Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Fire Station No. 8
History & Legacy Working Group
Langston Brown Recreation Center
March 8, 2018 from 7-9 p.m.
Agenda
• 7:00 – 7:05 Welcome and Opening Comments
• 7:10 – 7:20 Introduction of Members and Support Team
• 7:20 – 8:00 Process Overview
• Charge, Timeline & Process
• Fire Station Replacement Project
• Q&A
• 8:00 – 8:20 Imagining the Future of Fire Station No. 8
• Q&A
• 8:20 – 9:00 Public Comment
Fire Station No. 8 Walking Tour
2
Working Group Members
3
FS8HL Working Group Members
Name Affiliation
Noah Simon, Chair Fire Station 8 Task Force
Jennifer Burgin APS Teacher
Lydia Cole Community Member
Marguarite Gooden Community Member/Langston Brown CA
Edith Gravely Community Member/LHA
Saundra Green Community Member/Lee Highway Alliance
Wilma Jones Community Member/Langston Brown CA
Richard Lolich Lee Highway Alliance
Elizabeth Morton Public Art Committee
James Schroll PFRC
Dale Smith Community Member
Kitty Clark Stevenson Community Member
Denny Truesdale EPAC
Andrew Wenchel, Jr. HALRB, DRC
This slide was changed on 3/13/18 to reflect an updated membership list.
Working Group Charge
• The FS8HL Working Group will develop a report
providing recommendations for how the history and
legacy of the Hall’s Hill/High View Park Volunteer Fire
Department and Fire Station No. 8 should be celebrated
as part of the new fire station to be built at 4845 Lee
Highway.
4
Charge (cont.)
• Recommendations may address the following elements:
• The exterior of the station and site (i.e. distinctive architectural
features, signage, creative use of color and materials, lighting,
landscaping, paving, public art, possibilities for temporary and
permanent interpretative heritage exhibits);
• The interior public, non-operational spaces* (i.e. distinctive
architectural features, possibilities for temporary and permanent
interpretative heritage exhibits, public art, other design elements
or features); and
• Opportunities for reuse of existing building materials if
appropriate to honor history and legacy of the station.
• All recommendations will allow Arlington County Fire Department
(ACFD operational) requirements to be met and fall within the Key
Parameters laid out below.
5
Meeting Procedure and Communication
• Presentations and Question & Answer Period
• Requests for Information
• Public Comment
• Report
• https://projects.arlingtonva.us/projects/fire-station-
no-8-history-legacy-working-group//6
Working GroupTimeline
7
Kickoff Working Group Meetings Guiding Principles
Subcommittee Work Draft Report Report to County Manger
March March-May March-April
March-April Beginning-Mid May End of May
Fire Station No. 8
8
4845 Lee Highway
Arlington, VA 22207
Current Conditions of Fire Station No. 8
9
• Built in 1963
• 2 Bays
• Cannot handle required equipment
• Insufficient space for current
requirements such as gear storage,
decontamination area, and training
• Limited lockers and change facilities
• Inadequate cooking facilities
• Insufficient parking
• Technology upgrades
Fire Station Program
• ~ 15,000 Square Feet Building including• 4 Bays Apparatus Bay & Operation spaces
• Residential spaces
• Administrative rooms
• Support areas
• Drive Thru Bays
• Temporary Fire Station
• 12 staff parking
• Fuel Island
10
11
$000’s
FS 8 Base Bldg in 2017-2026 CIP $15,120
Not Included: $000’s
Temp Station Land $2,500
Temp Station Construction $1,150
New Fuel Island $1,500
Contingency (15% on above) $ 770
$5,920 $ 5,920
Forecast Cost $21,040
Funds Sources
2016 Referendum $ 1,120
FY16 Carryover $ 2,500
2018 Referendum $17,420 (was $14,000)
$21,040
BUDGET FORECAST
SCHEDULE FORECAST
12
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
TASK ORDER A/ E DESIGN AND PERMITTING TEMP
GLUP AMEND, REZONING 3 PARCELS TO S3A, & 2232 FINDING
CMAR RFP
AE PERM STATION RFP
PERM STATION - DESIGN & PERMITTING
2018 REFERENDUM
CONSTRUCT TEMPORARY FIRE STATION CofO
CONSTRUCT PERMANENT FIRE STATION & FUEL ISLAND
PROCUREMENT
DESIGN
REZOING AND 2232 FINDING, PUBLIC PROCESS
CONSTRUCTION
BOARD APPROVALS
PFRC REVIEW
2021ACTIVITY
2017 2018 2019 2020
SCHEDULE FORECAST
Temporary Fire Station &
Construction Zone
13
Temporary Fire Station & Construction
Zone
Finished Site Condition
14
Finished Site Condition
GLUP and Zoning – Current and
Proposed
• Existing Fire Station No. 8 parcel – No change from current S3-A
• Three parcels for temporary station change require GLUP amendment and rezoning from R-6 to S-3A
• S-3A:
– Consistent with permanent station S-3A zoning
– Allows for the program needs (i.e. by-right use, 45’ height maximum)
– Typically found adjacent to/surrounded by low residential areas
– Precedent: 5 of 10 stations in S3A
• Change GLUP for three parcels from “Low Residential’” to “Government and Community Facilities”, consistent with current FS parcel.
15
GLUP and Zoning
SCHEDULE FORECAST
16
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
TASK ORDER A/ E DESIGN AND PERMITTING TEMP
GLUP AMEND, REZONING 3 PARCELS TO S3A, & 2232 FINDING
CMAR RFP
AE PERM STATION RFP
PERM STATION - DESIGN & PERMITTING
2018 REFERENDUM
CONSTRUCT TEMPORARY FIRE STATION CofO
CONSTRUCT PERMANENT FIRE STATION & FUEL ISLAND
PROCUREMENT
DESIGN
REZOING AND 2232 FINDING, PUBLIC PROCESS
CONSTRUCTION
BOARD APPROVALS
PFRC REVIEW
2021ACTIVITY
2017 2018 2019 2020
SCHEDULE FORECAST
Questions & Answers
17
18
What’s Possible for the Future?
19
Themed Construction
Nauck Town Square
Bob Peck Chevrolet
HH/HVP
24
Walk of Honor
Fire Stations
26
Courthouse Mural
Heritage Wall
27
Heritage Walls
Wrap up
• Next Task Force Meetings
– March 22, 7:00 p.m. – 9:00 p.m.
Langston Brown CC
– April 5, 7:00 p.m. – 9:00 p.m.
Langston Brown CC
• Contact Information:
Noah Simon Email -
29