Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
EFFLUENT TREATMENT PLANT
By
G. H. Trivedi, SEE
J. D. Kalyani, R.O.
23rd October, 2012
26th November, 2012
1
12
/5/2
01
2
• ABOUT WASTE WATER
• EFFLUENT TREATMENT – FUNDAMENTALS
• EFFLUENT TREATMENT METHODOLOGIES
• PRIMARY TREATMENT OF EFFLUENT
• SECONDARY TREATMENT OF EFFLUENT
• TERTIARY TREATMENT OF EFFLUENT
• ADVANCE TREATMENT OF EFFLUENT
• DISPOSAL OF TREATED EFFLUENT
• SLUDGE DEWATERING
CONTENTS OF PRESENTATION :
2
12
/5/2
01
2
Effluent is
“wastewater - treated or untreated - that flows out of a treatment plant, sewer, or industrial outfall. “
-US EPA
“Trade effluent” includes any liquid, gaseous or solid substance which is discharged from any premises used for carrying on any [industry operation or
process, or treatment and disposal system], other than domestic sewage.
- Water Act 74
3
12
/5/2
01
2
EFFLUENT TREATMENT
“The mechanisms and processes used to treat
waters that have been contaminated in some
way by manmade industrial or commercial
activities prior to its release into the
environment or its re-use.”
4
12
/5/2
01
2
FROM WHERE WASTEWATER ORIGINATE ?
Wet processing – raw material / product
Process wastewater
Exhausted scrubbing media
Cooling
Cleaning
Washing – floor, equipments, drums / plastics / liners
decontamination,
Blow down / Bleed
MEE condensate, RO reject, leachate
Laboratory
Workshop 5
12
/5/2
01
2
FROM WHERE WASTEWATER ORIGINATE ?
D. G. Set room
Contaminated runoff / water
Spray dryer runoff
Contaminated water from dyked area / storage area
Contaminated fire fighting waste water – drain / channel
within premises including toxic chemical & pesticides
storage area connected to retention basin for collection
of such waste water be provided and shall then be
provided appropriate treatment.
Leakages
Sewage…….. 6
12
/5/2
01
2
EFFLUENT TREATMENT - FUNDAMENTALS
Effluent treatment Units fall into
two divisions
Unit Operations - treatment /
removal of pollutants is
brought about by Physical
forces
Unit Processes - pollutants’
removal is brought by chemical
and biological reactions 8
12
/5/2
01
2
EFFLUENT TREATMENT – ADVANCE METHODS
Fenton treatment – Oxidation Process
Hypo treatment – Sodium Hypo Chloride solution
Electrochemical / coagulation treatment
Ozonization
Wet air oxidation
FACCO – Fenton Activated Carbon Catalytic Oxidation
Membrane Separation
Multiple Effect Evaporation System
Incinerator
RO System
MBR
Tritron Aerators, liquid Oxygen injection in aeration tank
10
These advance methods act as
• Pretreatment to enhance the treatability of the
conventional treatment units
• Polishing treatment
• Alternate to conventional treatment
12
/5/2
01
2
12
STREAM WISE TREATMENT
COD
HIGH
LOW
BOD
BOD
HIGH
HIGH
LOW
LOW
TDS
TDS
TDS
TDS
HIGH
HIGH
HIGH
HIGH
LOW
LOW
LOW
LOW
FORCED EVPORATION
FOLLOWED BY BIOLOGICAL
TREATMENT-I
BIOLOGICAL TREATMENT-II
INCINERATION-III
SOLVENT/CHEMICAL RECOVERY-
IV
FORCED EVAPORATION
FOLLOWED BY BIOLOGICAL
TREATMENT-I
BIOLOGICAL TREATMENT-II
FORCED EVAPORATION
SOLVENT/CHEMICAL RECOVERY-
IV
12
/5/2
01
2
EFFLUENT TREATMENT METHODOLOGIES
Important effluent parameters Flow / Volume
Flow / volume details from source to ETP / treatment equipment
Plant wise / stream wise collection – treatability can be checked and treatability report shall be asked
Characteristics
Physical, chemical and biological
13
12
/5/2
01
2
CHARACTERIZATION – EFFLUENT
Physical properties
Colour / Odour / Solid (SS / Coarse / Grit) /
Temperature
Chemical constituents
Organic
Oil & Grease / Pesticides / Phenols / Proteins /
Surfactants / VOC / Other chemicals / COD/
Carbohydrates / Fats / Methane etc
Inorganic
Alkalinity / Chlorides / Heavy Metals /
Ammonical Nitrogen / pH / Phosphorus / Sulfur
/ H2S
Biological constituents
BOD/ Microorganisms / tree leaves
14
12
/5/2
01
2
STREAM WISE SEGREGATION & TREATMENT
High / Refractory COD waste water
Refractory COD is organic compound that show up in COD test as being
chemically oxidizeable but not readily biodegradable e.g. some detergents
(alkyl benzene sulphonate), EDTA, NTA, Halogenated organics, PCB , some
organic acids
FACCO, FENTON, MEE, Incineration, Electro Oxidation, Ozonisation etc.
High TDS wastewater
Treatment with RO, MEE, evaporation, spray dryers etc.
MEE is mainly used to treat high TDS & low COD effluent. However, High
TDS & refractory/high COD; low TDS & refractory/high COD can also be
treated with MEE as shown in previous slide. In MEE, water is boiled in
sequence of vessels each held at lower pressure than last. Vapour boiled off
in one vessel is used to heat next vessel and reduces steam consumption.
Generated solid waste can be by-product or landfillable waste. Generated
condensate can be recycled back in process or can be treated in ETP.
Concentrate generated from MEE as a result of treatment of low TDS & high
COD shall be sent for incineration and/or for co-processing.
16
12
/5/2
01
2
STREAM WISE SEGREGATION & TREATMENT
High NH3- N bearing wastewater
Recovery of ammonia or salt of ammonia, stripping,
nitrification-de nitrification, MAP , use as raw
material for other product etc.
Toxic
Detoxification and Incineration
17
12
/5/2
01
2
STREAM WISE SEGREGATION & TREATMENT
Heavy Metals
Alkaline sedimentation / filtration
Dilute waste water
Conventional Treatment methodologies together with
advance treatment methodologies, if required
Inorganic
Primary treatment and sedimentation / filtration
18
12
/5/2
01
2
WASTEWATER TREATMENT
Preliminary treatment
Primary treatment
Secondary treatment
Tertiary / polishing treatment
Advanced treatment
Sludge (bio solids) disposal
19
12
/5/2
01
2
PRIMARY EFFLUENT TREATMENT
Preliminary treatment :-
Screening
Grit removal
Stream wise pretreatments :-
Physical separation
Chemical treatment
21
12
/5/2
01
2
PRIMARY TREATMENT –UNITS/EQUIPMENTS
Primary treatment removes -
Suspended (Organic & inorganic)
Colids
Reduces the organic load (BOD) on the secondary
units
Primary treatment consists -
Oil and Grease trap / API Separator
To remove Oil & Grease from raw effluent. Oil &
Grease trap is chamber so arranged that floating
matter (Oil & Grease) rises and remains floated
22
12
/5/2
01
2
PRIMARY TREATMENT –UNITS/EQUIPMENTS
Collection / Equalization / Neutralization Tank Equalization of fluctuating effluent flow will make
hydraulic pollutant loading more uniform and may
improve effectiveness or reliability of essential treatment
process
Flow equalization is used to overcome downstream
problems caused by flow rate variations, to improve
performance of downstream process and reduce the size
& cost of downstream treatment facilities.
Batch process / continuous process / day shift / night shift /
seasonal products / holidays / weak ends / shut down – are
often associated with fluctuation in pollutant loading
Chemical Neutralization is required to bring the pH of
effluent to neutral range. Normally, lime treatment is
required
23
12
/5/2
01
2
PRIMARY TREATMENT –UNITS/EQUIPMENTS
Chemical coagulation and Flocculation
Coagulation :- Effect of chemical to colloidal particles, resulting
in particle destabilization
Flocculation :- Process of agglomerating destabilized colloids
after coagulation with gentle stirring. Smaller particle suspended
in solution come together as larger aggregates (flocks)
Chemical feeding system
Chemicals are introduced into effluent for coagulation and
flocculation. Chemicals are added as solutions or dilute
suspensions. As treatment is continuous process, flow of
chemicals is regulated and measured continuously through
chemical feeders. Feeding system can be either pumps for liquids
or charging system with hoppers for solids like lime
Mixing tank
Chemical coagulants are added in mixing tank to effluent where
it is thoroughly and vigorously mixed so that coagulant gets
uniformly dispersed into entire mass of effluent
24
12
/5/2
01
2
PRIMARY TREATMENT –UNITS/EQUIPMENTS
Primary settling tank / clarifloculation
Objective of primary sedimentation is to provide sufficient time
under quiescent conditions for removal of settleable solids by
force of gravity
The overflow from primary clarifier will go to biological
treatment
Sludge dewatering
Generated sludge from primary clarifier is to be taken out and
dewatered. For sludge dewatering system, industry can use
sludge drying beds / filter press / centrifuges / RVDF / Super
decanter etc. Generated sludge can be disposed off to TSDF and
generated filtrate can be taken back for treatment in ETP
25
12
/5/2
01
2
PRE-TREATMENT
Pre-treatment is required to remove certain pollutants
at the initial stage e.g. removal of Cyanide, Heavy
Metals
Helpful for improving the performance of effluent
treatment plant
Stream wise pretreatments :- Physical separation
(Solvents, products etc) and Chemical treatment
(Fenton, Electrochemical oxidation, FAACO, Ozonation
etc ) .
Screening, Grit removal
26
12
/5/2
01
2
INSPECTION POINTS
Oil & Grease Trap
Compliance to requirement of minimum detention time
Acid proof lining and Sludge cleaning provision
Adequacy of O & G trap
Regular removal of oil and proper collection and
storage at specific location so as there is no spillage
Regular cleaning of traps
Regular removal of bottom solid
Oil disposal / fuel / sent to registered recycler
Adequacy of O&G trap
27
12
/5/2
01
2
INSPECTION POINTS
Collection / Equalization / Neutralization tank
Compliance to minimum requirement of detention time, power / air
supply / mixing mechanism
Size of tank vis-à-vis effluent generation quantity
Buffer tank to store non-regular effluent – may be slowly mixed with
regular flow so as there is no shock load
Effluent receiving lines with measurement devices
Pumps (one regular – electricity driven and one standby pump – diesel
driven)
Tank cleaning provision
Tank overflow – shall be equipped with reflux or level controller like
mechanism to prevent overflow
Foaming / oil and grease floating
Bubbles are rising from bottom
High VOC and odour problem
Acid proof lining and leakages problem
Buffer tank to store non regular effluent – slowly feed control and
regulate flow 28
12
/5/2
01
2
INSPECTION POINTS Chemical coagulation and Flocculation
Compliance to requirement for detention time, flow, depth of
tank
Effluent inlet with constant flow
Chemical charging system with constant flow
No settling , low turbulence
Chemical solution preparation tank
Large ETPs – mechanism for metered dose of flocculants
proportionate to flow
Flash mixing tank – square / circulating tank with high speed
agitator and motor
Stock of chemical
Record of chemical consumed
Suggested design parameters
Design parameters vary depending on effluent quality and
quantity from different sector of industries. For arriving
design parameters, jar test is required
29
12
/5/2
01
2
INSPECTION POINTS
Chemical Feeding System
Separate tanks for each chemicals
Feeding of different chemical at required location in
requisite quantity to achieve maximum efficiency
Proper MoC and agitator / air sparger provided or not
Effluent with VOC and ammonia shall not be subjected to
compressed air
Proper flow control system – (metering pump)
Batch – in ETPs with capacity less than 100 KLD, batch
mode of chemical dosing is OK
Continuous – in ETPs with higher capacity, continuous
or semi-continuous addition of chemicals will be
desirable
Proper chemical charging system (platform)
Weight balance
Chemical storage (room) with safety equipments
30
12
/5/2
01
2
INSPECTION POINTS
Primary Settling Tank / Clariflocculator
Compliance to design criteria like detention time,
depth of tank, surface overflow rate, weir overflow
rate, weir length for circular clarifier, scraper
revolution, sludge removal interval, design of launder
Removal of accumulation from influent and effluent
baffles, weirs and scum box
Cleanliness of all inside exposed walls / channels
Black and odorous septic effluent in primary
treatment – not desired
Floating sludge indicate excessive sludge
accumulation in tank
Sludge drain line chocking problem
31
12
/5/2
01
2
INSPECTION POINTS
Primary Settling Tank / Clariflocculator
Low solid concentration in sludge due to short
circuiting
Excessive corrosion of metal due to Hydrogen Sulfide
gas
Uneven overflow
Continuous clear overflow - desired
Clarifier drum leakage problem due to corrosion
Frequency of sludge removal
For up-coming plant underground clarifier (primary
or secondary) shall be avoided. Above ground clarifier
with proper conical bottom shall be provided.
32
12
/5/2
01
2
Biological unit processes are of three type
Aerobic : A process requiring the presence of oxygen
Anaerobic : A process from which air or oxygen not in chemical combination is excluded
Facultative process : Combination of Aerobic and Anaerobic process
Remove biodegradable matter (organic matter)
from wastewater
APPLICATION OF BIOLOGICAL UNIT OPERATIONS IN
WASTEWATER TREATMENT
34
12
/5/2
01
2
SECONDARY TREATMENT Secondary treatment is a biological process Degrade organic content (dissolved organic matter) Utilizes bacteria and algae to metabolize organic matter
in the wastewater Added bacteria and protozoa 3 different approaches
Fixed film system Suspended film system Lagoon system
Attached Growth Process / Rotating Biological Contactors – attached Growth Processes include trickling filter, roughing filter, rotating biological contactor, and fixed film nitrification reactor. Organic material present in wastewater is degraded by population of micro-organisms attached to filter media
35
12
/5/2
01
2
INSPECTION POINTS
Secondary treatment Units
Compliance to design criteria viz. detention time, oxygen supply,
microbes concentration etc.
Dissolved Oxygen concentration in aeration tank – preferabably 1
to 2 mg/lit. Hence on-line DO analyzer required
Concentration of TDS. Hence on-line TDS analyzer required
TDS meter shall be provided on primary clarifier outlet
On line TDS analyzers are useful in the inlet of RO System
and in the permeate line of RO System
In industries where there is huge fluctuation in dissolved
solids, TDS meter may be helpful in controlling TDS in
biological reactor
MLSS, MLVSS - on spot check by volumetric cylinder – should be
fast settling
Foaming in aeration tank - Very high or no foam is not desired
Inlet and outlet flow
Chocking of diffusers
Uniformity of supply of air / oxygen
36
12
/5/2
01
2
INSPECTION POINTS Secondary treatment Units
Mechanism and frequency of recycling of sludge
Regular cleaning
Foul smell from anaerobic unit
Closed handling system can remove foul smell with regular preventive
maintenance
H2S coming out can be scrubbed with caustic sol., hypo sol. or advance
technology like SRB scrubber (Sulphur Reducing Bacteria)
Rate of gas generation, its collection and utilization e.g. methane
Efficiency of removal of organic load
By measuring inlet COD / BOD and outlet COD / BOD levels
Removal efficiency can also be calculated by taking inlet kg BOD load
(quantity X concentration) and outlet kg BOD load. Efficiency is defined as
(Inlet BOD load – outlet BOD load) / inlet BOD load
Health of microbes – brownish colour indicates healthy biomass
Seeding of specially cultured microbes – for improved efficiency
Carryover of biomass – short circuiting
Sludge wasting
Excess activated sludge produced each day must be wasted to maintain
given food-to-microorganism ratio or mean cell-residence time. Most
common practice is to waste sludge from return sludge line because it is
more concentrated and requires smaller waste sludge pumps
37
12
/5/2
01
2
INSPECTION POINTS RBC
Rotating biological reactor consists of series of closely
spaced circular disc of polystyrene or poly vinyl
chloride
In operation, biological growths become attached to
surfaces of disc and eventually form slim layer
pH in aerobic
To maintain in the range of 7 to 8
Aerobic System
Aerobic biological system used to remove organic
matters from wastewater in the presence of air
Anaerobic System
Anaerobic biological system used to remove organic
matters from wastewater in the absence of air 38
12
/5/2
01
2
INSPECTION POINTS – SECONDARY TREATMENT
• Compliance to design criteria Viz detention time, oxygen supply,
microbes concentration
• Dissolved oxygen concentration in aeration tank- preferably- 1 to 2
mg/lit . Hence on-line DO analyzer required
• MLSS,MLVSS – on spot check by volumetric cylinder – should be
fast settling
• Foaming in aeration tank- Very high or no- foam is not desired
• Inlet and Outlet flow
• Chocking of diffuser
• Uniformity of supply of oxygen
• Mechanism and frequency of recycling of sludge
• Regular cleaning
• Foul smell from anaerobic unit
• Rate of gas generation , its collection and utilization
• Efficiency of removal of organic load.
• Health of microbes- golden brownish color indicate healthy
biomass , Normal & flock –foaming
• Flock of size pin point – Excessive solid carry over 39
12
/5/2
01
2
INSPECTION POINTS – SECONDARY TREATMENT
• Sludge riding on the waves – This is normal sludge but can not
settle because of excess incoming flow(Hydraulic) and load .
• Sludge over-aerated – it entrapped air bubble. This problem is
caused where grease or oil has prevented the escape of air bubble
• Dispersed growth of microbes in the sludge – colour is white,
brown, grey and particle remain in the uniform suspension even
for 30 minute test period . shows a lack of bacterial build up in the
mixed liquor , the sludge is watery certain to occur when the
concentration of soluble organic extremely high. Microscope
shows filament growth
• Broken or sheared flock , deflocculating – otherwise a normal flock
but the sludge has undergone some sort of shock.
• Sludge rising – Entrapped Nitrogen gas Settle well in 30 minute
but again rise to top becoming lighter than water . This is driven
by entrapped gas bubble . The sludge floats on water surface in
large chunks of color light brown – Higher nitrogen compound
40
12
/5/2
01
2
INSPECTION POINTS – SECONDARY TREATMENT
• Sludge floating – if the sludge is floating for a small duration and
small amount may be taken as normal . this may be due to
presence of some filamentous bacteria or dead fungi
• Bulking sludge – Two type buoyant (a) Bound water – A flocculated
a sludge with high SVI and a low settling rate . The sludge flock
has large area and contain bound water , Generally an under-
oxidised and young sludge . (b) filament growth- colour light
brown, grey or white . Odor is sweet or fruity . settling is low SVI
180 above
• Seeding of specially cultured microbes – for improved efficiency
• Carry over of biomass – short circuiting
• Sludge wasting cycle
41
12
/5/2
01
2
INSPECTION POINTS
Tertiary treatment Units - Pressure sand filter / carbon
adsorption etc
Adequacy with regard to surface area vis-à-vis effluent load
Capacity of pump with stand by pump – shall be provided
with pressure gauge and safety valve / pressure release valve
and in case of over pressure spilled waste water shall go to
catch pit
Piping – coding of inlet / outlet / backwash pipe lines
Backwashing facility, frequency, final disposal of
backwashing waste water – Sand filter
Frequency of reactivation of activated carbon – how
frequency is decided?
Whether used continuously or intermittently?
Carbon Iodine value checking records and replacement
Spent carbon disposal
Pressure gauge – In let & out let flow
Sight glass on pipeline, Flow direction marking
Cleaning frequency
43
12
/5/2
01
2
INSPECTION POINTS
Advance treatment Units
Multiple Effect Evaporation
Adequacy of MoC vis-à-vis effluent characteristics
Uniformity in characteristics of feed
Proper segregation of effluent to be evaporated
Requirement of any pre treatment – solvent
stripper
Adequate supply of heat energy – calendria
temperature – preferable between 80 to 90o C
Adequate time for evaporation
Regular checking for scaling and removal, if any
Leakages
Management of condensate, concentrate, stripped
solvent , mother liquor, salts etc.
45
12
/5/2
01
2
INSPECTION POINTS
Advance treatment Units
Multiple Effect Evaporation
Adequacy of MOC vis- vis effluent characteristics
Uniformity in characteristics of feed
Proper segregation of effluent to be evaporated
Requirement of any pretreatment –solvent stripper , antiscalent
dosing , pH adjustment
Adequate supply of heat energy – calendric temperature preferable
between 80 to 90o c
Adequate time for evaporation & % distillate
Regular checking for scaling and removal , if any
Leakage in pump , body seal
Vacuum , gauge
Online TDS meter on condensate
Insulation on parts
Flow of liquid -marking on pipeline
Use of antifoaming agent
46
12
/5/2
01
2
INSPECTION POINTS
Advance treatment Units
Multiple Effect Evaporation
Analysis of feed , condensate , concentrated mass
Management of condensate , concentrate , stripped solvent , mother
liquor salts etc
Adequacy of salt removal facility – centrifuge , filter nutch , ATFD
Metering device with totalizer on various important line –inlet ,
condensate, reject
Energy meter , steam meter separate
Cleaning frequency
Log book
47
12
/5/2
01
2
INSPECTION POINTS Advance treatment Units
Reverse Osmosis
Uniformity in characteristics of feed
Pretreatment like filter cartridge filter to remove SS and colloidal
material if any . Addition of descaling , pH adjustment
Online- Conductivity meter , pH ,Temp
Online pressure measuring device
Cleaning frequency – Short cleaning , Long cleaning – Dosing of
cleaning agent
Leakage – spillage , storage tanks for Feed , permeate , reject
Flow marking on pipeline
De-gasifier and packing ring
Fouling of membrane – silica , algae , salt
Metering device with totalizer on various important line –inlet,
permeate , reject
Recycling of permeate
Reject handling methodology : Rejects can be treated in ETP or can be
evaporated in batch evaporator or in MEE
Log book
49
12
/5/2
01
2
Record Keeping by CETP member Valid membership certificate
Certificate from competent authority indicating that industry do not
have any other mode of disposal – underground drainage connection
Month wise
Production taken
Water consumed
Chemical consumed, energy consumed, sludge generated, if
treated in-house
Number of tankers and quantity of waste water sent to CETP –
stream wise, if any
Quality of effluent sent to CETP
These records shall be verified for quantity and quality with
respect to data submitted at the time of taking membership as
well as those submitted under application forms for CCA
Number of tanker(s) received back from CETP on account of non-
conformance to inlet / acceptance criteria and its further
management
52
12
/5/2
01
2
LOG BOOK FOR AMMONIA BEARING STREAM
53
Sr
No
Month Pruduct /
Production
Generation of
Soln Having NH3
In-house consumtion of solutions
having Ammonia for making
other products
Sell / Disposal of solutions having
Ammonia (please also submit
copy of valid documentary
evidences e.g. Bill, Receipt,
Challan, Gate Pass etc for each
such consignments)
(Name / Qty) [Name / Qty (Kls)
& Conentration
(%) ]
Name of Soln
and Quantity
(KLs)
Name of
Product &
Quantity
Name of Soln
and Quantity
(KLs)
Name, Address
of receiving
party 1
2
3
Details of Generation / Sell / Inhouse consumtion of Solutions having Ammonia Name of Industry :
Address :
Name of Products :
(Generating Ammonium Chloride / Ammonium Carbonate / Ammonium Acetate / Ammonium Bromide / Liquor
Ammonia / Other solutions having Ammonia)
Name and Designation of authorised person of the industry :
Name and Designation of authorized person of the industry :
Signature: :
Seal / Stamp of the industry :
Note: Please maintain daily logbook for generation and disposal of solutions having Ammonia and submit copy
at the end of month.
12
/5/2
01
2
INSPECTION POINTS
Disposal of treated waste water
Provision of totalizer on final treated waste water discharge line /
recycling line
Provision of disposal tank with sampling bottle to ensure
representative sample of the effluent that is being disposed
Quantity of disposal vis-à-vis consented quantity
Mode of disposal vis-à-vis consented disposal
Any dilution with fresh water prior to disposal or at any stage of
effluent treatment – comparison of TDS at inlet / outlet
Adequate availability of dedicated land with grid network for treated
waste water application for irrigation / plantation – 1 m2 for 5 lit
Reuse / recycle of treated waste water / permeate
Effluent carrying pipe network above ground or underground
Any bye pass – shall be investigated
Calibration of flow meters
Housekeeping and labeling
57
12
/5/2
01
2
DISCHARGE PIPE DIAMETER – CONTINUOUS FLOW
58
Description Quantity Unit Remark
100.00 KL per day
5.56 KL per hour Considering total discharge in 18 hours
0.0015 m3/s
Velocity 0.8000 m/s Minimum velocity in pressurized pipe lines
Cross Section Area of
pipe0.0019 m2
0.05 m
49.57 mm
50 mm Rounded
Q = A V
A = Q/V
V = 0.8 m/sec (assumed)
CCA Quantity
Dia. Of pipe
12
/5/2
01
2
59
Free flow outside sampling chamber
Schematic
Note d1: Diameter of the discharge line should be such that it can not allow discharging the daily flow in a
shorter duration say 2 – 3 hrs. Daily discharge strictly as per CCA, should take at least 18 – 22 hrs a day
Sample bottle 20 liter volume
Ground level
Dead volume (depth of dead
volume ~ 6 inch)
To GIDC chamber
Sampling point
Pump discharge pipe dia d1
Compound wall
Final Treated Effluent
Geometric volume of the tank 10 m3
Treated Effluent
Holding Tank
Valve
12
/5/2
01
2
INSPECTION POINTS
Sludge dewatering : Sludge drying bed / centrifuge /
vacuum filters / filter press / Belt Press / RVDF etc.
Physical condition of SDB – no cracks
Condition of sludge in SDB
Foul smell
Leachate collection system and leachate handling
methodology
Appropriateness of the sludge dewatering system adopted
vis-à-vis quantity and characteristics of the sludge generated
Appropriateness of disposal of sludge to TSDF vis-à-vis
acceptance criteria of TSDF
Sludge transferring, storage and loading
Logbook
61
12
/5/2
01
2
INSPECTION POINTS
Other Infrastructure / facility
Separate energy meter
Laboratory
Skilled work force, Qualified people for Advance Treatment
Supervision of middle management personnel : More in Field
No extra / old pipe network
Proper access point
House keeping
Preferably no underground effluent conveyance – from plant
to disposal.
Open surface drain from plant to ETP to be avoided, if
effluent contains VOC.
Sufficient lighting
Proper and safe accessibility and visibility to discharge point
62
12
/5/2
01
2
INSPECTION POINTS
Other Infrastructure
Detailed ETP diagram with piping and colour coding
Flow meter and back up battery both in sealed condition.
Repairing of metering devises on urgent basis along with its
relevant entry in log-book.
Calibration of meters
Availability of suitable PPEs and spare parts
Connectivity of on-line analyzer with XGN by concerned
industry
Potential Industries to be sensitized and motivated to reduce
generation of T/E and to recycle more and more treated
effluents in plant and processes
63
12
/5/2
01
2