71
FEDERAL GOVERNMENT OF NIGERIA FEDERAL MINISTRY OF WATER RESOURCES Third National Urban Water Sector Reform Project (NUWSRP3) Environmental and Social Management Framework (ESMF) FINAL REPORT Project Coordinating Unit (PCU) National Urban Water Sector Reform Project (NUWSRP) 20, Lingu Street, Wuse II, Abuja. June, 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

FEDERAL GOVERNMENT OF NIGERIA - World Bank · PDF file · 2016-07-09FEDERAL GOVERNMENT OF NIGERIA ... the ESMF report must be disclosed as a separate and stand-alone document by the

Embed Size (px)

Citation preview

FEDERAL GOVERNMENT OF NIGERIA

FEDERAL MINISTRY OF WATER RESOURCES

Third National Urban Water Sector Reform Project

(NUWSRP3)

Environmental and Social Management Framework

(ESMF)

FINAL REPORT

Project Coordinating Unit (PCU)

National Urban Water Sector Reform Project (NUWSRP)

20, Lingu Street, Wuse II,

Abuja.

June, 2013

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb452162
Typewritten Text
E4289
wb452162
Typewritten Text
v2

1

TABLE OF CONTENTS

TABLE OF CONTENTS ... ... ... ... ... … … … 1

LIST OF TABLES ... ... ... ... ... … … … … 3

LIST OF FIGURES … … … … … … … … … 4

LIST OF ACRONYMS & ABBREVIATIONS … … … … … 5

EXECUTIVE SUMMARY … … … … … … … … 7

CHAPTER ONE: Introduction … … … … … … … 11

1.1 Background … … … … … … … … 12

1.2 Objectives of the ESMF … … … … … … … … … 12

1.3 Scope of Work … … … … … … … … … … 12

1.4 Study Approach and Methodology … … … … … … 13

1.5 Structure of ESMF Report … … … … … … … 14

CHAPTER TWO: Description of Proposed Project … … … … 15

2.1 Project Overview … … … … … … … … 15

2.2 Project Components … … … … … … … … 15

CHAPTER THREE: Baseline Data … … … … … … … 19

3.1 Project Area and Location … … … … … … … 19

3.2 Water Supply Status … … … … … … … 20

3.3 Nigeria Water Resources and Sources … … … … … … 21

CHAPTER FOUR: Description of the World Bank Safeguard Policies … … 23

4.1 OP/BP 4.01 Environmental Assessment … … … … … … 24

4.2 OP/BP 4.12 Involuntary Resettlement … … … … … … 25

4.3 OP/BP 4.37 Safety of Dams … … … … … … … 25

4.4 OP/BP 7.50 Projects on International Waterways … … … … … 26

CHAPTER FIVE: Administrative, Policy, Legislative and Regulatory Framework .. 27

5.1 Administrative Structure for the Water Sector … … … … … 27

5.1.1 Administrative Structure at the Federal Level … … … … 27

5.1.2 Administrative Structure at the State Level … … … … 28

5.1.3 Administrative Structure at the Local Government Level … … 29

5.2 Administrative Structure for Environmental Management at the Federal Level 30

5.3 Administrative Structure for Environmental Management at the State Level 30

5.4 Relevant Federal Policies … … … … … … … 31

5.5 Legal Framework … … … … … … … … 32

5.6 Membership of International River Basin Commission … … … 35

CHAPTER SIX: Potential Environmental and Social Impacts … … 36

6.1 Introduction … … … … … … … … … 36

6.2 Positive Environmental and Social Impacts … … … … … 36

6.3 Mitigation Measures … … … … … … … … 44

2

CHAPTER SEVEN: Institutional Assessment and Framework for Environmental

and Social Management … … … … … 48

7.1 Institutional Roles and Responsibilities … … … … … … 48

7.2 Capacity Assessment to perform Attributed Institutional Roles … … … 50

7.3 Training Needs … … … … … … … … … 51

7.4 Cost Estimates … … … … … … … … … 52

CHAPTER EIGHT: Environmental and Social Assessment Process … … 53

8.1 Introduction … … … … … … … … … 53

8.2 The Environmental and Social Management Process … … … … 53

8.3 Costs of Preparing ESIAs … … … … … … … … 54

8.4 Environmental and Social Management Plans for Subprojects … … … 56

8.5 Estimated Budget for Implementing ESMF … … … … … 57

CHAPTER NINE: Monitoring Plan … … …. …. … … … 58

9.1 Introduction … … … … … … … … … 58

9.2 Monitoring Roles and Responsibilities … … … … … 59

9.3 Costs for Implementing the Monitoring Plan … … … … … 60

CHAPTER TEN: Public Consultation … … … … … … 63

10.1 Introduction … … … … … … … … … 63

10.2 Consultation Strategy … … … … … … … … 63

10.3 Summary of Public Consultation … … … … … … 63

10.4 Consultation Plan … … … … … … … … 66

ANNEXES

Annex 1: List of Officials Consulted during the Preparation of the ESMF … … 67

Annex 2A: List of Stakeholders Consulted in Bauchi State … … … … 68

Annex 2B: List of Stakeholders Consulted in Ekiti State … … … … … 69

Annex 3: Summary of World Bank Safeguards Policies … … … … … 71

Annex 4: Terms of Reference for EAs/ESIAs required of the SWAs … … … 74

3

LIST OF TABLES

Table 3.1 Nigeria’s Geopolitical Zones … … … … … … 19

Table 6.1 Summary of the Potential Environmental & Social Impacts

of the NUWSRP3 … … … … … … … 41

Table 6.2 Summary of Environmental Mitigation Measures … … … 44

Table 6.3 Impacts from Activities in the Water Treatment Plants … … … 46

Table 7.1 Summary Table of Institutional Framework for Environmental

and Social Management … … … … … … … 49

Table 7.2 Proposed training program for the implementation of ESMF … … 52

Table 8.1 Estimated Budget for Implementation of ESMF… … … … 57

Table 9.1 Generic Monitoring Plan for the NUWSRP3 Based on the

Mitigation Measures … … … … … … … 61

Table 10.1 Summary of Stakeholders Consultation … … … … … 64

Table 10.2 Consultation Plan … … … … … … … 66

4

LIST OF FIGURES

Figure 3.1 Map of Nigeria showing the project States … … … … 19

Figure 8.1 Key Stages in Project Cycle … … … … … … 55

5

LIST OF ACRONYMS & ABBREVIATIONS

ADP Agricultural Development Project

AfDB African Development Bank

BASEPA Bauchi State Environmental Protection Agency

BIPU Bureau of Infrastructure and Public Utilities

BP Bank Procedure

BSWB Bauchi State Water Board

EKSEPA Ekiti State Environmental Protection Agency

EKRUWASSA Ekiti Rural Water Supply & Sanitation Agency

EKSWC Ekiti State Water Corporation

EKWMB Ekiti State Water Management Board

EMP Environmental Management Plan

ESA Environmental Sensitive Area

ESIA Environmental and Social Impact Assessment

ESMF Environmental and Social Management Framework

ESMPs Environmental and Social Management Plans

FCT Federal Capital Territory

FEPA Federal Environmental Protection Agency (now FMEnv)

FGN Federal Government of Nigeria

FMEnv Federal Ministry of Environment

FMWR Federal Ministry of Water Resources

IDA International Development Association

IBNET International Benchmarking Network

IMM Impact Mitigation and Monitoring (branch under the EIA division of FMEnv)

JMP Joint Monitoring Programme

LCBC Lake Chad Basin Commission

LGA Local Government Area

M&E Monitoring & Evaluation

MCH Maternal & Child Health

NBA Niger Basin Authority

NGO Non-Governmental Organization

NUWSRP1 First National Urban Water Sector Reform Project

NUWSRP2 Second National Urban Water Sector Reform Project

NUWSRP3 Third National Urban Water Sector Reform Project

NWRI National Water Resources Institute

NWRP National Water Rehabilitation Project

NWSSP National Water Supply and Sanitation Policy

OBA Output Based Aid

OP Operational Policy

PCU Project Coordinating Unit

PHC Primary Healthcare Centre

PHWC Port Harcourt Water Corporation

PIM Project Implementation Manual

PPM Parts Per Million

PPP Public Private Partnership

PSP Private Sector Partner or Private Sector Participation

PTF Petroleum Trust Fund

RAP Resettlement Action Plan

RBDA River Basin Development Authority

RFP Request For Proposal

6

RMWRRD Rivers State Ministry of Water Resources and Rural Development

RPF Resettlement Policy Framework

RUWASSA Rural Water Supply & Sanitation Agency

RWSS Rural Water Supply Strategy

SE Supervising Engineer

SEPAs State Environment Protection Agencies

SMEnv State Ministry of Environment

SMWR State Ministry of Water Resources

SPIU State Project Implementation Unit

SWAs State Water Agencies

TOR Terms Of Reference

UCC Utilities Charges Commission

UNICEF United Nations International Children’s Emergency Fund

WB World Bank

WHO World Health Organization

WTP Water Treatment Plant

7

EXECUTIVE SUMMARY

Project Background

As part of continued efforts in ensuring water supply to the urban areas and following the successful

implementation of the ongoing First and Second National Urban Water Sector Reform Project (NUWSRP

1&2), the Federal Government of Nigeria requested the World Bank financing for the Third National

Urban Water Sector Reform Project (NUWSRP3). Three states under Tier-1, Bauchi, Ekiti and Rivers

States have been principally selected to participate in the project.

In recognition of the fact that environmental and social concerns may arise as a result of the proposed

project, the Government of Nigeria represented by the Federal Ministry of Water Resources (FMWR) is

developing an Environmental and Social Management Framework (ESMF) in fulfillment of the Bank

requirements for project appraisal. The ESMF establishes a mechanism to determine and assess future

potential environmental and social impacts of the participating State Water Agencies (SWA’s) subproject

investments under the NUWSRP3, and then sets out mitigation, monitoring and institutional measures to

be taken during implementation and operations of the proposed investments, to eliminate their adverse

environmental and social impacts, offset them, or reduce them to acceptable levels. The ESMF was

prepared in accordance with applicable World Bank guidelines and safeguard policies as well as the

Nigerian environmental assessment guidelines.

Project Description

The project development objective is to increase access to sustainable and safe water and improved

sanitation to households in the three selected states. The strategic approach is to facilitate the

transformation of the way water supply services are provided, by supporting the introduction of sector

reforms aimed at improving efficiency and sustainability of operations, accompanied with significant

improvements in water service delivery in both quality and coverage.

Project Component

The project consists of three components, namely:

Component 1: Rehabilitation and Expansion of Water Production and Distribution Facilities

and Small Towns Water Supply Improvement through PPP in the selected States. ($300M)

Investment under this component will include large Public Private Partnership (PPP) transactions in the

rehabilitation and expansion of water production and distribution facilities. It will also include

implementation of pilot experiences in the provision of small towns’ water services. The Small Towns

water component will be built on the experience of successful projects in Uganda, Colombia and

Paraguay, where “reverse concessions” allow the private sector in partnership with local governments and

water users associations to provide public and private financing for the construction and/or operation of

water supply systems under negotiated tariff. Payment may include an output-based system where

feasible.

Component 2: Institutional Reform, Capacity Building and Emergency Works at the State

Level ($45M)

This component will finance studies, training, goods, emergency and rehabilitation works and services in

the remaining selected States to lay a solid foundation for reform. Support to these States will be

customized into two levels of support: Tier-2 support would include establishment of water policy and

law, customers enumeration (cadaster), improving revenue billing and collection, tariff reform, regulatory

reform, improving financial management, reduction of non-revenue water including metering,

implementation of limited emergency works to maintain minimum service standards, and strategic

training of the State Water Agency (SWA) staff as well as development of urban water supply master-

8

plans. States preliminary identified under this tier-2 include Kano, Gombe, Benue, Jigawa, Ondo, Abia

and Plateau.

Component 3: Institutional Reform, Capacity Building and Project Management at the Federal

Level ($15M)

This component will be implemented by the Federal Ministry of Water Resources, and will cover

Capacity Building and Institutional Reform and Project Management, Monitoring & Evaluation

Baseline Data

Project Areas and Location

The states where the project will be implemented are Bauchi, Ekiti and Rivers States. In Bauchi State the

project sites will be located in Bauchi town, Ningi, Bununu, Yana, Kirfi and Darazo and in Ekiti State the

project will focus on the capital city Ado Ekiti and the University town of Iworoko in Ado. Project

activities will also be carried out in Port Harcourt and Obio Akpor LGA of Rivers State.

Water Supply Status

The baseline data on the water supply status nationally and in the participating states is discussed in

Chapter Three. The Chapter also contains information on Nigeria’s water resources and river sources in

the states.

Environmental and Social Requirements

The FGN by its Federal and State Laws and Decrees and the World Bank's Operational and Procedural

Policies, specifically OP 4.01 requires the government to prepare an ESMF. OP 4.01 further requires that

the ESMF report must be disclosed as a separate and stand-alone document by the Government of Nigeria

and the World Bank as a condition for Appraisal. The disclosure should be both in country and at the

Infoshop of the World Bank. The date for disclosure must precede the date for appraisal of the project.

Triggered World Bank Environmental and Social Safeguard Policies

The project is categorized as a B implying that the potential environmental and social impacts will be

minor, site-specific and manageable to a reasonable level. The environmental and social impacts of the

NUWSRP3 will come from the activities and investments to be made under Components 1 and 2 of the

project. The proposed project has triggered the following policies: OP/BP 4.01: Environmental

Assessment; OP/BP 4.12: Involuntary Resettlement; OP/BP 4.37: Safety of Dams and OP/BP 7.50:

Projects on International Waterways. Details of the Bank’s Environmental and Social Safeguard Policies

are presented in Annex 3.

Administrative, Policy, Legislative and Regulatory Framework

The Institutions and Agencies responsible for the administration and regulation of water resources/

services, and environmental management at the Federal, State and Local Government levels are discussed

in Chapter Five.

Potential Environmental and Social Impacts

The project interventions will have some limited positive and negative environmental and social impacts.

Adverse potential impacts likely to occur during construction/rehabilitation phases of the water project

may include: loss of vegetation cover; degradation of landscape and soil erosion because of improper

disposal of excavated materials and construction waste, spillage of oil and toxic substances during the

rehabilitation, use of temporary construction sites; use of borrow pits; noise and vibration disturbances

during trench excavation; air pollution (dust) related to increased truck traffic during the construction;

pollution of water resources (surface and groundwater) and soil; increased population and attendant

crimes and communicable diseases. On the positive angle, the rehabilitation of water treatment plants and

water distribution networks will improve water supply and sanitation and thus reduce water and sanitation

9

related diseases and child mortality. It will also alleviate poverty and facilitate the attainment of the

Millennium Development Goals. A more comprehensive assessment of the potential impacts is discussed

in Chapter Six with the corresponding mitigation measures.

Institutional Assessment and Framework for Environmental and Social Management

The roles and responsibilities of key institutions for the purposes of this ESMF are discussed in Chapter

Seven and summarized in Table 7.1 below:

Summary Table of Institutional Framework for Environmental and Social Management.

Institution Tasks/Activities

Project Coordinating Unit (PCU) at

Federal Ministry of Water

Resources(FMWR)

Project Coordination and Oversight; reporting to IDA

Federal Ministry of Environment

(FMEnv)

Review, approval and clearance of ESIAs;

Monitoring SEPAs and reporting to FMWR.

State Ministry of Environment Review of ESIAs; Monitoring SWAs and reporting to

FMEnv.

State Project Implementation Unit

(SPIU) or the State Water Agencies

(SWAs)

Prepare ESIAs; Self-monitoring and reporting to SEPAs

and FMWR.

The Chapter also proposes a training program estimated at US$124,000.

Environmental and Social Management Process

The Environmental and Social Assessment Process is contained in Chapter Eight with the following key

steps: (i) Preparation of an Environmental and Social Impact Assessment (ESIA) - each SWA is required

to prepare an ESIA for their sub project/activities; (ii) Incorporation of Mitigation Measures into the

Design - the SWAs will re-introduce into/adjust/adapt/revise their sub project technical and engineering

designs, the required mitigation measures identified in the prepared sub project ESIA, before submission

of the entire sub project proposal for review and subsequent clearance; (iii) Submission of proposals to

respective SMEnv - the respective SMEnv of the state in which the participating SWA is located will

review and clear the sub projects from an environmental and social standpoint for onward transmission

for approval, (iv) Approval for Funding - Approval for funding will be will be subject to the FMEnv and

Bank’s review and approvals of the ESIAs. The total cost of preparing the ESIA is estimated US$

240,000. The institutional arrangement for the management of the ESMP is also elaborated.

Monitoring Plan

Chapter Nine contains a generic Monitoring Plan, with verifiable indicators, monitoring roles and

responsibilities to implement this plan. A lump sum of US$150,000 is estimated for bi–annual reviews.

Public Consultation

Chapter Ten discusses the strategy and outcome of different consultations held with key stakeholders in

participating states as well as the plan for further consultations. Feedback from participants centered on

the urgent need for provision of potable water supply, compensation for would be project affected

persons, prevention of disruption of utility services during civil works, and the employment of indigenes

during project implementation.

10

Budget

The total cost to implement the ESMF is estimated at US$514,000. The breakdown is as shown in the

table below:

Table 8.2: Estimated Budget for the Implementation of ESMF

S/N Activity Quantity Unit Cost ($) Total ($)

1 Training on implementation of

ESMF 4 31,000 124,000

2 Preparation of ESIA 3 80,000 240,000

3 Bi-annual Review of ESMF

performance 3 50,000 150,000

Total 514,000

11

CHAPTER ONE: INTRODUCTION

1.1 Background

Water is one of the basic needs of man and is a key driver of sustainable economic growth and poverty

alleviation. Water supply and sanitation are central to improvements in so many aspects of human

development, such as health, education and poverty reduction. The linkage between water supply and

sanitation and the poor performance of a cluster of key sectors, including Health, Education, Agriculture,

Environment, Industry, Power and Sub-urban development is obvious.

The Nigerian government, over the years have made efforts to improve the deplorable water supply and

sanitation situation in the country. The World Bank and other development partners have in the past

provided fund supports for the Rural, Small Towns and Urban water supply. The supports have assisted

the government to reach the current status of 58% national access to water supply and 32% access to

sanitation. However, despite the considerable investment in the Water and Sanitation sector, a large

population still does not have access to water in adequate quantity and quality.

According to the 2012 report of the UNICEF/WHO Joint Monitoring Programme (JMP) for Water

Supply and Sanitation, access to improved water supply in Nigeria nationally is 58% with 74% of the

urban population having access and 43% of the rural population. This implies that as many as about 70

million Nigerians have no access to improved water supply. The JMP report estimates that between 1990

and 2010, the percentage of urban drinking water coverage has fallen by 5%, from 79% to 74%. Many

households often the poorest end up purchasing water from private vendors much more expensively than

the public supply. Water supply services, where they exist, are still unreliable and of low quality and are

not sustainable because of difficulties in management, operation and pricing and failure to recover costs.

Many water supply systems show extensive deterioration and poor utilization of existing capacities, due

to under-maintenance and lack of funds for operation.

As part of continued efforts in ensuring water supply to the urban areas, the Nigeria government, through

the assistance of the World Bank is implementing the First and Second National Urban Water Sector

Reform Project (NUWSRP 1&2) in some selected states of Kaduna, Ogun, Enugu, Lagos, and Cross

River States. In order to build on the gains of the ongoing urban water sector reforms and to scale up

access to sustainable and improved water supply, the Federal Government of Nigeria has requested the

World Bank financing for the Third National Urban Water Sector Reform Project (NUWSRP3) which is

to cover principally three states, namely: Bauchi, Ekiti and Rivers States.

The proposed civil works to be carried out during the implementation of the project have raised

environmental and social safeguard concerns. The project is categorized as a B implying that the potential

environmental and social impacts will be minor, site-specific and manageable to a reasonable level. Based

on the information provided until this stage, the Project triggers four World Bank safeguard policies,

namely, Environmental Assessment (OP/BP4.01), Involuntary Resettlement (OP/BP4.12), Safety of

Dams (OP/BP 4.37) and Projects on International Waterways (OP/BP7.60).

Therefore, in compliance with Federal and State laws of Nigeria and the World Bank’s Safeguards

Policies, the Government of Nigeria, represented by the Federal Ministry of Water Resources (FMWR)

has to prepare this Environmental and Social Management Framework (ESMF), to establish a mechanism

to determine and assess future potential environmental and social impacts of the participating State Water

Agencies (SWA’s) subproject investments under the NUWSRP3, and then sets out mitigation, monitoring

and institutional measures to be taken during implementation and operations of the proposed investments,

to eliminate their adverse environmental and social impacts, offset them, or reduce them to acceptable

levels. Essentially, the ESMF draws heavily from that of the NUWSRP1 and NUWSRP2 which has been

revised as needed to reflect the characteristics and needs of the NUWSRP3.

12

The FGN is also further required to disclose this document in-country as a separate and stand alone

document so that it is accessible by the general public, local communities, present and future customers of

the water sector, potential project affected people, local NGO’s and all other stakeholders and also at the

infoshop of the World Bank and the date for disclosure must precede the date for appraisal of the project.

Since the project investments mentioned above have not yet been clearly identified, the three participating

states will be required to prepare a separate and stand alone Environmental and Social Impact Assessment

(ESIA), which would then subsequently have to be cleared by their States Ministry of Environment

(SMEnv), the Federal Ministry of Environment (FMEnv) and World Bank, prior to approval of their

planned/proposed investments. These ESIAs would be the instruments through which the sub projects

environmental and social impacts are identified and assessed. The ESIAs would also evaluate alternatives

and design appropriate mitigation, management and monitoring measures.

1.2 Objectives of the ESMF

The objectives of this ESMF are to:

Establish clear procedures and methodologies for the environment and social planning, review,

approval and implementation of subprojects to be financed under the project;

Specify appropriate roles and responsibilities and outline the necessary reporting procedures for

managing and monitoring environmental and social concerns related to subprojects;

Determine the training, capacity building and technical assistance needed to successfully

implement the provisions of the ESMF;

Establish the project funding required to implement the ESMF requirements; and

Provide practical resources for implementing the ESMF.

1.3 Scope of Work

The scope of work entailed:

(i) Collection and review of existing ESMF prepared for the NUWSRP1 & NUWSRP2;

(ii) Review of the Concept Notes of NUWSRP3 and participating states, Mission Aide Memoir’s,

Integrated Safeguards Data Sheet (ISDS), Project Implementation Manual (PIM), the Constitution

of the Federal Republic of Nigeria, numerous relevant federal, state, and local laws, regulations,

decrees, acts, policies and guidelines, World Bank Safeguards Policies and other relevant

documents;

(iii) Discussions and consultations with the National Project Coordinating Unit (PCU) of the FMWR,

FMEnv, SWAs, SMEnv, SEPAs, potential projected affected persons and other stakeholders;

(iv) Preparation of draft ESMF for review and

(v) Preparation of final ESMF.

Another Safeguards instrument, the Resettlement Policy Framework (RPF) has also been prepared as a

separate document. The RPF establishes the resettlement and compensation principles, organizational

arrangements and design criteria to be applied to meet the needs of the people who may be affected by the

project activities requiring land acquisition and /or denial, restriction or loss of access to economic

resources. The RPF will also be disclosed before appraisal of this project.

1.4 Study Approach and Methodology

This ESMF was prepared in accordance with applicable World Bank guidelines and safeguard policies as

well as the Nigerian environmental assessment guidelines. The distinct phases of the study include:

Literature Review/Desktop Studies;

Data Gathering /Collection of Baseline Information;

Field Visits and Stakeholders Consultation; and

Preparation of ESMF Report.

13

Literature Review/Desktop Studies

The approach was based on comprehensive review of previous works and literature on the NUWSRP and

the water sector in Nigeria as well as other strategic planning documents at the national and state levels.

Specifically the following were reviewed: existing ESMF prepared for the NUWSRP1 and NUWSRP2;

Concept Notes of the NUWSRP3 and participating states, Mission Aide Memoir’s, ISDS, PIM, federal,

state, and local environmental and water related laws, regulations, decrees, acts, policies and guidelines,

Roadmap for Nigeria water sector, World Bank Safeguards Policies; literature on general management

conditions for construction contracts and other relevant documents.

Data Gathering /Collection of Baseline Information

The approach entailed gathering and evaluation of relevant information from the PCU, SWAs, SMEnv

and SEPAs. Information obtained included institutional arrangements and capacity to implement

environmental and social management process and mitigation process at the state levels as well as

baseline data related to the physical, biological and socio-cultural environment for each participating

State.

Field Visits and Stakeholders Consultation

Field visits were carried out to participating states. During the visits, discussions and consultations were

held with State Project Implementation Unit (SPIU), officials of the SWAs, SMEnv and SEPAs. Officials

of the PCU of the FMWR and the FMEnv were also consulted. A questionnaire/check list was developed

to guide the consultation process. (See Annex 1 for complete list of officials consulted during the

preparation of the ESMF).

Using the specific circumstances of each state, the institutional arrangements and capacity to implement

the proposed environmental and social management process and mitigation measures was assessed and

discussions held to determine appropriate recommendations to determine appropriate recommendations

for improvement in service delivery, mitigation, monitoring, institutional requirements and their training

and capacity building needs.

It was observed that the SWAs remained extremely supportive of the planned NUWSRP3 and their level

of support was evident in their enthusiasm to participate and their lively contribution to the discussions

and field visits, and also in their verbal statements. In this spirit of commitment, support and ownership,

the recommendations reached in this report were jointly agreed to as reflecting the needs of the SWAs,

SMEnv and the SEPAs and were thus seen as sustainable. The discussions and consultations with the

FMWR, SWAs, SMEnv and SEPAs proved invaluable in designing and coming up with appropriate

solutions and recommendations that the SWAs could claim ownership of and thus ensure the

sustainability of the project as a whole. The discussions and consultations formed the backbone of the

work done by the consultant.

1.5 Structure of ESMF Report

The ESMF report is structured into ten chapters as follows:

Chapter One: provides a background to the project and discusses the objectives, scope, approach and

methodology of the ESMF study as well as the structure of the report.

Chapter Two: describes the proposed project, provides a broad overview and highlights the project

objectives and components.

Chapter Three: presents the baseline data of the water situation in the country and in the participating

states.

14

Chapter Four: discusses the triggered World Bank Safeguard Policies.

Chapter Five: describes the administrative, policy, legislative and regulatory framework for water

resource and environmental management.

Chapter Six: identifies the potential environmental and social impacts that may be associated with the

project and prescribes mitigation measures.

Chapter Seven: discusses the institutional assessment and the framework for environmental and social

management.

Chapter Eight: describes the environmental and social assessment process.

Chapter Nine: presents the monitoring plan and outlines the roles, responsibilities and cost of

implementing the plan.

Chapter Ten: discusses the Public Consultation process and highlights the concerns, feedback and

recommendations proffered by stakeholders.

15

CHAPTER TWO: DESCRIPTION OF PROPOSED PROJECT

2.1 Project Overview

The Third National Urban Water Sector Reform Project (NUWSRP3) is designed as a scale up to the on-

going First and Second National Urban Water Sector Reform Project (NUWSRP1&2). The lessons learnt

in the on-going urban water projects have been taken into account in the design of the NUWSRP3 so as to

make it have meaningful impacts and sustainable results.

The project development objective is to increase access to sustainable and safe water and improved

sanitation to households in three selected states. The strategic approach is to facilitate the transformation

of the way water supply services are provided, by supporting the introduction of sector reforms aimed at

improving efficiency and sustainability of operations, accompanied with significant improvements in

water service delivery in both quality and coverage.

The project adopted a three tier approach in the selection of participating states in order to maximize

impact, encourage performance based competition amongst states, promote transparency and to provide a

common platform to access funds from other donors. Three states under Tier-1, Bauchi, Ekiti and Rivers

States have been principally selected to participate in the project and will be supported with large

investments by the Bank.

2.2 Project Components The NUWSRP3 has three components. The project components and key activities under each of them are

discussed below:

2.2.1 Component 1: Rehabilitation and Expansion of Water Production and Distribution

Facilities and Small Towns Water Supply Improvement Through PPP in the Selected States. (Total of $300M)

Subcomponent 1.1 - Rehabilitation and Expansion of Water Production and Distribution Facilities

The Credit would support the three states, and any other reforming State (Tier 1) in completing ongoing

sector reform processes, as well as implementation of large investments to rehabilitate and expand water

production and distribution facilities to improve and extend access to water supply services in a

sustainable manner. Specific activities under this component would include:

(a) Technical Assistance to support consolidations of water sector institutional and regulatory reform,

including establishment and elaboration of respective legal and regulatory frameworks and entities;

capacity building of sector staff; institutional reforms; technical and legal studies, tariff and demand

studies, including serving vulnerable populations such as the poor; and other activities related to the

reforms in these States (including those elaborated under Component 2 below, as required);

(b) Rehabilitating and replacing aging and ill maintained pipes and collectors;

(c) Improving and extending services to the potential customers;

(d) Restoring capacity of water intake facilities and treatment plants, and storage capacity, etc.;

(e) Installation and provision of equipment and facilities that will permit a more technical management of

the water system, including managing water quantity, i.e. bulk and micro-meters, billing and accounting

system, GIS and geo-referencing software, equipment and appliance, including customer management

and office space; as well as water quality, such as water quality laboratories, equipment, chemicals and

associated facilities.

In Rivers State, the sub component will cover Port Harcourt and Obio Akpor Local Government Areas. It

will involve civil works encompassing primarily (i) rehabilitation and augmentation of water production

16

and treatment systems, (ii) rehabilitation and extension of water transmission and distribution networks,

and (iii) installation of house connections, customer and bulk meters.

In Bauchi State, this sub component will cover the city of Bauchi and will specifically entail:

Improvement of the transmission capacity from Gubi Dam Treatment Facilities to guarantee

uninterrupted water supply from Bauchi Water Treatment Plan to 22,000 m3 clear water reservoirs,

from where water is distributed to the city of Bauchi.

Rehabilitation of 50 km of the water distribution network in high-density population areas of the city,

serving among others the poor residents

Replacement of dysfunctional and installation of new water meters at production and major

distribution points at the network; connecting meters into a system that supports operation and

investment decision process

Equipping and rehabilitation of the Water Treatment Plant laboratory to provide accurate and timely

information on water quality to Bauchi WSB.

Emergency interventions for Ensuring Safe Water Supply to finance the implementation of the

activities recommended by the Dam Safety Review undertaken during project preparation for Gubi

Dam.

In Ekiti State, the sub component will support the SWA in improving capacity utilization, improved

distribution network and service coverage expansion in the capital city Ado Ekiti and the nearby

University town of Iworoko. This may entail rehabilitation of the Ero Water scheme; relaying of

distribution and extension pipelines and construction of reinforced concrete reservoirs.

Sub-Component 1.2 Small Towns Water Supply Improvement in the selected States.

This sub-component will support the implementation of pilot sub-projects in the provision of

small towns’ water services. The Small Towns water component will focus on individual or

bundles of towns that have been pre-identified, within the Tier 1 States being financed through the Bank

project. It will take lessons where appropriate from the experience of successful projects in Uganda,

Colombia and Paraguay, where “reverse concessions” allow the private sector in partnership with local

governments and water users associations to provide public and private financing for the construction

and/or operation of water supply systems under negotiated tariff. Payment may include an output-based

system where feasible.

In Rivers State, the Terabor water supply network extension project in Gokana LGA is proposed for

funding under this sub component whilst in Bauchi State, Ningi, Bununu, Yana, Kirfi and Darazo towns

are being considered to be funded. In Ekiti State, Iworoko, Ikere and Odo towns may likely be funded

under the sub component.

2.2.2 Component 2: Institutional Reform, Capacity Building and Emergency Works at the State

Level ($45M) This component will finance studies, training, goods, relatively small but critical emergency and

rehabilitation works and operational, financial, and administrative actions in the remaining nine selected

States to lay a solid foundation for reform. Support to these States will support: Tier-2 States and will

include establishment of water policy and law, customers enumeration (cadaster), improving revenue

billing and collection, tariff reform, regulatory reform, improving utility financial management and

accounting systems, reduction of non-revenue water including supply and installation of macro- and

micro metering, implementation of limited emergency works to maintain minimum service standards, and

strategic training of the State Water Agency (SWA) staff as well as development of urban water supply

master-plans. States preliminary identified under this tier-2 include Kano, Gombe, Benue, Jigawa, Ondo,

Abia, Bayelsa, Anambra, and Plateau. The component will work on making these States “finance-ready”

17

for large investments, ensuring that the adequate technical, environmental and social provisions are

incorporated into the investment plans.

2.2.3 Component 3: Institutional Reform, Capacity Building and Project Management at the

Federal Level ($15M) Institutional Reform at the Federal Level, Capacity Building and Project Management ($15M) – This

component will be implemented by the Federal Ministry of Water Resources, and will cover Capacity

Building and Institutional Reform, Performance Monitoring & Evaluation and Support to the National

Hydrological Information Services Agency ($9M) and Project Management ($6M).

Subcomponent 3.1-(a) Institutional Reform and Capacity Building at the Federal Level ($3M). This

subcomponent will support the establishment of a framework that allows a more transparent and efficient

support from the Federal level to the State level. It will comprise the clarification of roles and

responsibilities, innovative mechanisms for co-financing between level of governments (Federal, State

and Local), as well as the elaboration and enactment of associated regulations and financial tools.

Additionally this subcomponent will explore on the feasibility of establishing continuous federal

programs –rather than single projects – that can redress the current geographical and sub-sector dispersion

of donor’s funds that limit projects’ impact. Specific activities under this subcomponent include

financing a Water Public Expenditure Review, the establishment of a common accounting standards and

methodology for water sector boards, study and analysis for potential for unbundling services (production

and distribution) among others. The capacity building would also promote and advocate the use of

monitoring tools to track impact of sector interventions on the poor, vulnerable populations and impacts

by gender, including strengthening of the FMWR Sector M&E and its Gender Unit. Other areas

preliminarily identified for capacity building and to be confirmed during preparation include management

of asbestos-cement pipes, mapping and GIS, rehabilitation and maintenance cycles, security of water

works, asset managements, utility customer relation, pipe and network material and useful live, linkages

and management of sanitation and pollution among others. The capacity building will be carried out with

the support of the different decentralized National Water Resources Institutes being partially financed by

the Urban Water Sector Reform Project 2.

Subcomponent 3.1-(b) Performance Monitoring to Support Institutional Reform ($3M). The

subcomponent will also finance the Monitoring and Evaluation Framework for the project. The objective

of the Monitoring & Evaluation sub-component is to implement performance assessment of Nigeria water

state water boards at the Federal Ministry of Water Resources. The lack of reliable, full and up-to-date

information on the actual situation in the water sector is considered as a serious obstacle for the successful

implementation of the effective policy reforms and establishment of the efficient mechanisms of housing

and communal sector management in the country. The absence of objective and reliable data and

performance parameters lead to considerable financial losses as well as to the poor control of this life-

supporting sector in general. The proposed Performance Monitoring and Information System (PMIS)

based on the tools and instruments of the Bank International Benchmarking Network (IBNET), will assist

the Government in monitoring of the Water Boards performance and progress of sector reforms. The

PMIS will provide real-time presentation of full, valid and up-to-date information on conditions of water

boards and their performance, as well as provide information for comprehensive analysis and establish of

fact-based informed decision process in the water sector at municipal, regional and state levels.

The PMIS will (a) Provide comprehensive information and analytical support to water reforms in Nigeria

at the national, state and lower levels; (b) Guarantee comprehensive information flow on quality and

quantity of the water services provided to population and other customers; (c) provide objective

information for control and correction levels of the tariffs for water and sanitation at the national, state

and municipal levels, and for different customer groups; (d) enhance effectiveness of the management of

the water sector through improvement of the decision making processes on the basis of up-to-date,

18

comprehensive and reliable information on performance of water facilities; (e) generate information for

energy and other resources conservation actions; (f) monitor and prevent emergency situations; (g)

prevent or reduce risk of environmental damage by water and sanitations facilities and their customers.

The proposed pilot with water monitoring system is expected to (a) introduce performance monitoring

and benchmarking of the water sector in Nigeria through: (i) regular collection of technical and financial

data from water boards, (ii) launch of a specific monitoring and benchmarking entity in the Government

of Nigeria; (iii) increase the reliability of data through staff training, through proposed small investments

(e.g. water metering, accounting software, pressure monitor, etc.) and through proposed organizational

and/or managerial changes, and (iv) disseminate of the results to all stakeholders, and (b) Build capacity

to improve the collection and the reliability of the technical and financial data within companies operating

in the water and sanitation sectors both in the urban and peri-urban areas of Nigeria.

Subcomponent 3.1-(c) Support to the National Hydrological Information Service Agency ($3M).

Under this sub-component the project would support additional equipment, personnel and technical

assistance to reinforce the capacity to the Agency to provide reliable information for the Hydraulic and

Hydrological models for the State intervention under Component 1, namely Hydrogeological Areas III, V

and VI for Bauchi, Rivers and Ekiti respectively.

Subcomponent 3.2. Project Management ($6M). Additional fiduciary, safeguards and technical staff

would be financed under this component, as well as other operational and logistical incremental costs

associated with the project as well as for the implementation and supervision of Component 2 and 3

activities.

19

CHAPTER THREE: BASELINE DATA

3.1 Project Area and Location

Nigeria is situated in West Africa and it covers an area of 923,768 km2. It lies between latitudes 4

o and

14oN and longitudes 3

o and 15

oE. It shares its 4,047-km international border in the east with Cameroon

Republic, in the north with Niger Republic and Chad, and part of the western boundary with Benin

Republic. In the south, the country is bounded by the Atlantic Ocean’s Gulf of Guinea. Nigeria operates a

federal system of government. The Federal Republic of Nigeria is made up of 36 states and a Federal

Capital Territory (FCT) and 774 Local Government Areas (LGAs). There is a central government with its

headquarters at Abuja. It is now common for reasons of coordination and for representation in national

affairs to regroup the 36 states into six geopolitical zones as follows in Table 3.1.

Table 3.1: Nigeria’s Geopolitical Zones

Zone Constituent States

North West Jigawa, Kaduna, Kano, Katsina, Kebbi, Sokoto, Zamfara

North East Adamawa, Bauchi, Borno, Gombe, Taraba, Yobe

North Central Benue, Kogi, Kwara, Nassarawa, Niger, Plateau

South West Ekiti, Lagos, Ogun, Ondo, Osun, Oyo

South East Abia, Anambra, Ebonyi, Enugu, Imo

South South Akwa-Ibom, Bayelsa, Cross-River, Delta, Edo, Rivers

Federal Capital The Federal Capital Territory (FCT)

The states where the project will be implemented are Bauchi, Ekiti and Rivers States (see figure 3.1).

Bauchi State’s southern and northern limits are demarcated by latitudes 9°30' North and 12°30' North,

respectively, its western and eastern limits are bounded by longitudes 8°45' East and 11°0' East,

respectively. These mark the points of longest and widest stretches of the state. The state's total land area

covers about 49,259 sq. km, about 5.3% of Nigeria’s total land mass. In Bauchi State the project will be

carried out in the city of Bauchi and small towns of Ningi, Bununu, Yana, Kirfi and Darazo in Ningi,

Dass and Kirfi, LGAs.

Figure 3.1: Map of Nigeria showing the project States

Ekiti State is located between Longitudes 40 45

1 and 5

0 45

1 East of Greenwich Meridian and Latitudes 7

0

151 and 8

0 5

1 North of Equator. The State has common boundary with Kwara and Kogi States in the

North, Osun State in the East, Edo State in the West and Ondo State in the South. Ekiti State lies in the

savannah belt of Nigeria with total land area of 6,353 km2 (2,453 sq miles). In Ekiti State the project will

20

focus on the capital city Ado Ekiti and the University town of Iworoko in Ado and Irepodun/Ifelodun

LGAs as well as in Ikere and Odo towns in Ikere and Ado LGAs.

Rivers State is located in Southern Nigeria, in the delta region. Rivers State covers 11,077 square

kilometres. It is bounded on the south by the Atlantic ocean, to the north by Imo, Abia and Anambra

States, to the east by Akwa Ibom State and to the west by Bayelsa and Delta States. The project will be

carried out in Port Harcourt and Obio Akpor LGAs of the state.

3.2 Water Supply Status

3.2.1 National Water Supply Status

According to the 2012 report of UNICEF/WHO Joint Monitoring Programme (JMP) on Water Supply

and Sanitation, access to improved water supply in Nigeria nationally is 58% with 74% of the urban

population having access and 43% of the rural population. This implies that as many as about 70 million

Nigerians have no access to improved water supply. The JMP report estimates that between 1990 and

2010, the percentage of urban drinking water coverage has fallen by 5%, from 79% to 74%.

Rapid population growth has not been accompanied by an increase in the delivery of essential urban

services such as water supply, sewerage and sanitation, and collection and disposal of solid wastes. Many

households often the poorest end up purchasing water from private vendors much more expensively than

the public supply. Water supply services, where they exist, are still unreliable and of low quality and are

not sustainable because of difficulties in management, operation and pricing and failure to recover costs.

Many water supply systems show extensive deterioration and poor utilization of existing capacities, due

to under-maintenance and lack of funds for operation. There is vast disparity in the rates of Water Supply

and Sanitation (WSS) services across states.

3.2.2 Water Supply Status in Bauchi State

According to the Water Supply and Sanitation Baseline Survey (WSSBS) undertaken in 2007 less than

17% of the population of the state, had access to improved drinking water source. The average hours of

water supply do not exceed 7 hours a day due to the poor status of both the distribution network and the

12 km water main that supply clear water reservoirs from a major Water Treatment Plant (WTP). Also

substantial part of the network serving the poorest areas of the Bauchi city has not been replaced during

the last 40-50 years and calls for immediate replacement.

3.2.3 Water Supply Status in Ekiti State

The water supply situation in Ekiti State remains very poor with more than half the present population,

lacking access to safe, reliable and affordable potable water supplies. The current coverage and access

rate is less than 40%. This means that about 60% of the people of the State obtain their water from

alternative sources. These alternative water sources are usually very costly, often impose high labour

requirements for fetching water, and the quality may be suspect. In such a situation, it is usually the poor

or the low income earners that are the culprit, thereby denying them the right to access potable water.

This situation is as a result of or a combination of many factors, including but not limited to: The level of

investment in the sector has not been adequate to match the rapid population growth; Operational costs

are high due to poor power supply, high treatment requirements for surface water sources and long

pumping distances which in turn affect pumping duration; Water has been treated as a social service by

government, and there has been a lack of emphasis on cost recovery; Water unaccounted for is very high

due to ageing equipment and leakages in pipeline distribution networks recently occasioned by damages

during construction of roads, drainages, side walkways and roundabouts for city beautification; Lack of

coordination in the sector, and duplication of efforts between the various organizations. In addition, water

supply has been delivered from the “top-down” approach with government being responsible for all the

decisions. Most development plans have not followed bottom – up, demand-driven approach and has been

21

without community based inputs to planning, designing, operation and maintenance of schemes,

especially at small towns and even urban areas of the State.

3.2.4 Water Supply Status in Rivers State

The Water sector in Rivers State has had a fragmented governance structure with institutional

arrangements that were not properly streamlined. The current state of infrastructure in the state is poor;

caused by years of under maintained facilities as well as decayed and limited pipe network. As a result,

state citizens do not benefit from any water services of acceptable quantity, quality or reliability

standards, as the water system reticulation systems is largely non-existent. Out of the existing 190km of

pipe network only 10km is actually useable today, 180km is mainly asbestos cement pipes that lack

integrity or have been exhumed due to on-going urban renewal programmes. In view of this, water supply

services have declined rapidly over the last 10 years with the lack of funding to replace decayed

infrastructure. The population obtains water from a combination of private boreholes/shallow wells

(directly in their household or bought through intermediate vendors) and water sachets, with varying

quality, costs and availability.

3.3 Nigeria Water Resources and Sources

Nigeria has a vast surface water system (estimated at 226 billion m3) including the two major rivers, the

Niger and the Benue, which traverse the northwest and northeast portion of the country The confluence of

these two rivers is at Lokoja, after which they (river Niger) flow southwards into a Delta at the Gulf of

Guinea where it empties into the Atlantic Ocean.

The River Niger is the most important river in Nigeria and it is the third longest in Africa. The Niger rises

from the Futa Jallon High Lands in the Republic of Guinea, flowing for two thirds of its 4169km through

Guinea, Mali, the Republic of Niger and enters Nigeria from the west and then runs south easterly to

Lokoja, confluence with the River Benue. The Benue River, which has its source in the Cameroon flows

southwesterly to its confluence with the Niger. As the Niger and its principal tributary the Benue, flow

through the territory of nine other countries, this has raised many sub-regional, regional and international

issues for development and management. There are several other rivers and quite a number of minor

streams and rivulets that crisscross the entire Nigeria land mass. They serve as the source of raw water for

most of the State Water Companies in Nigeria which is treated and channeled as potable water for the

urban and peri-urban centers, which are the focus of the NUWSRP3.

Bauchi State is watered by a number of rivers. They include the Gongola and Jama'are rivers. The

Gongola River crosses Bauchi State in Tafawa Balewa LGA in the south and in Kirfi and Alkaleri LGAs

in the eastern part of the state, while the Jama’are River cuts across a number of LGAs in the northern

part of the state. Moreover, a substantial part of the Hadeja-Jama'are River basin lies in Bauchi State,

which along with various fadama (floodplain) areas in the state provides suitable land for agricultural

activities. These are further supported by the number of dams meant for irrigation and other purposes.

These include the Gubi and Tilde-Fulani dams. Gubi dam was constructed 25 years ago with an estimated

storage of 38.4 million cubic meters of water and could be best classified as an old generation dam. The

dam is a heterogeneous zoned multi-purposed earth fill founded entirely on the basement complex rocks

of Nigeria. The primary purpose of the dam is to supply potable water to Bauchi town and its environs.

Ekiti State is blessed with water resources, some of its major rivers are Ero, Osun, Ose, and Ogbese. The

main water scheme is the Ero River Water Project which serves over sixty two towns and villages. The

Ose River Water Supply Project also supplies potable water to Ekiti East and Ikere LGAs. There are four

dams in the state namely, Ureje, Ero, Egbe and Itapaji. Ureje dam in Ado Ekiti is supplied majorly by

Ureje River that originated at a settlement called Oke Aso in Ado Ekiti. There are other two streams

namely Omisanjana and Sije that took their sources from Ile- Abiye area all in Ado Etiki. Ureje River

reduces drastically while Sije dries up during dry season. Omisanjana River is perennial. Ero Dam located

22

at Ikun community in Moba LGA of Etiki State was commissioned in1985 to supply water to nine LGAs

in the State. The dam was located at a confluence of two major Rivers with many tributaries (Ero and

Okunrum).

In Rivers State the rivers which affect and have direct impact on the topography of include among others,

New Calabar, Orashi, Bonny, Sombreiro and Bartholomew. The main source of raw water in the state is

ground water.

23

CHAPTER FOUR: DESCRIPTION OF THE WORLD BANK SAFEGUARD POLICIES

4.0 World Bank Environmental & Social Safeguard Policies

This ESMF has been designed so that all investments under the NUWSRP3 will comply with all Federal,

State and local laws of Nigeria and the Environmental and Social Safeguard Policies of the World Bank.

In this chapter, the Bank’s safeguards policies and their applicability are discussed and in the subsequent

chapter those of Nigeria are presented.

The NUWSRP3 has been categorized as B implying that the expected environmental impacts are largely

site-specific; few if any of them are irreversible; and in most cases mitigation measures can be designed

relatively readily. The environmental assessment for a Category B project usually:

examines the project’s potential negative and positive environmental impacts,

recommends measures to prevent, minimize, mitigate, or compensate for adverse impacts, and

recommends measures to improve environmental performance.

The World Bank has 10+1 Environmental and Social Safeguard Policies. They have been designed to

help prevent and mitigate undue harm to people and their environment in the development process and

ultimately ensuring that environmental and social issues are addressed through the project cycle of a

World Bank –financed project. These operational policies include:

OP/BP 4.01: Environmental Assessment

OP/BP 4.04: Natural Habitats

OP 4.09: Pest Management

OP 4.10: Indigenous Peoples

OP 4.11: Physical Cultural Resources

OP/BP 4.12: Involuntary Resettlement

OP 4.36: Forests

OP/BP 4.37: Safety of Dams

OP/BP 7.50: Projects on International Waterways

OP/BP 7.60: Projects in Disputed Areas

Plus 1

OP/BP 17.50: Disclosure of Information

Details of the Bank’s Environmental and Social Safeguard Policies are presented in Annex 3 and can be

found on the World Bank’s official web site www.worldbank.org

The proposed project has triggered the following policies:

1. OP/BP 4.01: Environmental Assessment

2. OP/BP 4.12: Involuntary Resettlement

3. OP/BP 4.37: Safety of Dams

4. OP/BP 7.50: Projects on International Waterways

4.1 OP/BP 4.01: Environmental Assessment

This policy requires environmental assessment (EA) of projects/investments proposed for Bank financing

to help ensure that they are environmentally sound and sustainable, and thus improve decision making.

The EA is a process whose breadth, depth, and type of analysis depend on the nature, scale, and potential

environmental impact of the activities proposed for funding under the NUWSRP3. Environmental

Assessment takes into account the natural environment (air, water, and land); human health and safety;

social aspects (involuntary resettlement, indigenous peoples, and physical cultural resources); and

transboundary and global environmental aspects.

24

OP 4.01 is triggered if a project is likely to present some risks and potential adverse environmental

impacts in its area of influence. The environmental and social impacts of the NUWSRP3 will come from

the activities and investments to be made under Components 1 and 2 of the project.

In Bauchi State, this sub component will cover the city of Bauchi and will specifically entail:

Improvement of the transmission capacity from Gubi Dam Treatment Facilities to guarantee

uninterrupted water supply from Bauchi Water Treatment Plan to 22,000 m3 clear water reservoirs,

from where water is distributed to the city of Bauchi.

Rrehabilitation of 50 km of the water distribution network in high-density population areas of the

city, serving among others the poor residents

Replacement of dysfunctional and installation of new water meters at production and major

distribution points at the network; connecting meters into a system that supports operation and

investment decision process

Equipping and rehabilitation of the Water Treatment Plant laboratory to provide accurate and timely

information on water quality to Bauchi WSB.

Emergency interventions for Ensuring Safe Water Supply to finance the implementation of the

activities recommended by the Dam Safety Review undertaken during project preparation for Gubi

Dam.

In Ekiti State, the sub component will support the SWA in improving capacity utilization, improved

distribution network and service coverage expansion in the capital city Ado Ekiti and the nearby

University town of Iworoko. This may entail rehabilitation of the Ero Water scheme; relaying of

distribution and extension pipelines and construction of reinforced concrete reservoirs.

In Rivers State, the sub component will cover Port Harcourt and Obio Akpor Local Government Areas. It

will involve civil works encompassing primarily (i) rehabilitation and augmentation of water production

and treatment systems, (ii) rehabilitation and extension of water transmission and distribution networks,

and (iii) installation of house connections, customer and bulk meters.

A range of instruments are used to satisfy the Bank’s EA requirement. They include ESMF, ESIA and

Environmental Management Plan (EMP). However, since the exact technical details and location of the

investments in the three selected states will not be identified before appraisal of this project, the EA

process calls for the FGN, represented by the PCU at FMWR, to prepare an ESMF document.

OP 4.01 further requires that the ESMF report must be disclosed as a separate and stand-alone document

by the FGN and the World Bank as a condition for Bank appraisal of the NUWSRP3. The disclosure

should be both in Nigeria where it can be accessed by the general public and at the Infoshop of the World

Bank. This also fulfills requirement of OP 17.50 on Disclosure of Information.

This ESMF stipulates that each State Project Implementation Unit (SPIU) will have to prepare an ESIA,

during project implementation for their planned activities. Section 8.0 and Annex 3.0 sets the relevant

process and requirements of the ESIA’s.

4.2 OP/BP 4.12: Involuntary Resettlement

This policy would be triggered when the planned activities of the SWA’s cause involuntary taking of land

and other assets resulting in: (a) relocation or loss of shelter, (b) loss of assets or access to assets (c) loss

of income sources or means of livelihood, whether or not the affected persons must physically move to

another location. Land acquisition is expected to be minimal to none since civil works will largely be

rehabilitation of existing infrastructure, and some extensions of treatment facilities within current plant

boundaries, and of distribution networks alongside existing roads.

25

Significant efforts are to be made in the design and screening stages of proposed SWA’s project

investments, to avoid impacts on people, land, property, including peoples access to natural and other

economic resources, as far as possible. Nonetheless, uncertainties about the nature and scope of civil

works in the targeted states, if left unmitigated could result into displacement or loss of livelihood. Thus,

OP 4.12 will be triggered.

Therefore, a Resettlement Policy Framework (RPF) has been prepared by the government. The RPF

provides the framework for determining the need for and content of a Resettlement Action Plan (RAP) for

subprojects. The RPF sets the guidelines for the Resettlement and Compensation Plans that would have to

be prepared when project activities triggers this policy. The RAPs would have to be submitted to the

respective SMEnv and to the FMEnv for approval but would also have to be approved by the Bank as a

condition for that particular investment. OP 4.12 requires the RPF to be disclosed both in Nigeria and at

the Bank Infoshop before appraisal of this project can occur.

4.3 OP/BP 4.37: Safety of Dams

The Bank may finance types of projects that do not include a new dam but will rely on the performance of

an existing dam such as water supply systems that draw directly from a reservoir controlled by an existing

dam, diversion dams or hydraulic structures downstream from an existing dam, where failure of the

upstream dam could cause extensive damage to or failure of a new Bank-funded structure; and or

irrigation or water supply projects that will depend on the storage and operation of an existing dam.

Projects in this category also include operations that require increases in the capacity of an existing dam,

or changes in the characteristics of the impounded materials, where failure of the existing dam could

cause extensive damage to or failure of the Bank-funded facilities.

The NUWSRP3 will not fund the construction of new dams, large or small. However, the operations of

SWA’s depend either on the use of existing dams run, operated and owned by themselves in some states

or in other states by the River Basin Development Authority (RBDA) of that state, for one or a

combination of the following:

a. As a reservoir

b. To manage water flow and levels in rivers

c. Provision of raw water.

A dam Specialist is required to (a) inspect and evaluate the safety status of existing dam, its appurtenance

and its performance history (b) review and evaluate the owners operation and maintenance procedures

and (c) provide a written report of findings and recommendations for any remedial work or safety related

measures necessary to upgrade the existing dam to an acceptable standard of safety. A Dam Safety Report

(DSR) is to be prepared and disclosed to the public before project appraisal. However the Bank may

accept previous assessment of dam safety or recommendations of improvement needed in the existing

dam. If there is evidence that (a) an effective dam safety program is already in operation and (b) full-level

inspections and dam safety assessments of the existing dam which are satisfactory to the Bank have

already been conducted and documented.

4.4 OP/BP 7.50: Projects on International Waterways

This policy applies to the following type of international waterways:

(a) any river, canal, lake, or similar body of water that forms a boundary between, or any river or body of

surface water that flows through, two or more states1

- The rivers Niger and Benue each flow through at least one other neighboring country, and through

Nigeria.

1 The word “states” in OP 7.50 is referring to countries and not states within federated countries like Nigeria.

26

(b) Any tributary or other body of surface water that is a component of any waterway described in (a) above.

- Many other rivers in Nigeria are tributaries of the Niger or Benue rivers.

(c) Any bay, gulf, strait, or channel bounded by two or more states or, if within one state, recognized as a

necessary channel of communication between the open sea and other states, and any river flowing into

such waters.

Projects on international waterways may affect relations between the Bank and its borrowers and between

states (whether members of the Bank or not). The Bank recognizes that the cooperation and goodwill of

riparians is essential for the efficient use and protection of the waterway. Therefore, it attaches great

importance to riparians making appropriate agreements or arrangements for these purposes for the entire

waterway or any part thereof. The Bank stands ready to assist riparians in achieving this end.

This policy requires the PCU at FMWR, to formally notify riparians of the proposed NUWSRP3. During

the identification mission, the mission reminded its counterparts about the requirements of OP/BP7.50

that soon during the preparation stage, riparian countries would need to be notified of the Project and its

estimated impact including in terms of water abstraction.

27

CHAPTER FIVE: ADMINISTRATIVE, POLICY, LEGISLATIVE AND REGULATORY

FRAMEWORK

5.1 Administrative Structure for the Water Sector

The Federal Republic of Nigeria (FGN), is a federation of 36 states2 and the Federal Capital Territory

(FCT) in which the federal capital, Abuja is located. The administrative structure for the Water sector at

the three tiers of government is discussed below.

5.1.1 Administrative Structure at the Federal Level

The Institutions and Agencies responsible for the administration of Water resources and services at the

Federal, State and Local Government levels include:

The Federal Ministry of Water Resources (FMWR), initially created in 1976, is responsible for

formulating and coordinating national water policies, management of water resources including allocation

between states, and approving development projects. Specifically the functions of the FMWR include:

Establishment and operation of the National Water Quality Laboratories and Monitoring Network and

water quality standards.

Maintenance of database on water supply and sanitation facilities and performance.

Mobilization of national and international funding and technical support. Promote and coordinate

other collaborative activities by other government and Non-governmental agencies in the sector.

Provide technical support and assistance to the state and Local Government Water Supply and

Sanitation Agencies and the community water supply and sanitation committees.

Creation of an enabling environment for meaningful private sector participation in the sector.

Provision of a framework for regulation of private sector participation in water supply and sanitation.

Under Decree 101, formulate laws for private initiatives in the water supply industry.

The River Basin Development Authorities (RBDA’s), now 12 in total, were also created in 1976 for

planning and developing water resources, irrigation work and the collection of hydrological, hydro-

geological and meteorological data. Their main involvement in potable water supply has been the

provision of multi-purpose dams and the supply of water in bulk, some to urban water systems. The 12

River Basin Development Authorities (RBDAs) are purely responsible for the development, operation

and management of reservoirs for the supply of bulk water in their areas of jurisdiction. RBDAs report to

the FMWR on the quantity of water harnessed, sold or released for water supply.

The National Water Resources Institute (NWRI) was legally established in 1985 and is responsible to

the FMWR for engineering research functions related to major water resources projects and training

sector professionals and technicians. The NWRI is a training institute, designated to provide capacity

building training and education, data collection and dissemination services in the field of water resources

development and management. NWRI is currently conducting research on water quality for domestic use,

sedimentation levels of selected dams/reservoirs and their downstream socio economic impacts on

communities and on causes of flooding. Core functions of the institute include promoting and developing

training courses on Water Resources (Regular and Short Courses), carrying out capacity development

assessments of sector organizations and providing skill-oriented training courses.

The Utilities Charges Commission (UCC) was established in 1992 to monitor and regulate utility tariffs,

including those of State Water Agencies (SWA’s).

2 The 36 states are: 1)Abia, 2)Adamawa, 3)Akwa Ibom, 4)Anambra, 5)Bauchi, 6)Bayelsa, 7)Benue, 8)Borno, 9)Cross Rivers, 10)Delta,

11)Ebonyi, 12)Edo, 13)Ekiti, 14)Enugu, 15)Gombe, 16)Imo, 17)Jigawa, 18)Kaduna, 19)Kano, 20)Kastina, 21)Kebbi, 22)Kogi, 23)Kwara,

24)Lagos, 25)Nassarawa, 26)Niger,27)Ogun, 28)Ondo, 29)Osun, 30)Oyo, 31)Plateau, 32)Rivers, 33)Sokoto, 34)Taraba, 35)Yobe and 36)Zamfara.

28

The Nigeria Integrated Water Resources Management Commission was established in 2007 and

charged with the responsibility for the regulation and management of water in Nigeria and for other

matters connected with it. The functions of the Commission amongst others include:-

Implement regulatory policies on activities relating to the management of water resources in Nigeria;

Be responsible for economic and technical regulation of all aspect of water resources exploitation and

provision (construction, operation, maintenance and tariffs) of public and private water resources

infrastructure;

Ensure the safety and quality of water resources development and public water services by regulating

standards for execution and performance;

Issue water resources licenses in accordance with the provision Act.

Nigeria Hydrological Services Agency (NIHSA) is the custodian of all water resources data. The

Agency was established by the Federal Executive Council Approval EC 18 (07) 4 of 16th May, 2007.

Specifically the agency provides services required for assessment of the nation's surface and groundwater

resources in terms of quantity, quality, distribution and availability in time and space; for efficient and

sustainable management of water resources; operate and maintain hydrological stations nationwide and

carryout groundwater exploration ; and monitoring using various scientific techniques in order to provide

hydrological data needed for planning, design, execution and management of water resources and allied

projects. NIHSA’s activities and functions have direct relation to the management of watersheds. NIHSA

provides data to Federal and State MDAs such as Ministry of Environment, RBDAs and international

organizations such as FAO, UNDP.

5.1.2 Administrative Structure at the State Level At the State Level, responsibility for potable water supply was traditionally entrusted to departments of

the state governments, all 36 of them. In the 1970’s, as the demand for potable water supply grew, most

water departments of state governments were gradually transformed into State Water Agencies (SWAs),

to provide urban, semi-urban and, in some cases, rural water supply. The SWA’s are responsible to their

state governments, generally through a State Ministry of Water Resources (SMWR) though in some cases

under alternative arrangements. In some states, responsibilities for rural water supply remain with or have

been transferred back to a state government department; additionally, in several states, state rural water

and sanitation agencies have been set up largely to implement some government/donor funded Rural

Water Supply Strategy (RWSS) programs.

5.1.2.1 Administrative Structure for Water Sector in Bauchi State The Ministry of Water Resources established in 1998 is the umbrella Ministry for the provision of potable

drinking water to the state, as well as management of dams and reservoirs for hydro power or irrigation

purpose. Bauchi State Water Board (BSWB), an Agency under the supervision of the Ministry established

in 1998, is responsible for the provision of water to the Urban and Small towns. The Bauchi State Rural

Water Supply and Sanitation Agency (RUWASSA) which was established in August 2011 is responsible

for provision of potable water and sanitation facilities to the rural communities of the State.

5.1.2.2 Administrative Structure for Water Sector in Ekiti State Delivery of water and sanitation services in the State has been through the State Agencies such as the

State Water Corporation and the newly established Ekiti State Rural Water Supply and Sanitation

Agency. The Water Corporation is responsible for the management, operation and maintenance of urban

based water schemes, while a unit of small town water supply in the corporation is responsible for water

supply in semi-urban/small towns. The State Agency for Rural Water Supply and Sanitation is

responsible for rural water supply and sanitation delivery in rural communities of the State. These

agencies are currently being supervised by the Bureau for Infrastructure and Public Utilities headed by a

Special Adviser to the Governor. Apart from these agencies, the Department for Millennium

29

Development Goal (MDG) in the Ministry of Integration and Inter-Government Affairs is also involved in

water supply service provision particularly to rural communities/small towns, schools and government

establishments such as Hospitals and public places such as market and abattoirs.

5.1.2.3 Administrative Structure for Water Sector in Rivers State The Ministry of Water Resources & Rural Development (MWRRD) has the mandate to deliver potable

water to the people of Rivers state and the main policy making body for water in the state. The key

agencies include Port Harcourt Water Corporation PHWC, Small Towns Water Supply Agency

(STOWA) and the State Regulatory Commission. The PHWC oversee affairs of water service delivery in

Port Harcourt city. Specifically, the function inter-alia include: control and manage all existing State-

owned water and sewerage infrastructure and assets for public, agricultural, domestic, industrial and

general purposes in its area of operation; develop, manage, operate and maintain new water and

waste/sewage infrastructure and assets for the purpose of providing wholesome, potable water for

domestic consumption of the public, water for commercial, industrial, scientific and other uses in its area

of operation; supply wholesome portable water to consumers; identify and implement projects for the

provision of water and sewage management services which may be undertaken with private sector

participation; and promote the rational use of water resources and potable water. The STOWA oversee

water service delivery in other towns of the state.

5.1.3 Administrative Structure at the local Level At the Local Government Level, the Local Government Authorities (LGAs), of which there are 774

nationally, are responsible for the provision of rural water supplies and sanitation facilities in their areas,

although only a few have the resources and skills to address the problem. Only few LGAs have rural

water supply divisions that are able to construct small water systems such as open wells and small

impoundments of surface water.

5.2 Administrative Structure for Environmental Management at the Federal Level The Institutions and Agencies responsible for regulating and monitoring environmental issues and

information at the Federal Government level include:

5.2.1 The Federal Ministry of Environment (FMEnv)

The Federal Environmental Protection Agency (FEPA) now the Federal Ministry of Environment

(FMENV) established through Decree No. 58 of 1988 as amended by Decree No. 59 of 1992 is the

statutory government institution mandated to coordinate environmental protection and natural resources

conservation for sustainable development in Nigeria. The Ministry’s mandate inter alia is to:

* Protect the environment and conserve natural resources, including procedure for environmental impact

assessment of all developing projects.

* Advise the Federal Government on National Environmental Policies and priorities, the conservation of

natural resources and sustainable development and scientific and technological activities affecting the

environment and natural resources.

* Prescribe standards for and make regulations on water quality, effluent limitations, air quality,

atmospheric protection, ozone protection, noise control as well as the removal and control of hazardous

substances, and;

* Monitor and enforce environmental protection measures.

Within FMENV, there is an Environmental Impact Assessment Division, headed by a Deputy Director, to

take all responsibility for EIA related issues and within the EIA Division is the Impact Mitigation &

Monitoring (IMM) Branch, with a special responsibility for monitoring the implementation of

Environmental Management Plans (EMP) contained in the approved EIAs.

30

As contained in FEPA Decree No. 58 of 1988 and No. 59, 1992, the Ministry has developed instruments

of intervention to halt environmental degradation in form of policies, regulations, standards, and

guidelines.

5.2.2 National Environmental Standards and Regulations Enforcement Agency (NESREA)

The National Environmental Standards and Regulations Enforcement Agency (NESREA) was established

by NESREA Act No 25 of 2007 as a parastatal of the then Federal Ministry of Environment, Housing and

Urban Development (now FMENV). By the NESREA Act, the FEPA Act Cap F 10 LFN 2004 has been

repealed. NESREA is charged with the responsibility of enforcing all environmental laws, guidelines,

policies, standards and regulations in Nigeria. It also has the responsibility to enforce compliance with

provisions of international agreements, protocols, conventions and treaties on the environment. The vision

of the Agency is to ensure a cleaner and healthier environment for all Nigerians, while the mission is to

inspire personal and collective responsibility in building an environmentally conscious society for the

achievement of sustainable development in Nigeria.

5.3 Administrative Structure for Environmental Management at the State Level Through State Edicts the State Ministries of Environment are responsible for environmental protection

within their states. Act No. 58 of 1988, as amended by Act No. 59 of 1992, which established FEPA, also

issued a federal directive to the states to establish State Environmental Protection Authorities. Bauchi and

Ekiti States have functioning Environmental Protection Agencies.

5.3.1 Administrative Structure for Environmental Management in Bauchi State

The Ministry of Environment established in March 2010 oversees all environmental agencies and their

activities in the State. Bauchi State Environmental Protection Agency (BASEPA) a parastatal under the

supervision of the Ministry established by an edict No 10 of 1994 as amended by Edict No 3 of 1997 is

responsible for regulation of urban environmental sanitation, environmental protection, biodiversity

conservation and the sustainable development of the State’s Natural Resources. BASEPA mandate also

includes implementation of environmental policies towards protection, sustenance and development of the

environment in general.

5.3.2 Administrative Structure for Environmental Management in Ekiti State The Ekiti State Ministry of Environment established in 2000 has the overall responsibility for

environmental protection in the state. The function of the Ministry includes; management and

development of state forestry; promotion of environmental health and sanitation, nature conservation;

wide life preservation; and pollution control. The Ministry has two Agencies under its jurisdiction, the

Ekiti State Environmental Protection Agency (EKSEPA) and the Ekiti State Waste Management Board

(EKWMB) which is responsible for waste management in the state.

The functions of EKSEPA inter alia is to ensure the protection of environment against all forms of

pollution on air, water, land and vegetation and promote efforts, which will prevent or eliminate damage

to the environment and biosphere and stimulate the health and welfare of citizens of the state.

5.3.3 Administrative Structure for Environmental Management in Rivers State The Rivers State Ministry of Environment is responsible for the promotion of a healthy and clean

environment. It formulates, executes and reviews policies on environmental/ecological programmes and

projects in the state. The Ministry of Environment which was created in 2003 subsumed the functions and

activities of the Rivers State Environmental Protection Agency (RSEPA) established by the Rivers State

Environment Protection edict No. 2 of 1994.

31

5.4 Relevant Federal Policies

5.4.1 National Water Policy

A National Water Supply and Sanitation Policy (NWSSP) was adopted in January 2000. The center-piece

of this policy is the provision of sufficient potable water and adequate sanitation to all Nigerians in an

affordable and sustainable way through participatory investment by the three tiers of government, the

private sector and the beneficiary. The Policy sets consumption standards for;

(i) Semi – urban (small towns) which represent settlements with populations between 5,000 – 20,000

with a fair measure of social infrastructure and some level of economic activity with minimum supply

standard of 90 liters per capita per day with reticulation and limited or full house connections.

(ii) Urban Water supply at 120 litres per capita per day for urban areas with population

greater than 20,000 inhabitants to be served by full reticulation and consumer premises

connection.

The Policy Strategies are:

(i) Increase service coverage for water supply and sanitation nationwide to meet the level of the socio-

economic demand of the nation on the sector.

(ii) Ensure good water quality standards are maintained by water supply undertakings.

(iii) Ensure affordability of water supply and sanitation services for the citizens.

(iv) Enhance national capacity in the operation and management of water supply and sanitation

undertaking.

(v) Privatize water supply and wastewater services (where feasible) with adequate protection for the poor.

(vi) Through Legislation, Regulations, Standards and laws for water supply and sanitation.

(vii) Reform of the water supply and sanitation sector to attain and maintain internationally acceptable

standards.

5.4.2 National Policy on Environment - 1999 The National Policy on the Environment describes the conceptual framework and strategies for achieving

the overall goal of sustainable development in Nigeria. The goal of the Policy in particular is to:

secure a quality of environment adequate for good health and well-being;

conserve and use the environment and natural resources for the benefit of present and future

generations;

restore, maintain and enhance the ecosystems and ecological processes essential for the

functioning of the biosphere to preserve biological diversity and the principle of optimum

sustainable yield in the use of living natural resources and ecosystems;

raise public awareness and promote understanding of the essential linkages between the

environment, resources and development, and encourage individual and community participation

in environmental improvement efforts; and

Co-operate with other countries, international organizations and agencies to achieve optimal use

of trans-boundary natural resources and effective prevention or abatement of trans-boundary

environmental degradation.

The Policy outlines strategies for water resources management, along with the Water Resources Decree

No. 101 of the FMWR, and together they are concerned with:

Environmental Impact of Water Resources development at the planning stages.

Specification of water quality criteria for different users.

Establishment of adequate control and enforcement procedures.

Public health implications or water resources development projects.

5.5 Legal Framework

5.5.1 Existing Legal Provisions for Water and Sanitation Supply at the Federal Level

At the Federal Level, there is the Water Resources Act, Act No. 101 which is An Act to promote the

optimum planning, development and use of the Nigeria's water resources and other matters connected

32

therewith. The Act took effect on the 23rd

of August 2003, and vests rights and control of water on the

Federal Government of Nigeria. There are also Acts establishing the River Basin Development

Authorities and the National Water Resources Institute.

5.5.2 Existing Legal Provisions for Water and Sanitation Supply at the State Level

At the State Level, the various State Water Authorities/ Boards have enabling Edicts setting them up to

supply potable water to inhabitants of their respective states. The relevant Edicts in the participating states

are the Bauchi State Water Board Edict of 1998, Ekiti State Water Corporation Amended Edict of 1997

and the Rivers State Water Sector Development Law No 7 of 2012.

The respective state Edicts generally give the following functions to the SWAs;

To control and manage all waterworks vested, or to be vested, in the Board under the provisions

of the respective edict.

To establish, control, manage, extend and develop such new waterworks and to extend and

develop existing ones as the Board may consider necessary for the purpose of providing water in

order to meet the requirements of the general public, agriculture, trade and industry in the State.

To ensure that water is supplied to the customers thereof at reasonable charges and in potable

quality and adequate quantity.

The respective state Edicts empowers the Boards (SWAs);

To adopt with or without amendments such master plans for the maintenance and development of

its undertakings as its officers may prepare and submit from time to time.

To construct, reconstruct, maintain and operate waterworks and all other stations, buildings and

works, necessary for the discharge of its functions.

To carry any water pipe through, across or under any street or any place laid out or intended as a

street, and after giving reasonable notice in writing to the owner or occupier thereof, into, through

or under any lands whatsoever without paying compensation, but making good any damage done.

This power is in direct contradiction to the provisions of the World Banks OP 4.12 Involuntary

Resettlement and the provisions of OP4.12 must be complied with if the World Bank is to fund part

or whole of this NUWSRP3.

To abstract water from any lake, river stream, or other natural source.

This ESMF sets out the conditions under Nigerian Law and the Bank’s Safeguards Policies, for

which this can be done in the project. Notably, abstraction of water from any lake, river stream, or

other source under this project must be done consistent to the provisions of Bank Safeguards

Policies OP 4.01 on Environmental Assessment, OP4.04 Natural Habitats, OP4.37 Safety of Dams

and OP 7.50 Projects on International Waters and this ESMF.

From time to time, to examine any surface or under-ground waters for the purpose of determining

what, if any, pollution exists and the causes thereof.

To enter upon any land at any time for the purpose of laying, examining, repairing or removing

any water-pipe.

This power must also be exercised consistent with the provisions of OP 4.12 Involuntary

Resettlement.

To construct public fountains in any street or other public place in the state.

To acquire, purchase, lease, mortgage, hold, construct, manufacture or maintain any property

whatsoever whether movable or immovable, required for or in connection with the performance

of its functions and to sell, dispose of, or otherwise deal with such property or any part thereof.

This power must also be exercised consistent with the provisions of OP 4.12 Involuntary

Resettlement.

The details of the powers of each SWA vary from state to state and can be found in the respective edict of

each state establishing the SWA.

33

5.5.3 Existing Legal Provisions for Water and Sanitation Supply at the LGA Level

At the Local Government Level, the various laws setting them up define rural water supply as one of

their primary functions.

5.5.4 Federal Requirements for Environmental Impact Assessment (EIA)

EIA Decree No. 86 of 1992 is the principal legislative instrument relating to activities that may likely or

to a significant extent affect the environment. It sets the goals and objectives of EIA and procedures

including the minimum requirements for the conduct of EIA of public or private projects. The Decree

makes EIA mandatory for any major development project likely to have adverse impacts on the

environment. The Decree further specifies the content of an Environmental Impact Assessment. In

addition to the guidelines for EIA, Decree No. 86 contains provisions for the screening of projects

according to impact potential, including listed activities3 for which mandatory EIA preparation is

required.

Category I projects will require a full Environmental Impact Assessment (EIA).

Category II projects may require only a partial EIA, which will focus on mitigation and

environmental planning measures, unless the project is located near an “Environmentally

Sensitive Area” (ESA) in which case a full EIA is required.

Category III projects are considered to have “essentially beneficial impacts” on the environment,

for which an Environmental Impact Statement (EIS) will be prepared by the FMEnv.

EIAs are then submitted to the EIA Division of the FMEnv for approval and monitoring of the project

during implementation and operation based on an EMP in the EIA.

5.5.5 Land Use Act 1978

The legal basis for land acquisition and resettlement in Nigeria is the Land Use Act 1978 and modified in

1990. The following are selected relevant sections:

Section 1: Subject to the provision of this Act, all land comprised in the territory of each state in the

Federation are hereby vested in the Governor of each state and such land shall be held in trust and

administered for the use and common benefit of all Nigerians in accordance with the provisions of this

Act.

Section 2: (a) All land in urban areas shall be under the control and management of the Governor of each

State; and (d) all other land shall be under the control and management of the local government within the

area of jurisdiction in which the land is situated.

5.5.6 Other Relevant Federal and State Laws

FEPA/FMENV EIA Procedural Guidelines and Sectoral Guidelines on Infrastructure of 1995

FEPA Guidelines and Standards for Environmental Pollution Control in Nigeria, 1991.

The FEPA Harmful Wastes (Criminal Provisions) Decree No. 42, 1998.

FEPA National Effluent Limitation Regulations, section 18, 1991.

FEPA Pollution Abatement in Industries and Facilities Generating Waste Regulations, section 19,

1991.

Solid and Hazardous Waste Management Regulations of 1991.

National Guidelines and Standards of Waste Management in the Oil Industry.

Bauchi State Environmental Protection and Conservation Agency Edict No 3 of 1997.

3 Listed are activities that impact coral reefs, mangrove forests, small islands, tropical forests, areas with erosion-prone soils, areas prone to

desertification, natural conservation areas, wetlands of national or international importance, areas which harbor threatened or endangered species,

areas of particular scientific interest, areas of historic or archeological interest and areas of importance to threatened ethnic groups.

34

Ekiti State Environmental Protection Agency Law, CAP E12 of 2010.

Ekiti State Environmental Health and Sanitation Law No 4 0f 2004.

5.5.7 International Conventions

Nigeria is also a party to other international agreements on Biodiversity, Climate Change, Desertification,

Endangered Species, Hazardous Wastes, Law of the Sea, Marine Dumping, Marine Life Conservation,

Nuclear Test Ban, Ozone Layer Protection and Wetlands. Examples are;

The African Convention on the Conservation of Nature and Natural Resources, 1968

The Convention Concerning the Protection of the World Cultural and Natural Heritage, The

World Heritage Convention, 1972.

The Convention on International Trade in Endangered Species of Wild Fauna and Flora, CITES,

1973.

Convention on Conservation of Migratory Species of Wild Animals, 1979.

The Basel Convention on the Control of Transboundary Movement of Hazardous Waste and

Disposal, 1989.

The Framework Convention on Climate Change, Kyoto Protocol

The Convention on Biological Diversity, 1992

The Convention on the Prevention of Marine Pollution by Dumping of Waste, MARPOL, 1972

5.6 Membership of International River Basin Commissions.

Nigeria is a member of the following international River Basin Commissions:

Lake Chad Basin Commission (LCBC) - headquartered in N’djamena, Republic of Chad)

Niger Basin Authority (NBA) - headquartered in Niamey, Republic of Niger)

35

CHAPTER SIX: POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS

6.1 Introduction

The implementation of the NUWSRP3 will enhance economic, social and political development of

participating states through increased access to sustainable supply of safe water and improved sanitation

to households. The project interventions will however have some limited environmental and social

impacts.

The overall environmental and social impacts from planned activities of this project are likely to be

positive as the NUWSRP3 offers the unique opportunity to address some of the key structural issues

affecting the water sector in Nigeria. The holistic approach of this project offers the opportunity to (i)

implement fundamental structural reforms in this sector, (ii) undertake institutional and legislative

reforms to address many concerns in the sector including environmental and social issues, (iii) provide

capacity building measures to implement these reforms and (iv) monitor the performance of the sector

after the project. The project will also strengthen capacities in the SWAs, resulting in enhancement of

organizational, financial and technical capabilities of SWAs. This section presents an analysis of the

potential environmental and social impacts of planned project activities.

Since all sub-activities are yet to be identified, the impact assessment is based on potential impacts from

anticipated project activities. It is expected that during project implementation, the SWAs will prepare

project-specific EAs/ESIAs and ensure that the selected contractors adhere to the general environmental

management conditions for construction contracts. It is recommended that the general environmental

management conditions for construction contracts be included by the PCU at FMWR as a standard in all

Requests for Proposals (RFP) for EAs or ESIAs of water supply projects involving civil works.

The potential environmental and social impacts are described for rehabilitation/construction phase for

each of the major activities of the project especially as detailed in Component 1 and for the operational

phase of the project. Environmental impacts of each activity were assessed qualitatively for the different

environment media (air, water, soil, vegetation) and perceived socio-economic impacts were identified

from key socio-economic indicators i.e. livelihood, community structure, public health, land use and

population. The details of the potential environmental and social impacts during the different phases of

project activities are discussed below:

6.2 Potential Environmental and Social Impacts.

6.2.1 Rehabilitation/Construction Phase

6.2.1.1 Environmental Impacts

Potential Negative Impacts

The potential adverse environmental impacts that may arise during rehabilitation/construction phase for

each of the major activities of the project as detailed in Component 1 is presented below:

Rehabilitation and augmentation of water production and treatment systems; rehabilitation and

extension of water transmission and distribution networks

Air Quality: Rehabilitation and construction works could result in the emission of dust and other odours

that may lead to the reduction of air quality. Inappropriate transporting, storage and use of materials such

as cement, petroleum products may emit pollutants. Air Quality may also be impacted by emissions from

vehicles, earthmoving equipment and released particulate matters.

Noise & Vibration: Noise and vibration is expected especially due to movement of heavy machines and

the process of soil excavation to lay pipes etc.

Water Quality: Water quality in the project areas may be compromised due to the rehabilitation works.

This is because during the rehabilitation, water in the treatment plant may be tampered with, thus the

36

water flowing through distribution lines and getting to homes may change colour or become contaminated

due to on-going civil works. Ground water sources may be polluted through accidental spills of paints, oil

or grease and other hazardous products from heavy equipment and machinery used during construction

works.

Soil and Land Degradation: Earth-moving equipment such as excavators will be used in cutting and

excavation during these activities. These equipment may affect the quality and stability of soil thereby

exposing the soil to erosion and compaction resulting in the breakdown of soil structure which may

potentially decrease the drainage of the areas. Furthermore, the risk of accidental spills of paints, oil or

grease and other hazardous products from construction machinery also constitutes potential sources of

soil pollution.

Flora and Fauna: The civil works during the rehabilitation and construction activities may lead to

depletion of vegetation and plant cover. This is due to the fact that vegetation may have already covered

some areas where pipes were laid before and that the new areas that water pipes will be extended to may

also have vegetation covers and trees that will obstruct pipe lines. These areas will have to be cleared to

enable civil works to be carried out. It may also affect fauna habitats in the location especially during

excavation and replacement of pipes.

Waste Management: Activities at construction sites will generate construction wastes such as excavated

soils, debris and potentially hazardous materials (e.g. asbestos). These materials can pollute the land and

also affect the aesthetics of the environment.

Rehabilitation of old and malfunctioning water pumps and installation of house connections, customer

and bulk meters

Air Quality: Air quality may be compromised due to bad odours that may result from chemicals used in

house connection but this is expected to be minimal.

Waste Management: This activity is expected to generate waste materials from previous installations,

such as old water taps and water pumps. These may litter the environment if not properly disposed.

Rehabilitation of water treatment laboratory

Air Quality: The rehabilitation could result in the emission of dust and other odours that may lead to the

reduction of air quality. Air Quality will also be impacted by emissions from vehicles, other movable

equipment and released particulate matters.

Soil and Land Degradation: The rehabilitation and equipping of water treatment laboratory may involve

reconstruction of building and then soil digging and excavation which in turn will lead to soil and land

degradation.

Waste Management: Activities during rehabilitation, for example, repair and reconstruction of laboratory

buildings will produce construction wastes such as excavated soils and debris which could litter the area,

obstruct workers as well as affect the aesthetics of the environment.

6.2.1.2 Social Impacts

Potential Positive Impacts

The activities during the rehabilitation and construction phase of the project will have some positive

impact on the population and livelihood of the people. These impacts include:

Increased Trade and Enhanced Income: The rehabilitation/construction works will attract a lot of persons

into the communities which will in turn result in increased trade and enhanced income for dwellers.

37

Creation of Employment Opportunities: The rehabilitation/construction works will generate employment

opportunities for a lot of people thus enhancing their income and livelihood.

Potential Negative Impacts

Activities during the rehabilitation and construction phase of the project may have some potential adverse

impact on the population and demographic structure in the localities and on health. These impacts

include:

Restricted Access to Water & Poor/Compromised Water Quality: The distribution of water to some

locations may be stopped for some time to facilitate the rehabilitation process while civil works carried

out during rehabilitation/construction may contaminate water sources thereby compromising water quality

and access to water.

Inconveniences Due to Increased Traffic Congestion: Movement of heavy equipment and materials to and

from rehabilitation/construction site could result in increased road traffic congestion, disruptions and

accident. Improper management of construction waste could also cause obstruction and affect easy

movement of public.

Public Health: Increased population as a result of the civil works during the rehabilitation/construction

phase may lead to increase in the prevalence of Sexually Transmitted Diseases (STDs) including

HIV/AIDs. Improper construction waste management may also lead to increased vector borne diseases

while the use of heavy machinery and equipment can be a potential noise nuisance to local communities.

Increased Crime Rate: Movement of more people into communities due to civil works may automatically

increase the crime rate in those communities

Restricted Access to Residential Accommodation and Source of Livelihood: Civil works during the

rehabilitation/construction phase may temporarily disrupt movement in and out of residential

accommodation also persons whose economic activities are located along the Right of Way (ROW) will

lose income due to temporary disruption of access.

Over Stretching of Existing Facilities: The project activities will attract more people to the area, thereby

increasing the number of people using existing facilities/infrastructures.

Disruption of Utility Services: Rehabilitation/construction works may damage existing underground

services like communication and electrical cables, sewage pipes and other service lines which may lead to

disruption of services.

Damage to Existing Road Network: Pipe laying and rehabilitation may result in damage to existing road

in location where the road construction may have encroached the water pipeline ROW.

Displacement of People: Land take may lead to displacement of people.

Occupational Health and Safety: Construction works such as: excavations; working with heavy

equipment; working in confined spaces; working on and along the traffic roads; heavy lifting, storage,

handling and use of dangerous substances and wastes, working under noisy conditions will expose the

workers to occupational health and safety hazards predisposing them to injuries and accidents.

6.2.2 Operational Phase

6.2.2.1 Environmental Impacts Potential Negative Impacts

38

During the operational phase, there could be effect on ground water as a result of over abstraction and

water flow rate may become low. There could also be water stagnation, water logging and water wastage

especially if there are burst pipes. Burst pipes during the operation phase can affect the aesthetics of the

environment and affect free movement of people in the locality.

6.2.2.2 Social Impacts

Potential Positive Impact

Activities during the operational phase of the project will have some positive impact on the livelihood of

the people, on health and availability of infrastructure. These impacts include:

Improved Quality and Quantity and Reliability of Water Supply: Enhanced water production and

distribution capacity as well as reduced losses from leakages will lead to increased quality and quantity of

water supply. The provision of improved and modern laboratory equipment and facilities that can

guarantee early detection of water contaminants will also enhance water quality.

Improved Sanitation and Hygiene and Reduced Prevalence of Diseases: Improved water supply and

sanitation facilities will lead to improved sanitation and hygiene which would consequently reduce water

and sanitation related diseases thereby reducing child mortality.

Gain of Time Especially for Girls and Women: Uninterrupted water supply will reduce the amount of

time girls and women use to source water. Such time would now be channeled to more economically

viable activities e.g. trading, schooling, farming etc.

Overall Economic Productivity: Businesses that use water as raw materials will be attracted to the

communities due to the availability of water thereby increasing the economic productivity of the

communities/towns.

Poverty Alleviation: Through cost savings on purchasing water from alternative sources and treatment of

water related diseases.

The project will also facilitate the attainment of Millennium Development Goal (MDG) 7 of reducing by

half the proportion of people without sustainable access to safe drinking water by the year 2015 and

beyond.

Potential Negative Impact

During the operational phase of the project there may be some negative impact on the population and

demographic structure in the localities and on health. These include:

Increased Malaria Prevalence: Burst pipes during the operational phase of the project may result in water

stagnation and logging which may in turn enhance the breeding of mosquitoes thereby increasing the

prevalence of malaria.

Increased HIV/AIDs Prevalence: Availability of water may consequently lead to increased population as

a result of influx of persons from neighbouring communities. This would in turn increase the possibility

of increased HIV prevalence

Loss of Means of Livelihood: Provision of water to communities /town may result in loss of means of

livelihood to local and commercial water vendors servicing the communities/towns

A summary of the potential environmental and social impacts of the project is shown in Table 6.1.

Table 6.1: Summary of the Potential Environmental and Social Impacts of the NUWSRP3

Planned Activities Environmental

Media

Environmental Impacts/Issues

Social Media

Social Impacts/Issues

Adverse Positiv

e Adverse Positive

Construction Phase

Rehabilitation and

augmentation of

water production and

treatment plant;

Rehabilitation and

extension of water

transmission and

distribution networks

Air Construction works, vehicular

emission and movement of

earthmoving equipment may affect

air quality through the release of

particulate matter and other

pollutants.

Inappropriate transporting,

storage and use of materials such as

cement, petroleum products may emit

pollutants.

Movement of heavy machinery

may generate noise.

Community

Structure

NA NA

Water Ground water may be polluted

through accidental spills of paints, oil

or grease and other hazardous products

from heavy equipment and machinery

Livelihood Civil works may

contaminate water thereby

compromising water

quality and access to water.

Improper management

of excavated waste could

cause obstruction and

affect easy movement of

public.

Increased number of people

as a result of construction works

will lead to increased trade and

enhanced income for dwellers.

Creation of employment for a

lot of people and thus enhance

their income and livelihood.

Soil/Land Heavy equipment and

machinery at construction sites may

compact soils and cause drainage

problems.

Excavation works may also

cause soil erosion.

Accidental spills of

hydrocarbons from heavy equipment

and machinery may result in pollution

Generation of construction

wastes can also impact the land

Community

Infrastructure

Vegetation Site clearing may lead to depletion of

vegetation and plant cover as well as

Public Health Noise nuisance from

construction activities may

40

affect fauna habitat. affect quality of life

Likely increase in HIV

prevalence rate due to

increased population

influx.

Vector borne diseases

may arise from improper

management of wastes

Accidents & injuries

from civil works

Land Use Land take may lead to

displacement of people

Population/

Demographics

Increased population

and attendant crimes due to

movement of more people

into the cities

Rehabilitation of old

and malfunctioning

water pumps and

installation of house

connections,

customer and bulk

meters.

Air Bad odour resulting from

chemicals used in house connections

may affect air quality.

Community

Structure

NA

Water NA Livelihood Installation process

may interrupt water supply.

Restricted access to

residential

accommodation &

source of livelihood

Soil/Land Waste materials from previous

installations if not properly disposed

may litter the environment.

Community

Infrastructure

Over stretching of

existing facilities

Damage to existing

road network

Improved and modern water

pumps would facilitate discharge

of water in the city

Vegetation NA Public Health NA

Land Use NA

Population/

Demographics

NA

Rehabilitation of

water treatment

laboratory

Air Laboratory repairs may emit

pollutants that may compromise air

quality.

Community

Structure

NA

41

Water None Livelihood NA

Soil/Land Construction works including soil

digging and excavation which in turn

will lead to soil and land degradation.

Community

Infrastructure

Vegetation NA Public Health NA

Land Use NA

Operational Phase

Air NA. Community

Structure

NA

Water Water use may lead to reduction

of underground water

Livelihood NA Uninterrupted water supply

will be guaranteed.

Gain of time especially for

girls and women.

Overall economic

productivity.

Soil/Land Water leakages from burst pipes

may result in water stagnation and

logging.

Community

Infrastructure

Improved and modern water

reservoirs through which clean

water can be pumped to the entire

community.

Improved and modern

laboratory equipment and facilities

that can guarantee early detection

of water contaminants.

Vegetation NA Public Health Water stagnation and

logging may enhance the

breeding of mosquitoes

thereby increasing the

prevalence of malaria.

Increased population

could also increase HIV

prevalence rate.

Improved water supply and

provision of sanitary facilities will

lead to improved sanitation and

hygiene and consequently

reduction in water and sanitation

diseases and reduced child

mortality.

Land Use NA

Population/

Demographics

Increased population as a

result of availability of

water supply.

Note: NA is for “Not Applicable”

6.3 Mitigation Measures

These include measures that can reduce the negative impacts associated with sub-project activities.

Potential impacts and the appropriate mitigation measures are identified in Table 6.2. The Table indicates

the areas to which the potential impact applies. In addition, mitigation measures are identified as either

social or physical measures. The measures serve as the basis for the cost estimates. During

implementation, the mitigation costs will be included in the bid for sub-project activities.

Table 6.2: Summary of Environmental Mitigation Measures

Potential Impacts Recommended Mitigation Measures

Physical

Noise

Disturbance of individuals in the vicinity during

reconstruction works employees and communities exposed

to high noise level. Noise is expected especially due to

movement of heavy machines, soil excavation to lay pipes

etc.

Installation of sound insulation such as silencers, mufflers, etc; Use appropriate well serviced machinery to reduce noise output

Air Quality

Air quality will be impacted upon considering that

inappropriate transporting, storage and use of materials

such as cement, petroleum products may emit pollutants.

Also excavation of soil to lay pipes may release dust

particles to pollute the environment.

Safety measures in transportation and handling of

materials should be adopted.

Materials, e.g cement should be well covered during

transportation

Workers should use PPEs (nose masks) during soil

excavation and other works that will lead to release of

dust.

Implement the measures to control spillage of toxic

substances that will be included in construction

contracts, including: guidelines for the proper storage

and sitting of hazardous material such as oil, grease,

fuel, asphalt, or ignitable and corrosive materials;

lubricants will be collected in clearly marked

containers and reused if possible, or disposed of at

properly regulated offsite locations; water samples

will be taken and tested for oil when there is a risk of

spills or leakages to canal waters, surface waters, or

groundwater.

Soil

Soil will be impacted considering that heavy equipment and

machinery at construction sites may compact soils and cause

drainage problems. Also the excavation of soils may cause

damage to soil structure

Minimal impact on soil should be carried out where

appropriate. Heavy machines should be removed from

site as soon as they are no longer in use.

Water Quality and Quantity

There will be improvement in water quality. Uninterrupted

water supply will be guaranteed. Also, water quality will be

ensured with the rehabilitation and re-equipment of laboratories.

Water quantity and access may be reduced due to reconstruction

and rehabilitation activities

None

Communicate to people on when water will be

stopped to facilitate repair activities, reduce time

period when water flow is disrupted.

Biological Resources

Vegetation

43

Potential Impacts Recommended Mitigation Measures

Vegetation may be affected considering that pipes will be

laid and soil will be excavated thus and vegetation will be

affected.

Avoid shrubs, trees and fallen timber. Minimize

clearance of natural vegetation.

Revegetate disturbed non -operational land.

Wildlife

Wildlife may be impacted. Create buffer zone or restricted area around site

Wetlands

May be impacted Create buffer zone

Farmlands and Grazing Areas

Loss of farmland and grazing areas may occur. Create buffer zone

Solid/Hazardous Waste Management

Waste containing potentially hazardous materials (e.g.

asbestos) may be generated during construction

Quick sorting, collection and disposal of waste

removed from the sites in accordance with applicable

regulations.

Employ services of registered waste management

company

Social

Health and Safety

Risks of communicable and sexually transmitted diseases due to high

influx of people to cities as a result of improved infrastructure.

Worker exposure to occupational health and safety hazards.

Conduct an awareness raising campaign for

the localities.

Develop, produce and circulate leaflets to

educate people of dangers of sexually

transmitted diseases and how to prevent

them.

Print posters to educate people on

HIV/AIDS.

Site specific HSE plans should be

developed and implemented.

Workers should comply with HSE rules and

instructions.

Workers should be provided with Personal

Protective Equipment and usage enforced.

Safety signages should be displayed at

appropriate locations

An Emergency Response Plan should be

prepared and approved before

commencement of work..

Table 6.3 shows typical stages of water treatment plant activities, their impacts (positive and negative)

and mitigating measures.

44

Table 6.3: Impacts from Activities in the Water Treatment Plants Key/Typical Activities in Water

Treatment Plants

Impacts Mitigation Measures

Positive Adverse

1st Step: Provision of Raw Water into

Rivers .

From Dams and Reservoirs owned

and operated by SWA’s or RBDA’s,

depending on what prevails in each

state.

Weirs constructed across river

channels downstream of raw water

intake point to ensure sufficient

water head upstream of intake.

Large quantities

of water stored

for controlled

use in SWA’s

and irrigation

during dry

spells.

Flooding of river banks.

Dam Failure

Weirs across rivers affects water levels and

flows for down stream users, especially

during dry season.

Implementation of measures in Dam Safety

report, especially ensuring that maintenance

budget available to owners/operators to undertake

preventive and corrective maintenance and early

warning/response for emergency situations.

Monitor water levels downstream of weirs to

ensure downstream users can sustain livelihoods.

2nd Step: Raw Water Extraction.

From river sources using large

electric and powerful suction pumps.

i) Pollution of water , air and natural habitats

from lubricant and fuel leaks from operation

of large suction pumps and large stand-by

power generators (e.g. 0.5mega watt).

ii)effects of reduction of water levels due to

excessive extraction of raw water from rivers

on downstream users e.g. irrigated farms,

fishermen, other industries).

iii) Also, excessive raw water extraction may

lead to possible draining of wetlands over

time and disturbance of natural ecosystems.

iv) Siltation on river bed to upstream soil

erosion exacerbated by water extraction.

i)Carefully designed regimes for safe operation

and maintenance of these heavy equipments, and

safe transportation and storage of lubricants and

fuel for same. Safe and suitable housing of pumps

and generators.

ii) Maintenance of minimum water levels in

rivers, downstream of intake. Maintain good and

reliable records of quantities of raw water

extracted. Sensitization of downstream users.

Monitoring of water levels downstream of intake.

(iii) Draining of wetlands not allowed. Regular

monitoring of effects on critical nearby

wetlands required.

iv) controlled dredging and suitable disposal of

material.

3rd Step: Sedimentation.

Standard method is by gravity flow

after intake to reduce turbulence. Raw

water is then mixed with Alom (

segregator) and pre-lime before water

enters clarifiers where the

sedimentation process occurs,

producing sludge which is then

extracted from the system. The

clearer water moves on by gravity to

the next step.

i) Contamination of rivers when sludge is

return untreated downstream of intake ,

adding to pollution levels in water for

downstream users.

Contamination of land when sludge is

dumped untreated on site.

ii) Contamination of surrounding land and

nearby water sources from inappropriate

transport, storage, handling, mixing of

chemicals and leaks of pipes supply

chemicals into system

i) treatment of sludge to rid off pollutant

chemicals in it either by in-situ treatment plant

and then return to river or continuous re-cycling

in water treatment plant.

Do not just dump untreated sludge on nearby

land.

ii) Suitable storage of chemicals in secure bags

and off the floor in well ventilated and secure

stores. Safe transportation of chemicals to mixing

areas and for introduction into supply piping

systems, and appropriate and safe disposal of

wasted and left over chemicals. Regular

inspection and repairs of piping systems.

4th Step: Filtration.

Water now enters the filtration

process which is through compacted

sand filters (progressive compaction

pattern of different sizes of sand grain

particles).

i) contamination from inappropriate disposal

of filtered waste material.

ii) and waste material from sand filters

cleaned by back-wash.

Suitable disposal of filtered waste through sludge

treatment plant or –re-cycling method. No

dumping on site allowed.

45

5th Step: Clear Water Quality

Control/ Chemical Treatment:

Immediately after the filtration

process, the clear water is tested to

determine quantities of Lime ( to

balance Ph) and chlorine ( to kill

harmful micro-biological organisms.)

to be added.

Each SWA has a Water Quality

Control Lab in the water treatment

plant.

Safe and potable

water produced

has good

positive impacts

on the

environment

and public

health of the

citizenry.

i) Contamination of surrounding land and

nearby water sources from inappropriate

transport, storage, handling, mixing of

chemicals and leaks of pipes supply

chemicals into system.

ii) Quality and reliability of lab services in

terms of adequate lab technicians, frequency

of testing regime, compliance with testing

regime, reliability and suitability of

equipment, close supervision of staff and

other due diligence practices, is questionable.

There is insufficient frequency of testing at

various stages.

There is no testing for the presence of

harmful chemical substances. Generally the

presence of harmful chemical substances such

as mercury, lead, arsenic and cyanide is not

conclusively determined. Chlorine works

against microbiological substances only.

Apparently, chemical tests responsibility of

State environment agencies only.

i) Suitable storage of chemicals in secure bags

and off the floor in well ventilated and secure

stores. Safe transportation of chemicals to mixing

areas and for introduction into supply piping

systems, and appropriate and safe disposal of

wasted and left over chemicals. Regular

inspection and repairs of piping systems.

ii) Lab services need to be drastically improved.

Better and modern equipment needed and

guarantee of supplies required. Some labs often

run out of testing material.

Better trained water chemist, biologist and other

water scientists in labs. required.

Better testing regime and improved frequency of

testing required.

Testing must include the determination of

harmful chemical substances too and effective

treatment or emergency plans where the presence

of dangerous levels detected in water leaving the

filtration stage required.

Closer supervision of lab. staff required.

Introduction of a Watch Dog body required ( see

later sections) to monitor these measures.

6th Step: Bulk Storage of Clean

Water.

Potable treated water is now pumped

to bulk storage/balancing tanks.

In some cases the water in these tanks

is tested again to check that the Ph

level is balanced, absence of micro-

biological substances, turbidity and

other tests.

i)Poor security around Bulk storage tanks,

presenting opportunities for sabotage,

terrorism etc.

ii) poor recording keeping. Unable to

independently determine efficiency of plant

in terms of losses from calculation of intake

and output quantities.

i) Need to completely fence off perimeter around

water treatment plants, better and more secure

manhole covers on tanks, more frequent testing of

water in bulk storage before it is pumped out for

distribution.

ii) Introduce a records Database/MIS.

7th Step: Distribution to Network .

i)Gravity feed from overhead tanks

into reticulation network.

ii) Distribution /connection to

consumers, customers.

iii) network expansion.

i)More pollution from significantly greater

waste water inappropriately disposed off.

ii) contamination due to illegal connections,

leaks from burst pipes, and sanitation

infrastructure in a state of disrepair can

adversely impact environmental public

health.

The SWA’s would have to introduce maintenance and monitoring program that covers all stages of their operations. This program would have to be fully

funded, with key institutional support, defined responsibilities and accountable to the top leadership, if adverse impacts are to be sustainably mitigated. This

may require new legislation at both the federal and states level to enforce this requirement. Above all, a fundamental shift in attitudes of the employees of the

SWA and their customers towards due diligence work, willingness to maintain standards and care for the environment is required.

CHAPTER SEVEN: INSTITUTIONAL ASSESSMENT AND FRAMEWORK FOR

ENVIRONMENTAL AND SOCIAL MANAGEMENT

7.1 Institutional Roles and Responsibilities

The main institutions with key responsibilities in this ESMF are:

7.1.1 The Federal Ministry of Water Resources (FMWR)

The role of the Federal Ministry of Water Resources (FMWR) is one of coordination and policy

development. FMWR’s principal function is to ensure that an enabling legal, regulatory and policy

environment at the federal level is in place to promote private sector participation (PSP) and involvement

in water utility management.

In this project, and specifically with regards to this ESMF, the PCU at FWMR will play an oversight role

by monitoring the SPIUs to ensure that they are performing and carrying out their responsibilities as

detailed in the approved ESIA. The PCU will play this role by relying on the analysis of periodic reports

of the respective SMEnv in the three participating states. These reports will be forwarded to the FMEnv

for analysis of cumulative impacts and efficacy of corresponding mitigation measures. Thus the FMWR

will perform a central processing and coordination role between the SMEnv and FMEnv on the activities

of the SWAs by being a channel for receiving, compiling and processing periodic monitoring reports and

for issuing necessary corrective guidelines and to report to IDA. In addition, the FMWR will monitor the

social aspects of the ESIAs to ensure poverty targets are being met. The FMWR will report to the World

Bank.

7.1.2 The Federal Ministry of Environment (FMEnv) One of the primary responsibilities of the Federal Ministry of Environment (FMEnv) is to ensure that all

major development projects in Nigeria are subject to mandatory EIA pursuant to EIA Act. No. 86 (Decree

No. 86) of 1992. The FMEnv reviews and approves EA documents.

The role FMEnv will play in this project is; (i) to ensure that the SPIUs are preparing ESIAs and

submitting them to EA Department of the Ministry (ii) receiving, reviewing, commenting, requiring

revisions where necessary and clearing and approving the Technical and Engineering Design details of

the SWAs and the mandatory and corresponding ESIA in collaboration with the SMEnv according to

Federal Guidelines, State Laws and World Bank Safeguards policies (iii) to ensure that the SMEnv are

monitoring the activities of the SPIUs during construction and post-construction (i.e. operations stage) at

all locations in the state on which the SPIUs have facilities and installations (iv) ensure that cumulative

impacts at the federal level from any collective impacts of the SWAs activities are adequately mitigated

and monitored at the state level. The FMEnv will report to the FMWR and will receive the periodic

monitoring reports of the SMEnv through and from the FMWR.

7.1.3 The State Water Agencies/Authorities/Boards (SWAs)

The SWAs or SPIUs will be responsible ; (i) for complying with all Federal, State and Local Laws

regarding the environment and with all social/poverty guidelines, parameters and targets set by the

project, and of all triggered World Bank Safeguards policies (ii) to conduct and prepare an ESIA report

for their planned investments under this project and to submit the ESIA to FMEnv for clearance (iii) to

incorporate all appropriate mitigation measures identified in the ESIA into the project planning cycle,

technical and engineering designs and drawings, and PSP contracts (iv) to ensure that these mitigation

measures are complied with during construction and post construction (i.e. operations ) stages of their

activities, by self monitoring of their activities and by periodically reporting to its SMEnv and the FMEnv

(v) to maintain an adequate budget to implement the appropriate maintenance procedures and practices of

their operations required to ensure mitigation measures identified in their ESIAs are implemented and

sustain (vi) to ensure that contractors/consultants adhere to the General Environmental Management

47

conditions for construction contracts and (vii) to comply with any directives that may be issued from time

to time from the SMEnv and FMEnv.

7.1.4 The State Ministry of Environment (SMEnv)

The SMEnv are responsible; (i) for ensuring that activities planned under this project by the SWAs

comply with their states environmental laws and requirements, and that of the Federal Government and

the World Bank’s triggered Safeguards Policies (ii) for reviewing, and commenting on the Technical and

Engineering Design details of the SWAs and the mandatory and corresponding ESIA (iii) in

collaboration with the SWAs ensure that contractors/consultants adhere to the General Environmental

Management conditions for construction contracts (iv) to perform regular and intrusive monitoring regime

of the construction, operations and maintenance stages of the activities of the SWAs (v) for preparing

periodic monitoring reports on the activities of the SWAs at all stages of operations and to send these

reports on a regular basis to the SPIUs who will send it to the PCU at FMWR, who then process them and

send them to the FMEnv and World Bank, (v) to comply with ( consistent with state laws) the directives

of the FMEnv and FMWR (vi) to issue directives to the SWAs consistent with state laws on

environmental requirements.

7.1.5 The World Bank

The World Bank has overall responsibility to ensure that its Safeguards Polices are complied with. In

addition, the Bank will be responsible for the final review and clearance of ESIAs; as well as review and

give “no objection” to ESIAs TORs. The roles of these institutions for environmental and social

management of this project are summarized in Table 7.1.

Table 7.1: Summary Table of Institutional Framework for Environmental and Social Management.

Institution Tasks/Activities

Project Coordinating Unit (PCU) at

Federal Ministry of Water

Resources(FMWR)

Project Coordination and Oversight; reporting to IDA

Federal Ministry of Environment

(FMEnv)

Review, approval and clearance of ESIAs;

Monitoring SEPAs and reporting to FMWR.

State Ministry of Environment Review of ESIAs; Monitoring SWAs and reporting to FMEnv.

State Project Implementation Unit (SPIU)

or the State Water Agencies (SWAs)

Prepare ESIAs; Self-monitoring and reporting to SEPAs and

FMWR.

7.2 Capacity Assessment to Perform Attributed Institutional Roles.

The environmental and social sustainability of projects is highly and unavoidably dependent on the

capacity of the PCU, SIUs, SMEnv, SEPAs and FMEnv to carry out the associated design, planning,

approval and implementation work. It is therefore vital that adequate capacity is available at all levels to

carry out their ESMF responsibilities as well as the implementation of Environmental & Social

Management Plans (ESMPs). An assessment of the existing institutional capacity is discussed below.

7.2.1 The Federal Ministry of Water Resources (FMWR)

The PCU at FMWR will manage and supervise the implementation of technical assistance sub-projects in

the federal component of the project. Additionally, the PCU will perform selected coordination tasks and

serve as a resource and information help desk. The PCU is currently in place and consists of experienced

staff who managed the Bank financed National Water Rehabilitation Project and who are currently

overseeing the two on-going 1st and 2

nd National Urban Water Sector Reform Project (NUWSRP1 &2).

48

The ESMF is recommending that those saddled with working on environmental and social concerns (as

specified in the ESMF) on the 1st and 2

nd NUWSRP be given additional responsibility of following up

same issues on this project.

Key responsibilities would be:

Coordinate and liaise with the SMEnv and FMEnv.

Review periodic Environmental Audit reports from SWAs, SMEnv and FMEnv.

Advice FMWR on Environmental issues.

Compile and prepare periodic Environmental reports for submission to World Bank.

Review ESIA reports from SWAs..

Prepare TOR’s for Poverty Studies such as, social/poverty assessment.

Review and comment on Poverty Studies.

Monitor the performance of SWAs/PSP performance in meeting poverty targets/goals.

Review and compile periodic poverty performance reports from SWAs/PSPs and prepare periodic

consolidated reports for FMWR and World Bank.

7.2.2 Federal Ministry of Environment (FMEnv)

The role of the FMEnv in this project is as enumerated in 7.1.2.

The staffing levels at the EIA division of the FMEnv and the Impact Mitigation and Monitoring (IMM)

Branch of the EIA division are sufficient with adequate experience to carry out these roles.

7.2.3 State Water Agencies (SWAs)

No institutional capacity exists in the SWAs to implement and follow-up environmental and social

concerns. However, positions for Environmental Specialist and Social safeguards Specialist are proposed

in the SPIU staffing. Technical assistance funds will be available to the SWAs to hire these Specialists or

contract consultants as and when needed to support fulfillment of environmental and social

responsibilities under the ESMF (and RPF). Key responsibilities of Environmental and/or Social

Safeguard Specialist (or Consultants) would be:

Responsible for preparing the required ESIA or RAP (if necessary) for respective SWAs.

Ensure SWAs comply with all environmental guidelines of Federal, State and Local Authorities,

and Bank Safeguards policies during investment planning, construction and operations.

Liaise with SMEnv in the preparation of periodic environmental reports for submission to SWAs.

7.2.4 State Ministry of Environment (SMEnv)

The SMEnv will perform four key roles in their state in this project:

Review and comment on SWA’s ESIAs.

Monitor activities/operations of the SWAs.

Enforce State laws.

Report to FMEnv and FMWR on a periodic/regular basis.

The staffing levels are sufficient to carry out these roles. Key staff in these departments will be provided

with training as per training program here below.

7.3 Training Needs

Institutional strengthening will be required for the PCU and SWAs to effectively carry out the

environmental and social management responsibilities for sub-project implementation. Capacity building

will encompass PCU and SWAs and other state agencies involved in sub-project implementation. An

assessment of training needs and the development of a training strategy plan need to be conducted as an

initial implementation activity which will, inter alia, determine and confirm whether the training

programme proposed will suffice or is required. The objective of the training under the ESMF is to:

49

- Support SWAs to identify, prepare, implement and manage the environmental and social aspects

of their sub projects;

- Ensure that relevant government officials have the capacity to assist SWAs in preparing their

subproject proposal, and to appraise, approve and supervise the implementation of subprojects.

7.3.1 Proposed Training Program

Modules and topics for proposed training is as shown in Table 7.2:

Table 7.2: Proposed Training Programme for the Implementation of ESMF Capacity Building

Activity Proposed Topic Target Audience Duration Budget ($)

Module 1:

Training on the

Environmental

and Social

Assessment

Process

Overview of Environmental and Social Management

Process

Environmental screening process: including use of

screening form and checklist

Preparation of TOR for carrying out appropriate EA

instrument (ESIA, ESMP, RAP/ARAP)

ESIA Process

Necessity for RAP/ARAP and preparation process

Review and Approval of ESIA

Importance of Public consultation in the ESIA

Monitoring mitigation measures in ESIA/ESMP

Integrating ESMP into Sub-project cycle

Case Studies

Management of water quality laboratories

Environment & Social

Officers of PCU of

FMWR, SPIU, FMEnv,

SMEnv, SEPA, relevant

LGA departments,

Officers of SWAs.

10 days 18,000

Module 2:

Training on

Environmental

and Social

Policies,

Procedures &

Guidelines

Review of Nigeria’s Federal and State Environmental

Policies, Procedures, Legislation and Sectorial

Guidelines

Review of World Bank Safeguard Policies

Review of ESIA & Resettlement

Action/Compensation Plans

Collaboration with Institutions at Federal, State &

Local levels

Environment & Social

Officers of PCU of

FMWR, SPIU, FMEnv,

SMEnv, SEPA, relevant

LGA departments,

Officers of SWAs,

NGOs, CBOs.

5 days 9,300

Module 3:

Selected Topics

on Environmental

Protection

Sustainable use of Water Resources and Prevention

of Contamination

Soil Erosion during Construction

Sanitation Management

Impacts and Monitoring of Ground and Surface

Water Management

Environment Officers of

PCU of FMWR, SPIU,

FMEnv, SMEnv, SEPA,

relevant LGA

departments, Officers of

SWAs.

2 days 3,700

TOTAL 15 days 31,000

7.4 Cost Estimates The costs estimates are based on the assumption that the training program will be held at the state level;

resource persons are likely to come from other parts of the country and therefore require travel

allowances; participants will come from the FMWR, SWAs, SMEnv, SEPAs and FMEnv and attend

during the day only but will receive a per diem. These estimates include an allowance for travel expenses.

It is proposed that the training program will be implemented in each participating state and one in Abuja

over the first two years of the project. It is estimated that one complete training module of 17 days will

cost in total about US$31,000. There will be 4 modules offered separately. The total training cost is

estimated at US$124,000.

50

CHAPTER EIGHT: ENVIRONMENTAL AND SOCIAL ASSESSMENT PROCESS

8.1 Introduction

This section identifies and illustrates the steps involved in the environmental and social assessment

process leading towards the clearance and approval of SWA sub projects from an environmental and

social management point of view. The purpose of the process is to determine whether subprojects are

likely to have potential negative environmental and social impacts; to determine appropriate mitigation

measures for activities with adverse impacts; to incorporate mitigation measures into the subproject

designs; to review and approve subprojects proposals and to monitor environmental parameters during

implementation. This process is embedded into the overall timeline, phasing and project implementation

process for the entire NUWSRP3. The steps is presented in the flow chart in figure 8.1 and this is done in

line with the requirements of both, relevant Federal/ State laws and the Bank’s triggered safeguards

policies.

8.2 The Environmental and Social Management Process

The key steps in the environmental and social planning process are:

1) Preparation of an Environmental and Social Impact Assessment (ESIA)

In view of the anticipated size and scale of each participating SWA’s sub project in terms of; (i) their

funding envelope (ii) the extent of civil works required in the system’s rehabilitation and expansion (iii)

the high technical standards required of their operations in a reformed sector, (iv) the need for extensive

monitoring of their operations, and (v) the need for the activities of the SWAs to be economically and

financially viable while requiring them to extend coverage to the urban poor as well; the Nigerian laws

and World Bank policies therefore requires that each participating state prepares a separate

Environmental and Social Impact Assessment (ESIA)4 for their sub project/activities to be funded under

this project. These ESIAs are required to identify adverse environmental and social impacts from their

planned sub project investments, then to set out mitigation, monitoring and institutional measures to be

taken during implementation and operation of the sub projects to eliminate adverse environmental and

social impacts, offset them, or reduce them to acceptable levels. These ESIAs will be prepared only

during project implementation and subject to Bank’s “no objection” to the TORs. This broadly covers

Steps 1 to 5 in the flow chart (figure 8.1).

2). Incorporate Mitigation Measures into the Design.

The SWAs will re-introduce into/adjust/adapt/revise their sub project technical and engineering designs

(i.e. drawings , specifications for materials and workmanship, bills of quantities, contract clauses, etc.) the

required mitigation measures identified in the prepared sub project ESIA, before submission of the entire

sub project proposal5 for review and subsequent clearance. This covers Step 5 in the flow chart (figure

8.1).

3). Submit Proposals to respective State Ministry of Environment for onward transmission to the

Federal Ministry of Environment

The respective Ministry of Environment of the state in which the participating SWA is located will review

and clear the sub projects from an environmental and social standpoint only, by ensuring sub project

designs have identified environmental and social impacts, recommended mitigation measures of the

identified potential impacts and have monitoring plans and institutional measures to be taken during

implementation and operation. The SMEnv would verify that the sub project designs for the SWA

4 Sample TOR’s for the preparation of these ESIA’s can be found in Annex of this ESMF. 5 Sub project proposal is the complete set of dossier including the engineering and technical designs and the ESIA report.

51

activities in their state, meet environmental and social requirements of their state and national and federal

requirements and that they are consistent with the Bank’s OP 4.01, the overall NUWSRP3 ESMF (i.e. this

report) and other applicable social policies and safeguards of the World Bank.

The SMEnv would also review and check for compliance with this EA process. If, however the sub

project proposal unsatisfactorily addresses these issues it will be sent back to the SWA for re-design and

re-screening and then it must be re-submitted to the SMEnv for re-review. The revised design and the

ESIA will be reviewed again by the respective SMEnv, and if now acceptable, will be cleared for onward

transmission to the FMEnv and World Bank for final review and approval. Any proposed sub projects

that do not comply with the federal, state and local requirements of the Environmental Laws of Nigeria

and Social requirement guidelines of this project, and the requirements of the World Bank Safeguards

policies will not be cleared.

This process is designed to ensure that the environmental and social assessment process is part of and

conducted during the sub project design process thereby ensuring that sub project activities are

environmentally and socially acceptable and sustainable. The process will be guided by the generic

potential adverse environmental and social impacts often associated with urban water service projects,

outlined in Section 6 of this ESMF. This broadly covers Step 6 of figure 8.1.

4). Approval for Funding.

Approval for funding will be referred to the FMWR only given when the SMEnv have given

environmental and social clearance of the SWA sub projects. However, this will be subject to the FMEnv

and Bank’s review and approvals of the ESIAs. This broadly covers Step 7 to 8 in flow chart in figure 8.1.

8.3 Costs of Preparing ESIAs

There will be three ESIA prepared, one for each state. The cost of preparing good quality ESIA is

estimated at about US$ 80,000/per ESIA which gives a total of US$240,000. This will however depend

on the anticipated impacts and the scope of the project.

52

Step 2 Conduct PSP Option Study in each Participating State to recommend appropriate PSP option: Lease, Service Contract, Management Contract , Concession, etc.

Step 3 Convene workshop in each participating state of all stakeholders to approve PSP Option based on study report.

Step 4 i) Conduct Willingness-to-pay and tariff studies. ii) Detailed Investment Planning begins; producing among other requirements:

a) Engineering and Technical Designs for system Rehabilitation and Network Expansion.

b) Land Assessment Needs.

Step 1 Transaction Adviser (TA)

Step 5 Conduct ESIA to identify adverse impacts of ii)a in step 4 and design of mitigation measures to be incorporated in engineering and technical designs. TOR of ESIA subject to Bank’s ‘No objection’ Prepare RAP’s based on disclosed RPF if necessary based on ii)b in step 4.

Step 6 ESIA’s, engineering and technical designs submitted to the respective SMEnv for review. RAPs are also to be submitted to the respective SMEnv for review and final approval by FMEnv and World Bank.

Step 7 Transaction Adviser (TA) will prepare draft bidding and contract documents for award of PSP contract based on chosen PSP option from Step 3 above. These documents will incorporate engineering and technical designs from Step 6, which would form part of the activities/investment planning SWA and PSP to jointly carry out after award of PSP contract.

Step 8 TA to launch bidding process and will evaluate technical bids and make a recommendation for PSP award.

Step 9 Award of PSP Contract Step 10

a)System Rehabilitation and Network Expansion through execution of PSP contract. b)Operations Phase: i.e at Treatment Plants, Connection to New Customers etc. c)Continued Environmental and Social Management during a) , b) and maintenance stage.

End of Phase 1

Start of Phase 2

Project Implementation Start of Phase 1

At the end of Step 6, Engineering and Technical Designs for the planned investments would have undergone the environmental planning process and impacts fully mitigated in the designs.

Fig. 8.1: Key Stages in Project Cycle

53

8.4 Environmental and Social Management Plan (ESMP) for the Sub-Projects

The Environmental and Social Impact Assessments (ESIAs) that the SWAs are required by this ESMF to

prepare must contain an ESMP that will consist of a set of mitigation, monitoring and institutional

measures and cost to be taken during implementation and operations to eliminate adverse environmental

and social impacts, offset them, or reduce them to acceptable levels. The ESMP (which will be part of the

ESIAs) should include the following:

Environmental Impacts: This should outline all the environmental impacts that are associated with the

project especially as it affects air quality, water (ground and surface water), flora/fauna, soil, waste

management issues, social impact issues, for both the rehabilitation/reconstruction and operational phases.

Mitigation: Based on the environmental and social impacts identified in the prepared ESIAs, the ESMP

should describe with technical details the mitigation measures, together with designs, equipment

descriptions and operating procedures as appropriate.

Monitoring: The ESMP should also outline the environmental and social monitoring procedure that will

be implemented during the execution of the sub-projects and during operation in order to determine the

success of the mitigation measures. The ESMP should include monitoring objectives that specify the type

of monitoring activities that will be linked to the mitigation measures, cost and responsible institution for

monitoring. Specifically, the monitoring section of the ESMP provides:

A specific description and technical details of monitoring measures that include the parameters to be

measured, the methods to be used, sampling locations, frequency of measurements, detection limits

(where appropriate), and definition of thresholds that will signal the need for corrective actions, e.g.

the need for on-site construction supervision, or the need to test and treat for presence of

harmful/poisonous metals such as Pb, Hg, etc.

Monitoring and reporting procedures to ensure early detection of conditions that necessitate particular

mitigation measures and to furnish information on the progress and results of mitigation.

The ESMP should also provide a specific description of institutional arrangements, (i.e. who is

responsible for implementing the mitigation measures and carrying out the monitoring regime for

operations, supervision, enforcement, monitoring of implementation, remedial action, financing, reporting

and staff training).The implementation arrangement for implementing Environmental and Social

management is discussed in Chapter Seven. Additionally, the ESMP should include an estimate of the

costs of the measures and activities recommended so that the SWAs can budget the necessary funds.

Similar to the process for carrying out the ESIA, the mitigation and monitoring measures recommended in

the ESMP should be developed in consultation with all the affected groups to include their concerns and

views in the design of the ESMP.

8.5 Estimated Budget for Implementing ESMF

The estimated to implement the ESMF is the recapitulation of the following:

- Training on the implementation of ESMF

- Preparation of ESIAs

- Bi-annual review of ESMF performance.

The total estimated cost for the implementation of the ESMF is US$514,000. Table 8.1 provides a

breakdown of the cost.

Table 8.1 Estimated Budget for the Implementation of ESMF S/N Activity Quantity Unit Cost ($) Total ($)

1 Training on implementation of

ESMF 4 31,000 124,000

2 Preparation of ESIA 3 80,000 240,000

3 Bi-annual Review of ESMF

performance 3 50,000 150,000

Total 514,000

54

CHAPTER NINE: MONITORING PLAN

9.1 Introduction

The Monitoring Plan is a schedule that itemizes the varying mitigation measures associated with each

sub-project phase and how implementation will be monitored. This is done for the purpose of ensuring

that compliance is made consistent with the programme of mitigation in the ESMF and ESMP. The

monitoring plan helps to ensure timely project completion, implementation to specification and quality as

well as detecting early possible variations in items that need to be addressed in the project

implementation. Thus the objective for monitoring is twofold:

1) to alert project authorities and to provide timely information about the success or otherwise of the

Environmental and Social Management process outlined in this ESMF in such a manner that changes can

be made as required to ensure continuous improvement to the process.

2) to make a final evaluation in order to determine whether the mitigation measures designed into the

SWA’s project activities ( sub projects) have been successful in such a way that the pre- project

environmental and social condition has been restored, improved upon or worse than before and to

determine what further mitigation measures may be required.

Items of the monitoring plan includes; (1) mitigation measures, (2) monitoring indicator,(3) parameters to

be monitored/measured, (4) monitoring device/equipment, (5) frequency of monitoring, (6) monitoring

responsibilities and (7) cost of monitoring (equipment, transportation and labor). A number of indicators

would be used in order to determine the status of affected people and their environment (land being used

compared to before, number of customers compared to before, level of new investment in sanitation

compared to before, how many poor customers connected to/served by SWAs compared to before, health

standards, how many clean water sources than before, how many people employed than before etc.).

The following are some pertinent parameters and verifiable indicators to be used to measure the ESMF

process, mitigation plans and performance;

Number of people at the PCU at FMWR, FMEnv, SMEnv, SEPAs and SPIUs/SWAs who have

successfully received ESIA training in screening methods etc., evaluate the training content,

methodology and trainee response to training through feedback.

Number of SWAs who have adopted the ESMF process as required for all their sub project

activities; evaluate the rate of adoption.

Number of SWA sub projects preparing the required ESIA.

How has the adoption of the ESMF requirements improved the environmental health and bio-

physical state of the customers of the SWAs?

Has the adoption of the ESMF processes by the SWAs resulted in improvements in the

sustainable use of water resources?

How many SWAs have implemented an effective and working facilities maintenance program?

How many SMEnv are up to date with their periodic monitoring reports?

Is the FMEnv receiving the periodic monitoring reports of the SMEnv and what are the main

concerns of the FMEnv at this stage?

Is the FMWR receiving and compiling the periodic reports of the SMEnv and is it forwarding it

to the FMEnv?

Overall assessment of (i) activities that are going well (ii) activities that need improvements and

(iii) remedial actions required.

Are the processes identified in this ESMF working well?

Final Question: Based on the performance of the SWAs/PSP, what, if any changes to the ESMF

or RPF is needed. Should there be additional training/ capacity building measures to increase the

performance of the SWAs, SMEnv and SEPAs.

55

9.2 Monitoring Roles and Responsibilities

9.2.1 The Federal Ministry of Water Resources (FMWR): The FMWR will be responsible for

ensuring project compliance of the SWAs with the environmental laws of Nigeria and social requirements

set by the NUWSRP3 project, but will be assisted as defined above by the SMEnv and the FMEnv. The

FMWR will monitor their activities by reviewing the consolidated periodic monitoring reports of the

FMEnv and by conducting periodic technical audits of the SWAs.

9.2.2 The Federal Ministry of Environment (FMEnv): The role of the FMEnv is as detailed in

Section 7.1.2. They will review periodic reports from the SMEnv and also undertake periodic site visits to

inspect and verify for themselves the nature and extent of the impacts and the success or lack off, of the

mitigation measures.. The FMEnv will report to the FMWR.

9.2.3 State Water Agencies/Authorities/ Boards: It is planned that the environmental and social

impacts and their designed mitigation measures are to be monitored during implementation

(construction/rehabilitation works) and operation including maintenance stages of the SWA’s sub

projects. The roles and responsibilities for monitoring impacts and mitigation measures will be as follows:

- The SWAs will monitor and evaluate the environmental and social impacts of sub-project activities

and the mitigation measures designed, regularly and as frequently as specified in the sub project

ESIAs and will maintain suitable records to be made available to their respective SEPA. The SWAs

will monitor the water quality effects from the treatment plants as part of normal plant operations, and

the impacts and mitigation measures during all phases of their sub project execution cycle, from

transaction stage in Phase 1 to construction, operations and maintenance executing stages in Phase 2.

- The SWAs will also be responsible for monitoring the environmental and social impacts and

mitigation measures resulting from the action of their contractors, sub-contractors, transporters,

suppliers and all other third parties in the course of their duties under the sub project.

- Furthermore, the SWAs would also be responsible for monitoring the environmental and social

impacts and mitigation measures of their subproject activities at other locations beyond their project

sites, at end user locations such as at the RBDA’s ( monitor Dam sites), sanitation infrastructure sites,

downstream of water treatment plants to monitor river water quality, etc.

Therefore, wherever environmental and social impacts are attributable to their sub project activities the

appropriate mitigation measures will apply consistent with the sub project ESIA, and they would be

responsible for monitoring and evaluating the same. The SWAs will report to their SMEnv and to the

FMWR.

9.2.4 State Ministry of Environment: The SMEnv will play the leading role of monitoring the

activities of the SWA in their state. The SMEnv will carry out this role by ensuring that the sub project

Environmental and Social Management Plan (ESMP) contained in the cleared sub project ESIA reports is

being implemented as specified therein. That is to say that the SMEnv will monitor the SWAs monitoring

procedures and report on a regular basis, perhaps quarterly. They will rely on a bottom up feedback

system from the SWAs by going through their monitoring reports and making regular site visits to inspect

and verify for themselves the nature and extent of the impacts and the success or lack off, of the

mitigation measures.

The Monitoring Plan specifies the monitoring measures to be carried out with linkages to the potential

adverse impacts that would have been identified through a process contained in chapter 8, by: (i)

Scheduling and coordinating monitoring tasks; (ii) Evaluating mitigation effectiveness; (ii) Identifying

where applicable, corrective management practices, and (iv) Ensuring that monitoring findings are

suitably evaluated and incorporated into future management decisions.

56

9.3 Costs for Implementing the Monitoring Plan

A third party bi-annual review of the ESMF (and RPF) performance (most likely by a reputable company

or individual consultant) is recommended. This is in order to assess difficulties, needed improvements,

capacity building requirements, lessons learned, etc. These reviews will be at a cost of US$ 50,000 each.

A lump sum of US $ 150,000 should be kept aside for these third party bi-annual reviews. A generic

motoring plan is presented in Table 9.1.

Table 9.1: Generic Monitoring Plan for the NUWSRP3 Project Based on the Mitigation Measures Mitigation Measures Parameters to be

Monitored

Where the

parameters will be

monitored

How the parameter

will be

monitored/monitoring

equipment

Unit Responsible Cost

Construction Phase

Maintain zones of preliminary accumulation of

wastes that will cause no damage to the vegetation

cover and other components of the environment

Area designated for

preliminary waste

accumulation

At work site Visual Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Arrange transport and disposal of wastes according

to the established traffic management plan,

procedure and in the approved dump sites designated

for the specific purpose.

Proper waste disposal At work site during

construction

Visual Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of

routine

supervision

Maintain appropriate operating rules for the camps in

identified suitable sites, including safe handling of

silt material, control of access, adequate drainage,

and rehabilitation after construction.

Written rules placed in

strategic position in

the site.

At work site during

construction

Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Implement the measures to control spillage of toxic

substances that will be included in construction

contracts, including: guidelines for the proper storage

and sitting of hazardous material such as oil, grease,

fuel, asphalt, or ignitable and corrosive materials;

lubricants will be collected in clearly marked

containers and reused if possible, or disposed of at

properly regulated offsite locations; water samples

will be taken and tested for oil when there is a risk of

spills or leakages to canal waters, surface waters, or

groundwater.

Ground water

pollution

(water and soil quality,

Suspended solids, oils,

pH value). Test results

of water samples,

containers for safe

storage of oils,

lubricants etc

At work site during

construction

Inspection and

Laboratory analysis

1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost and

contract

preliminaries

Use closed/covered trucks for transportation of

construction materials and wastes. Depending on

season, wash truck tires as appropriate to control

tracking mud and dust onto paved roads.

Covered trucks as part

of equipment

At work site during

construction

Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Provide workers who deal with hazardous materials

or are exposed to dust with necessary protection

gear, and follow applicable regulations and

procedures as established by the

Government authorities.

Safety equipment

provided- Fire

Extinguishers

inspection records,

Spill Kit, Personal

Protective Equipment

inspection checklist

At the work site Un announced

inspection

1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

58

records, First Aid

Shower, Eyewash and

Box Inspection

records)

Workers will have and use safety equipment during

cement pouring and while using heavy equipment.

Safety and protective

equipment

At work site Un announced

inspection

1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Development of Site Specific Emergency Response

Plan

Emergency response

plan and drills-

Chemical Spill

response drill records,

Emergency Fire Alarm

drill records

At work site Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Use appropriate well serviced machinery to reduce

noise output

Machinery on site,

Noise level in the

surrounding, noise

level should not

exceed 90dBA (

FMENV)

At work site Inspection of noise

levels

1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Communicate to people as regards when water will

be stopped to facilitate repair activities, reduce time

period when water flow is disrupted.

Means of

communication

employed e.g. radio

announcements,

newspaper adverts etc.

Office of

Participating SWA

Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

Conduct an awareness raising campaign for the

localities.

Develop, produce and circulate leaflets to educate

people of dangers of sexually transmitted diseases

and how to prevent them.

Print posters to educate people on HIV/AIDS.

Number of campaigns

conducted, leaflets and

posters education the

populace on

communicable

diseases produced

Office of

Participating SWA,

public notice boards

etc.

Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

If demolition and/or dislocation is required, the

project affected persons will be compensated in

accordance with WB OP4.12 before the construction

starts.

List of affected

persons compensated

Office of

Participating SWA

Inspection 1.Participating SWA

2. SMEnv

3. FMEnv

4. FMWR

Part of project

management

cost

If it is required, develop and implement a

Resettlement Action Plan (ARAP) and/or obtain

Servitude. The construction works will start after the

compensations are paid to the project affected

persons (PAPs) and servitudes acquired.

ARAP document Office of

Participating SWA

Inspection Participating SWA

2. SEPA

3. FMEnv

4. FMWR

Part of project

management

cost

59

CHAPTER TEN: PUBLIC CONSULTATION

10.1 Introduction

Public Consultation is an integral part of the Environmental and Social Management Process. And as

such, the success of NUWSRP3 depends on the meaningful participation of all stakeholders. The purpose

of consultation is to seek the participation of all the stakeholders in the water sector in the states, not least

of all the urban and peri-urban communities who will be served by the SWAs, NGOs, potential PSPs and

all other stakeholders, thereby introducing transparency and accountability in the project.

During the preparation of this revised ESMF and the RPF, field visits were carried out and consultations

were held with officials of relevant MDAs and other key stakeholders in order to adequately appreciate

their views and concerns with regards to the environmental and social impacts of planned project

activities. The consultations were aimed at presenting the proposed project, ESMF and RPF to the

stakeholders and getting their views and feedback.

10.2 Consultation Strategy

In order to ensure full participation of stakeholders, the consultation strategy adopted was based on the

identified project areas in the participating states. The Consultant with the assistance of SPIU staff

identified the following stakeholders:

Traditional Rulers and Chiefs

Community Leaders

Community Associations

Women Groups

Youths

Housing Estate Associations

The consultation approaches used in eliciting inputs from stakeholders into the ESMF included meetings,

administration of questionnaires and Stakeholders Consultation Forum. Consultations were basically

carried out in two forms, viz;

- Meeting/Discussions with PIU, SPIUs and officials of the FMEnv, SMEnv and SEPAs.

- Consultations with stakeholders in the project areas in Bauchi and Ekiti States.

10.3 Summary of Public Consultation

Stakeholder consultations were held in Bauchi town, and in Ado, Ikere, Odo and Iworoko in Ekiti State.

Participants comprised potential project affected persons, vulnerable groups (women, youth), traditional

ruler and chiefs, NGOs and local community representatives such as CBOs. The complete list of those

consulted can be found in Annexes1 & 2 of this report.

The proceedings took the form of:

Introduction of the project to community members and stakeholders;

Sensitizing them on environmental and social safeguard issues;

Entertaining comments and questions from stakeholders, and

Addressing concerns raised by stakeholders.

Table 10.1 captures the summary of the proceedings and outcomes of the public consultations.

60

Table 10.1 Summary of Stakeholders Consultations S/No Name of

Stakeholders

Date Language of

Comment

Response Feedback Concerns / Complaints Remarks / Recommendation

1 Ado Town 5th

June,

2013

English Respondents commend the

World Bank for selecting

Ekiti as one of the state to

benefit from the

NUWSRP 3 and are

anxious to see the project

come to reality.

• A lot of communities in Ado

town including schools are

without water.

• Most of the water pipes in the

state were constructed as far

back as 1962.

• Resident will spend less on

health problem if they have

access to good and quality water.

• Incessant digging of wells &

boreholes by residents may lead

to landslides.

• Will those who have illegally

encroached on the ROW be

compensated?

• Would stakeholders be expected

to contribute in any way to the

actualization of the projects?

• How soon would the project take

place?

• Flooding might occur in the

operational phase of project as a

result of busted pipe, what would

be done to prevent that?

• What will be done to those who

deliberately build houses on

water pipes?

• A lot of projects in the state are

carried out without due

consideration of the environment

• Project may result in damage to

existing utilities

• How would breaking of roads be

prevented during pipe laying?

• What would be done to prevent

incessant bursting of pipes and

subsequent contamination of

water?

• The PIU should liaise with the Ministry

of Information for proper sensitization

of residents of affected

communities/housing estate about the

project.

• The pipe should be laid deep into the

ground to avoid exposure

• ESIA should be conducted before the

commencement of the project

• There should be synergy between the

Water Corporation and the Ministry of

Works so pipeline ROW can be put

into consideration during the design

and construction of roads

• Routine inspection & maintenance

should be carried out on the pipes

• Old existing water pipes should be re-

laid.

• Structures closed to dams and other

water sources should be relocated

2 Afao/Kajola

in Ikere

Community

5th

June,

2013

English,

Yoruba

The stakeholders

acknowledge the role that

water plays in human and

community development

and therefore commend

the World Bank for their

effort in providing safe,

clean and affordable water

to the community

• Similar project was embarked

upon by the EU but was later

abandoned.

• Location of storage facilities has

been paid for through

community contribution

• Route for main and service lines

have been identified.

• How sustainable would the

project be?

• How would compensation be

carried out?

Pipeline network which has been

designed by the Water Consumer

Association executives can be

incorporated into the proposed project

3 Odo Town 5th

June,

2013

Yoruba Dwellers view the

provision of water as a

divine intervention to their

problem and are very

enthusiastic about the

• Town is suffering from acute

water problems

• Most dwellers depend on sachet

water their everyday needs

• Request has been made and

What role does the community

have to play in aiding the

actualization of the project

NA

61

project frequent visit has been conducted

to the Water Corporation but

nothing has been done to the

effect

• The community is willing to

sacrifice for the actualization of

the project

4 Iworoko

Town

5th

June,

2013

Yoruba They responded that they

are in dare need of regular

supply of piped water as

most of the dwellers

depend on hand dug wells

which does not completely

serve the town which is a

host community to a

higher institution

• The town had once benefited

from piped water long before the

creation of Ekiti state

• The use of heavy machinery

during the dualization of the road

passing through the town led to

the bursting of existing pipe

thereby alienating them from

their source of water supply.

The exact route of the pipes,

borehole location

• Compensation issues should be looked

into

• A main pipe should be laid to connect

the reservoir at Ifaki to with that at

Iworoko

• Employment of indigenes and the use

of companies sited at Iworoko should

be considered.

5. Bauchi town,

Bauchi State

4th Jun,

2013

English and

Hausa

• Water supply and

sanitation has been a

major concern in the

state

• This project is for the

wellbeing of the

community dwellers and

the inputs of the

community leaders.

• The project will attract

population increase,

introduction of social

vices, environmental

pollution such as dust

during soil excavation

e.t.c

• The expansion and

reconstruction of the

dams have issues on soil

nature.

• In Ningi the only

working water station

serve 2:3of the total

community

• All stakeholders should fully

participate in the project.

• Water scarcity has been a major

problem in the state

• The available water stations in

the rural towns is supplying low

amount of water compared to the

population in demand.

• Implementation of the project

may increase social vices health

problems , increase in crime,

e.t.c

• Who will be responsible for the

maintenance of the process,

equipments and infrastructures

that will be put in places in the

LGAs?

• A clarification of which

enforcement billing bodies

should be mentioned and

metering and metering public

water points

• When is the project

commencing?

• Will there be a capacity building

and the involvement of

stakeholders in the project?

• Who will compensate the

community dwellers?

• If the water treatment plant is

expanded a new reservoir should be

made, the new expansion should be

connected directly and that the old

one should be maintained.

• General public awareness,

mobilization and sensitization will be

needed.

• Extensive trainings for the

communities and other stakeholders

involved in the project in their

different aspects.

• Contracts should not be awarded to

low standard companies.

• Compensation of local business

women that may be affected due to

the project.

• The use of equipments and machinery

that will not affect the design of the

community settlement during civil

works due to the old nature.

62

10.4 Consultation Plan

The ESMF and RPF will be disclosed in Nigeria and at the World Bank’s infoshop. Consultations will

continue:

During the preparation of the ESIAs for each participating SWA. The approved and cleared ESIAs

will be disclosed publicly in each State.

During the preparation of Resettlement and Compensation Plans extensive consultations will take

place when the socio-economic study and census exercise is being conducted.

Public participation and consultations would take place through workshops, seminars, symposia,

meetings, radio programs, request for written proposals/comments, filling in of questionnaires/forms,

public readings and explanations of project ideas and requirements.

Public documents would be made available at the, federal, state and local levels at suitable locations like

the offices of the FMENV, the FMWR, the SMEnv, SEPAs and the SWAs, and at state/public libraries,

complying with federal and state laws regarding disclosure of public documents. In line with the legal

requirements, public consultation especially the display of the ESMF and other environmental documents

will be done for 28 days.

The consultation plan will be monitored by FMEnv and SMEnv who will set their own verifiable

indicators to assess the degree of participation of the key stakeholders during all phases of project

implementation.

The SMEnv will make recommendations when they clear/review SWA’s sub project ESIAs, consistent

with the consultation plan (Table 10.2).

Table 10.2 Consultation Plan

Project Stage Activities Institutional Responsibilities

During Project Preparation Preparation of ESMF and RPF PCU at FMWR

Implementation SWAs and PSP perform

according to transaction

contract.

SWAs, PSP partners, SMEnv

and FMWR

Monitoring Review of verifiable indicators FMEnv, FMWR, SWAs and

SMEnv.

63

ANNEX 1

LIST OF OFFICIALS CONSULTED DURING THE PREPARATION OF THE ESMF AND RPF

S/No Name Designation E-mail Phone No

1. Engr Benson Ajisegiri Project Coordinator – PCU-

NUWSRP [email protected]

08033737149

2. Mr. J.A. Alonge Deputy Director – EA

FMEnv - 08035893120

3. Kayode Jegede Special Adviser – BIPU [email protected] 07064172278

4 Mr. Foluso Daramola PS BIPU [email protected] 08035067313

4. Omobolanle Fakunle PS – Ekiti State Ministry of

Environment 08033970767

5 Engr. S. O Adetunji Chairman, EKSWC [email protected]

6 Engr. O S Ojuola General Manager EKSWC [email protected] 08063034659

7 Nancy Taiwo Communication and Social

Safeguard Specialist

[email protected] 08066647941

8 Olatunji O.D M&E Specialist [email protected] 08033887422

9 Olorunfemi D B HRDO [email protected] 08062941481

10 Adewumi A S Small Town & APC [email protected] 08033761170

11 Oluwole Ayodeji Procurement Specialist [email protected] 08034915726

12 Waziki Y Jaum BASEPA (PS) 08068112519

13 Engr. Aminu Aliyu

Gital

General Manager/project

coordinator, BSWB [email protected] 08032849137

14 Babangida Gambo Min. of Environment 08032305955

15 Mr. Idris Bello Environmental Safeguard

Officer [email protected] 08058629996

16 Abdulmumini

Mailafiya

Project Engineer- BSWB 08037902809

17 Mrs Patricia Simon-

Hart

Honorable Commissioner

MWRRD Rivers State [email protected]

18 Engr. M. M Mweo Ag. General Manager

PHWC [email protected]

19 Judith Martyns-

Yellowe

Tech Ass to Honorable

Commissioner MWRRD [email protected] 08175132482

20 Ijeoma Samuel [email protected]

21 Engr. Dahiru NUWSRP [email protected] 0803302536

64

LIST OF STAKEHOLDERS CONSULTED IN BAUCHI STATE

S/

N

NAME ORGANIZATION ADDRESS EMAIL PHONE NO

1 Engr. Hossana John

Dajari

SUWASA BSWB Hqtrs [email protected] 08036441206

2 Abdulrahman Ishaku NINGI L.G.A. Works & Housing

Dept. Ningi L.G.

- 08054952436

3 Khadijat Musa ‘’ ‘’ “ “ [email protected] 08058644624

4 Abdulmumin Mailafiya BSWB No 15 gombe road.

G.R.A. Bauchi

[email protected] 08037902809

5 Kabiru Adamu Sade Darazo L.G.A. Dazaro L.G.A. [email protected] 08096344100

08023557849

6 Garba Sabo Kirfi L.G.A Kirfi L.G.A. [email protected] 08050700015

08026911517

7 Idris D. Bello BSWB Bauchi [email protected] 08058629996

8 Yusuf B. Isah(Barde) Bauchi district Head

office

Railways road

bauchi

- 08058630897

9 Almustapha Rabiu SUWASA BSWB [email protected] 07038187505

10 Bala Shehu BSWB BSWB [email protected] 08020590063

11 Abdullahi Abubakar Gubi Dam FIRO - 07036460516

12 Inuwa T. Dass BSWB Bauchi - 08058630003

13 Mustpha Idris FAWOYAI Bauchi [email protected] 07054535362

14 Muhammad Suleiman

Dazaro

BSWB Bauchi [email protected] 07061206857

15 Aliyu Musa Dambam BSWB Bauchi [email protected] 07061206857

16 Adamu Ali MOWRBH Bauchi [email protected] 08060182506

17 Bitkon David O. BSWB Bauchi [email protected] 08025204274

18 Moh’d Dubigari Bello BSWB Bauchi [email protected] 08038953493

19 Engr. Haruna

Mohammed

BSWB Bauchi [email protected] 08023632817

20 Miriam Y. Iliya RAHAMA Bauchi [email protected] 08036199703

21 Gambo Saleh DEC Bauchi [email protected] 08029043748

22 Alh Nuhu Musa Giade Dir Works SHIRA

LGA

Shira LGA - 08035695057

23 Danbana balkakori S.U.P.R.W.S Shira LGA - 07069053479

24 Abdullahi Alhaji Tata Works Kirfi L.G Works &water

supply Kirfi

[email protected] 08058632300

25 Abdulhamid Adamu Work Tafawa Works and Water

supply

08099219211

26 Ibrahim Mohammed

Abubakar

Project Accountant BSWB [email protected] 08020591724

27

Engr. Ibrahim Moto

Suleiman

TPM

BSWB

[email protected]

07084704004

28 Ahmed A Jaji Works T/Balewa

L.G. Bununu

Works and housing

Water Supply

- 08167579898

29 Deborah D. Kogi WEIN/NEWSAN Bauchi weinig@[email protected] 08069770781

30 Abubakar A. Fateh M&E BSWB [email protected] 08069156672

31 Shehu Y. Jalam P.R.O BSWB [email protected] 08036909503

32 Ahmed Usman AGM/PRS BSWB - 08089778103

33 Engr. Aminu Aliyu

Gital

BSWB GM BSWB [email protected] 08032849131

34 Waziki Y. Jaurn BASEPA (PM) BASEPA - 08068112519

ANNEX 2A

65

LIST OF STAKEHOLDERS CONSULTED IN EKITI STATE

S/N NAME ORGANIZATION ADDRESS EMAIL PHONE NO

ADO

1 Sir A S Aluko Irewole Community C/o State Housing,

Ade-ekin

08035050241

2 Ch. F.A Daramola GRA/Onisinla/Onigari 2, Adebayo Daramola

cresc. GRA. Ado Ekiti

08033889197

3 J O Ogunleye GRA/Onisinla/Onigari 24, opp spotless hotels,

onigari

4 Komolafe B Sola Water Corp Water works road Ado 08062148966

5 Engr Ofere B.M Water Corp (STWSSP) Adusco Bldg Ado-Ekiti 08039151095

6 Mr. Olorunfemi D.B Water Corp (PIU) EKSWC Ado-Ekiti [email protected]

ov.ng

08062941481

7 Mr. Salam Omotoso

K

Water Corp (DCS) EKSWC Ado-Ekiti [email protected] 08063216366

8 Mr Adeyemi T A Water Corp (STWSSP) Adusco Bldg Ado-Ekiti 07068851813

9 Nancy Taiwo Comm & Social

Safeguard

BIPU [email protected] 08066647941

10 Oluwole Ayodeji Procurement Specialist BIPU [email protected] 08034915726

11 Olatunji O D M & E specialist (PIU) EKSWC [email protected]

g

08033887422

12 Olamiju E. O Information 08061240473

13 Dr. S O Ayo Stakeholder 15 Ekute Quarters Ado 08135033048

14 Foluso Daramola Infrastructure Gov. Office Ado [email protected] 08035067313

15 Engr. O S Ojuola Water Corporation

(SHAE)

EKSWC Ado-Ekiti [email protected] 08063034659

16 Dame A O

Olubummo

Stakeholder Prof. Egunjobi st. State

Housing Okeila

08066778865

17 V/R M.I Adebayo Stakeholder No 4 Oguniyi str, State

Housing Okeila

07065584957

18 Engr Daramola O. J Water Corporation EKSWC [email protected]

.ng

08038282246

19 Engr(Mrs.) Agbeyo

O.A

Water Corporation EKSWC Ado-Ekiti [email protected]

g

08035645188

20 Adunmo O Stephen BIPU Gov. Office Ado-Ekiti [email protected] 08061100438

21 Owoseni Gbenga BIPU Gov. Office Ado-Ekiti [email protected] 08067475550

22 Engr. Adewumi A S Small Towns Specialist,

PIU/APC

EKSWC [email protected]

.ng

08033761170

23 Hon Femi Babalola Stakeholder 4 Spotless road, Onigari [email protected] 08039105549

24 J.O Akinola Stakeholder 53 Bisi Egbeyemi

Crescent GRA Ado

[email protected] 08030657045

25 A K Adebayo EKRUWASSA Oke Osun Ikere-Ekiti [email protected] 08033175000

26 Owolabi G D EKRUWASSA Oke Osun Ikere-Ekiti [email protected] 08067311123

27 Engr. S O Adetunji EKSWC Headworks Ajilosun

Ado

[email protected]

g

08034306639

28 Dr Lola Okwuosa World Bank Abuja [email protected] 08066823007

29 Julius Afolami Min of Environment Ado Ekiti [email protected] 07034759333

30 Akodu D O SEPA Ado Ekiti 08030656672

31 Idoreyin Udosen GEHS Abuja [email protected] 07031846642

AFAO/KAJOLA (IKERE)

32 Fagbule S.J Secretary WCA Afao/Ikajola 08036344739

33 Engr Ariyo A O Scheme Supv Afao/Ikajola 08164029383

ANNEX 2B

66

34 Adamolekin J O Community Member Afao/Ikajola 08034853728

35 Samuel Akogun Community Member Afao/Ikajola 08074249807

36 Beatrice ilesanmi Community Member Afao/Ikajola

37 Folorunsho Jayeola Community Member Afao/Ikajola 07066226890

38 Joseph Omoyeni Community Member Afao/Ikajola 08076250880

ODO

39 Chief Francis

Adeseemo

07065718590

40 Chief Adekunle

Atoki

Olofun Compound Odo 08060837770

41 Mr Rotimi Ojo Behind Odo Health

centre

08060409636

42 Chief M A

Omotoguibo

Mayo Hostel 08033792663

43 Prince Adejo

Lawrence

Odo Ado 08037990001

44 Elder Tayo Adaolu Odo Ado 07060589828

45 Sunday Elesemi Odo Ado 08104735449

46 Prince Adeyemi

Adetokunbo

Odo Ado 07062323443

47 Olusola Dada Odo Ado 07032893295

48 Moses Opeyemi Odo Ado 08061202956

49 Isaac Moses Odo Ado 08035746381

50 Sunday Akin Odo Ado 08034160122

51 Veronica Ilesanmi Odo Ado 08136678358

52 Esther Adeola Odo Ado 07037994021

53 Funke Olalere Odo Ado 08050286379

54 Adedokun Olalere Odo Ado 08152484852

55 Adeola Julius Odo Ado 08062615998

56 Alice Usman Odo Ado

57 Makonjuola Mary Odo Ado 08105388447

58 Ajoke Ojo Odo Ado 08135368343

59 Comfort Kayode Odo Ado 08151941743

60 Chief Saro Odo Ado

61 Joseph Oberi Odo Ado

IWOROKO

62 HRM Oba M. A.

Aladejena

08038183394

63 High Chief Folare

JP

Akodi Arinjala 08067200854

64 Chief Bada J F 1, Okeeba st Iworoko 08068921064

65 High chief A.A

Ologunsaba

Olulodo of Iworoko Akodi, Arinjale 08166385058

66 Chief Odofin Oksobo street Iwokoro 08033736185

67 High Chief Kasali

Adeleye

4, Idafin QTRS

Iwokoro

07066656330

68 Chief ogunsanya

Odole

12, Okeede Iwokoro 08130240360

69 Chief Komolafe 11,Temidire Iwokoro 08063031682

70 Chief Fatayo

Odogun

Ayegunle St. Iwokoro 07064582046

67

ANNEX 3.0

World Bank Environmental and Social Safeguard Policies (Summary)

Environmental Assessment (OP 4.01). Outlines Bank policy and procedure for the environmental

assessment of Bank lending operations. The Bank undertakes environmental screening of each

proposed project to determine the appropriate extent and type of EA process. This environmental

process will apply to all sub-projects to be funded by NUWSRP3.

Natural Habitats (OP 4.04). The conservation of natural habitats, like other measures that protect and

enhance the environment, is essential for long-term sustainable development. The Bank does not

support projects involving the significant conversion of natural habitats unless there are no feasible

alternatives for the project and its siting, and comprehensive analysis demonstrates that overall

benefits from the project substantially outweigh the environmental costs. If the environmental

assessment indicates that a project would significantly convert or degrade natural habitats, the project

includes mitigation measures acceptable to the Bank. Such mitigation measures include, as

appropriate, minimizing habitat loss (e.g. strategic habitat retention and post-development restoration)

and establishing and maintaining an ecologically similar protected area. The Bank accepts other

forms of mitigation measures only when they are technically justified. Should the sub-project-specific

ESIAs indicate that natural habitats might be affected negatively by the proposed sub-project

activities with suitable mitigation measures, such sub-projects will not be funded under the

NUWSRP3.

Pest Management (OP 4.09). The policy supports safe, effective, and environmentally sound pest

management. It promotes the use of biological and environmental control methods. An assessment is

made of the capacity of the country’s regulatory framework and institutions to promote and support

safe, effective, and environmentally sound pest management. This policy will most likely not apply to

NUWSRP3.

Involuntary Resettlement (OP 4.12). This policy covers direct economic and social impacts that both

result from Bank-assisted investment projects, and are caused by (a) the involuntary taking of land

resulting in (i) relocation or loss of shelter; (ii) loss of assets or access to assets, or (iii) loss of income

sources or means of livelihood, whether or not the affected persons must move to another location; or

(b) the involuntary restriction of access to legally designated parks and protected areas resulting in

adverse impacts on the livelihoods of the displaced persons. The ESMF and RPF reports discuss the

applicability of this policy in detail.

Indigenous Peoples (OP 4.10). This directive provides guidance to ensure that indigenous peoples

benefit from development projects, and to avoid or mitigate adverse effects of Bank-financed

development projects on indigenous peoples. Measures to address issues pertaining to indigenous

peoples must be based on the informed participation of the indigenous people themselves. Sub-

projects that would have negative impacts on indigenous people will not be funded under NUWSRP3.

Forests (OP 4.36). This policy applies to the following types of Bank-financed investment projects:

(a) projects that have or may have impacts on the health and quality of forests; (b) projects that affect

the rights and welfare of people and their level of dependence upon or interaction with forests; and (c)

projects that aim to bring about changes in the management, protection, or utilization of natural

forests or plantations, whether they are publicly, privately, or communally owned. The Bank does not

finance projects that, in its opinion, would involve significant conversion or degradation of critical

forest areas or related critical habitats. If a project involves the significant conversion or degradation

of natural forests or related natural habitats that the Bank determines are not critical, and the Bank

determines that there are no feasible alternatives to the project and its siting, and comprehensive

analysis demonstrates that overall benefits from the project substantially outweigh the environmental

costs, the Bank may finance the project provided that it incorporates appropriate mitigation measures.

Sub-projects that are likely to have negative impacts on forests will not be funded under NUWSRP3.

68

Physical Cultural Resources (OP4.11). The term physical cultural resources also known as “cultural

property” includes sites having archeological (prehistoric), paleontological, historical, religious,

aesthetics or other cultural significance. The Bank’s general policy regarding cultural property is to

assist in their preservation, and to seek to avoid their elimination. Specifically, the Bank (i) normally

declines to finance projects that will significantly damage non-replicable physical cultural resources,

and will assist only those projects that are sited or designed so as to prevent such damage; and (ii) will

assist in the protection and enhancement of physical cultural resources encountered in Bank-financed

projects, rather than leaving that protection to chance. The management of physical cultural resources

of a country is the responsibility of the government. The government’s attention should be drawn

specifically to what is known about the physical cultural resources aspects of the proposed project site

and appropriate agencies, NGOs, or university departments should be consulted; if there are any

questions concerning physical cultural resources in the area, a brief reconnaissance survey should be

undertaken in the field by a specialist. NUWSRP3 will not fund sub-projects that will have negative

impacts on physical cultural resources.

Safety of Dams (OP 4.37). For the life of any dam, the owner is responsible for ensuring that

appropriate measures are taken and sufficient resources provided for the safety of the dam,

irrespective of its funding sources or construction status. The Bank distinguishes between small and

large dams. Small dams are normally less than 15 m in height; this category includes, for example,

farm ponds, local silt retention dams, and low embankment tanks. For small dams, generic dam

safety measures designed by qualified engineers are usually adequate. This policy does apply to

NUWSRP3 since existing dams owned by RBDAs or SWA’s will supply raw water to SWA’s.

Projects on International Waterways (O 7.50). The Bank recognizes that the cooperation and good

will of riparians is essential for the efficient utilization and protection of international waterways and

attaches great importance to riparians making appropriate agreements or arrangement for the entire

waterway or any part thereof. Projects that trigger this policy include hydroelectric, irrigation, flood

control, navigation, drainage, water and sewerage, industrial, and similar projects that involve the use

or potential pollution of international waterways. This policy most likely will apply to NUWSRP3 as

the rivers Niger and Benue and their tributaries are potential sources of supply of raw water.

Disputed Areas (OP/BP/GP 7.60). Project in disputed areas may occur between the Bank and its

member countries as well as between the borrower and one or more neighboring countries. Any

dispute over an area in which a proposed project is located requires formal procedures at the earliest

possible stage. The Bank attempts to acquire assurance that it may proceed with a project in a

disputed area if the governments concerned agree that, pending the settlement of the dispute, the

project proposed can go forward without prejudice to the claims of the country having a dispute. This

policy is not expected to be triggered by sub-projects. This policy is unlikely to be triggered by sub-

projects to be funded by NUWSRP3.

Disclosure of Information (OP 17.50). This policy requires that all safeguards policy documents

prepared for projects funded by the Bank be disclosed to the public at two levels: 1) In-Country

disclosure at domains accessible to stakeholders, 2) At World Bank infoshop.

69

ANNEX 4.0

GENERIC TERMS OF REFERENCE FOR THE PREPARATION OF THE MANDATORY ESIA

FOR SWA’S SUB PROJECT ACTIVITIES. (TO BE REVISED AT APPROPRIATE TIME BY

THE SWA ASSISTED BY THE FMWR)

Tasks:

1. The following specific tasks, among others, will be required:

Review of Engineering and Technical Designs for planned investments to identify, assess, and

quantify to the extent possible, all environmental and social impacts and risks in the state.

Provide detailed and tangible mitigation measures to reverse these adverse impacts or manage them

within acceptable limits according to law in Nigeria and World Banks Safeguards polices.

Develop an environmental and social management process to ensure successful mitigation of all

adverse impacts, a tangible monitoring plan and institutional arrangements to execute this plan.

Assess further the SWAs and PSP partners capacity to manage the sub project’s environmental and

social issues and propose measures on how to reinforce their capacity, for example, by establishing

an environmental unit/working group, and providing technical training. Suggest capacity building

and technical assistance requirements in relation to safeguard and awareness needs in the public and

private sectors to be implemented under the proposed sub project.

Develop a suitable maintenance plan with estimates of cost to ensure sustainability of mitigation

measures.

Outline of the ESIA Report

The ESIA report must be concise but detailed and thorough to include all significant environmental and

social impacts. The report should focus on identifying impacts, mitigating them in the technical designs,

during construction, operation and sustainable through an effective maintenance plan.

The FMEnv, the SEPAs and the World Bank (ASPEN) environmental and social reviewers will need to

approve the ESIA. The ESIAs will be disclosed in the respective state of the SWA and also in Abuja.

List of Acronyms

Table of Contents

Executive Summary

Description of Proposed Sub Project

Baseline Data Present State (where necessary trans state/border) baseline data pertaining to (i) the physical environment

(i.e., topography, geology climate and meteorology, surface water hydrology); (ii) biological environment

(i.e., flora types and diversity, rare and endangered species within or adjacent to project intervention sites,

including wetlands, sensitive habitats); and (iii) Socioeconomic and cultural environment, including

present and projected, where appropriate.

Environmental and Social Safeguard Issues and Triggers

Discuss the applicability of any of the World Bank’s Operational Policies and conduct the required

analyses as described above.

Legislative and Regulatory Framework

Discuss Nigeria’s and the State’s environmental and social national policies, laws, regulatory and

administrative frameworks.

70

Identification of Potential Environmental and Social Impacts

Identify and assess the changes brought about by the sub project in relation to the baseline data;

differentiate between short, medium and long-term impacts; and describe the extent and quality of

available data and any pertinent information deficiencies, which might preclude the projection of

impacts.

Identify Tangible Mitigation Measures

Develop and describe feasible and cost-effective mitigation measures to prevent or reduce negative

impacts. Provide cost outlays for the proposed measures, as well as their institutional and capacity

building requirements to implement them.

Institutional Assessment

The ESIA will establish appropriate institutional arrangements in the SWAs/PSP relationship, between its

SEPA and FMEnv consistent with this ESMF and recommend and develop training modules and prepare

associated costs.

Monitoring Plan

Design a monitoring plan for the implementation of measures requiring mitigation, as well as for the

impacts of sub project activities. The monitoring plan should clearly indicate the linkages between

impacts identified in the ESIA report, indicators to be measured, methods to be used, sampling locations,

frequency of measurements and definition of thresholds indicating the need for corrective actions. The

monitoring plan must identify parameters to be monitored, direct and indirect impact; conflicts arising

from competition for water and/or land resources and clear responsibilities for supervision, frequency of

inspections, and a budget for the recommended activities. It is important that all aspects of the

monitoring arrangements be appropriately costed and the responsibilities clearly defined