Final TL Presentation_10 04 2012

Embed Size (px)

Citation preview

  • 7/27/2019 Final TL Presentation_10 04 2012

    1/34

    Power Generation & Transmission

    20,000 MW

    Current

    4620 MW

    FY 2020

  • 7/27/2019 Final TL Presentation_10 04 2012

    2/34

    2

    Adani Power: Power Generation & Transmission

    Dahej

    Under Implementation:

    3,300 MW

    Under Implementation: 1,320 MW

    Kawai August 2013

    Commissioned: 4,620MW

    Under Planning: 2,640 MW

    Under Planning : 1,320 MW

    Chhindwara

    Mundra

    Tiroda July 2013

    Under Planning

    3,300 MW

    Bhadreshwar

    Sr. No. Connecting Locations Length(Kms)

    1 Mundra Dehgam

    1000 MW, 400 KV

    433

    2 Tiroda Warora

    1000 MW, 400 KV DC

    219

    3 Mundra Mohindergarh

    2500 MW, 500 KV HVDC

    1000

    4 Tiroda Aurangabad1

    4500 MW, 765 KV SC

    1290

    Total 2,942

    Power Generation

    Power TransmissionDehgam

    Mohindergarh

    Aurangabad Warora

    Notes:1 Project under AEL Subsidiary

    No Location Capacity (MW)1 Mundra (Gujarat)* 4,660

    2 Tiroda (Maharashtra) 3,300

    3 Kawai (Rajasthan) 1,320

    Total - Implementation 9,280Under Planning

    (Pench, Dahej & Bhadreshwar)7,260

    Grand Total 16,540

    Adani Power projects are in high growth states of India.

    40 MW Operational Solar Power Project in Gujarat1* In Operation 4660 MW

  • 7/27/2019 Final TL Presentation_10 04 2012

    3/34

    3

    Power Scenarioin India at a Glance

    As per the 17th Electric Power Survey (EPS), energy demand is estimated to

    increase at a CAGR of 7.4%, to 1392 billion kWh during the Eleventh Five-Year Planperiod (2012-17).

    The government has targeted a capacity addition of 1,00,00 MW during the Twelfth

    Five-Year Plan period.

    The central sector is expected to account for a major portion of the capacity additions(21.5%), followed by the state sector (15%) the private sector (45.5%) and captive

    power addition of 12%.

    The total installed capacity in the Northern region was 53,925 MW as on 31 th March,

    2012. The peak power deficit in Haryana as recorded in June, 2008 was 10.2% which

    is greater as compared to the overall figure for the entire northern region.

    The peak deficit for the whole of northern region was recorded at 8.5%.

  • 7/27/2019 Final TL Presentation_10 04 2012

    4/34

    4

    Power Generation & Transmission: The Story So Far Adani

    Thermal Operational Capacity 4,620 MW

    Five operational Super Critical units (660 MW each) first time in India

    Lower carbon and green house emission

    Current Projects under implementation

    At Advanced Stage : 4,620 MW (Tiroda 3,300 MW & Kawai 1,320 MW)

    At Development Stage : 7,260 MW

    (Pench 1,320 MW, Dahej 2,640 MW, Bhadreshwar 3,300 MW)

    Long term off take arrangement for 7,269 MW in place (79 % of 9,240 MW Mundra, Tiroda, Kawai)

  • 7/27/2019 Final TL Presentation_10 04 2012

    5/34

    5

    Installed Capacity in Haryana as on 30.06.2008

    Sector Hydro Thermal Nuclear R.E.S Total

    Coal Gas Diesel Total

    State 884.2 1,602.5 0.0 3.9 1,606.4 0.0 0.3 2,553.3

    Private 0.0 0.0 0.0 0.0 0.0 0.0 6.0 6.0

    Central 366.9 380.0 534.0 0.0 914.0 53.0 0.0 1,333.9

    Total 1,313.5 1,982.5 534.0 3.9 2,520.4 53.0 6.3 3,893.2

  • 7/27/2019 Final TL Presentation_10 04 2012

    6/34

    6

    Supply and Demand situation in Haryana 30.06.2008

    Period PeakDemand

    (MW)Peak

    Met

    (MW)Peak Deficit

    /

    Surplus

    (MW)

    Peak

    Deficit

    /

    Surplus (%)

    Energy

    Require-

    ment (MU)Energy

    Avail-

    ability

    (MU)

    Energy

    Deficit

    /

    Surplus (MU)

    Energy

    Deficit

    /

    Surplus

    (%)

    9th Plan

    End3,000 2,900 -100 -3.3 18,138 17,839 -299 -1.6

    2002-03 3,411 3,325 -86 -2.5 20,298 19,688 -610 -3.02003-04 3,465 3,278 -187 -5.4 20,743 19,779 -964 -4.62004-05 4,037 3,621 -416 -10.3 21,801 20,562 -1,239 -5.72005-06 4,333 3,931 -402 -9.3 23,791 21,631 -2,160 -9.12006-07 4,837 4,201 -636 -13.1 26,249 23,132 -3,117 -11.92007-08 4,956 4,821 -135 -2.7 29,353 25,652 -3,701 -12.6Apr 08 4,965 4,461 -504 -10.2 6,396 5,809 -587 -9.2June 08 4,965 4,461 -504 -10.2 2,180 2,089 -91 -4.2

  • 7/27/2019 Final TL Presentation_10 04 2012

    7/34

    7

    HVDC Project Back Ground

    ADANI POWER LIMITED has acquired an order for 1424

    MW of Power sale for 25 years to Haryana State fromHaryana Vidyut Prasaran Nigam Lt. ( HVPNL) under stiff

    competition with other Independent Power Producers in

    India.

    The Power to Haryana will be supplied from Adani PowerLtd.(APL) 4620 MW Mundra Power Plant situated in Gujarat.

  • 7/27/2019 Final TL Presentation_10 04 2012

    8/34

    8

    The Task

    The 1424 MW of Power will be delivered at HVPNLs 400

    kV Mohindergarh Substation in Haryana state which is

    situated 960 kM away from Mundra Power Plant in Gujarat.

    The Power Delivery date to HVPNL is August 2012.

  • 7/27/2019 Final TL Presentation_10 04 2012

    9/34

    9

    Criteria

    The system decision is based on the fulfillment of the following criteria:

    i) Minimum Losses in Transmission

    ii) Minimum Right of way for Line corridors (to save environment

    and save time and avoid disputes for obtaining ROW).

    iii) High reliability under system/ grid disturbances.

    iv) High availability to take care of contingencies.

    v) Proven Technology.

    vi) Possibility to control the Power flow.

    vii) Most optimum cost of the system to control investment.

  • 7/27/2019 Final TL Presentation_10 04 2012

    10/34

    10

    POWER DELIVERY TO HARYANA VARIOUS OPTIONS:

    In addition to PPA agreement with Haryana for 1424 MW of Power,

    about 416 MW of Power is available for trading and Northern Regionis already in need of Power, it is considered prudent to deliver this

    additional power to Northern Grid through Central Transmission

    Utility (CTU).

    Therefore the Transmission system to Haryana should have Powerhandling capacity = 1508 + 412 MW = 1920 MW ( say 2000 MW).

    Whatever opotion is chosen, any single contingency should be able to

    deliver atleast 1424 MW power to Haryana to fulfill PPA commitment.

  • 7/27/2019 Final TL Presentation_10 04 2012

    11/34

    11

    POWER DELIVERY TO HARYANA VARIOUS OPTIONS:

    Contd..

    3 Nos 400 kV Double Circuit quad conductor Lines with switching

    stations at every 300 kM with Reactive compensation and Seriescompensation.

    2 Nos Single Circuit 765 kV quad conductor Lines with 400/765 kV

    station at Mundra, 2 Nos 765 kV Switching stations in between with

    Reactive compensation and Series compensation.

    2500 MW, +/- 500 kV HVDC Bipole system with Quad Bipole line, 2

    Nos.Electrode stations 25 to 35 kM from Mundra and Mohindergarh,

    2 Nos. Optical communication booster stations.

    From the Techno- Economic Analysis, the 2500 MW, HVDC System

    becomes an obvious choice.

  • 7/27/2019 Final TL Presentation_10 04 2012

    12/34

    Power Limited

    FINANCIALS

  • 7/27/2019 Final TL Presentation_10 04 2012

    13/34

    13

    Project Cost

    The Project cost has been estimated to be Rs. 2,750crores which includes the turnkey cost of the EPC

    Contractor, Project management fee, financing charges

    and IDC, other miscellaneous expenditure, developmentexpenses, contingency and margin money towards

    working capital.

  • 7/27/2019 Final TL Presentation_10 04 2012

    14/34

    14

    Details of Project Cost

    Sr.No Particulars Amount

    1. Land 50.002. HVDC Converter stations, Electrode station and booster stations 1,457.81

    3. Transmission Lines and other Tower materials 304.88

    4 Conductor 181.91

    Insulators 126.81

    5. Hardware and Line Accessories 29.00

    Earth Wire 7.00

    PTCC/Forest Clearance 1.50

    Earth Electrode 22.66

    Miscellaneous Fixed Assets 30.00

    Sub Total 2,211.57

    7. Contingency 245.20

    8. PreOperative Expenses 48.00

    9. Margin money 6.49

    10. Interest during Construction 238.25

    Sub Total 537.94

    Total Project Cost ~ 2,750.00

  • 7/27/2019 Final TL Presentation_10 04 2012

    15/34

    15

    Means of Finance of the Project

    Particulars Amount PercentageCapital Contribution

    - Adani Power Limited 550.00 Cr 20%

    Debt Finance

    - Rupee Term Loans

    - Sub-Ordinate Debt2,062.50 Cr

    137.50 Cr75%

    5%

    Total 2,750.00 Cr 100%

  • 7/27/2019 Final TL Presentation_10 04 2012

    16/34

    16

    PROJECTED FINANCIAL INDICATORS - ASSUMPTIONS

    Debt Equity Ratio 4:1

    Upfront Equity 25%

    Tenure of Loan 12.5 years

    Construction & Moratorium period 30 monthsRepayment period 10 years

    Interest Rate of the Project Term Debt 11.25%

    Notice to Proceed (NTP) October 2009Line Capacity (MW) 2500

    Base Case Capacity for Transmission Revenues (MW) 1873

    Levelised Tariff for PPA with Haryana (Rs./kWh) 2.94

    Transmission Service Charge (Rs.) 0.40

  • 7/27/2019 Final TL Presentation_10 04 2012

    17/34

    17

    PROJECTED FINANCIAL INDICATORS

    Financial Yearend 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

    Total Transmission(MW) 557 1873 1873 1873 1873 1873 1873 1873 1873 1873Net generation(In MU) 22.3% 74.9% 74.9% 74.9% 74.9% 74.9% 74.9% 74.9% 74.9% 74.9%

    Transmission Tariff (Rs.) 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4

    Revenue 196.9 661.7 663.1 662.7 662.4 662.0 661.6 661.2 660.9 660.5

    Expenditure 9.2 30.2 31.0 31.9 32.8 48.6 49.6 50.7 51.8 53.0

    EBITDA 187.7 631.5 632.1 630.8 629.5 613.4 612.0 610.6 609.1 607.5

    Depreciation 46.5 139.6 139.6 139.6 139.6 139.6 139.6 139.6 139.6 139.6

    Interest 82.7 239.7 214.9 190.1 165.3 140.5 114.7 89.8 65.0 40.2

    PBT 58.5 252.2 277.6 301.2 324.7 333.3 357.8 381.1 404.5 427.7

    EBITDA Margin 95.3% 95.4% 95.3% 95.2% 95.0% 92.7% 92.5% 92.3% 92.2% 92.0%

    TTL 2062.1 1855.9 1649.7 1443.5 1237.3 1031.1 824.9 618.6 412.4 206.2

    TOL 2206.1 1999.1 1779.2 1559.3 1339.4 1119.5 899.6 679.7 459.8 239.9

    Interest Coverage 2.20 2.38 2.65 2.98 3.40 3.89 4.74 6.00 8.24 13.23

    FACR 1.31 1.38 1.47 1.58 1.73 1.94 2.25 2.78 3.83 6.98

  • 7/27/2019 Final TL Presentation_10 04 2012

    18/34

    18

    PROJECTED FINANCIAL INDICATORS - COMPANY

    Financial Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

    Revenue 464 2,108 5,172 9,025 9,069 9,110 9,152 9,204 9,058 9,116 9,180

    Expenditure 241 1,053 2,372 3,647 3,709 3,773 3,907 4,090 4,161 4,235 4,311

    EBITDA 223 1,055 2,801 5,378 5,359 5,337 5,246 5,114 4,897 4,881 4,869

    Depreciation 49 213 551 935 935 935 935 935 935 935 935

    Interest 80 383 1,225 1,841 1,678 1,501 1,325 1,149 969 793 616

    PBT 94 459 1,025 2,601 2,746 2,901 2,986 3,030 2,992 3,153 3,318

    PAT 84 394 804 1,872 1,983 2,100 2,172 2,659 2,623 2,764 2,908

    Cash Accruals 133 608 1,355 2,807 2,918 3,035 3,107 3,594 3,558 3,699 3,843

    EBITDA Margin 48.0% 50.0% 54.2% 59.6% 59.1% 58.6% 57.3% 55.6% 54.1% 53.5% 53.0%

    PAT Margin 18.0% 18.7% 15.5% 20.7% 21.9% 23.1% 23.7% 28.9% 29.0% 30.3% 31.7%

    Equity Capital 5,689 5,689 5,689 5,689 5,689 5,689 5,689 5,689 5,689 5,689 5,689

    Res. & Surplus 84 478 1,282 2,880 4,589 6,416 8,132 10,335 12,503 14,811 17,263

    TNW 5,773 6,167 6,971 8,569 10,279 12,105 13,821 16,024 18,192 20,500 22,953

    TTL 6,759 11,324 14,578 13,350 11,829 10,309 8,789 7,268 5,748 4,227 2,707

    TOL 7,100 12,460 16,675 15,970 14,813 13,365 11,871 10,294 8,694 7,108 5,523

    ROCE 1.4% 4.8% 10.4% 20.3% 20.0% 19.6% 19.1% 17.9% 16.5% 16.0% 15.3%

    TTL/TNW 1.17 1.84 2.09 1.56 1.15 0.85 0.64 0.45 0.32 0.21 0.12

    TOL/TNW 1.23 2.02 2.39 1.86 1.44 1.10 0.86 0.64 0.48 0.35 0.24

    Int. Coverage 2.67 2.59 2.06 2.47 2.68 2.97 3.29 4.07 4.62 5.62 7.19

    FACR 1.30 1.19 1.32 1.37 1.47 1.60 1.77 2.01 2.38 3.01 4.36

  • 7/27/2019 Final TL Presentation_10 04 2012

    19/34

    19

    Financial Indicator Estimated Value

    Minimum DSCR 1.41

    Average DSCR 1.74

    Project IRR 24.50 %

    Key Financial indicator - Project

    Key Financial indicator - Company

    Financial Indicator Estimated Value

    Minimum DSCR 1.26

    Average DSCR 1.73

    Project IRR 20.27 %

  • 7/27/2019 Final TL Presentation_10 04 2012

    20/34

    20

  • 7/27/2019 Final TL Presentation_10 04 2012

    21/34

    21

    Own transmission lines for Power evacuation

    433 Kms, 400 KV to transmit 1,000 MW - Operational

    1000 Kms, 500 KV HVDC to transmit 2,500 MW - Operational

    Carbon Credits: Projects certified as CDM Projects by UNFCCC

    Mundra Ph III (2 x 660 MW): First Super Critical technology project in the world

    Mundra Ph III - 1.84 Mil CER p.a. for 10 years from commissioning.

    Tiroda Ph I - 1.19 Mil CER p.a. for 10 years from commissioning

  • 7/27/2019 Final TL Presentation_10 04 2012

    22/34

    22

    Thank You

  • 7/27/2019 Final TL Presentation_10 04 2012

    23/34

    23

    Back up Slides

  • 7/27/2019 Final TL Presentation_10 04 2012

    24/34

    24

    Adani Power Limited (APL) owns the following transmission lines:

    - 400 kV D/C from Mundra Dehgam

    - 500kV HVDC Bipole Trans. Line Mundra Mohindergarh

    - 400 kV D/C from Mohindergarh - Bhiwani

    - 400 kV D/C from Mohindergarh Dhanonda

    Adani Power Maharashtra Limited (APML), subsidiary of APL, owns the following transmission line:

    - Tiroda Warora

    MEGPTCL, subsidiary of Adani Enterprise Limited (AEL), owns the following transmission line:

    - Tiroda - Aurangabad

    Current Structure

  • 7/27/2019 Final TL Presentation_10 04 2012

    25/34

    25

    Power Sector Scenario

    (in MW)

    Source Hydro Thermal Nuclear Total

    Central 8 ,654 24,840 3,380 36,874

    State 3,482 23,301 -- 26,783

    Private 3,491 11,552 -- 15,043

    Total 15,627 59,693 3,380 78,700

    Source: document on M id-Term Appraisal of the eleventh Five Year Plan. Planning Commission, GoI

    (in MW)

    Source Hydro Thermal Nuclear Total

    Central 2,922 14,920 3,380 21,222

    State 2,854 18 ,501 -- 21,355

    Private 2,461 17,336 -- 19,797

    Total 8 ,237 50 ,757 3,380 62,374

    Source: document on M id-Term Appraisal of the eleventh Five Year Plan. Planning Commission, GoI

    Original Targets f or Capacit y Addit ion in Power Sector during the Eleventh Plan

    Revised Targets for Capacity Addit ion in Power Sector during the Eleventh Plan as per

    Mid Term Appraisal of Planning Commission

  • 7/27/2019 Final TL Presentation_10 04 2012

    26/34

    26

    Power Sector Scenario

    Capacity Addition - (April 11 to February 12)Source Hydro Thermal Nuclear Res @ Total

    Target (MW) 1,9 80 14,636 1,000 - 17,616

    Acheivement 1,28 1 12,052 - - 13,333

    @Renewable Energy Sources (RES) includes Small Hydro Project(SHP), Biomass Gas(BG), Biomass Power(BP),

    Source : CEA

    h f

  • 7/27/2019 Final TL Presentation_10 04 2012

    27/34

    27

    Growth of Transmission Sector

    Central State JV/ Pvt Total Central State JV/ Pvt Total

    6th Plan 1,831 4,198 -- 6,029 1,641 44,364 -- 46,005

    7th Plan 13,0 68 6,756 -- 19,824 4,560 55,071 -- 59,631

    8 th Plan 23,0 01 13,141 -- 36,142 6,564 73,0 36 -- 79,600

    9Th Plan 29,345 20 ,0 33 -- 49,378 8 ,687 88 ,306 -- 96,993

    10 th Plan 50 ,992 24,730 -- 75,722 9,444 1,0 5,185 -- 1,14,629

    11t h Plan upt o Feb 12 75,337 33,399 7,520 1,16,256 10 ,919 1,28 ,0 53 430 1,39 ,40 2Source: CEA

    Central State JV/ Pvt Total Central State JV/ Pvt Total

    6th Plan 715 8 ,615 -- 9,330 50 0 36,791 -- 37,291

    7th Plan 6,760 14,820 -- 21,58 0 1,881 51,861 -- 53,742

    8 th Plan 17,340 23,525 -- 40,865 2,566 81,611 -- 84,177

    9Th Plan 23,575 36,80 5 -- 60,380 2,866 1,13,497 -- 1,16,363

    10 th Plan 40 ,455 52,487 -- 92,942 4,276 1,52,221 -- 1,56,497

    11th Plan upto Feb 12 74,880 73,172 630 1,48,682 5,956 2,13,735 1,567 2,21,258

    Source: CEA

    SINCE 6TH FIVE YEAR PLAN

    Sub Stations (MVA)

    220 kV Sub-Stat ions40 0 kV Sub-Stations

    At the end of

    At the end of

    400 kV t ransmission Lines 220 kV Transmission Lines

    Transmission Lines (ckm)

    h f i i

  • 7/27/2019 Final TL Presentation_10 04 2012

    28/34

    28

    Growth of Transmission Sector

    Cent ral Sector State Sector JV/ Pvt Total

    765 kV 6,0 01 473 -- 6,474

    40 0 kV 75,337 33,399 7,520 1,16,256

    220 kV 10 ,919 1,28 ,053 430 1,39,402

    +/- 500 kV HVDC Lines 5,948 1,504 1,980 9,432

    765 kV 13,500 -- -- 13,50 0

    40 0 kV 74,880 73,172 630 1,48 ,682

    220 kV 5,956 2,13,735 1,567 2,21,258

    BTB Stn Converter Terminal (MW) 9,500 1,700 -- 11,200

    Source: CEA

    GROWTH OF TRANSMISSION SECTOR (As on 29 -0 2-20 12)

    Transmission Lines (ckm)

    Substations (MVA)

    +/- 500 kV HVDC Converter

    G h f T i i S

  • 7/27/2019 Final TL Presentation_10 04 2012

    29/34

    29

    Eleventh Five Year Plan Rs in BillionsInter - State 750

    Int ra - State 650

    Total 1,400

    Source: Ministry of P ower, Report of the Working Group on Power for Eleventh Plan (2007-2012).

    Twelf th Five Year Plan Rs in Billions

    Inter - State 2,400

    Int ra - State 4 ,000

    Total 6 ,400

    Source: CEA, Key Inputs fo r XIIth Plan Financing of P ower Sector

    Investment Planned in Transmission Sector in Eleventh Plan

    CEA est imates for Targetted Investment in Transmission

    Sector in Twelfth Plan

    Growth of Transmission Sector

    T i i S

  • 7/27/2019 Final TL Presentation_10 04 2012

    30/34

    30

    Transmission Sector

    Transmission Lines (both AC

    and HVDC)

    6t h Plan 7th Plan 8t h Plan 9t h Plan At the end of

    10t h Plan

    Add. in first

    four yearsof 11th Plan

    (2007-11)

    Expected at

    end of 11thPlan

    Expected

    additionduring 12th

    Plan

    Expected by

    end of 12thPlan

    HVDC Bipole lines - - 1,634 3,138 5,872 1,580 9,432 9,440 18,872

    765 kV - - - 971 1,704 1,636 4,616 27,000 31,616

    400 kV 6,029 19,824 36,142 49,378 75,722 26,856 1,12,961 38,000 1,50,961220 kV 46,005 59,631 79,600 96,993 1,14,629 19,561 1,40,782 35,000 1,75,782

    Total Transmission Line, ckm 52,034 79,455 1,17,376 1,50,480 1,97,927 49,633 2,67,791 1,09,440 3,77,231

    Source

    Draft National Electricity Plan (Volume - II) Transmission

    [In fulf ilment of CEAs obligation under section 3(4) of t he Electricit y Act 200 3]Government of India

    Ministry of Power

    Central Electricit y Authority

    Feb-12

    (values in ckm)

    T i i S t

  • 7/27/2019 Final TL Presentation_10 04 2012

    31/34

    31

    Transmission Sector

    Draft National Electricity Plan (Volume II) considers 80 GW generation addition for 12 th Plan over and above 62 GW target as per

    Mid Term Assessment for 11th Plan by Planning Commission.

    Fund requirement for development of Transmission System estimated to be of the order of Rs. 1,80,000 Crore.

    ATL R t d S ti T

  • 7/27/2019 Final TL Presentation_10 04 2012

    32/34

    32

    APL / APML would provide following securities to existing lenders for the period they give NOC for release of

    Security till the time their money is paid.

    Undertaking from Adani Power Limited

    Corporate Guarantee of Adani Enterprises Limited

    ATL Requested Sanction Terms

    P d M h i

  • 7/27/2019 Final TL Presentation_10 04 2012

    33/34

    33

    Part II

    AEL to infuse Funds to extent of 30% of Total Assets to take over share of APL and APML amounting to Rs.

    1,397 Crores

    Funds from AEL will be utilized for repayment to APL (Rs 1201 Crs) & APML (Rs. 196 Crs.)

    Partnership Firm to be Converted in Company under Part IX of Companies Act, 1956 immediately which shall be

    WOS of AEL.

    Proposed Mechanism

    Ad t f S ti t APL & APML

  • 7/27/2019 Final TL Presentation_10 04 2012

    34/34

    34

    Advantages of Separation to APL & APML

    Transmission Lines shall be available for transferring Power generated by APL and other Power Generating Units

    and surplus capacity will be available to other power producers,

    Reduction in transmission cost for APL & APML

    To get priority on wheeling our power though other national gird in case of technical shut down / breakdown of

    our Transmission Line.

    Reduction in Debt of Rs. 3600 Crs in APL and Rs. 455 Crs in APML

    Debt Equity Ratio to Improve