Field Experiences of Installation ACCC Conductors: a growing part of capacity expansion and reliability at PLN Donny Rinaeldi PT. PLN (Persero) Asia Clean Energy Forum Grid Efficiency with HTLS Conductors June 16, 2015 Manila, Philippines

Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

Field Experiences of Installation ACCC Conductors: a growing part of capacity expansion and reliability at PLN

Donny Rinaeldi PT. PLN (Persero)

Asia Clean Energy Forum Grid Efficiency with HTLS Conductors June 16, 2015 – Manila, Philippines

Page 2: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

DONNY RINAELDI PLN P3B SUMATERA – PEKANBARU, INDONESIA TRANSMISSION DIVISION

Asia Clean Energy Forum June 16, 2015 – Manila, Philippines

Prabumulih

Baturaja

Tarahan

Pekalongan

Tes HEPP

Sukamerindu

Bangko

Tl.Kelapa

MarianaLubuk

Linggau

Payo

Selincah

3. PLTMG Sewa2. PLTG Ex Pulo Gadung1. IPP Palembang Timur

KiliranjaoSalak

Lubuk

Alung Pauh

Limo

S.Haru

Bagan Batu

PagarAlam

Singkarak

HEPP

Pd. Luar

Teluk

Lembu

Duri

SigliBireun Lhokseumawe

Idie

Langsa

Sipan

HEPP

Tele

BrastagiG.Para

Kisaran

Aek Kanopan

K.Pinang

Muara

Bungo

Maninjau

HEPP

Bangkinang

Sibolga

T.Morawa

Pd.Panjang

Keramasan

Simpang 3

Borang

Gumawang

Kalianda

Simpang

Empat

PLTUP.Susu

Musi HEPP

PLTUSumbar Pessel

PLTU

L.Angin

PLTG G.Megang

Sistem

JAWA

B.Umpu

Tualang Cut

Garuda

Sakti

Eksisting 70 kV

Eksisting 150 kV

Eksisting 275 kV (Operasi 150 kV)

Rencana 150 kV

TNB

Malaysia

Malaka

PT PLN (Persero)

PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA

5

67

12

3 4

Tegineneng

Sutami

P.Brandan

Batusangkar

Ombilin

Payakumbuh

T.Kuantan

Bungus

Indarung

Kt.Panjang

HEPP

Lahat

Bukit

Asam

Betung

PLTG Talang Duku

PLTU

S.Belimbing

Natar

Tlk.

Betung

Metro

Pd. Sidempuan

Pagelaran

Besai HEPP

Muara Bulian

Kambang

Pariaman

PIP

Solok

Dumai

D.Sanggul

Tarutung

Sidikalang

Renun HEPP

G.Tua

Simangkok

INALUM

Adijaya

B.Tegi

HEPP

Suka

rame

BanyakSp.

Sribawono

New

Tarahan

Aur Duri

R.PrapatAsahan I

HEPP

T.Tinggi

P.Siantar

Bukit

Kemuning

1. Bukit Siguntang

2. Talang Ratu

3. Seduduk Putih

4. Boom Baru

5. Sungai Juaro

6. Sungai Kedukan

7. Bungaran

Sewa

Sei Gelam

PLTG

Balai

Pungut

Eksisting 275 kV

K.Tanjung

Ulubelu

GEPP

Sibalang

PLTG

Jakabaring

MannaMenggala

Kotabumi

PLTU

Nagan Raya

SISTEM INTERKONEKSI SUMATERATAHUN 2015

Porsea

PLTU/GUBelawan

BinjaiP.Pasir

Mabar

P.Geli

NamorambeTiti Kuning

KIM

Glugur

Labuhan

Lamhotma

Sei.Rotan

Denai

Listrik

K.Namu

Perbau

ngan

Martabe

P.Labu

Tanjung

Api-api

Banda Aceh

Jantho

P3B SUMATERA (P3B : TRANSMISSION & LOAD DISPACTH CENTRE)

Presentation Topic: “Field Experience Of Installation ACCC Conductor”

Page 3: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

PLN Customers

70kV 150kV 275kV 500kV

Java-Bali 3.136 13.401 - 5.053

Sumatera 318 9.069 1.374 -

East Indonesia 658 6.381 - -

TOTAL 4.112 28.851 1.374 5.053

Length of Transmission Lines (kmc)

Page 4: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

28% more Aluminum Composite Core Steel

Core

Aluminum

28% more Aluminum Composite Core

ACCC® Conductor Traditional ACSR

Steel Core

Aluminum

HCLS (High Capacity Low Sag)

ACCC (Aluminum Conductor Composite Core)

Page 5: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

No Project NameTotal

CCTs

Line

LengthEx Upgraded New Conductor Status

1 Bukit Asam - Lahat (Sumatera) 2 44.7 ACSR Hawk ACCC 310 Lisbon Energized on October 2010

2 New Tangerang – Cengkareng 2 6.2 2 x ACSR Zebra 2 x ACCC 520 Dublin Energized on April 2011

3 Angke – Ancol 2 4.7 ACSR Drake ACCC 510 Warsaw Energized June 2011

4 Kota Bumi - Bukit Kemuning (Sumatera) 2 34.3 ACSR Hawk ACCC 310 Lisbon Energized June 2011

5 Bandung Selatan - Cigereleng 2 13.26 2 x ACSR Dove 2 x ACCC 310 Lisbon Energized on October 2011

6 Cibinong - Sentul - Bogor Baru 2 23 ACSR Dove ACCC 360 Amsterdam Energized Feb 2012

7 Mranggen Incomer 2 4.3 2 x ACSR Hawk 2 x ACCC 360 Amsterdam Energized 2012

8 Pedan - Klaten 2 12.7 1 x ACSR Hawk ACCC 310 Lisbon Energized on April 2012

9 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk ACCC 310 Lisbon 1cct energized Sept 2012

10 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk ACCC 310 Lisbon 2cct energized Sept 2012

11 Pagelaran – Tegineneng (Sumatera) 2 38.5 1 x ACSR Hawk ACCC 310 Lisbon Energized on Sept 2012

12 Mandai-Pangkep (Makassar) 1 39.5 ACSR 150/50 ACCC 150 Helsinki Energized on Sept 2012

13 Kediri-Kediri Baru 2 0.7 2 x ACSR Zebra 2 x ACCC 520 Dublin Energized Oct 2012

14 Gilimanuk – Celukan Bawang (Bali) 2 43 2 x ACSR Hawk 2 x ACCC 310 Lisbon Energized Jan 2013

15 Kapal - Padang Sambian - Pesanggaran (Bali) 2 17.28 ACSR Hawk ACCC 310 Lisbon Energized Jan 2013

16 Probolinggo - Lumajang 2 50.5 ACSR ACCC 415 Brussels Energized on Mei 2013

17 Natar-Sutami 2 26.4 ACSR HAWK ACCC 310 Lisbon Energized on May 2013

18 Mandai – Pangkep 1 39.5 ACSR 150/50 ACCC 150 Helsinki Energized June 2013

19 Cibinong – ITP 2 8.5 ACSR Hawk ACCC 310 Lisbon 1cct energized on Oct 2013

20 PLTGU Duri – Garuda Sakti 2 80.3 ACSR HAWK ACCC 360 Amsterdam Energized on Dec 2013

21 Surabaya Barat – Babatan 2 15.6 ACSR Hawk ACCC 310 Lisbon Energized on January 2014

22 PLTGU Duri – Duri 2 42 ACSR Hawk ACCC 310 Lisbon Energized on April 2014

23 Baturaja - Bukit Kemuning 2 98.5 ACSR Hawk ACCC 310 Lisbon Energized on July 2014

24 GI Sei Harapan - GI Baloi - GI Batu Besar (Batam) 2 16.72 1x ACSR Hawk ACCC 310 Lisbon Energized October 2014

25 Borang - Seduduk Putih 2 13 ACSR 120/25 ACCC 150 Helsinki 1 cct energized Oct 2014

26 Cilegon Baru – Serang 2 22.7 ACSR Zebra ACCC 550 Hamburg Under Construction

27 Dumai – Duri 2 55.8 ACSR Hawk ACCC 310 Lisbon Under Construction

28 Baturaja – Bukit Asam 2 72.74 ACSR Hawk ACCC 310 Lisbon Under Construction

29 Binjai - Paya geli 2 13.7 2x ACSR Hawk 2 x ACCC 310 Lisbon Under Construction

30 Padalarang - Cibabat 2 9.2 2x ACSR Hawk 2 x ACCC 310 Lisbon Under Construction

After 30 projects and almost 6,000 kilometers of installations, PLN is now have more experiences on composite core conductor installation and performance.

Page 6: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

1. Increasing Energy Transferred

Why do we need HCLS Conductor?

Section

Old Conductor New Conductor

Type Nominal

Current (A) Max Loaded

(A) Type

Nominal Current (A)

Max Loaded (A)

150 kV Bukit Asam - Baturaja ACSR - 240 645 570 ACCC - Lisbon 1250 750

150 kV Bukit Kemuning - Baturaja

ACSR - 240 645 475 ACCC - Lisbon 1250 775

150 kV Kotabumi - Bukit Kemuning

ACSR - 240 645 580 ACCC - Lisbon 1250 965

The 150 kV Kotabumi – Bukit Kemuning transmission, for each Line could transfer 52 MW bigger than before. 965 A = 130.3 MW 580 A = 78.3 MW

Page 7: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

2. Changing Conductor with using Existing Towers

Why do we need HCLS Conductor?

No Section Towers Line Length Old Conductor New Conductor

1 Bukit Asam - Lahat 138 89.4 ACSR - Hawk ACCC - Lisbon

2 Kota Bumi - Bukit Kemuning 101 68.6 ACSR - Hawk ACCC - Lisbon

3 Langsa - Pangkalan Brandan 236 156 ACSR - Hawk ACCC - Lisbon

4 Pagelaran - Tegineneng 118 77 ACSR - Hawk ACCC - Lisbon

5 Natar - Sutami 82 52.8 ACSR - Hawk ACCC - Lisbon

6 Balai Pungut - Garuda Sakti 247 160.6 ACSR - Hawk ACCC - Amsterdam

7 Balai Pungut - Duri 126 84 ACSR - Hawk ACCC - Lisbon

8 Baturaja - Bukit Kemuning 192 197 ACSR - Hawk ACCC - Lisbon

9 Borang - Seduduk Putih 50 26 ACSR 120/25 ACCC - Helsinki

10 Dumai - Duri 165 111.6 ACSR - Hawk ACCC - Lisbon

11 Baturaja - Bukit Asam 226 145.48 ACSR - Hawk ACCC - Lisbon

12 Binjai - Payageli 38 27.4 ACSR - Hawk ACCC - Lisbon

Total Tower and Line Length 1,719 1,195.88

1 tower = 10,000 USD

(material + service of

construction cost, but

without the area of

tower’s foundation fee)

1,719 towers =

17,190,000 USD

Page 8: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

3. Minimizing the Transmission Loses

Why do we need HCLS Conductor?

2009 2010 2011 2012 2013 2014 TW-I 2015

SBU 2.72 2.29 2.59 1.35 1.07 0.78 1.85

SBST 4.04 4.80 4.18 4.65 4.44 4.18 3.49

SUMATERA 3.47 3.74 3.57 3.33 3.13 2.9 2.9

0.00

1.00

2.00

3.00

4.00

5.00

6.00

Susu

t (%

)

SBU = NORTH SUMATERA AREA SBST = CENTRE AND SOUTH SUMATERA AREA SUMATERA = AVERAGE OF SBU AND SBST

Page 9: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

Magnetic and Electric Field related to ACSR and ACCC (ex. 150 kV Duri – Dumai Transmission Line)

Span (Tower)

2013 (ACSR) 2015 (ACCC)

Magnetic Field (kV/m)

Electric Field (µT) Magnetic Field

(kV/m) Electric Field

(µT)

1 - 2 1.990 1.216 1.990 2.490

3 - 4 1.997 0.802 1.990 2.490

4 - 5 0.976 1.164 0.380 2.490

9 - 10 1.990 0.789 1.990 0.700

24 - 25 1.990 1.403 1.610 2.490

29 - 30 1.987 0.980 2.250 1.470

EMF (Electric Magnetic Field) is not different between ACSR and ACCC conductor.

Page 10: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

Lampung

746 MW

438 MW

Sumsel

664 MW

950 MW

Bengkulu

110 MW

204 MW

Jambi

296 MW 308 MW

Sumbar

489 MW

566 MW

Riau

498 MW

356 MW

Sumut

1488 MW

NAD

297 MW

1440 MW (Inalum : 90 MW) 202 MW

Why do we need HCLS Conductor? 4. Reducing the Fuel Oil consumption in Producing Electricity

Sources Consumption

Geothermal 3%

Water 17%

Oil 21%

Gas 29%

Coal 30%

53.5% of Supply are

produced by Diesel Power

Plant

Most Power Plants use

Gas (39.8%) and Coal (36.3%)

Page 11: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

HCLS Conductor Plan in P3B Sumatera

2015 (Procurement process)

2016 (Evaluating process)

No Section No of

Cct Existing Conductor

Line Length (km)

1 150 kV Lhokseumawe - Idie - Panton Labuh - Langsa 2 ACSR 1x240 257

2 150 kV Lhokseumawe - Bireun 2 ACSR 1x240 31

3 150 kV Garuda Sakti - Teluk Lembu 2 ACSR 1x240 39.96

4 150 kV Pangkalan Branda - Binjai 2 ACSR 1x240 101.62

5 150 kV Kualatanjung - Kisaran 2 ACSR 1x240 114

Total Length 543.58

No Section No of

Cct Existing Conductor

Line Length (km)

1 150 kV Tebing Tinggi - Kuala Tanjung 2 ACSR 1x240 71.4

2 150 kV Tebing Tinggi - Perbauangan 2 ACSR 1x240 98.2

3 150 kV Sei Rotan - Perbaungan 2 ACSR 1x240 83 4 150 kV Sei Rotan - Tebing Tinggi 2 ACSR 1x240 107

5 150 kV Sibolga - Martabe 2 ACSR 1x240 70.2 6 150 kV Padang Sidempuan - Martabe 2 ACSR 1x240 77.2 7 150 kV Belawan - Payapasir 2 ACSR 2x400 12.4

8 150 kV Natar - Teluk Betung 2 ACSR 2x240 33.8 Total Length 553.2

Page 12: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

The Existing Type of Transmission Conductor in Sumatera

No Transmission

Voltage Type of

Conductor Percentage of Length

1 70 kV ACSR 3.0%

2 70 kV ACCC 0.2%

3 150 kV ACSR 71.8%

4 150 kV ACCC 11.5%

5 275 kV ACSR 13.5%

6 275 kV ACCC 0.0%

3.0% 0.2%

71.8%

11.5%

13.5%

0.0%

70 kV ACSR

70 kV ACCC

150 kV ACSR

150 kV ACCC

275 kV ACSR

275 kV ACCC

Page 13: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

The Future Expansion of PLN Transmission Capacity

• The Government plans for 35,000 MW of additional generation capacity in 5 years duration.

• PLN plans to add a new transmission and concern about the timing

• Reconductoring can potentially provide 50% of the evacuation capacity increase required by the five year plan

For a mature grid, reconductoring with HCLS conductors is the only way to meet the rapid growth of transmission capacity.

Page 14: Field Experiences of Installation ACCC Conductors · 2015. 6. 16. · T.Morawa Pd.Panjang K eramas an S impang 3 B orang Gumawang K alianda S impang E mpat PL TU P.S us u Mus i HE

Thank you…

Asia Clean Energy Forum Grid Efficiency with HTLS Conductors June 16, 2015 – Manila, Philippines