    METROPOLITAN PARK

    ARLINGTON COUNTY, VIRGINIA

    DESIGN GUIDELINES

    JANUARY 23, 2004

    Revised to incorporate design featuresrecommended or conditioned by the ArlingtonCounty Planning Commission and Board as ofFebruary 10, 2004.

  • 8/9/2019 Final Metro Park Designs Guidelines

    2/44

    TABLE OF CONTENTS

    Preface

    Framework Plan

    Street Classification

    Circulation: Pedestrian, Vehicular Bicycle

    Entrances: Residential, Parking, Service

    Phasing

    Overview

    Street Sections:

    12th Street Extended

    15th Street

    South Fern Street

    South Eads Street

    Elm and 14th Streets

    13th Street

    East and West Elm Street

    Typical Tertiary Streets

    Open Space

    Public Art

    Building Guidelines

    Height and Massing

    Architectural Elements

    Materials

    Ground Floor Retail Characteristics

    Signage

    Landscape Guidelines:

    Streetscape Features

    Pedestrian Arcade Detail

    Crosswalk Plan

    Plant Materials

    Quality and Size

    Soil Over Structure

    Suggested Plant Species

    Street Furniture Illustratives:

    Benches and Tables

    Lighting and Trash Receptacles

    3-12

    13-14

    15

    16

    16

    18

    19

    19

    20

    20

    21

    22

    23

    24

    25-26

    27-28

    29

    30

    30

    31

    32

    33-36

    37

    38

    40

    40

    41-42

    43

    44

    2METROPOLITAN PARK

    Purpose and Intent

    The Metropolitan Park Design Guidelines have been derived from

    design principles that were identified and discussed in a companionProject Book dated November 12, 2003. The guidelines in this book

    detail the pattern of development for this future residential community,and establish standards for streets, buildings, open space, andlandscaping as a means of insuring quality and consistency as phaseddevelopment proceeds over time.

    This Design Guidelines document and its companion Project Bookrepresent the evolution of Pentagon City planning and development and

    set the stage for the completion of the residential component of thePentagon City Plan.

    Sufficient detail is provided in the Design Guidelines document for the

    community and residents to know the quality of development which isexpected, but not so rigid as to stifle design and innovation for the

    future.

    The Design Guidelines insure a level of quality which can be easily

    referenced for future buildings.

    This Design Guidelines document is to be adopted by reference into theCounty Board approval of the Planned Development Site Plan (PDSP)for Pentagon City.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    3/44

    3 Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    4/44

    4METROPOLITAN PARK

    PREFACE

    The Metropolitan Park Design Guidelines is a

    companion to the project book compiled by Robert A.M. Stern Architects dated November 12, 2003.Excerpts of that project book are reprinted here toprovide context for the Design Guidelines.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    5/44

    5 Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    6/44

    PREFACE

    6METROPOLITAN PARKRevised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    7/44

    7 Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    8/44

    PREFACE

    8METROPOLITAN PARKRevised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    9/44

    9 Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    10/44

    PREFACE

    10METROPOLITAN PARKRevised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    11/44

    11 Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    12/44

    PREFACE

    12METROPOLITAN PARKRevised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    13/44

    13

    Framework Plan

    Lower buildingelements alongSouth Fern Street

    Three tall buildings in theproject core will anchorthe site and complimentexisting development tothe east

    Lower building heights at 15thstreet will complimentresidential development on the opposite side of the streetand provide variety at the site edges

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    14/44

    FRAMEWORK PLAN

    The street grid shall provide for theextension of 12th Street and construction of

    13th

    and 14th

    Streets between South Fernand South Eads Streets.

    A park feature shall approximate 2 acres in

    size and be accessible to the public.

    Building heights shall vary throughout thedevelopment generally tapering up from

    lower density residential development.The number of stories portrayed on theFramework Plan reflect locating all of theapproved residential units between 12th

    Street and 15th Street. The actual numberof stories may vary slightly with theapproval of the 4.1 site plans. Maximumheights are indicated in each phase ofdevelopment.

    Ground floor retail shall be provided alongSouth Fern Street and 12th Streetextended.

    Sidewalks shall be provided along both

    sides of streets and parks with otherpedestrian passageways provided as

    appropriate to enhance access into thesite. Final landscape design and the exactlocation of street trees will be determinedat the time of site plan review andapproval.

    Conceptual Ground Level Plan

    Ground level retailalong South Fernand 12thStreetextended

    Residential along 15thStreetand South Eads Street

    The following key features will be an integral part

    of Metropolitan Parks development plan.

    14METROPOLITAN PARK

    15th Street

    14th Street

    13th Street

    12th Street

    Elm

    Str

    ee

    t

    Elm

    Street

    S.Fe

    rnStr

    eet

    S.Ea d

    sS

    tre

    et

    E.

    Elm

    St r

    ee

    t

    W .E

    lmS

    tre

    et

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    15/44

    P

    P

    P

    P

    P

    P

    P

    PP

    15

    STREET CLASSIFICATION

    Primary streets are located around theperimeter of the development. They

    connect the proposed development withthe surrounding Pentagon Center area.12th Street shall be extended betweenSouth Fern and South Eads Streets. All

    primary streets shall be public streets.

    Secondary streets shall form a modified

    street grid pattern within the developmentbetween South Fern and South EadsStreets, and between 15th and 12th Streets.The north/south road shall be broken by

    the central park feature both to promotetraffic calming and to maximize openspace. All secondary streets shall beprivate with public access easements

    placed in them.

    Tertiary streets shall provide internal

    access for individual phases of thedevelopment. All tertiary streets shall beprivate with public access easements

    placed over them and where appropriate,the streetscape may incorporate unique

    design elements such as specialty paving,awnings and landscaping to create settingsfor particular buildings.

    Street names, as shown are i llustratives.Final names will be approved by ArlingtonCounty.

    Streets shall be classified as primary, secondary,

    and tertiary.

    Legend:

    Primary streetSecondary street

    Tertiary street

    Pedestrian connections

    Bike Lane

    Two-way street

    One-way street

    Parking entrance

    Service entrance

    Residential entrance

    P

    SR

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    16/44

    16METROPOLITAN PARK

    CIRCULATION

    12th, 13th , 14th and Elm Streets shall be

    constructed through the property to provideaccess for the development, and to break up thecurrent superblock so that access through it is

    enhanced.

    Sidewalks shall be provided along both sides ofstreets, and around/through parks, with other

    pedestrian passageways provided as appropriateto enhance access into and through the site.

    Parking along both sides of the streets will be

    provided to the extent possible to accommodateshort term visitors and retail customers, and topromote traffic calming as a means of enhancingthe pedestrian experience. Parking on both

    sides of project streets may reduce the amountof park acreage.

    A bike lane shall be provided along 15th street.

    Residential, Parking, Service

    Residential buildings shall have majorentrances on interior secondary and tertiarystreets, with dual access to primary streets as

    depicted on the exhibit (opposite page).

    Parking and service entrances shall be limitedto tertiary streets and non-park-frontagesecondary streets.

    Residential service and loading will be handledinside the building and managed so as to avoid

    blocking the street.

    Sufficient parking reserved for commercialusers shall be provided in each phase of thedevelopment. In Phases 3 and 4, commercial

    parking will be consolidated to facilitateconvenient access to all spaces by customers.Construction will be completed in the phasewith which the parking spaces are associated.

    ENTRANCES

    Vehicular, Pedestrian, Bicycle

    The following improvements shall be made to enhancevehicular, pedestrian, and bicycle circulation:

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    17/44

    17

    Phased DevelopmentBuildings, Streets and Open Space

    Legend:

    Street construction to beimplemented with current phase

    Street construction to beimplemented with previous phase

    SouthFernStr

    eet

    Alley

    SouthEadsStr

    eet

    15thStreet

    Existing condition Phase 1 Phase 2 Phase 3 Phase 4

    Phase 5 Phase 6 Phase 7 Phase 8 Proposed buildout withnew street grid pattern

    12thSt.

    13thSt.

    14thSt.

    15thSt.

    SouthFern

    St.

    WestElmSt.

    EastElmS

    t.

    ElmSt.

    ElmSt.

    SouthEadsSt.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    18/44

  • 8/9/2019 Final Metro Park Designs Guidelines

    19/44

    19

    12th Street Extended and 15th Street

    Key Map

    12th Street**View Looking West

    **Streets shall be officially designated 12thStreet South and15thStreet South per the adopted Transportation Plan.

    15th Street**View Looking West

    Revised as of February 10, 2004

    STREET SECTIONS

  • 8/9/2019 Final Metro Park Designs Guidelines

    20/44

    20METROPOLITAN PARK

    STREET SECTIONS

    South Fern and South Eads Streets

    South Eads Street

    View Looking North

    South Fern StreetView Looking North

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    21/44

    21

    Key Map

    Elm and 14th Streets

    14th Street (at Phase 1)**View Looking West

    14th Street (at Phases 6-7)**View Looking West

    **Streets shall be officially designated South Elm Street and14thStreet South per the adopted Transportation Plan.

    Elm Street**View Looking North

    Revised as of February 10, 2004

    STREET SECTIONS

  • 8/9/2019 Final Metro Park Designs Guidelines

    22/44

    22METROPOLITAN PARK

    STREET SECTIONS

    13th Street

    13th Street**View Looking West

    **Street shall be officially designated 13thStreet Southper the adopted Transportation Plan.

    Planting at building base

    Alternate: Hardscape up to building base

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    23/44

    23

    West and East Elm Streets

    Key Map

    West Elm Street**View Looking North

    East Elm Street**View Looking North

    ** West Elm Street shall be officially designated South Fair Street and East ElmStreet shall be designated South Elm Street, per the adopted Transportation Plan.

    Revised as of February 10, 2004

    STREET SECTIONS

  • 8/9/2019 Final Metro Park Designs Guidelines

    24/44

    24METROPOLITAN PARK

    STREET SECTIONS

    Typical Tertiary Streets

    Typical Tertiary Street Section (at Phase 1)**West Elm Street View Looking West

    **The Phase 1/Phase 7/Phase 8 tertiary street will be officiallydesignated 14thRoad South per the adopted Transportation Plan.

    The Phase 3/Phase 4/Phase 5 tertiary street will be officiallydesignated 12thRoad South per the adopted Transportation Plan.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    25/44

    Pathway Hierarchy

    25

    Central Green

    Central Green

    Revised as of February 10, 2004

    OPEN SPACE

  • 8/9/2019 Final Metro Park Designs Guidelines

    26/44

    26METROPOLITAN PARK

    A Central Green shall be designed as acontinuously accessible ground plane made upof large and small open space components witha prominent north/south pedestrian connectionthat helps to organize the open space. Asresidential build-out occurs and community

    needs are assessed, this portion of the park maybe programmed for a variety of active andpassive recreation. Large and small open spaceareas shall therefore be sized to accommodate

    outdoor community gatherings, more active usessuch as frisby toss and impromptu ball games

    with friends and family, recreation alternatives forsmall children, and passive uses such as sitting,strolling, and reading. A tot lot shall beincorporated into the open space plan.

    Smaller parks to the north, south and east of the

    central green shall be designed as integral partsof the residential components with which they areassociated while at the same time providing an

    extension both visually and physically to theCentral Green.

    Open space within the core of the project shall compriseapproximately 2 acres, be open to the public and be

    designed to accommodate a variety of passive andmore active uses.

    Landscaped courtyards located throughout theremaining areas of the site shall be designed to

    enhance the pedestrian experience either visually in thecase of private courtyards or physically wherepedestrians are expected to pass by on their way toother destination points.

    Public plaza space will be incorporated into thedevelopment as appropriate, either within the Central

    Green or along primary street frontage.

    All parks shall be designed to accommodate focal/public

    art features.

    Typical Residential Park

    Walkways Inside Park Areas

    Landscape Plan

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    27/44

    27 Revised as of February 10, 2004

    PUBLIC ART

  • 8/9/2019 Final Metro Park Designs Guidelines

    28/44

    28METROPOLITAN PARK

    Examples Of Public Art

    A public art concept plan shall be developed forMetropolitan Park, coordinated with the County

    Arts Commission, and approved by the County.At the time of approval of a final site plan foreach phase, a contribution shall be made towardfulfilling the concept plan, either in the form of

    actual art or a monetary contribution to helpprovide public art in a later phase of the project.In anticipation of the development by others of apublic art plan for the 10 acres located to thenorth of 12th Street-extended, a portion ofMetropolitan Parks total public art contribution

    may be allocated to art endeavors on thisadjacent parcel if such is determined to beappropriate during the art master planningprocess .

    A public art consultant shall be retained todevelop the concept plan. Public art features

    may include sculpture, fountains, specialtypaving or building details that have beenspecifically designed to promote art in the publiceye.

    Consideration shall be given to location of public

    art in relation to urban plazas, parks andpedestrian connections that are within the

    development or along its periphery.

    Revised as of February 10, 2004

    Building heights shall vary soas to add interest to the skyline

  • 8/9/2019 Final Metro Park Designs Guidelines

    29/44

    29

    The building base shall relate to the adjacentstreet and sidewalk and be scaled to enhance

    the pedestrian experience. The base may becharacterized by light-colored masonry materialswith a darker water-table and an articulatedfaade for first floor residential uses, and the

    addition of windowed facades for ground floorretail uses. Cornices may be used to differentiatethe building base from the shaft. First floor heightshall be a minimum of 18 feet .

    The shaft may be designed as a darker f ield with

    lighter accents so as to reinforce vertical andhorizontal rhythms of the architecture and break

    the scale of the building.

    The building crown shall define the building atthe skyline and shall incorporate as appropriatearchitectural elements to create a memorableimage.

    Height and Massing

    The project site shall be organized around 3, 22-story

    buildings which will serve as anchors and referencepoints to the various phases in the development.

    Buildings shall generally taper with height variation andsetbacks as they approach streets, to provide variety at

    the street level, to compliment established developmenton opposite sides of public streets and to enhance openspaces within the project. The principle for tapering upfrom existing low rise residential will be adhered to, and

    used where appropriate to enhance open space areas.The height of individual buildings shall be determined ona phase by phase basis once overall project density hasbeen established by the County under an amended

    PDSP allocation. Height maximums shall be asindicated on the Framework Plan.

    Individual buildings shall follow massing and stylistic

    strategies of traditional classical buildings, such as thedivision into base, shaft, and crown. Building materialand color may vary from building to building so as toprovide variety.

    as to add interest to the skyline

    Building shall taper and step back fromthe streets, to provide variety at the streetlevel, compliment nearby established uses andenhance open space within the development

    Three tall buildings in the core of thesite shall serve as organizing elementsand shall compliment established highrise residential development to the east

    The building base willactivate the streetscape

    and will be scaledto enhance the pedestrian

    experience

    Revised as of February 10, 2004

    BUILDING GUIDELINES

  • 8/9/2019 Final Metro Park Designs Guidelines

    30/44

    30METROPOLITAN PARK

    Street level residential shall feature individual

    entrances, views of courtyard open space and /or building articulation, to animate the faade and

    add interest to the streetscape.

    Street level commercial shall feature largewindowed retail space with awnings and/orsignage that varies with the commercial use.

    Architectural Elements

    First floor facades shall be articulated to enliven the

    street and enhance the pedestrian experience.

    Where balconies are provided, they shall be designedas an integral component of the faade.

    Mechanical systems shall either be internalized withinthe building or be carefully designed to blend into thebuilding faade.

    Materials

    Masonry (l ight and dark brick) with cast stonedetailing shall be the predominant building

    material. The palette of materials may alsoinclude Rockcast, Precast, Arriscraft, pre-formedarchitectural details, and natural stone.

    Windows shall be aluminum or steel in thefollowing configurations: casement, double hung,single hung, or slider. Color will be metallic orpainted to accent the architecture.

    Balconies shall have articulated rails or low wallsused in conjunction with a metal railing system.

    Loading doors shall be a solid metal horizontal

    slat door, painted to blend with the color of thebuilding. Garage doors shall be solid metal orhorizontal bar style designed to blend with thebuilding faade.

    Base

    Shaft

    Crown

    Cornice

    Cornice

    Revised as of February 10, 2004

    Ground Floor Retail Characteristics

    Approximately 100 000 square feet of ground floor

  • 8/9/2019 Final Metro Park Designs Guidelines

    31/44

    31

    Approximately 100,000 square feet of ground floorretail space shall be located along Metropolitan

    Parks South Fern Street and 12 th Street frontage.Storefronts shall be readily identifiable, anddifferentiation among tenants through individualsignage and storefront design shall be encouraged.The street faade shall be composed as a simple

    plane with limited jogs and inclination interruptedonly by streets, pedestrian arcades providingaccess to the interior of the development, and lobbyaccess for designated residential buildings.

    The maximum floor to floor story height l imitfor the ground floor shall be 24 feet.

    The ground floor faade shall have between

    60 and 90 percent fenestration (glass doorsshall count toward this requirement),

    measured as a percentage of the faade thatis between 2 and 10 feet above the frontingsidewalk.

    Awnings and overhangs will be encouraged.Where such is provided:

    There must be a minimum clear height of10 feet above the sidewalk.

    Awnings shall be made of canvas cloth orequivalent, metal or glass.

    Quarter cylinder configurations shall be

    discouraged. Windows and doors

    Windows shall be made of anodizedaluminum, wood, clad wood, vinyl, or steel.

    Window glass shall be clear or tinted. Noreflective glass shall be utilized. Specialtywindows may utilize stained, opalescent, orglass block but shall not be a predominantfeature.

    Doors shall be made of wood, clad wood,steel, glass, aluminum and shall match or

    compliment the storefront windows. There shall be functioning entry door(s)

    along the street faade at intervals notgreater than 80 feet.

    Recognizing the communitys desire toencourage commercial which helps to sustainthe residential development, the developer willprepare a Retail Attraction and Marketing Plan(RAMP) and will encourage professional offices(such as doctors and dentists) to locate within

    the first floor retail areas. Ground floor commercial space in Phases 2

    through 8 shall be serviced by loading facilitiesthat are internal to the building.

    Revised as of February 10, 2004

    BUILDING GUIDELINES

  • 8/9/2019 Final Metro Park Designs Guidelines

    32/44

    32METROPOLITAN PARK

    Wall signs will be permitted within an area

    between the second story floor line and the firstfloor ceiling, within a horizontal band not toexceed three feet in height. In no case shall thisband be higher than 20 feet or lower than 12 feetabove the adjacent sidewalk.

    Letters shall not exceed 24 inches in height or

    width and 8 inches in relief.

    Company logos or names may be placed withinthe horizontal band noted above, or placed or

    painted within ground floor windows. Companylogos or names shall not be larger than 9 squarefeet.

    Street addresses shall be placed at street entrydoors using 6 inch tall non-cursive type letteringthat no less than 6 tall, unless otherwise

    determined by County requirements.

    Shop signs (not more than 18 inches vertical by3 feet horizontal with a minimum of 9 foot clearheight above the sidewalk) may be wall mountedor hung from an overhang or awning.

    If lettering is applied to an awning, it shall belimited to the vertically hanging fabric on the curbside of the awning.

    Awning shall not have internal il lumination.

    Prohibited signs shall include billboards,marquees, any kind of animation, roof andpainted window signs (other than company

    logos), flat plexiglas box signs, and signs paintedon the exterior walls of buildings. No flashing,traveling, animated, or intermittent lighting shallbe on the exterior of any building whether such

    lighting is of temporary or long-term duration.Temporary sandwich board type signage shall

    be permitted as long as a minimum clearsidewalk width of 8 feet exists.

    Signage

    Individual signs for residential buildings will be approvedwith each 4.1 site plan application. A temporarywayfinding sign package shall be developed and shall

    remain in place until all secondary streets have been

    completed. Signage for the commercial portion of thedevelopment shall comply with the following guidelines:

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    33/44

    33 Revised as of February 10, 2004

    LANDSCAPE GUIDELINES

  • 8/9/2019 Final Metro Park Designs Guidelines

    34/44

    34METROPOLITAN PARK

    Streetscape Feature

    Streetscapes shall be designed to provide a safe meansof pedestrian circulation, easy access to buildings and

    amenities within the development and linkages to thegreater Pentagon City community. Streetscape

    conditions may vary, adding to the pedestrianexperience. However, consistency in sidewalk width,street tree species, tree pit details, and paving pattern

    details shall be maintained along individual streets.

    Street trees and ground plane planting shall beprovided between sidewalks and street curbs to

    soften the interface between pedestrians andvehicles.

    Buildings shall meet the sidewalk along retail

    facades.

    Planting areas may be provided at the base ofresidential buildings where individual unitentrances, stoops, etc. exist, so as to soften andenrich the streetscape and enhance theresidential character of the street.

    Street furniture such as benches and trashreceptacles shall be provided along streets and

    within parks. Street furniture design may vary

    within the development. Benches, lighting (perArlington County standards) and trashreceptacles provided along the retail edges of

    South Fern and 12th Streets may differ, forinstance, from those provided along the moreresidential perimeter streets of 15th and SouthEads Streets. Yet another street furniture

    package may be appropriate for park settingsand building entrances situated along secondaryand tertiary streets within Metropolitan Park.

    Consistency shall be maintained, however, alongindividual streets and within individual parkcomponents.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    35/44

    LANDSCAPE GUIDELINES

  • 8/9/2019 Final Metro Park Designs Guidelines

    36/44

    36METROPOLITAN PARKRevised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    37/44

    37

    Pedestrian Arcade Detail

    PedestrianArcades

    Pedestrian Arcades will have a minimum height of 14 feet and will be lighted in accordance with

    Arlington County standards with wall sconces, down lighting, ceiling fixtures or some combinationthereof. Arcade walls will be treated with the same building materials thatare specified for other public portions of the building face.

    Revised as of February 10, 2004

    LANDSCAPE GUIDELINES

  • 8/9/2019 Final Metro Park Designs Guidelines

    38/44

    38METROPOLITAN PARK

    Crosswalk Plan

    Note: Overall pedestrian circulation system is illustrated on page 5. Crosswalks

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    39/44

    39 Revised as of February 10, 2004

    LANDSCAPE GUIDELINES

    Plant Materials Quality and Size

  • 8/9/2019 Final Metro Park Designs Guidelines

    40/44

    40METROPOLITAN PARK

    Plant Materials Quality and Size

    All plant material and methods of installation shall be inaccordance with Arlington County standards and as set

    forth in this design manual. Plants shall be nursery-grown and specified in accordance with the latest

    edition of the American Standard for Nursery Stock(American Association of Nurserymen), ANSI Z60.1.Plants shall be true to species and variety, unless

    specifically noted otherwise, and shall be sound,healthy, vigorous, well branched and densely foliatedwhen in leaf. Unless otherwise specified, street treesshall be a minimum of 4 to 4-1/2 caliper and spaced

    approximately 30 on center.

    Plant Materials and Soil Over StructurePlanting over structure shall be in accordance withArlington County standards and as set forth in this

    design manual. Soil depth for trees shall be a minimumof four (4) feet, with one (1) foot of drain rock below anddrainage as required. Required soil depth may beaccomplished through mounding (where possible and/orpractical), depressing/folding the structural slab,constructing retaining walls not to exceed 30 in height,

    or a combination of these methods. Soil mix shall be in

    accordance with Arlington County standards and as setforth in this design manual. Root enhancementpractices (such as amended soil panels, root paths

    and/or structural soil) shall be specified by County stafffor street tree plantings.

    Revised as of February 10, 2004

  • 8/9/2019 Final Metro Park Designs Guidelines

    41/44

    41 Revised as of February 10, 2004

    LANDSCAPE GUIDELINES

    Streetscape Plantings Primary and Secondary Park AreasSuggested Plant Species

  • 8/9/2019 Final Metro Park Designs Guidelines

    42/44

    42METROPOLITAN PARK

    Streetscape Plantings:

    Deciduous Street Trees (canopy/shade trees)

    Acer rubrum Red Sunset (Red Sunset Maple)

    Gleditsia triacanthos var. inermis Skyline (Skyline Honeylocust)Platanus acerifolia Bloodgood ( Bloodgood Londonplane Tree)

    Quercus coccinea (Scarlet Oak)

    Quercus imbricaria (Shingle Oak)

    Quercus lyrata Highbeam (Highbeam Overcup Oak)

    Quercus phellos Hightower(Hightower Willow Oak)

    Quercus rubra (Red Oak)

    Tilia cordata (Littleleaf Linden)

    Tilia tomentosa (Silver Linden)Ulmus parvifolia Bosque (Bosque Lacebark Elm)

    Ulmus parvifolia Allee (Alee Lacebark Elm)

    Zelkova serrata Green Vase (Japanese Zelkova)

    Tree pit groundcover plantings

    Arctostaphylos uva-ursi (Bearberry)

    Gaultheria procumbens (Wintergreen)

    Hypericum calycinum (Aaronsbeard St. Johnswort)Juniperus horizontalis cultivars (creeping junipers)

    Liriope muscari (Lilyturf)

    Primary and Secondary Park Areas:

    Deciduous Ornamental/Understory Trees

    Amelanchier canadensis (Serviceberry)

    Lagerstroemia indica (Crape Myrtle)Prunus x. yedoensis (Yoshino Cherry)

    ShrubsAzalea cultivars and hybrids

    Cotoneaster dammeri (Bearberry cotoneaster)

    Ilex crenata (Japanese Holly)

    Ilex glabra (Inkberry)

    Ilex x meserveae Blue Princess (Meserve hybrid Holly)

    Juniperus chinensis Sargentii (Sargent Juniper)Prunus Laurocerasus (Cherry Laurel)

    Taxus baccata Repandens (Repandens Yew)

    Taxus x media Densiformis (Dense Yew)

    Pedestrian Alley in Central Green:

    Canopy Trees

    See street tree list, plus:

    Acer rubrum Armstrong (Columnar Red Maple)

    Magnolia grandiflora Greenback (Columnar Southern Magnolia)

    Evergreen Trees

    Metasequoia glyptostroboides (Dawn Redwood)

    gg p

    Revised as of February 10, 2004

    Street Furniture Illustrative: Benches and

  • 8/9/2019 Final Metro Park Designs Guidelines

    43/44

    43

    Tables

    Revised as of February 10, 2004

    LANDSCAPE GUIDELINES

    Street Furniture Illustrative: Lighting and

  • 8/9/2019 Final Metro Park Designs Guidelines

    44/44

    Trash Receptacles

    44METROPOLITAN PARKRevised as of February 10, 2004