February 1, 2012
Casino Facility Progress Report
Construction Progress – February 1, 2012
Contract sum to date: 164,372,575
Total project completed to date:
85%
MBE / WBE awarded to date: $ 35,900,000 *
Average daily # of construction workers on-site:
300
Note: * - MBE/WBE amount exceeds original goal by over $14,000,000.
Arial View
January 26, 2012 Tour
• Team member Training Room.
January 26, 2012 Tour – Team Member Dining Room
January 26, 2012 Tour – Epic Buffet
January 26, 2012 Tour – Gaming Floor
Comparative Photos (Final Cut Steak & Seafood House – photo #1)
Comparative Photos (Final Cut Steak & Seafood House – photo #2)
Comparative Photos (Epic Buffet)
Comparative Photos (Skybox Restaurant & Bar)
Comparative Photos (Serpentine Sign)
Comparative Photos (Poker Room)
Summary Timeline• Surveillance:
– System Programming/Testing: January 3-15, 2012– System Turnover to Property: January 16, 2012
• Food & Beverage:– Epic Buffet & Final Cut Steakhouse Partial Certificate of Occupancy: December 27, 2011– Team Member Dining Room Open: January 6, 2012
• Slots:– Carpet Installation: December 14, 2011 to February 10, 2012– Slot Bases Installation: December 19, 2011 to March 2, 2012– Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval)– Estimated Installation: TBD (30 day duration)
• Table Games:– Artwork/layouts submitted to Commission for review & approval: December 21, 2011– Carpet Installation (Pit areas): To be completed by February 29, 2012– Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval)– Estimated Installation: March 1-5, 2012
• Final Inspection/Certificate of Occupancy:– Certificate of Occupancy: March 15, 2012
Staffing Update
Status Number
Active Team Members 69
Future Dated Offers 228
Completed Offers in 2 Weeks 700
Total 997
• All employees identified as key employees to date have submitted a complete key license application (14 in total).
Vendor Update
Status Number Percentage
MBE/WBE Vendors 23 10.50
All Other Vendors 197 89.50
Total 220 100.00
Public Safety Outreach• Most recent meeting held on January 30, 2012 with the following
attendees:– Captain Brad Weis – Toledo PD (Strategic Response – Hollywood Contact
person for opening– Thomas Wiegand – Toledo PD (Area Commander)– Chief Mark Hetrick – Perrysburg Township PD– Chief Thomas Cairl – Northwood PD– John Altman – Ohio Highway Patrol– Eric Reynolds – Deputy Chief, Wood County– Seven (7) other members of local law enforcement
• Topics included: Team member & guest safety, Traffic flow, Natural Disasters, Gangs, Miscellaneous crimes & threats.
• Bi-weekly meetings to occur going forward.