MONTHLY TARGETPROJET NAME :- Salarpuria Sattva Cadenza PROJECT CODE:-96060MONTHLY PROGRAME FOR THE MONTH OF FEBRUARY 2015Work DescriptionTotal qty in FEB-15Unit Rate Amount1st Week2nd Week3rd Week4th WeekEarth Work excavationOrdinary Soil150.0200.0200.0100.0650.0Cum377245,050.00Hard Rock50.050.050.050200.0Cum1695339,000.00Earth Filling2,000.02,000.0Cum251502,000.00Plum concerete 15.015.025.055.0Cum4939271,645.00PCC45.020.015.085.0165.0Cum5350882,750.00RCC 50.01,300.0140.0135.01,625.0Cum643910,463,375.00shuttering 400.0400.0400.0400.01,362.2Sqm614836,420.89Reinforcement steel82.082.082.082.0328.0MT128894,227,592.00structural steel0.0MT0.0Block work0.00.0100 MM0.00.0150MM0.00.0200MM75.075.0Sqm128296,150.00Internal Plastering0.0Sqm0.0External plastering0.0Sqm0.0Expansion Joint50.050.0Sqm108054,000.0017,917,982.89
MILESTONES & MAN POWERSattva CadenzaPlanned V/S Achieved For the month of Feb-2015Date23.02.2015 Feb-15 ProgrammeMILESTONES TARGETFeb-15 QtyAchieved Up to datecum balanceUnitsWeek-1 (1st to 07th)Week-2 (8th to 15th)Week-3 (16th to 22nd)Week-4 (23rd to end )Barbenders in Noscarpenters in NosPlannedStatusPlannedStatusPlannedStatusPlannedStatusEarth work Excavation & surface dressing at Tower1, 2 & 3 location450.0360.090.0Cum450.080% Completed
1.0Tower 2 & 3 Raft Pour-1Barbending works85.885.80.0MT85.8Completed428.8Shuttering56.056.00.0Sqm56.0Completed18.7Concreting456.0456.00.0Cum456.0CompletedPour-2Barbending works159.3159.30.0MT159.3Completed796.3Shuttering104.0104.00.0Sqm104.0Completed34.7Concreting884.0876.08.0Cum884.0876.0
2.0Isolated footings (45 Nos), as weekly priority list Footings 22 nos (Tower-1 location Grid M,C/P1,P4)Earth work30.030.00.0CUM30.0CompletedPCC7.37.30.0CUM7.3CompletedBarbending works15.815.80.0MT15.8Completed90.5Shuttering150.7150.70.0Sqm150.7Completed53.8Concreting86.086.00.0Cum86.0Completed Footings (Tower-1 non tower location C,CA/P1,P5)Earth work14.012.02.0CUM14.012.0PCC3.21.02.2CUM3.21.0Barbending works7.32.05.3MT7.32.041.5Shuttering67.435.032.4Sqm67.435.024.1Concreting38.412.026.4Cum38.412.0Footings 12 Nos (Tower 2,3 Non Tower area Grid P9,P19/PA,PF)Earth work22.00.022.0CUM22.00.0PCC4.60.04.6CUM4.60.0Barbending works11.90.011.9MT11.967.9Shuttering95.40.095.4Sqm95.434.1Concreting50.10.050.1Cum50.1
3.0Tower 1, 2, 3Retaining wall South side (90 Mts) sideat parrelel to acces road+ B/W Tower 3 & 4 joining areaFoundation (South balance 10 Mts Length)Earth work8.08.00.0Cum8.08.0Barbending works3.03.00.0MT3.0Completed17.1Shuttering10.010.00.0Sqm10.0Completed3.6Concreting10.810.80.0Cum10.8Completed
R.wall at Lower basement lvl (90 Rmt Length)20 MtsCompleted38.5 Mts38.5 MtsBarbending works14.03.510.5MT2.8Completed5.6W.U.P5.680.0Shuttering683.8136.8547.1Sqm136.8Completed273.5W.U.P273.5244.2Concreting102.620.582.1Cum20.5Completed41.041.0
4.0Columns 1st Shift concreting 30 nos15 Nos7 nos15 NosBarbending works6.03.03.0MT3.0completed3.034.3Shuttering150.037.5112.5Sqm75.050% completed75.053.6Concreting20.05.015.0Cum10.050% completed10.05.0Back filling up to footingsat Tower-1 (Aprx 3000 cum)2000.050.01950.0Cum500.050.01500.06.0Tower-4 Lift pit PCC & ConcretingBarbending works24.50.024.5MT12.30.012.3140.0Shuttering45.00.045.0Sqm15.00.030.016.1Concreting140.00.0140.0Cum10.0130.0
7.0Excavation for Tower-4 Lift work225.0225.00.0Cum225.0Completed Labours required for the month of Feb-151696.3482.7Per Day Man Power Required65.221.1ACTUAL UP TO DATE LABOURS IN FEB1349.0468.0PLANNED V/S ACHIEVED - FEB 2015Cum % Achieved V/S Plan Feb 2015PER DAY Avg Labours71.024.6MAIN EVENTSPlanned-FebAchievedBALANCEUNITS1.0Concrete1787.91466.3321.6Cum82.0%2.0Shuttering1362.2529.9832.3Sqm38.9%3.0Steel327.5272.355.1MT83.2%4.0Earth work excavation749.0635.0114.0cum84.8%5.0Back Filling2000.050.01950.0cum2.5%
Retaining wallSattva CadenzaTantative Retaining Wall Quantity In Feb-15
LocationLength in MtswidthHeightConcrete QtyShuttering QtyTower 1, 2 & 3 Lower basement +Upper BasementRW South97.690.33.5102.5745Cum683.83Sqm
Total Concrete for Foundation102.40.4510.8Cum9Sqm
Total Concrete for Retaining wall113.37Cum692.83Sqm
Total Shuttering Qty 692.83Sqm
Sheet2PROJET NAME :- Salarpuria Sattva Cadenza PROJECT CODE:-96060MONTHLY PROGRAME FOR THE MONTH OF FEBRUARY 2015Work DescriptionQTY on FEB-15Target Quantity (Jan+Feb)Unit Rate Amount12345678910111213141516171819202122232425262728Earth Work excavationOrdinary Soil50.050.050.050.050.050.050.050.050.050.050.050.050.050.0700.01,000.0Cum377377,000.00Hard Rock50.050.050.050200.0500.0Cum1695847,500.00Earth Filling400.0600.0600.06006006003,400.03,500.0Cum251878,500.00Plum concerete 30.015.025.070.0160.0Cum4939790,240.00PCC45.05.05.05.05.010.05.05.080.0165.0230.0Cum53501,230,500.00RCC 12.010.010.010.010.010.015.010.0400.0450.0400.015.015.020.020.025.020.020.020.020.0130.020.020.020.025.01,727.02,000.0Cum643912,878,000.00shuttering 50.0140.0140.0140.0140.0140.0140.050.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.0140.03,460.03,500.0Sqm6142,149,000.00Reinforcement steel5.014.014.014.014.014.014.05.014.014.014.014.014.014.05.014.014.014.014.014.014.05.014.014.014.014.014.014.0356.0450.0MT128895,800,050.00structural steel0.00.0MT0.0Block work0.00.00.0100 MM0.00.00.0150MM0.00.00.0200MM50.025.075.0150.0Sqm1282192,300.00Internal Plastering0.00.0Sqm0.0External plastering0.00.0Sqm0.0Water Bar50.050.050.050.050.050.050.050.05050500.0500.0Rmt600300,000.00Expansion Joint10.010.010101050.050.0Sqm108054,000.00
25,497,090.00
RW estSattva CadenzaTantative Retaining Wall Quantity In over all Project
LocationLength in MtswidthHeightConcrete QtyShuttering QtyTower 1, 2 & 3 Lower basement +Upper BasementRW South97.690.37.1208.0797Cum1387.198SqmWest27.1050.37.157.73365Cum384.891SqmNorth105.7450.37.1225.23685Cum1501.579SqmEast14.3250.47.140.683Cum203.415Sqm27.360.87.1155.4048Cum388.512SqmTower 4 Upper Basement only
North35.8250.23.827.227Cum272.27SqmEast25.240.83.876.7296Cum191.824SqmEast16.440.23.812.4944Cum124.944SqmNorth36.2250.23.827.531Cum275.31Sqm
Tower 5 TO 82920.21.587.6Cum876Sqm
Total in Rmt711.85275
Total Concrete for Foundation711.852752.40.45768.80097Cum640.667475Sqm
Deduct in Raft-602.40.45-64.8Cum-54SqmTotal Concrete for Retaining wall1622.72Cum
Total Shuttering Qty 6192.61Sqm1576.333333333328.9333333333394.0833333333197.041666666765.6805555556
Iso FootingsIsolated footings Casting at Tower 1,2 & 32nd week target 08.02.15 to 14.02.15FOOTINGS NOLBDQTYPCCF13222.50.77.0012.60.594F1412.31.80.6252.595.1250.25CF612.52.60.74.557.140.378F413.32.30.856.459.520.4375F512.51.90.653.095.720.2835F7221.40.52.806.80.352F652.81.80.717.6432.21.5CF512.62.40.6253.906.250.364F1142.51.80.6511.7022.361.08F913.52.50.9258.0911.10.4995F231220.62.404.80.242F1012.51.40.551.934.290.216F313.12.10.7755.058.060.3795F1222.82.10.758.8214.70.692486.00CUM150.665Sqm7.266CUM3rd week target 15.02.15 to 21.02.15F323.12.10.77510.0916.120.759F413.32.30.856.459.520.4375F512.51.90.653.095.720.2835F7121.40.51.403.40.176F212.12.10.6752.985.670.2645F112.62.60.865.818.9440.392F1422.31.80.6255.1810.250.5F1512.11.60.551.854.070.207F17121.50.5251.583.6750.1871138.42CUM67.369Sqm3.2065CUM4th week target 22.02.15 to 28.02.15F1512.11.60.551.854.070.207CF212.11.70.72.505.320.2185F1872.31.90.6519.8838.221.8375F13322.50.710.5018.90.891F1412.31.80.6252.595.1250.25F1912.62.10.754.107.050.322CF313.22.20.755.288.10.408F1621.71.20.41.634.640.266CF4121.60.551.763.960.1981850.09CUM95.385Sqm4.598CUMNo of footings planned53174.50CUM313.42Sqm15.0705CUMHolded to Ramp20
Sheet1
T1LB720sqm144
8.490.3841355.7612201.849.4Tapas MaityFlooring Labour contractor# 438/118/2, Doddatagur, Electronic city post, Bangalore-100Pan No: BMSPM8708AM: 81235 19560Quotation for Tiling work in Toilets at cadenza site contractor & PMC Office.Details: Labour works of toilet Flooring & dadoing including hacking/chipping, Cutting, Grouting, Acid washing complete at 9 toilets in contractor & PMC office of cadenza site at rate of Over all lumpsum amount Rs.18,000/-
Signature
Tapas Maity53.584576.563842571.42857142868648.457625.7142857143
Sheet3WEEKLY PROGRAMME (FEB-20 TO 28) As Per Internal MeetingSTARTFINISHQUANTITYUNITDESCRIPTIONSTARGET UP TO DATE ACHIEVEDTOTAL PLANNEDREMARKS1TOWER-1AFOOTINGS20-Feb-1523-Feb-1552934NOSBRETAINING WALL (SOUTH)20-Feb-1524-Feb-1540040RMTCCOLUMNS20-Feb-1524-Feb-1512315NOSDBackfilling activity23-Feb-1528-Feb-15
2TOWER-2 & 3ASTARTER FOR COLUMNS & RETAINING WALL20-Feb-1521-Feb-1533740NOSBRETAINING WALL (SOUTH)21-Feb-1526-Feb-1530030RMTFor conventional method board preparation under progressCCOLUMNS23-Feb-1528-Feb-1532032NOSDPEDESTRALS & STARTERS (ALL COMPLETE)20-Feb-1528-Feb-1520020NOSELIFT PIT CORE WALL21-Feb-1522-Feb-15
3OTHER ACTIVITYABACK FILLING AT TOWER-123-Feb-1528-Feb-15200002000CUMBTOWER-4 LIFT PIT EXC/DRESSING21-Feb-1522-Feb-15CTOWER-4 LIFT PIT PCC & REINFORCEMENT24-Feb-1526-Feb-15ACTUAL QTYDTOWER-4 LIFT PIT RCC28-Feb-1528-Feb-15ACTUAL QTY
Sheet4MARCH LOOK AHEAD PROGRAMMEDESCRIPTIONSSTARTFINISHQUANTITYUNITDISTRIBUTIONREMARKSTARGET UP TO PREVIOUS PLANNEDTOTAL PLANNEDWEEK11 TO 7thWEEK 28th to 14thWEEK 315th to 21th22nd to 31CARPENTERFITTER1-Jul-862-May-831TOWER-1AFOOTINGS20-Feb-1523-Feb-1552934NOSBRETAINING WALL (SOUTH)20-Feb-1524-Feb-1540040RMTCCOLUMNS20-Feb-1524-Feb-1512315NOSDBackfilling activity23-Feb-1528-Feb-15
2TOWER-2 & 3ASTARTER FOR COLUMNS & RETAINING WALL20-Feb-1521-Feb-1533740NOSBRETAINING WALL (SOUTH)21-Feb-1526-Feb-1530030RMTFor conventional method board preparation under progressCCOLUMNS23-Feb-1528-Feb-1532032NOSDPEDESTRALS & STARTERS (ALL COMPLETE)20-Feb-1528-Feb-1520020NOSELIFT PIT CORE WALL21-Feb-1522-Feb-15
3OTHER ACTIVITYABACK FILLING AT TOWER-123-Feb-1528-Feb-15200002000CUMBTOWER-4 LIFT PIT EXC/DRESSING21-Feb-1522-Feb-15CTOWER-4 LIFT PIT PCC & REINFORCEMENT24-Feb-1526-Feb-15ACTUAL QTYDTOWER-4 LIFT PIT RCC28-Feb-1528-Feb-15ACTUAL QTY23-Feb-1523-Feb-15EVENTS AT TOWER-4-10464-11620RAFT -28.6684931507-31.8356164384EXCAVATION1-Mar-154-Mar-156006060PCC4-Mar-156-Mar-1542.5042.542.5REINFORCEMENT6-Mar-1510-Mar-15110011010100SHUTTERING9-Mar-1511-Mar-159509595RAFT/PEDESTRAL CONCRETING12-Mar-1513-Mar-156900690690
ISOLATED FOOTINGSEXCAVATION4-Mar-1510-Mar-151001010PCC6-Mar-1511-Mar-152022REINFORCEMENT11-Mar-1514-Mar-155055SHUTTERING14-Mar-1516-Mar-155305353CONCRETING14-Mar-1515-Mar-152902929RETAINING WALL Total length 113 RmtEXCAVATION1-Mar-154-Mar-1545.2045.245.2PCC/PLUM CONCRETING4-Mar-157-Mar-151001010REINFORCEMENT7-Mar-159-Mar-155050.54.5SHUTTERINGCONCRETING FOR FOUNDATION & WALL8-Mar-1518-Mar-1580080
COLUMNSREINFORCEMENT14-Mar-1519-Mar-1525025322SHUTTERING16-Mar-1522-Mar-153950395395CONCRETING17-Mar-1523-Mar-15420422121
BACK FILLING QTY- Tower-46500650200450
EVENTS AT TOWER-1, 2 & 3 TOWER-1, 2 & 3 SLABS AT UPPER BASEMENT LEVELSLAB POUR-1 AT TOWER-2 BUILT AREA ONLYSHUTTERING1-Mar-158-Mar-15950950REINFORCEMENT6-Mar-1511-Mar-151717CONCRETING-Pour-113-Mar-1513-Mar-151451458400SLAB POUR-2 AT TOWER-3 BUILT AREA ONLY31000SHUTTERING6-Mar-1513-Mar-15815707456400REINFORCEMENT11-Mar-1516-Mar-15161645800CONCRETING-Pour-118-Mar-1518-Mar-15125125
SLAB POUR-3 AT TOWER-1 BUILT AREA ONLYSHUTTERING11-Mar-1518-Mar-15940470470REINFORCEMENT16-Mar-1521-Mar-151313CONCRETING-Pour-123-Mar-1523-Mar-15135135
columns at upper basement level at tower 2& 3REINFORCEMENT15-Mar-1518-Mar-153003030SHUTTERING17-Mar-1522-Mar-15560056050060CONCRETING18-Mar-1523-Mar-1510401047034
RETAINING WALL NORTH SIDE 90 MTSPCC1-Mar-154-Mar-154.504.5FOUNDATION CONCRETE2-Mar-157-Mar-1540040WALLS REINFORCEMENT7-Mar-1517-Mar-152500250WALLS SHUTTERING10-Mar-1519-Mar-156200620WALLS CONCRETING10-Mar-1519-Mar-1577077
RETAINING WALL WEST SIDE 30 MTS b/w TOWER 3 & 4PCC15-Mar-1518-Mar-15202FOUNDATION CONCRETE16-Mar-1521-Mar-1515015WALLS REINFORCEMENT21-Mar-1531-Mar-15202WALLS SHUTTERING24-Mar-152-Apr-152000200WALLS CONCRETING24-Mar-152-Apr-1580080
RAMP-3 AT LOWER BASEMENT LEVEL 36 RMTFOOTINGS FOR RAMPEXCAVATION FOR RAMP FOOTINGS1-Mar-154-Mar-1513.2013.2CUMPCC4-Mar-157-Mar-152.202.2CUMRCC FOR FOOTINGS & COLUMNS 5-Mar-1513-Mar-1519.47019.47CUMSHUTTERING4-Mar-1513-Mar-151500150SQMREINFORCEMENT6-Mar-1512-Mar-15404MTCONCRETING FOR RAMP15-Mar-1516-Mar-1528028CUM