Upload
doanlien
View
245
Download
7
Embed Size (px)
Citation preview
Energy Transparency Centre of
Knowledge E-TRACK
1st Open Seminar
Amsterdam, 23 October 2014
First Open Seminar
Amsterdam, 23rd October 2014
Location: ROOM MATE AITANA, IJDok 6, 1013 MM Amsterdam, The Netherlands
The role of public participation in radioactive waste management and other sectors
Lessons learnt from research and practice
09.00 Participants Arrival – Registration
09.30 Presentation of E-TRACK and its activity on Radioactive Waste Management (RWM)
Ulrik von Estorff, Scientific Officer, Joint Research Centre, European Commission
Gianluca Ferraro, Scientific Officer, Joint Research Centre, European Commission
10.00 Public participation in environmental decision-making
Fiona Marshall, Environmental Affairs Officer, Aarhus Convention Secretariat, United
Nations Economic Commission for Europe
10.30 Coffee break
11.00 Chairwoman's introduction
Saida Laârouchi Engström, Vice President, SKB, Sweden
11.15 High-Level Waste and the experience of Olkiluoto
Harri Hiitiö, Mayor, Eurajoki Municipality, Finland
11.45 Changes in RWM policy. The participatory turn in Sweden
Johanna Yngve Törnqvist, Analyst, Östhammar’s Municipality, Sweden
12.15 A case from Low- and Intermediate-Level Waste
Sébastien Farin, Deputy Director of Communication and Dialogue with Civil Society,
ANDRA, France
12.45 Buffet Lunch
13.45 Public Participation: lessons from academia
Dirk Scheer, Senior Researcher, University of Stuttgart, Germany
14.15 Public participation and dialogue beyond nuclear
Melanie Provoost, Consultant, Triarii, R&Dialogue (Building a low-carbon future together),
The Netherlands
Sergio Olivero, Head of Energy and Security Research Area, SiTI – Higher Institute on
Territorial Systems for Innovation, Italy
15.15 Close of meeting
15.30 End of day
List of Participants
Ms Michaela BIHARYOVÁ Nuclear Regulatory Authority SlovakiaMs Paula-Alexandra BOTEANU European Commission EUMs Christine BRUN-YABA IRSN FranceMr Gunnar BUCKAU European Commission EUMr Cesar CHENEL European Commission EUMrs Anne DE MAEYER SOERENSEN Dansk Dekommissionering DenmarkDr Annick DE VRIES Rathenau Institute NetherlandsMs Katleen DERVEAUX vzw STORA BelgiumMr Hugo DRAULANS vzw STORA BelgiumDr Martin DURDOVIC Institute of Sociology AS CR Czech RepublicMs Rigmor EKLIND Oskarshamn municipality SwedenMr Sebastian FARIN ANDRA FranceMr Gianluca FERRARO European Commission EUMr Ansi GERHARDSSON Swedish Radiation Safety Authority SwedenMrs Ester GOMEZ BELINCHON ENRESA SpainMr Benno HAVERKATE NRG NetherlandsMr Harri HIITIO Eurajoki Municipality FinlandMr Wolfgang HILDEN ex-European Commission GermanyMrs Gudrun JÄCKEL LPTK NetherlandsDr Victor KARG BMLFUW AustriaMr Ole KASTBJERG NIELSEN Dansk Dekommissionering DenmarkMrs Melina KLEANTHIDOU-LEENHOUTS not employed NetherlandsMs Charlotte KOOT Leiden University, PhD Student NetherlandsMs Aneta KORCZYC Radioactive Waste Management Plant PolandMs Kanerva KUISMA Posiva Oy FinlandMs Saida LAAROUCHI ENGSTROM SKB SwedenMr Robert LANGMUIR Europe Analytica BelgiumMr Geert LAUWEN vzw STORA BelgiumMs Charlotte LILIEMARK Oskarshamn municipality SwedenMr Grégoire LITS University of Louvain BelgiumMr Pierre Yves LOCHET Electricité de France – Nuclear Fuel Division FranceMs Fiona MARSHALL UNECE INTMs Meritxell MARTELL UAB SpainMr Philip MATTHEWS NuLeAF (Nuclear Legacy Advisory Forum) United KingdomMs Melanie MBAH Karlsruhe Institute of Technology (KIT) GermanyMs Irena MELE IAEA INTMr Carlo MEYNANTS vzw STORA BelgiumDr Emma ter MORS Leiden University NetherlandsMr Sergio OLIVERO SITI ItalyMs Céline PAROTTE University of Liège, SPIRAL BelgiumMr Rolf PERSSON Oskarshamn municipality SwedenMr Claudio PESCATORE OECD-NEA INTMs Melanie PROVOOST TRARII NetherlandsMr Dirk SCHEER University Stuttgart GermanyMr Philipp SENN Nagra SwitzerlandMrs Heidi Sjølin SJOELIN THOMSEN Dansk Dekommissionering DenmarkMr Richard SMITH NuLeAF (Nuclear Legacy Advisory Forum) United KingdomMs Maria STERGIOPOULOU European Commission EUMr Johan SWAHN Nuclear Transparency Watch INTMr Wojciech SWIDNICKI RadWaste Management Plant "ZUOP" PolandMr Christian TAILLEBOIS EDF France Mr Gert-Jan VAN DER PANNE Triarii BV NetherlandsMr A.H. M. (Arnoud) VAN WAES Rathenau Instituut NetherlandsMs Marlies VERHAEGEN University of Antwerp BelgiumMr Mariano VILA D'ABADAL GMF SpainMs Liesbeth VOEST Ministry of Economic affairs NetherlandsMr Ulrik VON ESTORFF European Commission EUMs Asta VON OPPEN NGO Gorleben GermanyMr Andreas VON SCHMALENSEE Swedish Radiation Safety Authority SwedenMs Daniela WAGNER DAtF (German Nuclear Forum) GermanyMs Johanna YNGVE TORNQVIST Östhammar municipality SwedenMr Samuel YOUNG Europe Analytica BelgiumMrs Dagmar ZEMANOVÁ Nuclear Regulatory Authority Slovakia
1st Open Seminar Amsterdam, 23 Oct 2014
E-TRACK and its activity on Radioactive Waste Management Ulrik VON ESTORFF Gianluca FERRARO
www.jrc.ec.europa.eu
Serving society Stimulating innovation Supporting legislation
Open S e m i n a r 2014 Ulrik von Estorff Gianluca Ferraro
2 29 October 2014
Welcome
E-TRACK Energy – TRAnsparency Centre of Knowledge
E-TRACK
• A joint initiative between DG ENER and JRC
• A knowledge centre
• Promoting public participation in energy policy implementation
• A reliable source of information
• Collection and dissemination of knowledge and experiences in the EU
• Projects on public participation in multiple energy sources
3
E-TRACK
4
E-TRACK
Actions needed
• Collecting the existing information
• Organization and simplification for the general public ("Complexity reduction")
• Connecting the actors ("An interacting RWM community")
• Sharing knowledge
• Provision of practical examples of implementation
• Knowledge dissemination and active communication
5
E-TRACK / RWM
6
E-TRACK / RWM
Secretariat
• Joint Research Centre
• Management and coordination
7
Ulrik VON ESTORFF
Project leader
Gianluca FERRARO
Project officer
Maria STERGIOPOULOU
Project assistant
Cesar CHENEL RAMOS
Web content
manager
Aris GIACHNIS
Webmaster
E-TRACK / RWM
Stakeholders Network
• National/subnational authorities and agencies
• Civil society (municipalities, NGOs)
• Nuclear industry
8
E-TRACK / RWM
Advisory Group (AG)
• General guidance
• It mirrors the whole network's milieus
• AG meetings twice a year
9
E-TRACK / RWM
10 29 October 2014
E-TRACK / RWM
Last Name First Name Organization Sector Country
AdvisorsAdams Richard EESC International Organizations *EUCharleton Daphné FORATOM Industry *EUFarin Sébastien ANDRA WMO FranceLaârouchi Engström Saida SKB WMO SwedenSwahn Johan NTW NGO *EUMartell Meritxell UAB Academia SpainMele Irena IAEA International Organizations *IOMinon Jean-Paul ONDRAF/NIRAS WMO BelgiumMolina Mariano ENRESA WMO SpainPescatore Claudio OECD-NEA International Organizations *IOSpangenberg Jacob ENWD Civil society *EUTaillebois Christian EDF Industry FranceVajdova Zdenka Academy of Science Academia Czech RepublicVila d'Abadal Mariano GMF Civil society *EU
Partenered DGsBoteanu Paula DG ENER European Commission *EUPtackova Katerina DG RTD European Commission *EU
11 29 October 2014
COLLECT Information
CONNECT Actors
SHARE Knowledge
Overview on actions
• Stakeholders map
• DB of actors and participation practices
12
Questionnaire Purpose E-TRACK objectives
1 Practice of public participation (summary – link – keywords)
• DB of practices COLLECT Information
2
Mission of the organisation • DB of actors CONNECT Actors
3 Open relevant questions • List of relevant questions SHARE Knowledge
4 Accord to be in the Stakeholders Network • Network building
Overview on actions
13 29 October 2014
Overview on actions
• Website
14
Website
15
Website
16
Website
17
Website
• Papers
• Articles
18
Overview on actions
• Lessons learnt from EURATOM projects (a synthesis of principles)
• Collection of initiatives of public participation in RWM in the EU • Overview per country • Database of practices per organization • Meetings with municipalities GMF/ENWD
• Annual Report 2014 (January 2015)
• Second annual Open Seminar (Autumn 2015)
19
Overview on actions
20 29 October 2014
1st Open Seminar Amsterdam, 23 Oct 2014
Public participation in environmental decision-making Fiona MARSHALL
Ensuring effective public participation in decision-making on radioactive
waste management – the Aarhus way
1. Quick overview of the Aarhus Convention and its public participation requirements in the context of radioactive waste management
2. Some points of particular relevance for radioactive waste management
3. Tools to assist officials in ensuring effective public participation
1. Quick overview of the Aarhus Convention and its public participation requirements Some basic facts and figures: Full name: Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters As full name suggests, three interlinking “pillars”. Adopted in 1998, in Danish city of Aarhus. Entered into force on 30 October 2001. Currently has 47 Parties from across the UNECE region. Open globally. All EU Member States plus the EU itself are parties.
What is subject to public participation under the Convention?
Decisions on specific activities that may have
a significant effect on the environment – article 6 and annex I
Plans, programmes and policies relating to
the environment – article 7 Preparation of executive regulations and/or
generally applicable legally binding normative instruments that may have a significant effect on the environment– article 8
This means: Specific activities on radioactive waste
management (RWM). Plans, programmes and policies relating to
RWM. Legislation and other generally applicable
legally binding rules relating to RWM.
are all subject to the requirements of the Aarhus Convention.
Rights are granted to the public or public concerned: Public = one or more natural or legal persons, and in accordance with national legislation or practice, their associations, organizations and groups. Public concerned = the public affected or likely to be affected by, or having an interest in, the environmental decision-making; NGOs promoting environmental protection and meeting any requirements under national law deemed to have an interest.
Rights are granted to all persons irrespective of citizenship, residence or domicile (ie apply also across borders).
Which specific RWM activities are subject to article 6?
Installations designed: For the production or enrichment of nuclear fuel; For the processing of irradiated nuclear fuel or high-
level radioactive waste; For the final disposal of irradiated nuclear fuel; Solely for the final disposal of radioactive waste; Solely for the storage (planned for more than 10 years)
of irradiated nuclear fuels or radioactive waste in a different site than the production site (article 6(1)(a) and annex I, para. 1)
Any other RWM activity which may have a significant effect on the environment (article 6(1)(b))
Decisions on specific RWM activities - what does article 6 of the Aarhus Convention require?
1. Early, adequate and effective notice ↓ 2. Reasonable time-frames when all options are open ↓ 3. Access to all relevant information ↓ 4. Public entitled to comment/be heard ↓ 5. Due account to be taken of public participation
↓ 6. Prompt notice of decision ↓ 7. If operating conditions are updated or reconsidered, repeat as appropriate
Public to be promptly informed of the decision. Text of the decision shall be made accessible, along with reasons and considerations on which it is based
If conditions of activity are updated, the above requirements shall be applied mutatis mutandis and where appropriate
Early notice of the environmental decision-making procedure, in an adequate, timely and effective manner of, inter alia: • The proposed activity • Nature of possible decisions • Public authority responsible for making
the decision • The public participation procedure
envisaged (including timeframes and opportunities to participate)
Reasonable time-frames, allowing sufficient time for informing the public and for the public to prepare and participate effectively in the decision-making. Early public participation, when all options are open and effective public participation can take place
Public entitled to submit any comments, information, analyses or opinions it considers relevant to the proposed activity, in writing or, as appropriate at a public hearing or enquiry
Access to all information relevant to the decision-making, free of charge and as soon as it becomes available.
Parties shall ensure due account is taken of the outcome of the public participation
Plans, programmes and policies relating to RWM – what does article 7 require?
Plans and programmes: Practical and/or other provisions for the public to participate
during the the preparation of plans and programmes relating to the environment;
Within a transparent and fair framework; The necessary information must be provided to the public; Reasonable timeframes for the public to be informed, to
prepare and to participate effectively; Early public participation when all options are open and
effective public participation can take place; Due account to be taken of the outcome of the public
participation.
Policies Each Party shall endeavour to provide opportunities for
public participation in the preparation of policies related to the environment.
Preparation of executive regulations and other generally applicable legal rules relating to RWM – what does article 8 require?
Each Party must “strive to promote” effective public participation in the
preparation of executive regulations and other legally binding rules that may have a significant effect on the environment;
While options are still open;
Time-frames sufficient for effective participation should be fixed;
Draft rules should be published or otherwise made publicly available;
The public should be given the opportunity to comment, directly or through representative bodies;
The results of public participation should be taken into account as far as possible.
2. Some points of particular relevance for RWM Early public participation when all options are still open
Includes “zero option” of not engaging in activity at all.
Identification of the public concerned Includes not only public that may be affected on day-to-day basis, but also in
case of beyond design accident. Includes foreign public.
Access to all information relevant to the decision-making.
Any exceptions to be interpreted in a restrictive way, taking into account the public interest served by disclosure and taking into account whether the information requested relates to emissions into the environment.
Presumption that entire EIA will be made available to the public.
Obligation to take due account of the outcome of public participation. See Maastrict Recommendations on Promoting Effective Public Participation
in Decision-making in Environmental Matters (see slide 14)
Relevant findings of the Aarhus Convention Compliance Committee: ACCC/C/2009/41 (Slovakia)
Concerned, inter alia, the obligation to ensure early and effective public participation when all options are still open and when reconsidering/updating a nuclear permit’s operating conditions.
ACCC/C/2010/51 (Romania) Concerned, inter alia, the obligation to ensure sufficient time for the public to prepare and to
participate effectively in decision-making on the draft national energy strategy.
Communications currently under consideration concerning public participation in nuclear sector: ACCC/C/2012/71 (Czech Republic)
Concerns, inter alia, the obligations of a Party to ensure the effective public participation of the foreign public when deciding to permit a nuclear activity.
ACCC/C/2013/89 (Slovakia) Concerns, inter alia, the obligation of a Party to provide access to all information relevant to the
decision-making to permit a nuclear activity.
ACCC/C/2013/91 (United Kingdom) Concerns, inter alia, the obligations of a Party to ensure the effective public participation of the
public of another Party when deciding to permit a nuclear activity. ACCC/C/2013/92 (Germany)
Concerns, inter alia, the obligations of a Party whose public consider they are affected by a decision made by another Party to permit a nuclear activity.
3. Tools to assist officials in ensuring effective public participation
Aarhus Convention Implementation Guide
Maastricht Recommendations on Promoting Effective Public Participation in Decision-making in Environmental Matters
Relevant findings of the Aarhus Convention Compliance Committee
Task Force on Public Participation in Decision-making
Aarhus Convention Implementation Guide Second edition June 2014 Interactive electronic version available online at
http://www.unece.org/env/pp/implementation_guide.html French and Russian versions forthcoming
Maastricht Recommendations on Promoting Effective Public
Participation in Decision-making in Environmental Matters May 2014 Prepared through consultative two year process led by Task Force
on Public Participation in Decision-making English version available online at
http://www.unece.org/fileadmin/DAM/env/pp/mop5/Documents/Category_II_documents/ece.mp.pp.2014.8.eng_adv_edited_copy_01.pdf
French and Russian versions forthcoming
Relevant findings of the Aarhus Convention Compliance Committee All findings (and related documentation) available at
http://www.unece.org/env/pp/pubcom.html All findings available in English, French and Russian.
Task Force on Public Participation in Decision-making Focuses on issues identified by Parties and stakeholders
to be of particular high priority Open forum for Parties, other States, experts, academics, NGOs,
international organizations and other stakeholders to exchange experiences regarding challenges and good practices to implement the Convention’s provisions on public participation
Next meeting Geneva, 23-24 February 2015 – all welcome! For more information, see http://www.unece.org/env/pp/ppdm.html
Thank you!
For further information:
Website : http://www.unece.org/env/pp/welcome.html
Email: [email protected]
1st Open Seminar Amsterdam, 23 Oct 2014
High-Level Waste and the experience of Olkiluoto Harri HIITIÖ
FACTS OF EURAJOKI MUNICIPALITY • 6000 inhabitants • 53% works in industry, 41% in services and 6% in agriculture • State takes care of income distribution, municipalities of public services • 60% of costs to helthcare and social services, 20% to education and 12% to
infratructure • Municipalities have independent right to taxation • 78% of income from taxation, 14% from state and 8% from payments • Two power plant units in operation, one under construction, one under
planning • First power plant unit in operation 1979 • Interim storage for spent nuclear fuel, operating waste and decomissioning
and final disposal for spent fuel in operation 2020
40 YEARS JOURNEY 1978 Investigations for Geological sollution begins 1983 Government decided the schedule for final disposal Site investigations Site selection 2001 Parliament ratified the goverments positive decision Above-ground investigations in Onkalo 2009 Posivas capacity to apply for a construction lisence 2012 Construction licence Site construction 2018 Operation licence Test runs and comissioning 2020 Final disposal begins
ESSENTIAL FOR MUNCIPALITY • We have to take care of our own nuclear waste (fairness and responsibility) • No deed to delay final disposal with out important reason • Retrievability option, but with out safety risks • Effects in the future must not go over nowadays limits • Long term political commitment (several strategic decisions-in-principle) • Only safe final disposal is feasible • Sollutions have to be todays tecnology • Roles and responsibilities have to be clear • Up-to-date requirements and control over hole cycle • STUK verifyes suitability of site • STUK makes preparations, nominates and overlooks safety requirements • STUKs independence of subscriber, suplier and political decision making • Discipline on agreed issues
DECISION PROCEDURE EIA-LAW NUCLEAR ENERGY ACT Environmental programme Application for the decision-in-principle - announcment -general hearing -public opinions - public opinions and statements -ministrys statement - STUKs statement about safety Assessment report - muncipalitys statement (right of veto) -announcment - decision-in-principle (government) -public opinions - parliament ratification -ministrys statement Construction licence (government) Licence for each building (muncipality) Operating licence (government)
DECISION IN PRINCIPLE • Political decision
• Key issue is overall intrest of siciety
• Necessity of nuclear facility concerning energymaintenance • Site suitability and enviromental effects
• STUKs preliminary safety assessments • Final disposal facility = nuclear facility • Decisions-in-principle 2001 (OL1-2, LO1-2) 2002 (OL3) 2008 (OL4) 2009 (LO3) appication no decision • Total 12000 tU
CONSTRUCTION LICENCE • Verifyes qualifications to build safe nuclear facility • Licence to build deposition tunnels and encapculation plant • Not licence to handle or dispose spent fuel
• NEA specifyes content
• Statements and hearings according to NEA
• STUKs safety assessment is essential
• It can include reservations • Posivas capacity to apply for a construction licence is assessed 2009 • YEA 32§:n Reports and surveys for application according NEA 32§ 2012
OPERATING LICENCE • Licence to handle spent fuel and begin final disposal • Requirement to use safe nuclear facility • Safety ensurance and total time table • Licence official ministry, admits government • STUKs safety assessment is crucial • Reservations, for examble temporary assessment of safety
ACCEPTABILITY • Tvo:s and Posiva:s main policy is unconditional transparency which has
developed necessary confidence • Municipal cooperation committee since 1970 • Cooperation group of Eurajoki municipality, TVO and Posiva since 1995 • Seminars and public info sessions at the site • Visitor Centre (20 000 visitors every year) • Official information and public hearings organized by Ministry of
Employment and Economy, Radiation and Nuclear Safety Authority and Eurajoki municipality
• We relay on officials and authorities • All waste handling has been taken care of • Export or import of spent nuclear fuel is not allowed according legislation • Continuous improvement, new rulings after first licence
WELFARE • TVO and Posiva pays real estate taxes • Steady income, easy to make lonstanding plans • Employees and workers pay income taxes • Business opportunities for local companies • New jobs, a lot of local people works at the site • Cooperation with Posiva concernig Vuojoki mansion, economical benefit
straight away site selection
1st Open Seminar Amsterdam, 23 Oct 2014
Changes in RWM policy. The participation turn in Sweden Johanna YNGVE TÖRNQVIST
1976-today Nuclear waste and the municipality
Östhammar municipality Johanna Yngve Törnqvist
The 1970’s
• Nuclear waste – a burden • Governmental study – the AKA investigation 1976
– All nuclear waste should be stored in the bedrock – Preferable if all types of radioactive waste is stored at
the same site – Preferable if the site allready have nuclear facilities
• Forsmark proposed site: -Already a nuclear site -Good infrastructure -”Good enough” bedrock
1982-83
• Application to build SFR 1982 – Swedish referendum on
nuclear power – Public opinion in the
Östhammar area • Decision over SFR
– Municipal VETO – 1982 – a Swedish election
year
1995
• Question to the municipality – ”can you accept pre-studies to build a final storage for spent nuclear fuel?”
• Changed legislation – New atomic energy act in 1984 – Building act ceased in 1987 >>> municipality veto
moved to the environmental code – New environmental legislation, changes made from 1984
to 1996, ceased in 1998 >>> the environmental code – In 1995 municipalities where SKB are investigating sites
for a final storage or are planning to build a final storage for any type of radioactive waste are able to get funding for their work with the question from the nuclear waste fund
Funding for the municipality’s work
• Given the municipality the opportunity to work with the issue • Municipal organization
Municipal assembly
Municipal executive board
Executive Board Sub-Committee
Safety Committee EIA-Committee Consultative
Committee
Consultative Sub-Committee
Administration
Statements
The dialogue tour
Keys to ”success”
• For us a trustworthy process is one of the most important things: – The municipality’s participation is voluntarily which
means that we have the right to say no at any time during the process and will finally be asked by the national government if we can accept the establishment or not,
– knowledge and awareness of the effects that a final storage located in the municipality could have
– openness and transparency of the process – secure financing by the nuclear waste fund – clearly defined roles for all actors involved
The future…
• Application to build final storage for spent nuclear fuel – ongoing process since 2011
• Waiting for application to expand SFR with a final storage for low and intermediate demolition waste
The expansion of SFR - a guiding process for how a possible extension of final disposal of spent nuclear fuel could be handled
1st Open Seminar Amsterdam, 23 Oct 2014
A case from Low- and Intermediate-Level Waste Sébastien FARIN
The role of public part icipat ion in radioact ive waste management
A case from Low- and intermediate-Level Waste
E-Track – First Open Seminar
Amsterdam – 23rd october 2014
2 DICOD/ 14-0253
Andra’s sites
3 DICOD/ 14-0253
Andra sites
Manche disposal facilit y Aube disposal facilit y Indust rial facility for grouping, storage and disposal (Cires)
4 DICOD/ 14-0253
Andra sites
Manche disposal facilit y Aube disposal facilit y Indust rial facility for grouping, storage and disposal (Cires)
5
Public part icipat ion
During the site select ion process: Local elected representat ives, with a st rong support of the nat ional level Project owner Sit ing p rocess and Environm enta l in teg ra t ion of the facility Concep t ion of the facility, when it ’s p oss ib le In teg ra t ion of the p ro ject in the te rritory
During the op e ra t ion o f the facility and a fte r its closure :
Loca l In form at ion Com m it tee Loca l e lected rep resen ta t ives Pro ject owner Vis it s and op en house d ays , to crea te a rea l d ia log ue Environm enta l su rveys Mem ory keep ing (working g roup s )
Sites se lect ion in France
In the backyard of an exist ing facility Manche disposal facility (1960’)
Technical approach as a basis « No dialog approach » for a deep disposal facility(1980’) Strong support of local elected off icials and of nat ional representat ives (1980’)
Step by step approach as a basis Cires implantat ion « local mayors only » (2008) Cigéo project Low-level long-lived waste project
6 DICOD/ 14-0253
1st Open Seminar Amsterdam, 23 Oct 2014
Public participation: lessons from academia Dirk SCHEER
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 1 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Dirk Scheer & Wilfried Konrad (IÖW) 1
INTERNATIONAL SUMMER ACADEMY
Public Participation: Lessons from academia
Dirk Scheer Research Center for Interdisciplinary Risk and Innovation Studies (ZIRIUS) University Stuttgart
E-TRACK Open Seminar
– 24. October 2014 –
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 2 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Basics
2
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 3 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam 3
Basics in risk & acceptance reserach
– 1: human behaviour:
• is based on perception – not on facts – 2: risk perception ≠ expert knowledge
• voluntariness, controllability, dread, familiarity etc. – vs. – scientific facts
– 3: external technology: crucial role of risk-benefit assessment
• relevant factors: trust, values/visions, cost-benefit distribution, risk profile, analogues,
– 4: social conflicts are based on dissent
• disagreement on assessing a topic („NORMAL CASE“)
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 4 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam 4
Technology acceptance factors
Technology acceptance
Risk - Benefit considerations
Risks Benefits Knowledge
Risk profile
Trust in regulators/operators Technology alternatives
Distribution of costs/benefits
Values & visions
Individual risk type
Public perception & discourse
Frequency distribution of preferences and attitudes
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 5 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam 5
Carbon Capture & Storage: Perception & Conflicts
Acceptance Factor Results of studies Leads to .. Knowledge Very limited Cognitive conflicts
Risk Profiling High uncertainty & ambiguity perception Interpretative conflicts
Trust in regulators Limited Intentional conflicts
Equity issues Perceived as important Distributional conflicts
Alternative solutions ..available?
Many think yes Normative conflicts
Associations with… Nuclear waste disposal Affective conflicts
Acceptance of CSS an on-going challenge
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 6 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Conceptualizing Participation
6
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 7 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
A trend towards more participation: why?
• Conflict of interest between those who benefit and those who bear the risks. Why should risk-taker do this?
• Expert disagreement/dilemma becomes useless in mediation since every expert focuses on what he/she considers useful
• Discrepancy between risks calculated by specialists and subjectively perceived risk by the public leading to public mistrust
• People feel over-governed, thus defending themselves against everything they believe is being forced upon them
• Desire to participate in decision-making processes increases in line with education & economic affluence of the individuals
7
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 8 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Potentials & added-values of participation
• Enhancement of knowledge base (learning from experience of the affected)
• Information on distribution of preferences and values among the affected public
• Instrument for fair-minded bargaining process on resource distribution
• Battle of arguments on normative secured collective decisions
• Instrument for arranging and designing one‘s own environment
8
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 9 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
What can we expect from participation?
• Focusing on „real“ conflicts instead of centering on „sham“ conflicts
• Opportunities for agreement even if there is a mix of knowledge, interests, preferences & judgments
• Enabling respect & understanding of contrary and opposed positions
• Potential for creatively exploring new options and recommendations for action
• Possibilities to find consensus and compromise • Enhancing acceptance and legitimacy of collective
binding decisions • Opportunity to increase longterm trust in the political
system
9
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 10 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Meeting expectations? …well! The 4 concepts of participation –I-
10
Concept Main objective Rationale
Functionalist
To improve quality of decision output
Representation of all knowledge carriers; integration of systematic, experiential and local knowledge
Neo-liberal
To represent all values and preferences in proportion to their share in the affected population
Informed consent of the affected population; Pareto-rationality plus Caldor-Hicks methods (win–win solutions)
knowledge integration
bargaining
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 11 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Concept Main objective Rationale
Deliberative To debate the criteria of truth, normative validity and truthfulness
Inclusion of relevant arguments, reaching consensus through argumentation
Emancipatory
To empower less privileged groups and individuals
Strengthening the resources of those who suffer most from environmental degradation
Meeting expectations? …well! The 6 concepts of participation –II-
11
education & inclusion
arguing
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 12 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Implementing participation
12
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 13 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Crucial Questions for Participation
• Inclusion – Who: stakeholders, scientists, public(s) – What: options, policies, scenarios, frames, preferences – Scope: multi-level governance (vertical and horizontal) – Scale: space, time period, future generations
• Closure – What counts: acceptable evidence – What is more convincing: competition of arguments – What option is selected: decision making rule (consensus,
compromise, voting)
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 14 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Candidates for Participation Models
• Organized stakeholders – Hearing – Round Tables (Forum, Dialogue Processes) – Negotiated Rulemaking – Mediation and Alternate Conflict Resolution
• General public
– Ombudsperson – Public Hearings – Citizen Advisory Committees – Citizen Forum, Planning Cells, Citizen Juries – Consensus Conferences (Danish Model)
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 15 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Need for different management strategies
• Dealing with routine, mundane risks: – internal dialogue sufficient
• Dealing with complex and sophisticated risks (high degree of modeling necessary): – emphasis on analytic component
• Dealing with highly uncertain risks (high degree of second order uncertainty): – emphasis on link between analysis and deliberation
• Dealing with highly controversial risks (high degree of ambiguity): – emphasis on deliberative component
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 16 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Application to participation –I-
• For routine management, communication should include: – Information on the process of environmental management – Information on routine management actions – If necessary, a hot-line for questions and observations
• For highly complex topics, communication and
deliberation should include: – All of the above – Discourse among experts on ranges of acceptable evidence – Additional effort for collecting feedback
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 17 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Application to participation –II-
• For highly uncertain interventions, communication and deliberation should include – All of the above – Involvement of major stakeholders – Shift towards resilience approaches – Possibly, public hearings
• For highly ambiguous topics, communication and
deliberation should include – All of the above – Involvement of all parties affected by the decision
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 18 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Complexity
Epistemic Use experts to find valid, reliable and relevant knowledge about the risk
Uncertainty
Reflective Involve all affected stakeholders to collectively decide best way forward
Ambiguity
Participative Include all actors so as to expose, accept, discuss and resolve differences
Simple
Instrumental Find the most cost-effective way to make the risk acceptable or tolerable
Agency Staff
Dominant risk characteristic
Type of participation
Actors
Ladder of stakeholder involvment
Agency Staff Agency Staff Agency Staff
Scientists/ Researchers
Affected stakeholders
« Civil society »
Scientists/ Researchers
Scientists/ Researchers
Affected stakeholders
As the level of knowledge changes, so also will the type of participation need to change
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 19 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Evaluating participation
19
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 20 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
US National Research Council (2008)
− Overview on meta-studies in US and Europe − All located in the field of environment and infrastructre − High success rate: 70-85%
Success factors
− Sufficient ressources − Clear „commitment“ of contracting body − Constructive attitude among the participants − High transperency, but low media involvement − Adaptation of participation formats to the problem
Evaluation studies –I-
20
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 21 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Dialogik/Universität Stuttgart: Goldschmidt u.a. 2008; 2014 − Four European deliberative projects with more than 1200
participants − Combination of national & international formats − Very high subjective satisfaction among participants (> 87%)
Success factors
− Fairness: ++ − Competence: + − Transparency: + (o) − Efficiency: o − Effectivity: o (+) − Legitimacy: +
Evaluation studies –II-
21
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 22 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Nachgewiesene Erfolgskriterien
Willingness and adequate framework conditions for mutual learning processes
Clear mandate and sufficient, but limited time line Open and neutral moderator Transperancy of participation processes vis-à-vis outsiders Potentials for new and normative agreed win-win solutions Integration into legal decision-making processes Feedbacking the „decisions“ to all participants
22
Proven success factors
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 23 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
no summary – but a final note
23
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 24 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Deliberative processes for involving stakeholders and the general public are
instruments of art and science:
They require a solid theoretical knowledge, a personal propensity to engage in group
interactions, and lots of practical experience
Final note
6th international Conference of ESEE, Lisbon, 14-17 June 2005 Towards Environmental Governance: The Case of IPP 25 Participation: Lessons learnt « E-Track Seminar » 24. Oct. 2014 / Amsterdam
Konrad / Scheer (IÖW) 25
INTERNATIONAL SUMMER ACADEMY
Thank you:
Email: [email protected] Tel: ++49 (0)6221-6733986
Dirk Scheer University Stuttgart
1st Open Seminar Amsterdam, 23 Oct 2014
Public participation and dialogue beyond nuclear (1) Melanie PROVOOST
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
PUBLIC PARTICIPATION AND ITS CONSEQUENCES
E-TRACK – 23 October 2014 Melanie Provoost
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
R&Dialogue Creating a dialogue on how to achieve a low-carbon society
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
R&Dialogue Objective
• Organise 10 dialogues between R&D organisations, civil society organisations, industries, governments and communities in 10 European countries
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
WO WE ARE A consortium of 17 partners in the field of energy in 10 European countries
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
PRESENTATION OVERVIEW
Focus on the role of dialogue in policy and project implementation ▪ The case study CCS Barendrecht and its
consequences for Europe ▪ Dialogue on wind power and different
attitudes Main message: Having a dialogue asks for an open and flexible attitude towards the outcomes. The vision needs to be clear and the process should allow change.
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
Implementation of a project CCS Barendrecht
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
CCS BARENDRECHT
▪ Top-down decision-making process and implementation process
▪ This process caused local and political unrest
▪ Information meetings / town hall meetings were held to educate and explain the project
▪ Dialogue in the form of protests and opposed positions
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
CCS BARENDRECHT
▪ Dialogue on policy measure CCS inexistent with public ▪ Political and legal framework for project implementation does not
require dialogue with local authorities and public
▪ Dialogue in an early stage could have prevented protests ▪ The public is very powerful in a democracy ▪ Deadlock in dialogue and policy implementation of CCS
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
An ongoing dialogue On wind power
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
ONSHORE AND OFFSHORE WIND POWER
The Netherlands: ▪ SER Energy Agreement (2013): 4450 MW offshore in 2023 and 6000 MW
onshore in 2020, important factor to reach 16% RES in 2023. ▪ Government appointed locations with lower authorities (Provinces)
responsible for the implementation. Both the technology (wind power) and the locations were not a focal point of dialogue / open process with the public.
▪ Leading to public protests up to the UN
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
ONSHORE AND OFFSHORE WIND POWER
Germany: ▪ Renewable Energy Act (2000) introducing feed-in tariff (set rate for kWh of
renewable power over a period of 20 years) stimulating renewable developments in onshore wind (2011: feed-in tariff wind power < €0.09 per kWh). Offshore wind targets set on 20 GW by 2020.
▪ To increase acceptance focus on community ownership and on Bioenergy regions: promoting economic development of rural areas.
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
DIFFERENT DECISION-MAKING APPROACHES
The Netherlands ▪ Top-down approach ▪ Government and stakeholders decide
on how to reach set targets ▪ Shared responsibility of local authorities ▪ Project developers apply at responsible
authority ▪ Consultation / participation mandatory
at implementation stage – e.g. at Council of State
Germany ▪ Facilitate bottom-up initiatives ▪ Federal Government sets the legal framework
and targets in e.g. the Renewable Energy Act ▪ Local or regional authorities decide on location
and implementation ▪ Project developers hand-in application at local
level ▪ Consultation / participation mandatory in
planning and decision-making process
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
ROLE OF DIALOGUE
But: ▪ Dialogue has consequences for the outcomes / results ▪ Dialogue is risky ▪ Dialogue is a part of a larger process
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
ROLE OF DIALOGUE Dialogue brings uncertainties and risks How to deal with this?
trust
Project developer
Public authorities at different
levels
Local communities
Sector itself
Financers / investors
Public
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
If you want an open and flexible dialogue The vision needs to be clear and the process should allow change
This project has received funding from the European Union’s Seventh Framework Programme for research, technological development and demonstration under grant agreement no 288980 The views and opinions expressed in this publication reflect the authors' view and the European Union is not liable for any use that may be made of the information contained therein.
THANK YOU [email protected]
1st Open Seminar Amsterdam, 23 Oct 2014
Public participation and dialogue beyond nuclear (2) Sergio OLIVERO
1 Amsterdam, October 23th, 2014
Public participation and dialogue beyond nuclear
Experience gained in EC-funded Projects with reference to the context of critical infrastructures
The role of public participation in radioactive waste management
and other sectors -Lessons learnt from research and practice-
Sergio Olivero
2 Amsterdam, October 23th , 2014
ICT technologies are today leading to a more participatory approach, where people need to trust
security bodies, building confidence through awareness.
SECURITY
Security
The OBSOLETE APPROACH: “someone else takes care”
WHAT IS THE CORRECTS “INFORMATION SUPPLY
CHAIN”?
WHAT IS COMMUNICATION IN SECURITY DOMAIN?
WHO WILL INFORM WHOM ACCORDING TO WHAT LANGUAGES
AND PROTOCOLS?
3 Amsterdam, October 23th , 2014
• Awareness raising starts from a selected group of persons (i.e. voluntary firemen), who are directly involved in rescuing people and/or performing exercises.
• The security and safety messages are therefore conveyed through personal commitment.
• The voluntaries become trusted people, who can more easily explain “what happens”, including uncomfortable issues.
Case 1
Involvement of citizens starting from people who
volunteer to serve in initiatives to cope with
natural disasters.
1
• To create capacities able to ensure CITIZENS’ SECURITY against threats such as natural disasters, accidents, human mistakes,etc.
• Active involvement of citizens during crisis events to maximize the potential of emergency response measures.
PICRIT Project (INTERREG-ALCOTRA, I-F Border
Protection of Critical Infrastructures, 2011-2013)
4 Amsterdam, October 23th , 2014
Map data sources available on the territory
Platform for cross-border communication
Training tools and cooperation Cross-border exercise
PICRIT Project
5 Amsterdam, October 23th , 2014
Case 2 Cascading effects related to interdependencies among
infrastructures: providing useful information at the right points along
service supply chains • In case of a disaster, impacts will propagate according to the so-called “domino
effect”, often causing major damage because of interdependencies among systems. • In order to reduce the magnitude of the impacts, information must be released at
the various points along service supply chains, being aware that every ring of the chains uses his own language and protocols. Unjustified scaremongering must be avoided.
FORTRESS Project (FP7, Foresight tools for responding to cascading effects in a crisis, 2014-2017)
2
• To identify cascading effects by using an analysis of systems and their mutual interconnectivity and (inter-)dependency.
• To bridge the gap between the over-reliance on unstructured information collection on one side and a lack of attention to structural, communication and management elements of cross-border and cascading crisis situations on the other.
6 Amsterdam, October 23th , 2014
Geodatabase
Interdipendencies Dam Simulation
FORTRESS Case Studies
FORTRESS Project
7 Amsterdam, October 23th , 2014
• The choice of a security technology must take into account three main factors: performances, financial cost, and social impact.
• Decision-makers must ensure that the chosen technologies do not trigger any infringement, (e.g. the legal, social, or cultural norms that might be intruded upon by a security measure).
Case 3
Definition of criteria to choose security technologies that are
compliant with the law (e.g. for privacy) and intrinsically acceptable
for the cultural heritage of different persons
• These criteria can be effectively used to write tenders for the acquisition of technology apparatus, avoiding suits and the risk of being forced to withdraw them after their implementation.
SIAM Project (7FP, Security Impact Assessment
Measure, 2011-2014)
3
8 Amsterdam, October 23th , 2014
STEP (Security-Trust-Efficiency-Privacy) metodology Case studies
SIAM Project
9 Amsterdam, October 23th, 2014
Thank you for your attention
Sergio Olivero
Head of Energy & Security Research Area SiTI
Via Pier Carlo Boggio 61 10138 Torino
ITALY
+39 335 12 73 521 [email protected]
www.siti.polito.it
for further information