Upload
victor-onyeka
View
28
Download
0
Tags:
Embed Size (px)
Citation preview
CHAPTER ONE
1.0 INTRODUCTION
Nigeria spends about N400 billion yearly to import diesel to run our
homes and industries, but energy experts, some of whom work in the
Ministry of Power, say the real crisis in the sector today is the N1.8 trillion
loss in the nation’s annual Gross Domestic Product, as a consequence of
the current energy policy presided over by Rilwan Lanre Babalola, the
energy minister.(NEXT magazine 20th November 2010)
“The poorest in our community, currently pay more than N80 per kilowatt
burning candles and firewood, while our manufacturers pay in excess of
N60 per kilowatt on diesel generation and everyone else pays around N50
per kilowatt on self-generation” an energy expert in the Ministry of Power
who spoke confidentially to NEXT in Abuja at the weekend said. Gross
Domestic Product represents the total value of goods and services
produced in a country over a period of time, typically a year.
Startling revelations like this could only leave us to imagine what the
future holds for the power sector.It is fairly settled in the literature that
infrastructure plays a critical and positive role in economic development.
Infrastructure interacts with the economy through multiple and complex
processes. It represents an intermediate input to production, and thus
changes in infrastructure quality and quantity affect the profitability of
production, and invariably the levels of income, output and employment.
Moreover, infrastructure services raise the productivity of other factors of
production (Kessides, 1993). The provision of infrastructure in most
developing countries is the responsibility of the government. This is
because of the characteristics of infrastructure investment. First,
infrastructure supply is characterized by high set-up cost. Its lumpiness
and indivisibility precludes the private sector from investment. Second, its
indirect way of pay-off, coupled with its long gestation period, makes it
generally unattractive to private investors. Moreover, provision also
generates externalities that the producer may not be fully able to
internalize in the pricing structure. Thus, in the face of other numerous
competing, less risky and more familiar investment opportunities offering
1 | P a g e
the promise of higher and quicker returns, few private investors are willing
to embark on infrastructure investment (Ajayi, 1995). However, the nearly
exclusive concentration of infrastructure provision in the hands of the
public sector, especially in developing countries, has led to failures in the
supply of these services. Faced with declining economic fortunes and
dwindling revenue, most governments in developing countries found it
increasingly difficult to keep pace with adequate provision and
maintenance of infrastructure. Moreover, the perception of government
that economic infrastructure is a social service affected the pricing of its
products and consequently the effectiveness of their provision. Besides
these, the traditional inefficiency associated with public monopolies affects
the quality and reliability of their services. There are five main approaches
used in the literature to infer the welfare losses from power outages.
These are the production function approach, self-assessment analysis,
economic welfare analysis, contingent valuation and, finally, the revealed
preference approach. These methods have their relative strengths and
weaknesses. They have been used widely in both developed and
developing countries, especially the former, to infer outage costs. For the
industrial sector, existing measure of outage costs vary between $1.27 to
$22.46/kWh of unserved electricity. Residential outage costs vary between
$0.02 and $14.61/kWh unserved (Caves, Herriges and Windle, 1992).
1.1 STATEMENT OF THE PROBLEM
In Nigeria, poor electricity supply is perhaps the greatest infrastructure
problem confronting the business sector. The typical Nigerian firm
experiences power failure or voltage fluctuations about seven times per
week, each lasting for about two hours, without the benefit of prior
warning. This imposes a huge cost on the firm arising from idle workers,
spoiled materials, lost output, damaged equipment and restart costs. The
overall impact is to increase business uncertainty and lower returns on
investment. For the aggregate economy, this has seriously undermined
Nigeria’s growth potential and the attractiveness of the economy to
external investors. The Power holding Company of Nigeria (PHCN) is the
public/Private utility vested with the responsibility of electricity supply in
2 | P a g e
Nigeria. However, the failure of PHCN to provide adequate and reliable
electricity to consumers despite billions of naira of investment expenditure
has generated a confidence crisis in the industry. Public confidence in
PHCN’s ability to supply uninterrupted and stable electric power is so low
that consumers don’t longer rely on it’s supply they prefer to use own
generation device(s) like generator. The inefficiency of PHCN imposes a
huge cost on the economy. In 1990, the World Bank estimated the
economic loss to the country from then NEPA’s inefficiency at about N1
billion. There are essentially five ways by which firms may respond to
unreliable electricity supply. These are choice of location, factor
substitution, private provision, choice of business and output reduction.
While all these elements are presently observed among Nigerian firms, the
most common approach has been through private provision. Electricity
consumers have responded to PHCN’s inefficiency through self-generation.
Electricity users, both firms and households, now find it necessary to
provide their own electricity in part or in whole to substitute or
complement PHCN supply by factoring generator costs into the overall
investment cost, thus raising significantly the set-up cost for
manufacturing firms operating in the country. Incidentally, indigenous,
small-scale enterprises are worse affected. Lee and Anas (1991) report
that small-scale enterprises spend as much as 25% of the initial
investment on self-provision of a generator. Banks also insist that firms
seeking project loans must make provisions for investments in captive
generating equipment (Ajayi, 1995). This affects the range of profitable
investment available to budding entrepreneurs, raises cost of production,
reduces cost competitiveness of local production and represents a loss of
revenue to the electricity monopoly.
Electricity, strictly speaking, is not a private good. The sector is
characterized by high set-up costs and increasing returns to scale that
permit at most very few producers. However, the legislation setting up
PHCN effectively bars private operators from the markets and thus
prevents such possibilities as joint production and pooled supply, satellite
behaviours by private firms that could have led to shared costs and
guaranteed reliable supply of electricity. Thus, there are big firms with
huge excess scale that are not allowed to sell their excess production to
other firms. One implication of the existing electricity market structure is
3 | P a g e
that PHCN, by taking advantage of the huge economies of scale in the
industry, is able to supply electricity at
much lower cost than private provision. This cost differential is large,
sometimes running to over four times. A 1983 joint UNDP/World Bank
study estimated a cost differential of 16–30% for large industrial
establishments in the country with auto-generation. In spite of this large
cost differential, however, over 90% of Nigerian manufacturers make
provision for auto-generation. The relevant question then is, Why are
manufacturers willing to incur such a huge extra costs for self-generation?
Is it possible that the manufacturers are perfectly rational agents who are
willing to incur the extra cost of auto-generation as an insurance against
the larger costs from power outage? An understanding of the behavior of
the firm is important in proffering policy recommendations to solve their
energy problems. In addition, an analysis of outage costs may provide
useful data for measuring the willingness of consumers to pay for reliable
electricity supply, measure the inefficiency of PHCN and hence form a
basis for reform of the public monopoly. A few studies have tried to
measure the cost of electric power shortages in Nigeria. These include
Ukpong (1973), Iyanda (1982), Lee and Anas (1991, 1992), Uchendu,
(1993) and Ajayi (1995). Our study is different from these studies in two
important respects – the methodology and the scope. Our methodology
combines the benefits of the revealed preference and survey techniques.
The principle of revealed preference implies that the impact of an outage
may be inferred from the actions taken by consumers to mitigate losses
induced by unsupplied electricity. Investments in backup generators may
then be used to impute the costs incurred by power outages. In addition,
we also investigate the factors underlying the behaviors of consumers in
the attempt to mitigate outage losses. We complement the results from
the revealed preference methodology with those obtained from subjective
valuation. The survey technique enables us to measure the impact of
outage characteristics on outage costs. In terms of scope of coverage, the
study focuses on a disaggregated analysis of the manufacturing sector of
the Nigerian economy. This enables us to examine the differential impact
of outages across the various subsectors of the manufacturing sector, and
across sizes and locations.
4 | P a g e
1.2 PURPOSE OF THE STUDY
The central purpose of this study is to examine the impact of
infrastructure failures on the performance of the Nigerian manufacturing
sector, using the case of the electricity sector, and to understand the
behavior of firms in adapting to the uncertain business environment.
The specific objectives of the study are to:
Determine the severity of infrastructure problems in Nigeria.
To determine firms perception of the factors responsible for the
poor performance in the power sector.
To characterize electricity outages in Nigeria and the impact across
various Nigerian manufacturing sector.
To determine the level of impact that power outages has on the
industry and to also know the factors that contribute to the impact..
To determine the scale of production that suffers most.
To determine firms perception of how to improve the power sector.
1.3 RESEARCH QUESTIONS
Which of the infrastructures is most problematic to manufacturing
firms in Lagos state.
What are the factors responsible for the poor performance of the
power sector.
What impact does power failure has on Nigerian manufacturing
sectors.
What methods can be applied for the improvement of the power
sector.
1.5 SIGNIFICANCE OF THE STUDY
5 | P a g e
Technological infrastructure is an enabling environment required
for rapid growth of technological and industrial development and comprises
physical and human variables like energy, water, transport, communication,
financial and human capital (Chenery 1960; Afonja 2003). Ability to provide
and effectively apply these inputs is a direct indicator of the potential for
the development of any nation, and it is primarily differentiating factor
between the various levels of development worldwide.
As this research work examines the impact infrastructural failure
has on a developing economy using the electricity sector of the Nigeria.
1.6 SCOPE OF THE STUDY
The scope of this research work covers the three senatorial district
of Lagos. Lagos is chosen as sample so as to draw conclusion from it and
then make generalization about Nigeria.
1.8 LIMITATIONS OF STUDY:
In the course of this research work, we were faced with several
limitations. Our major limitation was the financial aspect. Due to lack of
finance, we limited the research to Lagos state only.
The respondents which are industries and manufacturing companies
on the other hand did not make things easy as we have to follow ‘due
process’ which in some cases it took weeks to return some questionnaires,
some were not even returned as at the time of the analysis.
Some companies refused to part with some information as they told
us that it is against the company’s policy.
We also had difficulty in obtaining a sample frame for all the
companies, thereby leaving us no option but to use decide the sample size
subjectively.
6 | P a g e
CHAPTER TWO
2.0 LITERATURE REVIEW
2.1 REVIEW OF THE LITERATURE ON ELECTRICITY OUTAGES
The poor state of infrastructure supply in developing countries has a
negative impact on their economic performance. For example, Lee and
Anas (1992) report that manufacturing establishments in Nigeria spend on
average 9% of their variable costs on infrastructure, with electric power
accounting for half of this share. Elhance and Lakshamanan (1988) show
that changes in the stock of economic infrastructure have important
implications for the cost structure of manufacturing firms in India. Even in
the informal sector, infrastructure can be a major share of business
expenses (e.g., in Zimbabwe, transport accounted for 26%, the largest
single item, according to Kranton, 1991). Similarly, a 1987 study focusing
on the effects of power outages in Pakistan estimated that the direct costs
of load shedding to industry during a year, coupled with the indirect
multiplier effects on other sectors, resulted in a 1.8% reduction in GDP and
a 4.2 reduction in the volume of manufactured exports. In India, a 1985
study concluded that power outages were a major factor in low capacity
utilization in industry, and estimated the total production losses in 1983/84
at 1.5% of GDP (USAID, 1988).
Similarly, power rationing in Colombia was estimated to reduce overall
economic output by almost 1% of GDP in 1992 (Kessides, 1993). Usually
small firms bear a relatively higher cost of infrastructure failures. Lee and
Anas (1992) in a 1988 study of 179 manufacturing establishments in
Nigeria found that the impact of infrastructure deficiencies of all types was
consistently higher for small firms. Private infrastructure provision (for
generators, boreholes, vehicles for personnel and freight transport, and
radio communications equipment) constituted 15% of total machinery and
equipment costs for large firms (over 50 employees), but 25% for small
firms. Small firms were found to generate a larger percentage of their
7 | P a g e
power needs privately than larger firms and to pay a higher premium for
doing so, as measured by the excess costs of privately generated power
over that of publicly provided. Other enterprise level surveys conducted in
several countries have found that infrastructure costs and problems of
unreliability rank high among issues in the business environment. A 1991
survey of small enterprises in Ghana cited power outages, transportation
costs and other infrastructure problems among the top four problems of
operations (behind taxes), with this response strongest among “micro”
and small firms. Electricity outage was ranked by very small firms among
their top four constraints to expansion (Steel and Webster, 1991). Thus,
the issue of infrastructure supply – its adequacy and reliability – is very
important for the overall performance of the business sector and deserves
policy attention.
The theoretical basis for estimating electricity outages is that
there is a consumer welfare loss when there is electric power failure. Quite
a number of studies have examined the cost of outages using the various
approaches noted earlier. However, until recently many of these studies
focused on the developed countries, which have less actual experience of
outage failures. Moreover, there are significant differences in the
methodologies used, leading to highly disparate results regarding the
impact of service interruptions. Finally, fewer studies have focused on the
impact of the characteristics of outage cost such as the warning time,
outage frequency and partial outages.
Table 2.1 provides a summary of the literature on outage costs estimates.
These estimates vary significantly according to the choice of
methodologies and reporting system used. The proxy methods have
yielded estimates that are generally lower than those reported by the
survey methods. For the industrial sector, existing studies put the cost of
interruptions in the range of $1.27 to $22.46/kWh of unserved electricity.
Residential outage costs vary between $0.02 and $14.61/kWh unserved. In
the case of commercial sectors of the economy, outage costs range from
$5.02 in the retail service sector to $21.73kWh for office buildings. The
evidence points to significantly lower outage cost for government agencies
and institutions (Caves et al., 1992).
8 | P a g e
Table 2.1 :A typology of selected previous study.
STUDY COUNTARY SECTOR METHODOLOGY
Bental and Ravid
(1982)
USA AND ISREAL INDUSTRIAL PROXY METHOD(GENERATOR)
Bernstein and Heganazy (1988)
EGYPT INDUSRIAL(PRODUCTION)
PROXY METHOD
Billinton, Wacker and Wojczynski (1982)
CANADA RESIDENCIAL SURVEY
Caves, Herriges and Windle (1992)
USA INDUSTRIAL PROXY METHOD
Matsukawa and Fujii
(1994)
JAPAN FINANCIAL AND COMMUNICATION
PROXY METHOD(GENERATOR & UPS)
Ontario Hydro (1977)
CANADA INDUSTRIAL SURVEY
Billinton, Wacker and
Wojczynski (1982)
CANADA INDUSTRIAL SURVEY
Doane, Hartman and
Woo (1988)
CANADA RESIDENCIAL SURVEY
Ukpong (1973 NIGERIA INDUSTRIAL(PRODUCTION)
PROXY METHOD
Iyanda (1982) NIGERIA RESIDENCIAL SURVEY
Uchendu (1993) NIGERIA INDUSTRIAL SURVEY
Lee and Anas (1992) NIGERIA INDUSTRIAL SURVEY
Beenstock, Goldin
and
ISREAL BUSINESS & PUBLI PROXY METHOD(GENERATOR)
9 | P a g e
Haitovsky (1997)
Source : compiled by the writers(authors)
Another study reported by Billinton et al. (1982) and Ontario Hydro (1980) on
the sectoral variation in outage costs yielded similar conclusion. Residential
outage costs are found to be at the lower end of the spectrum, with costs less
than one-third of those estimated for industrial and commercial consumers.
Industrial outage costs are consistently lower than those in the commercial
sector, but the differences are not large. However, government and institutional
costs are consistently placed between those for residential and industrial
sectors, while office buildings and large farms have outage costs well in excess
of those for the commercial sectors. Some studies have also considered the
varied impact of outage characteristics on outage costs. Power outages can be
characterized along a number of dimensions, including duration, frequency,
timing, warning time and interruption depth. Each of these characteristics
potentially alters the outage costs incurred by a customer. Billinton et al. (1982)
and Ontario Hydro (1980) report that firms experience high outage costs
initially. However, these average hourly costs diminish rapidly as duration
increases, leveling off at about 50% of a 1-hour interruption.
Table 2.2 : estimated outage cost in selected previous studies.(US$ PER KWH)
COUNTARY COST SOURCEUSA 0.57 Telson 1975ISREAL 1.67 Telson 1975ISREAL 0.21 Bental & Ravid 1982USA 1.16 Bental & Ravid 1982ISREAL 7.20a Beenstock, Goldin and
Haitovsky (1997)
USA 11.20a CAVES,HERRIGES & WINDLE(1992)
10 | P a g e
JAPAN 118.149b Matsukawa and Fujii (1994)
Note : a-measured at 1991 price
b-measured at 1988 price.
The relationship between outage costs and outage frequency has
received less attention in the literature. The available results indicate that
total outage costs are not proportional to outage frequency, but rather
decline per interruption as frequency increases. This pattern suggests that
customers may be able to adapt to more frequent outages. Customers also
prefer infrequent outages to frequent outages. Studies by Billinton et al.
(1982) and
Ontario Hydro (1980) among industrial and commercial sectors reveal that
these consumers prefer infrequent long duration interruptions (e.g., one 4-
hour interruption) to frequent short duration interruptions (e.g., four 1 hour
interruptions). However, the reverse result was reported for residential
consumers. Similarly, outage costs have been found to vary with the timing
of the power interruptions. Large industrial firms exhibit little variability in
estimated outage costs, while small firms exhibit a definite seasonal
pattern. Virtually all of the industrial and commercial outage cost studies
attempted to measure the variation in outage costs by industrial
classification. Billinton et al. (1982) reported outage costs for 15 industrial
classifications. One-hour outage costs range from $2.00/ average kWh for
mineral fuels and paper and allied industries to over $60.00/average kWh
for leather industries. Ontario Hydro (1977) reports similar results for 12
industry groups with less variation in the outage costs among groups.
However, Caves et al. (1990) observed some limitations with these studies.
First, industry specific outage costs are typically based on few observations
(i.e., fewer than ten) so that differences between them may not be
statistically significant. Second, much of the variation in outage costs by
industrial category may reflect differences in load
factors across groups.
Industrial firms with self-generation capabilities have lower outage costs.
Self-
11 | P a g e
generation is found to lower the probability that customers may assign
positive costs to an outage, and to reduce costs by approximately 40%
given outage costs are positive. Backup power is found to increase the
probability of a positive outage cost, but to reduce the level of outage costs
by 0.03% for each 1% of backup power capabilities. Perhaps the earliest
study on the costs of power outages to the industrial and commercial sector
in Nigeria was carried out by Ukpong (1973). He used the production
function approach to study power outage costs in the two years, 1965 and
1966. Using a sample of 38 firms, he estimated unsupplied electrical energy
to be 130 kWh and 172 kWh in 1965 and 1966, respectively. The
corresponding costs of the power outages to the industrial sectors in the
two years were estimated at N1.68 million and N2.75 million, respectively.
The shortcomings of this study include: first, he used aggregated data for
the manufacturing sector and thus omitted subsector effects of the power
outages; second, the study focused on output loss for unsupplied electricity
and thus ignored other important costs such as raw material and equipment
spoilage and the cost of auto-generation. Iyanda (1982) adopted the self-
assessment methodology to estimate the impact of power shortages on the
household sector. He focused on the high-income area of Lagos Island,
Ikoyi, Victoria Island, Yaba and Surulere areas of Lagos state in Nigeria. He
estimated an average electricity outage cost of N1.19 per hour for each
household. A similar framework of analysis was reported in Uchendu (1993),
but the focus was on the industrial and commercial firms in Lagos state
through a survey covering various industrial sectors. The study estimated
several types of outage costs such as on material and equipment loss and
value of unproduced output. The value of unproduced output was estimated
at N1.3 million, N2.01 million and N1.32 million in 1991, 1992 and mid-
1993, respectively. However, the study suffers from the methodological
limitations of self-assessment data and was limited only to Lagos state.
World Bank (1993b) estimated the adaptive costs of electricity failure
on the Nigerian economy at US$390 million, divided between consumer
backup capacity (US$250 million), operating and maintenance costs of
diesel auto-generators (US$90 million), and fuel and lubrication (US$50
million). The estimate of NEPA revenue lost to unserved consumer energy
amounted to US$40 million. However, the short-term losses incurred by
12 | P a g e
consumers such as raw material and equipment spoilage and lost output
were not estimated.
Finally, Lee and Anas (1991) used the self-assessment survey to measure
the adaptive costs to the business sectors in coping with infrastructural
deficiencies in Nigeria. Their study shows that most firms in Nigeria adapt to
the unreliability of publicly provided electricity by investing in backups. The
huge investment costs of the backup increases the set-up costs of these
firms and thus reduces their competitiveness and relative efficiencies. One
important finding of this study is that small firms have borne the brunt of
power failure in Nigeria because they cannot afford personal generators.
The study shares the shortcomings of World Bank (1993b) in that the short-
term losses incurred by consumers arising from raw material and
equipment spoilage and lost output were not estimated.
Our methodology incorporates the strengths of both the revealed
preference approach and the self-assessment approach. Also quite
important is that we investigated the impact of outage characteristics on
outage costs, an issue that was not considered in the previous studies.
2.2 HISTORICAL BACKGROUND OF ELECTRICITY IN NIGERIA
The history of electricity development in Nigeria can be traced back
to the end of the 19th century when the first generating power plant was
installed in the city of Lagos in 1898. From then until 1950, the pattern of
electricity development was in the form of individual electricity power
undertaking scattered all over the towns. Some of the few undertaking
were Federal Government bodies under the Public Works Dept, some by
the Native Authorities and others by the Municipal Authorities.
ELECTRICITY CORPORATION OF NIGERIA (ECN)
By 1950, in order to integrate electricity power development and
make it effective, the then colonial Government passed the ECN ordinance
No. 15 of 1950. With this ordinance in place, the electricity department
and all those undertakings which were controlled came under one body.
13 | P a g e
The ECN and the Niger Dam Authority (NDA) were merged to become the
National Electric Power Authority (NEPA) with effect from the 1st of April
1972. The actual merger did not take place until the 6th of January 1973
when the first General Manager was appointed. Despite the problems
faced by NEPA, the Authority has played an effective role in the nation's
socio-economic development thereby steering Nigeria into a greater
industrial society. The success story is a result of careful planning and
hard work. The statutory function of the Authority is to develop and
maintain an efficient co-ordinate and economical system of electricity
supply throughout the Federation. The decree further states that the
monopoly of all commercial electric supply shall be enjoyed by NEPA to
the exclusion of all other organisations. This however, does not produce
privy individuals who wish to buy and run thermal plants for domestic use
from doing so. NEPA, from 1989, has since gained another status-that of
quasi-commercialisation. By this, NEPA has been granted partial autonomy
and by implication, it is to feed itself. The total generating capacity of the
six major power stations is 3,450 megawatts. In spite of considerable
achievements of recent times with regards to its generating capability,
additional power plants would need to be committed to cover expected
future loads. At present, efforts would be made to complete the on-going
power plant projects. Plans are already nearing completion for the
extension and reinforcement of the existing transmission system to ensure
adequate and reliable power supply to all parts of the country. By 1970,
the Military Government appointed a Canadian Consultant firm "Showment
Ltd" to look into the technical details of the merger. The report was
submitted to the government in November 1981. By Decree No. 24 the
ECN were merged to become the NEPA with effect from April 1, 1972. The
actual merger did not take place until the 6th of January 1973 when the
first General Manager was appointed. The day-to-day running of the
Authority is the responsibility of the Managing Director.
In the early 1960s the Niger Dam Authorities (NDA) and Electricity
Corporation amalgamated to form the Electricity Corporation of Nigeria
(ECN). Then, immediately after the Nigerian civil war, the management of
ECN changed its nomenclature to NEPA. What is currently referred to as
the Power Holding Company of Nigeria was formally known as National
14 | P a g e
Electric Power Authority. For several years, despite consistent perceived
cash investment by the Federal Government, power outages have been
the standard for the Nigerian populace, and are now seen as normal by
the citizens of the country. Generally, the tariff has been criticised as
being too low compared to the cost of generating power. The federal
government of Nigeria has increased the tariff to attract foreign investors
since the 1st of July, 2010 in order to meet the growing concern for foreign
investors into the electricity sector.
2.3 ELECTRICITY POLICY AND DECISION MAKING PROCESS
The major power utility in the country, the National Electric Power
Authority (NEPA), now known as the Power Holding Company of Nigeria (PHCN) is
owned by the Federal Government. Until recently, it has been the main electric
power monopoly for the generation, transmission and distribution of centralized
grid power. In order to engender greater efficiency and sustainability in the
system, a process of reforms has been started to remove government’s
monopoly on generation, transmission and distribution. Thus, in 2005, the
Electric Power Sector Reform Act (EPSRA) was enacted. The law is aimed at
liberalizing the power sector. A component of the power reform law, was the
creation of the Nigerian Electricity Regulatory Commission (NERC), which is
mandated to regulate the electricity sector based on free market economic
principles and thereby create a level playing field for all interested stakeholders
to participate in the sub-sector.
As a consequence of the reform process, the generation and distribution
areas of the electricity market are being deregulated. The PHCN is being
unbundled into six separate generation companies and eleven distribution
companies for the various parts of the country. These would be individually
licensed, while only the transmission area would remain under government
control in the Transmission Company of Nigeria (TCN).
In light of the current pathetic power situation in the country, and in spite of
the current liberalization process, the Federal Government is still increasing
15 | P a g e
investments in the sector to increase the generation capacity to 10,000MW by
2011 and to 20,000MW by 2015 through the National Integrated Power Projects
being implemented across the country. Most of the additional capacity would be
thermal (Gas) plants with renewable such as solar, biomass and wind
contributing a minimal amount. Nuclear power has been factored into the energy
mix, and it is expected that the first nuclear power plant of 1,000MW capacity is
expected to be commissioned not later than 2020.
2.4 STRUCTURE OF ELECTRIC POWER SECTOR
The electric power sector is currently dominated by a government
company, namely, the Power Holding Company of Nigeria (PHCN). It
currently owns all the power generation stations, the transmission network
and the distribution system. It has an installed capacity of 6000MWe
through a number of hydro (Kainji, Jebba, Shiroro), and thermal stations
(Egbin, Ughelli, Afam, Sapele). The Power Holding Company of Nigeria
(PHCN) Generation and Transmission System and its geographical
distribution is graphically depicted in Figure 2. The transmission voltage
levels are 330KV for the grid transmission; 132KV for the sub-transmission
lines, whilst the 33kV, 11KV and lower voltages constitute the distribution
networks. The System normal frequency is 50Hz. With the expected full
implementation of the Electric Power Sector Reform Act of 2005, and the
unbundling of the PHCN into the proposed generation and distribution
companies under a functional regulatory regime, the electricity market will
be liberalized. However, a large number of manufacturing companies
currently generate their own power, which further leads to increased cost
of production.
Although PHCN is the main supplier of public electricity, the state
governments have also participated in the provision of electricity, dating
back to the Third National Development Plan period, 1975–1980. They are
restricted to supplies in the rural areas, where there is no PHCN supply,
through the Rural Electrification Boards (REB). The ultimate goal of these
16 | P a g e
isolated supplies, based on fossil fuels, is that they would eventually be
linked to PHCN’s network when feasible. There are many REBs in several
states but their performance has been abysmal. The state governments
could not meet the high costs of operating and maintaining these small
isolated diesel-fired generating plants. Only consumers lucky enough to be
absorbed into the national networks experienced electricity supply for a
larger fraction of the day. Although the legal instrument establishing PHCN
vested it with the sole responsibility of electric power production in
Nigeria, in practice the situation has been different because of the poor
performance of the organization in the provision of adequate and reliable
electricity supply. The response of the private sectors to the poor quality
of PHCN’s electricity supply has been widespread use of private provision
of electricity. Certainly, the need to minimize the enormous cost of
frequent interruptions in public electricity supply as manifested in
considerable loss of output, damage to machinery and equipment, and
idle labour time has aided the sustenance of the de facto situation. In
recent years virtually all major new establishments, whether privately or
publicly owned commercial or individual enterprises, have undertaken
substantial investment in private supply of electricity. Obviously the
impact of this is to increase costs and reduce the competitiveness of the
country’s production both locally and in international trade. There are
essentially five ways by which firms might respond to infrastructure
deficiencies:
Choice of location
Factor substitution
Private provision
Choice of sector
Output reduction
However,
private provision is by far the strategy most widely adopted by Nigerian
firms. Piqued by the extremely poor performance of PHCN, private
providers have had to make alternative private arrangements to reduce
their dependence on PHCN, with the attendant losses from infrequent
electricity supply. Lee and Anas (1991) identify four different private
response strategies pursued by firms:
17 | P a g e
Self-sufficiency: In this case, the firm provides its own
infrastructural services to the point where it does not need any
public input.
Stand-by private provision: Here, the firm has its own
infrastructural facilities in place and switches to these facilities
where the quality or reliability of the public service falls below a
critical level.
Public source as standby: The firm relies primarily on its own
facilities but switches to the public supply during those times of the
day when the public source delivers a high quality service.
Captivity: The firm continues to rely on the public source
exclusively despite the very low reliability of such services.
In Nigeria, government regulations in the supply and trading of
infrastructural services prevent the possibilities of three other
mechanisms: joint production, satellite behavior or shared production. The
unreliability of PHCN has led most manufacturers to incur extra costs for
private alternatives. The generator market is very vibrant. Most small gas-
powered electric generating sets in use are Japanese products (e.g.,
Honda, Suzuki, Yamaha). Most of these products are imported from Japan,
while some are assembled in Nigeria. Holt Engineering Limited, for
example, is the company assembling Yamaha generators. Moreover, many
small-scale industrialists now prefer locally fabricated generating sets,
which are considerably cheaper than the imported brand names. The
Federal Ministry of Mines, Power and Steel is empowered to register all
electricity generating sets being used in the country, but few users
register with them.
18 | P a g e
CHAPTER 3
3.0 RESEARCH METHODOLOGY
3.1 RESEARCH PROCEDURE
Here we look at the various sources of data, the rationale for the chosen
research methodology, and the methodology for the analysis.
3.2 METHODOLOGY OF THE SURVEY
The sample framework of the Federal Office of Statistics (FOS) provided the basis
for the selection of the firms used in the survey. The sampling frame is not
possible get due to inability to get the total number of manufacturing
establishments in Lagos state. The study used a stratified random sampling
method to select specific firms. The stratification was necessary to reflect the
following variation: size, industry and location. The study covers three main
industrial zones: the Lagos west (Somolu) axis, the Lagos central(Lagos Island)
axis and the Lagos east(Ikeja) axis. Besides contributing over 90% of
manufacturing output in Lagos state, these zones also represent more than 66%
of electricity consumption in the State. In all, 120 manufacturing enterprises
were included in the survey 40 firms from each axis but 104 questionaires was
successfully retrieved. These are distributed as shown in Table
Table 3.1 : Distribution of respondents by sector, scale of production and location
Freqeuncy PercentageSector
Food and Manufacturig 15 14.4
Wood and Product 10 9.6
Beverages and Tobacco 20 19.2
Paper and Product 9 8.7
Textile and Leather 8 7.7
Rubber and Chemical 16 15.4
Metal and Product 20 19.2
Others 6 5.8
Total 104 100.0Location (senotarial district)
Lagos west(Somolu) 20 19.2
Lagos central (Lagos island) 42 40.4
Lagos east (Ikeja) 42 40.4Scale of production
19 | P a g e
Small scale 52 50.0
Medium scale 32 30.8
Large scale 20 19.2Source: Authors sample survey
For the purpose of the survey, firms that employed fewer than 50 workers were
classified as small scale, and those with more than 100 as large scale. Hence
firms that employ between 50 and 100 were regarded as medium-scale
enterprises.
Table 3.1 shows the surveyed companies encompassed producers of a
wide range of commodities, including capital goods, intermediate goods
and final goods. Specifically, the sectors covered include: Food
manufacturing
Beverages and tobacco
Textiles and leather
Wood and furniture
Paper and printing
Rubber and chemicals
Metals and products
Others
Thus the firms eventually selected spread across sectors, scales of
operations and the major industrial clusters of Lagos state, and should
therefore reflect a broad spectrum of the manufacturing firms in Lagos
state. The analysis of the survey data was carried out with the aid of a
computer software packages designed for the analysis of qualitative data.
The package is SPSS VERSION 17 (Statistical package for social sciences),
which is a very versatile tool for the analysis of qualitative data.
3.3 TOOL OF ANALYSIS
3.4 MULTINIMOIAL LOGISTIC REGRESSION
Logistic regression is the linear regression analysis to conduct when
the dependent variable is dichotomous (binary). Like all linear
20 | P a g e
regressions the logistic regression is a predictive analysis. Logistic
regression is used to describe data and to explain the relationship
between one dependent binary variable and one or more metric (interval
or ratio scale) independent variables.
Standard linear regression requires the dependent variable to be of
metric (interval or ratio) scale. How can we apply the same principle to a
dichotomous (0/1) variable? Logistic regression assumes that the
dependent variable is a stochastic event. That is that for instance if we
analyze a pesticides kill rate the outcome event is either killed or alive.
Since even the most resistant bug can only be either of these two states,
logistic regression thinks in likelihoods of the bug getting killed. If the
likelihood of killing the bug is > 0.5 it is assumed dead, if it is < 0.5 it is
assumed alive.
Both logistic regression and least squares regression investigate the
relationship between a response variable and one or more predictors . A
practical difference between them is that logistic regression techniques are
used with categorical response variables, and linear regression techniques are
used with continuous response variables.
Minitab provides three logistic regression procedures that you can use to assess
the relationship between one or more predictor variables and a categorical
response variable of the following types:
Variable
type
Number of
categories Characteristics Examples
Binary 2 two levels success, failure
yes, no
Ordinal 3 or more natural ordering of
the levels
none, mild, severe
fine, medium,
coarse
Nominal 3 or more no natural ordering of
the levels
blue, black, red,
yellow
sunny, rainy, cloudy
Both logistic and least squares regression methods estimate parameters in the
model so that the fit of the model is optimized. Least squares minimizes the
sum of squared errors to obtain parameter estimates, whereas logistic
21 | P a g e
regression obtains maximum likelihood estimates of the parameters using an
iterative-reweighted least squares algorithm [29].
Multinomial Logistic Regression is useful for situations in which you want
to be able to classify subjects based on values of a set of predictor
variables. This type of regression is similar to logistic regression, but it is
more general because the dependent variable is not restricted to two
categories.
Linear regression is not appropriate for situations in which there is no
natural ordering to the values of the dependent variable. In such cases,
multinomial logistic regression may be the best alternative.
Model
SPSS calculates K - 1 logit functions for a model with K response categories. For
example, a response with three categories (1, 2, 3) has two logit functions
(reference event = 3):
gk(x) = loge pk (x) = qk +
x'bkpK (x)
where:
gk(x) = the logit link function
qk = the constant associated with the kth distinct response
category
xk = a vector of predictor variables
bk = a vector of coefficients associated with the kth logit
function
Event probability
Denoted as p. For a three-category model with categories 1, 2, and 3 (reference
event 3), the conditional probabilities are:
P(y = 1| exp(x'b1)
22 | P a g e
RE
SU
LT
x) = 1 + exp(x'b1) + exp(x'b2)
P(y = 2|
x) =
exp(x'b2)
1 + exp( x'b1) + exp(x'b2)
P(y = 3|
x) =
1
1 + exp(x'b1) + exp(x'b2)
where p k(x) = P(y = k|x) for k = 1, 2, 3. Each probability is a function of the
vector of 2(p + 1) parameters, b' = (b'1, b'2)
3.5 CHI-SQUARE TEST FOR INDEPENDENCE (CONTINGENCY TABLE
ANALYSIS)
The Chi-square statistic discussed in Section 8.7.1 and 8.7.2 can also be
used to test the independency of two factors or attributes in which the
data classified or summaized in a two-way table called a contingency
table.
An r x c Contingency Table
A contigency, table containing ‘r’ rows and ‘c’ columns is referred to as an
r c table.
Table 3.1
I.Q LEVEL
10% 30% 60% 100% Totals
High n11 n12 n13 n14 r1
med n21 n22 n23 n24 r2
Low n31 n32 n33 n34 r3
Total c1 c2 c3 c4 N
23 | P a g e
Table 3.1 can then be said to be of 3 4 contingency table, where
ri are row totals
cj are column totals
nij are observed frequencies and
N is the grand total
Therefore the procedure to test whether two factors are independent or not for a
r c contingency table is as follows:
(a). H0 : The two factors are independent
(b). Calculating expected frequencies (ei) for each cell i.e.
E(nij) =
=
(c). Compute the test statistic
2 = with 2,[(r-1)(c-1)] degrees of freedom
(d). Reject H0 if 2 > 2,[(r-1)(c-1)]
24 | P a g e
CHAPTER FOUR
4.0 PRESENTATION OF DATA AND ANALYSIS
4.1 ANALYSIS OF SURVEY FINDINGS
Table 4.1 .1 How do you view electricity supply in your industry?
Frequency Percent Valid Percent
Cumulative
Percent
Valid No obstacle 10 9.6 9.6 9.6
Moderate obstacle 42 40.4 40.4 50.0
Major obstacle 52 50.0 50.0 100.0
Total 104 100.0 100.0
Source : SPSS output
Figure 4.1.1
25 | P a g e
The table 4.1.1 and Figure 4.1.1 shows that 50% of the respondents view electricity
consumption as major obstacle in their firm,40.3% viewed it as moderate obstacle and 9.62%
viewed as minor obstacle .
Table 4.1.2 How important is Electricity in your factory?
Frequency Percent Valid Percent
Cumulative
Percent
Valid Most important 42 40.4 40.4 40.4
Important 42 40.4 40.4 80.8
Less important 20 19.2 19.2 100.0
Total 104 100.0 100.0
Source : SPSS output
Figure 4.1.2
26 | P a g e
The table 4.1.2 and Figure 4.1.2 Shows that 40.38% viewed electricity as most important,also
40.38% viewed electricity as important and the remaining 19.23% viewing electricity as less
important.
Table 4.1.3 Years of the use of Generator
Frequency Percent Valid Percent
Cumulative
Percent
Valid Less than 1 year 20 19.2 19.2 19.2
1-5 Years 21 20.2 20.2 39.4
5-10 Years 33 31.7 31.7 71.2
More than 10 years 30 28.8 28.8 100.0
Total 104 100.0 100.0
Source : SPSS output27 | P a g e
Figure 4.1.3
From Table 4.1.3 and Figure 4.1.3 above, firms that purchased their Generator 5 to 10 years
ago have the largest percentage with 31.73% while those with less than 1 year old has the
least percentage with 19.23%.
Table 4.1.4
The cost of the Generator
Frequency Percent Valid Percent
Cumulative
Percent
Valid Less than N250,000 20 19.2 19.2 19.2
N250,001-N1,000,000 32 30.8 30.8 50.0
N1,000,000-N5,000,000 42 40.4 40.4 90.4
More than N5,000,000 10 9.6 9.6 100.0
Total 104 100.0 100.0
28 | P a g e
Source : SPSS outputFigure 4.1.4
From table 4.1.4 and Figure 4.1.4,those that have the cost of their generator to be between
N1million and N5million have the largest percentage with 40.38% while those that have the
cost of their generator to be more than 5 million has the least with 9.63%.
Table 4.1.5
29 | P a g e
What is the proportion of total investment at start up level is devoted to own
electricity by your firm?
Frequency Percent Valid Percent
Cumulative
Percent
Valid 0-10% 22 21.2 21.2 21.2
11-20% 41 39.4 39.4 60.6
21-30% 31 29.8 29.8 90.4
ABOVE 30% 10 9.6 9.6 100.0
Total 104 100.0 100.0
Source : SPSS outputFigure 4.1.5
From Table 4.1.5 and Figure 4.1.5, 39.42% of the firms studied used 11% to 20% of their
total investment on supply of own electricity,29.81% used 21% to 30%,21.15 used only 0%
to 10% and 9.62 firms used over 30% of their total investment for the provision of own
electricity.
30 | P a g e
Table 4.1.5
How often do you fuel your generating set ?
Frequency Percent Valid Percent
Cumulative
Percent
Valid Daily 40 38.5 38.5 38.5
2 Times in a week 20 19.2 19.2 57.7
3 Times in a week 10 9.6 9.6 67.3
Weekly 23 22.1 22.1 89.4
Monthly 11 10.6 10.6 100.0
Total 104 100.0 100.0
Source : SPSS outputFigure 4.1.5
31 | P a g e
From Table and Figure 4.1.5, 38.46%(largest) fuel their generator daily,followed by weekly
with 22.12% and those that fuel their generator 3 times in a week have the least percentage
with 9.62%.
Table 4.1.6
How much does it cost you to pay electricity bill to PHCN in a month
Frequency Percent Valid Percent
Cumulative
Percent
Valid less than N100,000 40 38.5 38.5 38.5
N100,001-N500,000 34 32.7 32.7 71.2
N500,001-N1,000,000 20 19.2 19.2 90.4
More than N1,000,000 10 9.6 9.6 100.0
Total 104 100.0 100.0
Source : SPSS output
32 | P a g e
Figure 4.1.6.
From figure and object 4.1.6,32.69%(largest) of the respondents pay between N100,001 and
N500,000 as PHCN bill every month while those that pay more than N1million have the least
percentage with 9.62%.
Table 4.1.7
33 | P a g e
How much does it cost you to fuel and maintain your generating set in a month?
Frequency Percent Valid Percent
Cumulative
Percent
Valid Less than N100,000 40 38.5 38.5 38.5
N100,001-N500,000 23 22.1 22.1 60.6
N500,001-N1,000,000 21 20.2 20.2 80.8
N1,000,000-N5,000,000 10 9.6 9.6 90.4
More than N5,000,000 10 9.6 9.6 100.0
Total 104 100.0 100.0
Source : SPSS output
Figure 4.1.7
From Table and Figure 4.1.7, the largest percentage(38.46%) goes for those that spend less
than N100,000 for the fueling and maintenance of their generating set while those that
spends between N1million and N5million and those that spend more than N5,000,000 share
the same percentage(9.62%) as the least.
34 | P a g e
Table 4.1.8
Respondents perception of the frequency of power outages per week
Frequency Percent Valid Percent
Cumulative
Percent
Valid Fewer than 5 times 10 9.6 9.6 9.6
Between 5 and 10 times 32 30.8 30.8 40.4
More than 10 times 62 59.6 59.6 100.0
Total 104 100.0 100.0
Source : SPSS output
Figure 4.1.8
From Table and Figure 4.1.8, 59.62% of the firms studied experience power outages more
than 10 times a week,30.77% experience power outages between 5 and 10 times a week
while the remaining 9.62% experience power outages fewer than 5 times a week.
35 | P a g e
Table 4.1.9
Respondents perception of the average duration of power outages
Frequency Percent Valid Percent
Cumulative
Percent
Valid 1-6 hours 31 29.8 29.8 29.8
More than 6 hours 73 70.2 70.2 100.0
Total 104 100.0 100.0
Source : SPSS output
Figure 4.1.9
36 | P a g e
Table and Figure 4.1.9 shows that the larger percentage(70.19%) of the firms studied
experience more than 6 hours of power outages while the remaining 29.81% of the firms
experience power outages for 1hour to 6 hours.
Table 4.2.0
How has electricity shotages affected your business?
Frequency Percent Valid Percent
Cumulative
Percent
Valid No effect 6 5.8 12.0 12.0
Low effect 10 9.6 20.0 32.0
High effect 34 32.7 68.0 100.0
Total 50 48.1 100.0
Missing System 54 51.9
Total 104 100.0
Source : SPSS output
Figure 4.2.0
37 | P a g e
Multiple Response
Table 4.2.1
38 | P a g e
$Infracstructure Frequencies
Responses
N Percent Percent of Cases
Severity of infracstructure
problema
Land 10 4.8% 9.6%
Elecricity 104 49.8% 100.0%
Water 20 9.6% 19.2%
Telecommunication 20 9.6% 19.2%
Road 32 15.3% 30.8%
Petroleum shotages 23 11.0% 22.1%
a Total 209 100.0% 201.0%
a. Dichotomy group tabulated at value 0.
Source : SPSS output
MULT RESPONSE GROUPS=$Problems 'Problem of electricity outages'
(lowelectricitytarrif inefficiency toomuchgovt poorfunding corruptio n (0))
/FREQUENCIES=$Problems.
Multiple Response
39 | P a g e
Table 4.2.2
$Problems Frequencies
Responses
N Percent Percent of Cases
Problem of electricity
outagesa
Low electricity tarrif. 10 6.8% 18.2%
Inefficiency of PHCN 46 31.1% 83.6%
Too much government
control
31 20.9% 56.4%
Poor funding 21 14.2% 38.2%
Corruption 40 27.0% 72.7%
a Total 148 100.0% 269.1%
a. Dichotomy group tabulated at value 0.
Source : SPSS output
Crosstabs
Scale of Production * Respondents perception of the frequency of power
outages per week
Table 4.2.3
Crosstab
Count
Respondents perception of the frequency of power
outages per week
Fewer than 5
times
Between 5 and
10 times
More than 10
times Total
Scale of Production Small scale 10 22 20 52
Medium scale 0 0 32 32
Large scale 0 10 10 20
Total 10 32 62 104
Source : SPSS output
40 | P a g e
Table 4.2.4
Chi-Square Tests
Value df
Asymp. Sig. (2-
sided)
Pearson Chi-Square 37.468a 4 .000
Likelihood Ratio 49.641 4 .000
Linear-by-Linear Association 9.223 1 .002
N of Valid Cases 104
a. 2 cells (22.2%) have expected count less than 5. The minimum
expected count is 1.92.
Source : SPSS output
Scale of Production * Respondents perception of the average duration of
power outages
Crosstab
Table 4.2.5
Respondents perception of the
average duration of power outages
1-6 hours
More than 6
hours Total
Scale of Production Small scale 10 42 52
Medium scale 11 21 32
Large scale 10 10 20
Total 31 73 104
Source : SPSS output
41 | P a g e
Table 4.2.6
Chi-Square Tests
Value df
Asymp. Sig. (2-
sided)
Pearson Chi-Square 6.997a 2 .030
Likelihood Ratio 6.896 2 .032
Linear-by-Linear Association 6.929 1 .008
N of Valid Cases 104
a. 0 cells (.0%) have expected count less than 5. The minimum expected
count is 5.96.
Source : SPSS output
Crosstabs
Scale of Production * How has electricity shortages affected your business? Crosstabulation
Table 4.2.6
How has electricity shotages affected your business?
No effect Low effect High effect Total
Scale of Production Small scale 6 5 15 26
Medium scale 0 5 9 14
Large scale 0 0 10 10
Total 6 10 34 50
Source : SPSS output
42 | P a g e
Table 4.2.7
Chi-Square Tests
Value df
Asymp. Sig. (2-
sided)
Pearson Chi-Square 11.215a 4 .024
Likelihood Ratio 15.024 4 .005
Linear-by-Linear Association 6.473 1 .011
N of Valid Cases 50
a. 5 cells (55.6%) have expected count less than 5. The minimum
expected count is 1.20.
Source : SPSS output
Nominal Regression
Table 4.2.8
Model Fitting Information
Model
Model
Fitting
Criteria Likelihood Ratio Tests
-2 Log
Likelihood Chi-Square df Sig.
Intercept Only 83.857
Final .000 83.857 18 .000
Source : SPSS output
Table 4.2.9
43 | P a g e
Goodness-of-Fit
Chi-Square Df Sig.
Pearson .000 0 .
Deviance .0
00
0 .
Source : SPSS output
Table 4.3.0
Pseudo R-Square
Cox and Snell .713
Nagelkerke .762
McFadden 1.000
Source : SPSS output
44 | P a g e
Table 4.3.1
Likelihood Ratio Tests
Effect
Model
Fitting
Criteria Likelihood Ratio Tests
-2 Log
Likelihood
of Reduced
Model Chi-Square df Sig.
Intercept .000a .000 0 .
Years of the use
Generator*
83.857 83.857 18 .080
The cost of generator 77.545 65.931 19 .010
Proportion of total
invest on elec
177.547 84.899 16 .000
Cost of electricity bill 91.324E2 39.741 18 .092
Maintenance and
fueling of gen81.276E2 34.968 13 .020
How often do you fuel
gen.
9.000a .000 17 .000
Source : SPSS output
Table 4.3.2
How has electricity outages affected your business
Observed
Predicted
No effect Low effect High effect Percent Correct
No effect 6 0 0 100.0%
Low effect 0 10 0 100.0%
High effect 0 0 34 100.0%
Overall Percentage 12.0% 20.0% 68.0% 100.0%
Source : SPSS output
45 | P a g e
Multiple Response
Table 4.3.3
$Solution Frequencies
Responses
N Percent Percent of Cases
Solution to power problemsa Complete Privatization 25 25.0% 55.6%
Increase funding 20 20.0% 44.4%
Introduce competition 45 45.0% 100.0%
Increase tarrif 10 10.0% 22.2%
a Total 100 100.0% 222.2%
a. Dichotomy group tabulated at value 0.
Source : SPSS output.
Ranking of infrastructure problems in Nigeria
Respondents were asked to rank the severity of infrastructure problems in
Nigeria on a scale of 1 to 3 – no obstacle, moderate obstacle, major obstacle (see
Table 4.1.1 for the results). The responses we received show that a large
percentage of the firm regarded power and voltage fluctuations as major
obstacles to their operations. Most of the respondents also ranked electricity as
their number one problem with 49.8%. This is followed by Road in a distant
second(15.3%) and Land as the least(4.8%). More small-scale firms ranked
electricity as a problem (52%) compared with large firms (20%).
Electricity consumption Table 4.1.5 further shows the share of total investment
devoted by firms to their own provision of electricity facilities. This cost, as
expected, varies inversely with the scale of operations of the firms. Small-scale
firms spend on average between 11 and 20% of initial investment on self-
generation compared with large-scale firms, which spend less than 10%. Across
46 | P a g e
all the firms, however, the additional investment costs incurred to mitigate the
unreliability of PHCN is an avoidable cost that simply increases the costs of
business operations in Nigeria.
Power outage impacts
The poor reliability of publicly supplied power in Nigeria has imposed a lot of
impacts on manufacturing firms in the country. As a result of power outages
firms lost an average of 1382 working hours in 2005. Assuming a nine-hour
working day, this translates to about 88 working days in 2005. Also, about 35%
of the firms reported having to shut down production at one time or the other in
the year as a result of power outages. The dimension of the poor state of
electricity supply in the economy can be seen in
Tables 4.2.0 and 4.3.2, which confirm the seriousness of the power outage
problem in Nigeria. On the average, firms experience outages between five and
ten times in a week, with each outage lasting between 1and 6 hours hour. If
these outages occur during the working period of the firms (which they do), then
the potential losses would be so much and thus firms would need a form of
insurance.
Finally, the average cost for auto-generation with maintenance cost and for
Publicly provided electricity is presented in Table 4.1.7 and 4.1.6 respectively.
There is a sharp division in the perception of consumers and PHCN on the causes
of the poor supply of electricity in Nigeria. While PHCN emphasized inadequate
funding, low tariff rates, and technical problems arising from illegal connections
and tampering with PHCN installations, consumers are convinced that the tariff
rate has little or nothing to do with it. The general perception is that PHCN is
corrupt and inefficient. Hence, the consumers’ solution is to deregulate the
sector.
CHAPTER FIVE
5.0 FINDINGS, CONCLUSION AND RECOMMENDATIONS:
5.1 FINDINGS
The following findings were observed from the analysis:
It was observed that electricity is ranked among the first in terms of
47 | P a g e
severity problems in Nigeria with virtually all the sampled
companies agreeing to the fact, followed by road. While the least of
them is land.
It was observed that inefficiency and corruption are ranked among
the highest as regards to factors responsible for poor performance
in the power sector, while low tariff and poor funding is ranked
among the lowest.
It was observed that 90% of the respondents were of the opinion
that average duration of power outage is more than 6 hours.
Moreover this rate of power outages is spread across all the sectors
and scale of production.
It was observed from the multinomial logistic regression that 68% of
the respondents have suffered greatly as a result of power outages,
20% are have suffered with a negative low effect, while the
remaining 12% have not suffered at all. The factors that influenced
their opinion are cost of maintenance and fuelling of generator, cost
of generator, frequency of power outages and proportion of total
investment on auto-generation.
It was observed that the scale of production that suffered most is
the small scale industries.
It was also observed that introduction of competition is ranked
highest among the steps to be taken in order to improve the power
sector followed by complete privatization of the power sector, while
increasing funding and tariff were ranked among the lowest.
5.2 CONCLUSION;
This study analysed the impact of power outages to the business sector of
the Nigerian economy. The study applied both the survey technique. The
characteristics of the electricity market in Nigeria were also analysed. One strong
outcome of the study is that the poor state of electricity supply in Nigeria has
48 | P a g e
exerted a negative effect in terms of the cost of operating in the business sector
of the Nigerian economy. The bulk of these costs come in the form of acquisition
of very expensive backup power. However, the decision to acquire a backup is
actually a rational decision on the part of the firm in order to insure it from larger
losses arising from frequent and long power fluctuations.
The continuation of the existing state of power supply will no doubt
continue to have a negative impact on the attempt by the government to
diversify the production and export base of the economy away from oil. A
situation where firms spend as much as 20% to 30% of initial investment on the
acquisition of facilities to enhance electricity supply reliability has a significant
negative impact on the cost competitiveness of the manufacturing sector.
Furthermore, as the results of our analysis have shown, small-scale
operators are more heavily affected by the infrastructure failures. In many
instances they are unable to finance the cost of backup necessary to mitigate
the negative impact of frequent outages. Hence, they have to bear the full
burden of electricity failures. Small-scale operators that could afford to back up
their operations have to spend a significant proportion of their Investment outlay
on this.
5.3 RECOMMENDATION AND FURTHER STUDY
From the statement made by the president Dr. Goodluck Jonathan GCFR that
he will sell of the monopoly state of PHCN (Next magazine), this is also in line with the
outcome of the research that a complete privatization will be the best option to solve the
crippling effect of power outages in Nigeria.
One important area of further research is to examine the institutional
reforms that can enhance the public sector delivery of electricity. It is very
obvious from the study that private generation is inefficient relative to that by
the public sector. Private provision is, therefore, not the optimal way for the
economy to go. There is a need for an in-depth study of the institutional
structure of PHCN in Nigeria and how effective reforms could be carried out to
ensure its effectiveness.
REFERENCES:
ABE J.B (2002) Sampling Techniques One, New Waves publishers Festac Lagos.
49 | P a g e
ABE J.B (2004) Sampling Techniques Two, New Waves publishers Festac Lagos.
ADEBOWALE A.S (2003) “STATISTICS for Engineer, managers and scientists”,
Andkolad ventures Nig Ltd.
Agresti, A.(2002). Categorical Data Analysis, 2nd ed. New York: John Wiley and
Sons.
Bernstein, M. and Y. Heganazy. (1988). “Economic costs of electricity
shortages: Case study of Egypt”. The Energy Journal, Special Electricity
Reliability Issue, 9:173–88.
Caves, D.W., J.A. Herriges and R.J. Windle. (1992). “The cost of electric power
interruptions in the industrial sector: Estimates derived from interruptible
service
programmes”. Land Economics, 68: 49–61.
Elhance, A.P. and T.R. Lakshamanan. (1988). “Infrastructure-production system
dynamics in national and regional systems: An economic study of the Indian
Economy”. Regional Science and Urban Economics, 18, North-Holland.
http://www.nigerianinquirer.com/2010/08/26/president-jonathan-announces-
plans-to-privatize-phcn/
http://234next.com/csp/cms/sites/Next/Home/5499659-146/story.csp (Retrieved on the 19th
of November, 2010)
Kessides, C. (1993). The Contributions of Infrastructure to Economic
Development: A
Review of Experience and Policy Implications. World Bank Discussion Papers
No. 213. The World Bank.
Lee, K.S. and A. Anas. (1991). “Manufacturers’ responses to infrastructure
deficiencies in Nigeria: Private alternatives and policy options”. In A. Chibber
50 | P a g e
and
Fischer, S eds., Economic Reform in Sub-Saharan Africa. A World Bank
Symposium.
Lee, K.S and A. Anas. (1992). Impacts of Infrastructure Deficiencies on Nigerian
Manufacturing: Private Alternatives and Policy Options. Infrastructure and Urban
Development Department Report No. 98. World Bank, Infrastructure and Urban
Development Department, Washington, D.C.
Matsukawa, I. and Y. Fujii. (1994). “Customer preferences for reliable power
supply: Using data on actual choices of back-up equipment”. Review of
Economics and Statistics, 74: 434–46.
NEPA. (1997). “NEPA beyond the load schedding”. Advertorial, New Nigerian,
Wednesday, June 3, 18–9.
OLUFOLABO .O.O AND TALABI C.O (2002) Principles and Practice of statistics,
Hem Fem (Nig) enterprise.
OLUFOLABO .O.O AND TALABI C.O (2002) Principles and Practice of statistics,
Hem Fem (Nig) enterprise.
World Bank Technical Paper No. 138. The World Bank, Washington, D.C.
World Bank. (1993)a.The East Asian Miracle: Economic Growth and Public
Policy. New York: Oxford University Press.
World Bank. (1993)b. Energy Sector Management Assistance Programme
Report on Nigeria. Washington, D.C.
Zhang, D. (2005). "Analysis of Survival Data, lecture notes, Chapter 10."
Available at http://www4.stat.ncsu.edu/%7Edzhang2/st745/chap10.pdf.
51 | P a g e
YABA COLLEGE OF TECHNOLOGY,YABA LAGOS. P.M.B.2011,YABA LAGOS Department of StatisticsQUESTIONAIRE ON THE COST OF INFRASTRUCTRE FAILURE ON LAGOS STATE ECONOMY. (A case study of Electricity).
Dear Respondents,
We are Statistics students of Yaba college of Technology, we are carrying out a statistical survey on the cost of infrastructure failure on the Economy of Lagos state, In partial fulfilment of the requirement for Higher National Diploma award.
Answering each of the questions sincerely and correctly would really be appreciated as we promise to make every information provided confidential. In order to prove our anonymity, please do not involve you name or organisation name. Thank you for spearing part of your busy hours to attend to our questionnaire.
SOLAWON KEHINDE A. & ONYEKA VICTOR U.
1. SECTOR: Food and manufacturing Wood and Product.
52 | P a g e
Beverages and Tobacco Paper and Product.
Textile and Leather Rubber and Chemical.
Metal and Products. Others(specify)
……………………………
2 Location(Senatorial District) : Lagos west Lagos central
Lagos east.
2 Scale of Production: Small scale Medium scale Large scale.
3 How often do you have light in your industry? Less often Often
More often.
4 How do you view electricity supply in your industry?
No obstacle Moderate obstacle Major obstacle.
5 Rank the following infrastructure in order of their inportance in your factory
a. Land b. Electricity c. Water d. Telecommunication e. Road f. Petroleum shortages
6 How important is Electricity in your factory?
Most important Important Less important.
7 What is the source of elecricity in your factory?
PHCN only PHCN main Own generator only Own
generator main
8 Years of the use of Generator : less than 1 yr. 1-5 yrs
5-10yrs More than 10 yrs
.
9 The cost of the Generator : less than N250,000 N250,001-N1,000,000
N1,000,001N-5,000,000. More than N5,000,000
10 What proportion does provision of own electricity facilities from the total investment at
start?.
0-10% 11-20% 21-30% more than 30%
11 How often do you fuel your generating set ? Daily 2 times in a week
. 3 times a week weekly monthly
53 | P a g e
12 What does it cost you to pay electricity bill to PHCN in a month?
Less than N100,000 N100,001-N500,000 N500,000-N1,000,000
N1,000,001-N5,000,000 More than N5,000,000
13 What does it cost you to fuel and maintain your generating set in a month?
Less than N100,000 N100,001-N500,000
N500,001-N1,000,000 N1,000,000-N5,000,000
n More than N5,000,000.
14 What other materials do you use for the set’s maintenance?
Capital Cost : Generator house Operating cost : Fuel and grease
Stabilizer Wages and salary
Oil tank Maintenance cost
Others (specify)……………………. Others…………
15 How often do you have power failure in a week? Less than 5 times
5-10 times more than 10 times
16 What is the average of the duration of the power failure for each time?
Less than 30 mins 1-6 hrs more than 6 hrs
17 What is your perception on the factors responsible for the poor performance of PHCN?
Low electricity tariff Inefficiency of PHCN Too much govt.
control Poor funding Corruption.
18 Firms perspective of how to improve PHCN.
Increase funding Introduce competition Increase tariff.
19. How has electricity outages affected your business? No effect
Low effect High effect.
54 | P a g e