in the weekly progress meetings, please find attached revised programme of works for your consent.
page 52
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The revised programme takes into consideration the various events and changed circumstances since commencement up to 29 February 2008.
These events and changed circumstances, as separately notified to you and further illustrated in our situation report dated 29 February 2009, have caused the original planned timing and sequence of works to vary. They include the following;
Unforeseen hard rock excavation including spoiling;
Suspension of works, except for the mock up villas, for two months and associated acceleration measures;
Instructed design variations, e.g. exchange of galvanised steel with stainless steel components for installation in the roof resulting into delays in procurement;
Late Instructions, e.g. several changes to the location, position and orientation of buildings by revision in the setting out details have delayed and disrupted the works;
Late Design Information resulting into delays in procurement thus preventing timely arrival of materials at site;
Increased scope of works occasioned by unforeseen site conditions and instructed additional works;
Inclement weather condition; unexpected high amounts of rainfall currently being experienced at site is slowing down progress of works.
The overall effect of all the above has been to delay the completion date for the works up to 24 March 2009 as indicated in the attached revised programme.
We therefore request extension of time to completion of the works.
The Contractor wrote again on 21 April 2008 with a notice stating the events that delayed progress:
page 53
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Reference is made to your letter dated 7 April 2008, E17-07.04.2008 to which this letter relates.
The purpose of this letter is to seek approval to accelerate progress to Completion in solution to recovery of earlier delays experienced which is made without prejudice to our current contractual position.
Progress To Date and Causes of Delay
We have written on several occasions about various events that caused delay and disruption to the regular progress of the work since the outset of this Contract. Some of these events and changed circumstances are described below and are significant by either their impact on time to completion or cost or both:
Late Design Information
Both survey data and final construction design are being issued late and this has naturally caused delay. As example, drawings for construction are required at commencement in order to allow procurement; however, drawings are still being issued or remain outstanding 12 months after commencement. The lateness of such information prevents rapid conclusion and timely arrival of materials at Site.
The Contractor also records he has not received any structural drawings that must in the first instant, be approved by the Ministry of National Development.
A further complication arises from having two structural engineers engaged to design different parts of the Contract. This has led to disruption in the design process.
Provisional Sums
Almost 30% of the Contract Price is derived from lump sum provisions for works not sufficiently detailed or identified at time of tender. The subsequent introduction of these works requires an instruction in accordance with the conditions stated in the Contract. As such, they are not works necessarily envisaged as forming part of the Works until and unless the Project Manager issues an instruction.
A further complication is that for these particular works neither detailed bill of quantities exists nor design drawings, although almost 12-months of the Contract period have elapse. In practise the Quantity Surveyor
page 54
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
should have prepared these Bills for submission to the Contractor to enable pricing and material procurement. As a result, their value is not defined and detailed programming is not possible and that indicates the Contract Price and the time of Completion must change.
Material Procurement
In the absence of complete design information procurement has not proceeded as planned. Delays in procurement will undoubtedly cause delay to completion. In addition, prices quoted at tender stage cannot be secured because orders are confirmed much later than planned.
Suspension of work
The Works were suspended in the period from 29 August 2007 through to 29 October 2007 as recorded in minutes of monthly meeting No 27 held 9 November 2007. The reason for this suspension by the Project Manager relies on work covered-up before inspection (at one villa column base).
The Conditions of Contract contain provisions for breaking out and exposing work and this would have been the sensible solution, not suspension. As to progress, it is evident from the photographs taken of the site at that date excellent progress was being made at several locations. The impact of 2 months suspension has had on progress was significant.
Re-measurement Contract vis-à-vis Fixed Lump Sum
The Conditions of Contract adopted on this project is a standard form and allows re-measurement however, all Clauses that allow Variations have not been revised or amended as one would expect in order to suit a Fixed Lump Sum Contract.
In addition, the Letter of Acceptance states that:
“the lump sum contract price shall not be amended unless specifically agreed with the Employer and the Quantity Surveyor. No additional work (beyond the scope of the lump sum Contract Price) may be commenced prior to reaching agreement on the price thereof.” [Emphasis added]
It further states that:
page 55
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
“Any changes in the design, which affect the lump sum Contract Price, must be specifically agreed by the Employer.”
Clearly, any alteration to the scope of work, introduction of additional work or design change, is very likely to influence a change in the Contract Price and the time to Completion. On this contract three areas of change will cause the Contract Price to vary and the time to Completion to extend, namely:
Variations to Scope of Works
Changes in the scope of work do arise by virtue of drawings issued for construction that automatically increase quantities shown in the Bills of Quantities. This is for two reasons; a) the correlation between substructure design and actual ground conditions are at variance, and b) a general enhancement of the reinforced concrete structure designed.
Flowing from variations generally introduced by final design drawings or drawings issued for construction, the scope of work has increased considerably, as example:
A significant increase in excavation of hard rock for which a small provision was made in the Contract;
A significant increase in the quantity of normal excavation to that indicated in the Contract, which is dictated by the topographic site conditions;
A significant increase in volume of reinforced concrete placed to that indicated in the Contract;
A significant increase in associated temporary works such as shuttering to that indicated in the Contract; and
A significant increase in steel reinforcement to that indicated in the Contract.
All these changes are not within the control of the Contractor, they are instructed Variations and naturally have time and cost considerations.
Instructed Design Variations
Mainly changes brought by a) interior design requirements, and b) because of superstructure variations. Once again, these variations are not within the control of the Contractor, they are instructed Variations.
page 56
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
One example of a design change relates to the exchange of galvanised steel with stainless steel components for installation in the roof. Notwithstanding the delay in making procurement of this specialist item, the additional cost is significant.
Lump Sums
The values of many of the structures included in the Contract Price are based on a square-metre rate in the absence of a detailed bill of quantity. As design drawings are now issued (September 2007) these works need to be measured and valued. The outcome of this evaluation will undoubtedly cause the Contract Price to vary. In addition, the time required to complete these structures can only be evaluated once detailed design drawings are made available. At that juncture, the details of these structures can be introduced in the programme of works.
Other Factors Impacting Progress
Although the following issues were known and considered at time of tender and therefore, allowed in our programme of works, they clearly have an influence on progress. They are mentioned here because with the prevailing delays described in Points 1 and 2 above, their very existence compounds a situation that is already impacting progress.
Tidal Movement
Each and every day/month typical low-tide conditions exist that prevent movement of vessels delivering material to Long Island. This is not a situation that can change and such time considerations are incorporated in the programme of works. The situation is compounded as the immediate area to Long Island is a protected Marine Park.
Transport of Materials to Long Island
All materials are brought by sea via one large barge in deep water which off-loads to two small barges at shallower water. At times it is not uncommon for a barge to suffer mechanical failure and there is possibility of disruption in the material supply. There are no other methods available that allows bulk supply of materials to the island, so although these difficulties are present all efforts are made to ensure these operations are limited.
Procurement of Local Raw Materials
page 57
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The level of construction in the Seychelles is quite substantial and demands for natural quarry materials places a considerable strain on the local supplier. The supply of quarry materials in the Seychelles are a monopoly and alternate sources are not available. Occasionally, a quarry product is in short supply, usually because of demand, and this will cause disruption in placement of concrete at site.
Wet Weather Conditions
The weather patterns are fairly regular and wet seasons can cause considerable difficulty at site, particularly prior to establishment of all-weather access roads. Once again, this is not a situation that can change and such time considerations are incorporated in the programme of works.
Suspension of Quarry Operations
In parallel with wet weather seasons all quarry operations do not function, particularly when rainfall is persistent over several days. As a consequence quarry products such as dust and aggregates and composite items as concrete blocks are not produced which interrupts the regular supply to Site.
Financial Considerations
The events and changed circumstances described in the foregoing have directly impacted the Contractor’s income which, together with Advance repayments has caused a negative cash flow.
Reduced Income
Regular progress of the works has been reduced significantly because of the delays occasioned by Variations, additional works and suspension of the whole Site (except the two mock-up villas). As a consequence, the value of work performed is significantly lower than anticipated and as indicated on the original cash flow chart. Therefore, costs are constantly greater than income derived for work performed.
Also, during these periods of delay and disruption direct and indirect costs are not fully recovered because planned progress has not been achieved. In addition, and as a result of a continuous shortfall in income, the value of the Advance to the Contractor has diminished at a rate
page 58
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
greater than anticipated as it’s been consumed in loss and expense.
Repayment of Advance Loan
The repayment of the Advance is directly linked to projected income which is derived from the programme of works. However, because progress has not been achieved income is considerably lower and the time for completion has extended. As a result, the monthly value of repayment has to be adjusted in light of the change in income flowing from an extended time to completion.
Proposed Remedy
The revised programme of works issued under cover of our letter dated 14 March 2008 shows a revised completion date of 24 March 2009. This is the date substantial completion can be achieved and is based on two important criteria; a) an adjustment to the value and period of the initial Advance repayment and, b) the payment of a second Advance.
The programme considers delays experienced to date, which principally is the setting out, excavation in hard rock, delays in receipt of detailed design drawings and delayed arrival of major material components to site.
It is anticipated that with the measures to recover earlier delays explained below, this continuing delays will be halted and in some respects, time will be recovered.
For reasons provided in the foregoing, this situation with respect to cash flow is not sustainable. In order to rapidly and affectively halt escalation of this situation the Contractor proposes the following solutions:
Adjusting Repayment of Advance
The cash flow estimate has been adjusted once to date to meet changed circumstances on site and this must be done again. The monthly value and period of repayment will need to be aligned with the revised durations shown on the programme of works. A proposed revised recovery on this Advance is shown in the table below:
page 59
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Cert. No. Month AdvancePayment Certified AdvanceRepayment
Advance May-07 3,100,000.00 1 Jun-07 682,032.852 Jul-07 351,989.15 200,000.00 3 Aug-07 145,803.63 200,000.00 4 Sep-07 357,556.62 200,000.00
Oct-07 0.00 357,142.86 5 Nov-07 478,926.03 214,285.71 6 Dec-07 0.00 214,285.71
Jan-08 0.00 214,285.71 7 Feb-08 1,276,534.91 100,000.00 8 Mar-08 1,276,534.91 100,000.00 9 Apr-08 1,276,534.91 100,000.00
10 May-08 1,276,534.91 100,000.00 11 Jun-08 1,276,534.91 100,000.00 12 Jul-08 1,276,534.91 100,000.00 13 Aug-08 1,276,534.91 100,000.00 14 Sep-08 1,276,534.91 100,000.00 15 Oct-08 1,276,534.91 100,000.00 16 Nov-08 1,276,534.91 100,000.00 17 Dec-08 1,276,534.91 100,000.00 18 Jan-09 1,276,534.91 100,000.00 13 Feb-09 1,276,534.91 100,000.00 14 Mar-09 1,276,534.91 100,000.00 15 Apr-09 1,276,534.91 100,000.01 16 May-09 1,276,534.9117 Jun-09 1,276,534.9118 Jul-09 1,276,534.9117 Aug-09 1,276,534.9118 Sep-09 1,276,534.9113 Oct-09 1,276,534.9114 Nov-09 1,276,534.91
Total 3,100,000.00 30,100,076.26 3,100,000.00
Measures to Recover Earlier Delays
To facilitate measures to accelerate progress the Contractor will enhance existing resources. This will involve bringing to site additional equipment and staff and labour resource over and above that planned at tender.
The table below lists planned additional staff and labour and equipment that will be deployed at Site. It also includes the delay and disruption costs arising during the 2-month period of suspension.
page 60
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Designation Value UD$ Amount
Staff and Labour
1 Senior Project Manager 168,630.002 Quality Assurance Manager 168,630.003 Senior Quantity Surveyor 107,250.004 Assistant Quantity Surveyor 99,000.005 Expatriate Workers 880,000.00 1,423,510.00
Equipment
1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00
Delay and Disruption Costs 565,714.29
Total additonal resources 2,524,415.29
In recognition of the additional cost flowing from deploying additional resources and loss and expense suffered during periods of delay and disruption, the Contractor requests reimbursement of a portion of these direct costs. These have been established in the above table and amounts to US$2,524,415.29. The Contractor asks payment in nine (9) equal interim Certificates starting from April 200 with the last in December 2008.
Second Secured Advance Payment
The major and immediate expense typically flows from material and equipment procurement. A subsidiary of that is increased staff and labour over and above that originally planned.
The first component, materials, is the critical element to achieving sustained progress and once 80% has been secured and delivered at Site, a major obstacle is overcome. This is particularly significant with respect to the geographic location of the Seychelles and the difficulties this presents for material procurement.
Material not ordered is either because design details have not been availed or that Bills of Quantities and respective designs flowing from Provisional Sums is still in abeyance.
page 61
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The second component, equipment, dictates the methods and pace at which the works proceed. In other words, by increasing the number of certain pieces of equipment and by changing methods, progress can be improved significantly.
The last element considered is staff and labour, the major change will be deployment of two European Site Agents well experienced in this type of work. In addition, we will deploy further expatriates of all trades in order to meet the demands of a revised programme of works, which we will submit shortly.
As shown in the impacted programme issued 14 March 2008, because of earlier delays many operations have been delayed, therefore, commencement of most buildings have been compressed on the original programme of works. This means that site operations are not working sequentially but simultaneously and this is a major planning problem existing today. Consequently, all these resources will allow expansion of operations to many areas of site allowing work to proceed simultaneously and therefore achieve earliest completion.
To meet additional and immediate costs in this recovery program and to meet the changed circumstances, the Contractor requires a minimum Advance payment amounting to US$3,500,000.00. The proposed recovery on this Advance is shown in the table below:
Month Value Repaid
May-08 250,000.00Jun-08 250,000.00Jul-08 250,000.00Aug-08 300,000.00Sep-08 300,000.00Oct-08 350,000.00Nov-08 400,000.00Dec-08 550,000.00Jan-09 400,000.00Feb-09 450,000.00
Total 3,500,000.00
The next table is the projected combined recovery on both Advance payments:
page 62
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month FirstAdvance SecondAdvance Combined
May-07 0.00 0.00Jun-07 0.00 0.00Jul-07 200,000.00 0.00 200,000.00
Aug-07 200,000.00 0.00 200,000.00Sep-07 200,000.00 0.00 200,000.00Oct-07 357,142.86 0.00 357,142.86Nov-07 214,285.71 0.00 214,285.71Dec-07 214,285.71 0.00 214,285.71Jan-08 214,285.71 0.00 214,285.71Feb-08 100,000.00 0.00 100,000.00Mar-08 100,000.00 0.00 100,000.00Apr-08 100,000.00 0.00 100,000.00
May-08 100,000.00 250,000.00 350,000.00Jun-08 100,000.00 250,000.00 350,000.00Jul-08 100,000.00 250,000.00 350,000.00
Aug-08 100,000.00 300,000.00 400,000.00Sep-08 100,000.00 300,000.00 400,000.00Oct-08 100,000.00 350,000.00 450,000.00Nov-08 100,000.00 400,000.00 500,000.00Dec-08 100,000.00 550,000.00 650,000.00Jan-09 100,000.00 400,000.00 500,000.00Feb-09 100,000.00 450,000.00 550,000.00Mar-09 100,000.00 100,000.00Apr-09 100,000.01 100,000.01
Total 3,100,000.00 3,500,000.00 6,600,000.00
The revised Organisation Chart is attached to which has been added the additional management staff. Evidence of projected expenditure for staff, labour and materials is provided in the table below and is likely to exceed US$5 million.
page 63
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Designation Value UD$ Amount
Staff and Labour (one month)
1 Senior Project Manager 15,330.002 Quality Assurance Manager 15,330.003 Senior Quantity Surveyor 9,750.004 Assistant Quantity Surveyor 9,000.005 Expatriate Workers 80,000.00 129,410.00
Equipment
1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00
Materials
1 Balau timber (special size) 1,764,705.882 Stainless steel roof components 2,559,900.003 Shingles 333,600.00 4,658,205.88
Total Second Advance 5,322,806.88
Conclusion
It is evident from the foregoing the considerable difficulties encountered on this project since the outset are not the responsibility of the Contractor.
The majority of changes and consequent difficulties exist because a significant portion of design was not developed at tender. Of worthy note, after expiry of almost 12 months of the Contract period close to 30% of the scope of works has not been identified through detailed Bills of Quantities; an essential requirement outwith prevents material procurement and disrupts planning.
Recent suggestions to engage other contractors to perform portions of the scope of works will have little effect because constraints imposed by operational logistics and design development are unlikely to diminish.
Consequently, with the valuable knowledge and experience gained it is our considered opinion drastic measures must be implemented by both the Contractor and Employer’s design teams. The respective responsibility of each party is important and the
page 64
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Contractor has in this letter, set-out under paragraph 5 above, what he feels is required to bring this project to earliest completion.
First, the Contractor looks forward to receiving proposals from the Employer’s design team indicating what measures will be taken to address outstanding design issues. Secondly, the scope of works must be defined in order to establish the revised Contract Price outwith the Contract Completion date will remain at large.
Finally, payment of the Contractor’s acceleration costs and the Second Secured Advance is of paramount importance in the measures required to conclude this Contract thus allowing a reduction of the Contractor’s extended costs and indeed, the Employer’s losses.
We look forward to receiving approval in principle of the foregoing and subsequent instructions.
Accordingly, the Contractor is entitled to receive, under Sub-Clause 20.1, extensions of time and additional payment as described under Sub-Clause 8.4, 1.9 and 2.1 of the Contract Conditions.
4.2. Late and Inaccurate Survey Data
The completeness, accuracy and timely issue of survey information remain the responsibility of the Project Manager. Sub-clause 4.7 of the Contract Conditions is clear on this subject and it should be common ground as to the consequences of the Contractor being provided information inconsistent with design and site conditions.
The table below provides dates when setting-out was performed and reasons why for many the exercise was repeated. In most instances it was because the position and orientation were varied to suit site conditions.
Villa
Baseline Programme Setting Out Finish date Initial Setting Out Revised Setting Out
Delays due to Changes in Setting Out Details & Orientation (days)
A3/30 29-Mar-07 25-Apr-07 26-Jun-07 62.00A3/20 13-Apr-07 25-Apr-07 20-Jul-07 86.00A3/11 10-Apr-07 25-Apr-07 03-Jun-07 39.00A3/07 03-Apr-07 25-Apr-07 04-Jun-07 40.00
It can be seen in the table above critical delays occurred at four villas of between 40 and 86 calendar days. These delays are considered and included in the extension of time request.
page 65
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
4.3. Late Receipt of Final Design Information
In addition to receiving design information late, the Contractor has had the inconvenience and time-consuming problem of dealing with design drawings issued that are either late or are revised.
Structure/Villa
Commencement Completion
Drwgs Required 120 days prior POW Start Date Structural Architectural Delay (Days)
A3 Pool Villa 02-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00B223 Standard Villa 28-May-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00B4 Standard Villa with Pool 16-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00C311 Executive Villas 12-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00P3 Presidential Villas 20-Jun-07 20-Mar-08 28-Feb-07 19-Oct-07 09-Mar-07 233.00Sunset Deck 23-Jul-07 14-Mar-08 25-Mar-07 09-Apr-08 22-Aug-07 381.00Employees Facilities Complex 14-Jun-07 19-Mar-08 28-Feb-07 31-Aug-07 22-Aug-07 92.00Excom Villa 14-Jun-07 17-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00GM Villa 14-Jun-07 15-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00Health club 14-Jun-07 15-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00Single Treatment room 02-Jul-07 17-Mar-08 04-Mar-07 10-Jun-07 28-May-07 98.00Couple treatment room 02-Jul-07 19-Mar-08 04-Mar-07 25-Jun-07 28-May-07 113.00Sanctum 02-Jul-07 15-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00Yoga Pavilion 02-Jul-07 14-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00BOH Building 02-Jul-07 17-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00Wedding chapel 02-Jul-07 14-Mar-08 04-Mar-07 09-Apr-08 28-May-07 402.00Seafood Resort 18-Jun-07 19-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00Retail Pavilion 18-Jun-07 14-Mar-08 28-Feb-07 11/06/2007 28-May-07 103.00Kid's club 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Recreation House 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Water sport Rental 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Dive Center 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00Mechanical Area 22-Oct-07 09-Apr-08 24-Jun-07 Not Received Yet 08-Jan-08 326.003 Meal Restaurant 02-Jul-07 26-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00Signature Pool 02-Jul-07 15-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00Beach Pool Bar 02-Jul-07 17-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00
Drawing Receipt ScheduleBaseline Programme
The table above shows the timing of receipt of design drawings and is evidence of continuing delays. In some instances structural drawings are still outstanding where in others they have been issued late by between 14 and 438 calendar days.
Due to the lateness in receipt of design drawings, not only construction delayed but also procurement. Delays in procurement cause the Contractor to incur greater costs because prices secured at tender either expired or prices in the period increased.
4.4. Additional and Varied Work
4.4.1.Excavation in Hard Rock
Due to the nature of the ground and the topography of the Site, it was important to adhere to the Contractor’s original planning in terms of construction sequence.
Furthermore, the scope of this work was restricted to a) the numbers of buildings identified at tender stage and, b) the position of the buildings. Obviously, with a major part of the
page 66
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Contract Price falling under Provisional Sums, both these factors had to change and, with that change (Variation), brought a number of unforeseen difficulties.
One such consequent change involved significant increase in excavation in hard rock. Furthermore, the change in timing and sequence exacerbated the difficulty in extraction and the method in which the work could be performed.
4.4.1.1. Change in Sequence and Increased Cost
Although the sequence change was caused by survey work, rock excavation and more specifically the suspension of Works, work at each site then became in variance to the contractor’s original planning, the conversion and expenditure of Provisional sums exacerbated its impact.
4.4.1.2. Increased Quantity
In addition to the complications of performing controlled blasting, the quantity of rock excavated to date has increased between 20% and over 300% to that anticipated. In these conditions the Contractor has entitlement to the additional time to perform these varied works.
The following tables are recorded evidence of the significant increased volume of rock excavation found at almost every villa site. The tender provision was clearly too low and that has been reflected in the Contractor’s planning.
As example, the first table below illustrates the quantities of rock excavated using blasting methods otherwise not foreseen. At villa B2/01 the volume of hard rock excavated has already reached close to 240m3 whereas the allowance in the Contract was zero. The time taken to remove this rock to date, as it is not finished, is already close to 200 calendar days. Consequently, the duration taken for this activity at this villa is already 200 calendar days and delay is considered critical.
The following table lists volume of rock excavated at each villa which, as stated above, is all unforeseen. As such at each villa the delay caused in performing this activity is critical and prevents commenced of subsequent dependant activities.
page 67
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa Rock Blasting (m3) Increase
A3/02 95.00 100%A3/03 97.85 100%A3/04 23.00 100%A3/05 1.14 100%A3/06 12.69 100%A3/08 11.41 100%A3/09 54.50 100%A3/10 171.68 100%A3/11 139.00 100%A3/19 47.97 100%A3/20 65.10 100%A3/21 42.13 100%A3/28 4.17 100%A3/29 4.18 100%A3/31 2.31 100%B2/01 239.14 100%B2/04 147.55 100%B2/05 13.87 100%B2/06 48.40 100%B2/07 7.73 100%B2/08 5.04 100%B2/09 28.50 100%B2/10 52.50 100%
The next table provides a summary of volumes of hard rock excavated at the various sites. Once again it is apparent that the tender provision represents only between 8% and 55% of the actual quantity excavated. Once again with such a significant change it is obvious removing over 60m3 of rock takes significantly longer than 5m3.
Villa Rock Exc without blasting BOQ quantity Change
A3/01 9.05 5.00 81%A3/03 8.75 5.00 75%A3/04 18.75 5.00 275%A3/05 22.50 5.00 350%A3/06 19.50 5.00 290%A3/08 25.88 5.00 418%B2/01 60.62 5.00 1112%B2/02 64.28 5.00 1186%B2/04 60.45 5.00 1109%B2/07 4.74 5.00 -5%
The next table summarises excavated material volumes in common material. It can be seen volumes have increased significantly
page 68
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa Exc other than rock BOQ quantity Change
A3/04 124.54 38.00 228%A3/05 141.12 38.00 271%A3/09 37.81 38.00 0%A3/30 112.02 38.00 195%A3/31 122.80 38.00 223%A3/32 75.82 38.00 100%B2/01 191.68 70.00 174%B2/02 345.02 70.00 393%B2/03 383.36 70.00 448%B2/04 230.02 70.00 229%B2/05 191.68 70.00 174%B2/06 191.68 70.00 174%B2/07 345.02 70.00 393%B2/08 191.68 70.00 174%
The next table consolidates all the changed quantities of all materials excavated at each villa. Comparing anticipated durations based on bills of quantities and actual, it can be seen in the extreme right hand column the significant variance in time.
The durations shown which range from 26 to 354 calendar days are considered critical, as all subsequent activities that follow excavation are equally delayed.
Villa Rock Blasting (m3)Rock Excavation without
Blasting (m3)Excavation, other than
rock (m3)Duration Taken To Date (Days)
Baseline Duration based on BQ quantities (Days) Critical Delay
Commencement Completion A3/01 9.05 15 October 2007 25 December 2007 71.00 3.00 68.00A3/02 95.00 20 December 2007 on progress 90% 147.00 3.00 144.00A3/03 97.85 8.75 11 September 2007 on progress 95% 247.00 3.58 243.42A3/04 23.00 18.75 124.54 04 June 2007 22 July 2007 48.00 2.00 46.00A3/05 1.14 22.50 141.12 07 June 2007 25 July 2007 48.00 2.63 45.38A3/06 12.69 19.50 09 June 2007 18 December 2007 192.00 2.08 189.92A3/08 11.41 25.88 05 May 2007 16 January 2008 256.00 1.04 254.96A3/09 54.50 37.81 01 January 2008 on progress 90% 135.00 1.04 133.96A3/10 171.68 16 April 2007 15 August 2007 121.00 1.04 119.96A3/11 139.00 14 June 2007 on progress 40% 336.00 1.04 334.96A3/19 47.97 15 June 2007 on progress 20% 335.00 1.04 333.96A3/20 65.10 19 November 2007 on progress 45% 178.00 1.04 176.96A3/21 42.13 14 June 2007 on progress 45% 336.00 1.04 334.96A3/26 120.00 18 April 2007 05 March 2008 322.00 322.00A3/27 125.00 27 August 2007 28 November 2007 93.00 93.00A3/28 4.17 25 June 2007 22 November 2007 150.00 2.08 147.92A3/29 4.18 23 June 2007 10 August 2007 48.00 2.08 45.92A3/30 112.02 04 June 2007 23 July 2007 49.00 2.00 47.00A3/31 2.31 122.80 09 June 2007 24 July 2007 45.00 2.08 42.92A3/32 75.82 04 June 2007 02 July 2007 28.00 2.00 26.00B2/01 239.14 60.62 191.68 20 October 2007 on progress 50% 208.00 1.04 206.96B2/02 64.28 345.02 09 July 2007 18 November 2007 132.00 1.04 130.96B2/03 383.36 11 June 2007 24 July 2007 43.00 1.00 42.00B2/04 147.55 60.45 230.02 11 May 2007 06 March 2008 300.00 1.04 298.96B2/05 13.87 191.68 25 May 2007 on progress 95% 356.00 1.04 354.96B2/06 48.40 191.68 03 December 2007 on progress 65% 164.00 1.04 162.96B2/07 7.73 4.74 345.02 27 May 2007 20 November 2007 177.00 1.04 175.96B2/08 5.04 191.68 24 December 2007 on progress 65% 143.00 1.04 141.96B2/09 28.50 21 November 2007 on progress 75% 176.00 1.04 174.96B2/10 52.50 15 November 2007 on progress 75% 182.00 1.04 180.96
Actual excavation schedule
Note: it has not been possible to separate the delays resulting from blasting and those arising out of increased quantities of other excavated materials. The works are executed at the same time. The table above therefore shows the combined delays arising from the above 3 changed events.
page 69
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
4.4.2.Increased Quantity in Reinforced Concrete
The two examples below show changes in scope to standard villa, A3 and B2. The increase in quantities indicated relate to these two villas only. However, the Contract includes a further 32 number of type A and 10 number of Type B and the same change in scope is applicable to all villas. As a consequence, an equal or similar additional time will be required to perform the changed scope of work.
4.4.2.1. Villa Type A3 (Example)
Steel reinforcement, shuttering and the concrete volume has increased considerably and the example below is for one villa only. As detailed in the table, the duration to perform these works has extended from 12 calendar days as planned to 45 calendar days. Once again, the additional time is critical and has delayed dependant and subsequent activities shown on the programme of works.
Villa Type Item Unit Tender Quantity Design Quantities
A3 Frame Reinforcement kg 3,040.00 5,130.00
Concrete m3 32.00 43.00Formwork m2 305.85 351.00
Baseline duration for Tender Quantity 12 Days Actual Duration due to increased quantity 45 Days
The following table compares the planned and actual durations for completing various other concrete components of the building structure.
A3 Type Frame Baseline Duration Revised Duration
set kickers 1.00 2.00Conc. Columns & shear walls 2.00 11.00Conc. G. F Beams 2.00 6.00Conc. Plantroom 2.00 5.00Conc. Floor slab & swimming pool base 2.00 10.00Blockwork 2.00 9.00Conc. Swimming pool sides & overflow channels 3.00 7.00Conc. Ring & tie beams 2.00 7.00
page 70
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
4.4.2.2. Villa Type B2 (Example)
Villa Type Item Unit Tender Quantity Design Quantities
B2 FrameReinforcement kg 5,826.00 9,645.00Concrete m3 84.00 102.00Formwork m2 727.00 730.00
Baseline duration based on Tender Quantity 70 Days Actual Duration due to increased quantity 80 Days
B2 Type Frame Baseline Duration Revised Duration
set kickers 1.00 2.00Conc. Columns & shear walls to GF 8.00 6.00Conc. Plantrooms 6.00 8.00Conc. GF slab and beams 4.00 10.00Blockwork up to FF slab 7.00 6.00set kickers on GF 1.00 2.00Conc. Columns & shear walls to FF 8.00 8.00Conc. FF slab & beams 8.00 10.00Blockwork up to roof 7.00 6.00set kickers on FF 1.00 2.00Conc. Columns & shear walls to roof 8.00 8.00Conc. Ring & tie beams 7.00 7.00
In the circumstances, these variations dictate significant divergence from original designs. Therefore, in order to comply with these variations the Contractor’s construction duration for this activity has increased significantly, from an estimated 17 days (substructure) to 37 days for column construction, an increase of 22 working days for each villa.
4.4.3.Suspension of Works
The Contractor was instructed to suspend the works, which suspension lasted 61 days and directly effected progress of the villas listed. This period of suspension is considered a critical delay.
The following table summarises the delay at each villa in progress at the time of the instruction to suspend. However, it should be noted that the effect of this instruction is to delay all the Works on the whole project (except mock-up villas for this particular event).
page 71
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa Works Suspended From To Delay (Days)A3/03 Excavation 29-Aug-07 29-Oct-07 61.00A3/04 Concrete foundation 29-Aug-07 29-Oct-07 61.00A3/05 Concrete foundation 29-Aug-07 29-Oct-07 61.00A3/06 Excavation 29-Aug-07 29-Oct-07 61.00A3/08 Excavation 29-Aug-07 29-Oct-07 61.00A3/10 Concrete casting for foundation 29-Aug-07 29-Oct-07 61.00A3/27 Excavation 29-Aug-07 29-Oct-07 61.00A3/28 Excavation 29-Aug-07 29-Oct-07 61.00A3/29 Concrete works 29-Aug-07 29-Oct-07 61.00A3/30 Blinding 29-Aug-07 29-Oct-07 61.00A3/31 Blinding 29-Aug-07 29-Oct-07 61.00B2/02 Excavation 29-Aug-07 29-Oct-07 61.00
4.4.4.Variations to Design
The design drawings issued for construction show all steel roof members as stainless steel although the bill of quantities, as priced at tender, show galvanised steel. As a result the sourcing and procurement time consumed an additional 81 calendar days. This delayed roof construction at the 2 Mock-up Villas and is considered a critical delay.
Description Commenced Completion Delay (Days)Procurement, Fabrication & Installation of Stainless Steel Plates to complete roof structure 26-Nov-07 15-Feb-08 81
4.5. Material Procurement Programme
A critical feature of this project is timely supply of materials to site as most are being sourced off-shore. The timely arrival of materials is an integral part of his planning and any delay in the design and procurement process will automatically have a detrimental impact on his programme of works.
The current situation relative major material procurement is shown in the table below:
page 72
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Des c ription of MaterialsQuantity Ordered Date Ordered Amount rec eived B alanc e C omments
F OR AL L 55 VIL L AS
50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order subject to payment to supplierP lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order subject to payment to supplierC rusher Dust 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order subject to payment to supplierAggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order subject to payment to supplierP las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order subject to payment to supplier150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order subject to payment to supplier100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order subject to payment to supplierA252 Weld Mesh (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order subject to payment to supplierHigh tens ile s teel-8,10,12,16,25mm (tons) 500.00 14/01/07 158.00 342.00 B alance on order subject to payment to supplierC edar S hingles (sqm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order subject to payment to supplierIroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order subject to payment to supplier12mm G ypsum boards (S HE E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.DS tainless s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order subject to payment to supplier (Not B .O .Q item)S tainless s teel gusset plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order subject to payment to supplier (Not B .O .Q item)B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order subject to payment to supplierT reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order subject to payment to supplier
The following table summarises the dates drawings have been received. It is clear many drawings were not issued at commencement and therefore, complete procurement of all major materials was not possible.
It is also clear that drawings have been issued progressively throughout the Contract period; again this is contrary to planning expectations. Finally, it is also clear the majority of Interior Design drawings have yet to be issued.
Item Structure/Villa Structural Architectural Interior Design
1 A3 Pool Villa 14-Mar-07 09-Mar-07 09-Apr-072 B223 Standard Villa 14-Mar-07 09-Mar-07 09-Apr-073 B4 Standard Villa with Pool 14-Mar-07 09-Mar-07 09-Apr-074 C311 Executive Villas 14-Mar-07 09-Mar-07 09-Apr-075 P3 Presidential Villas 19-Oct-07 09-Mar-07 09-Apr-076 Sunset Deck 09-Apr-08 22-Aug-07 Not received 7 Employees Facilities Complex 31-Aug-07 22-Aug-07 "8 Excom Villa 19-Oct-07 22-Aug-07 "9 GM Villa 19-Oct-07 22-Aug-07 "
10 Health club 11-Jun-07 28-May-07 "11 Single Treatment room 10-Jun-07 28-May-07 "12 Couple treatment room 25-Jun-07 28-May-07 "13 Sanctum 19-Oct-07 28-May-07 "14 Yoga Pavilion 19-Oct-07 28-May-07 "15 BOH Building 19-Oct-07 28-May-07 "16 Wedding chapel 09-Apr-08 28-May-07 "17 Seafood Resort 11-Jun-07 28-May-07 "18 Retail Pavilion 11-Jun-07 28-May-07 "19 Kid's club 20-Dec-07 08-Jan-08 "20 Recreation House 20-Dec-07 08-Jan-08 "21 Water sport Rental 20-Dec-07 08-Jan-08 "22 Dive Center 20-Dec-07 08-Jan-08 "23 Mechanical Area Not Received Yet 08-Jan-08 "24 3 Meal Restaurant Not Received Yet 08-Jan-08 "25 Signature Pool Not Received Yet 08-Jan-08 "26 Beach Pool Bar Not Received Yet 08-Jan-08 "
Drawing Receipt Register
page 73
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
For all the foregoing reasons stated above, the Contractor could not have progressed major material procurement because he was constrained by two issues:
First. Cash flow prevented completion of orders to allow shipment, and
Second. Design drawings were not available at the times consistent with his programme of works.
4.6. Conclusion of Effects of Variations
Additional work is, under the Contract provisions, is also caused by Provisional Sums converted to Variations under Clause 13, by comparison with the value of work envisaged at tender. Nevertheless, additional work executed to date is certain to affect progress because the scope of such variations has only been defined post tender.
The degree of change reflects the changed requirements of the Employer after the award of the project. Although the Contractor received instructions throughout the project to include work anticipated under the Provisional Sums, this has been compounded by the delaying events described even for known works defined at award.
With so many variations, it is not possible to make an attribution of the overall delay to each item. It is true to say that the earlier variations were critical to the Contractor’s progress, and that any delays caused by them are subsumed into the latter period.
However, the delays caused by the changes to the setting out and rock excavation together with suspension of Works, and to other areas of the Works as all the design information, as listed in the tables above, are evident and the primary cause for remaining on site longer.
All the issues described above generally run consecutively, despite late information relative design is continuing simultaneously together with rock excavation. The factual matrix of variation instructions and late information is one of interwoven facts and events. It is not possible to disconnect them. However, the latest programme of works is evidence that work to most of the buildings and villas is in progress at the time of compiling this claim.
page 74
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5. Time Analysis
5.1. Method of Analysis
As some of the effects of unforeseen events are concurrent, not all of them will carry an automatic extension of time entitlement. The purpose of the form of analysis described below is to demonstrate which events have contributed to the project over-run and the precise amount of time attributable to each event. At time of preparing this document a Second Request for an Extension of Time has been submitted.
Furthermore, additional costs have arisen as a result of various notified delay and disruption events. The loss and expense are recoverable as:
direct costs in the period when resources suffered delay and disruption, and
indirect costs that will arise in the extended period of the Contract.
The time analysis has been carried out in three stages for each claimable event:
1. At the date immediately prior to the event, the progress status of the project has been established from the progress records. The Programme of Works has been updated with this information, to give a project completion date that was likely to have been achieved if the delay had not occurred. This element of the analysis takes into account and eliminates any delays that might have occurred before the point in time in question, for which the Contractor might be responsible.
2. Next, the effect of the claimable event on the scheduled activities has been calculated. These effects have been inserted into the time scheduled and the network re-analysed. This gives a revised project completion date, assuming that the work proceeds in the same sequence and with the same resources as were originally planned. The difference between this completion date and the progress completion date is the extension of time for the event if it is not reasonably possible to achieve any mitigation of its delaying impact.
3. Finally, there is an obligation on a contractor to attempt to mitigate the effects of any delaying event, if it is reasonably feasible. Accordingly, such opportunities for
page 75
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
mitigation have been considered in the evaluation of extension of time entitlement.
Any mitigation measures that the Contractor took, such as additional resources, re-sequencing of work etc., has been detailed and inserted into the schedule. The re-analysis of this programme gives the final assessment of additional time that the Contractor is entitled to claim for the cause under consideration.
These three stages have been repeated for each of the events in turn and the results are reflected in the Contractor’s two requests made to date for an extension of time.
5.1.1.Mitigation by Contractor
The Contractor mitigated the effects of the late supply of design information by starting work on a particular activity without waiting for the whole of the design needed for a particular piece of work. This was particularly noticeable at the Mock-up villas where architectural details were constantly revised as works progressed. The success in taking this phase-advanced approach to work has not produced the results anticipated.
These mitigation measures will be shown in the Programme of Works analysis by changing the logic links between design activities and construction activities.
5.1.2.Time for Completion
It is shown in the subsequent sections of this submission the impact of the changed events and circumstances of the various parts of the Site has caused to the planned progress. In addition, the failure by the Project Manager to provide the necessary design details in due time and the subsequent alterations in mode and manner of execution has also caused the Contractor, because of these events, to be delayed to such an extent that completion of the Contract Works has been unavoidably prolonged and will extend the date set for its completion.
Accordingly, the Contractor is entitled to treat the date for completion as no longer being fixed. That is to say, he is entitled to be allowed such additional time for completion as is reasonably necessary for him to accommodate and deal with the
page 76
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Project Manager’s and Employer’s fault to discharge the remainder of his obligations.
5.1.3.Impact on Time - Analyses
The purpose of this exercise is to determine the overall delay to the contractual completion date as indicated in the approved base programme of works. The impacted programme of works will establish the contractor’s entitlement to a delayed completion date for the project. This can then be used to evaluate the financial loss incurred by the contractor and the amount of acceleration required in the event that the client requires the project to be completed earlier.
Events are impacted on the programme according to chronological order to determine the effect in the sequence that the delays took place. When the Event is impacted correctly only the activity is affected and those which are dependent on its completion are delayed. If this activity falls in the critical path of the project then the completion date of the project is also delayed. The critical path of a project may change due to delay in a particular set of activities.
5.1.4.The Events that Impacted Progress
There has been initial delay in receipt of final setting out details for various parts of the project without which it was not possible for the contractor to start construction of that relevant section of the works. Additionally it will be seen that unforeseen ground conditions, the partial suspension of Works caused severe disruption to the contractors planned sequence of execution of the works. Initial events impacted will show the effect that these delays had on the execution of the works.
Furthermore there has been a substantial change to the scope of works as originally anticipated as shown on drawings and what the Contractor encountered on site. A significant variance is attributed to unknown site conditions, as for example, quantity of rock excavated required achieving foundation depth.
The rest of the changes will be attributed to changes in original design other than depicted on tender drawings such as the increased quantities of reinforced concrete. Needless to say the extra volume requires more time to secure placement of steel reinforcement, timber shuttering and concrete placement to columns and slabs, hence more time being required to
page 77
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
completion of activity and an overall delay experienced on this section.
The overall effect of these delays and disruptions can be evidenced by a reduced cash flow, and by his current position on site with regards completion of the works. It can be clearly evidenced that not only has the contractor taken steps to mitigate the delays experienced he has also in his eagerness to recover lost time already taken acceleration measures into account and deployed extra resources over and above his planned and contractually required resources.
This exercise serves to establish the contractor’s entitlement to additional time for completion of the project and the cause and effect on his progress to date.
The order of the impacted charts that follow are in the sequence each event occurred at Site.
page 78
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.1. Event No 1 – Setting Out
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
184 Villa A3/01
228 Villa A3/02
273 Villa A3/03
318 Villa A3/04
363 Villa A3/05
408 Villa A3/06
453 C311 Executive Villas ( 1 nos)
454 Villa C3/01
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
849 Villa A3/07
850 substructure
851 set out
852 Excavate
853 Conc. Foundation
854 Backfill
855 termite treatment
856 DPC (where applicable)
857 M&E inlet/outlet works - first fix
858 frame
859 set kickers
860 Conc. Columns & shear walls
861 Conc. G. F Beams
862 M&E first fix
863 Conc. Plantroom
864 Conc. Floor slab & swimming pool base
865 Blockwork
866 Conc. Swimming pool sides & overflow channels
867 Conc. Ring & tie beams
868 Roof & Ceiling
869 Fix wall plate & truss
870 Fix purlins and rafters
871 Fix shingles ( subject to receipt of timber)
872 Fix ceiing battens & joists
873 Fix ceiling boards
874 M&E first fix
875 Finishes
876 Wall plaster (internal & External)
877 M&E 1st fix
878 Floor finishes
879 Fix windows & doors
880 Swimming pool finishes
881 M&E final fix
882 Fix fittings and Fixtures
883 M&E Installations
884 Cable Tray, Conduit and Wiring
885 Electrical boards and connections
886 Electrical accessories
887 Light fittings and ceiling fans
888 Hot and cold water
889 Waste and sewage incl. biobox
890 Electric water heater
891 Swimming pool
892 Split unit installation
893 Toilet ventilation, grilles
894 Villa A3/08
939 Villa A3/09
984 Villa A3/10( mock up)
1029 Villa A3/11
1030 substructure
1031 set out
1032 Excavate
1033 Conc. Foundation
1034 Backfill
1035 termite treatment
1036 DPC (where applicable)
1037 M&E inlet/outlet works - first fix
1038 frame
1039 set kickers
1040 Conc. Columns & shear walls
1041 Conc. G. F Beams
1042 M&E first fix
1043 Conc. Plantroom
1044 Conc. Floor slab & swimming pool base
1045 Blockwork
1046 Conc. Swimming pool sides & overflow channels
1047 Conc. Ring & tie beams
1048 Roof & Ceiling
1049 Fix wall plate & truss
1050 Fix purlins and rafters
1051 Fix shingles ( subject to receipt of timber)
1052 Fix ceiing battens & joists
1053 Fix ceiling boards
1054 M&E first fix
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008
page 79
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1055 Finishes
1056 Wall plaster (internal & External)
1057 M&E 1st fix
1058 Floor finishes
1059 Fix windows & doors
1060 Swimming pool finishes
1061 M&E final fix
1062 Fix fittings and Fixtures
1063 M&E Installations
1064 Cable Tray, Conduit and Wiring
1065 Electrical boards and connections
1066 Electrical accessories
1067 Light fittings and ceiling fans
1068 Hot and cold water
1069 Waste and sewage incl. biobox
1070 Electric water heater
1071 Swimming pool
1072 Split unit installation
1073 Toilet ventilation, grilles
1074 Villa A3/12
1119 Villa A3/13
1164 Villa A3/18
1209 Villa A3/19
1254 Villa A3/20
1255 substructure
1256 set out
1257 Excavate
1258 Conc. Foundation
1259 Backfill
1260 termite treatment
1261 DPC (where applicable)
1262 M&E inlet/outlet works - first fix
1263 frame
1264 set kickers
1265 Conc. Columns & shear walls
1266 Conc. G. F Beams
1267 M&E first fix
1268 Conc. Plantroom
1269 Conc. Floor slab & swimming pool base
1270 Blockwork
1271 Conc. Swimming pool sides & overflow channels
1272 Conc. Ring & tie beams
1273 Roof & Ceiling
1274 Fix wall plate & truss
1275 Fix purlins and rafters
1276 Fix shingles ( subject to receipt of timber)
1277 Fix ceiing battens & joists
1278 Fix ceiling boards
1279 M&E first fix
1280 Finishes
1281 Wall plaster (internal & External)
1282 M&E 1st fix
1283 Floor finishes
1284 Fix windows & doors
1285 Swimming pool finishes
1286 M&E final fix
1287 Fix fittings and Fixtures
1288 M&E Installations
1289 Cable Tray, Conduit and Wiring
1290 Electrical boards and connections
1291 Electrical accessories
1292 Light fittings and ceiling fans
1293 Hot and cold water
1294 Waste and sewage incl. biobox
1295 Electric water heater
1296 Swimming pool
1297 Split unit installation
1298 Toilet ventilation, grilles
1299 Villa A3/21
1344 Villa A3/22
1389 Villa A3/23
1434 Villa A3/24
1479 Villa A3/25
1524 Villa A3/26
1569 Villa A3/27
1614 B223 Villas ( 7 nos)
1615 Villa B2/01
1665 Villa B2/02
1715 Villa B2/04 (mock up villa)
1765 Villa B2/05
1815 Villa B2/06
1865 Villa B2/07
1915 Villa B2/08
1965 B4 Villa (2 nos.)
1966 Villa B4/01
2011 Villa B4/02
2056 Retail 1( subject to receipt of GFW drawings)
2094 Retail 2( subject to receipt of GFW drawings)
2132 Retail 3( subject to receipt of GFW drawings)
2170 Seafood resort( subject to receipt of GFW drawings)
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2264 Villa A3/14
2309 Villa A3/15
2354 Villa A3/16
2399 Villa A3/17
2444 Villa A3/28
2489 Villa A3/29
2534 Villa A3/30
2535 substructure
2536 set out
2537 Excavate
2538 Conc. Foundation
2539 Backfill
2540 termite treatment
2541 DPC (where applicable)
2542 M&E inlet/outlet works - first fix
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009
page 80
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2543 frame
2544 set kickers
2545 Conc. Columns & shear walls
2546 Conc. G. F Beams
2547 M&E first fix
2548 Conc. Plantroom
2549 Conc. Floor slab & swimming pool base
2550 Blockwork
2551 Conc. Swimming pool sides & overflow channels
2552 Conc. Ring & tie beams
2553 Roof & Ceiling
2554 Fix wall plate & truss
2555 Fix purlins and rafters
2556 Fix shingles ( subject to receipt of timber)
2557 Fix ceiing battens & joists
2558 Fix ceiling boards
2559 M&E first fix
2560 Finishes
2561 Wall plaster (internal & External)
2562 M&E 1st fix
2563 Floor finishes
2564 Fix windows & doors
2565 Swimming pool finishes
2566 M&E final fix
2567 Fix fittings and Fixtures
2568 M&E Installations
2569 Cable Tray, Conduit and Wiring
2570 Electrical boards and connections
2571 Electrical accessories
2572 Light fittings and ceiling fans
2573 Hot and cold water
2574 Waste and sewage incl. biobox
2575 Electric water heater
2576 Swimming pool
2577 Split unit installation
2578 Toilet ventilation, grilles
2579 Villa A3/31
2624 Villa A3/32
2664 B223 Villas ( 3 nos)
2665 Villa B2/03
2708 Villa B2/09
2758 Villa B2/10
2808 B4 Standard Villas ( 2 nos)
2809 Villa B4/03
2854 Villa B4/04
2899 BC311 Executive Villa
2900 Villa C3/02
2943 Villa C3/03
2986 Villa C3/04
3029 Villa C3/05
3072 Villa C3/06
3115 P3 Presidential suites ( 3 nos)
3116 Villa P3/01
3159 Villa P3/02
3202 Villa P3/03
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009
The following table provides a summary of the delay caused by late setting out at each of the buildings.
Villa commencement completion commencement completion Baseline duration Revised Duration A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08A3/11 09-Apr-07 02-Jun-08 09-Apr-07 15-Mar-08 341.13 420.08A3/20 25-Apr-07 23-Jun-08 12-Apr-07 15-Mar-08 338.13 425.08A3/30 25-Apr-07 29-Mar-08 28-May-07 15-Mar-08 292.13 339.13
Baseline ProgrammeImpacted Programme
As a result of this delaying event the time for completion has been extended from 16 May 2008 to 9 August 2008, a period of 85 calendar days.
page 81
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.2. Event No 2 – Unforeseen Ground Conditions
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
184 Villa A3/01
185 Substructure
186 set out
187 Excavate
188 Conc. Foundation
189 Backfill
190 termite treatment
191 DPC (where applicable)
192 M&E inlet/outlet works - first fix
193 Frame
203 Roof & Ceiling
210 Finishes
217 M&E Installations
228 Villa A3/02
229 substructure
230 set out
231 Excavate
232 Conc. Foundation
233 Backfill
234 termite treatment
235 DPC (where applicable)
236 M&E inlet/outlet works - first fix
237 frame
247 Roof & Ceiling
254 Finishes
262 M&E Installations
273 Villa A3/03
274 substructure
275 set out
276 Excavate
277 Conc. Foundation
278 Backfill
279 termite treatment
280 DPC (where applicable)
281 M&E inlet/outlet works - first fix
282 frame
292 Roof & Ceiling
299 Finishes
307 M&E Installations
318 Villa A3/04
363 Villa A3/05
408 Villa A3/06
409 substructure
410 set out
411 Excavate
412 Conc. Foundation
413 Backfill
414 termite treatment
415 DPC (where applicable)
416 M&E inlet/outlet works - first fix
417 frame
427 Roof & Ceiling
434 Finishes
442 M&E Installations
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
849 Villa A3/07
894 Villa A3/08
895 substructure
896 set out
897 Excavate
898 Conc. Foundation
899 Backfill
900 termite treatment
901 DPC (where applicable)
902 M&E inlet/outlet works - first fix
903 frame
913 Roof & Ceiling
920 Finishes
928 M&E Installations
939 Villa A3/09
940 substructure
941 set out
942 Excavate
943 Conc. Foundation
944 Backfill
945 termite treatment
946 DPC (where applicable)
947 M&E inlet/outlet works - first fix
948 frame
958 Roof & Ceiling
965 Finishes
973 M&E Installations
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
page 82
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
984 Villa A3/10
985 substructure
986 set out
987 Excavate
988 Conc. Foundation
989 Backfill
990 termite treatment
991 DPC (where applicable)
992 M&E inlet/outlet works - first fix
993 frame
1003 Roof & Ceiling
1010 Finishes
1018 M&E Installations
1029 Villa A3/11
1030 substructure
1031 set out
1032 Excavate
1033 Conc. Foundation
1034 Backfill
1035 termite treatment
1036 DPC (where applicable)
1037 M&E inlet/outlet works - first fix
1038 frame
1048 Roof & Ceiling
1055 Finishes
1063 M&E Installations
1074 Villa A3/12
1119 Villa A3/13
1164 Villa A3/18
1209 Villa A3/19
1210 substructure
1211 set out
1212 Excavate
1213 Conc. Foundation
1214 Backfill
1215 termite treatment
1216 DPC (where applicable)
1217 M&E inlet/outlet works - first fix
1218 frame
1228 Roof & Ceiling
1235 Finishes
1243 M&E Installations
1254 Villa A3/20
1255 substructure
1256 set out
1257 Excavate
1258 Conc. Foundation
1259 Backfill
1260 termite treatment
1261 DPC (where applicable)
1262 M&E inlet/outlet works - first fix
1263 frame
1273 Roof & Ceiling
1280 Finishes
1288 M&E Installations
1299 Villa A3/21
1300 substructure
1301 set out
1302 Excavate
1303 Conc. Foundation
1304 Backfill
1305 termite treatment
1306 DPC (where applicable)
1307 M&E inlet/outlet works - first fix
1308 frame
1318 Roof & Ceiling
1325 Finishes
1333 M&E Installations
1344 Villa A3/22
1389 Villa A3/23
1434 Villa A3/24
1479 Villa A3/25
1524 Villa A3/26
1525 substructure
1526 set out
1527 Excavate
1528 Conc. Foundation
1529 Backfill
1530 termite treatment
1531 DPC (where applicable)
1532 M&E inlet/outlet works - first fix
1533 frame
1543 Roof & Ceiling
1550 Finishes
1558 M&E Installations
1569 Villa A3/27
1570 substructure
1571 set out
1572 Excavate
1573 Conc. Foundation
1574 Backfill
1575 termite treatment
1576 DPC (where applicable)
1577 M&E inlet/outlet works - first fix
1578 frame
1588 Roof & Ceiling
1595 Finishes
1603 M&E Installations
1614 B223 Villas ( 7 nos)
1615 Villa B2/01
1616 substructure
1617 set out
1618 Excavate
1619 Conc. Foundation
1620 Backfill
1621 termite treatment
1622 DPC (where applicable)
1623 M&E inlet/outlet works - first fix
1624 frame
1640 Roof & Ceiling
1647 Finishes
1654 M&E Installations
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 83
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1665 Villa B2/02
1666 substructure
1667 set out
1668 Excavate
1669 Conc. Foundation
1670 Backfill
1671 termite treatment
1672 DPC (where applicable)
1673 M&E inlet/outlet works - first fix
1674 frame
1690 Roof & Ceiling
1697 Finishes
1704 M&E Installations
1715 Villa B2/04
1716 substructure
1717 set out
1718 Excavate
1719 Conc. Foundation
1720 Backfill
1721 termite treatment
1722 DPC (where applicable)
1723 M&E inlet/outlet works - first fix
1724 frame
1740 Roof & Ceiling
1747 Finishes
1754 M&E Installations
1765 Villa B2/05
1766 substructure
1767 set out
1768 Excavate
1769 Conc. Foundation
1770 Backfill
1771 termite treatment
1772 DPC (where applicable)
1773 M&E inlet/outlet works - first fix
1774 frame
1790 Roof & Ceiling
1797 Finishes
1804 M&E Installations
1815 Villa B2/06
1816 substructure
1817 set out
1818 Excavate
1819 Conc. Foundation
1820 Backfill
1821 termite treatment
1822 DPC (where applicable)
1823 M&E inlet/outlet works - first fix
1824 frame
1840 Roof & Ceiling
1847 Finishes
1854 M&E Installations
1865 Villa B2/07
1866 substructure
1867 set out
1868 Excavate
1869 Conc. Foundation
1870 Backfill
1871 termite treatment
1872 DPC (where applicable)
1873 M&E inlet/outlet works - first fix
1874 frame
1890 Roof & Ceiling
1897 Finishes
1904 M&E Installations
1915 Villa B2/08
1916 substructure
1917 set out
1918 Excavate
1919 Conc. Foundation
1920 Backfill
1921 termite treatment
1922 DPC (where applicable)
1923 M&E inlet/outlet works - first fix
1924 frame
1940 Roof & Ceiling
1947 Finishes
1954 M&E Installations
1965 B4 Villa (2 nos.)
1966 Villa B4/01
1967 substructure
1968 set out
1969 Excavate
1970 Conc. Foundation
1971 Backfill
1972 termite treatment
1973 DPC (where applicable)
1974 M&E inlet/outlet works - first fix
1975 frame
1976 set kickers
1977 Conc. Columns & shear walls
1978 Conc. G. F Beams
1979 M&E first fix
1980 Conc. Plantroom
1981 Conc. Floor slab & swimming pool base
1982 Blockwork
1983 Conc. Swimming pool sides & overflow channels
1984 Conc. Ring & tie beams
1985 Roof & Ceiling
1986 Fix wall plate & truss
1987 Fix purlins and rafters
1988 Fix shingles ( subject to receipt of timber)
1989 Fix ceiing battens & joists
1990 Fix ceiling boards
1991 M&E first fix
1992 Finishes
1993 Wall plaster (internal & External)
1994 M&E 1st fix
1995 Floor finishes
1996 Fix windows & doors
1997 Swimming pool finishes
1998 M&E final fix
1999 Fix fittings and Fixtures
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 84
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2000 M&E Installations
2001 Cable Tray, Conduit and Wiring
2002 Electrical boards and connections
2003 Electrical accessories
2004 Light fittings and ceiling fans
2005 Hot and cold water
2006 Waste and sewage incl. biobox
2007 Electric water heater
2008 Swimming pool
2009 Split unit installation
2010 Toilet ventilation, grilles
2011 Villa B4/02
2012 substructure
2013 set out
2014 Excavate
2015 Conc. Foundation
2016 Backfill
2017 termite treatment
2018 DPC (where applicable)
2019 M&E inlet/outlet works - first fix
2020 frame
2021 set kickers
2022 Conc. Columns & shear walls
2023 Conc. G. F Beams
2024 M&E first fix
2025 Conc. Plantroom
2026 Conc. Floor slab & swimming pool base
2027 Blockwork
2028 Conc. Swimming pool sides & overflow channels
2029 Conc. Ring & tie beams
2030 Roof & Ceiling
2031 Fix wall plate & truss
2032 Fix purlins and rafters
2033 Fix shingles ( subject to receipt of timber)
2034 Fix ceiing battens & joists
2035 Fix ceiling boards
2036 M&E first fix
2037 Finishes
2038 Wall plaster (internal & External)
2039 M&E 1st fix
2040 Floor finishes
2041 Fix windows & doors
2042 Swimming pool finishes
2043 M&E final fix
2044 Fix fittings and Fixtures
2045 M&E Installations
2046 Cable Tray, Conduit and Wiring
2047 Electrical boards and connections
2048 Electrical accessories
2049 Light fittings and ceiling fans
2050 Hot and cold water
2051 Waste and sewage incl. biobox
2052 Electric water heater
2053 Swimming pool
2054 Split unit installation
2055 Toilet ventilation, grilles
2056 Retail 1( subject to receipt of GFW drawings)
2057 substructure
2058 set out
2059 Excavate (Drill in rock to anchor steel rods)
2060 Conc. Foundation
2061 Backfill ( where applicable )
2062 termite treatment
2063 DPC (where applicable)
2064 M&E inlet/outlet works
2065 frame
2066 set kickers
2067 Conc. Columns & shear walls
2068 Conc. G. F Beams
2069 Conc. Plantroom
2070 Conc. Floor slab
2071 Blockwork
2072 Conc. Ring & tie beams
2073 Roof & Ceiling
2074 Fix wall plate & truss
2075 Fix purlins and rafters
2076 Fix shingles ( subject to receipt of timber)
2077 Fix ceiing battens & joists
2078 Fix ceiling boards
2079 Finishes
2080 Wall plaster (internal & External)
2081 M&E 1st fix
2082 Floor finishes
2083 Fix windows & doors
2084 M&E final fix
2085 Fix fittings and Fixtures
2086 M&E Installations
2087 Cable Tray, Conduit and Wiring
2088 Electrical boards and connections
2089 Electrical accessories
2090 Light fittings and ceiling fans
2091 Hot and cold water
2092 Waste and sewage incl. biobox
2093 Fan coil unit
2094 Retail 2( subject to receipt of GFW drawings)
2095 substructure
2096 set out
2097 Excavate (Drill in rock to anchor steel rods)
2098 Conc. Foundation
2099 Backfill ( where applicable )
2100 termite treatment
2101 DPC (where applicable)
2102 M&E inlet/outlet works
2103 frame
2104 set kickers
2105 Conc. Columns & shear walls
2106 Conc. G. F Beams
2107 Conc. Plantroom
2108 Conc. Floor slab
2109 Blockwork
2110 Conc. Ring & tie beams
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 85
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2111 Roof & Ceiling
2112 Fix wall plate & truss
2113 Fix purlins and rafters
2114 Fix shingles ( subject to receipt of timber)
2115 Fix ceiing battens & joists
2116 Fix ceiling boards
2117 Finishes
2118 Wall plaster (internal & External)
2119 M&E 1st fix
2120 Floor finishes
2121 Fix windows & doors
2122 M&E final fix
2123 Fix fittings and Fixtures
2124 M&E Installations
2125 Cable Tray, Conduit and Wiring
2126 Electrical boards and connections
2127 Electrical accessories
2128 Light fittings and ceiling fans
2129 Hot and cold water
2130 Waste and sewage incl. biobox
2131 Fan coil unit
2132 Retail 3( subject to receipt of GFW drawings)
2133 substructure
2134 set out
2135 Excavate (Drill in rock to anchor steel rods)
2136 Conc. Foundation
2137 Backfill ( where applicable )
2138 termite treatment
2139 DPC (where applicable)
2140 M&E inlet/outlet works
2141 frame
2142 set kickers
2143 Conc. Columns & shear walls
2144 Conc. G. F Beams
2145 Conc. Plantroom
2146 Conc. Floor slab
2147 Blockwork
2148 Conc. Ring & tie beams
2149 Roof & Ceiling
2150 Fix wall plate & truss
2151 Fix purlins and rafters
2152 Fix shingles ( subject to receipt of timber)
2153 Fix ceiing battens & joists
2154 Fix ceiling boards
2155 Finishes
2156 Wall plaster (internal & External)
2157 M&E 1st fix
2158 Floor finishes
2159 Fix windows & doors
2160 M&E final fix
2161 Fix fittings and Fixtures
2162 M&E Installations
2163 Cable Tray, Conduit and Wiring
2164 Electrical boards and connections
2165 Electrical accessories
2166 Light fittings and ceiling fans
2167 Hot and cold water
2168 Waste and sewage incl. biobox
2169 Fan coil unit
2170 Seafood resort( subject to receipt of GFW drawings)
2171 substructure
2172 set out
2173 Excavate (Drill in rock to anchor steel rods)
2174 Conc. Foundation
2175 Backfill ( where applicable )
2176 termite treatment
2177 DPC (where applicable)
2178 M&E inlet/outlet works
2179 frame
2180 set kickers
2181 Conc. Columns & shear walls
2182 Conc. G. F Beams
2183 Conc. Plantroom
2184 Conc. Floor slab
2185 Blockwork
2186 Conc. Ring & tie beams
2187 Roof & Ceiling
2188 Fix wall plate & truss
2189 Fix purlins and rafters
2190 Fix shingles ( subject to receipt of timber)
2191 Fix ceiing battens & joists
2192 Fix ceiling boards
2193 Finishes
2194 Wall plaster (internal & External)
2195 M&E 1st fix
2196 Floor finishes
2197 Fix windows & doors
2198 M&E final fix
2199 Fix fittings and Fixtures
2200 M&E Installations
2201 Cable Tray, Conduit and Wiring
2202 Electrical boards and connections
2203 Electrical accessories
2204 Light fittings and ceiling fans
2205 Hot and cold water
2206 Waste and sewage incl. biobox
2207 Kitchen extraction duct
2208 Chilled water piping
2209 Fan coil unit
2210 Toilet ventilation, grilles
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2212 substructure
2213 set out
2214 Excavate (Drill in rock to anchor steel rods)
2215 Conc. Foundation
2216 Backfill ( where applicable )
2217 termite treatment
2218 DPC (where applicable)
2219 M&E inlet/outlet works
2220 frame
2221 set kickers
2222 Conc. Columns & shear walls
2223 Conc. G. F Beams
2224 Conc. Plantroom
2225 Conc. Floor slab
2226 Blockwork
2227 Conc. Ring & tie beams
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2008 2009 2010 2011
page 86
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2228 Roof & Ceiling
2229 Fix wall plate & truss
2230 Fix purlins and rafters
2231 Fix shingles ( subject to receipt of timber)
2232 Fix ceiing battens & joists
2233 Fix ceiling boards
2234 Finishes
2235 Wall plaster (internal & External)
2236 M&E 1st fix
2237 Floor finishes
2238 Fix windows & doors
2239 M&E final fix
2240 Fix fittings and Fixtures
2241 M&E Installations
2242 Cable Tray, Conduit and Wiring
2243 Electrical boards and connections
2244 Electrical accessories
2245 Light fittings and ceiling fans
2246 Hot and cold water
2247 Waste and sewage incl. biobox
2248 Fan coil unit
2249 Toilet ventilation, grilles
2250 External works ( subject to receipt of GFW drawings)
2251 Infrastructures
2252 Set out road (cabbies), vehicular
2253 Set out Pedestrian walkways
2254 Set out main water pipe alignment
2255 Set out main electricity network
2256 landscaping
2257 Villas milieu
2258 Main access road milieu
2259 Drainage works ( subject to receipt of EME details)
2260 Set out/implement main sewerage network
2261 Set out/implement main rain water drainage alignment
2262 Lot 3
2263 A3 Villas ( 9 nos)
2264 Villa A3/14
2309 Villa A3/15
2354 Villa A3/16
2399 Villa A3/17
2444 Villa A3/28
2445 substructure
2446 set out
2447 Excavate
2448 Conc. Foundation
2449 Backfill
2450 termite treatment
2451 DPC (where applicable)
2452 M&E inlet/outlet works - first fix
2453 frame
2463 Roof & Ceiling
2470 Finishes
2478 M&E Installations
2489 Villa A3/29
2490 substructure
2491 set out
2492 Excavate
2493 Conc. Foundation
2494 Backfill
2495 termite treatment
2496 DPC (where applicable)
2497 M&E inlet/outlet works - first fix
2498 frame
2508 Roof & Ceiling
2515 Finishes
2523 M&E Installations
2534 Villa A3/30
2535 substructure
2536 set out
2537 Excavate
2538 Conc. Foundation
2539 Backfill
2540 termite treatment
2541 DPC (where applicable)
2542 M&E inlet/outlet works - first fix
2543 frame
2553 Roof & Ceiling
2560 Finishes
2568 M&E Installations
2579 Villa A3/31
2624 Villa A3/32
2625 substructure
2626 set out
2627 Excavate
2628 Conc. Foundation
2629 Backfill
2630 termite treatment
2631 DPC (where applicable)
2632 frame
2641 Roof & Ceiling
2647 Finishes
2653 M&E Installations
2664 B223 Villas ( 3 nos)
2665 Villa B2/03
2666 substructure
2667 set out
2668 Excavate
2669 Conc. Foundation
2670 Backfill
2671 termite treatment
2672 DPC (where applicable)
2673 frame
2686 Roof & Ceiling
2692 Finishes
2697 M&E Installations
2708 Villa B2/09
2709 substructure
2710 set out
2711 Excavate
2712 Conc. Foundation
2713 Backfill
2714 termite treatment
2715 DPC (where applicable)
2716 M&E inlet/outlet works - first fix
2717 frame
2733 Roof & Ceiling
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 87
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2740 Finishes
2747 M&E Installations
2758 Villa B2/10
2759 substructure
2760 set out
2761 Excavate
2762 Conc. Foundation
2763 Backfill
2764 termite treatment
2765 DPC (where applicable)
2766 M&E inlet/outlet works - first fix
2767 frame
2783 Roof & Ceiling
2790 Finishes
2797 M&E Installations
2808 B4 Standard Villas ( 2 nos)
2809 Villa B4/03
2810 substructure
2811 set out
2812 Excavate
2813 Conc. Foundation
2814 Backfill
2815 termite treatment
2816 DPC (where applicable)
2817 M&E inlet/outlet works - first fix
2818 frame
2819 set kickers
2820 Conc. Columns & shear walls
2821 Conc. G. F Beams
2822 M&E first fix
2823 Conc. Plantroom
2824 Conc. Floor slab & swimming pool base
2825 Blockwork
2826 Conc. Swimming pool sides & overflow channels
2827 Conc. Ring & tie beams
2828 Roof & Ceiling
2829 Fix wall plate & truss
2830 Fix purlins and rafters
2831 Fix shingles ( subject to receipt of timber)
2832 Fix ceiing battens & joists
2833 Fix ceiling boards
2834 M&E first fix
2835 Finishes
2836 Wall plaster (internal & External)
2837 M&E 1st fix
2838 Floor finishes
2839 Fix windows & doors
2840 Swimming pool finishes
2841 M&E final fix
2842 Fix fittings and Fixtures
2843 M&E Installations
2844 Cable Tray, Conduit and Wiring
2845 Electrical boards and connections
2846 Electrical accessories
2847 Light fittings and ceiling fans
2848 Hot and cold water
2849 Waste and sewage incl. biobox
2850 Electric water heater
2851 Swimming pool
2852 Split unit installation
2853 Toilet ventilation, grilles
2854 Villa B4/04
2855 substructure
2856 set out
2857 Excavate
2858 Conc. Foundation
2859 Backfill
2860 termite treatment
2861 DPC (where applicable)
2862 M&E inlet/outlet works - first fix
2863 frame
2864 set kickers
2865 Conc. Columns & shear walls
2866 Conc. G. F Beams
2867 M&E first fix
2868 Conc. Plantroom
2869 Conc. Floor slab & swimming pool base
2870 Blockwork
2871 Conc. Swimming pool sides & overflow channels
2872 Conc. Ring & tie beams
2873 Roof & Ceiling
2874 Fix wall plate & truss
2875 Fix purlins and rafters
2876 Fix shingles ( subject to receipt of timber)
2877 Fix ceiing battens & joists
2878 Fix ceiling boards
2879 M&E first fix
2880 Finishes
2881 Wall plaster (internal & External)
2882 M&E 1st fix
2883 Floor finishes
2884 Fix windows & doors
2885 Swimming pool finishes
2886 M&E final fix
2887 Fix fittings and Fixtures
2888 M&E Installations
2889 Cable Tray, Conduit and Wiring
2890 Electrical boards and connections
2891 Electrical accessories
2892 Light fittings and ceiling fans
2893 Hot and cold water
2894 Waste and sewage incl. biobox
2895 Electric water heater
2896 Swimming pool
2897 Split unit installation
2898 Toilet ventilation, grilles
2899 BC311 Executive Villa
2900 Villa C3/02
2943 Villa C3/03
2986 Villa C3/04
3029 Villa C3/05
3072 Villa C3/06
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010
page 88
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3115 P3 Presidential suites ( 3 nos)
3116 Villa P3/01
3159 Villa P3/02
3202 Villa P3/03
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3290 Set out/implement main sewerage network
3291 Set out/implement main rain water drainage alignment
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2008 2009 2010 2011
The following table provides summary of the current delay caused by unforeseen ground conditions at each of the buildings. This change involved significant delay and difficulty excavating hard rock.
Villa commencement completion commencement completion Baseline duration Revised Duration A3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13A3/32 28-May-07 16-Nov-07 28-May-07 16-Nov-07 172.04 172.04B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08B2/03 28-May-07 25-Dec-07 28-May-07 04-Dec-07 190.17 211.13B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13
Impacted Programme Baseline Programme
The next table records the delays to other buildings as a consequence of the delays to the current to preceding tasks. In retaining the original planned sequence depicted on the original programme of works, the completion date is extended to 9 September 2009.
page 89
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa commencement completion commencement completion Delay P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-08 367.00Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-08 367.00Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-08 290.00Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-08 290.00GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-08 367.00Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-08 367.00Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 372.00Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-08 440.00Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-08 440.00Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00
Impacted Programme Baseline Programme
It should be noted that rock excavation is continuing at various sites where excavation activities is yet to start. Consequently, the delay attributed to this event is continuing.
As a result of the current delay caused by this event the time for completion has been further extended from 9 August 2008 to 9 September 2009, a period of 396 calendar days.
However, in recognition of more rock excavation at other areas of the Site it is anticipated further delays will be experienced. Accordingly, the Contractor gives notice of further delays likely at the remaining areas of the site where buildings will be positioned.
The revised completion date is now 9 September 2009.
page 90
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.3. Event No 3 – Later Receipt of Design Information
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
498 substructure
499 set out ( subject to receipt of GFW dwg by Mid June 07)
500 Excavate (Drill in rock to anchor steel rods as required)
501 Conc. Foundation
502 Backfill ( where applicable )
503 termite treatment
504 DPC (where applicable)
505 M&E inlet/outlet works
506 frame
507 set kickers
508 Conc. Columns & shear walls upto roof
509 Conc. G. F Beams
510 Conc. Floor slab GF
511 Blockwork upto roof
512 Conc. Ring & tie beams
513 Roof & Ceiling
514 Fix wall plate & truss
515 Fix purlins and rafters
516 Fix shingles ( subject to receipt of timber)
517 Fix ceiing battens & joists
518 Fix ceiling boards
519 Finishes
520 Wall plaster (internal & External)
521 M&E 1st fix
522 Floor finishes
523 Fix windows & doors
524 M&E final fix
525 Fix fittings and Fixtures
526 M&E Installations
527 Cable Tray, Conduit and Wiring
528 Electrical boards and connections
529 Electrical accessories
530 Light fittings and ceiling fans
531 Hot and cold water
532 Waste and sewage incl. biobox
533 Electric water heater
534 Swimming pool
535 Split unit installation
536 Toilet ventilation, grilles
537 Employees Facilities ( subject to receipt of GFW drawings)
538 substructure
539 set out
540 Excavate
541 Conc. Foundation
542 Backfill ( where applicable )
543 termite treatment
544 DPC (where applicable)
545 M&E inlet/outlet works
546 frame
547 set kickers
548 Conc. Columns & shear walls upto GF floor level
549 Conc. G. F Beams
550 Conc. G.F Floor slab
551 Conc. Columns & shear walls upto FF level
552 Blockwork upto FF level
553 Conc. F. Floor slab
554 Conc. Columns & shear walls upto roof level
555 Blockwork upto roof
556 Conc. Ring & tie beams
557 Roof & Ceiling
558 Fix wall plate & truss
559 Fix purlins and rafters
560 Fix shingles ( subject to receipt of timber)
561 Fix ceiing battens & joists
562 Fix ceiling boards
563 Finishes
564 Wall plaster (internal & External)
565 M&E 1st fix
566 Floor finishes
567 Fix windows & doors
568 M&E final fix
569 Fix fittings and Fixtures
570 M&E Installations
571 Cable Tray, Conduit and Wiring
572 Electrical boards and connections
573 Electrical accessories
574 Light fittings and ceiling fans
575 Hot and cold water
576 Waste and sewage incl. biobox
577 Boiler
578 Chiller
579 Fan coil unit
580 Toilet ventilation, grilles
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
626 substructure
627 set out
628 Excavate (Drill in rock to anchor steel rods)
629 Conc. Foundation
630 Backfill ( where applicable )
631 termite treatment
632 DPC (where applicable)
633 M&E inlet/outlet works
634 frame
635 set kickers
636 Conc. Columns & shear walls
637 Conc. G. F Beams
638 Conc. substructure
639 Conc. Floor slab
640 Blockwork
641 Conc. Ring & tie beams
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
page 91
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
642 Roof & Ceiling
643 Fix wall plate & truss
644 Fix purlins and rafters
645 Fix shingles ( subject to receipt of timber)
646 Fix ceiing battens & joists
647 Fix ceiling boards
648 Finishes
649 Wall plaster (internal & External)
650 M&E 1st fix
651 Floor finishes
652 Fix windows & doors
653 M&E final fix
654 Fix fittings and Fixtures
655 M&E Installations
656 Cable Tray, Conduit and Wiring
657 Electrical boards and connections
658 Electrical accessories
659 Light fittings and ceiling fans
660 Hot and cold water
661 Waste and sewage incl. biobox
662 Boiler
663 Chiller
664 Fan coil unit
665 Toilet ventilation, grilles
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
708 substructure
709 set out
710 Excavate
711 Conc. Foundation
712 Backfill ( where applicable )
713 termite treatment
714 DPC (where applicable)
715 M&E inlet/outlet works
716 frame
717 set kickers
718 Conc. Columns & shear walls upto GF floor level
719 Conc. G. F Beams
720 Conc. G.F Floor slab
721 Conc. Columns & shear walls upto FF level
722 Blockwork upto FF level
723 Conc. F. Floor slab
724 Conc. Columns & shear walls upto roof level
725 Blockwork upto roof
726 Conc. Ring & tie beams
727 Roof & Ceiling
728 Fix wall plate & truss
729 Fix purlins and rafters
730 Fix shingles ( subject to receipt of timber)
731 Fix ceiing battens & joists
732 Fix ceiling boards
733 Finishes
734 Wall plaster (internal & External)
735 M&E 1st fix
736 Floor finishes
737 Fix windows & doors
738 M&E final fix
739 Fix fittings and Fixtures
740 M&E Installations
741 Cable Tray, Conduit and Wiring
742 Electrical boards and connections
743 Electrical accessories
744 Light fittings and ceiling fans
745 Hot and cold water
746 Waste and sewage incl. biobox
747 Electric water heater
748 Split unit installation
749 Toilet ventilation, grilles
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
1614 B223 Villas ( 7 nos)
1965 B4 Villa (2 nos.)
2056 Retail 1( subject to receipt of GFW drawings)
2057 substructure
2058 set out
2059 Excavate (Drill in rock to anchor steel rods)
2060 Conc. Foundation
2061 Backfill ( where applicable )
2062 termite treatment
2063 DPC (where applicable)
2064 M&E inlet/outlet works
2065 frame
2066 set kickers
2067 Conc. Columns & shear walls
2068 Conc. G. F Beams
2069 Conc. Plantroom
2070 Conc. Floor slab
2071 Blockwork
2072 Conc. Ring & tie beams
2073 Roof & Ceiling
2074 Fix wall plate & truss
2075 Fix purlins and rafters
2076 Fix shingles ( subject to receipt of timber)
2077 Fix ceiing battens & joists
2078 Fix ceiling boards
2079 Finishes
2080 Wall plaster (internal & External)
2081 M&E 1st fix
2082 Floor finishes
2083 Fix windows & doors
2084 M&E final fix
2085 Fix fittings and Fixtures
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 92
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2086 M&E Installations
2087 Cable Tray, Conduit and Wiring
2088 Electrical boards and connections
2089 Electrical accessories
2090 Light fittings and ceiling fans
2091 Hot and cold water
2092 Waste and sewage incl. biobox
2093 Fan coil unit
2094 Retail 2( subject to receipt of GFW drawings)
2095 substructure
2096 set out
2097 Excavate (Drill in rock to anchor steel rods)
2098 Conc. Foundation
2099 Backfill ( where applicable )
2100 termite treatment
2101 DPC (where applicable)
2102 M&E inlet/outlet works
2103 frame
2104 set kickers
2105 Conc. Columns & shear walls
2106 Conc. G. F Beams
2107 Conc. Plantroom
2108 Conc. Floor slab
2109 Blockwork
2110 Conc. Ring & tie beams
2111 Roof & Ceiling
2112 Fix wall plate & truss
2113 Fix purlins and rafters
2114 Fix shingles ( subject to receipt of timber)
2115 Fix ceiing battens & joists
2116 Fix ceiling boards
2117 Finishes
2118 Wall plaster (internal & External)
2119 M&E 1st fix
2120 Floor finishes
2121 Fix windows & doors
2122 M&E final fix
2123 Fix fittings and Fixtures
2124 M&E Installations
2125 Cable Tray, Conduit and Wiring
2126 Electrical boards and connections
2127 Electrical accessories
2128 Light fittings and ceiling fans
2129 Hot and cold water
2130 Waste and sewage incl. biobox
2131 Fan coil unit
2132 Retail 3( subject to receipt of GFW drawings)
2133 substructure
2134 set out
2135 Excavate (Drill in rock to anchor steel rods)
2136 Conc. Foundation
2137 Backfill ( where applicable )
2138 termite treatment
2139 DPC (where applicable)
2140 M&E inlet/outlet works
2141 frame
2142 set kickers
2143 Conc. Columns & shear walls
2144 Conc. G. F Beams
2145 Conc. Plantroom
2146 Conc. Floor slab
2147 Blockwork
2148 Conc. Ring & tie beams
2149 Roof & Ceiling
2150 Fix wall plate & truss
2151 Fix purlins and rafters
2152 Fix shingles ( subject to receipt of timber)
2153 Fix ceiing battens & joists
2154 Fix ceiling boards
2155 Finishes
2156 Wall plaster (internal & External)
2157 M&E 1st fix
2158 Floor finishes
2159 Fix windows & doors
2160 M&E final fix
2161 Fix fittings and Fixtures
2162 M&E Installations
2163 Cable Tray, Conduit and Wiring
2164 Electrical boards and connections
2165 Electrical accessories
2166 Light fittings and ceiling fans
2167 Hot and cold water
2168 Waste and sewage incl. biobox
2169 Fan coil unit
2170 Seafood resort( subject to receipt of GFW drawings)
2171 substructure
2172 set out
2173 Excavate (Drill in rock to anchor steel rods)
2174 Conc. Foundation
2175 Backfill ( where applicable )
2176 termite treatment
2177 DPC (where applicable)
2178 M&E inlet/outlet works
2179 frame
2180 set kickers
2181 Conc. Columns & shear walls
2182 Conc. G. F Beams
2183 Conc. Plantroom
2184 Conc. Floor slab
2185 Blockwork
2186 Conc. Ring & tie beams
2187 Roof & Ceiling
2188 Fix wall plate & truss
2189 Fix purlins and rafters
2190 Fix shingles ( subject to receipt of timber)
2191 Fix ceiing battens & joists
2192 Fix ceiling boards
2193 Finishes
2194 Wall plaster (internal & External)
2195 M&E 1st fix
2196 Floor finishes
2197 Fix windows & doors
2198 M&E final fix
2199 Fix fittings and Fixtures
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2008 2009 2010 2011
page 93
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2200 M&E Installations
2201 Cable Tray, Conduit and Wiring
2202 Electrical boards and connections
2203 Electrical accessories
2204 Light fittings and ceiling fans
2205 Hot and cold water
2206 Waste and sewage incl. biobox
2207 Kitchen extraction duct
2208 Chilled water piping
2209 Fan coil unit
2210 Toilet ventilation, grilles
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2664 B223 Villas ( 3 nos)
2808 B4 Standard Villas ( 2 nos)
2899 BC311 Executive Villa
3115 P3 Presidential suites ( 3 nos)
3116 Villa P3/01
3117 substructure
3118 set out
3119 Excavate
3120 Conc. Foundation
3121 Backfill ( where applicable )
3122 termite treatment
3123 DPC (where applicable)
3124 M&E inlet/outlet works
3125 frame
3126 set kickers
3127 Conc. Columns & shear walls
3128 Conc. G. F Beams
3129 Conc. Plantroom
3130 Conc. Floor slab & swimming pool base
3131 Blockwork
3132 Conc. Swimming pool sides & overflow channels
3133 Conc. Ring & tie beams
3134 Roof & Ceiling
3135 Fix wall plate & truss
3136 Fix purlins and rafters
3137 Fix shingles ( subject to receipt of timber)
3138 Fix ceiing battens & joists
3139 Fix ceiling boards
3140 Finishes
3141 Wall plaster (internal & External)
3142 M&E 1st fix
3143 Floor finishes
3144 Fix windows & doors
3145 Swimming pool finishes
3146 M&E final fix
3147 Fix fittings and Fixtures
3148 M&E Installations
3149 Cable Tray, Conduit and Wiring
3150 Electrical boards and connections
3151 Electrical accessories
3152 Light fittings and ceiling fans
3153 Hot and cold water
3154 Waste and sewage incl. biobox
3155 Electric water heater
3156 Swimming pool
3157 Split unit installation
3158 Toilet ventilation, grilles
3159 Villa P3/02
3160 substructure
3161 set out
3162 Excavate
3163 Conc. Foundation
3164 Backfill ( where applicable )
3165 termite treatment
3166 DPC (where applicable)
3167 M&E inlet/outlet works
3168 frame
3169 set kickers
3170 Conc. Columns & shear walls
3171 Conc. G. F Beams
3172 Conc. Plantroom
3173 Conc. Floor slab & swimming pool base
3174 Blockwork
3175 Conc. Swimming pool sides & overflow channels
3176 Conc. Ring & tie beams
3177 Roof & Ceiling
3178 Fix wall plate & truss
3179 Fix purlins and rafters
3180 Fix shingles ( subject to receipt of timber)
3181 Fix ceiing battens & joists
3182 Fix ceiling boards
3183 Finishes
3184 Wall plaster (internal & External)
3185 M&E 1st fix
3186 Floor finishes
3187 Fix windows & doors
3188 Swimming pool finishes
3189 M&E final fix
3190 Fix fittings and Fixtures
3191 M&E Installations
3192 Cable Tray, Conduit and Wiring
3193 Electrical boards and connections
3194 Electrical accessories
3195 Light fittings and ceiling fans
3196 Hot and cold water
3197 Waste and sewage incl. biobox
3198 Electric water heater
3199 Swimming pool
3200 Split unit installation
3201 Toilet ventilation, grilles
3202 Villa P3/03
3203 substructure
3204 set out
3205 Excavate
3206 Conc. Foundation
3207 Backfill ( where applicable )
3208 termite treatment
3209 DPC (where applicable)
3210 M&E inlet/outlet works
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 94
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3211 frame
3220 Roof & Ceiling
3226 Finishes
3234 M&E Installations
3235 Cable Tray, Conduit and Wiring
3236 Electrical boards and connections
3237 Electrical accessories
3238 Light fittings and ceiling fans
3239 Hot and cold water
3240 Waste and sewage incl. biobox
3241 Electric water heater
3242 Swimming pool
3243 Split unit installation
3244 Toilet ventilation, grilles
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3246 substructure
3247 set out
3248 Excavate
3249 Conc. Foundation
3250 Backfill ( where applicable )
3251 termite treatment
3252 DPC (where applicable)
3253 M&E inlet/outlet works
3254 frame
3255 set kickers
3256 Conc. Columns & shear walls
3257 Conc. G. F Beams
3258 Conc. Plantroom
3259 Conc. Floor slab
3260 Blockwork
3261 Conc. Ring & tie beams
3262 Roof & Ceiling
3263 Fix wall plate & truss
3264 Fix purlins and rafters
3265 Fix shingles ( subject to receipt of timber)
3266 Fix ceiing battens & joists
3267 Fix ceiling boards
3268 Finishes
3269 Wall plaster (internal & External)
3270 M&E 1st fix
3271 Floor finishes
3272 Fix windows & doors
3273 M&E final fix
3274 Fix fittings and Fixtures
3275 M&E Installations
3276 Cable Tray, Conduit and Wiring
3277 Electrical boards and connections
3278 Electrical accessories
3279 Light fittings and ceiling fans
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3294 substructure
3295 set out
3296 Excavate
3297 Conc. Foundation
3298 Backfill ( where applicable )
3299 termite treatment
3300 DPC (where applicable)
3301 M&E inlet/outlet works
3302 frame
3303 set kickers
3304 Conc. Columns & shear walls
3305 Conc. G. F Beams
3306 Conc. Plantroom
3307 Conc. Floor slab
3308 Blockwork
3309 Conc. Ring & tie beams
3310 Roof & Ceiling
3311 Fix wall plate & truss
3312 Fix purlins and rafters
3313 Fix shingles ( subject to receipt of timber)
3314 Fix ceiing battens & joists
3315 Fix ceiling boards
3316 Finishes
3317 Wall plaster (internal & External)
3318 M&E 1st fix
3319 Floor finishes
3320 Fix windows & doors
3321 M&E final fix
3322 Fix fittings and Fixtures
3323 M&E Installations
3324 Cable Tray, Conduit and Wiring
3325 Electrical boards and connections
3326 Electrical accessories
3327 Light fittings and ceiling fans
3328 Hot and cold water
3329 Waste and sewage incl. biobox
3330 Electric water heater
3331 Water feature
3332 Split unit installation
3333 Toilet ventilation, grilles
3334 Single treatment room( subject to receipt of GFW drawings)
3335 substructure
3336 set out
3337 Excavate
3338 Conc. Foundation
3339 Backfill ( where applicable )
3340 termite treatment
3341 DPC (where applicable)
3342 M&E inlet/outlet works
3343 frame
3344 set kickers
3345 Conc. Columns & shear walls
3346 Conc. G. F Beams
3347 Conc. Plantroom
3348 Conc. Floor slab
3349 Blockwork
3350 Conc. Ring & tie beams
3351 Roof & Ceiling
3352 Fix wall plate & truss
3353 Fix purlins and rafters
3354 Fix shingles ( subject to receipt of timber)
3355 Fix ceiing battens & joists
3356 Fix ceiling boards
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011
page 95
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3357 Finishes
3358 Wall plaster (internal & External)
3359 M&E 1st fix
3360 Floor finishes
3361 Fix windows & doors
3362 M&E final fix
3363 Fix fittings and Fixtures
3364 M&E Installations
3365 Cable Tray, Conduit and Wiring
3366 Electrical boards and connections
3367 Electrical accessories
3368 Light fittings and ceiling fans
3369 Hot and cold water
3370 Waste and sewage incl. biobox
3371 Electric water heater
3372 Water feature
3373 Split unit installation
3374 Toilet ventilation, grilles
3375 Dive Centre( subject to receipt of GFW drawings)
3376 substructure
3377 set out
3378 Excavate
3379 Conc. Foundation
3380 Backfill ( where applicable )
3381 termite treatment
3382 DPC (where applicable)
3383 M&E inlet/outlet works
3384 frame
3385 set kickers
3386 Conc. Columns & shear walls
3387 Conc. G. F Beams
3388 Conc. Plantroom
3389 Conc. Floor slab
3390 Blockwork
3391 Conc. Ring & tie beams
3392 Roof & Ceiling
3393 Fix wall plate & truss
3394 Fix purlins and rafters
3395 Fix shingles ( subject to receipt of timber)
3396 Fix ceiing battens & joists
3397 Fix ceiling boards
3398 Finishes
3399 Wall plaster (internal & External)
3400 M&E 1st fix
3401 Floor finishes
3402 Fix windows & doors
3403 M&E final fix
3404 Fix fittings and Fixtures
3405 M&E Installations
3406 Cable Tray, Conduit and Wiring
3407 Electrical boards and connections
3408 Electrical accessories
3409 Light fittings and ceiling fans
3410 Hot and cold water
3411 Waste and sewage incl. biobox
3412 Toilet ventilation, grilles
3413 Kid's club( subject to receipt of GFW drawings)
3414 substructure
3415 set out
3416 Excavate
3417 Conc. Foundation
3418 Backfill ( where applicable )
3419 termite treatment
3420 DPC (where applicable)
3421 M&E inlet/outlet works
3422 frame
3423 set kickers
3424 Conc. Columns & shear walls
3425 Conc. G. F Beams
3426 Conc. Plantroom
3427 Conc. Floor slab
3428 Blockwork
3429 Conc. Ring & tie beams
3430 Roof & Ceiling
3431 Fix wall plate & truss
3432 Fix purlins and rafters
3433 Fix shingles ( subject to receipt of timber)
3434 Fix ceiing battens & joists
3435 Fix ceiling boards
3436 Finishes
3437 Wall plaster (internal & External)
3438 M&E 1st fix
3439 Floor finishes
3440 Fix windows & doors
3441 M&E final fix
3442 Fix fittings and Fixtures
3443 M&E Installations
3444 Cable Tray, Conduit and Wiring
3445 Electrical boards and connections
3446 Electrical accessories
3447 Light fittings and ceiling fans
3448 Hot and cold water
3449 Waste and sewage incl. biobox
3450 Electric water heater
3451 Toilet ventilation, grilles
3452 Recreation House( subject to receipt of GFW drawings)
3453 substructure
3454 set out
3455 Excavate
3456 Conc. Foundation
3457 Backfill ( where applicable )
3458 termite treatment
3459 DPC (where applicable)
3460 M&E inlet/outlet works
3461 frame
3462 set kickers
3463 Conc. Columns & shear walls
3464 Conc. G. F Beams
3465 Conc. Plantroom
3466 Conc. Floor slab
3467 Blockwork
3468 Conc. Ring & tie beams
3469 Roof & Ceiling
3470 Fix wall plate & truss
3471 Fix purlins and rafters
3472 Fix shingles ( subject to receipt of timber)
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011
page 96
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3473 Fix ceiing battens & joists
3474 Fix ceiling boards
3475 Finishes
3476 Wall plaster (internal & External)
3477 M&E 1st fix
3478 Floor finishes
3479 Fix windows & doors
3480 M&E final fix
3481 Fix fittings and Fixtures
3482 M&E Installations
3483 Cable Tray, Conduit and Wiring
3484 Electrical boards and connections
3485 Electrical accessories
3486 Light fittings and ceiling fans
3487 Hot and cold water
3488 Waste and sewage incl. biobox
3489 Electric water heater
3490 Toilet ventilation, grilles
3491 Watersports rental( subject to receipt of GFW drawings)
3492 substructure
3493 set out
3494 Excavate
3495 Conc. Foundation
3496 Backfill ( where applicable )
3497 termite treatment
3498 DPC (where applicable)
3499 M&E inlet/outlet works
3500 frame
3501 set kickers
3502 Conc. Columns & shear walls
3503 Conc. G. F Beams
3504 Conc. Plantroom
3505 Conc. Floor slab
3506 Blockwork
3507 Conc. Ring & tie beams
3508 Roof & Ceiling
3509 Fix wall plate & truss
3510 Fix purlins and rafters
3511 Fix shingles ( subject to receipt of timber)
3512 Fix ceiing battens & joists
3513 Fix ceiling boards
3514 Finishes
3515 Wall plaster (internal & External)
3516 M&E 1st fix
3517 Floor finishes
3518 Fix windows & doors
3519 M&E final fix
3520 Fix fittings and Fixtures
3521 M&E Installations
3522 Cable Tray, Conduit and Wiring
3523 Electrical boards and connections
3524 Electrical accessories
3525 Light fittings and ceiling fans
3526 Hot and cold water
3527 Waste and sewage incl. biobox
3528 Toilet ventilation, grilles
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3530 substructure
3531 set out
3532 Excavate
3533 Conc. Foundation
3534 Backfill ( where applicable )
3535 termite treatment
3536 DPC (where applicable)
3537 M&E inlet/outlet works
3538 frame
3539 set kickers
3540 Conc. Columns & shear walls
3541 Conc. G. F Beams
3542 Conc. Plantroom
3543 Conc. Floor slab
3544 Blockwork
3545 Conc. Ring & tie beams
3546 Roof & Ceiling
3547 Fix wall plate & truss
3548 Fix purlins and rafters
3549 Fix shingles ( subject to receipt of timber)
3550 Fix ceiing battens & joists
3551 Fix ceiling boards
3552 Finishes
3553 Wall plaster (internal & External)
3554 M&E 1st fix
3555 Floor finishes
3556 Fix windows & doors
3557 M&E final fix
3558 Fix fittings and Fixtures
3559 M&E Installations
3560 Cable Tray, Conduit and Wiring
3561 Electrical boards and connections
3562 Electrical accessories
3563 Light fittings and ceiling fans
3564 Hot and cold water
3565 Waste and sewage incl. biobox
3566 Boiler
3567 Chiller
3568 Fan coil unit
3569 Ducting and fans
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3571 substructure
3572 set out
3573 Excavate
3574 Conc. Foundation
3575 Backfill ( where applicable )
3576 termite treatment
3577 DPC (where applicable)
3578 M&E inlet/outlet works
3579 frame
3580 set kickers
3581 Conc. Columns & shear walls
3582 Conc. G. F Beams
3583 Conc. Plantroom
3584 Conc. Floor slab
3585 Blockwork
3586 Conc. Ring & tie beams
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011
page 97
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3587 Roof & Ceiling
3588 Fix wall plate & truss
3589 Fix purlins and rafters
3590 Fix shingles ( subject to receipt of timber)
3591 Fix ceiing battens & joists
3592 Fix ceiling boards
3593 Finishes
3594 Wall plaster (internal & External)
3595 M&E 1st fix
3596 Floor finishes
3597 Fix windows & doors
3598 M&E final fix
3599 Fix fittings and Fixtures
3600 M&E Installations
3601 Cable Tray, Conduit and Wiring
3602 Electrical boards and connections
3603 Electrical accessories
3604 Light fittings and ceiling fans
3605 Hot and cold water
3606 Waste and sewage incl. biobox
3607 Electric water heater
3608 Beach Pool
3609 Split unit installation
3610 Toilet ventilation, grilles
3611 Signature Pool area( subject to receipt of GFW drawings)
3612 substructure
3613 set out
3614 Excavate
3615 Conc. Foundation
3616 Backfill ( where applicable )
3617 termite treatment
3618 DPC (where applicable)
3619 M&E inlet/outlet works
3620 frame
3621 set kickers
3622 Conc. Columns & shear walls
3623 Conc. G. F Beams
3624 Conc. Plantroom
3625 Conc. Floor slab
3626 Blockwork
3627 Conc. Ring & tie beams
3628 Roof & Ceiling
3629 Fix wall plate & truss
3630 Fix purlins and rafters
3631 Fix shingles ( subject to receipt of timber)
3632 Fix ceiing battens & joists
3633 Fix ceiling boards
3634 Finishes
3635 Wall plaster (internal & External)
3636 M&E 1st fix
3637 Floor finishes
3638 Fix windows & doors
3639 M&E final fix
3640 Fix fittings and Fixtures
3641 M&E Installations
3642 Cable Tray, Conduit and Wiring
3643 Electrical boards and connections
3644 Electrical accessories
3645 Light fittings and ceiling fans
3646 Hot and cold water
3647 Waste and sewage incl. biobox
3648 Electric water heater
3649 Signature Pool
3650 Wedding Chapel( subject to receipt of GFW drawings)
3651 substructure
3652 set out
3653 Excavate
3654 Conc. Foundation
3655 Backfill ( where applicable )
3656 termite treatment
3657 DPC (where applicable)
3658 M&E inlet/outlet works
3659 frame
3660 set kickers
3661 Conc. Columns & shear walls
3662 Conc. G. F Beams
3663 Conc. Plantroom
3664 Conc. Floor slab
3665 Blockwork
3666 Conc. Ring & tie beams
3667 Roof & Ceiling
3668 Fix wall plate & truss
3669 Fix purlins and rafters
3670 Fix shingles ( subject to receipt of timber)
3671 Fix ceiing battens & joists
3672 Fix ceiling boards
3673 Finishes
3674 Wall plaster (internal & External)
3675 M&E 1st fix
3676 Floor finishes
3677 Fix windows & doors
3678 M&E final fix
3679 Fix fittings and Fixtures
3680 M&E Installations
3681 Cable Tray, Conduit and Wiring
3682 Electrical boards and connections
3683 Electrical accessories
3684 Light fittings and ceiling fans
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3686 substructure
3687 set out
3688 Excavate
3689 Conc. Foundation
3690 Backfill ( where applicable )
3691 termite treatment
3692 DPC (where applicable)
3693 M&E inlet/outlet works
3694 frame
3695 set kickers
3696 Conc. Columns & shear walls
3697 Conc. G. F Beams
3698 Conc. Plantroom
3699 Conc. Floor slab
3700 Blockwork
3701 Conc. Ring & tie beams
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011
page 98
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
3702 Roof & Ceiling
3703 Fix wall plate & truss
3704 Fix purlins and rafters
3705 Fix shingles ( subject to receipt of timber)
3706 Fix ceiing battens & joists
3707 Fix ceiling boards
3708 Finishes
3709 Wall plaster (internal & External)
3710 M&E 1st fix
3711 Floor finishes
3712 Fix windows & doors
3713 M&E final fix
3714 Fix fittings and Fixtures
3715 M&E Installations
3716 Cable Tray, Conduit and Wiring
3717 Electrical boards and connections
3718 Electrical accessories
3719 Light fittings and ceiling fans
3720 Hot and cold water
3721 Waste and sewage incl. biobox
3722 Electric water heater
3723 Pond
3724 Split unit installation
3725 Toilet ventilation, grilles
3726 Chi Sanctum( subject to receipt of GFW drawings)
3727 substructure
3728 set out
3729 Excavate
3730 Conc. Foundation
3731 Backfill ( where applicable )
3732 termite treatment
3733 DPC (where applicable)
3734 M&E inlet/outlet works
3735 frame
3736 set kickers
3737 Conc. Columns & shear walls
3738 Conc. G. F Beams
3739 Conc. Plantroom
3740 Conc. Floor slab
3741 Blockwork
3742 Conc. Ring & tie beams
3743 Roof & Ceiling
3744 Fix wall plate & truss
3745 Fix purlins and rafters
3746 Fix shingles ( subject to receipt of timber)
3747 Fix ceiing battens & joists
3748 Fix ceiling boards
3749 Finishes
3750 Wall plaster (internal & External)
3751 M&E 1st fix
3752 Floor finishes
3753 Fix windows & doors
3754 M&E final fix
3755 Fix fittings and Fixtures
3756 M&E Installations
3757 Cable Tray, Conduit and Wiring
3758 Electrical boards and connections
3759 Electrical accessories
3760 Light fittings and ceiling fans
3761 Hot and cold water
3762 Waste and sewage incl. biobox
3763 Electric water heater
3764 Pond
3765 Split unit installation
3766 Toilet ventilation, grilles
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3768 substructure
3769 set out
3770 Excavate
3771 Conc. Foundation
3772 Backfill ( where applicable )
3773 termite treatment
3774 DPC (where applicable)
3775 M&E inlet/outlet works
3776 frame
3777 set kickers
3778 Conc. Columns & shear walls
3779 Conc. G. F Beams
3780 Conc. Plantroom
3781 Conc. Floor slab
3782 Blockwork
3783 Conc. Ring & tie beams
3784 Roof & Ceiling
3785 Fix wall plate & truss
3786 Fix purlins and rafters
3787 Fix shingles ( subject to receipt of timber)
3788 Fix ceiing battens & joists
3789 Fix ceiling boards
3790 Finishes
3791 Wall plaster (internal & External)
3792 M&E 1st fix
3793 Floor finishes
3794 Fix windows & doors
3795 M&E final fix
3796 Fix fittings and Fixtures
3797 M&E Installations
3798 Cable Tray, Conduit and Wiring
3799 Electrical boards and connections
3800 Electrical accessories
3801 Light fittings and ceiling fans
3802 Hot and cold water
3803 Waste and sewage incl. biobox
3804 Electric water heater
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2008 2009 2010 2011
page 99
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
The following table summarises the timing of receipt of design drawings and information. It has been shown that although these drawings are significantly late, it has not affected progress at site.
The reason for this is the earlier delays caused by setting out and unforeseen ground conditions extended and revised the original start dates of many activities. Consequently, as the buildings revised schedule start date is much later than originally planned drawings issued for construction had no impact.
However, as a consequence of the lateness in receipt of detailed drawings, procurement of materials could not proceed as originally planned.
Item Building commencement completion commencement completion 1 P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-082 Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-083 Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-084 Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-085 GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-086 Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-087 Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-088 Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-089 Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-0810 Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0811 BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-0812 Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0813 Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-0814 Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-0815 Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0816 Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0817 Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0818 Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-0819 Mechanical Area 24-Oct-08 09-Jan-09 22-Oct-07 19-Feb-0820 3 Meal Restaurant 04-Sep-08 28-Mar-09 02-Jul-07 26-Mar-0821 Signature Pool 04-Sep-08 18-Mar-09 02-Jul-07 15-Mar-0822 Beach Pool Bar 04-Sep-08 19-Mar-09 02-Jul-07 17-Mar-08
Impacted Programme Baseline Programme
Delays’ resulting from hard rock excavation is a parallel delay to design drawings.
Items 1 - 18 relates to critical delays caused by hard rock excavation for preceding structures. Items 19 – 22 relates to delay arising from late design drawings, which is critical. More delays will be encountered once excavation works proceed at remaining locations.
As a result of the current delay caused by this event the time for completion has not extended the current revised date of 9 September 2009.
Consequently, the revised completion date remains at 9 September 2009.
page 100
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.4. Event No 4 – Increased Scope of Works
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
184 Villa A3/01
185 Substructure
193 Frame
194 set kickers
195 Conc. Columns & shear walls
196 Conc. G. F Beams
197 M&E first fix
198 Conc. Plantroom
199 Conc. Floor slab & swimming pool base
200 Blockwork
201 Conc. Swimming pool sides & overflow channels
202 Conc. Ring & tie beams
203 Roof & Ceiling
210 Finishes
217 M&E Installations
228 Villa A3/02
229 substructure
237 frame
238 set kickers
239 Conc. Columns & shear walls
240 Conc. G. F Beams
241 M&E first fix
242 Conc. Plantroom
243 Conc. Floor slab & swimming pool base
244 Blockwork
245 Conc. Swimming pool sides & overflow channels
246 Conc. Ring & tie beams
247 Roof & Ceiling
254 Finishes
262 M&E Installations
273 Villa A3/03
274 substructure
282 frame
283 set kickers
284 Conc. Columns & shear walls
285 Conc. G. F Beams
286 M&E first fix
287 Conc. Plantroom
288 Conc. Floor slab & swimming pool base
289 Blockwork
290 Conc. Swimming pool sides & overflow channels
291 Conc. Ring & tie beams
292 Roof & Ceiling
299 Finishes
307 M&E Installations
318 Villa A3/04
319 substructure
320 set out
321 Excavate
322 Conc. Foundation
323 Backfill
324 termite treatment
325 DPC (where applicable)
326 M&E inlet/outlet works - first fix
327 frame
328 set kickers
329 Conc. Columns & shear walls
330 Conc. G. F Beams
331 M&E first fix
332 Conc. Plantroom
333 Conc. Floor slab & swimming pool base
334 Blockwork
335 Conc. Swimming pool sides & overflow channels
336 Conc. Ring & tie beams
337 Roof & Ceiling
338 Fix wall plate & truss
339 Fix purlins and rafters
340 Fix shingles ( subject to receipt of timber)
341 Fix ceiing battens & joists
342 Fix ceiling boards
343 M&E first fix
344 Finishes
345 Wall plaster (internal & External)
346 M&E 1st fix
347 Floor finishes
348 Fix windows & doors
349 Swimming pool finishes
350 M&E final fix
351 Fix fittings and Fixtures
352 M&E Installations
353 Cable Tray, Conduit and Wiring
354 Electrical boards and connections
355 Electrical accessories
356 Light fittings and ceiling fans
357 Hot and cold water
358 Waste and sewage incl. biobox
359 Electric water heater
360 Swimming pool
361 Split unit installation
362 Toilet ventilation, grilles
363 Villa A3/05
364 substructure
365 set out
366 Excavate
367 Conc. Foundation
368 Backfill
369 termite treatment
370 DPC (where applicable)
371 M&E inlet/outlet works - first fix
372 frame
373 set kickers
374 Conc. Columns & shear walls
375 Conc. G. F Beams
376 M&E first fix
377 Conc. Plantroom
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
page 101
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
378 Conc. Floor slab & swimming pool base
379 Blockwork
380 Conc. Swimming pool sides & overflow channels
381 Conc. Ring & tie beams
382 Roof & Ceiling
383 Fix wall plate & truss
384 Fix purlins and rafters
385 Fix shingles ( subject to receipt of timber)
386 Fix ceiing battens & joists
387 Fix ceiling boards
388 M&E first fix
389 Finishes
390 Wall plaster (internal & External)
391 M&E 1st fix
392 Floor finishes
393 Fix windows & doors
394 Swimming pool finishes
395 M&E final fix
396 Fix fittings and Fixtures
397 M&E Installations
398 Cable Tray, Conduit and Wiring
399 Electrical boards and connections
400 Electrical accessories
401 Light fittings and ceiling fans
402 Hot and cold water
403 Waste and sewage incl. biobox
404 Electric water heater
405 Swimming pool
406 Split unit installation
407 Toilet ventilation, grilles
408 Villa A3/06
409 substructure
410 set out
411 Excavate
412 Conc. Foundation
413 Backfill
414 termite treatment
415 DPC (where applicable)
416 M&E inlet/outlet works - first fix
417 frame
418 set kickers
419 Conc. Columns & shear walls
420 Conc. G. F Beams
421 M&E first fix
422 Conc. Plantroom
423 Conc. Floor slab & swimming pool base
424 Blockwork
425 Conc. Swimming pool sides & overflow channels
426 Conc. Ring & tie beams
427 Roof & Ceiling
434 Finishes
442 M&E Installations
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
849 Villa A3/07
850 substructure
851 set out
852 Excavate
853 Conc. Foundation
854 Backfill
855 termite treatment
856 DPC (where applicable)
857 M&E inlet/outlet works - first fix
858 frame
859 set kickers
860 Conc. Columns & shear walls
861 Conc. G. F Beams
862 M&E first fix
863 Conc. Plantroom
864 Conc. Floor slab & swimming pool base
865 Blockwork
866 Conc. Swimming pool sides & overflow channels
867 Conc. Ring & tie beams
868 Roof & Ceiling
869 Fix wall plate & truss
870 Fix purlins and rafters
871 Fix shingles ( subject to receipt of timber)
872 Fix ceiing battens & joists
873 Fix ceiling boards
874 M&E first fix
875 Finishes
876 Wall plaster (internal & External)
877 M&E 1st fix
878 Floor finishes
879 Fix windows & doors
880 Swimming pool finishes
881 M&E final fix
882 Fix fittings and Fixtures
883 M&E Installations
884 Cable Tray, Conduit and Wiring
885 Electrical boards and connections
886 Electrical accessories
887 Light fittings and ceiling fans
888 Hot and cold water
889 Waste and sewage incl. biobox
890 Electric water heater
891 Swimming pool
892 Split unit installation
893 Toilet ventilation, grilles
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 102
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
894 Villa A3/08
895 substructure
896 set out
897 Excavate
898 Conc. Foundation
899 Backfill
900 termite treatment
901 DPC (where applicable)
902 M&E inlet/outlet works - first fix
903 frame
904 set kickers
905 Conc. Columns & shear walls
906 Conc. G. F Beams
907 M&E first fix
908 Conc. Plantroom
909 Conc. Floor slab & swimming pool base
910 Blockwork
911 Conc. Swimming pool sides & overflow channels
912 Conc. Ring & tie beams
913 Roof & Ceiling
920 Finishes
928 M&E Installations
939 Villa A3/09
940 substructure
941 set out
942 Excavate
943 Conc. Foundation
944 Backfill
945 termite treatment
946 DPC (where applicable)
947 M&E inlet/outlet works - first fix
948 frame
949 set kickers
950 Conc. Columns & shear walls
951 Conc. G. F Beams
952 M&E first fix
953 Conc. Plantroom
954 Conc. Floor slab & swimming pool base
955 Blockwork
956 Conc. Swimming pool sides & overflow channels
957 Conc. Ring & tie beams
958 Roof & Ceiling
965 Finishes
973 M&E Installations
984 Villa A3/10
985 substructure
986 set out
987 Excavate
988 Conc. Foundation
989 Backfill
990 termite treatment
991 DPC (where applicable)
992 M&E inlet/outlet works - first fix
993 frame
994 set kickers
995 Conc. Columns & shear walls
996 Conc. G. F Beams
997 M&E first fix
998 Conc. Plantroom
999 Conc. Floor slab & swimming pool base
1000 Blockwork
1001 Conc. Swimming pool sides & overflow channels
1002 Conc. Ring & tie beams
1003 Roof & Ceiling
1010 Finishes
1018 M&E Installations
1029 Villa A3/11
1030 substructure
1031 set out
1032 Excavate
1033 Conc. Foundation
1034 Backfill
1035 termite treatment
1036 DPC (where applicable)
1037 M&E inlet/outlet works - first fix
1038 frame
1039 set kickers
1040 Conc. Columns & shear walls
1041 Conc. G. F Beams
1042 M&E first fix
1043 Conc. Plantroom
1044 Conc. Floor slab & swimming pool base
1045 Blockwork
1046 Conc. Swimming pool sides & overflow channels
1047 Conc. Ring & tie beams
1048 Roof & Ceiling
1055 Finishes
1063 M&E Installations
1074 Villa A3/12
1075 substructure
1076 set out
1077 Excavate
1078 Conc. Foundation
1079 Backfill
1080 termite treatment
1081 DPC (where applicable)
1082 M&E inlet/outlet works - first fix
1083 frame
1084 set kickers
1085 Conc. Columns & shear walls
1086 Conc. G. F Beams
1087 M&E first fix
1088 Conc. Plantroom
1089 Conc. Floor slab & swimming pool base
1090 Blockwork
1091 Conc. Swimming pool sides & overflow channels
1092 Conc. Ring & tie beams
1093 Roof & Ceiling
1094 Fix wall plate & truss
1095 Fix purlins and rafters
1096 Fix shingles ( subject to receipt of timber)
1097 Fix ceiing battens & joists
1098 Fix ceiling boards
1099 M&E first fix
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 103
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1100 Finishes
1101 Wall plaster (internal & External)
1102 M&E 1st fix
1103 Floor finishes
1104 Fix windows & doors
1105 Swimming pool finishes
1106 M&E final fix
1107 Fix fittings and Fixtures
1108 M&E Installations
1109 Cable Tray, Conduit and Wiring
1110 Electrical boards and connections
1111 Electrical accessories
1112 Light fittings and ceiling fans
1113 Hot and cold water
1114 Waste and sewage incl. biobox
1115 Electric water heater
1116 Swimming pool
1117 Split unit installation
1118 Toilet ventilation, grilles
1119 Villa A3/13
1120 substructure
1121 set out
1122 Excavate
1123 Conc. Foundation
1124 Backfill
1125 termite treatment
1126 DPC (where applicable)
1127 M&E inlet/outlet works - first fix
1128 frame
1129 set kickers
1130 Conc. Columns & shear walls
1131 Conc. G. F Beams
1132 M&E first fix
1133 Conc. Plantroom
1134 Conc. Floor slab & swimming pool base
1135 Blockwork
1136 Conc. Swimming pool sides & overflow channels
1137 Conc. Ring & tie beams
1138 Roof & Ceiling
1139 Fix wall plate & truss
1140 Fix purlins and rafters
1141 Fix shingles ( subject to receipt of timber)
1142 Fix ceiing battens & joists
1143 Fix ceiling boards
1144 M&E first fix
1145 Finishes
1146 Wall plaster (internal & External)
1147 M&E 1st fix
1148 Floor finishes
1149 Fix windows & doors
1150 Swimming pool finishes
1151 M&E final fix
1152 Fix fittings and Fixtures
1153 M&E Installations
1154 Cable Tray, Conduit and Wiring
1155 Electrical boards and connections
1156 Electrical accessories
1157 Light fittings and ceiling fans
1158 Hot and cold water
1159 Waste and sewage incl. biobox
1160 Electric water heater
1161 Swimming pool
1162 Split unit installation
1163 Toilet ventilation, grilles
1164 Villa A3/18
1165 substructure
1166 set out
1167 Excavate
1168 Conc. Foundation
1169 Backfill
1170 termite treatment
1171 DPC (where applicable)
1172 M&E inlet/outlet works - first fix
1173 frame
1174 set kickers
1175 Conc. Columns & shear walls
1176 Conc. G. F Beams
1177 M&E first fix
1178 Conc. Plantroom
1179 Conc. Floor slab & swimming pool base
1180 Blockwork
1181 Conc. Swimming pool sides & overflow channels
1182 Conc. Ring & tie beams
1183 Roof & Ceiling
1184 Fix wall plate & truss
1185 Fix purlins and rafters
1186 Fix shingles ( subject to receipt of timber)
1187 Fix ceiing battens & joists
1188 Fix ceiling boards
1189 M&E first fix
1190 Finishes
1191 Wall plaster (internal & External)
1192 M&E 1st fix
1193 Floor finishes
1194 Fix windows & doors
1195 Swimming pool finishes
1196 M&E final fix
1197 Fix fittings and Fixtures
1198 M&E Installations
1199 Cable Tray, Conduit and Wiring
1200 Electrical boards and connections
1201 Electrical accessories
1202 Light fittings and ceiling fans
1203 Hot and cold water
1204 Waste and sewage incl. biobox
1205 Electric water heater
1206 Swimming pool
1207 Split unit installation
1208 Toilet ventilation, grilles
1209 Villa A3/19
1210 substructure
1211 set out
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 104
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1212 Excavate
1213 Conc. Foundation
1214 Backfill
1215 termite treatment
1216 DPC (where applicable)
1217 M&E inlet/outlet works - first fix
1218 frame
1219 set kickers
1220 Conc. Columns & shear walls
1221 Conc. G. F Beams
1222 M&E first fix
1223 Conc. Plantroom
1224 Conc. Floor slab & swimming pool base
1225 Blockwork
1226 Conc. Swimming pool sides & overflow channels
1227 Conc. Ring & tie beams
1228 Roof & Ceiling
1235 Finishes
1243 M&E Installations
1254 Villa A3/20
1255 substructure
1256 set out
1257 Excavate
1258 Conc. Foundation
1259 Backfill
1260 termite treatment
1261 DPC (where applicable)
1262 M&E inlet/outlet works - first fix
1263 frame
1264 set kickers
1265 Conc. Columns & shear walls
1266 Conc. G. F Beams
1267 M&E first fix
1268 Conc. Plantroom
1269 Conc. Floor slab & swimming pool base
1270 Blockwork
1271 Conc. Swimming pool sides & overflow channels
1272 Conc. Ring & tie beams
1273 Roof & Ceiling
1280 Finishes
1288 M&E Installations
1299 Villa A3/21
1300 substructure
1301 set out
1302 Excavate
1303 Conc. Foundation
1304 Backfill
1305 termite treatment
1306 DPC (where applicable)
1307 M&E inlet/outlet works - first fix
1308 frame
1309 set kickers
1310 Conc. Columns & shear walls
1311 Conc. G. F Beams
1312 M&E first fix
1313 Conc. Plantroom
1314 Conc. Floor slab & swimming pool base
1315 Blockwork
1316 Conc. Swimming pool sides & overflow channels
1317 Conc. Ring & tie beams
1318 Roof & Ceiling
1325 Finishes
1333 M&E Installations
1344 Villa A3/22
1345 substructure
1346 set out
1347 Excavate
1348 Conc. Foundation
1349 Backfill
1350 termite treatment
1351 DPC (where applicable)
1352 M&E inlet/outlet works - first fix
1353 frame
1354 set kickers
1355 Conc. Columns & shear walls
1356 Conc. G. F Beams
1357 M&E first fix
1358 Conc. Plantroom
1359 Conc. Floor slab & swimming pool base
1360 Blockwork
1361 Conc. Swimming pool sides & overflow channels
1362 Conc. Ring & tie beams
1363 Roof & Ceiling
1364 Fix wall plate & truss
1365 Fix purlins and rafters
1366 Fix shingles ( subject to receipt of timber)
1367 Fix ceiing battens & joists
1368 Fix ceiling boards
1369 M&E first fix
1370 Finishes
1371 Wall plaster (internal & External)
1372 M&E 1st fix
1373 Floor finishes
1374 Fix windows & doors
1375 Swimming pool finishes
1376 M&E final fix
1377 Fix fittings and Fixtures
1378 M&E Installations
1379 Cable Tray, Conduit and Wiring
1380 Electrical boards and connections
1381 Electrical accessories
1382 Light fittings and ceiling fans
1383 Hot and cold water
1384 Waste and sewage incl. biobox
1385 Electric water heater
1386 Swimming pool
1387 Split unit installation
1388 Toilet ventilation, grilles
1389 Villa A3/23
1390 substructure
1391 set out
1392 Excavate
1393 Conc. Foundation
1394 Backfill
1395 termite treatment
1396 DPC (where applicable)
1397 M&E inlet/outlet works - first fix
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 105
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1398 frame
1399 set kickers
1400 Conc. Columns & shear walls
1401 Conc. G. F Beams
1402 M&E first fix
1403 Conc. Plantroom
1404 Conc. Floor slab & swimming pool base
1405 Blockwork
1406 Conc. Swimming pool sides & overflow channels
1407 Conc. Ring & tie beams
1408 Roof & Ceiling
1409 Fix wall plate & truss
1410 Fix purlins and rafters
1411 Fix shingles ( subject to receipt of timber)
1412 Fix ceiing battens & joists
1413 Fix ceiling boards
1414 M&E first fix
1415 Finishes
1416 Wall plaster (internal & External)
1417 M&E 1st fix
1418 Floor finishes
1419 Fix windows & doors
1420 Swimming pool finishes
1421 M&E final fix
1422 Fix fittings and Fixtures
1423 M&E Installations
1424 Cable Tray, Conduit and Wiring
1425 Electrical boards and connections
1426 Electrical accessories
1427 Light fittings and ceiling fans
1428 Hot and cold water
1429 Waste and sewage incl. biobox
1430 Electric water heater
1431 Swimming pool
1432 Split unit installation
1433 Toilet ventilation, grilles
1434 Villa A3/24
1435 substructure
1436 set out
1437 Excavate
1438 Conc. Foundation
1439 Backfill
1440 termite treatment
1441 DPC (where applicable)
1442 M&E inlet/outlet works - first fix
1443 frame
1444 set kickers
1445 Conc. Columns & shear walls
1446 Conc. G. F Beams
1447 M&E first fix
1448 Conc. Plantroom
1449 Conc. Floor slab & swimming pool base
1450 Blockwork
1451 Conc. Swimming pool sides & overflow channels
1452 Conc. Ring & tie beams
1453 Roof & Ceiling
1454 Fix wall plate & truss
1455 Fix purlins and rafters
1456 Fix shingles ( subject to receipt of timber)
1457 Fix ceiing battens & joists
1458 Fix ceiling boards
1459 M&E first fix
1460 Finishes
1461 Wall plaster (internal & External)
1462 M&E 1st fix
1463 Floor finishes
1464 Fix windows & doors
1465 Swimming pool finishes
1466 M&E final fix
1467 Fix fittings and Fixtures
1468 M&E Installations
1469 Cable Tray, Conduit and Wiring
1470 Electrical boards and connections
1471 Electrical accessories
1472 Light fittings and ceiling fans
1473 Hot and cold water
1474 Waste and sewage incl. biobox
1475 Electric water heater
1476 Swimming pool
1477 Split unit installation
1478 Toilet ventilation, grilles
1479 Villa A3/25
1480 substructure
1481 set out
1482 Excavate
1483 Conc. Foundation
1484 Backfill
1485 termite treatment
1486 DPC (where applicable)
1487 M&E inlet/outlet works - first fix
1488 frame
1489 set kickers
1490 Conc. Columns & shear walls
1491 Conc. G. F Beams
1492 M&E first fix
1493 Conc. Plantroom
1494 Conc. Floor slab & swimming pool base
1495 Blockwork
1496 Conc. Swimming pool sides & overflow channels
1497 Conc. Ring & tie beams
1498 Roof & Ceiling
1499 Fix wall plate & truss
1500 Fix purlins and rafters
1501 Fix shingles ( subject to receipt of timber)
1502 Fix ceiing battens & joists
1503 Fix ceiling boards
1504 M&E first fix
1505 Finishes
1506 Wall plaster (internal & External)
1507 M&E 1st fix
1508 Floor finishes
1509 Fix windows & doors
1510 Swimming pool finishes
1511 M&E final fix
1512 Fix fittings and Fixtures
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 106
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1513 M&E Installations
1514 Cable Tray, Conduit and Wiring
1515 Electrical boards and connections
1516 Electrical accessories
1517 Light fittings and ceiling fans
1518 Hot and cold water
1519 Waste and sewage incl. biobox
1520 Electric water heater
1521 Swimming pool
1522 Split unit installation
1523 Toilet ventilation, grilles
1524 Villa A3/26
1525 substructure
1526 set out
1527 Excavate
1528 Conc. Foundation
1529 Backfill
1530 termite treatment
1531 DPC (where applicable)
1532 M&E inlet/outlet works - first fix
1533 frame
1534 set kickers
1535 Conc. Columns & shear walls
1536 Conc. G. F Beams
1537 M&E first fix
1538 Conc. Plantroom
1539 Conc. Floor slab & swimming pool base
1540 Blockwork
1541 Conc. Swimming pool sides & overflow channels
1542 Conc. Ring & tie beams
1543 Roof & Ceiling
1550 Finishes
1558 M&E Installations
1569 Villa A3/27
1570 substructure
1571 set out
1572 Excavate
1573 Conc. Foundation
1574 Backfill
1575 termite treatment
1576 DPC (where applicable)
1577 M&E inlet/outlet works - first fix
1578 frame
1579 set kickers
1580 Conc. Columns & shear walls
1581 Conc. G. F Beams
1582 M&E first fix
1583 Conc. Plantroom
1584 Conc. Floor slab & swimming pool base
1585 Blockwork
1586 Conc. Swimming pool sides & overflow channels
1587 Conc. Ring & tie beams
1588 Roof & Ceiling
1595 Finishes
1603 M&E Installations
1614 B223 Villas ( 7 nos)
1615 Villa B2/01
1616 substructure
1617 set out
1618 Excavate
1619 Conc. Foundation
1620 Backfill
1621 termite treatment
1622 DPC (where applicable)
1623 M&E inlet/outlet works - first fix
1624 frame
1625 set kickers
1626 Conc. Columns & shear walls to GF
1627 Conc. Plantrooms
1628 M&E first fix GF
1629 Conc. GF slab and beams
1630 Blockwork up to FF slab
1631 set kickers on GF
1632 Conc. Columns & shear walls to FF
1633 M&E first fix FF
1634 Conc. FF slab & beams
1635 Blockwork up to roof
1636 set kickers on FF
1637 Conc. Columns & shear walls to roof
1638 M&E first fix roof
1639 Conc. Ring & tie beams
1640 Roof & Ceiling
1647 Finishes
1654 M&E Installations
1665 Villa B2/02
1666 substructure
1667 set out
1668 Excavate
1669 Conc. Foundation
1670 Backfill
1671 termite treatment
1672 DPC (where applicable)
1673 M&E inlet/outlet works - first fix
1674 frame
1675 set kickers
1676 Conc. Columns & shear walls to GF
1677 Conc. Plantrooms
1678 M&E first fix GF
1679 Conc. GF slab and beams
1680 Blockwork up to FF slab
1681 set kickers on GF
1682 Conc. Columns & shear walls to FF
1683 M&E first fix FF
1684 Conc. FF slab & beams
1685 Blockwork up to roof
1686 set kickers on FF
1687 Conc. Columns & shear walls to roof
1688 M&E first fix roof
1689 Conc. Ring & tie beams
1690 Roof & Ceiling
1697 Finishes
1704 M&E Installations
1715 Villa B2/04
1716 substructure
1717 set out
1718 Excavate
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 107
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1719 Conc. Foundation
1720 Backfill
1721 termite treatment
1722 DPC (where applicable)
1723 M&E inlet/outlet works - first fix
1724 frame
1725 set kickers
1726 Conc. Columns & shear walls to GF
1727 Conc. Plantrooms
1728 M&E first fix GF
1729 Conc. GF slab and beams
1730 Blockwork up to FF slab
1731 set kickers on GF
1732 Conc. Columns & shear walls to FF
1733 M&E first fix FF
1734 Conc. FF slab & beams
1735 Blockwork up to roof
1736 set kickers on FF
1737 Conc. Columns & shear walls to roof
1738 M&E first fix roof
1739 Conc. Ring & tie beams
1740 Roof & Ceiling
1747 Finishes
1754 M&E Installations
1765 Villa B2/05
1766 substructure
1767 set out
1768 Excavate
1769 Conc. Foundation
1770 Backfill
1771 termite treatment
1772 DPC (where applicable)
1773 M&E inlet/outlet works - first fix
1774 frame
1775 set kickers
1776 Conc. Columns & shear walls to GF
1777 Conc. Plantrooms
1778 M&E first fix GF
1779 Conc. GF slab and beams
1780 Blockwork up to FF slab
1781 set kickers on GF
1782 Conc. Columns & shear walls to FF
1783 M&E first fix FF
1784 Conc. FF slab & beams
1785 Blockwork up to roof
1786 set kickers on FF
1787 Conc. Columns & shear walls to roof
1788 M&E first fix roof
1789 Conc. Ring & tie beams
1790 Roof & Ceiling
1797 Finishes
1804 M&E Installations
1815 Villa B2/06
1816 substructure
1817 set out
1818 Excavate
1819 Conc. Foundation
1820 Backfill
1821 termite treatment
1822 DPC (where applicable)
1823 M&E inlet/outlet works - first fix
1824 frame
1825 set kickers
1826 Conc. Columns & shear walls to GF
1827 Conc. Plantrooms
1828 M&E first fix GF
1829 Conc. GF slab and beams
1830 Blockwork up to FF slab
1831 set kickers on GF
1832 Conc. Columns & shear walls to FF
1833 M&E first fix FF
1834 Conc. FF slab & beams
1835 Blockwork up to roof
1836 set kickers on FF
1837 Conc. Columns & shear walls to roof
1838 M&E first fix roof
1839 Conc. Ring & tie beams
1840 Roof & Ceiling
1847 Finishes
1854 M&E Installations
1865 Villa B2/07
1866 substructure
1867 set out
1868 Excavate
1869 Conc. Foundation
1870 Backfill
1871 termite treatment
1872 DPC (where applicable)
1873 M&E inlet/outlet works - first fix
1874 frame
1875 set kickers
1876 Conc. Columns & shear walls to GF
1877 Conc. Plantrooms
1878 M&E first fix GF
1879 Conc. GF slab and beams
1880 Blockwork up to FF slab
1881 set kickers on GF
1882 Conc. Columns & shear walls to FF
1883 M&E first fix FF
1884 Conc. FF slab & beams
1885 Blockwork up to roof
1886 set kickers on FF
1887 Conc. Columns & shear walls to roof
1888 M&E first fix roof
1889 Conc. Ring & tie beams
1890 Roof & Ceiling
1897 Finishes
1904 M&E Installations
1915 Villa B2/08
1916 substructure
1917 set out
1918 Excavate
1919 Conc. Foundation
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 108
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1920 Backfill
1921 termite treatment
1922 DPC (where applicable)
1923 M&E inlet/outlet works - first fix
1924 frame
1925 set kickers
1926 Conc. Columns & shear walls to GF
1927 Conc. Plantrooms
1928 M&E first fix GF
1929 Conc. GF slab and beams
1930 Blockwork up to FF slab
1931 set kickers on GF
1932 Conc. Columns & shear walls to FF
1933 M&E first fix FF
1934 Conc. FF slab & beams
1935 Blockwork up to roof
1936 set kickers on FF
1937 Conc. Columns & shear walls to roof
1938 M&E first fix roof
1939 Conc. Ring & tie beams
1940 Roof & Ceiling
1947 Finishes
1954 M&E Installations
1965 B4 Villa (2 nos.)
2056 Retail 1( subject to receipt of GFW drawings)
2094 Retail 2( subject to receipt of GFW drawings)
2132 Retail 3( subject to receipt of GFW drawings)
2170 Seafood resort( subject to receipt of GFW drawings)
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2264 Villa A3/14
2265 Substructure
2266 set out
2267 Excavate
2268 Conc. Foundation
2269 Backfill
2270 termite treatment
2271 DPC (where applicable)
2272 M&E inlet/outlet works - first fix
2273 Frame
2274 set kickers
2275 Conc. Columns & shear walls
2276 Conc. G. F Beams
2277 M&E first fix
2278 Conc. Plantroom
2279 Conc. Floor slab & swimming pool base
2280 Blockwork
2281 Conc. Swimming pool sides & overflow channels
2282 Conc. Ring & tie beams
2283 Roof & Ceiling
2284 Fix wall plate & truss
2285 Fix purlins and rafters
2286 Fix shingles ( subject to receipt of timber)
2287 Fix ceiing battens & joists
2288 Fix ceiling boards
2289 M&E first fix
2290 Finishes
2291 Wall plaster (internal & External)
2292 M&E 1st fix
2293 Floor finishes
2294 Fix windows & doors
2295 Swimming pool finishes
2296 M&E final fix
2297 Fix fittings and Fixtures
2298 M&E Installations
2299 Cable Tray, Conduit and Wiring
2300 Electrical boards and connections
2301 Electrical accessories
2302 Light fittings and ceiling fans
2303 Hot and cold water
2304 Waste and sewage incl. biobox
2305 Electric water heater
2306 Swimming pool
2307 Split unit installation
2308 Toilet ventilation, grilles
2309 Villa A3/15
2310 substructure
2311 set out
2312 Excavate
2313 Conc. Foundation
2314 Backfill
2315 termite treatment
2316 DPC (where applicable)
2317 M&E inlet/outlet works - first fix
2318 frame
2319 set kickers
2320 Conc. Columns & shear walls
2321 Conc. G. F Beams
2322 M&E first fix
2323 Conc. Plantroom
2324 Conc. Floor slab & swimming pool base
2325 Blockwork
2326 Conc. Swimming pool sides & overflow channels
2327 Conc. Ring & tie beams
2328 Roof & Ceiling
2329 Fix wall plate & truss
2330 Fix purlins and rafters
2331 Fix shingles ( subject to receipt of timber)
2332 Fix ceiing battens & joists
2333 Fix ceiling boards
2334 M&E first fix
2335 Finishes
2336 Wall plaster (internal & External)
2337 M&E 1st fix
2338 Floor finishes
2339 Fix windows & doors
2340 Swimming pool finishes
2341 M&E final fix
2342 Fix fittings and Fixtures
2343 M&E Installations
2344 Cable Tray, Conduit and Wiring
2345 Electrical boards and connections
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 109
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2346 Electrical accessories
2347 Light fittings and ceiling fans
2348 Hot and cold water
2349 Waste and sewage incl. biobox
2350 Electric water heater
2351 Swimming pool
2352 Split unit installation
2353 Toilet ventilation, grilles
2354 Villa A3/16
2355 substructure
2356 set out
2357 Excavate
2358 Conc. Foundation
2359 Backfill
2360 termite treatment
2361 DPC (where applicable)
2362 M&E inlet/outlet works - first fix
2363 frame
2364 set kickers
2365 Conc. Columns & shear walls
2366 Conc. G. F Beams
2367 M&E first fix
2368 Conc. Plantroom
2369 Conc. Floor slab & swimming pool base
2370 Blockwork
2371 Conc. Swimming pool sides & overflow channels
2372 Conc. Ring & tie beams
2373 Roof & Ceiling
2374 Fix wall plate & truss
2375 Fix purlins and rafters
2376 Fix shingles ( subject to receipt of timber)
2377 Fix ceiing battens & joists
2378 Fix ceiling boards
2379 M&E first fix
2380 Finishes
2381 Wall plaster (internal & External)
2382 M&E 1st fix
2383 Floor finishes
2384 Fix windows & doors
2385 Swimming pool finishes
2386 M&E final fix
2387 Fix fittings and Fixtures
2388 M&E Installations
2389 Cable Tray, Conduit and Wiring
2390 Electrical boards and connections
2391 Electrical accessories
2392 Light fittings and ceiling fans
2393 Hot and cold water
2394 Waste and sewage incl. biobox
2395 Electric water heater
2396 Swimming pool
2397 Split unit installation
2398 Toilet ventilation, grilles
2399 Villa A3/17
2400 substructure
2401 set out
2402 Excavate
2403 Conc. Foundation
2404 Backfill
2405 termite treatment
2406 DPC (where applicable)
2407 M&E inlet/outlet works - first fix
2408 frame
2409 set kickers
2410 Conc. Columns & shear walls
2411 Conc. G. F Beams
2412 M&E first fix
2413 Conc. Plantroom
2414 Conc. Floor slab & swimming pool base
2415 Blockwork
2416 Conc. Swimming pool sides & overflow channels
2417 Conc. Ring & tie beams
2418 Roof & Ceiling
2419 Fix wall plate & truss
2420 Fix purlins and rafters
2421 Fix shingles ( subject to receipt of timber)
2422 Fix ceiing battens & joists
2423 Fix ceiling boards
2424 M&E first fix
2425 Finishes
2426 Wall plaster (internal & External)
2427 M&E 1st fix
2428 Floor finishes
2429 Fix windows & doors
2430 Swimming pool finishes
2431 M&E final fix
2432 Fix fittings and Fixtures
2433 M&E Installations
2434 Cable Tray, Conduit and Wiring
2435 Electrical boards and connections
2436 Electrical accessories
2437 Light fittings and ceiling fans
2438 Hot and cold water
2439 Waste and sewage incl. biobox
2440 Electric water heater
2441 Swimming pool
2442 Split unit installation
2443 Toilet ventilation, grilles
2444 Villa A3/28
2445 substructure
2446 set out
2447 Excavate
2448 Conc. Foundation
2449 Backfill
2450 termite treatment
2451 DPC (where applicable)
2452 M&E inlet/outlet works - first fix
2453 frame
2454 set kickers
2455 Conc. Columns & shear walls
2456 Conc. G. F Beams
2457 M&E first fix
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010
page 110
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2458 Conc. Plantroom
2459 Conc. Floor slab & swimming pool base
2460 Blockwork
2461 Conc. Swimming pool sides & overflow channels
2462 Conc. Ring & tie beams
2463 Roof & Ceiling
2470 Finishes
2478 M&E Installations
2489 Villa A3/29
2490 substructure
2491 set out
2492 Excavate
2493 Conc. Foundation
2494 Backfill
2495 termite treatment
2496 DPC (where applicable)
2497 M&E inlet/outlet works - first fix
2498 frame
2499 set kickers
2500 Conc. Columns & shear walls
2501 Conc. G. F Beams
2502 M&E first fix
2503 Conc. Plantroom
2504 Conc. Floor slab & swimming pool base
2505 Blockwork
2506 Conc. Swimming pool sides & overflow channels
2507 Conc. Ring & tie beams
2508 Roof & Ceiling
2515 Finishes
2523 M&E Installations
2534 Villa A3/30
2535 substructure
2536 set out
2537 Excavate
2538 Conc. Foundation
2539 Backfill
2540 termite treatment
2541 DPC (where applicable)
2542 M&E inlet/outlet works - first fix
2543 frame
2544 set kickers
2545 Conc. Columns & shear walls
2546 Conc. G. F Beams
2547 M&E first fix
2548 Conc. Plantroom
2549 Conc. Floor slab & swimming pool base
2550 Blockwork
2551 Conc. Swimming pool sides & overflow channels
2552 Conc. Ring & tie beams
2553 Roof & Ceiling
2560 Finishes
2568 M&E Installations
2579 Villa A3/31
2624 Villa A3/32
2625 substructure
2626 set out
2627 Excavate
2628 Conc. Foundation
2629 Backfill
2630 termite treatment
2631 DPC (where applicable)
2632 frame
2633 set kickers
2634 Conc. Columns & shear walls
2635 Conc. Ground Beams
2636 Conc. Plantroom
2637 Conc. Floor slab & swimming pool base
2638 Blockwork
2639 Conc. Swimming pool sides & overflow channels
2640 Conc. Ring & tie beams
2641 Roof & Ceiling
2647 Finishes
2653 M&E Installations
2664 B223 Villas ( 3 nos)
2665 Villa B2/03
2666 substructure
2667 set out
2668 Excavate
2669 Conc. Foundation
2670 Backfill
2671 termite treatment
2672 DPC (where applicable)
2673 frame
2674 set kickers
2675 Conc. Columns & shear walls to GF
2676 Conc. Plantrooms
2677 Conc. GF slab and beams
2678 Blockwork up to FF slab
2679 set kickers on GF
2680 Conc. Columns & shear walls to FF
2681 Conc. FF slab & beams
2682 Blockwork up to roof
2683 set kickers on FF
2684 Conc. Columns & shear walls to roof
2685 Conc. Ring & tie beams
2686 Roof & Ceiling
2692 Finishes
2697 M&E Installations
2708 Villa B2/09
2709 substructure
2710 set out
2711 Excavate
2712 Conc. Foundation
2713 Backfill
2714 termite treatment
2715 DPC (where applicable)
2716 M&E inlet/outlet works - first fix
2717 frame
2718 set kickers
2719 Conc. Columns & shear walls to GF
2720 Conc. Plantrooms
2721 M&E first fix GF
2722 Conc. GF slab and beams
2723 Blockwork up to FF slab
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan2007 2008 2009 2010
page 111
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2724 set kickers on GF
2725 Conc. Columns & shear walls to FF
2726 M&E first fix FF
2727 Conc. FF slab & beams
2728 Blockwork up to roof
2729 set kickers on FF
2730 Conc. Columns & shear walls to roof
2731 M&E first fix roof
2732 Conc. Ring & tie beams
2733 Roof & Ceiling
2740 Finishes
2747 M&E Installations
2758 Villa B2/10
2759 substructure
2760 set out
2761 Excavate
2762 Conc. Foundation
2763 Backfill
2764 termite treatment
2765 DPC (where applicable)
2766 M&E inlet/outlet works - first fix
2767 frame
2768 set kickers
2769 Conc. Columns & shear walls to GF
2770 Conc. Plantrooms
2771 M&E first fix GF
2772 Conc. GF slab and beams
2773 Blockwork up to FF slab
2774 set kickers on GF
2775 Conc. Columns & shear walls to FF
2776 M&E first fix FF
2777 Conc. FF slab & beams
2778 Blockwork up to roof
2779 set kickers on FF
2780 Conc. Columns & shear walls to roof
2781 M&E first fix roof
2782 Conc. Ring & tie beams
2783 Roof & Ceiling
2790 Finishes
2797 M&E Installations
2808 B4 Standard Villas ( 2 nos)
2899 BC311 Executive Villa
3115 P3 Presidential suites ( 3 nos)
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2007 2008 2009 2010
The following table summarises the revised durations to perform a significantly revised scope of work depicted on the design drawings issued for construction. It should be noted the delay indicated on the extreme right column also includes the earlier delays caused by the setting out, unforeseen ground conditions and design drawings.
Once again, the revised durations are not critical to completion but activities typically take longer than planned.
page 112
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13 261.00A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08 370.96A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13 214.00A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08 33.00A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08 416.96A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08 428.96A3/12 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00A3/13 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00A3/14 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/15 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/16 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/17 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/18 12-Apr-07 15-Mar-08 12-Apr-07 15-Mar-08 338.13 338.13 0.00A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13 455.00A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13 427.00A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13 440.00A3/22 12-Apr-07 13-Sep-08 12-Apr-07 15-Mar-08 338.13 520.33 182.21A3/23 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/24 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/25 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08 296.96A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00A3/32 28-May-07 10-Dec-07 28-May-07 16-Nov-07 172.04 196.38 24.33B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08 403.96B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08 178.96B2/03 28-May-07 17-Jan-08 28-May-07 04-Dec-07 190.17 234.17 44.00B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13 287.00B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13 377.00B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13 155.00B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13 362.00B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13 368.00
Impacted Programme Baseline Programme
As a result of the extended durations caused by this event the time for completion has not been extended and the revised completion date remains at 9 September 2009.
The revised completion date remains at 9 September 2009.
page 113
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.5. Event No 5 – Partial Suspension of Works
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
184 Villa A3/01
228 Villa A3/02
273 Villa A3/03
274 substructure
275 set out
276 Excavate
277 Conc. Foundation
278 Backfill
279 termite treatment
280 DPC (where applicable)
281 M&E inlet/outlet works - first fix
282 frame
283 set kickers
284 Conc. Columns & shear walls
285 Conc. G. F Beams
286 M&E first fix
287 Conc. Plantroom
288 Conc. Floor slab & swimming pool base
289 Blockwork
290 Conc. Swimming pool sides & overflow channels
291 Conc. Ring & tie beams
292 Roof & Ceiling
299 Finishes
307 M&E Installations
318 Villa A3/04
319 substructure
320 set out
321 Excavate
322 Conc. Foundation
323 Backfill
324 termite treatment
325 DPC (where applicable)
326 M&E inlet/outlet works - first fix
327 frame
328 set kickers
329 Conc. Columns & shear walls
330 Conc. G. F Beams
331 M&E first fix
332 Conc. Plantroom
333 Conc. Floor slab & swimming pool base
334 Blockwork
335 Conc. Swimming pool sides & overflow channels
336 Conc. Ring & tie beams
337 Roof & Ceiling
338 Fix wall plate & truss
339 Fix purlins and rafters
340 Fix shingles ( subject to receipt of timber)
341 Fix ceiing battens & joists
342 Fix ceiling boards
343 M&E first fix
344 Finishes
345 Wall plaster (internal & External)
346 M&E 1st fix
347 Floor finishes
348 Fix windows & doors
349 Swimming pool finishes
350 M&E final fix
351 Fix fittings and Fixtures
352 M&E Installations
353 Cable Tray, Conduit and Wiring
354 Electrical boards and connections
355 Electrical accessories
356 Light fittings and ceiling fans
357 Hot and cold water
358 Waste and sewage incl. biobox
359 Electric water heater
360 Swimming pool
361 Split unit installation
362 Toilet ventilation, grilles
363 Villa A3/05
364 substructure
365 set out
366 Excavate
367 Conc. Foundation
368 Backfill
369 termite treatment
370 DPC (where applicable)
371 M&E inlet/outlet works - first fix
372 frame
373 set kickers
374 Conc. Columns & shear walls
375 Conc. G. F Beams
376 M&E first fix
377 Conc. Plantroom
378 Conc. Floor slab & swimming pool base
379 Blockwork
380 Conc. Swimming pool sides & overflow channels
381 Conc. Ring & tie beams
382 Roof & Ceiling
383 Fix wall plate & truss
384 Fix purlins and rafters
385 Fix shingles ( subject to receipt of timber)
386 Fix ceiing battens & joists
387 Fix ceiling boards
388 M&E first fix
389 Finishes
390 Wall plaster (internal & External)
391 M&E 1st fix
392 Floor finishes
393 Fix windows & doors
394 Swimming pool finishes
395 M&E final fix
396 Fix fittings and Fixtures
397 M&E Installations
398 Cable Tray, Conduit and Wiring
399 Electrical boards and connections
400 Electrical accessories
401 Light fittings and ceiling fans
402 Hot and cold water
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep2007 2008 2009
page 114
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
403 Waste and sewage incl. biobox
404 Electric water heater
405 Swimming pool
406 Split unit installation
407 Toilet ventilation, grilles
408 Villa A3/06
409 substructure
410 set out
411 Excavate
412 Conc. Foundation
413 Backfill
414 termite treatment
415 DPC (where applicable)
416 M&E inlet/outlet works - first fix
417 frame
418 set kickers
419 Conc. Columns & shear walls
420 Conc. G. F Beams
421 M&E first fix
422 Conc. Plantroom
423 Conc. Floor slab & swimming pool base
424 Blockwork
425 Conc. Swimming pool sides & overflow channels
426 Conc. Ring & tie beams
427 Roof & Ceiling
434 Finishes
442 M&E Installations
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
849 Villa A3/07
894 Villa A3/08
895 substructure
896 set out
897 Excavate
898 Conc. Foundation
899 Backfill
900 termite treatment
901 DPC (where applicable)
902 M&E inlet/outlet works - first fix
903 frame
904 set kickers
905 Conc. Columns & shear walls
906 Conc. G. F Beams
907 M&E first fix
908 Conc. Plantroom
909 Conc. Floor slab & swimming pool base
910 Blockwork
911 Conc. Swimming pool sides & overflow channels
912 Conc. Ring & tie beams
913 Roof & Ceiling
920 Finishes
928 M&E Installations
939 Villa A3/09
984 Villa A3/10
985 substructure
986 set out
987 Excavate
988 Conc. Foundation
989 Backfill
990 termite treatment
991 DPC (where applicable)
992 M&E inlet/outlet works - first fix
993 frame
994 set kickers
995 Conc. Columns & shear walls
996 Conc. G. F Beams
997 M&E first fix
998 Conc. Plantroom
999 Conc. Floor slab & swimming pool base
1000 Blockwork
1001 Conc. Swimming pool sides & overflow channels
1002 Conc. Ring & tie beams
1003 Roof & Ceiling
1010 Finishes
1018 M&E Installations
1029 Villa A3/11
1074 Villa A3/12
1119 Villa A3/13
1164 Villa A3/18
1209 Villa A3/19
1254 Villa A3/20
1299 Villa A3/21
1344 Villa A3/22
1389 Villa A3/23
1434 Villa A3/24
1479 Villa A3/25
1524 Villa A3/26
1569 Villa A3/27
1570 substructure
1571 set out
1572 Excavate
1573 Conc. Foundation
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
page 115
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
1574 Backfill
1575 termite treatment
1576 DPC (where applicable)
1577 M&E inlet/outlet works - first fix
1578 frame
1579 set kickers
1580 Conc. Columns & shear walls
1581 Conc. G. F Beams
1582 M&E first fix
1583 Conc. Plantroom
1584 Conc. Floor slab & swimming pool base
1585 Blockwork
1586 Conc. Swimming pool sides & overflow channels
1587 Conc. Ring & tie beams
1588 Roof & Ceiling
1595 Finishes
1603 M&E Installations
1614 B223 Villas ( 7 nos)
1615 Villa B2/01
1665 Villa B2/02
1666 substructure
1667 set out
1668 Excavate
1669 Conc. Foundation
1670 Backfill
1671 termite treatment
1672 DPC (where applicable)
1673 M&E inlet/outlet works - first fix
1674 frame
1675 set kickers
1676 Conc. Columns & shear walls to GF
1677 Conc. Plantrooms
1678 M&E first fix GF
1679 Conc. GF slab and beams
1680 Blockwork up to FF slab
1681 set kickers on GF
1682 Conc. Columns & shear walls to FF
1683 M&E first fix FF
1684 Conc. FF slab & beams
1685 Blockwork up to roof
1686 set kickers on FF
1687 Conc. Columns & shear walls to roof
1688 M&E first fix roof
1689 Conc. Ring & tie beams
1690 Roof & Ceiling
1697 Finishes
1704 M&E Installations
1715 Villa B2/04
1765 Villa B2/05
1815 Villa B2/06
1865 Villa B2/07
1915 Villa B2/08
1965 B4 Villa (2 nos.)
2056 Retail 1( subject to receipt of GFW drawings)
2094 Retail 2( subject to receipt of GFW drawings)
2132 Retail 3( subject to receipt of GFW drawings)
2170 Seafood resort( subject to receipt of GFW drawings)
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2264 Villa A3/14
2309 Villa A3/15
2354 Villa A3/16
2399 Villa A3/17
2444 Villa A3/28
2445 substructure
2446 set out
2447 Excavate
2448 Conc. Foundation
2449 Backfill
2450 termite treatment
2451 DPC (where applicable)
2452 M&E inlet/outlet works - first fix
2453 frame
2454 set kickers
2455 Conc. Columns & shear walls
2456 Conc. G. F Beams
2457 M&E first fix
2458 Conc. Plantroom
2459 Conc. Floor slab & swimming pool base
2460 Blockwork
2461 Conc. Swimming pool sides & overflow channels
2462 Conc. Ring & tie beams
2463 Roof & Ceiling
2470 Finishes
2478 M&E Installations
2489 Villa A3/29
2490 substructure
2491 set out
2492 Excavate
2493 Conc. Foundation
2494 Backfill
2495 termite treatment
2496 DPC (where applicable)
2497 M&E inlet/outlet works - first fix
2498 frame
2499 set kickers
2500 Conc. Columns & shear walls
2501 Conc. G. F Beams
2502 M&E first fix
2503 Conc. Plantroom
2504 Conc. Floor slab & swimming pool base
2505 Blockwork
2506 Conc. Swimming pool sides & overflow channels
2507 Conc. Ring & tie beams
2508 Roof & Ceiling
2515 Finishes
2523 M&E Installations
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
page 116
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2534 Villa A3/30
2535 substructure
2536 set out
2537 Excavate
2538 Conc. Foundation
2539 Backfill
2540 termite treatment
2541 DPC (where applicable)
2542 M&E inlet/outlet works - first fix
2543 frame
2544 set kickers
2545 Conc. Columns & shear walls
2546 Conc. G. F Beams
2547 M&E first fix
2548 Conc. Plantroom
2549 Conc. Floor slab & swimming pool base
2550 Blockwork
2551 Conc. Swimming pool sides & overflow channels
2552 Conc. Ring & tie beams
2553 Roof & Ceiling
2560 Finishes
2568 M&E Installations
2579 Villa A3/31
2580 substructure
2581 set out
2582 Excavate
2583 Conc. Foundation
2584 Backfill
2585 termite treatment
2586 DPC (where applicable)
2587 M&E inlet/outlet works - first fix
2588 frame
2589 set kickers
2590 Conc. Columns & shear walls
2591 Conc. G. F Beams
2592 M&E first fix
2593 Conc. Plantroom
2594 Conc. Floor slab & swimming pool base
2595 Blockwork
2596 Conc. Swimming pool sides & overflow channels
2597 Conc. Ring & tie beams
2598 Roof & Ceiling
2599 Fix wall plate & truss
2600 Fix purlins and rafters
2601 Fix shingles ( subject to receipt of timber)
2602 Fix ceiing battens & joists
2603 Fix ceiling boards
2604 M&E first fix
2605 Finishes
2606 Wall plaster (internal & External)
2607 M&E 1st fix
2608 Floor finishes
2609 Fix windows & doors
2610 Swimming pool finishes
2611 M&E final fix
2612 Fix fittings and Fixtures
2613 M&E Installations
2614 Cable Tray, Conduit and Wiring
2615 Electrical boards and connections
2616 Electrical accessories
2617 Light fittings and ceiling fans
2618 Hot and cold water
2619 Waste and sewage incl. biobox
2620 Electric water heater
2621 Swimming pool
2622 Split unit installation
2623 Toilet ventilation, grilles
2624 Villa A3/32
2664 B223 Villas ( 3 nos)
2665 Villa B2/03
2708 Villa B2/09
2758 Villa B2/10
2808 B4 Standard Villas ( 2 nos)
2899 BC311 Executive Villa
3115 P3 Presidential suites ( 3 nos)
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov2007 2008 2009
The following table shows the individual delays arising at each villa suspended which also incorporates the delays described in Event 1 through to 4.
page 117
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00A3/06 09-Apr-07 05-Aug-08 23-Jul-07 15-Mar-08 236.13 484.38 248.25A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00B2/02 16-Apr-07 13-Sep-08 03-Jul-07 15-Mar-08 256.13 516.33 260.21
Impacted Programme Baseline Programme
As a result the delay caused by this event is not critical and the time for completion has not extended the revised date of 9 September 2009.
Consequently, the revised completion date remains at 9 September 2009.
page 118
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.1.4.6. Event No 6 – Design Variations (Stainless Steel Items)
ID Task Name
1 SHANGRI-LA , Long Island Resort Seychelles
2 General Conditions and Preliminaries
17 Site establishment
41 Material/equipment procurement
182 Lot 1
183 A3 Villas ( 6 nos)
184 Villa A3/01
228 Villa A3/02
273 Villa A3/03
318 Villa A3/04
363 Villa A3/05
408 Villa A3/06
453 C311 Executive Villas ( 1 nos)
497 GM Villa ( subject to receipt of GFW drawings)
537 Employees Facilities ( subject to receipt of GFW drawings)
581 Laundry F& B service office ( subject to receipt of GFW drawings)
625 Health Club/ Medical Centre( subject to receipt of GFW drawings)
666 Administration Block ( subject to receipt of GFW drawings)
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings)
750 Main Lobby ( subject to receipt of GFW drawings)
791 Tennis Courts ( subject to receipt of GFW drawings)
807 External works ( subject to receipt of GFW drawings)
816 Drainage works ( subject to receipt of EME details)
819 Fuel Farm ( subject to receipt of EME details)
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details)
827 Desalination plant( subject to receipt of EME details)
831 MLV Panel( subject to receipt of EME details)
835 Step Up Transformer( subject to receipt of EME details)
839 Incinerator/ Garbage room( subject to receipt of EME details)
843 Sewer treatement plant( subject to receipt of EME details)
847 Lot 2
848 A3 Villas (17 nos)
849 Villa A3/07
894 Villa A3/08
939 Villa A3/09
984 Villa A3/10
1029 Villa A3/11
1074 Villa A3/12
1119 Villa A3/13
1164 Villa A3/18
1209 Villa A3/19
1254 Villa A3/20
1299 Villa A3/21
1344 Villa A3/22
1389 Villa A3/23
1434 Villa A3/24
1479 Villa A3/25
1524 Villa A3/26
1569 Villa A3/27
1614 B223 Villas ( 7 nos)
1615 Villa B2/01
1665 Villa B2/02
1715 Villa B2/04
1765 Villa B2/05
1815 Villa B2/06
1865 Villa B2/07
1915 Villa B2/08
1965 B4 Villa (2 nos.)
2056 Retail 1( subject to receipt of GFW drawings)
2094 Retail 2( subject to receipt of GFW drawings)
2132 Retail 3( subject to receipt of GFW drawings)
2170 Seafood resort( subject to receipt of GFW drawings)
2211 Greeting Pavillion( subject to receipt of GFW drawings)
2250 External works ( subject to receipt of GFW drawings)
2259 Drainage works ( subject to receipt of EME details)
2262 Lot 3
2263 A3 Villas ( 9 nos)
2264 Villa A3/14
2309 Villa A3/15
2354 Villa A3/16
2399 Villa A3/17
2444 Villa A3/28
2489 Villa A3/29
2534 Villa A3/30
2579 Villa A3/31
2624 Villa A3/32
2625 substructure
2626 set out
2627 Excavate
2628 Conc. Foundation
2629 Backfill
2630 termite treatment
2631 DPC (where applicable)
2632 frame
2633 set kickers
2634 Conc. Columns & shear walls
2635 Conc. Ground Beams
2636 Conc. Plantroom
2637 Conc. Floor slab & swimming pool base
2638 Blockwork
2639 Conc. Swimming pool sides & overflow channels
2640 Conc. Ring & tie beams
2641 Roof & Ceiling
2642 Fix wall plate & truss
2643 Fix purlins and rafters
2644 Fix shingles ( subject to receipt of timber)
2645 Fix ceiing battens & joists
2646 Fix ceiling boards
2647 Finishes
2648 Wall plaster (internal & External)
2649 Floor finishes
2650 Fix windows & doors
2651 Swimming pool finishes
2652 Fix fittings and Fixtures
2653 M&E Installations
2654 Cable Tray, Conduit and Wiring
2655 Electrical boards and connections
2656 Electrical accessories
2657 Light fittings and ceiling fans
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep2007 2008 2009
page 119
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Task Name
2658 Hot and cold water
2659 Waste and sewage incl. biobox
2660 Electric water heater
2661 Swimming pool
2662 Split unit installation
2663 Toilet ventilation, grilles
2664 B223 Villas ( 3 nos)
2665 Villa B2/03
2666 substructure
2667 set out
2668 Excavate
2669 Conc. Foundation
2670 Backfill
2671 termite treatment
2672 DPC (where applicable)
2673 frame
2674 set kickers
2675 Conc. Columns & shear walls to GF
2676 Conc. Plantrooms
2677 Conc. GF slab and beams
2678 Blockwork up to FF slab
2679 set kickers on GF
2680 Conc. Columns & shear walls to FF
2681 Conc. FF slab & beams
2682 Blockwork up to roof
2683 set kickers on FF
2684 Conc. Columns & shear walls to roof
2685 Conc. Ring & tie beams
2686 Roof & Ceiling
2687 Fix wall plate & truss
2688 Fix purlins and rafters
2689 Fix shingles ( subject to receipt of timber)
2690 Fix ceiing battens & joists
2691 Fix ceiling boards
2692 Finishes
2693 Wall plaster (internal & External)
2694 Floor finishes
2695 Fix windows & doors
2696 Fix fittings and Fixtures
2697 M&E Installations
2698 Cable Tray, Conduit and Wiring
2699 Electrical boards and connections
2700 Electrical accessories
2701 Light fittings and ceiling fans
2702 Hot and cold water
2703 Waste and sewage incl. biobox
2704 Electric water heater
2705 Swimming pool ( not applicable)
2706 Split unit installation
2707 Toilet ventilation, grilles
2708 Villa B2/09
2758 Villa B2/10
2808 B4 Standard Villas ( 2 nos)
2899 BC311 Executive Villa
3115 P3 Presidential suites ( 3 nos)
3245 Hilltop sunset deck( subject to receipt of GFW drawings)
3280 External works ( subject to receipt of GFW drawings)
3289 Drainage works ( subject to receipt of EME details)
3292 Lot 4
3293 Couple treatment room( subject to receipt of GFW drawings)
3334 Single treatment room( subject to receipt of GFW drawings)
3375 Dive Centre( subject to receipt of GFW drawings)
3413 Kid's club( subject to receipt of GFW drawings)
3452 Recreation House( subject to receipt of GFW drawings)
3491 Watersports rental( subject to receipt of GFW drawings)
3529 3 Meals restaurant( subject to receipt of GFW drawings)
3570 Beach Pool Bar( subject to receipt of GFW drawings)
3611 Signature Pool area( subject to receipt of GFW drawings)
3650 Wedding Chapel( subject to receipt of GFW drawings)
3685 BOH/Admin Building( subject to receipt of GFW drawings)
3726 Chi Sanctum( subject to receipt of GFW drawings)
3767 Yoga Pavillion( subject to receipt of GFW drawings)
3805 External works ( subject to receipt of GFW drawings)
3814 Drainage works ( subject to receipt of EME details)
3817 M&E Installations- External
3828 Sundries
3829 Site cleaning & demobilisation
3830 Project Commissioning
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2007 2008 2009
Similarly, the following table shows the delay which occurred at the Mock-up Villas. Again, this delay is not critical to completion because of the earlier delays.
Villa commencement completion commencement completion Baseline duration Revised Duration DelayA3/32 28-May-07 19-Mar-08 28-May-07 16-Nov-07 172.04 296.17 124.13B2/03 28-May-07 12-May-08 28-May-07 04-Dec-07 190.17 350.38 160.21
Impacted Programme Baseline Programme
page 120
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
5.2. Conclusion
At the outset of the Contract the Contractor suffered delays in setting out the works. This was followed by significant disruption caused by excavation in hard rock and partial suspension of Works. With respect to the Contract and the Contractor’s Programme of Works to which consent has been given, such departure from his original planning has caused significant increased cost. In addition, significant increases in quantities of work caused the Contractor to fall further behind his programme.
The Project Manager also required the Contractor to perform his work in accordance with the Programme of Works. In addition, he has the duty to provide correct design details, in conformance with site conditions, to the Contractor in good time for him to be able to perform his material procurement and construction work in accordance with that programme.
By altering the sequence, timing and quality of the design details supplied to the Contractor, the Project Manager has acted outside the boundaries of the existing Contract provisions.
In failing to provide final survey data, unnecessarily suspending Works, failing to have identified and have taken account site conditions, and not providing design information to the Contractor in accordance with the Programme of Works, the Employer is in breach of his obligations (through the Project Manager in respect of design information) under the terms of the Contract.
Furthermore, by altering the sequence, timing and quality of the design information, when it was eventually provided to the Contractor, the Project Manager has required the Contractor to operate in a manner different from, slower and more expensive than had been shown on the Programme of Works than he had reasonably anticipated at the time of tender.
The consequences of this breach and variance of the Contract, in terms of time for completion and financial compensation, are explained in previous and subsequent sections of this submission.
page 121
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
6. Financial Analysis
6.1. Consequences
During the periods of delay and disruption which results directly from the varied site circumstances, varied scope of work, piece-meal work or an adverse condition, the Contractor has incurred costs of reduced and non-productive work necessitated by retaining levels of resources, which otherwise would have been decreased or deployed elsewhere. The Contractor would maintain that it was not reasonable to discharge Staff and Labour and remove equipment off Site for those periods. These costs include idle equipment and labour and other direct costs, and are recoverable under the terms and conditions of contract.
Furthermore, in response to the change in timing and sequence of the Works, the Contractor has reorganised his resources to meet the varied circumstances. As a consequence of such measures to improve his production, loss of efficiency costs caused by overtime, extra crews, larger crews, crowding or stacking of trades, are recoverable costs under the terms and conditions of contract. These additional costs are Wasted Costs (in order to use one title to capture all delaying events) and are recoverable as a Variation under the terms of the Contract.
Finally, because of the delays, which are not the fault of the Contractor, substantial completion of the whole Works can only be achieved beyond the original date. Consequently, the Contractor will incur additional costs in the extended period that is not recovered through the rates and prices of the contract.
An aspect of delay-induced expense is the cost of continuing work on a project over a longer time than first anticipated. Additional costs of labour, equipment and overhead has been incurred due to the fact that performance had to be spread out, sometimes leaving the Contractor’s resources idle or forced personnel and equipment to remain thus postponing other work sites.
Therefore, the amount of recovery is based on the total amount of cost expended during the period the contract was delayed. At the time of preparing this claim submission, delays and disruption continue and consequently, additional costs.
The Contractor is entitled to recover the cost of his resources, overheads and profit for this period. The additional costs will fall under three categories:
page 122
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
6.1.1.Direct Cost
The direct cost of this event, delay and disruption, is the cost of labour, staff and equipment directly employed at the Site including profit.
6.1.2.Indirect Cost
Indirect cost flows from on-site establishments such as the Contractor’s head and site offices and yard, which overheads are only partially recovered during the periods of planned construction operations when extended.
6.1.3.Consequential Cost
The consequential cost is the effect on the work in terms of disruption to the various activities and prolongation of the Contractor’s time related resources arising from re-sequencing the planned work.
This cause occurred at the outset of the project and disruption has been assessed as significant. The change, impacts planned logic and links of many tasks shown on his Programme of Works on which, the Contractor is heavily dependant if he is to retain his original tender cost provisions.
6.2. Costs in Extended Contract Period
6.2.1.Nature of Loss and Expense
The loss and expense flowing from the causes described in this Document are time-related. The loss and expense attributable to these causes has been incurred over all of the Periods identified in this claim. However, the major period in which variations have caused loss and expense is:
In the period of construction to date, May 2008, and
In the extended construction period.
page 123
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
6.2.2.Contractor’s Entitlement to Reimbursement
Instructions issued are covered by the first paragraph of Clause 13.1 of the Conditions. This refers to Instructions in regard to:
Revised setting out details;
Suspension of Work;
Design drawings issued for construction; and
Additional and varied works.
The criteria for allowing the Contractor reimbursement are given in the penultimate paragraph of Clause 12.3:
Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived from the reasonable Cost of executing the work, together with profit, taking account of any other relevant matters.
The loss and expense were not provided for, nor reasonably contemplated by, the Contract. The Instructions did not result from a breach by the Contractor. Accordingly, the loss and expense must be added to the Contract Price.
6.3. Finance Cost
As this is a claim for breach of contract, the Contractor’s approach to the quantum, or the measure of damage, is to follow the common law rule. This is that the damages should put the complaining party in the position he would have been, had the breach not taken place, insofar as damages can do that.
In order to attain this, the Contractor has approached the calculation of the quantum of the damages by asking what would have happened, had the breach not taken place, and comparing that with what did actually happen. The measure of the damage is the financial consequences flowing from the difference between the two positions.
There is one generic type of potential direct damage suffered while the other is the financing of the work. Those two aspects are summarised in the two points below:
page 124
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
1. Loss of anticipated income by way of financing. This is the cost to the Contractor of financing the shortfall between the income he reasonably expected to receive, and what he actually received.
2. The idle time, and/or reduced output, of resources from the outset of the contract to the present date.
In addition, for the purpose of satisfying the Employer’s requirements for identifying additional costs, the Contractor has also included additional costs anticipated to January 2010. This date is the latest the Contractor anticipates reaching substantial completion given all the varying circumstances existing at site.
6.4. Conclusions
In failing to provide final survey data and all the various design details, the unforeseen ground conditions, instructing suspension of the Works and subsequently altering the sequence, timing and logic of his original planning, the Employer has caused the Contractor to unavoidably incur greater costs, loss and expense than would have been the case had the failure not occurred. These costs are evaluated in subsequent sections of this submission.
Since these costs, losses and expense have flowed directly from the Employer’s failure and subsequent deviation from the terms of the Contract, the Contractor is entitled to be compensated for them by the Employer paying a fair value for the different type of work that has been performed.
page 125
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
7. Extension of Time Entitlement
The Project Manager is requested to refer to the Contractor’s two separate submissions for extensions of time and the detailed analysis included in those submissions.
The Contractor had planned that all his resources would be deployed at Site from 7 March 2007 through to 31 May 2008. In the event, because of circumstances beyond his control and not his responsibility, it is anticipated resources of the Contractor will be delayed at Site until 31 January 2010.
Therefore, in order to complete the whole Works, the Contractor requires a further 20 months to reach substantial completion. This includes the first and second requests for an interim extension of the period to Completion, whereas:
First. Requested on 21 November 2007 for an extension of time amounting to 191-calendar days from 31 May 2008 to 8 December 2008. The Project Manager’s determination has not been issued at time of compiling this submission;
Second. Requested on 14 March 2008 for an extension of time amounting to 106-calendar days from 8 December 2008 to 24 March 2009. The Project Manager’s determination has not been issued at time of compiling this submission.
The Contractor on 19 November 2007 had also updated his programme of works showing progress achieved at 6 November 2007. In the final paragraph he stated:
Unless notice is received stating the extent to which it does not comply with the Contract, we shall proceed in accordance with this programme and will rely upon this programme when planning our activities.
The Project Manager has not responded to this notice at time of compiling this submission or to making an interim determination for an extension of time requested in neither the Contractor’s First request nor his Second Request.
Consequently, the Extension of Time to which the Contractor is now fairly entitled to receive amounts to 20 months from 31 May 2008 to 31 January 2010 as substantiated in this submission. This is the date on which it is anticipated substantial Completion will be achieved.
page 126
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
8. Additional Payment
8.1. Introduction
Each of the sections in this document briefly describes the events that have occurred that are contrary to those envisaged at time of tender. Therefore, allowance for the event so described has not been made in the tender rates and prices. This Chapter of the document contains the financial details, demonstrating the reimbursable additional value or cost of these disruptive events.
This unforeseen difficulty has impacted all the Contractor's resources that were on site during the periods of delay and disruption. In addition, the same resources are, as a consequence of the varied circumstances, to be retained on Site for a further 20 months. That is from the original Completion date to 31 January 2010.
8.2. Evaluation of the Financial Consequences
The delay and disruption has been caused by late survey data, unforeseen ground conditions, suspension of works, varied scope of work and to incomplete and late design information.
Although the Contractor continued to perform as much work as possible in these periods, the unforeseen conditions and changed circumstances will cause the original time to completion to extend from 31 May 2008 to 31 January 2010.
The extension of time and associated loss and expense the Contractor has suffered falls into five categorises:
In the original construction period when equipment and labour resources were under-utilised and recovery of overheads were not secured because of a reduced income;
In an extended period when again the equipment and labour resources will be retained on Site for longer than planned and overheads are not recovered;
In measures taken to recover earlier delays by the addition of resources and working longer hours; and
Other Direct and Indirect Costs
page 127
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
In the original and extended period of construction where the cost of financing construction increased due to the longer period to completion.
8.2.1.Wasted Costs Arising from Delay and Disruption
These costs arise in the period from commencement to May 2008.
8.2.1.1. Staff and Labour
The following table provides a summary of planned revenue against actual. The fourth column records the shortfall value which is expressed as a percentage on planned.
Forecast Actual Shortfall as aMonth Monthly Monthly Shortfall % of Forecast
Feb-07 3,100,000.00 0.00 3,100,000.00 100%Mar-07 601,658.62 0.00 601,658.62 100%Apr-07 1,352,295.74 0.00 1,352,295.74 100%
May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%Jun-07 2,236,090.71 0.00 2,236,090.71 100%Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%
Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%Dec-07 1,754,288.50 0.00 1,754,288.50 100%Jan-08 1,289,372.84 0.00 1,289,372.84 100%Feb-08 1,040,280.70 274,355.16 765,925.54 74%Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%Apr-08 2,575,212.46 0.00 2,575,212.46 100%
May-08 0.00 0.00 0.00 0%
The next table provides a summary of the actual cost of labour from commencement to end of May 2008. Against these values the percentage calculated representing the shortfall on revenue has been applied to arrive at the value of wasted costs. To this figure 15% profit has been added in order to properly value the Variation.
page 128
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month LabourCost % Wasted AmountWasted 15%Profit Total
Mar-07 26,831.00 100% 26,831.00 4,024.65 30,855.65Apr-07 47,046.00 100% 47,046.00 7,056.90 54,102.90
May-07 52,890.00 -67% -35,606.35 -5,340.95 -40,947.30Jun-07 60,384.00 100% 60,384.00 9,057.60 69,441.60Jul-07 60,984.00 75% 45,489.26 6,823.39 52,312.65
Aug-07 61,812.00 84% 51,876.82 7,781.52 59,658.34Sep-07 61,812.00 93% 57,781.57 8,667.24 66,448.80Oct-07 67,056.00 84% 56,437.80 8,465.67 64,903.47Nov-07 80,944.00 79% 63,775.99 9,566.40 73,342.39Dec-07 86,068.00 100% 86,068.00 12,910.20 98,978.20Jan-08 86,709.00 100% 86,709.00 13,006.35 99,715.35Feb-08 85,629.00 74% 63,045.90 9,456.89 72,502.79Mar-08 90,629.00 -117% -106,171.08 -15,925.66 -122,096.75Apr-08 90,629.00 100% 90,629.00 13,594.35 104,223.35
May-08 115,007.00 0% 0.00 0.00 0.00
Total 683,441.44
8.2.1.2. Equipment
The following table provides a summary of planned revenue against actual. The fourth column records the shortfall value which is expressed as a percentage on planned.
Forecast Actual Shortfall as aMonth Monthly Monthly Shortfall % of Forecast
Feb-07 3,100,000.00 0.00 3,100,000.00 100%Mar-07 601,658.62 0.00 601,658.62 100%Apr-07 1,352,295.74 0.00 1,352,295.74 100%
May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%Jun-07 2,236,090.71 0.00 2,236,090.71 100%Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%
Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%Dec-07 1,754,288.50 0.00 1,754,288.50 100%Jan-08 1,289,372.84 0.00 1,289,372.84 100%Feb-08 1,040,280.70 274,355.16 765,925.54 74%Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%Apr-08 2,575,212.46 0.00 2,575,212.46 100%
May-08 0.00 0.00 0.00 0%
The next table provides a summary of the actual cost of equipment from commencement to end of May 2008. Against these values the percentage calculated representing the shortfall on revenue has been applied to arrive at the value of wasted costs. To this figure 15% profit has been added in order to properly value the Variation
page 129
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month EquipCost % Wasted AmountWasted 15%Profit Total
Mar-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Apr-07 262,545.19 100% 262,545.19 39,381.78 301,926.96
May-07 262,545.19 -67% -176,749.40 -26,512.41 -203,261.81Jun-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Jul-07 262,545.19 75% 195,838.02 29,375.70 225,213.72
Aug-07 262,545.19 84% 220,345.72 33,051.86 253,397.58Sep-07 262,545.19 93% 245,426.01 36,813.90 282,239.91Oct-07 262,545.19 84% 220,971.60 33,145.74 254,117.34Nov-07 262,545.19 79% 206,860.05 31,029.01 237,889.06Dec-07 262,545.19 100% 262,545.19 39,381.78 301,926.96Jan-08 262,545.19 100% 262,545.19 39,381.78 301,926.96Feb-08 269,952.60 74% 198,757.50 29,813.62 228,571.12Mar-08 293,656.30 -117% -344,015.79 -51,602.37 -395,618.16Apr-08 293,656.30 100% 293,656.30 44,048.44 337,704.74
May-08 293,656.30 0% 0.00 0.00 0.00
Total 2,729,888.31
8.2.1.3. Site and Head Office
The following table provides the wasted costs associated with the indirect staff and labour costs arising from the Site Office overheads. The value of overheads is estimated to be at 3%.
Month LabourCost % Wasted AmountWasted 15%Profit Total
Mar-07 26,831.00 3% 804.93 120.74 925.67Apr-07 47,046.00 3% 1,411.38 211.71 1,623.09
May-07 52,890.00 3% 1,586.70 238.01 1,824.71Jun-07 60,384.00 3% 1,811.52 271.73 2,083.25Jul-07 60,984.00 3% 1,829.52 274.43 2,103.95
Aug-07 61,812.00 3% 1,854.36 278.15 2,132.51Sep-07 61,812.00 3% 1,854.36 278.15 2,132.51Oct-07 67,056.00 3% 2,011.68 301.75 2,313.43Nov-07 80,944.00 3% 2,428.32 364.25 2,792.57Dec-07 86,068.00 3% 2,582.04 387.31 2,969.35Jan-08 86,709.00 3% 2,601.27 390.19 2,991.46Feb-08 85,629.00 3% 2,568.87 385.33 2,954.20Mar-08 90,629.00 3% 2,718.87 407.83 3,126.70Apr-08 90,629.00 3% 2,718.87 407.83 3,126.70
May-08 115,007.00 3% 3,450.21 517.53 3,967.74
Total 37,067.84
Similarly, the table below provides the wasted costs associated with indirect staff and labour costs arising from the Head Office overheads. The value of overheads is estimated to be 9%.
page 130
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month LabourCost % Wasted AmountWasted 15%Profit Total
Mar-07 26,831.00 9% 2,414.79 362.22 2,777.01Apr-07 47,046.00 9% 4,234.14 635.12 4,869.26
May-07 52,890.00 9% 4,760.10 714.02 5,474.12Jun-07 60,384.00 9% 5,434.56 815.18 6,249.74Jul-07 60,984.00 9% 5,488.56 823.28 6,311.84
Aug-07 61,812.00 9% 5,563.08 834.46 6,397.54Sep-07 61,812.00 9% 5,563.08 834.46 6,397.54Oct-07 67,056.00 9% 6,035.04 905.26 6,940.30Nov-07 80,944.00 9% 7,284.96 1,092.74 8,377.70Dec-07 86,068.00 9% 7,746.12 1,161.92 8,908.04Jan-08 86,709.00 9% 7,803.81 1,170.57 8,974.38Feb-08 85,629.00 9% 7,706.61 1,155.99 8,862.60Mar-08 90,629.00 9% 8,156.61 1,223.49 9,380.10Apr-08 90,629.00 9% 8,156.61 1,223.49 9,380.10
May-08 115,007.00 9% 10,350.63 1,552.59 11,903.22
Total 111,203.51
The following table provides the wasted costs associated with the indirect Equipment costs arising from the Site Office overheads. The value of overheads is estimated to be at 3%.
Month EquipCost % Wasted AmountWasted 15%Profit Total
Mar-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Apr-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
May-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jun-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jul-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Aug-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Sep-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Oct-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Nov-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Dec-07 262,545.19 3% 7,876.36 1,181.45 9,057.81Jan-08 262,545.19 3% 7,876.36 1,181.45 9,057.81Feb-08 269,952.60 3% 8,098.58 1,214.79 9,313.36Mar-08 293,656.30 3% 8,809.69 1,321.45 10,131.14Apr-08 293,656.30 3% 8,809.69 1,321.45 10,131.14
May-08 293,656.30 3% 8,809.69 1,321.45 10,131.14
Total 139,342.69
Similarly, the table below provides the wasted costs associated with indirect staff and labour costs arising from the Head Office overheads. The value of overheads is estimated to be 9%.
page 131
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month EquipCost % Wasted AmountWasted 15%Profit Total
Mar-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Apr-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
May-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jun-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jul-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Aug-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Sep-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Oct-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Nov-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Dec-07 262,545.19 9% 23,629.07 3,544.36 27,173.43Jan-08 262,545.19 9% 23,629.07 3,544.36 27,173.43Feb-08 269,952.60 9% 24,295.73 3,644.36 27,940.09Mar-08 293,656.30 9% 26,429.07 3,964.36 30,393.43Apr-08 293,656.30 9% 26,429.07 3,964.36 30,393.43
May-08 293,656.30 9% 26,429.07 3,964.36 30,393.43
Total 418,028.07
8.2.1.4. Summary of Wasted Costs
Item Category Amount
Staff and Labour 683,441.44Equipment 2,729,888.31Site Overheads Staff and Labour 37,067.84
Equipment 139,342.69Head Office Overheads Staff and Labour 111,203.51
Equipment 418,028.07
Total 4,118,971.85
8.2.2.Additional Costs Arising from Acceleration
In order to recover part of the earlier delays the Contractor has already implemented steps to improve and increase his staff, labour and equipment.
At this juncture the Contractor has ordered and organised the following additional resources shown in the table below.
page 132
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
ID Designation Value UD$ Amount
Staff and Labour
1 Senior Project Manager 168,630.002 Quality Assurance Manager 168,630.003 Senior Quantity Surveyor 107,250.004 Assistant Quantity Surveyor 99,000.005 Expatriate Workers 880,000.00 1,423,510.00
Equipment
1 Potain tower crane (2Nr) 131,400.002 Scaffolding 105,791.003 Merlo Car-Mix 62,500.004 JCB 70,000.005 Concrete Paver 45,000.006 Rock Breaker 32,000.007 Mini Excavator (15 Tonne) 88,500.00 535,191.00
Total additonal resources 1,958,701.00
8.2.3.Additional Costs in Extended Contract Period
The Contractor has entitlement to recovery of his indirect costs arising in the extended contract period. These costs arise in the period the Contract is extended as a result of critical delays.
Consequently, this allowance has no relation to additional expenditure arising in the original contract period as a result of non-critical delays. That is to say, those costs that are attributed to delay and disruption, the first period, are separate to costs flowing in an extended period, the second period.
The Contractor has entitlement to payment of additional indirect costs in the period they arise. However, this recovery would exclude his indirect costs not paid through his rates and prices for doing the work which remain recoverable in the extended period. These costs are detailed below:
page 133
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Item Nature of Cost Fixed Variable PlannedCost ExtendedPeriod
1 Insurance 250,000.00 17,857.14 321,428.572 Foreign Staff, Labour Repatriation 450,000.00 32,142.86 578,571.433 Facilities for Staff and Labour 170,000.00 12,142.86 218,571.434 Measures against Insect and Pect Nuisance 60,000.00 4,285.71 77,142.865 Supply of Foodstuffs 660,000.00 47,142.86 848,571.436 Supply of Water 80,318.00 5,737.00 103,266.007 Shop Drawings 10,000.00 714.29 12,857.148 As-Built Documents 5,600.00 400.00 7,200.009 Temporary Site Office for Employers Consultants 65,250.00 0.00 0.0010 Site Signboard 3,275.00 0.00 0.0011 Access to Site 35,000.00 2,500.00 45,000.0012 Site to be Tidy 12,727.00 909.07 16,363.2913 Co-ordination 14,727.00 1,051.93 18,934.7114 Site Records 3,275.00 233.93 4,210.7115 Site Records 29,913.00 2,136.64 38,459.5716 Safety Procedures 5,700.00 407.14 7,328.5717 Security at Site 13,426.00 959.00 17,262.0018 Contractors Site Operations 7,485.00 534.64 9,623.5719 Site Radio Communication 11,725.00 0.00 0.0020 Environmental Impact Assessment 5,000.00 0.00 0.0021 Taking Delivery from NS 50,000.00 3,571.43 64,285.7122 Contractors Temporary Accommodation 35,000.00 2,500.00 45,000.0023 Superintendence 15,000.00 1,071.43 19,285.7124 Transport of People 125,475.00 8,962.50 161,325.0025 Contractors Equipment 365,000.00 26,071.43 469,285.7126 Scaffolding 105,000.00 7,500.00 135,000.00
Total 3,218,973.43
8.2.4.Other Costs
The following activities caused the Contractor to incur additional costs because of the changed events described in this document. At time of preparing this submission these costs have yet to be ascertained and will therefore, be part of future claim submissions.
8.2.4.1. Procurement of Permanent Materials
The following table provides a summary of all major materials ordered on the project to date. It will be noted that all major materials required for 55 number villas are ordered although the constraint to receiving the complete order is payment.
The inability to complete full payment to the supplier has been explained in various notifications, particularly the Advance recovery which is disconnected from progress payments. This compounded an existing reduced income generated each month because progress could not be achieved as planned due to as example, unforeseen ground conditions.
page 134
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Des c ription of MaterialsQuantity Ordered Date Ordered Amount rec eived B alanc e C omments
F OR AL L 55 VIL L AS
50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order subject to payment to supplierP lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order subject to payment to supplierC rusher Dust 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order subject to payment to supplierAggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order subject to payment to supplierP las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order subject to payment to supplier150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order subject to payment to supplier100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order subject to payment to supplierA252 Weld Mesh (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order subject to payment to supplierHigh tens ile s teel-8,10,12,16,25mm (tons) 500.00 14/01/07 158.00 342.00 B alance on order subject to payment to supplierC edar S hingles (sqm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order subject to payment to supplierIroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order subject to payment to supplier12mm G ypsum boards (S HE E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.DS tainless s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order subject to payment to supplier (Not B .O .Q item)S tainless s teel gusset plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order subject to payment to supplier (Not B .O .Q item)B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order subject to payment to supplierT reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order subject to payment to supplier
Consequently, it is likely initial materials ordered and not secured by full payment will attract a different cost at a later date. The additional cost arising is not the responsibility of the Contractor. These costs will be identified and evidenced at a later date as they arise.
8.2.4.2. Temporary Materials including Equipment
A similar situation exists with temporary materials whereby orders could not be made to enhance productivity at Site.
8.2.5.Finance Costs
The additional costs defined within the preceding sections of this chapter on claim for additional payment have been borne and financed by the Contractor. The Contractor has paid the costs by obtaining bank loans or overdrafts, or by the use of working capital that would have been employed in profitable work. These financing costs are an additional cost incurred as a consequence of the circumstances herein and, become part of the reimbursable sum.
The Contractor has carried this additional cost since the outset of the Contract to the present date, end of May 2008, a period of about 14 months.
Compound interest over this period is against the heads of cost amount to:
page 135
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Month Labour Equipment Sub-total SiteO/H H/Q Total Sub-total Total
Mar-07 26,831.00 262,545.19 289,376.19 3.00% 9.00% 12.00% 34,725.14 324,101.33 Apr-07 47,046.00 262,545.19 309,591.19 3.00% 9.00% 12.00% 37,150.94 346,742.13 May-07 52,890.00 262,545.19 315,435.19 3.00% 9.00% 12.00% 37,852.22 353,287.41 Jun-07 60,384.00 262,545.19 322,929.19 3.00% 9.00% 12.00% 38,751.50 361,680.69 Jul-07 60,984.00 262,545.19 323,529.19 3.00% 9.00% 12.00% 38,823.50 362,352.69 Aug-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05 Sep-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05 Oct-07 67,056.00 262,545.19 329,601.19 3.00% 9.00% 12.00% 39,552.14 369,153.33 Nov-07 80,944.00 262,545.19 343,489.19 3.00% 9.00% 12.00% 41,218.70 384,707.89 Dec-07 86,068.00 262,545.19 348,613.19 3.00% 9.00% 12.00% 41,833.58 390,446.77 Jan-08 86,709.00 269,952.60 356,661.60 3.00% 9.00% 12.00% 42,799.39 399,460.99 Feb-08 85,629.00 293,656.30 379,285.30 3.00% 9.00% 12.00% 45,514.24 424,799.53 Mar-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53 Apr-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53 May-08 115,007.00 0.00 115,007.00 3.00% 9.00% 12.00% 13,800.84 128,807.84
Interest Finance TotalMonth/Year Days Monthly Cummulative Gross Rate Value Amount
Mar-07 31.00 324,101.33 324,101.33 324,101.33 11.00% 3,027.91 327,129.23Apr-07 30.00 346,742.13 327,129.23 673,871.36 11.00% 6,092.54 679,963.90May-07 31.00 353,287.41 679,963.90 1,033,251.31 11.00% 9,653.11 1,042,904.42Jun-07 30.00 361,680.69 1,042,904.42 1,404,585.11 11.00% 12,698.99 1,417,284.10Jul-07 31.00 362,352.69 1,417,284.10 1,779,636.79 11.00% 16,626.20 1,796,262.98Aug-07 31.00 363,280.05 1,796,262.98 2,159,543.03 11.00% 20,175.46 2,179,718.49Sep-07 30.00 363,280.05 2,179,718.49 2,542,998.54 11.00% 22,991.49 2,565,990.03Oct-07 31.00 369,153.33 2,565,990.03 2,935,143.36 11.00% 27,421.48 2,962,564.84Nov-07 30.00 384,707.89 2,962,564.84 3,347,272.73 11.00% 30,263.01 3,377,535.74Dec-07 31.00 390,446.77 3,377,535.74 3,767,982.51 11.00% 35,202.25 3,803,184.76Jan-08 31.00 399,460.99 3,803,184.76 4,202,645.74 11.00% 39,263.07 4,241,908.82Feb-08 28.00 424,799.53 4,241,908.82 4,666,708.35 11.00% 39,379.35 4,706,087.70Mar-08 31.00 430,399.53 4,706,087.70 5,136,487.23 11.00% 47,987.46 5,184,474.69Apr-08 30.00 430,399.53 5,184,474.69 5,614,874.22 11.00% 50,764.62 5,665,638.84May-08 31.00 128,807.84 5,665,638.84 5,794,446.68 11.00% 54,134.42 5,848,581.10
Total Amount 415,681.34
Period Principle Amount
Finance Costs will continue on this amount and in the remaining contract period unless these additional costs are paid.
8.2.6.Grand Summary
The additional costs defined within the preceding sections of this chapter are summarised below:
page 136
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
Gategory of Additional Cost Amount
Wasted Monthly Costs in Original Contract Period 4,118,971.85Acceleration Costs 1,958,701.00Finance Costs in Period 415,681.34Extended Costs 3,218,973.43
Total Additional Costs to May 2008 9,712,327.62
page 137
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
9. Statement of Claim
During the course of performing the Contract Works to May 2008, the Contractor has drawn the Project Manager’s attention to the fact that the Employer has deviated from certain of the contractual requirements established in the Contract. He has required the Contractor to perform the Contract Works in a manner significantly different from that laid down in the Contract Conditions and Specifications. These deviations are:
1. The Project Manager failed to provide setting out data in variance to the Contract or the timing depicted on the Programme of Works;
2. The Project Manager unnecessarily instructed a partial suspension of the Works;
3. The Project Manager did not issue construction design details in accordance with the Contract or the Contract Programme of Works;
4. The discovery of significant had rock at many of the Villa locations, which occurrence is an unforeseen condition as allowed and described in the Contract;
5. The Project Manager did not issue construction design details free from significant errors in accordance with the Contract; and
6. The Project Manager has not properly measured, valued, or paid for changes to the scope of work in respect of additional time and cost.
The Contractor is entitled to payment, in respect of the above matters for the reasons stated. In addition he is also entitled to an extension of time all as summarised below:
Head of Claim EOT Months ValueExtension of time (31 May 08 – 31Jan 09) 20 3,218,973.43Wasted Costs to May 2008 In period 4,118,971.85Acceleration Costs In extended period 1,958,701.00Finance Costs To May 2008 415,681.34Total Entitlement USD 9,712,327.62
page 138
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
10.Appendices
10.1. Wasted Costs
10.1.1. Record of Resources – Staff and Labour
10.1.2. Record of Resources – Equipment
10.1.3. Direct and Indirect Costs
The following table provides figures from the Contractor’s audited accounts.
The next table shows the average indirect costs for the head office (Victoria, Mahe) and site office expressed as a percentage. The Contractor expects to recover as a return on turnover, approximately 9% on the head office costs and 3% for the site office costs.
page 139
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
10.2. RFI and RFAID Date Reference From To Subject EventType Location EventDescription Notes
001 10-Mar-08 RFI-001 Island Construction Polus Investments
Roof trusses - Stainless steel plates - Detailed drawings required
Request for Information Villas & Buildings
Contractor requested for detailed designs for stainless steel plates for all the remaining buildings
PM stated the designs shall follow those of the mock up villas already constructed
002 10-Mar-08 RFI-002 Island Construction Polus Investments Thermal Roof Insulation - Design details required
Request for Information
Mock up villas and other buildings
Contractor requested the detailed design and insulation details for thermal roof insulation
PM provided the required information on 16 Mar '08. Information was required by 15 March 2008
003 12-Mar-08 RFI-003 Island Construction Polus Investments A3 Villas - Decking Span - Clarification Required
Request for Information A3 Villas
Contractor requested clarification on the span of the timber decking
PM provided clarification on 13 March 2008. Information was required by 15 March 2008
004 10-Mar-08 RFI-004 Island Construction Polus Investments Request for clarification on socket position at B2/03
Request for Information B2/03
Contractor requested clarification on the socket position at B2/03 Clarification provided
005 12-Mar-08 RFI-005 Island Construction Polus Investments A3 Villas - Lanai screens - designs required
Request for Information A3 Villas
Contractor requested design for lanai screens
Clarification provided on 13 Mar '08. Information was required by 15 Mar '08
006 12-Mar-08 RFI-006 Island Construction Polus Investments
All Villas – Bathroom Entrance Door Type DO.02 – Infill Bamboo Resin Panel – Discrepancy in Size
Request for Information Villas
Clarification required on the descrepancy in sizes of the bamboo resing panel Clarification provided
007 13-Mar-08 RFI-007 Island Construction Polus Investments
Mock Up Villas – Window Sill & Lining Details – Cut Stone Cladding – Discrepancy in Size
Request for Information
Mock up villas A3/32 and B2/03
Clarification required on the desrepancy in sizes of window sill shown in the desgn and the one supplied
Clarification provided on 16 Mar '08. Information was required by 16 Mar 08
008 14-Mar-08 RFI-008 Island Construction Polus Investments Ironmongery – Supplier – Other Contact Details Required
Request for Information Villas
Further contact details of ironmongery supplier required Not yet provided
page 140
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
10.3. CorrespondenceID Date Reference From To Subject EventType Location EventDescription Notes
001 05-Jul-07 FIN/PS/POLUS/83PS, Ministry of
Finance Polus Investments Concessions Granted for the Project Information
Shangri-La Resort Project
Concessions granted during the construction phase of the project
002 11-Jul-07 LIHRD/env/05 Island Construction Polus Investments Environment Visit Report - 10 July 2007 Environmental
Shangri-La Resort Project
Contractor's response to Environmental visit report
003 30-Aug-07 LIHRD/VO/01 Island Construction Polus Investments
Quotation for Retaining Wall along CHI-SPA area/Restaurant Area Quotation
Shangri-La Resort Project
Quotation for Retaining wall along CHI-SPA area/Restaurant area
004 30-Aug-07 LIHRD/VO/02 Island Construction Polus Investments List of Variations Variations Shangri-La Resort Project
PM requested to approve the list of variations
005 03-Sep-07 Angel Fish Island Construction New Rates for Boat Transport Information Shangri-La Resort Project
New rates for boat transport as a result of increased fuel prices
006 12-Sep-07 Island Construction Angel Fish Transfer Boat to Long Island Information Shangri-La Resort Project
Schedules for boat transport from Mahe to Long Island and back
007 19-Sep-07 Island Construction Polus Investments Inquiry from Independent Engineer Information
Shangri-La Resort Project
Submission of the company's technical profile
008 24-Oct-07 Island Construction Polus Investments
Lump Sum Contract Price - Variations to Scope of Works - Instructions Variations
Shangri-La Resort Project
Request for Employer's agreement to payment of changes and variations
Instructed variations and changes are being made prior to reaching agreement on the price contrary to terms and conditions of the contract. There exists disparities between BQ quantities and quantities measured from construction drawings.
009 24-Oct-07 Island Construction Polus Investments Mock-up Villas - Variation Instruction - Additional Costs
Variation & Notification
Shangri-La Resort Project
The requirement to complete Mock up villas is a variation. Detailed particulars of associated delays and additional costs shall be submitted once ready
Timing and sequence for the mock up villas is not allowed in the POW, material procurement and labour requirements are in variance to original planning, advance construction of the mock-up villas continues to be an impediment on the rate of progress for other parts of works.
010 24-Oct-07 Island Construction Polus Investments
Minutes of Meeting No.23 - Recorded Minutes - Not Approved Information
Shangri-La Resort Project
Disagreement to Minutes of meeting No. 23 and all previous minutes. Proposal by the Contractor to verify and comment on the minutes before circulation
The minutes are in Contractor's view inaccurate and have not received Contractor's concurrence.
011 26-Oct-07 Island Construction Polus Investments
Suspension of Works-Extension of Time & Additional Payment-Notice Notification
Shangri-La Resort Project
Notification of Contractor's entitlement to time extension and additional costs occassioned by suspension of works.
In addition, the Contractor awaits PM's instruction to proceed with all the works affected by the suspension notice
012 26-Oct-07 Island Construction Polus Investments Setting Out - Late Instructions & Variations - Additional Costs
Notification & Variation
Shangri-La Resort Project
Notification of delay and disruption occassioned by varied location, position and orientation of buildings
The changes constiture variation. Associated delays and costs to be submitted once ready
013 26-Oct-07 Island Construction Polus Investments
Advance Payment - Unfixed Materials & Goods - Payment Application Payment
Shangri-La Resort Project
Request for PM's concurrence with Contractor's intention to raise a separate statement for payment of Unfixed Materials and Goods
014 26-Oct-07 Island Construction Polus Investments Earth Filling to CHI-SPA area QuotationShangri-La Resort Project
Quotation for earth filling to CHI-SPA area
page 141
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
015 26-Oct-07 Island Construction Polus Investments Quotation for Rock Excavation QuotationShangri-La Resort Project Quotation for rock excavation
016 29-Oct-07 Island Construction Polus Investments Setting Out - Late Instructions & Variations - Additional Costs Variation
Shangri-La Resort Project
Contractor maintains changes in the location, position and orientation of buildings constitute variation, hence delays and additional costs, detailed particulars of which will be submitted once available
017 29-Oct-07 Island Construction Polus Investments
Suspension of Works-Extension of Time & Additional Payment-Entitlement Determination
Shangri-La Resort Project
Contractor maintains he has entitlement to extensions of time and recovery of costs due to suspension. Awaiting PM's determination
018 19-Nov-07 Island Construction Polus Investments
Programme - Revision 1 Dated 6th Nov 2007 - Progress of Works
Programme of Works
Shangri-La Resort Project
Submission of Revised Programme of Works
019 19-Nov-07 Island Construction Polus Investments
Interim Statement No. 3 - Issue of Interim Payment Certificate - Contract Procedure Payment
Shangri-La Resort Project
Undercertification shall subsequently attract finance costst
020 19-Nov-07 Island Construction Polus Investments Cash Flow Forecast - Advance Repayment - Ammendment Cash Flow
Shangri-La Resort Project Ammended cash flow forecast
021 20-Nov-07 LIHRD/PC/05 Island Construction Polus Investments Interim Statement No. 3 Statement Shangri-La Resort Project Application for Payment for works
022 21-Nov-07 Island Construction Polus Investments
Extension of Time for Completion-First Interim Entitlement-Claim Claim
Shangri-La Resort Project
The Contractor claims extension of time for completion up to 8 Dec 08 and additional costs amounting to US$ 857,145.00
023 21-Nov-07 Island Construction Polus Investments
Cash Flow Forecast - Advance Repayment - Proposed Revisions Cash Flow
Shangri-La Resort Project
Ammeded cash flow forecast consequent to the extended contract period as per the revised programme of works
024 21-Nov-07 Island Construction Polus Investments Minutes of Meeting Nr. 27 - Clarification - Notice
Clarification & Notice
Shangri-La Resort Project
Clarification on time and money issues contained in the minutes and notification of intention to submit additional costs for acceleration of works
025 23-Nov-07 Island Construction Polus Investments
Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation
Claims & Variations
Shangri-La Resort Project
Contractor requests a Variation Meeting to discuss and agree on all the variations and claims on the project to date
The Variations and claims identified so far are listed
026 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Suspension of works Claim Shangri-La Resort Project
PM states it is the Contractor who suspended the works hence refuse to approved any Extension of time and Additional Costs
The PM encloses previous email correspondences with the Contractor over the issue
027 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Minutes of Meeting Information Shangri-La Resort Project
PM will endeavour to issue meeting minutes by every Wednesday
page 142
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
028 23-Nov-07 E-03-23.11.07 Polus Investments Island Construction Measurement and Payment for Variations Variations
Shangri-La Resort Project
Instruction to vary any part of the works whether for the specification or quantities is additional work entitled to additional payment
PM agrees to have mutual measurement of variation and payment thereof
029 23-Nov-07 E-04-23.11.07 Polus Investments Island Construction Mock-up Villas Variations Shangri-La Resort Project
The PM states mock up villas do not comprise variation
030 23-Nov-07 E-05-23.11.07 Polus Investments Island Construction Clients Address AddressShangri-La Resort Project
All communications must be addressed to the Project Manager
031 23-Nov-07 E-06-23.11.07 Polus Investments Island Construction Setting out at Site - Changes in Positions, Orientation
Variation & Claim
Shangri-La Resort Project
PM requires detailed particulars for associated delays and costs
032 23-Nov-07 E-07-23.11.07 Polus Investments Island Construction Minutes of Meeting Clarification & Notice
Shangri-La Resort Project
PM awaits detailed document regarding Variations and claims so far identified
033 04-Dec-07 E-09-04.12.07 Polus Investments Island Construction
Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation Variations
Shangri-La Resort Project
PM agrees to value changes in design and quantities as Variations
034 04-Dec-07 E-08-04.12.07 Polus Investments Island Construction
Interim Statement No.3 - Issue of Interim Payment Certificate - Contract Procedure Payment
Shangri-La Resort Project
The Invoice required is not contractual but solely for accounting purposes
035 07-Dec-07 Island Construction Polus Investments
General Contractor's Obligations-Performance Security-Reduction of Amount
Performance Security
Shangri-La Resort Project
Contractor proposes the amount in the Performance Security is reduced equal to the amount of cover included in the EME's performance security
036 08-Dec-07 Island Construction Polus Investments
Variations & Adjustments - Instructed Changes & Additions - Measurement & Evaluation Variations
Shangri-La Resort Project
The Letter of Acceptance takes priority over the conditions of contract. As such, in practice it means that no variation arising from aditional work or design change can commence prior to receiving the agreement of the Employer
037 19-Dec-07 E-13-19.12.07 Polus Investments Island Construction List of Plants for A3/32 - B2/03 LandscapingShangri-La Resort Project Enclosed list of plants
038 24-Dec-07 Island Construction Polus Investments
Interim Statements for Payment - Issue of Interim Payment Certificate-Payment Payment
Shangri-La Resort Project
The PM can still issue a payment certificate even when the amount falls below the minimum payable by the Employer
039 24-Dec-07 Island Construction Polus Investments Mock-up Villas - Variation Instruction - Additional Costs Variation
Shangri-La Resort Project
Contractor maintains Mock-up villas is a variation because the procurement process is in complete variance to original planning
040 15-Jan-08 Polus Investments Island Construction Specification for Door panelling SpecificationShangri-La Resort Project Specification for door panelling
041 17-Jan-08 E-14-17.01.08 Polus Investments Island Construction Environment Visit Report - 13 Dec 2007 Environmental
Shangri-La Resort Project
Contractor required to take necessary measures to improve the situation
page 143
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
042 21-Jan-08 Island Construction Polus Investments
Environmental - Monitoring visit for Class 1 Project and SPA at Long Island Environmental
Shangri-La Resort Project
Steps being taken to address the environmental issues
043 22-Jan-08 Island Construction Polus Investments Roof structure gusset plate design Design
Shangri-La Resort Project
The proposed 4.5mm thick gusset plate is appropriate for use
044 29-Jan-08 Polus Investments Island Construction Revised cash flow Cash FlowShangri-La Resort Project PM forwards a revised cashflow
045 29-Jan-08 E-14-29.01.08 Polus Investments Island Construction Mock-up Villas - Variation Variation Shangri-La Resort Project
PM requires the mock-up villas completed as per original programme
046 30-Jan-08 E-15-30.01.08 Polus Investments Island Construction Certification and Payment Payment Shangri-La Resort Project
Payment has been made to the Main Contractor
047 30-Jan-08 Polus Investments Island Construction Approved Balustrade Design Shangri-La Resort Project Pictures of approved balustrade
048 04-Feb-08 E-16-04.02.08 Polus Investments Island Construction Statement Statement Shangri-La Resort Project
2 Hard copies of the statement required
049 06-Feb-08 Polus Investments Island Construction Site Issues General Shangri-La Resort Project
Minutes of meeting between Zsolt and Wilson. Action by Contractor required
050 07-Feb-08 Island Construction Polus Investments Site Issues General Shangri-La Resort Project Response to issues raised above
051 13-Feb-08 E-18-13.02.08 Polus Investments Island Construction Revised Programme of works Programme of Works
Shangri-La Resort Project
Contractor required to submit revised programme of works
052 13-Feb-08 E-19-13.02.08 Polus Investments Island Construction Payment Certificate & Rate of Progress Certificate
Shangri-La Resort Project
The negative amount reflects very slow progress at site. Submit revised POW and supporting report outlining methods to expedite progress
053 26-Feb-08 Island Construction Polus Investments
Nominated Subcontractor EME Overseas Ltd - Design and Build Subcontract Conditions - Objection to Nomination Subcontract
Shangri-La Resort Project
Existing contractual matters that prevent execution of agreement between Island Construction Pty ltd and EME overseas
054 27-Feb-08 Island Construction Polus Investments
Suspension of Works - Extension of time and Additional Payment - Entitlement
Suspension of Works
Shangri-La Resort Project
Entitlement to Extensions of time and additional payment arising from instruction to suspend works
055 01-Mar-08 Island Construction Polus Investments Situation ReportDelaying Events Details
Shangri-La Resort Project
Delaying Events and Proposed Financial Arrangements
057 14-Mar-08 Island Construction Polus Investments
Delaying Events & Changed Circumstances - Revised Programme of works - Extension of time for completion
Request for Extension of Time
Shangri-La Resort Project
Request for extension of time for completion to 24 March 2009
058 19-Mar-08 Island Construction Polus Investments
Cash Flow Forecast - Advance Repayment - Proposed Revision
Revision of Advance Recovery
Shangri-La Resort Project
Proposed amendment of cashflow with revised advance recovery
059 07-Apr-08 Island Construction Polus Investments Extension of time Time Extension Shangri-La Resort Project Detailed particulars required
page 144
Island Construction (Pty) Ltd Shangri-La Resort DevelopmentInterim Request for Extension of Time and Additional Payment
056 08-Apr-08 Island Construction Polus Investments Interim Report on Programme of Works, Progress & Valuation
Programme & Valuation Report
Shangri-La Resort Project
Report on Programme of Works and Request for Time Extension
060 09-Apr-08 E-18-09.04.08 Polus Investments Island Construction Nominated Subcontractor Subcontract Shangri-La Resort Project
PM responds to ICCL's objection to enter into nominated subcontract with EME
061 14-Apr-08 E-17-07.04.2008 Polus Investments Island Construction
Nominated Subcontract - Subcontract Agreement - Reason for Objection Subcontract
Shangri-La Resort Project
Reason for Objection of nominated subcontract agreement
062 15-Apr-08 Island Construction Polus Investments
Extension of Time for Completion - First Interim Entitlement - Detailed Particulars
Detailed particulars for Extension of time
Shangri-La Resort Project
Request for approval to submit detailed particulars within 45 days from 15 April 2008
063 15-Apr-08 Island Construction Polus Investments Interim Statement Nr. 08 Statement Shangri-La Resort Project
Statement for works done up to End of March 2008
064 17-Apr-08 Island Construction Polus Investments
Interim Statement Nr. 08 - Materials On & Off site - Amendment Statement
Shangri-La Resort Project
Amended statement incorporating off site Balau timber
065 17-Apr-08 Island Construction Polus Investments Landscaping - Additional Work - Confirmation of Oral Instruction Additional Works
Shangri-La Resort Project
Confirmation of oral instruction to execute landscaping works
066 21-Apr-08 Island Construction Polus Investments
Delay to Completion - Recovery Programme - Approval to Accelerate Programme
Shangri-La Resort Project
Request for approval to accelerate works
067 02-May-08 E19-02.05.08 Polus Investments Island Construction Delays Extension of Time
Shangri-La Resort Project
PM states ICCL has not demonstrated entitlement to time extension
068 05-May-08 E-21-05.05.08 Polus Investments Island Construction Valuation Certificate Payment Shangri-La Resort Project Valuation certificate No. 08
069 06-May-08 Island Construction Polus Investments Interim Payment - Invoice No. 7 Payment Shangri-La Resort Project Invoice for Interim Payment
070 07-May-08 Island Construction Polus Investments
Valuation No. 8 - Cession of Right for Material On and Off Site Materials On Site
Shangri-La Resort Project
Cession of right for materials on and off site
071 09-May-08 E20-09.05.08 Polus Investments Island Construction Accelerative measures Programme of Works
Shangri-La Resort Project
The Employer is contemplating engaging others to expedite progress of works
072 12-May-08 E21-12.05.08 Polus Investments Island Construction Recovery Measures Programme of Works
Shangri-La Resort Project
PM outlines ways of putting the recovery measures into effect
073 19-May-08 Polus Investments Island Construction Delays and Completion of works Delays
Shangri-La Resort Project
Employer proposes the contractor engages in discussions with PM on the ammendment of the contract and the remedial measures
074 28-May-08 Island Construction Polus Investments
Claim for Time and Additional Payment - Entitlement - Determination Claim
Shangri-La Resort Project
ICCL informs PM detailed particulars will be submitted on 09 June 2008
page 145