Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Fitchburg State University Fitchburg, MA
SB Project No. 700503.35
December 10, 2013
Prepared by:
Sebesta Blomberg Contact: Jesse Stallions
120 Presidential Way, Suite 320
Woburn, MA 01801
Main: 781-721-8356 Email: [email protected]
FINAL EXISTING CONDITIONS ASSESSMENT REPORT
Table of Contents
Section Page 1.0 Executive Summary .......................................................................................................................... 2
2.0 Facilities Overview ........................................................................................................................... 5
3.0 Main Campus Building Equipment Condition Assessment Summaries ........................................... 7
3.1 Anthony Student Services Center ........................................................................................... 7
3.2 Athletic Field House ............................................................................................................... 9
3.3 Athletic Storage .................................................................................................................... 10
3.4 Campus Police ...................................................................................................................... 10
3.5 Conlon Fine Arts .................................................................................................................. 12
3.6 Conlon Industrial Arts .......................................................................................................... 15
3.7 Dupont Facilities Building ................................................................................................... 21
3.8 Edgerly Hall ......................................................................................................................... 22
3.9 Elliott Press Box ................................................................................................................... 25
3.10 Exercise and Sports Science ................................................................................................. 25
3.11 Hammond Hall ..................................................................................................................... 26
3.12 Holmes Dining Hall .............................................................................................................. 29
3.13 Mazzafaro Center ................................................................................................................. 32
3.14 McKay Complex .................................................................................................................. 33
3.15 Miller Hall ............................................................................................................................ 38
3.16 Percival Hall ......................................................................................................................... 39
3.17 Recreation Center ................................................................................................................. 41
3.18 Sanders Administration ........................................................................................................ 43
3.19 Service Center ...................................................................................................................... 45
3.20 Thompson Hall ..................................................................................................................... 46
3.21 Weston Auditorium .............................................................................................................. 48
3.22 185 North St. Apartment Complex .................................................................................... 49
3.23 Aubuchon Hall ..................................................................................................................... 51
3.24 Cedar Street House (No. 22) ................................................................................................ 53
3.25 Cedar Street House (No. 30) ................................................................................................ 54
3.26 Herlihy Hall .......................................................................................................................... 56
3.27 Mara Village ......................................................................................................................... 58
3.28 Russell Towers ..................................................................................................................... 60
3.29 Townhouses .......................................................................................................................... 62
4.0 Central Boiler Plant Condition Assessment .................................................................................... 64
4.1 Furnace and Tube Condition ................................................................................................ 64
4.2 Corrosion Control ................................................................................................................. 67
4.3 Boiler Turndown .................................................................................................................. 71
4.4 Boiler Efficiency .................................................................................................................. 71
4.5 Feedwater System ................................................................................................................. 74
Executive Summary
Fitchburg State University Page 2 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
1.0ExecutiveSummary
Sebesta Blomberg & Associates, Inc. (Sebesta Blomberg) was retained by the Massachusetts Division
of Capital Asset Management and Maintenance (DCAMM) to provide building assessment and
energy/water conservation strategic planning for Fitchburg State University (FSU). The purpose of the
assessment is to lay the groundwork for renewal of facility mechanical and utility infrastructure under
an Equipment, Design, and Installation contract.
This report represents the Existing Conditions Assessment component of the effort and is divided into
the following four sections, each of which looks at a different level within the overall state of campus
and building level conditions and operations.
� Section 2: Facilities Overview
� Section 3: Utilities Overview
� Section 4: Individual Building Summaries
� Section 5: Central Heating Plant Assessment
In summary, the FSU mechanical infrastructure is a mix of older buildings, many with recent and
comprehensive renovations, others with antiquated equipment, and many with a combination of new
and old equipment. In addition, there have been several new construction projects; most notable is the
library addition, and science building opened this spring. The University is doing an excellent job
keeping up with its equipment and in almost all cases mechanical equipment and related controls are
providing reasonable occupant comfort.
In 1997, an energy performance contract with NORESCO was completed which included new
lighting, pneumatic overlay controls and some new mechanical equipment. Over the past few years,
the FSU has installed Direct Digital Control (DDC) controls in buildings recently constructed and
where renovations have taken place. A large portion of the campus buildings remain pneumatically
controlled with an overlay on existing HVAC equipment for feedback and control capability. The
feedback and control capability is limited and many of the controls appear to have failed. As expected,
equipment at newer facilities is in better condition. Table-1 on page 4 summarizes each building and
associated equipment condition.
Executive Summary
Fitchburg State University Page 3 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Acknowledgements
Sebesta Blomberg would like to thank Joe LoBuono, Director of Operations and Facilities, Mary Beth
McKenzie, Executive Director of Administrative Services and David Petrucci, Chief Engineer, for
their invaluable assistance in conducting site survey work and sharing their knowledge of the
Fitchburg State University buildings and mechanical systems outlined in this report.
Executive Summary
Fitchburg State University Page 4 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Table1.0–SummaryofFindings
Building Existing Controls HVAC
Supplied by
Central Steam Plant?
End of Equipment
Life Inoperable
Units
Damper / Valve /
Actuator Replacement
Required Comments
Anthony Building ALC RTUs (2), EFs, Steam to HHW Systems Yes No No No HVAC systems installed in 2011.
Athletic Field House Non-Programmable TSTAT Gas fired furnace, Electric UHs, DHW Heaters (2) No No No No DHW Heater ventilation issues.
Campus Police Trane Building TSTAT Control Furnace/AC units (2), Gas DHW Heater No No No No Systems in good condition. Consider controls interface.
Conlon Fine Arts NORESCO for AHUs and HHW, Pneumatic AHU Devices & TSTATS.
AHUs (2), EFs, Convectors, Steam and HHW Systems. Steam DHW
Yes No No Yes Old AHUs: failed steam control valves, rusted OA dampers. No controls communication to front end.
Conlon Industrial Arts NORESCO for AH-23, -24 and HHW, ALC on new AHUs, Pneumatic AHU Devices & TSTATs
Absorber Chiller Plant, Cooling Tower, AHUs (13), Reheat, Convectors, EFs, Steam and HHW Systems. Steam DHW
Yes Yes Yes Yes Abandoned equipment, AHUs in rough condition; potentially failed dampers, valves, etc. End of life chiller & cooling tower.
Dupont Facilities OEM Burner Combustion Controls. Pneumatic and Electric Non-Programmable TSTAT
Central Steam Boilers (3), Condensate Receiver, Dearator, Fuel Oil Heaters and Pumps, Baseboard Radiation, Split Systems (2), Window A/Cs.
Yes No No No Firetube boiler No. 1 is fairly new (’96). Boiler No. 2 and No. 3 (water tubes) are older, but internals are in reasonably good service condition.
Edgerly Hall Partial ALC (3
rd Flr), Otherwise Pneumatic
TSTATs and Local Electric TSTATs AHU (1), VAVs, UVs, Splits, Convectors. Elec DHW. Yes Yes No No
3rd Floor HVAC equipment was installed in 2010 and is in good
condition. Univents require rebuilding.
155 North St ALC Water Source Heat Pumps (8), ERUs (2), Elec DHW No No No No Mechanical equipment installed 2010 and in good condition.
Hammond Hall ALC for New Systems. Pneumatic TSTATS in Unrenovated Areas.
Chiller Plant, Cooling Tower, AHUs (6), Reheat, Convectors, Steam and HHW. Steam and Elec DHW.
Yes No No No Heavy renovation in progress. Chiller plant and AHUs are new. Consider Recommissioning building once complete.
Holmes Dining Hall Stand-alone DDC for RTUs, NORESCO for HHW, Pneumatic TSTATs.
RTUs (2), MUA, EFs, Steam Systems Yes Yes Yes No 1996 RTUs in reasonable condition. Kitchen supply fans have failed resulting in heavy air imbalance. RTU controls should be integrated to ALC front end.
Mazzaferro Stand-Alone DDC. Gas HHW Boiler, Packaged AHU, Reheat, Convectors. Yes No No No HVAC in good condition, but not controlling very well. Integrate controls with ALC front end. Consider more efficient boiler.
McKay Campus School Pneumatic Gas HHW Boilers (3), Chiller Plants (2), AHUs (4), UVs, Splits, Convectors. Steam and HHW/DT systems. Steam DHW.
No Yes No Yes Boiler plant newer. Steam traps and receiver require attention. Chiller plants at end of life. UVs require attention. Poor control. Overall, this building will require heavy investments to modernize systems.
Miller Hall ALC Chiller, AHUs (2), UVs, Splits. Elec DHW Yes No No No Equipment in good condition. Check VFDs on AHUs.
Percival Hall NORESCO, Pneumatic TSTATs Steam Systems: MUA (2), UVs, Convectors, DHW. Split Systems.
Yes Yes Yes No Failed Auditorium supply fans. UVs in rough condition.
Recreation Center Novar Gas HHW Boilers (6), Pool Water Boiler (1), Chiller, AHUs (5), Dectron Pool Unit, Reheats, Convectors. Gas DHW Heaters (2)
No No No No Equipment in fair condition. All VFDs have failed and are on bypass.
Sanders Administration ALC Controls RTU, NORESCO Controls MUA Unit, Pneumatic TSTATs
RTU, H&Vs (2), Water-Source HPs (2), steam FTRs Yes Yes No No One MUA unit and one HP not in operation, Operational HP uses once-thru water.
Science Center ALC Chiller Plant, Cooling Tower, AHUs, ERUs, Reheats, EFs. Steam and HHW Systems. Steam DHW and Process HW.
Yes No No No Commissioned in Spring 2013.
Service Center Programmable TSTAT Gas-Fired RTUs (4), HRVs (2), Gas-Fired UHs No Yes No No Two end of life RTUs. Ductwork in office should be updated.
Thompson Hall ALC Controls AHU, NORESCO Controls HHW, Pneumatic TSTATS
AHU (1), UVs, Convectors. Steam and HHW Systems. Steam DHW
Yes Yes No No Rebuild Univents. DHW tank past useful life.
Weston Auditorium NORESCO controls HHW, Pneumatic H&V and TSTAT.
H&V Units (4), ERV (1) Yes No No Yes H&V units may require rebuilding.
185 North Street Non-Programmable Thermostat Gas HHW Boilers (6), FTR. Gas DHW Heaters (6) No No No No Boilers and DHW heaters are older.
Aubuchon Hall ALC MAUs (2), ERUs (1), EFs, Convectors, Splits. Steam and HHW Systems. Steam DHW
Yes No No Yes Recent renovation, limited pneumatic remain.
22 & 30 Cedar Street House Non-Programmable Thermostat Gas-Fired HHW Boilers. Window A/C (2) No Yes No No Boilers are older. Replacement should be considered.
Herlihy Hall TCVs on FTR. Older Steam zone control valves Steam Convectors, Split (1), EFs. Steam DHW in Holmes, Yes No No Yes Older systems. Zone control valves do not work.
Russell Towers NORESCO Controls HHW, TCVs on FTRs, Pneumatic Valves.
AHUs (2), H&V (1), EFs, Convectors. Steam and HHW Systems. Steam DHW.
Yes No No No AHUs newer. Rest of the equipment is older.
Mara Village 1-7, Commons Non-Programmable Thermostat Gas-Fired HHW Boilers (7), FTR. Gas Fired DHW Heaters (7) No No No No Consider boiler replacement.
Mara 8 Viking DDC Gas HHW Boilers (2), Chiller, ERU, and 2-pipe FCUs. Gas DHW Heaters (2).
No No No No Newer building in good condition.
Town Houses 1-7 Thermostat. Tekmar Boiler Controller. Non-Programmable TSTAT
Gas HHW Boilers (7), FTR. Indirect DHW No No No No Consider boiler replacements.
Facilities Overview
Fitchburg State University Page 5 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
2.0FacilitiesOverview
The FSU campus consists of 45 buildings totaling over 1.4 million gross square feet (GSF), located in
Fitchburg, Massachusetts. The table below lists all buildings reviewed under this assessment.
Table 2.0
FSU Campus Buildings included in Assessment
Building Address Use Sq. Ft.
Anthony Building 280 Highland Ave. Offices, Records Storage 20,100
Athletic Field House / Trainer's Center 53 Pearl Hill Rd. Lockers, Physical Therapy 6,100
Athletic Storage - Elliott Field Pearl Hill Rd. Storage 300
Campus Police Station 32 Clinton St. Offices, Booking 4,700
Condike Science Building 333 North St. Under Renovation 48,800
Conlon Fine Arts 367 North St. Classrooms, Musical Studios 21,800
Conlon Industrial Arts 367 North St. Offices, Shop, Photo lab 111,500
Dupont Facilities Building 299 North St. Boiler Plant, Offices 17,500
Edgerly Hall 281 North St. Classrooms, Office 26,200
Elliott Press Box Pearl Hill Rd. Stadium Rooms 500
Exercise & Sports Science 155 North St. Offices 8,300
Hammond Building 160 Pearl St. Library, Bookstore, Offices, Café 165,100
Holmes Dining Hall 280 North St. Dining 34,400
Mazzaferro Alumni & Development Center 160 Pearl St. Offices, Conf. Room 6,000
McKay Campus School 67 Rindge Rd. Classrooms, Elementary School 194,700
Miller Hall 230 Highland Ave. Offices 22,100
Percival Hall 254 Highland Ave. Offices, Auditorium 34,200
Recreation Center 130 North St. Athletic Facility, Basketball Courts, Swimming Pool
84,200
Sanders Administration Building 300 Highland Ave. Offices 24,800
Science Center Addition 333 North St. Laboratory and Classrooms 55,000
Service Center 167 Klondike Ave. Offices, Print Shop, Trades Shops, Warehouse
58,300
Thompson Hall 240 Highland Ave. Classrooms, Nursing Labs, Offices 53,600
Weston Auditorium 353 North St. Auditorium 16,700
185 North St. 185 North St. Residences 7,100
Aubuchon Hall 234 North St. Residences 100,800
22 Cedar Street 22 Cedar St. Residences 3,800
30 Cedar Street 30 Cedar St. Residences 15,600
Herlihy Hall 320 North St. Residences 37,800
Mara Village #1 299 Highland Ave. Residences 10,200
Mara Village #2 210 Cedar St. Residences 10,500
Mara Village #3 220 Cedar St. Residences 10,500
Mara Village #4 329 Highland Ave. Residences 9,9000
Mara Village #5 339 Highland Ave. Residences 9,9000
Mara Village #6 250 Cedar St. Residences 10,200
Mara Village #7 260 Cedar St. Residences 10,200
Mara Village #8 349 Highland Ave. Residences 44,000
Mara Village Commons Building 319 Highland Ave. Residences 6,500
Russell Towers 260 North St. Residences 105,900
Townhouse #1 241, 243 Highland Ave. Residences 10,600
Townhouse #2 261, 263 Highland Ave. Residences 11,700
Townhouse #3 170 Cedar St. Residences 5,700
Townhouse #4 158 Cedar St. Residences 5,400
Townhouse #5 152 Cedar St. Residences 3,500
Townhouse #6 150 Cedar St. Residences 5,500
Townhouse #7 140 Cedar St. Residences 5,500
Facilities Overview
Fitchburg State University Page 6 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Central Plant:
Most of the central academic and administration buildings are supported by a central steam heating
plant (CHP) facility located in the Dupont Facilities Building currently. The plant primarily burns
natural gas, with No.6 fuel oil system remaining in place and fired occasionally. The CHP provides
60-65 psig-saturated steam with distribution to individual buildings where the steam pressure is
reduced to 7-9 psig. Where not used directly, the steam is converted to hot water typically via shell-in-
tube heat exchangers, which is then used for heating hot water, domestic hot water and snowmelt.
Further information on the CHP is provided in Section 4.7 and Section 5.
Maintenance Responsibility:
FSU staff is primarily responsible for any preventative maintenance (filters, belts, etc) associated with
the HVAC systems. FSU has maintenance contracts for the Building Management System (BMS) with
Automated Logic Control (ALC) for approximately 11 campus buildings. The remaining buildings
have various different EMS manufacturers or no EMS at all.
Condition Assessments
Fitchburg State University Page 7 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.0 Main Campus Building Equipment
Condition Assessment Summaries
This section provides an outline description of each Fitchburg State University facility surveyed with
HVAC equipment inventory and design data where available. Highlights of the equipment condition
assessment are included with details provided in the Appendix.
3.1 Anthony Student Services Center
This 20,100 square foot building is primarily used for administration offices including: Admissions,
Registrar, Financial Aid, Continuing Education, Student Accounts, This former Industrial Arts facility
also includes a large unheated records storage area on the first floor. There is no occupancy in the
basement. This building is occupied Monday – Friday, 8 a.m. to 5 p.m. year-round. There is additional
evening and weekend use during the school year.
Construction: 2-level brick structure with white EPDM roof. The building received a gut renovation
in approximately 2011 that included new interior architectural features, mechanical equipment,
windows, etc. Windows are double pane / aluminum frame in excellent condition. The roof and brick
exterior appears to be in good condition. The exterior doors appeared to be in good condition, although
some minor weather seal defects where noted.
HVAC Summary: The HVAC system consists of two newer rooftop units. RTU-1 is a cooling-only
15-ton Aaon DX unit serving the Executive Suite (NE side of the building) via terminal VAV boxes
with hydronic reheats. RTU-1 has a 7.5 hp supply fan equipped with VFD. RTU-2 is a similar 10 hp
packaged 18 ton Aaon rooftop unit serving the remainder of the building via VAV’s. Both units have
air-side economizer capability.
Air Handlers and Fans
Unit Type Serves Year hp SP (inch) cfm Preheat
coil MBH Cooling
Tons
RTU-1 VAV Exec Suite 2010 7.5 1.75 8,000 None 15
RTU-2 VAV 1ST
& 2nd
Flr 2010 10 NA NA None 18
EF-1 CV Toilet Exhaust 2010 NA 0.5 75 - -
EF-2 CV Toilet Exhaust 2010 NA 0.75 400 - -
EF-3 CV General 2010 NA 0.25 320 - -
NA = Not Available
Condition Assessments
Fitchburg State University Page 8 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
The building is also equipped with perimeter hydronic fin-tube radiation controlled by wall mount
thermostat. Steam is provided from the central heating plant at typically 60-65 psig where it’s reduced
to 7 psi and then converted to hot water via a steam to hot water heat exchanger (P&F type) in the
basement mechanical room. The exchanger is rated for 684-pph steam and 13-gpm hot water. Hot
water is distributed by one of two 900-watt Grundfos in-line pumps (53 gpm /35 feet). The heating
system was installed as part of a recent renovation.
A 30-gallon, 4.5 kW electric storage tank, provides domestic hot water.
Controls: The controls in this building are DDC by ALC and are used to manage the RTUs and
heating hot water system. The ALC system provides temperature control, static pressure fan control,
equipment scheduling, and demand ventilation management.
Other: A 27 kW Photovoltaic Array (PV) has also recently been installed on the roof.
Condition Assessment Summary Table
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
RTU-1 Yes 1 1 1 1 New
RTU-2 Yes 1 1 1 1 New
EF-1 Yes 1 NA NA NA New
EF-2 Yes 1 NA NA NA New
EF-3 Yes 1 NA NA NA New
P-1, -2 Yes 1 NA NA NA New
HX-1 Yes 1 NA NA NA New
Deficiency Rating: Overall
1 – New or good condition
2 – Fair condition, may require some updates (motors, controls, access)
3 – Requires repair/renovation (rebuilding, new controls, dampers)
4 – Requires replacement
N/A – Not applicable
Deficiency Notes (refer to Appendix A for details):
1. None.
Recommendations:
1. None.
Condition Assessments
Fitchburg State University Page 9 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.2 Athletic Field House
The Athletic Field House is located near the University’s athletic field. It houses team locker rooms as
well as a physical therapy room. There was an addition to the locker room area. Normally the building
is shutdown by mid to late November. It reopens as early as mid February as teams initiate practices.
Construction: The building is wood framed with cement bond siding. Given the age of the building
(2001), there is likely adequate insulation in the wall assembly and roof (unconfirmed). Windows are
vinyl and air sealing around doors was found to be in need of attention.
HVAC Summary: The original locker area is heated and ventilated by a gas-fired Reznor furnace. The
newer locker space has electric unit heaters (4). There are several exhaust fans and two domestic hot
water heaters.
Air Handling Unit
Tag Make Model Fuel CFM Input Output
AHU-1 Reznor SCE250-6-S2 Gas 2050 250,000 200,000
Domestic hot water in the main locker room building is provided by a 99-gallon (400 MBH) direct-
fired State hot water heater located in the storage room. The unit is in good condition and the draft
damper is operational. There is no pipe insulation on the hot discharge piping.
The second domestic hot water heater is located in a closet off of the physical therapy room. This is an
AO Smith condensing model. Maintenance staff informed us that they have directed the occupants of
the space to keep the door cracked due to poor ventilation in this space and the potential for mold to
form. At the time of our visit, the unit was operable however the casing was out of place. It appeared
that someone from the staff had been in the process of fixing the unit and did not replace the cover.
Domestic Hot Water Heater Information
Tag Make Model Fuel Capacity
HW-1 Bradford White MS230R5DS Gas 60
HW-2 AO Smith BTH 120 970 Gas 60
Controls: Heating unit is controlled by a local thermostat. The exhaust fans run from 6 a.m. to 9 p.m.
via mechanical timeclock.
Condition Assessment Summary Table
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AHU-1 Yes 1 1 1 N/A
HW-1 Yes 1 N/A N/A N/A
HW-2 Yes 1 N/A N/A N/A Ventilation issue.
Condition Assessments
Fitchburg State University Page 10 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Water heater near the physical therapy room appears not to have adequate ventilation.
2. Pipe insulation is missing from both DHW units.
Recommendations:
1. Review and improve closet ventilation requirements.
2. Insulate hot water pipe at the discharge of tank.
3.3 Athletic Storage
This is a 270 square foot athletic storage facility on Elliott Filed. The building has several storage
compartments for athletic equipment. The building is not heated or insulated. There are no mechanical
systems.
3.4 Campus Police
Description: The campus police station was opened in 2009. The three level 4,700 square foot facility
houses dispatch, a booking and holding area, offices and conference room, locker rooms for the
officers, and storage areas. The facility is operation continuously year-round.
Construction: This relatively new building is wood construction and is expected to have adequate
insulation and sealing, consistent with recent energy code requirements. Windows are double pane
vinyl and are in good condition. Entrance doors are in good condition, however light was visible
around some of the entrance doors.
HVAC Summary: The station is heated and cooled by two Trane condensing furnaces with DX
cooling coils. Each furnace is coupled with a 5 ton condensing unit located on the west side of the
building. There are a total of 8 zones, each controlled without their own thermostat. All thermostats
Condition Assessments
Fitchburg State University Page 11 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
have occupied/unoccupied buttons with temperature selection options. Thermostats are connected to a
main control module where occupied/unoccupied settings and temperature setpoints can be controlled.
Furnace/Air Conditioner
Tag Make Model Motor
HP Heating
MBH Cooling
ton
1 Trane TUX1C080A9601AB 0.5 76,000 5
2 Trane TUX1C080A9601AB 0.5 76,000 5
Condensing Unit Info
Tag Make Model Fan HP
1 & 2 Trane 4TTB3060A100AA 1/4
Controls: Systems are controlled with a Trane central controller. This unit integrates individual
thermostats to provide a centralized location for total building control. The system isn’t integrated
with the ALC system, which is a priority for the University
Condition Assessment Summary Table
Unit Operable
Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AC-1, -2 Yes 1 1 N/A N/A
CU-1, -2 Yes 1 1 N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. No deficiencies noted.
Recommendations:
1. Consider controls integration to central front end.
Condition Assessments
Fitchburg State University Page 12 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.5 Conlon Fine Arts
The Conlon Fine Arts (FA) building is a part of the Conlon Industrial Arts building. The FA building
totals 21,800 square foot and is a mix of offices, conference rooms, classrooms, practice rooms and
recital hall. This building is typically occupied Monday – Thursday, 6 a.m. to 10 p.m., Friday 6 a.m. to
6 p.m., and closed on weekends.
Construction: This is a 2-story mason block and brick structure with black EPDM roof. Windows are
original single pane / steel frame, generally in fair condition, although with poor thermal performance.
The roof and exterior appears to be in good condition. The exterior doors appeared to be in acceptable
condition with the exception of widespread worn or absent weather seals.
HVAC Summary: The HVAC equipment is located in the 1st and 2nd
floor mechanical rooms.
Steam enters the first floor mechanical room from the Conlon Industrial Arts building at 35 psig where
the pressure is reduced to about 7 psi. Steam is used directly in AHU preheat coils and is also
converted to heating hot water via a two steam to hot water heat exchangers. Heating hot water is used
for perimeter radiation as well a separate reheat loop. Chilled water is provided from the Conlon
Industrial Arts building.
One steam heat exchanger is dedicated to the perimeter fin-tube radiation while the other heat
exchanger serves the reheat loop. The perimeter fin-tube radiation is served by one of two 3 hp
constant volume pumps (one standby). The reheat loop is served by one of two constant volume 1 hp
pumps (one standby).
Air handling equipment is constant volume and provides air via ductwork distribution with reheat
coils. Air handler, AH-25, has a 7.5 hp motor and serves the recital hall. The unit has steam preheat
and chilled water coils. The chilled water control valve is 3-way. The associated return air fan (RAF-
6) has a 1.5 hp motor. Air handler, AH-26, has a 20 hp motor and serves the first and second floor.
The unit has steam preheat and chilled water coils. The chilled water control valve is 3-way. The
associated return air fan (RAF-7) has a 3 hp motor. The AH units have airside economizer capability;
however the outside air dampers and pneumatic damper actuators appear to be in rough shape so
functionality could be limited.
The air handlers currently use a pre-filter and final bag filter setup, which is typical for all AHUs
across campus. The pre-filters are changed twice per year while the final bag filters are changed only
once annually. This filter scenario is adding an unnecessary pressure drop across the filter bank, which
is causing the fan to consume additional horsepower in order to deliver the appropriate volume of air.
It’s typically acceptable for only a pre-filter to be installed for academic and administrative
Condition Assessments
Fitchburg State University Page 13 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
applications. A 50-gallon, 4.5 kW electric heater, generates domestic hot water. There is one exhaust
fan that serves the mechanical room. No other exhaust fans were seen.
Air Handlers and Fans
Unit Type Serves Year
cfm Preheat
coil MBH Cooling
Tons hp
AH-25 CV Recital Hall 1975 7.5 NA NA NA
AH-26 CV 1ST
& 2nd
Flr 1975 20 NA NA NA RAF-6 CV Toilet Exhaust 1975 1.5 NA - -
RAF-7 CV Toilet Exhaust 1975 3 NA - -
EF-1 CV Mechanical Room 1975 NA NA - -
EF-4 CV General 1975 NA NA - -
EF-5 CV General 1975 NA NA - -
NA = Not available
Pumps
Unit Type Serves hp Ft gpm
P-1 Centrifugal Fin-Tube Radiation 3 95 48
P-2 Centrifugal Fin-Tube Radiation 3 95 48
P-3 Centrifugal Reheat Loop 1 30 46
P-4 Centrifugal Reheat Loop 1 30 46
Controls: All building control end devices are pneumatic. This building is currently on the NORESCO
BMS providing limited feedback and control capability. The NORESCO system is intended to provide
overlay control on the air handlers (all control points except for the steam valve), however
communication to the system has been lost and the units are currently operated manually (on/off and
setting valve positions – no economizer or adjustment of outside air). Pneumatics was disconnected to
the preheat control valve of AH-25 causing the unit to always be providing heat unless isolated
manually at the unit. It’s also reported that AH-25 cycles a lot during the cooling season due to a lack
of control capability. Prior to loss of the NORESCO system the units in this building where scheduled
to conserve energy. Radiation temperature is via pneumatic thermostat, where equipped and/or
functional.
Condition Assessment Summary Table
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
AH-25 Yes 3 2 2 3 Steam pneumatic control valve tubing disconnected. OAD & RAD rusted.
AH-26 Yes 3 2 2 3 OAD & RAD rusted. SA flex duct broken
RAF-6 Yes 3 2 2 2 Original
RAF-7 Yes 3 2 2 2 Original
EF-1 Yes 3 2 2 2 Original
EF-4 Yes 3 NA 2 NA Original
EF-5 Yes 3 NA 2 NA Original
Condition Assessments
Fitchburg State University Page 14 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
Reheat Converter-1 Yes 3 NA 2 NA Original – Failed steam control valve
Fin-Tube Converter-2 Yes 3 NA 2 NA Original – Failed steam control valve
P-1 Yes 4 NA 2 NA Original
P-2 Yes 4 NA NA NA Original
P-3 Yes 4 NA NA NA Original
P-4 Yes 4 NA NA NA Original
Air Comp Yes 2 N/A N/A N/A Newer
Deficiency Rating: Overall
1 – New or good condition
2 – Fair condition, may require some updates (motors, controls, access)
3 – Requires repair/renovation (rebuilding, new controls, dampers)
4 – Requires replacement
N/A – Not applicable
Deficiency Notes (refer to Appendix A for details): 1. AH-25 & AH-26 outside and return air dampers are rusted. Functionality is likely to be
compromised.
2. OA dampers on both units are in rough condition and may not be fully functional.
3. AH-25 steam control valve pneumatic tubing has been disconnected. Only method of
controlling supply temperature is manually.
4. P-1 thru P-4 is in rough shape and leaking.
5. Heat exchanger control valves reportedly no longer function.
Recommendations:
1. Clean preheat and reheat coils for better air distribution and heat transfer.
2. Replace outside and return air dampers for AH-25 & AH-26.
3. Replace supply air flex duct on AH-25 and seal ductwork as necessary.
4. Replace hot water pumps, P-1 thru P-4.
5. Replace AH-25 steam control valve.
6. Insulation contractor should add insulation to pumps, heat exchanger and valve bodies where
missing or damaged insulation.
Condition Assessments
Fitchburg State University Page 15 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.6 Conlon Industrial Arts
This Industrial Arts (IA) facility totals 111,500 square feet and includes shop space, classrooms, and
offices. There is also a small data center, help desk and photo studios. Much of the building is
currently under renovation. This building is typically occupied Monday – Thursday, 6 a.m. to 10 p.m.,
Friday 6 a.m. to 6 p.m., and closed on weekends.
The first floor includes machine and woodworking shop teaching area, offices and several areas
currently under renovation. The second floor has the IT department, offices and classroom area that
are under renovation. The third floor has communication media, multi-cultural student services and
student photo labs. A portion of the third floor is currently under renovation as well. The offices are
located in the core of the building with an atrium that extends from the first floor up to the third floor.
The labs are concentrated on the perimeter of the third floor. There is a walkway that connects the IA
building with the Fine Arts building.
Construction: Built in 1975, this is a 3-story brick structure with white roof. Windows are original
single pane / steel frame, not very energy efficient. The exterior appears to be in good condition. The
exterior doors appear to be a mix or older and some new unit in acceptable condition, however
weather seals and alignment could use attention.
HVAC Summary: The majority of HVAC equipment is located in the basement mechanical space and
penthouse mechanical room. There are multiple smaller mechanical rooms on each floor, which house
air handlers dedicated to serving a particular area. Air handling equipment is constant volume with
steam preheat, hot water reheat and supplies air via ductwork distribution with a return air fan with the
exception of recently renovated IT Dept. which is variable air volume. The areas currently under
renovation will be receiving new air handlers, distribution ductwork and terminal devices.
Basement Equipment: The basement mechanical room has a single-effect estimated 250-ton steam
absorption chiller, which provides chilled water to both Conlon Industrial Arts and Conlon Fine Arts.
This single stage unit is original to the building and at end of life. This machine reportedly struggles to
maintain 50F chilled water supply temperature. On particularly warm days, the machine supplies 60-
65F CHWS temperatures. The associated roof mounted BAC induced draft cross-flow cooling tower is
also original to the building and in rough condition. The tower has a newer estimated 20 hp fan motor.
The cooling tower has widespread corrosion issues and is well past its useful life. Replacement of the
chiller and cooling tower should be a priority. Two constant volume pumps serve the chilled water
system, P-7A and P-7B; one is redundant. P-7A and P-7B each have a 20 hp motor and are rated for
600 gpm at 85’of head. Two constant volume pumps serve the condenser water system, P-6A and P-
Condition Assessments
Fitchburg State University Page 16 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
6B; one is redundant. P-6A and P-6B each have a 15 hp motor and are rated for 945 gpm at 45’of
head.
Steam is received from the central heating plant at typically 60-65 psi where the steam pressure is
reduced to 7 psi and converted to hot water via a steam to hot water heat exchangers located in the
basement mechanical space. The hot water reheat/AHU loop and perimeter fin-tube radiation have
dedicated heat exchangers. The perimeter fin-tube radiation and AHU pre-heat is served by two
constant volume pumps, P-1A and P-1B; one is redundant. P-1A and P-1B each have a 40 hp motor
and are rated for 1,500 gpm at 85’of head. Two constant volume pumps serve the reheat loop, P-2A
and P-2B; one is redundant. P-2A and P-2B each have a 3 hp motor and are rated for 115 gpm at 45’of
head.
A 530-gallon steam to hot water heat exchanger from 1973 provides domestic hot water. The
pneumatic steam control valve appeared to have some leaks. The condensate receiver pump was
leaking water onto the mechanical room floor.
Penthouse Equipment: The penthouse contains the major pieces of HVAC equipment. Air handler,
AH-23, has a 60 hp motor and serves classrooms in the core of floors 1-3, hallways and the lobby. The
unit has steam preheat and chilled water coils. The chilled water control valve is 3-way. The
associated return air fan (RAF-4) has a 20 hp motor. Air handler, AH-24, has a 10 hp motor and serves
the TV Studio. This unit has the same configuration as AH-23. The associated return air fan (RAF-5)
has a 5 hp motor. HV-7A and HV-7B are constant volume units that each has a 10 hp motor. Staff
report that these units are not in use.
The functional AHUs have airside economizer capability; however the outside air dampers appear to
be in rough shape so functionality could be limited. It was noted the intake plenum of AH-23 was
positively pressurized. The cause could stem from the bag type final filters causing a 0.8” W.C
pressure drop across the filter bank. The pleated box filters were not installed and the unit still had a
high filter bank pressure drop. The pilot positioner portion of the chilled water control valve is
disconnected.
There are multiple exhaust fans located on the roof and in small mechanical rooms on each floor. A
majority of these fans have failed and abandoned in place as a result of re-purposing space over the
years. New APC dry coolers are located on the roof to serve the recently renovated IT Dept.
Other Equipment: The third floor has four smaller air handlers, which are located in small
mechanical rooms that serve individual spaces respectively on each floor. Air handler, AH-22, has a 2
hp motor and serves the Photo Shop. The unit is cooling only with hot water reheat and steam
humidification. The steam humidifier has not been operational in several years. The chilled water
Condition Assessments
Fitchburg State University Page 17 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
control valve is 3-way. The associated return air fan (RAF-3) has a 3/4 hp motor. Air handler, AH-20,
has a 2 hp motor and also serves the Photo Shop. The unit is cooling only with hot water reheat and
steam humidification. The steam humidifier has also not currently operational. The chilled water
control valve is 3-way. The associated return air fan (RAF-1) has a 3/4 hp motor. This unit is
internally rusted and well past its useful life. The outside air damper appears to be stuck at about 40%
open. Replacement should be considered. Air handler, AH-21, has a 3 hp motor and also serves the
renovated computer room. The unit has hot water preheat and chilled water coils. There is also
terminal hot water reheat coils. The hot water and chilled water control valve is 3-way. The associated
return air fan (RAF-2) has a 3/4 hp motor. The pneumatic controls are disconnected and dampers in
rough shape as well. Air handler, AH-17, has a 1 hp motor and serves office space. At the time of our
visit, the unit was off at the electrical disconnect switch and overall in rough shape.
The second floor has a new cooling only York AHU which is variable air volume and has a 7.5 hp
motor on VFD that serves the recently renovated IT Dept. The VFD was operating at 60 hertz during
the survey. The data center area has two Heatcraft packaged units, which are water-cooled to rooftop
dry-cooler. These units each employ 3 hp fans with VFDs as well as electric reheat and
dehumidification. Air handler, AH-5, has a 5 hp motor and serves the old Automotive Shop. This area
is currently under a complete renovation. The future use of this unit is unknown but was in good
overall condition. Air handler, AH-13 has a 5 hp motor and serves offices. The unit has chilled water
and hot water coils. The chilled water control valve is 3-way. The unit seems limited run time.
The first floor has 5 smaller AHUs as well with a similar layout to the third floor. These units are
reportedly in good overall condition.
Air Handlers and Fans
Unit Type Serves Year hp SP
(inch) cfm
Heating coil MBH
Cooling Tons
AH-5A CV Mech Energy 1974 5 NA 9,000 827 NA
AH-7A, B CV Abandoned 1974 10 NA NA NA NA
AH-13 CV Offices /Low Usage 1974 5 NA NA NA NA
AH-17 CV Air Education 1974 2 NA 2,545 86 NA
AH-20 CV Photo Studio 1974 2 NA 3,120 82 NA
AH-21 CV Computer Room 1974 3 NA 4,300 99 NA
AC-22 CV Photo Shop 1974 2 NA 2,750 28 NA
AC-23 CV Flr 1-3 Core, Lobby 1974 60 NA 38,840 NA NA
AC-24 CV TV Studio 1974 10 NA 8,895 NA NA
York VAV It Dept ~2010 7.5 NA NA - -
RAF-1 CV AC-20 1974 0.75 NA 3,085 - -
RAF-2 CV AC-21 1974 0.75 NA 4,150 - -
RAF-3 CV AC-22 1974 0.75 NA 2,750 - -
RAF-4 CV AC-23 1974 20 NA 37,000 - -
RAF-5 CV AC-24 1974 5 NA 7,340 - -
NA = Not available
Pumps
Unit Type Serves hp Ft gpm
P-1A/1B Centrifugal AHUs / Fin-Tube Radiation
50 85 1,600
P-2A/2B Centrifugal Reheat 3 48 115
P-6A/6B Centrifugal Condenser Water 15 45 945
Condition Assessments
Fitchburg State University Page 18 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
P-7A/B Centrifugal Chilled Water 20 85 600
Controls: The building controls are a mix of full DDC, pneumatic and local control. Whenever an area
in the building area was renovated, DDC controls have been installed. The ALC controls provided full
feedback and control capability to the Building Management System (BMS) located in the facilities
building. The pneumatic controls portion of the building is on the NORESCO BMS providing very
limited feedback and control capability. The NORESCO system is intended to provide overlay control
on the penthouse air handlers (all control points except for the steam valve) as well as heating hot
water systems. However, communication to the system has been lost and the units are currently
operated manually (on/off and setting valve positions – no economizer or adjustment of outside air).
Prior to loss of communication, the NORESCO system provided equipment scheduling and heating
hot water reset to conserve energy. The smaller air handlers located on individual floors in are
completely stand-alone. Occupant’s turn the units on/off manually via the electrical disconnect switch.
The pneumatic control valves functionality is questionable on most of the equipment.
Condition Assessment Summary Table
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
Chiller Yes 4 N/A N/A N/A No longer reliable. End of life
Cooling Tower Yes 4 N/A N/A N/A Heavily corroded. End of life
York AHU Yes 1 1 1 1 Brand New
AH-5A Yes 2 2 2 2 Part of renovation
AH-7A Yes 2 2 2 2 Abandoned in-place
AH-7B Yes 2 2 2 2 Abandoned in-place
AH-13 Yes 2 2 2 2 Limited use
AH-17 Yes 4 3 4 4 Unit off at the disconnect. Rough shape
AH-20 Yes 4 3 4 4 Internally rusted
AH-21 Yes 3 3 4 4 Controls disconnected, HW coil dirty, OAD rusted.
AH-22 Yes 3 3 4 4 Access is very limited
AH-23 Yes 3 2 3 4
OA damper rusted. Intake plenum positively pressurized. SA flex duct broken
AH-24 Yes 3 2 3 3 OA damper rusted. SA flex duct broken
RAF-2 Yes 3 N/A N/A N/A Rough shape
RAF-3 Yes 4 N/A N/A N/A Rough shape
RAF-4 Yes 3 N/A N/A N/A Flex duct broken. Fan casing is moves
RAF-5 Yes 2 2 2 2
RAF-13 Yes 3 N/A N/A N/A Rough shape
Multiple No 4 N/A N/A N/A Abandoned
Condition Assessments
Fitchburg State University Page 19 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
Rooftop Exhaust Fans
HX-1 (Reheat) Yes 2 N/A N/A 3 Original
HX-2 (Perimeter) Yes 2 N/A N/A 3 Original
DHW HX Yes 3 N/A N/A 3 Original
P-1A, 1B Yes 3 N/A N/A N/A No Comment
P-7A, 7B Yes 3 N/A N/A N/A No Comment
P-2A, 2B Yes 4 N/A N/A N/A Rough shape and leaking
Air Comp. Yes 3 N/A N/A N/A High run time
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Cooling tower is corroded.
2. Chiller has trouble maintaining CHWS temperatures
3. No insulation around pump bodies.
4. Steam pipe insulation damaged/missing in basement mechanical room.
5. Hot water reheat pumps, 2A/2B, are in rough shape and leaking.
6. OAD on many of the units appeared to be failed and/or rusted in the closed position limiting
the amount of fresh air provided to the spaces.
7. Air compressor runs frequently indicating pneumatic air leaks within the system.
8. Air filters causing too high of a pressure drop in some air handlers.
9. RAF-4 casing visible moving.
10. Multiple exhaust fans abandoned in place.
11. Steam humidifiers no longer in use.
12. AH-17 is in rough shape.
13. AH-20 internals are rusted.
14. AH-23 and AH-24 supply air flex duct is broken.
15. Pre-heat coils are dirty.
16. Condensate receiver is leaking.
Condition Assessments
Fitchburg State University Page 20 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Recommendations:
1. Clean preheat and reheat coils for better air distribution and heat transfer.
2. Replace the cooling tower
3. Replace the absorption chiller.
4. Insulation contractor should add insulation to pumps, heat exchanger, steam piping and valve
bodies where missing or damaged insulation.
5. Replace pumps, 2A and 2B.
6. Replace AH-17 and AH-20.
7. Reinforce RAF-7 casing or replace unit.
8. Replace flex duct on AH-23 and AH-24.
9. Replace outside air dampers were found to be rusted.
10. Remove existing air filters and install low-pressure drop air filters.
11. Demo abandoned exhaust fans and patch roof.
12. Repair condensate receiver or replace as necessary.
13. Replace or repair failed pneumatic control valves as necessary. The University prefers to move
away from pneumatic devices, therefore consider electric actuation.
Condition Assessments
Fitchburg State University Page 21 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.7 Dupont Facilities Building
The Dupont Facilities Building houses the central steam boiler plant and facilities support areas. The
building totals 17,500 square feet. The steam plant is located on the ground, or street level and also
includes a garage bay, lock shop and storage area, and boiler and custodial staff break room. The
upper level of the facility is office space used by facilities and capital planning staff.
Construction: The 1977 building is constructed of brick and CMU with flat roof. Most exterior
partitions are painted CMU. Doors and windows are metal frames with single pane glass. Doors are in
reasonably good condition.
Steam Plant Summary: Boiler No. 1 is a 500 BHP natural gas fired steam boiler that was replaced in
approximately 1997. Boiler Nos. 2 and 3 are 1,100 BHP steam boilers each that currently fire #6 fuel
oil. There are three boiler feedwater pumps, BFWP-1,-2-3. All feedwater pumps are constant volume.
BFWP-1 is 25 hp and recently replaced. It is reported by the University that boiler No.1 can handle the
campus steam load with the exception of design heating days when boiler No. 2 or 3 is enabled.
Boilers 2 and 3 are kept on hot stand-by during the heating season.
HVAC Summary: steam-fired perimeter radiation units heat the building. Reduced pressure steam is
from the central plant below. There are two interior split DX units and at least four window A/C units
for the upper level offices.
General exhaust and bathroom exhaust fans are located on the roof. These fans operate 24 hours a day.
Split System Condenser
Tag Make Model Capacity (Tons)
AC-1 Sanyo CM1972A 1.5
Exhaust Fans
Tag Make Model HP Nom. RPM
EF-1 Centri Master P12F 1/3 1130
EF-2 Centri Master P24H 3/4 688
EF-3 Centri Master P24H 3/4 688
EF-4 Centri Master P12F 1/3 1130
EF-5 Centri Master P24H 3/4 688
Controls: There are local thermostats for heating, however many spaces do not require the use of heat
due to proximity to the boiler room. Thermostats in each zone control cooling. Window mounted air
conditions are controlled at each unit.
Condition Assessments
Fitchburg State University Page 22 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Condition Assessment Summary Table
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AC-1 Yes 1 1 N/A N/A
B-1 Yes 2 N/A N/A N/A
B-2 Yes 2 N/A N/A N/A
B-3 Yes 2 N/A N/A N/A
BFWP-1
Yes 4 N/A N/A N/A End of Life
BFWP-2
Yes 4 N/A N/A N/A End of Life
EF-1 Yes 1 N/A N/A N/A
EF-2 Yes 1 N/A N/A N/A
EF-3 Yes 1 N/A N/A N/A EF-4 Yes 1 N/A N/A N/A
EF-5 Yes 1 N/A N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Feed water pumps, FWP-2 and FWP-3, are approaching end of life
Recommendations:
1. Replace FWP-2 and FWP-3
3.8 Edgerly Hall
This four-story building including basement is primarily used as an academic building, also including
office space on the third floor with the campus’s secondary servers. The basement includes storage
(former university trade shops) and the mechanical room. The first and second floor is used for
computer science classrooms. The third floor was renovated approximately three years ago and is used
for faculty offices. This building is typically occupied Monday through Thursday, 7 a.m. to about 10
p.m., Friday 7 a.m. to 5 p.m. and Saturday 8 a.m. to 1 p.m. The building sees limited use in the
summer break period; in part this is due to limited air conditioning.
Condition Assessments
Fitchburg State University Page 23 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Construction: Originally built in 1900, this is a 4-story brick structure with shingle roof. Windows are
a mix of single-pane/wood frame and newer double-pane/ vinyl frame. The exterior appears to be in
good condition with the exception of the windows on the ground and 2nd
floor. Exterior doors are
newer and in good condition.
HVAC Summary: This facility has a mix of old and newer mechanical systems as follows:
A newer York DX split air handler located in the attic serves the 3rd floor offices. The unit is variable
volume serving terminal VAV boxes with hydronic reheat. The unit has a 10 hp motor on VFD that
was observed to be modulating fan speed. RTU-1 has a hot water preheat coil and has DX cooling.
The two stage York condensing unit is pad mounted adjacent to the building.
Steam-fired convectors and 1958 vintage Herman Nelson Univents serve the first and second floor
classrooms. The Univents have outside air dampers that are pneumatically controlled. Staff are unsure
about the functionality of the outside dampers, which were observed to be in rough condition.
Steam at 60-65 psi is supplied to the main basement mechanical room and reduced to 3-7 psi for
general distribution within the building. Heating hot water for the 3rd
floor is generated by a newer
steam to hot water heat exchanger (733 MBH). The heat exchanger is served by a 1½ hp circulator
pump on a VFD (70 gpm at 35 feet). There is also a glycol-based hot water sidewalk snowmelt system
that uses a separate new steam to hot water heat exchanger. The snowmelt serves the bridge to Holmes
Dining Hall.
The first and second floors include some air conditioning by Mitsubishi ductless mini splits. The
second floor also has two York DX fan coil units, which are controlled by stand-alone thermostats.
One unit has a steam reheat coil. This building has about seven splits. There are also several window
DX units.
There is a ¼ hp exhaust fan, which serves the bathrooms on the third floor.
Domestic hot water is produced by a 40 gallon, 4.5 kW electric residential style domestic hot water
heater.
Air Handlers and Fans
Unit Type Serves Year hp SP
(inch) cfm Preheat
coil MBH Cooling
tons
RTU-1 VAV 3rd floor 2010 10 3.4 6,000 142 15
EF-1 CAV Bathroom 2010 1/4 NA NA - -
NA = Not available
Condition Assessments
Fitchburg State University Page 24 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Controls: All controls are stand-alone on the first and second floors. The HVAC equipment associated
with the third floor renovation is DDC and controlled by the ALC system. Steam to the building is
setup to be regulated by an isolation valve tied to the NORESCO control system to perform nightly
shutdowns. However this system is not believed to be working at this time. University staff control
steam to the building manually.
Condition Assessment Summary Table
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
RTU-1 Yes 1 1 1 1 New in 2010
EF-1 Yes 1 1 1 1 New in 2010
Univents Yes 3 3 3 3 Original
CV-1 Yes 1 N/A N/A 2 New in 2010
P-1 Yes 1 N/A N/A N/A New in 2010
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Replace Univent controls and dampers as necessary.
2. Steam converter missing insulation.
3. Single pane windows are in rough shape.
Recommendations:
1. Rebuild / replace Univents as necessary
2. Insulate converter
3. Replace windows
Condition Assessments
Fitchburg State University Page 25 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.9 Elliott Press Box
This is enclosed spectator seating for the Elliott Field, also including announcement and press booth.
The 500 square foot facility is used during the fall and spring sporting season, but is shutdown for the
winter. There are several electric unit heaters.
3.10 Exercise and Sports Science
This facility is a former three-story residence building located at 155 North Street. The 8,300 square
foot property was recently purchased and renovated by the University. The building is currently
occupied by the Exercise and Sports Science department and includes a computer lab/student lounge
and an exercise lab on the 3rd
floor. The building’s operating hours are weekdays 7 a.m. to 8 p.m.
Occupancy at this building is typically light and there is limited use during the summer break.
Construction: The building is wood framed with flat roof section. Sprayed foam insulation was
observed under the roof deck. There is probably insulation in the stud cavities. Windows were
replaced during the renovation with double pane models. Exterior doors are new as well. The building
was originally constructed in 1900 and renovated in 2010.
HVAC Summary: The building is heated and cooled with geothermal heat pumps. Ground water is
pumped from a well through a heat exchanger and into a building loop that is used by all heat pump
units. Heating and cooling distribution is forced air. There are two condenser 2 hp circulation pumps
(27 gpm/55 feet) and one well pump (size unknown). Ventilation is provided via energy recovery
ventilators: one located in the basement (300 cfm) and another in the attic (450 cfm). These units pre-
heat or pre-cool fresh air using building exhaust air.
Domestic hot water is generated by electric tank unit (80 gallon, 6 kW)
Water Source Heat Pumps
Tag Make Model Serial Nom. Cap.
(Tons)
WSHP-1 Trane GEVE0243 W10H15735 3
WSHP-2 Trane GEVE0243 W10H15736 3
WSHP-3 Trane GEVE0121 W10H15737 1.5 WSHP-4 Trane GEVE0243 W10H15738 3
WSHP-5 Trane GEVE0243 W10H15739 3
WSHP-6 Trane Not Available Not Available 3
WSHP-7 Trane Not Available Not Available 3
WSHP-8 Trane Not Available Not Available 1.5
Condition Assessments
Fitchburg State University Page 26 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Energy Recovery Units
Tag Make Model Airflow Range Supply
Motor HP Exhaust Motor HP
ERU-1, -2 Trane MINIV-450-QD 150-500 0.25 0.25
Controls: The building is connected to and controlled by the campus-wide ALC system.
Condition Assessment Summary Table
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
WSHP-1 Yes 1 1 N/A N/A
WSHP-2 Yes 1 1 N/A N/A
WSHP-3 Yes 1 1 N/A N/A WSHP-4 Yes 1 1 N/A N/A
WSHP-5 Yes 1 1 N/A N/A
WSHP-6 Yes 1 1 N/A N/A
WSHP-7 Yes 1 1 N/A N/A
WSHP-8 Yes 1 1 N/A N/A ERUs Yes 1 1 1 N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. None
Recommendations:
1. None
3.11HammondHall
Hammond is one of the largest campus buildings at 165,100 square feet and serves as the central
library. The five level facility includes stacks on multiple floors, campus bookstore, lower level
cafeteria, work areas, classrooms, offices, etc. The building is nearing the end of a multiple-year
phased renovation. A number of areas on the 1st, 2
nd and 5
th floor, auditorium and large function space
were all under reconstruction at the time of this study. Most of the mechanical equipment has already
been replaced.
During the school year, the building is open Monday-Thursday 8 a.m.-12 a.m., Saturday 9 a.m. – 5
p.m. and Sunday 12 p.m. - 11:30 p.m.
Condition Assessments
Fitchburg State University Page 27 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Construction: Exterior construction is brick with insulation in the interior walls. The building is in
various levels of update, with a large addition on the corner of Pearl and North Streets. The roof (new)
is white EDPM with rigid insulation below. Most windows are double pane. There is excessive solar
gain on the northeastern exposure. There were no issues noted with weatherization in the sections that
have been renovated. The building was originally constructed in 1975.
HVAC Summary: This building has mostly all-new air handlers and cooling systems. There is a
mechanical room on the 5th floor that includes new central chiller plant and five new central VAV air
handlers. Each air handler has steam pre-heat coil and chilled water coil. Supply and return fans
operate with VFDs. There is smaller constant speed make-up H&V unit in the lower level that serves
the kitchen. The only older air handler in the building serves the auditorium and is located in the
ceiling. It is not clear if this unit will be replaced as part of the area renovation.
Heating hot water is generated in the basement mechanical room from central steam supply via two
exchangers. There are two distribution systems: perimeter radiation and reheat. The radiation loop is
circulated by a pair of 10 hp constant speed centrifugal pumps (208 gpm at 78 feet). The reheat loop is
circulated by a pair of 7.5 hp constant speed pumps (224 gpm at 63 feet). Both pump sets are setup
with a redundant pump (only one pump is supposed to operate at a time).
Exhaust for the building is provided by eleven roof exhausters. The fans are all new and serve a
variety of functions from general and toilet exhaust to specific kitchen equipment exhaust. Fans are all
in excellent condition.
Chiller Plant: Chilled water is generated by a new 600 ton Carrier centrifugal unit located in the upper
level mechanical room. The chiller uses R134A refrigerant. Load control is by inlet guide vane. This is
a primary/secondary system. Chilled water is distributed by two 30 hp centrifugal pumps (no tags)
with VFD load control. Condenser water is circulated by one of two 50 hp Taco constant speed
centrifugal pumps (1,800 gpm at 80 feet).
AirHandlingUnits
Tag Serves Make Model Supply Fan hp
Return Fan hp
AC-1 General Supply Racan Carrier A4D-112/120-DI 15 (4) 30
AC-2 General Supply Racan Carrier A4D-112/142-DI 15 (4) 30
AC-3 General Supply Racan Carrier A4D-110/108DI 10 (4) 15
AC-4 General Supply Racan Carrier A4D-110/132DI 15 (4) 30
AC-5 General Supply Racan Carrier A4D-110/108DI 10 (4) 15
AC-7 Kitchen Carrier 39MN12D02 NA -
Lecture Unit Lecture Hall N/A N/A N/A N/A
NA = Not available
Condition Assessments
Fitchburg State University Page 28 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Chiller
Tag Make Model Serial Capacity
(tons)
CH-1 Carrier 10XRV55574Q6LCH64 3011Q21043 600
CoolingTower
Tag Make Model Serial Fan Motor
hp
CT-1 BAC 3604C U111302501-01 ~25
ExhaustFans
Tag Make Model Serves HP
RF-1 Greenheck GB-141-7 General 3/4
RF-2 Greenheck GB-180-10 Toilets 1
RF-3 Greenheck GB-101HP-3 General 1/3 RF-4 Greenheck GB-180-10 Toilets 1
RF-5 Greenheck GB-101HP-3 General 1/3
RF-6 Greenheck 15-BISW-41-6-10-1 Toilets 1
RF-7 Greenheck 9-BISW-41-6-10-1 Subway Proofer 1
RF-8 Greenheck 9-BISW-41-6-10-1 Pizza Oven 1 RF-9 Greenheck 15-BISW-41-6-10-1 Griddle/Fryer Hood 1
RF-10 Greenheck SWB-206-5-CW-TH-G Dishwasher Hood 1/2
RF-11 Greenheck SWB-212-4-CCW-TH-F Elevator Control 1/4
Controls: All new HVAC units in the building are controlled by DDC controls. The ALC system
provides equipment scheduling, static pressure control, economizer initiation, CO2 control, etc.
Convectors and other systems that have not been replaced in the renovation use pneumatic controls.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AC-1 Yes 1 1 1 1
AC-2 Yes 1 1 1 1 AC-3 Yes 1 1 1 1
AC-4 Yes 1 1 1 1
AC-5 Yes 1 1 1 1
AC-7 Yes 1 1 1 1
Lecture Unit
Yes 2 2 2 2
AHU Yes 3 3 3 3 Auditorium unit original
RF-1 Yes 1 N/A N/A N/A
RF-2 Yes 1 N/A N/A N/A
RF-3 Yes 1 N/A N/A N/A
RF-4 Yes 1 N/A N/A N/A RF-5 Yes 1 N/A N/A N/A
RF-6 Yes 1 N/A N/A N/A
RF-7 Yes 1 N/A N/A N/A
RF-8 Yes 1 N/A N/A N/A
RF-9 Yes 1 N/A N/A N/A
RF-10 Yes 1 N/A N/A N/A RF-11 Yes 1 N/A N/A N/A
CH-1 Yes 1 N/A N/A N/A
CT-1 Yes 1 1 N/A N/A
Deficiency Rating: Overall
Condition Assessments
Fitchburg State University Page 29 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. AHU fan drives don’t seem to be tracking properly.
Recommendations:
1. Recommission fan drives and controls.
2. Address older pneumatic controls with DDC conversion as appropriate.
3.12HolmesDiningHall
This is the main campus common dining hall. The 34,400 square foot building is two-level with the
main level comprising the dining hall, serving area and kitchen and the lower level for basement, food
and general storage, etc. There is a bridge way where North Street passes underneath a portion of the
building. This building is primarily used as a student-dining hall but is also open to the public. The
first floor has a large dining hall area that can double as a presentation area. There is also multiple
food and beverage buffet lines. Behind the serving lines is the kitchen food prep area that has multiple
cooking ranges and four walk-in coolers and freezers for food storage. The basement is used for
additional food and furniture storage. There is a third walk-in freezer in the basement as well. This
building is typically occupied daily throughout the year, 7:00 a.m. to 9:00 p.m.
Construction: Originally built in 1970. Renovated in 2006, this is a 2-story brick and concrete
structure with membrane roof. Windows are mix of single and double-pane/aluminum frame. The
exterior appears to be in good condition. Doors are a mix of older and new units. Back of house doors
appear to be in rough condition; most doors require attention to weather stripping and/or alignment.
HVAC Summary: The dining hall rooftop units where replaced as part of the 2006 renovation. Air
handling equipment is variable air volume and supply air via ductwork distribution. RTU-1 and RTU-
2 are both gas-fired AAON DX units located on the rooftop. RTU-1 has two 3 hp supply fan motors
and serves the serving line and food area. It has a cooling capacity of 50 tons and a gas fired heating
output capacity of 632 MBH. RTU-2 has two 15 hp supply fan motors and a 5 hp exhaust fan motor
and serves the dining hall. It has a cooling capacity of 70 tons and a gas fired heating output capacity
of 775 MBH. Both units are controlled by VFDs and have enthalpy economizer capability.
Condition Assessments
Fitchburg State University Page 30 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
There are 2 newer exhaust fans, each 2 hp, located on the rooftop, which serve the kitchen hood and
dishwasher. Kitchen and serving area make-up air is tempered by two ceiling mounted terminal steam
coils, which are controlled via a stand-alone wall mounted thermostat. Two of the six 1.5 hp fans are
functional while the remainder have been abandoned in place. This equipment is very old and in rough
condition. Due to lack of active mechanical make-up capacity, there is an air balance concern in the
serving area and kitchen, reported to be particularly noticeable in the winter.
Steam is received from the central heating plant at typically 60-65 psi where the steam pressure is
reduced to 3-7 psi which is then converted to hot water located in the basement. Hot water is used for
perimeter fin-tube radiation and reheat (limited). A 1.5 hp pump circulates hot water.
AirHandlingUnits
Unit Type Serves Year hp cfmBurner
MBH
Cooling
tons
RTU-1 VAV Serving 2007 2 x 3 NA 632 50
RTU-2 VAV Dining 2007 2 x 15 NA 775 70
EF-1 CAV Serving Line 2007 2 NA - -
EF-2 CAV Serving Line 2007 2 NA - -
EF-3 CAV Bathrooms 2007 1/4 1,750 - -
EF-4 CAV Dishwasher Original 1/4 NA - -
EF-5 CAV Dishwasher Original 1/4 NA - -
SF-1 CAV Cooking Ranges
Original 2 NA - -
SF-2 CAV Cooking Ranges
Original 2 NA - -
SF-3 CAV Cooking Ranges
Original 2 NA - -
SF-4 CAV Cooking Ranges
Original 2 NA - -
SF-5 CAV Cooking Ranges
Original 2 NA - -
SF-6 CAV Cooking Ranges
Original 2 NA - -
NA = Not available
Domestic hot water is produced at 140oF by a 400-gallon horizontal steam to hot water heat exchanger
from 1958. The steam control valve appears to have been recently replaced.
The domestic hot water heat exchanger and storage tank for Herlihy Hall is also located in the
basement. The storage tank (1,190 gallon) is steam fired. The inlet flange is showing signs of heavy
Condition Assessments
Fitchburg State University Page 31 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
corrosion. This tank is also original from 1958. There is an older steam booster heater in this area that
has been abandoned in-place.
Controls: This building has a mix of controls. The Aaon units are managed by a stand-alone “System
Manager” DDC system that provides temperature control, static pressure fan management, economizer
activation and scheduling capability. This system is not interfaced with either of the central control
systems. The NORESCO control system manages the heating hot water system, including temperature
reset and unoccupied shutdown. Other controls in the building are strictly stand- alone, including some
remaining pneumatic thermostats.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
RTU-1 Yes 1 1 1 1 New in 2007
RTU-2 Yes 1 1 1 1 New in 2007
EF-1 Yes 1 1 1 1 New in 2007
EF-2 Yes 1 1 1 1 New in 2007
EF-3 Yes 1 1 1 1 New in 2007
EF-4 No 4 N/A N/A N/A Abandoned
EF-5 No 4 N/A N/A N/A Abandoned
SF-1 No 4 N/A N/A N/A Abandoned
SF-2 No 4 N/A N/A N/A Abandoned
SF-3 No 4 N/A N/A N/A Abandoned
SF-4 No 4 N/A N/A N/A Abandoned
SF-5 Yes 4 N/A N/A N/A End of Life
SF-6 Yes 4 N/A N/A N/A End of Life
CV-1 Yes 3 N/A N/A 3 Missing Insulation
P-1 Yes 3 N/A N/A 1 Original
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Abandoned exhaust fans.
2. Four abandoned kitchen make-up air fans.
3. Lack of equipment controllability.
4. Steam converter missing insulation.
Condition Assessments
Fitchburg State University Page 32 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
5. Motor control center in tough shape.
6. Steam pressure reducing piping in mechanical room has missing pipe insulation.
Recommendations:
1. Replace exhaust fans, where required
2. Replace make-up air supply fans to provide air balance to kitchen area
3. Confirm calibration and control of steam reheat thermostat
4. Replace/rebuild equipment motor control centers as necessary
5. Add HVAC equipment onto ALC BMS
3.13MazzafaroCenter
The 6,000 square foot center is housed in what used to be the Chapel building. It was renovated in
2009 to accommodate Alumni Development, Grant Center and the President’s Hall. The building
contains a mixture of offices, common space and the President’s Hall, a meeting and function space.
Standard operating hours are 7 a.m. to 5 p.m. although systems are kept on-line considerably longer to
accommodate unplanned evening meetings.
Construction: The building is wood construction with pitched roof. The roof was replaced during the
renovation. There is no access or documentation on attic insulation. There is believed to be insulation
in the stud cavities. Windows are double pane vinyl and are in good condition. Entrance doors were in
good condition; however some door seals were in need of repair. The building was originally
constructed in 1971 and renovated in 2009.
HVAC Summary: The building is conditioned by a 10 hp Aaon packaged VAV unit located on grade
besides the building. The DX unit has a fan motor VFD. Building heat is provided by hydronic reheat
and baseboard that is supplied by a gas-fired atmospheric boiler located in the basement. Thermostats
are located throughout the building for cooling control. Occupants note that the temperature in the
basement is widely variable, with the employees in the grants section being cold in both the heating
and cooling season.
Domestic hot water is served by a gas fired 40 gallon 37 MBH boiler.
Boiler
Unit Manuf. Make MBTU In MBTU Out Fuel
B-1 Peerless MI-09-SPRK-WPC 260,000 211,000 Gas
PackagedAirConditioningUnit
Unit Manuf. Make Capacity (Tons)
AC-1 Aaon RN-020-8-0-BB02-000 20
Condition Assessments
Fitchburg State University Page 33 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Controls: All controls are DDC; however there is no feedback to the ALC front-end system.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
B-1 Yes 3 N/A N/A N/A
B-2 Yes 3 N/A N/A N/A
AC-1 Yes 1 1 1 N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. No deficiencies noted.
Recommendations:
1. No recommendations.
3.14McKayComplex
The McKay Complex is one of the University’s largest academic buildings at 194,700 square feet. The
facility is located north of the main campus and is unusual in that about half of building is dedicated
for use as an elementary school (McKay Arts Academy). Other occupants include Business
Administration, Geo/Physical Sciences, and the Teacher Education Center. It is divided into three
distinct building sections: A, B and C: Building A is leased to the City of Fitchburg as the elementary
school (pre-K to 8th grade) with approximately thirty-two classrooms and a kitchen; Building B
includes office space, library, gymnasium and large auditorium; and Building C is used for University
classrooms and labs.
Operating hours vary considerably in the various building sections. The elementary school is generally
in session weekdays from roughly 9 a.m. to 3:30 p.m., but with considerable activity earlier and
through the afternoon. The gym is typically in use daily until about 6 p.m. The auditorium has variable
use Monday through Saturday between 8 a.m. and 10 p.m. University classes are generally scheduled
between 8 a.m. - 8 p.m. There is limited use of this facility in the summer.
Condition Assessments
Fitchburg State University Page 34 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Construction: The 1971 building is constructed of CMU and brick with concrete floor and roof decks.
The EDPM roofing is only 2-3 years old, however is showing signs of degradation. There is rigid
insulation in the built up roof system. Walls are not believed to include much, if any, insulation. The
windows are old and thermally inefficient – mostly single pane with metal frames. There is a mix of
newer and old exterior doors. Some of the doors are beyond repair. Most require attention to weather
seals.
HVAC Summary: The building has a mix of HVAC systems. The primary system is older steam-fired
unit ventilators located in perimeter classrooms (approximately 60 units). According to maintenance
staff, only approximately 50% of these unit ventilators operate properly. Many have had new ¼ hp
motors installed. There are typically two ventilators in each room; one provides heated outdoor air and
the other heats return air from the classroom. The unit ventilators are supplied steam from the boilers.
All unit ventilators are controlled by a pneumatic system using localized temperature sensing. All
rooms with unit ventilators are equipped with a thermostat.
There are rooms throughout the building that have been remodeled and most of them are equipped
with a ceiling mounted evaporator for cooling. There are a total of 15 condensing units located around
the building, some of which serve multiple rooms. The renovated rooms are heated with the same unit
ventilators as the rest of the building.
Common areas and the gymnasium are heated and cooled with air handling units located throughout
the building. Steam is supplied to the units from the boiler room and chilled water is supplied from the
(2) chillers.
There are a total of 21 exhaust fans on the roof. There was no clear marking as to which unit serves
which area. The fans have been well maintained.
Steam Boiler Plant Summary: There are three newer Smith section steam boilers rated at 4,095 MBH
output. Each has a 1½ hp dual fuel Riello burner. The University uses gas almost exclusively. No. 2
fuel oil is only used once and awhile to keep the oil systems functional. All three boilers have on-
board custom controls and are wired to a main control panel by Preferred Industries. The condensate
receiver is older and in rough condition. Steam traps in the building require service.
Chiller Plant Summary: The building has two chiller plants as follows:
Building B: 40-ton reciprocating water-cooled R-22 Trane chiller (Model CG40D). Chilled water is
distributed by one of two 3 hp centrifugal pumps (100 gpm at 73 feet). Condenser water is circulated
by one of two 3 hp centrifugal pumps (125 gpm at 45 feet) to rooftop Marley cooling towers. At the
Condition Assessments
Fitchburg State University Page 35 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
time of our visit, both condenser water pumps were in use. The plant is original to the building and
beyond its service life.
Building C: 15-ton reciprocating water-cooled R-22 Trane chiller located in the boiler room. Chilled
water is distributed by one of two 3 hp centrifugal dual temperature pumps (60 gpm at 83 feet). Areas
served include core area classrooms and offices. Condenser water is circulated to rooftop Marley
cooling tower by one of two 3 hp centrifugal pumps (no tag data available). The motors on the
condenser water pumps are older and not efficient. The plant is beyond its service life and requires
replacement.
Building A does not have any air conditioning except for a split serving a daycare room. There are
approximately seven split serving Building B and nine splits serving Building C.
There are two steam-fired domestic hot water storage tanks with individual circulation pumps. One
tank was showing a stored water temperature of 100º and the other of 130º.
A 140 kW emergency generator is also located in the mechanical room. The maintenance logs showed
maintenance tasks and testing are conducted regularly.
AirHandlingUnitInformation
Tag Serves Make Model CFM Range
AHU-1 Gymnasium Trane Torrivent T-14 4,000-12,000 AHU-2 Gymnasium Trane Torrivent T-14 4,000-12,000
AHU-3 Bldg A Lower Flrs Trane Torrivent T-14 4,000-12,000
AHU-4 Lower Flr Trane Climate Changer 6,500-15,000
CondensingUnitInformation
Tag Make Model Fan HP
CU-1 Sanyo C4272R
N/A
CU-2 Sanyo C4272R
CU-3 Samsung UH105CAV
CU-4 Mitsubishi PU42EK2
CU-5 Mitsubishi PU12EK CU-6 Fujitsu MXZ-2A20NA01
CU-7 MUM30NN
CU-8 Sanyo CMH3172
CU-9 Mitsubishi PU42EK2
CU-10 Mitsubishi PU18EK CU-11 Sanyo CMH3172
CU-12 Sanyo C2422
CU-13 Fujitsu AOU42RLX
CU-14 Fujitsu AOU42RLX
CU-15 Fujitsu AOU42RLX
CU-16 Sanyo C4822N
ExhaustFanInformation
Tag Make Model HP
EF-1 Centri Master P12D1 1/6
Condition Assessments
Fitchburg State University Page 36 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
EF-2 Centri Master P12D1 1/6 EF-3 Centri Master P18F 1/3
EF-4 Centri Master P27F 1/3
EF-5 Centri Master P16E 1/4
EF-6 Centri Master P12D1 1/6
EF-7 Centri Master P16D 1/6 EF-8 Centri Master P20D 1/6
EF-9 Centri Master P14D 1/6
EF-10 Centri Master P24H 3/4
EF-11 Centri Master P10D2 1/6
EF-12 Centri Master P14E 1/4
EF-13 Centri Master P14D 1/6 EF-14 Centri Master P24H 3/4
EF-15 Centri Master P22G 1/2
EF-16 Centri Master P24E 1/4
EF-17 Centri Master P10D2 1/6
EF-18 Centri Master P20G 1/2
EF-19 Centri Master P10D 1/6 EF-20 Centri Master P27H 3/4
EF-21 Centri Master P27F 1/3
Controls: All heating and older air handler systems are controlled by pneumatic control systems. The
system has day/night feature that includes a night setback (intended setpoint is 55oF) and shutdown of
exhaust fans. Activation of day/night mode is setup to be controlled by the NORESCO system;
however there is no longer communication back to the front end. According to maintenance, many of
the pneumatic systems do not fully control as required. Split A/C units are on local electric
thermostats.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Chiller (2) Yes 4 NA NA NA Beyond service life
CHWP (2) Yes 2 NA NA NA
CWP (4) Yes 2 NA NA NA
DTP (2) Yes 2 NA NA NA
CT (2) Yes 2 NA NA NA
AHU-1 Yes 3 2 2 2 AHU-2 Yes 3 2 2 2
AHU-3 Yes 3 2 3 2 Damper should be inspected
AHU-4 Yes 3 2 2 2 B-1 Yes 1 1 1 1 Newly installed boiler and burner
B-2 Yes 1 1 1 1 Newly installed boiler and burner
B-3 Yes 1 1 1 1 Newly installed boiler and burner
Univents Yes 3 2 3 3
CU-1 Yes 1 1 N/A N/A Plants debris in coils CU-2 Yes 1 1 N/A N/A Plants debris in coils
CU-3 Yes 1 1 N/A N/A Plants debris in coils
CU-4 Yes 1 1 N/A N/A Plants debris in coils
CU-5 Yes 1 1 N/A N/A Plants debris in coils
CU-6 Yes 1 1 N/A N/A Plants debris in coils
CU-7 Yes 1 1 N/A N/A Plants debris in coils CU-8 Yes 1 1 N/A N/A Plants debris in coils
CU-9 Yes 1 1 N/A N/A Plants debris in coils
CU-10 Yes 1 1 N/A N/A Plants debris in coils
CU-11 Yes 1 1 N/A N/A Plants debris in coils
CU-12 Yes 1 1 N/A N/A
CU-13 Yes 1 1 N/A N/A
Condition Assessments
Fitchburg State University Page 37 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Unit Operable Deficiency Rating Comment
CU-14 Yes 1 1 N/A N/A
CU-15 Yes 1 1 N/A N/A
CU-16 Yes 1 1 N/A N/A
EF-1 Yes 2 N/A N/A N/A
EF-2 Yes 2 N/A N/A N/A EF-3 Yes 2 N/A N/A N/A
EF-4 Yes 2 N/A N/A N/A
EF-5 Yes 2 N/A N/A N/A
EF-6 Yes 2 N/A N/A N/A
EF-7 Yes 2 N/A N/A N/A
EF-8 Yes 2 N/A N/A N/A EF-9 Yes 2 N/A N/A N/A
EF-10 Yes 2 N/A N/A N/A
EF-11 Yes 2 N/A N/A N/A
EF-12 Yes 2 N/A N/A N/A
EF-13 Yes 2 N/A N/A N/A
EF-14 Yes 2 N/A N/A N/A EF-15 Yes 2 N/A N/A N/A
EF-16 Yes 2 N/A N/A N/A
EF-17 Yes 2 N/A N/A N/A
EF-18 Yes 2 N/A N/A N/A
EF-19 Yes 2 N/A N/A N/A
EF-20 Yes 2 N/A N/A N/A EF-21 Yes 2 N/A N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Chiller plants beyond service lives.
2. Air handling units are reaching the end of useful life.
3. Condensate receiver in rough condition.
4. Pneumatic controls are not fully functional.
5. 50% of univent dampers/actuators have issues.
6. Attention to exterior doors.
Recommendations:
1. Replace chiller plants.
2. Consider air handling unit upgrades.
3. Replace condensate receiver.
4. Rebuild univents as necessary.
5. Commission controls – review and repair of each control unit on all unit ventilators
recommended.
6. Repair/replace damaged exterior doors. Update weather seals on all doors where applicable.
Condition Assessments
Fitchburg State University Page 38 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.15MillerHall
Miller Hall is a four level fully renovated 22,100 square foot building that houses faculty offices,
several meeting spaces and a large oval-shaped conference room. The building is typically occupied
weekdays from 6 a.m. to 6 p.m. There are occasionally evening events that take place in the
conference room, but rarely any activity on weekends.
Construction: Constructed in 1903, this is one of the original buildings on campus. Before being
converted into office space, it was used as a dorm. The building has a brick façade with built-out
interior walls. It is unclear if there is wall insulation. There is insulation in the attic, however it
inconsistently covers the attic floor and there doesn’t appear to be any effective vapor barrier. The
windows were replaced in the recent renovation and are double pane vinyl sash type. Exterior doors
are newer and in good condition.
HVAC Summary: The building has been converted to hot water heating. Low-pressure steam enters
the building in the basement and is used to generate heating hot water via a plate and frame exchanger.
Glycol treated heating hot water is circulated by one of two in-line 3 hp Grundfos pumps (82 gpm/60
feet). There are no direct steam users in the building.
Two Trane packaged air handlers located in the attic provide space conditioning. These are newer
VAV units with chilled water and hot water coils. Each unit has fan VFDs. There are also several new
unit ventilators in offices and a mini-split that serves the oval-shaped conference room.
Chilled water is provided by a packaged air-cooled liquid chiller located at ground level on the
southern exterior of the building. Chilled water enters in the basement and is pumped around the
building by one of two 5 hp variable speed Grundfos pumps located in the mechanical room.
Domestic hot water is provided by an electric tank located in the mechanical room (80 gallon, 12 kW).
AirHandlingUnits
Tag Make Model Motor
HP
AHU-1 Trane CSAA008UAC00 5
AHU-2 Trane CSAA008UAC00 5
Chiller
Tag Make Model Capacity
(tons) Voltage
# Compressors
# Fans
CH-1 Trane CGAM 052F 2F02 52 460 4 4
Condition Assessments
Fitchburg State University Page 39 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
CondensingUnit
Tag Make Model Capacity
(tons)
CU-1 Mitsubishi PUY-A18NHA 1.5
Controls: This building is part of the campus-wide ALC system.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AHU-1 Yes 1 1 1 N/A SF drive out on error
AHU-2 Yes 1 1 1 N/A
UVs Yes 1 1 1 1
CH-1 Yes 1 N/A N/A N/A
CU-1 Yes 1 1 N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Supply fan on AHU-1 was found to be in hand due to a drive error.
Recommendations:
1. Review error and place drive back in Auto.
3.16PercivalHall
This three-story building including basement is primarily used as an academic building. The basement
is used for offices. The first through third floors is used for classrooms (8 total). The first floor also
has an auditorium, which is generally limited to play practices and short assemblies (no productions).
This building is typically occupied Monday through Thursday, 7 a.m. to 10:30 p.m., Friday 7 a.m. to 6
p.m., Saturday 8 a.m. to noon. Use of this facility is limited in the summer, partially due to limited air-
conditioned space. The auditorium is mainly used at night and weekends.
Construction: Originally built in 1909, this is a three- story brick structure with shingle roof. The
exterior appears to be in good condition. There is batt insulation in the attic subfloor, but the material
is loosely fitted, missing in many areas and lacking any form of vapor barrier. The access stairway to
Condition Assessments
Fitchburg State University Page 40 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
the attic appears to be a source of exfiltration and heat loss. The majority of windows are newer
double-pane/ vinyl frame sash-type in good condition. Exterior doors are newer and in good condition
as well.
HVAC Summary: Steam is received in the basement mechanical room from a 9 psi branch steam line
where the steam pressure is reduced to 4 psi, which is then converted to heating and domestic hot
water or used in terminal heating units. The steam is manually shut off by University each summer so
domestic hot is not available during the summer break.
The auditorium is heated by steam radiators with pneumatic control valves, which are served by stand-
alone wall mount thermostats. A few of the radiators have Danfoss thermostatic control valves. There
are two fresh air fans (SF-1, -2), which serve this space, which are no longer functional. The
auditorium thus does not have any mechanical ventilation and staff frequently open windows during
events to maintain comfort.
Steam-fired convectors heat the first and second floor and Univents, which are controlled by stand-
alone wall mounted thermostats. The offices are primarily heated by steam fin-tube radiation. The
Univents are reportedly in rough shape. Dampers generally close, but not tightly and many don’t open
at all. Most of the Univents make excessive noise and are frequently turned off during classes.
Five of the classrooms are primarily cooled by Mitsubishi mini split air conditioners, which have
stand-alone wall mounted thermostats.
Controls: All controls are stand-alone pneumatic with fair to poor effectiveness. A dual 1 hp air
compressor supplies instrument air. Staff reports that this building can be too hot in the winter. The
NORESCO system manages a steam supply isolation valve to affect a night setback by cutting steam
according to occupancy schedule. The NORESCO system is not functional at this time. University
staff manually isolates steam to the building each summer.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
SF-1 No 4 Not seen Not seen N/A Abandoned
SF-2 Yes 4 Not seen Not seen N/A Abandoned
Univents Yes 3 3 3 3 Rough shape
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
Condition Assessments
Fitchburg State University Page 41 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Auditorium ventilation fans do not work.
2. Replace Univent controls and dampers as necessary.
Recommendations:
1. Replace make-up air fans
2. Replace univents as necessary
3.17RecreationCenter
The recreation center includes the University’s main gym and athletic facilities, including indoor
swimming pool, fitness training area, racquetball courts, lockers, offices, front desk, etc. The two-level
facility was built in 2000 and totals 84,200 square feet. There are plans to decommission the
swimming pool within the next three years.
The facility’s general operating hours are Monday through Friday 6:30 a.m. to 11 p.m., Saturday 12
p.m. to 4 p.m. and Sunday 3 p.m. to 11 p.m. The swimming pool is open weekdays from 11 a.m. to 7
p.m. with a break from 1 p.m. to 3:30 p.m. On weekends, the pool is open from 11 a.m. to 1 p.m.
Construction: The building is of CMU block and brick construction with insulation in the interior
cavities. The roof is EDPM with insulation. All windows and doors are double pane glass and are in
good condition. Exterior doors have weather typical weather seal issues. It was noted during the
walkthrough that there was an issue with moisture infiltration at the wall/roof junction in the
natatorium. There have been attempts to fix this with adding material into the gap between the walls
and the roof structure, but the repair does not appear to be holding.
HVAC Summary: Five Trane air handlers condition the building. Units serving the gym and lockers
are heating only. The other units serving the administration area and fitness center have cooling coils
and are equipment with VFDs. The swimming pool area is served by a Dectron unit with air-to-air and
condenser heat recovery.
There are six gas-fired Burnham atmospheric hot water boilers. Heating hot water is distributed to air
handlers, VAV box reheats and perimeter convectors by one of two 7.5 centrifugal constant speed
pumps. The second pump is standby. An air-cooled rooftop packaged chiller provides cooling for the
Condition Assessments
Fitchburg State University Page 42 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
air handler coils. The heating and cooling pumps are both controlled by the Novar control system and
are constant speed.
Domestic hot water is an A.O Smith Duramax 992 MBH indirect storage tank that is approximately
300 gallons.
Swimming Pool Equipment Summary: Swimming pool water is circulated through a Neptune sand
filter by a 10 hp centrifugal pump. The pump runs continuously. The pump motor is not particularly
efficient and the pump’s discharge valve is heavily throttled to reduce output. Pool water is heated by
heat recovery from the Dectron unit and by backup boiler. The boiler is 650 MBH gas-fired Lochinvar
unit that was installed after the facility was commissioned because the heat recovery system wasn’t
able to meet the pool’s heating requirements. Exhaust fans are located throughout the building and
terminate both on the roof and on the side walls.
AirHandlingUnits
Tag Serves Make Model Supply Fan hp
CHW ton
AHU-1 Gymnasium Trane MCCA035 15 NA
AHU-2 Gymnasium Trane MCCA035 15 NA
AHU-3 Administration Trane MCCA025 15 55 AHU-4 Fitness Center Trane MCCA014 7.5 56
AHU-5 Locker Rooms Trane MCCA006 2 NA
Dectron Swimming Pool Dectron DS-100-43 7.5 NA
AirCooledLiquidChiller
Tag Make Model Capacity (Tons)
CH-1 Trane CGAFC604ACA 60
BoilerPlant
Tag Make Model Input MBH
Output MBH
B-1 thru B-6 Burnham P81ONEI 594 475
Controls: Air handlers, VAVs, exhaust fans, boilers and the chiller plant are controlled through the
stand-alone Novar control system. The system does not control pool equipment or Dectron unit. The
system does not communicate with the ALC front end and staff do not use the system to its fully
capability. The system does schedule units and provide all basic control strategies. Having the system
tied to the ALC system is priority for the University.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
AHU-1 Yes 2 2 2 2 AHU-2 Yes 2 2 2 2
Condition Assessments
Fitchburg State University Page 43 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
AHU-3 Yes 2 2 2 2 VFD not operating AHU-4 Yes 2 2 2 2 VFD not operating
AHU-5 Yes 2 2 2 2
Dectron Yes 2 2 2 2
CH-1 Yes 2 N/A N/A N/A
DHW Boiler Yes 2 N/A N/A N/A B-1, -2, -3, -4,
-5, -6 Yes 2 N/A N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. VFDs in hand or removed on AHU supply and return fans.
2. NOVAR control system not fully utilized.
Recommendations:
1. Restore VFDs to operable condition.
2. Consider replacement of NOVAR system with campus standard ALC.
3.18SandersAdministration
The Sanders Administration building totals 24,800 square feet. The building is primarily used for
offices, including executive offices, Human Resources staff and professor offices in the lower level.
The first floor and basement have offices with the basement having cubicles. This building is typically
occupied Monday – Friday, 8 a.m. to 5:00 p.m., with the lower level having later hours to
accommodate student demand.
Construction: Built in 1963, this is a 2-story brick structure with white EPDM roof. Most of the
windows are newer double pane / aluminum frame except in the back portion of the building, which
has original single pane metal casement windows that are functional, but lack seals and are thermally
very poor. The roof and brick exterior appears to be in fair condition. The exterior doors are newer and
appear to be in good condition, except some attention is required to assure the door seals are tight.
HVAC Summary: The mechanical equipment in this building includes a mix of types including a
rooftop unit, interior make-up units, water-source heat pumps, newer ductless splits and perimeter
steam radiation. The packaged rooftop unit is DX cooling only with interior steam reheat that serves
Condition Assessments
Fitchburg State University Page 44 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
the executive suite. The first floor and basement each has a ceiling mounted once thru water source
heat pump. Only the unit serving the upper level presidential office is functional. This unit uses city
water to cool the condenser. The water flow is regulated by thermostatic valve. Only one of the two
Trane 3 hp H&V units is operable. Steam is received from the central heating plant at typically 60-65
psi where the steam pressure is reduced to 3-7 psi and fed directly to the fin-tube radiation and reheats.
Domestic hot water is provided by a 40 gallon electric residential style heater.
Controls: ALC controls the RTU, including temperature control and scheduling. The H&V unit is
controlled by the NORESCO system. Otherwise all building controls is local stand-alone, including
some pneumatic.
Other: A 62 kW solar photovoltaic array has been recently installed on the roof.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
RTU-1 Yes 3 2 3 N/A No comment
HV-1 Yes 3 3 3 3 Approaching end of life
HV-2 No 4 4 4 4 Abandoned in place
HP-1 Yes 4 Not seen Not seen N/A Reliability a concern
HP-2 Yes 4 Not seen Not seen N/A Not used
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. None
Recommendations:
1. Replace water source heat pump(s) with alternate
Condition Assessments
Fitchburg State University Page 45 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.19ServiceCenter
The University’s Service Center is located off-campus and contains Building Services, Financial
Services, and Print Service departments. The building includes a substantial warehouse and is the
University’s principal point for shipping and receiving. There are trade’s shops in the warehouse. The
building was formally owned by a paper distribution company and was purchased by the University in
approximately 2003. The facility is generally in use weekdays from 7:30 a.m. to 5 p.m.
Construction: The front portion of the building is concrete block. The presence of insulation was not
determined. The warehouse has a domed roof with interior insulation blanket. There is likely
insulation in other parts of the building’s built-up roof system. There aren’t very many windows at this
facility and those seen seemed to be in good condition. The exterior doors are in reasonably good
condition.
HVAC Summary: The administrative and print shop areas of the building are conditioned by gas-fired
DX rooftop units (see below). The warehouse has gas-fired unit heaters. Domestic hot water is
supplied by electric tank heater (60 gallon, 6 kW).
RTUSummary
Unit Serves Make Model Fan hp Gas MBH DX ton
None Financial Services York NA NA NA NA
None Print Shop Offices York NA NA NA NA
RTU-1 Print Shop York DH240N24B4AAA1C 7.5 300 15
RTU-2 Receiving York DINH030N05646C 0.5 70 2
ERU-1 RTU-1 York 82R2818XM33 2 + 2 None None
ERU-2 Print Shop York 82D11-02XH21 1.5 + 1.5 None None
NA = Not Available
Controls: local thermostats control all units. The front area of the building and maintenance office use
programmable thermostats, but few are setup properly.
ConditionAssessmentSummaryTable
Unit Operable Deficiency Rating
Comment Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
None Yes 4 Not seen Not seen N/A Beyond Service Life
None Yes 4 Not seen Not seen N/A Beyond Service Life
RTU-1 Yes 2 Not seen Not seen N/A
RTU-2 Yes 2 Not seen Not seen N/A
ERU-1 Yes 2 Not seen Not seen N/A ERU-2 Yes 2 Not seen Not seen N/A
Condition Assessments
Fitchburg State University Page 46 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Antiquated rooftop units (2).
2. There is an interior rated door between the print shop and warehouse (limited heating)
3. No pipe insulation in vicinity of DHW heater.
Recommendations:
1. Replace old York rooftop units.
3.20ThompsonHall
This four-level building totals 53,600 square feet is primarily used as an academic building. The
basement is used to have offices, classroom and a radio station, all no longer in use. There is a small
dance studio in the basement. The first and second floors are used for classrooms. The third floor is
used for nursing labs and office, and has recently undergone a complete renovation. This building is
typically occupied Monday through Friday, 8 a.m. to roughly 5:00 p.m. with frequent evening and
weekend use. Summer use is light due to limited air conditioning.
Construction: Originally built in 1895, this is a four-story brick structure with shingle roof. The
exterior appears to be in good condition, but probably does not include wall insulation. There is
fiberglass batt insulation in the attic, but no vapor barrier and the insulation is in poor condition. Most
of the building’s windows are single pane / wood frame in fair to rough condition. The third floor has
newer double-pane/ vinyl frame. Exterior doors are newer and are in good condition.
HVAC Summary: Steam is received from Dupont, reduced to 3-7 psi and used directly in convectors
and Univents as well as to generate heating and domestic hot water. Heating hot water is only in use
on the 3rd
floor, but the hot water distribution pipes that were installed are setup to carry the entire
building load. Domestic hot water is generated in an old approximately 450-gallon tank.
The first and second floor classrooms are heated by steam-fired Trane Univents. One of the units is
newer; otherwise all probably date from the 1950’s or 60’s. Residential style steam radiators that have
Condition Assessments
Fitchburg State University Page 47 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
been retrofitted with Danfoss radiator control valves serve the corridors and lobby areas. There are
several Mitsubishi ductless mini splits providing air conditioning to classrooms.
There is a newer 3 hp York AHU in the attic that serves part of the 3rd
floor. The DX unit is equipped
with a fan VFD and serves zone hydronic VAV/reheat boxes. There are two American Filter DX
Univents serving 3rd
floor labs. The condensing unit for these units is under the building’s porch and
not receiving enough air circulation for effective cooling. The rest of the 3rd
floor has perimeter hot
water fin-tube radiation controlled by wall-mounted thermostats.
The basement dance studio has two steam-fired Univents. The controls on these units no longer work
and the space is generally uncomfortable (usually too cold).
AirHandlersandFans
Unit Type Serves Year hp SP (inch) cfm Preheat
coil MBH Cooling
tons
AHU-1 CAV 3rd FL ~2010 3 NA NA NA NA
NA = Not Available
Controls: The third floor renovation is full ALC DDC controls. The remainder of the building’s older
equipment uses stand-alone pneumatic thermostats with day/night feature that is believed to function.
The mini splits have local electric thermostats.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
AHU-1 No 1 1 1 1 Newer
Univents Yes 3 3 3 3 Rough shape
CV-1 Yes 1 N/A N/A 1 Newer
P-1 Yes 1 N/A N/A N/A Newer
DHW Yes 4 N/A N/A N/A
Circa 1950s. Rough shape and possibly an asbestos issue
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Condition Assessments
Fitchburg State University Page 48 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Notes (refer to Appendix A for details):
1. Univent functionality is questionable.
2. DHW heat exchanger reportedly has asbestos and oversized for current usage.
3. AHU-1 was operating at full speed (60Hz)
4. Single pane windows are in rough shape.
Recommendations:
1. Replace windows
2. Rebuild Univents as necessary
3. Replace DHW heat exchanger
4. Further investigate root cause of AHU-1 operating at full speed.
3.21WestonAuditorium
The Weston Auditorium is located next to the Conlon Fine Arts building. The 16,700 square foot
facility is primarily used for rehearsals, theatre production and assemblies. The auditorium has seating
capacity for 800 people. There is an entrance foyer area with box office and bathrooms. Behind the
stage are dressing rooms and an additional bathroom. This building is typically used daily during the
school year and for frequent Saturday events.
Construction: Built in 1963, this is a 2-story mason block structure with black EPDM roof. The roof
and exterior appears to be in acceptable condition. The front vestibule appeared to have been
renovated. There are only a few single pane windows. At least one exterior door is beyond repair.
HVAC Summary: This building receives steam from Science Center. Steam is fed directly to AHU
coils. The HVAC equipment is located behind the stage suspended in the air. The H&V units are
accessible by a ladder and catwalks. Air handling equipment is constant volume and supply air via
ductwork distribution. The air handlers each typically have a 1 hp motors. There are four H&V units
(H&V-1, -2, -3,- 4). H&V-1 serves the lobby and bathrooms. H&V-2 and H&V-3 serve the
Auditorium via common ductwork. H&V serves the back of the stage. The units have steam heat only.
There is a small energy recovery ventilation unit with ¾ hp supply and exhaust motors serving the box
office.
Controls: The pneumatic controls are under currently on the NORESCO BMS providing very limited
feedback and control capability. Space thermostats currently do not provide feedback or control from
the BMS. The NORESCO system currently provided scheduling for air handlers, and main steam
valve.
Condition Assessments
Fitchburg State University Page 49 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
DEFICIENCY SUMMARY TABLE
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
H&V-1 Yes 3 3 4 4 Dampers and control valve appeared to be in rough shape
H&V-2 Yes 3 3 4 4 Dampers and control valve appeared to be in rough shape
H&V-3 Yes 3 3 4 4 Dampers and control valve appeared to be in rough shape
H&V-4 Yes 3 3 4 4 Dampers and control valve appeared to be in rough shape
ERV Yes 1 Not seen Not seen N/A Newer
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Belts were noted to be loose during inspection.
2. Control valve functionality is questionable.
Recommendations:
1. Replace dampers.
2. Replace steam control valves at each unit.
3. Replace drive belts on each unit.
3.22185NorthSt.ApartmentComplex
The 185 North Street Apartment building is a 3-story student residence complex, which includes two
apartments per floor with five bedrooms and 1.5 bathrooms in each apartment. The University
acquired the building in roughly 2009 and there has been some update of kitchen appliances;
otherwise the buildings remain original with rough windows, etc. The apartments are fully occupied
by upper classmen during the school year and partially or completely vacant during the summer break.
Condition Assessments
Fitchburg State University Page 50 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Construction: Built in approximately 1998, this is a 3-story wood framed structure with clapboard
vinyl exterior as asphalt roofing. Insulation details are unknown. The windows are original double
pane vinyl sash-type and are in rough condition (sashes stuck, won’t stay up, etc). The exterior doors
are in fair condition.
HVAC Summary: The mechanical equipment for each floor is located in the hallway between the two
apartments. Each apartment has identical heating systems consisting of a gas-fired atmospheric
heating hot water boiler and 30 gallon domestic hot water tank heater. There are two boilers per floor
(one boiler servers each apartment) as well as two domestic hot water heaters per floor (one per
apartment). Of the six heating boilers in the building, five of them are original to the building and near
the end of their useful service lives. One of the boilers was replaced within the last year. All but one of
the domestic hot water heaters are original and in rough condition.
The primary means of heat delivery is baseboard radiation on all floors. Each apartment has a single
non-programmable thermostat, which controls the entire apartment; the thermostat is located in the
living room and it is typical of all apartments.
Appliance Summary: In the kitchen, there is a gas stove, dishwasher, stackable washer/dryer unit as
well as an energy star rated refrigerator, which is typical on all floors. There is an irrigation system in
place, which is currently not in use. At the time of visit, it was noted that the system is currently in
bypass mode.
TypicalHotWaterBoilers(oneeachperapartment)
Unit Type Serves Year MBH
(Input)
B-1 Hot
Water HHW 1998 620 MBH
DHW-1 Hot
Water DHW 1998 30 MBH
Controls: All building controls are stand-alone.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
B-1 Yes 3 N/A N/A N/A Replacement should be considered (Typical of 5)
DHW-1 Yes 3 N/A N/A N/A Replacement should be considered (Typical of 5)
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
Condition Assessments
Fitchburg State University Page 51 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Boilers are in rough shape based on visual appearance.
2. Domestic Hot Water heaters near end of life based on visual appearance.
3. Vinyl windows are in poor condition and are subject to cold weather infiltration. In addition,
these windows present a security issue with inoperable locks on the windows.
Recommendations:
1. Replace the remaining five hot water boilers and domestic hot water heaters.
2. Replace all windows in bedrooms as well as in the main living space.
3.23AubuchonHall
This is an eleven-floor (plus basement) student housing facility is adjacent to Herlihy. The 100,800
square foot building was renovated about two years ago, including conversion from steam to hot water
heating systems, new doors and windows, etc. The ground level includes Housing and Residential
Services, including offices, conference room and break room. The 1st level includes building director’s
office and residence, a game room and kitchen area. There is a lobby area on the 2nd
floor. Otherwise
each floor is nearly identical with approximately sixteen student rooms per floor as well as student
lounge areas with kitchenette. Each dorm room typically has three beds.
The building is typically fully occupied during the school year. Actual occupancy varies considerably
during the course of the day and on weekends and school break periods. The Housing and Residence
Services Department is open weekdays from 8 a.m. to 5:00 p.m. and occasionally on weekends.
Construction: Originally built in 1966, this is an 11-story brick structure with flat membrane roof.
Windows and exterior doors where replaced with the renovation and are in good condition. Access
doors to the roof require attention.
HVAC Summary: This building has an entirely new HVAC system that was installed approximately
two years ago. The main mechanical room is on the 2nd
floor and includes steam to hot water
conversion exchangers, make-up air and energy recovery ventilation unit serving the entire facility.
Condition Assessments
Fitchburg State University Page 52 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Two Aerco exchangers generate domestic hot water: one unit has electric control, the other is
pneumatic. A dual ½ hp air compressor provides instrument air to the DHW unit. This is the only
pneumatic device in the building.
The elevator machine room has an exhaust fan only (½ hp).
AirHandlersandFans
Unit Type Serves Year hp cfm Preheat coil
MBH Cooling
tons
MUA-1 CAV Hallways 2010 NA NA NA -
MUA-2 VAV Bldg Dir. 2010 NA NA NA -
ERU-2 CAV MUA-2 2010 NA NA NA -
NA - Not available
Pumps
Unit Type Serves hp Ft gpm
P1-A Centrifugal HHW 7.5 70 275
P1-B Centrifugal HHW 7.5 70 275
Controls: The building has full a DDC system with ALC front end. All rooms and HVAC units are on
the system. There aren’t any setbacks and all systems are run 24/7.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
MUA-1 Yes 1 1 1 1 Newer
MUA-2 Yes 1 1 1 1 Newer
ERU-2 Yes 1 1 1 1 Newer
P1-A, -B Yes 1 N/A N/A N/A Newer
DHW Yes 1 N/A N/A N/A Newer
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Condition Assessments
Fitchburg State University Page 53 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Deficiency Notes (refer to Appendix A for details):
1. Roof access door seals in poor condition
Recommendations:
1. Attention to roof access doors.
3.24CedarStreetHouse(No.22)
The 22 Cedar Street Apartment is a 3-story building (including attic) totaling 3,800 square feet. The
property includes a single bedroom apartment on the ground floor for the building director and two
apartment units on the second floor for 6-7 students. There is storage in the basement. The attic area is
not occupied. The construction style is similar to a single-family house, which has been converted to
apartments.
Construction: Built in approximately 1909, this is a 3-story structure has wood clapboard exterior
with vinyl and wood frame windows. The foundation is block. The roof has been recently replaced
with a metal roof and is considered in good working condition. There is batt insulation in the roofing
rafters. The area on the east side of the attic is poorly sealed. There is also a stained glass window on
the west side, which could be sealed off. The windows are in fair condition, both wood and vinyl; the
vinyl windows are double pane. There are a few attractive stained glass windows. The exterior doors
appeared to be in good condition. The ground floor fireplace is not in use and blocked off.
HVAC Summary: The building is forced hot water. The gas-fired boiler is located in the basement.
This is an older atmospheric unit with standing pilot. There are three heating zones, one for each
apartment’s convectors. The boiler is beyond its useful service life and should be replaced. None of
the heating hot water piping in the basement is insulated. The 1st floor apartment has two window A/C
units. Otherwise the building does not have air conditioning. Domestic hot water is provided by a
newer 150 MBH condensing hot water heater which was installed in 2010.
HotWaterBoilers
Unit Type Mfgr Serves Year MBH
(Input)
B-1 Hot Water Burham Fin-Tube Radiation 1976 210 MBH
DHW-1 Hot Water Bradford White DHW ~2010 150 MBH
Appliances: Each apartment has an electric range and newer refrigerator.
Condition Assessments
Fitchburg State University Page 54 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Controls: a single wall mount non-programmable thermostat controls each apartment.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
B-1 Yes 4 N/A N/A N/A Near end of life
DHW-1 Yes 1 N/A N/A N/A Good working condition
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Boiler beyond its expected service life.
Recommendations:
1. Replace the boiler
2. Replace missing pipe insulation
3. Install programmable thermostats
3.25CedarStreetHouse(No.30)
The 30 Cedar Street Apartment is a 3-story former elderly residence building with 35 student resident
rooms. The property totals 15,600 square feet. The ground level includes a former dining hall that is
now used as a general-purpose area. There is also a pool game room. The building has been renovated
including remodeled kitchen, bathrooms and restoration of original millwork. There are storage areas
in the basement. The building is fully occupied during the school year.
Construction: Built in approximately 1900, this is a 3-story structure that has a brick exterior with flat
roofline. Roofing was recently replaced with white EPDM and is in good working condition without
leaks. There is some insulation at the roof access that indicates some attention to airseal details,
although further information on unseen parts of the building is not available. Windows are single pane/
wood frame windows throughout the entire building. The windows appear to have been retrofitted
with new chain counterweights and are in good working order. The exterior doors are in good
Condition Assessments
Fitchburg State University Page 55 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
condition. One of the building’s two fireplaces has been permanently sealed off, the other isn’t used
and the original damper is closed.
HVAC Summary: This is a steam-heated building. There is an old H.B. Smith steam boiler in the
basement that was recently converted from oil to gas service with a newer Carlin burner. The boiler is
rated for 675 MBH and is well past its useful life. Residential style steam radiators throughout the
building have been retrofitted with Danfoss steam control valves. The general-purpose room had
previously been served by a gas fired RTU, but the unit is no longer in use and is abandoned in place.
There are two exhaust fans, which serve the bathrooms.
A 15-plus year old Peerless unit in the basement supplies domestic hot water. The boiler is rated at
505 MBH. The heater formerly ran on No.2 fuel oil but has been converted to natural gas. The system
employs a 119-gallon indirect storage tank.
Appliances: The recently redone kitchen has new electric range and oven, large refrigerator. There is a
washer and electric drier.
HotWaterBoilers
Unit Type Serves Year MBH
(Input)
B-1 Steam House ~1981 675
DHW-1 Hot Water House ~1990 304
Controls: Danfoss thermostatic control valves and local electric thermostats.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
B-1 Yes 4 N/A N/A N/A End of life
DHW Yes 4 N/A N/A N/A Nearing end of life
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Heating boiler is in rough shape and should be considered for replacement in the near future.
Condition Assessments
Fitchburg State University Page 56 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
2. Domestic hot water boiler should be replaced.
Recommendations:
1. Replace both the heating and DHW boilers.
2. Replace or rebuild wood windows (if not needed for historical significance)
3.26HerlihyHall
This is a three-level (plus basement) student housing facility adjacent to Holmes Dining. The building
totals 37,800 square feet. In addition to dorm rooms, the 1st floor includes the building director’s office
and two RA suites, laundry and vending machine area. Otherwise each floor is nearly identical with
approximately twenty-two student rooms per floor as well as student lounge areas. Each dorm room
typically has two beds. The basement contains electrical and mechanical room.
The building is rented out to the Outward Bound program during the non-school year. Building
occupancy varies considerably during the course of the day and on weekends and school break
periods.
Construction: Built in 1957 and renovated in 2005; construction is brick/steel with flat EPDM roof.
The exterior appears to be in reasonable condition for the age of the building. Windows are roughly 10
year old double pane / aluminum frame. Public exterior doors are new and in good condition. Some of
the back doors are rough.
HVAC Summary: Steam from the central plant enters the basement of the building at typically 60-65
psi where the steam pressure is reduced to 3-7 psi for perimeter fin-tube radiation in dorm rooms.
There is limited mechanical exhaust and no make-up air provisions. The director’s office has a small
split unit. Otherwise there is no air conditioning in this building. Pipe insulation in the mechanical
room is in rough condition and/or missing on sections.
Domestic hot water is generated at Holmes Dining Hall via approximately 500-gallon tank unit with
steam exchanger.
Controls: This building currently does not provide feedback to the ALC or NORESCO BMS. Steam
to the building can be controlled by two steam control valves that serve the front and back (east and
west) side of the building. Depending on solar gains, the steam plant has the ability to vary steam flow
to either the front or rear of the building depending on space temperature. This control feature is no
longer functional due to valve problems. Room temperature is controlled by manual adjustment
Condition Assessments
Fitchburg State University Page 57 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Danfoss control valve on the convector. Students have full temperature control capabilities. However,
the building is reported to have poor temperature control and windows are often left open, even in
winter conditions. The University would like to see the building converted to DDC.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
FTR Yes 2 N/A N/A 3 Students have full control over temperature setpoint
DHW Yes 4 N/A N/A 3 Circa 1950s and well past useful life.
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Steam control valves are old and not functioning.
2. DHW tank, located in Holmes, appeared to be in rough shape and past useful life.
Recommendations:
1. Replace steam control valves
2. Replace DHW heat exchanger
3. Add unit level control and temperature monitoring
Condition Assessments
Fitchburg State University Page 58 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
3.27MaraVillage
The Mara Village dorm complex consists of eight student dorms buildings and Mara Commons. The
buildings date from the 1980’s, except Mara 8, which was completed in 2010 as a LEED Silver
building. Each Mara building is 4 floors (Commons is 3 floors). The typical building includes living
area on the ground floor with small kitchen and bathrooms. Upper floors are for student suites. A
summary of the buildings is provided below. The Mara dorms are usually fully occupied during the
school year. Mara 8 is frequently used in the summer for University hosted programs and events.
MaraVillageBuildingSummary
Bldg Sq. Ft. A/C? No.
Suites No.
Beds Other Uses
Mara Village #1 10,221 Yes 6 48
Mara Village #2 10,546 No 6 48
Mara Village #3 10,546 No 6 48
Mara Village #4 9,918 No 7 56
Mara Village #5 9,918 No 7 56
Mara Village #6 10,226 No 6 48
Mara Village #7 10,226 No 6 48
Mara Village #8 44,023 Yes 14 70 Laundry, Maint Shop, Conf. Room Mara Village Commons Building
6,483 Mail Room
Only 3 13 Laundry, Mail Room, Common Area
Construction: Built in sequence starting in the 1980’s, the Mara structures are all similar, except Mara
8, which is a newer and Commons, which includes a large laundry facility and common area. The four
story buildings all have a brick exterior with double pane/ aluminum frame windows. Exterior doors
are generally in good condition, although there are a number with worn or missing weather stripping.
HVAC Summary (Mara 1, 2, 3, 4, 5, 6, 7): These are forced hot-water building to locally controlled
convectors. Each building has toilet exhaust fans. The fans generally run continuously, but provide
fairly poor performance. Heating hot water is supplied from central gas-fired boiler plant. The typical
boiler is a Weil McLain section unit rated at 336 MBH output. Hot water is circulated by one of two
1.5 hp centrifugal pumps. Some of the pumps are in rough condition. Domestic hot water is supplied
by separate gas-fired boiler: the typical arrangement is a Lochinvar or Raytherm atmospheric unit with
separate 119 gallon storage tank. Hot water piping is poorly insulated.
HVAC Summary (Mara 8): This building is conditioned by 2-pipe fan coils located throughout the
building. There is an Energy Recovery Ventilation system in the attic with 3 hp supply fan and 1½ hp
exhaust fan. Heating hot water is supplied by a two gas-fired Cleaver Brooks condensing units rated at
675 MBH output. An approximately 100-ton McQuay split chiller supplies chilled water. The
condenser is located on the roof. Hot water or chilled water is circulated by a pair of 10 hp centrifugal
Condition Assessments
Fitchburg State University Page 59 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
pumps controlled by VFDs (184 gpm at 90 feet). Domestic hot water is generated via two 250-gallon
indirect PVI units.
HVAC Summary (Mara Commons): This is another forced hot-water building with locally controlled
convectors. Heating hot water is supplied from central gas-fired boiler plant consisting of Weil
McClain section unit rated at 264 MBH output. Hot water is circulated by one of two 1.5 hp
centrifugal pumps. One of the pumps is newer, the other original and in poor condition. Domestic hot
water is supplied by separate gas-fired condensing boiler that was installed in 2011. There is a
Mitsubishi split serving the ground floor mailroom.
Controls: Mara 8 has full DDC controls tied to the central ALC system. Non-programmable wall
thermostats locally control the remainder of the buildings.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
Mara 1 Boiler Yes 2 N/A N/A N/A
Mara 2 Boiler Yes 2 N/A N/A N/A
Mara 2 Boiler Yes 2 N/A N/A N/A
Mara 3 Boiler Yes 2 N/A N/A N/A
Mara 4 Boiler Yes 2 N/A N/A N/A
Mara 5 Boiler Yes 2 N/A N/A N/A
Mara 6 Boiler Yes 2 N/A N/A N/A
Mara 7 Boiler Yes 2 N/A N/A N/A
Mara 8 Boiler Yes 1 N/A N/A N/A
Mara Commons Boiler Yes 2 N/A N/A N/A
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Domestic hot water boiler should be considered for replacement
2. Mara 3: Exhaust fans appear to be inadequate
3. Original HHW pumps are rough
Recommendations:
1. Consider replacing older domestic hot water boilers.
Condition Assessments
Fitchburg State University Page 60 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
2. Replace original HHW pumps.
3.28RussellTowers
This multi-level 105,900 square foot building is primarily used as student housing. There are three
towers, A, B, and C. Tower A is has seven levels. Tower B has 9 levels. Tower C has eight levels. The
first floor has mechanical space, maintenance shop and Health Services offices. The second floor has
game rooms, kitchenette, laundry, and lounge area. The upper level floors are dorms. This building is
typically fully occupied during the school year. Health Services is open weekdays from 8 a.m. to 5:00
p.m. and occasionally on weekends. Student occupancy varies.
Construction: Originally built in the 1970’s, this is a multilevel brick structure with black roof.
Windows are double-pane/ aluminum frame that were installed in roughly 2006. The exterior appears
to be in good condition.
HVAC Summary: Steam from the CHP enters the building in the lower level mechanical room.
Distribution steam pressure is reduced to 3-7 psi via PRVs. Steam is used to generate heating hot
water via exchanger for perimeter radiation throughout the building. There are numerous issues with
steam and hot water pipe insulation in this mechanical area. Hot water is circulated by one of two
older 20 hp constant speed pumps.
There is a constant volume McQuay air handler, 5 hp, with a hot water preheat coil and DX cooling,
which serves Health Services. The hot water control valve is 3-way. There is an identical single zone
McQuay air handler located on the second floor, which serves the lounge area. This unit is about 6
years old and in good condition.
There is a Trane H&V unit that once provided make-up air to the building but is no longer in use.
During renovations over the years, ductwork has been disconnected in various places so facility staff
has discontinued the use of this unit. There are several abandoned roof exhausters. At least two 1½ hp
toilet exhaust fans operate continuously.
Two semi-instant steam fired AERCO domestic water heaters generate domestic hot water. A
pneumatic control valve controls steam.
Condition Assessments
Fitchburg State University Page 61 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
AirHandlersandFans
Unit Type Serves Year hp cfm Preheat coil
MBH Cooling
tons
AHU-1 CAV Health Services NA 5 NA NA NA
AHU-2 CAV Lounge NA NA NA NA NA
AHU-3 CAV Dorms NA NA NA NA - EF-1
thru EF-6
CAV General NA NA NA NA -
NA = Not available
Controls: The NORESCO BMS controls the main steam control valve for HHW temperature reset and
scheduling of the pumps otherwise all equipment is stand-alone. Stand-alone Danfoss thermostatic
control valves control perimeter radiation. When the windows were replaced about 6 years ago, the
control valves were re-installed in various different positions making temperature adjustments
challenging. In other areas, students have fully access to the valve for full range of temperature
adjustments.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
AHU-1 Yes 3 2 2 2 No Comment
AHU-2 Yes 1 1 1 1 No Comment
AHU-3 No 4 3 3 3 Discontinued Use
EF-1 thru EF-6 Yes 3 N/A N/A N/A Several abandoned
CV-1 Yes 2 N/A N/A 3 Missing Insulation
P-1 Yes 3 N/A N/A N/A Older – Rough
P-2 Yes 3 N/A N/A N/A Older - Rough
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. HW pumps older and rough shape.
2. Ductwork has been disconnected
3. Danfoss control valve installation varies
Condition Assessments
Fitchburg State University Page 62 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Recommendations:
1. Replace hot water pumps.
2. Replace DHW pneumatic control valves with DDC.
3. Determine where ductwork has been disconnected.
4. Assure the building has adequate ventilation.
3.29Townhouses
The Townhouse complex consists of seven similar style student dorms. The buildings have multiple
apartments associated with each building. The buildings are three floors. Each apartment has a kitchen
with a refrigerator, electric range and laundry. The townhouses are typically fully occupied during the
school year and vacant during the summer. The table below provides a summary of the buildings.
TownhouseSummary
Bldg Sq. Ft. A/C? No.
Suites No.
Beds
Townhouse #1 (Worcester House) 10,578 No 8 48
Townhouse #2 (Middlesex House) 11,749 No 8 48
Townhouse #3 (Essex House) 5,651 No 4 24
Townhouse #4 (Norfolk House) 5,425 No 4 24
Townhouse #5 (Hampden House) 3,499 Yes 1 7
Townhouse #6 (Plymouth House) 5,455 No 4 28
Townhouse #7 (Suffolk House) 5,455 No 4 28
Construction: Built in approximately the 1980’s, these architecturally similar buildings have brick
exterior with single and double pane/ aluminum frame sliding windows. Insulation details could not be
confirmed. Most of the exterior doors were replaced about 5 years ago and are in good condition.
HVAC Summary: These are forced hot water buildings. Only Townhouse #5 has A/C, which is only
used for special purposes in the summer. Each building has a central gas-fired atmospheric boiler that
provides hot water to the entire building in multiple zones. Domestic hot water is generated off the
heating boiler via typical 119-gallon indirect tank. The boiler in Townhouse #2 recently failed and has
been fitted with a temporary boiler.
HotWaterBoilers
Bldg Age Mfgr Model Input MBH
Output MBH
Townhouse #1 (Worcester House) ~2003 RBI DB600 600 510
Townhouse #2 (Middlesex House) Temporary boiler in service
Townhouse #3 (Essex House) ~2003 Lochinvar CHN501 500 420
Townhouse #4 (Norfolk House) ~2003 Lochinvar CHN501 500 420
Condition Assessments
Fitchburg State University Page 63 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Townhouse #5 (Hampden House) ~2003 RBI NA 399 339
Townhouse #6 (Plymouth House) ~2003 Laars NA 499 420
Townhouse #7 (Suffolk House) ~2003 Laars NA 499 420
Controls: a single wall mount non-programmable thermostat controls each apartment. A Tekmar
controller controls the boiler and domestic hot water systems.
ConditionAssessmentSummaryTable
Deficiency Rating
Unit Operable Overall Rating
Coil(s) Damper / Actuator
Valve / Actuator
Comment
TH1 Boiler Yes 3 N/A N/A N/A Approaching end of life
TH2 Boiler Yes 4 N/A N/A N/A Failed
TH3 Boiler Yes 3 N/A N/A N/A Approaching end of life
TH4 Boiler Yes 3 N/A N/A N/A Approaching end of life
TH5 Boiler Yes 3 N/A N/A N/A Approaching end of life
TH6 Boiler Yes 3 N/A N/A N/A Approaching end of life
TH6 Boiler Yes 3 N/A N/A N/A Approaching end of life
Deficiency Rating: Overall
1 - New or good condition
2 - Fair condition, may require some updates (motors, controls, access)
3 - Requires repair/renovation (rebuilding, new controls, dampers)
4 - Requires replacement
N/A - Not applicable
Deficiency Notes (refer to Appendix A for details):
1. Heating boilers should be considered for replacement in the near future.
Recommendations:
1. Consider replacing heating hot water boilers with condensing models
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 64 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
4.0CentralBoilerPlantCondition
Assessment
As part of the campus condition assessment, Sebesta Blomberg also provided a detailed assessment of
the central steam boiler plant at the Dupont Building. This section provides details on the boilers, their
operation, ancillary equipment and recommendations to maintain maximum operating efficiency and
boiler life.
4.1FurnaceandTubeCondition
For the purpose of evaluating boiler remaining life, this section examines condition of the furnace
refractory and tubes. Sebesta Blomberg physically inspected the interior of the boilers as part of this
assessment. Furnace tubes were inspected for signs of overheating and bulging. None were noted.
Photo of the tube are provided below.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 65 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Furnace Wall and Floor
Furnace refractory was inspected for sign of thermal fatigue. None were noted. Only small minor
cracks due to the material expanding and contracting with changes in temperature were noted. Photos
of this activity are shown below.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 66 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Refractory Baffle
Boiler Front Wall/Burner Refractory
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 67 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Recommendation
Continue operating the boilers in a safe/reliable fashion.
4.2CorrosionControl
Four common waterside problems are corrosion (oxygen pitting and ph), scale formation, sludge
formation and carryover. For the purpose of evaluating boiler remaining life, this section examines
corrosion and scale formation.
The presence of dissolved oxygen in boiler feed water leads to pitting of boiler waterside surfaces. If
allowed to proceed unchecked, the pitting will adversely affect boiler reliability and shorten its service
life. This oxygen pitting corrosion is prevented by reducing the level of oxygen in the feed water.
Oxygen is removed from the feed water through both mechanical and chemical means. Through
chemical means, oxygen levels are further reduced, by feeding nitrite (NO2) into the feed water.
Maintaining residual nitrite levels in the feed water ensures that oxygen levels in the feed system are
reduced down to less than 10 parts per billion (essentially zero).
A report from the plant indicates that the deaerator pegging steam valve has control issues. If the
pegging steam pressure cannot be maintained at its desired set point than more nitrite is needed to
maintain the dissolved oxygen level in the feed water at recommended levels. This results in an
increase in chemical cost. A photo of the valve is provided below.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 68 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Pegging Steam Valve
Recommendation
It is recommended that the dearator pegging valve and related components be investigated further with
consideration that the valve/controls be replaced.
A result of proper water treatment is establishment of a later of magnetite iron oxide on all boiler
surfaces (waterside). The oxide known as magnetite and is an effective barrier in preventing corrosion.
The stability of the magnetic layer formed in the boiler is highly dependent on the ph of the boiler
water. Corrosion occurs when, as a result of high or low ph, the integrity of the protective layer is
compromised and exposed steel comes in contact with water. Operators should strive to maintain a ph
range of 8.5 to 12.7. P alkalinity readings are used to benchmark boiler water pH and furnished a
correlation between p alkalinity readings and the actual pH of the boiler water. A P-Alkalinity range
recommended by Hoffmann Water Technology (the Water Treatment Consultant) is 150 to 300. Water
treatment service report P alkalinity readings were reviewed for the purpose of evaluating boiler water
ph. Plots of the data are provided below. Although there were indications that stricter control of boiler
water chemical levels should be instituted, it does not appear that the ph levels were such that
corrosion due to boiler water ph would be prevalent.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 69 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
The term scale describes a continuous adherent layer of calcium carbonate and magnesium carbonate
deposits that form on tubes and tube sheets. Scale formation in a boiler is a result of improper water
treatment. Scale is objectionable because of its insulating effect in resulting overheating and eventual
tube leakage, tube end cracking, other pressure vessel problems and costly repairs. Scale formation
also results in increased fuel usage, due to reduced heat transfer. An increase in fuel consumption due
to scale formation is provided below:
Table1–ScaleImpactonBoilerPerformance
Scale Thickness
Increase in Fuel
Consumption
1/16" 15%
1/8" 20%
1/4" 39%
A visual inspection of the steam drum and mud drum were performed in part to investigate for signs of
scale formation and stability of the magnetite layer. Photographs of this activity are provided below.
Indications of scale formation were not noted.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 70 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Mud Drum
Steam Drum
Recommendation
Continue maintaining boiler water treatment within Hoffman Water Technology guidelines.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 71 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
4.3BoilerTurndown
Turndown ratio is the range of the fuel-input rates that a burner will operate satisfactorily. It is
expressed as the ratio of the maximum to minimum heat input rates. Turndown is interdependent on
fuel fired and flame stability.
Every time the burner starts and stops the boiler goes through a purge cycle. The purpose of the purge
cycle is to eliminate all combustible/explosive gases from the boiler. As a result of a purge cycle,
energy in the form of heated air is blown to atmosphere. The energy loss due to purging is provided
below.
Table2-EnergyLossAssociatedwithPurging
Number of Cycles
per hour
Percent (%)
Energy Loss
2 2
5 8
10 30
Improving burner turndown can reduce the number of times a boiler cycles per hour. Moving the high
and low-pressure limits apart, thus keeping the boiler on and off for longer period of times, can also
reduce the number of times a boiler cycles per hour. When a burner cycles, boiler refractory and
pressure parts expand and contract. Over time, fatigue of critical parts can occur. Maintenance costs
are reduced when there is much less thermal cycling taking place in the boiler.
Recommendation
Replacement of the standard heavy oil burner with a 4 to 1 turndown with a high turndown gas burner
with a 10 to 1 turndown will result in reduced boiler cycling, improved plant efficiency, and reduced
annual fuel costs.
4.4BoilerEfficiency
There are several means of maximizing boiler efficiency and thereby reducing steam plant operating
costs. These include controlling excess air, stack temperature, load balancing, boiler blow down and
condensate return. This section of the report will examine excess air.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 72 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Every burner requires some excess air to ensure complete combustion. Excess air is generally defined
as air introduced above the theoretical requirements to effect complete and efficient combustion of the
fuel. Firing with minimal excess air decreases stack heat loss. By reducing flue gas flow and lowering
flue gas velocity through the boiler. As a result, boiler tube surfaces are in contact with hot flue gases
longer and the heat from combustion can be more thoroughly absorbed. Measuring oxygen in the flue
gas is the common and preferred method of monitoring the amount of excess air in the flue gas. It is
also the method most used to optimally control the air-to-fuel ratios associated with the given load
demand. Cleaver Brooks recommends that, when firing heavy oil, combustion readings stay within the
tabulated ranges shown below:
Table3-RecommendedExcessAir
Flue Gas Constituent Low Fire High Fire
Oxygen 8.0% to 7.0% 4.0 to 3.0%
As a rule of thumb, boiler efficiency can be increased one percent for each 1.3% reduction in oxygen
in flue gas.
On April 2012 Dillon Boiler tested the boilers at 5 firing rates. For the purpose of analyzing fuel oil
combustion within the plant, combustion data for boilers #2 & #3 were plotted. The analysis indicated
that under certain combustion rates, 3% to 6% of combustion efficiency is loss due to high levels of
excess air in the flue gas.
Inefficient combustion can be due to poor atomization of fuel oil resulting from low fuel oil
temperature or low excess air resulting from maladjustment of and/or slop in air/fuel ratio control
linkages.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 73 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 74 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Recommendations
Upgrading the combustion control linkage assembly with servomotors will help ensure tight control of
the burner air/fuel ratio. Also, converting the burners over to natural gas/light oil will prevent the
likeliness of having poor combustion due to low fuel oil temperatures.
4.5FeedwaterSystem
For the purpose of evaluating the life expectancy of the boiler feed water system a review of the feed
water pump installation was performed. Plant personnel indicated that annual internal inspections of
the deaerator do not reveal any signs of fatigue. Feed water pump #1 is the newest of the three and
appears to be in good operating condition. Feed water pumps #2 & #3 are older and appear to be in
need of maintenance/repairs/upgrades.
Photos of the feed water pumps are provided below.
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 75 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Feed Water Pump #1
Condition Assessment Summary Central Heating Plant Assessment (CHP)
Fitchburg State University Page 76 of 76
Energy and Performance Sebesta Blomberg Project No. 700503.35
Condition Assessment December 10, 2013
Feed Water Pump #3
Recommendation
It is recommended that Feed Water Pumps #2 & #3 be considered for replacement. For the purpose of
energy conservation, adding Variable Frequency Drives to the feed water pumps should be considered.