Upload
alexandre-claiborne
View
215
Download
0
Embed Size (px)
Citation preview
Federal AviationAdministration
Airport Development Process - Airport Capital Improvement Plan (ACIP)
By: Mahendra Raghubeer, Airport Planner & Engineer
Project Planning to Closeout
Date: 3/2/2006
Introduction
• This session will help Airport Sponsors and Consultants enhanced their understanding of the unique process involved with the Airport Capital Improvement Program, from project planning to project closeout.
Federal AviationAdministration
• 5 Years ACIP
• Pre-Application
• Application
• Correspondence
• Grant Offer
• Closeout
Federal AviationAdministration
Overview
• Note – Consult your local ADO on their grant process and requirements
Federal AviationAdministration
5 Years ACIP• Utilize last ACIP submission (Sample 1)
State FundsEntitlement State Appr. Discretionary State
Share:2.5% PFCSponsor
Share:2.5%
$150,000 $800,000 $0 $25,000 $0 $25,000 $1,000,000 C 6/11/2006 5/20/2008$0 $190,000 $0 $5,000 $0 $5,000 $200,000 A 5/10/2006 2/20/2007$0 $28,500 $0 $750 $0 $750 $30,000 A 5/10/2006 6/20/2007
Total $1,230,000
$150,000 $285,000 $0 $7,500 $0 $7,500 $450,000 B 8/20/2007 4/20/2008$0 $47,500 $1,250 $1,250 $50,000 A 2/11/2007 11/20/2008
Total $500,000
$150,000 $40,000 $0 $5,000 $0 $5,000 $200,000 A 6/11/2008 11/20/2009Total $200,000
Federal Aviation Administration Airport Capital Improvement Plan Date: 7/12/2005
1.Airport: New York International 2.State: NY 3.NPIAS No.: 4. LOCID: XYZ
Environmental: status
Start Date Completion Date
2006
5. Project Description & year (By funding year in priority order)
Federal Funds: 95% Local FundsTotal $
Runw ay 19 Extension (1000ftX150ft) - Design & Construct
Obstruction Removal - On/Off Arp.
Purchase Land - 25 Acres (R/W 19)AWOS - Design & Permit Only
2008Rehabilitate Apron - Design & Construct
AWOS - Construct
2007
Federal AviationAdministration
5 Years ACIP Con’t.
• ACIP entered into the FAA System Of Airport Reporting (SOAR) database
• Any changes must be reflected in SOAR
• Sponsor will receive AIP Program Letter (Sept. – Oct.) – (Sample 2)
Federal AviationAdministration
Pre-Application Process• Revised ACIP submission.• Sketch.• Project Narrative – Description & Justification.• Project Cost Estimate.• Certification for Selection of Consultant.• ALP “pen & ink” and/or Airspace Review.• Environmental Review.• Indicate project confirm to Airport Design
Standards.• Deadline for pre-application must be met .
Federal AviationAdministration
• Revised ACIP Submission/Meeting– Airport Sponsor & Consultant coordinates with
the ADO (meeting, teleconference, etc.).– Discuss ACIP & revisions, if any.– Restrictions (airport design standards, permits,
timeframe).– Alternatives.– Project priority.
Pre-Application Process Con't.
Federal AviationAdministration
Pre-Application Process Con't.• Sketch (E.G. R/W Extension)
5000’ X 150’ 1000’ X 150’
Extension
Proposed Land Acquisition
19
Federal AviationAdministration
• Project Narrative (E.G. R/W Extension)– Description – the project consist of extending
the approach end of R/W 19 to 1000’ X 150’; Acquire Land (25 acres); Establish new RSA and RPZ - Design/Permitting and Construct.
– Justification – extension is necessary to establish design requirements for aircraft currently using the airport and to enhance safety for the primary runway.
Pre-Application Process Con't.
Federal AviationAdministration
• Project Cost Estimate (E.G. R/W Extension) – FAA Form 5100-100 (9-03). (Sample 3)– Provide better detail & breakdown.– IFE, admin., federal, state and sponsor share.– Difficult to tell share amount when it is not
identified.
Pre-Application Process Con't.
• Sponsor Certification for Selection of Consultant (Sample 4)– Form certifies that sponsor select consultant based
on standards in AC 150/5100-14C, Architectural, Engineering, and Planning Consultant Services.
– Sponsor must sign and date.
Federal AviationAdministration
• ALP “pen & ink” change and/or Airspace Review– Review ALP for project depiction on drawing. – Any on airport ALP change must be submitted to the
applicable ADO for review.– 8 copies of Form 7460-1 and detailed drawing must be
submitted for FAA review. (Sample 5)– Review Form 7460-1 & drawing (7460-1 must be signed
by the sponsor).– Description – dimensions & location. – Late submission could jeopardize project schedule.
Pre-Application Process Con't.
Federal AviationAdministration
• Environmental Review– Contact the ADO Environmental Rep. to
determine the type of environmental form that is needed for AIP projects.
– Form A Basic Categorical ExclusionForm B Documented Categorical ExclusionForm C Short Environmental Assessment
– Submit form prior to deadline.– Could delay or prevent programming of projects.
Pre-Application Process Con't.
Federal AviationAdministration
• Indicate project conforms to Airport Design Standards.• Submit Modification of Standards, if required. • Intergovernmental Review
• ADO programming process– Review checklist.– Programming project pre-application.– OST clearance.– We will inform sponsor that we have programmed the project
and assigned an AIP grant number. (Sample 6)
Pre-Application Process Con't.
General Information
Federal AviationAdministration
• Application For Federal Assistance – Form 424 & Budget Form 5100-100.
• Sponsor Certification for Drug-Free Workplace.• Airport Sponsor/Engineers. Design and/or Inspection
Agreement.• Independent Fee Estimate.• Preliminary Plans & Spec. – 70% Complete• Final Plans & Spec.• Sponsor Certif. of Project Plans & Spec.• Grants Based on Bid, not estimate – date advertise & open.• Submit Bid Tabulation.
Application Process
Federal AviationAdministration
• Application For Federal Assistance – Form 424 & Budget Form 5100-100 (Sample 7)– AIP number must be shown on both forms (provide
accurate information).– Project description must be the same on all
correspondence.– Only the authorized representative must signsign and datedate
the application, if applicable a signed resolution should be attached.
– Budget sheet must reflect accurate amount.
Application Process Con't.
Federal AviationAdministration
• Sponsor Certification for Drug-Free Workplace (Sample 8)– Must be submitted for each project be signed and dated
by the Airport Sponsor.
Application Process Con't.
• Sponsor/Engineer Design and/or Inspection Agreement – Work Scope & Cost Breakdown.– Must be signed and dated by all parties.– Compensation/method of payment (cost-plus fixed fee or
lump sum).– Project schedule.– Work Scope must coincide with the Agreement cost
breakdown .
Federal AviationAdministration
• Sponsor/Engineer Design and/or Inspection Agreement– Cost summary (Sample 9)
• Clearly identify all cost and fees.• All subcontracts agreement must be provided.• Hourly classification must be shown and should not
fluctuate – cost summary and payment request.• No contingency costs.
Application Process Con't.
Federal AviationAdministration
• Independent Fee Estimate (IFE).– Dependent on cost of Design & Inspection Agre.– Must be solicit by the Airport Sponsor to another
consultant that is not affiliated with the project.– IFE must show similar work items associated with
the project.– Sponsor should negotiate with consultant,
utilizing the IFE. – FAA issues grant based on negotiated
agreement.
Application Process Con't.
Federal AviationAdministration
• Preliminary Plans & Spec.– 70% complete– Detail of Cover:
• AIP Grant Number• 70% complete• Re-Bid if necessary• Airport name & location• Date
Application Process Con't.
• Final Plans & Spec.– Should contain similar detail
Federal AviationAdministration
• Sponsor Certif. of Project Plans & Spec. – Purpose. (Sample 10)– Must be signed and dated by the Airport Sponsor.
Application Process Con't.
• BID– FAA issues grants based on Bid’s, not estimate. – Obtain permits prior to bidding project.– Inform FAA on advertise and bid opening dates.– Bid project prior to Spring Season.
Federal AviationAdministration
Application Process Con't.• BID Tabulation (Sample 11)
– Project could be bid as one or base bid with alternate/add-on (limited funds).
– Sponsor will send summary with recommendation on bid award (lowest qualified bidder).
– Cost Summary:• Should list items & cost for engineers estimate &
bidders on same page. • List all alternate/add-on bids. • Provide bidders contact information (address & tel.) • No contingency.
Federal AviationAdministration
• Sponsor/Engineer Design Services Agreement.• Sponsor/Engineer Inspection Services Agreement.• Concurrence of Award. (Sample 12,13 & 14)
FAA Approval Letters
Grant Offer• Issued after OST clearance. • Cover letter. (Sample 15)• Grant Offer/Agreement:
– Special Conditions & budget sheet.– Signed and dated by all parties.
• Master Agreement - contains Grant Assurance.
Federal AviationAdministration
• Notice To Proceed (NTP) (Sample 16)
– Executed grant received & accepted.– Conformed contract documents.– Performance & payment bonds (100%).– Insurance certificate (liability is not eligible
under AIP).– Construction management program.
Approval Letters Con't.
Federal AviationAdministration
• Change Order– Contact the ADO prior to performing work.– Cost must be justifiable & eligible. – 4 original signature sheet.– Approval.
• Weekly Const. Progress & Inspec. Reports – Form 5370-1. (Sample 17)
• Quarterly Federal Cash Transaction Report – Form 272. (Sample 18)
General
Federal AviationAdministration
• Payment Request– Electronic draw down is preferred.– AIP Grant number must be on the payment req.– Payment request must be the same for
percentage of work completed.– Request must follow one after another. (e.g. 1,
2, 3, etc.)
General Con't.
Federal AviationAdministration
• Outlay Report (Form 271), including funds spent (final project cost). (Sample 19)
• Sponsor Cert. Of Construction Project Final Acceptance. (Sample 20)
• Acceptance of construction work by Sponsor for each contract and/or acceptance of procurement for each piece of equipment.
• Request an amendment with or prior to close-out. Cannot exceed 15% of max. grant obligation
• Must satisfy special conditions of grant (deed rec.)
Project Close-Out
Federal AviationAdministration
Visit http://www.faa.gov/arp/forms for all associated forms.
Questions?
Mahendra RaghubeerAirport Planner & Engineer
New York Airports District Office
E-Mail: [email protected]: 516-227-3813