Upload
mars-mars
View
219
Download
0
Embed Size (px)
Citation preview
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 1/36
Instructors Team Members
Project Supervisor (MSD) :Mr. Najaf Yawar
Director
Project Coordinator (MSD) :Mr. Hassan Raza
EMBA- Program Lead
Project Supervisor ( ORIENT):
Mr. Kashif Shareef Production Manager
Ahmed Waqas1201-EMBA-09
Nuzhat Jahan1214-EMBA-09
Faheem A. Hameed1203-EMBA-09
Farhan Ahmad1204-EMBA-09
Consultancy Project
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 2/36
Table of Contents
EXECUTIVE SUMMARY .......................................................................................................................................................... 3 COMPANY PROFILE .......................................................................................................................................................... 4
V IS ION ..................................................................................................................................................................................... 5 M ISSION .................................................................................................................................................................................. 5
COMPANY M ANAGEMENT ............................................................................................................................................. 5 M IAN MUHAMMAD FAZAL CHAIRMAN O RIE NT GROUP OF COMPANIE S ........................................................... 5 M IAN T ALAT M AHMOOD FAZAL MANAGING D IR EC TOR ........................................................................................... 5 M IAN AHMED FAZAL EXEC UTIVE D IR EC TOR ............................................................................................................... 6 M IAN ZUB AIR FAZAL D IR EC TOR PHOTO D IVISION .................................................................................................... 6 M IAN AB DUL R EHMAN TALAT D IR EC TOR MAR KETING ............................................................................................ 6 MR . HOMAEER W AHEED D IR EC TOR OPER ATIONS ...................................................................................................... 6
MANDATE ................................................................................................................................................................................... 8 DELIVERABLES.......................................................................................................................................................................... 8 FIELD WORK (STARTING POINT) ....................................................................................................................................... 8 CAPACITY LIMITATION ........................................................................................................................................................ 8 REDUCTION OF WASTES ....................................................................................................................................................... 9
MATERIAL WASTE: .................................................................................................................................................................... 9 E NERGY WASTAGES................................................................................................................................................................... 9 TIME STUDY............................................................................................................................................................................... 9
FINAL WORK DIRECTION ..................................................................................................................................................... 9 METHODOLOGY ADOPTED ................................................................................................................................................ 10
ASSEMBLY LINE BALANCING................................................................................................................................................... 11 ERGONOMICS....................................................................................................................................................................... 11 WORK FATIGUE ................................................................................................................................................................. 12 SOLUTION... .......................................................................................................................................................................... 12 USE OF HUMAN BODY.............................................................................................................................................................. 12 ARRANGEMENT OF THE WORK PLACE...................................................................................................................................... 13 DESIGN OF TOOLS AND EQUIPMENT......................................................................................................................................... 13
OPTIMIZATION MODEL ....................................................................................................................................................... 14 WORK MEASUREMENT QUANTIFICATIONS ................................................................................................................. 16 BALANCING THE LINE AND SYNCHRONIZATION ......... ........... .......... ........... .......... ........... .......... .......... ........... .......... 19
BALANCING LINE...................................................................................................................................................................... 19 LINE SYNCHRONIZATION ......................................................................................................................................................... 19
Performance (Testing) loop Capacity............................................................................................... 19 EMPLOYEE MOTIVATION THROUGH INCENTIVE SCHEME FOR PRODUCTIVITY IMPROVEMENT .......... 21 WORK ENVIRONMENT ......................................................................................................................................................... 27
TEMPERATURE ......................................................................................................................................................................... 27 VENTILATION........................................................................................................................................................................... 29 LIGHTING ................................................................................................................................................................................. 30
PREVENTIVE MAINTENANCE ............................................................................................................................................ 32 ADVANTAGE OF PREVENTIVE MAINTENANCE.......................................................................................................................... 32
OBSERVATIONS AND RECOMMENDATIONS:................................................................................................................ 35 REFERENCES ........................................................................................................................................................................... 36
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 3/36
EXECUTIVE SUMMARY
Being student of EMBA in Management science department of GC University, doing a
consultancy project is a mandatory aspect of this program. Students are supposed to
search and work with an organization with whom they can tackle with real life problems. The idea is to give EMBA students a flavor of issues that people in industry
face on day to day basis and learn how to find a solution for them.
Keeping the above idea in mind, we took out consultancy project with OrientElectronics. The task assigned to us was to improve the efficiency of their Air
Conditioner assembly line and identify and reduce any wastes. The project falls into the
category of ―Operations Management‖.
We used the methodology of work study which comprises of two aspects. 1st is Method
Study (simplified work method) and 2nd
is Work Measurement (Standard Operationstime). We gathered and data and quantified the activities performed by the workers on
the assembly line. Once done, we found out there are places at which the line is not
balanced. We gave recommendations for balancing the assembly line. This will not only
increase the output of the Assembly line and Work force line to reduce manpower andcost.
We also calculated the optimum performance of the system without any stress.According to that system was able to generate 90 units per hour. The statistics reflects
that currently they are producing 72 units per hour. We devised an incentive plan for the workers by which each worker will get benefit if the production level rises to
certain limits.
Last we also studied the process of their maintenance teams and figured out lack of
documentation and slow response. We gave certain recommendation that help inimproving the response time. Secondly we worked on preventive maintenance routine
which needed to be carried out so a lot of break down can be avoided before they
happen during the production and cause wastage of time and resources.
We have studied various aspects of Lean Manufacturing at Orient’s assembly plant and
identified various areas where our client can make the significant improvements andenhance the effectiveness of their resources and achieve the optimum output.
In the growing competition of Home Appliance industry, many new entrants are making
their mark, so in order to get the competitive advantage over its competitors, they
should accelerate their efforts to achieve the standard of excellence in operational areasand quality. They should also strengthen and rejuvenate their operations & systems for
the efficient use of the resources for sustainable growth and maintaining their position
of market leader.
Summary
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 4/36
COMPANY PROFILE
Established in Lahore in 1957 with Photo Goods Business, today the Orient Group of
Companies is one of the largest consumer goods companies of Pakistan. In 1975, the
company launched its imports division. With hard work, excellent services, honesty and
strongly integrated business ethics, the imports business grew consistently and resultedin the formation of M/S Orient Enterprises.
In 1983, Orient Enterprises became a private limited company, and established minilabs all across the country. In 1985, Orient Group of Companies began marketing and
distributing various products nationwide. By sheer hard work and diligence, today
Orient enjoys a remarkable reputation throughout the nation.
Today, Orient Group of Companies is the sole distributor of the world’s most renowned brands like Mitsubishi Air Conditioners, Samsung Home Appliances & Samsung
Consumer Electronics. Orient also offers Mitsubishi Electric Mr. Slim air Conditioner,
which is the only 100% Japanese imported brand in Pakistan.
Orient Group of companies has also diversified into manufacturing by assessing
consumer insights & preferential trends. Orient Group of Companies also manufacturesan exclusive range of state of the art products like air conditioners, refrigerators,
microwave ovens water dispensers and vacuum cleaners.
The products are manufactured and assembled at the state of the art establishment at
Multan Road, just 26 kilometers away from the Lahore city centre. It comprises of the
manufacturing plant; corporate and sales offices, warehouses, and assembly line for allits products. The factory not only manufactures all of Orient Group of Companies’
product range, but also assembles Samsung air conditioners, televisions, home theatres
and Mitsubishi air conditioners on location. The Orient Factory is completely
automated and has incorporated a proprietary SAP ERP solution to meet its operationaland functional demands.
Product NaIntroduction
Introduction
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 5/36
The Orient Factory is completely automated and has incorporated a proprietary SAP
ERP solution to meet its operational and functional demands.
Vision Our vision is to be the leading provider of consumer electronics & in Pakistan. We aimto become the number one name in customer care and to deliver our best to the nation.
MissionOrient Group of Companies will achieve its vision
By keeping keen consumers insight
By assessing changing preferential trends to stay ahead of its competitors
By developing a loyal and steady consumer base through unparalleled service andcare
By implementing aggressive sales strategies through heavy promotions
By introducing cutting edge innovations in technology, ultimately improving the
lives of its consumers
COMPANY MANAGEMENT
Mian Muhammad Fazal
Chairman
Orient Group of Companies
Mian Talat Mahmood Fazal Managing Director
Mian Talat Mahmood Fazal is the Managing Director of Orient Group of Companies.
With over 30 years of experience in the consumer electronics business, Mr. Talat
Mahmood Fazal is a strategic thinker with an eye towards the bigger picture. As the
captain of the ship, he has steered Orient Group of companies through the tides of time.
Under his guidance and leadership, The Orient Group of companies has transformed
into one of the largest consumer electronics group in Pakistan.
Introduction
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 6/36
Mian Ahmed Fazal Executive Director Mian Ahmed Fazal is the Executive Director of the Orient Group of Companies. A
target driven mind, Mr. Ahmed Fazal keeps a keen sight towards the current and future
trends, and technological advancements, all the while setting challenging deadlines and
creating a benchmark for excellence that is shaping Orient Group of Companies as one
of the leading names in the business. He is particularly instrumental in automating the
Sales module of Orient Group of Companies with the current state of the art proprietary
ERP (SAP), thus channelizing the sales infrastructure that has efficiently streamlined
the revenue generation for the company.
Mian Zubair F azal Director Photo Division Orient Group of Companies began with the Photo Goods Industry. Even after 50 years,
and many divisions, the photo business remains very near to its core. Mr. Zubair Fazal
oversees the state of the art photographic business of Orient Group of Companies. Now
with the partnership with Samsung electronics, the innovative range of Samsung
photographic appliances are now part of the of the Orient’s family of products , being
managed brilliantly by Mr. Zubair Fazal
.
Mian Abdul Rehman Talat Director Marketing
Coming from the world of Information technology, Mr. Abdul Rehman Talat is arelatively new entrant in the consumer electronics business. However, with a tech savvy
background, this field is right up his alley. No company today can survive without an
integrated marketing strategy, especially using digital media to create user awareness
effectively and Mr. Abdul Rehman’s creative ideas in this regards are paving the way
for the Orient Group of Companies’ b right and shining future.
Mr. Homaeer Waheed Director Operations
Mr. Homaeer Waheed is the backbone of Orient Group of Companies’ ever expandingenterprise. Whether it be tackling administrative matters, managing the human and
technical resources, procurement of the best materials for manufacturing, channelizing
distribution, Mr. Homaeer Waheed has ensured a robust operational infrastructure that
lies at the core of Orient Group of Companies’ well oiled business machine.
IntroductionIntroduction
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 7/36
Mandate & Deliverable
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 8/36
Mandate
Productivity improvement on Air conditioners Assembly Line for Efficiency improvement andProcess improvement through Time Balancing.
Deliverables
To Identify Process Losses on the Assembly Line.
To identify Man and Machine Idle Times.
To identify Material Wastes.
To present Workable Solutions for the Balancing of Assembly Line and improve the overall performance of manpower and enhance the productivity of Resources.
FIELD WORK (STARTING POINT)
We started with visiting the Orient plant and we were appointed on the productivity enhancement of the
Air Conditioner assembly line. We observed all the stepwise processes through which an AC undergoes
to take the form of final product. Orient manufactures Split-type Air Conditioners which are in 2 separate pieces.
1. Indoor Unit
2. Outdoor Unit
Both the units are separately built on 2 different conveyor belts. They have altogether separate mechanism
and process flow. Our 1st task was to identify the system capacity and which process is exactly definingthe system hourly production rate.
Capacity Limitation
In the assembly of the outer unit of AC, there is a loop named as Vacuum loop on which there are 22
stations on which vacuum pumps are mounted. While moving on the assembly line, each unit has to go
through one of those stations so as to vacuum all the air inside the compressor and that later can becharged with the coolant.
Now that vacuum loop serves as the technical limitation of the hourly production that cannot be exceeded
more than a certain limit. The maximum speed that can be used it 15 min/revolution which is a minimumtime in order to essential create a vacuum in the compressor. Any less time will effect the performance of
the system.
Mandate & Deliverables
Reduction of Wastages
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 9/36
Hourly Vacuum Loop Capacity
Standard Time to Vacuum 1 unit 15 Min
No of Stations in the loop 22
No of complete rotations for loop in an Hour 60/15 =4
Total number of units in Hour 22*4=88
Reduction of Wastes
Material Waste:Since these are CKD and SKD unites and all components are in finished forms, so no such wastes are
applicable in case.Incase of any damaged parts, these are replaced by supplier
Energy Wastages
(A) Electricity…… We have observed, during lunch breaks, most of the lights and fans kept running (B) Compressed Gas…….Many connections were found leaking (specific places)
Time Study
We did ―Time study‖ with two aspects;
In order to identify the idle times, we observed work time on each workstation for each unitincluding waiting time and transport time.
In order to study the possibility of reducing the time or manpower on line, we observed theactual time being spent on each unit by each worker.
Final Work Direction
Considering the time frame and recommendation of supervisor of our project, we selected towork on Indoor unit’s assembly line.
Methodology
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 10/36
Methodology Adopted
Fig – I: Relationship between Method Study and Work Measurement
An Assembly line is a form of mass production where components are added in a specific, efficient
order to create a finished product at the end of a line.
The most basic assembly line consists of a simple conveyor belt which carries the products, through a
series of work stations until it is finished.
Henry Ford found this system of moving assembly lines for Mass Production and produced cars quickly
and efficiently; so efficiently that it considerably lowered the cost of assembling the cars.
The development of the assembly line revolutionized manufacturing, and contributed to the substantial
fortunes of several major players in the Industrial Revolution.
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 11/36
Fig – 2: First moving Assembly Line at Ford Motor Company 1914
Assembly Line Balancing
Line Balancing and Work Cell Balancing is an effective tool to increase the output of the Assembly line
and Work Cell line to reduce manpower and cost. Assembly Line Balancing is nothing but the Simple
Line Balancing is the calculation of assigning works to workstation alongside an Assembly Line.
ERGONOMICS
Study the Impact of Fatigue and Optimizing Productivity of an Assembly Line
Abstract — Improving productivity is one of the main concerns of every industry. This report provides theidea how productivity levels changes at different time during normal working hours in apparel industries.
There are many factors which act as obstacles to higher productivity. Unskilled workers, physical fatiguefrom extended working hour without rest, misplacement of worker at workstation, lack of training, lack of knowledge, awareness are few factors related to worker which directly affect the productivity.
Ergonomics
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 12/36
WORK FATIGUE
Fatigue lowers average productivity, measured as output per worker hour, for almost all of the industries.
As the overall daily performance of each worker is not same and the change in their performance defer
from one worker to another worker bottleneck creates in the assembly line.
During the investigation attention is concentrated on how physical fatigue of workers influences the daily
production rate and how to optimize the productivity.
The term "ergonomics" is derived from two Greek words: "ergon," meaning work, and "nomoi," meaning
natural laws. Ergonomists study human capabilities in relationship to work demands.
In recent years, ergonomists have attempted to define postures which minimize unnecessary static
work and reduce the forces acting on the body. We can significantly reduce worker’s fatigue and
strain on muscles if we follow the following ergonomic principles:
SOLUTION
The principles of motion economy can be classified into three groups:
1. Principles related to the use of human body,
2. Principles related to the arrangement of the work place,
3. Principles related to the design of tools and equipment .
Use of Human Body
The two hands should begin motions at the same time. The two hands should not be idle at the same time except during rest periods.
Motions of the arms should be made in opposite and symmetrical directions and should be madesimultaneously
Hand motions should be confined to the lowest classification with which it is possible to perform the
work satisfactorily:
1. Finger motions
2. Wrist motions3. Forearm motions
4. Upper arm motions
5. Shoulder motions
Momentum should be employed to assist the worker whenever possible, and it should be reduced
to a minimum if it must be overcome by muscular effort.
Smooth continuous motions of the hands are preferable to zigzag motions or straight-line motions
involving sudden and sharp changes in direction.
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 13/36
Arrangement of the Work Place
There should be a definite and fixed place for all tools and materials.
Tools, materials, and controls should be located close in and directly in front of the operator. Drop delivers should be used whenever possible.
Materials and tools should be located to permit the best sequence of motions.
Arrange the height of the workplace and chair for alternate sitting and standing, when possible.
Provide a chair of the type and height to permit good posture.
Design of Tools and Equipment
Combine tools whenever possible.
Preposition tools and materials.
Where each finger performs some specific movement, the load should be distributed in accordance
with the inherent capacities of the fingers. For light assembly, a screwdriver handle should be smaller at the bottom.
Momentum should be used to help the worker in doing their task not to increase their task.
Optimization Model
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 14/36
OPTIMIZATION MODEL
It is developed based on the overall daily performance of each worker. Due to the physical fatigue of
worker, performance of worker changes with time and the label of performance of each worker do notremain same.
Assumptions are continuous flow of material through the assembly lines, efficient workers are placed at
bottleneck points where bottleneck point’s workers are placed at less processing time taken operation’s
and can do that operation at its own efficiency, replaced bottleneck point workers have the capability of
reaching the line target at 100% efficiency or more, one workstation can be half, one or a group, there is
no effect on performance due to change in weather, variation in working environment, no effect of fatigue
of data collector in collecting whole day data.
At first by using stop watch, the observed processing time and average processing of each operation has
been obtained. Standard processing time of each operation is considered as factory standard. Then using
average processing time of each operation of each time segment, the performance of individual worker
has been found. Standard processing time of each operation is different. Then workers are assigned
randomly at different workstations without considering their level of performances. Number of workers at
each workstation depends on standard time of the corresponding operations.
Then identify bottleneck points based on more processing time taken operations. The efficient workers are
placed at bottleneck point where less efficient worker occupied by less processing time took operation.
Then again the new bottleneck points are identified and the process is repeated until decreases the
assembly line efficiency as well as increase the processing time at bottleneck points.
The production capacity of each workstation of each time segment has been calculated based on
processing time of bottleneck points. Then excess capacity has to remove by releasing inefficient worker
or increasing capacity or distribute works as well as balancing assembly line.
Un-necessary workers increase the production cost and the workers have no contributions in improving
production capacity. Finally the optimum production capacity, loss due to fatigue, line utilization and line
efficiencies are calculated. In the following figure 1, shows the steps necessary for optimizing
productivity.
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 15/36
Figure 3: Steps for optimizing assembly line productivity
Steps
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 16/36
WORK MEASUREMENT QUANTIFICATIONS
We performed the time measurement of each activity performed by each worker in different times of theday’s i.e. morning, afternoon and evening.
We collected 20 different samples at different timings and different dates and finally took an average of
all the values so as to remove any discrepancies. Following below is the sheet we produced on which we
made further recommendations.
No
Process DescriptionWorker
Name
Readings (seconds)
Comments
1st 2nd 3rd 4th
5thAvg.
time
1
Putting Unit on assembly lineand removing card box from
the unit.
Qaiser 9 6 9 6 8 7.6 This work
can be
done by a
single person2
Getting pallet board from downlane and adjusting it on the top
M. Ishfaq 7 7 13 6 8 8.2
3
Hold unit and rotate it on Z-
axis. Cut the tape with blade.
Put the remote and pack of screws in the box and remove
tape
Shoaib 19 13 24 25 24 21
4
Take off packing material and
put it in box and take the
mounting plate out from the packing and put it on top of
Box and remove tapes
Nasir 12 11 12 13 15 12.6
5
Holding unit box and putting it
on the separate pallet. Remove
plastic cover and put it in box
and remove tape from his side
Khadim
Bhutta19 18 23 16 12 17.6
6
Hold unit, remove top part, putthe drain assembly and air filter
in the box, Unscrew 2 screws.
KaramatAli
20 22 25 16 22 21
7
Hold unit and remove 6 screws
help removing top part of unitM. Naeem 30 16 29 16 16 21.4
Work Measurement Quantificatio
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 17/36
8
Pick the thermo sensor andtake it to separate table where
evaporator placed. Fit the
sensor with evaporator
Ali Nazir 26 18 16 20 25 21
9
Fit blower and remove the
motor cover and pasteassembly card on the box
Amir
Waqas25 23 24 18 21 22.2
10Evaporator Fitting andadjusting it in the unit.
NaeemAhmad
16 15 16 16 12 15
11
Motor fitting into motor cover
and putting /fixing it back in
the unit
Shaukat
Iqbal27 25 28 22 24 25.2
12 Put in 4 screws
Nasir
Mehmood15 14 13 13 10 13
13
Adjusting jig to balance the blower, screw in 3 screws and
put a small side cover
M. Faryaad 19 24 21 15 24 20.6
14
Fit the electrical panel and
adjust the motor wiring
connection as well as LCDconnection
Ishtiaq
Hussain20 19 23 27 18 21.4
15
Fit the drain assembly and fitthe connection of air loover
and adjust LCD panel
Ghulam
Rasool22 18 17 17 14 17.6
16
Adjust cable and connect inearthing wire and screw in 1
screw
Abid 32 27 29 33 30 30.2
Max Value
referencefor line
balancing
17
Connect thermo sensor wireand adjust emergency ss
witch. Also put the electrical
panel cover
Basharat 30 25 25 26 24 26
18
Check the earthing by
clamping unit to computer toverify the short circuit test
Saad Sohail Machine was out of order
19
Clamp power cable and
perform the resting and check
voltage, watt and Amperes
Ahsen 25 27 28 30 25 27
20
Put the top of unit back on the
body and put tape on the sides
to seal
M Shakeel 11 12 20 14 17 14.8
21
Screw in 3 screws and fit the
cover of LCD and electrical panel
Imdaad Ali 15 14 15 16 15 12
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 18/36
22
Put 2 screw clips
1 cover clip1 Air filter
Adeel
Malik 22 16 16 14 16 16.8
23Putting the 3 tapes to seal the body
Javaid Iqbal 20 18 20 20 19 19.4
24 Clean unit with cloth M Bilal 12 18 14 18 18 16
25
Final inspection and note Bar code on the assembly card and
remove assembly card from the
unit
M Usman 13 14 16 15 20 15.6
26
Put the cover sheet back on the
unit and put 2 side packingmaterials
M Iqbal 22 24 23 25 25 23.8
27
Put the wall mounting plate inthe packing and make/rotate
unit vertical and put inside card
box
Tasneem
Nawaz25 25 26 27 25 25.6
28
Tape the plastic cover and putremote control in packing ,
rotate unit vertically and putthe unit in the the box
Shahnawaz 22 20 21 23 24 22
29
Moving pallet to down lane
and moving unit forwards to packing machine
Mohsin Ali 22 13 16 15 12 15.6This work
can be
done by asingle
person30
Rotate box and adjust the striprole machine to put the strip on
box
Ahmad
Freed10 11 12 11 14 11.6
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 19/36
BALANCING THE LINE AND SYNCHRONIZATION
Balancing line
From the above work measurements we identified that there are a total of 30 workers in the line and the
maximum time taken by any activity is 30 Seconds. So in order to balance the line, we have to assign
each worker amount of work that is either equal or close to 30 seconds so all workers work in a balanced
line.
We identified 2 instances in the above table when 2 adjacent workers jointly working less than 30
Seconds and we recommended that the work of those 2 workers can be performed by an individual guy. It
saves 2 resources and line workers reduces from 30 to 28 without affecting any quality or time delays.
Line SynchronizationPerformance (Testing) loop Capacity
Current time set for the 1 complete cycle 20 Min
Number of working Stations in the loop 38
No of Complete rotations in an hour 60/20=3
No. of units that can be handled in 1 Hr 38*3=114
Note: We know that feed for the performance loop is coming from vacuum loop whose maximum
capacity is 80 units/Hr.
Balancing the line
Balancing the line
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 20/36
So we need to reduce the speed to optimize the solution
Proposed time set for the 1 complete cycle 25 Min
Number of Stations in the loop 38
No of Complete rotations in an hour 60/25=2.4
No. of units that can be handled in 1 Hr 40*2.4=91
We can see, even reducing the speed to 25 min, still we can handle 91 units in the performance loop.
The above work measurement table also gives us the optimum speed of work that can be done on the line
if there is no maintenance or unforeseen issues arise.
Below are the calculations for the optimum output for the indoor assembly line.
Max Activity time by a worker in line : 30Sec
Total time to make a unit in line :576 Sec = 600 Sec
600 Sec = 10 Min (Activity time)
We assume (including 10% tolerance) 10 Min for transport and wait time so time to make a
single unit by a single worker: 10 + 10 =20 Min
In 20 min 1 unit is producedIn 1 Hour 3 Units are produced
If Orient have 30 workers in line, they should produce (3*30=90 Units / Hr)
Employee Motivation
Balancing the line
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 21/36
The stats which we got from the hourly production sheet are 72 units / Hr.
So in spite of all the push and efforts of strict supervision, the average amount of hourly production is 72.
So we proposed an incentive model for the workers so as to enhance the production to at least 85 units
/Hr.
EMPLOYEE MOTIVATION THROUGH INCENTIVE SCHEME FOR
PRODUCTIVITY IMPROVEMENT
When employees feel valued and appreciated, they do their best to keep their employers pleased with their work. They will work harder, knowing that they have raises, promotions, days off and other perks, in
their future because of it.
The success of any business depends largely on the motivation of the employees. Human resources are
essential to the prosperity, productivity and performance of any company. Motivation is the key to
creating an environment where optimal performance is possible.
Perhaps the most significant impact of increased employee motivation is that of increased productivity.
This is a central aim when adopting an incentive program. If we can increase employee motivation and
high productivity will follow.
To motivate employees to do their best, they should be motivated through incentives and rewards.
During our visits we observed and also confirmed with the several months production record that the
maximum units produced per hour never exceed from 80 units. We mathematically calculated and logical
assumption is that there is still margin of 6-15% increase in production.
We propose that if company offers additional incentive on each marginal unit produced after 80 units,
they should be given incentive @ Rs. 5, however, in case they are able to deliver production beyond 85-
90 units, they should be given incentive of Rs. 10 on each marginal unit produced.
We have prepared a comparative statement of this incentive scheme, that how much contribution margin
(profits) company is going to make even after paying an incentive payment.
Employee Motivation
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 22/36
Proposed Incentive Scheme to Increase the Productivity of
Split Air conditioners at Orient Factory
Assumed Profit Margin per unit (Rs.) 4,000
Number of worker on indoor line 30
Number of worker on outdoor line 55
Number of Maintenance staff 5
Total Workers 90
Current Production units/hour 80
Current Profit margin per day*(Rs.) 3,520,000
*11 working hours
Proposed Incentive Scheme 1 (If per hour production increses to85 unit)
Minimum Incentive to each worker Rs. 5/hour on every additional
unit produced 5
Improved Production per hour 85
Per Day Production 935
Gross Profit per day 3,740,000
Additional Expenses (incentive to workers) per day
Extra Payment to each worker per day (11 x 5 x 5) 275
Amount to be paid to all workers in one day (275x90) 24,750
Net Income (profit minus expenses) 3,715,250
Per Day Additional Profit 195,250Per Week Profit 1,171,500
Per Month Profit 4,686,000
Incentive Scheme 2 (If production increses to 86-90 unit/hour)
Minimum Incentive to each worker Rs. 10 /hour on every additionalunit produced 10
Improved Production per hour 90
Per Day Production 990
Gross Profit per day 3,960,000
Additional Expenses (incentive to workers)
Extra Payment to each worker per day (11 x 5 x 10) 1,100Amount to be paid to all Workers in one day (550 x 1x90) 74,250
Net Income per day (profit minus expenses) 3,885,750
Per Day Additional Profit 365,750
Per Week Profit 2,194,500
Per Month Profit 8,778,000
Proposed Incentive Scheme
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 23/36
0
100,000
200,000
300,000
400,000
Pak Rs.
Incentive Scheme for Workers
Expense vs Profit Ratio
Expense
Profits
Expense 24,750 74,250
Profits 195,250 365,750
Scheme 1 Scheme 2
Expense v/s Profit Ratio
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 24/36
Working
80 units
per Hour
and 11
workinghours Profit
85 units per
Hour and 11working hours
Profit and
subtraction of
Dailyincentive
90 units per
Hour and 11working hours
Profit subtraction of Daily incentive
1 3,520,000 1 3,715,250 1 3,885,750
2 7,040,000 2 7,430,500 2 7,771,500
3 10,560,000 3 11,145,750 3 11,657,250
4 14,080,000 4 14,861,000 4 15,543,000
5 17,600,000 5 18,576,250 5 19,428,750
6 21,120,000 6 22,291,500 6 23,314,500
7 24,640,000 7 26,006,750 7 27,200,250
8 28,160,000 8 29,722,000 8 31,086,000
9 31,680,000 9 33,437,250 9 34,971,75010 35,200,000 10 37,152,500 10 38,857,500
11 38,720,000 11 40,867,750 11 42,743,250
12 42,240,000 12 44,583,000 12 46,629,000
13 45,760,000 13 48,298,250 13 50,514,750
14 49,280,000 14 52,013,500 14 54,400,500
15 52,800,000 15 55,728,750 15 58,286,250
16 56,320,000 16 59,444,000 16 62,172,000
17 59,840,000 17 63,159,250 17 66,057,750
18 63,360,000 18 66,874,500 18 69,943,500
19 66,880,000 19 70,589,750 19 73,829,25020 70,400,000 20 74,305,000 20 77,715,000
21 73,920,000 21 78,020,250 21 81,600,750
22 77,440,000 22 81,735,500 22 85,486,500
23 80,960,000 23 85,450,750 23 89,372,250
24 84,480,000 24 89,166,000 24 93,258,000
25 88,000,000 25 92,881,250 25 97,143,750
26 91,520,000 26 96,596,500 26 101,029,500
Days 80 Units 85 Units 90 Units
1 3.52 3.71525 3.885755 17.6 18.57625 19.42875
10 35.2 37.1525 38.8575
15 52.8 55.72875 58.28625
20 70.4 74.305 77.715
25 88 92.88125 97.14375
Days Diff 85 - 80 Diff 90 - 80
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 25/36
1 0.19525 0.36575
5 0.97625 1.82875
10 1.9525 3.6575
15 2.92875 5.48625
20 3.905 7.315
25 4.88125 9.14375
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 26/36
0
10
20
30
40
50
60
70
80
90
100
P r o f i t ( M i
l l i o n P K R )
1 5 10 15 20 25
Days of Month
Profit Comaparison
80 Units
85 Units
90 Units
0
1
2
3
4
5
6
7
8
9
10
P r o f i t D i f f e r e n c e ( P K R
M i l l i o n )
1 5 10 15 20 25
Working Days of Month
Profit Difference
Diff 85 - 80
Diff 90 - 80
Profit Comparison & Difference
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 27/36
WORK ENVIRONMENT
Now we shall look at three types of physical hazards in more detail:
• Temperature;
• Ventilation;
• Lighting
All of above have an impact on workers’ health and their productivity, therefore, require a variety of
control mechanisms.
Temperature
ObservationWe observed that about 20% low productivity after lunch hours was observed on hourly basis. Following
are the random dates when this data was collected:
17-05-2011
12-05-2011
21-05-2011
20-06-2011
13-06-2011
11-06-2011
We observed that it was due to high temperature and high humidity which was badly affecting the
performance of the workers and they were slowing down with every passing hour.
During hot and humid season which is peak production season and workers work 8-12 hours shift,
workers face extremes of temperature as part of their daily work and may suffer - fatigue and dizziness; -
- heat stress/strain (distress);
- sweating palms (become slippery); -
- heat cramps;- lower performance/alertness;
Work Environment
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 28/36
A worker’s ability to do his/her job is affected by working in hot environments. One of the most
important conditions for productive work is maintaining a comfortable temperature inside the workplace.
Of course the temperature inside the factory varies according to the season and several methods can beused to address the problem. There are two main ways in which heat (or cold) gets into the factory:
• Directly – through windows, doors, air bricks etc;
• Indirectly – by conduction through building namely the roof, walls and floor.
These warm up through the day as the sun shines and the heat is transferred to the internal environment
often making it hot and sticky for the workers.
There are a number of measures that management can take to try to reduce the sun’s heat from entering
the factory. These include:
Ensuring that the external walls are smooth in texture and painted in a light color to help to reflectthe heat;
improving the heat reflection of the roof;
improving heat insulation of walls and ceilings (investigate the possibility of dry lining walls or adding an insulated ceiling below the roof.
There are a number of basic approaches to tackling heat hazards in factories. All involve reducingexposure by keeping heat away from workers through:
the use of increased general ventilation throughout the factory by openingwindows, by ensuring that air bricks, doors etc are not blocked.
the use of ―spot cooling‖ by the use of fans to reduce the temperature in certain sections of the
factory
The use of air conditioners/coolers.
The use of Industrial size exhaust fans in the assembly hall.
increasing the duration of rest periods;
Whatever method is used to reduce workplace temperature, it is important that adequate supplies of drinks
are made available to workers. These drinks could be lemonade, energile, tang or Qurshi /Rohafza drinksand lemon tea - water alone will lead to muscle cramps.
Work Environment
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 29/36
VENTILATION
It is not only essential to provide a comfortable temperature inside the factory, but also ensure an adequate
supply of fresh air in the working area.
It is important not to confuse ventilation and air circulation inside the factory, air circulation, namely
moving the air around inside the factory without renewing it with fresh air from outside. In the case of air
circulation, fans are placed near workers to improve thermal comfort . In essence this means that you aresimply circulating stale air plus any contaminants around the factory. Ventilation refers to replacing stale
air with fresh air at regular intervals.
In an average workplace, the air needs to be changed between 8 and 12 times per hour and that there should be at least 10 cubic meters of air per worker
.
The general ventilation can be achieved by allowing the free flow of air through the factory from oneside to the other – referred to as horizontal air-flow, this can be achieved by opening doors and windows
and putting more air bricks in the walls to take advantage of any prevailing wind. However it is all too
common to find doors and windows etc., locked for security reasons or blocked with excess stock or boxes of finished goods awaiting despatch. As a result, ventilation is limited.
We think the general ventilation in your factory can be improved with few simple
suggestions that can help:
if you have ventilation systems or free standing fans in the factory, make sure that they increasethe natural flow of air through the factory and not try to blow air against any prevailing wind .
ensure that hot, stale air that rises to the factory roof can easily be removed and replaced withfresh air.
make sure that all fans are well maintained and regularly cleaned so that they work efficiently;
ensure that the air-flow to and from fans is not blocked.
Ventilation
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 30/36
LIGHTING
From the workers’ perspective, poor lighting at work can lead to eye strain, fatigue, headaches, stress and
accidents. On the other hand, too much light can also cause health and safety problems such as ―glare‖
headaches and stress.
Both can lead to mistakes at work, poor quality and low productivity. Various studies suggest that good
lighting at the workplace pays dividends in terms of improved productivity, and a reduction in errors.
Improvements in lighting do not necessarily mean that you need more lights and therefore use more
electricity – it is often a case of making better use of existing lights; making sure that all lights are clean
and in good condition; and that lights are positioned correctly for each task. It is also a case of making the best use of natural light.
Factories have a combination of natural and artificial lighting. However, little attention appears to be paid
on the nature of the work – it is as though all work in the factory requires the same degree of lighting. Aswe will see, this is not the case.
Let us look at some common lighting problems in the factory:
There is also a need to make sure that all windows, skylights, etc., are clean and in the best position to
allow the maximum amount of natural light into the workplace.
Similarly, all lights (and reflectors) in the factory should be well maintained and cleaned on a regular
basis.
It has been known for companies, when the order books are low, to introduce ―energy saving‖ programs
to save costs. In the case of lighting, ―non essential‖ light bulbs may be removed or reduced in number,
flickering fluorescent tubes which need changing are left in place – this proves to be a false economy asquality and productivity fall.
One simple way to improve the lighting levels in the factory is to paint the walls and ceilings with light, pale, matt colors – the use of matt paint avoids reflection of light.
By brightening up the workplace, this helps to produce a more pleasant place to work which impacts on
wor kers’ well-being and, ultimately productivity.
Lighting
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 31/36
The level of light is measured in LUX using a light meter. Unfortunately, few factories or the Labour
Inspectorate have any of these meters. The table below gives an indication of some typical light levels:
Very bright sunny day : Up to 100,000 lux
Overcast day 30,000 : 40,000 lux
Dusk : 1,000 lux
Shady room in daylight: 100 lux
There are a number of general guidelines which can be used for reference. These give recommendations
for the amount of light that should be available for the type of work – for example:
Lighting
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 32/36
For Assembly Shops
Rough Work e.g frame and heavy machine assembly 200 - 300 - 500
Medium Work, e.g., engine assembly, vehicle body assembly 300 - 500 - 750
Fine Work, e.g., Office machinery assembly 500 - 750 - 1000
Very Fine work, e.g., instrument assembly 750 - 1000 - 1500
Minute qork, e.g., watch making 1000 - 1500 - 2000
PREVENTIVE MAINTENANCE
• Preventive maintenance is a schedule of planned maintenance actions aimed at the prevention of breakdowns and failures. The primary goal of preventive maintenance is to prevent the failure of
equipment before it actually occurs. It is designed to preserve and enhance equipment reliability
by replacing worn components before they actually fail and result into Business loss due to production delays. However, it needs a more organized, planned environment
Advantage of Preventive Maintenance
• Reduced production downtime, resulting in fewer machine breakdowns.• Better conservation of assets and increased life expectancy of assets, thereby eliminating
premature replacement of machinery and equipment.• Timely, routine repairs circumvent fewer large-scale repairs.
• Reduced cost of repairs by reducing secondary failures. When parts fail in service, they usually
damage other parts.• Better quality products
• Identification of equipment with excessive maintenance costs
• Improved safety and quality conditions.
• • Preventive Maintenance makes sense• This is a logical choice that considers two conditions
– 1. The component in question has an increasing failure rate.
– 2. The overall cost of the preventive maintenance action must be less than the overall
cost of a corrective action.
Preventive Maintenance
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 33/36
HOW TO DETERMINE THE OPTIMUM AGE OF REPLACEMENT?
The key for a successful PM system
• Scheduling – Should be automated to the maximum extent possible
• Execution – Should be done before the actual break down occurs.
Execution
• The Bath Tub Model – Three stages of new parts
1. Infant morality stage
2. A fairly long run stage3. Wear out stage
• Traditional View according to Bath Tub Model – Replace components just before they entered
wear out stage
Optimum age of Replacement
Optimum age of Replacement
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 34/36
• Traditional view says – Wear out stage = Increased rate of failure.
Since, wear out stage represents increased rate of failure, it be advisable to execute the PM program at this stage
What really should Preventive Maintenance focus on?
• Cleaning Found through testing
• Lubrication and inspection
• And correcting deficiencies
Predetermined parts replacement should be minimal and done only where statistical evidence clearlyindicates wear-out characteristics
Motivating Preventive Maintenance Workers
• Training programs – most effective
• Establish inspection and preventive maintenance as a recognized, important part of the overallmaintenance program.
• Assign competent, responsible people to the preventive maintenance program.
• Follow-up to assure quality performance and to show everyone that management does care.
• Provide training in precision maintenance practices and training in the right techniques and procedures for preventive maintenance on specific equipment.
• Set high standards.
• Publicize reduced costs with improved up-time and revenues, which are the result of effective
preventive maintenance.
• It is an essential part for cost reduction.
• The biggest benefits of a PM program occur through painting, lubrication, cleaning and adjusting,and minor component replacement to extend the life of equipment and facilities.
One of the major reason for frequent down times the absence of PMR (preventive maintenance schedule).
Recommendations
7/28/2019 Final Consulatncy
http://slidepdf.com/reader/full/final-consulatncy 35/36
OBSERVATIONS AND RECOMMENDATIONS:
The access to maintenance staff is time taking task. It is recommended to get a permanentresource from the maintenance team so that he will be available in the assembly hall all the
time during the production hours. In case of emergency shut downs, (i.e. chain of assemblyline is broken), staff is difficult to trace. Secondly, once they are contacted, some one from
maintenance departs comes, check the problem and goes back. Then later on he or his
supervisor comes with the tool and start working for trouble shooting.
There are some repetitive faults on the line. Therefore, we recommend the following:
There should be daily and weekly maintenance schedule especially for the peak season whenline is over loaded.
Conveyor belt, its related electric motors, pneumatic guns and others accessories should be
inspected.
There should be dedicated manpower for A/C assembly are especially during peak hours Mar-June.
Each complaint, i.e. mechanical or electric should be fully documented and repetitive issuesshould be addressed on permanent basis.
There should be a separate work order against each maintenance complaint which should bemaintained.
The quality of maintenance service provided should also be observed and feedback from
operations and quality department should be obtained, in order to know the quality of maintenance work.
In conclusion, we can say that efficiency improvement is not single shot game, it is continuous and
permanent process with dedicated efforts & firm commitment by management and employees.
Though our client Orient is one of best performing assembly plant in the Industry. However, still there is
lot of room to perform efficiently and effectively with the given resource and manpower. In Operation
management, 80% of problem & issues can be resolved by making 20% extra efforts and resource. While
only remaining 20% needs relatively higher degree of attention and resources.